Sei sulla pagina 1di 423

Construction Estimating Using Excel

This page intentionally left blank


Construction Estimating Using Excel
S ECOND E DITION
Steven J. Peterson
MBA, PE

Prentice Hall
Boston Columbus Indianapolis New York San Francisco Upper Saddle River
Amsterdam Cape Town Dubai London Madrid Milan Munich Paris Montreal Toronto
Delhi Mexico City Sao Paulo Sydney Hong Kong Seoul Singapore Taipei Tokyo
Editor in Chief: Vernon Anthony Senior Art Director: Jayne Conte
Acquisitions Editor: David Ploskonka Cover Designer: Karen Salzbach
Editorial Assistant: Nancy Kesterson Cover Art: Shutterstock
Director of Marketing: David Gesell Full-Service Project Management and
Marketing Manager: Derril Trakalo Composition: Mohinder Singh/Aptara®, Inc.
Senior Marketing Coordinator: Printer/Binder: Edwards Brothers
Alicia Wozniak Cover Printer: Lehigh-Phoenix
Marketing Assistant: Les Roberts Color/Hagerstown
Project Manager: Holly Shufeldt Text Font: Minion

Credits and acknowledgments borrowed from other sources and reproduced, with permission, in
this textbook appear on appropriate page within the text.

Microsoft® and Windows® are registered trademarks of the Microsoft Corporation in the U.S.A.
and other countries. Screen shots and icons reprinted with permission from the Microsoft
Corporation. This book is not sponsored or endorsed by or affiliated with the Microsoft
Corporation.

Copyright © 2012, 2007. Pearson Education, Inc., publishing as Prentice Hall, Upper Saddle
River, New Jersey and Columbus, Ohio. All rights reserved. Manufactured in the United States of
America. This publication is protected by Copyright, and permission should be obtained from the
publisher prior to any prohibited reproduction, storage in a retrieval system, or transmission in any
form or by any means, electronic, mechanical, photocopying, recording, or likewise. To obtain
permission(s) to use material from this work, please submit a written request to Pearson Education,
Inc., Permissions Department, One Lake Street, Upper Saddle River, New Jersey 07458.

Many of the designations by manufacturers and seller to distinguish their products are claimed as
trademarks. Where those designations appear in this book, and the publisher was aware of a
trademark claim, the designations have been printed in initial caps or all caps.

Library of Congress Cataloging-in-Publication Data


Peterson, Steven J.
Construction estimating using excel / Steven J. Peterson. —2nd ed.
p. cm.
Includes bibliographical references and index.
ISBN-13: 978-0-13-800719-5
ISBN-10: 0-13-800719-5
1. Building—Estimates—Data processing. 2. Microsoft Excel (Computer file) I. Title.
TH437.P357 2012
692'.50285536—dc22
2010043121

10 9 8 7 6 5 4 3 2 1

ISBN 10: 0-13-800719-5


ISBN 13: 978-0-13-800719-5
DEDICATION
This book is dedicated to Bill Thiede,
who taught me how to estimate.
This page intentionally left blank
PREFACE

By working hard during the buyout process, I was able

T he second hand of the clock swept rapidly toward


the 12, signifying that it was 15 minutes to 1.
Fifteen minutes until bid closing, when the bid I
was working on was due. I had 10 minutes until our secretary
would call for the final price, giving her just enough time to
to get the project back on budget. I did this by finding local
subcontractors and suppliers for the items I had bid myself
who would do the work for less than I had budgeted. In the
end, we made a fair profit on the job, but that does not
make up for the money we left on the table because of my
error.
write the number on the bid forms, seal the bid, and turn it
The job of an estimator is to forecast as accurately as
in. The bid had been tallied and was ready to go, with the
possible the likely cost of a construction project, as well as
exception of one blank line. The words “Asphalt Paving”
the required amounts of materials, labor, and equipment
along with the blank space to the right glared at me. I had yet
necessary to complete the work. Because of the high degree
to receive a number from my asphalt contractor, who had
of uncertainty in estimating these items, estimating is more
promised me he would get me a bid. I called his phone num-
of an art than a science.
ber. No answer! There was only one thing left for me to do. I
There are three key pillars that support the success of an
had to do an asphalt takeoff myself, and I had only 8 minutes
estimator. The first is an understanding of the construction
left. Quickly I grabbed my scale, turned it to match the scale
process—how things are built and how the pieces are put to-
at the bottom of the drawing (1> 8⬙ ⫽ 1⬘), and began to de-
gether. The second is an understanding of the fundamental
termine the quantity of asphalt needed for the parking lot.
principles of estimating. Estimates that are not based on
Cutting corners where I could, scribbling numbers on a
these fundamental principles are nothing more than wild
piece of scratch paper, and punching the numbers on my
guesses. The third pillar is experience. For a person to be-
calculator, I arrived at the square footage of the asphalt. It
come a good estimator, it is required that he or she develop
wasn’t exact, but it was close. I then multiplied the square
good judgment on how to apply estimating principles. Rita
footage by the estimated cost per square foot for the asphalt.
Mae Brown said, “Good judgment comes from experience,
The phone rang as I added my estimated cost for the asphalt
and often experience comes from bad judgment.”1 The pillar
to the bid. It was our secretary calling for the bid. I gave her
of experience can only be acquired through practice.
the number, and she read it back to me.
The purposes of this book are to (1) give beginning es-
I relaxed for the next 20 minutes, waiting for our secre-
timators an understanding of the fundamental principles of
tary to call back with the bid results. The phone rang again
estimating, (2) provide beginning estimators with practical
and it was our secretary. We had won the bid. As I was enjoy-
estimating experience, (3) give beginning estimators a basic
ing the thrill of victory, I glanced at the plans and the words
understanding of how to use spreadsheets, such as
“Warning: Half Size Drawings” jumped off the page. The
Microsoft Excel2, to increase their estimating productivity
thrill of victory turned into a large lump in my stomach as I
and reduce errors, and (4) give experienced estimators an-
realized why I had won the bid. I had forgotten to double all
other view on estimating and a chance to improve their
my measurements as I measured the asphalt, so I had only
estimating skills.
25% of the money I needed to purchase the asphalt for the
project. Quickly, and carefully this time, I took off the as-
phalt again. Indeed, I only had a quarter of the asphalt I 1
Rita Mae Brown, as posted on http://www.1famousquote.com/b/
needed, and it would take all the profit in the job and then ritamaebrown.htm; accessed October 7, 2003.
2
some to pay for it. Microsoft® Excel is a trademark of the Microsoft Corporation.

vii
viii PREFACE

This book is divided into five sections. The first section 䊉 A discussion of the modified-average-end method has
introduces the reader to estimating. The second section in- been added to Chapter 16.
troduces the quantity takeoff and teaches the reader how to 䊉 The social security tax rates have been updated.
determine the quantity of materials needed to complete the 䊉 A section covering e-mail etiquette has been added to
project. The third section shows how to put costs to the esti- Chapter 28.
mate. The fourth section shows how to finalize the bid, in-
corporate the estimate into the schedule, and buy out the
project, and discusses bidding ethics. The fifth section
teaches how to tap into the power of computer spread- DOWNLOAD INSTRUCTOR
sheets—specifically Microsoft® Excel—and demonstrates RESOURCES FROM THE
how spreadsheets can be used to automate estimating func- INSTRUCTOR RESOURCE
tions. To provide practice in estimating, three drawing sets CENTER
are included—a residential garage, a residence, and a retail
building. To access supplementary materials online, instructors
I hope you will take the time to carefully read each need to request an instructor access code. Go to www.
chapter, work the problems at the end of each chapter, and pearsonhighered.com/irc to register for an instructor ac-
prepare estimates for the projects at the end of the book. cess code. Within 48 hours of registering, you will receive a
Doing this will help you begin to gain the experience needed confirming e-mail including an instructor access code.
to be a successful estimator. Once you have received your code, locate your text in the
I would like to thank the following people for providing online catalog and click on the Instructor Resources but-
reviews of the manuscript: Barry M. Eager (Arizona State ton on the left side of the catalog product page. Select a
University), Roger Killingsworth (Auburn University), supplement, and a login page will appear. Once you have
Huanqing Lu (East Carolina University), and Ihab M. H. logged in, you can access instructor material for all
Saad, Ph.D. (East Carolina University). Prentice Hall textbooks. If you have any difficulties access-
ing the site or downloading a supplement, please contact
Customer Service at http://247.prenhall.com.
NEW TO THIS EDITION
The following is a list of key changes that have been made to DISCLAIMER
this edition.
The sample Excel spreadsheets in this book are to provide the
䊉 The Excel contents have been updated to Excel 2007 and reader with examples of how Excel may be used in estimat-
2010. ing, and as such, are designed for a limited number of esti-
䊉 The equations have been stacked to make them easier to mating situations. Before using the spreadsheets in this book,
read. the reader should understand the limits of the spreadsheet
䊉 A Fifth type of materials (quantity from quantity) has and carefully verify that the spreadsheets (1) are applicable to
been added. The types of materials now includes his or her estimating situation and (2) produce an acceptable
counted items, linear components, sheet and roll goods, answer. The reader assumes all risks from the use and/or per-
volumetric goods, and quantity-from-quantity goods. formance of these spreadsheets.
BRIEF CONTENTS

PA R T
I Chapter
8
INTRODUCTION TO ESTIMATING 1 WOODS, PLASTICS, AND COMPOSITES 108

Chapter
1 Chapter
9
THE ART OF ESTIMATING 2
THERMAL AND MOISTURE PROTECTION 134

Chapter
2
OVERVIEW OF THE ESTIMATING AND
BIDDING PROCESS 10
Chapter
10
OPENINGS 153

Chapter
3 Chapter
11
INTRODUCTION TO EXCEL 18
FINISHES 162

PA R T
II Chapter
12
THE QUANTITY TAKEOFF 55 FIRE SUPPRESSION 172

Chapter
4
FUNDAMENTALS OF THE QUANTITY
Chapter
13
TAKEOFF 56 PLUMBING 176

Chapter
5 Chapter
14
CONCRETE 66
HEATING, VENTILATION, AND
AIR-CONDITIONING (HVAC) 181
Chapter
6
MASONRY 89
Chapter
15
ELECTRICAL 189

Chapter
7 Chapter
16
METALS 97
EARTHWORK 200

ix
x BRIEF CONTENTS

Chapter
17 Chapter
29
EXTERIOR IMPROVEMENTS 214 PROJECT BUYOUT 289

Chapter
18 Chapter
30
UTILITIES 220 THE ESTIMATE AS THE BASIS
OF THE SCHEDULE 293

PA R T
III Chapter
31
PUTTING COSTS TO THE ESTIMATE 227
ETHICS 295

Chapter
19 PA R T
V
MATERIAL PRICING 228
ADVANCED ESTIMATING WITH
EXCEL 297
Chapter
20
LABOR PRODUCTIVITY AND HOURS 233 Chapter
32
CONVERTING EXISTING FORMS 298
Chapter
21
LABOR RATES 240 Chapter
33
CREATING NEW FORMS 315
Chapter
22
EQUIPMENT COSTS 248 Chapter
34
PROPOSALS AND BEYOND 338
Chapter
23
CREW RATES 254 Appendix
A
REVIEW OF ESTIMATING MATH 341
Chapter
24
SUBCONTRACT PRICING 257
Appendix
B
SAMPLE JOB COST CODES 354
Chapter
25
MARKUPS 261 Appendix
C
SAMPLE LABOR PRODUCTIVITY
Chapter
26 RATES 359

PRICING EXTENSIONS 267


Appendix
D
Chapter
27 MODEL SCOPES OF WORK 364

AVOIDING ERRORS IN ESTIMATES 277


Appendix
E
PA R T
IV GLOSSARY 370

FINALIZING THE BID 281


Appendix
F
Chapter
28 INDEX OF DRAWING SETS 377

SUBMITTING THE BID 282


INDEX 378
CONTENTS

PA R T
I
INTRODUCTION TO ESTIMATING 1

Chapter
1
THE ART OF ESTIMATING 2

The Estimator 2

Types of Estimates 3

Bid Package 4

Estimating Tools 7

Computerized Estimating 8

Conclusion 9

Problems 9

References 9

Chapter
2
OVERVIEW OF THE ESTIMATING AND BIDDING PROCESS 10

Planning the Bid 10

Pre–Bid-Day Activities 10

Bid-Day Activities 14

Post-Bid Activities 16

Conclusion 17

Problems 17

Chapter
3
INTRODUCTION TO EXCEL 18

Conventions Used in This Book 18

Workbook Management 18

xi
xii CONTENTS

Working with Worksheets 22

Entering Data 26

Formatting Worksheets 30

Writing Formulas 39

Basic Functions 41

Printing 46

Testing Spreadsheets 49

Conclusion 53

Problems 53

PA R T
II
THE QUANTITY TAKEOFF 55

Chapter
4
FUNDAMENTALS OF THE QUANTITY TAKEOFF 56

Performing a Quantity Takeoff 56

Work Packages 57

Communication with the Field 58

Counted Items 60

Linear Components 61

Sheet and Roll Goods 61

Volumetric Goods 63

Quantity-From-Quantity Goods 64

Waste 64

Conclusion 65

Problems 65

Reference 65

Chapter
5
CONCRETE 66

Forms 66

Reinforcing 67

Concrete 67

Spread Footings 68

Columns 69

Continuous Footings 71

Foundation Walls 76

Beams 78

Slab on Grade 78

Raised Slabs 80

Stairs 81
CONTENTS xiii

Sample Takeoff for the Residential Garage 82

Conclusion 85

Problems 85

Chapter
6
MASONRY 89

Block and Structural Brick Walls 90

Brick Veneer 93

Conclusion 94

Problems 94

Chapter
7
METALS 97

Types of Structural Steel 97

Common Shapes for Structural Steel 97

Beams, Girders, and Columns 98

Joists and Joist Girders 100

Metal Deck 102

Steel Trusses 102

Stairs and Handrail 102

Miscellaneous Steel 103

Conclusion 104

Problems 104

Chapter
8
WOODS, PLASTICS, AND COMPOSITES 108

Floor Systems 108

Walls 113

Roof Systems 119

Finish Carpentry 124

Cabinetry and Countertops 124

Sample Takeoff for the Residential Garage 125

Conclusion 127

Problems 127

Reference 133

Chapter
9
THERMAL AND MOISTURE PROTECTION 134

Waterproofing and Dampproofing 134

Building Paper and Vapor Barriers 135

Insulation 138
xiv CONTENTS

Exterior Insulation Finish System 140

Shingle Roofs 141

Siding, Soffit, and Fascia 143

Membrane Roofing 146

Sample Takeoff for the Residential Garage 146

Conclusion 149

Problems 149

References 152

Chapter
10
OPENINGS 153

Doors 153

Windows 153

Commercial Storefront 155

Glazing 156

Hardware 157

Sample Takeoff for the Residential Garage 157

Conclusion 158

Problems 158

Reference 161

Chapter
11
FINISHES 162

Metal Stud Partitions 162

Gypsum Board 162

Tile 164

Suspended Acoustical Ceilings 165

Wood and Laminate Floors 166

Sheet Vinyl 167

Vinyl Composition Tile 168

Rubber Base 168

Carpet and Pad 168

Paint 168

Sample Takeoff for the Residential Garage 169

Conclusion 170

Problems 170

Chapter
12
FIRE SUPPRESSION 172

Conclusion 174

Problems 174
CONTENTS xv

Chapter
13
PLUMBING 176

Water Supply 176

Drain-Waste-and-Vent System 176

Fixtures and Equipment 179

Conclusion 179

Problems 179

Chapter
14
HEATING, VENTILATION, AND AIR-CONDITIONING (HVAC) 181

Residential HVAC Systems 181

Commercial HVAC Systems 184

Conclusion 186

Problems 186

Chapter
15
ELECTRICAL 189

Residential Wiring 189

Commercial Wiring 190

Sample Takeoff for the Residential Garage 193

Conclusion 196

Problems 196

Chapter
16
EARTHWORK 200

Characteristics of Soils 200

Swell and Shrinkage 200

Geometric Method 202

Average-Width-Length-Depth Method 203

Average-End Method 203

Modified-Average-End Method 204

Cross-Sectional Method 204

Comparison of Methods 209

Backfill 210

Soils Report 210

Sample Takeoff for the Residential Garage 210

Conclusion 212

Problems 212
xvi CONTENTS

Chapter
17
EXTERIOR IMPROVEMENTS 214

Asphalt and Base 214

Site Concrete 215

Landscaping 215

Sample Takeoff for the Residential Garage 216

Conclusion 217

Problems 217

Chapter
18
UTILITIES 220

Excavation 220

Bedding 223

Utility Lines 224

Backfill 225

Conclusion 225

Problems 225

PA R T
III
PUTTING COSTS TO THE ESTIMATE 227

Chapter
19
MATERIAL PRICING 228

Shipping Costs 229

Sales Tax 230

Storage Costs 230

Escalation 230

Conclusion 231

Problems 231

Chapter
20
LABOR PRODUCTIVITY AND HOURS 233

Factors Affecting Labor Productivity 233

Historical Data 235

Field Observations 235

National Standards 238

Labor Hours 238

Conclusion 238

Problems 238

Reference 239
CONTENTS xvii

Chapter
21
LABOR RATES 240

Billable Hours 240

Wages 240

Cash Equivalents and Allowances 241

Payroll Taxes 242

Unemployment Insurance 242

Workers’ Compensation Insurance 244

General Liability Insurance 244

Insurance Benefits 244

Retirement Contributions 245

Union Payments 245

Other Benefits 245

Annual Costs and Burden Markup 245

Conclusion 247

Problems 247

References 247

Chapter
22
EQUIPMENT COSTS 248

Depreciation and Interest 248

Taxes and Licensing 249

Insurance 249

Storage 249

Hourly Ownership Cost 249

Tires and Other Wear Items 250

Fuel 250

Lubricants and Filters 250

Repair Reserve 251

Leased Equipment 251

Rented Equipment 251

Conclusion 252

Problems 252

Chapter
23
CREW RATES 254

Conclusion 256

Problems 256
xviii CONTENTS

Chapter
24
SUBCONTRACT PRICING 257

Request for Quote 257

Writing a Scope of Work 258

Historical 259

Bid Selection 259

Conclusion 259

Problems 260

Chapter
25
MARKUPS 261

Building Permits 261

Payment and Performance Bonds 263

Profit and Overhead 263

Conclusion 265

Problems 265

Reference 266

Chapter
26
PRICING EXTENSIONS 267

Detail Worksheet 267

Material Costs 267

Labor Costs 268

Equipment Costs 268

Total Cost 269

Summary Worksheet 269

Sample Estimate: The Residential Garage 272

Conclusion 276

Problems 276

Chapter
27
AVOIDING ERRORS IN ESTIMATES 277

List Cost Codes 277

Spend More Time on Large Costs 277

Prepare Detailed Estimates 277

Mark Items Counted during the Quantity Takeoff 278

Double-Check All Takeoffs 278

Include Units in Calculations 278


CONTENTS xix

Automate with Spreadsheets 278

Use Well-Tested and Checked Formulas 278

Double-Check All Calculations 279

Perform Calculations in Two Ways 279

Drop the Pennies 279

Have Someone Review the Estimate 279

Review Each Cost Code as a Percentage of the Total Cost 279

Check Unit Costs for Each Cost Code 279

Compare Costs to Those for Another Project 279

Allow Plenty of Time 279

Conclusion 280

Problems 280

PA R T
IV
FINALIZING THE BID 281

Chapter
28
SUBMITTING THE BID 282

Bid Submission with Standardized Documents 282

Writing a Proposal 282

Writing a Business Letter 285

Letter Formats 286

Writing E-mails 286

Conclusion 288

Problems 288

Chapter
29
PROJECT BUYOUT 289

Subcontracts 289

Purchase Orders 291

Contracts for Materials 292

Conclusion 292

Problems 292

Chapter
30
THE ESTIMATE AS THE BASIS OF THE SCHEDULE 293

Estimating Durations 293

Sample Durations: The Residential Garage 294

Conclusion 294

Problems 294
xx CONTENTS

Chapter
31
ETHICS 295

Work Ethic 295

Bidding Practices 296

Loyalty to Employer 296

Ethical Dilemmas 296

Conclusion 296

Problems 296

Reference 296

PA R T
V
ADVANCED ESTIMATING WITH EXCEL 297

Chapter
32
CONVERTING EXISTING FORMS 298

Creating the Layout 298

Adding Formulas 298

Automating with Macros 301

Testing the Worksheets 306

Adding Error Protection 307

Conclusion 314

Problems 314

Chapter
33
CREATING NEW FORMS 315

Planning New Forms 315

Setting Up the Spreadsheet 319

Series 320

Naming Cells 323

Adding Dropdown Boxes 325

Referencing Worksheets in a Formula 328

Concatenate 329

LOOKUP and VLOOKUP 332

Conclusion 337

Problems 377

Chapter
34
PROPOSALS AND BEYOND 338

And Beyond 340


CONTENTS xxi

Appendix
A
REVIEW OF ESTIMATING MATH 341

Lengths 341

Scaling 342

Pythagorean Theorem 344

Areas 344

Volumes 350

Conversion Factors 352

Appendix
B
SAMPLE JOB COST CODES 354

Appendix
C
SAMPLE LABOR PRODUCTIVITY RATES 359

Appendix
D
MODEL SCOPES OF WORK 364

Footings and Foundations 364

Framing 364

Finish Carpentry 365

Drywall 365

Floor Coverings 366

Painting and Staining 366

Fire Sprinklers 367

Plumbing 367

HVAC 367

Electrical 368

Earthwork and Utilities—Roads and Parking Lots 368

Landscaping 369

Appendix
E
GLOSSARY 370

Appendix
F
INDEX OF DRAWING SETS 377

INDEX 378
This page intentionally left blank
Construction Estimating Using Excel
This page intentionally left blank
P A R T O N E

INTRODUCTION TO
ESTIMATING

Chapter 1 The Art of Estimating


Chapter 2 Overview of the Estimating and Bidding Process
Chapter 3 Introduction to Excel

I
n this section, you will be introduced to the art of estimating, the esti-
mating process, and Microsoft Excel 2010. These chapters will prepare
you for the rest of the book. For those of you who struggle with math or
just want to review the mathematical principles used in estimating, a review
of estimating math is given in Appendix A.
CHAPTER ONE

THE ART OF
ESTIMATING

In this chapter you will be introduced to the art of estimating. estimator is responsible for seeing that the estimate accu-
You will learn what it takes to become a good estimator, the rately determines the quantity of materials, labor, and equip-
components of a bid package, and the tools used by an estima- ment and incorporates the costs to complete the required
tor. Finally, you will be introduced to computerized estimating. scope of work along with a reasonable profit while remaining
competitive with other firms in the market. Great skill is re-
quired to balance the need to be competitive with the need to

E
be profitable.
stimating is the process of determining the expected
To be a good estimator a person must possess the fol-
quantities and costs of the materials, labor, and
lowing skills:
equipment for a construction project. The goal of
the estimating process is to project, as accurately as possible, 䊉 An estimator must have a sound understanding of the con-
the estimated costs for a construction project, as well as the struction methods, materials, and the capacities of skilled
required amount of materials, labor, and equipment neces- labor. Because of the great variety of work, it is impossible
sary to complete the work. The American Institute of for an estimator to be versed in all forms of construction.
Architects defines the work as “the construction and services Therefore, an estimator must specialize in one or more
required by the Contract Documents . . . and includes all areas of construction. An estimator may specialize in a
other labor, materials, equipment and services provided . . . subcontractor trade such as electrical, mechanical, or ex-
by the Contractor to fulfill the Contractor’s obligations.”1 cavation. An estimator may also specialize in an area of
The work is often referred to as the scope of work. construction such as residential, tenant finish, or highway
Estimating plays a key role in the operation of construc- construction. Because the methods of construction, the
tion companies. Accurate estimates are needed for a com- preferred materials of construction, and the skill of labor
pany to be successful in the bidding process while maintain- vary from market to market, estimators must also special-
ing a reasonable profit margin. If the estimates are too high, ize in a specific market area, such as a state or region.
the company may starve to death because of the lack of 䊉 An estimator must possess the basic skills needed to de-
work. If the estimates are too low, the company may lose termine the quantities of materials, labor, and equipment
money and go bankrupt. The estimator is constantly walking necessary to complete a project. This requires the estima-
a fine line between bidding too low and too high. tor to read blueprints, understand the design that the
architect or engineer has specified, and determine the
quantities needed to complete the project. Because much
THE ESTIMATOR of an estimator’s time is spent working with quantities,
The estimator is the person responsible for preparing the cost estimators must have strong mathematical skills. A review
estimates. Large companies may employ an estimating de- of estimating math is given in Appendix A.
partment with one or more full-time estimators. The esti- 䊉 An estimator must be a good communicator, both verbally
mating department is often charged with preparing all of the and in written form. Part of an estimator’s job is to obtain
company’s estimates. In smaller companies, the project man- pricing from vendors and subcontractors. To do this, the
agers or the company’s owner may be responsible for prepar- estimator must convince vendors and subcontractors to
ing the estimates. Regardless of their job title, employees who bid on projects, communicate what pricing is needed,
are responsible for preparing estimates are estimators. The and—when the company has won the job—communicate
2
The Art of Estimating 3

the responsibilities of the vendors and subcontractors 䊉 When reading the example problems that are based upon
in the form of purchase orders and subcontracts provided the garage drawings that accompany this book, refer to
to the vendor, subcontractor, superintendent, and so forth. these drawings and see if you can get a similar quantity of
Estimators may also be required to present estimates to materials. Minor differences will occur due to difference
owners—which requires good presentation skills—or pre- in rounding.
pare proposals—which requires good writing skills. 䊉 Complete all of the computer exercises and sidebars. Take
䊉 An estimator must possess strong computer skills. Much of existing sidebars and customize them to your estimating
today’s estimating is performed using computer software situation. This will help you to become proficient with
packages, such as Excel, takeoff packages such as On-Screen Excel.
Takeoff, and estimating software packages. Estimators also 䊉 Work all of the problems at the end of the chapters. Have
need to be able to prepare contracts, proposals, and other your instructor or a fellow estimator look over your solu-
documents using a word processing program. tions. These problems have been provided to give you
䊉 An estimator must be detail-oriented. Estimators must practice in solving simple estimating problems.
carefully and accurately determine the costs and quanti- 䊉 Prepare complete estimates for the Johnson Residence
ties needed to complete the project. Simple mistakes— and West Street Video projects listed in Appendix F. Have
such as forgetting that the drawings are half-scale or not your instructor or a fellow estimator look over your esti-
reading the specifications carefully enough to realize that mate. (The loose project drawings are provided in a sepa-
an unusual concrete mix has been specified—can quickly rate package shrink-wrapped to this text.)
turn a successful project into an unprofitable job and, in
extreme cases, bankrupt a company. In addition to these things, practice estimating when-

ever you get the chance. Volunteer to help an estimator with
An estimator must have the confidence to quickly prepare
his or her estimate. Ask questions of fellow estimators.
takeoffs and make decisions under pressure. Bid days are
Remember, learning to estimate takes time.
hectic. Many vendors and subcontractors wait until the
last hour to submit their bids. As the bid closing ap-
proaches, the estimator must compare and incorporate
new pricing as it is received and fill in missing pricing TYPES OF ESTIMATES
with limited time and information at his or her disposal.
There are three common types of estimates. They are the
Making a bad decision or failing to make a decision under
conceptual estimate, preliminary estimate, and final or de-
pressure can cause the company to lose the bid or take an
tailed estimate.
unprofitable job.
The conceptual estimate is an estimate prepared while
䊉 Finally, an estimator must have a desire for constant im- the project is still in a conceptual state. The conceptual esti-
provement. Much of a company’s success or failure rides mate is used to study the feasibility of a project or to compare
on the abilities of the estimator to obtain profitable work. two potential design alternatives (for example, a concrete
Because of the high degree of uncertainty in estimating structure versus a steel structure or three stories versus four
costs, estimating is more of an art than a science. As with any stories). These estimates are based on a description of the
art, only by practicing can one become a good estimator. project or on very limited drawings and as such are the least
One would not expect to become a good pianist after a few accurate type of estimate.
lessons. It takes practice. Likewise, becoming a good estima- The preliminary estimate is an estimate prepared from a
tor takes practice. But practice is not enough. Practicing bad partially completed set of drawings. A preliminary estimate
estimating skills will only turn a person into a bad estimator. is often performed when the drawings are 35% to 50% com-
Truly, practice makes permanent. To be a good estimator, a plete and is used to check to see if the proposed design is on
person must practice using good estimating skills; and for a budget and to identify changes to the design that need to be
person to practice good estimating skills, he or she must made to meet the budget. Preliminary estimates may be per-
have a sound understanding of the fundamental principles formed any time before the bid. Preliminary estimates are
of estimating. This understanding can only be obtained by more accurate than conceptual estimates because more de-
studying the art of estimating. sign information is available.
If you want to become a good estimator, it is very im- Final or detailed estimates are used to prepare bids and
portant to study and practice estimating. The following is a change orders, order materials, and establish budgets for
list of things that you can do as you read this book to become construction projects. They are prepared from a complete or
a good estimator: nearly completed set of drawings and are the most accurate
type of estimate.
䊉 Carefully read each chapter. The chapters provide you Sometimes shortcuts methods (methods which produce
with explanations of the basic principles of estimating. a close, but less accurate answer) are used to prepare bids in
䊉 As you read each example problem, check the math with a order to bid more projects in less time. This may save time
calculator. This will help you to gain a greater under- during the bidding process, but can cause cost-control prob-
standing of the estimating principles. lems for the company. When shortcut methods are used to
4 CHAPTER ONE

order materials, the wrong materials or wrong quantities are description, contact information for the owner and
often delivered to the site, which results in delays and in- design professional (architect or engineer), bid date,
creased construction costs. When a shortcut method pro- restrictions on bidders, expected price range, and the
duces a quantity within a few percent of the correct answer it expected duration of the project.
is hard to determine if a quantity overrun is due to poor ma- Bid Instructions: Bid instructions are instructions that
terial use in the field or inaccuracy in the estimating process. must be followed to prepare a complete bid. The goal
Similarly, when a quantity underrun occurs, it is unclear if it of the bid instructions is to help the bidders provide a
is due to good material use in the field or inaccuracy in the complete bid with all the necessary documents (for
estimating process. For cost-control purposes, it is impor- example, bid bond and schedule of values). Bidders
tant to have an accurate quantity and costs estimate for all may be disqualified for not following these instruc-
items, including an estimate for both unavoidable and tions, which may result in a bidder losing the job even
avoidable waste. Unavoidable waste is waste that is a result of though he or she was the low bidder.
the difference between design dimensions and the size of Bid Documents: Public agencies and owners typically
materials. For example, when carpeting a nine-foot by nine- use standard forms for the submission of the bid.
foot room with carpet that comes in 12-foot-wide rolls, you These forms may include bid forms, bid-bond forms,
will have a three-foot-wide strip of waste unless it can be a schedule of values, and contractor certifications. A
used elsewhere. Avoidable waste is waste that can be avoided sample bid form is shown in Figure 1-1. The bid bond
by good use of materials in the field. It is not uncommon to is discussed in the next paragraph. The schedule of
have one framing crew use 5% more materials to frame the values breaks the bid into smaller portions and is
same house as another crew. The extra materials used are used to determine and evaluate the amount of the
avoidable waste. Avoidable waste also includes materials that progress payments. A sample schedule of values is
are damaged or destroyed on the job. shown in Figure 1-2. Estimators should read these
The primary focus of this book is on preparing accurate documents carefully and comply fully with their re-
final or detail estimates, although many of these principles quirements. Bidders can be disqualified for not sub-
apply to conceptual and preliminary estimates. mitting all of the required bid documents.
Bonds: Bonds include the bid bond, the payment
BID PACKAGE bond, and the performance bond. Bonds are issued
by sureties. Bid bonds are provided by the contractor
Estimates are prepared from bid packages. The bid package at the time of the bid. The bid bond guarantees that
defines the scope of work for the construction project. Bid the contractor—should he or she be the low bidder—
packages range from a sketch on the back of a napkin to a will sign the contract and provide the payment and
well-developed set of plans and specifications consisting of performance bonds. The payment and performance
hundreds of sheets of drawings and a multivolume project bonds are provided when the contract for the work is
manual. A well-developed bid package includes a set of plans signed. The payment bond guarantees that the ven-
and a project manual. dors, subcontractors, and labor will be paid for the
The plans graphically show building dimensions and work they perform on the project. In the event that
where different materials are used. The process of converting the vendors, subcontractors, and labor are not paid
the building dimensions and details into estimated quanti- on the project, the surety will step in and make the
ties is known as the quantity takeoff. The estimator will pre- necessary payments. The performance bond guaran-
pare the bid from the quantity takeoff. Typically, the plans tees that the contractor will complete the construc-
are organized as follows: civil plans, architectural plans, tion project. In the event that the contractor fails to
structural plans, mechanical and plumbing plans, and elec- complete the project, the surety will step in and com-
trical plans. The project manual provides a lot of informa- plete the project. Providing payment and perfor-
tion for the bidder. The typical project manual includes the mance bonds can increase the costs of the project by
following items: 1% to 2%.
Invitation to Bid: The purpose of the invitation to bid Contract: Public agencies and owners often use stan-
is to invite bidders to bid on the project and give a dard contracts. Estimators should read the contract
bidder enough information to decide whether he or carefully and include any costs associated with meet-
she wants to bid on the project. Often, public agen- ing the terms of the contract in their bid.
cies are required to invite all qualified bidders to bid General Conditions: Public agencies and owners often
on the work. This is typically done by posting the in- use standard general conditions. General conditions
vitation to bid in a few predetermined locations (for affect the cost to complete the work. The general
example, the local library and the public agency’s of- conditions identify the relationships among the
fice) and by printing it in the local newspaper. The owner, design professionals, and the contractor and
invitation to bid is also placed at the front of the pro- addresses provisions that are common to the entire
ject manual. The invitation to bid provides a project project; for example, how changes in the scope of
The Art of Estimating 5

FIGURE 1-1 Bid Form

work are to be processed or the need for cleanup. complete. The specifications are typically organized
Estimators should read the general conditions care- according to the MasterFormat.2 The 2004 edition
fully and include any costs associated with the general expanded the MasterFormat from 16 divisions to 50
conditions in their bid. divisions (00 to 49).3 The 2010 MasterFormat is orga-
Special Conditions: Special conditions are additional nized as follows:
conditions that apply to this specific project. Like the Division 00: Procurement and Contracting
general conditions, the special conditions affect the Requirements
cost to complete the work. Estimators should read the Division 01: General Requirements
special conditions carefully and include any costs as-
Division 02: Existing Conditions
sociated with the special conditions in their bid.
Division 03: Concrete
Technical Specifications: Technical specifications
identify the quality of materials, installation proce- Division 04: Masonry
dures, and workmanship to be used on the project. Division 05: Metals
The specifications also specify the submittal and Division 06: Wood, Plastics, and Composites
testing requirements for individual building compo- Division 07: Thermal and Moisture Protection
nents. Estimators must read these carefully and un-
Division 08: Openings
derstand their implications. Bidding the wrong speci-
fication can lead to losing the bid unnecessarily or Division 09: Finishes
winning a bid that you do not have sufficient funds to Division 10: Specialties
6 CHAPTER ONE

FIGURE 1-2 Schedule of Values

Division 11: Equipment Division 43: Process Gas and Liquid Handling,
Division 12: Furnishings Purification, and Storage Equipment
Division 13: Special Construction Division 44: Pollution and Waste Control Equipment
Division 14: Conveying Equipment Division 45: Industry-Specific Manufacturing
Division 21: Fire Suppression Equipment
Division 22: Plumbing Division 46: Water and Waste Equipment
Division 23: Heating, Ventilating, and Air Division 48: Electrical Power Generation
Conditioning (HVAC) Other Inclusions: Other documents, such as a soils re-
Division 25: Integrated Automation port and environmental inspections, may be included
in the project manual. The soils report describes the
Division 26: Electrical
soil conditions and the water table at the construc-
Division 27: Communications tion site, which greatly affect the excavation costs.
Division 28: Electronic Safety and Security Estimators should take this information into account
Division 31: Earthwork when preparing an estimate for a project.
Division 32: Exterior Improvements Included by Reference: Other documents may be in-
Division 33: Utilities cluded in the specifications by reference. Documents
Division 34: Transportation included by reference are not physically attached to
the project manual but are treated as if they were.
Division 35: Waterway and Marine Construction
Documents that are often included by reference in-
Division 40: Process Integration clude standard agency specifications and other readily
Division 41: Material Processing and Handling available standards (for example, American Society
Equipment for Testing and Materials [ASTM] and American
Division 42: Process Heating, Cooling, and Drying National Standards Institute [ANSI] standards).
Equipment Estimators need to understand the implication of
The Art of Estimating 7

these standards because they affect how the work is


performed or are used to determine compliance with
a specification.

ESTIMATING TOOLS
The estimator has a number of tools at his or her disposal to
help prepare the estimate. They range from simple paper
forms to powerful estimating computer programs. An esti-
FIGURE 1-3 Architect’s Scale (bottom) and Engineer’s
mator’s tools include the following:
Scale (top)
Architect’s and Engineer’s Scales: Plans are prepared
at a reduced scale. Architect’s and engineer’s scales
have an unlimited number of scales and can perform
allow the estimator to measure dimensions from the
mathematical functions on distances and areas. A
plans. The architect’s scale typically includes the fol-
digitizer is shown in Figure 1-5.
lowing scales: 1⬙ ⫽ 1⬘, 1/2⬙ ⫽ 1⬘, 1/4⬙ ⫽ 1⬘, 1/8⬙ ⫽ 1⬘,
3/16⬙ ⫽ 1⬘, 3/32⬙ ⫽ 1⬘, 3/4⬙ ⫽ 1⬘, 3/8⬙ ⫽ 1⬘, 11/2⬙ ⫽ 1⬘, Takeoff Packages: The digitizer is being replaced by
and 3⬙ ⫽ 1⬘. The engineer’s scale typically includes takeoff packages, such as On Center Software’s On-
the following scales: 1:10, 1:20, 1:30, 1:40, 1:50, and Screen Takeoff and Trimble’s Paydirt that allows the
1:60. Architect’s and engineer’s scales are shown in user to determine the quantity of material needed
Figure 1-3. from a digital set of drawings. These software packages
Plan Measurer: A plan measurer or wheel measures the
length of a line by rolling the wheel of the measurer
along the item to be measured. A plan measurer has
the advantage of being able to follow curved lines
more easily than an architect’s or engineer’s scale.
Analogue plan measurers have fixed scales, such as
1/2⬙ ⫽ 1⬘, 1/4⬙ ⫽ 1⬘, and 1/8⬙ ⫽ 1⬘; digital plan mea-
surers have more scales available and often include
the ability to create custom scales. A digital plan mea-
surer is shown in Figure 1-4.
Digitizer: A digitizer consists of an electronic mat and
stylus or puck. The digitizer can measure distances
and areas. The digitizer may operate as a stand-alone
tool or be connected to a software package. Digitizers FIGURE 1-4 Digital Plan Measurer

FIGURE 1-5 Digitizer


8 CHAPTER ONE

make determining the length, perimeter, area, and hollow-metal door frame for a pair of doors that must be de-
volume quick and easy. On-Screen Takeoff will even livered to the tenth floor of an office building up a small ele-
allow the user to determine the length of the perime- vator must be constructed in pieces and fabricated on site,
ter, number of tiles, and length of grid needed for a whereas most door frames are constructed as a single mem-
dropped acoustical ceiling by having the estimator ber. Computers are good for performing repetitive tasks
trace the perimeter of the ceiling. These software quickly without error. They are good for handling the mind-
packages can be integrated with spreadsheet or other less and boring tasks such as totaling a column for the
estimating packages. umpteenth time. Estimators can make a minor change to an
Calculator and Paper Forms: In the days before com- estimate and the computer will calculate the changes to the
puters, most estimates were prepared by using paper estimate almost instantaneously.
estimating forms and calculators. Some estimates are Another danger of just entering data into the computer is
still prepared in this way, particularly estimates that that computer spreadsheets and formulas in estimating pack-
are prepared in the field; however, with modern lap- ages are developed for a limited number of circumstances
top computers and portable printers, even paper esti- based on a set of assumptions made by the writer of the
mates in the field are being replaced by computerized spreadsheet or formula. Whenever the estimator uses the
estimates. spreadsheet or formula on a situation that is outside the condi-
Spreadsheets: With the increased use of computers in tions anticipated by the developer, the estimator may get an in-
the construction industry and spreadsheet programs accurate estimate from the spreadsheet or formula. To protect
such as Excel, many companies have converted their against this, the estimator must have an understanding of the
estimating forms into computer spreadsheets. limits and design of the spreadsheet or formula and must make
Spreadsheets have the advantage of automating the sure the spreadsheet’s or formula’s response is reasonable.
calculations and allowing the estimator to see the ef- The second mistake is to create a new spreadsheet or
fects of minor changes in seconds. Developing formula and use it without properly testing it. After creating
spreadsheets for use in estimating is the topic of Part a spreadsheet or formula, the developer should test the
V of this book. spreadsheet or formula to make sure it is working properly,
not only on the situation that it was developed for, but on
Estimating Software: Estimating software packages,
other conceivable situations. In addition, the developer
such as Timberline Precision Estimating, combines
should try to make the spreadsheet or formula mess up and
the advantages of a computer spreadsheet with a data-
then build in ways to prevent other users from making the
base. This automates the estimating even further.
same mistakes by building in error-checking procedures.
Estimating software has the additional advantage of
Excel is the most popular estimating package. In a sur-
being capable of taking off assemblies as a single item.
vey performed by the American Society of Professional
For example, an estimator can take off a wall assembly
Estimators, 29% of the respondents reported using Excel as
that includes the top and bottom plates, the studs, in-
their estimating software, 22% reported using Timberline,
sulation inside the wall, and the finish material on both
and 25% reported using another estimating software pack-
sides of the wall as a single component. Estimating
age such as WinEst (WinEstimator, Inc.) and HeavyBid
software also allows the estimator to print the bid in-
(Heavy Construction System Specialists, Inc.).4 Users of esti-
formation in different formats for different uses with
mating packages commonly augment the software package
little or no setup.
with Excel worksheets to assist in the quantity takeoff and
other support functions.
Spreadsheets have the advantage of being inexpensive.
COMPUTERIZED ESTIMATING Spreadsheet software can be purchased for about $100 and is
Nothing has revolutionized estimating as much as the ad- often included along with other standard applications—
vent of computers along with spreadsheets, estimating soft- such as word processing—that are sold as a software package
ware, and takeoff packages. If used correctly, computers can for use in offices. In addition to being inexpensive, spread-
reduce the time needed to prepare an estimate and decrease sheets are easily adapted to the existing style and estimating
the errors in the estimate. If used improperly, they can in- procedures of the company. A company that uses paper
crease the number of errors in an estimate and decrease the forms can easily create a look-alike form in the spreadsheet
usefulness of the estimate. There are two dangerous mistakes and let the software perform the mundane and tedious cal-
estimators make when using estimating packages. culations. Finally, spreadsheets are easy to create. With a little
The first mistake is to turn the thinking over to the com- training and effort, anyone can develop spreadsheets for esti-
puter so the estimator becomes simply a means of entering mating. Developing spreadsheets for estimating in Excel is
data into the software package. The estimator determines the the topic of Part V of this book.
quantity of a given component and enters it into the com- Estimating software packages are powerful computer
puter without giving any thought to job conditions and design software applications that have been developed specifically
requirements that may require this component to be handled for estimating. There are a number of packages available,
in a different way than it is usually handled. For example, a with some packages having been designed for building
The Art of Estimating 9

construction and others for heavy and highway construction For example, one can print the costs by line item with the
that involves large amounts of earthwork. Estimating soft- sales tax appearing at the bottom of the report or one can
ware packages have the advantage of automating the takeoff have the sales tax allocated to the individual line items. All
process and decreasing the time it takes to prepare an esti- these features come at a price. Estimating software packages
mate by combining a spreadsheet with a database. The data- are more expensive than spreadsheets—often costing thou-
base contains a list of standard items along with their cost, sands of dollars. In addition to the dollar costs, they require
labor productivity, labor rates, equipment costs, and formu- a large time investment to set up and maintain the database.
las used to calculate the quantities and costs of the individual The pricing in the database must be kept current with mar-
items. Estimating packages often allow the user to create as- ket pricing, materials must be set up, formulas must be writ-
semblies—a group of items that are needed to create a com- ten and tested, and assemblies must be created. Companies
ponent such as a wall—and take off the assembly in a single must perform large amounts of estimating to justify the cost
step. Another feature of estimating packages is that the data and time commitment involved in using an estimating soft-
can be easily manipulated and printed in different formats. ware package.

CONCLUSION 9. What are the advantages and disadvantages of using


spreadsheets for estimating?
Successful estimates are the lifeblood of a construction com- 10. What are the advantages and disadvantages of using es-
pany. Winning bids while maintaining a good profit margin timating packages, such as Timberline, for estimating?
is necessary for a construction company to succeed. Accurate
quantities and costs are needed for strong cost controls. To
be a good estimator, a person must study and practice sound
principles of estimating. Computers have greatly changed REFERENCES
the way estimators prepare estimates. Computers and soft- 1. General Conditions of the Contract for Construction, American
ware packages, if used properly, can increase the productiv- Institute of Architects, AIA Document A201-1997, p. 9.
ity of the estimator while decreasing errors. Estimating soft- 2. The Numbers and Titles used in this textbook are from Master-
ware includes spreadsheet packages such as Excel, estimating FormatTM published by The Construction Specifications
software such as Timberline, and takeoff packages, such as Institute (CSI) and Construction Specifications Canada (CSC),
On-Screen Takeoff. and are used with permission from CSI, 2010.
For a more in-depth explanation of MasterFormatTM and
its use in the construction industry visit www.csinet.org/
PROBLEMS masterformat or contact:
The Construction Specifications Institute (CSI)
1. Define estimating. 110 South Union Street, Suite 100
2. Define work or scope of work. Alexandria, VA 22314
800-689-2900; 703-684-0300
3. What role does estimating play in the success of a con- CSINet URL: http://www.csinet.org
struction company? 3. Divisions 15 to 20, 24, 29, 30, 36 to 39, 46, 47, and 49 are re-
4. What is the role of an estimator? served for future use.
5. What skills are required to be a good estimator? 4. American Society of Professional Estimators, 2003 ASPE
Cost Estimating Software Survery, available at http://www.
6. Why is practice important for an estimator?
aspenational.com/cgi-bin/coranto/viewnews.cgi?id=EpZk
7. What role does the bid package play in estimating? ZkupuyHEPGialt&tmpl-fullstory&style=fullstory; accessed
8. What tools are available to estimators? February 4, 2004.
CHAPTER TWO

OVERVIEW OF THE ESTIMATING


AND BIDDING PROCESS

In this chapter you will be introduced to the estimating and the cost codes, the estimator needs to identify any
bidding process and gain an understanding of the steps needed items that may be difficult to find a price for (for ex-
to complete an estimate. The purpose of this chapter is to give ample, an indoor pistol range and other specialty
you an overview of the process so that as you read the subse- equipment) and any special items (such as a bid
quent chapters you will have a better idea of how they fit into bond, submission of a prequalification package, or
the estimating and bidding process. attendance at a pre-bid meeting) that are required of
the bidders.
Scheduling the Bid: Once the scope of the project has

O nce the bid package is complete, a detailed esti- been determined, the estimator must schedule the
mate is needed to establish a budget for the project tasks necessary to complete the bid such that the bid
and, in the case of competitive bidding, selection is completed in time to be submitted. If there is insuf-
of the contractor. This chapter looks at the process of ficient time to complete the bid, the estimator must
preparing a detailed estimate for a competitive bid project. get additional help, eliminate some of the estimating
Preparing a preliminary estimate during the design process steps, or decide not to bid on the project.
or preparing an estimate for a change order follows a similar Assigning Tasks: If the estimating team consists of
process. Preparing an estimate for a competitive bid project more than one person, once the scope of work has
is divided into four phases: planning the bid, pre–bid-day been identified and a schedule prepared for the bid
activities, bid-day activities, and post-bid activities. An package, the estimator must delegate the bidding
overview of these steps is shown in Figure 2-1. tasks to other members of the team and communi-
cate the deadlines for the completion of these tasks
to the team members. For example, for a bid that re-
PLANNING THE BID quires the use of in-house crews and requires a
Planning the bid consists of identifying the scope of work for schedule to be submitted as part of the bid, the esti-
the project, preparing a schedule for the bidding process, mator may assign the estimating of the in-house
and assigning tasks to members of the estimating team. work to the person responsible for the in-house
crews and the preparation of the schedule to the
Scope of Work: During the planning stage the estimator company’s scheduler.
needs to identify the general scope of work covered by
the bid package. Often, this is done by reviewing the
bid package and identifying which of the company’s
cost codes are needed for the project and what pric-
PRE–BID-DAY ACTIVITIES
ing needs to be obtained to complete the estimate. The pre–bid-day activities are activities or tasks that should
Many companies have standard summary sheets, like be completed before the day of the bid. The activities include
the one shown in Figure 2-2, where the estimator ordering the bid bond, requesting quotes from subcontrac-
marks the cost codes in the left column that he or she tors, completing the quantity takeoff, obtaining material
needs pricing for to complete the estimate. This pric- pricing from vendors, pricing in-house labor, pricing equip-
ing may come from suppliers or subcontractors or ment, determining project overhead, and preparing the bid
may be estimated in-house. In addition to identifying documents.
10
Overview of the Estimating and Bidding Process 11

FIGURE 2-1 The Estimating Process

Order Bond: One of the first activities that should be on the project and requesting quotes from these
done is to order a bid bond from the surety company. subcontractors. Starting this process early is impor-
This gives the surety time to prepare the bid bond, tant because subcontractors need to find the time to
obtain the necessary signatures on the bond, and mail look at the plans and project manual and prepare
it to the contractor. By ordering the bond early the their estimate. When dealing with a limited number
contractor eliminates the need to make a special trip of plan sets it can be quite a challenge to give all of the
to the surety’s office to pick up the bond. The estima- subcontractors a chance to look at the plans within
tor also finds out early in the bidding process if there the allowed time for the bid. When dealing with a
will be any problem getting the bond before spending limited number of plan sets, the goal of the estimator
a lot of time preparing the estimate. This is important should be to get one subcontractor to bid in each cat-
if the engineer’s or architect’s estimate is near the egory of work before getting second and third bids.
contractor’s bonding limits. By doing this the contractor has a bid for each cate-
Request Subcontractor Quotes: Another step that gory of work rather than having multiple bids in one
must be completed early in the bid process is identi- category and no bid in another category. In addition,
fying which subcontractors need to be invited to bid the contractor should try to get bids on the high-dollar
12 CHAPTER TWO

FIGURE 2-2a The Summary Worksheet

items first because these items carry the most risk that their quantities are accurate, and the estimator
should the contactor have to bid these items himself should prepare his or her own quantity takeoff to
or herself. Preparing requests for subcontractor make sure there are sufficient quantities of materials
quotes is discussed in Chapter 24. to complete the work. If time allows, the estimator
Quantity Takeoff: After lining up subcontractors and should prepare quantity takeoffs for subcontractor
arranging for the bid bond, the next most important work where there is a concern that the subcontrac-
task is to prepare a quantity takeoff for the work to tor’s bid may not be received in time to complete the
be performed in-house. The quantity takeoff is nec- bid. The quantity takeoff is discussed in Part II of
essary to prepare material, labor, and equipment this book.
costs (unless the vendors are doing the quantity Materials Pricing: Estimators often send their quantity
takeoff for their work) for the estimate. If the ven- takeoffs to vendors and request that the vendors pro-
dors are preparing quantity takeoffs for their work, vide pricing for the materials identified in the quan-
the estimator should request a quote from these tity takeoff. This requires the quantity takeoff to be
vendors at the same time he or she requests quotes completed in time to send the list of needed materials
from subcontractors. Often vendors who prepare a to the vendors, have the vendors price the materials,
quantity takeoff for contractors do not guarantee receive a quote from the vendors, and incorporate the
Overview of the Estimating and Bidding Process 13

FIGURE 2-2b The Summary Worksheet

pricing into the estimate. Materials pricing is dis- equipment needs of the project and determine the
cussed in Chapter 19. cost of the equipment. This may include obtaining
Labor Pricing: Once the quantity takeoff has been rental pricing or pricing company-owned equip-
completed, the estimator can determine which crews ment. Pricing equipment is discussed in Chapter 22.
are to be used on the in-house work, the associated Project Overhead: Before the bid day, the estimator
productivity rates for the work, hourly crew costs, and should prepare an estimate for project overhead.
the cost of the labor to perform the in-house work. Project overhead includes all costs that are associ-
Labor productivity is discussed in Chapter 20, and de- ated with the project but cannot be identified with a
termining labor rates is discussed in Chapter 21. specific component of the project’s construction.
Equipment Pricing: Once the quantity takeoff has The project overhead should be prepared by prepar-
been completed, the estimator can determine the ing a quantity takeoff for the project overhead and
14 CHAPTER TWO

FIGURE 2-3a Overhead Checklist

putting costs to the quantities just as is done with combining the labor, material, equipment, subcontractor, and
material estimates. An overhead checklist is shown overhead pricing; incorporating markups; reviewing the bid
in Figure 2-3. for errors; and submitting the bid.
Prepare Bid Documents: Finally, the bid documents Subcontractor Selection: When receiving bids from a
need to be prepared and the appropriate signatures subcontractor, it is important for the estimator to
need to be obtained. Any incomplete items that must verify that the subcontractor has included the entire
be filled in on the day of the bid, such as the bid price scope of work for the items that the subcontractor is
and the prices for the schedule of values, should be bidding. Any items that are missing must be added to
marked with Post-Its to minimize the possibility of the estimate for it to be complete and to avoid having
forgetting to fill in a blank on the day of the bid. an incomplete estimate. In addition, the estimator
must make sure the bids from the subcontractors
used in the estimate do not include items that are in-
BID-DAY ACTIVITIES cluded in other subcontractor’s bids or their bids.
The bid-day activities are activities or tasks that are performed Including an item twice inflates the estimate, and the
predominantly on the day of the bid, although some of these contractor risks losing the bid because of poor esti-
activities may be started before the bid day. This is because mating practices. When bids for a bid item are avail-
most subcontractors wait until a few hours before the bid able from more than one subcontractor, the best sub-
deadline to submit their bids. As a result, bid days can be quite contractor must be selected. Selection may be made
hectic. Bid-day activities include selecting subcontractors; based on completeness of the scope of work, price,
Overview of the Estimating and Bidding Process 15

FIGURE 2-3b Overhead Checklist

and past experience with the subcontractor. When a none of the items have been included twice. Combining
subcontractor phones in a quote, the estimator the pricing should begin before bid day and often con-
should take careful notes as to what the subcontrac- tinues right up until the bid is submitted.
tor is bidding. This information should include the Add Markups: On the day of the bid, the estimator
bidder and contact information, project name, what should finalize the rates for the markups. Markups
the bidder is bidding, addends received, specific exclu- are also known as add-ons. Markups include the
sions, whether freight and sales tax are included, bid profit markup, overhead markup, building permit
price, the date and time the bid was received, and who costs, bonding costs, and sales tax. The profit markup
took the bid. The best way to do this is to fill out a is used to provide the owners of the construction
phone quote sheet such as the one shown in Figure 2-4. company a return on their investment. Often, the
Today, most phone quotes have been replaced by profit markup is adjusted based on the competition
faxed or e-mailed quotes; however, they should contain bidding on the project. As the estimator finds out
the same basic information. If any of this information which plan holders have dropped out of the bidding,
is missing, the subcontractor should be contacted and the profit margin is often adjusted. The overhead
the information obtained. markup is used to cover the company’s general over-
Combing Pricing: As the pricing becomes available, head costs. The project’s specific overhead should
the estimator should add the pricing to the bid. The not be included in the overhead markup but should
pricing includes pricing for labor, materials, equip- be bid as part of the project costs. The bonding
ment, subcontractor, and overhead. The estimator costs, and sometimes the building permit costs, are
should exercise caution to be sure that all items neces- based on the estimated construction costs, which are
sary to complete the bid are included in the bid and not known until the bid is completed. This requires
16 CHAPTER TWO

FIGURE 2-4 Phone Quote

the costs for these items to be calculated near the Care must be taken to accurately enter the pricing
completion of the bid. Sales tax may be added to the and make sure all remaining blanks are filled in. It
individual material costs or to the material costs of would be a great waste of time to lose the bid because
the bid as a whole. When added to the material costs you forgot to fill in a blank or you wrote the wrong
of the bid as a whole, the sales tax is treated as a price on the bid document. Submitting the bid is dis-
markup and is incorporated into the bid when the cussed in Chapter 28.
material costs are totaled. For cost control purposes,
the sales tax must be added to the individual cost
codes when preparing the budget for the project. POST-BID ACTIVITIES
Markups are discussed in Chapter 25.
Review Bid for Errors: As the bid approaches comple- The post-bid activities are different for jobs for which the
tion, the bid needs to be reviewed for errors. This in- contractor is the low bidder than they are for jobs for which
cludes making sure that there is pricing for all of the the contractor is not. Here are some of the activities that may
bid items, comparing the bid to historical costs for occur after the submission of the bid.
similar projects, and having someone else check the Bid Review: After completing the bid, the estimator
estimate for errors. Avoiding errors in estimates is should review the bid and the bidding process to
discussed in Chapter 27. identify any mistakes that were made and try to
Submit Bid: Finally, the price and other bid-day infor- find ways to avoid these mistakes in the future.
mation should be added to the bid documents, and Besides identifying mistakes, the estimator should
the bid should be submitted to the contracting office. look at what works and identify ways to make sure
Overview of the Estimating and Bidding Process 17

that he or she does the same things on future bids. database as needed at this time. The project buyout is
One of the characteristics of a successful estimator discussed in Chapter 29.
is that he or she is committed to continuous im- Close-Out Audit: The project close-out audit consists
provement. To do this, estimators must learn from of reviewing all activities completed during the con-
their mistakes and repeat those actions that made struction process, including the estimating process,
them successful. after the project is complete. As part of this audit, the
Project Buyout: If the estimator wins the bid, the esti- estimator should review the actual costs to complete
mator must buyout the project. The project buyout is the project and compare the costs against the original
the process of hiring subcontractors and procuring estimate. The goal is to find ways to improve the accu-
materials and equipment for the construction pro- racy of the estimate. The estimator should look at areas
ject. During the buyout the estimator must prepare where his or her pricing is too high or low so that his or
contracts for the subcontractor’s work and purchase her future estimates will reflect the actual costs, updat-
orders for the materials used on the project and com- ing the pricing in the pricing database as needed. For
municate this information to the subcontractors, the close-out audit to be useful, the actual costs must be
suppliers, and the general contractor’s project man- accounted for in the same cost categories as they were
agement team (the superintendent, project manager, included in the estimate. For this to happen a company
and so forth). During the buyout process the estima- must have a set of standardized job cost codes that
tor should identify any errors in the estimate and identifies the job cost and spells out what is included in
identify ways to avoid the errors in the future. The es- each cost code. This needs to be done in a formal docu-
timator should also update the pricing in the pricing ment. Sample job cost codes are found in Appendix B.

CONCLUSION 3. Why should subcontractor quotes be requested early in


the bidding process?
There are a number of activities that must be completed to 4. Why should you get one bid in each area you are going
complete the bid. The first group of activities comprises to subcontract out before getting a second bid?
planning the bid. This includes defining the scope of work,
5. Why should you get a bid on the high-dollar subcon-
scheduling the bidding activities, and assigning the activities
tractor items first?
to the members of the estimating team. The second group of
activities comprises the pre–bid-day activities. These include 6. Why should you prepare a quantity takeoff for mate-
ordering the bond; requesting subcontractor quotes; prepar- rials even when the supplier is preparing a quantity
ing the quantity takeoff; pricing materials, equipment, and takeoff?
labor; preparing an overhead budget; and preparing the bid 7. What is one way you can prevent the possibility of for-
documents. The third group of activities comprises the bid- getting to fill in a blank on the bid forms that needs to
day activities. These include selecting the subcontractors, be filled in on bid day?
combining all of the prices together into the bid, adding the 8. Why is it important for an estimator to verify that a sub-
markups, reviewing the bid for errors, and submitting the contractor’s bid has a complete scope of work?
bid. The fourth group of activities comprises the post-bid 9. What are some of the criteria that may be used to select
activities. These include reviewing the bid and, if one is suc- subcontractors?
cessful in winning the bid, buying the project out and per- 10. What should be recorded when taking a telephone
forming a project close-out audit at the end of the project. quote from a subcontractor or material supplier?
11. Why should you use phone quote sheets?
PROBLEMS 12. Identify five different types of markups.
1. What are some of the things you can do if there is insuffi- 13. What is the overhead markup used for?
cient time to complete the estimate before the bid is due? 14. Define the term buyout.
2. Why should the bond be ordered early in the bid 15. At what two points in a project should an estimator up-
process? date the pricing database?
CHAPTER THREE

INTRODUCTION
TO EXCEL

In this chapter you will be introduced to the basic operation of Clicking, unless otherwise noted, means left clicking.
Excel. This includes managing workbooks and worksheets, enter- Bold words in the text represent buttons, tabs, icons,
ing data, formatting spreadsheets, writing formulas, using a few radio buttons, items in dropdown boxes, and check
of the basic functions, printing, and testing worksheets. Those boxes that must be selected and keys that must be
who are just learning Excel should carefully read this chapter and typed to complete the exercises.
complete all of the exercises, whereas those who are experienced Italic words in the text represent text or numbers that
with Excel are encouraged to quickly skim this chapter and work must be entered in a spreadsheet cell or text box to
the exercises to pick up additional knowledge on how to get the complete the exercises.
most out of Excel. Exercises 3-1 through 3-5, 3-8, and 3-9 are
The <> brackets signify that the user must enter data
used as the starting point for the exercises in Chapter 32.
represented by the text between the brackets, such as
a file name. The appropriate data rather than the text
should be entered between the brackets. For example,

E xcel is a powerful spreadsheet program that can be


used to perform mathematical calculations. An Excel
file is known as a workbook and has an .xlsx or .xlsm
(for files that contain macros) extension at the end of the file
name indicating its file type. Files created with Excel 2003 or
if you are instructed to type <your name> and your
name is John Smith, you would type John Smith.

WORKBOOK MANAGEMENT
older have an .xls extension. The Windows operating system Workbook management consists of creating new work-
has the option not to display the file type, therefore, you may books, opening existing workbooks, and saving changes to
not see the file type on your computer display. workbooks. Let’s look at creating new workbooks.
The screenshot figures in this book are based on Excel
2010 running on Windows 7 with the Windows 7 Basic theme. Creating Workbooks
Figure 3-1 shows the typical layout for Excel 2010. Your layout
may look different based on the selected theme, version of the A new workbook is created by clicking on the Excel icon
operating system, version of Excel, width of your screen, and shown in Figure 3-2.
settings used on your computer. As the width of excel de- A new workbook can be created while working in an ex-
creases, large buttons are replaced with smaller buttons, which isting Excel workbook by typing Ctrl+N (typing the N key
are stacked on the ribbon; therefore, your ribbon may not while holding down the Ctrl key) to bring up a blank work-
look the same as the screenshots used in this book. If you have book or by selecting the File tab (the Microsoft Office but-
customized the ribbon it will look different. ton for Excel 2007), clicking on New in the left pane to bring
up the New Workbook dialogue box (shown in Figure 3-3),
and double clicking on Blank Workbook.
CONVENTIONS USED
IN THIS BOOK Opening Workbooks
The following conventions are used in this book to describe Existing workbooks can be opened by double clicking on the
actions that must be performed to set up a worksheet or file name in the Windows folder. Workbooks can also be
change the settings for a worksheet: opened from Excel by typing Ctrl+O (typing the O key
18
Introduction to Excel 19

FIGURE 3-1 Excel Layout

while holding down the Ctrl key) or selecting the File tab
(the Microsoft Office button for Excel 2007), and clicking
on Open in the left pane to bring up the Open dialogue box
shown in Figure 3-4. From the Open dialogue box, the user
selects the folder where the file is stored in the left side of the
dialogue box (the Look in: dropdown box for Windows XP)
FIGURE 3-2 Excel Icon
and opens the file by (1) double clicking on the file name or

FIGURE 3-3 Adding a New Workbook


20 CHAPTER THREE

FIGURE 3-4 Open Dialogue Box

(2) clicking on the file name and clicking the Open button. following exercise will take you step by step through the
Recently used files may be opened by selecting the File tab process. You are encouraged to take the time to create the
and selecting Recent (the Microsoft Office button for Excel spreadsheet on your computer. This spreadsheet is used as a
2007) to bring up the Recent Files dialogue box (shown in starting point for the subsequent exercises in this chapter
Figure 3-5) and clicking on the file name in the list of re- and the exercises in Chapter 32.
cently used documents in the right pane.
Exercise 3-1
Saving Workbooks
Workbooks are saved by clicking on the Save button on the First, you will create a folder where you will store the exer-
Quick Access toolbar, by typing Ctrl+S (typing the S key cises from this book using the following steps:
while holding down the Ctrl key), or by selecting the File tab
1. Open the Documents (My Documents in Windows XP)
(the Microsoft Office button for Excel 2007), and clicking
folder on your hard drive. If you would like to store the
on Save in the left pane. The first time a file is saved, any one
documents in another folder or drive, open the folder or
of these actions will bring up the Save As dialogue box
drive of your choice rather than the Documents folder.
shown in Figure 3-6. From the Save As dialogue box the user
selects the folder where the file is to be stored on the left side 2. Select the New Folder button (shown in Figure 3-7) to
of the dialogue box (in the Save in: dropdown box for create a new folder. For Windows XP, select File from
Windows XP), types the file name in the File name: drop- the Menu bar, then select New from the popup menu,
down box, and clicks on the Save button. and select Folder from the subsequent popup menu to
An existing workbook is saved under a different file create a new folder. The default name of the folder
name by selecting the File tab (the Microsoft Office button should be “New Folder” and if there is a folder already
for Excel 2007) and clicking on Save As in the left pane to named “New Folder,” the new folder has a number in
bring up the Save As dialogue box. The workbook is saved parentheses included as part of its name.
with a different file name in the same manner that the user 3. The folder’s existing name should be highlighted. If it is
saved a workbook the first time. not, right click on the newly created folder and select
Now that you know the basics of spreadsheet file man- Rename from the popup menu to highlight the folder’s
agement, you are ready to create your first spreadsheet. The name.
Introduction to Excel 21

FIGURE 3-5 Opening Recent Files

FIGURE 3-6 Save As Dialogue Box


22 CHAPTER THREE

FIGURE 3-7 New Folder Button

4. Type Excel Exercises and press the Enter key to change Chapter 03 in the File Name text box. The Save As dia-
the name of the folder to Excel Exercises. logue box should appear as it does in Figure 3-6.
5. Double click on Excel Exercises to open the folder. 8. Click the Save button to save the workbook.

Next, create and save a workbook using the following steps:

6. Open a new workbook in Excel by clicking on the Excel WORKING WITH WORKSHEETS
icon (shown in Figure 3-2) on your desktop or by select- An Excel workbook contains one or more worksheets. The
ing it from the Windows’ start menu. worksheets are marked by tabs at the bottom of the screen.
7. Save the workbook by selecting the File tab (the You may move from one worksheet to another by clicking on
Microsoft Office button for Excel 2007), clicking on these tabs. By default new workbooks contain three work-
Save in the left pane to bring up the Save As dialogue sheets named Sheet1, Sheet2, and Sheet3. You can add,
box, selecting the Excel Exercises folder in the right pane delete, rename, and change the order of the worksheets. Let’s
(Save in: dropdown box for Excel 2007), and typing begin by looking at adding worksheets.

EXCEL QUICK TIP 3-1


Setting the Number of Worksheets in a New Workbook
The number of worksheets that appear when a new work- Options (Excel Options for Excel 2007) to bring up the
book is created is changed by clicking on the File tab (the Excel Options dialogue box, selecting General (Popular for
Microsoft Office button for Excel 2007), clicking on Excel 2007) in the left pane, and under the When creating
Introduction to Excel 23

new workbooks heading in the right pane choosing the sheets: list box. The General tab of the Excel Options dia-
number of sheets to be included in the Include this many logue box is shown in the figure below:

Adding Worksheets
Blank worksheets are added to the workbook in three ways.
First, a blank worksheet may be added to the right of the ex-
isting sheets by clicking on the Insert Worksheet tab located
to the right of the sheet tabs (see Figure 3-1). Second, a blank
worksheet may be added to the left of the active worksheet
by selecting the Home menu tab, selecting the arrow below
the Insert button in the Cells group, and selecting Insert
Sheet from the popup menu as shown in Figure 3-8. If the
Home menu tab is already displayed you need not select it.

FIGURE 3-9 Popup Menu

Third, a blank worksheet may be added to the left of a work-


sheet by right clicking on the tab to the right of the location
where the worksheet is to be inserted and selecting Insert...
from the popup menu (shown in Figure 3-9) to bring up the
Insert dialogue box (shown in Figure 3-10). From the Insert
dialogue box the user selects Worksheet and clicks the OK
FIGURE 3-8 Home: Insert Popup Menu button to insert the worksheet.
24 CHAPTER THREE

FIGURE 3-10 Insert Dialogue Box

Copying Worksheets
A worksheet is copied by (1) right clicking on the worksheet
tab and selecting Move or Copy... from the popup menu
(shown in Figure 3-9) or (2) by selecting the Home menu
tab, selecting the arrow below the Format button in the Cell
group, and selecting Move or Copy Sheet... from the popup
menu as shown in Figure 3-11 to bring up the Move or Copy

FIGURE 3-12 Move or Copy Dialogue Box

dialogue box, shown in Figure 3-12. The user checks the


Create a copy check box and selects the location where the
new sheet is to be inserted in the Before sheet: list box. If
the worksheet is to be the last worksheet in the workbook,
the user must select (move to end) as the location of the
worksheet. The user can copy the worksheet to another
workbook or a new workbook by selecting the desired work-
book in the To book: dropdown box. To copy the worksheet
to an existing workbook, the workbook must be open so it
will appear in the To book: dropdown box.

Deleting Worksheets
Worksheets can be deleted by right clicking the tabs of the
unneeded worksheets and selecting Delete from the popup
menu (shown in Figure 3-9) or by selecting the Home
FIGURE 3-11 Home: Format Popup Menu menu tab, selecting the arrow below the Delete button in
Introduction to Excel 25

Renaming Worksheets
Worksheets are renamed in three ways: (1) by right clicking
the tab of the worksheet to be renamed and selecting
Rename from the popup menu shown in Figure 3-9, (2) by
double clicking on the tab, or (3) by selecting the Home
menu tab, selecting the arrow below the Format button in
the Cells group, and selecting Rename Sheet from the popup
menu as shown in Figure 3-11. The name of the tab will then
be highlighted and can be edited as one would edit text in a
word processor. After changing the name of the worksheet,
the user must click on any of the cells or press the Enter key
FIGURE 3-13 Home: Delete Popup Menu to save the name change.

the Cells group, and selecting Delete Sheet from the popup Organizing Worksheets
menu as shown in Figure 3-13. If the worksheet contains
The order of the worksheets tab can be changed by holding
data, a warning dialogue box (see Figure 3-14) will appear
down the left mouse button and dragging the worksheet to
warning you that data exists and giving you the opportunity
its new location. When the user holds down the left mouse
to cancel the delete. If you still want to delete the worksheet,
button, a little black arrow will appear and show where the
click on the Delete button. To cancel the delete, click on the
worksheet’s tab will be located (as shown in Figure 3-15).
Cancel button.
When the user releases the left mouse button, the worksheet
is moved to the new location.

EXCEL QUICK TIP 3-2


Selecting Multiple Cells or Worksheets
The Shift and Ctrl keys are used to select multiple cells or
worksheets at a time.
The Shift key is used to select contiguous blocks of
cells or worksheets. For example, Cells A12 through B13
are selected by clicking on Cell A12, holding down the
Shift key, and clicking on Cell B13. Cells A12, A13, B12,
and B13 will now be selected. The user must hold down
the Shift key after he or she has selected Cell A12, because
the selection will begin at the cell the cursor is in when
the Shift key is held down.
The Ctrl key is used to select noncontiguous cells.
For example, Cells A15 and B16 are selected by clicking
on Cell A15, holding down the Ctrl key, and clicking on
Cell B16. Cells A15 and B16 are now selected.
Both the Shift and Ctrl keys may be used to select a
group of cells. For example, Cells A12 through B13, Cell
A15, and Cell B16 are selected by clicking on Cell A12,
holding down the Shift key, clicking on Cell B13, releas-
ing the Shift key, holding down the Ctrl key, and clicking
on Cells A15 and B16.
FIGURE 3-15 Location Where Worksheet Will Be Inserted

FIGURE 3-14 Warning Dialogue Box


26 CHAPTER THREE

Alternatively, a worksheet can be moved by (1) right Next, change the names of the worksheets to “Summary”
clicking on the worksheet tab and selecting Move or Copy . . . and “Detail” using the following steps:
from the popup menu (shown in Figure 3-9) or (2) by select-
ing the Home menu tab, selecting the arrow below the Format 4. Change the name of the right worksheet to “Summary”
button in the Cell group, and selecting Move or Copy Sheet... by double clicking on the tab and, with the worksheet
from the popup menu, as shown in Figure 3-11, to bring up name highlighted, typing Summary.
the Move or Copy dialogue box, shown in Figure 3-12. The 5. Change the name of the left worksheet to “Detail” by
user must select the location where the worksheet is to be in- right clicking the tab of the worksheet, selecting
serted in the Before sheet: list box. If the worksheet is to be Rename from the popup menu (shown in Figure 3-9),
the last worksheet in the workbook, the user must select and, with the sheet name highlighted, typing Detail.
(move to end) as the location of the worksheet. The user can 6. Move the cursor to Cell D1 by clicking on Cell D1.
move the worksheet to another workbook or a new work-
book by selecting the desired workbook in the To book: Next, move the Detail worksheet so it is on the right (the end
dropdown box. To move the worksheet to an existing work- of the workbook) and save the workbook using the follow-
book, the workbook must be open so it will appear in the To ing steps:
book: dropdown box. If the user checks the Create a copy
check box, a copy of the worksheet is created rather than 7. Right click on the Detail worksheet tab and select Move
moving the existing worksheet. or Copy... from the popup menu (shown in Figure 3-9)
to bring up the Move or Copy dialogue box.
8. Select (move to end) in the Before sheet: list box.
Exercise 3-2 The Move or Copy dialogue box should look like
Figure 3-12.
In this exercise you will modify the file you created in 9. Click the OK button to complete the move. The Detail
Exercise 3-1 to contain two worksheets named “Summary” worksheet should be on the right and the Summary
and “Detail.” Begin by changing the number of worksheets worksheet should be on the left.
to two, using the following steps: 10. Save the workbook by clicking on the Save button on
1. Make sure that Chapter 3, the workbook created in the Quick Access toolbar or typing Ctrl+S.
Exercise 3-1, is open. If it is not open, open it by selecting
the File tab (the Microsoft Office button for Excel 2007),
clicking on Open in the left pane to bring up the Open
dialogue box shown in Figure 3-4, selecting the folder ENTERING DATA
where the file is stored in the left side of the dialogue box
Data is entered in the worksheet by clicking on the cell and
(the Look in: dropdown box for Windows XP), and
typing the data. When the Enter key is typed, the cursor will
opening the file by double clicking on Chapter 3.
move to the next cell. Data is moved from one cell or group
2. If there is more than one worksheet, delete all but one of of cells to another cell or group of cells by cutting and past-
the worksheets by right clicking the tabs of the un- ing the data from one cell to another cell. When the same
needed worksheets and selecting Delete from the popup data is used in multiple cells, the data may be copied and
menu (shown in Figure 3-9). pasted from one cell to a number of cells. Pictures can also
3. Insert an additional worksheet by clicking on the Insert be added to worksheets. Let’s begin by looking at cutting and
Worksheet tab located to the right of the sheet tab. pasting data.

EXCEL QUICK TIP 3-3


Move after Typing Enter
After you press the Enter key, Excel moves to a neighboring display the Advanced options for working with Excel in the
cell. The user can set Excel to move to the left, right, up, or right pane, and under the Edit options selecting Left, Right,
down when the Enter key is typed. The default direction is Up, or Down in the Direction: dropdown box directly
down. To set the direction, select the File tab (the Microsoft under the After pressing Enter, move selection check box. To
Office button for Excel 2007), click on the Options button prevent the cursor from moving, uncheck the After press-
(Excel Options button for Excel 2007) to bring up the Excel ing Enter, move selection check box. The Excel Options di-
Options dialogue box, select Advanced in the left pane to alogue box is shown in the figure below:
Introduction to Excel 27

Cut and Paste pasting. The data is pasted to a cell or cells by selecting the
upper-left cell of the paste location, selecting the Home
Data is moved by cutting the data from a cell or group of cells menu tab, and clicking on the Paste button (shown in
to the clipboard and then pasting the data to a new cell. The
data is cut by selecting the cell or cells containing the data to
be cut and (1) selecting the Home menu tab, and clicking on
the Cut button in the clipboard group (shown in Figure 3-16),
(2) right clicking on one of the selected cells and selecting Cut
from the popup menu (shown in Figure 3-17), or (3) typing
Ctrl+X (typing the X key while holding down the Ctrl key). A
moving dashed line will then appear around the cells that have
been cut and placed on the clipboard.
The data must be pasted to the desired cells before you
perform any other action. If you perform another action
before pasting the data, the data on the clipboard is left in
the original cell and the user must cut the data again before

FIGURE 3-16 Home: Cut Button FIGURE 3-17 Popup Menu


28 CHAPTER THREE

FIGURE 3-18 Home: Paste Button

Figure 3-18) or by typing Ctrl+V (typing the V key while


holding down the Ctrl key). Alternatively, the user may
right click on the upper-left cell and select the Paste button
from the popup menu (shown in Figure 3-17 below Paste FIGURE 3-20 Paste Special Popup Menu
Options:). The data will then be moved from the original
cell or cells to the new cell or cells. paste. From this popup menu, the user may Paste, Formulas,
Formulas & Number Formatting, Keep Source Formatting,
No Borders, Keep Source Column Widths, Transpose,
Copy and Paste Values, Values & Number Formatting, Values & Source
Data is copied from a cell or group of cells to multiple cells Formatting, Formatting, Paste Link, Picture, and Linked
or groups of cells by copying the data in a cell or cells to the Picture.
clipboard and pasting the data to new cells. The data is Clicking on Paste Special... from the either of the
copied by selecting the cell or cells containing the data to be popup menus will open the Paste Special dialogue box
copied and (1) selecting the Home menu tab, and clicking (shown in Figure 3-21). From the Paste Special dialogue
on the Copy button (shown in Figure 3-19), (2) right click- box the user may select to paste All (this performs the same
ing on one of the selected cells and selecting Copy from the function as the paste command), Formulas, Values,
popup menu (shown in Figure 3-17), or (3) by typing Formats, Comments, Validation, All using Source theme,
Ctrl+C (typing the C key while holding down the Ctrl key). All except borders, Column widths, Formulas and number
A moving dashed line will then appear around the cells that formats, or Values and number formats. Once the user se-
have been copied and placed on the clipboard. lects the attributes that he or she wants to paste, the user
The data must be pasted to the desired cells before per- must click the OK button to complete the paste. For exam-
forming any other action. Once you have performed an- ple, if the user selects Values from the Paste Special dia-
other action, you cannot paste the data from the clipboard logue box, only the values of the cell will be pasted instead
to a cell. The data is pasted using the same process as was of any formulas; whereas, if All except borders is selected,
used to paste data after cutting it from a cell with one ex- the contents of the cell and all of its attributes except the
ception: you may paste the data multiple times until you borders will be copied.
perform another action.
When copying, the user has the option to use the paste
special command, which allows the user to copy only certain
properties of the cell. The paste special command is used by
right clicking on a cell and placing the cursor over Paste
Special... from the popup menu (shown in Figure 3-17) or
by selecting the Home menu tab and clicking on the arrow
below the Paste button to bring up the Paste Special popup
menu (shown in Figure 3-20) and selecting the attributes to

FIGURE 3-19 Home: Copy Button FIGURE 3-21 Paste Special Dialogue Box
Introduction to Excel 29

In the next few exercises you will modify the Detail work-
sheet you created in Exercise 3-2 to look like Figure 3-24.

Exercise 3-3

In this exercise you will modify the file from Exercise 3-2 by
adding data to the cells. Begin by adding data to individual
cells using the following steps:
FIGURE 3-22 Insert: Picture Button
1. Make sure that Chapter 3, the workbook modified in
Exercise 3-2, is open. If it is not open, open it by select-
Adding Pictures ing the File tab (the Microsoft Office button for Excel
2007), clicking on Open in the left pane to bring up the
Pictures are added to the worksheet by selecting the Insert
Open dialogue box shown in Figure 3-4, selecting the
menu tab and clicking on the Picture button in the
folder where the file is stored in left side of the dialogue
Illustrations group (shown in Figure 3-22) to bring up the
box (the Look in: dropdown box for Windows XP), and
Insert Picture dialogue box (shown in Figure 3-23). From
opening the file by double clicking on Chapter 3.
the Insert Picture dialogue box, the user selects the folder
where the file is stored in the left pane (the Look in: drop- 2. Make sure the worksheet named Detail is the active
down box for Windows XP) and opens the file by double worksheet by clicking on the Detail tab.
clicking on the file name or clicking on the file name and 3. Begin setting up the spreadsheet by typing MATERIALS
clicking the Insert button. in Cell A1.

FIGURE 3-23 Insert Picture Dialogue Box

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL

FIGURE 3-24 Detail Worksheet


30 CHAPTER THREE

TABLE 3-1 Data for Cells in Exercise 3-3


Cell Data Cell Data

G1 Labor F2 LHR/UNIT
J1 Equipment G2 LHR
A2 Item H2 $/LHR
B2 Quantity J2 $/LHR
D2 $/Unit L2 Total
E2 Cost

4. Type the text shown in Table 3-1 into the specified cells.
Next, move the data from Cell A1 to Cell D1 using the fol- FIGURE 3-25 Changing the Width of Column B
lowing steps:
5. Right click on Cell A1 and select Cut from the popup cursor changes to a vertical line with arrows pointing to the
menu (shown in Figure 3-17) to cut the contents of the right and left. Place the cursor in the location shown in
cell to the clipboard. Figure 3-25 to adjust the width of Column B. Second, the
6. Right click on Cell D1 and select the Paste button user may double click on the right side of the column’s head-
below Paste Options: from the popup menu (shown in ing to have Excel automatically change the width of the col-
Figure 3-17) to paste the contents of the clipboard to umn to the minimum width necessary to show the data in
Cell D1. Cell A1 should now be blank and “MATERIALS” the widest cell within the column. Double clicking on the lo-
should be in Cell D1. cation shown in Figure 3-25 will make this column width
adjustment to Column B. Third, the user may set the width
Next, copy the data from Cell E2 to Cells I2 and K2 using the using the Column Width dialogue box shown in Figure 3-26.
following steps: To bring up the Column Width dialogue box, the user right
7. Right click on Cell E2 and select Copy from the popup clicks on the heading for the column and selects Column
menu (shown in Figure 3-17) to copy the contents of Width... from the popup menu (shown in Figure 3-27) or
the cell to the clipboard.
8. Select Cell I2, select the Home menu tab, and click on
the Paste button (shown in Figure 3-18) to paste the
contents of the clipboard to Cell I2.
9. Select Cell K2 and type Ctrl+V to paste the contents of
the clipboard to Cell K2. “COST” should now appear in
Cells E2, I2, and K2. FIGURE 3-26 Column Width Dialogue Box
10. Save the workbook by clicking on the Save button on
the Quick Access toolbar or typing Ctrl+S.

FORMATTING WORKSHEETS
Formatting allows the user to create a specific look for work-
sheets and makes the worksheets easier to read. Common
formatting includes setting the column widths, formatting
and aligning the data in the cells, adding borders around a
cell or group of cells, setting how much of the worksheet is
visible on the computer screen, and adding footers and
headers. Let’s begin by looking at the column widths.

Column Widths
The width of the columns can be changed in three ways.
First, the user may place the cursor over the right side of a
column’s heading and hold down the left mouse button to
drag the right side of the column to the desired width. When
the cursor is over the right side of the column heading, the FIGURE 3-27 Popup Menu
Introduction to Excel 31

FIGURE 3-28 Home: Format Button FIGURE 3-30 Home: Align Text Left Button

selects the Home menu tab, selects the Format button in the
Cells group shown in Figure 3-28, and selects Column
Width... from the popup menu (shown in Figure 3-29) . The
column width is then entered into the Column width: text
box on the Column Width dialogue box and the OK button
is selected to change the width of the column.

Row Heights
FIGURE 3-31 Home: Center Button
Row heights are adjusted in the same way as column heights
except that the user selects row rather than column.
the Alignment group. The Center button is shown in
Cell Formatting Figure 3-31.
The data is aligned right by selecting the desired cells,
Data in the cells is divided into two types: text (alphanu- selecting the Home menu tab, and selecting the Align Text
meric) and numeric data. Both numeric and text data can be Right button in the Alignment group. The Align Text Right
aligned left, aligned right, or centered, and the font can be button is shown in Figure 3-32.
changed. The data is aligned left by selecting the desired The font style for the data is changed by selecting the
cells, selecting the Home menu tab, and selecting the Align desired cells, selecting the Home menu tab, and then select-
Text Left button in the Alignment group. The Align Text Left ing the desired font from the Font dropdown box in the Font
button is shown in Figure 3-30. group. The Font dropdown box is shown in Figure 3-33.
The data is centered by selecting the desired cells, se- The font size for the data is changed by selecting the de-
lecting the Home menu tab, selecting the Center button in sired cells, selecting the Home menu tab, and then selecting
the desired font size from the Font Size dropdown box in

FIGURE 3-32 Home: Align Text Right Button

FIGURE 3-29 Format Popup Menu FIGURE 3-33 Home: Font Dropdown Box
32 CHAPTER THREE

FIGURE 3-34 Home: Font Size Dropdown Box


FIGURE 3-37 Home: Format Cells: Font Dialogue Box
the Font group. The Font Size dropdown box is shown in Launcher
Figure 3-34.
The font is bolded by selecting the desired cells and (1) Alternatively, both the font style and font size can be
selecting the Home menu tab, and clicking on the Bold but- changed and the font bolded from the Format Cells dialogue
ton in the Font group or (2) by typing Ctrl+B (typing the B box, shown in Figure 3-36, which is accessed by selecting the
key while holding down the Ctrl key). The Bold button is desired cells and performing one of the following actions:
shown in Figure 3-35. (1) by typing Ctrl+1 (typing the 1 key while holding down
the Ctrl key) and selecting the Font tab, (2) right clicking on
one of the selected cells, selecting Format Cells... from the
popup menu (shown in Figure 3-17), and selecting the Font
tab, or (3) selecting the Home menu tab and selecting the
Format Cells: Font Dialogue Box Launcher (shown in
Figure 3-37) located at the lower-right corner of the Font
group. From the Font: combo box, the user selects the font;
from the Font style: combo box, the user can bold the font;
and from the Size: combo box, the user selects the font size.
The user must complete the changes by clicking on the OK
FIGURE 3-35 Home: Bold Button box to close the Format Cells dialogue box.

FIGURE 3-36 Font Tab of the Format Cells Dialogue Box


Introduction to Excel 33

FIGURE 3-38 Home: Wrap Text Button FIGURE 3-39 Home: Merge and Center Button

FIGURE 3-40 Warning Dialogue Box

For very wide text, the text may be wrapped to allow the thousands and hundreds. An easy way to do this is to se-
the text to occupy more than one line. This is done by se- lect the desired cells, select the Home menu tab, and select
lecting the cells in which the text is to be wrapped, selecting the Comma Style button in the Number group. The Comma
the Home menu tab, and selecting the Wrap Text button in Style button is shown in Figure 3-41. The Comma Style but-
the Alignment group. The Wrap Text button is shown in ton will format the data to an accounting style with two dec-
Figure 3-38. imal places shown, negative numbers will be placed in
At times the user may want to have text cover a number parentheses, and zeros will be shown as a dash.
of rows or columns, as is the case when creating headings. Numbers can be expressed as a percentage by selecting
This is done by selecting the cells to be combined, selecting the desired cells, selecting the Home menu tab, and selecting
the Home menu tab, and selecting the Merge and Center the Percentage Style button in the Number group. The
button in the Alignment group. The Merge and Center but- Percentage Style button is shown in Figure 3-42.
ton is shown in Figure 3-39. In addition to merging the The number of decimal places is increased by selecting
cells, the Merge and Center button centers the data. For the the desired cells, selecting the Home menu tab, and selecting
merge and center to be successful, the selected cells must be the Increase Decimal button in the Number group. The
in the shape of a rectangle. If more than one of the cells Increase Decimal button is shown in Figure 3-43. The number
contains data, only data from the upper-leftmost cell is re- of decimal places is decreased by selecting the desired cells,
tained and the remaining data is lost. If data is to be lost,
Excel will provide the user with the warning dialogue box
shown in Figure 3-40 before proceeding. If the user wants to
continue, he or she must click on the OK button.
To unmerge cells, select the merged cells and click the
Merge and Center button. The data from the cells will be
placed in the upper-left cell.
With numeric data, the user often wants to control how
the data is displayed. For estimating the user often wants to
display the numbers as dollars and cents with commas between FIGURE 3-42 Home: Percentage Style Button

FIGURE 3-41 Home: Comma Style Button FIGURE 3-43 Home: Increase Decimal Button
34 CHAPTER THREE

FIGURE 3-44 Home: Decrease Decimal Button


FIGURE 3-46 Home: Borders Button

selecting the Home menu tab, and selecting the Decrease The user can select from the twelve preset borders
Decimal button in the Number group. The Decrease Decimal shown in Figure 3-47 by selecting the small arrow on the
button is shown in Figure 3-44. right side of the Borders button to bring up the Borders
Other formatting styles, such as date and time, are se- popup menu. After selecting a preset border type, the popup
lected from the Number tab of the Format Cells dialogue menu will disappear and the Border button will change to
box (shown in Figure 3-45), which is open by (1) right click- show the most recently used preset border. To erase all bor-
ing on one of the selected cells, selecting Format Cells... ders associated with a cell, select the No Border from the
from the popup menu (shown in Figure 3-17), and selecting Borders popup menu shown in Figure 3-47.
the Number tab or (2) selecting the Home menu tab and se-
lecting the Format Cells: Number Dialogue Box Launcher at Zooming
the lower-right corner of the Number group.
The extent of the spreadsheet shown on the computer screen
is controlled by the Zoom slider located in the lower-right
Borders hand corner. The user may zoom in and out by sliding the
Borders are drawn around cells or groups of cells using the control knob as shown in Figure 3-48 or by clicking on the
Borders button, located in the Font group on the Home Plus or Minus buttons located to the right and left of the
menu tab. The Borders button is shown in Figure 3-46. The slider. When clicking on the Plus or Minus buttons the zoom
user may use the most recently used border by clicking on progresses in increments of 10%. From the Zoom dialogue
the left side of the button. box (shown in Figure 3-49), the user can select from one of

FIGURE 3-45 Number Tab of the Format Cells Dialogue Box


Introduction to Excel 35

FIGURE 3-50 Zoom Level

FIGURE 3-51 View: Zoom Button

FIGURE 3-52 View: Zoom to Selection Button


FIGURE 3-47 Borders Popup Menus
the Zoom button (shown in Figure 3-51). By selecting a num-
ber of rows or columns and selecting Fit selection from the
Zoom dialogue box the spreadsheet will zoom to match the
width of the selected columns or the height of the selected
rows. This may also be done by selecting the rows or columns,
selecting the View menu tab, and selecting the Zoom to
FIGURE 3-48 Zoom Slider Selection button (shown in Figure 3-52). It is important to
understand that changing the zoom will not change the scale
at which the spreadsheet will be printed. This is done by set-
ting the print scale, which is discussed later in this chapter.

Exercise 3-4

In this exercise you will modify the file from Exercise 3-3 by
changing the column widths, merging and formatting cells,
and adding borders. Begin by changing the column widths
using the following steps:
1. Make sure that Chapter 3, the workbook modified in
Exercise 3-3, is open.
2. Change the width of Column A to 25 by right clicking
FIGURE 3-49 Zoom Dialogue Box on the letter A at the top of Column A, selecting
Column Width... from the popup menu (shown in
the standard zoom percentages, select a custom zoom per- Figure 3-27) to bring up the Column Width dialogue
centage, or zoom to fit the width or height of a selected num- box (shown in Figure 3-26), enter 25 in the Column
ber of cells. The Zoom dialogue box is opened by clicking on Width: text box, and click the OK button.
the Zoom level located to the right of the Status bar (shown in 3. Change the width of Column B to 6, that of Column C to
Figure 3-50) or by selecting the View menu tab and selecting 4, and that of Columns D through L to 10 by using the
36 CHAPTER THREE

same procedures. Hint: Columns D through L can be 17. Click on the Zoom level (shown in Figure 3-50) at the
changed at once by selecting Columns D through L using left of the Status bar to bring up the Zoom dialogue box
the Shift key, right clicking on any one of the highlighted (shown in Figure 3-49), select Fit selection, and click
columns, and selecting Column Width... from the popup the OK button to close the Zoom dialogue box.
menu to bring up the Column Width dialogue box. You Columns A through L should cover the entire width of
can now change the width of all of the columns at once. the spreadsheet.
Next, format the cells using the following steps: 18. Save the workbook by clicking on the Save button on
4. Center the text in Cells D2 through L2 by selecting Cells the Quick Access toolbar or typing Ctrl+S.
D2 through L2 using the Shift key and clicking the The first two rows of your spreadsheet should be the same as
Center button (shown in Figure 3-31) in the Alignment the first two rows of the spreadsheet in Figure 3-24.
group on the Home menu tab.
5. Center the text in Column C by selecting Column C and
clicking the Center button. Headers and Footers
6. Change the formatting for columns E, I, K, and L to the Custom headers and footers can be added to each spread-
accounting style by selecting Column E and holding sheet. The headers and footers may include text, data from
down the Ctrl key while selecting Columns I, K, and L to the workbook and computer, or graphics. To edit headers
highlight these columns. With the columns highlighted, and footers, the worksheet must be displayed in Page Layout
click the Comma Style button (shown in Figure 3-41) in
view. The Page Layout view is displayed by clicking on the
the Number group on the Home menu tab to change the
Page Layout button located on the Status bar (shown in
formatting to the accounting style and then reduce the
Figure 3-53) or by clicking on the View menu tab and click-
number of decimal points to zero by clicking on the
ing on the Page Layout button in the Workbook Views
Decrease Decimal button (shown in Figure 3-44) in the
group (shown in Figure 3-54). Once the spreadsheet is in
Number group on the Home menu tab twice.
Page Layout view, the user can click on the header or footer
7. Change the formatting for columns D, F, G, H, and J to to edit the header or footer. Alternately, the user may click on
the comma style as done previously; however, do not the Insert menu tab and click on the Header & Footer but-
change the number of decimal points. ton in the Text group (shown in Figure 3-55) to switch to the
8. Merge Cells A1 and A2 by highlighting Cells A1 and A2 Page Layout view and open the header and footer for editing.
and clicking on the Merge and Center button (shown in
Figure 3-39) in the Alignment group on the Home
menu tab.
9. Left justify the text in the merged cells by clicking the
Align Text Left button (shown in Figure 3-30) in the
Alignment group on the Home menu tab.
FIGURE 3-53 Page Layout Button
10. Merge Cells B1 through C2 by highlighting Cells B1
through C2 and clicking on the Merge and Center but-
ton (shown in Figure 3-39) in the Alignment group on
the Home menu tab.
11. Merge Cells D1 and E1 in the same manner.
12. Merge Cells F1 through I1.
13. Merge Cells J1 and K1.
14. Merge Cells L1 and L2.
Next, you will underline the headings you have created using
the following steps:
15. Underline Row 2 by highlighting Cells A1 through L2 FIGURE 3-54 View: Page Layout Button
and clicking the Bottom Border button (shown in
Figure 3-46) in the Font group on the Home menu tab. If
another border is shown in the Borders button, select the
correct border by clicking on the small arrow to the right
of the Borders button and selecting the Bottom Border
from the Borders popup menu (shown in Figure 3-47).
Next, set the zoom so you can see Columns A through L
using the following steps:
16. Select Columns A through L by clicking on Column A
and hold down the Shift key while clicking on Column L. FIGURE 3-55 Insert: Header & Footer Button
Introduction to Excel 37

FIGURE 3-56 Header

The headers and the footers are divided into three


areas: left (for left-justified elements), center (for centered Icon Name Use
elements), and right (for right-justified elements). A sam- Page Number Adds the page number to each
ple header is shown in Figure 3-56. It is important to note page of the header or footer.
that elements in any of these areas are not limited to their
areas. They simply identify how the element is aligned.
Text is typed in the headers or footers and the font is
changed in the same manner as the font in the cells is Number of Adds the total number of pages
Pages in the header or footer.
changed. When the header or footer has been selected, the
Header & Footer Tools: Design menu tab become visible.
Elements are added to the header and footers by clicking
on the Header & Footer Tools: Design tab and selecting Current Date Adds the current date from
the appropriate element from the Header & Footer the computer to the header or
Elements group. The elements of the Header & Footer footer.
Elements group, along with an explanation of their use are
shown in Figure 3-57.
The Page Number button is used to automatically num- Current Time Adds the current time from
ber the pages. The Number of Pages button is used to display the computer to the header or
the total number of pages in the worksheet. This, along with footer.
the Page Number button, allows the user to number the
pages “1 of 5,” “2 of 5,” and so forth. By numbering the pages
in this manner, it is easy to see if pages at the end of the doc- File Path Adds the file name and path
(location of the folder) to the
ument are missing.
header or footer.
The Current Date button adds the current date from the
computer to the header or footer. The Current Time button
adds the current time from the computer to the header or
File Name Adds the file name to the
footer. The date and time will be automatically updated header or footer.
when the worksheet is printed. By putting the date and time
on each worksheet, it is easy to determine which printed ver-
sion of the worksheet is the most current. This is very useful
when preparing bids and the user wants to make sure he or Sheet Name Adds the name on the
she is using the most current worksheet. worksheet tab to the header
The File Path button adds the file name and path (the or footer.
location of the folder) to the header or footer. This is useful
when trying to locate the computer file for a worksheet that
has been printed. The File Name button adds just the file Picture Brings up the Picture dialogue
name to the header or footer. The Sheet Name button adds box that is shown in Figure 3-23,
which allows pictures to be
the name on the worksheet tab to the header or footer.
added to the header or footer.
The Insert Picture button brings up the Insert Picture
dialogue box, which allows the user to add a picture, such as Format Picture Allows inserted pictures to be
formatted.
the company’s logo, to the worksheet. The Insert Picture dia-
logue box is shown in Figure 3-23. Pictures are added to the
headers and footers in the same manner as pictures are
added to the worksheet. The Format Picture button brings
up the Format Picture dialogue box, which allows inserted FIGURE 3-57 Elements Available to Headers and Footers
38 CHAPTER THREE

FIGURE 3-61 Normal Button on the Status Bar

FIGURE 3-62 View: Normal Button

FIGURE 3-58 Format Picture Dialogue Box Exercise 3-5


pictures to be resized, rotated, and cropped. The Format In this exercise you will modify the file from Exercise 3-4 by
Picture dialogue box is shown in Figure 3-58. adding headers and footers to the Detail worksheet. In the
The user may move from the header to the footer by header you will add the sheet name. In the footer you will
clicking on the Header & Footer Tools: Design menu tab and add the date and time (which will record the date and time
clicking on the Go to Footer button (shown in Figure 3-59) the spreadsheet is printed), the file location, the page num-
and from the footer to the header by clicking on the Header ber, and a place for the preparer and reviewer to initial. Begin
& Footer Tools: Design menu tab and clicking on the Go to by adding a header using the following steps:
Header button (shown in Figure 3-60).
Once the header and footers have been set up the user 1. Make sure that Chapter 03, the workbook created in
clicks on a cell in the worksheet to close the header or footer Exercise 3-1, is open.
and return to editing the worksheet. The user may return to 2. Click on the Insert menu tab and click on the Header &
the Normal view by clicking on the Normal button located Footer button (shown in Figure 3-55) to edit the header.
on the Status bar (shown in Figure 3-61) or by clicking on 3. Place the cursor in the center section and click the Sheet
the View menu tab and clicking on the Normal button in the Name button from the Header & Footer Elements
Workbook Views group (shown in Figure 3-62). group. The Header should look like Figure 3-56. When
the cursor is moved from the center section of the
header, the &[Tab] will be replaced with the name of the
tab, in this case Detail.
Next, add a footer using the following steps:
4. Right click on the Go to Footer button from the
Navigation group (see Figure 3-59) to move to the footer.
5. Place the cursor in the right section and type Prepared
FIGURE 3-59 Header & Footer: Design: Navigation: by: followed by pressing the Underline key ten times.
Go to Footer Button
6. Press the Return key and type Checked by: followed by
pressing the Underline key ten times.
7. Place the cursor in the center section and click the Page
Number button from the Header & Footer Elements
group.
8. Following “&[Page]” type of, including a space before
and after the of.
9. Click the Number of Pages button from the Header &
FIGURE 3-60 Header & Footer: Design: Navigation: Footer Elements group and press the Enter button to
Go to Header Button move it up one line.
Introduction to Excel 39

FIGURE 3-63 Footer

10. Place the cursor in the left section, click the Current For Excel to recognize the data being entered into a cell as
Date button from the Header & Footer Elements group, a formula, the formula must begin with an equal sign, a plus
type the Space bar, and click the Current Time button sign, or a minus sign. If the user enters a plus sign, Excel will
from the Header & Footer Elements group. change the plus sign to an equal sign. If the user enters a
11. Press the Enter key to move to the following line and minus sign, Excel will add an equal sign before the minus sign.
click the File Path button from the Header & Footer For each opening parenthesis there must be a closing
Elements group. parenthesis. As the formula is entered, Excel will color code
the parentheses in pairs. Should the user forget to have an
12. The Footer should look like Figure 3-63. When the cur-
equal number of opening and closing parentheses, Excel will
sor is moved from the left section of the footer, the
warn the user of the problem and suggest a correction.
&[Date] &[Time] will be replaced with the current date
The caret character allows the user to raise a value to a
and time and the &[Path]&[File] will be replaced with
power. For example, the mathematical function XY is written
the path and file name.
in Excel as follows:
13. Click on any cell to return to the worksheet.
X^Y
14. Click on the View menu tab and click on the Normal
The formula 4^2 is equal to 4 squared or 16. To find the
button (shown in Figure 3-62) to return to the Normal
square root of a number, raise the number to the 0.5 power
view.
as follows:
15. Save the workbook by clicking on the Save button on
X^0.5
the Quick Access toolbar or typing Ctrl+S.
Order of Operation
WRITING FORMULAS Excel performs the calculation of a formula in the following
order:
Formulas allow Excel to perform simple or complex calcula-
tions. The formulas may contain mathematical calculations First, the calculations enclosed by the parentheses are
and functions. In this segment, the writing of formulas is performed, starting with the innermost pair and
discussed. Formulas may consist of numbers, variables, and working out to the outermost pair of parentheses.
operators. Numbers are typed in from the key board and do Second, the variable or number raised to a power is
not change. Cells within the worksheets that are referenced performed.
by the formula are known as variables. Variables are entered Third, multiplication and division are performed.
by typing the cell reference or by selecting the cell with the Finally, addition and subtraction are performed.
mouse while writing the formula. When two calculations have the same priority, they are
performed left to right.
Operators For example, Excel calculates the following formula by
Excel allows the use of the following operators: adding 2 and 1 together to get 3, then squaring the 3 to get 9,
⫽ Equals Sign adding 7 to the 9 to get 16, dividing the 16 by 4 to get 4, and,
finally, adding 1 to get 5:
⫹ Plus Sign
⫺ Minus Sign ⫽ ((2 ⫹ 1)^2 ⫹ 7)>4 ⫹ 1
* Multiplication Sign or Asterisk ⫽ (3^2 ⫹ 7)>4 ⫹ 1
/ Division or Backslash ⫽ (9 ⫹ 7)>4 ⫹ 1
( Opening Parentheses ⫽ 16>4 ⫹ 1
) Closing Parentheses ⫽4⫹1
^ Caret ⫽5
40 CHAPTER THREE

Editing Formulas
Existing formulas are edited by selecting the cell (clicking on
the cell) and editing the formula in the Formula bar. When
building complex formulas, it is a good idea to build formu-
las in steps, making sure each step of the formula works be-
fore adding the next step. FIGURE 3-66 Copying a Relative Column, Absolute Row
Reference
Absolute and Relative References
By default, when a cell is copied into the cell to the right, all of
the cell references move one cell to the right. Likewise, when a
cell is copied to the cell to the left, to the cell above, or to the
cell below, all of the cell references move one cell left, up, or
down, respectively. This is known as a relative reference be-
cause the cells used in the formula maintain the same relative
position with cells containing the formula. Figure 3-64 shows FIGURE 3-67 Copying an Absolute Reference
what happens when Cell B2 contains a relative reference and
is copied to Cells A1 through C3.
The dollar sign ($) used in conjunction with a cell refer- reference would then be an absolute reference. Figure 3-67
ence allows the user to fix a portion of the cell’s reference as shows what happens when Cell B2 contains an absolute ref-
it is copied. For example, the use of a cell reference of $H22 erence and is copied to Cells A1 through C3.
fixes the column portion of the reference to the H column as The user may move between the absolute and relative
it is copied to other columns, allowing only the row reference reference types by highlighting the reference to be changed
to change as it is copied to different rows. The column por- and pressing the F4 key. This cycles the reference from rela-
tion of the reference would then be an absolute reference tive, to both the column and rows being absolute, to only the
and the row portion would be relative. Figure 3-65 shows row being absolute, to only the column being absolute, and
what happens when Cell B2 contains an absolute-column, back again to a relative reference.
relative-row reference and is copied to Cells A1 through C3.
Likewise, the use of a cell reference of H$22 fixes the
row portion of the reference to the twenty-second row as it is Exercise 3-6
copied to other rows, allowing only the column reference to
change as it is copied to different columns. The row portion In this exercise you will explore absolute and relative refer-
of the reference would then be an absolute reference and the ences. Begin by completing the following steps:
column portion would be relative. Figure 3-66 shows what
1. Begin by opening a new workbook. If Excel is not open,
happens when Cell B2 contains a relative-column, absolute-
open it. If Excel is open, type ctrlⴙN to open a new
row reference and is copied to Cells A1 through C3.
workbook.
The use of a cell reference of $H$22 would fix both the
row and the column, preventing the row and column refer- 2. Type the data shown in Table 3-2 into the indicated
ence from being changed as the cell is copied. The entire cells.
Next, create a relative reference using the following steps.
3. Type ⫽ B2 into Cell B6.
4. Copy Cell B6 to Cells A5 through C7 by right clicking
on Cell B6 and selecting Copy from the popup menu
(shown in Figure 3-17), selecting Cells A5 through C7,
and clicking on the Paste button from the Home tab
FIGURE 3-64 Copying a Relative Reference (shown in Figure 3-18).

TABLE 3-2 Data for Example 3-6


Cell Data Cell Data Cell Data

A1 1 B1 4 C1 7
A2 2 B2 5 C2 8
FIGURE 3-65 Copying an Absolute Column, Relative Row
A3 3 B3 6 C3 9
Reference
Introduction to Excel 41

BASIC FUNCTIONS
In addition to mathematical equations, computer func-
tions can also be included in the formulas. Functions are
entered by (1) typing the functions, (2) selecting the
Formulas menu tab, selecting the function category from
the Function Library group, and selecting the function
from the popup menu, or (3) by clicking on the Insert
Function button (shown in Figure 3-69) on the formula
bar to bring up the Insert Function dialogue box (shown in
Figure 3-70). This section covers the rounding functions
(including the CEILING and FLOOR functions), the SUM
function, the AVERAGE function, and the IF function.
Additional functions are available from the Insert Function
dialogue box.
From the Function dialogue box the user may make a
function available for selection by selecting All or the func-
tion’s category from the Or select a category: dropdown box.
Alternatively, the user may perform a key word search by
typing key words in the Search for a function: text box and
clicking on the Go button. When the function is shown in
the Select a function: list box, the user double clicks on the
FIGURE 3-68 Spreadsheet for Exercise 3-6 function or selects the function and clicks on the OK button
to bring up the Function Arguments dialogue box. The
Cells A5 through A7 should contain the numbers shown in Function Arguments dialogue box for the ROUND function
Figure 3-68. is shown in Figure 3-71. Each function has its own Function
Next, create an absolute reference using the following steps: Arguments dialogue box.
The Function Arguments dialogue box prompts the
5. Type ⫽ $B$2 into Cell B10. user for the information necessary to complete the function.
6. Copy Cell B10 to Cells A9 through C11. The user enters the requested information and clicks the OK
button to close the Function Arguments dialogue box and
Because it is an absolute reference, the formula in all of the cells
create the function.
is the same as the formula entered into Cell B10; therefore, the
value in all of the cells is the same as the value in Cell B2 or 5.
Cells A9 through C11 should appear as they do in Figure 3-68.
Next, create a formula with an absolute row reference
using the following steps: FIGURE 3-69 Insert Function Button
7. Type ⫽ B$2 into Cell B14.
8. Copy Cell B14 to Cells A13 through C15.
Because the row portion of the reference is an absolute refer-
ence, it does not change. The value for Cells A13 through A15
should be 2, the value for Cells B13 through B15 should be 5,
and the value for Cells C13 through C15 should be 8. Cells
A13 through C15 should appear as they do in Figure 3-68.
Next, create a formula with an absolute column refer-
ence using the following steps:
9. Type ⫽ $B2 into Cell B18.
10. Copy Cell B18 to Cells A17 through C19.
Because the column portion of the reference is an absolute ref-
erence, it does not change. The value for Cells A17 through C17
should be 4, the value for Cells A18 through C18 should be 5,
and the value for Cells A19 through C19 should be 6. Cells A17
through C19 should appear as they do in Figure 3-68.
11. Close the workbook without saving it.
FIGURE 3-70 Insert Function Dialogue Box
42 CHAPTER THREE

FIGURE 3-71 Function Arguments Dialogue Box for the ROUND Function

Rounding functions will not round to quarters of a yard. For this we


must use the CEILING or FLOOR functions.
Excel provides the user three standard rounding func-
tions: (1) ROUND, which rounds to the closest number;
(2) ROUNDDOWN, which rounds the number down;
Ceiling
and (3) ROUNDUP, which rounds the number up. Each The CEILING function may be used to round up a number
of these functions requires the user to indicate the number to the next multiple of a specified number (referred to by
or cell containing the number to be rounded (Number) Excel as significance). For example, if the significance is 0.25,
and the number of digits to round to (Num_digits), in the the CEILING function will round up to the next 0.25 incre-
following format: ment. The CEILING function requires the user to indicate
the number or cell containing the number to be rounded
=ROUND(<Number>,<Num_digits>)
(Number) and the significance, in the following format:
The user does not need to capitalize the word “round” be-
=CEILING(<Number>,<significance>)
cause Excel will automatically capitalize the word “round”
when the formula is completed. Rounding to a positive num- For example, the function
ber of digits represents the number of digits on the right side
=CEILING(123.228,0.25)
of the decimal point. For example, if the number of digits
equals 2, the function rounds to hundredths. The function rounds 123.228 to 123.25. Figure 3-72 shows how this func-
tion would be set up using the Function Arguments dialogue
=ROUND(123.228,2)
box for the CEILING function.
rounds 123.228 to 123.23. Figure 3-71 shows how this func-
tion would be set up using the Function Arguments dialogue Floor
box for the ROUND function. Rounding to a negative num-
ber of digits represents the number of digits on the left side The FLOOR function works in the same way as the CEILING
of the decimal point. The function function except it rounds down. For example, the function
=ROUND(123.228,-2) =FLOOR(123.228,0.25)

rounds 123.228 to 100.00. The ROUNDUP function always rounds 123.228 to 123.00.
rounds the number up and the ROUNDDOWN function al-
ways rounds the number down. The function
EXCEL QUICK TIP 3-4
=ROUNDUP(123.228,2) Rounding to Nearest Quarter Yards
rounds 123.228 up to 123.23, whereas the function Excel’s rounding, CEILING, and FLOOR functions do
=ROUNDDOWN(123.228,2) not allow the user to automatically round to the nearest
quarter-cubic-yards because Excel’s rounding functions
rounds 123.228 down to 123.22. will only round to decimal places (such as hundredths,
The three standard rounding functions can only be used tenths, tens, hundreds, and whole numbers) and the
to round to decimal places, such as the hundreds, tens, whole CEILING and FLOOR functions only round up or down,
numbers, tenths, hundredths, and so forth. The rounding
Introduction to Excel 43

FIGURE 3-72 Function Arguments Dialogue Box for the CEILING Function

In Excel, the formula


not to the nearest quarter-cubic-yard. However, the user
can round to the nearest quarter-cubic-yards by convert- =SUM(C1:C5)
ing the units to quarter-cubic-yards, rounding the num- adds the numbers in Cells C1, C2, C3, C4, and C5.
ber to a whole number, and converting back to cubic Noncontiguous cells may be added by placing a comma be-
yards. The formula for rounding a number in cubic yards tween the cells references. The formula
to the nearest quarter-cubic-yard is written as follows:
=SUM(C1:C5,D17)
=ROUND(<Number>*4,0)/4
adds the numbers in Cells C1, C2, C3, C4, C5, and D17. The
For example, the following function is used to round SUM function is quickly inserted into a cell by clicking on the
123.228 cubic yards to the nearest quarter-cubic-yard: Formula menu tab and clicking on the AutoSum button in
the Function Library group. The AutoSum button is shown in
=ROUND(123.228*4,0)/4
Figure 3-73. The AutoSum will place a moving dashed line
The function first multiplies 123.228 cubic yards by 4 to around the cells that Excel thinks the user wants to sum. If the
get 492.912 quarter-cubic-yards, rounds 492.912 quarter- user wants to include different cells, the user must select the
cubic-yards to 493 quarter-cubic-yards (the nearest whole cells. The AutoSum is completed by pressing the Enter key.
number), and then divides 493 quarter-cubic-yards by 4 to
get 123.25 cubic yards. Formulas can be written for other Average Function
fractions of a whole number by using the same concepts.
The AVERAGE function allows the computer to average the
values in a range of cells. Only the cells containing numbers
are included in the average. The AVERAGE function is writ-
Sum ten as follows:
The SUM function adds a group of numbers. It is particu- =Average(<Beginning Cell>:<Ending Cell>)
larly useful when adding a column, row, or block numbers,
inasmuch as only the cells containing the first and last num- In Excel, the formula
ber need to be included in the formula. The SUM function is =Average(C1:C5)
written as follows:
takes the average of the numbers in Cells C1, C2, C3, C4, and
=SUM(<Beginning Cell>:<Ending Cell>) C5, ignoring blank cells and cells with text. If Cell C1 is 3;

FIGURE 3-73 Formulas: AutoSum Button


44 CHAPTER THREE

FIGURE 3-74 Average Example


FIGURE 3-75 Popup Menu

Cell C2 is blank; Cell C3 contains the text “Joe”; Cell C4 is against. Excel allows for the use of the following logical
10; and Cell C5 is 17, the AVERAGE function ignores Cells operators:
C2 and C3 and averages Cells C1, C4, and C5 to get 10. This
> Greater Than
example is shown in Figure 3-74.
The AVERAGE function may be typed directly into a cell < Less Than
or may be quickly inserted into a cell by clicking on the arrow ⫽ Equal to
below the AutoSum button (shown in Figure 3-73) in the >⫽ Greater Than or Equal to
Function Library group on the Formula menu tab to bring <⫽ Less Than or Equal to
up the popup menu (shown in Figure 3-75) and selecting <> Not Equal to
Average from this menu. When selecting Average from the
popup menu, Excel will place a moving dashed line around For example, the formula
the cells that Excel thinks the user wants to average. If the user =IF(B10=B32,0,10)
wants to include different cells, the user must select the cells.
is equal to 0 if Cell B10 is equal to Cell B32 and is equal to 10
The AVERAGE is completed by pressing the Enter key.
if Cell B10 is not equal to Cell B32. Figure 3-76 shows how
this function would be set up using the Function Arguments
IF Function dialogue box for the IF function.
The IF function allows the computer to select between two The value_if_true and the value_if_false may contain
responses based on the value found in a specified cell. If the numbers, cell references, functions, and text. For example,
value in the specified cell meets the test requirements, then the formula
Excel does one thing, and if it does not meet the test require- =IF(B10=B32,B34*B35,SUM(C17:C28))
ment, it does another. The IF function is written as follows:
is equal to Cell B34 multiplied by Cell B35 if Cell B10 is
=IF(<logical_test>,<value_if_true>, equal to B32, and is equal to the sum of Cells C17 through
<value_if_false>) C28 if Cell B10 is not equal to Cell B32.
The logical test consists of any statement that is either true When using text for the value_if_true or the
or false. The logical test should consist of (1) the cell to be value_if_false, the text is placed between quotation marks.
tested, (2) a logical operator that identifies the type of test For example, the formula
to perform, and (3) a cell, function, or value to test =IF(B10=B32,“True”,“False”)

FIGURE 3-76 Function Arguments Dialogue Box for the IF Function


Introduction to Excel 45

FIGURE 3-77 Nested IF function

is equal to “True” if Cell B10 is equal to B32, and is equal to TABLE 3-3 Data for ROUND Function
“False” if Cell B10 is not equal to Cell B32.
The user can select among more than two options by Cell Data
creating nested IF functions: placing one IF function inside
another IF function, as follows:
B1 ⫽ROUND(A1,2)
B2 ⫽ROUNDUP(A1,2)
=IF(B10<B32,-10,IF(B10>B32,10,0))
B3 ⫽ROUNDDOWN(A1,2)
The logic for this function is shown in Figure 3-77. This func- B4 ⫽ROUND(A1*4,0)/4
tion will first test to see if Cell B10 is less than Cell B32. If Cell
B10 is less than Cell B32, the function is equal to –10. If Cell
C1 ⫽ROUND(A1,0)
B10 is not less than Cell B32, the function will test to see if C2 ⫽ROUNDUP(A1,0)
Cell B10 is greater than Cell B32. If Cell B10 is greater than C3 ⫽ROUNDDOWN(A1,0)
Cell B32, then the function is equal to 10. If Cell B10 is not C4 ⫽ROUND(A1,-2)
greater than Cell B32, then Cell B10 must be equal to B32 be-
cause we have already checked and know that Cell B10 is not
D1 ⫽CEILING(A1,0.25)
less than Cell B32, and the function is equal to zero. D2 ⫽CEILING(A1,2)
These functions are used in the following exercise. D3 ⫽FLOOR(A1,0.25)
D4 ⫽FLOOR(A1,2)
Exercise 3-7
In the first section you will work with the rounding func-
In this exercise you will practice using the rounding func- tions using the following steps:
tions, the SUM function, the AVERAGE function, and the IF 2. Enter the data in Table 3-3 into the indicated cells.
function. At the completion of this exercise your spreadsheet
should look like Figure 3-78. 3. Type 57.3333 in Cell A1. Cells B1 through C4 should
have the values shown in Table 3-4.
1. Begin by opening a new workbook. If Excel is not open,
open Excel. If Excel is open, type Ctrl+N to open a new TABLE 3-4 Results for 57.3333
workbook.
Cell Value Explanation

B1 57.33 Rounded to nearest hundredth


B2 57.34 Rounded up to nearest hundredth
B3 57.33 Rounded down to nearest hundredth
B4 57.25 Rounded to nearest quarter
C1 57 Rounded to nearest whole number
C2 58 Rounded up to nearest whole number
C3 57 Rounded down to nearest whole number
C4 100 Rounded to nearest hundred
D1 57.5 Rounded up to nearest quarter
D2 58 Rounded up to nearest even number
D3 57.25 Rounded down to nearest quarter
D4 56 Rounded down to nearest even number
FIGURE 3-78 Spreadsheet for Exercise 3-7
46 CHAPTER THREE

4. Experiment with the rounding function by changing


Cell A1 to different numbers.
5. Now change Cell A1 back to 57.3333.
In this next section you will sum Cells B1 through C4 with
the SUM function using the following steps:
6. Select Cell C5, click on the Formula menu tab, click on
the AutoSum button in the Function Library group
(shown in Figure 3-73), select Cell B1, hold down the
FIGURE 3-79 Print Button
left mouse button, and drag the cursor to Cell C4. A
dashed line should be around Cells B1 through C4, and
⫽SUM(B1:C4) will appear in Cell C5.
right of the Quick Access toolbar and selecting Quick Print
7. Press the Enter key to complete the function. Cell C5 from the popup menu shown in Figure 3-80.
should now contain 501.25. To open the Print dialogue box, shown in Figure 3-81
In this next section you will average Cells B1 through C4 (Figure 3-82 for Excel 2007), the user may (1) type Ctrl+P
with the AVERAGE function using the following steps: (type the P key while holding down the Ctrl key) or (2) se-
8. Select Cell B5 and type ⫽AVERAGE(B1:C4). lect the File tab (the Microsoft Office button for Excel 2007)
and click on Print in the left pane to bring up the Print dia-
9. Press the Enter key to complete the function. Cell B5 logue box.
should now contain 62.65625 when five decimal places For Excel 2010, the user can select the printer to be used
are shown. under Printer and set the properties for the printer by click-
In this next section you will create an IF function and a ing on Printer Properties to bring up a dialogue box for the
nested IF function using the following steps: printer. The user can select to print the active sheet, the en-
tire workbook, or only the selected area (the highlighted
10. In Cell C10, type ⫽IF(A10<A11, "Less Than","Equal to
cells) from the first settings dropdown box.
or Greater Than"). If the value in Cell A10 is less than the
For Excel 2007, the user can select the printer to be
value in Cell A11, the words Less Than will appear in Cell
used in the Name: dropdown box and set the properties for
C10. If Cell A10 is equal to or greater than Cell A11, the
the printer by clicking on the Properties... button to bring
words Equal to or Greater Than will appear in Cell C10.
up a dialogue box for the printer. By selecting the Entire
11. In Cell C11, type ⫽IF(A10<A11,"Less Than",IF(A10⫽A11, workbook radio button, the user can print all of the work-
"Equal to","Greater Than")). If the value in Cell A10 is less sheets in the workbook. By selecting the Selection radio
than the value in Cell A11, the words Less Than will appear button, the user can print the selected (highlighted) cells of
in Cell C11. If Cell A10 is equal to Cell A11, the words a worksheet.
Equal to will appear in Cell C11. If Cell A10 is greater than
Cell A11, the words Greater Than will appear in Cell C11.
12. In Cell A10, type 10 and in Cell A11 type 11. The words
Less Than should appear in Cells C10 and C11.
13. In Cell A10, type 11. The words Equal to or Greater Than
should appear in Cell C10 and the words Equal to
should appear in Cell C11.
14. In Cell A10, type 12. The words Equal to or Greater Than
should appear in Cell C10 and the words Greater Than
should appear in Cell C11.
15. Close the workbook without saving it.

PRINTING
A worksheet is printed by clicking on the Print button on
the Quick Access toolbar or by opening the Print dialogue
box. By clicking on the Print button on the Quick Access
toolbar (shown in Figure 3-79) , the worksheet is printed
without giving the user a chance to change the printing set-
tings—which printer, number of copies, range, and so forth.
If the Print button does not appear on the Quick Access
toolbar, the user may add it by clicking on the arrow at the FIGURE 3-80 Customize Quick Access Toolbar Popup Menu
Introduction to Excel 47

FIGURE 3-81 Excel 2010 Print Dialogue Box

Page Orientation
The orientation of the page is selected by clicking on the
Page Layout menu tab, clicking on the Orientation button
in the Page Setup group (shown in Figure 3-83), and clicking
on Portrait or Landscape from the popup menu.

Repeating Row at the Top of Each Page


Rows from the spreadsheet can be repeated at the top of each
page to create column headings. This is done by clicking on
the Page Layout menu tab, clicking on the Print Titles

FIGURE 3-82 Excel 2007 Print Dialogue Box FIGURE 3-83 Page Layout: Orientation Button
48 CHAPTER THREE

FIGURE 3-84 Page Layout: Print Titles Button

button in the Page Setup group (shown in Figure 3-84) to


bring up the Sheet tab of the Page Setup dialogue box FIGURE 3-86 Printing Gridlines
(shown in Figure 3-85), typing the beginning row followed
by a colon followed by the ending row in the Rows to repeat
at top: text box, and clicking on the OK button to close the
Page Setup dialogue box. The settings in Figure 3-85 would
repeat the first row of the worksheet on every page printed.

Printing Gridlines
To have the grid line of the workbook print, the user must FIGURE 3-87 Page Settings: Scale to Fit Group
check the Gridlines check box on the Sheet tab of the Page
Setup dialogue box (shown in Figure 3-85). Alternately, the
user may click on the Page Layout menu tab and check the dropdown box from the Scale to Fit group shown in Fig-
Print check box (shown in Figure 3-86) under the Gridlines ure 3-87. Similarly, the worksheet may be scaled fit on one to
heading in the Sheet Options group. nine pages high by selecting the number of pages high from
the Height: dropdown box from the Scale to Fit group. To
scale the workbook to more than nine pages high or wide,
Setting Print Scale the user must open the Page tab of the Page Setup dialogue
The area of a worksheet that fits onto one page is changed by box (shown in Figure 3-88) by clicking on the Page Layout
adjusting the scale in the Scale to Fit group on the Page menu tab and clicking on the Page Setup Dialogue Box
Layout menu tab (shown in Figure 3-87) or from the Page Launcher located at the bottom-right corner of the Scale to
Break Preview. Fit group. The page width and height are set by clicking Fit
The worksheet may be scaled fit on one to nine pages to: radio button and entering the number of pages wide and
wide by selecting the number of pages wide from the Width: high the printout is to be scaled to. Excel will then adjust the

FIGURE 3-85 Sheet Tab of the Page Setup Dialogue Box FIGURE 3-88 Page Tab of the Page Setup Dialogue Box
Introduction to Excel 49

FIGURE 3-89 Page Break Preview

scale to match the number of pages specified by the user. The Exercise 3-8
user must click on the OK button to close the Page Setup di-
alogue box. In this exercise you will prepare the file from Exercise 3-5 to
The printout of the worksheet may be set to a specific be printed by changing the orientation to landscape, repeat-
scale by clicking on the Page Layout menu tab and selecting ing Row 1 at the top of each page, and changing the scaling
the scale from the Scale: box. By default the print scale is set to one page wide using the following steps:
to Adjust to: with a scale of 100% of the normal size.
1. Make sure that Chapter 3, the workbook modified in
Exercise 3-5, is open.
Setting Page Breaks
Next, change the page orientation to landscape using the fol-
The layout of the page breaks is viewed and adjusted from lowing steps:
the Page Break View (shown in Figure 3-89). The Page Break
view is displayed by clicking on the Page Break button lo- 2. Click on the Page Layout menu tab, click on the
cated on the Status bar (shown in Figure 3-90) or by clicking Orientation button in the Page Setup group (shown in
on the View menu tab and clicking on the Page Break Figure 3-83), and click on Landscape from the popup
Preview button in the Workbook Views group (shown in menu.
Figure 3-91). Next, set Row 1 to be repeated at the top of each page using
The page breaks are moved by placing the cursor over the following steps:
the page-break line to be moved, holding down the left
mouse button while dragging the page-break line to the de- 3. Click on the Page Layout menu tab, click on the Print
sired location, and releasing the mouse button. When the Titles button in the Page Setup group (shown in Fig-
page breaks are moved they automatically change the scaling ure 3-84) to bring up the Sheet tab of the Page Setup di-
shown on the Page tab of the Page Setup dialogue box. The alogue box (shown in Figure 3-85), type 1:1 in the Rows
user may return to the Normal view by clicking on the to repeat at top: text box, and click on the OK button to
Normal button located on the Status bar (shown in Fig- close the Page Setup dialogue box.
ure 3-61) or by clicking on the View menu tab and clicking Next, you are going to set the spreadsheet so its width
on the Normal button in the Workbook Views group matches the width of a piece of paper using the Page Break
(shown in Figure 3-62). Preview view. This is done by completing the following steps:
4. Click on the View menu tab and click on the Page Break
Preview button in the Workbook Views group (shown
in Figure 3-91) to bring up the Page Break Preview view.
The spreadsheet should look similar to Figure 3-89,
with a dashed blue line between columns J and K.
5. Using the cursor, drag the dashed line to the right side of
FIGURE 3-90 Page Break View Button on the Status Bar column L. This will reduce the printing size of the detail
sheet to one page wide.
6. Click on the View menu tab and click on the Normal
button in the Workbook Views group (shown in Fig-
ure 3-62) to return to the Normal view.
7. Click the Save button on the Quick Access toolbar or
type Ctrl+S to save the workbook.

TESTING SPREADSHEETS
Before using any spreadsheet for estimating, the user must
carefully test the spreadsheet to make sure it is performing the
FIGURE 3-91 View: Page Break View Button calculations correctly. The object is to make the spreadsheet
50 CHAPTER THREE

foolproof. This is very important when someone other than Exercise 3-9
the spreadsheet designer is going to use the spreadsheet.
Foolproofing a spreadsheet is done by trying to find ways to This exercise, when completed, will be used as the starting
mess up the spreadsheet and then finding ways to prevent point for the exercises in Chapter 32. In this exercise you will
this from happening. This is not as easy as it sounds because setup the Summary Worksheet in the file from Exercise 3-8
there is always someone out there who will come up with a using the following steps:
new and creative way to mess things up. No spreadsheet can
be completely foolproof; therefore, it is important that the 1. Make sure that Chapter 3, the workbook modified in
user understand what the spreadsheet does and the limita- Exercise 3-8, is open.
tions of the spreadsheet. It is best if you test the spreadsheet 2. Select the Summary tab.
as you go rather than waiting until the spreadsheet is com-
plete. It is much easier to make small changes to the work- Begin by entering the data into the cells using the following
sheet, solving the problems as you go, than it is to find a steps:
small error in a large worksheet. 3. Type the text shown in Table 3-5 into the specified cells.

TABLE 3-5 Data for Cells in Exercise 3-9


Cell Data Cell Data Cell Data Cell Data

B1 Code C2 General Requirements B28 05-500 C36 Wood Trim


C1 Description C3 Supervision B29 05-900 C37 Cabinetry and Counter Tops
D1 Materials C4 Temporary Utilities B31 06-000 C38 Counter Tops
E1 Labor C5 Temporary Phone B32 06-100 C40 THERMAL AND MOISTURE
F1 Equipment C6 Temporary Facilities PROTECTION
G1 Subcontract C7 Cleanup B33 06-110 C41 Waterproofing
H1 Total C9 EXISTING CONDITIONS B34 06-120 C42 Insulation
B2 01-000 C10 Demolition B35 06-200 C43 Rigid Insulation
B3 01-300 C12 CONCRETE B36 06-210 C44 Stucco
B4 01-500 C13 Rebar B37 06-400 C45 Siding
B5 01-510 C14 Footing and Foundation—Labor B38 06-410 C46 Roofing
B6 01-520 C15 Footing and Foundation—Concrete B40 07-000 C47 Sheet Metal
B7 01-700 C16 Slab/Floor—Labor B41 07-100 C48 Roof Specialties
B9 02-000 C17 Slab/Floor—Concrete B42 07-200 C49 Rain Gutters
B10 02-400 C18 Concrete Pump B43 07-210 C50 Fireproofing
B12 03-000 C19 Pre-cast Concrete B44 07-220 C51 Caulking and Sealants
B13 03-200 C20 Light-weight Concrete B45 07-400 C53 OPENINGS
B14 03-300 C22 MASONRY B46 07-500 C54 Metal Doors and Frames
B15 03-310 C23 Masonry B47 07-600 C55 Wood Doors
B16 03-320 C25 METALS B48 07-700 C56 Overhead Doors
B17 03-330 C26 Structural Steel B49 07-710 C57 Store Fronts
B18 03-340 C27 Joist and Deck B50 07-800 C58 Windows
B19 03-400 C28 Metal Fabrications B51 07-900 C59 Hardware
B20 03-500 C29 Erection B53 08-000 C60 Glass and Glazing
B22 04-000 C31 WOOD, PLASTICS, AND B54 08-100 C61 FINISHES
COMPOSITES B55 08-110 C62 Drywall
B23 04-200 C32 Rough Carpentry B56 08-300 C63 Metal Studs
B25 05-000 C33 Lumber B57 08-400 C64 Ceramic Tile
B26 05-100 C34 Trusses B58 08-500 C65 Acoustical Ceilings
B27 05-200 C35 Finish Carpentry B59 08-700 C66 Flooring
Introduction to Excel 51

TABLE 3-5 (Continued)


Cell Data Cell Data Cell Data Cell Data
B60 08-800 C67 Wall Coverings B94 26-000 C104 EXTERIOR IMPROVEMENTS
B61 09-000 C68 Paint B95 26-100 C105 Asphalt
B62 09-200 C70 SPECIALTIES B97 27-000 C106 Site Concrete—Labor
B63 09-210 C71 Signage B98 27-100 C107 Site Concrete—Concrete
B64 09-300 C72 Toilet Partitions B100 31-000 C108 Rebar
B65 09-500 C73 Toilet and Bath Accessories B101 31-100 C109 Fencing
B66 09-600 C74 Fire Extinguishers and Cabinets B102 31-200 C110 Retaining Walls
B67 09-700 C76 EQUIPMENT B104 32-000 C111 Dumpster Enclosures
B68 09-900 C77 Appliances B105 32-100 C112 Signage
B70 10-000 C79 FURNISHINGS B106 32-110 C113 Outside Lighting
B71 10-100 C80 Window Treatments B107 32-120 C114 Landscaping
B72 10-200 C82 CONVEYING EQUIPMENT B108 32-130 C116 UTILITIES
B73 10-210 C83 Elevators B109 32-300 C117 Water Line
B74 10-400 C85 FIRE SUPPRESSION B110 32-310 C118 Sanitary Sewer
B76 11-000 C86 Fire Sprinklers B111 32-320 C119 Storm Drain
B77 11-300 C88 PLUMBING B112 32-330 C120 Gas Lines
B79 12-000 C89 Plumbing B113 32-340 C121 Power Lines
B80 12-200 C91 HVAC B114 32-900 C122 Telephone Lines
B82 14-000 C92 HVAC B116 33-000 C123 SUBTOTAL
B83 14-200 C94 ELECTRICAL B117 33-100 C124 Building Permit
B85 21-000 C95 Electrical B118 33-300 C125 Bond
B86 21-100 C97 COMMUNICATIONS B119 33-400 C126 SUBTOTAL
B88 22-000 C98 Communications B120 33-500 C127 Profit and Overhead Markup
B89 22-100 C100 EARTHWORK B121 33-700 C128 Profit and Overhead
B91 23-000 C101 Clearing and Grubbing B122 33-800 C129 TOTAL
B92 23-100 C102 Grading and Excavation

4. Save the workbook by clicking on the Save button on Use the ctrl key to select multiple rows before changing
the Quick Access toolbar or typing Ctrl+S. their height.
Next, format the cells to match those in Figure 2-2 using the 8. Select columns A through H, click on the View menu
following steps: tab, and click on Zoom to Selection, so that Columns A
through H cover the entire width of the spreadsheet.
5. Change the width of column A to 4, that of column B to
9. Change the formatting for Columns D through H to
8, that of column C to 36, and that of columns D
the accounting style using the Comma Style button
through H to 12.
in the Number group on the Home menu tab and then
6. Bold the data in the following Cells: B2, C2, B9, C9, B12, reduce the number of decimal points to zero by click-
C12, B22, C22, B25, C25, B31, C31, B40, C40, B53, C53, ing the Decrease Decimal button in the Number group
B61, C61, B70, C70, B76, C76, B79, C79, B82, C82, B85, on the Home menu tab twice.
C85, B88, C88, B91, C91, B94, C94, B97, C97, B100,
C100, B104, C104, B116, C116, C123, C126, and C129. 10. Center the text in Column A by selecting Column A,
Hint. Use the ctrl key to select multiple cells before clicking the Home menu tab, and clicking on the Center
changing them to bold. button in the Alignment group.
7. Change the height of Rows 8, 11, 21, 24, 30, 39, 52, 69, 11. Center the text in Column B.
75, 78, 81, 84, 87, 90, 93, 96, 99, 103, and 115 to 5. Hint. 12. Center the text in Cells D1 through H1.
52 CHAPTER THREE

13. Change the formatting for Cells D127 through H127 to 27. Click the Number of Pages button from the Header &
percentage using the Percent Style button in the Footer Elements group and press the Enter button to
Number group on the Home menu tab, and then in- move it up one line.
crease the number of decimal points to one by clicking 28. Place the cursor in the left section, click the Current
the Increase Decimal button in the Number group on Date button from the Header & Footer Elements group,
the Home menu tab. press the Space bar, and click the Current Time button
14. Underline Row 1 by selecting Cells A1 through H1 and from the Header & Footer Elements group.
clicking the Bottom Borders button in the Font group 29. Press the Enter key to move to the following line and
on the Home menu tab. If another border is shown in click the File Path button from the Header & Footer
the Borders button, select the correct border by clicking Elements group.
on the small arrow to the right of the Borders button 30. The Footer should look like Figure 3-63. When the cur-
and selecting the Bottom Border from the popup sor is moved from the left section of the footer, the
menu. &[Date] &[Time] will be replaced with the current date
15. Underline Rows 122, 125, and 128 in the same manner. and time and the &[Path]&[File] will be replaced with
16. Save the workbook by clicking on the Save button on the path and file name.
the Standard toolbar or typing Ctrl+S. 31. Click on any cell in the workbook.
Next, change the font for Column A so a checkmark (✓) can Next, prepare the worksheet to be printed by repeating the
be placed in the column indicating that the associated cost first row on each page, adding gridlines, and setting the page
code is needed for the bid. This is done as follows: breaks using the following steps:
17. Select Column A and select Webdings from the Font 32. Click on the Page Layout menu tab, click on the Print
dropdown box in the Font group on the Home menu Titles button in the Page Setup group to bring up the
tab. If Webdings is not available, try to find another font Sheet tab of the Page Setup dialogue box, type 1:1 in the
that has a check mark or replace the check marks with Rows to repeat at top: text box, and click on the OK but-
another symbol, such as an X. ton to close the Page Setup dialogue box.
18. Type an a in Cell A2, and a check mark (✓) should ap- 33. Click on the Page Layout menu tab and check the Print
pear in Cell A2. check box under the Gridlines heading in the Sheet
19. Delete the contents of Cell A2. Options group.
34. Click on the View menu tab and click on the Page Break
Headers and footers must be set up for each individual sheet.
Preview button in the Workbook Views group to bring
Next, add a header and footer to the Summary worksheet
up the Page Break Preview view.
using the following steps:
35. Using the cursor, drag the horizontal page-break line
20. Click on the Insert menu tab and click on the Header & (the dashed line) at the bottom of Page 1 between Rows
Footer button to edit the header. 60 and 61.
21. Place the cursor in the center section and click the 36. Drag the horizontal page-break line for the bottom of
Sheet Name button from the Header & Footer Page 2 below Row 129.
Elements group. The header should look like the
37. If there are any vertical page-break lines, drag the page
header of Figure 3-56. When the cursor is moved
break to the right side of Column H. The Summary
from the center section of the header, the &[Tab] will
Worksheet should now be on two pages.
be replaced with the name of the tab, in this case
Summary. 38. Click on the View menu tab and click on the Normal
button in the Workbook Views group to return to the
22. Right click on the Go to Footer button from the
Normal view.
Navigation group to move to the footer.
39. Click the Save button on the Quick Access toolbar or
23. Place the cursor in the right section and type Prepared type Ctrl+S to save the workbook.
by: followed by pressing the Underline key ten times.
24. Press the Return key and type Checked by: followed by When you print the Summary Worksheet, the worksheet
pressing the Underline key ten times. should be the same as Figure 2-2.
25. Place the cursor in the center section and click the Page
Number button from the Header & Footer Elements When you set up the Summary Worksheet for your com-
group. pany, you should use your company’s cost codes rather than
26. Following “&[Page]” type of, including a space before the ones used here. The formulas are added to the Summary
and after the of. and Detail Worksheets in Chapter 32.
Introduction to Excel 53

CONCLUSION 8. What are two ways to change the font for a cell?
9. What does the Merge and Center button do?
Excel allows the user many ways to customize the look of the
10. How do you add the worksheet name to the header of
spreadsheet and perform calculations. This chapter covered
the worksheet?
how to manage workbooks and worksheets; enter data; for-
mat spreadsheets; write formulas; round numbers using the 11. How do you add the date the worksheet was printed to
rounding functions (including CEILING and FLOOR func- the header of the worksheet?
tions); use the SUM, the AVERAGE, and IF functions; set up 12. What is the caret (^) used for?
and print the worksheets; and test worksheets. These skills 13. List the calculation steps taken to solve the following
are needed to complete the Sidebar worksheets found in the formula: (2^5+4/2)*2-1.
following chapters. 14. Cell C17 was copied to Cells B16 through D18, and the
content of Cell C17 is $B5. What are the contents of
Cells B16 through D18?
PROBLEMS 15. What value would Excel calculate for the formula
1. What is the difference between a workbook and a ROUND(122.568,-1)?
worksheet? 16. What value would Excel calculate for the formula
2. What three ways can be used to save a workbook? ROUNDUP(17.222,1)?
3. How are worksheets added to a workbook? 17. When A12 equals 17, what value would Excel calculate
4. How can a copy of a worksheet be created? for the formula IF(A12>10,"Error","OK")?
5. How are worksheets renamed? 18. When A12 equals 25, what value would Excel calculate
for the formula IF(A12<0,"Error",IF(A12>20,"Error"
6. If you were to cut the contents from Cell H15 and then
"OK"))?
save the worksheet, what would happen to the contents
from Cell H15? 19. How are rows of a spreadsheet repeated at the top of
every page?
7. Besides using the Column Width dialogue box, what are
two other ways to change the width of a column? 20. What is the page break view used for?
This page intentionally left blank
P A R T T W O

THE QUANTITY
TAKEOFF

Chapter 4 Fundamentals of the Quantity Takeoff


Chapter 5 Concrete
Chapter 6 Masonry
Chapter 7 Metals
Chapter 8 Woods, Plastics, and Composites
Chapter 9 Thermal and Moisture Protection
Chapter 10 Openings
Chapter 11 Finishes
Chapter 12 Fire Suppression
Chapter 13 Plumbing
Chapter 14 Heating, Ventilation, and Air-Conditioning (HVAC)
Chapter 15 Electrical
Chapter 16 Earthwork
Chapter 17 Exterior Improvements
Chapter 18 Utilities

I
n this section, you will be introduced to the quantity takeoff. The purpose
of this section is not to provide an all-inclusive list of equations and tables
to determine the quantities of every conceivable component on a con-
struction project, but to provide basic quantity takeoff concepts and show
how these concepts can be applied to common estimating situations. The
basic concepts are covered in Chapter 4. Chapters 5 through 18 apply these
concepts to common estimating situations grouped by MasterFormat divi-
sion. The 2004 MasterFormat moved most of the site work previously located
in Division 2 to Divisions 31 to 35. This book covers Division 31—Earthwork
(Chapter 16), Division 32—Exterior Improvements (Chapter 17), and
Division 33—Utilities (Chapter 18). The 2004 MasterFormat also divided
Division 15—Mechanical into three divisions: Division 21—Fire
Suppression, Division 22—Plumbing, and Division 23—Heating, Ventilating,
and Air Conditioning. It also moved Division 16—Electrical to Division 26.
In this book the quantity takeoff topics are covered in the order in which they
appear in the 2004/2010 MasterFormat, beginning with concrete and ending
with utilities. If the reader is more comfortable learning about estimating
using the order of the old MasterFormat, then after completing Chapter 4, he
or she can complete Chapters 16 through 18 before starting Chapter 5. Not all
divisions of the MasterFormat are covered. For example, Divisions 10 through
14 are not covered because they are often a matter of counting the items.
CHAPTER FOUR

FUNDAMENTALS OF THE
QUANTITY TAKEOFF

In this chapter you will be introduced to the process of com- PERFORMING A QUANTITY
pleting the quantity takeoff and the basic methods of deter- TAKEOFF
mining the quantities for counted items (both nonrepetitive
and repetitive members), linear components, sheet and roll While performing the quantity takeoff the estimator needs
goods, volumetric goods, and quantity-from-quantity goods. to determine all the materials, equipment, and labor tasks
The purpose of this chapter is to introduce you to the basic needed to complete the construction of the project. The
concepts used in the quantity takeoff, not to make you profi- most accurate method of doing this is for the estimator to
cient in them. As you complete Chapters 5 through 18 you build the construction project in his or her mind while
will see how these concepts apply to specific construction recording the materials, equipment, and labor tasks needed
components, and your understanding of these concepts will to complete the work.
be solidified. To demonstrate this, let’s look at the construction of the
prehung door shown in Figure 4-1. To construct the door,
the worker would begin by cutting the two side jambs and

T
top jamb to length. Next, the worker would rabbet the top of
he quantity takeoff is the process whereby the esti- the side jambs to receive the top jamb, mortise one of the
mator prepares a complete list of all building com- side jambs for the hinges, mortise the other side jamb for the
ponents that need to be constructed to complete bolt and strike, and staple the top and side jambs together to
the project. The quantity takeoff may also be called the complete the door frame. Next, the worker would cut stops
quantity survey. The quantity takeoff includes components for the top and side jambs and staple the stops to the jambs.
that are incorporated into the building (for example, foot- The worker then would mortise the door slab for the hinges
ings, masonry walls, and windows) as well as jobsite or di- and drill the holes for the door handle. Finally, the worker
rect overhead. Jobsite or direct overhead includes all items would fasten the hinges to the door slab and the door frame
that are needed to support construction that can be identi- to complete the prehung door. The door is now ready to in-
fied with a specific project, such as supervision and tempo- stall or to be packaged for shipping to the jobsite.
rary facilities. The materials needed to complete the prehung door are
Commonly used units for the quantity takeoff include shown in Table 4-1. The materials are listed in the order they
feet or lineal feet, square feet, board feet, square yards, cubic were used to complete the prehung door.
yards, acres, each, months, and lump sum. Months are used The labor tasks required to complete the prehung door
when the quantity of an item is based on the duration of the are shown in Table 4-2. Again they are listed in the order in
project, such as office trailer rental. Lump sum is used when which they are performed. Often on construction projects,
multiple items are combined into a single item for pricing, the estimator will combine a number of labor tasks into a sin-
such as all of the plumbing. The selection of takeoff units is gle task. In the case of the prehung door, the labor tasks could
determined by the way the bid is to be priced. For a concrete be combined into a single task entitled assemble prehung door.
slab on grade, the concrete is priced in cubic yards, the Finally, let’s look at the equipment needed to complete
forming in lineal feet, the labor to pour the concrete in the prehung door. To determine the equipment needed, the
cubic yards, and the labor to finish the slab in square feet or estimator must determine the equipment that will be used
square yards.

56
Fundamentals of the Quantity Takeoff 57

by the worker while completing the labor tasks. The equipment


needed to complete the labor tasks is shown in Table 4-2. To
complete the prehung door, the worker will need a miter saw to
cut the jambs and stop; a router with the appropriate bits to
rabbet the jambs and mortise the jambs and the door slab; a
staple gun and compressor to assemble the jambs and stops;
and a drill with the appropriate bits to drill the door slab and
attach the hinges. This equipment will vary based on the con-
struction techniques used by the worker. For example, if the
worker constructs the frame with nails rather than staples, he
or she would need a nail gun in place of a staple gun.
This same method is used on a large, complex building.
The estimator begins at the bottom of the building and con-
structs it from the ground up: first the excavation, then the
footings, the foundation, and so forth.

WORK PACKAGES
As the estimator performs the quantity takeoff the materials,
equipment, and labor tasks must be divided into work pack-
ages. A work package is a group of items that are related. At a
minimum the quantity takeoff should be broken down by
the job cost codes to be used on the job. Sample job cost
codes are shown in Appendix B. The job cost codes are used
FIGURE 4-1 Prehung Door to track the material, labor, and equipment costs on the job,
and, as such, a budget will need to be established for each of
TABLE 4-1 Materials for a 2ⴕ6ⴖ ⴛ 6ⴕ8ⴖ Prehung Door the job cost codes.
A single job cost code may be broken down into multi-
Quantity Item ple work packages because the materials are ordered at dif-
ferent times. For example, the lumber for a three-story
2 ea 4 5/8⬙ ⫻ 6⬘10⬙ Jamb
building may be ordered in the following lumber packages:
1 ea 4 5/8⬙ ⫻ 2⬘6 3/4⬙ Jamb first-floor walls, floor between the first and second floors,
2 ea 3/8⬙ ⫻ 1 1/4⬙ ⫻ 6⬘9⬙ Stop second-floor walls, floor between the second and third
1 ea 3/8⬙ ⫻ 1 1/4⬙ ⫻ 2⬘6⬙ Stop floors, third-floor walls, and roof. To facilitate the ordering
of these materials in lumber packages, the estimate must be
1 ea 2⬘6⬙ ⫻ 6⬘8⬙ Door Slab
grouped by work packages that divide the work into the
3 ea Hinges first-floor walls, the floor between the first and second
floors, and so forth.
The work packages also should match the way the work
TABLE 4-2 Labor Tasks and Equipment for a
on the project is scheduled. The estimate for the labor hours
2ⴕ6ⴖ ⴛ 6ⴕ8ⴖ Prehung Door should be used to determine the durations for the schedule.
As a result, the work packages should also match the sched-
Labor Task Equipment
uling tasks.
Cut jambs Miter saw As the estimator develops the work packages, he or she
must make sure everything needed for the work packages is
Rabbet side jambs Router
included in the work package at the point it will be first in-
Mortise side jambs Router stalled. For example, if the footing and foundation wall
Staple jambs together Staple gun and compressor shown in Figure 4-2 are to be included in separate work pack-
Cut stops Miter saw ages, the footing package would consist of the forms for the
footing, the four #4 continuous rebar, the #5 dowels, and the
Staple stops to jambs Staple gun and compressor
concrete for the footing. The #5 dowels, even though they are
Mortise door slab Router part of both the footing and foundation, will need to be in-
Drill door slab for handles Drill stalled with the footing; therefore, they are part of the footing
Fasten hinges to jamb and slab Drill package. The foundation wall package would consist of the
forms for the foundation, the #4 rebar located at the top and
58 CHAPTER FOUR

One of the great advantages of building the project in


the estimator’s mind is that he or she can organize the mate-
rial orders by work packages and collect the data needed to
prepare the schedule at the same time he or she prepares the
estimate.

COMMUNICATION
WITH THE FIELD
To eliminate many potential problems and delays, the esti-
mator must communicate to field employees the planned
method of construction and the usage of materials and
equipment. If the field employees use different construction
methods or different materials or equipment, the materials
and equipment ordered based on the estimator’s quantity
takeoff may be insufficient. This is shown in the following
case study.
A project contained a small, slab-on-grade office build-
ing with an attic. The construction between the office and the
attic consisted of 2×12 wood joists as shown in Figure 4-3.
To avoid the expense of ordering 22-foot-long joists, the
estimator planned to break the joists along the bearing walls
and ordered nine 8-foot joists, ten 10-foot joists, ten 12-foot
joists, and nine 14-foot joists. The estimator planned that the
FIGURE 4-2 Wall Section
carpenters would use the joists as shown in Figure 4-4.
The carpenters, not knowing how the estimator had bid
bottom of the wall, the #4 rebar at 12 inches on center run- the materials, decided to add a header as shown in Figure 4-5.
ning vertical and horizontal, concrete for the walls, and the The materials needed by the carpenters were nineteen 8-foot
anchor bolts. The anchor bolts, although they are often con- joists and twenty-one 14-foot joists. As a result the carpenters
sidered part of the lumber package, need to be included in the ran short of ten 8-foot joists (which they cut from 12-foot
foundation wall package because they will be installed at the joists), and twelve 14-foot joists had to be ordered from the
time the foundation wall is poured. The same is the case with lumber yard, causing additional expense and construction
seismic straps that are poured into the foundation wall. delays. These costs and delays could have been avoided had

FIGURE 4-3 Floor Design


Fundamentals of the Quantity Takeoff 59

FIGURE 4-4 Estimator’s Material Order

the estimator provided the carpenters a figure similar to principles for estimating each of these broad categories are
Figure 4-4 to show the planned material usage on the build- applied to many different materials. For example, the princi-
ing. This can be accomplished by redlining the framing plan ples for estimating the number of rolls of building felt
in Figure 4-3. needed for a roof are the same principles used to estimate
As the estimator builds the project in his or her mind the number of rolls of wire mesh that are needed in a slab.
the materials can be grouped into five broad categories: The remainder of this chapter looks at these general princi-
counted items, linear components, sheet and roll goods, vol- ples, which are applied to specific materials in Chapters 5
umetric goods, and quantity-from-quantity goods. The through 18.

FIGURE 4-5 Field Material Use


60 CHAPTER FOUR

COUNTED ITEMS
The simplest way to determine the quantity of an item is to
count the number of items. There are shortcut methods that
may be used when the counted items are repetitive members
such as studs in a wall. The most common unit for the quan-
tity takeoff of counted items is each.
Items that may be estimated as counted items include
rebar in spot footings, dowels, anchor bolts, steel lintels, timber
brackets, metal stairs, steel beams and columns, steel joists, steel FIGURE 4-6 Stud Placement
trusses, joist headers, joist hangers, wood columns and beams,
wood joists, wood studs, wood trusses, wood rafters, cabinetry, Five studs allows for one stud at the left end, one at 1 foot from the
residential doors and windows, hollow-metal doors, hardware, end, one at 2 feet from the end, one at 3 feet from the end, and one
at the right end, as shown in Figure 4-6. 䊏
overhead doors, metal studs, many HVAC and plumbing com-
ponents, electrical fixtures, and landscaping plants.
When counting items it is important to mark the items If a repetitive member is only needed at one end, then Eq. (4-1)
off as they are counted to avoid counting an item twice. Care can be written as follows:
also must be exercised to ensure that all of the items are Distance
counted. After counting the items one must review the draw- Number ⫽ (4-2)
Spacing
ings to make sure that no items have been missed. When
counting items, care must be taken to avoid grouping similar If a repetitive member is not needed at either end, then Eq. (4-1)
but different items together. For example, when counting can be written as follows:
doors in a residence, closet doors, which have a simple pas- Distance
sage lockset, must be kept separate from bedroom and bath- Number ⫽ ⫺1 (4-3)
Spacing
room doors, which require a privacy lockset. This slight dif-
ference in items, a passage versus a privacy lockset, may only When calculating the number of repetitive members, one
amount to a few dollars in material costs, but can be very must be careful to make sure that the distance and spacing
costly in both labor costs and construction delays if the are converted to the same units; otherwise, the number will
wrong materials are delivered to the jobsite. be off by a significant amount.
When counted items are repetitive, as with studs in a When using Eqs. (4-1) through (4-3), one must round
wall, time is saved by using a mathematical equation to count up the quantity to the next whole number to have adequate
the number of studs needed. The following equation is used materials, as shown in the following example.
to calculate the number of respective members over a speci-
fied distance and includes a repetitive member at both ends: EXAMPLE 4-2
Determine the number of studs needed for a wall 3 feet 4 inches
Distance
Number ⫽ ⫹1 (4-1) long where the studs are spaced at 1 foot on center.
Spacing
Solution: This example is the same as Example 4-1, except that the
where wall is 8 inches shorter. The number of studs is calculated using
Number ⫽ Number of Counted Items Eq. (4-1) as follows:
Distance ⫽ Distance over Which the Items Occur 3 ft!4 in
Number ⫽ ⫹ 1 ⫽ 4.33
Spacing ⫽ Spacing between the Items 1 ft

The distance and spacing should be measured in the same Using conventional rules of rounding, one would round this down
to 4, leaving the estimate 1 stud short of the needed number of
units (feet or inches), or a conversion factor needs to be in-
studs. Rounding this up, one gets 5 studs, the number of studs
cluded in the equation. The 1 in this equation adds a repetitive
needed to complete this wall. The stud placement for this wall is
member to the beginning of the distance (hereafter referred to shown in Figure 4-7.
as the end condition). This is shown in the following example.

EXAMPLE 4-1
Determine the number of studs needed for a 4-foot-long wall
where the studs are spaced at 1 foot on center.
Solution: The number of studs is calculated using Eq. (4-1) as
follows:

4 ft
Number ⫽ ⫹1⫽5
1 ft FIGURE 4-7 Stud Placement 䊏
Fundamentals of the Quantity Takeoff 61

are converted to the same units; otherwise, the number will


be off by a significant amount.
Substituting Eq. (4-5) into Eq. (4-4), we get the following:
Length
Number ⫽ (4-6)
LengthPiece ⫺ Lap
FIGURE 4-8 Connection of Linear Components When the pieces are butt jointed, the lap is zero, and we get
the following equation:
LINEAR COMPONENTS Length
Number ⫽ (4-7)
Linear components are components that are measured by LengthPiece
their length. When a linear component is composed of mul-
tiple pieces, the pieces may be attached by butting one piece These equations ignore the end conditions, such as the
to another piece or overlapping the pieces as shown in cover over the end of the rebar, and the fact that unless the
Figure 4-8. Common units for linear components include linear component makes a complete circle, there is one less
lineal feet (often referred to as feet) or each when the compo- lap than there are pieces. In most cases, this provides a
nent is composed of pieces. Items that may be estimated as slight increase in the materials calculated over the actual
linear components include footing forms, rebar for continu- materials needed. These effects are shown in the following
ous footings, steel handrails, wood sills, blocking, top and example.
bottom plates, fascia, soffit, cant strips, wood trim, sheet
metal, cabinetry, rubber base, and fencing. EXAMPLE 4-3
The linear feet of a component is often measured di-
Determine the number of 20-foot-long pieces of rebar that are
rectly off of the plans by using a scale, plan measurer, digi-
needed to complete a 40-foot-long footing. The pieces are spliced
tizer, or computer takeoff package. The number of pieces
with a lap of 2 feet and form a single bar running the length of the
that are needed for a linear component is calculated using footing. Three inches of cover over the rebar is required at each end
the following equation: of the footing.
Length Solution: The number of pieces is calculated using Eq. (4-6) as
Number ⫽ (4-4)
Effective Length follows:

where Length 40 ft
Number ⫽ ⫽ ⫽ 2.22 pieces
Number ⫽ Number of Pieces Needed LengthPiece ⫺ Lap 20 ft ⫺ 2 ft
Length ⫽ Length of Linear Component
This is slightly more than the required amount. The first piece will
Effective Length ⫽ Distance between the Start of the start 3 inches from the end of the footing and end 20 feet 3 inches
Pieces from the end of the footing. The second piece will start at 18 feet
3 inches, lapping the previous bar by 2 feet, and end at 38 feet
The effective length is shown in Figure 4-9.
3 inches. The third, and final, piece will start at 36 feet 3 inches and
The effective length is equal to the length of the pieces end at 39 feet 9 inches. The third piece is 3 feet 6 inches long or
that make up the component less the length of the lap and is 0.175 (3.5 ft>20 ft) of a 20-foot-long bar.
written as follows: Linear components should be rounded up to the next whole
Effective Length ⫽ LengthPiece ⫺ Lap (4-5) number to make sure that there are adequate materials. 䊏

where
LengthPiece ⫽ Length of the Pieces That Make up the SHEET AND ROLL GOODS
Linear Component
Sheet and roll goods are components that are measured by
Lap ⫽ Length of the Lapping of the Pieces
their area. When sheet and roll goods are composed of mul-
When calculating the number of linear components, tiple pieces, the pieces are attached by butting or lapping
one must be careful to make sure that the length and spacing them together in two directions, as shown in Figure 4-10. In

FIGURE 4-9 Effective Length


62 CHAPTER FOUR

FIGURE 4-10 Lapping of Sheet and Roll Goods

other cases, such as with brick, a space is placed between the


pieces that is filled with another material, such as mortar.
Common units for sheet and roll goods include square feet,
square yards, squares (100 square feet), or each when the
component is composed of pieces.
The key difference between sheet goods and roll goods
is that the length of rolled goods is much greater than their
width. Items that may be estimated as sheet goods include FIGURE 4-11 Effective Area for Spaced Pieces
concrete wall forms, face brick, block and structural brick,
steel deck, tongue and groove sheeting, oriented strand
board (OSB) sheathing, wood decks, wood siding, building The laps at the end and sides of a roll or sheet may be
paper, ridged insulation, asphalt shingles, membrane roof- different or they may be the same.
ing, siding, drywall, ceramic tile, acoustical tile, and vinyl The effective area for spaced pieces equals the effective
composition tile (VCT). Items that may be estimated as roll length times the effective width of the piece. The effective
goods include wire mesh, building paper, vinyl, and carpet. length equals the length plus one-half of the spacing around
The quantities for sheet and roll goods can be deter- the piece as shown in Figure 4-11.
mined by one of two methods: the area method and the row Therefore, the effective length equals the length plus
and column method. two times one-half of the spacing around the piece or the
length of the piece plus the width of one space. The effec-
tive width equals the width plus the width of one space.
Area Method The effective area for spaced pieces is calculated by the fol-
The area method determines the quantities of materials lowing equation:
needed by determining the area to be covered by the materi-
Effective Area
als and dividing it by the area covered by one sheet or roll of
⫽ (Length ⫹ SpaceLength )(Width ⫹ SpaceWidth ) (4-11)
the materials as shown in the following equation:
Care must be taken when using the area method be-
Area
Number ⫽ (4-8) cause it ignores edge conditions and may underestimate the
Effective Area quantities needed to complete the work, as seen in the fol-
where lowing example.
Number ⫽ Number of Pieces Needed
Area ⫽ Area to Be Covered EXAMPLE 4-4
Effective Area ⫽ Area Covered by One Piece Including A 21-inch-high by 48-inch-long wall is constructed of 15 5>8-inch-
Spacing or Lap long by 7 5>8-inch-high block. The mortar joints between the
The effective area for butt-jointed pieces equals the blocks are 3>8 inch thick. How many blocks are needed to construct
the wall?
length times the width of the piece and is calculated by the
following equation: Solution: Using Eq. (4-11), we calculate the effective area of one
block as follows:
Effective Area ⫽ (Length)(Width) (4-9)
Effective Area ⫽ (15 5>8 in ⫹ 3>8 in)(7 5>8 in ⫹ 3>8 in)
The effective area for lapped pieces equals the effective
⫽ (16 in)(8 in) ⫽ 128 in2
length times the effective width of the piece. The effective
length equals the length less one lap joint, just as it did with The area of the wall is calculated as follows:
linear components. The effective width equals the width less Area ⫽ (Length)(Height) ⫽ (48 in)(21 in) ⫽ 1,008 in2
one lap joint. The effective area for lapped pieces is calcu-
lated by the following equation: The number of blocks is calculated using Eq. (4-8) as follows:

Effective Area 1,008 in2


Number ⫽ ⫽ 7.87 blocks
⫽ (Length ⫺ LapLength )(Width ⫺ LapWidth ) (4-10) 128 in2
Fundamentals of the Quantity Takeoff 63

Length
NumberColumns ⫽ (4-16)
LengthPiece
Length
NumberColumns ⫽ (4-17)
LengthPiece ⫹ Space

Width may be substituted for Height and WidthPiece for


HeightPiece in Eqs. (4-12) through (4-14) for horizontal sur-
faces such as slabs on grade.
The number of pieces is then determined by multiply-
ing the number of rows by the number of columns using the
FIGURE 4-12 Block Layout
following equation:
Number ⫽ (NumberRows )(NumberColumns ) (4-18)
Using the area method, we would have ordered eight blocks. The
blocks would be laid out as shown in Figure 4-12. The first row
would require three blocks. The second row would require three
blocks, with one of the blocks being cut in half and each half placed
EXAMPLE 4-5
on either end of the row. The top row will require three blocks cut
to a height of about 5 inches. From this example we see that we Solve Example 4-4 using the row and column method. How many
would need nine rather than eight blocks because the waste from blocks are needed to construct the wall?
the cut blocks cannot be spliced together to form a new block. This
Solution: Using Eq. (4-14) to find the number of rows, we get the
waste is unavoidable. 䊏
following:

21 in 21 in
Row and Column Method NumberRows ⫽
7 5>8 in ⫹ 3>8 in

8 in
⫽ 2.625 rows

Example 4-4 introduces us to the other method for calcu-


Three rows of blocks are needed. Using Eq. (4-17) to get the num-
lating the quantities for sheet and roll goods: the row and
ber of columns, we get the following:
column method. With the row and column method, one
determines the number of rows and the number of 48 in 48 in
NumberColumns ⫽ ⫽ ⫽ 3 columns
columns needed to construct the components. The number 15 5>8 in ⫹ 3>8 in 16 in
of rows is calculated using Eq. (4-12) for lapped compo-
Three columns of blocks are needed. Using Eq. (4-18), we calculate
nents, Eq. (4-13) for butt-jointed components, and Eq. (4-14)
the number of blocks needed as follows:
for spaced components:
Number ⫽ (3 rows)(3 columns) ⫽ 9 blocks 䊏
Height
NumberRows ⫽ (4-12)
HeightPiece ⫺ Lap The row and column method calculates the correct
Height number of blocks needed to construct the wall, and it is
NumberRows ⫽ (4-13) easy to see that the entire top row of blocks will need to be
HeightPiece
cut. This allows the estimator to take this into account as
Height he or she calculates the labor for the installation of the
NumberRows ⫽ (4-14)
HeightPiece ⫹ Space block.
These equations should be familiar because they are sim-
ilar to those used for linear components. When determining VOLUMETRIC GOODS
the number of rows, one should always round up, unless the
fraction of a row is less than the lap. Rounding up should be to Volumetric goods are commonly measured in cubic yards or
the next whole number, 1>2, 1>3, 1>4, or 1>n (where n is a cubic feet. Items that may be estimated as volumetric goods
whole number) fraction of a sheet or roll. Rounding up to 2>5, include concrete, excavation, and asphalt. The quantity of
for example, will give you the wrong quantity because 1>5 of rectangular column-shaped volumetric goods is calculated
the material will be wasted when you take two pieces that are by multiplying the height by the width by the length as ex-
2>5 of a sheet; therefore, 2/5 should be rounded up to 1>2, pressed in the following equation:
which will properly take the waste into account. Volume ⫽ (Height)(Width)(Length) (4-19)
The number of pieces per row (hereafter referred to as
columns) is calculated using Eq. (4-15) for lapped compo- Chapter 16 discusses four additional methods for cal-
nents, Eq. (4-16) for butt-jointed components, and Eq. (4-17) culating the volume of excavation. These are the average-
for spaced components: width-length-depth method, average-end method, modified-
average-end method and cross-sectional method. Appendix A
Length has additional formulas that may be used to calculate the vol-
NumberColumns ⫽ (4-15)
LengthPiece ⫺ Lap ume of a cylinder, prism, cone, and pyramid.
64 CHAPTER FOUR

Solution: Using Eq. (4-20), we get the follow quantity:


EXAMPLE 4-6
5,000 sf 2
Determine the volume of a 100-foot by 100-foot concrete slab. The Quantity ⫽ ⫽ 16.7 gallons 䊏
300 ft 2/gallon
slab is 4 inches thick. Express your answer in cubic yards.
Solution: The volume of the slab is determined by Eq. (4-19) as
follows: EXAMPLE 4-8
3 Determine the quantity of roofing nails needed for a 14 square
ba b ⫽ 123.5 yd3
4 in 1 yd
Volume ⫽ (100 ft)(100 ft)a 䊏 (square ⫽ 100 square foot) roof. Historically, 340 nails are needed
12 in/ft 27 ft3
per square.
Solution: Using Eq. (4-21), we get the follow quantity:
QUANTITY-FROM-QUANTITY
Quantity ⫽ (14 sq)(340 nails>sq) ⫽ 4,760 nails 䊏
GOODS
Quantity-from-quantity goods are estimated based upon the
quantity of another item. For example, the number of gallons WASTE
of paint may be estimated by dividing the area of the surface Ordering the foregoing quantities may not provide the quan-
to be painted by the coverage rate for a gallon of paint. tities necessary to complete the construction project because
Alternately, roofing nails may be estimated by multiplying the some of the materials are lost because of waste. Unavoidable
area of the roof in squares (100 square feet) by the average waste is waste that is the result of not being able to use scrap
number of nails used per square. Items that may be estimated materials (as we saw in Examples 4-4 and 4-5). Avoidable
by the quantity-from-quantity method include mortar, per- waste is waste that is due to improper use of materials, lost or
lite, fasteners, saw blades, waterproofing and dampproofing, damaged materials, and the difference between the actual di-
blown insulation, stucco, shims, drywall tape and mud, adhe- mensions and the design dimensions. Where possible, un-
sives, grout, tack strip and seaming tape for carpet, paint, and avoidable waste should be included in the original quantity
electrical wiring. Quantity-from-quantity estimates are per- takeoff of the materials as it was in Example 4-5. This is neces-
formed using one of the following equations: sary to accurately track and control avoidable waste. A waste
QuantityBase factor is often added to the quantities to account for avoidable
Quantity ⫽ (4-20) waste, as well as unavoidable waste that has not already been
Coverage
included. The waste factor is expressed as a percentage of the
where calculated quantity. The quantity of material needed, includ-
Quantity ⫽ Quantity of Material Needed ing the waste, is calculated using the following equation:
QuantityBase ⫽ Quantity of the Item that the Estimate Quantitywith Waste
is Based Upon
⫽ Quantitywithout Waste a1 ⫹ b (4-22)
Waste Percentage
Coverage ⫽ Coverage of the Material Needed 100
Quantity Volume, area, or number may be substituted into
⫽ (QuantityBase )(Average Quantity Required) (4-21) Eq. (4-22) for the quantity. The inclusion of waste is shown
in the following example.
where
Quantity ⫽ Quantity of Material EXAMPLE 4-9
Needed
Determine the volume of concrete for the slab in Example 4-6.
QuantityBase ⫽ Quantity of the Item
Include 10% waste in the calculated volume.
that the Estimate is
Based Upon Solution: From Example 4-6, the volume of the slab is 123.5 cubic
yards. Using Eq. (4-22), we add the waste as follows:
Average Quantity Required ⫽ Average Quantity
b
Needed to Cover One 10
Volumewith Waste ⫽ (123.5 yd3 )a1 ⫹
Unit of Base Material 100
The coverage and average quantity required may be obtained ⫽ (123.5 yd3 )(1.10) ⫽ 135.8 yd3 䊏
from historical data, manufactures’ data, or reference books.
Estimating the quantity from quantity is shown in the fol- The waste factor should be determined from historical
lowing two examples: data. Historical data is obtained by comparing the estimated
quantity without waste to the actual quantities used on the
EXAMPLE 4-7
project, using the following equation:

Waste Percentage ⫽ 100 a


Determine the quantity of paint needed to paint 5,000 square feet QuantityUsed
⫺ 1b (4-23)
of wall. One gallon of paint will cover 300 square feet of wall. QuantityEstimated
Fundamentals of the Quantity Takeoff 65

Data on the quantities used should be available from the


EXAMPLE 4-10
company’s accounting system.i When performing the quan-
The slab in Example 4-6 required 138 cubic yards of concrete. tity takeoff, the estimator should keep an accurate estimate
Determine the actual waste percentage for the slab. of the quantities before adding avoidable waste. This quan-
Solution: From Example 4-6, the estimated volume of the slab was tity is to be used to measure the actual quantity of waste. On
123.5 cubic yards. The waste percentage is calculated using Eq. (4-21) one apartment project the author reviewed, he found that
as follows: the number of studs needed to complete identical apartment
units varied by almost 10% because of differences in the use
138 yd3
Waste Percentage ⫽ 100 a ⫺ 1b ⫽ 11.74% 䊏 of materials.
123.5 yd3

CONCLUSION 8. An 8-foot-high by 50-foot-long wall is faced with 7 1>2-


inch-long by 2 1>2-inch-high bricks. The mortar joints
The quantity takeoff is best performed by the estimator between the bricks are 1>2-inch thick. Using the area
building the project in his or her mind, keeping track of the method, determine the number of bricks needed to face
materials, equipment, and labor tasks needed to complete the wall.
the project. The estimate should be broken down into work
9. Use the row and column method to solve Problem 7.
packages that contain related materials and tasks, such as
materials that will be ordered together. The planned use of 10. Use the row and column method to solve Problem 8.
materials, labor, and equipment must be communicated 11. Determine the volume of a 200-foot by 75-foot concrete
with the field personnel. slab. The slab is 6 inches thick. Express your answer in
The quantity takeoff for materials can be divided into cubic yards and include 10% waste.
counted items (both repetitive and nonrepetitive), linear 12. Determine the volume of a 20-foot by 15-foot by 4-
components, sheet and roll goods, volumetric goods, and foot-high concrete footing. Express your answer in
quantity-from-quantity goods. Similar methods are used to cubic yards and include 5% waste.
determine the quantities in each of these categories. 13. Determine the quantity of paint needed to paint 12,620
square feet of wall. One gallon of paint will cover 250
square feet of wall.
PROBLEMS 14. Determine the quantity of joint compound needed to
finish 3,000 square feet of gypsum-board wall. One
1. What is the best way of performing the quantity takeoff?
gallon of joint compound will cover 200 square feet of
2. Why should the estimator communicate the planned wall.
material use and construction methods to the field
15. Determine the quantity of roofing nails needed for a
personnel?
27.65 square (square ⫽ 100 square foot) roof. Historically,
3. Determine the number of studs needed for a 75-foot- 375 nails are needed per square.
long wall where the studs are spaced at 1 foot on center.
16. Determine the quantity of shims needed to install 22
4. Determine the number of studs needed for a 120-foot- doors. Historically, 0.75 bundles of shims are needed
long wall where the studs are spaced at 16 inches on per door.
center.
17. The slab in Problem 11 required 300 cubic yards of
5. Determine the number of 20-foot-long pieces of pipe concrete. Determine the actual waste percentage for
needed to complete 150 feet of pipe. The pipe is con- the slab.
nected with a butt joint.
18. The footing in Problem 12 required 47 cubic yards of
6. Determine the number of 20-foot-long pieces of rebar concrete. Determine the actual waste percentage for
needed to complete a 240-foot-long footing. The pieces the slab.
are spliced with a lap of 18 inches and form a single bar
running the length of the footing.
7. An 8-foot-high by 50-foot-long wall is constructed of REFERENCE
15 5>8-inch-long by 7 5>8-inch-high blocks. The mortar 1. For more information on construction accounting systems
joints between the blocks are 3>8 inch thick. Using the and tracking quantities, see Steven J. Peterson, Construction
area method, determine the number of blocks needed to Accounting and Financial Management, Prentice Hall, Upper
construct the wall. Saddle River, NJ, 2005.
CHAPTER FIVE

CONCRETE

In this chapter you will learn how to apply the principles in than accounting for each of the items needed. To do this the
Chapter 4 to concrete, forms, and reinforcing for continuous estimator must have historical data on the equipment, mate-
and spread footings, walls, square and round columns, beams, rials, and labor needed to complete a square foot, lineal foot,
slab on grade, raised slab, and stairs. This chapter includes or set of forms.
sample worksheets that may be used in the quantity takeoff. Beams, girders, walls, and tall footings (footings greater
You are encouraged to set these worksheets up in Excel and than 12 inches high) are often bid based on the square
learn how to use them. This chapter also includes example footage of forms needed to form the concrete member.
takeoffs from the residential garage drawings given in When figuring the area, the estimator must make sure to in-
Appendix F. clude forms on all sides and the bottom (if needed) of the
concrete member. For example, on a foundation wall the es-
timator will need to include both sides of the wall and the

C
ends of the wall. The area of the forms should be based on
oncrete work consists of three tasks: installation
the area of the forms, not the area of the wall. Wall forms
and removal of the forms, installation of the rein-
typically come in 2-, 4-, and 8-foot heights. When forming
forcement (rebar and wire mesh), and placement
an 18-inch-high footing or wall, a 2-foot-high form would
and finishing of the concrete. The installation of the forms
be used. In this case the forming height would be 2 feet
and rebar may occur in many different orders. For footings,
rather than the wall height of 18 inches.
the forms are placed and then the rebar is placed inside the
Short footings (footings 12 inches high or less) can be
forms; for columns, the rebar is placed and the forms are
formed by using 2 ⫻ 10s and 2 ⫻ 12s; therefore, they are
placed around the rebar; and for walls, one side of the forms
often bid based on the lineal footage of forms. Just as in the
is placed, the rebar is placed, and then the forms are finished.
case of the walls, the estimator needs to be sure to include
After the rebar is placed and the forms are completed, the
forms on both sides and ends of the footings.
concrete is placed and then finished. After the concrete has
Columns are often bid based on the square footage
cured, the forms are removed. With careful planning and
(square and rectangular columns only), lineal footage of
scheduling of the concrete work, the forms can be reused
the column, or set of forms. When prefabricated forms or
many times on the same job.
Sonotube are used, they may be bid based on the set of
forms required.
Raised slabs are often bid based on the square footage of
FORMS the slab, often ignoring the small amount of forms needed
Forms or formwork may be bid by itemizing all of the com- around the perimeter. When forming a raised slab, the bot-
ponents of the forms, or they may be bid by the square foot, tom forms of the slab need to be supported until the slab has
the lineal foot, or set of forms. When bidding formwork by cured sufficiently to support its own weight.
itemizing all of the components of the forms, the estimator When estimating forms, the estimator must determine
must be familiar with the forming system to be used and not only the quantity of forms to be installed, but also the
build the forms in his or her mind, counting the items as he quantity of form material that must be purchased for the
or she goes. project, as it affects the cost of the forms. The quantity of
Estimators will often bid the formwork based on the forms that needs to be purchased for a project is based on
square footage, the lineal footage, or the set of forms, rather how many times the forms can be reused, whether the forms
66
Concrete 67

can be used on other projects, and the life of the forms. If the jobs, the rebar is often shop fabricated and shipped to the
concrete for a project can be poured in four separate pours jobsite ready for placement.
with sufficient time between the pours to allow the concrete Many projects are now specifying epoxy-coated rebar.
to cure, the project will take one-fourth of the forms it Typically, epoxy-coated rebar is light green and is cut and
would need if the concrete on the project was poured in a bent in a fabrication shop. Epoxy-coated rebar that has
single pour. If the forms are available from another project been field cut and bent must have all cuts and bends re-
or can be used on a subsequent project, the purchase of the coated. This will require additional installation time in the
forms may be spread out over many projects, reducing the field and epoxy paint to coat the rebar. Field cuts and bends
cost of forms that need to be included in the estimate for the should be noted in the estimate so they can be included in
project. However, if a project requires a custom form that the estimate.
will not be reused, the entire purchase of the forms must be Welded wire fabric (WWF), often called wire mesh, is
included in the estimate. The final factor is how long the designated by the spacing of the wires and the wire size. For
forms will last before they wear out or are consumed as they example, WWF 6 ⫻ 6 10>10 is made up of #10 wires welded
are cut to meet specific dimensions. at 6 inches on center in both ways. Welded wire fabric is
available in flat sheets or rolls 5 feet wide by 150 feet long.
Like continuous rebar, welded wire fabric must be lapped as
REINFORCING specified by the design profession or building code. A com-
Concrete reinforcing consists of rebar, welded wire fabric, mon lapping is the spacing between wires. In the case of
chairs to position the rebar, and so forth. Rebar is designated WWF 6 ⫻ 6 10>10 it is 6 inches.
by bar size, which represents the nominal diameter of the bar
in eighths of an inch. For example, a #7 bar has a nominal di- CONCRETE
ameter of 7>8 inch. Rebar is taken off by the lineal foot or by
the number of pieces. Small quantities of rebar are often The specifications for concrete vary based on its use.
purchased by the piece or by the lineal foot, whereas large Concrete used for slabs often has a higher strength than con-
quantities of rebar are often purchased by the pound or ton. crete used for footings and foundations. The estimator must
The weight per foot for common rebar sizes is shown in read the specification to determine the different types of
Table 5-1. concrete used on the project. When estimating concrete, the
Continuous rebar must be lapped. The lapping is speci- quantities for different types of concrete must be kept sepa-
fied by the structural engineer or other design professional. rate. Concrete specifications may be performance based, de-
In the event it is not specified by the design professional, the sign based, or both. A performance-based specification sets
contractor has to meet the lapping requirement in the build- the requirements for the physical properties of the concrete,
ing code of the jurisdiction where the building is being con- such as strength and slump. A design-based specification sets
structed. Lapping is specified by a minimum length or a limits on the various components used to compose the con-
number of bar diameters or both. For example, the drawings crete. Concrete is typically composed of cement, large aggre-
may require that the rebar be lapped 24 bar diameters or gate, fine aggregate, and water. Cement powder comes in five
1 foot, whichever is greater. For a #3 bar, 24 bar diameters is types. Type I is normal cement, Type II is moderate-sulfate-
9 inches (24 ⫻ 3>8 in). The bar would have to be lapped the resistance cement, Type III is high-early-strength cement,
greater of 9 inches or 1 foot; therefore, the bar would have to Type IV is low-heat-of-hydration cement, and Type V is
be lapped 1 foot. For a #6 bar, 24 bar diameters is 18 inches high-sulfate-resistance cement. In some concrete mixes, part
(24 ⫻ 6>8 in), and the bar would have to be lapped the of the cement is replaced by fly ash, a pozzolan. Admixtures
greater of 18 inches or 1 foot. may be added to achieve specific physical properties, such as
On small jobs the rebar is often fabricated in the field air entrainment. All of these affect the price of the concrete.
from straight bar. A common length for rebar is 20 feet; The estimator needs to carefully review the specifications to
however, lengths up to 60 feet are often available. For large make sure he or she understands what type of concrete is re-
quired to complete the job.
Pricing for concrete is best obtained from the concrete
TABLE 5-1 Rebar Sizes and Weights (lb/ft) suppliers. It is best to provide the supplier with a copy of
Bar Size Weight Bar Size Weight the specifications for use in pricing the concrete. Concrete
companies often charge extra for small or short loads.
2 0.167 8 2.670 Care should be taken to note any short loads during the
3 0.376 9 3.400 takeoff process.
During hot weather, ice or chilled water is often
4 0.668 10 4.303
added to keep the concrete from overheating. This in-
5 1.043 11 5.313 creases the cost of the concrete, and the estimator must
6 1.502 14 7.650 incorporate these costs into the concrete estimate. During
7 2.044 18 13.600 the quantity takeoff the estimator needs to identify the
need for ice or chilled water.
68 CHAPTER FIVE

When concrete is placed in cold weather, precautions waste factors should be monitored and compared to estimated
need to be taken to ensure that the concrete does not freeze. quantities to ensure that an appropriate waste factor is being
During cold weather the water added to the concrete is usu- used in the estimates. In addition, extra gravel is often pro-
ally heated, adding to the cost of the concrete. In addition, vided to the concrete crew to be used to fill in low spots in an
the concrete is often protected by covering the concrete with effort to minimize concrete waste.
plastic, straw, or concrete blankets and by providing heat. Let’s look at how the equations in Chapter 4 are used
The need for hot water and concrete protection should be to calculate the quantities for some common concrete
included in the concrete takeoff. components.
The labor required to place the concrete consists of two
components: the placement of the concrete and the finishing
of the concrete. The placement of the concrete is bid by the SPREAD FOOTINGS
cubic yard; the finishing of the concrete is bid by the square The work package for the spread footings (sometimes re-
foot or square yard of the finished surface. Often the two ferred to as spot footings) includes the concrete for the foot-
components are combined into a single cost for a concrete ings, forms, the horizontal rebar in the footings, and the
component of a specified size. dowels needed to connect the footings to columns. The ties
A concrete pump is often used to place concrete that can- at the bottom of the column are often included in the rebar
not be discharged directly from the concrete truck into its order for the spread footings because they are used to prop-
final place. Estimators need to be sure they understand what erly space the dowels that run between the spread footing
access is available to the site so they can determine the amount and the column. The concrete is treated as a volumetric
of concrete pumping that will be necessary to complete the good, the forms for short footings (12 inches thick or less)
work. When pumping concrete, care must be taken to ensure are treated as a linear component, the form for tall footings
that the concrete mix has been designed for pumping. Not all (thicker than 12 inches) are treated as sheet goods and are
concrete mixes can be pumped with satisfactory results. measured by the square foot, and rebar is treated as a
Concrete waste varies based on the type of member counted item. The quantity takeoff for a spread footing is
being constructed. Beams, columns, walls, and other mem- shown in the following example.
bers that have a small area of contact with the ground require
less waste than members that have a high area of contact with
the ground, such as slabs and curbs. A typical waste factor for EXAMPLE 5-1
beams, columns, walls, and other members that have a small
Determine the volume of concrete in cubic yards, the lineal feet of
area of contact with the ground is 5%. A typical waste factor
forms, and the rebar needed to complete 10 of the footings shown
for slabs, curbs, footings, and other members that have a high in Figure 5-1. Provide 3 inches of cover for the rebar in the footings
area of contact with the ground is 10%. Leaving an area and 2 inches of cover for the rebar in the columns. Include 10%
1>2 inch too low increases the amount of concrete needed to waste in the calculated volume of concrete, and express the volume
construct a 4-inch concrete slab by 12.5%. Careful grading of of concrete in quarter-yard increments. The ties are to be ordered
the subgrade is critical to controlling concrete waste. Actual with the column rebar.

FIGURE 5-1 Footing and Column Details


Concrete 69

Solution: The volume of the concrete is determined as follows:


The following formulas need to be entered into the
Volume ⫽ (No. of Footings)(Width 1)(Width 2)(Thickness) associated cells:
⫽ (10 ea) c 3 ft ⫹ d c 3 ft ⫹ d (1 ft)
2 in 2 in
12 in/ft 12 in/ft
Cell Formula
1 yd3
⫽ (100.3 ft )a
3
b ⫽ 3.71 yd3
27 ft3 B9 =IF((B6*12+B7)>12,2*B1*(B2+B3/
Add the waste using Eq. (4-22) as follows: 12+B4+B5/12)
*Roundup((B6+B7/12)/2,0)*2,2*B1
Volumewith Waste ⫽ (3.71 yd3 ) a1!⫹ ! b
10 *(B2+B3/12+B4+B5/12))
100
B10 =B1*(B2+B3/12)*(B4+B5/12)*
⫽ (3.71 yd3 )(1.10) ⫽ 4.08 yd3 (B6+B7/12)/27*(1+B8/100)
Rounding up to quarter-yard increments, we get 4.25 cubic yards. C9 =IF((B6*12+B7)>12,"sft","ft")
The lineal feet of forms are calculated as follows:
Length The formula in Cell B9 uses an IF function to select be-
⫽ (No. of Footings)(Width 1 ⫹ Width 2 ⫹ Width 1 ⫹ Width 2) tween square footage of forms for footings over 12 inches
⫽ (No. of Footings)(2)(Width 1!⫹ !Width 2) thick and linear feet for footings 12 inches thick or less.
When calculating the area of forms, Cell B9 uses a
⫽ (10 ea)(2) c3 ft ⫹ d ⫽ 127 ft
2 in 2 in
⫹ 3 ft ⫹ ROUNDUP function to round up the form height to 2-
12 in/ft 12 in/ft
foot increments. Cell C9 uses an IF function to select be-
Each footing will require eight #4 horizontal bars for a total of tween the units of feet (ft) and square feet (sft).
80 bars (10 footings ⫻ 8 bars/footing). The length of the bars needs The data for the spread footings are entered in Cells
to be 3 inches shorter on both ends of the bar than the width of the
B1 through B8. The data shown in the foregoing figure is
footings. The bars will be 32 inches (3 ft 2 in ⫺ 2 ⫻ 3 in) long.
from Example 5-1 and is formatted using the comma
Each footing will require eight #5 dowels for a total of 80
dowels. The length of the long leg of the dowels is the height of the style, which replaces zeros with dashes.
footing less the cover at the bottom of the footing plus the height
of the dowel above the top of the footing, or 25 inches (1 ft ⫺ 3 in ⫹
1 ft 4 in). The short leg of the dowels will begin 3 inches inside
the footing and run 2 inches inside the column. The distance
from the edge of the column to the edge of the footing is 11 inches COLUMNS
(3 ft 2 in>2 ⫺ 16 in>2). The length of the short leg is 10 inches The work package for the columns includes the concrete
(11 in ⫺ 3 in ⫹ 2 in).
for the columns, forms, the vertical rebar in columns, and
the ties. The dowels, and often the ties at the bottom of
the column, are included in the footing package. The con-
crete is treated as a volumetric good. The forms for square
EXCEL QUICK TIP 5-1 and rectangular columns are estimated by the square foot,
lineal foot, or set of forms. The forms for round columns
Spread Footing are estimated by the lineal foot or set of forms. The rebar
The volume of concrete and square footage of forms (for is treated as a counted item. The quantity takeoff for a
footing greater than 12 inches thick) or lineal feet of square and round column is shown in the following
forms (for footings 12 inches thick or less) needed for a examples.
spread footing is set up in a spreadsheet by entering the
data and formatting the cells as follows:
EXAMPLE 5-2
A B C Determine the volume of concrete in cubic yards, the square feet of
1 No. of Footings 10 ea forms, and the rebar needed to complete 10 of the columns shown
2 Width 1 3 ft in Figure 5-1. Provide 2 inches of cover for the rebar in the
3 2 in columns. The ties begin 3 inches from the bottom of the column
4 Width 2 3 ft and end 3 inches from the top of the column. Include 5% waste in
5 2 in the calculated volume of concrete and express the volume of con-
6 Thickness 1 ft crete in quarter-yard increments.
7 - in
Solution: The volume of the concrete is determined as follows:
8 Concrete Waste 10 %
9 Forms 126.67 ft Volume ⫽ (No. of Columns)(Width 1)(Width 2)(Height)
1 yd3
ba b(8 ft)a b ⫽ 5.27 yd3
10 Volume 4.09 cyd 16 in 16 in
⫽ (10 ea)a
12 in/ft 12 in/ft 27 ft3
70 CHAPTER FIVE

Add the waste using Eq. (4-22) as follows:


The following formulas need to be entered into the
b ⫽ 5.53 yd3
5 associated cells:
Volumewith Waste ⫽ (5.27 yd3 )a1 ⫹
100
Rounding to quarter-yard increments, we get 5.5 cubic yards. The Cell Formula
square feet of forms are calculated as follows:
Area
B8 =B1*2*(B2+B3/12+B4+B5/12)*B6
⫽ (No. of Columns) (Width 1 ⫹ Width 2 ⫹ Width 1 ⫹ Width 2) B9 =B1*(B2+B3/12)*(B4+B5/12)*(B6)/
27*(1+B7/100)
⫻ (Height)
⫽ (No. of Columns)(2)(Width 1!⫹ !Width 2)(Height) The data for the column footings is entered in Cells B1
b(8 ft) ⫽ 427 ft2
16 in 16 in through B7. The data shown in the foregoing figure is
⫽ (10 ea)(2)a ⫹
12 in/ft 12 in/ft from Example 5-2 and is formatted using the comma
Each column will require eight #6 vertical bars for a total of 80 bars style, which replaces zeros with dashes.
(10 columns ⫻ 8 bars/column). The length of the bars needs to be
3 inches shorter than the height of the column, or 7 foot 9 inches (8 ft
⫺ 3 in) long.
The ties for the column are located in 6-inch increments start-
ing at 3 inches and ending at 7 foot 9 inches. The distance over
EXAMPLE 5-3
which the ties occur is 7 feet 6 inches (7 ft 9 in ⫺ 3 in). The number
of ties is calculated using Eq. (4-1) as follows: Determine the volume of concrete in cubic yards, the lineal feet of
the sonotube, and the rebar needed to complete 10 of the columns
7 ft 6 in shown in Figure 5-2. Provide 2 inches of cover for the rebar in the
Number ⫽ ⫹ 1 ⫽ 16 ties
6 in columns. The ties begin 3 inches from the bottom of the column
Two additional ties are needed to meet the requirement for three and end 3 inches from the top of the column. Include 5% waste in
ties at 3 inches on center at the top and bottom of the column. the calculated volume of concrete, and express the volume of con-
These ties are located at 6 inches from the bottom and top of the crete in quarter-yard increments.
column. The ties will be located at the following distances from the Solution: The volume of the concrete is determined as follows:
bottom of the column: 3 in, 6 in, 9 in, 1 ft 3 in, 1 ft 9 in, 2 ft 3 in, 2 ft
9 in, 3 ft 3 in, 3 ft 9 in, 4 ft 3 in, 4 ft 9 in, 5 ft 3 in, 5 ft 9 in, 6 ft 3 in, 6 Volume ⫽ (No. of Columns)(␲)(Diameter>2) 2 (Height)
2 1 yd3
b (8 ft)a b ⫽ 4.13 yd3
ft 9 in, 7 ft 3 in, 7 ft 6 in, and 7 ft 9 in. 16 in
⫽ (10 ea)(␲)a
The number of ties needed for each column is 18 (16 ⫹ 2), (12 in/ft)(2) 27 ft3
and the number of ties needed for 10 columns is 180 (10 columns ⫻
18 ties/column) ties. The width of the ties will be 2 inches shorter Add the waste using Eq. (4-22) as follows:
on both sides of the column, or 12 inches (16 in ⫺ 2 in ⫺ 2 in)
b ⫽ 4.33 yd2
5
square. 䊏 Volumewith Waste ⫽ (4.13 yd3 )a1 ⫹
100
Rounding up to quarter-yard increments, we get 4.50 cubic yards.
The lineal feet of forms are calculated as follows:
Length ⫽ (No. of Columns)(Height) ⫽ (10 ea)(8 ft) ⫽ 80 ft

EXCEL QUICK TIP 5-2 Each column will require eight #6 vertical bars for a total of 80 bars
(10 columns ⫻ 8 bars/column). The length of the bars needs to be
Rectangular Column 3 inches shorter than the height of the column, or 7 feet 9 inches
The volume of concrete and area of forms needed for a (8 ft ⫺ 3 in) long.
rectangular column is set up in a spreadsheet by entering The ties for the column are located at 6-inch increments start-
ing at 3 inches and ending at 7 feet 9 inches. The distance over
the data and formatting the cells as follows:
which the ties occur is 7 feet 6 inches (7 ft 9 in ⫺ 3 in). The number
A B C of ties is calculated using Eq. (4-1) as follows:
1 No. of Columns 10 ea 7 ft 6 in
2 Width 1 - ft Number ⫽ ⫹ 1 ⫽ 16 ties
6 in
3 16 in
4 Width 2 - ft Two additional ties are needed to meet the requirement for
5 16 in three ties at 3 inches on center at the top and bottom of the column.
These ties are located at 6 inches from the bottom and top of the
6 Height 8 ft
column. The total number of ties needed for each column is 18
7 Concrete Waste 5 %
(16 ⫹ 2). The total number of ties needed for 10 columns is 180
8 Forms 427 sft (10 columns ⫻ 18 ties/column) ties. The width of the ties will be
9 Volume 5.53 cyd 2 inches smaller than the diameter of the column on both sides of the
column, or 12 inches (16 in ⫺ 2 in ⫺ 2 in) in diameter. 䊏
Concrete 71

FIGURE 5-2 Column Detail

forms for short footings (12 inches thick or less) are treated
EXCEL QUICK TIP 5-3 as a linear component, the forms for tall footings (thicker
Round Column than 12 inches) are treated as sheet goods and are measured
by the square foot, the dowels are treated as a counted item,
The volume of concrete needed for a round column is set
and the continuous rebar is treated as a linear component.
up in a spreadsheet by entering the data and formatting
Continuous footings are similar to spread footings except
the cells as follows:
that they are much longer than they are wide and they often
A B C turn to follow the outline of the building. Continuous footings
1 No. of Columns 10 ea are handled in a similar manner to spread footings with two
2 Diameter - ft exceptions that are a result of the footing turning to follow the
3 16 in outline of the building. First, when measuring the length of
4 Height 8 ft continuous footings one must be careful not to count the cor-
5 Concrete Waste 5 % ners twice. If one were to measure the outside of the footings,
6 Volume 4.34 cyd the corners would be counted twice as shown in Figure 5-3.
To avoid counting the corners twice, one must begin the
The following formula needs to be entered into
measurement for L2 as shown in Figure 5-4.
Cell B6:
Second, when calculating the number of dowels, a dowel
=B1*(PI()*((B2+B3/12)/2)^2)*B4/27* to account for the end condition must be included for each
(1+B5/100) straight segment of continuous footing. This ensures that
there is a dowel located at each corner, end, or intersection.
In Excel, ␲ (3.141592654) is written as follows: PI()
The quantity takeoff for a continuous footing is shown
The data for the column is entered in Cells B1
in the following example.
through B5. The data shown in the foregoing figure is
from Example 5-3 and is formatted using the comma
style, which replaces zeros with dashes.

CONTINUOUS FOOTINGS
The work package for the continuous footing includes the
concrete for the footing, forms, the horizontal rebar in the
footings, and the dowels needed to connect the footings to
columns. The concrete is treated as a volumetric good, the FIGURE 5-3 Double-Counted Corner
72 CHAPTER FIVE

FIGURE 5-4 Proper Way to Measure Corners

EXAMPLE 5-4
Determine the volume of concrete in cubic yards, the lineal feet of
forms, and the rebar needed to complete the footings shown in
Figures 5-5 and 5-6. Include 8% waste in the calculated volume of
concrete, and express the volume of concrete in quarter-yard in-
crements. Provide 3 inches of cover for the rebar in the footings.
The continuous rebar is purchased in 20-foot lengths and is lapped
18 inches.
Solution: The first step is to find the length of the footings. We
begin by dividing the footings into segments as shown in Figure 5-7.
The length of the footing at the top of the foundation plan is
equal to the length of the foundation wall plus the length the foot-
ing extends beyond the foundation wall at both ends. The footing
extends half of the difference between the width of the footing FIGURE 5-6 Foundation Section
and the width of the wall, or 11 inches (30 in>2 ⫺ 8 in>2) beyond
the foundation wall as shown in Figure 5-8. The length of the The footing at the left side of the foundation plan begins at the
footing is 25 feet 10 inches (24 ft ⫹ 11 in ⫹ 11 in). Similarly, the bottom of the top footing and ends at the top of the bottom footing
length of the footing at the bottom of the foundation plan is also as shown in Figure 5-7. The distance from the exterior of the foun-
25 feet 10 inches. dation wall and the bottom of the top footing is 1 foot 7 inches

FIGURE 5-5 Foundation Plan


Concrete 73

FIGURE 5-7 Segments for Footings

(11 ft ⫺ 1 ft 7 in ⫺ 1 ft 7 in). The lengths of the footings are shown


in Figure 5-10.
The total length of the footing is the sum of the individual
lengths and is calculated as follows:
Length ⫽ 25 ft 10 in ⫹ 25 ft 10 in ⫹ 18 ft 10 in ⫹ 18 ft 10 in
⫹ 11 ft 4 in ⫹ 7 ft 10 in
Length ⫽ 108 ft 6 in ⫽ 108.5 ft
The volume of the concrete is determined as follows:
FIGURE 5-8 Footing Distances
Volume ⫽ (Length)(Width)(Thickness)
1 yd3
(8 inches ⫹ 11 inches) as shown in Figure 5-9. Similarly, the dis- ⫽ (108.5 ft)(2.5 ft)(1 ft)a b ⫽ 10.04 yd3
tance from the exterior of the foundation wall and the top of the 27 ft3
bottom footing is 1 foot 7 inches. The length of the footing is 18 feet Add the waste using Eq. (4-22) as follows:
10 inches (22 ft ⫺ 1 ft 7 in ⫺ 1 ft 7 in).
b ⫽ 10.84 yd3
Similarly, the length of the right footing is 18 feet 10 inches. 8
Volumewith Waste ⫽ (10.04 yd3 )a1 ⫹
The length of the right-center footing is 11 feet 4 inches (12 ft ⫺ 1 ft 100
7 in ⫹ 11 in). The length of the top-center footing is 7 feet 10 inches Rounding up to quarter-yard increments, we get 11 cubic yards.
Using the same procedures that were used to determine the
length of the footing, we can determine the length of the indi-
vidual forms. The lengths of the individual forms are shown in
Figure 5-11.
The lineal feet of forms is the sum of the individual lengths
and is calculated as follows:
Length ⫽ 25 ft 10 in ⫹ 23 ft 10 in ⫹ 25 ft 10 in ⫹ 23 ft 10 in
⫹ 9 ft 6 in ⫹ 10 ft 4 in ⫹ 11 ft 4 in ⫹ 8 ft 6 in
⫹ 20 ft 10 in ⫹ 18 ft 10 in ⫹ 8 ft 10 in ⫹ 7 ft 10 in
⫹ 8 ft 10 in ⫹ 7 ft 10 in
FIGURE 5-9 Footing Distances ⫽ 212 ft
74 CHAPTER FIVE

FIGURE 5-10 Footing Lengths

There are four continuous bars in the footings with an average total the rebar in the interior footings. A total of 458 feet is needed. The
length of 108.5 feet per bar, for a total length of 434 feet. In addition number of 20-foot bars is calculated using Eq. (4-6) as follows:
to this rebar, four 36-inch-long (twice the lap or 2 ⫻ 18 inches) L-
458 ft
shaped bars are needed at each intersection for an additional 24 Number ⫽ ⫽ 25 each
feet (2 intersections ⫻ 4 bars/intersection ⫻ 3 ft/bar). The L- (20 ft ⫺ 1.5 ft)
shaped bars are used to connect the rebar in the exterior footings to

FIGURE 5-11 Lengths of the Footing Forms


Concrete 75

The short leg of the #5 dowels will run from a point 3 inches inside
the footing to the center of the footing. The short leg will be EXAMPLE 5-5
12 inches long (30 in>2 ⫺ 3 in). The long leg will run from a point Determine the volume of concrete in cubic yards for the footing in
3 inches above the bottom of the footing to 18 inches (the required Example 5-4 using the centerline method.
lap) above the top of the footing. The long leg will be 27 inches long
(12 in ⫺ 3 in ⫹ 18 in). The number of dowels is calculated using Solution: The length of the centerline of the footing on the top of
the following equation: the foundation plan is equal to the length of the foundation wall
less one-half of the thickness of the foundation wall on both ends,
Distance 108.5 ft or 23 feet 4 inches (24 ft ⫺ 8 in>2 ⫺ 8 in>2). The length of the cen-
Number ⫽ ⫹6⫽ ⫹ 6 ⫽ 115 each
Spacing 1 ft terline of the footing on the bottom of the foundation plan is the
same as that at the top.
The 6 in this equation is to account for the end condition for all of
The length of the centerline of the footing on the left of the foun-
the six walls. 䊏
dation plan is equal to the length of the foundation wall less one-half of
the thickness of the foundation wall on both ends, or 21 feet 4 inches
Although it is time-consuming to calculate the length of (22 ft ⫺ 8 in>2 ⫺ 8 in>2). The length of the centerline of the footing on
the footing and the length of the side of the footings, this can the right of the foundation plan is the same as that on the left.
be rapidly done by using a plan measurer, such as the one in The length of the centerline of the right-center footing is equal
Figure 1-4, a digitizer, such as the one in Figure 1-5, or a to the length of the foundation wall less one-half of the thickness of
takeoff software package. The length of the forms can be ap- the foundation wall on the left end less the distance from the outside
of the foundation wall to the inside of the footing on the right end.
proximated by multiplying the footing length by two. Using
This distance is 19 inches (11 in ⫹ 8 in) as shown in Figure 5-8. The
this method for the preceding example gives the length of
length of the footing is 10 feet 1 inch (12 ft ⫺ 8 in>2 ⫺ 19 in).
the forms as 217 feet rather than the actual length of 212 feet. The length of the centerline of the top-center footing is calcu-
This method of calculation can overstate or understate the lated in the same way as the right-center footing. Its length is 9 feet
quantity of forms needed. 1 inch (11 ft ⫺ 8 in>2 ⫺ 19 in). The dimensions for the footings are
Another method used to determine the length of a foot- shown in Figure 5-14.
ing is the centerline method. With the centerline method the The total length of the footing is the sum of the individual
lengths of the footings are measured along the centerlines of lengths and is calculated as follows:
the footings. When measuring around corners, the center- Length
line method double counts one-fourth of the corner and ig- ⫽ 23 ft 4 in ⫹ 23 ft 4 in ⫹ 21 ft 4 in ⫹ 21 ft 4 in ⫹ 10 ft 1 in
nores one-fourth of the corner as shown in Figure 5-12. The ⫹ 9 ft 1 in
area double counted offsets the area ignored. When using ⫽ 108 ft 6 in ⫽ 108.5 ft
the centerline method at intersections, such as the one
shown in Figure 5-13, the measurement of the intersecting The volume of the concrete is determined as follows:
footing must stop at the edge of the other footing to avoid Volume ⫽ (Length)(Width)(Thickness)
including an area twice. If you measure to the centerline, the 1 yd3
shaded area in Figure 5-13 will be measured twice. ⫽ 108.5 ft(2.5 ft)(1 ft)a b ⫽ 10.04 yd3
27 ft3
ˇ ˇ

Add the waste using Eq. (4-22) as follows:

b ⫽ 10.84 yd3
8
Volumewith Waste ⫽ (10.04 yd3 )a1 ⫹
100
Rounding up to quarter-yard increments, we get 11 cubic yards.
This is the same answer as we got for Example 5-4. 䊏

EXCEL QUICK TIP 5-4


Continuous Footing

FIGURE 5-12 Measuring Corners The volume of concrete needed for a continuous footing
is set up in a spreadsheet by entering the data and for-
matting the cells as follows:
A B C
1 Length 108 ft
2 6 in
3 Width 2 ft
4 6 in
5 Thickness 1 ft
6 - in
7 Concrete Waste 8 %
8 Volume 10.85 cyd
FIGURE 5-13 Measuring Intersections
76 CHAPTER FIVE

FIGURE 5-14 Footing Dimensions

foundation wall in Figures 5-5 and 5-6. Include 5% waste in the


The following formula needs to be entered into calculated volume of concrete, and express the volume of concrete
Cell B8: in quarter-yard increments. Provide 2 inches of cover for the rebar
=(B1+B2/12)*(B3+B4/12)*(B5+B6/12)/ in the wall and lap the continuous rebar 18 inches. The continuous
rebar will be ordered in 20-foot lengths.
27*(1+B7/100)

The data for the footings is entered in Cells B1 through Solution: The length of the wall is calculated in the same manner
B7. The data shown in the foregoing figure is from as the lengths of the footings were calculated in Example 5-4. The
Example 5-4 and is formatted using the comma style, lengths of the walls are shown in Figure 5-15.
which replaces zeros with dashes. The total length of the wall is calculated as follows:

Length
⫽ 24 ft ⫹ 20 ft 8 in ⫹ 24 ft ⫹ 20 ft 8 in ⫹ 9 ft 8 in ⫹ 11 ft 4 in
FOUNDATION WALLS ⫽ 110!ft 4 in
The work package for the foundation walls includes the
The volume of the concrete is determined as follows:
concrete for the walls, forms, the vertical and horizontal
rebar in walls, and anchor bolts. The dowels are included in Volume ⫽ (Length)(Width)(Thickness)
the footing package. The concrete is treated as a volumetric 1 yd3
a b
(8 in)
⫽ (110.33 ft)(8 ft)
ˇ

good. The forms are estimated by the square foot. The verti- ( 12 in/ft) 27 ft3
˛˛

cal rebar is treated as a counted item; the horizontal rebar is


⫽ 21.79 yd3
treated as a linear good. The same principles used for han-
dling corners of continuous footings apply to foundation Add the waste using Eq. (4-22) as follows:
walls. Foundation walls may be thought of as narrow, tall,
b ⫽ 22.88 yd3
continuous footings. The quantity takeoff for a foundation 5
Volumewith Waste ⫽ (21.79 yd3 )a1 ⫹
wall is shown in the following example. 100

Rounding up to quarter-yard increments, we get 23 cubic yards.


The length of the individual forms can be determined using the
EXAMPLE 5-6
same procedures that were used to determine the length of the
Determine the volume of concrete in cubic yards, the square feet of footing forms. The lengths of the individual forms are shown in
forms, the rebar, and the anchor bolts needed to complete the Figure 5-16.
Concrete 77

FIGURE 5-15 Lengths of the Foundation Walls


The lineal feet of forms is the sum of the individual lengths Alternatively, they may be measured using a plan measurer, digi-
and is calculated as follows: tizer, or software takeoff package. The area of the forms is calcu-
Length ⫽ 24 ft ⫹ 22 ft ⫹ 24 ft ⫹ 22 ft ⫹ 11 ft 4 in ⫹ 10 ft 4 in lated as follows:
⫹ 11 ft 4 in ⫹ 10 ft 4 in ⫹ 22 ft 8 in ⫹ 20 ft 8 in Area ⫽ (Length)(Height) ⫽ (219.33 ft)(8 ft)
⫹ 10 ft 8 in ⫹ 9 ft 8 in ⫹ 10 ft 8 in ⫹ 9 ft 8 in ⫽ 1,755 ft2
⫽ 219 ft 4 in

FIGURE 5-16 Lengths of the Foundation Forms


78 CHAPTER FIVE

The number of continuous bar needed, for one bar every 12 inches The key differences are that forms need to be included for
is calculated using Eq. (4-1) as follows: the bottom of the beam and the forms will need to be sup-
8 ft ported until the concrete has cured. The takeoff for a con-
Number ⫽ ⫹ 1 ⫽ 9 each crete beam is shown in the following example.
1 ft
Because the top and bottom bars are doubled, two additional bars
need to be added to the number of bars needed, for one bar every EXAMPLE 5-7
12 inches. The number of continuous bars is 11 (9 ea ⫹ 2 ea). The av-
Determine the volume of concrete in cubic yards, the square feet of
erage length of the continuous bars is 110.33 feet for a total length of
forms, and rebar needed to complete the beam in Figure 5-17.
1,214 feet. As was done for the footings, eleven 36-inch L-shaped bars
Only half of the beam is shown in Figure 5-17, with the other half
need to be added at each intersection for an additional 66 feet of rebar
being a mirror image of the one shown. Include 5% waste in the
(2 intersections ⫻ 11 bars>intersection ⫻ 3 ft>bar). The L-shaped bars
calculated volume of concrete, and express the volume of concrete
are used to connect the rebar in the exterior walls to the rebar in the
in quarter-yard increments. Provide 2 inches of cover for the rebar
interior walls. The total length of continuous rebar is 1,280 feet. The
in the beam.
number of 20 foot bars is calculated using Eq. (4-6) as follows:
Solution: The volume of the concrete is calculated as follows:
1,280 ft
Number ⫽ ⫽ 70 each
(20 ft ⫺ 1.5 ft) Volume ⫽ (Length)(Width)(Thickness)
1 yd3
The vertical bars run from the bottom of the wall to 2 inches below ⫽ (16 ft)(1.5 ft)(1 ft)a b
27 ft3
˛˛

the top of the wall, for a length of 7 feet 10 inches. The number of
vertical bars is calculated using the following equation: Volume ⫽ 0.89 yd3
Distance 110.33 ft Add the waste using Eq. (4-22) as follows:
Number ⫽ ⫹6⫽ ⫹ 6 ⫽ 117 each
Spacing 1 ft
b ⫽ 0.93 yd3
5
Volumewith Waste ⫽ (0.89 yd3 )a1 ⫹
The 6 in this equation is to account for the end condition for all of 100
the six walls. The number of anchor bolts is calculated as follows:
Rounding up to quarter-yard increments, we get 1 cubic yard.
Distance (110.33 ft)(12 in/ft) Forms are needed on the bottom of the beam between the end
Number ⫽ ⫹6⫽ ⫹6
Spacing (32 in) columns. The area of the forms is calculated as follows:
⫽ 48 each 䊏 Area ⫽ 2(Area of Side) ⫹ 2(Area of End) ⫹ Area of Bottom
Area ⫽ 2(16 ft)(1.5 ft) ⫹ 2(1 ft)(1.5 ft)
⫹ (16 ft ⫺ 2 ⫻ 1 ft 4 in)(1 ft)
EXCEL QUICK TIP 5-5
⫽ 64.34 ft2
Foundation Wall
The #5 dowels should have been ordered with the column. Two #5
The volume of concrete needed for a foundation wall is bars 5 feet 1 inch long are needed for each end of the beam, for a
set up by changing the Cell A5 of the worksheet in Excel total of four. Three #5 bars 8 feet 4 inches (4 ft 2 in ⫻ 2) are
Quick Tip 5-4 to Height as follows: needed for the center of the beam. Six stirrups are needed for each
end, for a total of 12. The stirrups will need to be 4 inches less
A B C than the dimensions for the beam in order to provide 2 inches of
1 Length 110 ft cover. The dimensions for the stirrups are 14 inches high by
2 4 in 8 inches wide. 䊏
3 Width - ft
4 8 in
5 Height 8 ft SLAB ON GRADE
6 - in
7 Concrete Waste 5 % The work package for a slab on grade includes the concrete
8 Volume 22.88 cyd for the slab, the area to be finished, forms, and rebar or wire
mesh. The concrete is treated as a volumetric good, the
The data for the foundation wall is entered in Cells B1 forms are treated as a linear component, rebar is treated as a
through B7. The data shown in the foregoing figure is linear component, and wire mesh is treated as a sheet good.
from Example 5-6 and is formatted using the comma The quantity takeoff for a slab on grade is shown in the fol-
style, which replaces zeros with dashes. lowing examples.

EXAMPLE 5-8
BEAMS
Determine the volume of concrete in cubic yards, the area to be
The same principles that were used to determine the quan- finished, the lineal feet of forms, and number of 20-foot bars of #4
tity of concrete, forms, and rebar for footings, columns, and rebar needed to complete a slab on grade 100 feet long by 40 feet
walls can be used for determining the quantities for beams. wide. The slab is reinforced with #4 rebar at 18 inches on center.
Concrete 79

FIGURE 5-17 Beam Section

Include 12% waste in the calculated volume of concrete, and The total length of rebar is calculated as follows:
express the volume of concrete in quarter-yard increments.
Length ⫽ 28 bars(100 ft/bar) ⫹ 68 bars(40 ft/bar) ⫽ 5,520 ft
Provide 36 bar diameters of lap on the rebar.
The lap is 18 inches (36 ⫻ 0.5 in) or 1.5 feet. The number of 20-foot
Solution: The volume of concrete is calculated as follows:
bars is calculated using Eq. (4-6) as follows:
Volume ⫽ (Length)(Width)(Thickness)
5,520 ft
1 yd3 Number ⫽ ⫽ 299 each 䊏
ba b ⫽ 49.38 yd3
1 ft
⫽ (100 ft)(40 ft)(4 in)a (20 ft ⫺ 1.5 ft)
12 in 27 ft3
Add the waste using Eq. (4-22) as follows:

b ⫽ 55.31 yd3
12
Volumewith Waste ⫽ (49.38 yd3 )a1 ⫹
100 EXCEL QUICK TIP 5-6
Rounding up to quarter-yard increments, we get 55.50 cubic yards. Slab on Grade with Rebar
The area to be finished is calculated as follows: The volume of concrete and the number of bars of rebar
Area ⫽ (100 ft)(40 ft) ⫽ 4,000 ft2 needed for a slab on grade are set up in a spreadsheet by
entering the data and formatting the cells as follows:
The length of the forms is calculated as follows:
A B C
Length ⫽ 2(Length of Side1 ) ⫹ 2(Length of Side2 )
1 Slab Length 100 ft
⫽ 2(100 ft) ⫹ 2(40 ft) 2 Slab Width 40 ft
⫽ 280 ft 3 Slab Thickness 4 in
The number of 100-foot-long bars needed to cover the slab in the
4 Waste 12 %
long direction is calculated using Eq. (4-1) as follows: 5 Bar Spacing 18 in
6 Bar Size 4 #
40 ft 7 Bar Length 20 ft
Number ⫽ ⫹ 1 ⫽ 28 bars
1.5 ft 8 Lap 36 # of dia.
9
The number of 40-foot-long bars needed to cover the slab in the
10 Area 4,000 sft
short direction is calculated using Eq. (4-1) as follows:
11 Volume 55.31 cyd
100 ft 12 No. of Bars 299 each
Number ⫽ ⫹ 1 ⫽ 68 bars
1.5 ft
80 CHAPTER FIVE

The following formulas need to be entered into the The following formulas need to be entered into the
associated cells: associated cells:

Cell Formula Cell Formula


B10 =B1*B2 B9 =B1*B2
B11 =(B1*B2*(B3/12)/27)*(1+B4/100) B10 =(B1*B2*(B3/12)/27)*(1+B4/100)
B12 =ROUNDUP((ROUNDUP(B1*12/B5+1,0)* B11 =ROUNDUP(ROUNDUP(2*B2/(B6-B7/
B2+ROUNDUP(B2*12/B5+1,0)*B1)/ 12),0)/2*B1/(B5-B7/12),0)
(B7-B8*(B6/8)/12),0)
The formula for Cell B11 rounds the number of rows up
The data for the slab is entered in Cells B1 through B8. The to the nearest half row. The data for the slab is entered in
data shown in the foregoing figure is from Example 5-8. Cells B1 through B7. The data shown in the foregoing
figure is from Example 5-9.

EXAMPLE 5-9
Determine the number of 150-foot by 5-foot rolls of wire mesh that
would be needed for the slab in Example 5-8 if the #4 rebar were re-
placed by wire mesh. The wire mesh will need to be lapped 6 inches. RAISED SLABS
Solution: Run the rolls the long direction in the slab. Using the The estimating of raised slabs is similar to the estimating of
row and column method, determine the number or rows of wire slabs on grade, with two exceptions. First, the thickness of
mesh needed to cover the 40-foot width of the slab using Eq. (4-12) the slab may vary because the bottom of the slab is poured
as follows: over an intentionally uneven surface (such as a metal deck)
40 ft and because the structure supporting the slab may sag under
NumberRows ⫽ ⫽ 9 rows
(5 ft ⫺ 0.5 ft) the weight of the concrete, making the slab thicker at the
center of the spans than near the supports. To account for
The number of columns is calculated using Eq. (4-15) as follows:
the uneven surface of the deck, the average slab thickness
100 ft must be determined.
NumberColumns ⫽ ⫽ 0.67 columns
(150 ft ⫺ 0.5 ft) For the metal deck shown in Figure 5-18, the average
The number of rolls is calculated using Eq. (4-18) as follows:
thickness is determined by the following equation:

Number ⫽ (9 rows)(0.67 columns) ⫽ 6.03 rolls 䊏 (W1 ⫹ W2 )(D)


TAve ⫽ T ⫹ (5.1)
2S

where
EXCEL QUICK TIP 5-7 T ⫽ Distance from Top of Slab to Top of Metal Deck
Wire Mesh–Reinforced Slab on Grade W1 ⫽ Width of the Metal Deck Cell at the Top
W2 ⫽ Width of the Metal Deck Cell at the Bottom
The volume of concrete and the number of rolls/sheets of
D ⫽ Depth of the Metal Deck Cell
wire mesh needed for a slab on grade are set up in a
spreadsheet by entering the data and formatting the cells S ⫽ Spacing of the Metal Deck Cells
as follows:
A B C
1 Slab Length 100 ft
2 Slab Width 40 ft
3 Slab Thickness 4 in
4 Waste 12 %
5 Wire Mesh Length 150 ft
6 Wire Mesh Width 5 ft
7 Wire Mesh Lap 6 in
8
9 Area 4,000 sft
10 Volume 55.31 cyd
11 Wire Mesh 7 each
FIGURE 5-18 Metal Deck
Concrete 81

The amount of concrete needed to account for the sag is


a function of how much a structure deflects under the
weight of the concrete as it is being poured. This additional
concrete is treated in the same manner as waste; identify
the historical amount of concrete needed to account for the
sag as a percentage of the estimated volume of concrete.
Typically, sag adds 10% to 15% to the amount of concrete
needed to pour the slab.
The second way that estimating raised slabs differs
FIGURE 5-19 Metal Deck Dimensions from estimating slabs on grade is that the bottom of the
slab must be formed. There are three basic ways to form
the bottom of the slab. The first is to form the bottom of the
EXAMPLE 5-10 slab with removable forms with a structural support that
A 100-foot by 50-foot by 3-inch-thick slab is poured over the metal are removed after the concrete has cured to the point that it
deck shown in Figure 5-19. The depth of the slab is measured from can support its own weight. In this case, the cost of the
the top of the slab to the top of the metal deck. Determine the aver- forms and supporting structure is often based on the square
age thickness of the slab and the number of yards of concrete footage of the slab. A second way is to use a self-support-
needed to pour the slab. Add 10% waste. ing metal deck as the form. In this case, the metal deck and
Solution: The average thickness is determined using Eq. (5-1) as
the building structure that supports it remain as part of the
follows: building after the construction of the slab is complete. The
metal deck and supporting structure are included in the
(4 1>2 in ⫹ 2 1>2 in)(1 1>2 in)
TAve ⫽ 3 in ⫹ ⫽ 3.875 in materials needed for the construction of the building. The
2 ⫻ 6 in third way is to use a metal deck that is not capable of sup-
The volume of concrete is calculated as follows: porting the weight of the concrete, which must be sup-
Volume ⫽ (Length)(Width)(Thickness) ported until the concrete has cured to the point that it can
support its own weight, as is the case with composite slabs.
1 yd3
ba b ⫽ 59.80 yd3
1 ft
⫽ (100 ft)(50 ft)(3.875 in)a When the concrete has cured, the support structure is re-
12 in 27 ft3
moved, leaving the metal deck and concrete. In this case
Add the waste using Eq. (4-22) as follows: the support structure is included in the forming, and the
metal deck is included in the materials needed for the con-
b ⫽ 65.78 yd3
10
Volumewith Waste ⫽ (59.80 yd3 )a1 ⫹ 䊏 struction of the building.
100

EXCEL QUICK TIP 5-8 STAIRS


Concrete Slab on Metal Deck
The volume of concrete needed for stairs can be estimated by
The volume of concrete needed for a concrete slab on a determining the cross-sectional area of the stairs and multi-
metal deck similar to Figure 5-18 is set up in a spreadsheet plying the cross-sectional area by the width of the stairs as
by entering the data and formatting the cells as follows: shown in the following example.
A B C
1 Slab Length 100 ft
EXAMPLE 5-11
2 Slab Width 50 ft
3 T 3.00 in Determine the volume of concrete needed to construct the stairs in
4 D 1.50 in Figure 5-20.
5 W1 2.50 in Solution: The cross-sectional area of the stairs can be treated as a
6 W2 4.50 in parallelogram and seven triangles as shown in Figure 5-21.
7 S 6.00 in The area of the parallelogram equals the length of two of the
8 Waste 10 % parallel sides multiplied by the perpendicular distance between the
9 Volume 65.78 cyd two sizes and is calculated as follows:

b ⫽ 2.84 ft2
The following formula needs to be entered into 1 ft
Area ⫽ (6.5 in)(5.25 ft)a
Cell B9: 12 in

=B1*B2*((B3+(B5+B6)*B4/(2*B7))/12)/27* The area of the triangles is one-half the base times the height mul-
(1+B8/100) tiplied by the number of stairs. The area of the seven triangles is
calculated as follows:
The data for the slab is entered in Cells B1 through B8. The
1 ft 2
Area ⫽ (7 ea)a b(10 in)(7 in)a b ⫽ 1.70 ft2
data shown in the foregoing figure is from Example 5-10. 1
2 12 in
82 CHAPTER FIVE

FIGURE 5-20 Stairs

EXAMPLE 5-12
Determine the concrete, rebar, and forms needed to pour the foot-
ings, foundation wall, and interior concrete slab for the residential
garage given in Appendix F. Add 5% waste for the footings and
foundation wall and 10% waste for the floor slab. The continuous
rebar is to be lapped 18 inches and is ordered in 20-foot lengths.
Solution: The dimensions for the concrete footing are shown in
Figure 5-22.
The footing length and volume of concrete needed to pour the
footing are calculated as follows:
Length ⫽ 3 ft 4 in ⫹ 27 ft ⫹ 21 ft 8 in ⫹ 27 ft ⫹ 3 ft 4 in
⫽ 82 ft 3 in ⫽ 82.33 ft
Volume ⫽ (Length)(Width)(Thickness)
1 ft 2 1 yd3
⫽ (82.33 ft)(10 in)(20 in)a b a b ⫽ 4.24 yd3
12 in 27 ft3
Add the waste using Eq. (4-22) as follows:
FIGURE 5-21 Stair Cross-Sectional Area
b ⫽ 4.45 yd3
5
Volumewith Waste ⫽ (4.24 yd3 )a1 ⫹
100
The length of 10-inch-high forms needed for the footing is shown
in Figure 5-23.
The length of the forms needed to pour the footing is calcu-
The cross-sectional area is 4.54 square feet (2.84 ft2 ⫹ 1.70 ft2). The lated as follows:
volume is calculated as follows:
Length ⫽ 27 ft ⫹ 25 ft ⫹ 27 ft ⫹ 5 ft ⫹ 1 ft 8 in ⫹ 3 ft 4 in
1 yd3
Volume ⫽ (4.54 ft )(5 ft)a
2
b ⫽ 0.84 yd
3
䊏 ⫹ 23 ft 8 in ⫹ 21 ft 8 in ⫹ 23 ft 8 in ⫹ 3 ft 4 in
27 ft3
⫹ 1 ft 8 in ⫹ 5 ft
⫽ 168 ft
The footing requires three #4 continuous bars, for a total length of
SAMPLE TAKEOFF FOR 247 feet (3 ⫻ 82.33 ft). The number of 20-foot bars is calculated
THE RESIDENTIAL GARAGE using Eq. (4-6) as follows:
A sample takeoff from a set of plans is shown in the follow- 247 ft
Number ⫽ ⫽ 14 each
ing example. (20 ft ⫺ 1.5 ft)
Concrete 83

FIGURE 5-22 Length of Footings

FIGURE 5-23 Length of Footing Forms


84 CHAPTER FIVE

The short leg of the #5 dowels will run from a point 3 inches in-
side the footing to the center of the footing. The short leg will be
7 inches long (20 in>2 ⫺ 3 in). The long leg will run from a point
3 inches above the bottom of the footing to 2 inches below the
top of the 24-inch-high foundation wall. The long leg will be
29 inches long (10 in ⫺ 3 in ⫹ 24 in ⫺ 2 in). The dowels only
need to be located in the footing where there is a foundation wall
above the footing. The length of the foundation wall is calculated
as follows:

Length ⫽ 3 ft 4 in ⫹ 26 ft ⫹ 22 ft 8 in ⫹ 26 ft ⫹ 3 ft 4 in
⫽ 81 ft 4 in ⫽ 81.33 ft
The number of dowels is calculated using the following equation:
Distance (81.33 ft)(12 in/ft)
Number ⫽ ⫹5⫽ ⫹ 5 ⫽ 66 each FIGURE 5-24 Cross Section at Overhead Door
Spacing 16 in
The 5 in this equation is to account for the end condition for all five
of the wall segments. The foundation wall consists of the 2-foot-
high by 8-inch-wide wall around the perimeter of the garage and
the 14-inch-high by 8-inch-wide frost wall under the garage door. The length of the wall that needs anchor bolts equals the length of
The volume of concrete needed for the foundation wall is calcu- the wall less the width of the 3-foot-wide door. The number of an-
lated as follows: chor bolts with nuts and washers is calculated using the following
equation:
Volume ⫽ (Length)(Width)(Height)
Distance (81.33 ft ⫺ 3 ft)
Number ⫽ ⫹5⫽ ⫹ 5 ⫽ 45 each
b
1 ft
⫽ (81.33 ft)(2 ft)(8 in)a Spacing 2 ft
12 in
1 ft 2 In addition, four HPAHD22 hold-downs are needed at the front
⫹ (16 ft)(14 in) (8 in)a b of the garage. The floor slab extends from the inside of the foun-
12 in
dation wall around the perimeter of the garage except at the over-
1 yd3
⫽ (120.88 ft3 )a b ⫽ 4.48 yd3 head door, where it extends to the exterior of the wall. At the over-
27 ft3 head door the floor slab is thickened. The concrete for the interior
Add the waste using Eq. (4-22) as follows: slab without the concrete at the overhead door is calculated as
follows:
b ⫽ 4.70 yd3
5
Volumewith Waste ⫽ (4.48 yd3 )a1 ⫹ Volume ⫽ (Length)(Width)(Thickness)
100
1 yd3
ba b
1 ft
Two-foot-high forms are used to form both the foundation wall ⫽ (24 ft 8 in)(22 ft 8 in)(4 in)a
12 in 27 ft3
and the frost wall. The length of the forms needed is calculated as
follows: ⫽ 6.90 yd3

Length ⫽ 26 ft ⫹ 24 ft ⫹ 26 ft ⫹ 24 ft ⫹ 24 ft 8 in ⫹ 22 ft 8 in The cross-sectional area of the slab at the overhead door is shown
in Figure 5-24. The cross-sectional area is calculated as follows:
⫹ 24 ft 8 in ⫹ 22 ft 8 in
⫽ 194 ft 8 in Area ⫽ (8 in)(4 in) ⫹ 0.5(12 in ⫹ 8 in)(4 in)
1 ft 2
The area of the forms needed is calculated as follows: ⫽ 72 in2 a b ⫽ 0.5 ft2
12 in
Length ⫽ (194 ft 8 in) (2 ft) ⫽ 390 ft2
The volume of concrete at the overhead door is calculated as follows:
Four #4 bars of rebar are needed in the foundation wall and frost
1 yd3
wall. The length of the rebar is calculated as follows: Volume ⫽ (Area)(Length) ⫽ (0.5 ft2 )(16 ft)a b
27 ft3
Length ⫽ 4(81.33 ft ⫹ 16 ft) ⫽ 389.32 ft
⫽ 0.30 yd3
The number of 20-foot-long bars needed is calculated using Eq. (4-6)
as follows: The volume of concrete without waste is 7.20 cubic yards (6.90 yd3
⫹ 0.30 yd3). Add the waste using Eq. (4-22) as follows:
389.32 ft
Number ⫽ ⫽ 21 each
b ⫽ 7.92 yd3
10
(20 ft ⫺ 1.5 ft) Volumewith Waste ⫽ (7.20 yd3 )a1 ⫹
100
Eighteen-inch by 18-inch L-shaped #4 dowels are needed between
the frost wall and the floor slab. The number of dowels is calculated The area that needs to be finished is calculated as follows:
using Eq. (4-1) as follows: Area ⫽ (24 ft 8 in)(22 ft 8 in) ⫹ (16 ft)(8 in) ⫽ 570 ft2
(16 ft)(12 in/ft) The quantities needed for the garage, grouped by the cost codes in
Number ⫽ ⫹ 1 ⫽ 13 each
16 in Appendix B, are shown in Table 5-2. 䊏
Concrete 85

TABLE 5-2 Quantities for Residential Garage


03-200 Rebar 03-300 Footings and Foundation—Labor

#4 ⫻ 20⬘ rebar (footings) 14 ea Install continuous rebar 20⬘ 21 ea


70 ⫻ 29⬙ L-dowels (footings) 66 ea Install dowels 13 ea
#4 ⫻ 20⬘ rebar (foundation) 21 ea Install anchor bolt 45 ea
18⬙ ⫻ 18⬙ L-dowels (foundation) 13 ea Pour foundation 4.75 yd3
1/2⬙ ⫻ 10⬙ anchor bolt (foundation) 45 ea
03-310 Footings and Foundation—Concrete
1/2⬙ nut (foundation) 45 ea
1/2⬙ washer (foundation) 45 ea 3,500-psi concrete (footings) 4.50 yd3
HPAHD22 hold-downs 4 ea 3,500-psi concrete (foundation) 4.75 yd3

03-300 Footings and Foundation—Labor 03-320 Slab/Floor Labor

10⬙-high footing forms 168 ft Pour slab 8.00 yd3


Install continuous rebar 20⬘ 14 ea Finish slab 570 ft2
Install dowels 66 ea
03-330 Slab/Floor Concrete
Pour footings 4.50 yd3
2⬘-high foundation forms 390 ft2 4,000-psi concrete (slab) 8.00 yd3

CONCLUSION 5. Determine the length of forms needed for Problem 4.


6. The footing in Problem 4 has three #4 continuous bars.
Concrete consists of the concrete materials, forms, and The rebar is lapped 21 inches. Determine the number
rebar. The amount of concrete materials needed is deter- of 20-foot-long bars that needs to be ordered for the
mined by the cubic yard. The amount of forms needed footing.
may be calculated by the lineal foot, square foot, or each.
7. How many cubic yards of concrete are required to con-
Forms need to be included on both sides of the concrete
struct a 145-foot-long by 4-foot-wide by 18-inch-thick
member. When calculating the square footage of forms,
continuous footing? Include 5% waste. Concrete must
the area should be based on the height of the forms
be ordered in quarter-yard increments.
rather than the height of the concrete member. Short
pieces of rebar are determined by the number of pieces, 8. Determine the square footage of forms needed for
and continuous bars are determined by the number of Problem 7.
shorter bars of rebar. 9. How many cubic yards of concrete are required to con-
struct 11 each 36-inch by 36-inch by 18-inch-thick
spread footings? Include 5% waste. Concrete must be
ordered in quarter-yard increments.
PROBLEMS 10. Determine the square footage of forms needed for
1. How many cubic yards of concrete are required to con- Problem 9.
struct a 100-foot-long by 30-inch-wide by 12-inch- 11. How many cubic yards of concrete are required to con-
thick continuous footing? Include 8% waste. Concrete struct 20 each 32-inch by 32-inch by 14-inch-thick
must be ordered in quarter-yard increments. spread footings? Include 5% waste. Concrete must be
2. Determine the length of forms needed for Problem 1. ordered in quarter-yard increments.
3. The footing in Problem 1 has four #4 continuous bars. 12. Determine the square footage of forms needed for
The rebar is lapped 18 inches. Determine the number Problem 11.
of 20-foot-long bars that needs to be ordered for the 13. How many cubic yards of concrete are required to con-
footing. struct a 250-foot-long by 8-foot-high by 8-inch-thick
4. How many cubic yards of concrete are required to con- concrete wall? Include 5% waste. Concrete must be or-
struct a 75-foot-long by 24-inch-wide by 10-inch-thick dered in quarter-yard increments.
continuous footing? Include 10% waste. Concrete must 14. Determine the square footage of forms needed for
be ordered in quarter-yard increments. Problem 13.
86 CHAPTER FIVE

15. How many cubic yards of concrete are required to con-


struct a 59-foot-long by 4-foot-high by 6-inch-thick
concrete wall? Include 5% waste. Concrete must be or-
dered in quarter-yard increments.
16. Determine the square footage of forms needed for
Problem 15.
17. How many cubic yards of concrete are required to con-
struct 7 each 16-inch by 16-inch by 10-foot-high con-
crete columns? Include 5% waste. Concrete must be or- FIGURE 5-25 Metal Deck Dimensions
dered in quarter-yard increments.
18. Determine the square footage of forms needed for
Problem 17. 26. The slab in Problem 23 is reinforced with wire mesh,
which is lapped 6 inches. Determine the number of 5-foot
19. How many cubic yards of concrete are required to
by 150-foot rolls of wire mesh needed to reinforce the slab.
construct 5 each 24-inch by 12-inch by 8-foot-high
concrete columns? Include 5% waste. Concrete must 27. How many cubic yards of concrete are required to con-
be ordered in quarter-yard increments. struct a 75-foot by 40-foot by 5-inch-thick concrete
slab? Include 10% waste. Concrete must be ordered in
20. Determine the square footage of forms needed for
quarter-yard increments.
Problem 19.
28. Determine the length of forms needed for Problem 27.
21. How many cubic yards of concrete are required to con-
29. The slab in Problem 27 is reinforced with #4 rebar at 24
struct 14 each 22-inch-diameter, 12-foot-high concrete
inches on center. The rebar is lapped 12 inches.
columns? Include 5% waste. Concrete must be ordered
Determine the number of 20-foot-long bars of #4 rebar
in quarter-yard increments.
needed to reinforce the slab.
22. How many cubic yards of concrete are required to con-
30. The slab in Problem 27 is reinforced with wire mesh,
struct 36 each 12-inch-diameter, 10-foot-high concrete
which is lapped 6 inches. Determine the number of 5-
columns? Include 5% waste. Concrete must be ordered
foot by 10-foot sheets of wire mesh needed to reinforce
in quarter-yard increments.
the slab.
23. How many cubic yards of concrete are required to con- 31. A 75-foot by 75-foot by 4-inch-thick slab is poured over
struct a 100-foot by 50-foot by 4-inch-thick concrete the metal deck shown in Figure 5-25. The depth of the
slab? Include 8% waste. Concrete must be ordered in slab is measured from the top of the slab to the top of
quarter-yard increments. the metal deck. Determine the average thickness of the
24. Determine the length of forms needed for Problem 23. slab and the number of yards of concrete needed to
25. The slab in Problem 23 is reinforced with #4 rebar at 16 pour the slab. Include 12% waste.
inches on center. The rebar is lapped 18 inches. 32. How many cubic yards of concrete are needed to con-
Determine the number of 20-foot-long bars of #4 rebar struct the continuous footing shown in Figures 5-26
needed to reinforce the slab. and 5-27? Include 10% waste.

FIGURE 5-26 Footing Plan


Concrete 87

37. Determine the rebar that needs to be ordered to con-


struct the spread footings shown in Figures 5-26 and 5-28.
Provide 3 inches of cover in the footing and 2 inches of
cover in the column. The ties are to be ordered with the
column rebar.
38. How many cubic yards of concrete are needed to con-
struct the wall shown in Figures 5-26 and 5-27? Add
10% waste.
39. How many square feet of forms are needed to construct
the wall shown in Figures 5-26 and 5-27?
40. Determine the rebar that needs to be ordered to con-
struct the wall shown in Figures 5-26 and 5-27? The
rebar is to be lapped 18 inches and 2 inches of cover is
required.
41. How many cubic yards of concrete are needed to con-
struct the columns shown in Figures 5-26 and 5-28?
Add 5% waste.
42. How many square feet of forms are needed to construct
the columns shown in Figures 5-26 and 5-28?
43. Determine the rebar that needs to be ordered to con-
struct the columns shown in Figures 5-26 and 5-28. Two
inches of cover is required on the ties.
44. Determine the concrete, rebar, and forms needed to
FIGURE 5-27 Wall Section pour the footings, foundation wall, and interior con-
crete slab for the Johnson Residence given in Appendix
F. Add 5% waste for the footings and foundation wall
33. How many lineal feet of forms are needed to construct and 10% waste for the floor slab. The continuous rebar
the continuous footing shown in Figures 5-26 and 5-27? is to be lapped 18 inches and will be ordered in 20-foot
34. Determine the rebar that needs to be ordered to con- lengths.
struct the continuous footing shown in Figures 5-26 45. Determine the concrete, rebar, and forms needed to
and 5-27. The rebar is to be lapped 18 inches. pour the footings and interior concrete slab for the West
35. How many cubic yards of concrete are needed to con- Street Video project given in Appendix F. Add 5% waste
struct the spread footings shown in Figures 5-26 and for the footings and 10% waste for the floor slab. The
5-28? Include 10% waste. continuous rebar is to be lapped 18 inches and will be
36. How many lineal feet of forms are needed to construct ordered in 20 foot lengths.
the spread footings shown in Figures 5-26 and 5-28? 46. Set up Excel Quick Tip 5-1 in Excel.

FIGURE 5-28 Column Detail


88 CHAPTER FIVE

47. Set up Excel Quick Tip 5-2 in Excel. 54. Modify Excel Quick Tip 5-3 to allow the height to be en-
48. Set up Excel Quick Tip 5-3 in Excel. tered in feet and inches.
49. Set up Excel Quick Tip 5-4 in Excel. 55. Modify Excel Quick Tip 5-6 to allow the length and
width to be entered in feet and inches.
50. Set up Excel Quick Tip 5-5 in Excel.
56. Modify Excel Quick Tip 5-7 to allow the length and
51. Set up Excel Quick Tip 5-6 in Excel. width to be entered in feet and inches.
52. Set up Excel Quick Tip 5-7 in Excel. 57. Modify Excel Quick Tip 5-8 to allow the length and
53. Set up Excel Quick Tip 5-8 in Excel. width to be entered in feet and inches.
CHAPTER SIX

MASONRY

In this chapter you will learn how to apply the principles in beam must be lapped. The combination of the lapping and
Chapter 4 to block and structural brick walls and brick veneer. the short lengths of rebar used to reinforce the wall vertically
This chapter includes sample spreadsheets that may be used in greatly increases the amount of rebar needed to complete the
the quantity takeoff. job. The estimator should read the specifications carefully and
fully understand the reinforcing requirements for the project
when preparing a bid.

F
Brick veneer is brick applied to the surface of a wood or
or this chapter we divide masonry into two cate-
block wall as an architectural finish material. The compo-
gories: (1) block and structural brick and (2) brick
nents of brick veneer include the brick, weather barrier
veneer.
(when installed over wood walls), lintels, and ties. Wood
Block and structural brick walls are characterized by
walls should be covered with a weather barrier, such as as-
being self-supporting and are often used as structural walls.
phalt-impregnated felt or Tyvek, prior to installation of
The components of block and structural brick walls include
brick veneer. The weather barrier may be installed by the
the block or brick, reinforcement, mortar, grout, imbeds, in-
framers or the mason. The quantity takeoff of weather barri-
sulation used to fill the ungrouted cells, and anchor bolts.
ers is covered in Chapter 9. Steel lintels must be used to sup-
Commonly the wall is reinforced with rebar running in the
port the brick wherever the brick is not supported by a con-
vertical and horizontal directions. The bars running in the
crete wall. The lintels consist of steel angles that are fastened
vertical direction are commonly spaced at 32 inches on cen-
to a structural wall or imbedded in the brick veneer. The
ter, and additional bars are often added around openings.
brick veneer must be attached to the surface of the wood or
This vertical rebar often consists of a single bar (often a #5
block wall. This is often done with masonry ties. The ma-
bar) placed in a column of cells that are grouted solid.
sonry ties are secured to wood walls with nails and are se-
Because the rebar is placed in the cells of the blocks or
cured to block and brick by placing the ties in the mortar
bricks, the rebar spacing must match the block or brick cell
joints. In addition, masonry ties should be included at the
spacing. When placing the blocks, they must be lifted over
corners to strengthen the corners.
the top of the rebar and then placed on the blocks in the
Let’s look at estimating block and structural brick walls.
wall, or the rebar must be stabbed down the cells after the
block is placed. This requires that the rebar be ordered in
short lengths. One way to do this is to reinforce the walls in
4-foot increments with rebar that is 4 feet long plus the
length of the lap.
Bars running in the horizontal direction are placed in a
bond beam. The bond beam consists of a block with a channel
in the top of the block, similar to the one shown in Figure 6-1.
The rebar is placed in the channel, and the cells of the blocks
are grouted solid. A typical bond beam consists of two #4 bars.
The bond beams are commonly spaced 4 feet on center.
Additional bond beams are located at the top of the walls and
over openings. Like rebar in concrete, the rebar in the bond FIGURE 6-1 Bond Beam Block

89
90 CHAPTER SIX

BLOCK AND STRUCTURAL required for a total length of 600 feet. The lap for the #4 rebar is
30 bar diameters, or 15 inches (30 ⫻ 0.5 in). The number of 20-
BRICK WALLS foot bars is calculated using Eq. (4-6) as follows:
The work package for block and structural brick walls in- 600 ft
cludes the block or brick, reinforcement, mortar, grout, in- Number ⫽ ⫽ 32 each
(20 ft ⫺ 1.25 ft)
sulation (such as perlite) used to fill the ungrouted block
cavities, and imbeds and anchor bolts used to connect the The number of vertical bars is calculated using Eq. (4-1) as follows:
building components to the wall. The block and brick walls (100 ft)(12 in/ft)
are treated as a sheet good. When calculating the number Number ⫽ ⫹ 1 ⫽ 39 each
32 in
of blocks, the estimator must separate standard blocks
from bond beam blocks and other specialty shapes. The The required lap on the vertical bar is 18.75 inches (30 ⫻ 0.625 in).
Each of these vertical bars will be ordered in the following incre-
vertical rebar is treated as a counted item; the horizontal
ments: 5 feet 7 inches long for the first 4 feet of the wall and 5 feet
rebar is treated as a linear good. The mortar and grout are
11 inches long for the remaining 6 feet of the wall. If we ordered
treated as quantity-from-quantity goods. The best way to 5-foot 7-inch-long bars for the second four feet of the wall and
determine the quantities of mortar and grout is based on 1-foot 11-inch-long bars for the last two feet of the wall, the last
past experience. Finally, anchor bolts and imbeds are bar will lap the second to last bar 19 of its 23-inch length. It is
treated as counted items. Steel imbeds and anchor bolts more economical and is just as easy to replace the last two bars
through structural steel are often provided by the struc- with a single bar. The wall will require 39 #5 rebar 5 feet 7 inches
tural steel supplier and need to be delivered before the long and 39 #5 rebar 5 feet 11 inches long. The area of the wall is
structural steel so they can be installed by the mason. calculated as follows:
Anchor bolts not through the structural steel also need to Area ⫽ (100 ft)(10 ft) ⫽ 1,000 ft2
be provided so they can be installed by the mason. The
quantity takeoff for a block or structural brick wall is The number of cubic yards of mortar needed is calculated as follows:
shown in the following example. 5 ft3 1 yd3
Volume ⫽ (1,000 ft2 )a ba b ⫽ 1.9 yd3
100 ft2 27 ft3
The number of cubic yards of grout needed is calculated as follows:
EXAMPLE 6-1
17 ft3 1 yd3
Determine the number of blocks, the rebar, mortar, and grout Volume ⫽ (1,000 ft2 )a ba b ⫽ 6.3 yd3
100 ft2 27 ft3
needed to construct a 100-foot-long by 10-foot-high block wall con-
structed of 7 5>8-inch-high by 7 5>8-inch-wide by 15 5>8-long The number of anchor bolts is calculated using Eq. (4-1) as follows:
blocks. The mortar joint is 3>8 inch thick. The wall is horizontally
(100 ft)(12 in/ft)
reinforced by bond beams at 4 feet on center containing two #4 bars. Number ⫽ ⫹ 1 ⫽ 39 each 䊏
The wall is vertically reinforced with #5 rebar at 32 inches on center. 32 in
All rebar is to be lapped 30 bar diameters. The rebar for the bond
beam is to be delivered to the site in 20-foot lengths, and the vertical
rebar is to be delivered cut to the required lengths. Allow 5 cubic feet The estimator must take openings into account when
of mortar and 17 cubic feet of grout per 100 square feet of block estimating block walls. Openings reduce the number of
wall. Anchor bolts are placed in the top of the wall at 32 inches on blocks needed and may require the use of special blocks
center. How many of the blocks need to be bond beam blocks? around the openings. Additional rebar is often placed
Solution: Using Eq. (4-14) to find the number of rows, we get the around the opening as shown in Figure 6-2. The blocks
following: above the opening are often supported by multiple bond
(10 ft)(12 in/ft) beams. To allow the bond beams to provide a finished sur-
NumberRows ⫽ ⫽ 15 rows face, a lintel block with a flat bottom, as shown in Figure 6-3,
(7 5>8 in ⫹ 3>8 in)
may be used for the bottom bond beam. Other specialty
Using Eq. (4-17) to get the number of columns, we get the following: blocks, such as the bullnose block shown in Figure 6-3, may
(100 ft)(12 in/ft) be used on the sides of the opening.
NumberColumns ⫽ ⫽ 75 columns When estimating block, the estimator must determine
(15 5>8 in ⫹ 3>8 in)
the additional reinforcing for the opening, the specialty
Using Eq. (4-18), we calculate the number of blocks as follows: blocks needed, and the quantity of standard block that can
Number ⫽ (15 rows)(75 columns) ⫽ 1,125 blocks be deducted for the opening. Block waste around the open-
ing is greater than for other areas of the wall; therefore, the
Three bond beams are required: one at 4 feet, one at 8 feet, and one
estimator cannot determine the number of standard blocks
at 10 feet. The number of bond beam blocks is calculated using
Eq. (4-18) as follows:
to be deducted by simply deducting the area of the opening
and the specialty blocks. Many estimators do not deduct any
Number ⫽ (3 rows)(75 columns) ⫽ 225 blocks blocks for small openings and deduct only half of the area
The project requires a total of 1,125 blocks of which 225 are bond for medium-sized openings. In addition to accounting for
beam blocks. For the bond beams, six 100-foot-long #4 bars are the opening, support for the bond beam needs to be provided
Masonry 91

FIGURE 6-2 Reinforcing around an Opening

until the grout in the beam has cured. The following exam-
ple looks at how to take openings into account when esti-
mating block and structural brick walls.

EXAMPLE 6-2
Determine the number of specialty blocks needed, additional
rebar required, and the number of standard blocks that can be de-
ducted when building a wall with the opening shown in Figure 6-
2. The wall is constructed of 7 5>8-inch-high by 7 5>8-inch-wide
by 15 5>8-inch-long blocks with a 3>8-inch mortar joint. The
blocks at the top and bottom of the opening are to be the lintel
block shown in Figure 6-3, with the blocks at the bottom placed
upside down to provide a smooth surface. Bullnose blocks are to
be provided at the sides of the opening. A 2 ⫻ 8 wood frame with
a center support will be provided to support the bond beam until
the grout has cured.

Solution: Lintel blocks are needed at the top and bottom of the
opening. The number of lintel blocks needed for the top of the
opening is calculated by dividing the width of the opening by the
length of the block including one mortar joint as follows:
40 in
Blocks ⫽ ⫽ 2.5 blocks
FIGURE 6-3 Specialty Blocks (15 5>8 in ⫹ 3>8 in)
92 CHAPTER SIX

The number of blocks will be rounded up to three blocks. Three lintel Six bond beam blocks are needed for each bar for a total of 18
blocks are needed at the top and three at the bottom for a total of six. blocks. Six of these blocks are replaced with lintel blocks; therefore,
Bullnose blocks are needed at both sides. The number of bull- 12 bond beam blocks are needed.
nose blocks needed for one of the sides of the opening is calculated The vertical rebar to the sides of the opening extends about
by dividing the height of the opening by the height of the block in- two blocks above and one block below the opening: therefore, six
cluding one mortar joint as follows: #6 bars 6 feet (16 in ⫹ 4 ft ⫹ 8 in) long are needed.
The number of standard blocks that can be deducted for the
(4 ft)(12 in/ft)
Blocks ⫽ ⫽ 6 blocks opening is determined by multiplying the number of full blocks
(7 5>8 in ⫹ 3>8 in) that can fit in the width of the opening and the number of full
Twelve bullnose blocks are needed. blocks that can fit in the height of the opening. In this case two full
The horizontal #6 rebar above and below the opening extends blocks can fit in the width of the opening and six full blocks can fit
about a block and a half (about 24 in) beyond the opening in both di- in the height of the opening. The number of standard blocks that
rections; therefore, three #6 bars 7 foot 4 inches (2 ft ⫹ 3 ft 4 in ⫹ 2 ft) can be deducted is 12 (6 ⫻ 2). The bond beam blocks, bullnose
long are needed. Bond beam blocks are needed for each of these blocks, and lintel blocks will replace standard blocks. A total of 42
bars. The number of bond beam blocks that are needed for one bar (12 ⫹ 12 ⫹ 12 ⫹ 6) standard blocks may be deducted from the es-
is calculated by dividing the length of the bar by the length of the timate for the opening.
block including one mortar joint as follows: Two 3-foot 4-inch-long 2 ⫻ 8s are needed for the top and bot-
tom of the opening. Three 3-foot 9-inch-long (4 ft ⫺ 1 1>2 in ⫺
88 in 1 1>2 in) 2 ⫻ 8s are needed for the sides and center of the opening.
Blocks ⫽ ⫽ 5.5 blocks
(15 5>8 in ⫹ 3>8 in) Order three 8-foot-long 2 ⫻ 8s. 䊏

EXCEL QUICK TIP 6-1


Block Wall
The numbers of standard blocks, bond beam blocks, bars block wall are set up in a spreadsheet by entering the data
of horizontal rebar, and bars of vertical rebar needed for a and formatting the cells as follows:

A B C
1 Wall Length 100 ft
2 - in
3 Wall Height 10 ft
4 - in
5 Block Length 15.625 in
6 Block Height 7.625 in
7 Joint Thickness 0.375 in
8 Bond Beam Spacing 48 in
9 Number of Horizontal Bars per Bond Beam 2 ea
10 Splice Length for Bond Beam Rebar 15.00 in
11 Order Length of Horizontal Rebar 20.00 ft
12 Vertical Rebar Spacing 32 in
13 Splice Length for Vertical Rebar 18.75 in
14 Mortar 5 cft/100 sft
15 Grout 17 cft/100 sft
16
17 Rows 15 ea
18 Columns 75 ea
19 Bond Beams 3 ea
20 Standard Blocks 900 ea
21 Bond Beam Blocks 225 ea
22 Horizontal Rebar 32 ea
23 Length of Vertical Rebar (1) 67 in
24 Vertical Rebar (1) 39 ea
25 Length of Vertical Rebar (2) 71 in
26 Vertical Rebar (2) 39 ea
27 Mortar 1.9 cyd
28 Grout 6.3 cyd
Masonry 93

In this spreadsheet, if the distance between the second- B25 =IF((B3*12+B4-(B19-1)*B8)>24,


to-last bond beam and the top of the wall is 24 inches or B3*12+B4-(B19-1)*B8-1,B3*
less, the last vertical bar runs from the third-to-last bond 12+B4-(B19-2)*B8-1)
beam to 1 inch below the top of the wall. The Length of
Vertical Rebar (1) and the Vertical Rebar (1) are used to cal- B26 =ROUNDUP((B1*12+B2)/B12,0)+1
culate the vertical rebar for the wall from the bottom of the B27 =(B1+B2/12)*(B3+B4/12)*B14/
wall to the second-to-last or third-to-last bond beam. The (100*27)
Length of Vertical Rebar (2) and the Vertical Rebar (2) are B28 =(B1+B2/12)*(B3+B4/12)*B15/(100*27)
used to calculate the last vertical rebar for the wall, which
runs from the second-to-last or third-to-last bond beam to
1 inch below the top of the wall. The following formulas The data for the block wall is entered in Cells B1 through
need to be entered into the associated cells: B15. Cell B20 determines the total number of blocks and
subtracts the number of bond beam blocks. Cell 23 deter-
Cell Formula mines the length of the vertical rebar for all of the wall except
the wall above the second-to-last or third-to-last bond beam
B17 =ROUNDUP((B3*12+B4)/(B6+B7),0) by adding the lap on the vertical rebar to the spacing be-
B18 =ROUNDUP((B1*12+B2)/(B5+B7),0) tween the bond beams. Cell C25 determines the length of the
B19 =ROUNDUP((B3*12+B4)/B8,0) last vertical rebar for the wall by determining the distance
B20 =B17*B18-B21 between the second-to-last or third-to-last bond beam and
the top of the wall and subtracting 1 inch. An IF function is
B21 =B18*B19
used in Cells B24 and B25 to determine if the last vertical bar
B22 =ROUNDUP((B1+B2/12)*B19*B9/ runs from the second-to-last or third-to-last bond beam
(B11-B10/12),0) based upon the distance between the second-to-last bond
B23 =ROUNDUP(B8+B13,0) beam and the top of the wall. The data shown in the forego-
B24 =IF((B3*12+B4-(B19-1)*B8)>24, ing figure is from Example 6-1 and is formatted using the
(B19-1)*B26,(B19-2)*B26) comma style, which replaces zeros with dashes.

BRICK VENEER Using Eq. (4-17) to get the number of columns, we get the
following:
The work package for brick veneer includes brick, weather
(50 ft)(12 in/ft)
barrier, lintels, mortar, and ties. The brick is treated as sheet NumberColumns ⫽ ⫽ 50 columns
goods, the ties are treated as a counted item, and the mortar (11 1>2 in ⫹ 1>2 in)
is treated as a quantity-from-quantity good. The best way to Using Eq. (4-18), we calculate the number of blocks needed as
determine the quantities of mortar is based on past experi- follows:
ence. The brick veneer must bear on a footing, foundation
wall, or a steel ledger created by bolting a steel angle iron to Number ⫽ (40 rows)(50 columns) ⫽ 2,000 blocks
the wall. Steel angle iron is used as lintels over window and The ties are laid out in rows and columns along the wall. A column
door openings and must be bolted to the wall or bear on the will occur every 3 feet along the wall. The columns will consist of
brick at the sides of the opening. A common bearing dis- seven rows of ties, which are located at 1 foot 6 inches, 3 feet, 4 feet
tance for steel lintels is 4 inches. The quantity takeoff for 6 inches, 6 feet, 7 feet 6 inches, 9 feet, and 9 feet 9 inches above the
brick walls is shown in the following example. base of the wall. A tie is not needed at the base of the wall because it
will bear on a footing, foundation, or steel lintel. Using Eq. (4-1) to
determine the number of vertical columns of ties, we get the fol-
EXAMPLE 6-3 lowing:
Determine the number of bricks, corrugated masonry ties, and 50 ft
mortar needed to face a wall 50 feet long by 10 feet high. The brick is Number ⫽ ⫹ 1 ⫽ 18 columns
3 ft
2 1>2 inches high by 3 1>2 inches wide by 11 1>2 inches long. Allow
for a 1>2-inch mortar joint. The spacing between the ties is to be The number of ties is 126 (7 rows ⫻ 18 columns). The area of the
18 inches measured vertically and 36 inches measured horizontally. wall is calculated as follows:
Historically, 10.2 cubic feet of mortar is required per 100 square feet
of brick. Area ⫽ (50 ft)(10 ft) ⫽ 500 ft2

Solution: Using Eq. (4-14) to find the number of rows of brick, we The number of cubic yards of mortar needed is calculated as
get the following: follows:

10.2 ft3 1 yd3


ba b ⫽ 1.9 yd3
(10 ft)(12 in/ft)
NumberRows ⫽ ⫽ 40 rows Volume ⫽ (500 ft2 )a 䊏
(2 1>2 in ⫹ 1>2 in) 100 ft2 27 ft3
˛
94 CHAPTER SIX

EXCEL QUICK TIP 6-2 Cell Formula


Brick Wall
B12 =ROUNDUP((B3*12+B4)/(B6+B7),0)
The numbers of bricks and brick ties needed for a brick
wall are set up in a spreadsheet by entering the data and B13 =ROUNDUP((B1*12+B2)/(B5+B7),0)
formatting the cells as follows: B14 =B12*B13
A B C B15 =ROUNDUP((B3*12+B4)/B8,0)
1 Wall Length 50 ft B16 =ROUNDUP((B1*12+B2)/B9,0)+1
2 - in
3 Wall Height 10 ft B17 =B15*B16
4 - in B18 =(B1+B2/12)*(B3+B4/12)*B10/
5 Brick Length 11.500 in (100*27)
6 Brick Height 2.500 in
7 Joint Thickness 0.500 in
8 Vertical Tie Spacing 12 in The data for the brick wall is entered in Cells B1 through
9 Horizontal Tie Spacing 24 in B10. The data shown in the foregoing figure is from
10 Mortar 10.2 cft/100 sft Example 6-6 and is formatted using the comma style,
11
12 Rows of Brick 40 ea
which replaces zeros with dashes.
13 Columns of Brick 50 ea
14 Bricks 2,000 ea
15 Rows of Ties 10 ea
16 Columns of Ties 26 ea EXAMPLE 6-4
17 Ties 260 ea A 4-foot wide opening is placed in a brick wall. The top of the
18 Mortar 1.9 cyd opening is supported by an L3 ⫻ 3 ⫻ 3>8 steel lintel. Determine the
minimum length of the lintel.
The following formulas need to be entered into the asso-
ciated cells: Solution: Allow 4 inches of bearing on both sides of the lintel. The
lintel needs to be 4 feet 8 inches (4 in ⫹ 4 ft ⫹ 4 in) long. 䊏

CONCLUSION beam has two each #4 bars. The rebar is to be lapped


18 inches.
Masonry consists of block, structural brick, and brick ve- 4. Determine the quantity and length of vertical rebar
neer. The work package for a block or structural brick wall needed for the wall in Problem 1 if the wall is vertically
includes the block or brick, reinforcement, mortar, grout, in- reinforced with #5 rebar at 32 inches on center. The
sulation, and imbeds and anchor bolts used to connect the rebar is to be lapped 18 inches.
building components to the wall. The block and brick are
5. Determine the quantity of mortar needed for the wall in
treated as a sheet good. The vertical rebar is treated as a
Problem 1 if 4.5 cubic feet of mortar is required per 100
counted item; the horizontal rebar is treated as a linear good.
square feet of block.
The mortar and grout are treated as quantity-from-quantity
goods. The work package for brick veneer includes brick, 6. Determine the quantity of grout needed for the wall
weather barrier, lintels, and ties. The brick is treated as a in Problem 1 if 18 cubic feet of grout is required per
sheet good, the ties are treated as a counted item, and the 100 square feet of block.
mortar is treated as a quantity-from-quantity good. 7. Determine the number of 7 5>8-inch-high by 5 5>8-inch-
wide by 15 5>8-inch-long concrete blocks required to
complete a wall 160 feet long by 8 feet high. Allow for a
3>8-inch mortar joint.
PROBLEMS
8. How many of the blocks in Problem 7 need to be bond
1. Determine the number of 7 5>8-inch-high by 5 5>8- beam blocks if the bond beams are 4 feet on center?
inch-wide by 15 5>8-inch-long concrete blocks required 9. Determine the number of 20-foot-long #4 bars needed
to complete a wall 80 feet long by 12 feet high. Allow for for the wall in Problem 7 if the wall is horizontally rein-
a 3>8-inch mortar joint. forced by bond beams at 4 feet on center. Each bond
2. How many of the blocks in Problem 1 need to be bond beam has two #4 bars. The rebar is to be lapped 18 inches.
beam blocks if the bond beams are 4 feet on center? 10. Determine the quantity and length of vertical rebar
3. Determine the number of 20-foot-long #4 bars needed needed for the wall in Problem 7 if the wall is vertically
for the wall in Problem 1 if the wall is horizontally re- reinforced with #5 rebar at 32 inches on center. The
inforced by bond beams at 4 feet on center. Each bond rebar is to be lapped 18 inches.
Masonry 95

FIGURE 6-4 Opening

11. Determine the quantity of mortar needed for the wall blocks with a 3>8-inch mortar joint. The blocks at the
in Problem 7 if 4.3 cubic feet of mortar is required per top and bottom of the openings are to be the lintel block
100 square feet of block. shown in Figure 6-3, with the blocks at the bottom
12. Determine the quantity of grout needed for the wall placed upside down to provide a smooth surface.
in Problem 7 if 16 cubic feet of grout is required per Bullnose blocks are to be provided at the sides of the
100 square feet of block. opening. A 2 ⫻ 8 wood frame will be provided to sup-
port the bond beam until the grout has cured.
13. Determine the number of specialty blocks needed, addi-
tional rebar required, and number of standard blocks 15. Determine the number of 2 1>2-inch-high by 3 1>2-
that can be deducted when building a wall with the inch-wide by 11 1>2-inch-long bricks that are required
opening shown in Figure 6-4. The wall is constructed of to face a wall 80 feet long by 4 feet high. Allow for a 1>2-
7 5>8-inch-high by 7 5>8-inch-wide by 15 5>8-inch-long inch mortar joint.
blocks with a 3>8-inch mortar joint. The blocks at the 16. Determine the number of corrugated masonry ties that
top and bottom of the opening are to be the lintel block are required to complete the wall in Problem 15. The
shown in Figure 6-3, with the blocks at the bottom spacing between the ties is to be 12 inches measured
placed upside down to provide a smooth surface. vertically and 24 inches measured horizontally.
Bullnose blocks are to be provided at the sides of the 17. Determine the quantity of mortar needed for the wall in
opening. A 2 ⫻ 8 wood frame with a center support will Problem 15 if 9.7 cubic feet of mortar is required per
be provided to support the bond beam until the grout 100 square feet of brick.
has cured. 18. Determine the number of 3 1>2-inch-high by 3 1>2-
14. Determine the number of specialty blocks needed, addi- inch-wide by 11 1>2-inch-long bricks that are required
tional rebar required, and number of standard blocks to face a wall 40 feet long by 8 feet high. Allow for a 1>2-
that can be deducted when building a wall with the inch mortar joint.
openings shown in Figure 6-5. The wall is constructed of 19. Determine the number of corrugated masonry ties that
7 5>8-inch-high by 7 5>8-inch-wide by 15 5>8-inch-long are required to complete the wall in Problem 18. The
96 CHAPTER SIX

FIGURE 6-5 Openings

spacing between the ties is to be 24 inches measured 22. Determine the block and rebar needed to complete the
vertically and 24 inches measured horizontally. West Street Video project given in Appendix F. The con-
20. Determine the quantity of mortar needed for the wall in tinuous rebar is to be lapped 18 inches and will be or-
Problem 18 if 7.5 cubic feet of mortar is required per dered in 20-foot lengths.
100 square feet of brick. 23. Set up Excel Quick Tip 6-1 in Excel.
21. Determine the brick veneer and ties needed to complete 24. Set up Excel Quick Tip 6-2 in Excel.
the Johnson Residence given in Appendix F.
CHAPTER SEVEN

METALS

In this chapter you will learn how to apply the principles in TYPES OF STRUCTURAL
Chapter 4 to steel beams and columns, joists, metal deck, STEEL
trusses, stairs and handrails, and miscellaneous steel. This
chapter includes sample spreadsheets that may be used in the Buildings can be constructed of different types of steel.
quantity takeoff. The most common type of steel is A36 carbon steel. Other
types of steel include A529 carbon steel; A440 high-
strength steel; A441 high-strength, low-alloy steel; A572

T
high-strength, low-alloy steel; A242 corrosion-resistant,
he steel for a building is fabricated and primed at a high-strength, low-alloy steel; and A588 corrosion-resistant,
steel fabrication shop and shipped to the site for high-strength, low-alloy steel. The estimator needs to
erection, where it is bolted or field welded together. make sure he or she knows what type of structural steel
Because it is fabricated off-site and assembled on-site, care- the engineer is specifying.
ful dimensioning and fabrication of each piece must occur
for the steel to fit together when it is erected at the jobsite.
Many structural engineers leave the actual design of the con- COMMON SHAPES FOR
nections of the steel up to the fabricator, allowing fabricators
STRUCTURAL STEEL
to use the connection type that is most economical for them.
When the design of the connectors is left up to the fabrica- There are a number of different shapes of structural steel
tor, the fabricator is required to submit shop drawings to the used in the construction of buildings. Common shapes are
structural engineer for approval. The engineer will check to shown in Figure 7-1.
make sure the connections are adequate and approve the de- The properties, dimensions, and weight per foot for
sign or require changes to the shop drawings. steel shapes can be found in the Manual of Steel Construction

FIGURE 7-1 Common Steel Shapes


97
98 CHAPTER SEVEN

published by the American Institute of Steel Construction. weight of pipe. This pipe has a wall thickness of
Commonly used shapes include the following: 0.237 inches, a weight of 10.79 pounds per foot, an
inside diameter of 4.026 inches, and an outside di-
Wide-Flange Beam: Wide-flange beams are used as
ameter of 4.500 inches.
columns, girders, and beams. A wide-flange beam is
designated by a “W” followed by its nominal depth Plate: Plate steel is used as base plates and connectors.
and weight per foot. For example, a W12 ⫻ 40 beam Plate steel is designated by the thickness. The weight
has a nominal depth of 12 inches and a weight of 40 of plate steel is about 490 pounds per cubic foot.
pounds per foot. Its actual depth is 11.94 inches.
American Standard Beams: American standard beams
are sometimes used as girders and beams. An EXAMPLE 7-1
American Standard beam is designated by an “S” fol- Determine the weight in pounds for a 50-foot-long W30 ⫻ 90.
lowed by its nominal depth and weight per foot. For
Solution: The W30 ⫻ 90 weighs 90 pounds per foot. The beam
example, an S18 ⫻ 70 beam has a nominal depth of weighs 4,500 pounds (50 ft ⫻ 90 lb/ft). 䊏
18 inches and a weight of 70 pounds per foot. The ac-
tual depth of this beam is also 18 inches.
American Standard Channels: American standard BEAMS, GIRDERS,
channels are used as beams and stair stringers. An
American Standard channel is designated by a “C”
AND COLUMNS
followed by its nominal depth and weight per foot. When estimating beams, girders, and columns, it is impor-
For example, a C12⫻30 channel has a nominal depth tant to estimate not only the number of structural steel
of 12 inches and a weight of 30 pounds per foot. The members needed, but also the weight of each member so the
actual depth of this channel is also 12 inches. crane can be properly sized. General contractors often esti-
Structural Tees: Structural tees are used in steel mate beams, girders, and columns based on the weight of the
trusses. Structural tees are created by cutting a beam steel members and add a percentage to the cost to allow for
along the length of the beam’s web to create a “T” connectors and bolts because the design of the connector is
shape. A structural tee cut from a wide-flange beam is often left up to the steel fabricator. Estimates by steel fabrica-
designated by “WT” followed by its nominal depth tors must include the connectors and bolts. Let’s look at esti-
and weight per foot. A structural tee cut from an mating the structural steel members.
American standard beam is designated by “ST” fol- The length of a structural steel member depends on
lowed by its nominal depth and weight per foot. For how it is connected to the surrounding steel members.
example, a WT4 ⫻ 29 structural tee has a nominal Common connections are shown in Figure 7-2, along with
depth of 4 inches and a weight of 29 pounds per foot. how the connection is drawn on the structural steel plan
Its actual depth is 4.375 inches. view for all but the splice connections. The first type of
connection is a splice and is used to connect two shorter
Angles: Angles are used as cross-bracing, lintels,
beams or columns into a longer beam or column. The next
ledgers, and connectors and in the construction of
type of connection is a beam-to-beam (or beam-to-
steel trusses. Angles are designated by an “L” followed
girder) connection, in which the end of one beam is joined
by the length of its longest leg, the length of the other
to the web of another beam. In this case the beam being
leg, and the thickness of the angle. For example, an
connected must run to the web of the beam that it is being
L5 ⫻ 3 ⫻ 1>2 would have one leg with a length of
connected to. The next three types of connections are con-
5 inches, one leg with a length of 3 inches, and a thick-
ness of 1>2 inch. The weight of this angle is 12.8 pounds
nections used to connect a beam to a column made from a
wide flange beam. In one type of connection the beam is
per foot.
connected to the web of the column. In this case the beam
Structural Tubing: Structural tubing is used as columns must run to the web of the column. In another type of
and cross-bracing and in the construction of steel connection the beam is connected to the flange of the col-
trusses. Structural tubing is designated by the length umn. In this case the beam must run to the flange of the
of its longest cross-sectional axis, the length of the column. In the third type of connection the beam rests on
other axis, and the thickness of the wall of the tubing. a plate attached to the top of the column. In this case the
For example, a 4 ⫻ 4 ⫻ 1>2 tube steel would have a beam runs over the top of the column to the edge of the
cross section of 4 inches by 4 inches and would have a building or the next column. Making a connection to a
wall thickness of 1>2 inch. Its weight is 21.63 pounds tubular-steel column is similar to connecting the beam to
per foot. the flange of the column, with the beam running to the ex-
Pipe: Pipe is used for columns. Pipe is designated by terior of the column or connecting the beam to a plate at-
“Pipe” followed by the nominal diameter of the pipe tached to the top of the column.
and the type of pipe. For example, Pipe 4 Std. has a The following example shows how the lengths of indi-
nominal diameter of 4 inches and is the standard vidual structural steel members are calculated.
Metals 99

FIGURE 7-2 Typical Connections

TABLE 7-1 Column Properties


EXAMPLE 7-2
Prepare a structural steel materials list for the roof-framing plan Flange
shown in Figure 7-3. The columns are 15 feet high. The flange
width for the W18 ⫻ 86 is 11 1>8 inches. The properties of the Column Size Width (in) Depth (in)
columns are given in Table 7-1. How many pounds of steel need to
be purchased for the roof? What is the weight of the heaviest struc- C1 W12 ⫻ 40 8.005 11.94
tural steel member needed to construct the roof? C2 W12 ⫻ 53 9.995 12.06
Solution: One C12 ⫻ 30 is needed to the right of the opening. The
channel will run from the flange of the W12 ⫻ 45 beams and has a
length of approximately 10 feet. The weight of the channel is 300 flange of column C2. The length of the beam is 30 feet less the
pounds (10 ft ⫻ 30 lb/ft). depth of column C1 less half the depth of column C2, or 28.5 feet
Four W12 ⫻ 45 beams are needed between the C1 and C2 (30 ft - 12 in - 12 in/2). The weight of one of these beams is 1,283
columns. These beams will run from the flange of column C1 to the pounds (28.5 ft ⫻ 45 lb/ft).

FIGURE 7-3 Steel Framing Plan


100 CHAPTER SEVEN

Six W12 ⫻ 45 beams are needed between the W18 ⫻ 86 girders The length of the girder is approximately 40 feet less the flange
and the W18 ⫻ 175 girder. These beams will run from the web of the width of the column, or 39 feet 2 inches (40 ft - 10 in). The weight
two girders. The web of the W8 ⫻ 86 will be set back 5 9>16 inches of one of these girders is 6,854 pounds (39.167 ft ⫻ 175 lb/ft).
(11.125 in/2) so that the flange of the W8 ⫻ 86 is flush with the Four 15-foot-long C1 columns are needed and will weigh 600
flange of the W12 ⫻ 40 column. The length of the beam is approx- pounds (15 ft ⫻ 40 lb/ft) each. Two 15-foot-long C2 columns are
imately 30 feet less 5 inches, or 29 feet 7 inches. The weight of one needed and will weigh 795 pounds (15 ft ⫻ 53 lb/ft) each. The total
of these beams is 1,331 pounds (29.583 ft ⫻ 45 lb/ft). weight of the steel is calculated as follows:
Two W18 ⫻ 86 girders are needed to go between the C1
columns. These girders will run from the webs of the two columns. Weight ⫽ 1(300 lb) ⫹ 4(1,283 lb) ⫹ 6(1,331 lb) ⫹ 2(3,383 lb)
The length of the girder is approximately 40 feet less the flange ⫹ 1(6,854 lb) ⫹ 4(600 lb) ⫹ 2(795 lb)
width of the column, or 39 feet 4 inches (40 ft - 8 in). The weight of
b ⫽ 15.514 tons
1 ton
one of these girders is 3,383 pounds (39.33 ft ⫻ 86 lb/ft). Weight ⫽ (31,028 lb)a ˛˛

2,000 lb
One W18 ⫻ 175 girder is needed to go between the C2
columns. This girder will run from the webs of the two columns. The heaviest member is the W18 ⫻ 175 girder at 6,854 pounds. 䊏

EXCEL QUICK TIP


Structural Steel
Calculating the weight of structural steel is set up in a spreadsheet by entering the data and formatting the cells as follows:

A B C D E F G
1 Length Weight
2 Item Quantity Feet Inches lb/ft Each Total
3 C12x30 1 10 - 30.0 300 300
4 W12x45 4 28 6 45.0 1,283 5,130
5 W12x45 6 29 7 45.0 1,331 7,988
6 W18x86 2 39 4 86.0 3,383 6,765
7 W18x175 1 39 2 175.0 6,854 6,854
8 W12x40 4 15 - 40.0 600 2,400
9 W12X53 2 15 - 53.0 795 1,590
10 Weight (lb) 31,027
11 Weight (tons) 15.51

The following formulas need to be entered into the as- The formula in Cell F3 will need to be copied to Cells F4
sociated cells: through F9, and the formula in Cell G3 will need to be
copied to Cells G4 through G9. The data for the steel is en-
Cell Formula tered in Cells A3 through E9. The data shown in the fore-
going figure is from Example 7-2 and is formatted using
F3 =(C3+D3/12)*E3
the comma style, which replaces zeros with dashes.
G3 =F3*B3
G10 =SUM(G3:G9)
G11 =G10/2000

When estimating steel connections, the estimator must JOISTS AND JOIST GIRDERS
account for the angles, plate steel, bolts, and welds that make
up most connectors. Estimating connectors is shown in the Floor-framing systems are often made up of joists and joist
following example. girders. The requirements for joists and joist girders are set
by the Steel Joist Institute. The most common joist in use is
the K-series joist, which is designated as shown in Figure 7-5.
EXAMPLE 7-3
The joist in Figure 7-5 is a 24-inch-deep K-series joist with a
section number of three. The larger the section number, the
Determine the items needed for the connection shown in Figure 7-4. stronger is the joist.
Solution: The connection will require 9 inches of L3 ⫻ 3 ⫻ 1>4 Joist girders are joists that are designed to support joists
angle, 11 inches of 1>4 fillet weld, and three 1>2-inch-diameter just as girders support beams. Joist girders are designated as
A325 bolts. 䊏 shown in Figure 7-6. The number of spaces is one more
Metals 101

FIGURE 7-4 Connection Details

When estimating joists and joist girders, the estimator


needs to determine the number of joist and joist girders,
their lengths, and their weights. The approximate weights for
joists and joist girders are given in the Catalogue of Standard
FIGURE 7-5 Joist Designation Specifications and Load Tables for Steel Joists and Joist Girders
published by the Steel Joist Institute. Estimating joists and
joist girders is shown in the following example.

EXAMPLE 7-4
Prepare a steel joist materials list for the roof-framing plan shown
in Figure 7-7. The approximate weights of the joists are given in
Table 7-2. What is the total number of pounds of steel joists that
FIGURE 7-6 Joist Girder Designation
need to be purchased for the roof? What is the weight of the heavi-
est steel joist needed to construct the roof?

than the number of joists that are supported by the joist


girder. The load on each panel point is the load applied by TABLE 7-2 Joist Weights
each joist in kips, where 1 kip is 1,000 pounds. If the joist
girder supports two joists at each point, one on each side of Joist Approximate Weight (lb/ft)
the joist girder, the load on each panel point is the com-
bined load applied by the pair of joists. The joist girder in 24K12 16.0
Figure 7-6 is a 24-inch-deep joist girder with five spaces 24G8N8K 47.0
(supporting four joists), and each panel point supports 8 kips, 36G8N16K 73.0
or 8,000 pounds.

FIGURE 7-7 Joist Framing Plan


102 CHAPTER SEVEN

Solution: Four 24K12 joists are needed to run between the columns.
The length of these joists is approximately 38 feet 6 inches (40 ft - 12 in The following formulas need to be entered into the
- 6 in). They weigh 616 pounds (38.5 ft ⫻ 16.0 lb/ft) each. The num- associated cells:
ber of joists in one bay is calculated using Eq. (4-3) as follows:
40 ft Cell Formula
Number ⫽ ⫺ 1 ⫽ 7 each
5 ft
B8 =B1/(B3-B5/12)
Fourteen (2 bays ⫻ 7 joists/bay) 24K12 joists are needed to run be-
tween the joist girders. The length of these joists is approximately B9 =ROUNDUP(B2/(B4-B6/12),0)
40 feet, and each joist weighs 640 pounds (40 ft ⫻ 16.0 lb/ft). Two B10 =ROUNDUP(B8*B9,0)
24G8N8K joist girders are needed. The length of each of these joist
girders is 38 feet (40 ft - 12 in - 12 in). These girders weigh 1,786
pounds (38 ft ⫻ 47.0 lb/ft) each. One 36G8N16K is needed. The
The data for the metal deck is entered in Cells B1
length of this joist girder is 38 feet (40 ft - 12 in - 12 in). This girder through B6. This spreadsheet assumes that the waste
weighs 2,774 pounds (38 ft ⫻ 73.0 lb/ft). The total weight of the from one column can be used on the next column and
steel is calculated as follows: that the lengths of the sheets are run parallel to the length
of the building. The data shown in the foregoing figure is
Weight ⫽ 4(616 lb) ⫹ 14(640 lb) ⫹ 2(1,786 lb) ⫹ 1(2,774 lb)
from Example 7-5 and is formatted using the comma
b ⫽ 8.885 tons
1 ton style, which replaces zeros with dashes.
⫽ (17,770 lb)a ˛

2,000 lb
The heaviest member is the 36G8N16K joist girder at 2,774 pounds.

STEEL TRUSSES
METAL DECK Like all other items constructed of steel, steel trusses are es-
Metal deck is often placed on top of the steel framing and steel timated by listing the steel components, including connec-
joists. The deck comes in sheets and is treated as a sheet good. tors, needed to construct the steel truss. Estimating the
Estimating metal deck is shown in the following example. components needed to fabricate a steel truss is shown in the
following example.

EXAMPLE 7-5
Determine the amount of metal deck that needs to be purchased to EXAMPLE 7-6
construct the floor shown in Figure 7-7. The deck comes in panels 4 Determine the items, including welds, needed to fabricate the steel
feet wide by 40 feet long. The panels must be lapped 6 inches. truss shown in Figure 7-8. The right side of the truss is the same as
the left side of the truss. What is the estimated weight of the truss if
Solution: Each panel will run the entire width of the building;
an L3 ⫻ 3 ⫻ 1>2 weighs 9.4 pounds per foot?
therefore, the number of rows is one. Determine the number of
columns of metal deck that are needed using Eq. (4-15) as follows: Solution: Two 13-foot 5-inch-long WT4 ⫻ 20 (a tee cut from a
80 ft wide-flange beam) are needed for the top cord and one 24-foot-long
NumberColumns ⫽ ⫽ 23 columns WT4 ⫻ 20 is needed for the bottom cord. Four 2-foot 9-inch-long
(4 ft ⫺ 0.5 ft)
L3 ⫻ 3 ⫻ 1>2 (one pair on each side of the truss), four 6-foot 2-inch-
The number of sheets of metal deck needed is 23 (1 rows ⫻ long L3 ⫻ 3 ⫻ 1>2 (one pair on each side of the truss), and two
23 columns). 䊏 5-foot 9-inch-long L3 ⫻ 3 ⫻ 1>2 (one pair at the center of the truss)
are needed for the truss. Two 20-inch-long V-welds (one on each
side of the truss) and one 3-inch-long V-weld are needed, for a total
EXCEL QUICK TIP 7-2 of 43 inches of V-weld. Each L3 ⫻ 3 ⫻ 1>2 will need 7 inches (2 in
Metal Deck Floor or Roof ⫹ 3 in ⫹ 2 in) of fillet weld on each end. There are 10 L3 ⫻ 3 ⫻
1>2s; therefore, 140 inches (10 ⫻ 7 in/end ⫻ 2 ends) of fillet weld are
The number of sheets of metal deck needed for a floor or needed. The estimated weight of the truss is found by multiplying
roof is set up in a spreadsheet by entering the data and the length of the steel members by their weights as follows:
formatting the cells as follows:
Weight ⫽ (2 ⫻ 13 ft 5 in ⫹ 24 ft)(40 lb/ft) ⫹ (4 ⫻ 2 ft 9 in
˛ ˛

A B C ⫹ 4 ⫻ 6 ft 2 in ⫹ 2 ⫻ 5 ft 9 in)(9.4 lb/ft)
1 Length of Building 40 ft
b ⫽ 1.24 tons
1 ton
2 Width of Building 80 ft Weight ⫽ (2,477 lb)a 䊏
2,000 lb
3 Length of Sheet 40 ft
4 Width of Sheet 4 ft
5 Lap at Ends of Sheet - in STAIRS AND HANDRAIL
6 Lap at Sides of Sheet 6 in
7 Like all other items constructed of steel, steel stairs and
8 Number of Rows 1.00 ea handrail are estimated by listing the steel components, includ-
9 Number of Columns 23 ea ing connectors, needed to construct the steel stairs and
10 Number of Sheets 23 ea handrail. Estimating the components needed to fabricate a
steel stairs and handrail is shown in the following example.
Metals 103

FIGURE 7-8 Steel Truss

1>2-inch plate are needed at the ends of the channel. Six stair pans,
EXAMPLE 7-7 each bent from 15-inch (1.5 in ⫹ 12 in ⫹ 1.5 in) by 4-foot pieces of
Determine the steel materials needed to fabricate the steel stairs 1>8-inch-thick steel plate, are needed. Seven 6-inch by 4-foot pieces
and handrail shown in Figure 7-9. The treads are 1.5 inches deep, of 1>8-inch-thick steel plate are needed for the risers. Two 42-inch-
and the stairs are 4 feet wide. The depth of the flange on the chan- long, two 11-inch-long, one 10-inch-long, and six 7 feet 5-inch-long
nel is 3 inches, and the thickness of the web is 5>16 inch. The 1 1>2-inch steel pipes and two 90° 1 1>2-inch elbows are needed for
handrail is on one side of the stairs only. the railing. 䊏

Solution: Two C12 ⫻ 20.7 are needed for the stair stringers
along with two 1>2-inch-diameter by 2-inch-long bolts and two MISCELLANEOUS STEEL
1>2-inch-diameter by 3-inch-long expansion bolts to fasten the
stringers. The half-inch plates will be 2 11>16 inches (3 in - 5>16 in) Miscellaneous items including imbeds, angles used to sup-
wide. Two 19-inch by 2 11>16-inch by 1>2-inch plate, two 6-inch by port the deck, timber brackets, and so forth are estimated in
2 11>16-inch by 1>2-inch plate, and two 10-inch by 2 11>16-inch by the same manner as steel trusses and stairs.

FIGURE 7-9 Steel Stairs


104 CHAPTER SEVEN

CONCLUSION TABLE 7-3 Column Properties for Problems 2 to 4


The steel for a building is fabricated and primed at a steel Flange
fabrication shop and shipped to the site for erection, where it
is bolted or field welded together. Common steel shapes used Column Size Width (in) Depth (in)
in the construction industry include the wide-flange beam,
American standard beams, American standard channels,
C1 W12 ⫻ 40 8.005 11.94
structural tees, angles, structural tubing, pipe, and plate. The C2 W12 ⫻ 50 8.080 12.19
estimator must determine the weight of the steel needed for
the construction of the building to price the steel and the
weight of each steel member to properly size the crane. This 6. Determine the number of pounds of steel that need to
is done by determining the weights of the individual compo- be purchased for the roof in Problem 5.
nents and adding them together. 7. What is the weight of the heaviest structural steel mem-
ber needed to construct the roof in Problem 5?
8. Prepare a steel joist materials list for the roof-framing
PROBLEMS plan shown in Figure 7-12. The approximate weights of
the joists are given in Table 7-5.
1. Determine the weight in pounds of the following struc-
tural steel members: 9. Determine the total weight of the joists needed to com-
plete the roof-framing plan shown in Problem 8.
a. A 20-foot-long W16 ⫻ 40
10. What is the weight of the heaviest joist needed to con-
b. A 15-foot-long S18 ⫻ 54.7
struct the roof in Problem 8?
c. A 25-foot-long W21 ⫻ 62
11. Prepare a steel joist materials list for the roof-framing
d. A 20-foot-long C7 ⫻ 9.8 plan shown in Figure 7-13. The approximate weights of
e. A 20-foot-long C15 ⫻ 50 the joists are given in Table 7-6.
2. Prepare a structural steel materials list for the roof-framing 12. Determine the total weight of the joists needed to com-
plan shown in Figure 7-10. The columns are 18 feet high. plete the roof-framing plan shown in Problem 11.
The flange width for the W16 ⫻ 77 is 10 1>4 inches. The
properties of the columns are given in Table 7-3.
3. Determine the number of pounds of steel that need to TABLE 7-4 Column Properties for Problems 5 to 7
be purchased for the roof in Problem 2.
4. What is the weight of the heaviest structural steel mem- Flange
ber needed to construct the roof in Problem 2?
Column Size Width (in) Depth (in)
5. Prepare a structural steel materials list for the roof-framing
plan shown in Figure 7-11. The columns are 20 feet high. C1 W8 ⫻ 28 6.535 8.06
The flange width for the W12 ⫻ 35 is 6 1>2 inches and C2 W12 ⫻ 40 8.005 11.94
the flange width for the W12 ⫻ 72 is 12 inches. The C3 W12 ⫻ 53 9.995 12.06
properties of the columns are given in Table 7-4.

FIGURE 7-10 Steel Framing Plan


Metals 105

FIGURE 7-11 Steel Framing Plan

TABLE 7-5 Joist Weights for Problems 8 to 10 TABLE 7-6 Joist Weights for Problems 11 to 13

Joist Approximate Weight (lb/ft) Joist Approximate Weight (lb/ft)

24K10 13.1 18K9 10.2


32G8N5K 30.0 24G6N6K 23.0
32G8N10K 57.0 24G6N12K 45.0

13. What is the weight of the heaviest joist needed to con-


struct the roof in Problem 11? 15. Determine the amount of metal deck that needs to be
14. Determine the amount of metal deck that needs to be purchased to construct the floor shown in Figure 7-13.
purchased to construct the floor shown in Figure 7-12. The deck comes in panels 4 feet wide by 40 feet long.
The deck comes in panels 4 feet wide by 40 feet long. The panels must be lapped 6 inches at the sides and 12
The panels must be lapped 6 inches. inches at the ends.

FIGURE 7-12 Steel Joist Plan


106 CHAPTER SEVEN

FIGURE 7-13 Steel Joist Plan

16. Determine the items, including welds, needed to fabri- L4 ⫻ 4 ⫻ 1>2 weighs 12.8 pounds per foot, and the
cate the steel truss shown in Figure 7-14. The right side plate weighs 20.4 pounds per square foot?
of the truss is the same as the left side of the truss. 20. Determine the structural steel, steel joist, and metal
17. What is the estimated weight of the truss in Figure 7-14 deck needed to complete the West Street Video project
if an L3 ⫻ 2 ⫻ 1>2 weighs 7.7 pounds per foot? given in Appendix F.
18. Determine the items, including connectors, needed to 21. Set up Excel Quick Tip 7-1 in Excel.
fabricate the steel truss shown in Figure 7-15. The right 22. Set up Excel Quick Tip 7-2 in Excel.
side of the truss is the same as the left side of the truss. 23. Modify Excel Quick Tip 7-2 to allow the length and
19. What is the estimated weight of the truss in Figure 7-15 width to be entered in feet and inches.
if an L3 ⫻ 3 ⫻ 1>2 weighs 9.4 pounds per foot, an

FIGURE 7-14 Steel Truss


Metals 107

FIGURE 7-15 Steel Truss


CHAPTER EIGHT

WOODS, PLASTICS,
AND COMPOSITES

In this chapter you will learn how to apply the principles in the concrete wall and the wood sill. This sealing material
Chapter 4 to wood floor systems (wood sills, columns, beams, is provided with the lumber package and installed by the
joists, joist headers, trimmer, blocking, joist hangers, tongue framer. Wood sills are bid as linear components. The
and groove sheeting), walls (top and bottom plates, studs, quantity takeoff for wood sill is shown in the following
headers, blocking, sheathing), roof-framing (trusses, rafters, example.
fascia, soffit), wood trim, and cabinetry. This chapter includes
sample spreadsheets that may be used in the quantity takeoff. It
also includes example takeoffs from the residential garage EXAMPLE 8-1
drawings given in Appendix F.
The perimeter of the floor system in Figure 8-2 sits on a redwood
sill. Determine the number of 16-foot-long pieces of redwood that
are needed to complete the floor system.

R ough carpentry consists of framing the floors, walls,


and roof of the structure. A typical wood structure
is shown in Figure 8-1. Finish carpentry consists of
installing finish material including wood trim, shelving, and
handrails. Cabinetry includes the installation of cabinets and
Solution: The perimeter of the building is 132 feet (40 ft ⫹ 26 ft ⫹
40 ft ⫹ 26 ft). The number of pieces is calculated using Eq. (4-7) as
follows:

Number ⫽
132 ft
⫽ 9 each 䊏
16 ft
countertops. We begin by looking at framing the building’s
floor system.
Large quantities of sill plate are often purchased in
random lengths. When lumber is purchased in random
lengths the pricing is quoted in board feet. The quantity
FLOOR SYSTEMS takeoff of random-length wood sill is shown in the follow-
The floor system consists of joists covered with OSB or ply- ing example.
wood sheathing and bears on sills, walls, or girders sup-
ported by posts. Sometimes 2⫻ or 3⫻ material is substituted
for the sheathing as is the case with wood decks. Let’s look at EXAMPLE 8-2
each of the components of the floor system beginning with How many board feet of sill are needed to complete the floor
the sill. system in Figure 8-2 if the sill is constructed of random lengths of
2 ⫻ 4 redwood?
Sills Solution: From Example 8-1 the perimeter of the building is 132
feet. The number of board feet (bft) is calculated as follows:
When the floor system is supported by concrete walls, the
floor system must be placed on a naturally durable wood (Depth) (Width)(Length)
Board Feet ⫽
(for example, redwood) or pressure-treated wood sill. A (12 in/ft)
sealing material, such as Sill Seal, is often required to be (2 in)(4 in)(132 ft)
⫽ ⫽ 88 bft 䊏
placed below the sill to prevent air infiltration between (12 in/ft)

108
Woods, Plastics, and Composites 109

FIGURE 8-1 Typical Wood Structure

FIGURE 8-2 Floor-Framing Plan


110 CHAPTER EIGHT

EXCEL QUICK TIP 8-1


Board Foot Worksheet
The conversion of lineal feet to board feet is set up in a
spreadsheet by entering the data and formatting the cells
as follows:
A B C
1 Board Depth 2 in
2 Board Width 4 in
3 Board Length 132 ft
4
5 Board Feet 88.0 bft
FIGURE 8-3 Web Stiffener
The following formula needs to be entered into
Cell B5: Engineer I-joists are gaining in popularity because
=B1*B2*B3/12 they can produce a superior-quality floor system at prices
similar to that of standard wood joists. Engineered I-joists
The data for lumber is entered in Cells B1 through B3. The are available in lengths of up to 60 feet, which allows a sin-
data shown in the foregoing figure is from Example 8-2. gle joist to span across many of the bearing walls or girders
in a building, which decreases the bending of the floor
joist. Engineered I-joists may require blocking and web
Posts and Girders stiffeners (a piece of wood on either side of the flange in
the space between the webs). A web stiffener is shown in
Posts and girders may be used to support a floor system and
Figure 8-3. Short pieces of I-joists are often used as block-
open up the space below. The girder may consist of a glue-
ing. The manufacturer’s data should be consulted to deter-
laminated beam (GLB) or two or three 2⫻s nailed together.
mine the need for blocking and web stiffeners.
The posts should be secured to footing using a framing an-
Joist headers are required at the ends of the joists. Joist
chor, such as a Simpson post base (PB), and should be se-
headers around the perimeter of the floor are often referred
cured to the girder using a framing anchor, such as a
to as rim joist or rim board. When using 2⫻ lumber the
Simpson post cap (BC). Posts and framing hardware are bid
header is constructed of 2⫻ lumber with the same depth as
as counted items and girders are bid as linear components or
the joists. Manufacturers of engineered I-joists produce en-
as counted items. The quantity takeoff for posts and girders
gineered wood products for use as joist headers.
is shown in the following example.
Joist headers and trimmers are used when openings
are required in the floor system. The framing for a typical
opening is shown in Figure 8-4. The joist header is con-
EXAMPLE 8-3 structed of the same material used for the joists or the joist
Determine the materials needed to complete the posts and girder header at the edge of the building. The joist header and
supporting the floor joists in Figure 8-2. The posts are connected to joist trimmers are required to be doubled if the opening is
footings using a Simpson PB66 post base and are connected to the greater than 4 feet wide. When the opening is greater than
girder using a Simpson BC6 post cap. The distance between the top 6 feet wide the joist header is to be connected to the joist
of the footing and the bottom of the girder is 7 feet. The posts are trimmers with framing anchors.1 The location of the joist
equally spaced along the girder.
trimmers may or may not line up with the standard joist
Solution: The 6 ⫻ 6 posts come in 8-foot lengths. Two 8-foot- spacing. If the trimmer joist does not line up with the stan-
long 6 ⫻ 6 posts, two Simpson PB66 post bases, and two dard joist spacing, as is the case in Figure 8-4, more joists
Simpson BC6 post caps are needed. The posts are 13 feet 4 inches will be needed than if the trimmer joist lined up with the
(40 ft/3) on center; therefore, 14-foot-long 2 ⫻ 12s will be used standard joist spacing.
for the girder. Nine (3 spaces ⫻ 3) 14-foot-long 2 ⫻ 12s are The joists are doubled under bearing walls running
needed for the girder. 䊏 parallel to the joist including perimeter walls and may be
doubled under nonbearing walls running parallel to the
joists. The estimator must take into account the doubled
Floor Joists joist when performing the takeoff. Joists are taken off as a
Floors are constructed of floor joists that span from bearing counted item.
wall or girder to bearing wall or girder. The floor joists may The joists must be blocked at specified intervals to
be constructed of 2 ⫻ 6, 2 ⫻ 8, 2 ⫻ 10, or 2 ⫻ 12 lumber or of prevent them from rolling onto their sides. The joists
engineered wood I-joists. must also be blocked when the joists pass over walls to
Woods, Plastics, and Composites 111

FIGURE 8-4 Framing for Opening in Floor

prevent the spread of fire. The blocking is usually con- under the wall on the left of the drawing). Two additional joists
structed of the same material used for the joists or joist are needed for the double joist under the wall on the right be-
headers. Joist blocking is taken off as a linear component. cause the wall is not located above the joists used to meet the
The takeoff of the joists for a floor system is shown in the spacing requirements. This brings the total number of joists to
67 (58 ⫹ 7 ⫹ 2). Fourteen-foot-long 2 ⫻ 12s will be ordered for
following example.
these joists.
The number of joists needed on each side of the building for
the joist header is calculated using Eq. (4-7) as follows:
EXAMPLE 8-4
40 ft
Determine the materials needed to construct the joists for the floor Number ⫽ ⫽3
14 ft
system shown in Figure 8-2. The joists are blocked over the girder
and at the midpoint, between the girder and the exterior wall on Three additional 14-foot-long joists are needed as joist headers on
joists over 8 feet long. The joist headers at the opening are attached each side of the building. Four 8-foot-long joists are needed as joist
to the trimmer joists with Simpson U210-2 hangers. headers around the opening.
The joists above the opening are 3 feet 6 inches long (13 ft
Solution: Beginning with the 13-foot-long joists, the number of ⫺ 3 ft ⫺ 6 ft 6 in). The number of joists is calculated using Eq. (4-3)
joists needed to meet the spacing of 16 inches on center for the top as follows:
half of the drawing is calculated using Eq. (4-1) as follows:
(8 ft)(12 in/ft)
(40 ft)(12 in/ft) Number ⫽ ⫽6
Number ⫽ ⫹ 1 ⫽ 31 16 in
16 in
Two 3-foot 6-inch-long joists can be cut from one 8-foot-long 2 ⫻ 12;
The number of joists needed to meet the spacing of 16 inches on therefore, three more 8-foot-long 2 ⫻ 12s are needed. Six 3-foot-long
center for the bottom half of the drawing located to the left of the joists are needed below the opening. Three of these joists can be cut
opening is calculated using Eq. (4-1) as follows: from a 10-foot-long 2 ⫻ 12; therefore, two more 10-foot-long 2 ⫻ 12s
are needed.
(17 ft)(12 in/ft)
Number ⫽ ⫹ 1 ⫽ 14 Three rows of blocking are needed. The top row is located
16 in in the top half of the drawing and is 40 feet long. The second
row is located over the girder and is 40 feet long. The third row
The number of joists needed to meet the spacing of 16 inches on
is located in the bottom half of the drawing and is not needed in
center for the bottom half of the drawing located to the right of the
the opening. The length of blocking needed for this row is
opening is calculated using Eq. (4-1) as follows:
32 feet (17 ft ⫹ 15 ft). A total of 112 feet (40 ft ⫹ 40 ft ⫹ 32 ft)
(15 ft)(12 in/ft) of blocking is needed. Order twelve 10-foot-long 2 ⫻ 12s for the
Number ⫽ ⫹ 1 ⫽ 13 blocking.
16 in
Four Simpson U210-2 hangers are needed to attach the joist
A total of 58 (31 ⫹ 14 ⫹ 13) joists are needed to meet the spac- headers to the trimmer joists.
ing requirements. Seven additional joists are needed to double Order seventy-three (67 ⫹2 ⫻ 3) 14-foot-long 2 ⫻ 12s, four-
up joists already included in this number (4 for the ends of the teen 10-foot-long 2 ⫻ 12s, and seven 8-foot-long 2 ⫻ 12s for the
building, 1 at each side of the stairs, and 1 for the double joist floor and four Simpson U210-2 hangers. 䊏
112 CHAPTER EIGHT

EXCEL QUICK TIP 8-2


Joists
The number of joists needed for a floor is set up in a spreadsheet by entering the data and formatting the cells as follows:

A B C D E F G
1 Area 1 Area 2 Area 3
2 Building Length 40 ft 17 ft 15 ft
3 Joist Spacing 16 in 16 in 16 in
4 End Condition 1 1 1
5
6 Joists 31 ea 14 ea 13 ea
7
8 Additional Joists 9
9
10 Total # of Joists 67

The following formulas need to be entered into the as- in Cells B2 through B4, D2 through D4, and F2 through
sociated cells: F4. If a joist is required at both ends of the floor area, a
“1” is entered as the end condition. If a joist is required at
Cell Formula only one end of the floor area, a “0” is entered as the end
condition. If joists are not required at either ends of the
B6 =ROUNDUP(B2*12/B3,0)+B4 floor area, a “⫺1” is entered as the end condition. The
B10 =B6+D6+F6+B8 number of additional joists needed for joist trimmers,
doubled joists, and joists that do not fall on the standard
After entering the formulas, Cell B6 must be copied to spacing are entered in Cell B8. The data shown in the
Cells D6 and F6. This spreadsheet is designed for three foregoing figure is from Example 8-4 for the 14-foot-
separate building areas. The data for the floor is entered long joists.

Floor Sheathing Because the sheathing is tongue and groove, the leftover half-sheet
cannot be used; therefore, seven rows are needed. The number of
Commonly 23>32-inch T&G (tongue and groove) OSB (ori- columns is calculated using Eq. (4-16) as follows:
ented-strand board) or plywood is used as floor sheathing.
40 ft
The use of T&G sheathing provides for a stiffer flooring sys- NumberColumns ⫽ ⫽ 5 columns
8 ft
tem with less squeaking than sheathing without tongues and
grooves. When using T&G sheathing, the estimator must The number of sheets is calculated using Eq. (4-18) as follows:
make sure that the sheathing can be cut in such a manner that Number ⫽ (7 rows)(5 columns) ⫽ 35 sheets 䊏
there is a tongue and a groove for each joint that runs per-
pendicular to the joists. This often limits the use of waste ma-
terial even if it is of sufficient size, because it lacks the proper
tongue or groove. Sheathing should be placed with the
longest direction perpendicular to the joists, and the sheets
should span at least three joists. Floor sheathing is commonly EXCEL QUICK TIP 8-3
glued and nailed with a slip-resistant nail, such as a ring- Floor Sheathing
shank nail, to minimize squeaking. The takeoff of the sheath- The number of sheets of T&G floor sheathing for a rec-
ing for a floor system is shown in the following example. tangular floor is set up in a spreadsheet by entering the
data and formatting the cells as follows:
EXAMPLE 8-5 A B C
Determine the number of 4-foot by 8-foot sheets of 23>32-inch 1 Building Length 40 ft
T&G OSB sheathing needed to construct the floor system shown in 2 Building Width 26 ft
Figure 8-2. 3
4 No. of Rows 7.00 ea
Solution: The number of rows is calculated using Eq. (4-13) as
5 No. of Columns 5.00 ea
follows:
6
26 ft 7 Sheathing 35.00 ea
NumberRows ⫽ ⫽ 6.5
4 ft
Woods, Plastics, and Composites 113

The following formulas need to be entered into the EXCEL QUICK TIP 8-4
associated cells: Decking
The number of board feet needed for a deck is set up in a
Cell Formula
spreadsheet by entering the data and formatting the cells
B4 =ROUNDUP(B2/4,0) as follows:
B5 =CEILING(B1/8,1/3) A B C
B7 =ROUNDUP(B4*B5,0) 1 Deck Length 20 ft
2 Deck Width 20 ft
The data for the floor is entered in Cells B1 and B2. The 3 Nominal Width 6 in
4 Actual Width 5.50 in
spreadsheet assumes the sheets are 4 feet by 8 feet and the
5 Nominal Thickness 3 in
long direction of the sheet is run parallel to the length of
6 Spacing between Boards - in
the building. The number of rows is rounded up to the 7
next whole sheet, and the number of columns is rounded 8 Lineal Feet 880 ft
up to the next one-third of a sheet using the CEILING 9 Board Feet 1,320 bft
function, which equals the distance covered by three joists
when the joists are spaced at 16 inches on center. The data The following formulas need to be entered into the
shown in the foregoing figure is from Example 8-5. associated cells:

Cell Formula

Wood Decks B8 =ROUNDUP(B2*12/(B4+B6),0)*B1


B9 =B3*B5*B8/12
In heavy timber construction and on outdoor decks, 2⫻
and 3⫻ lumber laid flat is often used as a decking material in
lieu of OSB or plywood. The lumber may be laid with a space The data for deck and lumber is entered in Cells B1
between the boards or laid right next to each other. Wood through B6. The data shown in the foregoing figure is
decks are treated as a sheet good. When purchasing random from Example 8-6 and is formatted using the comma
lengths of decking, the length of the decking is assumed to style, which replaces zeros with dashes.
run the entire length of the deck. The takeoff of wood deck-
ing is shown in the following example.
WALLS
EXAMPLE 8-6 Walls consist of top and bottom plates, studs, headers, hold-
downs, blocking, and sheathing. Let’s look at each of these
How many board feet of 3 ⫻ 6 redwood decking are needed to con-
components.
struct a 20-foot by 20-foot deck? The boards are to be placed with-
out any space between them.
Top and Bottom Plates
Solution: The width of a 3 ⫻ 6 is 5 1>2 inches; therefore, the
boards are spaced 5 1>2 inches apart. Begin by finding the number When the wall is placed on concrete or masonry, the bottom
of lineal feet of 3 ⫻ 6 redwood needed for the deck, using the row plate must be a naturally durable wood (for example, red-
and column method. Let the rows be made up of one 20-foot-long wood) or pressure-treated wood. A sealing material, such as
board. The number of columns is calculated using Eq. (4-16) as Sill Seal, is often placed below the bottom plate of exterior
follows: walls when the walls bear on concrete or masonry. When the
(20 ft)(12 in/ft) wall is placed on a wood floor, the bottom plate is of the
NumberColumns ⫽ ⫽ 44 columns same lumber as the studs. For the bottom plate, the door
5 1>2 in
openings are not deducted from the length because the bot-
The number of lineal feet of 3 ⫻ 6 boards is calculated by multiply-
tom plate is run through the opening and is cut out after the
ing the number of columns by their length as follows:
framing is complete. This helps ensure that the walls are
Lineal Feet ⫽ (20 ft/column)(44 columns) ⫽ 880 ft framed straight.
The number of board feet is calculated as follows: Bearing walls require two top plates. Nonbearing walls
may be built with one top plate, but they are often built
(Thickness)(Width)(Lineal Feet) with two top plates to allow the same length of studs to be
Board Feet ⫽
12 in/ft used for both the bearing and nonbearing walls. Top and
(3 in)(6 in)(880 ft) bottom plates are taken off in the same way that sills are
⫽ ⫽ 1,320 bft 䊏
12 in/ft taken off.
114 CHAPTER EIGHT

FIGURE 8-5 Wall Layout

end conditions into account. When the wall forms a corner, the
EXAMPLE 8-7
end condition will be accounted for with the corner.
How many feet of treated plate and untreated plate are needed to Two extra studs are needed at corners. One of these
construct the walls shown in Figure 8-5? The walls are constructed studs provides for the end condition, and the other stud pro-
of 2 ⫻ 4s and the exterior walls are sheathed with 7>16-inch OSB. vides backing for the interior finish. Two methods of fram-
The wall bears on a concrete floor. ing a corner are shown in Figure 8-6. The difference in these
Solution: The thickness of the exterior walls is 4 inches, and the two corners is how the backing stud is placed. In this book,
thickness of the interior walls is 3 1>2 inches. The total length of the two additional studs are added for each corner.
walls is calculated as follows:
Length ⫽ 2(22 ft) ⫹ 3(24 ft 4 in) ⫹ 2(11 ft 5 in) ⫹ 2 ft 1 in
⫽ 141 ft 11 inches
Because the walls bear on a concrete floor, the bottom plate
needs to be constructed of treated plate; therefore, 142 feet of
treated plate are needed. The top requires a double top plate of
untreated lumber; therefore, 284 feet (2 ⫻ 142 ft) of untreated
plate are needed. 䊏

Studs
Precut studs are available for 8- and 9-foot ceilings. Precut
studs for an 8-foot ceiling are 92 5>8 inches long, and when
used with a single bottom plate and double top plate, they
provide a rough ceiling height of 97 1>8 inches. The extra
1 1>8 inches allows for floor and ceiling finishes. Precut
studs for a 9-foot ceiling are 104 5>8 inches long, and when
used with a single bottom plate and double top plate, they
provide a rough ceiling height of 109 1>8 inches.
The number of studs in a wall is determined by the stud
spacing and the number of ends, corners, intersections,
openings, and hold-downs. The number of studs needed to
meet the spacing requirements is determined by Eq. (4-2).
When a wall ends without forming a corner, an additional
stud is needed, as was shown in Chapter 4. This is to take the FIGURE 8-6 Framing of Corners
Woods, Plastics, and Composites 115

wider stud (a 2 ⫻ 6 for a 2 ⫻ 4 wall or a 2 ⫻ 8 for a 2 ⫻ 6 wall)


be provided for each intersection. In this book, two addi-
tional studs are added for each intersection.
Each opening requires additional studs. A typical door
opening is shown in Figure 8-8. Narrow openings require a
jack stud and a king stud on both sides of the opening. The
jack studs are used to support the header. Wider openings
may need two or three jack studs on each side of the open-
ing to support the header, depending on the load sup-
ported by the header and the width of the opening. The
number of jack studs should be determined by the design
professional or the building code when it has not been
specified by the design professional. For the opening
shown in Figure 8-8, two additional studs are needed be-
cause two of the studs needed to meet the spacing require-
ments have been deleted and two king studs and two jack
studs have been added. The actual number of additional
studs will vary based on the location of the door. If the
opening in Figure 8-8 were moved a few inches to the right,
the right king stud would meet the stud spacing require-
FIGURE 8-7 Framing for Wall Intersections ment, and only one additional stud would be needed. For
wider openings a greater number of studs will be replaced
by the openings; however, this is often offset by the need
When walls intersect, backing is needed for the interior for a greater number of jack studs. In this book, two addi-
finish and to secure the intersecting walls together. Two tional studs are added for each doorway.
methods of framing an intersection are shown in Figure 8-7. Window openings are similar to door openings except
The top method requires two additional studs to be pro- that there is framing below the opening that reduces the
vided for each intersection. The bottom method requires a deletion of the regularly spaced studs. The framing of a win-

FIGURE 8-8 Framing of a Door Opening


116 CHAPTER EIGHT

FIGURE 8-9 Framing of a Window Opening

dow opening is shown in Figure 8-9. Cripple studs and a sill are
used to frame the wall below the opening. A cripple stud is lo-
cated at each end of the sill, and cripple studs are placed under
the sill to maintain the regular spacing of the studs. The num-
ber of additional studs that are needed will change depending
on the location of the opening, the height of the opening, and
the width of the opening. If the opening in Figure 8-9 were
moved a few inches to the right, the right king stud would meet
the stud spacing requirement and reduce the number of addi-
tional studs by one. Less material is required for the cripple FIGURE 8-10 Framing of Corners with Hold-downs
studs in taller openings than in shorter openings. For example,
if the top of the sill in Figure 8-9 was below 49 inches, two crip-
ple studs could be cut from one 92 5>8-inch stud and two studs additional stud is needed to form a solid blocked corner as
would be required for the cripple studs. If the top of the sill shown in Figure 8-10. When a hold-down occurs at other
were above 49 inches, four studs would be required for the places, up to three additional studs are needed. In this book
cripple studs. Wider openings may need additional jack studs. no studs are added when a hold-down occurs at the edge of a
For an opening up to 8 feet wide with single jack studs, up to door or window opening, one additional stud is added for
seven additional studs may be needed to frame the opening. If each hold-down located at a corner, and three additional
the opening required double jack studs, up to nine additional studs are added for all other hold-downs.
studs may be needed to frame the opening. In this book six ad- The quantity takeoff for studs is shown in the following
ditional studs are added for each window opening that requires example.
only two jack studs; eight additional studs are added for each
window opening that requires a pair of jack studs on each side.
Posts or doubled or tripled studs are needed wherever a EXAMPLE 8-8
hold-down occurs. If the hold-down occurs at the edge of a How many studs are needed to frame the wall in Figure 8-5? The
door or window, the hold-down may be attached to the jack stud spacing is 16 inches on center. Allow for one additional stud
and king studs. When a hold-down occurs at a corner, an for each wall that does not have a corner; two additional studs for
Woods, Plastics, and Composites 117

each corner, intersection, or doorway; six additional studs for each Headers in a 2 ⫻ 4 wall can be made from two pieces of 2⫻
window less than 6 feet in width; eight additional studs for each material and a 1>2-inch plywood or 7>16-inch OSB spacer.
window 6 feet or more in width; and one additional stud for each Headers in a 2 ⫻ 6 wall can be made from three pieces of 2⫻
hold-down located at a corner. Do not add additional studs for
material and two 1>2-inch or 7>16-inch spacers. The headers
hold-downs located at the edge of windows or doors.
must extend over all of the jack studs, requiring the header
Solution: From Example 8-7 the length of the wall is 142 feet. The to be 3 inches wider than the opening for openings with sin-
number of studs needed for the standard spacing is calculated using gle jack studs and 6 inches wider than the opening for open-
Eq. (4-2) as follows: ings with double jack studs. Openings for doors with jambs
(142 ft)(12 in/ft) are typically framed 2 inches wider than the door size to
Number ⫽ ⫽ 107 each allow for the doorjamb and shimming. A 36-inch-wide door
16 in
with single jack studs would require a 41-inch-long header
All four interior walls lack corners at both ends; therefore, four ad- (36 in ⫹ 3 in ⫹ 2 in). Window openings are typically framed
ditional studs are needed for these walls. There are 4 corners, 8 in-
1>2 to 1 inch wider than the opening to allow for placement
tersections, and 5 doorways that will require 2 additional studs
of the window.
each, for a total of 34 additional studs. There are 2 windows that
will require 6 additional studs each and 1 window that will require
8 additional studs for a total of 20 additional studs. There are 2
EXAMPLE 8-9
hold-downs located at corners that will require an additional stud
per hold-down for 2 additional studs. The total number of studs is Prepare a materials list for the headers required to complete the
167 (107 ⫹ 4 ⫹ 34 ⫹ 20 ⫹ 2). 䊏 walls in Figure 8-5. All headers are made from 2 ⫻ 12s, and the wall
is made from 2 ⫻ 4s. The doors are 32 inches wide. Openings 6 feet
and wider require double jack studs.
EXCEL QUICK TIP 8-5 Solution: Each header will consist of two 2 ⫻ 12s with a 7>16-inch
Studs OSB spacer. The 32-inch-wide doors will require a 34-inch-wide
opening and a 37-inch (34 in ⫹ 3 in) header. Three 37-inch headers
The number of studs needed for walls is set up in a are needed and can be cut from two 10-foot-long 2 ⫻ 12s.
spreadsheet by entering the data and formatting the cells Approximately 10 square feet of spacer are needed for these headers.
as follows: The 4-foot windows and closet doors will require 49-inch
openings and 52-inch (49 in ⫹ 3 in) headers. Because the bifold
A B C closet doors do not have jambs, the opening only needs to be
1 Wall Length 142 ft framed 1 inch wider than the doors to allow for two layers of half-
2 Stud Spacing 16 in inch drywall. Four 52-inch headers are needed and can be cut from
3 Walls without Corners 4 ea four 10-foot-long 2 ⫻ 12s. Approximately 20 square feet of spacer
4 Corners 4 ea are needed for these headers.
5 Intersections 8 ea The 6-foot window will require a 73-inch-wide opening and a
6 Doorways 5 ea 79-inch (73 in ⫹ 6 in) header. This header can be cut from two
7 Windows, Small 2 ea 8-foot-long 2 ⫻ 12s. Approximately 7 square feet of spacer are
8 Windows, Large 1 ea needed for this header. The total amount of spacer required is ap-
9 Hold Downs at Corners 2 ea proximately 37 square feet (10 ft2 ⫹ 20 ft2 ⫹ 7 ft2) and can be cut
10 Other Hold Downs - ea from two sheets of OSB.
11 Order six 10-foot-long 2 ⫻ 12s, two 8-foot-long 2 ⫻ 12s, and
12 Studs 165 ea two sheets of 7>16-inch OSB. 䊏

The following formula needs to be entered into Cell B12: Hold-downs


=ROUNDUP(B1*12/B2,0)+B3+B4*2+B5*2+B6*2 Shear panels are used to stiffen the building against lateral
+B7*6+B8*8+B9+B10*3 forces generated by wind and earthquakes. Shear panels are
created by covering the wall framing with a rigid material
The data for walls is entered in Cells B1 through B10. The
such as OSB or plywood. Wide shear panels may be tied to
data shown in the foregoing figure is from Example 8-8
the foundation with anchor bolts. Narrow shear panels re-
and is formatted using the comma style, which replaces
quire hold-downs. Hold-downs are specialty framing an-
zeros with dashes.
chors that tie the shear panel to the foundation. Hold-downs
come in a variety of types and sizes.

Headers Blocking
Headers are constructed of solid wood, laminated lumber, or Blocking is used to strengthen load-bearing walls, prevent
2⫻ materials. Because of cost, most headers are constructed the spread of fire, and provide backing for wall-mounted
of 2⫻ material and require plywood or OSB spacers such items, such as grab bars. Blocking used to strengthen load-
that the width of the header matches the width of the wall. bearing walls is placed between the studs near the midpoint
118 CHAPTER EIGHT

FIGURE 8-11 Blocking in Bearing Walls

of the studs as shown in Figure 8-11. Blocking used to pre- fraction of a sheet such as 1>8, 1>6, 1>5 1>4, 1>3, or 1>2.
vent the spread of fire is placed at points where walls inter- Openings for doors and windows in the wall are commonly
sect with mechanical drops and parallel to stair stringers. ignored because the material cut from these openings usu-
Blocking in walls is estimated using the same procedures as ally cannot be used as wall sheathing, but it may be used for
estimating blocking in floors. headers built after the wall is sheathed. The quantity takeoff
of wall sheathing is shown in the following example.

EXAMPLE 8-10
How many lineal feet of blocking are needed for the walls in EXAMPLE 8-11
Figure 8-5 if the studs in the exterior walls are blocked at their How many 4-foot by 8-foot sheets of 7>16-inch OSB are needed to
midpoints, as shown in Figure 8-11? sheet the outside of the exterior walls shown in Figure 8-5 if the
wall height is 9 feet?
Solution: Only the perimeter wall will need to be blocked.
Blocking is not needed at openings for doors and windows. The Solution: The number of rows is calculated using Eq. (4-13) as
length of the wall that needs to be blocked is calculated as follows: follows:
Length ⫽ 2(22 ft) ⫹ 2(24 ft 4 in) ⫺ 2(4 ft) ⫺ 6 ft ⫺ 32 in 9 ft
NumberRows ⫽ ⫽ 1.125 rows
⫽ 76 ft 䊏 8 ft
The number of rows is rounded up to the nearest 1>8 of a sheet.
The length of the outside surface of the exterior wall is calculated
Sheathing as follows:
Wood-framed exterior walls are commonly sheathed with Length ⫽ 2(22 ft) ⫹ 2(25 ft) ⫽ 94 ft
7>16-inch OSB or 1>2-inch plywood. Interior walls may also
be sheeted with OSB or plywood to create a shear panel. The The number of columns is calculated using Eq. (4-16) as follows:
wood sheathing is treated as a sheet good. When calculating 94 ft
NumberColumns ⫽ ⫽ 24 columns
the number of rows, one must round the rows to a common 4 ft
Woods, Plastics, and Composites 119

FIGURE 8-12 Building End Elevation

The number of sheets is calculated using Eq. (4-18) as follows: of the wall, which is 1 foot at the eaves and 6 foot 4 inches (1 ft
⫹ 5 ft 4 in) at the peak. Two pieces of sheathing can be cut from
Number ⫽ (1.125 rows) (24 columns) ⫽ 27 sheets 䊏 one sheet on the top row; therefore, only four sheets are required.
The layout of the sheathing is shown in Figure 8-13. The number
When sheathing gable ends, the waste from the sheets on each piece of sheathing represents the sheet from which the
used near the peak of the gable ends can often be used for sheathing was cut.
the sheets near the eaves of the gable ends as shown in the Because the height at the eaves (1 ft) plus the height at the
following example. peak (6 ft 4 in) is less than 8 feet, the scrap from the short side of the
gable end can be used at the peak as shown in Figure 8-14. A total of
12 sheets of sheathing are needed. 䊏
EXAMPLE 8-12
Determine the number of sheets of 7>16-inch OSB required for the
end of the building shown in Figure 8-12.
ROOF SYSTEMS
Roof systems may be stick framed using rafters, ceiling joists,
Solution: The rise for the gable end is calculated as follows:
and collar ties or may be constructed of manufactured
Rise ⫽ a ba b ⫽ 5.33 ft ⫽ 5 ft 4 in
32 ft 4 trusses. Complex roofs that use trusses often have stick-
2 12 framed overbuilds. Let’s look at using rafters to construct a
The height of the wall at the peak is 14 foot 4 inches. The number of roof:
rows of sheathing is calculated using Eq. (4-13) as follows:
14.33 ft
Rafters
NumberRows ⫽ ⫽ 2 rows
8 ft A typical rafter is shown in Figure 8-15.
The length of the rafter must be measured parallel to the
The number of columns of sheathing is calculated using Eq. (4-16)
as follows: rafter from the top corner of the rafter near the ridge to
the bottom corner of the rafter at the eaves. The length of
32 ft the rafter along the top or bottom edge may be determined
NumberColumns ⫽ ⫽ 8 columns
4 ft from the Pythagorean theorem using the rise and the run of
The first row of sheathing will run from the bottom of the wall to a the rafter. To this length, we must add the length needed to
height of 8 feet and will consist of eight sheets of sheathing. The allow the ends of the rafter to be cut at an angle, which is
second row of sheathing will run from a height of 8 feet to the top equal to the slope of the rafter times the width of the board

FIGURE 8-13 Sheathing Layout FIGURE 8-14 Layout for Sheet 9


120 CHAPTER EIGHT

FIGURE 8-15 Rafter

used for the rafter. The length of the rafter is calculated using Alternatively, it may be calculated by finding the rise as follows:
the following equation:
b ⫽ 3.67 ft
4
Rise ⫽ (Run)(Slope) ⫽ (11 ft)a
b (8-1)
Rise 12
Length ⫽ (Run2 ⫹ Rise2 ) 0.5 ⫹ (Thickness)a
Run and then calculating the length of the rafter using Eq. (8-1) as follows:
0.5
Length ⫽ c(11 ft) 2 ⫹ (3.67 ft) 2 d a b
Letting the slope equal the rise over the run and substituting (7.25 in) 3.67 ft

the slope into Eq. (8-1), we get the following equation: (12 in/ft) 11 ft
⫽ 11.8 ft
Length ⫽ (Run)(1 ⫹ Slope2) 0.5 ⫹ (Thickness)(Slope) (8-2)
Order 12-foot rafters. 䊏
The slope may also be expressed as the relationship between
the rise and the run such as a 4:12 slope or a 6:12 slope. A hip roof is shown in Figure 8-17. The length of a hip
Determining the length of a rafter is shown in the following or valley rafter for a roof with the same slope on all surfaces
example. may be calculated by finding the run of the hip or valley
rafter using the Pythagorean theorem and using Eq. (8-1) or
EXAMPLE 8-13 Eq. (8-2) to find the length. Alternatively, the length of the
hip rafter may be determined from the run of the common
What length of rafters needs to be ordered for the building shown rafter using the following equation:
in Figure 8-16? The rafters are 2 ⫻ 8s with a slope of 4:12.
Length ⫽ (RunCommon )(2 ⫹ Slope2Common ) 0.5
Solution: The thickness of a 2 ⫻ 8 is 7.25 inches. The run of the
rafter is calculated as follows: ⫹ (Thickness)(SlopeHip ) (8-3)
Span 20 ft The hip and valley rafters have a flatter slope than the
Run ⫽ ⫹ Overhang ⫽ ⫹ 1 ft ⫽ 11 ft
2 2 common rafters because their run is 41% longer than the
run of the common rafters even though they have the same
The length of the rafter may be calculated using Eq. (8-2) as follows:
rise. The slope of a hip and valley rafter for a roof of a con-
4 2 0.5
Length ⫽ (11 ft)c 1 ⫹ a b d ⫹ a b ⫽ 11.8 ft
(7.25 in) 4 stant slope can be found by replacing the 12 in the slope of
12 (12 in/ft) 12 the roof with 17. A roof with a 4:12 slope will require hip and

FIGURE 8-16 Rafter Section


Woods, Plastics, and Composites 121

FIGURE 8-17 Roofing Plan for Hip Roof

valley rafters with a 4:17 slope. Similarly, a roof with a 6:12 There are 6 common rafters on each side of the roof for a total of
slope will require hip and valley rafters with a 6:17 slope. The 12. There are also two king rafters, one on each end, that are the
length of hip and valley rafters is calculated in the same same length as the common rafters. The run for the common and
manner as the length of common rafters. king rafters is 12 feet (24 ft>2). The length of the common and king
rafters is calculated using Eq. (8-2) as follows:
For the roof in Figure 8-17, the king rafter is the same
4 2 0.5
Length ⫽ (12 ft) c1 ⫹ a b d ⫹ a b ⫽ 12.9 ft
length as the common rafters. The jack rafters will be (7.25 in) 4
shorter. When ordering lumber for the jack rafters in a hip 12 (12 in/ft) 12
roof, it is common practice to order lumber the same length
Fourteen-foot-long 2 ⫻ 8s will be used for the common and king
as the common rafters and cut two jack rafters from each rafters. There are four hip rafters. The length of the hip rafters is
piece of lumber. calculated using Eq. (8-3) as follows:
To prevent the wall from spreading apart due to the forces
4 2 0.5
Length ⫽ (12 ft) c2 ⫹ a b d ⫹ a b ⫽ 17.6 ft
(7.25 in) 4
on the rafters, collar ties spaced at no more than 4 feet on cen-
ter or ceiling joists connecting the walls must be used. Collar 12 (12 in/ft) 17
ties are commonly 1 ⫻ 4s that connect rafters and are located Eighteen-foot-long 2 ⫻ 8s will be used for the hip rafters. Each of
at least one-third of the rise below the peak of the rafters. the four corners consists of two jack rafters with the following runs:
Ceiling joist may be used to prevent the spread of the 2, 4, 6, 8, and 10 feet. The length of these rafters is calculated using
rafters in lieu of collar ties. Ceiling joists are taken off in the Eq. (8-2) as follows:
same manner as floor joists. 4 2 0.5
Length2ft ⫽ (2 ft)c1 ⫹ a b d ⫹ a b ⫽ 2.3 ft
(7.25 in) 4
The quantity takeoff for a hip roof is shown in the fol- 12 (12 in/ft) 12
lowing example.
4 2 0.5
Length4 ft ⫽ (4 ft)c1 ⫹ a b d ⫹ a b ⫽ 4.4 ft
(7.25 in) 4
12 (12 in/ft) 12
EXAMPLE 8-14
4 2 0.5
Length6 ft ⫽ (6 ft)c1 ⫹ a b d ⫹ a b ⫽ 6.5 ft
(7.25 in) 4
The hip roof shown in Figure 8-17 is constructed of 2 ⫻ 8 rafters 12 (12 in/ft) 12
spaced 24 inches on center. The roof has a slope of 4:12. Determine
4 2 0.5
Length8 ft ⫽ (8 ft)c1 ⫹ a b d ⫹ a b ⫽ 8.6 ft
the quantities and lengths of 2 ⫻ 8s needed for the roof. Ceiling (7.25 in) 4
joists will be used to prevent the walls from spreading. Do not in- 12 (12 in/ft) 12
clude the ceiling joists in your estimate. 4 2 0.5
Length10 ft ⫽ (10 ft)c1 ⫹ a b d ⫹ a b ⫽ 10.7 ft
(7.25 in) 4
Solution: The roof is 10 feet longer than it is wide; therefore, the 12 (12 in/ft) 12
common rafters must cover 10 feet on each side of the roof. The
From one 14-foot-long 2 ⫻ 8, one can cut one 2.3-foot and one
number of common rafters on each side of the roof is calculated
10.7-foot-long rafters, or one 4.4-foot and one 8.6-foot-long rafter,
from Eq. (4-1) as follows:
or two 6.5-foot-long rafters. Five 14-foot-long 2 ⫻ 8s will produce
10 ft two 2.3-foot-long rafters, two 4.4-foot-long rafters, two 6.5-foot-
Number ⫽ ⫹ 1 ⫽ 6 each
2 ft long rafters, two 8.6-foot-long rafters, and two 10.7-foot-long
122 CHAPTER EIGHT

FIGURE 8-18 Gable-End Truss

rafters; this is enough rafters to complete one corner. Twenty 14-foot- the truss, and the length of the overhang (often referred to as
long 2 ⫻ 8s are needed for the corners. A total of 34 (12 ea ⫹ 2 ea the length of the tails). A special kind of truss is a gable-end
⫹ 20 ea) 14-foot-long 2 ⫻ 8s are needed. One 10-foot-long 2 ⫻ 8 is truss, which is used at the ends of a building and anywhere
needed for the ridge board. the walls extend up beyond the ceiling line, such as in the
The materials needed are as follows: one 10-foot-long, thirty-
case of firewalls. A gable-end truss is shown in Figure 8-18.
four 14-foot-long, and four 18-foot-long 2 ⫻ 8s. 䊏
The purpose of the gable-end truss is to provide an easy-to-
frame-and-sheet end that matches the slope and dimension
of the trusses. As such, a gable-end truss must be supported
EXCEL QUICK TIP 8-6 along its full length by a bearing wall. The gable-end truss
Length of a Rafter provides an alternative to stick framing the gable ends.
The quantity takeoff for a roof using trusses is shown in
The calculation of the length of a rafter is set up in a the following example.
spreadsheet by entering the data and formatting the cells
as follows:
EXAMPLE 8-15
A B C
1 Span 20 ft What size and number of trusses need to be ordered for the roof
2 Overhang 24 in shown in Figure 8-19? The gable ends of the building are to be con-
3 Slope 4 :12 structed as part of the walls. The slope of the roof is 4:12. The
4 Thickness 7.25 in trusses are spaced 24 inches on center and are made of 2 ⫻ 4s. How
5 many 8-foot-long 2 ⫻ 4s need to be ordered if the lookouts are
6 Rise 4.00 ft constructed of 2 ⫻ 4s spaced 24 inches on center?
7 Common Rafter 12.9 ft Solution: The trusses need to cover 26 feet (30 ft ⫺ 2 ft ⫺ 2 ft) of
8 Hip Rafter 17.6 ft roof. The number of trusses needed is calculated using Eq. (4-1) as
follows:
The following formulas need to be entered into the asso-
26 ft
ciated cells: Number ⫽ ⫹ 1 ⫽ 14 each
2 ft

Cell Formula The trusses are to have a 4:12 slope, a 20-foot span, and 2-foot-long
tails. The lookouts are on the sloped end of the roof; therefore, the
B6 =(B1/2+B2/12)*B3/12 sloped length of the roof from the eave of the roof to the peak of the
roof must be calculated using the Pythagorean theorem as follows:
B7 =(B1/2+B2/12)*(1+(B3/12)^2)^0.5
Rise ⫽ a b a b ⫽ 4 ft
+B4*B3/(12*12) 24 ft 4
B8 =(B1/2+B2/12)*(2+(B3/12)^2)^0.5 2 12
24 ft 2 0.5
+B4*B3/(17*12) Length ⫽ c a b ⫹ (4 ft) 2 d ⫽ 12.7 ft
2
The data for rafter is entered in Cells B1 through B4. The Excluding the lookout at the peak and the lookout at the eave (the
data shown in the foregoing figure is from Example 8-14. lookout at the eave of the roof is part of the fascia), we calculate the
number of lookouts needed for the roof from the eave to the peak
using Eq. (4-3) as follows:
12.7 ft
Trusses Number ⫽ ⫺ 1 ⫽ 6 ea
2 ft
Trusses are used to span larger distances using less lumber. Adding 1 for the peak, the number of lookouts needed on each end
Trusses consist of a top cord, a bottom cord, and truss mem- of the building is 13 (6 ⫹ 1 ⫹ 6) for a total of 26 4-foot-long look-
bers that are used to transfer the loads. Trusses are specified outs. Two lookouts can be cut from one 8-foot-long 2 ⫻ 4; there-
based on the slope of the top and bottom cords, the span of fore, 13 (26>2) 8-foot-long 2 ⫻ 4s are needed. 䊏
Woods, Plastics, and Composites 123

FIGURE 8-19 Roofing Plan

Sheathing The number of columns is rounded to half of a sheet because the


sheet must span at least two trusses, or 4 feet. The number of sheets
The quantity takeoff for roof sheathing is done in the same needed for the roof is calculated using Eq. (4-18) as follows:
manner as floor sheathing. The sheathing for each surface of
Number ⫽ (2 sides)(3.2 rows/side)(4.5 columns) ⫽ 29 sheets
the roof should be done separately because changes in the
surface of the roof increase the waste. Unlike floor sheathing, The area of the sheets is 928 square feet (29 sheets ⫻ 32 ft2/sheet).
roof sheathing is seldom T&G, which allows more of the The waste for the roof is 7.4% (928>864 ⫺ 1). 䊏
waste to be used. The takeoff for roof sheathing is shown in
the following example.
Fascia
When fascia is being installed on the gable ends of a roof, the
EXAMPLE 8-16 length of the fascia is calculated in the same manner as the
length of the rafters is calculated using Eq. (8-1) or Eq. (8-2).
What is the area of the roof in Figure 8-19? How many sheets of
7>16-inch OSB are needed for the roof? What is the waste factor for
When fascia is installed on the eaves, the height of the fascia
this roof? is greater than the width of the framing member to which it
is being installed, as shown in Figure 8-20. For example, the
Solution: The sloped area of one side of the roof is calculated fascia being attached to a truss constructed of 2 ⫻ 4s will
using the Pythagorean theorem to determine the slope length of the need to be constructed from a 2 ⫻ 6.
roof, which is multiplied by the width of the roof. This area is mul-
tiplied by two to get the area of the roof. In Example 8-15, the
sloped length of the roof in Figure 8-19 is found to be 12.7 feet. The
area of the roof is calculated as follows:
Area ⫽ 2(12.7 ft)(34 ft) ⫽ 864 ft2
The number of rows of sheathing needed for one side of the roof is
calculated using Eq. (4-13) as follows:
12.7 ft
NumberRows ⫽ ⫽ 3.2 rows
4 ft
The number of rows is rounded to one-fifth of a sheet. The number
of columns is calculated using Eq. (4-16) as follows:
34 ft
NumberColumns ⫽ ⫽ 4.5 columns
8 ft FIGURE 8-20 Fascia
124 CHAPTER EIGHT

The size of the lumber needed to construct the fascia is The number of columns for the sides is calculated using Eq. (4-16)
calculated using the following equation: as follows:

WidthFascia ⫽ (WidthRafter )(1 ⫹ Slope2 ) 0.5 NumberColumns ⫽


30 ft
⫽ 7.5 columns
4 ft
⫹ (ThicknessFascia )(Slope) (8-4)
The number of sheets needed for the sides of the roof is calculated
The quantity takeoff for fascia is shown in the following using Eq. (4-18) as follows:
example.
Number ⫽ (2 sides)(0.25 rows/side)(7.5 columns) ⫽ 4 sheets
The number of rows for the ends is calculated using Eq. (4-13) as
EXAMPLE 8-17 follows:
How many feet of 2⫻ fascia are needed for the roof in Figure 8-19? (1 ft 10 1>2 in)
What size of fascia is needed? NumberRows ⫽ ⫽ 0.5 rows
4 ft
Solution: The width of the fascia is calculated using Eq. (8-4) as
The number of columns for the ends is calculated using Eq. (4-16)
follows:
as follows:
4 2 0.5
WidthFascia ⫽ (3.5 in)c1 ⫹ a b d ⫹ (1.5 in)a b ⫽ 4.2 in
4 12.7 ft
12 12 NumberColumns ⫽ ⫽ 1.75 columns
8 ft
Use 2 ⫻ 6s for the fascia. The length of the fascia on the ends of the The number of columns is rounded to the quarter-sheet increment,
roof is calculated using Eq. (8-2) as follows: which is 2 feet. The number of sheets needed for the side of the roof
4 2 0.5 is calculated using Eq. (4-18) as follows:
Length ⫽ (24 ft>2)c1 ⫹ a b d ⫹ a b ⫽ 12.8 ft
(5.5 in) 4
12 (12 in/ft) 12 Number ⫽ (4 end)(0.5 rows/end)(1.75 columns) ⫽ 3.5 sheets
The 2 ⫻ 6 fascia needed to frame the perimeter of the roof (in- The number of sheets needed is 8 (4 ⫹ 3.5). 䊏
cluding the lookouts at the eaves) is four 14-foot-long 2 ⫻ 6s for
the sloped ends of the building (whose length is 12.8 ft) and six
12-foot-long 2 ⫻ 6s for the side of the building (whose length is FINISH CARPENTRY
34 ft). 䊏
Finish carpentry often includes the installation of trim,
wood shelving, and wood paneling. Trim and shelving is bid
Soffit by the lineal foot and paneling is bid by the sheet in the same
manner as sheathing is bid. The quantity takeoff of wood
Sometimes sheathing is used for the soffit. The quantity
trim is shown in the following example.
takeoff for soffit is done using the row and column method,
where the number of rows of soffit is a fraction (1>2, 1>3,
1>4, 1>5, 1>6, 1>7, or 1>8) of a sheet. The quantity takeoff for EXAMPLE 8-19
soffit is shown in the following example.
Determine the wood base and wood casing needed to complete the
rooms shown in Figure 8-5. The casing is only located around the
single-hung doors. The base comes in 8-, 12-, and 16-foot lengths and
EXAMPLE 8-18 the casing comes in 7-foot lengths. Minimize the number of joints.
Determine the number of sheets of 4-foot by 8-foot by 7>16-inch
Solution: Six 12-foot-long pieces of base are needed for the main
OSB that are needed for the soffit of the roof in Figure 8-19. The
room. Three 12-foot-long pieces and one 8-foot-long piece of base
soffit is installed parallel to the surface of the roof. The soffit is
are needed for each of the bedrooms. One 8-foot-long piece of base
held back the width of the fascia (1 1>2 inches) from the edge of
along with scraps left over from the door opening to the bedroom is
the roof.
needed for each closet. The following base needs to be ordered:
Solution: The soffit will be divided into six areas: two 30-foot-long twelve 12-foot-long and four 8-foot-long pieces of base.
areas on the sides of the building and four 12.7-foot-long by 2- Each side of a door requires 2 1>2 pieces of casing. Only the in-
foot-wide areas at the ends of the building. First, we will look at the side of the exterior door needs casing; therefore, 13 (5 ⫻ 2.5) pieces
two 30-foot-long areas. The width of these areas is determined by of door casing are needed. 䊏
the Pythagorean theorem as follows:

b ⫽ 0.62 ft
4 CABINETRY AND
Rise ⫽ (1 ft 10 1>2 in)a
12
COUNTERTOPS
Length ⫽ 3(1 ft 10 1>2 in) 2 ⫹ (0.62 ft) 2 4 0.5 ⫽ 2.0 ft
The type and size of each cabinet need to be quantified.
The number of rows for the sides is calculated using Eq. (4-13) as Countertops are bid by the lineal foot. For corners, the
follows:
length of the countertop is measured at the longest side of
2.0 ft the countertop. The quantity takeoff of cabinets and coun-
NumberRows ⫽ ⫽ 0.25 rows
8 ft tertops is shown in the following example:
Woods, Plastics, and Composites 125

and a 14-foot-long redwood plate are ordered for the north wall,
two 12-foot-long redwood plates are ordered for the east wall, and a
12-foot-long and a 14-foot-long redwood plate are ordered for the
south wall. Order one 8-foot-long, four 12-foot-long, and two 14-
foot-long redwood 2 ⫻ 4 plates.
Two 50-foot-long rolls of seal sill are needed under the bottom of
wall. Nine 10-feet-long Z-flashings are needed for the exterior walls.
The number of studs needed for a 16-inch on-center spacing
is calculated using Eq. (4-2) as follows:
(82 ft 8 in)(12 in/ft)
Number ⫽ ⫽ 62 each
16 in
Two additional studs are needed for each of the four corners,
2 for the doorway, 6 for the overhead door, and 1 for each of the
two hold-downs located at the corners, for a total of 80 studs (62 ⫹
2 ⫻ 4 ⫹ 2 ⫹ 6 ⫹ 2 ⫻ 1).
The door header will require one 8-foot-long 2 ⫻ 6 and a
sheet of 7>16 OSB for a spacer. The garage header will require a
16-foot 6-inch-long 3 1>2-inch by 12-inch GLB.
The top plates for the north, east, and south walls need twice
the quantities needed for the bottom plate. For the west wall, four
12-foot-long plates are needed. Order twelve 12-foot-long and four
14-foot-long 2 ⫻ 4 plates.
FIGURE 8-21 Cabinet Elevation The number of standard trusses needed is calculated using Eq.
(4-3) as follows:
26 ft
Number ⫽ ⫺ 1 ⫽ 12 each
EXAMPLE 8-20 2 ft
Determine the cabinets and lineal feet of countertop needed for the Twelve 24-foot trusses with a 4:12 slope and 18-inch tails are
cabinet layout shown in Figure 8-21. needed along with two 24-foot gable end trusses. Twenty-four hur-
Solution: Starting with the left, the following base cabinets are ricane ties are needed to secure the standard trusses to the roof.
needed: a 36-inch-wide by 36-inch-high sink base, an 18-inch-wide Next, the 2 ⫻ 4 framing for the soffit will be taken off begin-
by 36-inch-high four-drawer base, and a 36-inch-wide by 36-inch- ning with the north side. A 29-foot-long ledger is needed at the wall
high standard base. Starting with the left, the following wall cabi- and a 29-foot fascia board is needed at the edge of the roof. Sixteen
nets are needed: two 36-inch-wide by 30-inch-high wall cabinets (one at each truss and one at both ends of the roof) 15-inch-long
and one 18-inch-wide by 30-inch-high wall cabinet. A plastic lami- pieces of blocking are needed between the ledger and the fascia
nated countertop with a 4-inch backsplash 7 feet 6 inches long is board. The same is needed for the south side of the roof.
needed. 䊏 Next, the 2 ⫻ 4 framing on the west end of the building will be
taken off. A 2 ⫻ 4 ledger is needed along the truss from the north
side of the building to the peak of the roof. The length is deter-
mined by Eq. (8-2) as follows:
SAMPLE TAKEOFF FOR THE
4 2 0.5
Length ⫽ a b c1 ⫹ a b d ⫹ a b ⫽ 12.8 ft
RESIDENTIAL GARAGE 24 ft (3.5 in) 4
2 12 (12 in/ft) 12
A sample takeoff for rough carpentry, lumber, trusses, finish
carpentry, and wood trim from a set of plans is shown in the The fascia board will run parallel to the truss from the edge of the roof
to the peak of the building. The length is determined by Eq. (8-2)
following example.
as follows:
4 2 0.5
Length ⫽ a b c1 ⫹ a b d ⫹ a b ⫽ 14.3 ft
27 ft 3.5 in 4
EXAMPLE 8-21 2 12 (12 in/ft) 12
Determine the rough carpentry, lumber, trusses, finish carpentry, Blocking is located at 24 inches on center on the sloped end of the
and wood trim needed to complete the residential garage found in roof; therefore, the sloped length of the roof from the eave of the roof
Appendix F. to the peak of the roof must be calculated using the Pythagorean the-
Solution: The thickness of the exterior wall is 4 inches (3 1>2-inch- orem as follows:
thick stud plus 1>2-inch-thick exterior sheathing). Find the length
Rise ⫽ a b a b ⫽ 4.5 ft
27 ft 4
of the wall as follows: 2 12
Length ⫽ 4 ft ⫹ 25 ft 4 in ⫹ 24 ft ⫹ 25 ft 4 in ⫹ 4 ft ⫽ 82 ft 8 in 27 ft 2 0.5
Length ⫽ c a b ⫹ (4.5 ft) 2 d ⫽ 14.3 ft
Eighty-three feet of wall with one opening for a single-hung door 2
and one opening for an overhead door need to be framed. An 8- Excluding the blocking at the peak and the blocking at the eave (the
foot-long redwood plate is ordered for the west wall, a 12-foot-long blocking at the eave of the roof is part of the fascia), we calculate
126 CHAPTER EIGHT

the number of pieces of blocking needed for the roof from the eave The quantities needed for the garage, grouped by the cost
to the peak using Eq. (4-3) as follows: codes in Appendix B, are shown in Table 8-1. 䊏
14.3 ft
Number ⫽ ⫺ 1 ⫽ 7 ea TABLE 8-1 Quantities for Residential Garage
2 ft
Adding 1 for the peak, we find that the number of pieces of block- 06-100 Rough Carpentry
ing needed on the west end of the building is 15 (7 ⫹ 1 ⫹ 7). Each
of these is 15 inches long. The same quantities are needed for the 2 ⫻ 4 wall 83 ft
east side. Single-hung door opening 1 ea
The total length of ledger needed is 110 feet (29 ⫹ 12.8 ⫹ 12.8 ⫹
Overhead door opening 1 ea
29 ⫹ 12.8 ⫹ 12.8). Order fourteen 8-foot-long 2 ⫻ 4s for the
ledger. The total length of fascia is 116 feet (29 ⫹ 14.3 ⫹ 14.3 ⫹ 29 ⫹ Install trusses 14 ea
14.3 ⫹ 14.3). Order fifteen 8-foot-long 2 ⫻ 4s for the fascia. The Install ledger 110 ft
number of 15-inch-long blockings is 62 (16 ⫹ 15 ⫹ 16 ⫹ 15). Six
pieces 15 inches long can be cut from one 8-foot-long 2 ⫻ 4. Order
Install fascia board 116 ft
eleven 8-foot-long 2 ⫻ 4s for the blocking. A total of 40 (14 ⫹ 15 ⫹ Install 15⬙ blocking 62 ea
11) 8-foot-long 2 ⫻ 4s are needed for the soffit framing. Install ceiling blocking 48 ft
Two 24-foot-long pieces of blocking are needed for the ceiling
(see detail K5 on Sheet 7 in Appendix F). Order six 8-foot-long 2 ⫻ 4s Install roof sheathing 829 sft
for the ceiling blocking. Order a total of forty-six 8-foot-long 2 ⫻ 4s,
to frame the soffit and block the ceiling. 06-110 Lumber
Next, the roof sheathing will be taken off. The width of one
Walls
side of the roof is 14.3 feet. The area of the roof that needs to be
sheathed is calculated as follows: 2 ⫻ 4-8⬘ redwood 1 ea
Area ⫽ 2(14.3 ft)(29 ft) ⫽ 829 ft2 2 ⫻ 4-12⬘ redwood 4 ea
2 ⫻ 4-14⬘ redwood 2 ea
The number of rows of sheathing needed for one side of the roof is
calculated using Eq. (4-13) as follows: Seal sill 50⬘ 2 ea
14.3 ft Z-flashing 10⬘ long 9 ea
NumberRows ⫽ ⫽ 4 rows
4 ft 2 ⫻ 4-92 5>8⬙ stud 80 ea
The number of columns is calculated using Eq. (4-16) as follows: 2 ⫻ 6-8⬘ 1 ea

29 ft
7>16⬙⫻4⬘ ⫻ 8⬘ OSB 1 ea
NumberColumns ⫽ ⫽ 4 columns 3-1>2⬙ ⫻ 12⬙ GLB 16.5 ft
8 ft
The number of sheets needed for the roof is calculated using 2 ⫻ 4-12⬘ 12 ea
Eq. (4-18) as follows: 2 ⫻ 4-14⬘ 4 ea
Number ⫽ (2 sides)(4 rows/side)(4 columns) ⫽ 32 sheets Roof
Hurricane ties 24 ea
Three rows of plywood clips are needed on each side of the roof
with a plywood clip located between each pair of trusses; there- 2 ⫻ 4-8⬘ 46 ea
fore, 13 (1 less than the number of trusses) columns of clips are 7>16⬙ ⫻ 4⬘ ⫻ 8⬘ OSB 32 ea
needed. The number of clips is calculated using Eq. (4-18) as
follows: Plywood clips 78 ea

Number ⫽ (2 sides)(3 rows/side)(13 columns) ⫽ 78 each 06-120 Trusses


The finish carpentry includes the installation of the trim. The trim 12 ea
24⬘ 4:12 standard trusses w/18⬙ tails
consists of the fascia and the casing on the inside of the door. The
T1-11 siding, the soffit, and 1 ⫻ 4 cedar trim associated with the 24⬘ 4:12 gable trusses w/18⬙ tails 2 ea
siding are covered under siding in Chapter 9. The total length of
fascia is 116 feet (29 ⫹ 14.3 ⫹ 14.3 ⫹ 29 ⫹ 14.3 ⫹ 14.3). The 06-200 Finish Carpentry
height of the fascia is calculated using Eq. (8-4) as follows:
Install shaped fascia 116 ft
4 2 0.5
WidthFascia ⫽ (3.5 in) c1 ⫹ a b d ⫹ (1.5 in)a b ⫽ 4.2 in
4 Install door casing 1 set
12 12
The fascia is cut from 2 ⫻ 6s. Three 10-foot pieces of 1 ⫻ 6 trim are 06-210 Wood Trim
needed for the north and south sides of the building. Two 16-foot
1⫻6-10⬘ cedar 6 ea
pieces of trim are needed for each gable end. Order six 10-foot-long
1 ⫻ 6 and four 16-foot-long 1 ⫻ 6 pieces of cedar for the fascia. 1⫻6-16⬘ cedar 4 ea
Three 7-foot pieces of casing are needed for the inside of the 7⬘ casing 3 ea
single-hung door.
Woods, Plastics, and Composites 127

CONCLUSION 6. The perimeter of the floor system in Figure 8-23 sits on


a redwood sill. Determine the number of 16-foot-long
Woods and plastics consist of rough carpentry, finish car- pieces of redwood that are needed to complete the floor
pentry, and cabinets and countertops. Rough carpentry con- system.
sists of framing the floors, walls, and roof of the structure. 7. Determine the materials needed to complete the posts
Finish carpentry consists of installing finish material includ- and girder supporting the floor joists in Figure 8-23.
ing wood trim, shelving, and handrails. Cabinetry includes The posts are connected to footings using a Simpson
the installation of cabinets and countertops. PB46 post base and are connected to the girder using a
Simpson BC46 post cap. The distance between the top
of the footing and the bottom of the girder is 7 feet.
PROBLEMS The posts are equally spaced along the glue-laminated
1. The floor system in Figure 8-22 sits on a redwood sill on beam.
a concrete wall. Determine the number of 16-foot-long 8. Determine the materials needed to construct the
pieces of redwood that are needed to complete the floor joists and joist headers for the floor system shown in
system. Figure 8-23. An engineered rim board is used for the
2. Determine the materials needed to complete the posts joist headers.
and girder supporting the floor joists in Figure 8-22. 9. For the floor system shown in Figure 8-23, the joists are
The posts are connected to footings using a Simpson blocked over the girder and at the midpoint between the
PB44 post base and are connected to the girder using a girder and the exterior wall on the joists over 8 feet long.
Simpson BC4 post cap. The distance between the top of I-joists are to be used for the blocking. How many feet
the footing and the bottom of the girder is 7 feet. The of I-joists are needed for the blocking?
posts are spaced 12 feet apart. 10. Determine the number of 4-foot by 8-foot sheets of
3. Determine the materials needed to construct the 23>32-inch T&G OSB sheathing that are needed to con-
joists and joist headers for the floor system shown in struct the floor system shown in Figure 8-23.
Figure 8-22. 11. How many board feet of 2⫻6 redwood decking are
4. For the floor system shown in Figure 8-22, the joists are needed to construct a 20-foot by 30-foot deck? The
blocked over the girder, at the concrete wall at the over- boards are to be placed without any space between them.
hang, and at the midpoint between the girder and the 12. How many board feet of 2⫻4 redwood decking are
exterior wall on the joists over 8 feet long. Determine needed to construct a 10-foot by 20-foot deck? The boards
the materials needed for the blocking. are to be placed with a 1>2-inch space between them.
5. Determine the number of 4-foot by 8-foot sheets of 13. How many board feet of 2⫻4 treated and untreated
23>32-inch T&G OSB sheathing that are needed to con- plate are needed to construct 100 feet of 2⫻4 wall? The
struct the floor system shown in Figure 8-22. wall bears on a concrete floor.

FIGURE 8-22 Floor-Framing Plan


128 CHAPTER EIGHT

FIGURE 8-23 Floor-Framing Plan

14. How many board feet of 2 ⫻ 4 treated and untreated 18. Prepare a materials list for the headers required to com-
plate are needed to construct 75 feet of 2 ⫻ 4 wall? The plete the wall in Problem 17. All headers are made from 2
wall bears on a wood floor. ⫻ 12 materials and the wall is made from 2 ⫻ 6s. Openings
15. How many studs are needed to construct 100 feet of 2 6 feet or more in width require double jack studs.
⫻ 4 wall? The wall has one 8-foot-wide window, four 19. How many sheets of 7>16-inch OSB are needed to con-
4-foot-wide windows, two 36-inch-wide doors, one struct 100 feet of wall 8 feet high?
30-inch-wide door, four corners, two intersections, 20. How many sheets of 7>16-inch OSB are needed to con-
and eight hold-downs located at corners. The stud struct 100 feet of wall 9 feet 3 inches high?
spacing is 16 inches on center. Allow for two addi-
21. How many feet of treated and untreated plate are
tional studs for each corner, intersection, or doorway;
needed to construct the walls shown in Figure 8-24? The
six additional studs for each window less than 6 feet in
walls are constructed of 2⫻4s with the exterior walls
width; eight additional studs for each window 6 feet
being sheathed with 7>16-inch OSB. The walls bear on a
or more in width; and one additional stud for each
concrete floor.
hold-down located at a corner.
16. Prepare a materials list for the headers required to com- 22. How many studs are needed to frame the wall in Fig-
plete the wall in Problem 15. All headers are made from ure 8-24? The stud spacing is 16 inches on center. Allow
2 ⫻ 12 materials and the wall is made from 2 ⫻ 4s. for one additional stud for each wall that does not have a
Openings 6 feet or more in width require double jack corner; two additional studs for each corner, intersection,
studs. or doorway; six additional studs for each window less
than 6 feet in width; and eight additional studs for each
17. How many studs are needed to construct 180 feet of 2
window 6 feet or more in width. The closet doors are
⫻ 6 wall? The wall has two 6-foot-wide windows, four
6 feet wide and the single-hung doors are 30 inches wide.
4-foot-wide windows, three 3-foot-wide windows,
one 60-inch-wide door, one 36-inch-wide door, one 23. Prepare a materials list for the headers required to com-
30-inch-wide door, six corners, eight intersections, plete the walls in Figure 8-24. All headers are made from
and four hold-downs located at corners. The stud 2⫻12s and the wall is made from 2⫻4s. The single-
spacing is 24 inches on center. Allow for two addi- hung doors are 32 inches wide and the closet doors are 6
tional studs for each corner, intersection, or doorway; feet wide. Openings 6 feet or more in width require
six additional studs for each window less than 6 feet in double jack studs.
width; eight additional studs for each window 6 feet 24. How many lineal feet of blocking are needed for the
or more in width; and one additional stud for each walls in Figure 8-24 if the studs in the exterior walls are
hold-down located at a corner. blocked at their midpoints as shown in Figure 8-11?
Woods, Plastics, and Composites 129

FIGURE 8-24 Wall Layout

25. How many 4-foot by 8-foot sheets of 7>16-inch OSB are being sheathed with 7>16-inch OSB. The walls bear on a
needed to sheet the outside of the exterior walls shown concrete floor.
in Figure 8-24 if the wall height is 9 feet? 27. How many studs are needed to frame the wall in
26. How many feet of treated and untreated plate are Figure 8-25? The stud spacing is 16 inches on center.
needed to construct the walls shown in Figure 8-25? The Allow for one additional stud for each wall that does
walls are constructed of 2 ⫻ 4s with the exterior walls not have a corner; two additional studs for each corner,

FIGURE 8-25 Wall Layout


130 CHAPTER EIGHT

intersection, or doorway; six additional studs for each slope of 4:12. Prepare a list of lengths and quantities for
window less than 6 feet in width; and eight additional the 2 ⫻ 6s. Hint: The lengths of the valley rafters are calcu-
studs for each window 6 feet or more in width. lated in the same way as those for the hip rafters. Ceiling
28. Prepare a materials list for the headers required to com- joists will be used to prevent the walls from spreading. Do
plete the walls in Figure 8-25. All headers are made from not include the ceiling joists in your estimate.
2 ⫻ 12s and the wall is made from 2 ⫻ 4s. The exterior 35. What size of trusses needs to be ordered for the roof
doors are 36 inches wide and the interior single-hung shown in Figure 8-28? The gable ends of the building
doors are 32 inches wide. Openings 6 feet or more in are to be constructed as part of the walls. The slope of
width require double jack studs. the roof is 4:12. The trusses are spaced 24 inches on
29. How many lineal feet of blocking are needed for the center and are made of 2 ⫻ 4s. How many 8-foot-long
walls in Figure 8-25 if the studs in the exterior walls are 2 ⫻ 4s need to be ordered if the lookouts are con-
blocked at their midpoints as shown in Figure 8-11? structed of 2 ⫻ 4s spaced 24 inches on center?
30. How many 4-foot by 8-foot sheets of 7>16-inch OSB are 36. What size of trusses needs to be ordered for the roof shown
needed to sheet the outside of the exterior walls shown in Figure 8-29? The slope of the roof is 4:12. The trusses are
in Figure 8-25 if the wall height is 10 feet 4 inches? spaced 24 inches on center and are made of 2 ⫻ 4s.
31. A roof framed with 2 ⫻ 8 rafters has a span of 30 feet, an 37. What is the area of the roof in Figure 8-28? How many
overhang of 18 inches, and a slope of 6:12. What length sheets of 7>16-inch OSB are needed for the roof? What
of common rafters needs to be ordered for the roof? is the waste factor for this roof?
32. A roof framed with 2 ⫻ 6 rafters has a span of 18 feet, an 38. What is the area of the roof in Figure 8-29? How many
overhang of 12 inches, and a slope of 4:12. What length sheets of 7>16-inch OSB are needed for the roof? What
of common rafters needs to be ordered for the roof? is the waste factor for this roof?
33. The hip roof shown in Figure 8-26 is constructed of 2 ⫻ 8 39. How many feet of 2⫻ fascia are needed for the roof in
rafters spaced 16 inches on center. The hip rafters are Figure 8-28? What size of fascia is needed?
1 1>2-inch-wide by 12-inch-high GLBs. The roof has a 40. How many feet of 2⫻ fascia are needed for the perimeter
slope of 6:12. Prepare a list of lengths and quantities for of the roof in Figure 8-29? What size of fascia is needed?
the 2 ⫻ 8s and GLBs. Ceiling joists will be used to pre- 41. Determine the number of sheets of 4-foot by 8-foot by
vent the walls from spreading. Do not include the ceil- 7>16-inch OSB that are needed for the soffit of the roof
ing joists in your estimate. in Figure 8-28. The soffit is installed parallel to the roof.
34. The hip roof shown in Figure 8-27 is constructed of 2 ⫻ 6 42. Determine the number of sheets of 4-foot by 8-foot by
rafters spaced 24 inches on center. The hip and valley 7>16-inch OSB that are needed for the soffit of the roof
rafters are also constructed of 2 ⫻ 6s. The roof has a in Figure 8-29. The soffit is installed horizontally.

FIGURE 8-26 Roofing Plan for Hip Roof


Woods, Plastics, and Composites 131

FIGURE 8-27 Roofing Plan for Hip Roof

FIGURE 8-28 Roofing Plan


132 CHAPTER EIGHT

FIGURE 8-29 Roofing Plan

43. Determine the wood base and wood casing needed to


complete the rooms shown in Figure 8-24. The casing is
only located around the single-hung doors. The base
comes in 8-, 12-, and 16-foot lengths and the casing
comes in 7-foot lengths.
44. Determine the wood base and wood casing needed to
complete the rooms shown in Figure 8-25. The casing is
only located around the single-hung doors. The base
comes in 8-, 12-, and 16-foot lengths and the casing
comes in 7-foot lengths.
45. Determine the cabinets and lineal feet of countertop
needed for the cabinet layout shown in Figure 8-30.
46. Determine the cabinets and lineal feet of countertop
needed for the cabinet layout shown in Figure 8-31.
FIGURE 8-30 Cabinet Elevation

FIGURE 8-31 Cabinet Elevation


Woods, Plastics, and Composites 133

47. Determine the lumber needed to frame the Johnson 54. Set up Excel Quick Tip 8-3 in Excel.
Residence given in Appendix F. 55. Set up Excel Quick Tip 8-4 in Excel.
48. Determine the wood base and casing needed to com- 56. Set up Excel Quick Tip 8-5 in Excel.
plete the Johnson Residence given in Appendix F. 57. Set up Excel Quick Tip 8-6 in Excel.
49. Determine the cabinetry and countertops needed to 58. Modify Excel Quick Tip 8-3 to allow the building length
complete the Johnson Residence given in Appendix F. and width to be entered in feet and inches.
50. Determine the lumber needed to complete the West 59. Modify Excel Quick Tip 8-6 to allow the span to be en-
Street Video project given in Appendix F. tered in feet and inches.
51. Determine the cabinetry and countertops needed to com-
plete the West Street Video project given in Appendix F.
REFERENCE
52. Set up Excel Quick Tip 8-1 in Excel.
53. Set up Excel Quick Tip 8-2 in Excel. 1. International Building Code, International Code Council,
2009, Table 2308.8.3.
CHAPTER NINE

THERMAL AND MOISTURE


PROTECTION

In this chapter you will learn how to apply the principles in increase the effectiveness of the waterproofing, a drain board
Chapter 4 to waterproofing and dampproofing, building paper may be placed on the outside of the waterproof membrane.
and vapor barriers, insulation, exterior insulation finish sys- The drain board allows water to travel freely in the vertical
tem (EIFS), shingles, siding, and membrane roofing. This direction, thus minimizing the chance that it will penetrate
chapter includes sample spreadsheets that may be used in the the waterproof membrane. For a drain board to be effective,
quantity takeoff. It also includes example takeoffs from the res- there must be a drainage system at the bottom of the drain
idential garage drawings in Appendix F. board to prevent the accumulation of water.
Sprayed-on waterproofing is bid by the square foot or as
a quantity-from-quantity good. Waterproof membranes and

T
building paper is bid as a sheet or roll good. The quantity
his chapter deals with the insulation and exterior
takeoff for sprayed-on waterproofing is shown in the follow-
finishes that protect the building against heat loss
ing example.
and the infiltration of water. Let’s begin by looking
at waterproofing and dampproofing.
EXAMPLE 9-1
WATERPROOFING AND Figure 9-1 shows the foundation plan and a wall section for a build-
DAMPPROOFING ing. The entire exterior perimeter of the building is to be water-
proofed with a sprayed-on membrane starting 6 inches from the top
Waterproofing and dampproofing consist of a water-resistant of the wall, continuing down the wall, and covering the top of the
coat that is sprayed or brushed onto the exterior of the foun- footing. How many square feet of waterproofing are needed for the
dation. Sometimes a waterproof membrane or layers of building? If one gallon of waterproofing material covers 80 square
building paper are included in the waterproofing system. To feet, how many gallons of waterproofing material are needed?

FIGURE 9-1 Foundation Plan and Section


134
Thermal and Moisture Protection 135

FIGURE 9-2 Corners

Solution: The perimeter of the building is 100 feet (20 ft + 30 ft +


20 ft + 30 ft). The height of the waterproofing is the height of the
wall less 6 inches plus the width of the top of the footing on one
Cell Formula
side of the wall, or 8.5 feet (8 ft - 0.5 ft + 1 ft). The area of the wa- =SUM(B1:B6)
B13
terproofing is 850 square feet (100 ft ⫻ 8.5 ft). To this, one needs to
add the four 1-foot by 1-foot corners (shown in Figure 9-2) on top B14 =B12*(B7-B8/12+B9/12)+B10*(B9/12)*
of the footing. The total area is 854 square feet. The number of gal- (B9/12)
lons of waterproofing is determined using Eq. (4-20) as follows:
B15 =B14/B11
854!sft
Quantity ⫽ ⫽ 10.7!gallons 䊏
80 sft/gallon
The data for the foundation is entered in Cells B1
through B10. The data shown in the foregoing figure is
from Example 9-1 and is formatted using the comma
EXCEL QUICK TIP 9-1 style, which replaces zeros with dashes.
Waterproofing
The calculation of the area of the waterproofing is set up
in a spreadsheet by entering the data and formatting the
cells as follows: BUILDING PAPER AND
A B C
VAPOR BARRIERS
1 Wall Length 1 30 ft Building paper and vapor barriers are used behind masonry
2 Wall Length 2 20 ft or siding, under shingles, and between the insulation and the
3 Wall Length 3 30 ft inside finish of the exterior walls. Building paper and vapor
4 Wall Length 4 20 ft barriers are bid as a rolled good and must be lapped to be ef-
5 Wall Length 5 - ft fective. The quantity takeoff for building paper behind ma-
6 Wall Length 6 - ft sonry or siding is shown in the following example.
7 Wall Height 8 ft
8 Start __ Below Top of Wall 6 in
9 Width of Top of Footing 12 in EXAMPLE 9-2
10 Extra Corners 4 ea
11 Coverage 80 sft/gal Determine the number of rolls of 30-pound asphalt-impregnated
12 felt needed to cover a wall 90 feet long by 8 feet high. The felt comes
13 Perimeter 100 ft in rolls 3 feet wide with 2 squares (200 ft2) per roll. The felt must be
lapped 12 inches on the ends and 6 inches on the sides.
14 Area of Waterproofing 854 sft
15 Gallons of Waterproofing 10.6 gal Solution: The number of rows of felt is calculated using Eq. (4-12)
as follows:
The following formulas need to be entered into the asso-
ciated cells: 8!ft
NumberRows ⫽ ⫽ 3.2!rows
(3!ft ⫺ 0.5!ft)
136 CHAPTER NINE

FIGURE 9-3 Roof Plan

Because the partial row is equal to the lap, the number of rows can the roof to a point 24 inches inside the exterior face of the
be rounded down. Three rows of felt are needed. The first row will exterior wall.2 Local codes may increase this distance.
run from the bottom of the wall to 3 feet high, the second row will When taking off roofs, distances that are perpendicular
run from 2 feet 6 inches to 5 feet 6 inches, and the last row will run to the slope of the roof can be measured directly off of the
from 5 feet to 8 feet, the top of the wall. The length of a roll is 66
plans, whereas distances that are parallel to the slope of the
feet 8 inches (200 ft2/3 ft). The number of columns is calculated
roof must be converted from a plan view (horizontal) dis-
using Eq. (4-15) as follows:
tance to a sloped distance. This is done using the following
90!ft equation:
NumberColumns ⫽ ⫽ 1.4!columns
(66.67!ft ⫺ 1!ft)
LengthSloped ⫽ LengthPlan View (1 ⫹ Slope2 ) 0.5 (9-1)
The number of sheets needed for the wall is calculated using Eq.
(4-18) as follows: The plan view area is substituted into Eq. (9-1) to get the fol-
lowing equation, which is used to convert the plan view area
Number ⫽ (3!rows)(1.4!columns) ⫽ 5!rolls 䊏 into the actual surface area:
AreaSurface ⫽ AreaPlan View (1 ⫹ Slope2 ) 0.5 (9-2)
When using asphalt-impregnated felt on roofs with a
slope greater than or equal to 2:12 and less than 4:12 the felt Hips and valleys on roofs increase the waste and the
must be lapped 19 inches. When using asphalt-impregnated amount of material needed to complete the roof. For the hip
felt on roofs with a slope greater than or equal to 4:12, the roof in Figure 9-3, the felt layout for the trapezoidal areas is
felt must be lapped 2 inches.1 In areas of the country where shown in Figure 9-4. During installation, the dashed areas of
there is the possibility of ice forming on the eaves, two layers the felt are folded over onto the triangular areas of the roof.
of felt cemented together or self-adhering bitumen sheet A similar situation occurs on the triangular areas. This in-
such as Ice and Water Shield are required from the edge of creases the amount of material needed to complete the roof.

FIGURE 9-4 Felt Layout


Thermal and Moisture Protection 137

To do a proper takeoff for a roof, each roof surface must A 13-foot-long (12 ft ⫹ 2 ⫻ 0.5 ft) piece of felt is needed for the
be taken off individually. The felt folded over onto the ad- ridge. The area of this felt is 39 square feet (13 ft ⫻ 3 ft). The area of
joining roof surfaces is taken into account by increasing the felt needed for the entire roof is calculated as follows:
width of the surface by the width of the roll of felt plus the Area ⫽ 2(AreaTrapezoidal ) ⫹ 2(AreaTriangular ) ⫹ AreaRidge
required end lap. In the case of a 36-inch-wide roll of felt ⫽ 2(672!ft2 ) ⫹ 2(420!ft2 ) ⫹ 39!ft2 ⫽ 2,223!ft2
with a 12-inch end lap, the length of each row is increased by
The number of rolls of felt is calculated as follows:
4 feet (48 in). It is important to note that the increase in
width is perpendicular to the length of the roll (parallel to 2,223!ft2
Rolls ⫽ ⫽ 6!rolls 䊏
the slope of the roof surface) rather than parallel to the hip (400!ft2/roll)
˛

or valley.
Rather than calculate the length of each of the rows, one Alternatively, the quantity of felt is approximated by the
can approximate the lengths by using the average length. following equation:

AreaFelt ⫽ AreaRoof (1 ⫹ Slope2 ) 0.5 c d


Unless the top row of felt has sufficient material to be folded Width
over the ridge and meet the lapping requirements, an addi- (Width ⫺ LapSide )
tional piece of felt is needed for the ridge whose length (1 ⫹ Slope2 ) 0.5
equals the length of the ridge plus twice the required edge ⫹ LengthHip/Valley c d
lap. The takeoff of felt is shown in the following example. 2
⫻ (Width ⫹ LapEnd ) c d
Width
(Width ⫺ LapSide )
EXAMPLE 9-3 ⫹ 3LengthRidge ⫹ 2(Ridges)(LapEnd ) 4Width
Determine the number of rolls of 15-pound asphalt-impregnated (9-3)
felt needed for the roof in Figure 9-3. The felt is to be lapped 6 where
inches on the side and 12 inches on the ends. The felt is available in AreaFelt ⫽ Area of the Felt Needed for the Roof
rolls 3 feet wide with 4 squares (400 ft2) per roll. The slope on the
roof is 6:12.
AreaRoof ⫽ Area of the Roof in Plan View
Slope ⫽ Slope of the Roof (Rise/Run)
Solution: The sloped length of the roof from the eaves to the ridge
is calculated using Eq. (9-1) as follows:
Width ⫽ Width of the Felt
LapSide ⫽ Required Lap at the Sides of the Felt
6 2 0.5
LengthSloped ⫽ (16!ft) c 1 ⫹ a b d ⫽ 17.89!ft LengthHip/Valley ⫽ Length of the Hips and Valleys in
12
Plan View
The number of rows is calculated using Eq. (4-12) as follows: LapEnd ⫽ Required Lap at the Ends of the Felt
17.89!ft LengthRidge ⫽ Length of Ridges
NumberRows ⫽ ⫽ 7.156!rows
(3!ft ⫺ 0.5!ft) Ridges ⫽ Number of Ridges
Because the width of the partial row is less than the width of the The purposes of the various components of Eq. (9-3)
lap, the number of rows is rounded down to 7. The rows will run are shown in Table 9-1.
from the eave to 3 feet, from 2 feet 6 inches to 5 feet 6 inches, from
5 feet to 8 feet, from 7 feet 6 inches to 10 feet 6 inches, from 10 feet
to 13 feet, from 12 feet 6 inches to 15 feet 6 inches, and from 15 feet EXAMPLE 9-4
to 18 feet, covering the side of the roof. The average length of a row
for trapezoidal areas is the average of the length of the ridge and the Solve Example 9-3 using Eq. (9-3).
eave plus the width of the felt plus the required end lap and is cal- Solution: The lengths of the hips in plan view are calculated using
culated as follows: the Pythagorean theorem as follows:
(44!ft ⫹ 12!ft) Length ⫽ 冤(16!ft) 2 ⫹ (16!ft) 2冥0.5 ⫽ 22.62!ft
LengthTrapezoidal ⫽ ⫹ 3!ft ⫹ 1!ft ⫽ 32!ft
2 The total length of the hips is 91 feet (4 ⫻ 22.62 ft). The quantity of
The area of felt needed for a trapezoidal area is equal to the average felt needed is calculated as follows:
length multiplied by the number of rows multiplied by the width of
AreaFelt ⫽ (44!ft)(32!ft)冤1 ⫹ (6>12) 2冥0.5 c d
3!ft
the felt and is calculated as follows:
(3!ft ⫺ 0.5!ft)
AreaTrapezoidal ⫽ (32!ft)(7!rows)(3!ft/row) ⫽ 672!ft2 (1 ⫹ (6>12) 2 ) 0.5
⫹ (91!ft) c d (3!ft ⫹ 1!ft) c d
˛ ˛

3!ft
The average length of a row for the triangular areas is calculated as 2 (3!ft ⫺ 0.5!ft)
follows: ⫹ !冤12!ft ⫹ 2(1)(1!ft)冥(3!ft)
(32!ft ⫹ 0!ft) ⫽ 2,276!ft2
LengthTriangular ⫽ ⫹ 3!ft ⫹ 1!ft ⫽ 20!ft
2 The number of rolls of felt is calculated as follows:
The area of felt needed for a triangular area is calculated as follows: 2,276!ft2
Rolls ⫽ ⫽ 6!rolls 䊏
AreaTriangular ⫽ (20!ft)(7!rows)(3!ft/row) ⫽ 420!ft2
˛
(400!ft2> roll)
˛ ˛
138 CHAPTER NINE

TABLE 9-1 Components of Eq. (9-3)


Equation Component Purpose

(1 ⫹ Slope2 ) 0.5 Converts the area from the plan view to the actual area of the roof
using Eq. (9-2)

c d
Width
(Width ⫺ LapSide ) Takes into account the lap on the side of the rolls

(1 ⫹ Slope2 ) 0.5 Converts the length of hips and valleys in the plan view to the
c d length along the roof surface as measured perpendicular to the felt
2
(Width ⫹ LapEnd ) Takes into account the lap on the hips and valleys
2(Ridges)(LapEnd ) Takes into account the lap at the ends of the ridges

When Ice and Water Shield is used at the eaves, the num- INSULATION
ber of rows of Ice and Water Shield required is determined.
The Ice and Water Shield reduces the area covered by the felt. The two most common types of insulation are fiberglass batt
The felt must cover the area not covered by the Ice and Water insulation and blown insulation. Batt insulation may be pa-
Shield and must lap over the edge of the Ice and Water Shield. perbacked or unfaced. Paperbacked insulation is installed
The felt needed to cover the remaining area is calculated with the paper on the interior side of the wall. Unfaced insu-
using the procedures shown in Examples 9-3 and 9-4. lation requires a vapor barrier, such as a plastic sheet, to be
placed on the interior side of exterior walls. Batt insulation is
available in rolls or precut blankets packaged in bundles.
EXCEL QUICK TIP 9-2 Batt insulation comes in two common widths: 15 inches for
Roofing Felt use in 2⫻ framing with a spacing of 16 inches on center and
23 inches for a spacing of 24 inches on center. The quantity
The calculation of the number of rolls of roofing felt of insulation needed for a wall or ceiling is bid as a sheet
needed for a roof is set up in a spreadsheet by entering the good with a 1-inch spacing between the sheets; a sample cal-
data and formatting the cells as follows: culation is shown in the following example.
A B C
1 Roof Length (Plan View) 44 ft EXAMPLE 9-5
2 Roof Width (Plan View) 32 ft
3 Slope 6 :12 How many square feet of wall insulation are needed to insulate 90
4 Underlayment Width 3 ft feet of an 8-foot-high wall? The stud spacing is 16 inches on center.
5 Squares Per Roll 4 squ How many rolls of insulation are needed if there are 40 square feet
6 Side Lap 6 in per roll?
7 End Lap 12 in Solution: The number of rows is one row 8 feet high. The number
8 Total Length of Hips/Valleys 91 ft of columns is calculated using Eq. (4-17) as follows:
9 Total Length of Ridges 12 ft
10 Number of Ridges 1 ea (90!ft)(12!in/ft)
NumberColumns ⫽ ⫽ 68!columns
11 (15!in ⫹ 1!in)
12 Area 2,276 sft
The number of sheets of 8-foot by 15-inch-wide insulation needed
13 Rolls 6 ea
is 68. The area of insulation needed is equal to number of sheets
The following formulas need to be entered into the asso- multiplied by the area of the sheet, which is equal to the length of
the sheet multiplied by the width of the sheet:
ciated cells:
b ⫽ 680!ft2
1!ft
Area ⫽ (68)(8!ft)(15!in)a
Cell Formula 12!in

=B1*B2*(1+(B3/12)^2)^0.5* The number of rolls is calculated as follows:


B12
(B4/(B4-B6/12)) 680!ft2
Number ⫽ ⫽ 17!rolls 䊏
+B8*((1+(B3/12)^2)/2)^0.5*(B4+B7/12) (40!ft2> roll)
˛ ˛

*(B4/(B4-B6/12))+(B9+2*B10*B7/12)*B4
B13 =ROUNDUP(B12/(B5*100),0) Alternatively, the square footage of insulation for an in-
sulated surface is approximated by the following equation:
The data for roof is entered in Cells B1 through B10. The
b
Width
data shown in the foregoing figure is from Example 9-4. AreaInsulation ⫽ (AreaWall )a ˛ (9-4)
Spacing
Thermal and Moisture Protection 139

where Solution: The area of the wall is calculated as follows:


Width ⫽ Width of the Insulation AreaWalls ⫽ (90!ft)(8!ft) ⫽ 720!ft2
Spacing ⫽ Spacing of the Framing Members
The area of the insulation is calculated using Eq. (9-4) as follows:
The width of the insulation should be 1 inch less than the
b ⫽ 675!ft2
15!in
AreaInsulation ⫽ (720!ft2 )a
˛

stud spacing. The use of this equation is shown in the fol- 16!in
lowing example:
The number of rolls is calculated as follows:
675!ft2
EXAMPLE 9-6 Number ⫽ ⫽ 17!rolls 䊏
(40!ft2/roll)
Solve Example 9-5 using Eq. (9-4).

EXCEL QUICK TIP 9-3


Batt Insulation
The calculation of the number of rolls of insulation needed is set up in a spreadsheet by entering the data and formatting
the cells as follows:

A B C D E F G
1 Insulation Width 15 in
2 Square Foot per Roll 40 sft
3
4 Rectangular Areas
5 Number 1 ea ea ea
6 Width/Height 8 ft ft ft
7 Length 90 ft ft ft
8 Area 720 sft - sft - sft
9 Triangular Areas
10 Number ea ea ea
11 Base ft ft ft
12 Height ft ft ft
13 Area - sft - sft - sft
14
15 Total Area 720 sft
16 Area of Insulation 675 sft
17 Rolls 17 ea

The following formulas need to be entered into the associ- Once these formulas have been entered, Cell B8 needs to be
ated cells: copied to Cells D8 and F8, and Cell B13 needs to be copied
to Cells D13 and F13.
Cell Formula The data for insulation is entered in Cells B1 and B2,
and the data for the insulated surface is entered in Cells B5
B8 =B5*B6*B7 through B7, D5 through D7, F5 through F7, B10 through
B13 =B10*B11*B12/2 B12, D10 through D12, and F10 through F12. The data
shown in the foregoing figure is from Example 9-6 and is
B15 =B8+D8+F8+B13+D13+F13
formatted using the comma style, which replaces zeros
B16 =B15*B1/(B1+1) with dashes.
B17 =ROUNDUP(B16/B2,0)

Blown insulation may be made from fiberglass, shred-


EXAMPLE 9-7
ded newspaper, or spun rock. Blown insulation is bid as a
quantity-from-quantity good using historical data or data How many bags of blown insulation are needed to insulate a
from the manufacturer on how many bags of insulation are 1,250-square foot ceiling with R-38 insulation? The manufac-
required to cover 1,000 square feet. The quantity takeoff for turer’s recommended coverage rate is 58 bags per 1,000 square
blown insulation is shown in the following example. feet.
140 CHAPTER NINE

FIGURE 9-5 Building End

Solution: The quantity is calculated as follows: Solution: The rise for the gable end is calculated as follows:

b ⫽ 73!bags Rise ⫽ a b a b ⫽ 5.33!ft


58!bags 32!ft 4
Bags ⫽ (1,250!ft2 )a 䊏
1,000!ft2
˛

˛
2 12
The height of the wall at the peak is 14 feet 4 inches. The number of
EXTERIOR INSULATION rows of insulation is calculated using Eq. (4-13) as follows:
FINISH SYSTEM 14.33!ft
NumberRows ⫽ ⫽ 2!rows
Exterior insulation finish system (EIFS) consists of a ridged 8!ft
insulation layer covered with a synthetic stucco system. The The number of columns of insulation is calculated using Eq. (4-16)
stucco system includes a base coat, a reinforcing layer, a as follows:
brown coat, and a colored finish coat. The insulation is bid
32!ft
as a sheet good using the same principles as for bidding NumberColumns ⫽ ⫽ 8!columns
4!ft
sheathing. The synthetic stucco system is bid as a quantity-
from-quantity good using historical data or coverage rates The first row of insulation will run from the bottom of the wall to a
from the manufacturer. Any specialty features, such as height of 8 feet and will consist of eight sheets of insulation. The sec-
raised areas or areas of a different color, need to be ac- ond row of insulation will run from a height of 8 feet to the top of
counted for. The quantity takeoff for EIFS is shown in the the wall, which is 1 foot at the eaves and 6 feet 4 inches at the peak.
Because the height at the eaves (1 ft) plus the height at the peak (6 ft
following example.
4 in) is less than 8 feet, the scrap from the short side of the gable end
can be used at the peak, allowing two pieces of insulation to be cut
EXAMPLE 9-8 from one sheet on the top row. Four sheets are required for the top
row. The layout of the insulation is shown in Figure 9-6. The num-
Determine the quantities of insulation, mesh reinforcement, and ber on each piece of insulation represents the sheet from which the
stucco needed to cover the end of the building shown in Figure 9-5. insulation was cut. A total of 12 sheets of insulation are needed.
The insulation comes in 4-foot by 8-foot sheets. The reinforcement The number of rows of reinforcement is calculated using Eq.
comes in rolls 100 feet long by 3 feet wide and needs to be lapped 3 (4-12) as follows:
inches. One cubic foot of base or brown coat will cover 75 square
feet of wall, and one bucket of finish coat will cover 130 square feet 14.33!ft
NumberRows ⫽ ⫽ 6!rows
of wall. (3!ft ⫺ 0.25!ft)

FIGURE 9-6 Insulation Layout


Thermal and Moisture Protection 141

The first row will run from the bottom of the wall to 3 feet high, the they are 5 inches narrower than a standard shingle and are
second row will run from 2 feet 9 inches to 5 feet 9 inches, the third entirely covered by the next row of shingles. For some shin-
row will run from 5 feet 6 inches to 8 feet 6 inches, the fourth row gle types, a special shingle is available for use as the starter
will run from 8 feet 3 inches to 11 feet 3 inches, the fifth row will row. Starter rows are required for all roof edges that are par-
run from 11 feet to 14 feet, and the last row will run from 13 feet 9
allel to the rows of shingles. The gable ends of gable roofs do
inches to 14 feet 4 inches. The first four rows will need to be 32 feet
not require a starter row; however, all the edges of a hip roof
wide. For the gable ends, the rows are 3 feet shorter on each end for
every foot above the point where the gable end begins to slope. The require a starter row. The quantity of shingles required for
fifth row, which is 2 feet above the point where the roof begins to the starter row is equal to the length of the edge multiplied
slope, will need to be 20 feet wide (32 ft - 2 ⫻ 2 ft ⫻ 3 ft/ft). The by the exposure of the shingle. This result is divided by 100
last row can be cut from the scraps. The length of reinforcement square feet to convert the quantity into squares. The quan-
needed is calculated as follows: tity of shingles is calculated using the following equation:
Length ⫽ 4(32!ft) ⫹ 1(20!ft) ⫽ 148!ft (Exposure)(Length)
SquaresStarter ⫽ (9-5)
(100!ft2/square)
˛˛

The number of rolls is calculated as follows:


148!ft The quantity of field shingles for a gable roof is equal to
Rolls ⫽ ⫽ 2!rolls the area of the roof in squares (100 ft2). When determining
(100!ft/roll)
the area of the roof, the estimator must take the slope of the
The area of the wall, exclusive of the windows, is calculated as follows:
roof into account as was done with sheathing. This is done
Area ⫽ (32!ft)(9!ft) ⫹ 0.5(32!ft)(5.33!ft) with the following equation:
⫺ 2(4!ft)(4!ft) ⫽ 341!ft2 (Length)(Width)(1 ⫹ Slope2 ) 0.5
SquaresField ⫽
˛

(9-6)
The quantity of the base coat is calculated using Eq. (4-20) as follows: (100 ft2/square)
341!ft2
Quantity ⫽ ⫽ 4.6!ft3 where
(75!ft2/ft3 )
Length ⫽ Length of the Roof in Plan View
The quantity of the brown coat is calculated using Eq. (4-20) as Width ⫽ Width of the Roof in Plan View
follows:
Slope ⫽ Rise/Run (4>12 for a 4:12 slope)
341!ft2
Quantity ⫽ ⫽ 4.6!ft3 Substituting the plan view area for length and width into
(75!ft2/ft3 )
Eq. (9-6), we get the following equation:
The quantity of the finish coat is calculated using Eq. (4-20) as
follows: (Area)(1 ⫹ Slope2 ) 0.5
SquaresField ⫽ (9-7)
(100!ft2/square)
341!ft2
Quantity ⫽ ⫽ 3!buckets
(130!ft2/bucket) The area of a hip roof is calculated using Eq. (9-6) or Eq.
(9-7) just as for the area of a gable roof. Although a hip roof
In addition, there are two trim pieces, which will require an addi-
tional bucket of finish coat that is a different color. 䊏
has the same area as a gable roof with the same slope and di-
mensions, the presence of hips and valleys increases the
amount of material needed to cover a roof because they are
SHINGLE ROOFS required to overlap at the hips and valleys. Therefore, a
Asphalt shingles are often specified by their expected life, building covered with a hip roof will require more materials
with 20-, 25-, and 30-year shingles being the most common. than the same building covered with a gabled roof with the
Asphalt shingles may be three-tab or architectural-grade same slope, even though the roof areas are the same. The
shingles. Flashings are required at all penetrations (such as added material needed for the hips and valleys in a hip roof
vent pipes) and where the roof intersects a wall or chimney. is approximated by the following equation:
Drip edge is required at all edges of the roof, including edges SquaresHip/Valley
on a gable end.
(1 ⫹ Slope2 ) 0.5
LengthHip/Valley c d (Exposure)
˛

Shingle roofs consist of underlayment (building paper


and Ice and Water Shield), a starter row of shingles located at 2
⫽ (9-8)
(100!ft2/square)
˛

the eaves of the roof, standard shingles placed over most of


the surface of the roof, and cap shingles placed on the hips
and ridges. The standard exposure for shingles is 5 inches, or where
in other words, the shingles are lapped so that the rows of
LengthHip/Valley ⫽ Length of the Hips and Valleys in
shingles are 5 inches apart. Shingles are bid by the square,
Plan View
which equals the number of shingles needed to cover 100
square feet of roofing. Cap shingles are shingles 1 foot wide and are used to
Starter rows of shingles consist of shingles with the area cover hips and ridges. The quantity of cap shingles is equal
of the shingle that is normally exposed cut off, and as a result to the length of the hips and ridges times the width (1 ft)
142 CHAPTER NINE

divided by 100 square feet to convert the quantity into The quantity of cap shingles needed for the hips is calculated using
squares. Ridges are horizontal and can be measured directly Eq. (9-10) as follows:
from the plans. The quantity of ridge shingles needed for a (91!ft)冤1 ⫹ (6>17) 2冥0.5 (1!ft)
ridge is calculated using the following equation: SquaresHip ⫽ ⫽ 0.97!square
(100!ft2/square)
(LengthRidge )(1!ft)
SquaresRidge ⫽ (9-9) The total number of squares is calculated as follows:
(100!ft2/square)
˛

Squares ⫽ 0.63!square ⫹ 15.74!squares ⫹ 0.30!square


Because hips are sloped, the slope of the hip must be ⫹ !0.12!square ⫹ 0.97!square
taken into account when calculating the quantity of shingles ⫽ 17.76!squares 䊏
needed for the hip and is calculated using the following
equation:
(LengthHip )(1 ⫹ Slope2Hip ) 0.5 (1!ft) EXCEL QUICK TIP 9-4
SquaresHip ⫽ 2
(9-10)
(100 ft /square) Roofing

where The calculation of the number of squares of shingles


needed for a roof is set up in a spreadsheet by entering the
LengthHip ⫽ Length of the Hip in Plan View
data and formatting the cells as follows:
SlopeHip ⫽ Rise/Run (4>17 for a 4:12 slope)
Note that the slope is divided by 17 rather than 12 because A B C
the slope of the hip rafter is flatter than the slope of the roof 1 Roof Length (Plan View) 44 ft
as discussed in Chapter 8. 2 Roof Width (Plan View) 32 ft
The amount of shingles needed is calculated by sum- 3 Slope 6 :12
ming the shingles needed for the starter row, the field, the 4 Shingle Exposure 5 in
waste at the hips and valleys, and the cap shingles placed on 5 Length of Starter Row 152 ft
the ridges and hips. The quantity takeoff for a hip roof is 6 Total Length of Hips/Valleys 91 ft
shown in the following example. 7 Total Length of Ridges 12 ft
8
9 Starter Strip 0.63 squ
EXAMPLE 9-9 10 Field Shingles 15.74 squ
Determine the number of squares of shingles needed for the hip 11 Hip/Valley Shingles 0.30 squ
roof shown in Figure 9-3. The shingles have a 5-inch exposure and 12 Ridge Cap Shingles 0.12 squ
the slope of the roof is 6:12. The cap and starter strip will be cut 13 Hip/Valley Cap Shingles 0.97 squ
from a standard shingle. 14 Total Shingles 17.76 squ

Solution: From Example 9-4, the length of the hips in plan view is
The following formulas need to be entered into the asso-
91 feet. The quantity of shingles needed for the starter row is calcu-
ciated cells:
lated using Eq. (9-5) as follows:
(5 in)(1 ft/12 in)(32 ft ⫹ 44 ft ⫹ 32 ft ⫹ 44 ft)
SquaresStarter ⫽ Cell Formula
(100 ft2/square)
˛

⫽ 0.63!square B9 =(B4/12)*B5/100
The quantity of shingles needed for the field is calculated using Eq. B10 =B1*B2*(1+(B3/12)^2)^0.5/100
(9-6) as follows: B11 =B6*((1+(B3/12)^2)/2)^0.5*(B4/12)/100
(44!ft)(32!ft)(1 ⫹ (6>12) ) 2 0.5
B12 =B7/100
SquaresField ⫽ ⫽ 15.74!squares
(100!ft2/square) B13 =B6*(1+(B3/17)^2)^0.5/100
The quantity of shingles needed for the hips is calculated using Eq. B14 =SUM(B9:B13)
(9-8) as follows:
(1 ⫹ (6>12) 2 ) 0.5
(91!ft) c d (5!in)(1!ft/12!in) The data for the roof is entered in Cells B1 and B7. The
2 data shown in the foregoing figure is from Example 9-9.
SquaresHip/Valley ⫽
(100!ft2/square)
˛

⫽ 0.30!square
The drip edge is bid as a linear component. When calcu-
The quantity of cap shingles needed for the ridge is calculated using
lating the lineal feet of drip edge needed for the roof, the
Eq. (9-9) as follows:
slope of the roof must be taken into account on all gable
(12)(1!ft) ends. This is done using Eq. (9-1). The calculation of the lin-
SquaresRidge ⫽ ⫽ 0.12!square
(100!ft2/square) eal feet of drip edge is shown in the following example.
Thermal and Moisture Protection 143

FIGURE 9-7 Roof Plan

measures the starter strip, outside corners, and the J-mold-


EXAMPLE 9-10
ing off the plans. The number of squares of siding needed
Determine the number of lineal feet of drip edge needed for the for rectangular areas is the area of the rectangular. For trian-
roof in Figure 9-7. The slope of the roof is 4:12. The drip edge gular and trapezoidal areas, additional siding needs to be
comes in 10-foot lengths and needs to be lapped 2 inches. added to the width of the area to account for waste at the
Solution: The length of the gable ends of the roof is calculated ends. This is done by the following equation:
using Eq. (9-1) as follows: LengthTop ⫹ LengthBottom
Area ⫽ ca b⫹ d Height
Exposure
4 2 0.5
LengthSloped ⫽ a b c 1 ⫹ a b d ⫽ 19!ft
36!ft
˛

2 Slope
2 12 (9-11)
The total length is calculated as follows: where
Length ⫽ 4(19!ft) ⫹ 2(44!ft) ⫽ 164!ft LengthTop ⫽ Length at the Top of the Area
LengthBottom ⫽ Length at the Bottom of the Area
The number of pieces of drip edge is calculated using Eq. (4-6) as
follows: Exposure ⫽ Exposure of the Siding
Slope ⫽ Slope (Rise/Run) of Triangular or Trapezoidal
164!ft
Number ⫽ ⫽ 17!each 䊏 Area (for example, 4>12)
冤10!ft ⫺ (2!in)(1!ft/12!in)冥
Height ⫽ Height of the Area
The siding is taken off by the square foot using the same
SIDING, SOFFIT, AND FASCIA procedures as for taking off shingles. Soffit and fascia are
Siding includes vinyl and aluminum siding, wood board sid- taken off using the same procedures as for taking off sheath-
ing, and wood sheet siding (such as T1-11). Let’s begin by ing for soffit and fascia (see Chapter 8).
looking at vinyl and aluminum siding. When the area of the openings, such as windows, is small
Vinyl and aluminum siding consists of a starter strip lo- they are often ignored. To deduct an opening, the number of
cated at the bottom of the wall; outside corner pieces on the rows of siding is calculated, and two rows are subtracted for
outside corners; J-molding around windows and doors, on the top and bottom of the opening. The number of rows is
the inside corners, and at the top of the wall; and long, nar- then multiplied by the width of the opening. The takeoff of
row siding panels. Aluminum soffit and fascia consists of an vinyl and aluminum siding is shown in the following example.
L-shaped piece of aluminum used for the fascia, a J-molding
located on the wall side of the soffit, and narrow soffit pan-
els, which may be vented or nonvented. The siding panels are EXAMPLE 9-11
designated by their width of coverage; for example, a 10-inch Determine the quantities of starter strip, outside corners, J-mold-
panel is wider than 10 inches because it includes the material ings, and 10-inch-wide siding needed to cover the end of the
that goes under the next panel, but it covers a 10-inch wide building shown in Figure 9-8. The starter strip, outside corners,
swath of wall. When performing the quantity takeoff, one and J-moldings are available in 10-foot lengths. The siding comes
144 CHAPTER NINE

FIGURE 9-8 Building End

in packages of 200 square feet. When calculating the siding, do not Divide the wall into two areas: a 32-foot-wide by 9-foot-high rec-
deduct the area of the windows. tangular area and a 32-foot-wide by 5.33-foot triangular area. The
area of the rectangular area is calculated as follows:
Solution: Four 10-foot lengths of starter strip and two 10-foot
lengths of outside corner are needed. J-molding is required around Area ⫽ (32!ft)(9!ft) ⫽ 288!ft2
the windows and at the top of the wall. The length of the J-molding
The siding has an exposure of 10 inches, or 0.833 ft. The triangular
at the top of the wall is calculated using Eq. (9-1) as follows:
area is calculated using Eq. (9-11) as follows:
4 2 0.5
LengthSloped ⫽ a b c 1 ⫹ a b d ⫽ 16.9!ft
32!ft
(0!ft ⫹ 32!ft)
Area ⫽ c d (5.33!ft) ⫽ 99!ft2
(0.833!ft)
2 12 ⫹
2 (4>12)
To minimize splicing, order two 10-foot lengths for each side of the
The total area is 387 square feet (288 ft2 + 99 ft2). The number of
roof and two 10-foot lengths for each window, for a total of eight
packages of siding is calculated as follows:
10-foot lengths. The rise for the gable end is calculated as follows:
387!ft2
Rise ⫽ a b a b ⫽ 5.33!ft
32!ft 4 Number ⫽ ⫽ 2!packages 䊏
2 12 (200!ft2/package)

EXCEL QUICK TIP 9-5


Siding
The calculation of the number of square feet of siding needed for a wall is set up in a spreadsheet by entering the data and
formatting the cells as follows:

A B C D E F G
1 Exposure 10 in
2 Slope 4 :12
3
4 Rectangular Areas
5 Number 1 ea ea ea
6 Width/Height 9.00 ft ft ft
7 Length 32.00 ft ft ft
8 Area 288 sft - sft - sft
9 Triangular Areas
10 Number 1 ea ea ea
11 Base 32.00 ft ft ft
12 Height 5.33 ft - ft - ft
13 Area 99 sft - sft - sft
14
15 Total Area 387 sft
Thermal and Moisture Protection 145

The following formulas need to be entered into the associ- Once these formulas have been entered, Cell B8 needs to be
ated cells: copied to Cells D8 and F8; Cell B12 needs to be copied to
Cells D12 and F12; and Cell B13 needs to be copied to Cells
Cell Formula D13 and F13.
The exposure for the siding is entered in Cell B1, the
B8 =B5*B6*B7
slope is entered into Cell B3, and the data for the wall is en-
B12 =(B11/2)*$B$2/12 tered in Cells B5 through B7, D5 through D7, F5 through
B13 =B10*(B11/2+$B$1/$B$2)*B12 F7, B10, B11, D10, D11, F10, and F11. The data shown in
the foregoing figure is from Example 9-11 and is formatted
B15 =B8+D8+F8+B13+D13+F13
using the comma style, which replaces zeros with dashes.

must be accounted for by determining the length of the


boards before their ends are cut to match the slope. The av-
erage length of the boards can be approximated by using the
following equation:
(LengthTop ⫹ LengthBottom ) Exposure
LengthAve ⫽ ˛ ⫹ ˛˛

2 Slope
(9-12)
where
LengthTop ⫽ Length at the Top of the Area
LengthBottom ⫽ Length at the Bottom of the Area
FIGURE 9-9 Board Siding Section
Exposure ⫽ Exposure of the Siding
Slope ⫽ Slope (Rise/Run) of Triangular or Trapezoidal
Board siding consists of wood boards (such as 1 ⫻ 8s) or en- Area (for example, 4>12)
gineered siding (such as Hardiplank) that are shipped Openings are handled in the same way as they were for
lapped on the side of the building. A section for wood board vinyl and aluminum siding. Soffit and fascia are taken off
siding is shown in Figure 9-9. using the same procedure as for taking off sheathing for sof-
Board siding requires a starter strip and wood trim on fit and fascia (see Chapter 8). The takeoff of wood board sid-
the corners, around the doors and windows, and at the tops ing is shown in the following example.
of the wall. When estimating wood board siding, the ends
are butt jointed and the sides of the board are lapped, greatly
reducing the coverage of the board. For example, a 1 ⫻ 8 EXAMPLE 9-12
board siding that is lapped 1 inch has an exposure of 6.25 Determine the quantities of starter strip, 1 ⫻ 4 trim, and 1 ⫻ 8
inches because the 1 ⫻ 8 is 7.25 inches wide and 1 inch is lost wood siding needed to cover the end of the building shown in
because of lapping. When performing the quantity takeoff, Figure 9-10. The siding is lapped 1 inch on the sides and the ends are
one measures the starter strip and trim off of the plans, as butt jointed. The starter strip and 1 ⫻ 4 trim are available in 8-, 10-,
discussed in Chapter 8. The siding is taken off as a sheet and 12-foot lengths. The siding comes in 12-foot lengths. When cal-
good. In dealing with triangular and trapezoidal areas waste culating the siding, do not deduct the area of the windows.

FIGURE 9-10 Building End


146 CHAPTER NINE

Solution: Four 8-foot lengths of starter strip are needed. The ex- taking off sheets of sheathing, and the soffit and fascia are
posure of the siding is 6.25 inches. The rise for the gable end is cal- taken off using the same procedures as for taking off sheath-
culated as follows: ing for soffit and fascia (see Chapter 8).

Rise ⫽ a b a b ⫽ 5.33!ft
32!ft 4
2 12
MEMBRANE ROOFING
The height at the peak of the gable end is 14.33 feet (9 ft + 5.33 ft).
The number of 32-foot-long rows needed for the rectangular area is
Membrane roofing consists of a single-ply polyvinyl chloride
calculated using Eq. (4-12) as follows: (PVC), ethylene propylene diene monomer (EPDM), or
other type of membrane that is used to cover a roof.
(9!ft)(12!in/ft) Membrane roofing comes in sheets or rolls; for example, a
NumberRows ⫽ ⫽ 18!rows
(7.25!in ⫺ 1!in) PVC membrane is available in 75-foot-wide by 300-foot-
The number of columns is calculated using Eq. (4-16) as follows: long sheets folded up on a pallet. The sheets must be glued
or welded together to form a single membrane. The mem-
32!ft
NumberColumns ⫽ ⫽ 2.67!columns brane must be fastened at the edges of the roof using a bat-
12!ft ten strip and flashing to prevent water from getting between
The number of pieces of siding needed for the rectangular area is the membrane and the wall. The membrane must be fas-
calculated using Eq. (4-18) as follows: tened to the roof deck or held in place with rock ballast.
Flashings are required on all penetrations. The membrane is
Number ⫽ (18!rows)(2.67!columns) ⫽ 48!each
taken off as a sheet or roll good, and the batten strip is taken
The average length of each of the rows in the triangular area is cal- off as a linear good. The takeoff of membrane roofing is
culated using Eq. (9-12) as follows: shown in the following example.
(0!ft ⫹ 32!ft) (7.25!in ⫺ 1!in)(1!ft/12!in)
LengthAve ⫽ ⫹
2 (4>12)
EXAMPLE 9-13
⫽ 17.6!ft
Determine the number of 25-foot-wide by 100-foot-long sheets of
The number of rows needed for the entire end is calculated using
membrane roofing needed for a roof 110 feet wide by 210 feet long.
Eq. (4-12) as follows:
Allow 3 feet at the perimeter of the roof for the membrane to be at-
(14.33!ft)(12!in/ft) tached to the parapet wall. The roofing must be lapped 3 inches at
NumberRows ⫽ ⫽ 28!rows the sides and ends.
(7.25!in ⫺ 1!in)
Therefore, 10 rows (28 - 18) of siding are needed for the gable end. Solution: The membrane needs to cover an area 116 feet (110 ft +
The average number of columns is calculated using Eq. (4-16) as 2 ⫻ 3 ft) wide by 216 feet (210 ft + 2 ⫻ 3 ft) long. The number of
follows: rows needed for the roof is calculated using Eq. (4-12) as follows:

17.6!ft 116!ft
NumberColumns ⫽ ⫽ 1.47!columns NumberRows ⫽ ⫽ 5!rows
12!ft 冤25!ft ⫺ 3!in(1!ft>12!in)冥

The number of pieces of siding needed for the triangular area is cal- The number of columns is calculated using Eq. (4-15) as follows:
culated using Eq. (4-18) as follows: 216!ft
NumberColumns ⫽ ⫽ 2.2!columns
Number ⫽ (10!rows) (1.47!columns) ⫽ 15!each 冤100!ft ⫺ 3!in(1!ft>12!in)冥
Order sixty-three (48 + 15) 12-foot-long 1 ⫻ 8s. Two 10-foot The number of sheets of roofing needed is calculated using Eq. (4-18)
lengths of 1 ⫻ 4s are needed for the corners. A 4-foot 7-inch piece as follows:
of trim is needed for the top of the window, two 4-foot 3.5-inch
Number ⫽ (5!rows)(2.2!columns) ⫽ 11!sheets
pieces of trim are needed for the sides of the windows, and a 4-foot
piece of trim is needed for the bottom of the window. Order
three 10-foot and one 8-foot lengths of 1 ⫻ 4s for the windows.
The length of the top of the wall is calculated using Eq. (9-1) as SAMPLE TAKEOFF FOR THE
follows: RESIDENTIAL GARAGE
4 2 0.5
LengthSloped ⫽ a b c 1 ⫹ a b d ⫽ 16.9!ft
32!ft A sample takeoff for insulation, wood siding, and roofing
2 12 from a set of plans is shown in the following example.
Order an 8-foot length and a 10-foot length for each side of the
roof. A total of seven 10-foot lengths and three 8-foot lengths of
EXAMPLE 9-14
1 ⫻ 4s are needed. 䊏
Determine the insulation, wood siding (including trim), and roof-
Sheets of wood siding require wood trim on the corners, ing (including underlayment) needed to complete the residential
garage given in Appendix F.
around the windows and doors, and at the top of the wall. In
performing the quantity takeoff, trim is measured off of the Solution: From Example 8-21 there is 83 feet of 8-foot-high wall.
plans, the siding is taken off using the same procedure as for There is also 16 feet of 2-foot-high wall above the garage door, but
Thermal and Moisture Protection 147

only 1 foot can be insulated. For the 8-foot-high wall, there is one The number of rows of T1-11 needed for the 8-foot-high walls is
8-foot-high row of insulation. The number of columns is calcu- one, and the number of columns is calculated using Eq. (4-16) as
lated using Eq. (4-17) as follows: follows:
(83!ft)(12!in/ft) 83!ft
NumberColumns ⫽ ⫽ 63!columns NumberColumns ⫽ ⫽ 21!columns
(15!in ⫹ 1!in) 4!ft

The number of 1-foot-high columns needed above the garage is Twenty-one sheets are needed for the 8-foot-high wall. Four 2-foot-
calculated using Eq. (4-17) as follows: high by 4-foot-wide sheets are needed above the garage door and
can be cut from one sheet of T1-11. The number of columns on a
(16!ft)(12!in/ft) gable end is calculated using Eq. (4-16) as follows:
NumberColumns ⫽ ⫽ 12!columns
(15!in ⫹ 1!in)
24!ft
Two columns of insulation 7 feet high (the height of the door and NumberColumns ⫽ ⫽ 6!columns
4!ft
header) can be deducted for the single-hung door. The area of insu-
lation can be calculated as follows: The three columns on each side of the peak can be cut from one
sheet; thus, four sheets are required. A total of 26 sheets (21 + 1 + 4)
Area ⫽ 冤63(8 ft) ⫹ 12(1 ft) ⫺ 2(7 ft)冥(15 in)(1 ft> 12 in) ⫽ 628 ft2
˛ ˛
of T1-11 are needed.
The number of rolls is calculated as follows: Next, the T1-11 for the soffit will be calculated. The soffit is
18 inches wide. Determine the length of the soffit, making sure
628!ft2 that the corners are not double counted. The sloped length of the
Number ⫽ ⫽ 16!rolls roof from the eave to the ridge is calculated using Eq. (9-1) as
(40!ft2/roll)
follows:
A vapor barrier is needed on the unfaced insulation. Use 8-foot by
4 2 0.5
LengthSloped ⫽ a b c 1 ⫹ a b d ⫽ 14.2!ft
12-foot sheets of 3-mil-thick plastic. One 8-foot-high row is 27!ft
needed. The number of columns is calculated using Eq. (4-16) as 2 12
follows:
The length of the soffit is calculated as follows:
83!ft Length ⫽ 4(14.2!ft) ⫹ 2(26!ft) ⫽ 109!ft
NumberColumns ⫽ ⫽ 7!columns
12!ft
Five 18-inch-wide by 4-foot-long pieces of soffit can be cut from
Seven sheets are needed for the walls, and one additional sheet is one sheet of T1-11. The number of sheets is calculated as follows:
needed above the garage door.
The area of the ceiling to be insulated is 26 feet wide by 24 feet 109!ft
Number ⫽ ⫽ 6!sheets
long, or 624 square feet. The insulation comes in 32-foot-long rolls. (5 ⫻ 4!ft)
The number of rows is calculated using Eq. (4-13) as follows:
The area of the soffit is calculated as follows:
24!ft
NumberRows ⫽ ⫽ 0.75!row Area ⫽ (1.5!ft)(109!ft) ⫽ 164!ft2
32!ft
In addition, 58 feet (2 ⫻ 29 ft) of 3-inch-wide screen and two 12-
The number of columns is calculated using Eq. (4-17) as follows: inch-wide by 14-inch-high vents are needed.
(26!ft)(12!in/ft) The amount of 1 ⫻ 4 cedar trim needed, along with its use, is
NumberColumns ⫽ ⫽ 13!columns shown in Table 9-2. The sloped trim will be cut in the field. The
(23!in ⫹ 1!in)
trim will be ordered in 8-, 10-, and 12-foot lengths.
The number of rolls of insulation needed for the ceiling is calcu- The total length of sloped trim that needs to be cut and in-
lated using Eq. (4-18) as follows: stalled is as follows:
Number ⫽ (0.75!row)(13!columns) ⫽ 10!rolls Length ⫽ 4!ft ⫹ 17!ft ⫹ 2(24!ft) ⫹ 2(2!ft) ⫹ 2(1!ft) ⫽ 75!ft
The area of insulation is calculated as follows: The total length of unsloped trim that needs to be installed is as
follows:
Area ⫽ (13!columns)(23!in)(1!ft/12!in)(24!ft) ⫽ 598!ft 2

Length ⫽ 8(9!ft) ⫹ 2(7!ft) ⫹ 2(7!ft) ⫹ 2(26!ft) ⫹ 4(13!ft) ⫹ 4(2!ft)


Next, determine the number of sheets of T1-11 siding needed for
the garage. The siding will be broken down into three areas: the ⫽ 212!ft
8-foot-high walls, the 2-foot-high wall above the garage door, and The perimeter of the roof is calculated as follows:
the gable ends. From Example 8-21 there is 83 feet of 8-foot-high
wall. The rise for the gable end is calculated as follows: Perimeter ⫽ 4(14.2!ft) ⫹ 2(29!ft) ⫽ 115!ft
The area of the roof is calculated as follows:
Rise ⫽ a b a b ⫽ 4!ft
24!ft 4
2 12 Area ⫽ 2(14.2!ft)(29!ft) ⫽ 824!ft2
The area of siding needed to be installed is as follows: Determine the number of pieces of 10-foot-long drip edge, allow-
Area ⫽ Area8-Foot Walls ⫹ AreaAbove Garage Door ⫹ 2(AreaGable End ) ing 0.2 foot for lap, using Eq. (4-6) as follows:

b ⫽ 792!ft2
(4!ft)(24!ft) 115!ft
⫽ (8!ft)(83!ft) ⫹ (2!ft)(16!ft) ⫹ 2a Number ⫽ ⫽ 12!ea
2 (10.0!ft ⫺ 0.2!ft)
148 CHAPTER NINE

TABLE 9-2 1 ⴛ 4 Cedar Trim


Actual Order

Quantity Length Quantity Length


Use (ea) (ft) (ea) (ft) Sloped

Corners 8 9 8 10 No
Single-hung door (sides) 2 7 2 8 No
Single-hung door (top) 1 4 0.5 8 Yes
Overhead door (sides) 2 7 2 8 No
Overhead door (top) 1 17 1 8 Yes
1 10
Top of side walls 2 26 4 8 No
2 10
Top of end walls 4 13 4 8 No
2 10
Gable ends at seam 2 24 4 12 Yes
Vents (tops) 2 2 0.5 8 Yes
Vents (sides) 4 2 1 8 No
Vents (bottoms) 2 1 0.5 8 Yes

Determine the number of rolls of 15-pound felt. The number of TABLE 9-3 Quantities for Residential Garage
rows per side is calculated using Eq. (4-12) as follows: 07-200 Insulation
14.2!ft
NumberRows ⫽ ⫽ 5.7!rows R-13 15 – ⫻ 32 ¿ unfaced 16 ea
(3!ft ⫺ 0.5!ft)
3-mil plastic 8 ¿ ⫻ 12¿ 8 ea
Round to 6 rows, and use the extra to lap at the ridge, thus elimi-
Install R-13 insulation 628 sft
nating the need for a row at the ridge. The area of felt needed for
the roof is calculated as follows: R-25 23 – ⫻ 32 ¿ unfaced 10 ea
Area ⫽ (29!ft)(2!sides)(6!rows/side)(3!ft/row) ⫽ 1,044!ft2 Install R-25 insulation 598 sft

The number of rolls of felt is calculated as follows: 07-400 Siding


1,044!ft2 T1-11 26 ea
Rolls ⫽ ⫽ 3!rolls
(400!ft2/roll)
Install siding 792 sft
The quantity of shingles needed for the starter row is calculated T1-11 soffit 6 ea
using Eq. (9-5) as follows:
Install soffit 164 sft
(5!in)(1!ft/12!in)(29!ft ⫹ 29!ft)
SquaresStarter ⫽ ⫽ 0.24!square 3 – -wide screen 58 ft
˛

(100!ft2/square)
12 – ⫻ 14 – vent 2 ea
The quantity of shingles needed for the field is equal to the area of
1 ⫻ 4 cedar 8¿ 16 ea
the roof, which is 824 square feet, or 8.24 squares. The quantity of
cap shingles needed for the ridge is calculated using Eq. (9-9) as 1 ⫻ 4 cedar 10¿ 13 ea
follows: 1 ⫻ 4 cedar 12¿ 4 ea
(29)(1!ft) Cut and install trim 75 ft
SquaresRidge ⫽ ⫽ 0.29!square
(100!ft2/square) Install trim 212 ft
The total number of squares is calculated as follows:
07-500 Roofing
Squares ⫽ 0.24!square ⫹ 8.24!squares ⫹ 0.29!square
⫽ 8.77!squares Drip edge 10¿ 12 ea
15-lb felt, 4-square roll 3 ea
Each bundle of shingles is 1/3 square. Round to 9 squares. Twenty-
seven (3 ⫻ 9) bundles of shingles are needed. 20-yr three-tab shingles 9 sq
The quantities needed for the garage, grouped by the cost Install roofing 824 sft
codes in Appendix B, are shown in Table 9-3. 䊏
Thermal and Moisture Protection 149

CONCLUSION the ends. The felt is available in rolls 3 feet wide with 4
squares (400 square feet) per roll. The slope on the roof
Thermal and moisture protection includes exterior finishes is 6:12.
(such as siding, stucco, and roofing) that protect the building 4. Determine the number of rolls of 30-pound asphalt-
against moisture infiltration, and insulation that protects the impregnated felt needed for the roof in Figure 9-12. The
building against heat loss. Many of the components used for felt is to be lapped 6 inches on the side and 12 inches on
thermal and moisture protection are bid as a sheet or roll the ends. The felt is available in rolls 3 feet wide with 2
good. squares (200 square feet) per roll. The slope on the roof
is 4:12.
PROBLEMS 5. How many square feet of wall insulation are needed to
insulate 25 feet of an 8-foot-high wall? The stud spacing
1. How much waterproofing is needed to cover the foun- is 16 inches on center.
dation walls of a 24-foot by 50-foot basement? The wall 6. How many rolls of insulation are needed for Problem 5
is 8 feet high. The wall sits on a footing that is 12 inches if the insulation comes in rolls 15 inches wide and 32
high and extends 16 inches beyond the wall on the exte- feet long? Do not include a waste factor.
rior side. Assume that the waterproofing starts 12 inches
7. How many square feet of wall insulation are needed to
below the top of the foundation wall and covers the top
insulate 175 feet of a 10-foot-high wall? The stud spac-
surface of the footings. If one gallon of waterproofing
ing is 24 inches on center.
material covers 75 square feet, how many gallons of wa-
terproofing material are needed? 8. How many rolls of insulation are needed for Problem
7 if the insulation comes in rolls 23 inches wide and
2. How much waterproofing is needed to cover the foun-
32 feet long? Do not include a waste factor.
dation walls of a 32-foot by 48-foot basement? The wall
is 8 feet high. The wall sits on a footing that is 12 inches 9. How many bags of blown insulation are needed to in-
high and extends 12 inches beyond the wall on the exte- sulate a 1,835-square-foot ceiling with R-30 insula-
rior side. Assume that the waterproofing starts 24 inches tion? The manufacturer’s recommended coverage rate
below the top of the foundation wall and covers the top is 41 bags per 1,000 square feet.
surface of the footings. If one gallon of waterproofing 10. How many bags of blown insulation are needed to in-
material covers 90 square feet, how many gallons of wa- sulate a 1,120-square-foot ceiling with R-25 insula-
terproofing material are needed? tion? The manufacturer’s recommended coverage rate
3. Determine the number of rolls of 15-pound asphalt- is 34 bags per 1,000 square feet
impregnated felt needed for the roof in Figure 9-11. The 11. Determine the quantities of insulation, mesh reinforce-
felt is to be lapped 6 inches on the side and 12 inches on ment, and stucco needed to cover the end of the building

FIGURE 9-11 Roof Plan


150 CHAPTER NINE

FIGURE 9-12 Roof Plan

shown in Figure 9-13. The insulation comes in 4-foot by 15. How many pieces of drip edge are needed for Problem
8-foot sheets. The reinforcement comes in rolls 100 feet 14 if the drip edge comes in 10-foot lengths and needs
long by 3 feet wide and needs to be lapped 3 inches. One to be lapped 2 inches?
cubic foot of base or brown coat will cover 75 square 16. How many squares of roofing are required to cover the
feet of wall, and one bucket of finish coat will cover building in Figure 9-12? The shingles have a 5-inch ex-
130 square feet of wall. posure, and the slope on the roof is 4:12. The cap and
12. Determine the quantities of insulation, mesh rein- starter strip will be cut from a standard shingle.
forcement, and stucco needed to cover the end of the 17. Drip edge is to be installed around the entire perimeter
building shown in Figure 9-14. The insulation comes of the roof in Figure 9-12. How many feet of drip edge
in 4-foot by 8-foot sheets. The reinforcement comes in are needed for the roof?
rolls 100 feet long by 3 feet wide and needs to be lapped 18. How many pieces of drip edge are needed for Problem
3 inches. One cubic foot of base or brown coat will cover 17 if the drip edge comes in 10-foot lengths and needs
60 square feet of wall, and one bucket of finish coat will to be lapped 2 inches?
cover 120 square feet of wall.
19. Determine the quantities of starter strip, outside cor-
13. How many squares of roofing are required to cover the ners, J-moldings, and 10-inch-wide vinyl siding needed
building in Figure 9-11? The shingles have a 5-inch ex- to cover the end of the building shown in Figure 9-15.
posure, and the slope on the roof is 6:12. The cap and The starter strip, outside corners, and J-moldings are
starter strip will be cut from a standard shingle. available in 10-foot lengths. The siding comes in pack-
14. Drip edge is to be installed around the entire perimeter ages of 200 square feet. When calculating the siding, do
of the roof in Figure 9-11. How many feet of drip edge not deduct the area of the windows.
are needed for the roof?

FIGURE 9-13 Building End


Thermal and Moisture Protection 151

FIGURE 9-14 Building End

FIGURE 9-15 Building End

20. Determine the quantities of starter strip, outside cor- building shown in Figure 9-17. The siding is lapped 1
ners, J-moldings, and 10-inch-wide vinyl siding needed inch on the sides and butt jointed on the ends. The
to cover the end of the building shown in Figure 9-16. starter strip and 1 ⫻ 4 trim are available in 8-, 10-, and
The starter strip, outside corners, and J-moldings are 12-foot lengths. The siding comes in 12-foot lengths.
available in 10-foot lengths. The siding comes in pack- When calculating the siding, do not deduct the area of
ages of 200 square feet. When calculating the siding, do the windows.
not deduct the area of the windows and doors. 22. Determine the quantities of starter strip, 1 ⫻ 4 trim,
21. Determine the quantities of starter strip, 1 ⫻ 4 trim, and 1 ⫻ 8 wood siding needed to cover the end of the
and 1 ⫻ 8 wood siding needed to cover the end of the building shown in Figure 9-18. The siding is lapped

FIGURE 9-16 Building End


152 CHAPTER NINE

FIGURE 9-17 Building End

FIGURE 9-18 Building End

1 inch on the sides and butt jointed on the ends. The 29. Determine the insulation needed to complete the West
starter strip and 1 ⫻ 4 trim are available in 8-, 10-, and Street Video project given in Appendix F.
12-foot lengths. The siding comes in 12-foot lengths. 30. Determine the membrane roofing and sheet metal
When calculating the siding, do not deduct the area of needed to complete the West Street Video project given
the windows and door. in Appendix F.
23. Determine the number of 15-foot-wide by 200-foot- 31. Set up Excel Quick Tip 9-1 in Excel.
long sheets of membrane roofing needed for a roof 80 32. Set up Excel Quick Tip 9-2 in Excel.
feet wide by 90 feet long. Allow 3 feet per side at the
33. Set up Excel Quick Tip 9-3 in Excel.
perimeter of the roof for the membrane to be attached
to the parapet wall. The roofing must be lapped 3 inches 34. Set up Excel Quick Tip 9-4 in Excel.
at the sides and ends. 35. Set up Excel Quick Tip 9-5 in Excel.
24. Determine the number of 25-foot-wide by 75-foot-long 36. Modify Excel Quick Tip 9-1 to allow the wall lengths
sheets of membrane roofing needed for a roof 300 feet and wall height to be entered in feet and inches.
wide by 400 feet long. Allow 4 feet per side at the 37. Modify Excel Quick Tip 9-2 to allow the roof length and
perimeter of the roof for the membrane to be attached width to be entered in feet and inches.
to the parapet wall. The roofing must be lapped 6 inches 38. Modify Excel Quick Tip 9-4 to allow the length and
at the sides and ends. width to be entered in feet and inches.
25. Determine the insulation needed to complete the
Johnson Residence given in Appendix F.
26. Determine the vinyl siding, soffit, and fascia needed to
complete the Johnson Residence given in Appendix F. REFERENCES
27. Determine the stucco needed to complete the Johnson 1. International Building Code, International Code Counsel,
Residence given in Appendix F. 2009, Section 1507.2.8.
28. Determine the roofing, including underlayment, needed 2. International Building Code, International Code Counsel,
to complete the Johnson Residence given in Appendix F. 2009, Section 1507.2.8.2.
CHAPTER TEN

OPENINGS

In this chapter you will learn how to apply the principles in The right-hand reverse and left-hand reverse swings are
Chapter 4 to residential doors and windows, hollow metal used for exterior doors that swing out. The right-hand and
doors, overhead doors, storefronts, and hardware. This chapter left-hand swings are used for all interior doors and exterior
includes example takeoffs from the residential garage drawings. doors that swing in. Residential sliding glass doors are pro-
vided by the window supplier and are included as windows.
Commercial glass doors are a part of commercial store-

O
fronts and are discussed under storefronts.
penings consist of the doors, frames, glazing, and
Doors are bid as a counted item. When bidding doors
hardware to cover openings in both the interior
the estimator locates the door on the floor plan and uses the
and exterior walls of buildings. Let’s begin by
symbol next to the door along with the door schedule to de-
looking at doors.
termine the size and type of door needed for the opening. In
addition, the estimator should identify any holes that need
DOORS to be predrilled or mortised in the door for the hardware and
the size of the doorjambs. The estimating of doors is shown
Doors include residential prehung doors and commercial in the following example.
wood and hollow metal doors. Most often doors are marked
with a numbered symbol that relates to a door schedule
found in the plans. In this book, the doors are marked with EXAMPLE 10-1
numbers inside a hexagon (a six-sided polygon). Each door
Using the door schedule in Figure 10-3, determine the number,
may have its own unique identification, or each type of size, and type of doors needed to complete the building shown in
door may have its own unique identification. Doors come Figure 10-2.
in four standard swings, which are shown in Figure 10-1.
Solution: The following prehung doors are needed: one right-
hand 6-foot 8-inch-high by 3-foot-wide by 1 3>8-inch-thick solid-
core wood exterior door, one right-hand 6-foot 8-inch-high by
2-foot 8-inch-wide by 1 3>8-inch-thick hollow-core birch interior
door, one left-hand 6-foot 8-inch-high by 2-foot 8-inch-wide by
1 3>8-inch-thick hollow-core birch interior door, and two pairs of
6-foot 8-inch-high by 2-foot wide by 1 3>8-inch-thick hollow-core
birch interior bifold doors. The prehung doors have 4 5>8-inch
jambs. The holes that need to be drilled in the doors are discussed
in Example 10-6 where hardware is discussed. 䊏

WINDOWS
Windows include windows and sliding glass doors. Most
often windows are marked with a numbered or lettered sym-
bol that relates to a window schedule or a set of window
FIGURE 10-1 Standard Door Swings drawings found in the plans. In this book, the windows are
153
154 CHAPTER TEN

FIGURE 10-2 Floor Plan

FIGURE 10-3 Door Schedule

marked with a number inside a triangle. Each window may


EXAMPLE 10-2
have its own unique identification, or each type of window
may have its own unique identification. When bidding slid- Using the window schedule in Figure 10-4, determine the number,
ing windows the estimator must note which panels are fixed size, and type of windows needed to complete the building shown
and which panels are operable. The estimator must also in Figure 10-2.
identify any windows that require safety glazing (tempered Solution: The following windows are needed: one 4-foot-high by
glass). With glass placed in hollow metal window frames, the 4-foot-wide sliding window with the left panel fixed and the right
frames are bid with the hollow metal doors and the glass is panel operable, one 4-foot-high by 4-foot-wide sliding window
included as part of glazing.
Windows are bid as a counted item. When bidding win-
dows, the estimator locates the window on the floor plan and
uses the symbol next to the window along with the window
schedule or drawings to determine the size and type of win-
dow needed for the opening. The estimating of windows is
shown in the following example. FIGURE 10-4 Window Schedule
Openings 155

FIGURE 10-5 Storefront Elevation FIGURE 10-6 Hardware Schedule

with the right panel fixed and the left panel operable, and one 4-
foot-high by 6-foot-wide sliding window with the center panel EXAMPLE 10-3
fixed and the right and left panels operable. 䊏 Determine the square footage of storefront and hardware needed to
construct the storefront in Figure 10-5 using the hardware schedule
shown in Figure 10-6.
COMMERCIAL STOREFRONT
Solution: The area of the storefront is 112.5 square feet (9 ft ⫻
Commercial storefront is a glass wall that is made up of glass 12.5 ft). The hardware needed is 1 1>2 pairs (3 each) of hinges, a
together with metal tubing (commonly aluminum) and may single-keyed lock with the cylinder being provided by the hardware
include doors. It is commonly used at the front of retail stores, supplier, panic hardware, one set (17 ft) of weather stripping, one
hence the name commercial storefront. Commercial store- 3-foot-wide threshold, and one floor-mounted doorstop. 䊏
front is provided by the glazing contractor, who provides the
glass, metal tubing, and hardware (except for the cylinder) for Glazing contractors should bid the storefront based on the
the doors. A cylinder to match the rest of the hardware is pro- necessary components required to fabricate the storefront.
vided by the hardware supplier for the storefront doors. When bidding storefront based on the necessary components
Often, commercial storefront is bid based on the square required to fabricate the storefront, the estimator often uses
footage of the storefront and the hardware is bid as a nominal dimensions for the storefront and glazing and then
counted item. The estimating of storefront using the square- verifies the required sizes by field measuring the opening. The
footage method is shown in the following example. different components of a storefront are shown in Figure 10-7.

FIGURE 10-7 Storefront


156 CHAPTER TEN

TABLE 10-1 Metal Tubing Required TABLE 10-2 Glazing Required

Quantity Item Notes Quantity Item


18 ft Jamb Left and right ends 3 ea 2-0 ⫻ 3-0 glass
12 ft 6 in Head Top 1 ea 4-0 ⫻ 3-0 glass
9 ft 6 in Sill Bottom, except at door 1 ea 4-0 ⫻ 3-0 tempered glass
14 ft Door mullion Left and right sides of door 1 ea 3-0 ⫻ 3-0 glass
3 ft Transom profile Above door 1 ea 3-0 ⫻ 3-0 tempered glass
32 ft Intermediate mullion All other locations 1 ea 7-0 ⫻ 3-0 tempered glass door
1 ea 2-0 ⫻ 3-6 glass
1 ea 4-0 ⫻ 3-6 tempered glass
The estimator must also identify any glazing that requires 1 ea 3-0 ⫻ 3-6 tempered glass
safety glazing (tempered glass). The rules for safety glass are
found in Section 2406 of the International Building Code.1
Estimating commercial storefront by the components GLAZING
needed to fabricate the storefront is shown in the following
example. Glazing includes installing glass in wood and hollow metal
frames. Glazing is bid as a counted item. The estimator
often uses nominal dimensions for the glazing when bid-
EXAMPLE 10-4 ding and then verifies the required sizes with the frame
manufacturer or by field measuring the frame. The estima-
Determine the components and hardware needed to fabricate the
tor must also identify any windows that require safety glaz-
storefront in Figure 10-5 using the hardware schedule shown in
ing (tempered glass). Estimating glazing is shown in the
Figure 10-6. The glass in the door and the two panels on either side
of the door needs to be tempered glass. following example.

Solution: The metal tubing needed for the door is shown in


Table 10-1, and the glazing needed is shown in Table 10-2.
EXAMPLE 10-5
The hardware needed is 1 1>2 pairs (3 each) of hinges, a sin-
gle-keyed lock with the cylinder being provided by the hardware Determine the glazing needed for the transom and sidelight shown
supplier, panic hardware, one set (17 ft) of weather stripping, one in Figure 10-8. The two panels on the side of the door need to be
3-foot-wide threshold, and one floor-mounted doorstop. 䊏 tempered glass. Use nominal dimensions.

FIGURE 10-8 Door Elevation


Openings 157

FIGURE 10-9 Hardware Schedule

Solution: The following panels of glass are needed: one 1 foot


10 inches high by 3 feet 3 inches wide, one 1 foot 10 inches high by EXAMPLE 10-7
3 feet wide, one 4 feet 2 inches high by 3 feet wide tempered, and Determine the doors, overhead doors, and hardware needed to
one 3 feet high by 3 feet wide tempered. 䊏 complete the residential garage given in Appendix F.
Solution: The garage needs one 3-foot by 6-foot 8-inch, six-
panel metal exterior prehung door with 4 5>8-inch wood jambs
HARDWARE and 1 1>2 pairs of hinges drilled for the deadbolt and lockset. A
prehung exterior door includes the hinges, weather stripping, and
Hardware is taken off as a counted item and includes threshold.
hinges (butts), locksets, cylinders, silencers, doorstops, To complete the hardware for the door, one single-keyed dead-
thresholds, weather stripping, closers, and panic hardware. bolt, one keyed lockset, and one floor-mounted doorstop are needed.
The hardware group for each door is shown on the door The garage needs one 16-foot by 7-foot prefinished, insulated,
schedule, and the hardware items included in each hard- sectional overhead door with one screw-drive opener, two remotes,
ware group is shown on the plans by the door schedule or and one keyless entry.
in the specifications. Frequently, some of the hardware The quantities needed for the garage, grouped by the cost
codes in Appendix B, are shown in Table 10-3. 䊏
comes with the doors. For example, a prehung exterior
residential door includes the frame, the hinges, the
weather stripping, and the threshold. Hardware that
comes with the door is not included in the hardware take-
off because it has already been included in the quantity TABLE 10-3 Quantities for Residential Garage
takeoff with the door. Estimating hardware is shown in the
following example. 08-100 Metal Doors

3-0 ⫻ 6-8, six-panel metal prehung door with


EXAMPLE 10-6 4 5>8 wood jambs, 1 1>2 pairs of hinges,
Using the hardware schedule shown in Figure 10-9, determine the weather stripping, and threshold, drilled for
hardware needed for the doors in Figures 10-2 and 10-3. deadbolt and lockset 1 ea

Solution: The hinges, weather stripping, and threshold come with 08-300 Overhead Doors
the prehung doors. One single-keyed deadbolt, one key lockset, and
one wall-mounted doorstop are needed for Door 1. Door 1 should 16-ft ⫻ 7-ft prefinished, insulated, sectional
be ordered predrilled for the deadbolt and lockset; otherwise, they overhead door 1 ea
will have to be drilled in the field. Two privacy locksets and two
wall-mounted doorstops are needed for Doors 2 and 3. These doors 1>2-hp screw-drive opener 1 ea
should be predrilled for a lockset. Four brass pulls are needed for Keyless entry 1 ea
Doors 4 and 5. 䊏 Remotes 2 ea

08-700 Hardware
SAMPLE TAKEOFF FOR THE Single-keyed deadbolt 1 ea
RESIDENTIAL GARAGE Keyed lockset 1 ea
A sample takeoff from a set of plans is shown in the follow- Floor-mounted doorstop 1 ea
ing example:
158 CHAPTER TEN

FIGURE 10-10 Floor Plan

CONCLUSION 2. Using the door schedule in Figure 10-13, determine the


number, size, and type of doors needed to complete the
Doors and windows consist of the doors, frames, glazing, building shown in Figure 10-12.
and hardware to cover the opening in both the interior and 3. Using the window schedule in Figure 10-14, determine
exterior walls of buildings. These items are bid as counted the number, size, and type of windows needed to com-
items, with the exception of storefront, which is bid by the plete the building shown in Figure 10-10.
square foot or lineal foot for the tubing.
4. Using the window schedule in Figure 10-15, determine
the number, size, and type of windows needed to com-
plete the building shown in Figure 10-12.
PROBLEMS 5. Determine the square footage of storefront needed to
1. Using the door schedule in Figure 10-11, determine the construct the storefront in Figure 10-16.
number, size, and type of doors needed to complete the 6. Determine the square footage of storefront needed to
building shown in Figure 10-10. construct the storefront in Figure 10-17.

FIGURE 10-11 Door Schedule


Openings 159

FIGURE 10-12 Floor Plan

FIGURE 10-13 Door Schedule

FIGURE 10-14 Window Schedule FIGURE 10-15 Window Schedule


160 CHAPTER TEN

FIGURE 10-16 Storefront Elevation

FIGURE 10-17 Storefront Elevation

7. Determine the metal tubing needed to fabricate the 14. Using the hardware schedule shown in Figure 10-9, de-
storefront in Figure 10-16. termine the hardware needed for the doors in Figures
8. Determine the glazing needed to fabricate the storefront 10-12 and 10-13.
in Figure 10-16. The glass in the door and the two pan- 15. Determine the doors needed to complete the Johnson
els on either side of the door needs to be tempered glass. Residence given in Appendix F.
Use nominal dimensions.
9. Determine the metal tubing needed to fabricate the
storefront in Figure 10-17.
10. Determine the glazing needed to fabricate the storefront
in Figure 10-17. No tempered glass is needed. Use nom-
inal dimensions.
11. Determine the glazing needed for the transom and side-
light shown in Figure 10-18. The glass in the two panels
to the side of the door needs to be tempered glass. Use
nominal dimensions.
12. Determine the glazing needed for the transom and side-
light shown in Figure 10-19. The glass needs to be tem-
pered glass. Use nominal dimensions.
13. Using the hardware schedule shown in Figure 10-9, de-
termine the hardware needed for the doors in Figures
10-10 and 10-11. FIGURE 10-18 Door Elevation
Openings 161

16. Determine the windows needed to complete the


Johnson Residence given in Appendix F.
17. Determine the hardware needed to complete the
Johnson Residence given in Appendix F.
18. Determine the doors and hardware needed to complete
the West Street Video project given in Appendix F.
19. Determine the storefront needed to complete the West
Street Video project given in Appendix F.

REFERENCE
1. International Building Code, International Code Counsel,
FIGURE 10-19 Door Elevation 2009, Section 2406.
CHAPTER ELEVEN

FINISHES

In this chapter you will learn how to apply the principles in stud or fire-treated wood stud to provide backing for the in-
Chapter 4 to metal studs, gypsum board, acoustical ceiling tile, stallation of the door frame. The quantity takeoff for a metal
carpet and pad, ceramic tile, sheet vinyl, vinyl composition tile stud partition is shown in the following example.
(VCT), rubber base, and paint. This chapter includes sample
spreadsheets that may be used in the quantity takeoff. It also
includes example takeoffs from the residential garage drawings. EXAMPLE 11-1
Determine the number of metal studs and feet of runner needed to
construct 125 feet of interior wall with four corners, six intersec-

F inishes include interior partition (nonbearing) walls


and the finishes applied to floors, walls, and ceilings.
We begin by looking at metal stud partitions.
tions, six walls without corners, and six 3-foot-wide doorways. Stud
spacing is 16 inches on center. Allow two extra studs for each cor-
ner, doorway, or intersection and one extra stud for each wall with-
out corners. How many pieces of runner are needed if the runner
comes in 10-foot lengths and is lapped 2 inches?

METAL STUD PARTITIONS Solution: The number of studs needed for the standard spacing is
calculated using Eq. (4-2) as follows:
Nonbearing metal stud partitions consist of light-gage steel
studs set in a C-shaped runner at the top and bottom of the (125!ft)(12!in/ft)
Number ⫽ ⫽ 94!each
partition. The studs are fastened to the runner with screws. 16!in
The bottom runner is fastened to the floor. The top runner Six interior walls lack corners at both ends; therefore, six additional
may be located at the bottom of the floor or roof deck above, studs are needed for these walls. There are four corners, six doorways,
in which case it is fastened to the floor or roof deck, or it may and six intersections that will require 2 additional studs each, for
stop at the ceiling line, in which case the wall must be braced 32 additional studs. The total number of studs is 132 (94 ⫹ 6 ⫹ 32).
to the floor or roof deck above. This bracing is done with Determine the number of pieces of runner using Eq. (4-6) as
metal studs. Unlike wood-framed walls, where the wood follows:
stud must be long enough to run from the top of the bottom (125!ft ⫹ 125!ft)
plate to the bottom of the lower top plate, the metal studs Number ⫽ ⫽ 26
(10!ft ⫺ 2!in)
must run from the floor to the top of the wall.
The number of studs needed to construct a metal stud For the door openings, six 3-foot 6-inch-long pieces of runner are
partition is calculated in the same manner as determining the needed above the doors. Only 2 of these pieces can be cut from one
piece of runner; therefore, 3 additional pieces of runner are needed,
number of studs needed to construct a wood wall (see
for a total of 29 pieces. 䊏
Chapter 8). Because the partitions are nonbearing, the open-
ings are framed differently. Instead of a king stud and a jack
stud on either side of an opening, two king studs are placed
on either side of the opening and a piece of runner is screwed
GYPSUM BOARD
between the king studs to act as the header. Each door open- Gypsum board (drywall) consists of the gypsum board,
ing requires a piece of runner 6 inches longer than the width metal or plastic trim, fasteners, tape, and drywall compound
of the opening. When installing wood-framed doors in metal (mud). Gypsum board comes in different thicknesses with
stud partitions, one of the king studs is replaced with a wood 1>2!and!5>8!inches being the most common sizes. The width
162
Finishes 163

of the sheets is 4 feet, and the length of the sheets varies from 14-foot-long and one 12-foot-long sheet for the columns for a total
8 to 16 feet. Gypsum board comes in three common types: length of 26 feet. The number of rows is determined by Eq. (4-13)
standard, Type-X (fire rated), and water resistant. Type-X is as follows:
used to create fire-rated partitions and ceilings, and their lo- 9!ft!8!in
cation is identified on the plan. Water-resistant gypsum NumberRows ⫽ ⫽ 2.5!rows
4!ft
board, which can be identified by its green color, is required
in wet locations. It is not uncommon for water-resistant Order two 12-foot-long sheets and three 14-foot-long sheets for
gypsum board to be used in entire bathrooms, laundry the ceiling. The gypsum board on the ceiling of the bedrooms will
be run with the long direction running east and west, perpendicu-
rooms, and other rooms subject to continuous moisture.
lar to the ceiling joists. Use one 12-foot-long sheet for the columns
Gypsum board is bid as a sheet good using the same proce- in the bedrooms. The number of rows is determined by Eq. (4-13)
dures as when bidding sheathing. as follows:
Trim includes corner molding on the outside corners
and J-molding on exposed ends of gypsum board. Trim is (11 ft!5!in)
NumberRows ⫽ ⫽ 3!rows
bid by the linear foot or piece. Fasteners, tape, and drywall 4!ft
compound are quantity-from-quantity goods and are bid Order three 12-foot-long sheets for each bedroom. In addition, one
based on historical data or data from the manufacturer. The 8-foot-long sheet is needed for each closet.
quantity takeoff for gypsum board is shown in the following The drywall on the walls will need to be two rows high. For
example. the top row of drywall for the north and south walls of the main
room, a 14-foot-long sheet and a 12-foot-long sheet are needed
for each wall. The bottom row of the north wall does not need to
EXAMPLE 11-2 run through the door; therefore, one 10-foot-long sheet and one
12-foot-long sheet are needed. For the bottom row of the south
Determine the number of sheets of gypsum board, the number of
wall, two 10-foot-long sheets are needed. Two 10-foot-long sheets
pieces of trim, the pounds of screws, boxes of joint compound, and
are needed for the east wall and two for the west wall. The walls of
rolls of tape needed for the rooms in Figure 11-1. The ceiling height
each bedroom will require six 12-foot-long sheets and two 8-foot-
is 8 feet, and the ceiling joists run north to south. The gypsum
long sheets. The 8-foot-long sheets will be used for the bottom
board on the walls is to be run with the long direction of the board
row of the two walls with doors. Two 8-foot-long sheets will cover
running horizontal. The gypsum board may be ordered in 8-, 10-,
the east and north walls of the closet, and two additional 8-foot-
12-, 14-, or 16-foot-long sheets. The trim is available in 10-foot
long sheets will cover the south and west walls of the closet. Order
lengths. Historical data indicates that 1.1 pounds of screws, 0.4 box
the following sheets of gypsum board: fourteen 8-foot-long,
of joint compound, and 0.13 roll of tape are needed for 100 square
seven 10-foot-long, twenty-five 12-foot-long, and five 14-foot-
feet of drywall. The doors are 30 inches wide.
long sheets.
Solution: The gypsum board on the ceiling of the main room will A 4-foot piece of J-molding is needed above each closet
be run with the longest direction running east and west. Use one door. Four 7-foot-long pieces (sides) and one 4-foot-long piece

FIGURE 11-1 Wall Layout


164 CHAPTER ELEVEN

(above) of corner are needed for each closet door opening. Order ⫹ 2(5!ft!7!in) ⫹ 2(2!ft!1!in) ⫹ 2(5!ft!6!in)
one 10-foot-long piece of J-molding and nine 10-foot-long ⫹ 2(2!ft!1!in)](8!ft)
pieces of corner molding.
⫽ 1,500!ft2
To calculate the pounds of nails, boxes of joint compound,
and rolls of tape, one needs the area of gypsum board needed for The total area is 2,006 square feet (506 ft2 ⫹ 1,500 ft2). The number
the ceiling and walls. The area of the ceiling is the length times the of pounds of screws needed is calculated using Eq. (4-21) as follows:
width and is calculated as follows:
b ⫽ 22.1!lb
1.1!lb
Number ⫽ (2,006!ft2)a
Area ⫽ (Length)(Width) 100!ft2
⫽ (24!ft!4!in)(9!ft!8!in) ⫹ (11!ft!5!in)(10!ft!10!in)
The number of boxes of joint compound needed is calculated using
⫹ (11 ft!5!in)(10!ft!10!in) ⫹ (5!ft!7!in)(2!ft!1!in) Eq. (4-21) as follows:
⫹ (5 ft!6!in)(2!ft!1!in)
b ⫽ 8!boxes
0.4!box
⫽ 506!ft2 Number ⫽ (2,006!ft2)a
100!ft2
The area of the walls is their perimeter times their height and The number of rolls of tape needed is calculated using Eq. (4-21) as
is calculated as follows: follows:
Area ⫽ [2(24!ft!4!in) ⫹ 2(9!ft!8!in) ⫹ 2(11!ft!5!in)
b ⫽ 3!rolls
0.13!roll
Number ⫽ (2,006!ft2)a 䊏
⫹ 2(10!ft!10!in) ⫹ 2(11!ft 5!in) ⫹ 2(10!ft!10!in) 100!ft2

EXCEL QUICK TIP 11-1


Drywall
The calculation of the square footage of drywall needed for a rectangular room is set up in a spreadsheet by entering the
data and formatting the cells as follows:

A B C D E F G H I J K
1 Room 1 Room 2 Room 3 Room 4 Room 5
2 Room Length 24 ft 11 ft 11 ft 5 ft 5 ft
3 4 in 5 in 5 in 7 in 6 in
4 Room Width 9 ft 10 ft 10 ft 2 ft 2 ft
5 8 in 10 in 10 in 1 in 1 in
6 Room Height 8 ft 8 ft 8 ft 8 ft 8 ft
7 - in - in - in - in - in
8
9 Ceiling Area 235 sft 124 sft 124 sft 12 sft 11 sft
10 Wall Area 544 sft 356 sft 356 sft 123 sft 121 sft
11
12 Totals
13 Ceiling Area 506 sft
14 Wall Area 1,500 sft

The following formulas need to be entered into the associ- The formulas in Cells B9 and B10 need to be copied to
ated cells: Cells D9 and D10, F9 and F10, H9 and H10, and J9 and J10.
The data for the room is entered in Cells B2 through B7,
Cell Formula D2 through D7, F2 through F7, H2 through H7, and J2
through J7. The data shown in the foregoing figure is from
B9 =(B2+B3/12)*(B4+B5/12) Example 11-1 and is formatted using the comma style,
B10 =(2*(B2+B3/12)+2*(B4+B5/12))* which replaces zeros with dashes.
(B6+B7/12)
B13 =B9+D9+F9+H9+J9
B14 =B10+D10+F10+H10+J10

procedures used to estimate sheathing (see Chapter 8).


TILE Thickset mortar, thinset glue, and grout are quantity-from-
Tile comes in a variety of sizes. The number of tiles needed is quantity goods and are bid based on historical data or the es-
estimated using the row and column method. If backing board, timated coverage rate provided by the manufacturer. When
such as Hardibacker, is required it is estimated using the same estimating the materials needed for tile, the estimator must
Finishes 165

take into account any layout requirements set by the archi-


tect, such as a minimum size of tile. Tile estimating is shown
in the following example.

EXAMPLE 11-3
Determine the number of 7!3>4-inch by 7!3>4-inch tiles needed to
tile a 30-inch by 48-inch entry. The tile is to have 1>4-inch grout
joints. Where possible the tiles should be centered in the space with
at least one-half of a tile at the edge of the space.
Solution: The number of rows is calculated using Eq. (4-14) as
follows: FIGURE 11-2 Tile Layout
30!in
Number ⫽ ⫽ 4!rows
(7.75!in ⫹ 0.25!in)
The number of columns is calculated using Eq. (4-17) as follows:
SUSPENDED ACOUSTICAL
48!in
Number ⫽ ⫽ 6!columns CEILINGS
(7.75!in ⫹ 0.25!in)
The total number of tiles is calculated using Eq. (4-18) as follows: Suspended acoustical ceilings consist of ceiling tiles sus-
pended in a metal grid. The metal grid consists of wall
Number ⫽ (4!rows)(6!columns) ⫽ 24!each moldings, main tees, 4-foot cross tees, and 2-foot cross
The entry is laid out as shown in Figure 11-2 with the minimum tees. The ceiling grid is suspended from the structure by
size of tile being about 7 inches wide. 䊏 wire. Wall molding is required around the entire perimeter
of the room, and the main tees are run at 4 feet on center
throughout the room. The main tees have a connection on
both ends that allow them to be connected end to end to
form continuous tees long enough to span the room.
Four-foot cross tees are run between the main tees and be-
EXCEL QUICK TIP 11-2 tween the main tees and the walls. The 4-foot cross tees are
Ceramic Tile run perpendicular to the main runners such that a 4-foot
by 2-foot grid is created. To achieve a 2-foot by 2-foot
The calculation of the number of ceramic tiles needed for grid, 2-foot cross tees are run between the 4-foot cross
a rectangular room is set up in a spreadsheet by entering tees. Two-foot cross tees can also be used between the
the data and formatting the cells as follows: main runners and the walls. Each end of a cross tee has a
connection that allows it to be connected to a main or
A B C
cross tee. When using leftover pieces of tees, one must
1 Length - ft
make sure the piece has the connection needed to connect
2 48 in
3 Width - ft to the main and cross tees. At the edge of the ceiling, the
4 30 in main and cross tees are cut to length and riveted to the
5 Tile Size 7.75 in wall molding.
6 Joint Width 0.25 in Suspended acoustical ceilings often are bid by the
7 square foot; however, this does not provide the necessary
8 Tiles 24 ea information to order the correct materials for the ceiling.
The tiles in the acoustical ceiling are bid based on the row
The following formula needs to be entered into Cell C8. and column method deducting any tiles that are being re-
placed by lighting fixtures, diffusers, registers, and grilles.
=ROUNDUP((B3*12+B4)/(B5+B6),0)*
The wall moldings and main tees are bid as linear compo-
ROUNDUP((B1*12+B2)/(B5+B6),0) nents. The cross tees are bid as a counted item. When esti-
The data for the room and tile is entered in Cells B1 mating the materials needed for an acoustical ceiling, the
through B6. Both the row and the column are rounded estimator must take into account any layout requirements
up to the next full tile to ensure that at least a 1/2 of tile is set by the architect, such as a minimum size of tile. When
located around the perimeter of the room. The data dealing with odd-shaped rooms, often the easiest way to
shown in the foregoing figure is from Example 11-3 and determine the components needed for the grid is to pre-
is formatted using the comma style, which replaces zeros pare a layout for the room. The estimate of materials
with dashes. needed for an acoustical ceiling is shown in the following
example.
166 CHAPTER ELEVEN

are located between the second and third rows, the fourth and fifth
EXAMPLE 11-4 rows, and the sixth and seventh rows. Three main tees are required
A 13-foot-wide by 15-foot-long ceiling is to receive a 2-foot by and are 15 feet long. The number of 12-foot-long main tees needed
2-foot acoustical ceiling. The ceiling includes four 2-foot by 2-foot is calculated as follows:
fluorescent light fixtures and one 2-foot by 2-foot mechanical regis- (3)(15!ft)
ter. Determine the number of 12-foot-long wall moldings, 12-foot- Number ⫽ ⫽ 4!each
12!ft
long main runners, 4-foot cross tees, 2-foot cross tees, and 2-foot by
2-foot tiles needed for the ceiling. The tiles should be centered in the Ordering four main tees will require the first main tee to be a
room, and, where possible, there should be at least half a tile at the 12-foot piece and a 3-foot piece, the second main tee to be the
edge of the room. leftover 9-foot piece and a 6-foot piece, and the last main tee to be
the leftover 6-foot piece and a 9-foot piece because only two
Solution: Use the row and column method to calculate the number
pieces can be cut from a 12-foot-long main tee while maintaining
of tiles. The number of rows is calculated using Eq. (4-13) as follows:
the required end connections. If the ceiling was constructed by
13!ft starting each of the main tees with a full-length 12-foot-long
Number ⫽ ⫽ 7!rows
2!ft piece, 1 1/2 full-length pieces will be needed for each main tee, for
a total of five 12-foot-long pieces.
To center the rows, the following widths of rows are needed (from bot- The main runners divide the ceiling into four 15-foot-long
tom to top): one at 18 inches, five at 24 inches, and one at 18 inches. rectangles with the following widths: 3.5, 4, 4, and 1.5 feet. These
The number of columns is calculated using Eq. (4-16) as follows: rectangles are subdivided by cross tees running the width of the
15!ft room. For each of the first three rectangles, seven (one less than the
Number ⫽ ⫽ 8!columns number of tiles required for the length of the rectangle) 4-foot
2!ft
cross tees are needed, for a total of twenty-one 4-foot cross tees.
To center the columns, the following widths of columns are Each of these rectangles is further subdivided into 2-foot by 2-foot
needed (from left to right): one at 18 inches, six at 24 inches, and or smaller squares using 2-foot cross tees. Eight (the number of tiles
one at 18 inches. The total number of squares in the grid is calcu- required for the length of the rectangle) 2-foot cross tees are needed
lated using Eq. (4-18) as follows: for each of these rectangles, for a total of 24. For the 1.5-foot-wide
rectangle, seven 2-foot cross tees are needed, bringing the total
Number ⫽ (7!rows)(8!columns) ⫽ 56!each
number of 2-foot cross tees to 31. The layout for the ceiling is
Five of these squares are filled with light fixtures and a mechanical shown in Figure 11-3. 䊏
register; therefore, 51 (56 – 5) tiles are needed.
The number of wall moldings can be calculated using Eq. (4-7)
as follows: WOOD AND LAMINATE
(13!ft ⫹ 15!ft ⫹ 13!ft ⫹ 15!ft) FLOORS
Number ⫽ ⫽ 5!each
12!ft Laminate floors, such as Pergo, and many wood floors are not
The main tees will be run in the long direction. A 15-foot-long fastened to the underlying floor but float over it. A gap is left
main tee is needed between every two rows of tiles. The main tees at all edges of the floor. The gap and the floating nature of the

FIGURE 11-3 Ceiling Layout


Finishes 167

floor allow the flooring to move, expand, and contract. To


protect the flooring against moisture, a vapor barrier may be
required in certain applications. The flooring comes in
planks and is bid using the row and column method. Because
the flooring is connected using a form of tongue and groove,
waste from one row may only be used when it has the neces-
sary tongue or groove. In addition, the pieces must be stag-
gered, which may also increase the waste.
A sound-deadening underlayment is often used directly
below the flooring. There are different types of underlay-
ment that provide differing levels of cushioning and sound
attenuation. The underlayment is bid as a rolled good.
Trim must be provided at all edges of the flooring to FIGURE 11-4 Vinyl Seaming Plan
cover the gap between the floor and the wall. Trim pieces
may include stair nosing for use on stairs; base and shoe The number of packages of flooring is calculated as follows:
molding to terminate the flooring at walls; end molding to 43!each
terminate the flooring where base or shoe molding will not Number ⫽ ⫽ 6!packages 䊏
(8!each/package)
work, such as around a raised fireplace hearth; T-molding as
a transition between floors of the same height; and reducer
strips as a transition between floors of different heights.
Trim pieces are bid as a counted item or a linear good de-
SHEET VINYL
pending on where it is used. Sheet vinyl is available in 12-foot widths. Vinyl must be in-
stalled in one direction, and the pattern must be matched.
When the room is wider than 12 feet, the vinyl must be
EXAMPLE 11-5 seamed. This may be done by installing one large piece and
a number of smaller pieces of vinyl as shown in Figure 11-4
Determine the number of 7.3-inch by 50.6-inch pieces of laminate
flooring and rolls of underlayment that are needed for a 10-foot by
or by installing two large pieces as shown in Figure 11-5.
10-foot floor. The flooring must be staggered at least 24 inches and The advantage of installing the vinyl as shown in Figure 11-4
comes eight pieces per package. The underlayment comes in rolls 3 is that less material is required. The advantage of installing
feet wide by 50 feet long. the vinyl as shown in Figure 11-5 is there are fewer seams,
which improves the aesthetics of the installation and the
Solution: Determine the number of rolls of underlayment. The
wear of the vinyl because it wears out at the seams faster
number of rows is calculated using Eq. (4-13) as follows:
than elsewhere.
10!ft To calculate the quantity of vinyl using the seaming plan
Number ⫽ ⫽ 4!rows
3!ft in Figure 11-4, one calculates the number of rows of vinyl
The number of columns is calculated using Eq. (4-16) as follows: using Eq. (4-13). The number of rows is rounded up to the
twelfth, sixth, quarter, third, or half of a row. The number in
10!ft the denominator of the fraction of a row represents the
Number ⫽ ⫽ 0.20!columns
50!ft number of smaller pieces of vinyl that are used. For example,
The total number of rolls of underlayment is calculated using if the fraction of a row is 1>12, then 12 smaller pieces will be
Eq. (4-18) as follows: used. The length of the room is multiplied by the fraction of
a row (or divided by the number of pieces) to determine the
Number ⫽ (4!rows)(0.2!columns) ⫽ 1!each length of vinyl needed for the small pieces. The length of
Determine the required number of pieces of flooring. The number
of rows is calculated using Eq. (4-13) as follows:
(10!ft)(12!in/ft)
Number ⫽ ⫽ 2.5!rows
50.6!in
The number of rows is rounded to one half of a piece of flooring to
ensure proper staggering. The number of columns is calculated
using Eq. (4-16) as follows:
(10!ft)(12!in/ft)
Number ⫽ ⫽ 17!columns
7.3!in
The total number of pieces of flooring is calculated using Eq. (4-18)
as follows:
Number ⫽ (2.5!rows)(17!columns) ⫽ 43!each FIGURE 11-5 Vinyl Seaming Plan
168 CHAPTER ELEVEN

vinyl needed for the large pieces equals the number of large good. The coverage for a gallon of glue can be obtained from
pieces times the length of the room. To ensure that the pat- the manufacturer or from historical data.
tern matches, the length of the vinyl needs to be rounded up
to whole increments of the pattern. For example, if the pat-
tern in the vinyl repeats every 16 inches, the length would be RUBBER BASE
rounded up to increments of 16 inches. In Excel, the CEIL- Rubber base comes in rolls or pieces and is bid as a linear
ING function would be used to round to increments of 16 good. The rubber base may be bent around corners, or the
inches. The calculation of vinyl using this method is shown architect may require that manufactured corners be used.
in the following example. Base is bid as a linear good, and manufactured corners are
bid as a counted item.
EXAMPLE 11-6
How many yards of vinyl need to be ordered for a 13-foot-long by CARPET AND PAD
14-foot 6-inch-wide room? The pattern repeats every 12 inches.
Carpet is handled in the same manner as sheet vinyl. In resi-
Solution: The number of rows is calculated using Eq. (4-13) as dential applications, the carpet is laid over a pad. Tackless fas-
follows: tening strips are required around the perimeter of the carpet,
14.5!ft and trim is required anytime the carpet transitions to vinyl.
NumberRows ⫽ ⫽ 1.21 The pad is bid as a sheet good using the same procedure as in
12!ft
estimating underlayment (pad) for wood and laminate floors.
Round the number of rows up to 1.25. The additional length The tackless fastening strips and trim are bid as linear goods.
needed for the small pieces is 4 feet (13!ft ⫻ 1>4). The length of In commercial applications the carpet is glued down.
vinyl needed is 17 feet (13 ft ⫹ 4 ft). The number of yards of vinyl is The glue is bid as a quantity-from-quantity good. The
calculated as follows:
amount of glue needed for the carpet is based on historical
1!yd2
b ⫽ 22.7!yd2
or manufacturer’s data.
Area ⫽ (17!ft)(12!ft)a 䊏
9!ft2

To calculate the quantity of vinyl using the seaming PAINT


plan in Figure 11-5, one calculates the number of rows of Paint is bid based on the square footage for walls, ceilings,
vinyl using Eq. (4-13) and rounds up to the whole number of and floors. Trim is bid based on the lineal foot when the trim
rows. The length of vinyl needed equals the number of rows is a separate color or a different type of paint than the sur-
times the length of the room. The calculation of vinyl is rounding area. When the trim is painted with the same paint
shown in the following example. as the surrounding area, it is bid as part of the surrounding
area. Doors are bid as counted items. The amount of paint
needed depends on the type of paint being used and the
EXAMPLE 11-7
surface that is being painted. The paint usage is bid as a
How many yards of vinyl need to be ordered for a 13-foot-long by quantity-from-quantity good based on historical data or
14-foot 6-inch-wide room? The pattern repeats every 12 inches. Lay coverage rates from the manufacturer. Sometimes residential
the vinyl out to minimize the seams. painters bid painting based on the square footage of floor
Solution: The number of rows needed is calculated using Eq. (4-13) space. The bidding of paint is shown in the following example.
as follows:
(14.5!ft) EXAMPLE 11-8
NumberRows ⫽ ⫽ 1.21
(12!ft)
How much paint is needed to paint 100 lineal feet of an 8-foot-high
Round the number of rows up to 2. The length of vinyl needed is block wall with one coat of primer and two coats of latex paint?
26 feet (2 ⫻ 13 ft). The number of yards of vinyl is calculated as From historical data, 1 gallon of primer will cover 250 square feet of
follows: wall and 1 gallon of latex paint will cover 400 square feet of wall
with a single coat.
1!yd2
Area ⫽ (26!ft)(12!ft)a b ⫽ 34.7!yd2 䊏
9!ft2 Solution: The area of the wall is calculated as follows:
Area ⫽ (100!ft)(8!ft) ⫽ 800!ft2

VINYL COMPOSITION TILE The amount of primer and paint needed is calculated using Eq. (4-20)
as follows:
Vinyl composition tile (VCT) is available in 12-inch by 12-inch
squares. The number of tiles is estimated in the same manner 800!ft2
VolumePrimer ⫽ ⫽ 4!gal
as for ceramic tile, with one exception: there is no space be- (250!ft2/gal)
tween the tiles, which eliminates the need for grout. The tiles (2!coats)(800!ft2)
VolumePaint ⫽ ⫽ 4!gal 䊏
are glued down and the glue is bid as a quantity-from-quantity (400!ft2/gal)
Finishes 169

SAMPLE TAKEOFF FOR THE area of the ceiling is the length times the width and is calculated
as follows:
RESIDENTIAL GARAGE
Area ⫽ (25!ft!4!in)(23!ft!4!in) ⫽ 591!ft2
A sample takeoff for gypsum board and paint from a set of
plans is shown in the following example. The area of the walls is their perimeter times their height less the
openings, and is calculated as follows:
Area ⫽ [2(25!ft!4!in) ⫹ 2(23!ft!4!in)]8
EXAMPLE 11-9 ⫺ (16!ft)(7!ft) ⫺ (3!ft)(6!ft!8!in)
Determine the number of sheets of gypsum board, the number ⫽ 647!ft2
of pieces of trim, the pounds of screws, boxes of joint com- The total area is 1,238 square feet (591 ft2 ⫹ 647 ft2). The number of
pound, rolls of tape, gallons of primer, and gallons of paint pounds of screws needed is calculated using Eq. (4-21) as follows:
needed for the residential garage given in Appendix F. The gyp-
b ⫽ 14!lb
sum board on the walls is to be run with the long direction of the 1.1!lb
Number ⫽ (1,238!ft2)a
board running horizontal. The gypsum board may be ordered in 100!ft2
8-, 10-, 12-, 14-, or 16-foot-long sheets. Historical data indicates The number of boxes of joint compound needed is calculated using
that 1.1 pounds of screws, 0.4 box of joint compound, and 0.13 Eq. (4-21) as follows:
roll of tape are needed for 100 square feet of drywall. From his-
b ⫽ 5!boxes
torical data, 1 gallon of PVA primer will cover 300 square feet of 0.4!box
Number ⫽ (1,238!ft2)a
drywall, 1 gallon of interior latex paint will cover 400 square feet 100!ft2
of drywall with a single coat, 1 gallon of oil base primer will The number of rolls of tape needed is calculated using Eq. (4-21) as
cover 250 square feet of T1-11 siding, and 1 gallon of exterior follows:
latex paint will cover 375 square feet of siding with a single coat
b ⫽ 2!rolls
or four single-hung doors with two coats. 0.13!roll
Number ⫽ (1,238!ft2)a
100!ft2
Solution: The gypsum board on the ceiling will be run east-west,
Now we will look at the paint. The area of drywall to be painted is
perpendicular to the trusses. Use one 14-foot-long sheet and one
1,238 square feet. The amount of primer and paint needed is calcu-
12-foot-long sheet for the columns, for a total length of 26 feet. The
lated using Eq. (4-20) as follows:
number of rows is determined by Eq. (4-13) as follows:
1,238!ft2
(23!ft!4!in) VolumePrimer ⫽ ⫽ 5!gal
NumberRows ⫽ ⫽ 6!rows (300!ft2/gal)
4!ft
(2!coats)(1,238!ft2)
VolumePaint ⫽ ⫽ 7!gal
The drywall on the walls will need to be two rows high. The num- (400!ft2/gal)
ber of sheets needed for the north wall is two 14-foot-long sheets
From Example 9-14, the area of T1-11 to be painted is 956 square
and two 12-foot-long sheets. The number of sheets needed for the
feet (792 ft2 ⫹ 164 ft2). The amount of primer and paint needed is
south wall is one 14-foot-long sheet and three 12-foot-long sheets
calculated using Eq. (4-20) as follows:
because the single-hung door will allow us to use two 12-foot-long
sheets on the bottom row. The number of sheets needed for the east 956!ft2
VolumePrimer ⫽ ⫽ 4!gal
wall is two rows and two columns of 12-foot-long sheets, for a total (250!ft2/gal)
of four sheets. For the west wall two 12-foot-long sheets are needed (2!coats)(956!ft2)
for the top row, and one 8-foot-long sheet is needed for the bottom VolumePaint ⫽ ⫽ 6!gal
row. Order one 8-foot-long, seventeen 12-foot-long, and nine (375!ft2/gal)
14-foot-long sheets. One quart is needed for the single-hung door.
The area of gypsum board is needed to calculate the The quantities needed for the garage, grouped by the cost
pounds of nails, boxes of joint compound, and rolls of tape. The codes in Appendix B, are shown in Table 11-1. 䊏

TABLE 11-1 Quantities for Residential Garage

09-200 Drywall 09-900 Paint

Hang and finish drywall 1238 sft Interior primer 5 gal


4¿ ⫻ 8¿ ⫻ 1>2– gypsum!board 1 ea Interior latex 7 gal
4¿ ⫻ 12¿ ⫻ 1>2–!gypsum!board 17 ea Paint drywall with 3 coats 1238 sft
4¿ ⫻ 14¿ ⫻ 1>2– gypsum board 9 ea Exterior primer 4 gal
1 5>8– screws 14 lbs Exterior latex 6 gal
Joint compound 5 box Paint T1-11 with 3 coats 956 sft
Joint tape 2 rolls Exterior latex 0.25 gal
Paint single-hung door 1 Ea
170 CHAPTER ELEVEN

CONCLUSION 10-foot-long lengths and is lapped 2 inches? The


perimeter walls are already in place.
Finishes include interior partition (nonbearing) walls and the 7. How many 4-foot-wide by 9-foot-high sheets of drywall
finishes applied to the floors, walls, and ceilings. Metal stud are needed for the walls of the tenant finish in Figure
walls are bid by using the same procedures as for wood stud 11-6 if the walls are 9 feet high? The perimeter walls
walls. Drywall, tile, acoustical ceiling tile, wood and laminate need to be drywalled on the tenant’s side only.
floors, vinyl, carpet, pad, and vinyl composition tile are all bid
8. Determine the number of pieces of trim, the pounds of
using the row and column method. Painting is bid by the square
screws, boxes of joint compound, and rolls of tape
foot or lineal foot. Fasteners, drywall tape and mud, adhesives,
needed for the walls of the tenant finish in Figure 11-6.
grout, primer, and paint are quantity-from-quantity goods and
The ceiling height is 9 feet. The trim is available in 10-
are bid based on historical data or data from the manufacturer.
foot lengths. Historical data indicates that 1.2 pounds of
screws, 0.45 box of joint compound, and 0.15 roll of
PROBLEMS tape are needed for 100 square feet of drywall.
9. Determine the number of 11!3>4-inch by 11!3>4-inch
1. Determine the number of metal studs needed to con- tiles needed to tile a 10-foot 4-inch by 12-foot floor. The
struct 83 feet of interior wall with six corners, eight in- tile is to have 1>4-inch grout joints. Where possible, the
tersections, and four 3-foot-wide doorways. Stud spac- tiles should be centered in the room with at least one-
ing is 16 inches on center. Allow two extra studs for each half of a tile at the edge of the room.
corner, intersection, or doorway.
10. Determine the number of 7!3>4-inch by 7!3>4-inch tiles
2. How many pieces of runner are needed for Problem 1 if needed for the floor in Figure 11-7. The tile is to have
the runner comes in 10-foot-long lengths and is lapped 1>4-inch grout joints. Where possible, the tiles should
2 inches? be centered in the room with at least one-half of a tile at
3. How many 4-foot-wide by 8-foot-high sheets of drywall the edge of the room.
are needed for the wall in Problem 1 if the wall is 8 feet 11. A 21-foot-wide by 23-foot-long ceiling is to receive a 2-foot
high and drywall is placed on both sides? by 2-foot acoustical ceiling. The ceiling includes twelve
4. Determine the pounds of screws, boxes of joint com- 4-foot by 2-foot fluorescent light fixtures and five 2-foot
pound, and rolls of tape needed for the wall in Problem 1. by 2-foot mechanical diffusers. Determine the number of
Historical data indicates that 1.1 pounds of screws, 0.4 box 12-foot-long wall moldings, 12-foot-long main runners,
of joint compound, and 0.13 roll of tape are needed for 4-foot cross tees, 2-foot cross tees, and 2-foot by 2-foot
100 square feet of drywall. tiles needed for the ceiling. Where possible, the tiles
5. Determine the number of metal studs needed to con- should be centered in the room with at least one-half of a
struct the walls for the tenant finish in Figure 11-6. The tile at the edge of the room.
studs for the perimeter walls are already in place, but dry- 12. The room in Figure 11-8 is to receive a 2-foot by 2-foot
wall has not been installed on the walls. Stud spacing is 16 acoustical ceiling. The ceiling includes five 2-foot by
inches on center. Allow two extra studs for each corner or 2-foot fluorescent light fixtures and two 2-foot by 2-foot
intersection and four extra studs for each doorway. mechanical diffusers. Determine the number of 12-foot-
6. How many pieces of runner are needed for the walls of long wall moldings, 12-foot-long main runners, 4-foot
the tenant finish in Figure 11-6 if the runner comes in cross tees, 2-foot cross tees, and 2-foot by 2-foot tiles

FIGURE 11-6 Wall Layout


Finishes 171

18. How many 12-inch by 12-inch vinyl composition tiles


(VCT) need to be ordered for the room in Figure 11-8?
19. How many feet of rubber base need to be ordered for a
17-foot-long by 22-foot 6-inch-wide room?
20. How many feet of rubber base need to be ordered for
the room in Figure 11-8?
21. How many yards of carpet need to be ordered for a 17-foot-
long by 22-foot-wide room? The carpet is 12 feet wide.
22. How many yards of carpet need to be ordered for the
room in Figure 11-8? The carpet is 12 feet wide.
23. How many rolls of pad need to be ordered for a 17-foot-
long by 22-foot-wide room? The pad comes in rolls 6
FIGURE 11-7 Bathroom Floor Plan feet wide by 50 feet long.
24. How many rolls of pad need to be ordered for the room in
Figure 11-8? The pad comes in rolls 6 feet wide by 50 feet
needed for the ceiling. Where possible, the tiles should
long.
be centered in the room with at least one-half of a tile at
the edge of the room. 25. How much paint is needed to paint 75 lineal feet of a
12-foot-high block wall with one coat of primer and two
13. Determine the number of 7.3-inch by 50.6-inch pieces
coats of latex paint? From historical data, 1 gallon of
of laminate flooring and rolls of underlayment needed
primer will cover 250 square feet of wall and 1 gallon of
for a 22-foot by 24-foot floor. The flooring must be
latex paint will cover 400 square feet of wall with a single
staggered at least 24 inches and comes eight pieces per
coat. Only one side of the wall is painted.
package. The underlayment comes in rolls 3 feet wide by
50 feet long. Run the long direction of the flooring par- 26. How much paint is needed to paint the walls in Figure 11-
allel to the short direction of the room. 8 with one coat of primer and two coats of latex paint? The
ceiling is 8 feet 6 inches high. From historical data, 1 gallon
14. Determine the number of 7.3-inch by 50.6-inch pieces
of primer will cover 300 square feet of wall and 1 gallon of
of laminate flooring and rolls of underlayment needed
latex paint will cover 400 square feet of wall with a single
for the room in Figure 11-8. The flooring must be stag-
coat. Only one side of the wall is painted.
gered at least 24 inches and comes eight pieces per pack-
age. The underlayment comes in rolls 3 feet wide by 27. Determine the drywall needed to complete the Johnson
50 feet long. Run the long direction of the flooring par- Residence given in Appendix F.
allel to the short direction of the room. 28. Determine the ceramic tile needed to complete the
15. How many yards of vinyl need to be ordered for a 17-foot- Johnson Residence given in Appendix F.
long by 22-foot-wide room? 29. Determine the laminate flooring and underlayment
16. How many yards of vinyl need to be ordered for the (pad) needed to complete the Johnson Residence given
room in Figure 11-8? in Appendix F.
17. How many 12-inch by 12-inch vinyl composition tiles 30. Determine the carpet and pad needed to complete the
(VCT) need to be ordered for a 17-foot-long by 22-foot- Johnson Residence given in Appendix F.
wide room? 31. Determine the paint needed to complete the Johnson
Residence given in Appendix F.
32. Determine the metal stud and track needed to complete
the West Street Video project given in Appendix F.
33. Determine the drywall needed to complete the West
Street Video project given in Appendix F.
34. Determine the acoustical ceiling components needed to
complete the West Street Video project given in Appendix F.
35. Determine the ceramic tile needed to complete the West
Street Video project given in Appendix F.
36. Determine the carpet needed to complete the West
Street Video project given in Appendix F.
37. Determine the paint needed to complete the West Street
Video project given in Appendix F.
38. Set up Excel Quick Tip 11-1 in Excel.
FIGURE 11-8 Room Layout 39. Set up Excel Quick Tip 11-2 in Excel.
C H A P T E R T W E LV E

FIRE SUPPRESSION

In this chapter you will learn how to apply the principles in Fire sprinkler systems consist of the underground ser-
Chapter 4 to fire sprinkler systems. vice, the valve assembly, fire department connections, the
riser pipe, main lines, branch lines, and the sprinkler heads.
The underground service provides water from the utility’s

T
pipeline to the building. The portion of the service provided
he design drawings and specifications may provide a
by the fire sprinkler subcontractor usually stops 5 feet out-
complete fire sprinkler design or they may identify
side the building, with the remaining portion of the under-
the requirements that the systems must meet. In the
ground service being provided by the site utility contractor.
latter case, the fire sprinkler system is built under a design-
A valve assembly (which includes check valves, drain valves,
build subcontract, which precludes the general contractor
and a flow alarm) is located where the fire sprinkler system
from identifying and quantifying the components, leaving
enters the building. A typical valve assembly for a wet pipe
the estimator to rely on average square foot pricing or bids
system is shown in Figure 12-1. The valve assembly allows
from the subcontractor. When the fire sprinkler system has
the system to be serviced and sets off an alarm when the
been designed, the estimator can identify the components
water flows.
and provide an accurate bid for the sprinkler system.

FIGURE 12-1 Valve Assembly


172
Fire Suppression 173

FIGURE 12-2 Main and Branch Lines

The fire department connection allows the fire depart- typical pipe hanger is shown in Figure 12-3. The main and
ment to connect their hoses to the fire sprinkler system. In branch lines are hung so they slope to a drain; therefore, the
Figure 12-1, a fire department Siamese connection is pro- pipe hangers will vary in length.
vided as part of the valve assembly. The riser pipe runs verti- The final components of the fire sprinkler system are the
cally through the building delivering water to the different sprinkler head and the piece of pipe, known as a drop, that
levels of the building. In addition, valves and drains may be connects the head to the branch line. Like the pipe hanger, the
provided along the riser pipe at each floor, allowing the indi- drop will vary in length to allow the lines to be sloped so the
vidual floors to be isolated. The main line runs horizontally system can be drained. A typical head is shown in Figure 12-4.
through the building supplying water to the branch lines. Fire sprinkler systems, where there is sufficient design,
The branch lines run horizontally providing water to the in- are bid as counted items. Long runs of pipe are bid as a linear
dividual sprinkler heads. A layout of a main line and branch component. The bid of a fire sprinkler is shown in the fol-
lines is shown in Figure 12-2. lowing example.
The main and branch lines are supported from the roof
or floor above by pipe hangers. Typically, steel pipe is sup-
ported at 12 feet on center, and pipes 4 inches in diameter EXAMPLE 12-1
and larger require sway bracing anytime they have a change Determine the fire sprinkler components needed to complete the
in direction greater than 45 degrees. In addition, pipe hang- fire sprinkler system shown in Figure 12-2. The drops range from
ers are required within 1 foot of all changes in direction. A 1 to 2 feet in length.

FIGURE 12-3 Pipe Hanger


174 CHAPTER TWELVE

TABLE 12-1 Sprinkler System Components


Quantity Item
12 ea Heads with fusible link
12 ea 1 – dia. ⫻ 1- to 2-ft drop
12 ea Escutcheon
4 ea 1 – elbow
4 ea 1 – ⫻ 1 – ⫻ 1 – ⫻ tee
4 ea 1 1>4 – ⫻ 1 – ⫻ 1 – tee
1 ea 1 1>4 – elbow
1 ea 2 – ⫻ 1 1>4 – ⫻ 1 1>4 – tee
1 ea 2 – ⫻ 2 – ⫻ 1 1>4 – tee
FIGURE 12-4 Sprinkler Head
1 ea 2 1>2 – ⫻ 2 – ⫻ 1 1>4 – tee
8 ea 1 – dia. ⫻ 14-ft pipe
4 ea 1 – dia. ⫻ 7-ft pipe
1 ea 1 1>4 – dia. ⫻ 8-ft pipe
Solution: There are 12 sprinkler heads, each of which requires a
sprinkler head with a fusible link, an escutcheon, and a 1-inch-
2 ea 2 – dia. ⫻ 8-ft pipe
diameter pipe 1 to 2 feet long for the drop. There are four branch 1 ea 2 1>2 – dia. ⫻ 5-ft pipe
lines. The components for each branch line, from right to left, are as 20 ea Pipe hangers
follows: a 1 – elbow, a 14-foot-long 1-inch-diameter pipe, a 1 – ⫻ 1 –
⫻ 1 – tee, a 14-foot-long 1-inch-diameter pipe, a 1 1>4 – ⫻ 1 – ⫻ 1 –
tee, and a 7-foot-long 1 1>4-inch-diameter pipe. The components
for a main line, from top to bottom, are as follows: a 1 1>4 – elbow,
an 8-foot-long 1 1>4-inch-diameter pipe, a 2 – ⫻ 1 1>4 – ⫻ 1 1>4 –
tee, an 8-foot-long 2-inch-diameter pipe, a 2 – ⫻ 2 – ⫻ 1 1>4 – tee,
an 8-foot-long 2-inch-diameter pipe, a 2 1>2 – ⫻ 2 – ⫻ 1 1>4 – tee,
The number of pipe hangers required for the main line is calculated
and a 5-foot-long 2 1>2-inch-diameter pipe. The actual lengths of
using Eq. (4-1) as follows:
pipe are slightly shorter to account for the length of the fitting.
Pipe hangers are required every 12 feet. The number of pipe (8!ft ⫹ 8!ft ⫹ 8!ft ⫹ 5!ft)
hangers required for a branch line is calculated using Eq. (4-1) as Number ⫽ ⫹1⫽4
12!ft
follows:
A total of 20 hangers (4 ea/branch ⫻ 4 branches ⫹ 4 ea for the
(7!ft ⫹ 14!ft ⫹ 14!ft) main line) are required. The components for the sprinkler system
Number ⫽ ⫹1⫽4
˛

12!ft are shown in Table 12-1. 䊏

CONCLUSION 2. Determine the components needed to complete the fire


sprinkler system shown in Figure 12-6. The drops range
A typical fire sprinkler system consists of the underground from 2 to 3 feet in length.
service, the valve assembly, the fire department connections, 3. Determine the components needed to complete the fire
the riser pipe, main lines, branch lines, and the sprinkler sprinkler system for the West Street Video project given
heads. The pipes are supported by pipe hangers. Fire sprin- in Appendix F.
kler systems are bid as a counted item. Long runs of pipe are
bid as a linear component.

PROBLEMS
1. Determine the components needed to complete the fire
sprinkler system shown in Figure 12-5. The drops range
from 1 to 2 feet in length.
Fire Suppression 175

FIGURE 12-5 Fire Sprinkler Layout

FIGURE 12-6 Fire Sprinkler Layout


CHAPTER THIRTEEN

PLUMBING

In this chapter you will learn how to apply the principles in Solution: We begin with the hot water line. Approximately 19 feet
Chapter 4 to plumbing systems. Whole books have been written of 3/4-inch pipe are needed. Beginning with the left side of the
on estimating plumbing; therefore, this chapter will limit its bathroom, the following fittings are needed: four 3>4– ⫻ 3>4– ⫻
scope to the basics of estimating plumbing. 1>2– tees (one at each lavatory), four 1>2– ⫻ 6– stub-out fittings
(one at each lavatory), one 3>4– ⫻ 1>2– 90-degree elbow (near the
air chamber), and one 1/2– ⫻ 12– air chamber.
For the cold water line, a 1 1>4-inch water line runs to the mid-

P lumbing systems consist of the water supply, the fix-


tures and equipment, and the drain-waste-and-vent
(DWV) piping. Most plumbing is bid as a counted
item. Long runs of pipe are bid as a linear good. We begin by
looking at the water supply.
dle pair of water closets (approximately 8 feet), a 1-inch water line
runs from the middle pair of water closets to the urinal (approxi-
mately 3 feet), and a 3>4-inch water line runs from the urinal to the
air chamber (approximately 8 feet). Five 1>2-inch risers are needed
for the water closets (allow 18 inches each), and one 1>2-inch riser
is needed for the urinal (allow 30 inches). The pipe needed for the
cold water is 8 feet of 1 1>4-inch, 3 feet of 1-inch, 8 feet of 3>4-inch,
and 10 feet of 1>2-inch pipe. Beginning with the left side of the
WATER SUPPLY bathroom, the following fittings are needed: three 1 1>4– ⫻ 1 1>4–
The water supply provides potable water to the plumbing ⫻ 1>2– tees (water closets), one 1 1>4– ⫻ 1– ⫻ 1>2– tee (water
fixtures and equipment. A pressure-reducing valve (PRV) closet), one 1– ⫻ 1– ⫻ 1>2– tee (water closet), one 1– ⫻ 3>4– ⫻ 1>2–
and shutoff valve are required at the point where the water tee (urinal), four 3>4– ⫻ 3>4– ⫻ 1>2– tees (lavatories), one 3>4– ⫻
supply enters the building. The water is supplied to the vari- 1>2– 90-degree elbow (near the air chamber), one 1>2– ⫻ 12– air
chamber, six 1>2– ⫻ 1>2– 90-degree elbows (one per riser), and ten
ous plumbing fixtures and equipment by copper or plastic
1>2– ⫻ 6– stub-out fittings (one at each fixture). 䊏
(Pex or CPVC) pipes of varying sizes. For fixtures that use
both hot and cold water, a cold water pipe must be run from
the water supply and a hot water pipe must be run from the DRAIN-WASTE-AND-VENT
water heater. Copper pipe is connected with copper fittings SYSTEM
that are sweated (soldered) to the pipe. Pex is coupled with
compression fittings, and CPVC is coupled with CPVC fit- The drain-waste-and-vent (DWV) is used to carry soiled
tings solvent welded to the pipe. Water lines are bid using the water from the building and consists of three types of com-
same procedure as for fire sprinkler systems. New water sys- ponents: drain, waste, and vent. The drain piping and waste
tems must be capped at the fixture to allow the system to be piping are used to carry waste water from the building. The
pressure tested. Stub-out fittings for fixtures come pre- distinction between drain piping and waste piping is that
capped. The bidding of water supply is shown in the follow- waste piping includes water with solid waste from water
ing example. closets (toilets) and drain piping does not. P-traps are re-
quired at each fixture to prevent sewer gas from leaving the
DWV system and entering the room. This is accomplished
EXAMPLE 13-1 by creating a water barrier in the fixture or DWV system
Determine the water line components needed to complete the cop- near the point where the fixture connects to the DWV sys-
per water supply for the bathroom shown in Figures 13-1 and 13-2. tem. For the p-trap to work properly, the DWV system must

176
Plumbing 177

FIGURE 13-1 Water Supply Plan

FIGURE 13-2 Water Supply Isometric

be vented near it. This venting must occur before the top of
the DWV pipe falls below the elevation of the flow line of the
pipe as it leaves the p-trap. If this does not occur, the water
will be siphoned from the p-trap and allow gasses to enter
the building. Figure 13-3 shows the design of the p-trap.
The vent piping must be vented outside the building. A
flashing must be provided for the vent pipe where it leaves
the building. Cleanouts must be provided to allow block-
ages in the drain and waste piping to be cleaned out. The
quantity takeoff for the DWV system is shown in the fol-
lowing example. FIGURE 13-3 P-trap
178 CHAPTER THIRTEEN

FIGURE 13-4 DWV Plan

Solution: The DWV piping will be taken off in three steps: the
EXAMPLE 13-2 main (horizontal) waste, the vertical waste servicing the fixtures,
Determine the DWV components needed to complete the DWV and the vent. Beginning with the cleanout, the lengths of pipe
system for the bathroom shown in Figures 13-4 and 13-5. The hor- needed for the main waste line are as follows: 4 feet of 2-inch
izontal waste piping is 2 feet below the finished floor, the horizontal pipe run vertically, 8 feet of 2-inch pipe run horizontally, and
vent piping is 9 feet above the finished floor, and the vent termi- 12 feet of 4-inch pipe. The following fittings are needed: one 2–
nates 14 feet above the finished floor. cleanout plug, one 2– cleanout adapter, two 2– 90-degree elbows,

FIGURE 13-5 DWV Isometric


Plumbing 179

one 2– sanitary tee, one 4– ⫻ 2– bushing, one 4– ⫻ 4– ⫻ 2– re- FIXTURES AND EQUIPMENT
ducing sanitary tee, two 4– ⫻ 4– ⫻ 3– reducing sanitary tees, one
4– ⫻ 4– ⫻ 2– reducing sanitary tee, and one 4– ⫻ 4– ⫻ 3– reduc- Fixtures are bid as a counted item. When bidding fixtures,
ing sanitary tee. the estimator must include shut-off valves for each fixture at
Each of the pair of lavatory risers will require 4 feet of 2-inch the water supply, supply lines from the shut-off valve to the
pipe, one double 2– sanitary tee, two 6-inch-long 2-inch pieces of fixture, and a waste line (including the p-trap, if needed)
pipe, and two male adapters. The risers for the urinal and water from the fixtures to the DWV system. A shut-off valve is re-
closet require 1 foot of 3-inch pipe, one 3– sanitary tee, 2 feet of
quired for both the hot and cold water pipes at each fixture.
3-inch pipe, a 3– 90-degree elbow, and a 3– toilet flange servicing
the water closet, one 3– ⫻ 2– bushing, 3 feet of 2-inch pipe, one 2–
All of these components are installed as part of the finish
sanitary tee, and one 6-inch-long 2-inch piece of pipe servicing plumbing package. The quantity takeoff for plumbing fix-
the urinal. Each of the pairs of water closets will require 1 foot of tures is shown in the following example.
3-inch pipe, one 3– double sanitary tee, one 3– ⫻ 2– bushing, two
2-foot-long 3-inch pipes, two 3– 90-degree elbows, and two 3– toi-
let flanges. The pair of floor drains will require 1 foot of 2-inch EXAMPLE 13-3
pipe, one 2– double sanitary tee, two 4-foot-long 2-inch pipes, two Determine the fixtures needed for the bathroom in Figures 13-1,
2– p-traps, and two 2– floor drains. 13-2, 13-4, and 13-5.
For the vertical venting pipe, beginning at the lavatories, three
7-foot-long 2-inch pipes, one 5-foot-long 3-inch pipe, and three 10- Solution: The bathroom requires five water closets (toilets), one
foot-long 2-inch pipes are needed. Fifteen feet of 2-inch pipe are urinal, and four lavatories (sinks). Each toilet will require a shut-off
needed for the horizontal vent pipe. The following fittings are needed valve and a supply line to connect the water closet to the shut-off
for the vent pipe: two 2– 90-degree elbows, four 2– tees, one 3– tee, valve. The p-trap is built into the water closet. The urinal will re-
and two 3– ⫻ 2– bushings. quire a flush valve assembly. Each lavatory will require two shut-off
In addition, seven 2– test caps, five 3– test caps, one 3– thermo- valves, two supply lines, a faucet with a drain assembly, and a 1 1>2–
plastic roof flashing, and one decorative cleanout cover are needed. p-trap. 䊏

CONCLUSION 2. Determine the DWV components needed to complete


the DWV system for the bathroom shown in Figures 13-8
Plumbing consists of the water supply lines, the drain-waste- and 13-9. The horizontal waste piping is 2 feet below the
vent (DWV) lines, and the fixtures. Plumbing components, finished floor, the horizontal vent piping is 9 feet above
pipe, fittings, and fixtures, are bid as counted items. Long the finished floor, and the vent terminates 14 feet above
runs of pipe are bid as a linear good. the finished floor.
3. Determine the plumbing components needed to com-
PROBLEMS plete the Johnson Residence given in Appendix F.
4. Determine the plumbing components needed to com-
1. Determine the water line components needed to com- plete the West Street Video project given in Appendix F.
plete the water supply for the bathroom shown in
Figures 13-6 and 13-7.

FIGURE 13-6 Water Supply Plan


180 CHAPTER THIRTEEN

FIGURE 13-7 Water Supply Isometric

FIGURE 13-8 DWV Plan

FIGURE 13-9 DWV Isometric


CHAPTER FOURTEEN

HEATING, VENTILATION, AND


AIR-CONDITIONING (HVAC)

In this chapter you will learn how to apply the principles in in Figure 14-4. Gas- and oil-fired furnaces must be vented to
Chapter 4 to HVAC systems. Whole books have been written on the outside to allow combustion gases to escape. The furnace
estimating HVAC systems; therefore, this chapter will limit its may be equipped with a split air-conditioning unit consist-
scope to the basics of estimating HVAC. ing of a coil in the ductwork leaving the furnace and a con-
denser located outside the building. The coil is connected to
the condenser using two flexible copper pipes known as a

H
line set. Central heating may also include humidifying or de-
eating, ventilation, and air-conditioning (HVAC)
humidifying equipment and air filtration equipment.
systems consist of equipment, ductwork, and pip-
The takeoff of a residential central HVAC system is
ing used to heat and ventilate buildings and to con-
shown in the following example.
dition (cool and dry) the air. Many components are bid as a
counted item, including short runs of duct and pipe. Longer
runs of duct and pipe are bid as a linear good. Residential
EXAMPLE 14-1
and commercial HVAC systems are discussed separately.
Let’s begin with two common residential systems. Determine the HVAC components needed for the residence in
Figures 14-1 and 14-2. The furnace includes an air conditioner. A
2– ⫻ 12– register is required at each of the base cabinets and a 6– ⫻
18– grille is needed at the beginning of each return air. The distance
RESIDENTIAL HVAC SYSTEMS from the top of the furnace to the roof is 20 feet. The vent pipe is
Central heating and air-conditioning, the most common 4 inches in diameter.
residential HVAC system, consists of a forced air furnace
Solution: The equipment needed is a furnace, an air-conditioning
supplying heated air through metal ductwork located under
coil, and an air-conditioning compressor. A plenum is needed be-
the floor or above the ceiling. The supply duct, the duct that tween the furnace and the supply trunk line. For the supply trunk
provides heated air, may consist of a main trunk line of rec- line, 16 feet of 8– ⫻ 12– rectangular duct, two 8– ⫻ 12– to 8– ⫻ 8–
tangular duct running almost the entire length of the build- transitions, 17 feet of 8– ⫻ 8– square duct, and two 8– ⫻ 8– end
ing with individual supply lines running from the trunk line caps are needed. For the individual supply lines, the following items
to the registers (vents) in the individual rooms. Figures 14-1 are needed: nine 6-inch 90-degree elbows to connect to the trunk
and 14-2 show a heating system with a main trunk line. line, 90 feet (17 ft ⫹ 17 ft ⫹ 2 ft ⫹ 19 ft ⫹ 19 ft ⫹ 4 ft ⫹ 3 ft ⫹ 3 ft
When the supply duct is run in the attic or crawl space, the ⫹6 ft) of 6-inch-diameter duct, three 6-inch 90-degree elbows to
trunk line may be eliminated by running the supply lines connect to the base cabinets, three 2– ⫻ 12– registers, six 4– ⫻ 12–
from the furnace to the individual rooms. For bathrooms boots, and six 4– ⫻ 12– registers.
and kitchens, the supply line may be run into the bottom of The following items are needed for the return air: two 6– ⫻
18– grilles, 15 feet (1 ft ⫹ 4 ft ⫹ 1 ft ⫹ 1 ft ⫹ 7 ft ⫹ 1 ft) of 18-inch-
a base cabinet, and a register is placed in the base cabinet to
wide sheet metal to create return air chases between the joists, two
supply the kitchen or bathroom with air, thereby using the 8– ⫻ 12– end caps, 12 feet of 8– ⫻ 12– duct, and 8 feet of 12– ⫻ 18–
bottom of the cabinet as part of the supply line as shown in duct to run from the trunk line to the bottom of the furnace.
Figure 14-3. The return air duct, which returns the air from The venting needs to run from the furnace to a point at least
the rooms to the furnace, usually draws air from the hallways 2 feet above the roof, and 4 feet of pipe is allowed to enter the chase.
and uses the natural space between framing members (joists The pipe in the chase will need to be double walled. For the venting,
and studs) as well as metal duct to transport the air as shown the following items are needed: two 4-inch 90-degree single-wall
181
182 CHAPTER FOURTEEN

FIGURE 14-1 Plan View of Residential System

FIGURE 14-2 Isometric View of a Residential System

FIGURE 14-3 Supply Air in a Base Cabinet FIGURE 14-4 Return Air Using Framing Members
Heating, Ventilation, and Air-conditioning (HVAC) 183

FIGURE 14-5 Radiant Heating Pipe Layout

elbows, 4 feet of 4-inch-diameter single-wall pipe, 22 feet of 4-inch- warms the living space. A typical tubing layout for a room is
diameter double-wall pipe, one 4-inch roof flashing, and one shown in Figure 14-5. This tubing is often embedded in con-
4-inch termination cap. crete or gypcrete. In snowy climates, radiant heat located in
Other items needed for the furnace include one box of line set driveways and sidewalks may be used to melt snow on these
to connect the condenser to the coil, one thermostat, and one roll of
surfaces. The water used by radiant heat is heated by a boiler
low-voltage wiring. In addition, the electrician will need to provide
and is recirculated by a pump. Like furnaces, gas- and oil-
power and a switch at the furnace, and a gas line will need to be
provided from the gas source. 䊏 fired boilers must be vented. To prevent damage to the sys-
tem, an expansion tank and an air ejector are located on the
Another type of residential heating is radiant heating. supply side of the boiler. A supply manifold with valves and
Radiant heating uses hot water circulating in flexible plastic return manifold allow the boiler to provide water for multi-
tubing located in the floor to warm the floor, which in turn ple heating circuits. The temperature of each circuit may be

FIGURE 14-6 Equipment for Radiant Heating


184 CHAPTER FOURTEEN

FIGURE 14-7 Pipe Spacing for Example 14-2

individually controlled. The equipment for a typical radiant The length of pipe needed for a 180-degree turn is 1.6 feet
heating system is shown in Figure 14-6. Radiant heating sys- (␲ ⫻ 0.5!ft). Nine 180-degree turns are needed. The length of pipe
tems cannot be used to cool the space; therefore, a separate needed for a 90-degree turn is 0.8 feet (␲ ⫻ 0.5!ft>2). Two 90-degree
cooling system must be included if cooling is required. turns are needed. The total length of pipe (including the 40 feet
needed to connect to the boiler) is calculated as follows:
The takeoff of a radiant heating system uses the same
principles as that for plumbing and is shown in the following Length ⫽ 9!ft ⫹ 8.25!ft ⫹ 9(7.75!ft) ⫹ 9(1.6!ft) ⫹ 2(0.8!ft) ⫹ 40!ft
examples. Length ⫽ 143!ft 䊏

EXAMPLE 14-2 EXAMPLE 14-3


Determine the piping needed for a radiant heating system for a Determine the HVAC equipment needed for a radiant heat system
10-foot by 10-foot room. The pipe spacing is shown in Figure 14-7. for a residence with six heating circuits.
Allow 40 feet of pipe to connect the pipe in the room to the boiler.
Solution: The following equipment is needed: one boiler, one ex-
Solution: The radius on the bends will be one-half of the pipe pansion tank, one air ejector, one pump, two manifolds with six
spacing, or 6 (12>2) inches. The pipe along the south wall will begin outlets, and six valves. 䊏
its turn 1 foot from the wall, which equals the distance of the west
pipe from the west wall (6 inches) plus the radius of the turn Other types of heating and cooling used in residences in-
(6 inches). Nine feet of pipe will be needed for this pipe.
clude through-the-wall heat pumps, heat pumps that include
The pipe along the west wall will begin 1 foot from the south
wall and will begin its turn 9 inches from the north wall. Eight feet
ductwork, electric baseboard heaters, and swamp coolers.
3 inches (8.25 ft) of pipe will be needed for this pipe. In addition to heating and cooling equipment, resi-
The remaining pipes running north-south will begin their turn dences may include gas fireplaces, gas piping, exhaust fans,
18 inches from the south wall and will begin their turn 9 inches from and temperature controls. Gas piping is bid using the proce-
the north wall. Each of these pipes will require 7 feet 9 inches (7.75 ft) dures used to bid pipe in Chapters 12 and 13.
of pipe. The distance from the pipe along the west wall to the pipe
along the east wall is 9 feet (10 feet - 6 inches - 6 inches). Because we
have already accounted for the pipe at the west end, we will use COMMERCIAL HVAC
Eq. (4-2) to determine the number of pipes as follows: SYSTEMS
!9!ft Small commercial buildings (such as buildings in strip malls)
Number ⫽ ⫽9
1!ft and churches, often use HVAC systems similar to that of the
The number of pipes running north-south must be an even residential system shown in Figures 14-1 and 14-2, using
number for the supply and return to enter the room at the same multiple units as the building gets larger. Larger single-story
point. We have 10 pipes (9 ⫹ 1). buildings often use a roof-top unit (sometimes referred to as
Heating, Ventilation, and Air-conditioning (HVAC) 185

a package unit) that heats or cools the air and then distributes Solution: The HVAC system requires one air handler and two
it through the building using ductwork. A package unit is VAV boxes. Beginning with the air handler, the following duct is
similar to a central heating and air-conditioning system, needed: 6 feet of 12-inch-diameter duct with one 45-degree, 8-inch-
except that it combines the heating and air-conditioning diameter boot attached; one 45-degree, 8-inch-diameter elbow;
9 feet of 8-inch-diameter duct with one 6-inch-diameter boot at-
equipment into a single unit. As buildings get taller it be-
tached; one 8-inch-diameter to 6-inch-diamter reducer; 11 feet of
comes impractical to use ductwork for all of the air require-
6-inch-diameter duct; one 90-degree, 6-inch-diameter elbow; one
ments because the duct would take up an enormous amount 12-inch-diameter to 10-inch-diameter reducer; 6 feet of 10-inch-
of space. In these cases, the heating and cooling is accom- diameter duct; one 90-degree, 10-inch-diameter elbow; 6 feet of
plished by heating or cooling water at a central point, distrib- 10-inch-diameter duct with a 6-inch-diameter boot attached; one
uting the water to the point where heating and cooling is 10-inch-diameter to 8-inch-diameter reducer; 10 feet of 8-inch-
needed, transferring heat from the water to air (or air to the diameter duct with a 6-inch-diameter boot attached; one 8-inch-
water when cooling is needed) by use of a heat exchanger, diameter to 6-inch-diameter reducer; 6 feet of 6-inch-diameter
and, finally, distributing the air to the needed areas, often by duct; one 90-degree, 6-inch-diameter elbow; five 2-foot-long 6-inch-
blowing the air through ductwork using a fan. An air handler diameter flexible duct with two clamps each; and five diffusers. In
combines a heat exchanger and fan to perform this function. addition, two thermostats with wiring are needed. The calculation
of wiring is covered in Chapter 15. To connect the air handler to the
In each of these cases, the heating and cooling equipment and
supply and return lines two 2– ⫻ 2– ⫻ 1– copper tees and two
ductwork are bid using the same procedure as for a residen-
4-foot-long pieces of copper pipe are needed. 䊏
tial system, and the water piping is bid using the procedures
in Chapter 13. Often a commercial HVAC system uses the Many commercial buildings use fin-tube convectors
plenum, the space between a dropped ceiling and the roof or along the exterior walls of the building below the windows to
floor above, as the return air pathway. When this is done, re- assist in heating the building. The fin-tube convector uses a
turn-air grilles are provided in the ceiling. Commercial sys- fin-tube to transfer heat from a pipe carrying hot water to
tems may include a wide variety of equipment including the surrounding air. Convection, the rising of hot air and the
chillers, boilers, dampers, fans, and variable-air-volume falling of cool air, is used to move air past the fin-tube con-
(VAV) boxes. The takeoff of a commercial HVAC system is vector. A fin-tube convector is shown in Figure 14-9.
shown in the following example. The takeoff of for fin-tube convectors uses the same
principles as those for plumbing and is shown in the follow-
ing example.
EXAMPLE 14-4
Determine the HVAC components needed for the commercial ten-
EXAMPLE 14-5
ant finish shown in Figure 14-8. Two feet of 6-inch-diameter flexi-
ble duct is used to connect the diffuser to the ductwork. The Determine the HVAC components needed for the fin-tube convec-
plenum is used for return air. The existing supply and return lines tors shown in Figure 14-10. The supply lines are run into the bot-
are made of copper. tom of the fin-tube convectors from the floor below.

FIGURE 14-8 HVAC for Example 14-4


186 CHAPTER FOURTEEN

Solution: The supply line (beginning at the exiting line) requires


one 2– ⫻ 2– ⫻ 1– copper tee, one piece of 1-inch-diameter pipe
approximately 26 feet long to connect (from supply to interior
wall), one 1– 90-degree elbow, one piece of 1-inch-diameter pipe
1 foot long, one 1– ⫻ 1– ⫻ 1– copper tee, one piece of 1-inch-
diameter pipe 11 feet long, one 1– ⫻ 1– ⫻ 1– copper tee, one piece
of 1-inch-diameter pipe 11 feet long, one 90-degree elbow, and
three pieces of 1-inch-diameter pipe 2 feet long to connect the fin-
tube convectors to the tees and elbow.
The return line (beginning at the exiting line) requires one
2– ⫻ 2– ⫻ 1– copper tee, one piece of 1-inch-diameter pipe ap-
proximately 26 feet long to connect (from supply to interior wall),
one 1– 90-degree elbow, one piece of 1-inch-diameter pipe 11 feet
long, one 1– ⫻ 1– ⫻ 1– copper tee, one piece of 1-inch-diameter
pipe 11 feet long, one 1– ⫻ 1– ⫻ 1– copper tee, one piece of 1– pipe
11 feet long, one 90-degree elbow, and three pieces of 1-inch-diameter
pipe 2 feet long to connect the fin-tube convectors to the tees and
elbow.
Three 10-foot 10-inch-long fin-tube convectors will be
needed. 䊏

FIGURE 14-9 Fin-Tube Convector

FIGURE 14-10 HVAC for Example 14-5

CONCLUSION PROBLEMS
Heating, ventilation, and air-conditioning (HVAC) systems 1. Determine the HVAC components needed for the resi-
consist of equipment, ductwork, and piping used to heat and dence in Figure 14-11. The furnace includes an air condi-
ventilate buildings and to condition (cool and dry) the air. tioner. A 2– ⫻ 12– register is required at each of the base
Many components are bid as a counted item, including short cabinets and a 6– ⫻ 18– grille is needed at the beginning of
runs of duct and pipe. Longer runs of duct and pipe are bid each return air. The distance from the top of the furnace to
as a linear good. the roof is 22 feet. The vent pipe is 4 inches in diameter.
Heating, Ventilation, and Air-conditioning (HVAC) 187

FIGURE 14-11 HVAC for Problem 1

2. Determine the piping needed for a radiant heating sys- 3. Determine the HVAC components needed for the com-
tem for an 11-foot by 14-foot room. The pipe spacing is mercial tenant finish shown in Figure 14-12. Two feet
shown in Figure 14-7. Allow 65 feet of pipe to connect of 6-inch-diameter flexible duct is used to connect the
the pipe in the room to the boiler. diffuser to the ductwork. The plenum is used for return

FIGURE 14-12 HAVC for Problem 3


188 CHAPTER FOURTEEN

air. The existing supply and return lines are made of 5. Determine the HVAC components needed to complete
copper. the Johnson Residence given in Appendix F. The furnace
4. Determine the HVAC components needed for the fin- includes an air conditioner.
tube convectors shown in Figure 14-13. The supply lines 6. Determine the HVAC components needed to complete
are run into the bottom of the fin-tube convectors from the West Street Video project given in Appendix F.
the floor below.

FIGURE 14-13 HVAC for Problem 4


CHAPTER FIFTEEN

ELECTRICAL

In this chapter you will learn how to apply the principles in Residential wiring is run horizontally or vertically in the
Chapter 4 to electrical systems. Whole books have been written walls and diagonally through ceiling spaces. When calculat-
on estimating electrical systems; therefore, this chapter will ing the needed length of wiring, the estimator must not only
limit its scope to the basics of estimating electrical systems. This take into account the horizontal distance between electrical
chapter includes example takeoffs from the residential garage devices, but must take into account the length of wire
drawings. needed to run the wire vertically within the walls and make
connections to the electrical devices. Many residential esti-
mators include a standard length of wire for each duplex

T
outlet, light fixture, and switch rather than determine the
he electrical system can be divided into two parts:
needed length of wire. When this is done, the wiring is being
(1) electrical devices such as light fixtures, outlets,
bid as a quantity-from-quantity good. Estimating the wire
panels, transformers, starters, motors, motor con-
length is shown in the following example.
trols, and so forth and (2) the wiring that connects the de-
vices. Electrical devices are typically bid as counted items;
therefore, estimating the electrical devices is simply a matter EXAMPLE 15-1
of locating them and counting them up. Estimating the
Determine the number of devices and wiring needed to complete
wiring is more difficult. For the wiring the estimator must
the lighting shown in Figure 15-1. The light fixtures are to be re-
determine the length of wiring and, if included, the conduit cessed-can fixtures. The outlet is existing and will be used to supply
carrying the wire. To simplify the preparation of an estimate, the power to the lighting. Use Romex with #12 wires. The ceiling
sometimes the wiring is bid as a quantity-from-quantity height is 9 feet.
good. Let’s look how to estimate the wiring.

RESIDENTIAL WIRING
The most common wiring used in residential wiring is
Romex, in which two or three conductors and a ground wire
are sheathed in a plastic sheathing. Wiring for duplex outlets
and lights consists of two #12 or #14 wires and a ground,
with three #12 or #14 wires and a ground being run between
three-way switches. Most dryers, ranges, cook tops, air con-
ditioners, and electrical heaters run on 220 volts and require
three conductors and a ground wire. Typically a range or an
oven requires a 40-ampere breaker with #8 copper wires, and
air conditioners and dryers require a 30-ampere breaker
with #10 copper wires. All electrical equipment must be
sized by the required volt-amp rating for the appliance and
per code requirements. FIGURE 15-1 Electrical Plan

189
190 CHAPTER FIFTEEN

Solution: The lighting will require four can lights with trim and wiring between the outlet and the switch is 7 ft (2 ft ⫹ 3 ft ⫹ 2 ft).
light bulbs and two three-way switches with single-gang boxes and The lighting will require 42 feet (23 ft ⫹ 12 ft ⫹ 7 ft) of wire with
covers. The outlet is already there. The distances between the elec- two #12 wires and a ground. The wiring between switches will re-
trical devices are shown in Figure 15-2. When preparing an esti- quire three #12 copper wires with a ground and must be run
mate, these distances would be taken off using a scale, a plan mea- through the wall rising over the door frame or must be run in the
surer, or software takeoff package. ceiling space. If the wire is run through the ceiling space, it will
The wiring between the right switch and the lights and outlet need to be run 6 vertical feet in the wall to go from the switch to the
is to be two #12 copper wires with a ground. When figuring this ceiling space at both ends. The lighting will require 25 feet (6 ft ⫹
wiring we add 1 foot to each end of the wire to allow the wiring to 11 ft ⫹ 6 ft ⫹ 2 ft) of wire with three #12 copper wires and a
be secured to the framing and connected to the electrical device. ground. In addition, wire nuts are needed to connect the wires, and
The wiring between lights can be run in the ceiling spaces. The staples are needed to secure the wires to the framing. 䊏
length of wiring between the light fixtures is calculated as follows:
Length ⫽ (6.33!ft ⫹ 2!ft) ⫹ (4.33!ft ⫹ 2!ft)
⫹ (6.33!ft ⫹ 2!ft) ⫽ 23!ft COMMERCIAL WIRING
The wiring between the switch and the light will need to run 6 ver- From an estimator’s point of view, commercial wiring differs
tical feet in the wall to go from the switch to the ceiling space. The from residential wiring in a number of key ways, including the
length of wiring between the switch and the light fixture is 12 feet following: (1) all commercial wiring must be run in conduit
(4 ft ⫹ 6 ft ⫹ 2 ft). The wiring from the outlet to the switch will or raceways (except for low-voltage wiring), (2) the wiring is
need to run 3 feet vertically and 2 feet horizontally. The length of usually run parallel to the side of the building or structure
within the ceiling spaces, increasing the length of the wire
needed, (3) the design of the wiring is better defined, (4) com-
mercial wiring is more extensive and services more equip-
ment, and (5) commercial wiring includes multiple electrical
panels. When estimating commercial wiring, the estimator
must include the conduit, boxes, connector between the con-
duit and boxes, electrical devices, and wiring. The conduit
may be ridged or flexible. As is the case with residential wiring,
the estimator must take into account not only the horizontal
distance between electrical devices, but also the length of wire
needed to run the wire vertically within the walls and make
connections to the electrical devices.
Figure 15-3 shows the typical wiring for a fluorescent
light fixture in a dropped acoustical ceiling. To complete this
light fixture, not only do the conduit and wiring need to be
run to the fixture, but at each fixture the following items are
needed: a junction box with a cover, two set-screw/threaded
FIGURE 15-2 Distances between Electrical Devices connectors to connect the ridged conduit to the box, two

FIGURE 15-3 Wiring for a Fluorescent Light Fixture


Electrical 191

FIGURE 15-4 Electrical Plan

set-screw/threaded connectors to connect the flexible conduit, are used to center the fixtures in the hall. Four set-screw/threaded
and a length of flexible conduit whose length will depend on connectors are needed to connect the flexible conduit to the junc-
the difference in elevation between the ridged conduit and the tion boxes and the light fixtures. In addition, fasteners to secure the
dropped ceiling. Estimating commercial electrical compo- conduit in place are needed. The material the conduit is being fas-
tened to will determine the type of fastener used.
nents and wiring is shown in the following examples.
Allow for an extra foot of wire on both ends of each wire. Forty
feet (38 ft ⫹ 2 ft) of red wire are needed to connect the switches.
EXAMPLE 15-2 Similarly, 40 feet of black wire are needed to connect the switches.
Sixteen feet (9 ft ⫹ 5 ft ⫹ 2 ft) of black wire are needed to connect the
Determine the number of electrical devices, conduit, and wiring right switch to the junction box above the right light fixture. Twelve
needed to complete the lighting shown in Figure 15-4. The light fix- feet (10 ft ⫹ 2 ft) of black wire are needed to connect the junction
tures are to be 120-volt, 4-foot by 2-foot fluorescent light fixtures boxes together, and 7 feet (5 ft ⫹ 2 ft) of black wire are needed at each
with three bulbs. The power will be provided to the light switch on light fixture to connect the junction boxes to the light fixtures. A total
the left. Use #12 copper wires in a 1>2-inch conduit. The ceiling of 82 feet (40 ft ⫹ 16 ft ⫹ 12 ft ⫹ 7 ft ⫹ 7 ft) of black wire is needed.
height is 9 feet, and the conduit will be run at a height of 12 feet. For the white wire, 16 feet is needed to connect the left switch to the
Solution: The lighting will require two 120-volt, 4-foot by 2-foot junction box above the left light fixture, 12 feet is needed to connect
fluorescent light fixtures, six fluorescent light bulbs, two junction the junction boxes, and 7 feet is needed at each light fixture to con-
boxes with covers, and two three-way switches with single-gang nect the junction boxes to the light fixtures, for a total of 42 feet (16 ft
boxes and covers. Two hot wires will need to be run between the ⫹ 12 ft ⫹ 7 ft ⫹ 7 ft). For the green ground wire, 16 feet is needed at
switches, a hot wire will need to be run between the right light each end to connect the switches to the junction boxes, 12 feet is
switch and the two light fixtures, a common wire will need to be needed to connect the junction boxes, and 7 feet is needed at each
run between the two light fixtures and the left light switch, and a light fixture to connect the junction boxes to the light fixtures, for a
ground wire will need to be run to the switches and fixtures. The total of 58 feet (16 ft ⫹ 16 ft ⫹ 12 ft ⫹ 7 ft ⫹ 7 ft). 䊏
wiring diagram for the lights is shown in Figure 15-5.
Ridged conduit will be run from the switch at one end of the EXAMPLE 15-3
hall to the switch at the other end of the hall, passing through two
junction boxes. The conduit can be bent in a radius to change direc- Determine the electrical components needed to complete the elec-
tions. Nine feet of conduit is required at both switches to go from trical distribution system (excluding wire from the panelboards)
the switch to the height of 12 feet. Thirty-eight feet of conduit are for the schematic shown in Figure 15-6. The distance to the meter is
needed (9 ft ⫹ 20 ft ⫹ 9 ft) as well as 6 set-screw/threaded connec- 60 feet through a 3 1>2-inch conduit that includes three 90-degree
tors, which are used to connect the ridged conduit to the junction elbows. The wireway is 5 feet long, and the three panels are
boxes and single-gang boxes. Two 5-foot lengths of flexible conduit mounted 1 foot above the wireway. The panelboard schedules are
are needed to run from the junction boxes to the light fixtures and shown in Figures 15-7 through 15-9.

FIGURE 15-5 Wiring Diagram


192 CHAPTER FIFTEEN

The information for the panelboards, wiring size servicing the


panelboards, and conduit sizes are found at the top of each panel
schedule. For Panel P, a 120>208 three-phase 225-ampere panel-
board with 30 spaces is needed. The panel is serviced by three #4/0
(0000) wires and one #12 wire. Each of these wires will need to be
approximately 70 feet long to allow 2 feet for connection in the
panelboard and meter, wire in the conduits, and wireway. The pan-
elboard is connected to the wireway by 1 foot of 2-inch conduit
with two 2-inch set-screw/threaded connectors. The rated amps
and number of poles for the circuit breakers are specified in the
“CB A-P” column of the panel schedules. The following breakers
FIGURE 15-6 Distribution Schematic are needed for Panel P: two 90-ampere three-pole, one 35-ampere
three-pole, one 30-ampere three-pole, three 30-ampere single-pole,
two 25-ampere single-pole, one 20-ampere single-pole, and three
Solution: Beginning at the meter, 60 feet of 3 1>2-inch conduit, 30-ampere double-pole breakers.
three 3 1>2-inch 90-degree elbows, two 3 1>2-inch set-screw/threaded For Panel L, a 120>208 three-phase 150-ampere panelboard
connectors (to connect the conduit to the meter and wireway), and with 30 spaces is needed. The panelboard is connected to the wire-
one 5-foot wireway are needed to house the wiring from the meter way by 1 foot of 1 1>2-inch conduit with two 1 1>2-inch set-
to the panelboards. screw/threaded connectors. The panel is serviced by four #1>0 (0)

FIGURE 15-7 Panel P Schedule


Electrical 193

FIGURE 15-8 Panel L Schedule

wires approximately 70 feet long. The panel requires twenty 20- Solution: We begin with the service from the house to the garage.
ampere single-pole circuit breakers. To install this service we need to run a metal conduit down the side
For Panel D, a 120>208 three-phase 150-ampere panelboard of the house, run PVC conduit from the house to the garage, and
with 30 spaces is needed. The panelboard is connected to the wire- install the panel with breakers in the garage. From the site plan, the
way by 1 foot of 1 1>2-inch conduit with two 1 1>2-inch set- horizontal distance between the panel at the house and the panel at
screw/threaded connectors. The panel is serviced by four #1>0 (0) the garage is 33 feet. The wire will need to be buried 18 inches in the
wires approximately 70 feet long. The panel requires twenty-three ground, and the boxes are mounted about 4 feet off of the ground,
20-ampere single-pole circuit breakers. 䊏 requiring at least 6 additional feet of wire at each end. To be safe we
will order 50 feet of wire. The quantity takeoff for the service is as
shown in Table 15-1. The conduit stops at the bottom of the garage
SAMPLE TAKEOFF FOR THE wall and the wire will be run exposed through the wall to the panel
RESIDENTIAL GARAGE in the garage. Next, we prepare the quantity takeoff for the electrical
devices in the garage, exclusive of wiring. The items needed are
A sample takeoff from a set of plans is shown in the follow- shown in Table 15-2. Next, we prepare the quantity takeoff for the
ing example. electrical wiring. The wire is to be Romex with two #12 copper
wires and a ground. The wiring distances for the outlets are shown
in Figure 15-10. There are two outlet circuits; therefore, the outlet
EXAMPLE 15-4
for the overhead door and two wall outlets are connected on one
Prepare a quantity takeoff for the electrical system for the residen- circuit and the remaining two wall outlets are connected on the
tial garage given in Appendix F. other circuit.
194 CHAPTER FIFTEEN

FIGURE 15-9 Panel D Schedule

TABLE 15-1 Quantity Takeoff for Service


Quantity Item Use
1 ea Meter tap Connect wire to existing meter
1 ea 1 1>4– set-screw/threaded connector Connect conduit to existing meter
10 ft 1 1>4– conduit Comes in 10-ft lengths
1 ea 1 1>4– compression/male threaded coupling Connect ridged conduit to PVC conduit
1 ea 1 1>4– slip/female threaded PVC coupling Connect ridged conduit to PVC conduit
2 ea 1 1>4– PVC 90-degree sweep Turn from horizontal to vertical at both ends
40 ft 1 1>4– PVC conduit Run wire underground
50 ft 3 ea #4 copper wire with ground Wire from meter to panel
1 ea 70-ampere single-phase panel with main breaker slot Panel for garage
1 ea 70-ampere main breaker Main breaker for panel
1 ea 20-ampere breaker Breaker for lighting
2 ea 20-ampere GFCI breaker Breakers for outlets
1 ea 6⬘ copper ground rod Ground rod per plan
Electrical 195

TABLE 15-2 Quantity Takeoff for Electrical


Devices
Quantity Item Use
3 ea Octagon box Exterior lights
2 ea Single-gang box Fluorescent lights
5 ea Single-gang box Outlets
5 ea Duplex outlets Outlets
4 ea Outlet covers Interior outlets
1 ea Weatherproof outlet Exterior outlet
cover
1 ea Quad-gang box Switches
1 ea Quad-gang switch cover Switches
4 ea Single-pole switches Switches
2 ea Four-tube fluorescent Interior light fixtures
FIGURE 15-10 Horizontal Wiring Distances for Outlets
fixtures
8 ea 4 ¿ fluorescent light bulbs Interior light fixtures
to be run 7 feet up the wall, 17 feet across the ceiling, and 7 feet
3 ea Brass coach lights Exterior light fixtures down the wall, and it will require 2 feet for connections at the out-
3 ea 100-w light bulbs Exterior light fixtures lets, for a total of 33 feet. The wire from the panel to the outlet on
the inside of the south wall will need to be run 3 feet down the
wall, and 10 feet along the wall, and it will require 3 feet for connec-
One foot of wire is allowed for each connection and 2 feet of tions at the panel and outlet, for a total of 16 feet. The wire from the
wire is allowed at the panel. The wire from the panel to the over- outlet on the inside of the south wall to the outside outlet will need
head door outlet will need to be run 5 feet up the wall and 13 feet to be run 9 feet along the wall and 2 feet up the wall and it will re-
across the ceiling and will require 3 feet for connections at the quire 2 feet for connections at the outlets, for a total of 13 feet. The
panel and outlet, for a total of 21 feet. The wire from the overhead total length of wire needed for the outlets is 110 feet (21 ft ⫹ 27 ft
door outlet to the outlet on the east wall will need to be run 18 feet ⫹ 33 ft ⫹ 16 ft ⫹ 13 ft).
across the ceiling and 7 feet down the wall and will require 2 feet The wiring distances for the lights are shown in Figure 15-11.
for connections at the outlets, for a total of 27 feet. The wire from One foot of wire is allowed for each connection and 2 feet of wire is
the outlet on the east wall to the outlet on the north wall will need allowed at the panel. The wire from the panel to the switches is run

FIGURE 15-11 Horizontal Wiring Distances for Lights


196 CHAPTER FIFTEEN

TABLE 15-3 Quantities for Residential Garage


26-100 Electrical
Meter tap 1 ea Duplex outlets 5 ea
1 1>4– set-screw/threaded connector 1 ea Outlet covers 4 ea
1 1>4– conduit 10 ft Weatherproof outlet cover 1 ea
1 1>4– compression/male threaded coupling 1 ea Quad-gang box 1 ea
1 1>4– slip/female threaded PVC coupling 1 ea Quad-gang switch cover 1 ea
1 1>4– PVC 90-degree sweep 2 ea Single-pole switches 4 ea
1 1>4– PVC conduit 40 ft Four-tube fluorescent fixtures 2 ea
Install conduit 40 ft 4 ¿ fluorescent light bulbs 8 ea
3 ea #4 copper wire with ground 50 ft Brass coach lights 3 ea
70-ampere single-phase panel with main 1 ea 100-w light bulbs 3 ea
70-ampere main breaker 1 ea 250 ¿ roll 2 #12 with ground Romex 1 ea
20-ampere breaker 1 ea NM/SE cable connectors 3 ea
20-ampere GFCI breaker 2 ea Electrical staples 1 box
6⬘ copper ground rod 1 ea Red wire nuts 1 bag
Install panel 1 ea Install light fixture 5 ea
Octagon box 3 ea Install outlet 5 ea
Single-gang box 7 ea Install switch 4 ea

20 feet and will require 3 feet for connections at the panel and out- and 2 feet down the wall and will require 2 feet for connections at
let, for a total of 23 feet. The wire from the switch to the north inte- ends, for a total of 26 feet. The wire from the switch to the light on
rior light will need to be run 5 feet up the wall and 17 feet across the the south exterior wall of the garage will need to be run 4 feet up
ceiling and will require 2 feet for connections at ends, for a total of the wall and will require 2 feet for connections at ends, for a total of
24 feet. The wire from the switch to the south interior light will 6 feet. The total length for wire needed of the lighting is 124 feet
need to be run 5 feet up the wall and 8 feet across the ceiling and (23 ft ⫹ 24 ft ⫹ 15 ft ⫹ 30 ft ⫹ 26 ft ⫹ 6 ft). Six feet of wire are
will require 2 feet for connections at ends, for a total of 15 feet. The needed to connect the panel to the ground rod.
wire from the switch to the light on the south side of the overhead A 250-foot roll of Romex is needed for the wiring. In addition,
door will need to be run 5 feet up the wall, 21 feet across the ceiling, three NM/SE cable connectors to secure the Romex to the panel, a
and 2 feet down the wall and will require 2 feet for connections at box of electrical staples to secure the Romex to the framing, and a
ends, for a total of 30 feet. The wire from the light on the south side bag of red wire nuts to connect the wires are needed.
of the overhead door to the light on the north side of the overhead The quantities needed for the garage, grouped by the cost
door will need to be run 2 feet up the wall, 20 feet across the ceiling, codes in Appendix B, are shown in Table 15-3. 䊏

CONCLUSION PROBLEMS
The electrical system consists of electrical devices such as 1. Determine the number of electrical devices needed to
light fixtures, outlets, panels, transformers, starters, motors, complete the electrical system in Figure 15-12. The light
motor controls, and so forth and the wiring that connects fixtures are to be 9-inch mushroom light fixtures.
the devices. Electrical devices are typically bid as counted 2. Determine the wiring needed to complete the electrical
items. For the wiring the estimator must determine the system shown in Figure 15-12. Forty feet of wire are
length of wiring and the conduit, including connectors, car- needed to run from the top-right corner of the room to
rying the wire. The estimator must also include fasteners the panel. All wiring in the room is to be run on the
used to secure the wire or conduit and wire nuts used to con- same circuit and is to be run with #12 Romex. The ceil-
nect the wires. ing height is 8 feet.
Electrical 197

FIGURE 15-12 Electrical Plan

3. Determine the number of electrical devices needed to from the panelboards) for the schematic shown in
complete the lighting shown in Figure 15-13. The light Figure 15-6. The distance to the meter is 35 feet through
fixtures are to be 120-volt, 4-foot by 2-foot fluorescent a 2 1>2-inch conduit that includes three 90-degree el-
light fixtures with three bulbs. bows. The wireway is 5 feet long, and the three panels
4. Determine the conduit and wiring needed to complete are mounted 2 feet above the wireway. The panelboard
the lighting shown in Figure 15-13. Assume that power schedules are shown in Figures 15-14 through 15-16.
will be provided to the light switches and #12 wires will 6. Determine electrical devices and wiring needed for the
be used. The ceiling height is 9 feet and the conduit will Johnson Residence given in Appendix F.
be run at a height of 12 feet. 7. Determine the electrical devices, conduit, and wiring
5. Determine the electrical components needed to com- needed for the West Street Video project given in
plete the electrical distribution system (excluding wire Appendix F.

FIGURE 15-13 Electrical Plan


198 CHAPTER FIFTEEN

FIGURE 15-14 Panel P Schedule

FIGURE 15-15 Panel L Schedule


Electrical 199

FIGURE 15-16 Panel D Schedule


CHAPTER SIXTEEN

EARTHWORK

In this chapter you will learn about the characteristics of soils The water content of the soils is important to the estima-
as they relate to excavation and how to estimate excavation tor because the soils must meet specific water content re-
using the geometric method, average-width-length-depth quirements for the soils to properly compact. Soils that are
method, average-end method, modified-average-end method, too wet will need to be dried out before compaction, whereas
and cross-sectional method. It also includes example takeoffs soils that are too dry will require the addition of moisture.
from the residential garage drawings. The dry unit weight is important to the estimator be-
cause it can be used to describe how the volume of the soil
changes as it is excavated, transported, and compacted.

B efore we can learn about estimating excavation


quantities, we must first understand the basic char-
acteristics of soils. SWELL AND SHRINKAGE
During the excavation and placement process, the volume of
the soils changes. The volume of the soils can be described in
CHARACTERISTICS OF SOILS three conditions: bank (or in situ), loose, and compacted.
Soils are made up of three basic components: solids, water, These conditions are shown in Figure 16-1. The bank or in
and air. The composition of a soil may be described by four situ condition describes the conditions of the soil before it
terms: wet unit weight (or wet density), dry unit weight (or has been excavated.
dry density), unit weight of water, and water content. When soils are excavated they swell, their volume in-
The wet unit weight describes the density of the soil, creases, and their density decreases. Soils that have been ex-
both the solids and the water. The wet unit weight is calcu- cavated and have not been placed are described as being in a
lated by dividing the total weight of the soil (solids and loose condition. Soils are transported in the loose condition.
water) by the total volume of the soil and is expressed in The relationship between the bank and loose conditions
pounds per cubic foot or pounds per cubic yard. is described as the swell percentage. The swell, or the amount
The dry unit weight describes the density of the solid the volume increases as the soils are excavated, is calculated
portion of the soil. The dry unit weight is calculated by di- using the following equation:
viding the weight of the solids by the total volume of the soil
Swell!% ⫽ a
DB
and is expressed in pounds per cubic foot or pounds per ⫺ 1b100 (16-1)
DL
cubic yard. The dry unit weight is used to measure how well
the soil is compacted. where
The unit weight of water is the weight of the water in the DB ⫽ Bank Dry Density (Unit Weight)
soil and is expressed in pounds per cubic foot. The unit
DL ⫽ Loose Dry Density (Unit Weight)
weight of water equals the wet unit weight less the dry unit
weight. Another way of describing the swell percentage is to
The water content describes the relationship between imagine that we dig a hole and loosely place the excavated
the solids and the water in the soils and is the weight of the soil back in the hole, only to find that we have more soil than
water (not volume) expressed as a percentage of the weight fits in the hole. This additional soil is due to swell. This ex-
of the solids. ample is shown in Figure 16-2.
200
Earthwork 201

FIGURE 16-1 Volumes of Soils

FIGURE 16-3 Shrinkage Percentage

EXAMPLE 16-1
FIGURE 16-2 Swell Percentage
A soil has a bank dry density of 110 pounds per cubic foot, a loose
dry density of 80 pounds per cubic foot, and a compacted dry den-
When soils are placed and compacted, their volume de- sity of 115 pounds per cubic foot. Determine the swell percentage
and shrinkage percentage for the soil.
creases and their density increases. This decrease in volume
is measured against the original volume of the soils in the Solution: The swell percentage is calculated using Eq. (16-1) as
bank condition. Soils that have been placed as backfill are follows:
described as being in the compacted condition. 110!lb/ft3
The relationship between the bank and compacted con- Swell!% ⫽ a ⫺ 1b100 ⫽ 37.5%
80!lb/ft3
ditions is described as the shrinkage percentage. The shrink-
age percentage is calculated using the following equation: The shrinkage percentage is calculated using Eq. (16-2) as follows:
110!lb/ft3
Shrinkage!% ⫽ a1 ⫺
DB
b100 (16-2) Shrinkage!% ⫽ a1 ⫺ b100 ⫽ 4.3% 䊏
DC 115!lb/ft3

where The relationships between the bank volume (VB), the


DB ⫽ Bank Dry Density (Unit Weight) loose volume (VL), and the compacted volume (VC) are
DC ⫽ Compact Dry Density (Unit Weight) shown in Table 16-1. The relationships between the bank dry
density (DB), the loose dry density (DL), and the compacted
Another way of describing the shrinkage percentage is dry density (DC) of a soil are also shown in Table 16-1.
to imagine that we dig a hole and place the excavated soil The use of these equations is shown in the following
back in the hole, compacting as we go. When all of the soil is example.
placed in the hole we might find that the hole is not com-
pletely filled because we packed the soil at a higher level of
compaction than when it was in its bank condition. The un- EXAMPLE 16-2
filled volume is due to shrinkage. This example is shown in A construction project needs 1,000 cubic yards of compacted fill.
Figure 16-3. Soil with a swell percentage of 37.5% and a shrinkage percentage of
The calculation of the swell percentage and the shrink- 4.3% is to be used for the fill. How many cubic yards of soil must be
age percentage is shown in the following example. excavated? How many cubic yards of soil must be transported?
202 CHAPTER SIXTEEN

TABLE 16-1 Volume and Density Conversion To determine the volume of soil transported, we need to determine
Equations the loose volume. Compacted cubic yards (VC) are converted to
loose cubic yards (VL) using Eq. (16-4) as follows:
To Find From Use
a1 ⫹ b
37.5
100
VL ⫽ VB a1 ⫹ b
Swell!% VL ⫽ (1,000!yd3) ⫽ 1,437!yd3
VL VB (16-3)
a1 ⫺ b
4.3
100
100
a1 ⫹ b
Swell!%
Alternatively, the loose cubic yards (VL) can be calculated from the
100 previously determined bank cubic yards (VB) using Eq. (16-3) as
VL VC VL ⫽ VC (16-4)
a1 ⫺ b
Shrinkage!% follows:
100
b ⫽ 1,437!yd3
37.5
VL ⫽ (1,045!yd3)a1 ⫹ 䊏
VL 100
VB VL VB ⫽ (16-5)
a1 ⫹ b
Swell!%
Determining the volume of excavation is only an ap-
100 proximation or estimate of the actual volume of soils that
VC needs to be excavated because of variations in the surface of
VB VC VB ⫽ (16-6)
a1 ⫺ b
Shrinkage!% the area to be excavated and the inability of excavation equip-
100 ment to quickly excavate exact geometric shapes. In spite of
this, some methods of calculating excavation quantities are
a1 ⫺ b
Shrinkage!%
more accurate than others. Let’s begin by looking at the most
100 accurate of the methods, the geometric method.
VC VL VC ⫽ VL (16-7)
a1 ⫹ b
Swell!%
100 GEOMETRIC METHOD
VC ⫽ VB a1 ⫺ b
Shrinkage!%
VC VB (16-8) The geometric method breaks the excavation into geomet-
100 ric shapes and calculates the volume for each of the shapes.
DB The use of the geometric method is shown in the following
DL DB DL ⫽ (16-9)
a1 ⫹ b
Swell!% example.
100

a1 ⫺ b
Shrinkage!% EXAMPLE 16-3
100 A contractor needs to install a 16-foot by 26-foot by 8-foot-high
DL DC DL ⫽ DC (16-10)
a1 ⫹ b
Swell!% footing for a bridge. The bottom of the footing is to be 10 feet
below grade. The sides of the excavation need to be sloped 1:1
100
(horizontal:vertical). A 2-foot space between the footing and the sides
DB ⫽ DL a1 ⫹ b
Swell!% of the excavation must be provided to form the footing. Determine
DB DL (16-11) the volume of the excavation using the geometric method.
100

DB ⫽ DC a1 ⫺ b
Shrinkage!% Solution: The width of the excavation at the bottom is 20 feet (2 ft
DB DC (16-12) ⫹ 16 ft ⫹ 2 ft), and the length of the excavation at the bottom is
100
30 feet (2 ft ⫹ 26 ft ⫹ 2 ft). The width of the excavation is 20 feet
a1 ⫹ b
Swell!%
100
DC DL DC ⫽ DL (16-13)
a1 ⫺ b
Shrinkage!%
100
DB
DC DB DC ⫽ (16-14)
a1 ⫺ b
Shrinkage!%
100

Solution: To determine the soil excavated, we need to convert the


compacted volume to a bank volume. Compacted cubic yards (VC)
are converted to bank cubic yards (VB) using Eq. (16-6) as follows:
(1,000!yd3)
VB ⫽ ⫽ 1,045!yd3
a1 ⫺ b
4.3
100 FIGURE 16-4 Excavation Cross Sections
Earthwork 203

AVERAGE-WIDTH-LENGTH-
DEPTH METHOD
The average-width-length-depth method calculates the vol-
ume of excavation by multiplying the average width of the
excavation by the average length of the excavation by the av-
erage depth of the excavation using the following equation:
Volume ⫽ (Wave)(Lave)(Dave) (16-15)
The average depth of the excavation is measured at the
bottom of the excavation and does not include the side
slopes. This method produces an approximate volume and
is less accurate than the geometric method. The use of the
average-width-length-depth method is shown in the fol-
FIGURE 16-5 Excavation for Footing lowing example.

EXAMPLE 16-4
Determine the excavation volume for Example 16-3 using the aver-
age-width-length-depth method.
Solution: The average depth is 10 feet. Using the dimensions
from Figure 16-5, the average width and length are calculated as
follows:
(20!ft ⫹ 40!ft)
Wave ⫽ ⫽ 30!ft
2
(30!ft ⫹ 50!ft)
Lave ⫽ ⫽ 40!ft
2
The volume is calculated using Eq. (16-15) as follows:
1!yd3
Volume ⫽ (30!ft)(40!ft)(10!ft)a b ⫽ 444!yd3 䊏
27!ft3

FIGURE 16-6 Excavation for Footing

AVERAGE-END METHOD
wider at the top than at the base. Cross sections of the excavation
The average-end method calculates the volume by cutting
are shown in Figure 16-4. A three-dimensional representation of
cross sections through the excavation and determining the
the excavation is shown in Figure 16-5. This excavation can be di-
vided into a column, four prisms, and four pyramids as shown in area of cut and fill for each of the cross sections. The vol-
Figure 16-6. The volume of the column is calculated as follows: ume of cut or fill between two cross sections is equal to the
average of the two cross-sectional areas of the cut or fill
1!yd3
VolumeColumn ⫽ (30!ft)(20!ft)(10!ft)a b ⫽ 222!yd3 multiplied by the perpendicular distance between the cross
27!ft3 sections:
There are two different sizes of prisms. Their volumes are calcu- (A1 ⫹ A2)
lated as follows: Volume ⫽ L (16-16)
2
3
a b ⫽ 56!yd3
(30!ft)(10!ft)(10!ft) 1!yd
VolumePrism!1 ⫽ where
2 27!ft3
(20!ft)(10!ft)(10!ft) 1!yd3 L = Perpendicular Distance between the Cross
VolumePrism!2 ⫽ a b ⫽ 37!yd3 Sections
2 27!ft3
A1 = Area of Cross Section 1
The volume of the pyramids is calculated as follows:
A2 = Area of Cross Section 2
(10!ft)(10!ft)(10!ft) 1!yd3
VolumePyramid ⫽ a b ⫽ 12!yd3 When more than two cross sections are taken and the
3 27!ft3
distances between them are the same, the following equation
The total volume is calculated as follows: may be used to calculate the volume:
Volume ⫽ 222!yd3 ⫹ 2(56!yd3) ⫹ 2(37!yd3) ⫹ 4(12!yd3) Volume ⫽ L(0.5A1 ⫹ A2 ⫹ A3 ⫹ p ⫹ An⫺1 ⫹ 0.5An)
⫽ 456!yd 3
䊏 (16-17)
204 CHAPTER SIXTEEN

TABLE 16-2 Area of Cuts Solution: The cross sections will be cut at the top and bottom of
the excavation. Using the dimensions from Figure 16-5, the areas of
Station Cut (ft2) the top and bottom of the excavation are calculated as follows:
5⫹00 0 AreaTop ⫽ (40!ft)(50!ft) ⫽ 2,000!ft2
5⫹50 75 AreaBottom ⫽ (20!ft)(30!ft) ⫽ 600!ft2
6⫹00 110 The volume is calculated using Eq. (16-16) as follows:
6⫹20 0 (2,000!ft2 ⫹ 600!ft2) 1!yd3
Volume ⫽ (10!ft) a b ⫽ 481!yd3 䊏
2 27!ft3

where
L = Perpendicular Distance between the Cross MODIFIED-AVERAGE-END
Sections METHOD
A1 = Area of Cross Section 1 Equation (16-16) may be modified as follows:
A2 = Area of Cross Section 2
A1 ⫹ A2 ⫹ 1A1A2
A3 = Area of Cross Section 3 Volume ⫽ L!a b (16-18)
3
An = Area of Cross Section n
where
The average-end method produces an approximate vol-
L = Perpendicular Distance between the Cross
ume and is less accurate than the geometric method. The ac-
Sections
curacy is improved by increasing the number of cross
sections and locating cross sections at major changes in A1 = Area of Cross Section 1
grades. Historically, this method has been used for road con- A2 = Area of Cross Section 2
struction by cutting the cross sections perpendicular to the Equation (16-18) gives an answer closer to the answer
centerline of the road as shown in the following example. provided by the geometric method, although not mathemat-
ically identical. The use of the modified-average-end method
EXAMPLE 16-5 to calculate basement excavation is shown in the following
example.
Using the average-end method, determine the required excavation
for a new road giving the stations and their associated cuts shown
in Table 16-2. EXAMPLE 16-7
Solution: The distance between Stations 5+00 and 5+50 is 50 feet. Determine the excavation volume for Example 16-3 using the mod-
The distance between Stations 5+50 and 6+00 is 50 feet. The dis- ified-average-end method.
tance between Stations 6+00 and 6+20 is 20 feet. The volumes of
the cuts are calculated using Eq. (16-16) as follows: Solution: From Example 16-6, the area of the top is 2,000 ft2 and
the area of the bottom is 600 ft2. The volume is calculated using Eq.
(0!ft2 ⫹ 75!ft2 ) 1!yd3
a b ⫽ 69!yd3
(16-16) as follows:
Volume5⫹00!to!5⫹50 ⫽ (50!ft)
2 27!ft3
Volume ⫽
(75!ft2 ⫹ 110!ft2 ) 1!yd3
Volume5⫹50!to!6⫹00 ⫽ (50!ft) a b ⫽ 171!yd3 10!ft a
600!ft2 ⫹ 2,000!ft2 ⫹ 2(600!ft2)(2,000!ft2) 1!yd3
ba b
2 27!ft3 3 27!ft3
(110!ft2 ⫹ 0!ft2 ) 1!yd3
Volume6⫹00!to!6⫹20 ⫽ (20!ft) a b ⫽ 41!yd3 Volume ⫽ 456!yd2 䊏
2 27!ft3
The total volume is calculated as follows:
Volume ⫽ 69!yd3 ⫹ 171!yd3 ⫹ 41!yd3 ⫽ 281!yd3 䊏 CROSS-SECTIONAL METHOD
The cross-sectional method is most commonly used for cal-
The average-end method may also be used to calculate culation of site excavation on sites where the grade around
the volume of a basement excavation. When using this the building changes dramatically. Like the average-width-
method to calculate excavation volumes, a cross section length-depth method, the average-end method, and the
should be cut at each horizontal step on the excavation. The modified-average-end method, the cross-sectional method
use of the average-end method to calculate basement excava- produces an approximate volume and is less accurate than
tion is shown in the following example. the geometric method. The following steps need to be com-
pleted to calculate the volume using the cross-sectional
method:
EXAMPLE 16-6
Determine the excavation volume for Example 16-3 using the Step 1: Divide the site into grids.
average-end method. Step 2: Calculate the cut or fill at each grid intersection.
Earthwork 205

FIGURE 16-7 Site Plan

Step 3: Separate the cuts and fills with a zero line. site is divided into twelve 50-foot by 50-foot squares as
Step 4: Calculate the volume of the cuts and fills. shown in Figure 16-8.

Let’s look at each of these steps.


Step 2: Calculate Cut or Fill at Each
Step 1: Divide the Site into Grids Grid Intersection
The first step is to divide the proposed area or site into grids. The next step is to calculate the cut or fill at each grid inter-
The grids may be evenly spaced or aligned with site features. section where the grades are going to change. Often the
Figure 16-7 shows a site plan for the construction of a build- grades around the perimeter of the site are not going to
ing, with the existing grades to be changed drawn as dashed change; therefore, there is neither a cut nor a fill at these in-
lines and the proposed final grades drawn as solid lines. The tersections. The cut or fill is calculated by subtracting the

FIGURE 16-8 Grids


206 CHAPTER SIXTEEN

existing grade from the proposed grade using the following Solution: For the intersection at B2, the existing grade is 100.0
equation: and the proposed grade is 99.0. The cut or fill is calculated using
Eq. (16-19) as follows:
Cut>Fill ⫽ GradeProposed ⫺ GradeExisting (16-19)
Cut>FillB2 ⫽ 99.0 ⫺ 100.0 ⫽ ⫺1.0
If the result of Eq. (16-19) is positive, a fill (the adding
of soil) is required; if the result is negative, a cut (the removal Because the answer is negative, there is a cut of 1.0 foot at B2. For B3
the existing grade is 101.0 and the proposed grade is 99.0. For B4 the
of soil) is required. The existing and proposed grades are de-
existing grade is 102.0 and the proposed grade is 99.0. For C2 the
termined by estimating the existing or proposed elevation
existing grade is 98.0 and the proposed grade is 99.0. For C3 the ex-
from the contours or other information (for example, slab isting grade is 101.0 and the proposed grade is 99.0. For C4 the
elevation) on the drawings. When an intersection falls be- existing grade must be interpolated using Eq. (16-20). The distance
tween two grade lines, the grade at the intersection of the between the 101.0 contour line and the intersection is 50 feet, and
grid lines is estimated by interpolating between two adjacent the distance between the 101.0 and 102.0 contour lines is about
contour lines using the following equation: 75 feet. The grade at the intersection is calculated as follows:
(DistP⫺1) (50!ft)
GradeP ⫽ (Grade2 ⫺ Grade1) ⫹ Grade1 (16-20) GradeP ⫽ (102.0 ⫺ 101.0) ⫹ 101.0 ⫽ 101.7
(Dist2⫺1) (75!ft)

where The proposed grade at C4 is 99.0. The cuts and fills for the intersec-
GradeP = Grade at Intersection tions are calculated using Eq. (16-19) as follows:

Grade1 = Grade of First Contour Line Cut>FillB3 ⫽ 99.0 ⫺ 101.0 ⫽ ⫺2.0


Grade2 = Grade of Second Contour Line Cut>FillB4 ⫽ 99.0 ⫺ 102.0 ⫽ ⫺3.0
DistP-1 = Distance between the Intersection and the Cut>FillC2 ⫽ 99.0 ⫺ 98.0 ⫽ 1.0
First Contour Line Cut>FillC3 ⫽ 99.0 ⫺ 101.0 ⫽ ⫺2.0
Dist2-1 = Distance between the Second and First Cut>FillC4 ⫽ 99.0 ⫺ 101.7 ⫽ ⫺2.7 䊏
Contour Lines
This step is shown in the following example. The existing grades, proposed grades, and cut or fill for each
intersection are shown in Figure 16-9. The existing grades
are above and left of the intersection, the proposed grades
EXAMPLE 16-8 are below and left of the intersection, and the cuts or fills are
Determine the cuts and fills for the site plan shown in Figures 16-7 below and right of the intersections. The fills begin with the
and 16-8. The bottom of the building excavation is at 99.00 feet. letter “F” and the cuts begin with the letter “C.”

FIGURE 16-9 Cuts and Fills


Earthwork 207

Step 3: Separate the Cuts and Fills When the rectangle on a grid has three zeros, as is the
with a Zero Line case with rectangles 5 and 10 in Figure 16-9, the zero line is
drawn as shown in Figure 16-10. This condition often occurs
The next step is to draw a line between the cuts and fills. This is at boundaries.
referred to as a zero line because it represents the location Locating the zero line is shown in the following example.
where there is neither a cut nor a fill. Before drawing the zero
line, one needs to determine the points where cuts change into EXAMPLE 16-9
fills. A change will occur any time there is a cut and a fill next to
each other on the grid. For the site plan in Figure 16-9, this will Determine the location of the zero line for the site plan shown in
occur between points B2 and C2 and between points C2 and Figure 16-9.
C3. The location of the zero is determined by interpolating be- Solution: The distance from B2 to the zero line in the direction of
tween two adjacent intersections using the following equation: C2 is calculated using Eq. (16-21) as follows:
(Cut) (1.0)
DistC⫺0 ⫽ (DistC⫺F ) (16-21) DistC2⫺0 ⫽ (50!ft) ⫽ 25!ft
(Cut ⫹ Fill) (1.0 ⫹ 1.0)
where The distance from C3 to the zero line in the direction of C2 is cal-
DistC–0 ⫽ Distance from the Intersection with a Cut to culated using Eq. (16-21) as follows:
the Zero Line (2.0)
DistC2⫺0 ⫽ (50!ft) ⫽ 33!ft
DistC–F ⫽ Distance from the Intersection with a Cut to (2.0 ⫹ 1.0)
the Intersection with a Fill
The zero line for Figure 16-9 is drawn as shown in Figure 16-11. 䊏
Cut ⫽ Cut at the Intersection with a Cut (must be
positive)
Fill ⫽ Fill at the Intersection with a Fill Step 4: Calculate the Volume of the Cuts
and Fills
The next step is to calculate the volume of the cuts and the
fills. The volume of the cuts is calculated separately from
that for the fills. When a rectangle contains both cuts and
fills, the rectangle is divided into separate areas (a cut area
and a fill area) by the zero line as shown in Figure 16-11.
The volume of the cut for a rectangle equals the average of
the cuts and zeros surrounding the cut area within the

FIGURE 16-10 Zero Lines at Boundaries

FIGURE 16-11 The Zero Line


208 CHAPTER SIXTEEN

rectangle multiplied by the area of the cut area of the rectan- 0!ft ⫹ 0!ft ⫹ 2.7!ft ⫹ 3.0!ft 1!yd3
gle. Similarly, the volume of the fill for a rectangle equals the Volume8 ⫽ a b(50!ft)(50!ft)a b
4 27!ft3
average of the fills and zeros surrounding the fill area within ⫽ 132!yd3
the rectangle multiplied by the area of the fill area of the rec-
tangle. These calculations are shown in the following example. Rectangle 9 does not have any cuts. The cut volume for rectangle 10
is calculated in the same manner as for rectangle 5 and is calculated
as follows:
EXAMPLE 16-10
0!ft ⫹ 0!ft ⫹ 2.0!ft (50!ft)(33!ft) 1!yd3
Determine the cuts and fills for each of the 12 rectangles shown in Volume10 ⫽ a bc da b
Figure 16-11. What is the total cut for all of the areas? What is the 3 2 27!ft3
total fill for all of the areas? ⫽ 20!yd3
Solution: First we will calculate the cuts. All of rectangle 1 is a cut The cut volumes for rectangles 11 and 12 are as follows:
comprising zero cuts at three corners and a cut of 1.0 foot at the
0!ft ⫹ 0!ft ⫹ 2.0!ft ⫹ 2.7!ft 1!yd3
fourth. The cut volume is calculated as follows: Volume11 ⫽ a b(50!ft)(50!ft)a b
4 27!ft3
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 1.0!ft 1!yd3
Volume1 ⫽ a b(50!ft)(50!ft)a b ⫽ 109!yd3
4 27!ft3
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 2.7!ft 1!yd3
⫽ 23!yd3 Volume12 ⫽ a b(50!ft)(50!ft)a b
4 27!ft3
The cut volumes for rectangles 2 through 4 are calculated in a sim- ⫽ 63!yd3
ilar manner. They are as follows:
The total volume of the cut is calculated by summing the individual
0!ft ⫹ 0!ft ⫹ 2.0!ft ⫹ 1.0!ft 1!yd3
Volume2 ⫽ a b(50!ft)(50!ft)a b cut volumes as follows:
4 27!ft3
⫽ 69!yd3 Volume ⫽ 23!yd3 ⫹ 69!yd3 ⫹ 116!yd3 ⫹ 69!yd3 ⫹ 8!yd3 ⫹ 85!yd3
0!ft ⫹ 0!ft ⫹ 2.0!ft ⫹ 3.0!ft 1!yd3 ⫹ 225!yd3 ⫹ 132!yd3 ⫹ 20!yd3 ⫹ 109!yd3 ⫹ 63!yd3
Volume3 ⫽ a b(50!ft)(50!ft)a b ⫽ 919!yd3
4 27!ft3
⫽ 116!yd3 The volume of the fills is calculated as follows:
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 3.0!ft 1!yd3
Volume4 ⫽ a b(50!ft)(50!ft)a b Volume5 ⫽ a
0!ft ⫹ 0!ft ⫹ 1.0!ft (50!ft)(25!ft) 1!yd3
bc da b
4 27!ft3 3 2 27!ft3
⫽ 69!yd3 ⫽ 8!yd3
For rectangle 5, the area must be divided into three areas: a cut area, 0!ft ⫹ 0!ft ⫹ 1.0!ft (17!ft)(25!ft) 1!yd3
a fill area, and an area that is neither a cut nor a fill. From Example Volume6 ⫽ a bc da b
3 2 27!ft3
16-9, the area of the cut is a triangle with a base of 25 feet and a
height of 50 feet. The triangle is surrounded by two zeros and a cut ⫽ 3!yd3
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 1.0!ft 1!yd3
Volume9 ⫽ a b(50!ft)(50!ft)a b
of 1.0 foot. The cut volume is calculated as follows:
0!ft ⫹ 0!ft ⫹ 1.0!ft (50!ft)(25!ft) 1!yd3 4 27!ft3
Volume5 ⫽ a bc da b
3 2 27!ft3 ⫽ 23!yd3
⫽ 8!yd3 0!ft ⫹ 0!ft ⫹ 1.0!ft (50!ft)(17!ft) 1!yd3
Volume10 ⫽ a bc da b
For rectangle 6, the area must be divided into two areas: a cut area and 3 2 27!ft3
a fill area. From Example 16-9, the area of the fill is a triangle with a ⫽ 5!yd3
base of 25 feet (50 ft - 25 ft) and a height of 17 feet (50 ft - 33 ft). The
The total fill volume is calculated by summing the individual fill
area of the cut is the area of the rectangle (50 ft × 50 ft) less the area of
volumes as follows:
the triangle. The cut area is surrounded by two zeros, a cut of 1.0 foot,
and two cuts of 2.0 feet. The cut volume is calculated as follows: Volume ⫽ 8!yd3 ⫹ 3!yd3 ⫹ 23!yd3 ⫹ 5!yd3 ⫽ 39!yd3 䊏
0!ft ⫹ 0!ft ⫹ 1.0!ft ⫹ 2.0!ft ⫹ 2.0!ft
Volume6 ⫽ a b
5 The cross-sectional method may be used on building
⫻ c (50!ft)(50!ft) ⫺ d
(17!ft)(25!ft)
excavation even when contours do not exist, as long as cuts
2 and fills can be calculated. The use of the cross-sectional
(17!ft)(25!ft) 1!yd3
!⫽ a b c (50!ft)(50!ft) ⫺ da b
5!ft method is shown in the following example.
5 2 27!ft3
⫽ 85!yd3
The cut volumes for rectangles 7 and 8 are as follows: EXAMPLE 16-11
2.0!ft ⫹ 2.0!ft ⫹ 3.0!ft ⫹ 2.7!ft
Volume 7 ⫽ a b
Determine the excavation volume for Example 16-3 using the
4 cross-sectional method.
3
b ⫽ 225!yd3
1!yd Solution: The grids are aligned with the top and bottom of the
⫻ (50!ft)(50!ft)a
27!ft3 slopes. The grids and the cuts are shown in Figure 16-12. The cuts
Earthwork 209

FIGURE 16-12 Grid and Cuts for Example 16-11

are shown below and to the right of each intersection. The cuts for The total cut is calculated as follows:
each of the rectangles are calculated as follows:
Volume ⫽ 9!yd3 ⫹ 56!yd3 ⫹ 9!yd3 ⫹ 37!yd3 ⫹ 222!yd3
3
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 10!ft
Volume1 ⫽ a b(10!ft)(10!ft)a b
1!yd ⫹ 37!yd3 ⫹ 9!yd3 ⫹ 56!yd3 ⫹ 9!yd3
4 27!ft3 Volume ⫽ 444!yd3 䊏
⫽ 9!yd 3

0!ft ⫹ 0!ft ⫹ 10!ft ⫹ 10!ft 1!yd3


Volume2 ⫽ a b(10!ft)(30!ft)a b
4 27!ft3 COMPARISON OF METHODS
⫽ 56!yd3
1!yd3 The excavation in Example 16-3 has been calculated using
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 10!ft
Volume3 ⫽ a b(10!ft)(10!ft)a b the five methods presented in this chapter. The geometric
4 27!ft3
method produces an exact quantity for the excavation. A
⫽ 9!yd3 comparison among the methods is shown in Table 16-3.
0!ft ⫹ 0!ft ⫹ 10!ft ⫹ 10!ft 1!yd3
Volume4 ⫽ a b(10!ft)(20!ft)a b Although the geometric method and the modified-average-
4 27!ft3 end method both produce 456 cubic yards, when the calcu-
⫽ 37!yd3 lations are done without rounding, there is a 0.1% difference
10!ft ⫹ 10!ft ⫹ 10!ft ⫹ 10!ft 1!yd3 in their answers. In some cases, these two methods can
Volume5 ⫽ a b(30!ft)(20!ft)a b produce vastly different numbers. With four methods for
4 27!ft3
⫽ 222!yd3
calculating volume, it can be hard to know which method is
best. The most accurate method is the geometric method,
0!ft ⫹ 0!ft ⫹ 10!ft ⫹ 10!ft 1!yd3
Volume6 ⫽ a b(10!ft)(20!ft)a b
4 27!ft3
⫽ 37!yd3
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 10!ft 1!yd3 TABLE 16-3 Comparison of Volumes
Volume7 ⫽ a b(10!ft)(10!ft)a b
4 27!ft3
Method Volume (yd3) Error (%)
⫽ 9!yd3
0!ft ⫹ 0!ft ⫹ 10!ft ⫹ 10!ft 1!yd3 Geometric 456 0
Volume8 ⫽ a b(10!ft)(30!ft)a b
4 27!ft3 Average-width-length-depth 444 -2.6
⫽ 56!yd3 Average-end 481 +5.5
0!ft ⫹ 0!ft ⫹ 0!ft ⫹ 10!ft 1!yd3
Volume9 ⫽ a b(10!ft)(10!ft)a b Modified-average-end 456 -0.1
4 27!ft3
Cross-sectional 444 -2.6
⫽ 9!yd3
210 CHAPTER SIXTEEN

but in many cases it will be very hard, if not impossible, to One hundred and forty cubic yards of soil will need to be
use. The method most often used is the method that is easi- exported. 䊏
est to use based on the grading and excavation data available.
SOILS REPORT
BACKFILL Estimators should read soils report carefully. A soils report
The easiest way to calculate the quantity of backfill for foot- provides valuable information, such as the presence of
ing, foundations, and so forth is to determine the volume of groundwater or rocky soil. Both of these conditions increase
excavation and subtract the volume of the footing or foun- the cost of excavation. If a soils report is not provided with
dation. This is shown in the following example. the bid documents, the estimator should contact the design
professionals to see if a copy is available.
EXAMPLE 16-12
SAMPLE TAKEOFF FOR THE
The footing in Example 16-3 supports a 2-foot by 12-foot column.
Using the quantity of excavation from Example 16-3, determine the
RESIDENTIAL GARAGE
volume of backfill that needs to be placed after the footing has been A sample takeoff for excavation from a set of plans is shown
constructed. in the following example.
Solution: The volume of excavation from Example 16-3 is 456
cubic yards. The entire footing and the bottom 2 feet (10 ft - 8 ft) of EXAMPLE 16-14
the column are below the finished grade. The volume of the footing
and column that displaces soil is calculated as follows: Determine the excavation, under-slab gravel, and backfill needed to
complete the residential garage given in Appendix F. The excavated
1!yd3
VolumeFooting ⫽ (16!ft)(26!ft)(8!ft)a b ⫽ 123!yd3 soils may be used as backfill.
27!ft3
Solution: The excavation will consist of excavating the entire foot-
1!yd3
VolumeColumn ⫽ (2!ft)(12!ft)(2!ft)a b ⫽ 2!yd3 print of the building, the sidewalk, and the driveway and excavating
27!ft3 and backfilling the footings. The pad excavation will extend 1 foot
The volume of backfill is calculated as follows: beyond the sidewalk and driveway and 2 feet beyond the building.
The excavation quantities are calculated using the cross-sectional
Volume ⫽ 456!yd3 ⫺ 123!yd3 ⫺ 2!yd3 ⫽ 331!yd3 䊏 method. Begin by calculating the excavation for the building, includ-
ing 2 feet beyond in all directions. The excavation grade is 8 inches
Once the quantities of excavation and backfill have been (0.67 ft) below the grade of the building slab shown on the floor plan.
calculated, these quantities along with the quantity of soil im- The cuts for the building corners and total cut volume are as follows:
ported or exported need to be related to each other. If the ex- CutNW!Corner ⫽ 99.51!ft ⫺ 98.83!ft ⫽ 0.68!ft
cavated material is suitable, it may be used for the fill. If it is
CutSW!Corner ⫽ 99.47!ft ⫺ 98.83!ft ⫽ 0.64!ft
unsuitable for fill, it must be hauled off (exported) and an ac-
CutSE!Corner ⫽ 99.95!ft ⫺ 99.33!ft ⫽ 0.62!ft
ceptable fill material brought in (imported). The calculation
of soil import and export is shown in the following example. CutNE!Corner ⫽ 100.00!ft ⫺ 99.33!ft ⫽ 0.67!ft
0.68!ft ⫹ 0.64!ft ⫹ 0.62!ft ⫹ 0.67!ft
Volume ⫽ a b
4
EXAMPLE 16-13
1!yd3
The soils in Example 16-12 have a swell percentage of 30% and a ⫻ (28!ft)(30!ft)a b
27!ft3
shrinkage percentage of 5%. The excavated soils may be used as back-
fill. Determine the volume of the soils that needs to be exported. ⫽ 20.3!yd3

Solution: From Example 16-12 the volume of excavation is 456 Next, the volume of the driveway is calculated. The east side of the
cubic yards and the volume of backfill is 331 cubic yards. The com- drive has already been excavated to a point 2 feet west of the garage.
pacted volume of the backfill is converted to a bank quantity using At the west end, the drive will need to match the grade of the exist-
Eq. (16-6) as follows: ing driveway. The cuts for the slab corners and total cut volume are
as follows:
(331!yd3)
VB ⫽ ⫽ 348!yd3 CutNW!Corner ⫽ 98.60!ft ⫺ 97.93!ft ⫽ 0.67!ft
a1 ⫺ b
5
CutSW!Corner ⫽ 98.70!ft ⫺ 98.03!ft ⫽ 0.67!ft
100
CutNE!Corner ⫽ 99.50!ft ⫺ 98.78!ft ⫽ !0.72!ft
Three hundred and forty-eight yards of the excavated material are
needed for the backfill. The quantity exported is 108 bank cubic CutSE!Corner ⫽ 99.52!ft ⫺ 98.78!ft ⫽ 0.74!ft
0.67!ft ⫹ 0.67!ft ⫹ 0.72!ft ⫹ 0.74!ft
Volume ⫽ a b
yards (456 yd3 - 348 yd3). The loose volume of the exported soils is
converted from a bank quantity to a loose quantity using Eq. (16-3) 4
as follows: 1!yd3
⫻ (20!ft)(24.58!ft)a b
27!ft3
b ⫽ 140!yd3
30
VL ⫽ (108!yd3)a1 ⫹
100 ⫽ 12.7!yd3
Earthwork 211

Next, the volume of the sidewalk is calculated. The width of the TABLE 16-4 Quantities for Residential Garage
sidewalk to be excavated is 4 feet plus the 1 foot over-excavation less
the 2 feet of over-excavation already accomplished when excavating 31-200 Grading and Excavation
the garage. The length of the sidewalk to the south of the building is
32 feet (1 ft ⫹ 4 ft ⫹ 26 ft ⫹ 1 ft), which includes 1 foot over-exca- Excavation 56 bank cyd
vation at both ends. The length of sidewalk to the west is 5 feet (3 ft Backfill 19 bank cyd
⫹ 2 ft). For the grades of the sidewalk we use the cut of the south-
Export 36 bank cyd
east building corner and southeast corner of the driveway. The total
cut volume is calculated as follows: 3>4 – gravel 15 compacted
1!yd3 cyd
0.74!ft ⫹ 0.62!ft
Volume ⫽ a b(32!ft ⫹ 7!ft)(3!ft)a b
2 27!ft3
⫽ 2.9!yd3
Next, the excavation for the foundation wall is calculated. The cuts
0.34!ft ⫹ 0.83 1!yd3
to the bottom of the foundation in the four corners of the building VolumeNorth!Wall ⫽ (26!ft)a b(0.67!ft)a b
are as follows: 2 27!ft3
⫽ 0.38!yd3
CutNW!Corner ⫽ 98.83!ft ⫺ 97.66!ft ⫽ 1.17!ft
1!yd3
CutSW!Corner ⫽ 98.83!ft ⫺ 97.66!ft ⫽ 1.17!ft VolumeEast!Wall ⫽ (22.66!ft)(0.83)(0.67!ft)a b ⫽ 0.47!yd3
27!ft3
CutSE!Corner ⫽ 99.33!ft ⫺ 97.66!ft ⫽ 1.67!ft
0.34!ft ⫹ 0.83 1!yd3
CutNE!Corner ⫽ 99.33!ft ⫺ 97.66!ft ⫽ 1.67!ft VolumeSouth!Wall ⫽ (26!ft)a b(0.67!ft)a b
2 27!ft3
Allow for a 4-foot-wide trench for the footings. Extend the trench
⫽ 0.38!yd3
out 1 foot beyond the outside of the footings. The north and south
trenches are 29 feet (1 ft ⫹ 0.5 ft ⫹ 26 ft ⫹ 0.5 ft ⫹ 1 ft) long and VolumeConcrete ⫽ 4.24!yd3 ⫹ 0.52!yd3 ⫹ 0.38!yd3
include the corners. The east and west trenches are 19 feet long and ⫹ 0.47!yd3 ⫹ 0.38!yd3
will run from the inside of the north trench to the inside of the ⫽ 6.0!yd3
south trench. Because the excavations are shallow, the wall can be
VolumeBackfill ⫽ 20.2!yd3 ⫺ 6.0!yd3 ⫽ 14.2!yd3
vertical. The excavation is calculated using the average-width-
length-depth method as follows: The volume of backfill needed for the over-excavation is calculated
1.67!ft ⫹ 1.17!ft 3 as follows:
b(4)a b ⫽ 6.1!yd3
1!yd
VolumeN ⫽ (29!ft)a
2 27!ft3 Volume ⫽ [(1!ft)(24.58!ft) ⫹ (2!ft)(3!ft) ⫹ (2!ft)(30!ft)
1.67!ft ⫹ 1.67!ft 1!yd3
b(4)a b ⫽ 4.7!yd3
⫹ (2!ft)(24!ft) ⫹ (1!ft)(4!ft) ⫹ (1!ft)(32!ft)
VolumeE ⫽ (19!ft)a
2 27!ft3 ⫹ (1!ft)(7!ft) ⫹ (1!ft)(21.58!ft)](0.67!ft)(1!yd3/27!ft3)
1.67!ft ⫹ 1.17!ft 1!yd3
VolumeS ⫽ (29!ft)a b(4)a b ⫽ 6.1!yd3 ⫽ 5.0!yd3
2 27!ft3
The total backfill is 19.2 cubic yards (14.2 yd3 ⫹ 5.0 yd3). Assuming
1.17!ft ⫹ 1.17!ft 1!yd3
VolumeW ⫽ (19!ft)a b(4)a b ⫽ 3.3!yd3 a shrinkage percentage of 5%, we calculate the quantity of exca-
2 27!ft3 vated material needed for the fill using Eq. (16-6) as follows:
Volume ⫽ 6.1!yd3 ⫹ 4.7!yd3 ⫹ 6.1!yd3 ⫹ 3.3!yd3 ⫽ 20.2!yd3
(19.2!yd3)
The total excavation is calculated as follows: VB ⫽ ⫽ 20.2!yd3
a1 ⫺ b
5
Volume ⫽ 20.3!yd3 ⫹ 12.7!yd3 ⫹ 2.9!yd3 ⫹ 20.2!yd3 ⫽ 56!yd3 100
Backfill is needed around the footings and in the areas over-excavated The amount of export is 36 bank cubic yards (56 yd3 - 20 yd3).
during the excavation of the pad. The backfill of the footings is calcu- The last item to calculate is the volume of gravel needed under
lated by determining the volume of the concrete in the excavation and the concrete slab, driveway, and sidewalk. The volume is calculated
subtracting it from the volume of excavation. The height of the wall as follows:
below the excavation level on the west side is 0.34 feet (1.17 ft - 10 in)
and on the east side is 0.83 feet (1.67 ft - 10 in). The west wall includes AreaSlab ⫽ (24!ft!8!in)(22!ft!8!in) ⫹ (16!ft)(8!in) ⫽ 570!ft2
the wall on the footing and the frost wall. The footing volume is calcu- AreaDrive ⫽ (18!ft)(26!ft!7!in) ⫽ 479!ft2
lated as follows: AreaSidewalk ⫽ (33!ft)(4!ft) ⫽ 132!ft2
LengthFooting ⫽ 3!ft!4!in ⫹ 27!ft ⫹ 21!ft!8!in ⫹ 27!ft ⫹ 3!ft!4!in Area ⫽ 570!ft2 ⫹ 479!ft2 ⫹ 132!ft2 ⫽ 1,181!ft
⫽ 82!ft!3!in ⫽ 82.33!ft (4!in) 1!yd3
Volume ⫽ (1,181!ft2) a b ⫽ 14.6!yd3
(10!in)(20!in) 1!yd3 (12!in/ft) 27!ft3
VolumeFooting ⫽ (82.33!ft) a b ⫽ 4.24!yd3
(12!in>ft)2 27!ft3 The quantities needed for the garage, grouped by the cost codes in
VolumeWest!Wall ⫽ [2(3.33!ft)(0.34!ft)(0.67!ft) Appendix B, are shown in Table 16-4. 䊏
⫹ (16!ft)(1.17!ft)(0.67!ft)]
1!yd3
⫽ 14.0!ft3a b ⫽ 0.52!yd3
27!ft3
212 CHAPTER SIXTEEN

CONCLUSION
The volume of excavation can be calculated in a number of
ways including the geometric method, the average-width-
length-depth method, the average-end method, the modi-
fied-average-end method, and the cross-sectional method.
Because of variation in the surface area to be excavated and
the inability of excavating equipment to quickly excavate
exact geometric shapes, any calculation of the volume of ex-
cavation is only an approximation.
When soils are excavated their volume increases. This is
known as swell. When soils are compacted their volume de-
creases to a volume less than their volume before they were
excavated. This is known as shrink. Swell and shrink must be
taken into account when determining the volume of soil that
needs to be transported and placed as compacted fill. FIGURE 16-13 Basement Plan

PROBLEMS
10. Solve Problem 4 using the modified-average-end
1. A soil has a bank dry density of 108 pounds per cubic method.
foot, a loose dry density of 85 pounds per cubic foot, 11. Solve Problem 3 using the cross-sectional method.
and a compacted dry density of 120 pounds per cubic 12. Solve Problem 4 using the cross-sectional method.
foot. Determine the swell percentage and shrinkage per-
13. Using the average-end area method, determine the re-
centage for the soils.
quired excavation for a new road given the stations and
2. A soil has a bank dry density of 100 pounds per cubic their associated cut areas shown in Table 16-5. Express
foot, a loose dry density of 90 pounds per cubic foot, your answer in cubic yards.
and a compacted dry density of 105 pounds per cubic
14. Using the average-end area method, determine the re-
foot. Determine the swell percentage and shrinkage per-
quired volume of the cuts and fills for a new road given
centage for the soils.
the stations and their associated cut and fill areas shown
3. Using the geometric method, determine the amount of in Table 16-6. Express your answer in cubic yards.
excavation required for a 24-foot by 50-foot basement.
15. Determine the volume of backfill needed for the base-
The measurements are from the outside of the founda-
ment in Problem 3. The footing height is 12 inches. Use
tion walls. The depth of the excavation is 7 feet. The
the excavation quantities from Problem 3.
footings extend 1 foot outside of the foundation walls,
and a 3-foot space between the footing and the sides of 16. Determine the volume of backfill needed for the base-
the excavation must be provided to form the footings. ment in Problem 4. The footing height is 12 inches. Use
The soil is excavated at a 1:1 (horizontal:vertical) slope. the excavation quantities from Problem 4.
Express your answer in cubic yards. 17. The soils in Problem 15 have a bank dry unit weight of
4. Using the geometric method, determine the amount of 105 pounds per cubic foot, a loose dry unit weight of 80
excavation required for the basement in Figure 16-13. pounds per cubic foot, and a compacted dry unit weight
The basement measurements are from the outside of of 110 pounds per cubic foot. Determine the volume of
the foundation walls. The average depth of the excava- the soils that needs to be exported.
tion is 6 feet. The footings extend 1 foot outside of the
foundation walls, and a 2-foot space between the foot-
ing and the sides of the excavation must be provided to
TABLE 16-5 Cuts for Problem 11
form the footings. The soil is excavated at a 1.5:1 (hori-
zontal:vertical) slope. Express your answer in cubic Station Cut (ft2)
yards.
5. Solve Problem 3 using the average-width-length-depth 0⫹00 0
method. 0⫹50 235
6. Solve Problem 4 using the average-width-length-depth 1 ⫹00 475
method. 1 ⫹50 232
7. Solve Problem 3 using the average-end method. 2 ⫹00 52
8. Solve Problem 4 using the average-end method.
2 ⫹25 0
9. Solve Problem 3 using the modified-average-end method.
Earthwork 213

TABLE 16-6 Cuts and Fills for Problem 12 method. The grids are 50 feet apart in both directions.
The existing grade appears above the proposed grade.
Station Cut (ft2) Fill (ft2) Express your answer in cubic yards. The shrinkage per-
centage is 5% and the swell percentage is 28%.
0 ⫹00 0 0
20. Determine the excavation and backfill needed for the
0 ⫹50 175 10
Johnson Residence given in Appendix F. Assume that a
1⫹00 250 45 3-foot space between the footing and the sides of the ex-
1⫹50 75 225 cavation must be provided to form the footings. The
2⫹00 0 450 sides are excavated at a 1:1 (horizontal:vertical) slope.
2 ⫹25 0 0 21. Determine the excavation and backfill needed for the
West Street Video project given in Appendix F. Assume
that a 1-foot space between the footing and the sides of
the excavation must be provided to form the footings.
18. The soils in Problem 16 have a swell percentage of 25%
The sides are excavated at a 0.5:1 (horizontal:vertical)
and a shrinkage percentage of 8%. Determine the vol-
slope.
ume of the soils that needs to be exported.
22. Determine the under-slab gravel needed for the West
19. For the site plan in Figure 16-14, determine the total vol-
Street Video project given in Appendix F.
ume of the cuts, the total volume of the fills, and the vol-
ume of the import or export using the cross-sectional

FIGURE 16-14 Site Plan


CHAPTER SEVENTEEN

EXTERIOR
IMPROVEMENTS

In this chapter you will learn how to apply the principles in


EXAMPLE 17-1
Chapter 4 to exterior improvements including asphalt, site con-
crete, and landscaping. This chapter includes a sample spread- Determine the tons of asphalt and base required to complete the
sheet that may be used in the quantity takeoff. parking lot in Figure 17-1. The base has an average thickness of
8 inches and a density of 125 pounds per cubic foot. The asphalt
has an average thickness of 3.5 inches and a density of 150 pounds
per cubic foot. The curb and gutter is 30 inches wide and has an in-

E xterior improvements includes base, flexible and


ridged paving, curbs and gutters, fences, athletic sur-
faces, retaining walls, bridges, irrigation systems, and
landscaping. In this chapter we limit the discussion of exte-
rior improvements to asphalt and base, site concrete, and
side radius of 5 feet.
Solution: The area of the parking lot will be divided into four
areas: the large main area, the drive, and the two small pieces next
to the radius of the curb and gutter. The main area is 151 feet long
(156 ft ⫺ 30 in ⫺ 30 in) by 62 feet wide (67 ft ⫺ 30 in ⫺ 30 in). The
landscaping. We begin by looking at asphalt and base. drive is 25 feet wide by 13.5 feet long (11 ft ⫹ 30 in). The outside
radius (R) of curb and gutter is 7.5 feet (5 ft ⫹ 30 in). The small
areas next to the radius of the curbs are each equal to a square less a
quarter circle. The areas are calculated as follows:
ASPHALT AND BASE
AreaMain ⫽ (151!ft)(62!ft) ⫽ 9,362!ft2
Asphalt and base are bid by the ton. The volume of asphalt
and base is determined by multiplying the area of the asphalt AreaDirve ⫽ (25!ft)(13.5!ft) ⫽ 338!ft2
␲ ␲
or base by the depth of the asphalt or base. The density of the AreaCurves ⫽ 2 c R2 a1 ⫺ b d ⫽ 2 c (7.5!ft)2 a1!⫺ b d ⫽ 24!ft2
asphalt or base is used to convert the volume to tons as 4 4
shown in the following example. AreaTotal ⫽ 9,362!ft2 ⫹ 338!ft2 ⫹ 24!ft2 ⫽ 9,724!ft2

FIGURE 17-1 Parking Lot Layout


214
Exterior Improvements 215

The volume of base and asphalt needed is calculated as follows: Solution: The length of curb and gutter needed for each side of the
entry is equal to 11 feet minus the inside radius (5 ft) of the curb and
b ⫽ 6,483!ft3
1!ft
VolumeBase ⫽ (9,724!ft)(8!in)a gutter, or 6 feet. The length of the curb and gutter on the north and
12!in south sides is 156 feet. The length of the curb and gutter on the east
b ⫽ 2,836!ft3
1 ft end is 67 feet less twice the width of the curb and gutter, or 62 feet
VolumeAsphalt ⫽ (9,724!ft2)(3.5!in)a
12!in (67 ft ⫺ 30 in ⫺ 30 in). This reduction in length is necessary to
avoid double counting the corners. The length of the curb and gut-
The tons of base and asphalt needed are calculated as follows: ter needed on the west ends is 13.5 feet less the width of the curb and
gutter, or 11 feet each. The length of the curved portion of the gutter
ba b ⫽ 405!tons
125!lb 1!ton
WeightBase ⫽ (6,483!ft3)a is based on the radius (R) of the centerline (average of the inside and
ft3 2,000!lb
outside radius), or 6.25 feet (5 ft>2 ⫹ 7.5 ft>2). The length of one of
WeightAsphalt ⫽ (2,836!ft3)a 3 ba b ⫽ 213!tons
150!lb 1!ton
䊏 the curved portions of the curb and gutter is calculated as follows:
ft 2,000!lb
2␲R 2␲(6.25)
Length ⫽ ⫽ ⫽ 10 ft
4 4
EXCEL QUICK TIP 17-1 The total length of curve (clockwise from the driveway) is calcu-
Asphalt or Base lated as follows:

The tons of asphalt or base needed for an area is set up in Length ⫽ 6!ft ⫹ 10!ft ⫹ 11!ft ⫹ 156!ft ⫹ 62!ft ⫹ 156!ft
a spreadsheet by entering the data and formatting the ⫹ 11!ft ⫹ 10!ft ⫹ 6!ft
cells as follows: Length ⫽ 428!ft

A B C The cross-sectional area of the curb is calculated as follows:


1 Area 9,723 sft (6!in ⫹ 7!in) 1!ft2
2 Thickness 3.50 in Area ⫽ c (6!in)(12!in) ⫹ (24!in) da b
2 144!in2
3 Density 150 lb/cft
4 ⫽ 1.58!ft2
5 Weight 212.69 tons The volume of concrete is calculated as follows:
1!yd3
b ⫽ 25.0!yd3
The following formula needs to be entered in Cell B5: Volume ⫽ (428!ft)(1.58!ft2)a
27!ft2
=B1*(B2/12)*B3/2000
The lengths of the forms needed to form the outside and the inside
The data for asphalt or base is entered in Cells B1 through of the curb and gutter are calculated as follows:
B3. The data shown in the foregoing figure is for the as-
2␲(5!ft)
phalt from Example 17-1. LengthOutside ⫽ 6!ft ⫹ ⫹ 13.5!ft ⫹ 156!ft ⫹ 67!ft
4
2␲(5!ft)
⫹ 156!ft ⫹ 13.5!ft ⫹ ⫹ 6!ft
SITE CONCRETE 4
LengthOutside ⫽ 434!ft
Site concrete is bid using the same principles as for building
concrete. The quantity takeoff of site concrete is shown in 2␲(7.5!ft)
LengthInside ⫽ 6!ft ⫹ ⫹ 11!ft ⫹ 151!ft ⫹ 62!ft
the following example. 4
2␲(7.5!ft)
⫹ 151!ft ⫹ 11!ft!⫹ ⫹ 6!ft
4
EXAMPLE 17-2
LengthInside ⫽ 422!ft 䊏
Determine the quantity of concrete and lineal footage of form
needed for the parking lot in Figure 17-1. The cross section of the
curb is shown in Figure 17-2. LANDSCAPING
Landscaping includes providing and grading topsoil; provid-
ing an underground sprinkler system; and planting seed, sod,
and plants. Providing topsoil is bid by the cubic yard, with the
volume of topsoil being determined by the area times the
thickness. The finish grading of the topsoil is bid based on
the area. The underground sprinkler system is most often
placed using a trenching machine to dig a narrow trench in
which the pipe is placed. The trenching is bid based on the
length of the trench, and the sprinkler system is bid based on
the same principles used to determine the components of a
FIGURE 17-2 Curb Cross Section plumbing system. Sod and seed are bid based on the area, and
216 CHAPTER SEVENTEEN

FIGURE 17-3 Landscaping Plan

plants are bid as a counted item. The quantity takeoff for TABLE 17-1 Quantities for Residential Garage
landscaping is shown in the following example.
32-110 Site 32-120 Site 32-900
Concrete—Labor Concrete—Concrete Landscaping
EXAMPLE 17-3
Form driveway 54 ft
The planter shown in Figure 17-3 requires 2 inches of topsoil.
Determine the topsoil and landscaping plants required to complete Screed 27 ft
the planter. The dimensions are measured to the outside of a 6-inch- Pour driveway 5.9 cyd
wide curb.
Finish driveway 479 sft
Solution: The area of the planter consists of one rectangle 124 feet Form sidewalk 37 ft
(130 ft ⫺ 2 ⫻ 3 ft) long and 5 feet (6 ft ⫺ 2 ⫻ 6 in) wide and two
half circles with a radius of 2.5 feet (3 ft ⫺ 6 in). The area is calcu- Pour sidewalk 1.6 cyd
lated as follows: Finish sidewalk 132 sft
2␲(2.5 ft)2 10⬘ expansion joint 5 ea
Area ⫽ (124 ft)(5 ft) ⫹ ⫽ 640 ft2
2 Driveway 5.9 cyd
The volume of topsoil is calculated as follows: Sidewalk 1.6 cyd
1 yd3 Sod Repair 291 sft
a b ⫽ 4 yd3
(2 in)
Volume ⫽ (640 ft2)
(12!in/ft) 27 ft3
The number of flowering dogwood trees is five. The number of
Boston ivy is calculated as follows: The driveway will require forms on the north and south side for a
total of 54 feet of forms. In addition, a 27-foot-long screed will
b ⫽ 160 each
1 ea need to be set up in the middle of the driveway. There is 33 feet
Number ⫽ (640 ft2)a 䊏
4 ft2 (26 ft ⫹ 4 ft ⫹ 3 ft) of 4-foot-wide sidewalk. The area and volume
of concrete needed for the sidewalk are calculated as follows:
Area ⫽ (33!ft)(4!ft) ⫽ 132!ft2
SAMPLE TAKEOFF FOR THE
1!yd2
a b ⫽ 1.6!yd3
(4!in)
RESIDENTIAL GARAGE Volume ⫽ (132!ft2)
(12!in\ft) 27!ft2
A sample takeoff for site improvements from a set of plans is
The sidewalk will require 37 feet (26 ft ⫹ 4 ft ⫹ 4 ft ⫹ 3 ft) of
shown in the following example. forms. Expansion joints are required between the driveway and the
garage and the sidewalk and the garage, requiring 47 feet (18 ft ⫹ 3 ft
⫹ 26 ft) of expansion joint, or five 10-foot-long pieces.
EXAMPLE 17-4
The landscaping will consist of landscape repair around the
Determine the site concrete and landscaping needed to complete garage. For this we allow for an area 2 feet wide to be repaired.
the residential garage in Appendix F. Beginning at the top left and going clockwise around the garage, we
calculate the area of landscape repair as follows:
Solution: The site concrete consists of the driveway and the side-
walk. The area and volume of concrete needed for the driveway are Area ⫽ (2!ft)(26!ft!7!in ⫹ 3!ft ⫹ 26!ft ⫹ 24!ft
calculated as follows: ⫹ 4!ft ⫹ 26!ft ⫹ 4!ft ⫹ 7!ft ⫹ 24!ft!7!in)
Area ⫽ (18!ft)(26!ft!7!in) ⫽ 479!ft 2 ⫽ 291!ft2
1!yd2
a b ⫽ 5.9!yd3
(4!in) The quantities needed for the garage, grouped by the cost codes in
Volume ⫽ (479!ft2)
(12!in\ft) 27!ft2 Appendix B, are shown in Table 17-1. 䊏
Exterior Improvements 217

CONCLUSION 5. Determine the number of tons of asphalt required to


complete the parking lot in Figure 17-4. The asphalt has
Asphalt and base are bid by the ton, which is determined by an average thickness of 3 inches and a density of 145
calculating the volume and multiplying it by the density of pounds per cubic foot. The curb is 6 inches wide and
the asphalt or base. Site concrete is bid in the same way as has an inside radius of 5 feet.
building concrete. Topsoil is bid by the cubic yard; grading, 6. Determine the volume of concrete needed to complete
seeding, and sod are bid by the square foot; plants are bid as the curb in Figure 17-4. The curb is 6 inches wide by
a counted item; trenching is bid by the foot; and a sprinkler 18 inches high. Include 10% waste. Concrete must be
system is bid using the same principles used to bid plumbing ordered in quarter-yard increments.
systems.
7. Determine the number of tons of base required to com-
plete the parking lot in Figure 17-5. The base has an av-
erage thickness of 6 inches and a density of 120 pounds
PROBLEMS per cubic foot. The curb is 6 inches wide and has an in-
side radius of 5 feet.
1. Determine the number of tons of base required to com- 8. Determine the number of tons of asphalt required to
plete 1,000 feet of road 22 feet wide. The base has a complete the parking lot in Figure 17-5. The asphalt
compacted weight of 125 pounds per cubic foot and is has an average thickness of 2.5 inches and a density of
12 inches thick. 150 pounds per cubic foot. The curb is 6 inches wide
2. Determine the number of tons of asphalt required to and has an inside radius of 5 feet.
complete 1,000 feet of road 22 feet wide. The asphalt has 9. Determine the volume of concrete needed to complete
a compacted weight of 145 pounds per cubic foot and the curb in Figure 17-5. The curb is 6 inches wide by
is 4 inches thick. 18 inches high. Include 6% waste. Concrete must be
3. How many cubic yards of concrete are required to con- ordered in quarter-yard increments.
struct an 80-foot by 5-foot by 4-inch-thick concrete 10. The site shown in Figure 17-6 requires 4 inches of top-
sidewalk? Include 8% waste. Concrete must be ordered soil. The bark is 2 inches thick. Determine the topsoil,
in quarter-yard increments. bark, and landscaping plants required to complete the
4. Determine the number of tons of base required to com- planter.
plete the parking lot in Figure 17-4. The base has an av- 11. The site shown in Figure 17-7 requires 2 inches of top-
erage thickness of 8 inches and a density of 115 pounds soil. Forty-five percent of the planter is covered with
per cubic foot. The curb is 6 inches wide and has an in- pansies. Determine the topsoil and landscaping plants
side radius of 5 feet. required to complete the planter.

FIGURE 17-4 Parking Lot Layout


218 CHAPTER SEVENTEEN

FIGURE 17-5 Parking Lot Layout

12. Determine the number of tons of asphalt and base re- 13. Determine the site concrete needed to complete the
quired to complete the West Street Video project given West Street Video project given in Appendix F.
in Appendix F. The asphalt has a density of 145 pounds 14. Determine the landscaping needed to complete the
per cubic foot and the base has a density of 130 pounds West Street Video project given in Appendix F.
per cubic foot. 15. Set up Excel Quick Tip 17-1 in Excel.

FIGURE 17-6 Landscaping Plan


Exterior Improvements 219

FIGURE 17-7 Landscaping Plan


CHAPTER EIGHTEEN

UTILITIES

In this chapter you will learn how to apply the principles in


Chapter 4 to utilities including sanitary sewers, water lines,
storm drains, gas lines, underground power lines, and tele-
phone lines. This chapter includes sample spreadsheets that
may be used in the quantity takeoff.

U nderground utilities are often placed in a similar


manner, whether they are sanitary sewers, water
lines, storm drains, gas lines, underground power
lines, or telephone lines. They all consist of piping or cable
placed in an underground trench. The lines may also include
such features as manholes, boxes, and so forth. The work of
placing underground utilities may be divided into four basic
components: excavation, placement of bedding material (if
required), placement of the utility line, and backfill. Let’s FIGURE 18-1 Typical Trench
begin by looking at excavation.

EXAMPLE 18-1
EXCAVATION A utility contractor is to install the sewer line whose plan and pro-
file are shown in Figure 18-2. The trench is to have the cross section
Excavation for manholes, boxes, and other such items is cal-
shown in Figure 18-3. Using the average-end method, determine
culated in the same manner as excavation for a footing.
the volume of excavation in cubic yards needed to install the sewer
A typical utility trench is shown in Figure 18-1. The line. The excavation for the manhole is to be 6 feet by 6 feet and
sides of utility trenches often consist of a vertical component 2 feet deeper than the flow line at the manhole.
(in this case with a constant height of dv) and a sloped com-
ponent with a slope of S horizontal feet per vertical foot. The Solution: The depth of excavation at either manhole equals the el-
evation of the rim less the flow line (FL) of the sewer line plus the
sides of the trench are sloped to prevent cave-in and to meet
distance between the flow line and the bottom of the trench. The
safety regulations. The height of the sloped component of
depth of excavation (d1) at Station 14⫹30.20 and the depth of ex-
the sides of the trench varies as the depth of the trench cavation (d2) at Station 15⫹80.20 are calculated as follows:
varies. The height dv and the slope of the sidewalls S are set
by safety regulations and the soil conditions. d1 ⫽ 1,148.20!ft ⫺ 1,140.88!ft ⫹ 0.50!ft ⫽ 7.82!ft
The volume of excavation may be estimated by the d2 ⫽ 1,146.71!ft ⫺ 1,143.88!ft ⫹ 0.50!ft ⫽ 3.33!ft
average-end method or the modified-average-end method At Station 14⫹30.20 the trench wall begins to slope at 4.82 feet
presented in Chapter 16. As previously stated, the average- (7.82 ft ⫺ 3 ft) below the top of the trench and widens each side of
end method often understates the volume. The use of the the trench by 3.62 feet (0.75 ⫻ 4.82 ft). At Station 15⫹80.20 the
average-end method to calculate the volume of excavation is trench wall begins to slope at 0.33 feet (3.33 ft ⫺ 3 ft) below the
shown in the following example. top of the trench and widens each side of the trench by 0.25 feet
220
Utilities 221

FIGURE 18-2 Sewer Line Plan and Profile

are calculated as follows:


2(4.82!ft)(3.62!ft)
Area1 ⫽ (2!ft)(7.82!ft) ⫹ ⫽ 33.1!ft2
2
2(0.33!ft)(0.25!ft)
Area2 ⫽ (2!ft)(3.33!ft) ⫹ ⫽ 6.7!ft2
2
The volume of excavation required for the trench is calculated
using Eq. (16-16) as follows:
(33.1!ft2 ⫹ 6.7!ft2) 1!yd3
Volume ⫽ (150!ft) c da b ⫽ 111!yd3
2 27!ft3
The depth of the manhole is calculated as follows:
d ⫽ 1,146.71!ft ⫺ 1,143.88!ft ⫹ 2.00!ft ⫽ 4.83!ft
The volume of manhole excavation is calculated using the volume
FIGURE 18-3 Sewer Line Cross Section of column as follows:
1!yd3
Volume ⫽ (6!ft)(6!ft)(4.83!ft)a b ⫽ 6!yd3
(0.75 ⫻ 0.33 ft). The cross sections for the end of the trenches are 27!ft3
shown in Figure 18-4. A small amount of the calculated quantity of excavation for the
The area of the end of the trench (Area1) at Station 14⫹30.20 manhole is also included in the calculated quantity for the trench.
and the area of the end of the trench (Area2) at Station 15⫹80.20 The total excavation is 117 cubic yards (111 YD3 ⫹ 6 YD3). 䊏

FIGURE 18-4 Trench Cross Sections


222 CHAPTER EIGHTEEN

EXCEL QUICK TIP 18-1 A B C


Trench Excavation Using Average-End Method 1 Length of Trench 150 ft
2 Width of Trench Bottom 2.00 ft
The volume of trench excavation using the average-end 3 Depth at One End 7.82 ft
method is set up in a spreadsheet by entering the data and 4 Depth at Other End 3.33 ft
formatting the cells as follows: 5 Depth of Vertical Wall 3.00 ft
6 Slope of Trench Walls 0.75 ft:ft
A B C 7
1 Length of Trench 150 ft 8 Volume 101 cyd
2 Width of Trench Bottom 2.00 ft
3 Depth at One End 7.82 ft The following formula needs to be entered in Cell B8:
4 Depth at Other End 3.33 ft
5 Depth of Vertical Wall 3.00 ft =B1*(B2*B3+IF(B5>B3,0,B6*(B3-B5)^2)
6 Slope of Trench Walls 0.75 ft:ft +B2*B4+IF(B5>B4,0,B6*(B4-B5)^2)
7 +((B2*B3+IF(B5>B3,0,B6*(B3
8 Volume 111 cyd -B5)^2))*(B2*B4+IF(B5>B4,0,B6*
(B4-B5)^2)))^0.5)/(3*27)
The following formula needs to be entered in Cell B8: The data for the trench is entered in Cells B1 through
=B1*(B2*B3+IF(B5>B3,0,B6*(B3-B5)^2) B6. The data shown in the foregoing figure is from
+B2*B4+IF(B5>B4,0,B6*(B4-B5)^2))/ Example 18-2.
(2*27)

The data for the trench is entered in Cells B1 through


B6. The data shown in the foregoing figure is from A more accurate volume may be obtained by determin-
Example 18-1. ing the volume of the geometric shape of the trench. This is
done for the trench in Figure 18-1 by using the following
equation:

The modified-average-end method often produces a more Volume ⫽


(d1 ⫹ d2) (d12 ⫹ d1d2 ⫹ d22 ⫹ 3dv2 ⫺ 3d1dv ⫺ 3d2dv)
L cW d
accurate answer but may also overstate the quantity. The use ⫹S
of the modified-average-end method to calculate the volume 2 3
of excavation is shown in the following example. (18-1)

where
EXAMPLE 18-2
L ⫽ Length of the Trench
Solve Example 18-1 using the modified-average-end method.
W ⫽ Width of the Trench at the Bottom
Solution: From Example 18-1, excavation volume for the manhole is d1 ⫽ Depth at One End of the Trench
6 cy3 and the end areas are 33.1 ft2 and 6.7 ft2. The volume of excava-
tion required for the trench is calculated using Eq. (16-18) as follows: d2 ⫽ Depth at the Other End of the Trench
33.1!ft2 ⫹ 6.7!ft2 ⫹ 2(33.1!ft2)(6.7!ft2)
dv ⫽ Depth of the Vertical Trench Wall
Volume ⫽ (150!ft)a b S ⫽ Slope of the Trench Walls
3
1!yd3
⫻a b This equation is based on five assumptions. First, the
27!ft3 width at the bottom of the trench is constant. Second, the
Volume ⫽ 101!yd3 height of the vertical sidewall of the trench is constant.
Third, the height of the vertical sidewall is less than or equal
A small amount of the calculated quantity of excavation for the
manhole is also included in the calculated quantity for the trench. to the depth at both ends (dv ⱕ d1 and dv ⱕ d2). Fourth, the
The total excavation is 107 cubic yards (101 yd3 ⫹ 6 yd3). 䊏 slope of the sloped sidewalls is constant and, as a result, as
the trench gets deeper, the width of the trench at the surface
increases. Fifth, the change in depth of the trench is uniform
over the length of the trench; therefore, the depth may be ex-
EXCEL QUICK TIP 18-2
pressed as a linear function of the distance from one end of
Trench Excavation Using the trench to the other. The use of Eq. (18-1) is shown in the
Modified-Average-End Method following example.
The volume of trench excavation using the modified-
average-end method is set up in a spreadsheet by enter- EXAMPLE 18-3
ing the data and formatting the cells as follows:
Solve Example 18-1 using Eq. (18-1).
Utilities 223

Solution: From Example 18-1 the depths of excavation at the BEDDING


manholes are 7.82 feet and 3.33 feet. The volume of excavation re-
quired for the trench is calculated using Eq. (18-1) as follows: Often underground pipes are placed on a bedding material,
(7.82!ft ⫹ 3.33!ft) such as gravel or sand, which provides a place for the pipe to
Volume ⫽ (150!ft) e(2!ft) ⫹ 0.75 c (7.82!ft)2 rest in and may even surround the pipe. These two conditions
2
are shown in Figure 18-5. The volume of bedding material is
⫹ (7.82!ft)(3.33!ft) ⫹ (3.33!ft)2 ⫹ 3(3!ft)2!
determined by calculating the cross-sectional area of the bed-
⫺ 3(7.82!ft)(3!ft) ⫺ 3(3.33!ft)(3!ft) d ^3 f a
1!yd3
b ding material and multiplying it by the length of the pipe.
27!ft3
Bedding material is also placed below manholes and boxes.
⫽ 97!yd3
For pipe sitting on the bedding material, the angle a is
From Example 18-1, the volume of excavation for the manhole is determined by the following equation:
6 cubic yards, bringing the total excavation volume to 103 cubic
a ⫽ cos⫺1 a1 ⫺ b
yards (97 yd3 ⫹ 6 yd3). 䊏 2Y
(18-2)
DP
EXCEL QUICK TIP 18-3 where
Trench Excavation Using Eq. (18-1) Y ⫽ Depth of the Pipe in the Bedding
The volume of trench excavation using Eq. (18-1) is set DP ⫽ Outside Diameter of the Pipe
up in a spreadsheet by entering the data and formatting The quantity of bedding is estimated using Eq. (18-3) if
the cells as follows: the angle a is measured in radians and Eq. (18-4) if the angle
A B C a is measured in degrees:
1 Length of Trench 150 ft 3a ⫺ (sin!a)(cos!a)4
2 Width of Trench Bottom 2.00 ft Volume ⫽ eW(DB) ⫺ (DP)2 f L
4
3 Depth at One End 7.82 ft
4 Depth at Other End 3.33 ft (18-3)
5 Depth of Vertical Wall 3.00 ft 32␲a>360 ⫺ (sin a)(cos a)4
6 Slope of Trench Walls 0.75 ft:ft Volume ⫽ eW(DB) ⫺ (DP)2 f L
4
7
8 Volume 97 cyd (18-4)
where
The following formula needs to be entered in Cell B8: W ⫽ Width of the Trench at the Bottom
=IF(B5>B3,“ERROR”,IF(B5>B4,“ERROR”, DB ⫽ Depth of the Bedding
B1*(B2*(B3+B4)/2+B6*(B3^2+B3*B4+B4^2 a ⫽ Angle from Eq. (18-2)
+3*B5^2-3*B3*B5-3*B4*B5)/3)/27))
DP ⫽ Outside Diameter of the Pipe
The use of the nested IF statements will display the word L ⫽ Length of the Trench
“ERROR” in Cell B8 should the depth of the vertical wall
be greater than the depth at one of the ends. The data for For pipes barely in the bedding material, the area of the
the trench is entered in Cells B1 through B6. The data pipe is often ignored. The calculation of bedding material
shown in the foregoing figure is from Example 18-3. for a pipe partially buried in the bedding material is shown
in the following example.

FIGURE 18-5 Bedding Conditions


224 CHAPTER EIGHTEEN

DP ⫽ Outside Diameter of the Pipe


EXAMPLE 18-4
L ⫽ Length of the Trench
The pipe in Example 18-1 is bedded in gravel. The depth of the
gravel is 1 foot, and the pipe is bedded into the gravel 6 inches. The For bedding below manholes and boxes, the quantity of
outside diameter of the sewer pipe is 11 inches. Ignoring the man- bedding is calculated using one of the excavation methods
hole, determine the quantity of gravel needed for the sewer line. from Chapter 16. The calculation of bedding material is
Solution: Find the angle a in radians using Eq. (18-2) as follows: shown in the following example.

a ⫽ cos⫺1 c 1 ⫺ d ⫽ 1.66!radians
2(6!in)
EXAMPLE 18-5
11!in
The pipe in Example 18-1 is surrounded by gravel. The depth of the
The volume of bedding needed for the pipe is calculated using
gravel is 2 feet. The outside diameter of the sewer pipe is 11 inches.
Eq. (18-4) as follows:
Twelve inches of bedding is also placed below the manhole.
3 1.66 ⫺ (sin 1.66)(cos 1.66)4
Volume ⫽ e(2!ft)(1!ft) ⫺
Determine the quantity of gravel needed for the sewer line.
4 Solution: The volume of bedding needed for the pipe is calculated
11!in 2 1!yd3
⫻ c d f (150!ft)a b
using Eq. (18-5) as follows:
(12!in/ft) 27!ft3 ␲ 11!in 2 1!yd3
⫽ 9!yd 3
䊏 Volume ⫽ e(2!ft)(2!ft) ⫺ c d f (150!ft)a b
4 (12!in/ft) 27!ft3
⫽ 18.6!yd3
EXCEL QUICK TIP 18-4 The volume of bedding needed for the manhole is calculated using
Bedding Volume for Pipe Resting on Bedding the volume of a column as follows:
1!yd3
The volume of bedding using Eqs. (18-2) and (18-3) is set Volume ⫽ (6!ft)(6!ft)(1!ft)a b ⫽ 1.3!yd3
up in a spreadsheet by entering the data and formatting 27!ft3
the cells as follows: The total volume needed is 20 cubic yards. 䊏
A B C
1 Width of Trench 2.00 ft EXCEL QUICK TIP 18-5
2 Depth of Bedding 1.00 ft
Bedding Volume for Pipe Surrounded by Bedding
3 Depth of Pipe in Bedding 6.00 in
4 Diameter of Pipe 11.00 in The volume of bedding using Eq. (18-5) is set up in a
5 Length of Pipe 150 ft spreadsheet by entering the data and formatting the cells
6 as follows:
7 Angle a 1.66 rad
8 Volume 9.1 cyd A B C
1 Width of Trench 2.00 ft
The following formulas need to be entered in the associ- 2 Depth of Bedding 2.00 ft
ated cells: 3 Diameter of Pipe 11.00 in
4 Length of Pipe 150 ft
5
Cell Formula
6 Volume 18.6 cyd
B7 =ACOS(1-2*B3/B4)
The following formula needs to be entered in Cell B6:
B8 =(B1*B2–(B7–SIN(B7)*COS(B7))*
(B4/12)^2/4)*B5/27 =IF(B3/12>B1, “ERROR”,IF(B3/12>B2,
“ERROR”,
(B1*B2-PI()*(B3/12)^2/4)*B4/27))
The data for the pipe and bedding is entered in Cells B1
through B5. The data shown in the foregoing figure is The use of the nested IF statements will display the word
from Example 18-4. “ERROR” in Cell B6 should the diameter of the pipe ex-
ceed the width of the trench or the depth of bedding. The
For pipe surrounded by bedding material, the quantity of data for pipe and bedding is entered in Cells B1 through
bedding material is estimated using the following equation: B4. The data shown in the foregoing figure is from

Volume ⫽ c W(DB ) ⫺ (D ) 2 d L (18.5)
4 P UTILITY LINES
where The quantities of utility components (such as pipe, man-
W ⫽ Width of Trench at the Bottom holes, valves, conduit, wire, and so forth) needed for the
DB ⫽ Depth of the Bedding utility line are calculated in the same manner as plumbing
Utilities 225

and electrical components were calculated. The quantity cussed in Chapter 16, and whether the excavated material
takeoff for utility components is shown in the following can be used as backfill. The volume of backfill is shown in
example. the following example.

EXAMPLE 18-6 EXAMPLE 18-7


Determine the utility components needed for the sewer line in Using the excavation volume from Example 18-3 and the bedding
Example 18-1. The pipe is available in 20-foot lengths and includes quantity from Example 18-5, determine the volume of backfill for
a bell with a gasket at one end. the sewer line in Example 18-1. The manhole has an outside diam-
eter of 4 feet and its bottom is 1 foot below the flow line.
Solution: The new manhole will require a 3-foot-high manhole
base with a hole and gasket for the sewer pipe, a flat manhole top, a Solution: From Example 18-3, the volume of excavation is 103
metal ring, and a manhole cover. Eight (150!ft>20!ft) sections of cubic yards. From Example 18-4, the volume of bedding is 20 cubic
20-foot-long pipe are needed. The existing manhole will need to be yards. The volume of the pipe is calculated as follows:
core drilled for the new pipe, and the pipe will need to be sealed
␲ 11!in 2 1!yd3
with a gasket or concrete. 䊏 Volume ⫽ c d (150!ft)a b ⫽ 4!yd3
4 (12!in/ft) 27!ft3
The height of the manhole is 3.83 feet, and it has a radius of 2 feet.
BACKFILL The volume of the manhole is calculated as follows:
The quantity of backfill is determined by subtracting the 1!yd3
volume of bedding and the volume of the utility compo- Volume ⫽ ␲(2!ft)2(3.83!ft)a b ⫽ 2!yd3
27!ft3
nents from the excavation volume. When determining the
quantity of material that must be exported or imported, the The volume of the backfill is calculated as follows:
estimator must take into account shrink and swell, as dis- Volume ⫽ 103!yd3 ⫺ (20!yd3 ⫹ 4!yd3 ⫹ 2!yd3) ⫽ 77!yd3 䊏

CONCLUSION 4. How much backfill is needed for the water line in


Problem 1?
Underground utilities consist of the excavation, placement 5. A utility contractor is to install the sewer line whose
of bedding material (if required), placement of the utility plan and profile are shown in Figure 18-6. The trench is
line, and backfill. The quantity of excavation may be calcu- to have the cross section shown in Figure 18-7. Using
lated by the average-end method, the modified-average-end the average-end method, determine the volume of exca-
method, or Eq. (18-1). The quantity of bedding for pipes vation in cubic yards needed to install the sewer line.
partially surrounded by bedding is calculated using Eq. (18-2) The excavation for the manhole is to be 6 feet by 6 feet
through (18-4), and the quantity of bedding for pipe fully and 2 feet deeper than the flow line at the manhole.
surrounded by bedding is calculated using Eq. (18-5). The
6. Solve Problem 5 using the modified-average-end method.
components of the utility lines are calculated in the same
manner as plumbing and electrical components are calcu- 7. Solve Problem 5 using Eq. (18-1).
lated. The quantity of backfill needed equals the quantity of 8. The pipe in Problem 5 is bedded in gravel. The depth of
excavation less the quantity of backfill less the volume of the the gravel is 1 foot, and the pipe is bedded into the
utility lines. gravel 3 inches. The outside diameter of the sewer pipe
is 9 inches. Ignoring the manhole, determine the quan-
tity of gravel needed for the sewer line.
PROBLEMS 9. The pipe in Problem 5 is surrounded by gravel. The
depth of the gravel is 18 inches. The outside diameter of
1. An 18-inch-wide by 3-foot-deep trench is dug in the the sewer pipe is 9 inches. Twelve inches of bedding is
ground and a water line with a 3.5 inch outside diame- also placed below the manhole. Determine the quantity
ter is placed in the trench. The water line is placed on of gravel needed for the sewer line.
6 inches of bedding, and bedding surrounds the pipe to 10. Determine the utility components needed for the sewer
a height of 2.5 inches above the water line. The length of line in Problem 5. The pipe is available in 20-foot
the trench is 500 feet. Determine the volume of excava- lengths and includes a bell with a gasket at one end.
tion needed for the water line. 11. Using the excavation volume from Problem 7 and the
2. How much bedding is needed for Problem 1? bedding quantity from Problem 9, determine the vol-
3. The water line in Problem 1 is constructed of 20-foot- ume of backfill for the sewer line in Problem 5. The
long pipes with a bell and gasket on one end. How many manhole has an outside diameter of 4 feet and its bot-
pieces of pipe are needed? tom is 1 foot below the flow line.
226 CHAPTER EIGHTEEN

FIGURE 18-6 Sewer Line Plan and Profile

12. Determine the quantities of excavation, bedding mater-


ial, utility components, and backfill needed for the
Johnson Residence given in Appendix F.
13. Determine the quantities of excavation, bedding mater-
ial, utility components, and backfill needed for the West
Street Video project given in Appendix F.
14. Set up Excel Quick Tip 18-1 in Excel.
15. Set up Excel Quick Tip 18-2 in Excel.
16. Set up Excel Quick Tip 18-3 in Excel.
17. Set up Excel Quick Tip 18-4 in Excel.
18. Set up Excel Quick Tip 18-5 in Excel.

FIGURE 18-7 Sewer Line Cross Section


P A R T T H R E E

PUTTING COSTS
TO THE ESTIMATE

Chapter 19 Material Pricing


Chapter 20 Labor Productivity and Hours
Chapter 21 Labor Rates
Chapter 22 Equipment Costs
Chapter 23 Crew Rates
Chapter 24 Subcontract Pricing
Chapter 25 Markups
Chapter 26 Pricing Extensions
Chapter 27 Avoiding Errors in Estimates

I
n this section, you will learn how to put costs to the estimate, including
how to price materials, labor, and equipment. You will also learn to calcu-
late markups and how to check for errors in the estimate. In Chapter 26
you will see how to apply these principles to the residential garage given in
Appendix F.
CHAPTER NINTEEN

MATERIAL PRICING

In this chapter you will learn how to determine material pric- supply residential door and bathroom hardware at a set unit
ing. Material costs include the cost of the materials, shipping price for a period of one year. You may then use these prices
costs, sales tax, storage costs, and escalation allowance. on all jobs that you bid during the year. One advantage of
Material pricing can be obtained from suppliers, historical annual contracts is that suppliers often give better pricing
data, and national reference books. because the contractor is committing to buy a large quantity
of materials over the course of the year.
The next best way to determine pricing is to price ma-

T
terials based on historical costs. Historical costs may be
he best way to determine pricing for materials is to
obtained by determining past costs from the accounting
obtain current pricing from suppliers. This is done
system or by looking at previous materials invoices.
by sending information on the quantity of materials
Determining historical costs based on data from the ac-
needed to the supplier for pricing. Sometimes the supplier
counting system is done by determining the material cost
will do the quantity takeoff for you; however, when you have
for a certain quantity of work and dividing it by the quan-
the supplier perform the quantity takeoff, you must make
tity of work performed. This calculation is performed by
sure that the supplier is guaranteeing that there are sufficient
solving Eq. (19-1) for cost per unit and is expressed by the
quantities to perform the work. If the supplier does not
following equation:
guarantee that there are sufficient quantities, you should
perform your own quantity takeoff to verify that there are Cost
sufficient quantities of materials to complete the work. Cost!per!Unit ⫽ ˛ (19-2)
˛Quantity
Supplier pricing can be obtained by sending the supplier a
Request for Materials Quote, such as the one shown in
Figure 19-1, or by calling for pricing. It is usually better to EXAMPLE 19-1
get written pricing than a telephone quote because there is A recent project included 1,235 square feet of 4-inch-thick side-
less of a chance that there will be a misunderstanding. When walk. The cost of the concrete materials for the sidewalk was
you receive a telephone quote, you should document it on a $1,372. Determine the material cost for 1 square foot of sidewalk.
phone quote sheet such as the one shown in Figure 2-4.
Solution: The material cost per square foot is determined by using
In Figure 19-1, two columns are used for the quantity.
Eq. (19-2) as follows:
The left column is used for the numeric portion of quantity
(for example, 23, 56, and so forth) and the right column is $1,372
Material!Cost ⫽ ⫽ $1.111/ft2 䊏
used for units (for example, ft, cyd, miles, and so forth). The 1,235!ft2
˛ ˛

total cost for each item equals the numeric portion of the
quantity multiplied by the cost per unit. This calculation is For historical data to be accurate, the actual project
expressed by the following equation: costs and quantities must be accurately tracked in the ac-
counting system. Poor tracking of costs or failure to update
Cost ⫽ (Quantity)(Cost!per!Unit) (19-1)
changes in the quantities will render the data useless.
Another way to obtain current pricing from suppliers is The other method of determining historical cost is to
to set up contracts for materials with them. For example, you look at previous invoices to see what prices the company has
may set up an annual contract with a hardware supplier to been paying. When looking at previous invoices one should

228
Material Pricing 229

FIGURE 19-1 Request for Materials Quote

use the most current invoices from a job with equivalent the shipping from the factory to the jobsite, and should the
specifications and similar quantities. unit be damaged during shipping, the purchaser would be re-
The least accurate source of data is national standards sponsible for the cost of the damage. However, if the price for
books. Material prices vary greatly around the country. As a the HVAC unit is quoted FOB the jobsite, the supplier is re-
result, national standard books should only be used as a last sponsible for shipping the unit to the jobsite, and should the
resort for material pricing when supplier quotes or historical unit be damaged during shipping, the supplier, not the pur-
data are not available. chaser, would be responsible for the cost of the damage.
In addition to the cost of the materials, material pricing Prices for shipping should be obtained from the sup-
needs to include shipping costs, sales tax, and storage costs. plier or a shipper. Shipping charges from local suppliers are
When material prices are not guaranteed or materials are often a flat rate per delivery or by the hour. For example, a
purchased over a long period of time, changes in the mater- lumber supplier may charge $25 per delivery and an aggre-
ial prices (escalation) need to be included in the pricing. gate supplier may charge $65 per hour for delivery. Long-
Let’s look at these costs. distance shipping by truck is often charged by the hundred-
weight (cwt) or fraction thereof. One hundredweight equals
100 pounds. Shipping rates may also be based upon the size
SHIPPING COSTS of the item being shipped. Long-distance shipping charges
are calculated as shown in the following example.
Material prices are often quoted FOB the factory, FOB the
supplier’s warehouse, or FOB the jobsite. The term “FOB” is
short for “free on board,” which identifies the point where the EXAMPLE 19-2
supplier relinquishes responsibility for shipping and protec- The price for an 11,225-pound HVAC unit has been quoted FOB
tion of the materials against loss to the purchaser of the ma- the factory. You have obtained a shipping price of $25.65/cwt to
terials. For example, if the price for a HVAC unit is quoted ship the unit from the factory to the jobsite. Determine the cost of
FOB the factory, the purchaser is responsible for paying for shipping the HVAC unit.
230 CHAPTER NINTEEN

Solution: The weight, in hundredweight, of the unit is calculated the project, in which case the material must be stored in an
as follows: out-of-the-way place and protected against theft and dam-
11,225!lb age. Storage costs for on-site storage may include temporary
Weight ⫽ ⫽ 112.25!cwt fencing or containers in which to store the material or secu-
100!lb/cwt
rity to protect the material and equipment from theft.
The shipper will charge for 113 cwt. The shipping cost is calculated Alternatively, the materials can be stored off-site. When the
as follows: materials are stored off-site, secure storage space for the ma-
Shipping!Cost ⫽ (113!cwt)($25.65/cwt) ⫽ $2,898.45 䊏 terials may need to be rented, and the materials are shipped
to the site as they are needed, all of which adds to the cost of
the materials.
SALES TAX
States often charge sales tax on material purchases. Some ESCALATION
states may charge sales tax on permanent materials (materi-
als incorporated into the finish project such as doors and Sometimes material suppliers will not guarantee the mater-
windows) but not charge sales tax on construction materials ial prices for the duration of the construction project, as is
(materials used in the construction process but not incorpo- often the case with lumber. When the material prices are ex-
rated into the finished project, such as saw blades). The sales pected to increase over the duration of their use on the con-
tax rate is expressed as a percentage of the sales price of the struction project, the estimator needs to include an escala-
taxable materials. Some states allow counties and cities to tion allowance in the material prices to cover the anticipated
levy additional sales tax. As a result, the sales tax rate may increases. When dealing with annual contracts or material
vary by city and county as well as by state. In addition, some suppliers that raise their prices annually, it is easy to antici-
public projects are exempt from sales tax. If this is the case, it pate price changes and incorporate these changes into the
will be identified in the construction documents. Because bids. With pricing that fluctuates with market prices, such as
the sales tax rate can vary by project, city, county, and state, it lumber, escalation is impossible to accurately predict, but es-
is important for the estimator to determine the local sales tax calation still needs to be included in the bid. Trade maga-
rate for each project. zines, which report on the trends in the industry, can give a
When purchasing materials from an in-state supplier, contractor insight into factors within the economy and in-
the supplier often collects the sales tax along with the cost of dustry that may lead to escalation of material costs. Material
the materials. When purchasing materials from an out-of- pricing can be adjusted for escalation using the following
state supplier, the supplier often does not pay sales tax on the equation:
materials, leaving purchasers to pay their local sales tax di- CostEscalated ⫽ Cost(1 ⫹ f ) (19-4)
rectly to the state. When getting prices from suppliers, the es-
timator must find out whether a supplier has included sales where
tax in the pricing or if sales tax needs to be added. CostEscalated ⫽ Escalated Material Cost
The cost of the sales tax is determined by multiplying Cost ⫽ Quoted Cost of Materials
the cost of the taxable materials by the sales tax rate. This f ⫽ Expected Escalation or Inflation Rate (in
calculation is expressed by the following equation: decimal format)
Sales!Tax ⫽ (Taxable!Materials)(Sales!Tax!Rate) (19-3) If material prices are expected to decline, a negative es-
calation rate may be used in this equation. The calculation of
the escalated cost is shown in the following example.
EXAMPLE 19-3
You have been quoted $125,236.23 for an order of lumber, all of
EXAMPLE 19-4
which is subject to sales tax. The price does not include sales tax.
The local sales tax rate is 5.25%. How much sales tax must be paid You have been quoted $88,325 for an order of lumber. You expect
on the lumber? lumber prices to increase by 3.5% between now and the time you
place the order. How much should you include in your bid to cover
Solution: The sales tax is calculated using Eq. (19-3) as follows: the cost of the lumber?
Sales!Tax ⫽ ($125,236.23)(0.0525) ⫽ $6,574.90 䊏 Solution: The expected escalation rate is 3.5%, or 0.035. The esca-
lated cost is calculated using Eq. (19-4) as follows:
CostEscalated ⫽ ($88,325)(1 ⫹ 0.035) ⫽ $91,416 䊏
STORAGE COSTS
When purchasing large quantities of materials, large equip- To protect against material price increases, some con-
ment, or materials before they are needed, the contractor tractors may purchase large quantities of materials at the be-
may have to provide a place to store the materials and equip- ginning of the construction project and store the materials
ment until they are installed. The storage can take place on and pay the storage costs rather than risk price increases.
Material Pricing 231

EXCEL QUICK TIP 19-1


Request for Materials Quote
The request for materials quote shown in Figure 19-1 is set up in a spreadsheet by entering the data and formatting the cells
as follows:
A B C D E

1 REQUEST FOR MATERIALS QUOTE


2
3 To:
4
5
6 From:
7
8
9 Project:
10
11 QUANTITY DESCRIPTION $/UNIT COST
12 -
13 -
14 -
15 -
16 -
17 -
18 -
19 -
20 -
21 -
22 -
23 -
24 -
25 -
26 -
27 -
28 -
29 -
30 -
31 -
32 SUBTOTAL -
33 DELIVERY -
34 SUBTOTAL -
35 SALES TAX 0.00% -
36 TOTAL -
37
The supplier agrees to supply the materials in a timely manner and for the prices stated above. This
38 quote is good for 60 days.
39
40 By: Date:
41

The following formulas need to be entered into the asso- After entering the formula in Cell E12, copy the formula
ciated cells: in Cell E12 to Cells E13 through E31. One assumption in
this spreadsheet is that all material costs (except for the
Cell Formula delivery cost) are subject to sales tax. The cells containing
the costs are formatted using the comma style, which re-
E12 =A12*D12 places zeros with dashes.
E32 =SUM(E12:E31)
E33 =E32*D33
E34 =E32+E33
E36 =E34+E35

CONCLUSION PROBLEMS
Material costs include the cost of the materials, shipping 1. A recent project included 11,000 square feet of 5-inch-
costs, sales tax, storage costs, and escalation allowance. thick concrete slab. The cost of the concrete material for
Material pricing may be obtained from suppliers, historical the sidewalk was $15,950. Determine the material cost
data, and national reference books. for 1 square foot of sidewalk.
232 CHAPTER NINTEEN

2. A recent project included 6,450 square feet of painting. 6. You have been quoted $27,569.65 for electrical
The cost of the paint for the painting was $609.10. switchgear, which is subject to sales tax. The price does
Determine the material cost for 1 square foot of painting. not include sales tax. The local sales tax rate is 7.60%.
3. The price for a 5,595-pound HVAC unit has been quoted How much sales tax must be paid on the switchgear?
FOB the factory. You have obtained a shipping price of 7. You have been quoted $165,665 for an order of lumber.
$15.75/cwt to ship the unit from the factory to the job- You expect lumber prices to increase by 7.0% between
site. Determine the cost of shipping the HVAC unit. now and the time you place the order. How much
4. The price for a 3,023-pound transformer has been quoted should you include in your bid to cover the cost of the
FOB the factory. You have obtained a shipping price of lumber?
$21.29/cwt to ship the unit from the factory to the jobsite. 8. You have been quoted $2,359 for an order of drywall.
Determine the cost of shipping the transformer. You expect drywall prices to increase by 4.25% between
5. You have been quoted $13,568.22 for an order of lum- now and the time you place the order. How much
ber, all of which is subject to sales tax. The price does should you include in your bid to cover the cost of the
not include sales tax. The local sales tax rate is 4.25%. drywall?
How much sales tax must be paid on the lumber? 9. Set up Excel Quick Tip 19-1 in Excel.
CHAPTER TWENTY

LABOR PRODUCTIVITY
AND HOURS

In this chapter you will learn what factors affect labor pro- (2!persons)(8!hr/person-day)
Labor Hours/Unit ⫽
ductivity and how to calculate labor productivity using his- (1,600!ft2/day)
torical data, field observations, and national reference books. ⫽ 0.010!lhr/ft2 䊏
You will also learn how to calculate labor hours from labor
productivity. Output per labor hour is converted to labor hours per
unit by dividing 1 by the output, using the following equation:
1

L abor productivity is a measure of how fast construc- Labor Hours/Unit ⫽ (20-2)


Output
tion tasks can be performed. Productivity can be re-
ported as the number of units performed during a
labor hour1 or crew day, which is often referred to as output. EXAMPLE 20-2
For example, the productivity for a two-person framing crew Convert the output of 100 square feet of sheathing per labor hour
installing sheathing may be 1,600 square feet of sheathing to labor hours per square foot.
per 8-hour day. It also may be expressed as 100 square feet of
sheathing per labor hour (lhr). When measuring output, the Solution: The number of labor hours per square foot is calculated
using Eq. (20-2) as follows:
larger the number, the greater is the productivity.
Alternatively, it can be expressed as the number of labor 1
hours required to complete one unit of work. For example, Labor Hours/Unit ⫽ ⫽ 0.010!lhr/ft2 䊏
(100!ft2/lhr)
the productivity to install the sheathing may be expressed as
0.010 labor hour per square foot. In most estimating, labor
hours per unit are used rather than output. When measuring FACTORS AFFECTING LABOR
productivity in labor hours per unit, the smaller the number, PRODUCTIVITY
the greater is the productivity.
Productivity is affected by many factors, including project
Daily output per crew day is converted to labor hours
size, overtime, size of crew, delays, interruptions, weather,
per unit by dividing the number of labor hours performed
project layout, safety, and so forth. Because these factors vary
by the crew per day by the output, using the following
from project to project, it is impossible to assign one pro-
equation:
ductivity rate to a given task. Each time an estimator bids a
Labor Hours project, he or she must look at these factors and determine
Labor Hours/Unit ⫽ (20-1)
Output whether to expect a higher or lower productivity than on
previous projects and adjust the productivity accordingly.
Let’s look at some of these factors.
EXAMPLE 20-1
Convert the output of 1,600 square feet of sheathing per 8-hour day
for a two-person framing crew to labor hours per square foot.
Project Size
Solution: The number of labor hours per square foot is calculated Larger projects tend to have higher productivities, which is
using Eq. (20-1) as follows: particularly true for projects that are highly repetitive. This is

233
234 CHAPTER TWENTY

because of a number of factors, including the spreading out should only be used to solve short-term labor problems. If a
of the fixed time over a greater number of units, workers long-term solution is needed, additional workers or crews
learning to do the task faster, and specialization among the need to be added.
crew.
The time it takes to complete a task can be divided into Size of Crew
a fixed component and a variable component. The fixed
component includes things that must be done regardless of The size of the crew has a great effect on productivity.
the number of units of work completed. Daily setup takes a Having a crew that is too large or too small will lead to a de-
fixed amount of time each day, regardless of the daily pro- crease in productivity. With crews that are too large, mem-
duction. The variable component includes things that are a bers of the crew are often in each other’s way, or there may
function of the number of units of work completed. To not be sufficient work to keep all of the members of the crew
demonstrate fixed and variable time, let’s look at an example busy. Crews that are too small often lack enough members to
of installing entry doors on a residence. To install one entry complete the tasks. For example, a two-person framing crew
door, the carpenter needs to go to the residence, familiarize will find it difficult to stand walls because they lack a suffi-
himself or herself with the plans, set up the equipment, in- cient number of workers to lift all but the smallest walls in
stall the door, clean up, and leave. Although the installation place. Because of this, there is an optimum size of crew,
of the door by itself may only take 1 hour, the total process which is different for different projects.
may take 4 hours. In this case, the fixed time is 3 hours and
the variable time is 1 hour (the time actually used to install Delays
the door), with the fixed time being spread over one door.
One of the greatest enemies to productivity comes from de-
This results in a productivity of 4 labor hours per door.
lays on the construction project. For work to proceed on the
Should the carpenter install a second door at the same time,
project, the right materials, equipment, labor, and design in-
both doors could be installed in 5 hours, resulting in a pro-
formation must be on the project when the project is ready
ductivity of 2!1>2 labor hours per door, spreading the fixed
for it. If the right materials and equipment are not available
time over two doors. Three doors would result in a produc-
when they are needed, time must be spent obtaining them or
tivity of 2 labor hours per door.
the crews must leave the project until they have been obtained.
As a person performs a task over and over, he or she
This wastes time and decreases productivity. When the
should become more proficient in performing the task. This
wrong class of labor is on the project, work may stop on the
is often referred to as moving down the learning curve. An
project until the right class of labor is available. If work pro-
example of this is an electrician wiring hotel rooms. On the
ceeds with the wrong class of labor, it is often less productive
first room he or she has to consult the plans often to deter-
than if it was performed by the correct class of labor. When
mine the location of the outlets, switches, and fixtures,
the necessary design information is not available or is incor-
which increases the time it takes to wire the room. On the
rect, work must stop until the correct design information is
second room, the electrician needs to consult the plans less
obtained, decreasing the productivity of the work.
than he or she did on the first room. By the time the electri-
cian has done a dozen or so rooms, he or she can complete
the rooms without consulting the plans, further increasing Interruptions
his or her productivity. Interruptions in work flow decrease productivity. When a
As the projects get larger, the crew can specialize in per- worker is jumping from task to task, he or she is less produc-
forming certain tasks. For example, one framing crew may tive than if he or she is allowed to work on a single task until
frame the walls while another frames the floors and yet an- it is complete because time is being wasted moving in from
other frames the roof. This specialization moves the crews task to task.
down the learning curve faster than if all three crews framed
walls, floors, and roofs.
Weather
Weather has a great affect on productivity. Hot weather tires
Overtime workers out and drains their strength, requiring them to take
Increasing the amount of time workers work each week de- frequent breaks for rest and to drink fluids, thus decreasing
creases the productivity of the workers. The longer this goes their productivity. Cold weather requires workers to wear
on, the greater is the decrease in productivity. For example, weather protection that decreases their mobility and ability to
workers may easily work an extra Saturday one week to handle small items (such as nails) and in turn decreases their
complete a project with little or no loss in production. productivity. In cold weather, workers tire easily and must
However, if the workers work every Saturday for 2 months, take frequent breaks for rest and to warm up. Wet weather
they will begin to tire and will need a rest. As a result, a makes the site muddy and working surfaces slippery, decreas-
greater loss in productivity will occur than it did when they ing productivity. Snow requires workers to remove the snow
only worked one Saturday. Because of the loss in productiv- from the work area before beginning to work and covers up
ity and the higher labor costs, it is uneconomical to use materials, making them harder to find. This results in a de-
overtime to solve long-term labor problems. Overtime crease in productivity. In addition, adverse weather requires
Labor Productivity and Hours 235

that workers protect their work against the weather. For ex- Cycle Time
ample, concrete must be protected against drying too quickly
on hot days and freezing on cold days. Protecting construc- Cycle time is used for repetitive tasks. Repetitive tasks are
tion work from weather also decreases productivity. tasks that repeat over and over, such as installing sheathing
on a floor. In the case of sheathing, the process of placing
Project Layout one piece of sheathing is known as a cycle. The cycle consists
of picking up a sheet of sheathing from the stock pile, mov-
The location where materials can be delivered and stored in ing it to where it is going to be used, placing and fastening
relationship to the construction project affects productivity. the sheathing, and returning to the stock pile. The produc-
On sites where materials cannot be delivered or stored near tivity of repetitive tasks is determined by measuring the time
the location at which they will be used, the time it takes to it takes to complete a cycle, which is known as the cycle time.
move the materials will increase and the productivity will Because the time it takes to complete a cycle varies from
decrease. cycle to cycle, at least 30 cycles should be measured when
determining the cycle time. The average cycle time is deter-
Safety mined by summing the cycle times and dividing by the num-
The setup and use of safety equipment often decreases pro- ber of observations, using the following equation:
ductivity. In spite of the time it takes to set up and use safety (CT1 ⫹ CT2 ⫹ p ⫹ CTn)
equipment, safety should never be sacrificed for production. CTAve ⫽ (20-4)
n
Estimators need to incorporate the time it takes to set up and
use safety equipment into the productivity rates. where
Production can be estimated using historical data, field CT ⫽ Cycle Time
observations, and national standards. n ⫽ Number of Observations

HISTORICAL DATA EXAMPLE 20-4


The best source for labor productivity is historical data. The cycle times in Table 20-1 were observed for the process of in-
Historical labor productivity is obtained by determining the stalling plywood sheathing. Determine the average cycle time.
number of labor hours required to complete a certain quan- Solution: The average cycle time is calculated using Eq. (20-4) as
tity of work on past jobs. This information is obtained from follows:
the accounting system. The productivity is calculated by di-
Average CT ⫽ [(10.34 ⫹ 12.27 ⫹ 10.90 ⫹ 17.67 ⫹ 8.74 ⫹ 10.90
viding the number of labor hours by the quantity of work
performed as expressed by the following equation: ⫹ 10.48 ⫹ 8.32 ⫹ 11.84 ⫹ 15.42 ⫹ 10.11 ⫹ 11.09
⫹ 10.48 ⫹ 10.34 ⫹ 10.53 ⫹ 8.98 ⫹ 7.99
Labor Hours
Labor Hours/Unit ⫽ (20-3) ⫹ 12.22 ⫹ 13.82 ⫹ 14.10 ⫹ 10.25 ⫹ 15.60 ⫹ 10.25
Quantity
⫹ 12.41 ⫹ 16.45 ⫹ 11.47 ⫹ 10.01 ⫹ 13.91
⫹ 8.08 ⫹ 9.35) min/cycle]/30
EXAMPLE 20-3 (344.32!min/cycle)
⫽ ⫽ 11.48!min/cycle 䊏
A recent project included 1,235 square feet of 4-inch-thick sidewalk. 30
It took 11 labor hours to complete the sidewalk. Determine the pro-
ductivity in labor hours per square foot based on this historical data. To convert the average cycle time to labor hours per
unit, one must take into account how the observed condi-
Solution: The number of labor hours per square foot is calculated tions compare to typical conditions, size of the crew, system
using Eq. (20-3) as follows: efficiency, and the units constructed per cycle.
11!lhr Often the observations are taken over a short period of
Labor Hours/Unit ⫽ ⫽ 0.0089!lhr/ft2 䊏 time, and, as a result, they are not representative of the aver-
1,235!ft2
age conditions under which the work is performed. To ac-
For historical data to be accurate, the actual labor hours count for this, an adjustment factor is used. If the cycle times
must be accurately tracked in the accounting system and an were measured at a time when productivity was higher than
accurate record of the quantities of work performed must be average because of favorable conditions, an adjustment factor
kept. Poor tracking of labor hours or failure to update that is less than 1 is used. If the cycle times were measured at
changes in the quantities of work performed will render the a time when productivity was lower than average because of
data useless. unfavorable conditions, an adjustment factor that is greater
than 1 is used. The adjustment factor must be estimated by
the person making the observations, which is a judgment call.
FIELD OBSERVATIONS No systems or processes are 100% efficient, and people
Labor productivity from field observations can be calculated are not always working on those items measured during a
in three ways: cycle time, rate of progress, and daily produc- cycle time. During an hour the workers may only be spending
tion. Let’s look at each of these ways. 50 minutes working on tasks measured in the cycle time.
236 CHAPTER TWENTY

TABLE 20-1 Cycle Times (CTs) for Example 20-4


Observation CT (min) Observation CT (min) Observation CT (min)
1 10.34 11 10.11 21 10.25
2 12.27 12 11.09 22 15.60
3 10.90 13 10.48 23 10.25
4 17.67 14 10.34 24 12.41
5 8.74 15 10.53 25 16.45
6 10.90 16 8.98 26 11.47
7 10.48 17 7.99 27 10.01
8 8.32 18 12.22 28 13.91
9 11.84 19 13.82 29 8.08
10 15.42 20 14.10 30 9.35

During the remaining 10 minutes the workers may be taking where


breaks or engaged in other nonproductive tasks, such as CTAve ⫽ Average Cycle Time in Minutes per Cycle
going to the bathroom. The system efficiency is the number AF ⫽ Adjustment Factor
of productive minutes per hour. Typical system efficiencies
Size ⫽ Size of Crew
are 45 to 50 minutes per hour.
When measuring the cycle time the number of workers SE ⫽ System Efficiency (Minutes per 60-Minute Hour)
that were required to complete one cycle was not taken into Units ⫽ Number of Units Produced per Cycle
account. A one-hour cycle using two crew members will re-
quire twice the number of labor hours as a one-hour cycle EXAMPLE 20-5
using a single crew member. The size of the crew takes this Using the average cycle time from Example 20-4, a system efficiency
into account. of 50 minutes per hour, an adjustment factor of 0.90, and a crew
Finally, one needs to account for the number of units size of two, determine the productivity in labor hours per square
produced during a single cycle because production is mea- foot of sheathing.
sured by the number of units produced. Solution: One sheet is 32 square feet. The productivity is calcu-
All of these factors are accounted for in the following lated using Eq. (20-5) as follows:
equation:
(11.48!min/cycle)(0.9)(2)
Labor Hours/Unit ⫽
(CTAve)(AF)(Size) (50!min/hr)(32!ft2/cycle)
Labor Hours/Unit ⫽ (20-5)
(SE)(Units) ⫽ 0.0129!lhr/ft2 䊏

EXCEL QUICK TIP 20-1


Cycle Time Worksheet
The spreadsheet shown in the following figure can be used to calculate the average cycle time and the labor hours per unit.
A B C D E F G H
1 Cycle Time Calculator
2 OBS. CT (min) OBS. CT (min) Adjustment Factor 0.90
3 1 10.34 16 8.98 Crew Size 2
4 2 12.27 17 7.99 System Efficiency 50
5 3 10.90 18 12.22 Units 32.00
6 4 17.67 19 13.82
7 5 8.74 20 14.10 Average Cycle Time 11.48
8 6 10.90 21 10.25 Labor-Hour/Unit 0.01291
9 7 10.48 22 15.60
10 8 8.32 23 10.25
11 9 11.84 24 12.41
12 10 15.42 25 16.45
13 11 10.11 26 11.47
14 12 11.09 27 10.01
15 13 10.48 28 13.91
16 14 10.34 29 8.08
17 15 10.53 30 9.35
Labor Productivity and Hours 237

To complete this spreadsheet, enter the data and format the The data is entered into Cells B3 through B17, E3 through
cells as shown in the figure. The following formulas need to E17, and H2 through H5. The data shown in the foregoing
be entered into the associated cells: figure is from Examples 20-4 and 20-5.

Cell Formula
H7 =AVERAGE(B3:B17,E3:E17)
H8 =H7*H2*H3/(H4*H5)

Rate of Progress Quantity ⫽ (4!ea)(440!ft/ea) ⫹ (200!ea)(40!ft/ea)


⫹ (100!ea)(20!ft/ea)
Rate of progress is used for linear tasks. Linear tasks are tasks
that progress along a line rather than in a cyclical motion. ⫽ 11,760!ft
Linear tasks include paving roads, installing pipes, painting The number of times the operator needs to travel is one less than
striping on roads, installing curbs, and so forth. The produc- the number of lines. The number of lines and travel time are calcu-
tivity for linear tasks is measured by the rate the task proceeds lated as follows:
or rate of progress. Linear tasks consist of two components: Number!of!Lines ⫽ 4!ea ⫹ 200!ea ⫹ 100!ea ⫽ 304!ea
production time and travel time. Production time includes
TT ⫽ (303!ea)(0.5!min/ea) ⫽ 151.5!min
the time spent producing the finished product. In the case of
an employee operating a pavement-striping machine to paint The productivity is calculated using Eq. (20-6) as follows:
parking stalls, this time includes the time the employee is
a
11,760!ft
painting the lines in the parking lot. The second component ⫹ 151.5!minb(1)
40!ft/min
of a linear task is the travel time. In the case of the employee Labor Hours/Unit ⫽
(11,760!ft)(50!min/hr)
painting the parking stalls, the travel time is the time spent
Labor Hours/Unit ⫽ 0.000758!lhr/ft 䊏
moving the striping machine from the end of one line to the
beginning of the next line. The travel time represents breaks
in the work and must be included in the production rate. As
EXCEL QUICK TIP 20-2
with repetitive tasks, when calculating the productivity of lin-
ear tasks, one must include the system efficiency. The produc- Rate of Progress Worksheet
tivity is calculated from the following equation: The spreadsheet shown in the following figure can be
used to calculate the labor hours per unit using the rate of
a
Quantity
⫹ TTb(Size) progress:
RoP
Labor Hours/Unit ⫽ (20-6)
(Quantity)(SE)
A B C
where 1 Rate of Progress Calculator
Quantity ⫽ Quantity of Work to Be Performed 2 Quantity 11,760 units
3 Rate of Progress 40 units per min
RoP ⫽ Rate of Progress Measured in Units per
4 No. of Moves 303 ea
Minute 5 Time per Moves 0.5 min
TT ⫽ Travel Time (Minutes) 6 Crew Size 1 persons
Size ⫽ Size of Crew 7 System Efficiency 50 per 60 min hr
SE ⫽ System Efficiency (Minutes per 60-Minute 8 Labor-Hour/Unit 0.000758 lhr/unit
Hour)
To complete this spreadsheet, enter the data and format
the cells as shown in the figure. The following formula
needs to be entered into Cell B8:
EXAMPLE 20-6
An operator of a paint-striping machine is painting parking stalls =(B2/B3+B4*B5)*B6/(B2*B7)
in a parking lot. The work consists of 4 lines 440 feet long, 200 In this equation the travel time is broken down into two
lines 40 feet long, and 100 lines 20 feet long. When striping, the components: number of moves and the time per move.
operator can paint 40 feet of line per minute. The travel time be-
The travel time is calculated by multiplying the number of
tween lines is 0.5 minute. Using a system efficiency of 50 minutes
moves (Cell B4) by the time per move (Cell B5).
per hour, determine the productivity for striping of the parking lot
in labor hours per foot. The data is entered into Cells B2 through B7. The data
shown in the foregoing figure is from Example 20-6.
Solution: The quantity of work is calculated as follows:
238 CHAPTER TWENTY

Daily Production used when historical data or field observations are not avail-
able or as a check of the calculated productivity. When using
Alternatively, the production for all tasks can be determined national standards, the labor productivity should be ad-
by measuring the quantity of work performed during a day justed for area, project size, time of year, and so forth.
and dividing it into the number of labor hours required to Sample labor productivity rates for many tasks in Part II of
complete the work. The productivity is determined by Eq. this book are given in Appendix C.
(20-3) in the same manner the productivity was determined
from historical data. Because the whole day is used, the sys-
tem efficiency is already incorporated in the calculation. LABOR HOURS
The number of labor hours required to complete a task is
EXAMPLE 20-7 calculated by multiplying the labor productivity (lhrⲐunit)
by the quantity of work and is expressed by the following
The measured output for a crew is 1,696 square feet of sheathing in
1 day. The crew consists of two crew members, who work 8 hours
equation:
each during the day. Determine the productivity of the crew in Labor!Hours ⫽ (Quantity)(Labor Hours/Unit) (20-7)
labor hours per square foot of sheathing.
Solution: The number of labor hours per square foot is calculated
EXAMPLE 20-8
using Eq. (20-3) as follows:
A crew needs to install 100 square feet of ceramic tile. The esti-
(2!persons)(8!hr/person ⫺ day)
Labor Hours/Unit ⫽ 2
mated productivity is 0.2!lhrⲐsft. Determine the number of labor
(1,696!ft /day) hours required to install the ceramic tile.
⫽ 0.0094!lhr/ft2 䊏
Solution: The number of labor hours needed is calculated using
Eq. (20-7) as follows:
NATIONAL STANDARDS
Labor Hours ⫽ (100!ft2)(0.2!lhr/ft2) ⫽ 20!lhr 䊏
The least accurate source of data is that from national stan-
dards books. Labor productivity varies greatly around the
country. As a result, national standard books should only be

CONCLUSION counter top. Determine the productivity in labor hours


per linear foot based on this historical data.
Productivity is affected by a number of factors, including 6. A recent project included 2,015 square feet of sus-
project size, overtime, size of crew, delays, interruptions, pended acoustical ceiling. It took 26 labor hours to
weather, project layout, and safety. On each estimate, the es- complete the ceiling. Determine the productivity in
timator must take these factors into account when estimat- labor hours per square foot based on this historical data.
ing labor productivity. Labor productivity can be calculated
7. The cycle times in Table 20-2 were observed for the in-
from historical data, field operations, and national stan-
stallation of 8-foot by 15-inch batts of fiberglass insula-
dards. Field observations can be based on measured cycle
tion. Determine the average cycle time.
times, rate of progress, or daily production.
8. The cycle times in Table 20-3 were observed for the in-
stallation of residential windows. Determine the average
PROBLEMS cycle time.
9. Using the average cycle time from Problem 7, a system
1. Convert the output of 3,000 square feet of 6-inch-thick efficiency of 50 minutes per hour, an adjustment factor
blown fiberglass insulation per 8-hour day for a three- of 1.10, and a crew size of one, determine the productiv-
person crew to labor hours per square foot. ity in labor hours per square foot of insulation.
2. Convert the output of 165 square feet of brick veneer 10. Using the average cycle time from Problem 8, a system
per 8-hour day for a five-person crew to labor hours per efficiency of 45 minutes per hour, an adjustment factor
square foot. of 0.95, and a crew size of two, determine the productiv-
3. Convert the output of 9.9 square feet of concrete ma- ity in labor hours per window.
sonry unit per labor hour to labor hours per square 11. An operator of a paint-striping machine is painting the
foot. centerline of a road. The road is 5 miles long and in-
4. Convert the output of 35 lineal feet of trim per labor cludes 30 intersections. Each intersection is 50 feet wide,
hour to labor hours per lineal foot. and the centerline is not painted in the intersections.
5. A recent project included 40 lineal feet of counter top. It When striping, the operator can paint 50 feet of line per
took 12.5 labor hours to complete the installation of the minute. The average time it takes to get through the
Labor Productivity and Hours 239

TABLE 20-2 Cycle Times for Problem 7


Observation CT (min) Observation CT (min) Observation CT (min)
1 2.47 11 4.26 21 3.85
2 3.00 12 2.70 22 2.50
3 2.67 13 2.39 23 3.58
4 3.11 14 2.64 24 2.11
5 3.18 15 3.11 25 3.60
6 3.08 16 2.59 26 2.69
7 3.89 17 3.00 27 2.54
8 3.10 18 4.90 28 2.70
9 4.38 19 3.72 29 2.88
10 4.62 20 2.93 30 2.77

TABLE 20-3 Cycle Times for Problem 8


Observation CT (min) Observation CT (min) Observation CT (min)
1 37.26 11 56.55 21 39.57
2 28.55 12 37.90 22 29.82
3 52.57 13 55.91 23 46.70
4 34.85 14 38.51 24 30.95
5 42.27 15 41.47 25 35.41
6 42.41 16 27.97 26 61.83
7 30.87 17 32.15 27 31.12
8 46.36 18 60.10 28 33.37
9 36.77 19 36.27 29 50.72
10 32.89 20 39.33 30 37.64

intersection is 2 minutes. Using a system efficiency of plumber and an apprentice, who work 10 hours each
45 minutes per hour, determine the productivity for during the day. Determine the productivity of the crew
striping the road in labor hours per mile. in labor hours per foot of pipe.
12. An asphalt-paving crew is paving a 36-foot-wide section 15. A crew needs to install 3,200 square feet of sheathing.
of road 12 miles long. The road will be paved in widths The estimated productivity is 0.011!lhr/sft. Determine
of 12 feet, requiring the paving crew to make three the number of labor hours required to install the
passes along the road. At the end of each pass, it will take sheathing.
the paving crew 2 hours to move to the start of the road 16. A crew needs to paint 11,625 feet of parking lot striping.
in preparation for the next pass. The paving crew con- The estimated productivity is 0.8 labor hour per 1,000
sists of 11 persons. When paving, the paving crew can feet. Determine the number of labor hours required to
pave 12 feet of 12-foot-wide road per minute. Using a paint the striping.
system efficiency of 50 minutes per 60-minute hour, de-
17. Set up Excel Quick Tip 20-1 in Excel.
termine the productivity for paving the road in labor
hours per square yard. 18. Set up Excel Quick Tip 20-2 in Excel.
13. The measured output for a crew finishing concrete is
2,050 square feet per day. The crew consists of three
crew members, who work 8 hours each during the day.
Determine the productivity of the crew in labor hours REFERENCE
per square foot of concrete finished. 1. Labor hours are often referred to as man hours. A labor hour
14. The measured output for a plumbing crew is 115 feet of is defined as one person working for 1 hour. This book uses
1!1>2-inch steel pipe per day. The crew consists of a the term labor hour in lieu of man hour.
CHAPTER TWENTY–ONE

LABOR RATES

In this chapter you will learn how to determine hourly labor travel time to, between, and from a job that is paid by the
rates for a given class of employees. This chapter includes how company may not be billable to the job.
to determine wage rates and labor burden, including cash
equivalents and allowances, payroll taxes, unemployment in-
surance, workers’ compensation insurance, general liability in- WAGES
surance, insurance benefits, retirement contributions, union The annual wages should include the wages paid to employ-
payments, and other benefits. ees including all bonuses and any anticipated raises that may
occur during the project. Employees may be separated into
two groups based on how their wages are calculated.

T he hourly wage rate for a given employee class in- The first group includes all employees who are paid an
cludes the wages paid to the employee plus labor hourly wage based on the number of hours they work during
burden. Labor burden includes cash equivalents and the pay period. These employees are often referred to as
allowances paid to the employee, payroll taxes, unemploy- hourly employees. To estimate the wages for hourly employ-
ment insurance, workers’ compensation insurance, general ees, one must first estimate the number of hours each em-
liability insurance, insurance benefits, retirement contribu- ployee will work during an average pay period. Remember
tions, union payments, vacation, sick leave, and other bene- that pay rates for hourly employees may be different for
fits paid by the employer. The average wage rate paid during overtime, holidays, and weekends. The number of hours
the year is calculated by determining the annual costs of an worked may vary during different times of the year.
employee and dividing it by the number of billable hours as The wage rates for hourly employees and the rules gov-
shown in the following equation: erning overtime are set forth by union contracts or govern-
ment regulatory agencies. Federal Davis-Bacon wages—wage
Annual Costs rates that must be used on contracts with federal funding—
Labor Rate ⫽ (21-1)
Billable Hours vary by state, county, and type of work being performed; for
example, road work has different wages than residential con-
Let’s look at how to calculate the average hourly wage
struction. These rates are published as General Decisions by
rate for an employee class.
the U.S. Department of Labor. A sample General Decision is
given in Figure 21-1. To ensure that you are using the correct
BILLABLE HOURS General Decision for a specific project, you should obtain the
decision from the contracting officer for the project. The total
Billable hours are the number of hours an employee can be wages for an employee or group of employees is calculated by
billed to projects during a year, which is different than the multiplying the number of hours by the wage rate for these
number of hours an employee is paid during the year. Often hours and adding any anticipated bonuses.
employees are paid for holidays, vacation, and sick leave,
which are not billable to a project. The costs of holidays, va-
cation, and sick leave should be accrued throughout the year EXAMPLE 21-1
by billing it to the jobs as a burden cost and paid from the ac- A typical laborer works 50 hours per week for 20 weeks of the year
cruals at the time the holidays, vacation, and sick leave are and 40 hours per week for 29 weeks of the year, and the remaining
taken.1 In addition to holidays, vacation, and sick leave, 3 weeks per year comprises holiday leave, vacation, and sick leave,
240
Labor Rates 241

FIGURE 21-1a General Decision FIGURE 21-1b General Decision

for which the laborers are paid for 40 hours per week. Laborers are The total wages for an employee or group of employees is
paid $10.50 per hour and are paid time and a half on any hours calculated by summing the salaries of the employees and
worked over 40 hours per week. In the past the laborers received a adding any anticipated bonuses. The costs for salaried em-
$100 Christmas bonus. Determine the wages paid to the typical la- ployees are calculated by the week or month rather than by
borer and the number of billable hours during a one-year period.
the hour.
Assume that all hours are billable except holidays, vacation, and
Burden includes all payroll taxes, unemployment insur-
sick leave.
ance, workers’ compensation insurance, general liability in-
Solution: The typical laborer is paid $10.50 per hour for 40 hours surance, and fringe benefits or their cash equivalent paid for
per week for 52 weeks a year and is paid $15.75 ($10.50 ⫻ 1.5) for by the employer. Holidays, vacation, and sick leave are also
10 hours per week for 20 weeks. The wages, including bonus, are part of labor burden; however, they have already been ac-
calculated as follows:
counted for by not including these hours in the billable
Wages ⫽ ($10.50/hr)(40 hr/wk)(52 wk/yr) hours. Let’s look at how labor burden is calculated.
⫹ ($15.75/hr)(10 hr/wk)(20 wk/yr) ⫹ $100/yr
⫽ $25,090/yr
CASH EQUIVALENTS AND
The number of billable hours per year is calculated as follows:
ALLOWANCES
Billable Hours ⫽ (50 hr/wk)(20 wk/yr) ⫹ (40 hr/wk)(29 wk/yr)
Cash equivalents and allowances include cash paid in lieu of
⫽ 2,160 hr/yr 䊏
providing fringe benefits or cash paid as an allowance. In
The second group includes all employees who are paid a some cases where a company is required to provide fringe
flat rate per pay period and are known as salaried or exempt benefits, the employer may be allowed to pay the cash equiv-
employees. To estimate the wages for salaried employees, you alent of those benefits and let employees use the money to
do not need to know how many hours each employee works. purchase their own benefits if they so desire. Allowances are
242 CHAPTER TWENTY-ONE

Allowances ⫽ ($20/mo)(12 mo/yr) ⫽ $240/yr


Wages and Allowances ⫽ $25,090/yr ⫹ $240/yr
⫽ $25,330/yr 䊏

PAYROLL TAXES
The Federal Insurance Contributions Act (FICA) requires
employers to pay Social Security and Medicare taxes for each
employee. For the year 2010, the employer pays a Social
Security tax of 6.2% of each employee’s first $106,800 in
wages.2 Although the tax rate has not changed for many
years, the amount of wages on which the Social Security tax
is paid increases almost every year. Be sure to check with
your tax advisor or the Internal Revenue Service for the cur-
rent rates. For the year 2010, the employer pays a Medicare
tax of 1.45% of the employee’s entire wages.3 The employee
is required to match these payments. The Social Security and
Medicare taxes paid by an employee are deducted from his
or her wages and are not a cost to the employer. Cash equiv-
alents and allowances must be included when calculating
these taxes; however, in some cases the amount the employee
pays for his or her benefits may be excluded.

EXAMPLE 21-3
Determine the Social Security and Medicare taxes paid by the em-
ployer during the year for the typical laborer in Example 21-2. The
typical laborer pays $150 per month for health insurance, which is
not subject to Social Security and Medicare taxes. Use the tax rates
FIGURE 21-1c General Decision
for the year 2010.
Solution: The wages used in calculating the Social Security and
Medicare tax must include the allowances paid to the typical la-
used to help the employee cover out-of-pocket expenses as- borer and exclude the $150 per month paid by the employee for
sociated with their job. For example, a company located in health insurance. From Example 21-2 the annual wages, including
an out-of-the-way place or a company that requires their allowances, for the typical laborer are $25,330. This is reduced by
employees to use their personal vehicles during work hours the $1,800 ($150/mo ⫻ 12 mo/yr) per year the typical laborer pays
for health insurance. The typical laborer’s wages that are subject to
may pay employees a vehicle allowance. An allowance is dif-
Social Security and Medicare taxes are $23,530 ($25,330 – $1,800).
ferent than reimbursing the employee for expenses or
Because the typical laborer’s wages are less than $106,800, the em-
mileage because it is not based on the actual cost or mileage. ployer must pay 6.2% for Social Security tax on all of his or her
Reimbursements are not considered part of the labor wages wages. The Social Security tax is calculated as follows:
and burden but are costs that can be billed to the appropriate
project. Social Security Tax ⫽ (0.062)($23,530/yr) ⫽ $1,458.86/yr
Cash equivalents and allowances are treated as regular The Medicare tax is 1.45% of the laborer’s wages and is calculated
wages for the purpose of payroll taxes, unemployment in- as follows:
surance, workers’ compensation insurance, and general lia-
Medicare Tax ⫽ (0.0145)($23,530/yr) ⫽ $341.18/yr
bility insurance.
These same amounts are deducted from the laborer’s paychecks. 䊏

EXAMPLE 21-2
The typical laborer in Example 21-1 is paid a tool allowance of $20
UNEMPLOYMENT INSURANCE
per month. Determine the annual wages including allowances paid By law, employers are required to pay federal unemployment
to the typical laborer during a one-year period. tax (FUTA) and, if a state program exists, state unemploy-
Solution: From Example 21-1, the typical laborer is paid $25,090 per ment tax (SUTA).
year plus allowances. The wages, including allowances, are calculated For the year 2010 the federal unemployment tax rate is
as follows: 6.2% on the first $7,000 of each employee’s wages paid
Labor Rates 243

during the year.4 If a company pays into a state unemploy- the first laborer was paid $5,130, the second laborer was paid
ment program, the company may reduce its FUTA liability $11,000, and the third laborer was paid $9,200. Determine the fed-
by the amount paid into the program. This reduction is eral unemployment taxes paid by the employer on this laborer po-
limited to 5.4% of first $7,000 of each employee’s wages. To sition. The company can take the full 5.4% credit against its federal
unemployment tax.
receive the entire 5.4%, the company must pay its state un-
employment tax on time. When a company is eligible for Solution: The employer must pay 0.8% on the first $7,000 paid
the full credit, its federal unemployment tax rate is reduced to each employee. The federal unemployment tax is calculated as
to 0.8% (6.2% - 5.4%) of the first $7,000 of each em- follows:
ployee’s wages paid during the year. FUTA ⫽ ($5,130/yr)(0.008) ⫹ ($7,000/yr)(0.008)
A company’s state unemployment tax rate is based in
⫹ ($7,000/yr)(0.008)
part on its claims history and must be obtained from the
⫽ $153.04/yr 䊏
state agency that administers the state unemployment tax.
The maximum rate a state charges and the amount of the
employees’ wages that are subject to tax vary from state to Here employee turnover increased the costs of FUTA by
state. For example, for the year 2006, Texas’ minimum rate 273%. The same situation occurs with SUTA. One way to take
was 0.40%, the maximum rate was 7.64%, and companies this into account is to determine the average FUTA and SUTA
paid SUTA on the first $9,000 of each employee’s wages paid paid during the last year as a percentage of labor costs based on
during the year. Arizona’s minimum rate was 0.02%, the data from the company’s accounting system. These percentages
maximum rate was 5.40%, and companies paid SUTA on the then can be applied to all labor costs when determining labor
first $7,000 of each employee’s wages paid during the year. burden. The calculations are shown in the following example:
Utah’s minimum rate was 0.40%, the maximum rate was
9.4%, and companies paid SUTA on the first $24,000 of each EXAMPLE 21-6
employee’s wages paid during the year.
Last year your company paid $1,191,300 in wages, $2,486 in FUTA,
and $7,992 in SUTA. Determine the company’s FUTA and SUTA
EXAMPLE 21-4 rate as a percentage of wages paid. Also determine the state unem-
ployment and federal unemployment taxes paid by the employer
Determine the state unemployment and federal unemployment for the typical laborer in Example 21-2 based on these rates.
taxes paid by the employer during the 2010 year for the typical la-
borer in Example 21-2. The company’s state unemployment rate is Solution: The FUTA rate as a percentage of wages is calculated as
2.0% on the first $9,000 of the employee’s wages. The company can follows:
take the full 5.4% credit against its federal unemployment tax. $2,486/yr
FUTA Percentage ⫽ ⫽ 0.00209 or 0.209%
Solution: The wages used in calculating the unemployment taxes $1,191,300/yr
must include the allowances paid to the laborer. From Example 21-2
The FUTA paid on a typical laborer is calculated as follows:
the annual wages, including allowances, for the laborer are $25,330.
Because the laborer’s wages are more than $9,000, the employer FUTA ⫽ ($25,330/yr)(0.00209) ⫽ $52.94/yr
must pay 2.0% on $9,000 for state unemployment tax. The state un-
employment tax is calculated as follows: The SUTA rate as a percentage of wages is calculated as follows:
$7,992/yr
SUTA ⫽ 0.02($9,000/yr) ⫽ $180.00/yr SUTA Percentage ⫽ ⫽ 0.00671 or 0.671%
$1,191,300/yr
The federal unemployment tax is calculated as follows:
The SUTA paid on a typical laborer is calculated as follows:
FUTA ⫽ 0.008($7,000/yr) ⫽ $56.00/yr
SUTA ⫽ ($25,330/yr)(0.00671) ⫽ $169.96/yr
The total unemployment tax paid is $236.00 ($180.00 ⫹ $56.00).
䊏 The total unemployment tax is $222.90 ($52.94 ⫹ $169.96). 䊏

The underlying assumption in the calculations for Looking at Examples 21-4 and 21-6, one notices that the
Example 21-4 is that the same person fills the laborer posi- amount calculated by Example 21-6 is less than the legally re-
tion for the entire year. This is seldom the case. If more than quired amount calculated by Example 21-4. This is because the
one person fills the laborer position during the year because method used in Example 21-6 uses an average percentage for
of employee turnover, the company must pay FUTA on the the FUTA and SUTA calculations and bases these calculations
first $7,000 of wages from each employee as shown by the fol- on the total wages paid. As a result it understates the FUTA and
lowing example. SUTA on lower-cost employees (such as laborers) and over-
states the cost on higher-paid employees. For all of the field
employees, the company in the foregoing examples paid 20%
EXAMPLE 21-5 more FUTA and SUTA in Example 21-6 than would have been
During the year, a laborer’s position is filled by three different la- calculated using the procedures used to calculate FUTA and
borers, two of whom left the company during the year. For the year, SUTA in Example 21-4 because of employee turnover.
244 CHAPTER TWENTY-ONE

WORKERS’ COMPENSATION pensation insurance rate for laborers is $6.25 per $100.00 in
wages.
INSURANCE
Solution: The wages used in calculating the workers’ compensa-
By law all employers are required to provide their employees tion insurance must include the allowances paid to the laborer.
with workers’ compensation insurance. Workers’ compensa- From Example 21-2 the annual wages, including allowances, for the
tion insurance is governed by the individual states, and the typical laborer are $25,330 per year. The workers’ compensation in-
requirements vary from state to state. surance cost is calculated as follows:
Workers’ compensation insurance covers reasonable
Workers’ Compensation ⫽ ($6.25/$100)($25,330/yr)
medical costs as well as some of the lost wages for employees
who are injured on the job or who contract an occupational ⫽ $1.583.12/yr 䊏
illness. For employees who are killed on the job, workers’
compensation insurance may pay part of the burial expense GENERAL LIABILITY
and may provide surviving family members a weekly or
monthly benefit.
INSURANCE
The cost of the insurance is to be paid entirely by the em- General liability insurance protects the company against
ployer. The premium is based on the gross payroll, the type of claims because of negligent business activities and failure to
work performed by the employees, the company’s accident use reasonable care. The types of claims include bodily in-
history, and other factors. Employees are grouped into a stan- jury, property damage or loss, and other personal injury
dard set of classifications established by the National Council such as slander or damage to reputation. Like workers’ com-
on Compensation Insurance (NCCI) based on the type of pensation insurance, the cost of the insurance is based on
work they do. The NCCI sets a standard lost cost factor for gross revenues and varies by worker class.
each job classification, which is modified by the individual Throughout the year, companies pay general liability in-
states to take into account local variances in losses and regu- surance premiums based on the estimated payroll. At the
lations. The premium rate is based on the lost cost factor and end of the year or more frequently the insurance carrier will
is expressed in dollars per $100 of payroll. audit the payroll of the company and make adjustments in
The premium rate may be modified by multiplying the the premiums to reflect the actual payroll. This is an adjust-
premium rate by a so-called experience modifier. Experience ment to the total premium and not the premium rates.
modifiers are calculated by NCCI and reflect the relationship
between the company’s actual losses and the expected losses
for similar companies. An experience modifier greater than 1 EXAMPLE 21-8
indicates that a company had higher-than-expected losses, Determine the cost of general liability insurance for the typical la-
whereas an experience modifier of less than 1 indicates that a borer in Example 21-2. The company’s workers’ compensation in-
company had lower-than-expected losses. The experience surance rate for laborers is 0.97% of wages.
modifiers are based on the past three years of losses, not in- Solution: The wages used in calculating the general liability insur-
cluding the most recent policy year. For example, the experi- ance must include the allowances paid to the typical laborer. From
ence modifier for the year 2011 would be based on the years Example 21-2 the annual wages, including allowances, for the typi-
2007, 2008, and 2009. For companies to receive an experi- cal laborer are $25,330 per year. The general liability insurance cost
ence modification they must meet a minimum level of pre- is calculated as follows:
miums, and thus companies with small payrolls are often Liability Insurance ⫽ (0.0097)($25,330/yr) ⫽ $245.70/yr 䊏
not given experience modifiers. Experience modifiers may
be as low as 0.6 and as high as 2.0.
The workers’ compensation insurance premiums may INSURANCE BENEFITS
also be adjusted based on the safety practices of the com-
As part of the employee benefit package, the employer may
pany. Other discounts may be offered for such items as
provide health, dental, life, and disability insurance for
policy size.
which the employee and their families are beneficiaries.
Throughout the year, companies pay workers’ compensa-
The employer may pay the entire cost of the benefits, split
tion insurance premiums based on the estimated payroll. At
the cost with the employee, or require the employee to pay
the end of the year or more frequently the insurance carrier
the entire amount. The amount the employees pay is de-
will audit the payroll of the company and make adjustments
ducted from their wages and does not represent a cost to the
in the premiums to reflect the actual payroll. It is important to
employer. The part of the cost that is paid by the employer is
note that this is an adjustment in the total premium, not the
a real cost to the employer and needs to be included in the
premium rate.
cost of the benefits.

EXAMPLE 21-7 EXAMPLE 21-9


Determine the cost of workers’ compensation insurance for the Determine the cost of health insurance for the typical laborer in
typical laborer in Example 21-2. The company’s workers’ com- Example 21-2. The company pays $100 per month toward health
Labor Rates 245

insurance for its employees. An additional $150 is deducted from ANNUAL COSTS AND
the employee’s paycheck.
BURDEN MARKUP
Solution: The cost of the health insurance includes only those
costs paid by the employer and is calculated as follows: The annual cost of the employee is determined by summing
the individual burden items and adding the wages paid to
Health Insurance ⫽ ($100/mo)(12 mo/yr) ⫽ $1,200.00/yr 䊏 the employee. The burden markup is calculated as follows:
Annual Cost
Burden Markup ⫽ ⫺1 (21-2)
WagesBillable Hours
RETIREMENT where the wages include only those wages paid for billable
CONTRIBUTIONS hours and should include allowances. By doing this the
As part of the employee benefit package, the employer may wages paid on unbillable hours, vacation, and sick leave are
provide traditional pension plans, pay funds to a union to included as part of the burden.
provide pension benefits, or participate in a profit-sharing
plan such as a 401(k). Like insurance benefits, the employer
may pay all, part, or none of the cost of the retirement. The EXAMPLE 21-11
amount the employees pay is deducted from their wages and
does not represent a cost to the employer. The part of the Determine the annual cost, average hourly cost, and burden
markup for the typical laborer in Example 21-1 using Examples 21-2
cost that is paid by the employer is a real cost to the employer
through 21-4 and 21-7 through 21-10. Assume that the same per-
and needs to be included in the cost of the benefits.
son fills the position during the entire year.
Solution: From Examples 21-1 through 21-4, and 21-7 through
21-10 the following costs were calculated:
EXAMPLE 21-10
Determine the cost of retirement for the typical laborer in Example Wages and Allowances ⫽ $25,330/yr
21-2. For retirement, the company has provided the employee with
access to a 401(k) plan and matches the employee’s contributions Social Security Tax ⫽ $1,458.86/yr
to the plan at a rate of $0.50 per $1.00 contributed by the employee Medicare Tax ⫽ $341.18/yr
on the first 6% of the employee’s wages—including allowances— SUTA ⫽ $180.00/yr
for a maximum matching contribution of 3% of the employee’s
FUTA ⫽ $56.00/yr
wages. The typical laborer is expected to contribute at least 6% of
his or her wages to the 401(k) plan. Workers Compensation ⫽ $1,583.12/yr
Liability Insurance ⫽ $245.70/yr
Solution: From Example 21-2 the annual wages, including al-
lowances, for the typical laborer are $25,330. The cost of retirement Health Insurance ⫽ $1,200.00/yr
is calculated as follows: Retirement ⫽ $759.90/yr

Retirement ⫽ a b(0.06)($25,330/yr) ⫽ $759.90/yr


$0.50

$1.00 The annual cost is calculated as follows:
Annual Cost ⫽ $25,330/yr ⫹ $1,458.86/yr ⫹ $341.18/yr
⫹ $180.00/yr ⫹ $56.00/yr ⫹ $1,583.12/yr
UNION PAYMENTS ⫹ $245.70/yr ⫹ $1,200/yr ⫹ $759.90/yr
Employee unions often require the employer to make Annual Cost ⫽ $31,154.76/yr
payments directly to the union for the union to provide ben-
Using the billable hours from Example 21-1, we calculate the aver-
efits to the employees. Payments to unions are governed by age hourly wage rate using Eq. (21-1) as follows:
the contract between the company and the union. Union
costs paid by the employer should be included in the cost of $31,154.76/yr
Average Hourly Wage Rate ⫽ ⫽ $14.42/hr
the benefits. Unions may also require the employer to deduct 2,160 hr/yr
union dues from the employees’ paycheck. The amounts the The burden markup is calculated using Eq. (21-2) as follows:
employees pay do not represent a cost to the employer and
should not be included in the cost of the benefits. $31,154.76/yr
Burden Markup ⫽ ⫺1
($25,330/yr ⫺ $1,260/yr)
⫽ 0.2943 or 29.43% 䊏
OTHER BENEFITS It is important to note that one cannot take the base hourly
The employer may provide other benefits not covered in one rate of $10.50 and add the burden markup to get the hourly
of the foregoing categories. Where possible the costs of these cost because some of the employee’s hours are paid at time-
benefits should be included. and-a-half.
246 CHAPTER TWENTY-ONE

EXCEL QUICK TIP 20-1


Labor Rate Worksheet
The spreadsheet shown in the following figure can be used to calculate the average hourly wage and labor burden for a class
of employees.
A B C D E F
1 Wage Calculation Worksheet
2 Hours per Weeks Base
3 Week per Year Rate Wages
4 Week Type 1 50.00 20.00 10.50 11,550
5 Week Type 2 40.00 29.00 10.50 12,180
6 Week Type 3 -
7 Week Type 4 -
8 Vacation & Sick Leave 40.00 3.00 10.50 1,260
9 Bonus 100
10 Billable Hours 2,160
11 Wages 25,090
12 Allowances 20.00 per mo 12 mo 240
13 Employee Paid Health Ins. 150.00 per mo 12 mo 1,800
14 Social Security/Med. Wages 23,530
15
16 Wages and Allowances 25,330
17 Social Security 6.20% on first 106,800 of wages 1,459
18 Medicare 1.45% on first of wages 341
19 SUTA 2.00% on first 9,000 of wages 180
20 FUTA 0.80% on first 7,000 of wages 56
21 Workers' Compensation 6.25 $/$100 of wages 1,583
22 General Liability 0.97% of wages 246
23 Employer Paid Health Ins. 100.00 per mo 12 mo 1,200
24 Retirement 50.00% match on 6.00% of wages 760
25 Union Payments 0.00% of wages -
26 Annual Cost of Employee 31,155
27 Average Hourly Wage Rate 14.42
28 Labor Burden Markup 29.43%

To complete this spreadsheet, enter the data and format the cells as shown in the figure. The following formulas need to be
entered into the associated cells:

Cell Formula
E4 =IF(B4>40 ,40*D4+(B4-40)*D4*1.5,B4*D4)*C4
F10 =B4*C4+B5*C5+B6*C6+B7*C7
F11 =SUM(E4:E9)
F12 =B12*D12
F13 =B13*D13
F14 =F11+F12-F13
F16 =F11+F12
F17 =IF(D17="",F14*B17,IF(F14<D17,F14*B17,D17*B17))
F18 =IF(D18="",F14*B18,IF(F14<D18,F14*B18,D18*B18))
F19 =IF(D19="",F16*B19,IF(F16<D19,F16*B19,D19*B19))
F20 =IF(D20="",F16*B20,IF(F16<D20,F16*B20,D20*B20))
F21 =(B21/100)*F16
F22 =B22*F16
F23 =B23*D23
F24 =B24*D24*F16
F25 =F16*B25
F26 =SUM(F16:F25)
F27 =F26/F10
F28 =F26/(F16–E8)-1
Labor Rates 247

An IF statement is used in cell E4 to calculate the weekly see if the wages in Cell F14 are less than the wage limit in
wages while including time-and-a-half for hours worked in Cell D17. If this is true, the wages in Cell F14 are multiplied
excess of 40 hours per week. The IF statement checks to see if by the FICA rate in Cell B17; if the wages are greater than
the hours worked is greater than 40 hours per week. If this is the limit, the FICA limit in D17 is multiplied by the FICA
the case, the weekly wages equal the hours over 40 hours per rate in Cell B17. If there is not a limit, then this equation
week multiplied by 1.5 times the wage rate plus 40 hours at applies the FICA rate to all of the wages.
the wage rate. If the hours worked are less than or equal to After entering these formulas, one needs to copy Cell
40 hours, the weekly wages are equal to the hours per week E4 into Cells E5 through E8. The data for the employee
times the wage rate. The weekly wages are then multiplied by class is entered into Cells B4 through D8, E9, B12, B13,
the number of weeks per year to get total wages. D12, D13, B17 through B25, D17 through D20, D23, and
Cells F17 through F20 use a nested IF statement, D24. The data shown in the foregoing figure is from
which works as follows for Row 17. If Cell D17 is blank, the Examples 21-1 through 21-4 and 21-7 through 21-11and is
wages in Cell F14 are multiplied by the FICA rate in Cell formatted using the comma style, which replaces zeros
B17; if the cell is not blank, the next IF statement checks to with dashes.

CONCLUSION 2. During the year, the average equipment operator works


50 hours per week for 35 weeks, 40 hours per week for
When projecting costs that include labor, it is important to 5 weeks, and 20 hours per week for 9 weeks. He or she is
include all of the costs associated with the employee. The paid time-and-a-half for any hours over 40 hours per
cost of an employee includes wages and the associated labor week and receives 15 paid days off per year in the form
burden. The employee’s wages may be determined by market of vacation, sick leave, and holidays. The employee pays
rates, union contracts, or federal Davis-Bacon wage deci- $200 per month for health insurance, which is not sub-
sions. Labor burden includes cash equivalents and al- ject to Social Security and Medicare taxes. Assuming
lowances paid to the employee, payroll taxes, unemployment that the employee takes full advantage of the 401(k)
insurance, workers’ compensation insurance, general liabil- benefit, determine the average hourly cost and burden
ity insurance, insurance benefits, retirement contributions, markup for the average equipment operator given the
union dues, and other benefits. following information:

PROBLEMS Item Cost


1. During the year, the average carpenter works 50 hours Wages $15/hr
per week for 30 weeks, 40 hours per week for 15 weeks, Bonus $1,000
and 30 hours per week for 5 weeks. He or she is paid Allowances $25/month
time-and-a-half for any hours over 40 hours per week Social Security 6.2% of wages to $106,800
and receives 10 paid days off per year in the form of va- Medicare 1.45% of wages
cation, sick leave, and holidays. The employee’s health FUTA 0.8% of wages to $7,000
insurance is paid for entirely by the employer. Assuming
SUTA 2.85% of wages to $12,000
that the employee takes full advantage of the 401(k)
Workers’ Compensation $4.60 per $100 of wages
benefit, determine the average hourly cost and burden
markup for the average carpenter given the following General Liability 1.05% of wages
information: 401(k) 50% match up to 6% of wages
Health Insurance $100/month
Item Cost
3. Set up the worksheet in Excel Quick Tip 21-1 in Excel.
Wages $12/hr
Bonus $500
Allowances None
REFERENCES
Social Security 6.2% of wages to $106,800 1. For more information on how to accrue vacation and sick
Medicare 1.45% of wages leave costs, see Steven J. Peterson, Construction Accounting and
Financial Management, Prentice Hall, Upper Saddle River, NJ,
FUTA 0.8% of wages to $7,000
2009.
SUTA 1.85% of wages to $20,000 2. Internal Revenue Service, Circular E, Employer’s Tax Guide,
Workers’ Compensation $7.85 per $100 of wages Publication 15, 2010, p. 18.
General Liability 0.65% of wages 3. Internal Revenue Service, Circular E, Employer’s Tax Guide,
401(k) 50% match up to 6% of wages Publication 15, 2010, p. 18.
Health Insurance $200/month 4. Internal Revenue Service, Circular E, Employer’s Tax Guide,
Publication 15, 2010, p. 31.
C H A P T E R T W E N T Y- T W O

EQUIPMENT COSTS

In this chapter you will learn how to determine equipment tax, transportation cost, set up of the equipment, and any
costs for owned, leased, and rented equipment. The cost of other costs the equipment dealer charges in conjunction with
equipment includes depreciation and interest, taxes and its purchase. Tires and other wear items, such as cutting
licenses, insurance, storage, tires and other wear items, fuel, edges, are considered operation costs and are often excluded
lubricants and filters, and repair reserves. from the purchase price and treated as a separate item. The
salvage value for a piece of equipment should include all ex-
pected revenues from its sale or disposal. The depreciation

T
discussed here should not be confused with depreciation for
he equipment used on construction projects can be
tax purposes, which is handled in a different manner.
divided into three types of equipment: owned,
By investing in equipment a company in effect takes out
leased, and rented. Let’s begin by looking at deter-
a loan at a specified interest rate or forgoes the opportunity
mining the cost of owned equipment.
to invest its capital in other opportunities that would in-
Equipment costs for owned equipment can be divided
crease the value of its invested funds. In either case, there is
into two categories: ownership costs and operating costs.
an interest cost (either paid or lost) that the company must
Ownership costs are those costs that are most closely related
recoup as part of the cost of the equipment.
to how long a piece of equipment is owned rather than how
The annual cost of depreciation and interest is incorpo-
much a piece of equipment is used. Ownership costs include
rated into the equipment costs by the following equation:
depreciation and interest, taxes and licensing, insurance, and
storage. Operation costs are those costs that are more closely [P(1 ⫹ i)n ⫺ F]i
CostD&I ⫽ (22-1)
related to how long a piece of equipment is operated rather [(1 ⫹ i)n ⫺ 1]
than how long it has been owned. Operation costs include
tires and other wear items, fuel, lubricants and filters, and re- where
pair reserves. During the life of a piece of equipment, the CostD&I ⫽ Annual Depreciation and Interest Costs
ownership costs tend to decrease, whereas the operation P ⫽ Purchase Price
costs increase. For the purpose of estimating, the costs are F ⫽ Salvage Value
often equally spread throughout the expected life of the
i ⫽ Interest Rate Expressed in Decimal Format
piece of equipment.
n ⫽ Life of the Equipment in Years

DEPRECIATION AND
INTEREST EXAMPLE 22-1
The purchase price of a front-end loader, including the tires, sales
One of the costs the company must recoup on equipment is
tax, and all other costs associated with its purchase, is $135,000. The
its loss in value over its useful life. This is known as deprecia- life of the loader is 7 years, at which time it will have an estimated
tion. Depreciation over the useful life of a piece of equipment salvage value of $20,000. The replacement cost of the tires is $5,000
equals the purchase price less the salvage value. When work- for all tires on the loader and is not included in the depreciation
ing with equipment, the purchase price of a piece of equip- and interest cost. Determine the annual depreciation and interest
ment should include the cost of the piece of equipment, sales cost of the loader using an interest rate of 9%.

248
Equipment Costs 249

Solution: The purchase price for the loader must be reduced by equipment in two ways. The first uses actual cost of the
the cost of the tires, for a cost of $130,000 ($135,000 – $5,000). The storage, which is done by allocating the storage costs to all of
annual depreciation and interest cost of the loader is determined by the pieces of equipment owned by the company. The second
Eq. (22-1) as follows: way is to add a percentage to the interest rate used in Eq.
[$130,000(1 ⫹ 0.09)7 ⫺ $20,000](0.09) (22-1) to cover the cost of storage.
CostD&I ⫽ ⫽ $23,656/yr
[(1 ⫹ 0.09)7 ⫺ 1]

HOURLY OWNERSHIP
COST
TAXES AND LICENSING
Thus far the ownership cost of the piece of equipment has
Taxes and licensing includes all taxes and licensing fees as-
been determined on an annual basis. Because most equip-
sessed by government agencies. Companies that own equip-
ment is not used on a project for an entire year, the costs
ment usually have to pay a property tax based on the value of
must be converted to an hourly, weekly, or monthly cost.
the equipment. These property taxes are often calculated by
This is done by estimating the number of billable hours,
multiplying an assessed value for the equipment by a speci-
weeks, or months the equipment will be used during the year
fied tax rate. The property tax due each year is the same for a
and dividing the annual cost by the billable number of
piece of equipment that sits in the equipment yard all year as
hours, weeks, or months. The hourly cost is determined by
for a piece of equipment that is used for most of the year;
the following equation:
therefore, it is considered an ownership cost. Additional li-
censing fees are often required for vehicles that travel over CostAnnually
public roads. CostHourly ⫽ (22-2)
Hours
Taxes and licensing can be incorporated into the cost of
the equipment in two ways. The first uses the actual cost of where
the taxes and licensing, which is obtained from the com- CostHourly ⫽ Hourly Cost
pany’s accountant or estimated from the previous year’s tax CostAnnually ⫽ Annual Cost
and licensing bills. The second way is to add the tax rate to
Hours ⫽ Billable Hours
the interest rate used in Eq. (22-1) to cover the cost of taxes.
The weekly and monthly costs are determined by sub-
stituting billable weeks or billable months for hours into
INSURANCE Eq. (22-2), respectively. Because the ownership costs are the
same regardless of the number of hours the equipment is
Insurance is based on potential loss because of damage to used each year, the hourly, weekly, and monthly costs are
the insured equipment and potential loss because of damage highly sensitive to the number of hours, weeks, and months
to other equipment and to people caused by the equipment. the equipment is used. If the usage of the equipment dou-
The potential loss because of damage to the insured equip- bles, the ownership costs are cut in half.
ment is a function of the value of the equipment. The loss of
a $10,000 dump truck in an accident is less than the loss of a
$60,000 dump truck. The potential loss because of damage
EXAMPLE 22-2
to other equipment and to people caused by the equipment
is independent of the cost of the equipment. A $10,000 For the front-end loader in Example 22-1, the annual taxes and
dump truck can cause the same amount of damage as a licensing are $2,600, the annual insurance is $2,100, and the stor-
$60,000 dump truck. age cost is $1,200. It is estimated that the loader will operate 1,200
Insurance costs can be incorporated into the cost of the hours per year. Determine the hourly ownership cost of the
loader.
equipment in two ways. The first uses the actual cost of the
insurance, which is obtained from the company’s insurance Solution: From Example 22-1, the annual depreciation and inter-
agent or estimated from the previous year’s insurance bills. est cost is $23,656. The annual ownership cost is as follows:
The second way is to add a percentage to the interest rate CostOwnership ⫽ CostD&I ⫹ CostTaxes!&!Licensing ⫹ CostInsurance
used in Eq. (22-1) to cover the cost of insurance.
⫹ CostStorage
⫽ $23,656/yr ⫹ $2,600/yr ⫹ $2,100/yr ⫹ $1,200/yr
STORAGE ⫽ $29,556/yr

Companies often include equipment storage in the cost of The hourly ownership cost of the loader is determined by Eq. (22-2)
as follows:
the equipment. Storage costs include the cost of property
used to store equipment, security for the property, and so ($29,556/yr)
CostOwnership ⫽ ⫽ $24.63/hr 䊏
forth. Storage costs can be incorporated into the cost of the (1,200!hr/yr)
250 CHAPTER TWENTY-TWO

TIRES AND OTHER the following equation:


WEAR ITEMS Repair!Cost
Repair!Multiplier ⫽ (22-5)
Wear items include tires, cutting edges, bucket teeth, and CostTires
other items that frequently wear out. The cost of tires and A common repair multiplier is 15%.
other wear items includes all costs associated with the pur-
chase or replacement of the item. Because the costs of tires
EXAMPLE 22-3
and other wear items are operating costs and their consump-
tion is more closely based on the hours of operation than the For the front-end loader in Example 22-1, the estimated life of the
duration of ownership, their life is often expressed in operat- tires is 3,000 hours and the repair multiplier is 15%. Determine the
ing hours. hourly cost of the tires, including tire repair.
If the life of the tires and wear items is one year or less, Solution: From Example 22-1, the cost of the tires is $5,000. The
the hourly cost is determined by dividing the cost of the tires life of the tires in years is calculated as follows:
or wear items by their life. The hourly cost is calculated by (3,000!hr)
the following equation: n⫽ ⫽ 2.5!yr
(1,200!hr/yr)
Cost The annual cost of the tires is calculated using Eq. (22-1) as follows:
CostTires/Wear ⫽ (22-3)
Life [$5,000(1 ⫹ 0.09)2.5 ⫺ $0](0.09)
CostAnnual ⫽ ⫽ $2,322/yr
where [(1 ⫹ 0.09)2.5 ⫺ 1]

CostTires/Wear ⫽ Hourly Cost of Tires or Wear Items The hourly cost of the tires is calculated using Eq. (22-2) as follows:
Cost ⫽ Cost of the Tires or Wear Items CostHourly ⫽
($2,322/yr)
⫽ $1.94/hr
Life ⫽ Useful Life of the Tires or Wear Items (1,200!hr/yr)
in Hours The hourly repair cost is calculated using Eq. (22-4) as follows:

When the useful life of the tires or wear items is greater (0.15)($5,000)
CostTire!Repair ⫽ ⫽ $0.25/hr
than one year, the costs associated with these items are then (3,000!hr)
spread out over the life of the items, just as the price of a The total hourly cost of tires and tire repair is $2.19 per hour
piece of equipment is spread over the life of the piece of ($1.94/hr ⫹ $0.25/hr). 䊏
equipment. The annual costs of the tires or wear items are
calculated using Eq. (22-1) and substituting the life of the
tires or wear items for the life of the equipment. The hourly
FUEL
cost is then determined by using Eq. (22-2). Because the tires Fuel consumption is a function of the number of hours of
and other wear items have a different useful life than the operation. Like tires and other wear items, the consumption
equipment, they cannot simply be included in the deprecia- of fuel varies based on the conditions under which the
tion and interest costs. equipment operates. For example, an excavator digging in
Although the life of the tires and other wear items is hard-to-dig shale will consume more fuel per hour than will
based on operating hours, their life varies based on the the same piece of equipment digging in easy-to-dig sand.
conditions under which the equipment operates. For ex- When determining fuel consumption, the operation condi-
ample, a bucket tooth digging in hard, blasted rock will tions must be taken into account. The equipment manufac-
wear out faster than the same bucket tooth digging in turer is a good source of information on the rate of fuel con-
clay. When determining the life of tires and other wear sumption. The cost of fuel is calculated by multiplying the
items, the operation conditions must be taken into ac- fuel consumption by the estimated fuel cost per gallon.
count. The equipment manufacturer is a good source of
information on costs and life of tires and other wear
items. EXAMPLE 22-4
Tire repair is included in the cost of the tires by using For the front-end loader in Example 22-1, it is estimated that under
the following equation: normal conditions it will consume 3 gallons of diesel per hour.
Using a cost of $1.95 per gallon of diesel, determine the fuel cost for
(Repair!Multiplier)(CostTires) the front-end loader.
CostTire!Repair ⫽ (22-4)
Life Solution: The cost of the fuel is calculated as follows:
where CostFuel ⫽ (3!gal/hr)($1.95/gal) ⫽ $5.85/hr 䊏
CostTire Repair ⫽ Hourly Cost of Tire Repair
CostTires ⫽ Cost of the Tires LUBRICANTS AND FILTERS
Life ⫽ Useful Life of the Tires in Hours
Lubricants and filters include oils for use in the engine,
The repair multiplier is the historical repair cost of the transmission, and final drives; hydraulic fluids; grease; air fil-
tire as a percentage of the cost of the tires and is calculated by ters; oil filters; hydraulic filters; transmission filters; and fuel
Equipment Costs 251

filters. Lubricant consumption includes the replacement of the early life of the piece of the equipment, which is placed in
the lubricants at regular intervals and the loss of lubricants reserve to cover the higher cost of maintenance during the
because of leaks. The cost of lubricants and filters is a func- latter part of a piece of equipment’s life. These excess funds
tion of the number of hours of operation. Like other oper- are known as a repair reserve. Equipment manufacturers
ating costs, the cost of lubricants and filters varies based on often provide information on the repair reserve required for
the conditions under which the equipment operates. For a piece of equipment.
example, a truck working in a dusty, off-road environment
will require more frequent changing of the air filter than
would a truck operating on a paved highway. The opera- EXAMPLE 22-6
tion conditions must be taken into account when deter- For the front-end loader in Example 22-1, the repair reserve is
mining the cost of lubricants and filters. Equipment manu- $6.50 per hour. Determine the hourly operation cost and hourly
facturers often provide information on the rate of ownership and operation cost of the loader.
consumption of lubricants and filters, which, combined Solution: Using data from Examples 22-3 through 22-5, we calcu-
with local pricing, can be used to estimate the cost of lubri- late the hourly operation cost as follows:
cants and filters.
CostOperation ⫽ CostTire ⫹ CostFuel ⫹ CostL&F ⫹ CostRepair!Reserve
⫽ $2.19/hr ⫹ $5.85/hr ⫹ $0.90/hr ⫹ $6.50/hr
EXAMPLE 22-5 ⫽ $15.44/hr
For the front-end loader in Example 22-1, it is estimated that under Using the hourly cost of ownership from Example 22-2, we calcu-
normal conditions its hourly lubricant consumptions are as fol- late the hourly ownership and operation cost as follows:
lows: crankcase, 0.010!gal/hr; transmission, 0.006!gal/hr; final dri-
ves including differential, 0.006!gal/hr; and hydraulic controls, Cost ⫽ CostOwnership ⫹ CostOperation ⫽ $24.63/hr ⫹ $15.44/hr
0.007!gal/hr. A tube of grease is used during each 8-hour day to lu- ⫽ $40.07/hr 䊏
bricate the grease fittings. The local costs of lubricants are as fol-
lows: oil for the crankcase, $7.43/gal; transmission fluid, $5.83/gal;
oil for the final drives, $9.34/gal; hydraulic fluid, $3.61/gal; and LEASED EQUIPMENT
grease, $4.24/tube. The filters for the loader cost $0.18 per hour of
operation including the labor to install them. Determine the cost of With leased equipment the depreciation and interest costs
lubricants and filters for the loader. are replaced with the lease payment. With a typical lease, the
Solution: The cost of lubricants and filters is calculated as follows: company leasing the equipment is still responsible for pay-
ing the cost of the taxes and licenses, insurance, storage, tires
CostL&F ⫽ (0.010!gal/hr)($7.43/gal) ⫹ (0.006!gal/hr)($5.83/gal) and wear items, fuel, lubricants and filters, and repairs.
⫹ (0.006!gal/hr)($9.34/gal) ⫹ (0.007!gal/hr)($3.61/gal) These costs are calculated in the same manner as they are
⫹ (1!tube/8!hr)($4.24/tube) ⫹ $0.18/hr calculated for owned equipment.
⫽ $0.90/hr 䊏

RENTED EQUIPMENT
REPAIR RESERVE With most rented equipment the depreciation and interest,
Repairs include all operation costs not included in one of the taxes and licenses, insurance, storage, tires and wear items,
foregoing items and including preventative maintenance lubricants and filters, and repairs are covered by the com-
(not included in lubricants and filters), repairs from damage pany that rents the equipment. This leaves the contractor to
and wear (not included in tires and other wear items), and pay the rental cost and the cost of fuel. However, rental
overhauls. As a piece of equipment gets older, the need for agreements may vary, and the estimator should verify which
repairs and the associated costs increase, resulting in the costs are covered by the rental cost. The cost of the equip-
need to increase the operational cost over the life of the piece ment equals the rental cost plus any costs not covered by the
of equipment. Rather than increasing the cost over time, the rental agreement. The costs not covered by the rental agree-
average hourly cost over the life of the equipment is used. ment are calculated in the same manner as they are calcu-
Using the average hourly cost produces excess funds during lated for owned equipment.

EXCEL QUICK TIP 22-1


Equipment Cost Worksheet
A spreadsheet can be set up to calculate the ownership and ternatively, the user may replace the tires with another wear
operation cost for equipment. The spreadsheet shown in item. This spreadsheet assumes that the tires have a life of
the following figure allows the user to account for tires; al- greater than one year.
252 CHAPTER TWENTY-TWO

A B C D E
1 Ownership Cost Operation Cost
2 Purchase Price ($) 135,000 Tires ($) 5,000
3 Salvage Value ($) 20,000 Tire Life (hr) 3,000
4 Equipment Life (yr) 7 Repair Multiplier 15.00%
5 Billable Hours (hr/yr) 1,200 Fuel Consumption (gal/hr) 3.00
6 Interest Rate 9.00% Fuel Cost ($/gal) 1.95
7 Taxes & Licensing ($/yr) 2,600 Crankcase (gal/hr) 0.010
8 Insurance ($/yr) 2,100 Transmission (gal/hr) 0.006
9 Storage ($/yr) 1,200 Final Drives (gal/hr) 0.006
10 Ownership Cost ($/hr) 24.63 Hydraulic Controls (gal/hr) 0.007
11 Grease (tubes/hr) 0.125
12 Total ($/hr) 40.07 Filters ($/hr) 0.18
13 Crankcase Oil ($/gal) 7.43
14 Transmission Fluid ($/gal) 5.83
15 Final Drive Oil ($/gal) 9.34
16 Hydraulic Fluid ($/gal) 3.61
17 Grease ($/tube) 4.24
18 Repair Reserve ($/hr) 6.50
19
20 Tires ($/hr) 2.18
21 Fuel ($/hr) 5.85
22 Lubricants and Filters ($/hr) 0.90
23 Operation Cost ($/hr) 15.44

To complete this spreadsheet, enter the data and format the cells as shown in the figure. The following formulas need to be
entered into the associated cells:

Cell Formula
B10 =(((B2-E2)*(1+B6)^B4–B3)*B6/((1+B6)^B4-1)+B7+B8+B9)/B5
B12 =B10+E23
E20 =E2*(1+B6)^(E3/B5)*B6/((1+B6)^(E3/B5)-1)/B5+E4*E2/E3
E21 =E5*E6
E22 =E7*E13+E8*E14+E9*E15+E10*E16+E11*E17+E12
E23 =E18+E20+E21+E22

The data for the equipment is entered into Cells B2 and is formatted using the comma style, which replaces
through B9 and Cells E2 through E18. The data shown in zeros with dashes.
the foregoing figure is from Examples 22-1 through 22-6

CONCLUSION the loader. The life of the tires is estimated to be 3,600


hours. Tire repairs are expected to be 15% of the cost of
Equipment costs include the ownership costs of deprecia- the tires. The interest rate is 7.5%. The company adds to
tion and interest, taxes and licenses, insurance, and storage; the interest rate 1.5% for property taxes, 2.0% for insur-
and the operation costs of tires and other wear items, fuel, ance, and 1.0% for storage. The fuel consumption is es-
lubricants and filters, and repair reserves. Data to calculate timated to be 10.75!gal/hr, at an estimated cost of
these costs are available from historical data and the equip- $2.10/gal. It is estimated that under normal conditions
ment manufacturer. its hourly lubricant consumptions are as follows:
crankcase, 0.064!gal/hr; transmission, 0.018!gal/hr; final
PROBLEMS drives including differential, 0.039!gal/hr; and hydraulic
controls, 0.035!gal/hr. Two tubes of grease are used dur-
1. The purchase price of a loader including the tires, sales ing each 8-hour day to lubricate the grease fittings. The
tax, and all other costs associated with its purchase is local costs of lubricants are as follows: oil for the
$210,000. The life of the loader is 9 years, at which time crankcase, $6.99/gal; transmission fluid, $5.49/gal; oil
it will have an estimated salvage value of $23,000. The for the final drives, $8.79/gal; hydraulic fluid, $3.41/gal;
replacement cost of the tires is $11,000 for all tires on and grease, $3.89/tube. The filters for the loader cost
Equipment Costs 253

$0.44/hr of operation, including the labor to install its hourly lubricant consumptions are as follows:
them. The estimated repair reserve is $14.40/hr. Using crankcase, 0.008!gal/hr; final drives, 0.001!gal/hr; and
1,500 billable hours per year, determine the hourly own- hydraulic controls, 0.021!gal/hr. One tube of grease is
ership and operation cost of the loader. used during each 8-hour day to lubricate the grease fit-
2. The purchase price of the hydraulic excavator, including tings. The local costs of lubricants are as follows: oil for
sales tax and all other costs associated with its purchase, the crankcase, $7.43/gal; oil for the final drives,
is $150,000. The life of the excavator is 6 years, at which $8.99/gal; hydraulic fluid, $3.56/gal; and grease,
time it will have an estimated salvage value of $20,000. $4.01/tube. The filters for the excavator cost $0.25/hr of
The interest rate is 8.25%. The taxes and licensing costs operation, including the labor to install them. The esti-
are $3,220/yr, the insurance costs are $2,930/yr, and the mated repair reserve is $4.20/hr. Using 1,400 billable
storage costs are $2,110/yr. The fuel consumption is hours per year, determine the hourly ownership and op-
estimated to be 3.0!gal/hr, at an estimated cost of eration cost of the excavator.
$1.85/gal. It is estimated that under normal conditions, 3. Set up Excel Quick Tip 22-1 in Excel.
C H A P T E R T W E N T Y- T H R E E

CREW RATES

In this chapter you will learn how to calculate crew labor and Alternatively, the equipment cost may be determined
equipment rates, the average cost of labor per labor hour, and from daily rates by multiplying the number of pieces of the
the equipment cost per labor hour. same type of equipment by the equipment cost, as shown in
the following equation:
CostEquipment ⫽ (No.!of!Pieces)(Equipment!Cost)

M ost work on a construction project requires the


use of more than one class of employee and may
involve multiple pieces of equipment. For exam-
ple, the framing of a building often requires a lead carpenter
or foreperson, journeyman carpenters, apprentice carpen-
Determining the equipment cost is discussed in
(23-3)

Chapter 22. Determining the average cost of labor per labor


hour and equipment cost per labor hour is shown in the fol-
lowing example.
ters, and laborers, as well as compressors, nail guns, and a
forklift. An estimator needs to be able to calculate the aver-
age cost of labor per labor hour for a specific crew and the
EXAMPLE 23-1
equipment cost per labor hour. This is because the produc-
tivity is based on the number of labor hours needed to per- A pipe-laying crew consists of two hydraulic excavators, a front-end
form a unit of work. loader, a trench box, a gravel box, a foreperson, a pipe layer, two
The average labor cost is calculated by summing the cost equipment operators, and a laborer. The cost of a hydraulic excavator
of labor for the entire crew for one day and then dividing it is $90.00 per hour, a front-end loader is $75.00 per hour, a trench box
is $25.00 per day, and a gravel box is $18.00 per day. The foreman
by the number of labor hours performed by the crew during
costs $25.00 per hour, an operator costs $18.00 per hour, the pipe
one day. The labor cost is determined by multiplying the layer costs $16.50 per hour, and the laborer costs $12.00 an hour.
number of workers in the class by the labor rate for the class Labor costs include labor burdens. All employees work an 8-hour day
by the number of hours worked per day, as shown in the fol- except the foreperson, who works a 9-hour day. Determine the aver-
lowing equation: age cost of labor per labor hour and the equipment cost per labor
CostLabor ⫽ (Workers)(Labor!Rate)(Hours!Worked!per!Day) hour for the pipe-laying crew.
(23-1) Solution: The daily labor costs for each class of worker are calcu-
lated using Eq. (23-1) as follows:
Determining the labor rate is discussed in Chapter 21.
The equipment cost per labor hour is determined by CostForeperson ⫽ (1)($25.00/hr)(9!hr/day) ⫽ $225.00/day
summing the cost of all of the equipment for one day and CostPipe!Layer ⫽ (1)($16.50/hr)(8!hr/day) ⫽ $132.00/day
then dividing it by the number of labor hours performed by CostOperators ⫽ (2)($18.00/hr)(8!hr/day) ⫽ $288.00/day
the crew during one day. The equipment cost is calculated
CostLaborer ⫽ (1)($12.00/hr)(8!hr/day) ⫽ $96.00/day
from hourly rates by multiplying the number of pieces of the
same type of equipment by the equipment cost by the number The daily labor cost for the entire crew is calculated as follows:
of hours worked per day, as shown in the following equation: CostLabor ⫽ $225.00/day ⫹ $132.00/day ⫹ $288.00/day
CostEquipment ⫽ (No.!of!Pieces)(Equipment!Cost) ⫹ $96.00/day
⫻ (Hours!Worked!per!Day) (23-2) ⫽ $741.00/day

254
Crew Rates 255

The number of labor hours (lhr) worked in one day is calculated as The daily equipment cost for the entire crew is calculated as follows:
follows:
CostEquipment ⫽ $1,440.00/day ⫹ $600.00/day
Hours ⫽ (1)(9!hr/day) ⫹ (1)(8!hr/day) ⫹ (2)(8!hr/day) ⫹ $25.00/day ⫹ $18.00/day
⫹ (1)(8!hr/day) ⫽ $2,083.00/day
⫽ 41!lhr/day The equipment cost per labor hour (lhr) is calculated as follows:
The average cost per labor hour is calculated as follows: ($2,083.00/day)
CostEquipment ⫽ ⫽ $50.80/lhr 䊏
(41!lhr/day)
($741.00/day)
CostLabor Hour ⫽ ⫽ $18.07/lhr
(41!lhr/day) The crew makeup can be determined by a number of
factors. Sometimes, limits on the crew makeup are set by con-
The daily equipment costs for each type of equipment are calcu- tract or government regulations. For example, state law may
lated using Eq. (23-2) and (23-3) as follows:
require there be at least one journeyman plumber for every
CostExcavators ⫽ (2)($90.00/hr)(8!hr/day) ⫽ $1,440.00/day two apprentice plumbers on a job. Crew makeup is also de-
CostLoader ⫽ (1)($75.00/hr)(8!hr/day) ⫽ $600.00/day termined by the size of the job. A small framing job may only
require a journeyman carpenter and a laborer, whereas a
CostTrench!Box ⫽ (1)($25.00/day) ⫽ $25.00/day
large job may require a lead carpenter, three journeyman car-
CostGravel!Box ⫽ (1)($18.00/day) ⫽ $18.00/day penters, four apprentice carpenters, and three laborers.

EXCEL QUICK TIP 23-1


Crew Rates Worksheet
The following spreadsheet can be used to calculate the average cost of labor per labor hour and the equipment cost per
labor hour for a crew.

A B C D E F
1 Labor
2 Daily
3 Class Number Rate Hr/Day Wages
4 Foreperson 1 25.00 9.00 225.00
5 Pipe Layer 1 16.50 8.00 132.00
6 Operators 2 18.00 8.00 288.00
7 Labor 1 12.00 8.00 96.00
8 -
9 -
10 41.00 741.00
11
12 Cost Per Labor Hour 18.07
13
14 Equipment
15 Hourly Daily
16 Class Number Rate Hr/Day Daily Rate Wages
17 Excavator 2 90.00 8.00 1,440
18 Loader 1 75.00 8.00 600
19 Trench Box 1 25.00 25
20 Gravel Box 1 18.00 18
21 -
22 -
23 2,083
24
25 Cost Per Labor Hour 50.80

To complete this spreadsheet, enter the data and format the cells as shown in the figure. The following formulas need to be
entered into the associated cells:
256 CHAPTER TWENTY-THREE

After entering these formulas, copy Cell E4 to Cells E5


Cell Formula
through E9 and copy Cell F17 to Cells F18 through F22.
E4 =B4*C4*D4 The data for the labor and equipment is entered into
Cells A4 through E9 and Cells A17 through F22. Costs for
D10 =B4*D4+B5*D5+B6*D6+B7*D7+B8*D8+B9*D9
equipment should only be entered in Column D (the
E10 =SUM(E4:E9)
hourly rate) or Column E (the daily rate) but not both. The
E12 =E10/D10 data shown in the foregoing figure is from Example 23-1
F17 =B17*C17*D17+B17*E17 and is formatted using the comma style, which replaces
zeros with dashes.
F23 =SUM(F17:F22)
F25 =F23/D10

CONCLUSION labor burdens. All employees work an 8-hour day.


Determine the average cost per labor hour and the
The average labor rate per labor hour for a crew is deter- equipment cost per labor hour for the excavation crew.
mined by calculating the daily cost of the crew and dividing 2. A carpentry crew consists of a lead carpenter, three
it by the labor hours performed by the crew. The equipment journeyman carpenters, four apprentice carpenters, and
cost per labor hour is determined by calculating the daily three laborers. The lead carpenter costs $24.00/hr, a
cost of the equipment and dividing it by the number of labor journeyman carpenter costs $19.59/hr, an apprentice
hours worked by the crew. carpenter costs $15.75/hr, and a laborer costs $11.52/hr.
Labor costs include labor burdens. All employees work an
8-hour day, except the foreperson, who works a 9-hour
PROBLEMS day. The equipment to support the carpenters includes
1. An excavation crew consists of a hydraulic excavator, six nail guns, three saws, two compressors, and a forklift.
three dump trucks, a foreperson, and three truck dri- A nail gun costs $5/day, a saw costs $4/day, a compressor
vers. The foreperson operates the hydraulic excavator. costs $10/day, and a forklift costs $35.00/hr. Determine
The cost of a hydraulic excavator is $90.00/hr and a the average cost per labor hour and the equipment cost
truck costs $55.00/hr. The foreperson costs $25.00/hr per labor hour for the carpentry crew.
and a truck driver costs $15.00/hr. Labor costs include 3. Set up Excel Quick Tip 23-1 in Excel.
C H A P T E R T W E N T Y- F O U R

SUBCONTRACT PRICING

In this chapter you will learn how to obtain subcontract pric- has agreed to bid. This is done to prevent miscommunica-
ing, including how to prepare a request for a quote and a scope tions as to the project, its bid time, and the scope of the work
of work, as well as how to select the best bid. needed to be performed to complete the work package. The
RFQ should contain the name of the subcontractor from
whom the quote is being requested, the name of the contrac-

S
tor requesting the quote, the project for which the quote is
ubcontractors provide labor and often materials
being requested, the bid date and time for the project, and
and equipment to the project for a fixed price or for
the scope of the work included in the work package. A sam-
a unit price. The best source of subcontractor pricing
ple RFQ is shown in Figure 24-1.
is the subcontractor. When pricing from the subcontractor is
not available, the subcontractor pricing can be estimated
from historical data.
When obtaining pricing from the subcontractor, it is
important for the subcontractor and the contractor to
clearly communicate the work that is to be performed, the
price for the work, and any other conditions associated with
the work. This is best done by communicating these parame-
ters in writing in the form of a Request for Quote (RFQ) and
having the subcontractor respond with a written proposal.
The Request for Quote, sometimes referred to as a Request
for Proposal (RFP), is sent to the subcontractor. The prepa-
ration and submission of quotes is discussed in Chapter 28.

REQUEST FOR QUOTE


Prior to preparing the RFQ, the estimator needs to break the
project down into work packages. Each work package should
consist of work that would be done by a specific class of sub-
contractor or in-house crew. For example, a project may
contain an electrical work package that consists of the elec-
trical work needed to complete the project. Once the work
packages have been identified, the estimator needs to iden-
tify which subcontractors he or she wants to bid on each of
the work packages to be subcontracted out. Next, the estima-
tor needs to contact each of the subcontractors and obtain a
commitment that the subcontractor will provide a bid for
the project. Finally, the estimator should send each subcon-
tractor the RFQ for the work package that the subcontractor FIGURE 24-1 Request for Quote
257
258 CHAPTER TWENTY-FOUR

WRITING A SCOPE OF WORK fired furnace provided by the HVAC subcontractor, which
subcontractor is responsible for providing the gas lines? If the
For the RFQ to be useful it must clearly define the scope or HVAC subcontractor provides the gas lines, is the HVAC sub-
limits of work to be performed; it will become the basis of contractor responsible for connecting the gas lines to the hot-
the contract. Writing contracts is discussed in Chapter 29. water heater, or does the HVAC subcontractor just provide a
The scope of work should clearly delineate what work is in- valve next to the hot-water heater, with the plumbing sub-
cluded in the work package and what is excluded. The scope contractor responsible for connecting the hot-water heater to
of work should include any clarifications, exclusions, and the gas lines? The reverse is true for the furnace when the
other assumptions necessary to clearly define the scope of plumbing subcontractor is providing the gas lines.
the work package. The scope of work can be prepared by referencing all or
The different scopes of work should cover all materials, part of a set of contract documents, for example, the plans
labor, and equipment needed to complete the project. There and project manual. When referencing a set of contract doc-
should be no gaps among different scopes of work, other- uments, the reference should include the title of the project,
wise the contractor might leave some costs out of the pricing the architect or engineer who prepared the documents, and
and be open to a change order. Care must also be taken to the document dates. It is very important to include the date
ensure that there are no overlaps between multiple scopes of for the drawings because the drawings may be revised dur-
work. This would not only create confusion by duplicating ing the bidding process and it is important to know on
work in two different scopes of work, but might lead the which drawings the scope of work is based. This may require
contractor to pay for the work twice if the duplication goes that a table of drawings, with their dates, be included in the
unnoticed. If an overlap between scopes of work is identi- scope of work. A scope of work based on the contract docu-
fied, the contractor must issue a change order or have ment may be written as shown in Figure 24-1
changes made to the quotes to rectify the mistake. Alternatively, the scope of work can be prepared by
Well-prepared scopes of work are particularly important specifically spelling out what is included and what is ex-
when the lines delineating the work performed by two sub- cluded, as shown in Figure 24-2. In this scope of work the
contractors are not clearly defined. This often occurs when framing subcontractor provides the labor, equipment, and
there are two subcontractors working on a piece of equip- some of the materials to construct a home and the general
ment. For example, when installing a gas-fired hot-water contractor provides the rest of the materials.
heater provided by the plumbing subcontractor and a gas-

FIGURE 24-2 Sample Scope of Work


Subcontract Pricing 259

Sample scopes of work are given in Appendix D and sible to do this because the pricing data is often a single
may be used as the basis of writing your own scopes of work. price for an entire work package. Because of this, the esti-
mator must make sure that the historical data used in esti-
mating subcontractor work is for a project that is very simi-
HISTORICAL lar to the project he or she is bidding; otherwise, there could
In the absence of subcontractor pricing for the project, the es- be a big discrepancy between the actual cost of the work and
timated subcontractor cost can be calculated from historical the cost used in the estimate. The comparison should be
data. Historical costs are determined by obtaining past costs based on the size of the project, complexity of the work, and
from the accounting system or contracts for a certain quantity materials used.
of work and dividing it by the quantity of work performed.
This calculation is expressed by the following equation:
BID SELECTION
Cost
Cost!per!Unit ⫽ (24-1) When receiving bids from multiple subcontractors, the esti-
Quantity
mator must select the subcontractor with the best quote.
Selection should be based on completeness of the scope of
EXAMPLE 24-1 work, price, schedule, quality, and performance of the sub-
A recent project included 1,235 square feet of wood-framed build- contractor.
ing. The framing was subcontracted out for $5,700. Determine the The most important thing to do when one receives a
framing cost per square foot of building. quote from a subcontractor is to verify that the subcontrac-
tor has bid a complete work package without any extras. If
Solution: The framing cost per square foot is calculated using
the subcontractor has not bid a complete work package, the
Eq. (24-1) as follows:
estimator needs to fill in the missing items or have the sub-
($5,700) contractor provide costs for the missing items. If the subcon-
Cost!per!Unit ⫽ ⫽ $4.62/ft2 䊏
(1,235!ft2) tractor has extra items in the bid, the estimator needs to have
the subcontractor deduct them.
The historical cost is then multiplied by the quantity of Historically, contractor and subcontractor selection has
work that needs to be performed on the project to obtain an been based on price alone. Many owners and contractors are
estimate of the cost of the subcontract work. This calcula- beginning to select their contractors and subcontractors
tion is expressed by the following equation: based on which subcontractor provides the best bid based
on price, the ability of the subcontractor to meet the sched-
Cost ⫽ (Quantity)(Cost!per!Unit) (24-2)
ule and quality standards, and the past performance of the
subcontractor. It may well be worth the extra cost to pay
EXAMPLE 24-2 more for a subcontractor who can shorten the schedule and
meet the quality standards the first time. Failure to meet the
Using the data from Example 24-1, estimate the cost to subcontract
out the framing for a 2,200-square foot building. The framing of
quality standards increases the duration of a project because
the building in Example 24-1 is similar to this building. it takes time to rework the materials. It also increases costs
because the employees who are to perform these tasks have
Solution: The estimated framing cost is calculated using Eq. (24-2) to wait for the quality defect to be repaired before proceed-
as follows: ing. Scheduling delays, either because of poor schedule per-
Costs ⫽ ($4.62/ft2)(2,200!ft2) ⫽ $10,164 䊏 formance or poor quality, increase the duration of the pro-
ject, which increases the project’s overhead cost. The best
With materials, one is able to determine accurate quan- way to judge the quality and schedule performance of sub-
tities for each component. With subcontracting, it is impos- contractors is based on their past performance.

CONCLUSION work is included in the work package and what is excluded.


The scope of work should be clearly defined including any
Subcontractor pricing is best obtained from the subcontrac- clarifications, exclusions, and other assumptions. When
tors who are interested in performing the work on the pro- pricing from the subcontractor is not available, the esti-
ject. When getting bids from subcontractors it is important mated subcontractor cost can be calculated from historical
that the estimator clearly communicate the work package data. Historical costs are determined by obtaining past costs
that he or she wants the subcontractor to bid, the project to from the accounting system or contracts for a certain quan-
be bid, and the bid date and time. This is best done by send- tity of work and dividing it by the quantity of work per-
ing a Request for Quote (RFQ) to the subcontractor. The formed. When selecting among subcontractors, selection
RFQ should contain a complete scope of work for the work should be based on completeness of the scope of work, price,
package. The scope of work should clearly delineate what schedule, quality, and performance.
260 CHAPTER TWENTY-FOUR

PROBLEMS 18,000-square foot warehouse. The warehouse design is


similar to that of the warehouse in Problem 1.
1. A recent project included a 21,000-square foot ware- 4. Using the data from Problem 2, estimate the cost to sub-
house with tilt-up concrete panel exterior. The con- contract out the roofing for a 2,800-square foot office
struction of the tilt-up panels was subcontracted for building. The roofing and roof design are similar to
$74,000. Determine the cost of the tilt-up panels per those of the office building in Problem 2.
square foot of warehouse. 5. Prepare scope of works for the drawings of the residen-
2. In a recent project, a 2,200-square foot, single-story of- tial garage given in Appendix F.
fice building was constructed with a 30-year architec- 6. Prepare scope of works for the drawings of the Johnson
tural shingle. The roofing was subcontracted for $3,900. Residence given in Appendix F.
Determine the cost of the roofing per square foot of of-
7. Prepare scope of works for the drawings of the West
fice building.
Street Video given in Appendix F.
3. Using the data from Problem 1, estimate the cost to
subcontract out the tilt-up concrete panels for an
C H A P T E R T W E N T Y- F I V E

MARKUPS

In this chapter you will learn how to determine markups for the permits nor do many state and municipal projects. Building
building permit, payment and performance bonds, and profit permits are used to cover the costs of inspections to verify
and overhead. that the project is being built in accordance with the applica-
ble building codes. The cost of the building permit is based
on the valuation of the project, which may be based on the

M
actual bid for the project or a standardized cost per square
arkups are costs that are added to the cost of the
foot established by the code enforcement agency. Sample
bid. The most common markups include a build-
building permit costs are shown in Table 25-1. The estimator
ing permit, payment and performance bonds,
should check with the contracting officer or code enforce-
and profit and overhead. Let’s begin by looking at the build-
ment agency to determine (1) if a building permit is re-
ing permit costs.
quired, (2) how the valuation of the building is established,
and (3) the building permit cost schedule used by the code
BUILDING PERMITS enforcement agency.
Building permits are required on many construction pro- The building permit costs are calculated by selecting the
jects. Highway and federal projects do not require building appropriate range for the valuation of the project in the left

TABLE 25-1 Sample Building Permit Costs


Total Valuation ($) Rate
1.00 to 500.00 $23.50
501.00 to 2,000.00 $23.50 for first $500.00 plus $3.05 for each additional $100.00 or fraction thereof, to and
including $2,000.00
2,001.00 to 25,000.00 $69.25 for first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof, to and
including $25,000.00
25,001.00 to 50,000.00 $391.25 for first $25,000.00 plus $10.10 for each additional $1,000.00 or fraction thereof, to
and including $50,000.00
50,001.00 to 100,000.00 $643.75 for first $50,000.00 plus $7.00 for each additional $1,000.00 or fraction thereof, to and
including $100,000.00
100,001.00 to 500,000.00 $993.75 for first $100,000.00 plus $5.60 for each additional $1,000.00 or fraction thereof, to
and including $500,000.00
500,001.00 to 1,000,000.00 $3,233.75 for first $500,000.00 plus $4.75 for each additional $1,000.00 or fraction thereof, to
and including $1,000,000.00
1,000,000.00 and up $5,608.75 for first $1,000,000.00 plus $3.15 for each additional $1,000.00 or fraction thereof

1997 Uniform Building Code. Copyright 2003. Falls Church, Virginia: International Code Council, Inc. Reproduced with permission.
All Rights Reserved.
261
262 CHAPTER TWENTY-FIVE

column and determining the cost in accordance with the In this example, it was assumed that the building permit
right column. These calculations are shown in the following valuation was known and did not change when the cost of
example. the building permit was added to the bid. This is the case
when the valuation is based on a standardized cost per
square foot established by the code enforcement agency
EXAMPLE 25-1 rather than the bid. When the cost of the building permit is
Using the building permit costs in Table 25-1, determine the build- based on the bid, the cost of the building permit will increase
ing permit cost for a project valued at $250,061. the cost of the bid, which will in turn change the cost of the
Solution: The valuation falls between $100,001 and $500,000; building permit, which will increase the cost of the bid, and
therefore, the cost of the building permit is $993.75 for the first so on until the changes are insignificant. When this is the
$100,000 plus $5.60 for each additional $1,000 or fraction thereof. case, either a rough estimate for the cost of the building per-
The valuation exceeds $100,000 by $150,061, or 151 additional mit must be included in the bid prior to the calculation of
$1,000s. The building permit cost is calculated as follows: the cost of the building permit or the cost of the building
Building!Permit!Cost ⫽ $993.75 ⫹ (151)($5.60) ⫽ $1,839.35 䊏
permit must be calculated by iteration. Chapter 32 will look
at using iteration in a spreadsheet.

EXCEL QUICK TIP 25-1


Building Permit Cost Worksheet
The following spreadsheet can be used to calculate the cost of the building permit:
A B C D E F
Per
Additional
1 From To Base Rate $1,000
2 2,001 25,000 69.25 for first 2,000 14.00
3 25,001 50,000 391.25 for first 25,000 10.10
4 50,001 100,000 643.75 for first 50,000 7.00
5 100,001 500,000 993.75 for first 100,000 5.60
6 500,001 1,000,000 3,233.75 for first 500,000 4.75
7 1,000,001 5,608.75 for first 1,000,000 3.15
8
9 Input Valuation 250,061
10 Valuation Rounded 251,000
11 Buiding Permit Cost 1,839.35

To complete this spreadsheet, enter the data and format the cells as shown in the above figure. The following formulas need
to be entered into the associated cells:

Cell Formula
B2 =A3-1
E2 =A2-1
E10 =ROUNDUP(E9,-3)
E11 =IF(E10<A2,C2,
IF(E10<A3,C2+(E10-E2)*F2/1000,
IF(E10<A4,C3+(E10-E3)*F3/1000,
IF(E10<A5,C4+(E10-E4)*F4/1000,
IF(E10<A6,C5+(E10-E5)*F5/1000,
IF(E10<A7,C6+(E10-E6)*F6/1000,C7+(E10-E7)*F7/1000))))))

After entering these formulas, copy Cell B2 to Cells B3 through B6 and Cell E2 to Cells E3 through E7. Cell E10 uses the
ROUNDUP function to round up the valuation to the nearest $1,000 increment. Cell E11 uses nested IF functions to cal-
culate the permit cost.
The building permit cost data is entered into Cells A2 through A7, C2 through C7, and F2 through F7, and the valua-
tion is entered in Cell F9. The data shown in the foregoing figure is from Table 25-1 (excluding permits under $2,000) and
Example 25-1.
Markups 263

PAYMENT AND TABLE 25-2 Sample Bond Schedule


PERFORMANCE BONDS Total Estimate ($) Bond Rate (%)
Many jobs require payment and performance bonds. The
0 to 50,000 1.50
cost of the bond is based on the total bid. The bonding
schedule is divided into different brackets with a different 50,001 to 100,000 1.25
bonding rate being applied to each bracket. A sample bond- 100,001 to 250,000 1.00
ing schedule is shown in Table 25-2. A contractor using the 250,001 to 500,000 0.90
bonding schedule in Table 25-2 would pay 1.5% on the first
500,001 to 1,000,000 0.80
$50,000 of a bid, 1.25% on the next $50,000 ($100,000 ⫺
$50,000), 1% on the next $150,000 ($250,000 ⫺ $100,000), 1,000,001 PLUS 0.75
and so forth.

EXAMPLE 25-2
Using the bond costs in Table 25-2, determine the bonding cost for
a project bid at $458,265. Cell Formula
Solution: The company will pay 1.5% on the first $50,000, 1.25% =A3-1
B2
on the next $50,000, 1% on the next $150,000, and 0.9% on the re-
maining $208,265. The bonding cost is calculated as follows: C10 =IF(C9<=B2,C9*C2,
IF(C9<=B3,(C9-B2)*C3+B2*C2,
Bond!Cost ⫽ ($50,000)(0.015) ⫹ ($50,000)(0.0125)
IF(C9<=B4,(C9-B3)*C4+(B3-B2)*
⫹ ($150,000)(0.01) ⫹ ($208,265)(0.009)
C3+B2*C2,
Bond!Cost ⫽ $4,749.39 䊏
IF(C9<=B5,(C9-B4)*C5+(B4-B3)*C4+
Because the cost of the bonds is based on the bid, the (B3-B2)*C3+B2*C2,
cost of the bonds will increase the bid, which will in turn in- IF(C9<=B6,(C9-B5)*C6+(B5-B4)*C5+
crease the cost of the bonds, which will increase the cost of (B4-B3)*C4+(B3-B2)*C3+B2*C2,
the bid, and so on until the changes are insignificant. To deal (C9–B6)*C7+(B6-B5)*C6+
with this, either a rough estimate for the cost of the bonds (B5-B4)*C5+(B4-B3)*
must be included in the bid prior to the calculation of the
C4+(B3-B2)*C3+B2*C2)))))
cost of the bonds or the cost of the bonds must be calculated
by iteration. Chapter 32 will look at using iteration in a
spreadsheet to determine the cost of the bonds. After entering these formulas, copy Cell B2 to Cells B3
through B6. Cell C10 uses nested IF functions to calculate
the cost of the bond.
The bond ranges and rates are entered into Cells A3
EXCEL QUICK TIP 25-2 through A7 and C2 through C7. The bid is entered into
Bond Cost Worksheet Cell C9. The data shown in the foregoing figure is from
Table 25-2 and Example 25-2.
The following spreadsheet can be used to calculate the
cost of a bond:

A B C
1 From To Rate(%)
2 - 50,000 1.50% PROFIT AND OVERHEAD
3 50,001 100,000 1.25%
4 100,001 250,000 1.00% The profit and overhead (P&O) markup is used to cover the
5 250,001 500,000 0.90% general overhead required by the main office and to provide
6 500,001 1,000,000 0.80% a profit to the company owners. The profit and overhead
7 1,000,001 0.75% markup is expressed as a percentage of the construction cost,
8 which often includes the cost of the building permit and
9 Bid 458,265 bond. The profit and overhead markup is determined by
10 Bond 4,749 multiplying the construction cost by the profit and overhead
markup rate as shown in the following equation:
To complete this spreadsheet, enter the data and format (Construction!Cost)(P&O!Markup!%)
the cells as shown. The following formulas need to be en- P&O!Markup ⫽
tered into the associated cells: 100%
(25-1)
264 CHAPTER TWENTY-FIVE

more than their minimum profit and overhead markup;


EXAMPLE 25-3
however, when competition is meager, companies can often
The estimated construction cost for a project is $452,632. The com- increase their profit and overhead markup. To assist in deter-
pany’s profit and overhead markup is 5% of construction cost. mining when to charge a higher profit and overhead
Determine the profit and overhead markup. markup, a company must track how its competitor’s prices
Solution: The profit and overhead markup is determined as fol- compare to its own. The easiest way to do this is to keep a
lows using Eq. (25-1): record of all of the competitors who have bid against your
company along with each of their bids and the profit and
($452,632)(5%)
P&O!Markup ⫽ ⫽ $22,631.60 䊏 overhead markup that your company would have had to add
100%
to your construction costs for your bid to equal the competi-
tors’ bids. This is done by using the following equation:
Not all projects can or should be bid at the same profit
and overhead markup. A company should set a minimum Bid
P&O!Markup ⫽ !⫺ !1 (25-2)
profit and overhead markup and then increase the markup Construction!Costs
when conditions warrant1. The difficult part is to determine
when the conditions warrant an increase. The following are
some common reasons for increasing the profit and over- EXAMPLE 25-4
head markup.
Your construction company recently bid against ABC Construction
First, the company is submitting a bid as a courtesy to
Company. Your construction costs were $157,260 and you added a
the customer but really doesn’t want the project unless it is 15% profit and overhead markup for a total bid of $180,849. ABC’s
very profitable. This may happen when a company is asked bid was $179,249. What profit and overhead markup would you
to bid on a project that is outside its geographical area or need to add to your construction costs to match ABC’s bid?
area of specialization or when it already has plenty of work.
Solution: The profit and overhead markup is determined as fol-
Second, the project is a difficult project, has a high de-
lows using Eq. (25-2):
gree of risk, or the project owners are difficult to work with.
The level of risk is increased by poor document (plans and $179,249
P&O!Markup ⫽ ⫺ 1 ⫽ 0.1398!or!13.98% 䊏
project manual) quality, short construction schedules, high $157,260
liquid damages, and uncertainty that may lead to cost or
schedule overruns. In this case the risk and headaches of the When tracking the competitors’ bids it is important to
project are acceptable to the construction company only if keep track of the name of the project and the bid date as well
there is a higher level of profit. as the competitor’s bid and your construction costs.
Third, the company is bidding on the project to check Competitors may be tracked using the simple spreadsheet
their prices but really doesn’t want the project unless it is format shown in Figure 25-1.
profitable. When starting to bid after not bidding for a few When deciding whether to increase the profit and over-
months or bidding in a new market, it is wise to bid on two head markup, you need to take into account the size of the
or three projects to get a feel for the market and to get back project, type of project, and bid date. It is important to take
into a bidding rhythm. This gives the company’s manage- size into account because as the project’s size increases, the
ment a chance to get a feel for the level of profit and over- profit and overhead markup tends to decrease. It is impor-
head markup that they can add to their bids, as well as give tant to take the type of project into account because some
their estimators a chance to warm up. Should they win the companies may bid different types of projects at different
job by accident, the project usually has a good profit margin. profit and overhead markups. Finally, it is important to take
Fourth, the other companies bidding on the project are the bid date into account because projects bid in the
expected to be charging a higher profit and overhead spring—when companies are looking for the year’s work—
markup or they have higher construction costs. When com- are often bid at a lower rate than projects later in the year
petition in the market is stiff, companies can seldom charge when contractors begin filling up.

FIGURE 25-1 Spreadsheet for Tracking Competitors’ Bids


Markups 265

The construction bidding market is constantly chang-


EXAMPLE 25-5
ing. Contractors who are winning work and feeling less
Your construction company is bidding against the two construction pressure to get work may raise their profit and overhead
companies shown in Figure 25-1 on a municipal project with an en- markups, whereas other contractors who are completing
gineer’s estimate of $750,000 to $850,000. Your company’s minimum projects and need more work may lower their profit and
profit and overhead markup is 8%. What are the chances of increas- overhead markups to get this work. At the same time, other
ing your profit and overhead markup above the minimum 8%?
contractors may be adjusting the profit and overhead on
Solution: Your company bid against ABC Construction on the courtesy bids or when they perceive that a project has a
West City Park—a municipal project of similar size—where their higher degree of risk. All of this makes it difficult to predict
bid was 7.57% above your costs. It is unlikely that you will be able to where contractors are going to bid. By tracking your
raise your profit and overhead markup and still be competitive with competitors you increase your odds of reading the market
ABC Construction. You also bid against ABBCO on the same pro- right.
ject, where their bid was 9.55% above your costs. If ABC
Construction were not to bid, you might be able to raise your profit
and overhead a little. 䊏

EXCEL QUICK TIP 25-3


Competitor Tracking Worksheet
The competitor-tracking worksheet in Figure 25-1 is set up as a spreadsheet by entering the data and formatting the cell as
follows:

A B C D E
1 ABBCO
2 Project Date Bid Costs P&O
3 West City Park 6/24/02 $ 875,256 $ 798,952 9.55%
4 Platt Park Restrooms 8/14/02 $ 52,326 $ 42,165 24.10%
5
6
7 ABC Construction
8 Project Date Bid Costs P&O
9 South Street Improvements 3/15/02 $ 179,249 $ 157,260 13.98%
10 West City Park 6/24/02 $ 859,462 $ 798,952 7.57%
11 East Side Community Center 7/22/02 $ 1,152,634 $ 1,092,215 5.53%

The following formula needs to be entered into Cell E3: to be copied to Cells E4, E9, E10, and E11. Data for the bids
is entered in Columns A through D. The data shown in the
=(C3/D3-1)
foregoing figure is from Figure 25-1.
This formula will need to be copied to all other applicable
rows in Column E. In the foregoing example Cell E3 needs

CONCLUSION PROBLEMS
Common markups include building permits, bonds, and the 1. Using the building permit costs in Table 25-1, deter-
profit and overhead markup. The building permit may be mine the building permit cost for a project valued at
based on the bid or a standardized cost per square foot estab- $1,102,365.
lished by the code enforcement agency. The bond is based on 2. Using the building permit costs in Table 25-1, deter-
the bid and a bond schedule. The profit and overhead markup mine the building permit cost for a project valued at
is added to construction costs and may be added to the cost of $55,268.
the building permit and bond. Estimators should track the
3. Using the bond costs in Table 25-2, determine the bond-
bidding history of their competitors to identify where it may
ing cost for a project bid at $1,102,365.
be possible to increase their profit and overhead markup.
266 CHAPTER TWENTY-FIVE

4. Using the bond costs in Table 25-2, determine the bond- 8. Your construction company recently bid against ABC
ing cost for a project bid at $55,268. Construction Company. Your construction costs were
5. The estimated construction cost for a project is $1,125,572, and you added a 6% profit and overhead
$875,264. The company’s profit and overhead markup is markup for a total bid of $1,193,106. ABC’s bid was
8% of construction cost. Determine the profit and over- $1,179,999. What profit and overhead markup would
head markup. you need to add to your construction costs to match
6. The estimated construction cost for a project is $25,654. ABC’s bid?
The company’s profit and overhead markup is 20% of 9. Set up Excel Quick Tip 25-1 in Excel.
construction cost. Determine the profit and overhead 10. Set up Excel Quick Tip 25-2 in Excel.
markup. 11. Set up Excel Quick Tip 25-3 in Excel.
7. Your construction company recently bid against ABC
Construction Company. Your construction costs were
$265,815, and you added an 11% profit and overhead REFERENCE
markup for a total bid of $295,055. ABC’s bid was 1. For information on how to set the profit and overhead
$301,251. What profit and overhead markup would markup, see Steven J. Peterson, Construction Accounting and
you need to add to your construction costs to match Financial Management, Prentice Hall, Upper Saddle River,
ABC’s bid? NJ, 2009.
C H A P T E R T W E N T Y- S I X

PRICING EXTENSIONS

In this chapter you will learn how to calculate the price for each
EXAMPLE 26-1
takeoff item and the total cost for the bid.
A project requires the installation of 150 feet of water line. The
work includes 70 cubic yards of excavation, 23 cubic yards of bed-
ding to be placed around the pipe, and 42 cubic yards of compacted

T he previous chapters covered how to determine ma-


terial pricing, labor productivity, labor hours, labor
rates, equipment costs, crew rates, subcontractor
pricing, and markups. It is now time to combine all of these
concepts into preparing a total cost for the estimate. This is
backfill. The cost of the pipe is $12.46 per foot, and the cost of the
bedding is $19.78 per cubic yard. The sales tax rate is 5% and is paid
only on materials. No materials are needed for the excavation, and
the excavated materials are used for the compacted backfill. Excess
materials from the excavation may be left on site. Determine the
done by using the Detail worksheet created in the exercises material costs for the installation of the water line.
in Chapter 3 and the Summary worksheet (Figure 2-2) in Solution: The material costs are calculated using Eq. (26-1) as
Chapter 2. follows:
Material!CostBedding ⫽ (23!yd3)($19.78/yd3!) ⫽ $455
DETAIL WORKSHEET Material!CostPipe ⫽ (150!ft)($12.46/ft) ⫽ $1,869
The Detail worksheet is used for performing detailed esti- Material!CostSubtotal ⫽ $455 ⫹ $1,869 ⫽ $2,324
mates of the materials, labor, and equipment needed to com- The sales tax is calculated using Eq. (19-3) as follows:
plete the work in a cost code. Let’s look at each of these costs.
Sales!Tax ⫽ ($2,324)(0.05) ⫽ $116

MATERIAL COSTS The total cost is calculated as follows:

Material costs are calculated by multiplying material unit Material!CostTotal ⫽ $2,324 ⫹ $116 ⫽ $2,440 䊏
costs by the quantity of materials needed to get the cost of
the materials, as expressed by the following equation: This can also be done by entering the unit costs in
Column D of the Detail worksheet created in Chapter 3. The
Material!Cost ⫽ (Material!Unit!Cost)(Quantity) (26-1) material cost in Column E equals the quantity in Column B
The material unit cost should include shipping costs, multiplied by the unit costs in Column D. These calculations
sales tax, storage costs, and escalation. These calculations are are shown in Figure 26-1. The cells are formatted using the
shown in the following example. comma style, which replaces zeros with dashes.

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
3 33-100 Water Line
4 Trench excavation 70 cyd - -
5 Bedding 23 cyd 19.78 455
6 10" water line 150 ft 12.46 1,869
7 Backfill 42 cyd - -
8 Subtotal 2,324
9 Sales Tax 116
10 Total 2,440

FIGURE 26-1 Detail Worksheet for Example 26-1


267
268 CHAPTER TWENTY-SIX

Alternatively, the Request for Materials Quote form The total labor cost is calculated as follows:
discussed in Chapter 19 could be used to calculate the mate- Labor!CostTotal ⫽ $632 ⫹ $125 ⫹ $705 ⫹ $2,429 ⫽ $3,891 䊏
rials costs.
This can also be done by entering the productivity in
labor hours per unit in Column F and the average labor rate
LABOR COSTS for the crew in Column H of the Detail worksheet created in
Labor costs are obtained by multiplying the productivity Chapter 3. The labor hours in Column G equals the quantity
by the quantity to get the number of labor hours using in Column B multiplied by the productivity in Column F.
Eq. (20-7). The number of labor hours is then multiplied The labor cost in Column I equals the labor hours in
by the average labor rate for the crew performing the task Column G multiplied by the average labor rate for the crew
as expressed by the following equation: in Column H. These calculations are shown in Figure 26-2.
The difference in the total labor cost in Example 26-2 and
Labor!Cost ⫽ (Labor!Hours)(Labor!Rate) (26-2) Figure 26-2 is because of rounding.
Labor productivity is discussed in Chapter 20, and the
average labor rate for a crew is discussed in Chapter 23.
These calculations are shown in the following example. EQUIPMENT COSTS
Equipment costs are obtained by multiplying equipment
EXAMPLE 26-2 cost per labor hour by the number of labor hours as ex-
pressed by the following equation:
Using the average labor rate per labor hour from Example 23-1,
determine the labor costs for the installation of the water line in Equipment!Cost ⫽ (Equipment!Cost!per!Labor!Hour)
Example 26-1. For excavation of the trench the productivity is ⫻ (Labor!Hours) (26-3)
0.50 labor hour per cubic yard, for the placement of bedding the
productivity is 0.30 labor hour per cubic yard, for the placement The labor hours used in this equation are the labor
of the pipe the productivity is 0.26 labor hour per foot, and for hours calculated from Eq. (20-7). Determining the equip-
the backfill of the trench the productivity is 3.20 labor hour per ment cost per labor hour is discussed in Chapter 23. These
cubic yard. calculations are shown in the following example.
Solution: The number of labor hours for excavation is calculated
using Eq. (20-7) as follows: EXAMPLE 26-3
Labor!HoursExcavation ⫽ (0.50!lhr/yd )(70!yd ) ⫽ 35!lhr
3 3
Using the equipment cost per labor hour from Example 23-1 and
The labor cost for the excavation is calculated using Eq. (26-2) as the labor hours from Example 26-2, determine the equipment costs
follows: for the installation of the water line in Examples 26-1 and 26-2.

Labor!CostExcavation ⫽ (35!lhr)($18.07/lhr) ⫽ $632 Solution: The equipment costs are calculated using Eq. (26-3) as
follows:
The labor hours and labor costs for the remaining items are calcu-
lated as follows: Equipment!CostExcavation ⫽ (35!lhr)($50.80/lhr) ⫽ $1,778
Equipment!CostBedding ⫽ (6.9!lhr)($50.80/lhr) ⫽ $351
Labor!HoursBedding ⫽ (0.30!lhr/yd3)(23!yd3) ⫽ 6.9!lhr
Equipment!CostPipe ⫽ (39!lhr)($50.80/lhr) ⫽ $1,981
Labor!CostBedding ⫽ (6.9!lhr)($18.07/lhr) ⫽ $125
Equipment!CostBackfill ⫽ (134.4!lhr)($50.80/lhr) ⫽ $6,828
Labor!HoursPipe ⫽ (0.26!lhr/ft)(150!ft) ⫽ 39!lhr
Labor!CostPipe ⫽ (39!lhr)($18.07/lhr) ⫽ $705 The total equipment cost is calculated as follows:
Labor!HoursBackfill ⫽ (3.20!lhr/yd )(42!yd ) ⫽ 134.4!lhr
3 3 Labor!CostTotal ⫽ $1,778 ⫹ $351 ⫹ $1,981 ⫹ $6,828
Labor!CostBackfill ⫽ (134.4!lhr)($18.07/lhr) ⫽ $2,429 ⫽ $10,938 䊏

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
3 33-100 Water Line
4 Trench excavation 70 cyd - - 0.50 35.00 18.07 632
5 Bedding 23 cyd 19.78 455 0.30 6.90 18.07 125
6 10" water line 150 ft 12.46 1,869 0.26 39.00 18.07 705
7 Backfill 42 cyd - - 3.20 134.40 18.07 2,429
8 Subtotal 2,324 3,890
9 Sales Tax 116 -
10 Total 2,440 3,890

FIGURE 26-2 Detail Worksheet for Example 26-2


Pricing Extensions 269

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
3 33-100 Water Line
4 Trench excavation 70 cyd - - 0.50 35.00 18.07 632 50.80 1,778
5 Bedding 23 cyd 19.78 455 0.30 6.90 18.07 125 50.80 351
6 10" water line 150 ft 12.46 1,869 0.26 39.00 18.07 705 50.80 1,981
7 Backfill 42 cyd - - 3.20 134.40 18.07 2,429 50.80 6,828
8 Subtotal 2,324 3,890 10,937
9 Sales Tax 116 - -
10 Total 2,440 3,890 10,937

FIGURE 26-3 Detail Worksheet for Example 26-3

This can also be done by entering the equipment cost


EXCEL QUICK TIP 26-1
per labor hour in Column J of the Detail worksheet created
in Chapter 3. The equipment cost in Column K equals the Detail Worksheet
quantity in Column G multiplied by the equipment cost per The calculations for the Detail worksheet from Chapter 3,
labor hour in Column J. These calculations are shown in the worksheet shown in Figure 26-4, is set up by entering
Figure 26-3. The difference in the total labor cost in Example the data and formatting the cells as shown in that figure.
26-3 and Figure 26-3 is because of rounding. The following formulas need to be entered into the asso-
ciated cells:
TOTAL COST
Cell Formula
The total cost for each bid item equals the material cost plus
E4 =B4*D4
the labor cost plus the equipment cost, as shown in the fol-
lowing example. G4 =F4*B4
I4 =G4*H4

EXAMPLE 26-4 K4 =G4*J4

Using the costs for Examples 26-1 through 26-3, determine the L4 =E4+I4+K4
total cost for each bid item and for the installation of the water line L8 =SUM(L4:L7)
in Examples 26-1 through 26-3.
Solution: The total cost for each bid item is calculated as follows: The formula in Cell E4 will need to be copied to all other
Total!CostExcavation ⫽ $0 ⫹ $632 ⫹ $1,778 ⫽ $2,410
applicable rows in Column E, which in the case of the
foregoing example are Cells E5 through E7. The same is
Total!CostBedding ⫽ $455 ⫹ $125 ⫹ $351 ⫽ $931
true of Columns G, I, K, and L. The formula in Cell L8
Total!CostPipe ⫽ $1,869 ⫹ $705 ⫹ $1,981 ⫽ $4,555 needs to be copied to Cells E8, I8, and K8. Chapter 32
Total!CostBackfill ⫽ $0 ⫹ $2,429 ⫹ $6,828 ⫽ $9,257 looks at automating the writing of the formulas for Row 4
Total!CostSales!Tax ⫽ $116 ⫹ $0 ⫹ $0 ⫹ $0 ⫽ $116 using a macro.
Data for the costs are entered in Columns A through
The total cost of the water line is calculated as follows:
D, F, H, and J.
Total!CostTotal ⫽ $2,410 ⫹ $931 ⫹ $4,555 ⫹ $9,257 ⫹ $116
⫽ $17,269 䊏

This can also be done by summing Columns E, I, and K


SUMMARY WORKSHEET
of the Detail worksheet created in Chapter 3. These calcula- The Summary worksheet is used to record costs from the
tions are shown in Figure 26-4. The difference in the total Request for Material Quotes, the Detail worksheet, and sub-
cost in Example 26-4 and Figure 26-4 is because of rounding. contractor bids. The costs from the material quote sheet are

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
3 33-100 Water Line
4 Trench excavation 70 cyd - - 0.50 35.00 18.07 632 50.80 1,778 2,410
5 Bedding 23 cyd 19.78 455 0.30 6.90 18.07 125 50.80 351 930
6 10" water line 150 ft 12.46 1,869 0.26 39.00 18.07 705 50.80 1,981 4,555
7 Backfill 42 cyd - - 3.20 134.40 18.07 2,429 50.80 6,828 9,256
8 Subtotal 2,324 3,890 10,937 17,152
9 Sales Tax 116 - - 116
10 Total 2,440 3,890 10,937 17,268

FIGURE 26-4 Detail Worksheet for Examples 26-1 through 26-3


270 CHAPTER TWENTY-SIX

FIGURE 26-5 Summary Worksheet for Example 26-5

entered into the materials column next to their respective to provide the concrete for the site work, for which you have a ma-
cost codes. The costs from the Detail worksheet are entered terial quote from a local concrete supplier to supply the specified
into the materials, labor, and equipment columns next to quantities of concrete for $10,234.
their respective cost codes. Subcontract pricing is entered Solution: The Summary worksheet is filled out and the columns
into the subcontract column next to the respective cost are totaled as shown in Figure 26-5. 䊏
codes. The total of each cost code is then summed. The ma-
terials, labor, equipment, subcontract, and total cost for each Once the construction costs have been totaled, the cost
cost code are then totaled to get the total construction cost of the building permit, the bonds, and the profit and over-
for the project. The markups (building permit, bond, and head markup can be added to them. This is shown by the fol-
profit and overhead) will need to be added to these costs. lowing example.

EXAMPLE 26-6
EXAMPLE 26-5
Determine the bid for the project in Example 26-5. A building per-
Using the Summary worksheet from Example 3-9 and the costs
mit is not required, and the cost of the bond is $1,025, which is
from Figure 26-4, determine the construction costs for a site im-
treated as a material cost. The profit and overhead markup on ma-
provement project consisting of the water line, asphalt paving, and
terials, labor, and equipment costs is 15%, and the profit and over-
concrete sidewalk and curb. In addition to the cost of the water line
head markup on subcontracted items is 5%.
from Examples 26-1 through 26-4, you have received a bid to com-
plete the asphalt for $25,256 and a bid to form, pour, finish, and Solution: The Summary worksheet is filled out and the columns
protect the concrete site work for $11,999. Your company will need are totaled as shown in Figure 26-6.

FIGURE 26-6 Summary Worksheet for Example 26-6


Pricing Extensions 271

The profit and overhead markups are calculated using ($37,255)(5%)


Eq. (25-1) as follows: P&O!MarkupSubcontract ⫽ ⫽ $1,863
100%
($13,699)(15%) P&O!MarkupTotal ⫽ $2,055 ⫹ $584 ⫹ $1,641 ⫹ $1,863
P&O!MarkupMaterials ⫽ ⫽ $2,055
100% ⫽ $6,143
($3,890)(15%)
P&O!MarkupLabor ⫽ ⫽ $584 The difference in the total cost in Example 26-6 and Figure 26-6 is
100% because of rounding. 䊏
($10,937)(15%)
P&O!MarkupEqupment ⫽ ⫽ $1,641
100%

EXCEL QUICK TIP 26-2


Summary Worksheet
The Summary worksheet in Figure 26-6 is set up as a spreadsheet by completing Example 3-9. The Summary worksheet is
as follows:

In this figure, Rows 2 through 103 have been hidden. The Cell D123 needs to be copied to Cells E123 through H123.
following formulas need to be entered into the associated Cell D126 needs to be copied to Cells E126 through H126.
cells: Cell D128 needs to be copied to Cells E128 through G128.
Cell D129 needs to be copied to Cells E129 through H129.
Cells H129 and H130 should be the same value and are
Cell Formula used as a check for errors. The data shown in the foregoing
D123 =SUM(D2:D122) figure is from Example 26-6 and Figure 26-6. The data is
formatted using the comma style, which replaces zeros
H124 =SUM(D124:G124)
with dashes.
H125 =SUM(D125:G125)
D126 =SUM(D123:D125)
D128 =D126*D127
H128 =SUM(D128:G128)
D129 =D126+D128
H130 =SUM(D129:G129)
272 CHAPTER TWENTY-SIX

SAMPLE ESTIMATE: THE TABLE 26-1 Labor Rates for Residential Garage
RESIDENTIAL GARAGE Cost Code Rate ($/lhr)
A sample estimate for the residential garage drawings
03-000 19.00
given in Appendix F is shown in Figures 26-7 and 26-8.
The small differences in the numbers in Figures 26-7 and 06-100 to 06-120 22.00
26-8 are due to rounding. This estimate uses the quantities 06-200 to 06-210 26.00
from Chapters 5, 8 through 11, and 15 through 17 and the 07-000 22.00
burdened labor rates in Table 26-1. 08-000 26.00
09-200 24.00
09-900 24.50
26-100 29.00
31-200 25.00
32-000 19.00

MATERIALS LABOR EQUIPMENT


ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
03-000 CONCRETE
03-200 Rebar
#4x20' rebar (footings) 14 ea 5.75 81 - - 19.00 - - - 81
7"x29" L-dowels (footings) 66 ea 1.12 74 - - 19.00 - - - 74
#4x20' rebar (found.) 21 ea 5.75 121 - - 19.00 - - - 121
18"x18" L-dowels (found.) 13 ea 1.53 20 - - 19.00 - - - 20
1/2"x10" anchor bolt (found.) 45 ea 0.40 18 - - 19.00 - - - 18
1/2" nut (found.) 45 ea 0.80 36 - - 19.00 - - - 36
1/2" washer (found.) 45 ea 0.07 3 - - 19.00 - - - 3
HPAHD22 holddowns 4 ea 6.25 25 - - 19.00 - - - 25
377 - - - 377
Sales Tax 6.50 25 25
402 - - - 402

03-300 Footings and


Foundation--Labor
10" high footing forms 168 ft - - 0.08 13.44 19.00 255 10.00 134 390
Install continuous rebar 20' 14 ea - - 0.25 3.50 19.00 67 10.00 35 102
Install dowel 66 ea - - 0.06 3.96 19.00 75 10.00 40 115
Pour footings 4.50 cyd - - 0.50 2.25 19.00 43 1.50 3 46
2' high foundation forms 390 sft - - 0.15 58.50 19.00 1,112 15.00 878 1,989
Install continuous rebar 20' 21 ea - - 0.25 5.25 19.00 100 15.00 79 179
Install dowel 13 ea - - 0.06 0.78 19.00 15 15.00 12 27
Install anchor bolt 45 ea - - 0.08 3.60 19.00 68 15.00 54 122
Pour foundation 4.75 cyd - - 0.50 2.38 19.00 45 1.50 4 49
- 94 1,779 1,238 3,017

03-310 Footings and


Foundation--Concrete
3500 psi concrete (footings) 4.50 cyd 79.00 356 - - 19.00 - - - 356
3500 psi concrete (found.) 4.75 cyd 79.00 375 - - 19.00 - - - 375
731 - - - 731
Sales Tax 6.50 47 47
778 - - - 778

03-320 Slab/Floor--Labor
Pour slab 8.00 cyd - - 0.50 4.00 19.00 76 1.50 6 82
Finish slab 570 sft - - 0.01 5.70 19.00 108 1.50 9 117
- 10 184 15 199

03-330 Slab/Floor--Concrete
4000 psi concrete (slab) 8.00 cyd 82.00 656 - - 19.00 - - - 656
656 - - - 656
Sales Tax 6.50 43 43
699 - - - 699

06-000 WOODS AND PLASTICS


06-100 Rough Carpentry
2x4 wall 83 ft - - 0.15 12.45 22.00 274 1.28 16 290
Single-hung door opening 1 ea - - 0.40 0.40 22.00 9 1.28 1 9
Overhead door opening 1 ea - - 1.50 1.50 22.00 33 1.28 2 35
Install trusses 14 ea - - 1.00 14.00 22.00 308 1.28 18 326
Install ledger 110 ft - - 0.05 5.50 22.00 121 1.28 7 128
Install fascia board 116 ft - - 0.06 6.96 22.00 153 1.28 9 162
Install 15" blocking/outlooks 62 ea - - 0.05 3.10 22.00 68 1.28 4 72
Install ceiling blocking 48 ft - - 0.04 1.92 22.00 42 1.28 2 45
Install roof sheathing 829 sft - - 0.014 11.61 22.00 255 1.28 15 270
- 57 1,264 74 1,337

06-110 Lumber
Walls
2x4-8 redwood 1 ea 6.25 6 - - 22.00 - - - 6
2x4-12 redwood 4 ea 9.40 38 - - 22.00 - - - 38
2x4-14 redwood 2 ea 11.55 23 - - 22.00 - - - 23
Seal sill 50' 2 ea 3.60 7 - - 22.00 - - - 7
Z-flashing 10' long 9 ea 3.00 27 - - 22.00 - - - 27
2x4-92 5/8" stud 80 ea 2.79 223 - - 22.00 - - - 223
2x6-8' 1 ea 5.02 5 - - 22.00 - - - 5
7/16"x4'x8' OSB 1 ea 9.90 10 - - 22.00 - - - 10
3-1/2"x12" GLB 16.5 ft 7.95 131 - - 22.00 - - - 131
2x4-12 12 ea 5.16 62 - - 22.00 - - - 62
2x4-14 4 ea 6.00 24 - - 22.00 - - - 24
Roof
Hurricane ties 24 ea 0.58 14 - - 22.00 - - - 14
2x4-8 46 ea 3.37 155 - - 22.00 - - - 155
7/16"x4'x8' OSB 32 ea 9.90 317 - - 22.00 - - - 317
Plywood clips 78 ea 0.12 9 - 22.00 - - - 9
1,051 - - - 1,051
Sales Tax 6.50 68 68
1,120 - - - 1,120

FIGURE 26-7 Costs for Residential Garage


Pricing Extensions 273

MATERIALS LABOR EQUIPMENT


ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
06-120 Trusses
24' 4:12 standard trusses w/18"
tails 12 ea 57.00 684 - - 22.00 - - - 684
24' 4:12 gable end trusses w/18"
tails 2 ea 62.00 124 - - 22.00 - - - 124
808 - - - 808
Sales Tax 6.50 53 53
861 - - - 861

06-200 Finish Carpentry


Install shaped fascia 116 ft - - 0.10 11.60 26.00 302 2.50 29 331
Install door casing-set 1 ea - - 0.50 0.50 26.00 13 1.28 1 14
- 12 315 30 344

06-210 Wood Trim


1x6-10' cedar 6 ea 6.70 40 0.30 1.80 26.00 47 1.28 2 89
1x6-16' cedar 4 ea 11.95 48 0.48 1.92 26.00 50 1.28 2 100
7' foot casing 3 ea 6.00 18 0.21 0.63 26.00 16 1.28 1 35
106 4 113 6 225
Sales Tax 6.50 7 7
113 4 113 6 232

07-000 THERMAL & MOISTURE PROTECTION


07-200 Insulation
R-13 15"x32' unfaced 16 ea 13.25 212 - - 22.00 - - - 212
3 mil plastic 8' by 12' 8 ea 3.00 24 - - 22.00 - - - 24
install R-13 insulation 628 sft - - 0.007 4.40 22.00 97 - - 97
R-25 23"x32' unfaced 22 ea 17.75 391 - - 22.00 - - - 391
Install R-25 insulation 598 sft - - 0.006 3.59 22.00 79 - - 79
627 8 176 - 802
Sales Tax 6.50 41 41
667 8 176 - 843

07-400 Siding
T1-11 26 ea 21.50 559 - - 22.00 - 1.28 - 559
Install siding 792 sft - - 0.020 15.84 22.00 348 1.28 20 369
T1-11 sofit 6 ea 21.50 129 - - 22.00 - 1.28 - 129
Install soffit 164 sft - - 0.06 9.84 22.00 216 1.28 13 229
3" wide screen 58 ft 1.00 58 0.06 3.48 22.00 77 1.28 4 139
12x14 vent 2 ea 28.00 56 0.50 1.00 22.00 22 1.28 1 79
1x4 cedar 8' 16 ea 3.25 52 - - 22.00 - 1.28 - 52
1x4 cedar 10' 13 ea 4.50 59 - - 22.00 - 1.28 - 59
1x4 cedar 12' 4 ea 5.72 23 - - 22.00 - 1.28 - 23
Cut and install trim 75 ft - - 0.10 7.50 22.00 165 1.28 10 175
Install trim 212 ft - - 0.03 6.36 22.00 140 1.28 8 148
935 44 968 56 1,960
Sales Tax 6.50 61 61
996 44 968 56 2,021

07-500 Roofing
Drip edge 10' 12 ea 3.75 45 0.03 0.36 22.00 8 4.95 2 55
15 pound felt, 4 square roll 3 ea 16.00 48 1.20 3.60 22.00 79 4.95 18 145
20 yr 3-tab shingles 9 sq 32.00 288 2.00 18.00 22.00 396 4.95 89 773
381 22 483 109 973
Sales Tax 6.50 25 25
406 22 483 109 998

08-000 DOORS & WINDOWS


08-100 Metal Doors
3-0x6-8 6-panel metal prehung
door w/4-5/8 wood jambs, 1-1/2
pair hinges, weather stripping,
and threshold, drilled for deadbolt
and lockset 1 ea 135.00 135 2.00 2.00 26.00 52 1.28 3 190
135 2 52 3 190
Sales Tax 6.50 9 9
144 2 52 3 198

08-300 Overhead Doors


16'x7' pre finished, insulated,
sectional overhead door 1 ea 475.00 475 4.00 4.00 26.00 104 1.28 5 584
1/2 hp screw-drive opener 1 ea 183.00 183 1.00 1.00 26.00 26 1.28 1 210
Keyless entry 1 ea 30.00 30 1.00 1.00 26.00 26 1.28 1 57
Remotes 2 ea - - - - 26.00 - 1.28 - -
688 6 156 8 852
Sales Tax 6.50 45 45
733 6 156 8 896

08-700 Hardware
Single-keyed deadbolt 1 ea 20.00 20 1.00 1.00 26.00 26 1.28 1 47
Keyed lockset 1 ea 17.00 17 1.00 1.00 26.00 26 1.28 1 44
Floor mounted doorstop 1 ea 1.00 1 0.25 0.25 26.00 7 1.28 0 8
38 2 59 3 99
Sales Tax 6.50 2 2
40 2 59 3 102

09-000 FINISHES
09-200 Drywall
Hang and finish drywall 1238 sft - - 0.020 24.76 24.00 594 1.28 32 626
4'x8'x1/2" gypsum board 1 ea 6.50 7 - - 24.00 - 1.28 - 7
4'x12'x1/2" gypsum board 17 ea 7.65 130 - - 24.00 - 1.28 - 130
4'x14'x1/2" gypsum board 9 ea 11.25 101 - - 24.00 - 1.28 - 101
1-5/8" screws 14 lbs 18.00 252 - - 24.00 - 1.28 - 252
Joint compound 5 box 7.00 35 - - 24.00 - 1.28 - 35
Joint tape rolls 2 ea 3.00 6 - - 24.00 - 1.28 - 6
531 25 594 32 1,157
Sales Tax 6.50 35 35
565 25 594 32 1,191

09-900 Paint
Interior primer 5 gal 8.50 43 - - 24.50 - 1.50 - 43
Interior latex 7 gal 13.50 95 - - 24.50 - 1.50 - 95
Paint drywall w/3 coats 1238 sft - - 0.020 24.76 24.50 607 1.50 37 644
Exterior primer 4 gal 15.00 60 - - 24.50 - 1.50 - 60
Exterior latex 6 gal 15.00 90 - - 24.50 - 1.50 - 90
Paint T1-11 w/3 coats 956 sft - - 0.020 19.12 24.50 468 1.50 29 497
Exterior latex 0.25 gal 20.00 5 - - 24.50 - 1.50 - 5
Paint single hung door 1 ea - - 2.00 2.00 24.50 49 1.50 3 52
292 46 1,124 69 1,485
Sales Tax 6.50 19 19
311 46 1,124 69 1,504

FIGURE 26-7 continued


274 CHAPTER TWENTY-SIX

MATERIALS LABOR EQUIPMENT


ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
26-000 ELECTRICAL
26-100 Electrical
Meter tap 1 ea 5.00 5 - - 29.00 - 1.28 - 5
1-1/4” set screw/threaded
connector 1 ea 2.00 2 - - 29.00 - 1.28 - 2
1-1/4” conduit 10 ft 14.00 140 - - 29.00 - 1.28 - 140
1-1/4” comp./male threaded
coupling 1 ea 2.00 2 - - 29.00 - 1.28 - 2
1-1/4” slip/female threaded PVC
cup. 1 ea 2.00 2 - - 29.00 - 1.28 - 2
1-1/4” PVC 90 sweep 2 ea 2.40 5 - - 29.00 - 1.28 - 5
1-1/4” PVC conduit 40 ft 4.00 160 - - 29.00 - 1.28 - 160
Install Conduit 40 ft - - 0.14 5.60 29.00 162 1.28 7 170

3 ea #4 copper wire with ground 50 ft 1.75 88 0.03 1.50 29.00 44 1.28 2 133
70 amp single-phase panel
w/main 1 ea 20.00 20 - - 29.00 - 1.28 - 20
70 amp main breaker 1 ea 15.60 16 - - 29.00 - 1.28 - 16
20 amp breaker 1 ea 8.00 8 - - 29.00 - 1.28 - 8
20 amp GFI breaker 2 ea 31.00 62 - - 29.00 - 1.28 - 62
6’ copper ground rod 1 ea 14.00 14 - - 29.00 - 1.28 - 14
Install panel 1 ea - - 8.00 8.00 29.00 232 1.28 10 242
Octagon box 3 ea 1.25 4 - - 29.00 - 1.28 - 4
Single gang box 7 ea 0.25 2 - - 29.00 - 1.28 - 2
Duplex outlets 5 ea 0.50 3 - - 29.00 - 1.28 - 3
Outlet covers 4 ea 0.60 2 - - 29.00 - 1.28 - 2
Weather proof outlet cover 1 ea 4.25 4 - - 29.00 - 1.28 - 4
Quad-gang box 1 ea 4.00 4 - - 29.00 - 1.28 - 4
Quad-gang switch cover 1 ea 2.50 3 - - 29.00 - 1.28 - 3
Single-pole switches 4 ea 0.60 2 - - 29.00 - 1.28 - 2
4-tube fluorescent fixtures 2 ea 60.00 120 - - 29.00 - 1.28 - 120
4’ fluorescent light bulbs 8 ea 2.00 16 - - 29.00 - 1.28 - 16
Brass coach lights 3 ea 18.00 54 - - 29.00 - 1.28 - 54
100 watt light bulbs 3 ea 0.75 2 - - 29.00 - 1.28 - 2

250’ roll 2-#12 w/ground Romex 1 ea 32.00 32 - - 29.00 - 1.28 - 32


NM/SE cable connectors 3 ea 0.50 2 - - 29.00 - 1.28 - 2
Electrical staples 1 box 1.00 1 - - 29.00 - 1.28 - 1
Red wire nuts 1 bg 2.07 2 - - 29.00 - 1.28 - 2
Install light fixture 5 ea - - 1.00 5.00 29.00 145 1.28 6 151
Install outlet 5 ea - - 0.60 3.00 29.00 87 1.28 4 91
Install Switch 4 ea - - 0.60 2.40 29.00 70 1.28 3 73
775 26 740 33 1,547
Sales Tax 6.50 50 50
826 26 740 33 1,598

31-000 Earthwork
31-200 Grading and Excavation
Excavation 56 cyd - - 0.10 5.60 25.00 140 85.00 476 616
Backfill 19 cyd - - 0.20 3.80 25.00 95 85.00 323 418
Export 36 cyd - - 0.10 3.60 25.00 90 65.00 234 324
3/4” gravel 15 cyd 25.5 383 0.20 3.00 25.00 75 5.00 15 473
383 16 400 1,048 1,831
Sales Tax 6.50 25 25
407 16 400 1,048 1,855

32-000 Exterior Improvements


32-110 Site Concrete-Labor
Form driveway 54 ft - - 0.09 4.86 19.00 92 5.00 24 117
Screed 27 ft - - 0.09 2.43 19.00 46 5.00 12 58
Pour driveway 5.9 cyd - - 0.60 3.54 19.00 67 1.50 5 73
Finish driveway 479 sft - - 0.03 14.37 19.00 273 1.50 22 295
Form sidewalk 37 ft - - 0.09 3.33 19.00 63 5.00 17 80
Pour sidewalk 1.6 cyd - - 0.60 0.96 19.00 18 1.50 1 20
Finish sidewalk 132 sft - - 0.03 3.96 19.00 75 1.50 6 81
10' expansion joint 5 ea - - 0.10 0.50 19.00 10 1.50 1 10
- 34 645 88 733

32-120 Site Concrete-Concrete


Driveway 5.9 cyd 82.00 484 - - 19.00 - - - 484
Sidewalk 1.6 cyd 82.00 131 - - 19.00 - - - 131
615 - - - 615
Sales Tax 6.50 40 40
655 - - - 655

32-900 Landscaping
Sod Repair 291 sft 0.30 87 0.02 5.82 19.00 111 1.50 9 207
87 6 111 9 207
Sales Tax 6.50 6 6
93 6 111 9 212

FIGURE 26-7 continued


Pricing Extensions 275

FIGURE 26-8 Summary of Costs for Residential Garage


276 CHAPTER TWENTY-SIX

Code Description Materials Labor Equipment Subcontract Total


09-000 FINISHES
✔ 09-200 Drywall 565 594 32 - 1,191
09-210 Metal Studs - - - - -
09-300 Ceramic Tile - - - - -
09-500 Acoustical Ceilings - - - - -
09-600 Flooring - - - - -
09-700 Wall Coverings - - - - -
✔ 09-900 Paint 311 1,124 69 - 1,504
10-000 SPECIALTIES
10-100 Signage - - - - -
10-200 Toilet Partitions - - - - -
10-210 Toilet & Bath Accessories - - - - -
10-400 Fire Extinguishers & Cabinets - - - - -
11-000 EQUIPMENT
11-300 Appliances - - - - -
12-000 FURNISHINGS
12-200 Window Treatments - - - - -
14-000 CONVEYING EQUIPMENT
14-200 Elevators - - - - -
21-000 FIRE SUPPRESSION
21-100 Fire Sprinklers - - - - -
22-000 PLUMBING
22-100 Plumbing - - - - -
23-000 HVAC
23-100 HVAC - - - - -
26-000 ELECTRICAL
✔ 26-100 Electrical 826 740 33 - 1,599
27-000 COMMUNICATIONS
27-100 Communications - - - - -
31-000 EARTHWORK
31-100 Clearing and Grubbing - - - - -
✔ 31-200 Grading and Excavation 407 400 1,048 - 1,855
32-000 EXTERIOR IMPROVEMENTS
32-100 Asphalt - - - - -
✔ 32-110 Site Concrete—Labor - 645 88 - 733
✔ 32-120 Site Concrete—Concrete 655 - - - 655
32-130 Rebar - - - - -
32-300 Fencing - - - - -
32-310 Retaining Walls - - - - -
32-320 Dumpster Enclosures - - - - -
32-330 Signage - - - - -
32-340 Outside Lighting - - - - -
✔ 32-900 Landscaping 93 111 9 - 213
33-000 UTILITIES
33-100 Water Line - - - - -
33-300 Sanitary Sewer - - - - -
33-400 Storm Drain - - - - -
33-500 Gas Lines - - - - -
33-700 Power Lines - - - - -
33-800 Telephone Lines - - - - -
SUBTOTAL 9,816 10,163 2,821 - 22,800
✔ Building Permit 442 44 2
✔ Bond 444 44 4
SUBTOTAL 10,702 10,163 2,821 - 23,686
✔ Profit and Overhead Markup 25.0% 25.0% 25.0% 25.0%
Profit and Overhead 2,676 2,541 705 - 5,922
TOTAL 13,378 12,704 3,526 - 29,608
29,608

FIGURE 26-8 continued

CONCLUSION PROBLEMS
The Detail worksheet is used for performing detailed esti- 1. Prepare a detailed estimate and a total estimate for the
mates of the materials, labor, and equipment needed to com- residential plans given in Appendix F.
plete the work in a cost code. The Summary worksheet is 2. Prepare a detailed estimate and a total estimate for the
used to total the costs for materials quotes, the Detail work- West Street Video plans given in Appendix F.
sheet, and subcontractor bids and to include the markups
3. Set up Excel Quick Tip 26-2 in Excel.
into the bid.
C H A P T E R T W E N T Y- S E V E N

AVOIDING ERRORS
IN ESTIMATES

In this chapter you will learn how to check the bid for errors LIST COST CODES
and learn the difference between accuracy and completeness.
Estimating is the lifeblood of any construction company. Before preparing the estimate make a list of all cost codes to
Produce good competitive estimates and the company thrives. be included in the estimate. This is best done by marking off
Produce bad estimates and the company loses work or, worse, the needed cost codes on a standardized form, such as the
wins work that it cannot afford to complete. Errors are the form given in Figure 2-2. If a checked item on Figure 2-2
greatest threat to producing good estimates. does not have pricing, it is easy for the estimator to see that
the estimate is incomplete, which helps to ensure the com-
pleteness of the estimate.

N othing can ruin a construction company faster


than bad estimating. Bad estimating will either
lose the company work or win work for the com-
pany that it cannot complete while making a reasonable
profit. The opposite of a bad estimate is a good estimate.
SPEND MORE TIME ON
LARGE COSTS
Large costs carry more risk of error than small costs. For ex-
Good estimates have two characteristics: they are accurate ample, guessing the price for a large HVAC unit is riskier
and complete. than guessing the price of a bathroom faucet. Being off by
The accuracy of an estimate is a measure of how accu- 10% on the cost of the HVAC unit will create a larger cost
rate or correct the numbers in the estimate are. Problems in error than would being off by 300% on the cost of the faucet.
accuracy can occur in the quantity takeoff (the quantity is Similarly, you should spend more time on small-dollar items
wrong), productivity (too high or too low), labor rates (the that are used frequently in the building than on small-dollar
wrong labor rates have been used), or pricing (the wrong items that are seldom used because the total cost of the fre-
prices have been used). quently used items can be large. Underbidding a faucet by
The completeness of an estimate is a measure of $10 becomes a big error when there are a few hundred
whether the bid has all the items needed for the project faucets, as there would be in a hotel. This helps to ensure the
without duplicating items. Problems in completeness in- accuracy of the estimate.
clude failing to include all items needed to complete the
project (for example, forgetting to add the cost of a bond to PREPARE DETAILED
the bid) or duplicating items (for example, including the
cost of the gas lines for the project in both the HVAC and
ESTIMATES
plumbing costs). Broad estimates, such as bidding HVAC based on the square
Bad estimates are estimates that contain excessive footage of a building, carry more risk of error than prepar-
errors in accuracy or completeness. It is impossible to elim- ing a detailed estimate for the HVAC system. This is because
inate all errors from bids; however, there are a number of the errors in the detailed estimate have the tendency to can-
ways errors can be minimized. Let’s look at some of these cel each other out. For example, if one were to take a single
ways. item with an estimated cost of $300,000 and an estimated

277
278 CHAPTER TWENTY-SEVEN

error of plus or minus 10% (±$30,000) and break it down them out and verify that you end up with the desired units.
into three items with an estimated cost of $100,000 each For example, if you end up with cubic feet and you needed
with the same estimated error of plus or minus 10% cubic yards, you know you forgot to convert from cubic feet
(±$10,000) each, on average the combined error for all three to cubic yards. Consider another example of how including
items would be plus or minus $17,320 or 5.77%. This is be- the units can avoid an error: if an estimator mistakenly di-
cause the errors will tend to cancel each other out. When one vided by 9!ft2/yd2 to convert from cubic feet to cubic yards,
item is priced too high, it is likely that another item is priced he or she would find that the units after the conversion were
too low, reducing the overall total error. Estimators should ft-yd2, indicating that he or she used the wrong conversion
not rely on errors canceling each other out as justification to factor. This is shown in the following equation:
ignore known errors. Preparing detailed estimates only
27!ft3
works when you have sufficient data to prepare the estimate. 27!ft3 ⫽ ⫽ 3!ft-yd2
Preparing detailed estimates helps to ensure their accuracy. (9!ft2/yd2)
Similarly, if the estimator was converting cubic feet to cubic
yards and multiplied by 27!ft3/yd3 rather than dividing, he
MARK ITEMS COUNTED or she would end up with ft6/yd3, indicating that there were
DURING THE QUANTITY problems with the conversion. This is shown in the following
TAKEOFF equation:
One of the hardest things for an estimator to do is to remem- ft6
27!ft3 ⫽ (27!ft3)(27!ft3/yd3) ⫽ 729
ber which items have been taken off and which items still need yd3
to be taken off. On a complex set of plans it is easy to miss
Including the units in the calculations helps to ensure the ac-
items unless they are marked off as they are taken off. The best
curacy of the estimate, as shown in the following equation:
way to do this is with a light-colored highlighter through
which the blueprints can still be read. As items are taken off (27!ft3)
they are marked off. When all items in a detail are taken off, 27!ft3 ⫽ ⫽ 1!yd3
(27!ft3/yd3)
the detail should be marked off by marking the title of the de-
tail with the highlighter. When all items on a page are ac-
counted for, the page should be marked off by marking the
page number with the highlighter. At the end of the estimate,
AUTOMATE WITH
all pages in the plans should be marked off, which is easy for SPREADSHEETS
the estimator to check. Takeoff software packages mark the Another source of error is use of the wrong formula. The
items as they are taken off. Marking off items and pages en- best way to avoid this problem is to set up standard formulas
sures both completeness (none of the construction details in spreadsheets and macros (computer functions that auto-
have been left out) and accuracy (the quantities are correct). mate processes) to be used in the bidding process rather than
using hand calculations or writing new spreadsheet formulas
each time. For this to be successful, the formulas, spread-
DOUBLE-CHECK ALL sheets, and macros must be carefully tested for errors. This
TAKEOFFS helps to ensure the accuracy of the estimate.
It is easy for an estimator to lose count or miscount items.
For this reason it is important to double-check all takeoff
quantities by performing all takeoffs at least twice until the USE WELL-TESTED AND
same quantity is obtained on two separate takeoffs. Any dif- CHECKED FORMULAS
ference in the numbers should be because of rounding. In a
pinch, a quick-and-dirty takeoff can be used to double- Formulas used in spreadsheets and macros must be well
check complex takeoffs. Double-checking takeoffs helps to tested to ensure that they do not contain errors. An error in a
ensure the accuracy of the quantity takeoffs. spreadsheet can promulgate the error to a number of bids
before it is found, increasing rather than decreasing the
number of errors. The formulas should be tested under a va-
INCLUDE UNITS IN riety of conditions. It is not uncommon for a formula to
produce errors only in some conditions. Testing spread-
CALCULATIONS sheets and formulas is discussed further in Chapter 32.
A number of common mistakes can be avoided by including When a new formula is written that will only be used
the units in the calculations. They include (1) failing to con- once, it is important to verify that it is free of error and that
vert the quantities to the proper units, (2) using the im- it references the correct cells. A common mistake is to insert
proper conversion factor, and (3) dividing when one should a row for an item at the top or bottom of a group of items
be multiplying, or multiplying when one should be dividing. that are summed without having the row included in the
By including the units in the calculations, you can cancel sum. In this case, the item is left out of the bid. Testing and
Avoiding Errors in Estimates 279

checking formulas is needed to ensure the accuracy and REVIEW EACH COST CODE
completeness of the bid. AS A PERCENTAGE OF THE
TOTAL COST
DOUBLE-CHECK ALL Another way to prevent errors is to calculate the cost for each
CALCULATIONS cost code as a percentage of the total cost of the estimate and
review these percentages to see whether any of the percent-
It is easy for an estimator to make a mistake when entering a
ages are higher or lower than expected. As one does this he or
number into a calculator. For this reason, it is important to
she will become familiar with the expected range for each
double-check all calculations by entering the numbers into
cost code (for example, electrical costs may run between 6%
the calculator at least twice until you get the same answer.
and 9% of the bid) and the relationships among the percent-
Some estimators like to use a different calculator when
ages (for example, electrical costs may be about the same per-
double-checking calculations. This helps to ensure the accu-
centage as the HVAC and plumbing costs combined) for the
racy of the estimate.
type of work the company typically bids. Reviewing the per-
centages does not identify errors but may point to areas in the
bid where one might find errors. For example, if framing is
PERFORM CALCULATIONS 5% of the bid and lumber is 20% of the bid, one may suspect
IN TWO WAYS there is an error in either the framing or lumber costs or
Where possible, perform spreadsheet calculations in two both. Reviewing the percentages of the bid for each cost code
ways. For example, the total construction cost for a project helps to ensure the accuracy and completeness of the bid.
can be obtained by summing the total cost for each cost
code, or the total can be obtained by summing the totals CHECK UNIT COSTS FOR
for material, labor, equipment, subcontract, and other costs
EACH COST CODE
and then summing these totals. Performing the calcula-
tions in both of these ways should result in the same an- Another way to prevent errors is to calculate and review the
swer. When the totals are different it is an indication that unit costs for each cost code. The unit cost can be based on
there is an error in the spreadsheet and it is likely a number the cost per square foot, cost per parking space, cost per
has been left out of one of the totals. Performing calcula- apartment unit, or any other relevant unit of measure. As in
tions in two ways helps to ensure the completeness of the calculating the percentages, over time one becomes familiar
estimate. with the expected range for each cost code and the relation-
ships among the costs. Reviewing the unit costs of the bid
helps to ensure the accuracy and completeness of the bid.
DROP THE PENNIES
Another common error is to inadvertently leave out a deci- COMPARE COSTS TO THOSE
mal point when adding costs consisting of dollars and cents. FOR ANOTHER PROJECT
For this reason, pennies should be dropped from all costs
where dropping the pennies will not make a significant dif- Another way to prevent errors is to compare the cost of the
ference on the cost of the project. Pennies should be estimate to the cost of other similar projects that have been
dropped from the material cost, labor cost, equipment cost, bid to see if the costs are similar. For example, if a company
and total columns of Figure 26-4 . Pennies and fractions recently bid a 10,000-square-foot warehouse for $195,000
thereof (if desired) should be included on unit costs and and they are bidding on a 9,500-square-foot warehouse of
labor rates because dropping the pennies on these items will similar design, one would expect the costs for the warehouse
have a significant effect on the cost of the work. Dropping they are bidding to be slightly less than those for the 10,000-
pennies, where appropriate, helps to ensure the accuracy of square-foot warehouse. If they are vastly different, either
the estimate. higher or lower, the estimator should check the bid carefully
for errors. The costs can be compared based on the total cost
or by the cost code. Comparing the costs to another project
HAVE SOMEONE REVIEW helps to ensure the accuracy and completeness of the bid.
THE ESTIMATE
Before submitting an estimate it should be reviewed by a
ALLOW PLENTY OF TIME
peer or boss. As a person works intensively on a project over One of the most important things an estimator can do is
a long period of time he or she begins to see what he or she allow plenty of time to complete the estimate, especially on
expects to see. Often, when someone else reviews the esti- bid day. Bid days can be quite hectic. It is better to be over-
mate he or she will spot problems that the estimator has prepared than to scramble to fill in missing prices at the last
missed. This helps to ensure both the accuracy and the com- minute. This helps to ensure both the accuracy and the com-
pleteness of the estimate. pleteness of the bid.
280 CHAPTER TWENTY-SEVEN

CONCLUSION 4. Why are detailed estimates more accurate than square-


footage estimates?
It is impossible to eliminate all errors from a bid; however, 5. Why should items on the drawings be marked off as
with careful procedures you can greatly reduce the number they are taken off?
and size of errors. Errors can be reduced by listing all of the
6. Why should you perform takeoffs twice?
needed cost codes on a standardized form at the start of the
estimating process, spending more time on the larger-cost 7. Why should you include units in all calculations?
items, preparing more detailed estimates, marking off items 8. What are the advantages of using formulas and macros
on the drawings as they are taken off, double-checking all in spreadsheets?
takeoffs, including units in calculations, automating the esti- 9. Why must spreadsheet formulas be tested?
mating process with spreadsheets, using well-tested formu- 10. Why should you always double-check your calculations?
las, double-checking all calculations, performing calcula- 11. Why should calculations, where possible, be performed
tions in two ways, dropping pennies from numbers where it in two different ways?
will make little difference in the total bid, having someone
12. Why should pennies be dropped from the material cost,
review the estimate, reviewing each cost code as a percentage
labor cost, equipment cost, and total columns from
of the total cost, checking the unit cost for each cost code,
Figure 26-4?
comparing the bid to bids from other projects, and allowing
plenty of time to complete the bid. 13. Why should the estimate be reviewed by a peer or boss?
14. Why is it important to check the percentage of the total
bid for each cost code?
PROBLEMS 15. Why is it important to check the unit cost for each cost
1. Define accuracy and completeness. What is the differ- code?
ence between accuracy and completeness? 16. Why should one compare the costs of the bid to the
2. Why is it important to use a bid summary form similar costs of other, similar projects?
to the one shown in Figure 2-2? 17. Why is it important to allow plenty of time to prepare
3. Why should you spend more time on items with large the bid?
costs than on items with small costs?
P A R T F O U R

FINALIZING THE BID

Chapter 28 Submitting the Bid


Chapter 29 Project Buyout
Chapter 30 The Estimate as the Basis of the Schedule
Chapter 31 Ethics

I
n this section, you will learn how to complete and submit the bid, pur-
chase the materials and hire subcontractors to complete the work, and
incorporate data from the bid into the schedule. This section also in-
cludes a discussion of ethics as it relates to bidding.
C H A P T E R T W E N T Y- E I G H T

SUBMITTING THE BID

In this chapter you will learn how to submit a bid using stan-
dardized bid documents and also how to write a proposal letter.

O ne of the most important things to do when sub-


mitting a bid is to have the bid in on time. For
some owners, particularly public agencies, bids
that are late, even by 1 minute, are not considered. The types
of bids submitted may be divided into two broad categories:
submitting the bid using standardized bid documents pro-
vided by the design professional and owner, or submitting a
proposal. Let’s first look at submitting the bid with standard-
ized bid documents.

BID SUBMISSION WITH


STANDARDIZED DOCUMENTS
Many owners or design professionals have a set of standardized
bid documents that they use on all projects. The documents
may include a bid form (such as the one shown in Figure 1-1),
a schedule of values (such as the one shown in Figure 1-2), a
bid bond, certifications, and so forth. When bidding using
standardized bid forms, it is important to make sure that the
form is completely filled out and that the pricing is accurate.
For many municipalities, incomplete or missing forms result in FIGURE 28-1 Sample Bid Submission Checklist
the bid being classified as a nonresponsive bid, and the bid
ends up being discarded. It would be unfortunate for the esti-
mator to spend days preparing a bid and having the low price
WRITING A PROPOSAL
only to have the bid discarded because a form was missing or a The second category is submitting a proposal. With a pro-
line had been left blank on a form. Before submitting a bid, the posal, rather than using documents provided by the owner
estimator should carefully check the bid documents to make or the design professional, the estimator must prepare his
sure they are complete and accurate. Any blank items that must or her own proposal. The owner may specify what needs to
be filled in just before the bid is submitted, such as the price, be included in the documents, but the actual format and
should be marked with Post-Its to minimize the possibility of organization of the documents is left up to the company
forgetting to fill in a blank on the day of the bid. It is also a good submitting the bid. The documents may include a proposal
idea to use a checklist to make sure that nothing is forgotten. A letter, breakdown of the bid price, bid bonds, schedule, cat-
sample checklist is shown in Figure 28-1. alogue cut sheets, samples, and so forth.
282
Submitting the Bid 283

FIGURE 28-2 Sample Proposal Letter

One of the most important documents in the proposal is of values add up to the total bid price. Any backup to
the proposal letter. The proposal letter should identify the the pricing required by the owner, such as bids from
price for the work, payment terms, the scope of the work being subcontractors, should also be attached. In the letter in
bid, work that is excluded from the bid, any clarifications that Figure 28-2, the price for the work is $956,250.
need to be made, the latest date the proposal may be accepted, Payment Terms: Along with the price, the terms of
the schedule for the start and completion of the work, sug- payment (for example, retention rate and when pay-
gested alternatives, severe-weather clauses, and other items ments are due) should be included in the letter. In the
that help to clarify the proposal. The proposal letter should be letter in Figure 28-2, the payments terms are that the
kept to under five or six pages. When all of this information owner will be billed progress payments at the end of
cannot be contained in a short letter, these items should be in- each month, and payment is due from the owner 25
cluded as attachments to the proposal. All attachments to the days after receipt of the bill.
proposal should be referenced in the proposal letter. Let’s look
Scope of Work: The proposal letter should clearly state
at the specific components of the proposal letter.
the scope of work being bid. Often, with a proposal
Price: The proposal letter must clearly communicate to there is some flexibility to specify or modify the scope
the client the price to complete all or a specified por- of work. Some owners may allow the contractor to
tion of a construction project. The letter should con- bid on all or part of the work, may leave the specify-
tain a price or price range. Price ranges are often used ing of materials up to the contractor, or leave design
when dealing with preliminary bids when the design of of all or part of the project to the contractor, as is the
the project is still being established to indicate that the case in a design-build project. The scope of work
price is not a hard-and-fast number. If the price is to be should be prepared as discussed in Chapter 24 and
broken down into a number of items, then the break- should identify work that is included in the bid, work
down of the pricing should be submitted on a schedule that is excluded from the bid, and any clarifications
of value form (similar to Figure 1-2) that is attached to that need to be made. This may require the attach-
the letter. When a schedule of values is included, the es- ment of a sample specification (such as the one
timator must make sure that the costs on the schedule shown in Figure 28-3), catalogue cut sheets, and so
284 CHAPTER TWENTY-EIGHT

FIGURE 28-3 Sample Specifications


Submitting the Bid 285

forth. In the letter in Figure 28-2, the work will be printed on letterhead that includes the sender’s ad-
completed as per the plans and specification pre- dress, the sender’s address is not included in the letter.
pared by John Lake, AIA, and dated April 26, 2006. Date: The date of the letter should be the date the letter
Included in the price is the cost of the building per- was written. When writing a letter that takes a num-
mit, and all other fees assessed by the local munici- ber of days to complete, the completion date of the
pality are excluded. letter is used instead of the date the letter was started
Time Frame: The proposal letter should identify how to avoid the appearance that the letter has been sitting
long the client has to accept the proposal and the an- around for a long time before someone got around to
ticipated start and completion of the work. Because mailing it. The date should contain the month (writ-
bids that have not been rejected can tie up the bond- ten out completely), the day of the month, and the
ing capacity for a company and leave the company year. A comma should separate the day of the month
wondering whether they are going to do the work, a and the year. The date should be directly below the
company needs to include a time frame for accepting sender’s address, if there is one.
the bid in the proposal letter. Because the time of the Inside Address: The inside address is the address of the
year the work is being done can greatly affect the person to whom the letter is being sent. Every letter
price, the time frame for starting and completing should be addressed to a person and not just a com-
the work should be included in the proposal letter. pany. The inside address should include the name,
In the letter in Figure 28-2, the owner has 60 days personal title (Miss, Mrs., Mr., or Dr.), and job title
from the date of the proposal to accept the proposal, (for example, president). If one is not sure of the
and the proposal is based on the project being started spelling of a person’s name, preferred personal title,
before August 15, 2006, and being completed in 160 or job title, one should call his or her secretary or the
calendar days. company’s receptionist and find out this information.
Alternatives: The proposal letter may also include a list When the sender’s address is above the date in the let-
of suggested alternatives for consideration by the ter, there should be one blank line between the date
owner. For example, the contractor may be able to and the inside address. When the sender’s address is
obtain a piece of equipment that has not been ap- not above the date in the letter, the inside address
proved but is similar to the equipment specified at a should be 1 inch below the date.
lower price. In this case the contractor should include
Subject Line: Every letter should have a subject line.
the specified piece of equipment in the company’s bid
The subject line allows the reader of the letter to
and offer the owner the opportunity to reduce the bid
quickly identify the main topic of the letter. A subject
by changing to the proposed piece of equipment.
line is very useful when trying to locate an old letter
Other: The proposal should contain any severe- about a certain subject when one is not sure of the
weather clauses or other items that help to clarify the date the letter was sent. During the course of a pro-
proposal. ject, hundreds of letters may be written between the
Contact Information: Finally, the proposal should contractor and the owner. Without a subject line, it
contain the name of the person to contact and how can take hours to locate old correspondence related
to get a hold of him or her should the client have to a specific topic. Subject lines often begin with RE:,
any questions or desire to make any changes to the short for regarding. Most often the subject line is not
proposal. a complete sentence; therefore, it should not end with
a period. The subject of the letter in Figure 28-2 is the
submission of the bid for the West 10th Street Office
WRITING A BUSINESS LETTER Complex. There should be one blank line between the
The proposal should be written in a standard business letter inside address and the subject line.
format. All business letters should leave the client with a Salutation: The salutation is the greeting to the per-
good impression of the company. This is done by preparing son to whom the letter is being written. The saluta-
a clearly written letter free of spelling and typographical er- tion should begin with the word Dear and end with
rors and written in a standard business format. When work- a colon. The person who is greeted in the salutation
ing for a company, one should determine whether the com- is the person whose name appears in the inside ad-
pany has a standard format or template for business letters, dress. Unless the writer is a close personal business
and if so, it should be used. The following is an overview of acquaintance or friend, the person should be ad-
the parts and layout of a standard business letter. dressed by personal title and last name. If the writer
Sender’s Address: The sender’s address should include is a close business acquaintance or friend, he or she
the company name, street address, city, state, and zip may choose to address the recipient of the letter in a
code. The senders address may appear at the top of less formal manner, such as Dear Bob. There should
the letter as shown in Figure 28-2 or be included as a be one blank line between the subject line and the
footer to the first page of the letter. When the letter is salutation.
286 CHAPTER TWENTY-EIGHT

Body: The body of the letter should be written in a the writer’s initials and the typist’s initials are often
clear, concise, and orderly manner. For the proposal included after the copies. The writer’s initials are cap-
letter, the body of the letter should identify the price italized and the typist’s initials are written in lower-
of the work, payment terms, and so forth. The first case. When both sets of initials are included, a colon
paragraph should contain a friendly opening, such separates the initials. There should be a blank line be-
as “Thank you for giving us the opportunity to bid tween the initials and the text that appears directly
on the West 10th Street Office Complex.” Next, the above the initials.
body of the letter should state the main point of the File Name and Location: With the advent of the com-
letter. This is done in the first or second paragraph. puter, people often want to locate an electronic copy
After stating the main point, the body of the letter of a document. To make letters easier to find, the
should continue to logically justify or clarify the writer often includes the file name and file location
main point of the letter. These justifications and (folder) at the end of the letter. There should be a
clarifications should be organized in the order of blank line between the file name and location and the
importance, with the most important points first text that appears directly above it.
and the least important points last. Near the end of
Letters Longer Than One Page: Two things must be
the body of the letter, the main points may be re-
done for letters longer than one page. First, the clos-
stated, and, if desired, the writer of the letter should
ing should not begin at the top of the page. The page
urge the recipient to take some specific action.
breaks of the letter should be changed so that there
Finally, the writer of the letter should identify who
are at least two lines of body on the page before the
to contact and how to contact him or her for an-
closing. Second, in case the pages of the letter get sep-
swers to questions or for more information. This is
arated from each other, the pages need to be individ-
very important because often letters are signed by
ually identified so they can be reunited. This is done
someone other than the person who prepared the
by including a header on the second through last
letter. There should be one blank line between the
pages of the letter. The header should include the
salutation and the body of the letter. The paragraphs
page number, whom the letter was written to, and the
of the letter should be single spaced with a space be-
date of the letter.
tween the paragraphs.
Closing: The closing of a letter contains a closing
statement (such as “Sincerely” or “Best regards”), a
space for the signature, and the name and title of the
LETTER FORMATS
person who signed the letter. There should be a There are three common formats for letters: block, modified
blank line between the body of the letter and the block, and semiblock. In the block format, all contents in the
closing statement. Only the first word of the closing letter are left justified and the first line of each paragraph is
statement should be capitalized, and the closing not indented. The letter in Figure 28-2 is written in the block
statement should be followed by a comma. Three format. For a letter written in the modified block format, the
blank lines should be provided for the signature be- sender’s address, date, and closing (signature block) begin at
fore the name and title of the person who signs the the center of the page (not centered), whereas all other items
letter. The name and title of the person who signs of the letter are left justified. Figure 28-4 shows a letter writ-
the letter follows the same rules as the name and ten in modified block format. The semiblock format is the
title of the recipient. same as the modified format except that the first line of each
Enclosures: If documents are included with the letter, paragraph is indented. Figure 28-5 shows a letter written in
the word Enclosure (for a single document) or the semiblock format.
Enclosures (for multiple documents) is included
after the closing. There should be one blank line be-
tween the closing and the enclosure. If desired, the WRITING E-MAILS
writer of the letter may list the documents enclosed
E-mail is widely used by contractors to communicate with
with the letter.
design professionals, subcontractors, and suppliers, as well
Copies: Next, the letter should identify who received as with the company’s own personnel. E-mail is often used to
copies of the letter. This is done by typing CC: (short invite subcontractors to bid on a project, obtain pricing
for carbon copies) followed by the name of the recip- from suppliers, and submit bids to the general contractor.
ients. In Figure 28-2 a copy of the letter was sent to During both the bidding process and the construction of the
the file. There should be one blank line between the project, e-mail is often used to request additional informa-
copies and the enclosure or closing if there are not tion and obtain clarifications regarding the drawings and the
any enclosures. project manual.
Writer’s and Typist’s Initials: If the letter was written It is important that e-mails leave the client, design pro-
or typed by someone other than the signer of the letter, fessional, subcontractor, or supplier with a good impression
Submitting the Bid 287

FIGURE 28-4 Modified Block Letter

FIGURE 28-5 Semiblock Letter


288 CHAPTER TWENTY-EIGHT

From: ABC Construction


the subject line. If the topic changes, the subject line
To: XYZ Lumber should change to reflect the change. If an e-mail is impor-
Date: 8/22/2009 10:55 AM tant enough to send, it is important enough to have a well
Subject: Lumber Pricing for West 10th Street Office Complex
written subject line. E-mails with poor subject lines are
Attached is the list of the lumber needed to construction often placed in the trash without even being opened. In
the West 10th Street Office Complex. Please provide
us with a quote for this lumber by 10:00 am on Figure 28-6, the subject of the e-mail is “Lumber Pricing
September 1, 2009. for West 10th Street Office Complex.”
Steven Peterson, MBA, PE 䊉 E-mails should be brief and to the point. They should
Phone 801-626-0000 clearly state the desired action the sender wants the recip-
Fax 801-626-0001
ient to take. The e-mail should not leave them wondering
FIGURE 28-6 Sample E-mail why it was sent. In Figure 28-6, the desired action is for
the lumber supplier to provide ABC Construction a lum-
ber quote for the West 10th Street Office Complex by
of the company. As with letters, this is done by preparing a 10:00 am on September 1, 2009.
clearly written e-mail, free from spelling and typographical 䊉 E-mails should be checked for proper spelling, punctua-
errors. A sample e-mail is shown in Figure 28-6. E-mails tion, and capitalization. If your e-mail software does not
should abide by the following rules: check for spelling and grammar, the e-mail should be
䊉 E-mails should only be sent to the parties that need the written in a word processer that does and copied to the
information. Sending e-mails to a large number of people e-mail software. E-mails should not be written using all
to cover your bases wastes their time and leaves them with capital letters.
a bad impression. Junk e-mails, cute stories, and other 䊉 Emotion icons should not be used in business communi-
similar e-mails should not be forwarded unless you have cation. Too often they do not come across as expected.
permission from those you are sending them to. 䊉 The signature block should contain the contact informa-
䊉 E-mails should have a subject line so that it can be quickly tion for the sender, such as his or her phone number(s)
found. A common mistake is to reply to an e-mail with an and fax number.
e-mail that discusses a different topic without changing

CONCLUSION PROBLEMS
It is important for bids to be submitted on time because 1. Why is it important to submit the bid on time?
owners may reject late bids. Sometimes bids are submitted 2. Why is it important to make sure a complete bid pack-
on standard bid documents that may include the bid form, age has been submitted?
a schedule of values, a bid bond, certifications, and so 3. Why should the proposal letter include the anticipated
forth. Other times, the contractor may be required to sub- start and completion of the work?
mit a proposal that may include a proposal letter, break-
4. Why should a letter or e-mail have a subject line?
down of the bid price, bid bonds, schedule, catalogue cut
sheets, samples, and so forth. The proposal letter should 5. Why should a letter contain the person to contact and
include the price for the work, payment terms, the scope how to get a hold of him or her should the recipient
of the work being bid, work that is excluded from the bid, have questions?
any clarifications that need to be made, the latest date the 6. Why should letters longer than one page have a header
proposal may be accepted, the schedule for the start and containing the page number, recipient’s name, and date?
completion of the work, suggested alternatives, severe- 7. What is the difference between the block, modified
weather clauses, and other items that help to clarify the block, and semiblock formats?
proposal. 8. What are the rules for writing a good e-mail?
C H A P T E R T W E N T Y- N I N E

PROJECT BUYOUT

In this chapter you will learn how to write subcontracts and Parties to the Contract: The subcontract is a legal
purchase orders. agreement between the contractor and the subcon-
tractor, or a subcontractor and a second-tier subcon-
tractor (a subcontractor to a subcontractor). The par-

T
ties to the contract should be clearly identified at the
he buyout is the process of hiring subcontractors
beginning of the contract. After identifying the par-
and procuring materials and equipment for a con-
ties, the parties to the contract are referred to as the
struction project. Subcontractors are hired by writ-
“Contractor” and “Subcontractor.” The contract
ing a subcontract between the contractor and the subcon-
should address the procedures for the assignment
tractor. Materials and equipment are procured by issuing
(the subcontracting) of part of or the entire subcon-
purchase orders or contracts to the materials and equipment
tract to another party. If one or more of the parties
suppliers. The estimator should write the subcontracts and
are persons rather than corporations, what happens
the majority of the purchase orders before construction be-
in the event of the death of one of the parties should
gins or during the early stages of construction. Let’s begin by
be addressed.
looking at subcontracts.
Project Identification: The project name and loca-
tion of the project should be clearly identified in the
SUBCONTRACTS contract.
Subcontracts are issued to subcontractors who provide labor Scope of Work: The contract should include the scope
at the construction site. These subcontractors may also pro- of work covered by the subcontract. The scope of
vide materials and equipment. If a subcontractor does not work is different for each subcontract. The scope of
provide labor at the construction site, a purchase order or work should be written in accordance with Chapter
material contract should be issued rather than a subcontract. 24 and should be tied to a set of construction docu-
During the buyout process, the estimator should prepare all ments along with their dates. This may be done by
of the subcontracts. The owner or designee should review attaching a list of construction documents, such as
and sign the contracts. the one given in Appendix F, to the contract and ref-
Many companies have standard subcontracts they use. erencing the attachment in the subcontract.
Standard subcontracts are also available from the American Schedule of Values: The subcontract should clearly es-
Institute of Architects (AIA) and the Associated General tablish the price to be paid for the completion of the
Contractors of America (AGC). Construction companies scope of the work. When work is done in phases, such
should make sure that the subcontracts that they use meet as rough and finish electrical, the price for each phase
their needs rather than assume that standard subcontracts needs to be established to avoid billing disputes dur-
are right for them. If contractors write their own subcon- ing the construction process. When unit prices are in-
tracts or make changes to a standard subcontract, the con- cluded in the subcontract, the unit prices, as well as
tract and changes should be reviewed by an attorney. When how the quantities will be determined, need to be in-
selecting or writing a subcontract to use, the contractor cluded in the subcontract. If the contractor has the
should consider the following issues: right to accept an alternative, such as constructing an

289
290 CHAPTER TWENTY-NINE

additional building, during the construction of the release of retention. The subcontract should give the
project, the terms for acceptance and pricing need contractor the right to withhold payments for defec-
to be addressed in the contract. For example, the tive work; failure to meet contractual requirements,
contractor may have the right to build a second including providing lien waivers, insurance certifi-
identical building for the same price as the first cates, certified payrolls, as-built drawings, operation
building provided the construction of the second and maintenance manuals, and so forth; claims
building is started within 6 months of the start of against the subcontractor; failure to pay for materials;
the first building. and liens against the project caused by the subcon-
Schedule: The subcontract should require the subcon- tractor. The contractor should have the right to
tractor to meet the schedule set by the general con- backcharge the subcontractor for damage to the work
tractor. Often a preliminary schedule is attached to the of other trades done by the subcontractor and charge
subcontract. The number of days the subcontractor the subcontractor the penalties set forth in the sub-
has to begin the work after receiving notice to pro- contract. The contractor should have the right to
ceed, the number of days the subcontractor has to issue a joint check to the subcontractor and the sub-
complete the work, the minimum crew size the sub- contractor’s suppliers if the contractor has concerns
contractor agrees to maintain at the site during the about the suppliers getting paid.
period the work is being performed, and a require- Change Orders: The subcontract should clearly iden-
ment for the subcontractor to work overtime may be tify the process for issuing change orders and indicate
included in the subcontract. The subcontract should that payment will not be made for unauthorized
identify any coordination meetings the subcontractor change orders.
is required to attend and any special coordination Insurance, License, and Bond Requirements: The sub-
needed between the subcontractor and other trades. contract should require the subcontractor to maintain
For example, if the mechanical subcontractor needs specified insurance limits and name the general con-
to coordinate the delivery of the roof-top units with tractor as an additional insured on their insurance
the contractor so the contractor’s crane is available to policy. It should also require the subcontractor to sub-
place the units, these requirements should be spelled mit proof that they have workers’ compensation in-
out in the contract. The penalties for missing coordi- surance and a copy of their contractor’s license (if
nation meetings and missing deadlines should also be licensing is required) and notify the contractor in the
included in the subcontract. event either of these changes. The subcontract should
Submittals: The subcontract should identify the sub- identify any bonds required, and require the subcon-
mittals required, the process for their approval, and tractor to indemnify the contractor against any suits
their due dates. If these requirements are included in that are a result of the subcontractor’s actions.
the project’s specifications, the specifications can sim- Warranty: The subcontract should identify the war-
ply be referenced in the subcontract. ranty requirements and spell out response times for
Quality: The subcontract should identify the level of different classes of warranty issues. For example,
quality required along with any required testing and problems with heating systems should be handled
inspections. If these requirements are included in the within hours, whereas problems with paint should be
project’s specifications, the specifications can simply handled within days.
be referenced in the subcontract. The penalties for Protection of Work: The subcontract should require
unacceptable quality and the procedures and time al- the subcontractor to protect the work of other trades
lowed for correcting the work need to be included in from damage caused by the subcontractor’s work,
the subcontract. protect their own work against weather, and protect
Payment: The subcontract should clearly identify their materials and equipment against theft and
when and how payments will be made. The subcon- vandalism. It should also identify the subcontractor’s
tract should include (1) when invoices are due and rights and responsibility for using the existing or
when they will be paid, (2) whether partial or newly constructed facilities. For example, can the
progress payment will be made versus payment on subcontractor park on the new parking lot? If so,
completion, (3) whether retention will be withheld what must the subcontractor do to protect the
from the payment, (4) whether the work is required facilities?
to be billed within a specified number of days of its Safety: The subcontract should require the subcontrac-
completion, (5) whether the payment will be held tor to comply with Occupational Safety and Health
until payment is received from the owner (a paid- Act (OSHA) and other state and federal safety regula-
when-paid clause), (6) whether payment will be tions, comply with the contractor’s safety plan, attend
made for materials ordered or delivered to the site or hold safety meetings, and provide Material Safety
that have not been incorporated into the building, Data Sheets (MSDS). A copy of the contractor’s safety
and (7) the requirements for final payment and plan should be attached to the subcontract.
Project Buyout 291

Cleanup: The subcontract should require subcontrac- PURCHASE ORDERS


tors to clean up after themselves on a daily basis and
should identify the penalties for not cleaning up. Purchase orders are written to material and equipment sup-
pliers. If these suppliers are providing labor at the construc-
Termination: The subcontract should set the proce-
tion site, a subcontract should be written rather than a pur-
dures for terminating the contract for nonperfor-
chase order. During the buyout process, the estimator should
mance of the subcontractor or in the event the con-
write the majority of purchase orders. The project manager
tractor’s contract with the owner is canceled.
and superintendent will write additional purchase orders as
Dispute Resolution: The subcontract should set the materials not purchased by the estimator are ordered.
procedures for dispute resolution. They may include The purchase orders are based on the Request for
mediation, arbitration, and going to court. The pay- Materials Quote and should contain the following informa-
ment of attorney’s fees in the event of a dispute tion: the number of the purchase order; the cost code to
should be addressed. If any of the parties to the con- which the purchase order will be charged; the contractor’s
tract are located in a different state than the state name, address, and contact information; the supplier’s
where the project is located, the jurisdiction under name, address, and contact information; the project’s name,
which the contract will be interpreted and where dis- address, and contact information; the quantities, descrip-
putes will be resolved should be identified. tion, and pricing for the materials or equipment being or-
General Clauses: General provisions include how the dered; delivery costs; sales tax; a total price for the purchase
contract is administered. They include (1) stating the order; payment terms; the signature of the contractor’s em-
contractor’s right to waive a provision without hav- ployee ordering the materials; and the date the purchase
ing to waive the provision in the future or without order was signed. A sample purchase order is shown in
voiding the contract, (2) allowing unenforceable pro- Figure 29-1.
visions thrown out by the courts to be severed from Purchase orders should be sequentially numbered and
the contract, (3) describing under which state’s law recorded in a purchase order log when they are issued. The
the contract will be enforced, (4) making sure that the purchase order log should contain the following informa-
entire agreement is contained within the contract, tion: the purchase order number, the project the purchase
and (5) stipulating that the agreement supersedes all order was issued for, to whom the purchase order was issued,
previous agreements. All attachments to the contract and a brief description of the materials or equipment or-
should be identified in the contract. dered. A sample purchase order log is shown in Figure 29-2.

PO # Cost Code
1001 PURCHASE ORDER
To:

From:

Project:

QUANTITY DESCRIPTION $/UNIT COST

SUBTOTAL
SALES TAX 0.00%
SUBTOTAL
DELIVERY
TOTAL

Invoices received by the 25th day of the month will be paid on the 25th of the following month. Any
application for payment received sixty (60) days or more after materials have been delivered shall not be
honored. All invoices must be submitted to the contractor's office.

By: Date:

FIGURE 29-1 Sample Purchase Order


292 CHAPTER TWENTY-NINE

FIGURE 29-2 Sample Purchase Order Log

CONTRACTS FOR MATERIALS the case of an annual contract for materials. Second, mate-
rial suppliers do not perform work on the jobsite.
When materials are purchased over a long period of time Contracts for materials should be similar to subcontracts
or annual agreements are made for materials, a contract for with the nonapplicable clauses eliminated. For example,
materials may be written rather than a purchase order. material suppliers do not need to attend the weekly safety
Material contracts differ from subcontracts in two ways. meetings.
First, the contract may not be tied to a specific project as in

CONCLUSION 3. What payment terms are established by the subcontract?


4. Under what circumstances can the contractor backcharge
The buyout is the process of hiring subcontractors and the subcontractor?
procuring materials and equipment for a construction pro-
5. What are the procedures for processing a change order?
ject. Subcontractors are hired by writing a subcontract be-
tween the contractor and the subcontractor. Materials and 6. What are the insurance requirements?
equipment are procured by issuing purchase orders or con- 7. What are the bonding requirements?
tracts to the materials and equipment suppliers. The estima- 8. How does the subcontract address warranty issues?
tor should prepare the subcontracts and the majority of the 9. How does the subcontract address protection of work?
purchase orders before construction begins or during the 10. How does the subcontract address safety?
early stages of construction.
11. Under what conditions can the subcontract be termi-
nated?
PROBLEMS 12. What are the procedures for dispute resolution?
For Problems 1 through 12, obtain a copy of a subcontract 13. Prepare subcontracts and purchase orders for the Johnson
used by a local contractor or a standard AIA or AGC subcon- Residence given in Appendix F.
tract. 14. Prepare subcontracts and purchase orders for the West
1. How does the subcontract address scheduling issues? Street Video project given in Appendix F.
2. How does the subcontract address quality issues?
CHAPTER THIRTY

THE ESTIMATE AS THE BASIS


OF THE SCHEDULE

In this chapter you will learn how the data from the estimate Materials Required: The materials required to com-
relates to the project’s schedule. plete a task come from the estimate. Often, the pur-
chase orders are written to coincide with the tasks on
the schedule. For example, the purchase orders for

D
lumber on a building may be divided into a wall
uring the process of estimating the project, the esti-
package coinciding with the task of framing the walls
mator should have collected much of the data
and a roof package coinciding with the task of fram-
needed to prepare the schedule. For a task on the
ing the roof.
project to be completed, the proper labor, materials, and
equipment must come together on the project at the same Labor Required: The crew makeup and the number of
time the project is ready for the work to be done. For exam- labor hours to complete a task come from the estimate.
ple, for a roof-top HVAC unit to be placed, the materials (the Equipment Required: The equipment required to com-
roof-top unit), the labor (the HVAC subcontractor), and the plete a task comes from the estimate and is based on the
equipment (a crane) must come together when the building method of construction used to determine the costs.
is ready for the roof-top unit. If the materials, labor, or Subcontractor Required: The plans to use subcontrac-
equipment is not available or if the building is not ready for tors to supply the labor for a task and possibly some
the work to be performed, the work cannot be performed. of the equipment and materials are identified in the
The following information from the estimate is needed to estimate.
prepare the schedule. Special Coordination, Inspections, and Long-Lead
Task Relationships: In preparing the estimate, the esti- Items: In preparing the estimate, the estimator
mator should identify what tasks will need to be done should identify special coordination, special inspec-
before a task or group of tasks can be completed and tions, and long-lead items that are needed to complete
what tasks must be done concurrently. Often, these the project. It is vital that the estimator pass the infor-
relationships are very obvious; at other times they are mation along to the persons responsible for preparing
not. For example, realizing that the footing must be the schedule and completing the construction.
placed before foundation walls and columns is obvi- This information can be recorded on the form in
ous, whereas realizing that the HVAC unit must be Figure 30-1.
placed as the trusses are placed, because there is lim-
ited access, is not obvious. It is such unobvious rela-
tionships that the estimator needs to pay particular ESTIMATING DURATIONS
attention to and should have identified as he or she
The estimated duration of a task should be related to the
builds the project in his or her mind.
number of labor hours required to complete the task and the
Method of Construction: The method of construction size of the crew assigned to it. The duration is estimated by
affects the work flow. For example, if the estimator dividing the number of labor hours from the estimate by the
bid the project planning to reuse the foundation crew size, using the following equation:
forms on the project four times, the schedule will
need to reflect that the foundation will be poured in (Labor!Hours)
Duration ⫽ (30-1)
four phases. (Crew!Size)
293
294 CHAPTER THIRTY

TABLE 30-1 Durations for the Residential Garage


Labor Crew
Hours Size Duration
Footings and foundation 94 3 4
Slab/floor 10 2 1
Rough carpentry 57 3 3
Finish carpentry 12 1 2
Wood trim 4 1 1
Insulation 8 1 1
Siding 44 2 3
Roofing 22 2 2
Metal doors 2 1 1
Overhead doors 6 2 1
Hardware 2 1 1
Drywall 25 2 2
Paint 46 2 3
Electrical 26 2 2
FIGURE 30-1 Task Planning Form Grading and excavation 16 1 2
Site concrete 34 2 3
The schedule duration may need to be longer to reflect Landscaping 6 1 1
curing time and other time it takes to complete a task where
labor is not working on the project. The calculation of dura-
tion is shown in the following example.
SAMPLE DURATIONS:
EXAMPLE 30-1 THE RESIDENTIAL GARAGE
It is estimated it will take 475 labor hours to frame the interior par- The estimated crew sizes and the durations for the residen-
titions of an office building. How long will it take a five-person tial garage drawings given in Appendix F are shown in
crew to complete the framing if they work 8 hours per day? Table 30-1. The labor hours are from Figure 26-7. These
Solution: The duration is calculated using Eq. (30-1) as follows: durations are based upon an eight-hour day and are
rounded up to the next full day.
b ⫽ 12!days
(475!lhr) 1!day
Duration ⫽ ⫽ (95!hr)a 䊏
(5!persons) 8!hr

CONCLUSION will it take a three-person crew to complete the framing


if they work 8 hours per day?
The estimate forms the basis of the schedule. The following 2. It is estimated that it will take 88 labor hours to set the
information is obtained from the estimate: the order in tile in a residence. How long will it take a two-person
which tasks need to take place; the method of construction; crew to complete the tile if they work 9 hours per day?
the required materials, labor, equipment, and subcontrac-
3. Prepare task-planning forms for the residence given in
tors; special coordination and inspections; and long-lead
Appendix F.
items. The duration is estimated by dividing the number of
labor hours from the estimate by the crew size. 4. Prepare task-planning forms for the West Street Video
project given in Appendix F.

PROBLEMS
1. It is estimated that it will take 265 labor hours to frame
the interior partitions of an office building. How long
C H A P T E R T H I R T Y- O N E

ETHICS

In this chapter you will be introduced to ethics as it relates to be neat, with spelling and grammatical errors kept to a min-
estimating. imum. Estimates should be carefully documented and kept
in an organized manner.
Each estimator should commit to expanding his or her

E
area of expertise and keeping current with updates. This is
thics as it relates to estimating may be defined by two
done by attending classes and conferences, reading trade
broad definitions: (1) a set of principles or rules that
journals and publications, discussing estimating issues with
members of a group agree to abide by and (2) a set of
other members of the profession, and discussing advances in
values or a guiding philosophy of the individual.
materials and construction methods with field personnel,
Professional groups, such as the American Society of
subcontractors, and suppliers.
Professional Estimators,1 have established a set of ethics by
Each estimator should commit to spending the time he
which their members agree to abide. These ethical princi-
or she is at work to promoting the goals of the company. In
ples, also known as canons, are shown in Figure 31-1.
Principles such as these set minimum standards of behavior
for members of the profession. Members of the industry
help to improve the image and trustworthiness of the profes-
sion by following these standards.
Besides the ethical principles established by professional
groups, each person has his or her set of ethical values or
guiding philosophy that affects how he or she behaves in a
given situation. Let’s look at a few of these.

WORK ETHIC
Work ethic relates to issues of how the estimator views the
work he or she does and includes (1) the completeness and
accuracy of bids he or she prepares, (2) the quality of his or
her work, (3) the commitment to expanding his or her skills,
and (4) how hard he or she works.
Each estimator should commit to preparing an estimate
that is as complete and as accurate as permitted by the time
allowed and the quality of the construction documents.
When there is insufficient time to prepare a complete and
accurate bid for a project, the estimator has the duty to dis-
cuss with his or her supervisor the situation and how the
time and document limitations will affect the bid.
Each estimator should commit to preparing work that FIGURE 31-1 ASPE Canon of Ethics (Courtesy of American
positively reflects on the estimating profession. Work should Society of Professional Estimators)
295
296 CHAPTER THIRTY-ONE

short, the employer should expect that the person will work data) confidential and making decisions that are in the best
hard to complete his or her duties as an estimator. interest of the employer rather than of oneself.
When there is a potential conflict of interest that may
lead to the estimator making a decision that is not in the best
BIDDING PRACTICES interest of the employer (for example, the estimator is pur-
Bidding practices relate to how the estimator handles bids. chasing materials from a family member), the estimator has
When bids are handled in a manner that is fair to the client the duty to disclose this conflict of interest and allow his or
and all subcontractors and suppliers, relationships of trust her work and decisions to be reviewed by someone else in
are established among the parties. This trust results in better the company. Conflicts of interest occur whenever an esti-
working relationships among the parties and often results in mator does business with a family relation or a business he
obtaining more work. When bids are handled in an unfair or she has an interest in or when he or she accepts gifts or fa-
manner, or when it appears that bids were handled in an un- vors from a company with which the estimator’s company
fair manner even if they were handled fairly, mistrust is cre- does business. It is not unethical to be in a situation in which
ated among parties, and working relations are strained. a conflict of interest occurs provided everything is handled
The best way to ensure that bids are handled in a fair in an open, honest manner and the company’s interests are
manner is to establish a policy regarding how bids are han- held above the interest of the estimator. For the conflict of
dled and follow it. In addition, the criteria for bid selection interest to be handled in an open manner, the potential con-
should be made available to all subcontractors and suppliers flict must be disclosed.
so they have an understanding of what they must do to be Employers should be able to expect that their employees
the selected bidder. The practices of bid rigging and bid are honest. Employers who expect an employee to steal, cheat,
shopping must be avoided. and lie for them should also expect the employee to steal from,
lie to, and cheat them. Honesty is truly the best policy.

LOYALTY TO EMPLOYER
ETHICAL DILEMMAS
Each estimator has the duty to be loyal to his or her employer,
as long as the employer is behaving in an ethical manner. Ethical dilemmas occur when the company’s and one’s per-
Estimators are not obligated to support or be involved in ille- sonal ethics conflict or when one’s personal ethics as they re-
gal or unethical behavior in the name of loyalty. Being loyal late to a specific situation are in conflict. Each person must
to an employer includes keeping the employer’s proprietary decide how he or she will act when confronted with an ethi-
information (such as bidding practices and historical cost cal dilemma.

CONCLUSION 5. A long-time subcontractor is the second-lowest bidder,


whereas an unknown subcontractor is the low bidder.
Ethics is both a set of principles or rules that members of a Your boss asks you to call the long-time subcontractor
group agree to abide by and a set of values or a guiding phi- and ask him or her to meet the price of the low bidder.
losophy of the individual. The personal ethics of the estima- What do you do? How would having a company policy
tor include his or her work ethic (how he or she views the that established the procedure for selecting subcontrac-
work), bidding practices (how bids are handled), and loyalty tors affect your decision?
to the employer. 6. You are responsible for the budget on a cost-plus con-
struction project. A supplier or subcontractor offers to
PROBLEMS overbill the client and split the difference with your
company. What do you do?
1. A long-time supplier or subcontractor asks you to share 7. You work for a subcontractor and are responsible for
a competitor’s pricing or quantities before he or she preparing the subcontractor’s bids. A general contractor
submits a bid or before the bid closes. What do you do? has a small project and asks you how much you would
2. A long-time supplier or subcontractor asks you what charge to do the work on the side. What do you do?
price they have to beat to get the work. What do you do?
3. A salesperson offers you a gift in order to influence your
purchasing decision. What do you do?
REFERENCE
4. A long-time subcontractor is the second-lowest bidder, 1. For more information on the American Society of Professional
whereas an unknown subcontractor is the low bidder. Estimators, visit www.ASPEnational.org.
Whom do you choose? Why?
P A R T F I V E

ADVANCED ESTIMATING
WITH EXCEL

Chapter 32 Converting Existing Forms


Chapter 33 Creating New Forms
Chapter 34 Proposals and Beyond

I
n this section, you will learn how to take advantage of the full features of
Excel, including how to convert existing forms to Excel, create new forms
in Excel, prepare proposals using Excel, and incorporate error checking
in your spreadsheets.
C H A P T E R T H I R T Y- T W O

CONVERTING EXISTING FORMS

In this chapter you will learn the procedures for converting ex- CREATING THE LAYOUT
isting paper forms to spreadsheets, how to automate a series of
commands or steps using macros, and three methods of adding The first step is to create the form’s layout in Excel. For
error protections to a worksheet. The chapter will take you step both the Detail and the Summary worksheets, this was
by step through the process of converting two paper forms (the done in Chapter 3, and they were saved as Chapter 03.xlsx
Detail worksheet from Figure 3-24 and the Summary work- in the Excel Exercise folder. If you have not completed
sheet from Figure 2-2) into computer spreadsheets and the cre- Exercises 3-1 through 3-5, 3-8, and 3-9 from Chapter 3, you
ation of a macro. should do so now.

ADDING FORMULAS

T he easiest way to create a computerized estimating


form is to create it from an existing paper form. This
is because the user already has established a layout
for the form and understands how to perform the calcula-
tions. There are five steps needed to convert existing forms.
The second step is to add formulas into the Excel worksheet.
If you have completed Exercise 3-7 and the sidebars found in
some of the preceding chapters, you have already had an op-
portunity to create some formulas. In the next exercise, you
will add formulas to the Summary worksheet created in
First, create the form’s layout in Excel. Second, add the for-
Chapter 3. The formulas for the Detail worksheet are added
mulas into Excel. Third, automate the worksheets with
using macros. Macros are discussed in the next section.
macros. Fourth, test the spreadsheets to ensure that they are
free of errors. Fifth, add protection against errors. The
process is shown in Figure 32-1.
Exercise 32-1

In this exercise you will add formulas to the Summary work-


sheet created in Chapter 3. Many of the formulas discussed in
the individual steps of this exercise are shown in Figure 32-2.
The formulas are set up using the following steps:
1. Open Chapter 03, the workbook you created in Chapter 3.
2. Save the workbook as Chapter 32.xlsx by selecting the
File tab (the Microsoft Office button for Excel 2007),
clicking on Save As in the left pane to bring up the Save
As dialogue box, selecting the Excel Exercises folder in
the left pane (Save in: dropdown box for Excel 2007),
typing Chapter 32 in the File Name text box, and click-
ing on the Save button.
3. Make sure the spreadsheet is open to the Summary
worksheet. If not, click on the Summary tab to open the
FIGURE 32-1 Process for Converting Forms to Excel Summary worksheet.
298
Converting Existing Forms 299

A B C D E F G H
1 Code Description Materials Labor Equipment Subcontract Total
2 01-000 GENERAL REQUIREMENTS
3 01-300 Supervision =SUM(D3:G3)
4 01-500 Temporary Utilities =SUM(D4:G4)
5 01-510 Temporary Phone =SUM(D5:G5)
6 01-520 Temporary Facilities =SUM(D6:G6)
7
8 01-700 Clean-Up =SUM(D7:G7)
9 02-000 EXISTING CONDITIONS
10
11 02-400 Demolition =SUM(D10:G10)
116 33-000 UTILITIES
117 33-100 Water Line =SUM(D117:G117)
118 33-300 Sanitary Sewer =SUM(D118:G118)
119 33-400 Storm Drain =SUM(D119:G119)
120 33-500 Gas Lines =SUM(D120:G120)
121 33-700 Power Lines =SUM(D121:G121)
122 33-800 Telephone Lines =SUM(D122:G122)
123 SUBTOTAL =SUM(D2:D122) =SUM(E2:E122) =SUM(F2:F122) =SUM(G2:G122) =SUM(H2:H122)
124 Building Permit =SUM(D124:G124)
125 Bond =SUM(D125:G125)
126 SUBTOTAL =SUM(D123:D125) =SUM(E123:E125) =SUM(F123:F125) =SUM(G123:G125) =SUM(H123:H125)
127 Profit and Overhead Markup
128 Profit and Overhead =D126*D127 =E126*E127 =F126*F127 =G126*G127 =SUM(D128:G128)
129 TOTAL =D126+D128 =E126+E128 =F126+F128 =G126+G128 =H126+H128
130 =SUM(D129:G129)

FIGURE 32-2 Formulas for Summary Worksheet

Next, total the rows using the following steps: Next, enter the formulas used to calculate the profit and over-
head markup found in Row 128 using the following steps:
4. Type =Sum(D3:G3) in Cell H3, and press the Enter key
to sum Row 3. A dash will appear indicating that the 11. Type =D126*D127 in Cell D128, and press the Enter key
sum is zero. to calculate the profit and overhead for the materials
column.
5. Copy Cell H3 to Cells H4 through H7, H10, H13
through H20, H23, H26 through H29, H32 through 12. Copy Cell D128 to Cells E128 through G128 to calculate
H38, H41 through H51, H54 through H60, H62 the profit and overhead for the labor, equipment, and
through H68, H71 through H74, H77, H80, H83, H86, subcontract columns. Do not copy Cell D128 to Cell
H89, H92, H95, H98, H101, H102, H105 through H114, H128.
H117 through H122, H124, H125, and H128 to sum the Next, you will enter the formulas used to calculate the total
total for each of these rows. found in Row 129 using the following steps:
6. When you copied Cell H3 to Cells H122, H125, and
13. Type =D126+D128 in Cell D129, and press the Enter
H128, the borders under these cells was erased.
key to calculate the total for the materials column.
Underline Cells H122, H125, and H128 by highlighting
the cells and clicking the Bottom Border button (shown 14. Copy Cell D129 to Cells E129 through H129 to calculate
in Figure 3-46) in the Font group on the Home menu the total for the labor, equipment, subcontract, and total
tab. If another border is shown in the Borders button, columns.
select the correct border by clicking on the small arrow 15. As a check of the totals, type =Sum(D129:G129) in Cell
to the right of the Borders button and selecting the H130, and press the Enter key to calculate the total.
Bottom Border from the Borders popup menu. Cells H129 and H130 should contain the same value.
Next, enter the formulas used to calculate the subtotals 16. Save the workbook by clicking on the Save button on
found in Row 123 using the following steps: the Quick Access toolbar or by typing Ctrl+S.

7. Type =Sum(D2:D122) in Cell D123, and press the Enter


key to sum the materials column. Chapter 25 looked at basing the building permit and
bond costs on the total estimate of the bid using iteration.
8. Copy Cell D123 to Cells E123 through H123 to sum the
Because the building permit and bond costs are based on the
labor, equipment, subcontract, and total columns.
total estimate and the total estimate is based on the building
Next, enter the formulas used to calculate the subtotals permit and bond costs, a circular reference is created. To
found in Row 126 using the following steps: solve a circular reference, Excel must be allowed to perform
the calculations a number of times, each time getting closer
9. Type =Sum(D123:D125) in Cell D126, and press the to the correct answer. This is known as iteration. To allow
Enter key to calculate the subtotal. Excel to use iteration to solve circular references, the user
10. Copy Cell D126 to Cells E126 through H126 to calculate clicks on the File tab (the Microsoft Office button for Excel
the subtotal for the labor, equipment, subcontract, and 2007), clicks on Options (Excel Options for Excel 2007) to
total columns. bring up the Excel Options dialogue box, selects Formulas
300 CHAPTER THIRTY-TWO

FIGURE 32-3 Change Options Related to Formulas Calculation, Performance, and Error Handling Tab

in the left pane to display the Change options related to for- The table was generated using Table 25-2 and calculating
mulas calculation, performance, and error handling in the the bonding costs for the upper end of the previous range. For
right pane (shown in Figure 32-3), and under the Calculation example, a $500,000 bond costs $5,125 ($50,000 ⫻ 0.015 ⫹
options heading checks the Enable Iterative calculation $50,000 ⫻ 0.0125 ⫹ $150,000 ⫻ 0.01 ⫹ $250,000 ⫻ 0.009);
check box. The maximum number of iterations is set in the therefore, the cost of a bond in the range of $500,001 to
Maximum iterations: text box and the maximum change in $1,000,000 is 0.80% on any amount over $500,000 plus
the Maximum change: text box. For example, if the maxi- $5,125 (the rate on the first $500,000).
mum iterations is set to five and the maximum change is set This exercise is completed by the following steps:
to one, Excel will stop performing calculations after five itera-
1. Make sure that Chapter 32, the workbook created in
tions or after the change in values resulting from the last iter-
Exercise 32-1, is open.
ation was less than one, whichever comes first. For use on the
summary sheet, five iterations and a maximum change of one 2. Make sure that the spreadsheet is open to the Summary
is generally adequate for bids under $1,000,000. Setting the worksheet.
number of iterations higher and the maximum change lower Next, Excel needs to be set to allow it to perform iterations
will result in longer calculation times. In the next exercise you using the following step:
will incorporate the bond cost into the Summary worksheet.
3. Click on the File tab (the Microsoft Office button for
Excel 2007), click on Options (Excel Options for Excel
Exercise 32-2 2007) to bring up the Excel Options dialogue box, select
Formulas in the left pane to display the Change options
In this exercise you will add the bond rates from Table 25-2 to related to formulas calculation, performance, and error
the Summary worksheet modified in Example 32-1. To simplify handling in the right pane, under the Calculation op-
the calculations, Table 25-2 is rewritten as shown in Table 32-1. tions heading check the Enable Iterative calculation

TABLE 32-1 Sample Bond Schedule


Total Estimate ($) Bond Rate
0 to 50,000 1.50
50,001 to 100,000 1.25% on amount over $50,000 plus $750
100,001 to 250,000 1.00% on amount over $100,000 plus $1,375
250,001 to 500,000 0.90% on amount over $250,000 plus $2,875
500,001 to 1,000,000 0.80% on amount over $500,000 plus $5,125
1,000,001 plus 0.75% on amount over $1,000,000 plus $9,125
Converting Existing Forms 301

AUTOMATING WITH MACROS


The third step is to automate the spreadsheets with macros.
As we saw in Chapter 26, the following mathematical rela-
tionships exist on the Detail worksheet:
Column!E ⫽ Column!B ⫻ Column!D
Column!G ⫽ Column!B ⫻ Column!F
Column!I ⫽ Column!G ⫻ Column!H
Column!K ⫽ Column!G ⫻ Column!J
Column!L ⫽ Column!E ⫹ Column!I ⫹ Column!K
Each time the user adds a row to the Detail worksheet,
he or she will need to add these formulas to Columns E, G, I,
K, and L. Not only would this be time consuming, but would
also require the user to test each formula. Alternatively, the
user could copy the formulas from one row to another row.
FIGURE 32-4 Logic for the Bond Formula Although this is less time consuming, it is still slower than
using a macro and is prone to errors. Macros greatly reduce
the possibility of errors and increase efficiency.
When the user records a macro, he or she creates an ex-
check box, type 5 in the Maximum iterations: text box, ecutable code that can be infected by computer viruses.
type 1 in the Maximum change: text box, and click the Running a macro with a virus can spread the viruses and
OK button to close the Options dialogue box. This set- their damage to other files on the user’s computer. To mini-
ting will need to be changed on any computer that runs mize the risk of infection, the user should only run macros
this worksheet or when you get a circular reference he or she creates or macros from a trusted source.
warning. Excel allows the user to set the security level for macros
so that Excel (1) disables all macros without notifying the
The logic used to calculate the bond is shown in Figure 32-4.
user, (2) disables all macros but notifies the user and gives
Next, you will enter the bond formula as follows: him or her the option to run the macro, (3) disables all
macros except those digitally signed, or (4) enables all
4. Type the following formula into Cell D125:
macros. When Excel is set to disable all macros with notifi-
=IF(H129<50000,H129*0.015, cation given to the user, a Security Warning indicating that
IF(H129<100000,(H129-50000)*0.0125+750, the macro has been disabled appears below the menu rib-
IF(H129<250000,(H129-100000)*0.01+1375, bon. This warning is shown in Figure 32-5 (Figure 32-6 for
Excel 2007). To enable the macro in Excel 2010, the user
IF(H129<500000,(H129-250000)*0.009+2875,
clicks on Enable Content. Once you have enabled a docu-
IF(H129<1000000,(H129-500000)*0.008+5125,
ment, Excel 2010 will remember it and you will not have to
(H129-1000000)*0.0075+9125))))) enable it again.
5. Save the workbook by clicking on the Save button on To enable the macro in Excel 2007, the user clicks on the
the Quick Access toolbar or by typing Ctrl+S. Options... button next to the warning to bring up the
Microsoft Office Security Options dialogue box (shown in

FIGURE 32-5 Excel 2010 Security Warning


302 CHAPTER THIRTY-TWO

FIGURE 32-6 Excel 2007 Security Warning

Figure 32-7). From the Microsoft Office Security Options di- settings in the right pane, where he or she can select to (1)
alogue box, the user may select Help protect me from un- Disable all macros without notification, (2) Disable all
known content (recommended) to keep the macro disabled macros with notification, (3) Disable all macros except digi-
or select Enable this content to enable the macro. The user tally signed macros, or (4) Enable all macros (not recom-
must click on the OK button to close the Microsoft Office mended; potentially dangerous code can run). The Trust
Security Options dialogue box. Center dialogue box is shown in Figure 32-8. The user closes
To set the level of security, the user clicks on the File tab the Trust Center dialogue box by clicking on the OK button.
(the Microsoft Office button for Excel 2007), clicks on Macros are written in a complex programming lan-
Options (Excel Options for Excel 2007) to bring up the guage; however, macros can be recorded as you would record
Excel Options dialogue box, selects Trust Center in the left your voice on a tape recorder, eliminating the need to learn a
pane to display the Help keep your documents safe and your programming language. When recording a macro, you
computer secure and healthy in the right pane, and under record the actions (key strokes, cursor movements, and so
the Microsoft Office Excel Trust Center clicks on the Trust forth) taken while recording the macro. These actions can be
Center Settings . . . button to bring up the Trust Center dia- repeated by playing back the macro.
logue box. From the Trust Center dialogue box, the user The actions recorded by macros can be absolute or rela-
clicks on Macro Settings in the left pane to view the macro tive. Absolute macros are always executed in the same location

FIGURE 32-7 Microsoft Office Security Options Dialogue Box


Converting Existing Forms 303

FIGURE 32-8 Trust Center Dialogue Box

FIGURE 32-9 View: Macros Button

on the spreadsheet, regardless of the location of the cursor Relative References is shaded, macros will be recorded with
when the macro is executed. For example, if an absolute relative references. Relative references are turned off the same
macro was recorded starting in Cell A1, it will always move to way they are turned on.
Cell A1 before executing the macro. Relative macros are exe- To record a macro, the user clicks on the View menu tab,
cuted relative to the current position of the cursor. For exam- clicks on the arrow below the Macros button (shown in Figure
ple, if a relative macro was recorded with a start point in Cell 32-9), and selects Record Macro... from the popup menu
A1 and then immediately moved the cursor to Cell A2, when- (shown in Figure 32-10) to bring up the Record Macro dia-
ever the macro was executed it would start by moving the cur- logue box shown in Figure 32-11. The name of the macro is
sor one cell below the active cell. If the active cell were G17, the typed into the Macro name: text box. Each macro must have a
macro would move the active cell to G18. To select between unique name. Spaces may not be used in the name. A shortcut
absolute and relative references, the user clicks on the View key can be assigned to a macro by typing a key into the
menu tab, clicks on the arrow below the Macros button Shortcut key: Ctrl+ text box. The macro can be stored in one
(shown in Figure 32-9), and selects Use Relative References of three places—this workbook (the workbook you are work-
from the popup menu (shown in Figure 32-10). When the Use ing on), a new workbook, or a personal macro workbook—by
selecting the place to store the macro in the Store macro in:
dropdown box. Macros that are used for a single workbook
should be stored in the workbook, whereas macros that are
used in multiple workbooks, such as inserting your name and
title, should be stored in a personal workbook. A description
of the macro is entered in the Description text box.
After completing the information on the record dia-
FIGURE 32-10 Use Relative References Button logue box, the user begins recording the macro by clicking
304 CHAPTER THIRTY-TWO

the OK button. The user then enters the keystrokes, cursor


movements, and so forth that are to be recorded. The user
stops the recording of the macro by clicking on the View
menu tab, clicking on the arrow below the Macros button
(shown in Figure 32-9), and selects Stop Recording from the
popup menu (shown in Figure 32-12).
Workbooks containing macros must be saved as an
Excel macro-enable workbook. This is done by selecting the
File tab (the Microsoft Office button for Excel 2007), click-
ing on Save As in the left pane to bring up the Save As dia-
logue box, and selecting Excel Macro-Enabled Workbook
(.xlsm) from the Save as Type dropdown box. The Save As
dialogue box is shown in Figure 32-13.
The following exercise shows how to record a macro.

FIGURE 32-11 Record Macro Dialogue Box


Exercise 32-3

In this exercise you will record a macro to add the formulas


to a row on the Detail worksheet and assign it to the Ctrl+E
keys so that it can be executed from the keyboard. Because
this macro needs to work on all rows in the spreadsheet, the
macro will need to be a relative macro. The macro is to be
executed from Column D and will move the cursor down a
row every time it is executed, so it can be executed over and
FIGURE 32-12 Stop Recording
over without the user having to move the cursor down a
row. In addition, the macro will set the default labor rate to

FIGURE 32-13 Save As Dialogue Box


Converting Existing Forms 305

$18.00 per hour. The macro is created using the following 11. With the cursor on Cell D5, type Ctrl+E, and the for-
steps: mulas typed on Row 4 should be repeated on Row 5,
except that they should reference Row 5 rather than
1. Make sure that Chapter 32, the workbook modified in
Row 4. For example, the formula in Cell E5 will read
Exercise 32-2, is open.
=B5*D5 rather than =B4*D4. The cursor should have
2. Click on the Detail tab to move to the Detail worksheet moved to Cell D6. The formulas for this example are
and place the cursor on Cell D4. shown in Figure 32-14. The formulas on Row 4 were en-
3. Make sure that the macro is set to use relative references tered while creating the macro; whereas the formulas on
by clicking on the View menu tab, clicking on the arrow Row 5 were entered by executing the macro.
below the Macros button (shown in Figure 32-9), and 12. Save the workbook as a macro-enabled workbook by se-
making sure that Use Relative References is highlighted lecting the File tab (the Microsoft Office button for
as shown in Figure 32-10. If it is not highlighted, click Excel 2007), clicking on Save As in the left pane to bring
on Use Relative Reference to highlight it. up the Save As dialogue box, and selecting Excel Macro-
4. Click on the arrow below the Macros button (shown in Enabled Workbook (.xlsm) from the Save as Type drop-
Figure 32-9) and select Record Macro... from the down box. Do not change the name or location of the
popup menu (shown in Figure 32-10) to bring up the workbook. Click on OK to save the file.
Record Macro dialogue box.
5. Type Extension in the Macro name: text box and e in the
Shortcut key: Ctrl+ text box. Macros are deleted by clicking on the View menu tab
6. Type This macro adds the formulas for an individual line and (1) clicking on the Macros button (shown in Figure 32-9)
on the Detail worksheet. in the Description: text box. or (2) clicking on the arrow below the Macros button (shown
The Record Macro dialogue box should be similar to in Figure 32-9) and selecting View Macros from the popup
Figure 32-11. menu (shown in Figure 32-10) to bring up the Macro dia-
logue box shown in Figure 32-15. The user selects the macro
7. Click the OK button to start recording the macro.
to be deleted and clicks on the Delete button. The user is
You will now record the key strokes and cursor movements asked if he or she wants to delete the macro. The macro is
that make up the macro. deleted by clicking on the Yes button.
8. Enter the formulas in Table 32-2 into the specified cells.
After entering the formula for a cell, press the Enter key
to complete the formula.
9. After completing the entries in Table 32-2, move the
cursor to Cell D5.
10. Click on the View menu tab, click on the arrow below
the Macros button (shown in Figure 32-9), and select
Stop Recording from the popup menu (shown in
Figure 32-12) to end the macro.

TABLE 32-2 Data for Cells


E4 =B4*D4
G4 =B4*F4
H4 18
I4 =G4*H4
K4 =G4*J4
L4 =E4+I4+K4
FIGURE 32-15 Macro Dialogue Box

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
3
4 =B4*D4 =B4*F4 18.00 =G4*H4 =G4*J4 =E4+I4+K4
5 =B5*D5 =B5*F5 18.00 =G5*H5 =G5*J5 =E5+I5+K5

FIGURE 32-14 Formulas for Exercise 32-3


306 CHAPTER THIRTY-TWO

TESTING THE WORKSHEETS 3. Click on the Summary tab.


4. Hide rows 9 through 115 by selecting (highlighting) the
After creating formulas and macros, the user needs to test
rows, right clicking on the selected rows, and selecting
the formulas to verify that they are working correctly. To do
Hide from the popup menu shown in Figure 32-17.
this, the user enters data with a known result into the for-
mula or macro to verify that it is producing the correct re- First, verify the totals in Column H and Row 123 using the
sults. One at a time, each cell should be changed to verify following steps:
that the formula works under all circumstances. This is
5. Type 10 in Cell D3. Cells H3, D123, and H123 should all
shown in the following examples.
equal 10.
6. Type 20 in Cell E3. Cells H3 and H123 should equal
Exercise 32-4 30, Cell D123 should equal 10, and Cell E123 should
equal 20.
In this exercise you will verify the formulas entered into the
7. Type 30 in Cell F3. Cells H3 and H123 should equal 60,
Summary worksheet in Exercises 32-1 and 32-2. For this
Cell D123 should equal 10, Cell E123 should equal 20,
worksheet, the formula created to sum the rows, the formula
and Cell F123 should equal 30.
created to sum the material, labor, equipment, subcontract,
and equipment columns, and the formulas created to total 8. Type 40 in Cell G3. Cells H3 and H123 should equal
the bid are verified. The verification process is done with the 100, Cell D123 should equal 10, Cell E123 should equal
following steps. 20, Cell F123 should equal 30, and Cell G123 should
equal 40.
1. Make sure that macro-enabled version of Chapter 32
9. Type 100 in Cells D122 through G122. Cell H3 should
(Chapter 32.xlsm), the workbook modified in Exercise
equal 100, Cell H122 should equal 400, Cell D123
32-3, is open. If the file extensions are not displayed, hold
should equal 110, Cell E123 should equal 120, Cell F123
your cursor over the file names and a popup box (similar
should equal 130, Cell G123 should equal 140, and Cell
to Figure 32-16) will appear that identifies the file type.
H123 should equal 500.
2. If the Security Warning appears, click on the Enable
Content button. For Excel 2007, click on the Option... By completing these actions we have verified the original
button to open the Microsoft Office Security Options formula that summed the rows and one of the copied for-
dialogue box (shown in Figure 32-7), select the Enable mulas. We have also verified the formulas that summed the
this content radio button, and click on the OK button column by entering data in the top and bottom of the for-
to enable the macros written in Exercise 32-3. mula. Next, verify the formulas that create the total bid.
10. Type 150 in Cell D124. This will enter the cost of the
building permit.
11. Type 40 in Cell D127, 30 in Cell E127, 20 in Cell F127,
and 10 in Cell G 127. This will enter the profit markup
FIGURE 32-16 Popup Box for materials, labor, equipment, and subcontract.
12. Verify that the cells in the Summary worksheet have the
same values shown in Figure 32-18.
13. Exit the workbook without saving the changes.

A B C D E F G H
1 Code Description Materials Labor Equipment Subcontract Total
2 01-000 GENERAL REQUIREMENTS
3 01-300 Supervision 10 20 30 40 100
4 01-500 Temporary Utilities -
5 01-510 Temporary Phone -
6 01-520 Temporary Facilities -
7 01-700 Clean-Up -
116 33-000 UTILITIES
117 33-100 Water Line -
118 33-300 Sanitary Sewer -
119 33-400 Storm Drain -
120 33-500 Gas Lines -
121 33-700 Power Lines -
122 33-800 Telephone Lines 100 100 100 100 400
123 SUBTOTAL 110 120 130 140 500
124 Building Permit 150 150
125 Bond 13 13
126 SUBTOTAL 273 120 130 140 663
127 Profit and Overhead Markup 40.0% 30.0% 20.0% 10.0%
128 Profit and Overhead 109 36 26 14 185
129 TOTAL 382 156 156 154 848
130 848

FIGURE 32-17 Popup Menu FIGURE 32-18 Results for Example 32-4
Converting Existing Forms 307

A B C D E F G H I J K L
1 MATERIALS LABOR EQUIPMENT
2 ITEM QUANTITY $/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST TOTAL
3 33-100 Water Line
4 Bedding 23 cyd 19.78 455 0.30 6.90 18.07 125 50.80 351 930
5 10" water line 150 ft 12.46 1,869 0.26 39.00 18.07 705 50.80 1,981 4,555

FIGURE 32-19 Results for Exercise 32-5

Exercise 32-5 ADDING ERROR PROTECTION


This chapter looks at three ways of adding error protection.
In this exercise you will verify the macro created for the They are conditional formatting, data validation, and pro-
Detail worksheet in Exercise 32-2 using the following steps: tecting the worksheet. Let’s look at conditional formatting.
1. Open Chapter 32.xlsm, the workbook modified in
Exercise 32-3.
Conditional Formatting
2. Click on the Detail tab to move to the Detail worksheet.
Conditional formatting allows the user to set the font,
3. Enter the data shown in Table 32-3 into the specified
border, color, and pattern for a cell by comparing the value
cells.
or formula in a cell to a value, range of values, or other
After you complete the entries in Table 32-3, the spreadsheet cells. Conditional formatting is very useful for marking
should look like Figure 32-19. cells that have unexpected values. For example, in the
Summary worksheet, Cell H123 should equal the sum of
4. Exit the workbook without saving the changes.
Cells D123 through G123. If this is not the case, it would
be very helpful to change the background color of Cell
H123 to make it very apparent that the cells are not equal
TABLE 32-3 Data for Cells to each other.
The user sets the conditional formatting for a cell by
A3 33-100 Water Line
placing the cursor in the cell or cells to be conditionally
A4 Bedding formatted, clicks on the Home menu tab, clicks on the
B4 23 Conditional Formatting button in the Styles group
C4 cyd (shown in Figure 32-20), places the cursor over the
Highlight Cell Rules from the popup menu (shown in
D4 19.78
Figure 32-21), and selects the type of rules to be used in
F4 0.30 the conditional formatting from the popup menu (shown
H4 18.07
J4 50.80
A5 10 – water line
B5 150
C5 ft
D5 12.46
F5 0.26
H5 18.07
J5 50.80

FIGURE 32-21 Conditional


FIGURE 32-20 Home: Conditional Formatting Button Formatting Pop Menu
308 CHAPTER THIRTY-TWO

when opening the New Rule Formatting dialogue box in the


manner described above. In the left dropdown box, the user
selects whether he or she wants to compare the cell’s value or
other property. For our example we are going to compare the
cells value. In the next dropdown box (the second box from
the left) the user selects the type of comparison to make by
selecting from the following: between, not between, equal
to, not equal to, greater than, less than, greater than or
equal to, and less than or equal to. Based on the selection in
the second box from the left, one or two boxes will appear to
the right of this box. In these boxes the user enters cells, for-
mulas, or values to be used in the comparison. Next, the user
clicks on the Format... button to bring up the Format Cells
dialogue box shown in Figure 32-24. The user then selects
the desired formatting to use in conjunction with the condi-
tional formatting and clicks on the OK button to close the
Format Cells dialogue box.
Multiple rules for one cell can be written using the
above procedures. To select the order the rules are applied,
edit a rule, or to delete a rule, the user clicks on the Home
menu tab, clicks on the Conditional Formatting button in
the Styles group (shown in Figure 32-20), and clicks on
FIGURE 32-22 Cell Rules Popup Menu
Manage Rules... from the popup menu (shown in Figure
32-21) to bring up the Conditional Formatting Rules
Manager dialogue box (shown in Figure 32-25). Only the
in Figure 32-22). The user may select from one of the pre- rules that apply to the selected cell will be shown. From the
set rules or create their own rule by clicking on More Conditional Formatting Rules Manager dialogue box the user
Rules... to bring up the New Rule Formatting dialogue box can add a new rule by clicking on the New Rule... button,
(shown in Figure 32-23). We will look at creating our own edit the selected rule by clicking on the Edit Rule... button,
rules. or delete the selected rule by clicking on the Delete Rule
From the New Rule Formatting dialogue box, the user button. When there are two or more rules, the user can se-
selects the type of rule in the Select a Rule Type: box. We will lect the order which the rules are applied by highlight the
limit our discussion to the Format only cells that contain rule to move and clicking on the Move Up or Move Down
rule, which is the rule type that is automatically selected buttons.

FIGURE 32-23 New Formatting Rule Dialogue Box


Converting Existing Forms 309

FIGURE 32-24 Fill Tab of the Format Cells Dialogue Box

FIGURE 32-25 Conditional Formatting Rules Manager Dialogue Box

Exercise 32-6 appears, click on the Enable Content button to enable


the macro. For Excel 2007, click on the Options... but-
In this exercise you will set the conditional formatting for ton next to the warning to bring up the Microsoft Office
Cell H123 so it turns red if the value in Cell H123 (the sum Security Options dialogue box, select Enable this con-
of Cells H2 through H122) does not equal the sum of Cells tent, and click on the OK button.
D123 through G123 using the following steps: 2. Select the Summary worksheet.
1. Make sure that Chapter 32.xlsm, the workbook modi- 3. Place the cursor in Cell H123, click on the Home menu
fied in Exercise 32-3, is open. If the Security Warning tab, click on the Conditional Formatting button in the
310 CHAPTER THIRTY-TWO

A B C D E F G H
1 Code Description Materials Labor Equipment Subcontract Total
116 33-000 UTILITIES 22
117 33-100 Water Line -
118 33-300 Sanitary Sewer -
119 33-400 Storm Drain -
120 33-500 Gas Lines -
121 33-700 Power Lines -
122 33-800 Telephone Lines -
123 SUBTOTAL 22 - - - -
124 Building Permit -
125 Bond 0 0
126 SUBTOTAL 22 - - - 0
127 Profit and Overhead Markup
128 Profit and Overhead - - - - -
129 TOTAL 22 - - - 0
130 22

FIGURE 32-26 Spreadsheet for Exercise 32-6

Styles group (shown in Figure 32-20), place the cursor Data Validation
over the Highlight Cell Rules from the popup menu
(shown in Figure 32-21), and click on More Rules... to Data validation allows the user to set limits on the data en-
bring up the New Rule Formatting dialogue box (shown tered into a cell. For example, using data validation, the
in Figure 32-23). user may limit the values in a cell to a positive number.
The user may limit the cell contents to a whole number, a
4. Select Cell Value from the first dropdown box and not
decimal number, a list, dates, a time, or a text of a given
equal to from the second dropdown box and type
length. Numeric data may be limited to values between
=D123+E123+F123+G123 in the text box.
two values, not between two values, equal to a value, not
5. Click on the Format... button to bring up the Format equal to a value, greater than a value, less than a value,
Cells dialogue box (shown in Figure 32-24), click the greater than or equal to a value, or less than or equal to a
Fill tab, select the color red, and click the OK button. value. Values may be fixed, be a value located in a cell, or
6. The Conditional Formatting dialogue box should ap- calculated from a formula.
pear as shown in Figure 32-23, with a red background The user sets these limits by clicking on the Data menu
for the Preview box. tab, clicking on the Data Validation button in the Data Tools
7. Click the OK button to complete the formatting. group (shown in Figure 32-27) to bring up the Data
Validation dialogue box, and selecting the Settings tab. The
In the Summary worksheet there are rows that represent the Settings tab of the Data Validation dialogue box is shown in
division headings. One example is Row 116, which is the di- Figure 32-28.
vision heading of the Utilities division. As such, costs should From the Data Validation dialogue box the user sets the
not be entered on this row. If costs are entered on this row, type of validation to be used in the Allow: dropdown box, se-
they will not be totaled in the Total column (Column H) be- lects the type of comparisons to be made in the Data: drop-
cause the row summing function was not copied to this row. down box, and the values, functions, or cells to compare it to
We will enter a number onto this row to verify the condi- in the remaining boxes, which will change based on what is
tional formatting. selected in the Allow: dropdown box.
8. Enter 22 in Cell D116. Cell H123 should now be red and In addition to making the comparison, the user may
with a dash in the cell indicating that it is equal to zero. also create a custom prompt message on the Input Message
Cell D123 should be equal to 22. The spreadsheet tab and create a custom error message on the Error Alert tab.
should look like Figure 32-26. A custom prompt message, which will appear when the cell
is selected, is created by selecting the Input Message tab,
9. Delete the contents of Cell D116 by selecting Cell D116
checking the Show input message when cell is selected
and pressing the Delete key.
check box, typing the title of the message in the Title: text
10. Save the workbook. box, and typing the message in the Input message: text box.

FIGURE 32-27 Data: Data Validation Button


Converting Existing Forms 311

FIGURE 32-28 Settings Tab of the Data Validation Dialogue FIGURE 32-30 Error Alert Tab of the Data Validation
Box Dialogue Box

The Input Message tab of the Data Validation dialogue box is Exercise 32-7
shown in Figure 32-29.
A custom error message is created by selecting the Error In this exercise you will limit the profit and overhead markups
Alert tab, checking the Show error alert after invalid data is on the Summary worksheet to between 0% and 50% using
entered check box, typing the title of the message in the Title: data validation. This is done by the following steps:
text box, and typing the message in the Error message: text
box. The user may select between a stop, warning, and infor- 1. Make sure that Chapter 32.xlsm, the workbook modified
mation error message in the Style: dropdown box. The stop in Exercise 32-6, is open. If necessary, enable the macros.
error message does not let the user enter a value that does not 2. Place the cursor in Cell D127, click on the Data menu
meet the validation criteria. The warning error message will tab, and then click on the Data Validation button in the
ask the user if he or she wants to continue even though the Data Tools group (shown in Figure 32-27) to bring up
data does not meet the validation criteria. Although the in- the Data Validation dialogue box.
formation error message will inform the user that he or she 3. Select the Settings tab, select Decimal from the Allow:
has entered data that does not meet the validation criteria, it dropdown box, select between from the Data: drop-
still makes the change. The Error Alert tab of the Data down box, and type 0 in the Minimum: box and 0.5 in
Validation dialogue box is shown in Figure 32-30. the Maximum: box. The Data Validation box should
now appear as in Figure 32-28.
4. Select the Input Message tab, check the Show input
message when cell is selected check box, type Profit and
Overhead Markup in the Title: text box, and type Must
be between 0% and 50%. in the Input message: text box.
The Data Validation box should now appear as Figure
32-29. When the cursor is placed in Cell D127, the mes-
sage in Figure 32-31 will appear next to the cell.
5. Select the Error Alert tab, check the Show error alert
after invalid data is entered check box, select Stop from
the Style: dropdown box, type Error in the Title: text box,
and type Profit and overhead markup must be between 0%
and 50%. in the Error message: text box. The Data
Validation box should now appear as in Figure 32-30.
When numbers greater than 50% (0.50) or less than zero

FIGURE 32-29 Input Message Tab of the Data Validation


Dialogue Box FIGURE 32-31 Input Message Created in Exercise 32-7
312 CHAPTER THIRTY-TWO

14. Select Cells E127, F127, and G127, right click on the se-
lected cells and, select Paste Special... from the popup
menu to bring up the Paste Special dialogue box.
15. Select the Validation radio button to paste only the data
validation and click on the OK button to complete the
paste.
FIGURE 32-32 Error Alert Created in Exercise 32-7 16. Place the cursor in Cells E127, F127, and G127 one at a
time and verify that the popup box shown Figure 32-31
are entered into Cell D127, the error message in Figure appears next to each of the cells.
32-32 will appear and require the user to enter an ap- 17. Save the workbook.
proved value or cancel the attempt to change the value.
6. Click the OK button to complete the data validation.
Protecting the Worksheet
Next, you will verify that the data validation is working cor-
rectly using the following steps: The creator of a worksheet may protect specified cells of the
worksheet against changes. Protecting the cells prevents the
7. Place the cursor in Cell D127 and verify that the popup user of the worksheet from accidentally or intentionally
box shown in Figure 32-31 appears next to the cell. changing a formula or entering data into a cell where data
8. Type 55 in Cell D127 and verify that Figure 32-32 appears. should not be entered. All estimating worksheets should be
9. Click the Retry button, type ⫺5 (minus five) in Cell protected.
D127, and verify that Figure 32-32 again appears. Before the creator of a worksheet can protect a work-
sheet, he or she must identify which cells the user will be al-
10. Click the Retry button, type 50 in Cell D127, and verify
lowed to change. This is done by selecting the cells that the
that the data is accepted.
user will be allowed to change, right clicking on the selected
11. Type 0 into Cell D127 and verify that the data is accepted. cells, selecting Format Cells... from the popup menu to
12. Delete the contents of Cell D127. bring up the Format Cells dialogue box, selecting the
Protection tab, unchecking the Locked check box, and click-
Finally, copy the data validation from Cell D127 to Cells
ing on the OK button to close the dialogue box. The Format
E127, F127, and G127 using the following steps:
Cells dialogue box is shown in Figure 32-33. By default, all
13. Right click on Cell D127 and select Copy from the cells should have the Locked check box checked.
popup menu.

FIGURE 32-33 Protection Tab of the Format Cells Dialogue Box


Converting Existing Forms 313

FIGURE 32-34 Review: Protect Worksheet Button

Once the creator of the worksheet has unchecked the


Locked check box for all cells the user will be allowed to
change, the user may protect the worksheet. This is done by
clicking on the Review menu tab and clicking on the Protect
Sheet button in the Changes group (shown in Figure 32-34)
to bring up the Protect Sheet dialogue box shown in Fig-
ure 32-35. The user then makes sure that the Protect work-
sheet and contents of locked cells check box is checked,
enters a password in the Password to unprotect sheet: text
box, unchecks the Select locked cells check box (so the user
can only select cell that can be changed), makes sure the Select
unlocked cells check box is checked, makes sure all other
check boxes are unchecked, and clicks on the OK button to
bring up the Confirm Password dialogue box shown in Fig-
ure 32-36. The user retypes the password in the Reenter pass-
word to proceed. text box and clicks on the OK button to close
the dialogue box and protect the worksheet. The user may
FIGURE 32-35 Protect Worksheet Dialogue Box now only select and change the cells that are not locked. A
worksheet may be protected without a password by leaving
the Password to unprotect sheet: text box blank, but it is not
recommended because anyone can unprotect the worksheet
and make changes.
To unprotect a worksheet, the creator clicks on the
Review menu tab and clicks on the Unprotect Sheet button
in the Changes group shown in Figure 32-37, which has re-
placed the Protect Worksheet button, to bring up the
Unprotect Sheet dialogue box shown in Figure 32-38. The
user types the password used to protect the worksheet in
the Password: text box and clicks on the OK button to close
the dialogue box and unprotect the worksheet. The work-
sheet cannot be unprotected without the password, so it is a
FIGURE 32-36 Confirm Password Dialogue Box good idea to keep a record of the passwords used to protect
worksheets in a safe place.

FIGURE 32-37 Review: Unprotect Worksheet Button FIGURE 32-38 Unprotect Sheet Dialogue Box
314 CHAPTER THIRTY-TWO

Exercise 32-8 G102, D105 through G114, D117 through G122, D124,
and D127 through G127.
In this exercise you will protect the Summary worksheet 5. Protect the worksheet by clicking on the Review menu
using the following steps: tab and clicking on the Protect Sheet button in the
Changes group (shown in Figure 32-34) to bring up the
1. Make sure Chapter 32.xlsm, the workbook modified in Protect Sheet dialogue box (shown in Figure 32-35).
Exercise 32-7, is open. If necessary, enable the macros.
6. Make sure the Protect worksheet and contents of
2. Select Cells A3 through A7, right click on the selected locked cells check box is checked.
cells, select Format Cells... from the popup menu to
bring up the Format Cells dialogue box (shown in 7. Type 1234 in the Password to unprotect sheet: text box.
Figure 32-33), select the Protection tab, uncheck the 8. Uncheck the Select locked cells check box.
Locked check box, and click on the OK button to close 9. Make sure the Select unlocked cells check box is
the dialogue box. checked.
3. Repeat Step 2 for the following: A10, A13 through A20, 10. Make sure that all other checks boxes are unchecked.
A23, A26 through A29, A32 through A38, A41 through 11. Click on the OK button to bring up the Confirm
A51, A54 through A60, A62 through A68, A71 through Password dialogue box (shown in Figure 32-36).
A74, A77, A80, A83, A86, A89, A92, A95, A98, A101,
A102, A105 through A114, A117 through A122, A124, 12. Type 1234 in the Reenter password to proceed. text box,
and A125. Hint: Multiple cells may be selected at one and click on the OK button to close the dialogue box
time using the Shift and the Ctrl keys. and protect the worksheet.
4. Repeat Step 2 for the following: Cells D3 through G7, 13. Verify that you can only select and change the unlocked
D10 through G10, D13 through G20, D23 through G23, cells by placing the cursor in Cell A3 and pressing the
D26 through G29, D32 through G38, D41 through G51, Right Arrow key. The cursor should move to the right
D54 through G60, D62 through G68, D71 through G74, and when it reaches Column G it should return to
D77 through G77, D80 through G80, D83 through G83, Column A. When it reaches Cell G127 it should return
D86 through G86, D89 through G89, D92 through G92, to Cell A3.
D95 through G95, D98 through G98, D101 through 14. Save the workbook.

CONCLUSION 3. How can Excel solve circular references?


4. What is a macro?
The steps for setting up an existing form are to create the
form layout, enter the formulas, automate with macros, test 5. What risk do you take if you use macros created by
the spreadsheets, and protect against errors. Macros are used someone else?
to automate key strokes and cursor movements by recording 6. How do you change the security level for macros?
the keystrokes and cursor movements as you would record 7. What must you do to run a macro from the keyboard?
your voice on a tape recorder. These actions will then be re- 8. What is the purpose of conditional formatting?
peated each time the macro is used. Error protection may be 9. How can conditional formatting be used to protect
added to the worksheet by (1) using conditional formatting against errors?
to change the format for a cell when the specified conditions
are met, (2) using data validation to only allow specific types 10. What is the purpose of data validation?
of data to be entered into a cell, and (3) protecting the work- 11. How can data validation be used to protect against errors?
sheet so only specified cells can be selected and modified. 12. What is the purpose of protecting a worksheet?
13. How can worksheet protection be used to protect against
errors?
PROBLEMS
14. For a worksheet that has been protected by a password,
1. What are the steps for converting an existing form? is there any way you can unprotect the worksheet with-
2. What is a circular reference? out a password?
C H A P T E R T H I R T Y- T H R E E

CREATING NEW FORMS

In this chapter you will learn how to create new Excel forms. In this chapter we will prepare a spreadsheet for an as-
This chapter will take you step by step through the creation of a phalt shingle roof. The desired results of the spreadsheet are
spreadsheet to calculate the materials, labor, and costs for an the quantities of roofing materials needed for the roof in
asphalt shingle roof. standard ordering quantities (for example, whole bundles
of shingles), the number of labor hours needed to complete
the roof, and the cost to install the roof. The materials used

C
on a typical asphalt shingle roof and that need to be in-
reating spreadsheet estimating forms from scratch
cluded in the spreadsheet are bundles of shingles, bundles
is a more difficult task than creating spreadsheets
of cap shingles, pounds of roofing nails, rolls of underlay-
from existing paper forms because the user has to
ment (felt), the number of underlayment nails in hundreds,
decide what the form is going to accomplish and how it will
be laid out. New forms should be carefully planned before
starting to create them in Excel.

PLANNING NEW FORMS


When creating a spreadsheet form from scratch, it is best to
carefully think through its design before beginning to set it
up. There are five steps in planning a new spreadsheet: (1)
Determine the desired output or results from the spread-
sheet, (2) determine what input data will be entered into the
spreadsheet, (3) solve different sample problems, (4) identify
the steps and equations that were used to arrive at the solu-
tion, and (5) prepare a sketch of the layout for the spread-
sheet. Once the spreadsheet has been carefully planned, it
can be set up using the same process used to convert existing
forms. This process is shown in Figure 33-1. Let’s look at
each of the planning steps.

Identify Desired Results


The first step is to determine the desired output or result from
the spreadsheet. This is what the estimator wants the spread-
sheet to accomplish. This could be a materials list, a cost to
complete an item, a proposal, or a preliminary cost estimate.
The unit of measure associated with each of the results should
be identified. For example, concrete materials should be in
cubic yards, asphalt-impregnated felt in rolls, and so forth. FIGURE 33-1 Process for Creating New Spreadsheets
315
316 CHAPTER THIRTY-THREE

pieces of 10-foot-long drip edge, pieces of 10-foot-long underlayment (for example, 15-pound felt), the total
counter flashings, rolls of ridge vent, the number of turtle length of the ridge(s) in feet, the number of ridges, the total
vents, the number of HVAC flashings, and the number of length of the hip(s) and valley(s) in feet, the total length of
plumbing pipe flashings. the perimeter of the roof that is horizontal in feet, the total
length of the perimeter of the roof that is sloped in feet, the
total length of counter flashing placed horizontally in feet,
Identify Input Data
the total length of counter flashing that is along a slope in
The second step is to determine the data the user of the feet, the number of HVAC flashings, the number of plumb-
spreadsheet will input (enter) into the spreadsheet for it to ing pipe flashings, and the type of attic ventilation (for ex-
calculate the desired results. The units associated with each ample, gable end, ridge, or turtle vent). To determine the
entry should be identified and should be the same as the number of labor hours required to shingle the roof, the
units used in the takeoff or pricing. For example, most con- labor productivities for the different types of shingles are
crete footings are specified in a combination of feet and needed. To calculate total cost, the pricing for the materials
inches or just inches. Footing dimensions are never specified and labor rates are needed.
in yards, which is the unit of measure used in specifying the For the spreadsheet developed in this chapter, there are
quantity of concrete. The spreadsheet should be set up to four types of shingles: 20-year three tab, 25-year architec-
make the necessary conversions. tural, 30-year architectural, and 40-year architectural. There
To bid an asphalt shingle roof, the following data will also be two types of underlayment: 15-pound and
needs to be collected from the plans and specifications: the 30-pound asphalt-impregnated felt. The pricing for the ma-
slope of the roof (for example, 4:12 or 6:12), the type of terials to be used in the spreadsheet is given in Table 33-1, and
shingle (for example, 25-year architectural), the type of the labor productivity rates are given in Table 33-2. The crew

TABLE 33-1 Material Pricing


Item Price Conversion

Shingles
20-year three tab $12.39/bundle bundle ⫽ 1/3 square
25-year architectural $15.98/bundle bundle ⫽ 1/3 square
30-year architectural $16.65/bundle bundle ⫽ 1/3 square
40-year architectural $17.35/bundle bundle ⫽ 1/3 square
Cap Shingles
20-year three tab $15.75/bundle bundle ⫽ 21 ft
25-year architectural $31.29/bundle bundle ⫽ 21 ft
30-year architectural $33.29/bundle bundle ⫽ 21 ft
40-year architectural $35.29/bundle bundle ⫽ 21 ft
Underlayment
15-pound felt $14.95/roll roll ⫽ 4 square
30-pound felt $13.95/roll roll ⫽ 2 square
Flashings and Vents
Drip edge $ 2.99/ea each ⫽ 10 ft
Counter $ 3.99/ea each ⫽ 10 ft
Ridge vent $42.00/ea roll ⫽ 20 ft
Turtle vents (61 sq in) $ 7.00/ea
HVAC pipe flashing $ 9.00/ea
Plumbing flashing $ 4.00/ea
Nails
Roofing nails $ 1.39/lb
Underlayment nails $ 1.00/C (hundreds)
Creating New Forms 317

TABLE 33-2 Labor Productivity adding their areas together. If the user were to use a takeoff
software package, the total area of the roof could be used
20-year three tab 2.50 lhr/square in lieu of dividing the roof into rectangles and calculating
25-year architectural 2.80 lhr/square the area.
30-year architectural 3.00 lhr/square The third step is to determine the quantities of materi-
als. Unless noted, the spreadsheet will need to round all
40-year architectural 3.20 lhr/square
quantities up to the next whole number.
The quantity of shingles is found by summing the re-
sults of Eqs. (9-5), (9-7), and (9-8) using a standard expo-
rate per labor hour is $35. The pricing and productivity data sure of 5 inches. The quantity is converted to bundles, where
are set up so they can be easily modified as material costs and 3 bundles equal 1 square (100 square feet).
labor rates change. Also given in Table 33-1 are conversion The quantity of cap is found by summing the results of
factors from standard order quantities (for example, rolls) to Eqs. (9-9) and (9-10). The quantity is converted to bundles,
common units of measure (for example, feet). where 1 bundle equals 21 lineal feet of 1-foot-wide cap or
0.21 squares of cap.
Solve Practice Problems Based on historical data, 1 pound of roofing nails is
needed for every 3 bundles of shingles, including cap shin-
The third step is to manually solve sample problems that gles, and is calculated from the ordered quantities of shingles.
cover all of the different types of problems the spreadsheet is The quantity of underlayment is found using Eq. (9-3)
to solve. During this process the developer of the spreadsheet and is converted to rolls. For 15-pound felt there are 4 squares
will often discover additional input data that is needed to of felt per roll, and for 30-pound felt there are 2 squares of
complete the calculations; this data should be added to the felt per roll. The spreadsheet should decide which conver-
list prepared in the second step. For the roofing spreadsheet sion factor to use.
being set up in this chapter, sample problems similar to From historical data, 125 nails are needed for 1 square
Examples 9-4 and 9-9 need to be solved. The reader should of felt; therefore, 250 nails are needed for 1 roll of 30-pound-
review these examples before continuing. felt and 500 nails are needed for 1 roll of 15-pound felt. The
number of nails is based on the order quantity of felt, and
the spreadsheet will need to determine if 250 or 500 nails per
Identify Steps and Equations roll will need to be ordered. Nails are ordered in units of
The fourth step is to identify the steps and equations taken 10 nails or 0.1 C, where C is the notation for 100.
to solve the practice problems. Not all problems are solved in The total drip edge equals the sum of the length of the
the same manner. For example, if the project specifies that drip edge placed horizontally plus the sum of the length of
turtle vents are needed, then the number of turtle vents the drip edge placed on a sloped edge. The length of the
needs to be calculated, whereas if the project specifies gable- drip edge placed on a sloped edge is determined by Eq. (9-1).
end vents (which are not a part of the roofing package), then The length of the drip edge is converted to 10-foot-long
nothing would be done. As a result, the steps should identify pieces the length by dividing by 9.8 feet, thus allowing
any decisions made (such as selecting between two formu- 0.2 foot per lap. The counter flashing is calculated in the
las) in the process of arriving at the solution. same manner.
For the roofing worksheet, the first step is to do a takeoff If ridge vent is specified, the length of the ridge will
for the quantities from the roof. The slope of the roof, type equal the quantity of ridge vent needed. If ridge vent is not
of shingle, type of underlayment, and type of attic ventila- specified, then the length is zero. The quantity of ridge vent
tion are read off the plans and specifications. The total needs to be converted to 20-foot rolls.
length of the ridge(s), hip(s), valley(s), perimeter, and If turtle vents are specified, 1 square foot of venting is
counter flashing are measured off the plans using a plan required for every 150 square feet of attic, with half of this
measurer, thus eliminating the need to add their lengths to- required ventilation in the upper portion of the roof and the
gether. The drip edge and counter flashing on sloped edges other half located in the eaves; therefore, the turtle vents are
are measured separately from the drip edge and counter required to provide 1 square foot of venting for every 300
flashing on horizontal edges so that the slope can be taken square feet of attic space. Each vent provides 61 square
into account. The number of ridges, HVAC flashings, and inches (0.42 ft2) of venting; thus 2.38 (1>0.42) vents are re-
plumbing pipe flashings are counted off the plans. The roof quired to for every 300 square feet. As a result one vent is re-
is divided into rectangles and the length and width of each quired for every 126 square feet (300 ft2>2.38).
rectangle is measured; the spreadsheet will need to calculate The quantities of HVAC and plumbing flashings are
the total area of the roof. All of these measurements are mea- taken off from the plans.
sured in the plan view. All quantities will be rounded up to the next whole or-
The second step is to calculate the area of the roof in dering unit (for example, bundle of shingles).
the plan view. This is done by multiplying the length by The fourth step is to determine the material costs. The
the width of each rectangle taken off the plans and then cost for each type of material (for example, shingles) is
318 CHAPTER THIRTY-THREE

FIGURE 33-2 First Tab of New Spreadsheet

determined by using Eq. (26-1) and the previously deter- Sketch Spreadsheet Layout
mined quantities and the material unit cost for the item. The
subtotal of the material cost is determined by summing The final step of planning is to sketch a preliminary layout
the costs for each type of material. One adds to this subtotal for the spreadsheet. This helps the developer of the spread-
the sales tax, which is calculated by using Eq. (19-3). The sheet to plan how the final spreadsheet is to look.
sales tax rate is 6.5%. The spreadsheet being developed in this chapter will
The fifth step is to determine the labor cost. The num- consist of three tabs. The first tab will contain the results in-
ber of labor hours is based on the sloped area of the roof, cluding the quantity of materials to be ordered, the number
which is calculated by using Eq. (9-7). The number of labor of labor hours, and the costs. A preliminary layout for this
hours is calculated using Eq. (20-7) and the productivity tab is shown in Figure 33-2.
associated with the type of shingle being installed. Two The second tab will contain the takeoff information, the
hours of mobilization time are added to the number of plan view area of the roof, and the cost per square foot for the
labor hours, which are rounded to the tenth of an hour. roof. A preliminary layout for this tab is shown in Figure 33-3.
The labor cost is calculated using Eq. (26-2) and a labor The third tab will contain the pricing information and
rate of $35 per hour. labor productivity rates. Two columns are used for the price
Finally, the total cost is calculated by summing the ma- and labor productivity. The left column will contain the nu-
terial and labor costs, and the cost per square foot is calcu- meric value and be used in the calculations. The right col-
lated by dividing the total cost by the sloped area. umn will contain the units. A preliminary layout for this tab
is shown in Figure 33-4.

Roof Information Roof Area


Roof Slope: Area Length Width
Shingle Type: 1
Underlayment: 2
Ridge(s): 3
No. of Ridges: 4
Hip(s)/Valley(s): 5
Horiz. Perimeter: 6
Sloped Perimeter: 7
Horiz. Counter: 8
Sloped Counter: 9
HVAC Flashings: 10
Plumbing Flashings:
Vent Type:

Plan View Area:


Unit Price:
FIGURE 33-3 Second Tab of New Spreadsheet
Creating New Forms 319

1. Begin by opening a new workbook.


2. Save the workbook by clicking the Save button on the
Quick Access toolbar or typing Ctrl+S, selecting the
Excel Exercises folder in the Save in: dropdown box,
typing Chapter 33 in the File Name text box, and click-
ing the Save button.
For this spreadsheet three worksheets are needed in the
workbook.
3. If there are more than three sheets, delete the extra
sheets by right clicking on the tabs of the extra sheets
and selecting Delete from the popup menu.
4. If there are one or two sheets, add the needed sheets by
clicking on the Insert Worksheet tab located to the
right of the sheet tabs.
5. Name the left worksheet “Bid” by right clicking the tab
of the worksheet, selecting Rename from the popup
FIGURE 33-4 Third Tab of New Spreadsheet menu, and, with the sheet name highlighted, typing Bid.
6. Rename the center worksheet “Takeoff ” and the right
worksheet “Pricing Data” using the same procedures
SETTING UP THE
used to rename the left worksheet.
SPREADSHEET
Next, you will format and add the pricing data to the Pricing
Now that the spreadsheet is planned it is ready to be set up. The Data worksheet.
setting up of a new form follows the process used to set up ex-
isting forms. The first step in setting up the spreadsheet is to 7. Make sure that the Pricing Data worksheet is selected.
create the form layouts, which is done in the next two exercises. 8. Change the width of Column A to 20 by right clicking
on Column A, selecting Column Width... from the
Exercise 33-1 popup menu to bring up the Column Width dialogue
box, entering 20 in the Column Width: text box, and
In this exercise you will create the layout for the third tab to clicking the OK button.
be used in the roof-estimating spreadsheet by completing 9. Change the width of Columns B and C to 8.
the following steps: 10. Type the text shown in Table 33-3 into the specified cells.

TABLE 33-3 Data for Cells in Pricing Data Worksheet


Cell Data Cell Data Cell Data Cell Data

A1 Item A23 HVAC Pipe Flashing B15 14.95 C9 $/bundle


A2 Shingles A24 Plumbing Flashing B16 13.95 C10 $/bundle
A3 20-year Three Tab A26 Nails B19 2.99 C11 $/bundle
A4 25-year Architectural A27 Roofing Nails B20 3.99 C12 $/bundle
A5 30-year Architectural A28 Underlayment Nails B21 42.00 C15 $/roll
A6 40-year Architectural A30 Item B22 7.00 C16 $/roll
A8 Cap Shingles A31 20-year Three Tab B23 9.00 C19 $/ea
A9 20-year Three Tab A32 25-year Architectural B24 4.00 C20 $/ea
A10 25-year Architectural A33 30-year Architectural B27 1.39 C21 $/ea
A11 30-year Architectural A34 40-year Architectural B28 1.00 C22 $/ea
A12 40-year Architectural B1 Price B30 Labor Productivity C23 $/ea
A14 Underlayment B3 12.39 B31 2.50 C24 $/ea
A15 15# Felt B4 15.98 B32 2.80 C27 $/lb
A16 30# Felt B5 16.65 B33 3.00 C28 $/C
A18 Flashings & Vents B6 17.35 B34 3.20 C31 lhr/squ
A19 Drip Edge B9 15.75 C3 $/bundle C32 lhr/squ
A20 Counter B10 31.29 C4 $/bundle C33 lhr/squ
A21 Ridge B11 33.29 C5 $/bundle C34 lhr/squ
A22 Turtle B12 35.29 C6 $/bundle
320 CHAPTER THIRTY-THREE

A B C 17. Merge and center Cells B30 and C30.


1 Item Price 18. Save the workbook.
2 Shingles
3 20-year Three Tab 12.39 $/bundle The workbook should look like Figure 33-5.
4 25-year Architectural 15.98 $/bundle
5 30-year Architectural 16.65 $/bundle
6 40-year Architectural 17.35 $/bundle
7
8 Cap Shingles SERIES
9 20-year Three Tab 15.75 $/bundle
Excel will automatically create a series or list of consecutive
10 25-year Architectural 31.29 $/bundle
11 30-year Architectural 33.29 $/bundle numbers (for example, 1, 2, 3, 4, and 5), dates, days, week-
12 40-year Architectural 35.29 $/bundle days, months, or other text (for example, #4, #5, #6, and #7).
13 A series is created by entering a start value in a cell and drag-
14 Underlayment ging the little box in the lower right-hand corner of the cell
15 15# Felt 14.95 $/roll
down or to the right the appropriate number of cells. If Excel
16 30# Felt 13.95 $/roll
17 simply copies the cell, it can be changed to a series by click-
18 Flashings & Vents ing on the Auto Fill Options button shown in Figure 33-6
19 Drip Edge 2.99 $/ea that appears at the lower right-hand corner of the filled cells
20 Counter 3.99 $/ea and selecting Fill Series from the popup box shown in
21 Ridge Vent 42.00 $/ea
22 Turtle Vents (61 sq in) 7.00 $/ea
Figure 33-7.
23 HVAC Pipe Flashing 9.00 $/ea The series may consecutively number the lists by 10s or
24 Plumbing Flashing 4.00 $/ea other increments by entering the first two numbers in the se-
25 ries, selecting both cells, and dragging the little box in the
26 Nails lower right-hand corner of the cell down or to the right the
27 Roofing Nails 1.39 $/lb
28 Underlayment Nails 1.00 $/C
appropriate number of cells. In the following exercise a se-
29 ries is used in the creation of the second tab of the roofing
30 Item Labor Productivity worksheet:
31 20-year Three Tab 2.50 lhr/squ
32 25-year Architectural 2.80 lhr/squ
33 30-year Architectural 3.00 lhr/squ Exercise 32-2
34 40-year Architectural 3.20 lhr/squ
FIGURE 33-5 Pricing Data Worksheet In this exercise you will create the layout for the first and sec-
ond tabs to be used in the roof-estimating spreadsheet by
11. Underline Cells A1 through C1 by highlighting A1 completing the following steps:
through C1 and clicking the Bottom Border button 1. Make sure that Chapter 33, the workbook created in
(shown in Figure 3-46) in the Font group on the Home Exercise 33-1, is open.
menu tab. If another border is shown in the Borders
2. Select the Takeoff worksheet by clicking on the Takeoff
button, select the correct border by clicking on the small
tab.
arrow to the right of the Borders button and selecting
the Bottom Border from the Borders popup menu.
12. Underline Cells A30 through C30 using the same proce-
dure used to underline Cells A1 through C1.
13. Bold the data in Cells A2, A8, A14, A18, and A26 by se-
lecting the cells, selecting the Home menu tab, and
clicking on the Bold button in the Font group (shown
in Figure 3-35).
14. Format the numbers in Column B to have two decimal
places by selecting Column B, selecting the Home menu
tab, and selecting the Comma Style button in the FIGURE 33-6 Auto Fill Options Button
Number group (shown in Figure 3-41).
15. Center the text in Column C by selecting Column C, se-
lecting the Home menu tab, selecting the Center button
in the Alignment group (shown in Figure 3-31).
16. Merge and center Cells B1 and C1 by highlighting Cells
B1 and C1, selecting the Home menu tab, and selecting
the Merge and Center button in the Alignment group
(shown in Figure 3-39). FIGURE 33-7 Auto Fill Options Popup Box
Creating New Forms 321

TABLE 33-4 Data for Cells in Takeoff Worksheet group (shown in Figure 3-41), and clicking the
Decrease Decimal button in the Number group (shown
Cell Data Cell Date in Figure 3-44) twice.
B2 Roof Information E6 ft 12. Format the numbers in Cell D18 to the comma style
B3 Roof Slope: E7 ea with two numbers after the decimal place by selecting
B4 Shingle Type: E8 ft Cell D18, selecting the Home menu tab, and selecting
B5 Underlayment: E9 ft the Comma Style button in the Number group (shown
B6 Ridge(s): E10 ft in Figure 3-41).
B7 No. of Ridges: E11 ft 13. Center the text in Cells E3 through E18 by selecting the
B8 Hip(s)/Valley(s): E12 ft cells, selecting the Home menu tab, selecting the Center
B9 Horiz. Perimeter: E13 ea button in the Alignment group (shown in Figure 3-31).
B10 Sloped Perimeter: E14 ea 14. Center the text in Cells G3 through G13, H3, and I3.
B11 Horiz. Counter: E17 sft
15. Merge and center Cells B2 through E2 by highlighting
B12 Sloped Counter: E18 /sft
Cells B2 through E2, selecting the Home menu tab, and
B13 HVAC Flashings: G2 Roof Area
selecting the Merge and Center button in the
B14 Plumbing Flashings: G3 Area
Alignment group (shown in Figure 3-39).
B15 Vent Type: G4 1
B17 Plan View Area: H3 Length 16. Merge and center Cells G2 through I2.
B18 Unit Price: I3 Width 17. Underline Cells B2 through E2 by selecting the cells and
E3 :12 clicking the Bottom Border button (shown in Figure 3-46)
in the Font group on the Home menu tab. If another
border is shown in the Borders button, select the correct
3. Change the width of Column A to 4, of Column B to 18, border by clicking on the small arrow to the right of the
of Column C to 1, of Column D to 20, of Columns E Borders button and selecting the Bottom Border from
through G to 5, and of Columns H and I to 8. the Borders popup menu.
4. Type the text shown in Table 33-4 into the specified 18. Underline Cells G2 through I2.
cells. 19. Place a thick box border around Cells B2 through E15
Next you will use the series command to create the numbers by selecting the cells, clicking on the Home menu tab,
1 through 10. clicking on the small arrow to the right of the Borders
button, and selecting the Thick Box Border from the
5. Select Cell G4. popup menu.
6. Drag the little square at the lower right-hand corner of 20. Place a thick box border around Cells B17 through E18.
Cell G4 down to Cell G8 by placing the cursors over the
21. Place a thick box border around Cells G2 through I13.
square, clicking and holding the left mouse button while
dragging the cursor down to the bottom of Cell G8, and 22. Save the workbook.
releasing the left mouse button. Cells G4 through G8 The workbook should look like Figure 33-8.
should now contain the number 1. Next, you will create the layout for the first tab.
7. Change these numbers to a series by clicking on the 23. Select the Bid worksheet by clicking on the Bid tab.
Auto Fill Options button (shown in Figure 33-6) at the
lower right-hand corner of the cells and selecting Fill 24. Change the width of Column A to 2, of Column B to 35,
Series from the popup box (shown in Figure 33-7). of Columns C and D to 9, and of Columns E and F to 15.
Cells G4 through G8 should now contain the numbers 1 25. Type the text shown in Table 33-5 into the specified cells.
through 5. 26. Center the text in Cells D3 through D13, D16, E2, and F2.
8. Select Cells G7 and G8. 27. Right justify the text in Cells E14 and E17.
9. Drag the little square at the lower right-hand corner of 28. Merge and center the text in Cells C2 and D2.
Cell G8 down to Cell G13. Cells G4 through G13 should 29. Format Cells C3 through C6 and C8 through C13 to
now contain the numbers 1 through 10. whole numbers by selecting the cells, selecting the
10. Right justify the text in Column B by selecting Column Home menu tab, selecting the Comma Style button in
B, selecting the Home menu tab, selecting the Align the Number group, and clicking the Decrease Decimal
Text Right button in the Alignment group (shown in button in the Number group twice.
Figure 3-31). 30. Format Cells C7 and C16 to a number with one number
11. Format the numbers in Cells D3 through D15 and D17 after the decimal point by selecting the cells, selecting
to the comma style with no numbers after the decimal the Home menu tab, selecting the Comma Style button
place by selecting the cells, selecting the Home menu in the Number group, and clicking the Decrease
tab, selecting the Comma Style button in the Number Decimal button in the Number group once.
322 CHAPTER THIRTY-THREE

A B C D E F G H I
1
2 Roof Information Roof Area
3 Roof Slope: :12 Area Length Width
4 Shingle Type: 1
5 Underlayment: 2
6 Ridge(s): ft 3
7 No. of Ridges: ea 4
8 Hip(s)/Valley(s): ft 5
9 Horiz. Perimeter: ft 6
10 Sloped Perimeter: ft 7
11 Horiz. Counter: ft 8
12 Sloped Counter: ft 9
13 HVAC Flashings: ea 10
14 Plumbing Flashings: ea
15 Vent Type:
16
17 Plan View Area: sft
18 Unit Price: /sft

FIGURE 33-8 Takeoff Worksheet

TABLE 33-5 Data for Cells in Takeoff Worksheet 31. Format Cells E3 through F17 to a number with two
numbers after the decimal point by selecting the cells,
Cell Data Cell Data selecting the Home menu tab, selecting the Comma
Style button in the Number group.
B2 Materials D6 rolls
32. Underline Cells B2 through F2, B13 through F13, and
B5 Roofing Nails D7 C
B16 through F16.
B7 Underlayment Nails D8 ea
B8 10′ Drip Edge D9 ea 33. Place a thick box border around Cells B2 through E17.
B9 10′ Counter Flashing D10 ea 34. Save the workbook.
B10 20′ Ridge Vent D11 ea
The workbook should look like Figure 33-9.
B11 Turtle Vents D12 ea
B12 HVAC Flashing D13 ea
B13 Plumbing Flashing D16 lhr The next step in creating the roofing spreadsheet is to
B15 Tax (6.5%) E2 Unit Price create the formulas and functions needed for the spread-
B16 Roofing Crew E14 Subtotal sheet to operate. In addition to the functions previously in-
C2 Quantity E16 35.00 troduced, the roofing spreadsheet uses the naming, concate-
D3 bundle E17 Total nate, and lookup functions. It will also use dropdown boxes
D4 bundle F2 Total for entering data. We will begin by looking at the naming
D5 lbs function and the creation of dropdown boxes.

A B C D E F
1
2 Materials Unit Price Total
3 25-year Architectural bundle
4 25-year Architectural Cap bundle
5 Roofing Nails lbs
6 15# Felt rolls
7 Underlayment Nails C
8 10' Drip Edge ea
9 10' Counter Flashing ea
10 20' Ridge Vent ea
11 Turtle Vents ea
12 HVAC Flashing ea
13 Plumbing Flashing ea
14 Subtotal
15 Tax (6.5%)
16 Roofing Crew lhr 35.00
17 Total

FIGURE 33-9 Bid Worksheet


Creating New Forms 323

FIGURE 33-10 Formulas: Define Name

NAMING CELLS
In lieu of referencing a cell by its column and row number
(for example, C5), one can reference a cell or group of cells by
a name given to the cell or group of cells. Cells are given a
name by selecting the cell or group of cells to be named, click-
ing on the Formulas menu tab, and clicking on Define Name
in the Defined Names group (shown in Figure 33-10) to
bring up the New Name dialogue box shown in Figure 33-11.
The name for the cells is typed in the top text box. The name
can be assigned to the entire workbook or the individual
sheet in the Scope: dropdown box.
The location of the cells named is changed by changing
the reference in the Refers to: box. This is done by typing the FIGURE 33-12 Click Here to Open New Name-Refers to:
correct reference in the box or by clicking the button at the Dialogue Box
right (shown in Figure 33-12) to go to the worksheet and
bring up the New Name – Refers to: dialogue box shown in
Figure 33-13. The user then selects the correct cells and
clicks on the button to the right of the cell reference (shown
in Figure 33-14) to return to the New Name dialogue box.
The New Name dialogue box is closed by right clicking on
the OK button. FIGURE 33-13 New Name – Refers to: Dialogue Box
Once a cell has been named, the cell may then be refer-
enced by its name rather than its column and row number.
For example, if Cell B12 were given the name “Area,” the
Excel formula
=B12

could be rewritten as follows: FIGURE 33-14 Click Here to Return to the New Name
Dialogue Box
=Area

A series or block of cells may also be named. When the


named cell or the entire block of named cells is selected,
the name appears in the Name Box located at the left of
the Formula bar, which usually contains the cell reference by
column and row. The Name Box is shown in Figure 33-15.
Alternatively, cells may be named by selecting the cells, click-
ing on the Name Box, and typing their name.
The name is inserted into a formula by (1) typing the
name in the formula, (2) clicking on the Formulas menu
tab, clicking on Use In Formula from the Defined Names
group (shown in Figure 33-16), and selecting the name from
the popup menu shown in Figure 33-17, or (3) clicking on the
Formulas menu tab, clicking on Use In Formula from the
Defined Names group, and selecting Paste Names... from
FIGURE 33-11 New Name Dialogue Box the popup menu shown in Figure 33-17, to bring up the
324 CHAPTER THIRTY-THREE

FIGURE 33-15 Name Box

FIGURE 33-16 Formulas: Use in Formula

FIGURE 33-17 Paste Name Popup Box

FIGURE 33-18 Paste Name Dialogue Box


Paste Name dialogue box shown in Figure 33-18. From the
Paste Name dialogue box, the user selects the name to be
used and clicks the OK button to close the dialogue box.
The advantage of naming cells is that it makes the for- on Name Manager button in the Defined Names group
mulas easier to follow because the cell can be named with a (shown in Figure 33-20). From the Name Manager the user
name that is representative of the data contained in the cells may create another name by clicking on the New button, edit
rather than a nondescriptive cell reference. a name by highlighting a name and clicking the Edit button,
Names are edited and deleted by opening the Name or delete a name by highlighting a name and clicking the
Manager dialogue box (shown in Figure 33-19), which is Delete button. The Name Manager dialogue box is closed by
opened by clicking on the Formulas menu tab and clicking clicking on the Close button.
Creating New Forms 325

FIGURE 33-19 Name Manager Dialogue Box

FIGURE 33-20 Formulas: Name Manager Button

ADDING DROPDOWN BOXES


Dropdown boxes are created using the same data validation
feature that was used to set limits on the data entered into a
cell, which was discussed in Chapter 32. To create a drop-
down box, the user selects the cell where the dropdown box
is to be located, clicks on the Data menu tab, clicks on the
Data Validation button in the Data Tools group (shown in
Figure 32-27) to bring up the Data Validation dialogue box
shown in Figure 33-21. From the Setting tab the user selects
List from the Allow: dropdown box. For the dropdown box
to appear, the user must make sure the In-cell dropdown
check box is checked.
The list of options or cells containing the list of options
for the dropdown box is entered into the Source: text box. FIGURE 33-21 Settings Tab of the Data Validation Dialogue
The list may be entered in a number of ways. Box
326 CHAPTER THIRTY-THREE

First, the cells containing the list of options are selected


by clicking on the button to the right of the Source: text box
and selecting the cell as was done with the naming function.
Second, the cells containing the list of options are
named and the name of the cells is pasted into the Source:
text box by clicking on the Formulas menu tab, clicking on
Use In Formula from the Defined Names group (shown in
Figure 33-16), and selecting the name from the popup menu
(shown in Figure 33-17) or selecting Paste Names... from
the popup menu (shown in Figure 33-17) to bring up the
Paste Name dialogue box (shown in Figure 33-18), selecting
the name of the cells, and clicking on the OK button.
Alternatively, the name may be typed into the Source: text
box by typing the equals sign and the name of the cells.
Third, the list of acceptable options is typed directly FIGURE 33-22 Input Message Tab of the Data Validation
into the Source: box with a comma separating the items in Dialogue Box
the list.
Input messages and error alerts may be added to the
dropdown box as was shown in Chapter 32. The Data 8. Place the cursor in the Source: text box, click on the
Validation dialogue box is closed by clicking on the OK but- Formulas menu tab, click on Use In Formula from
ton. When the user selects the cell where the dropdown box is the Defined Names group (shown in Figure 33-16),
located, an arrow appears to the side of the cell, and the user and select Shingle from the popup menu (shown in
can select from the list of options by clicking on this arrow. Figure 33-17).
9. Make sure the In-cell dropdown check box is checked.
Exercise 32-3 10. Select the Input Message tab and make sure the Show
input message when cell is selected check box is
In this exercise you will add three dropdown boxes to the checked.
Takeoff worksheet, which will be used to select the shingle 11. Type Shingle Type in the Title: text box and Select shingle
type, felt type, and vent type. You will begin by naming the cells type in the Input message: text box. The Input Message
containing the shingle and vent types by completing the fol- tab should look like Figure 33-22.
lowing steps: 12. Select the Error Alert tab and make sure that the Show
1. Make sure that Chapter 33, the workbook modified in error alert after invalid data is entered check box is
Exercise 33-2, is open. checked.
2. Select the Pricing Data worksheet. 13. Type Error in the Title: text box and Please select from
dropdown list in the Input message: text box. The Error
3. Select Cells A3 through A6, select the Name Box at the
Alert tab should look like Figure 33-23.
left of the Formula bar (shown in Figure 33-15), type
Shingle, and press the Enter key. 14. Click the OK button to complete the data validation.
4. Select Cells A15 and A16, click on the Formulas menu 15. Verify that the dropdown arrow and prompt appear
tab, click on Define Name in the Defined Names group when you select Cell D4 as shown in Figure 33-24.
(shown in Figure 33-10) to bring up the New Name dia-
logue box, and type Felt in the top text box. The New
Name dialogue box should look like Figure 33-11. Click
the OK button to close the dialogue box.
5. Select the Takeoff worksheet by clicking on the Takeoff
tab.
Next, you will restrict the values in Cell D4 to the values
listed in the cells you named Shingle and add custom input
and error messages to this cell.
6. Select Cell D4, click on the Data menu tab, click on the
Data Validation button in the Data Tools group (shown
in Figure 32-27) to bring up the Data Validation dia-
logue box (shown in Figure 33-21).
7. Select the Setting tab and select List from the Allow: FIGURE 33-23 Error Alert Tab of the Data Validation
dropdown box. Dialogue Box
Creating New Forms 327

FIGURE 33-24 Dropdown Arrow and Prompt

FIGURE 33-25 Dropdown List

16. Verify that when you click on the dropdown arrow the 20. From Cell D5, click on the Data menu tab, click on the
values in Cells A3 through A6 on the Pricing Data work- Data Validation button in the Data Tools group to
sheet are available for selection as shown in Figure 33-25. bring up the Data Validation dialogue box.
17. Verify that the error message shown in Figure 33-26 ap- 21. Select the Setting tab and type =Felt in the Source: text
pears when you enter unacceptable data by entering box. Be sure to include the equals sign.
shake in the cell. 22. Select the Input Message tab.
18. Click the Cancel button to close the error message.
Next, you will restrict the values in Cell D5 to the values
listed in the cells you named Felt and add custom input and
error messages to this cell. For this example the error mes-
sage is copied from Cell D4 to Cell D5, and it does not have
to be reentered.
19. Copy Cell D4 to Cell D5. When a cell is copied, the data
validation properties are also copied. FIGURE 33-26 Error Message
328 CHAPTER THIRTY-THREE

REFERENCING WORKSHEETS
IN A FORMULA
When one writes a formula on one worksheet, cells on an-
other worksheet may be used in the formula by clicking on
the worksheet where the cell is found and clicking on the
cell or by typing the name of the sheet followed by an ex-
clamation point (!) followed by the cell reference. For ex-
ample, Cell F17 on the Bid worksheet would be referenced
as follows:
Bid!F17

When the worksheet name contains a space, the name of the


worksheet must be enclosed in single quotes. For example,
Cell B20 on the Pricing Data worksheet would be referenced
as follows:
FIGURE 33-27 Paste Special Dialogue Box
'Pricing Data'!B20
23. Replace the text in the Title: text box with Felt Type and
replace the text in the Input message: text box with
Select felt type.
Exercise 32-4
24. Click the OK button to complete the data validation.
25. Verify that the dropdown arrow, prompt, and error In this exercise you will create the formulas for the Takeoff
message are working, and that 15# Felt and 30# Felt are worksheet using the following steps:
available for selection from the dropdown list.
1. Make sure that Chapter 33, the workbook modified in
Next, you will restrict the values in Cell D15 to gable end, ridge, Exercise 33-3, is open.
or turtle and add custom input and error messages to this cell. 2. Select Cell D17 on the Takeoff worksheet.
26. Right click on Cell D4 and select Copy from the popup
The area of the roof in plan view is calculated by multiply-
menu.
ing the individual lengths and widths and adding the resul-
27. Right click on Cell D15, select Paste Special... from the tants together. The area may be written by the following
popup menu to bring up the Paste Special dialogue box formula:
(shown in Figure 33-27), click on the Validation radio
button, and click on the OK button to copy the data val- Area ⫽ (Length1)(Width1) ⫹ (Length2)(Width2) ⫹ p
idation properties from Cell D4 to Cell D15. If the paste ⫹ (Length10)(Width10)
command were used, the border at the bottom of the
cell would be deleted and would need to be replaced. This formula is written in Excel as follows:
28. From Cell D15, click on the Data menu tab, click on the =H4*I4+H5*I5+H6*I6+H7*I7+H8*I8+H9*I9+H10*
Data Validation button in the Data Tools group to I10+H11*I11+H12*I12+H13*I13
bring up the Data Validation dialogue box.
3. Type this formula into Cell C17, or select Cell C17 and
29. Select the Setting tab and type Gable End,Ridge,Turtle in type the equals sign (⫽), select Cell H4, type the aster-
the Source: text box. Do not include a space between the isks (*), select Cell I4, type the plus sign (⫹), select Cell
commas and the words, before Gable, or after Turtle. H5, and so forth until the formula is complete.
The only space should be between the words Gable and
End. Do not include an equals sign. The unit price (found in Cell D18) is the total cost (found in
30. Select the Input Message tab. Cell F17 on the Bid worksheet) divided by the sloped area of
the roof. The sloped area of the roof is calculated from the
31. Replace the text in the Title: text box with Vent Type and area in plan view (found in Cell C17) by Eq. (9-7). The Excel
replace the text in the Input message: text box with formula for this is as follows:
Select vent type.
32. Click the OK button to complete the data validation. =Bid!F17/(D17*(1+(D3/12)^2)^0.5)

33. Verify that the dropdown arrow, prompt, and error 4. Enter this formula into Cell D18 on the takeoff work-
message are working and that Gable End, Ridge, and sheet. When Cell D17 is zero, “#DIV/0!” will be dis-
Turtle are available for selection from the dropdown list. played in Cell D18
34. Save the file. 5. Save the workbook.
Creating New Forms 329

FIGURE 33-28 CONCATENATE Function Arguments Dialogue Box

FIGURE 33-29 Functions: Text Button

CONCATENATE
The CONCATENATE function allows the user to link text,
the results of formulas, and the contents of cells together
into a single string of text. The contents of the cell may be
text or the result of a formula. The CONCATENATE func-
tion is written as follows:
=CONCATENATE(text1,text2,...)
where text1, text2, and so forth are the references of the cells
and text to be linked. The linking occurs without the addi-
tion of any spaces, so the user must add spaces as necessary.
The spaces and text to be added must be enclosed in double
quotes. For example, if B1 were 17, the formula
=CONCATENATE("Cell B1 equals ",B1,".")

would result in the following text:


Cell B1 equals 17.

The space after the equals in the formula provides the space
between the equals and the 17. Alternatively, this CON-
CATENATE function can be setup using the Function
Arguments dialogue box shown in Figure 33-28. The
Function Argument dialogue box for the CONCATENATE
function is opened by clicking on the Formulas menu tab,
clicking on the Text button in the Function Library (shown
in Figure 33-29), and clicking on CONCATENATE in the
popup menu (shown in Figure 33-30). FIGURE 33-30 Text Popup Menu
330 CHAPTER THIRTY-THREE

FIGURE 33-31 New Formatting Rule Dialogue Box

Alternatively, text, the results of formulas, and the con- 4. Place the cursor in Cell B3, click on the Home menu
tents of cell can be linked together by the And sign (&). tab, click on the Conditional Formatting button in the
Styles group (shown in Figure 32-20), place the cursor
="Cell B1 equals "&B1&"."
over the Highlight Cell Rules from the popup menu
produces the same result as (shown in Figure 32-21), and click on More Rules... to
bring up the New Rule Formatting dialogue box (shown
=CONCATENATE("Cell B1 equals ",B1,".").
in Figure 33-31).
5. Select Cell Value from the first dropdown box and not
Exercise 32-5 equal to from the second dropdown box and type
=Takeoff!D4 in the text box.
In this exercise you will add material names for Cells B3, B4, 6. Click on the Format... button to bring up the Format
and B6 and add the formulas that will calculate the quanti- Cells dialogue box (shown in Figure 33-32), click the
ties of materials. The type of materials ordered for the shin- Font tab, select the color red in the color dropdown box,
gles, cap shingles, and underlayment depend on the type of and click the OK button.
material specified and will need to change on the Bid work- 7. The New Formatting Rule dialogue box should appear
sheet to match the items selected on the Takeoff worksheet. as shown in Figure 33-31, with red text in the Preview
This is done using the following steps: box.
1. Make sure that Chapter 33, the workbook modified in 8. Click on the OK button to close the New Formatting
Exercise 33-4, is open. Rule dialogue box. “Select Shingle” should now be in
2. Click on the Bid tab and click on Cell B3. red.

Cell B3 on the Bid worksheet should be the same as Cell D4 Cell B4 should combine the shingle type shown in Cell D4 of
on the Takeoff worksheet, unless the Cell D4 is blank, in the Takeoff worksheet with the word “cap.” This is done by
which case Cell B3 should be “Select Shingle Type.” This is using the CONCATENATE function. The Excel function is
done with an IF function, which checks to see if Cell D4 on written as follows:
the Takeoff worksheet is blank. If it is blank, the cell should =CONCATENATE(Takeoff!D4," Cap")
contain Select Shingle Type; otherwise, the cell’s contents
9. Enter this function into Cell B4. Be sure to include a
should be the same as Cell D4 on the Takeoff worksheet. A
space before the word Cap.
blank dropdown box carries a numeric value of zero. The
formula is written as follows: Cell B6 on the Bid worksheet should be the same as Cell D5
=IF(Takeoff!D4=0,"Select Shingle Type",
on the Takeoff worksheet, unless Cell D5 is blank, in which
Takeoff!D4) case Cell B6 should be “Select Underlayment Type.” This is
done in the same manner as was done for Cell B3. The Excel
3. Enter this formula into Cell B3 on the Bid worksheet. formula is written as follows:
Next we will use conditional formatting to change the font of =IF(Takeoff!D5=0,"Select Underlayment
Cell B3 to red when the shingle type has not been selected. Type",Takeoff!D5)
Creating New Forms 331

FIGURE 33-32 Font Tab of the Format Cells Dialogue Box

10. Enter this formula into Cell B6 on the Bid worksheet. 100+Takeoff!D8*((1+(Takeoff!D3/12)^2)/
2)^0.5*(5/12)/100),0)
11. Add the same conditional formatting to Cell B6 as was
added to Cell B3 except type =Takeoff!D5 in the text box 13. Enter this formula into Cell C3 on the Bid worksheet.
of New Formatting Rule dialogue box.
The quantity of cap shingles is determined by the sum of
12. Save the workbook. Eqs. (9-9) and (9-10). Equation (9-9) is written in Excel as
The quantity of shingles is determined by the sum of Eqs. (9-5), follows:
(9-7), and (9-8). Equation (9-5) for an exposure of 5 inches =Takeoff!D6/100
is written in Excel as follows:
Equation (9-10) is written in Excel as follows:
=(5/12)*Takeoff!D9/100
=Takeoff!D8*(1+(Takeoff!D3/17)^2)^0.5/100
Equation (9-7) is written in Excel as follows:
These equations will determine the number of squares of
=Takeoff!D17*(1+(Takeoff!D3/12)^2)^0.5/100 materials. The number of squares needs to be converted to
Equation (9-8) for an exposure of 5 inches is written in Excel bundles before the quantity is rounded up to the next whole
as follows: number. This is done by multiplying the sum by 100 and di-
viding by 21, because there are 21 square feet in a bundle.
=Takeoff!D8*((1+(Takeoff!D3/12)^2)/2) The sum of these equations, including the rounding, is writ-
^0.5*(5/12)/100 ten in Excel as follows:
These equations will determine the number of squares of =ROUNDUP((100/21)*(Takeoff!D6/100+Takeoff!
materials. The number of squares needs to be converted to D8*(1+(Takeoff!D3/17)^2)^0.5/100),0)
bundles before the quantity is rounded up to the next whole
14. Enter this formula into Cell C4 on the Bid worksheet.
number. This is done by multiplying the sum by 3 because
there are 3 bundles in a square. The sum of these equations, The number of roofing nails equals the number of bundles
including the rounding up to the next whole number, is of shingles divided by 3 because 1 pound of nails is needed
written in Excel as follows: for every 3 bundles of shingles. The Excel formula for the
number of nails is written as follows:
=ROUNDUP(3*((5/12)*Takeoff!D9/100
+Takeoff!D17*(1+(Takeoff!D3/12)^2)^0.5/ =ROUNDUP((C3+C4)/3,0)
332 CHAPTER THIRTY-THREE

15. Enter this formula into Cell C5 on the Bid worksheet. If a ridge vent is specified, the length of the ridge will equal
the quantity of ridge vent needed. If a ridge vent is not spec-
The quantity of underlayment is calculated using Eq. (9-3).
ified then the length is zero. The quantity of ridge vent needs
For a standard 3-foot width and a 6-inch lap, Eq. (9-3) is
to be converted to 20-foot rolls. The Excel function for the
written in Excel as follows:
ridge vent is written as follows:
=(Takeoff!D17*(1+(Takeoff!D3/12)^2)^0.5*
(3/2.5)+Takeoff!D8*((1+(Takeoff!D3/ =IF(Takeoff!D15="Ridge",ROUNDUP
12)^2)/2)^0.5*(3+1)*(3/2.5)+(Takeoff!D6 (Takeoff!D6/20,0),0)
+Takeoff!D7)*3) 20. Enter this function into Cell C10 on the Bid worksheet.
For 30-pound felt, the quantity is divided by 200; for 15-pound If turtle vents are specified, the quantity of turtle vents is cal-
felt, the quantity is divided by 400. This decision is made using culated by dividing the area of the roof in plan view by 127.
an IF function written as follows: The number of vents must be rounded up. The Excel func-
=IF(Takeoff!D5="30# Felt",200,400) tion for the turtle vents is as follows:

The IF function does not need to check to see if the cell =IF(Takeoff!D15="Turtle",ROUNDUP
contains 15-pound felt because the dropdown box for felt (Takeoff!D17/127,0),0)
is only allowed to contain 30-pound felt or 15-pound felt, 21. Enter this function into Cell C11 on the Bid worksheet.
if it is not 30-pound felt, it must be 15-pound felt.
Combining these two functions, we get the following Excel The quantities of HVAC and plumbing flashings are directly
formula: taken off of the plans and are equal to Cells D13 and D14 on
the Takeoff worksheet.
=ROUNDUP((Takeoff!D17*(1+(Takeoff!D3/
12)^2)^0.5*(3/2.5)+Takeoff!D8*((1 22. Enter =Takeoff!D13 into Cell C12 on the Bid worksheet.
+(Takeoff!D3/12)^2)/2)^0.5*(3+1)*(3/2.5) 23. Enter =Takeoff!D14 into Cell C13 on the Bid worksheet.
+(Takeoff!D6+Takeoff!D7)*3)/IF(Takeoff!
24. Save the worksheet.
D5="30# Felt",200,400),0)

16. Enter this formula into Cell C6 on the Bid worksheet.


From historical data, 125 nails are needed for 1 square of felt.
The quantity of underlayment nails needed equals the num- LOOKUP AND VLOOKUP
ber of squares of felt multiplied by 125, where there are The LOOKUP function is used to select the correct material
2 squares on a roll of 30-pound felt and 4 squares on a roll of price based on the type of shingle or underlayment selected.
15-pound felt. The quantity is based on the number of rolls This is done by comparing the type of material on the
of felt ordered and is divided by 100 to express the quantity Takeoff worksheet to the list of materials and their prices on
in 100s (C). The quantity is rounded to tens or 0.1 C. The the Pricing Data worksheet. The LOOKUP function is writ-
Excel function is written as follows: ten as follows:
=ROUNDUP(C6*IF(Takeoff!D5="30# =LOOKUP(lookup_value,array)
Felt",2,4)*125/100,1)
where the lookup_value is the value to be looked up (the
17. Enter this function into Cell C7 on the Bid worksheet. type of material in our case) and the array is where the list of
The quantity of drip edge equals the length of the horizontal values is stored (the materials and their prices in our case).
perimeter plus the sloped perimeter of the roof, where the The array should be two columns wide with the lookup
sloped perimeter is converted from a plan view to a length value in the left column and the associated value in the col-
along the slope using Eq. (9-1). The length of the drip edge is umn to the right. The values in the left column of the array
converted to 10-foot-long pieces by dividing by 9.8 feet, thus must be in ascending order (⫺1, 0, 1, 2, ... , A-Z) because the
allowing 0.2 feet for lap. The Excel function for the drip edge LOOKUP function will begin comparing the lookup value
is written as follows: to the values in the left column of the array beginning with
the top and working its way down, stopping when it finds a
=ROUNDUP((Takeoff!D9+Takeoff!D10*(1+ value equal to or greater than the lookup value. If the
(Takeoff!D3/12)^2)^0.5)/9.8,0) LOOKUP function finds a value in the left column of the
18. Enter this function into Cell C8 on the Bid worksheet. array equal to the lookup value, it will return the value of
the cell to its right. If the LOOKUP function finds a value in
Counter flashing is handled in the same manner. The Excel the left column of the array greater than the lookup value
function for the counter flashing is written as follows: before it finds a value it is equal to, it will return the value of
=ROUNDUP((Takeoff!D11+Takeoff!D12* the cell one column to the right and one row up. For exam-
(1+(Takeoff!D3/12)^2)^0.5)/9.8,0) ple, for the data in Figure 33-33, the formula
19. Enter this function into Cell C9 on the Bid worksheet. =LOOKUP(A1,A3:B6)
Creating New Forms 333

A B
1
2
3 a 1
4 b 2
5 g 3
6 e 4
FIGURE 33-33 LOOKUP array

is equal to 2 when cell A1 is equal to b. Alternatively, this


LOOKUP function is equal to 2 when cell A1 is equal to e be-
cause the function finds g (which is greater than e) before it
finds the e. In this case the LOOKUP function selects the
value from the cell to the right and one row up (Cell B4)
from Cell A5, where g is found.
Alternatively, this LOOKUP function can be set up using
the Function Arguments dialogue box shown in Figure 33-34.
The Function Argument dialogue box for the LOOKUP
function is opened by clicking on the Formulas menu tab,
clicking on the Lookup & Reference button in the Function
Library (shown in Figure 33-35), clicking on LOOKUP in
the popup menu (shown in Figure 33-36), clicking on
lookup_value,array from the Select Arguments dialogue
box (shown in Figure 33-37), and clicking on OK.
The VLOOKUP function works in a way similar to the
LOOKUP function, but it allows the user to select between FIGURE 33-36 Lookup & Reference Popup Menu
multiple return values stored in different columns. The
VLOOKUP function is written as follows:
=VLOOKUP(lookup_value,table_array,
col_index_number)

FIGURE 33-34 LOOKUP Function Arguments Dialogue Box

FIGURE 33-35 Functions: Lookup & Reference Button


334 CHAPTER THIRTY-THREE

TABLE 33-6 Formulas


Cell Formula

E5 ='Pricing Data'!B27
E7 ='Pricing Data'!B28
E8 ='Pricing Data'!B19
E9 ='Pricing Data'!B20
FIGURE 33-37 Select Arguments Dialogue Box
E10 ='Pricing Data'!B21
E11 ='Pricing Data'!B22
A B C D E12 ='Pricing Data'!B23
1 E13 ='Pricing Data'!B24
2
3 a 1 11 21
4 b 2 12 22 1. Make sure that Chapter 33, the workbook modified in
5 c 3 13 23 Exercise 33-5, is open.
6 d 4 14 24 2. Begin by entering the formulas in Table 33-6 into the as-
FIGURE 33-38 VLOOKUP array sociated cells on the Bid worksheet.
The materials pricing for the shingles must be selected
from Cells B3 through B6 based on the shingles specified.
This is done by using a LOOKUP function, which is written
where the lookup_value is the value to be looked up, the as follows:
table_array is where the list of values is stored, and the
col_index_number identifies which column is to be used =LOOKUP(Takeoff!D4,'Pricing Data'!A3:B6)
for the return values. The table array should be at least two 3. Enter this function into Cell E3 on the Bid worksheet.
columns wide with the lookup values in the left column and The cell will contain #N/A when a shingle type has not
the return values in the columns to the right. The lookup been selected.
values in the left column must be listed in ascending order
4. Enter =LOOKUP(Takeoff!D4,'Pricing Data'!A9:B12)
just as they were for the LOOKUP function. The
into Cell E4 on the Bid worksheet.
VLOOKUP function follows the same rules as the LOOKUP
function when looking for the lookup value. A column 5. Enter =LOOKUP(Takeoff!D5,'Pricing Data'!A15:B16)
index number of 2 selects return values from the second into Cell E6 on the Bid worksheet.
column of the array, whereas a column index number of 3 The next step is to calculate the total cost for each type of ma-
selects return values from the third column. The column terial. This is done by multiplying Column E by Column C.
index number must be greater than 1 and less than or equal
to the number of columns in the array. For example, for the 6. Enter =E3*C3 into Cell F3 on the Bid worksheet.
data in Figure 33-38, the formula 7. Copy Cell F3 to Cells F4 through F13 without copying
the border by right clicking on Cell F3, selecting Copy
=VLOOKUP(A1,A3:D6,2)
from the popup menu, selecting Cells F4 through F13,
is equal to 2 when Cell A1 is equal to b. If the column index right clicking on one of the selected cells, selecting Paste
number is changed to 3 as follows: Special... from the popup menu to bring up the Paste
Special dialogue box, selecting All except borders, and
=VLOOKUP(A1,A3:D6,3)
clicking on the OK button.
then the function returns 12 when Cell A1 is equal to b. The
Next, we calculate the total cost of the materials without
VLOOKUP function can be used for multiple pricing lists or
sales tax.
skipping columns when looking up prices. The use of the
LOOKUP function is shown in the following exercise: 8. Enter =SUM(F3:F13) into Cell F14 of the Bid worksheet.
Next, we calculate the tax at a fixed rate of 6.5%.
Exercise 32-6
9. Enter =F14*0.065 into Cell F15 of the Bid worksheet.
In this exercise you will determine the material, labor, and The next step is to determine the number of labor hours
total costs of the roof by completing the following steps. The needed for the roof, which is determined by multiplying
prices in Cells E3, E4, and D6 will need to change based on the labor hours per square for the specified type of shin-
the type of materials specified. The prices in Cells E5, and E7 gle by the sloped area of the roof and adding two hours
through E13 do not change. for mobilization. The labor hours per square is found in
Creating New Forms 335

Cells B31 through B34 of the Pricing Data worksheet, and TABLE 33-7 Test Case
the LOOKUP function is used to select the appropriate
production rate. The Excel formula for the sloped area is Cell Data Cell Data
as follows:
C3 6 C11 4
=Takeoff!D17*(1+(Takeoff!D3/12)^2)^0.5/100 C4 25-year Architectural C12 8
The Excel function to determine the labor hours is written as C5 15# Felt C13 2
follows: C6 12 C14 4
=ROUNDUP(LOOKUP(Takeoff!D4,'Pricing C7 1 C15 Turtle
Data'!A31:B34)*Takeoff!D17*(1+ C8 91 H4 44
(Takeoff!D3/12)^2)^0.5/100+2,1) C9 152 I4 32
10. Enter this function into Cell C16 on the Bid worksheet. C10 0
The next step is to calculate the total labor costs by multiply-
ing Column E by Column C. The final step is to protect the worksheet against er-
11. Enter =E16*C16 into Cell F16 of the Bid worksheet. rors. For the roofing spreadsheet, this protection will be in
two forms. First, data validation is used to restrict the val-
The next step is to calculate the total costs by summing the ues entered into Cells D3 through D15 and H4 through
material cost without tax, the sales tax, and the labor. I13 on the Takeoff worksheet. This has already been done
12. Enter =SUM(F14:F16) into Cell F17 of the Bid worksheet. for Cells D4, D5, and D15. Cell C3 is limited to a whole
13. Save the workbook. number between 0 and 12. Cells D6 through D12 are lim-
ited to a whole number between 0 and 200. Cells D13 and
D14 are limited to a whole number between 0 and 20.
The next step is to automate with macros; however, Finally, Cells H4 through I13 are limited to a whole num-
macros are not needed in this workbook. The next step is to ber between 0 and 200.
test the worksheet. This is done in the following exercise. Second, the worksheet is protected so only Cells D3
through D15 and H4 through I13 can be changed. In the
following exercise you will protect the worksheets against
errors:
Exercise 32-7

In this exercise you will test the workbook as follows: Exercise 32-8
1. Make sure that Chapter 33, the workbook modified in
Exercise 33-6, is open. In this exercise you will protect the worksheet against errors
2. Begin by entering the numbers and text in Table 33-7 by using the following steps:
into the associated cell in the Takeoff worksheet. 1. Make sure that Chapter 33, the workbook modified in
The Bid worksheet should appear as it does in Figure 33-39. Exercise 33-6, is open.
3. Exit without saving the worksheet. 2. Click on the Takeoff tab to move to the Takeoff work-
sheet.

A B C D E F
1
2 Materials Quantity Unit Price Total
3 25-year Architectural 51 bundle 15.98 814.98
4 25-year Architectural Cap 6 bundle 31.29 187.74
5 Roofing Nails 19 lbs 1.39 26.41
6 15# Felt 6 rolls 14.95 89.70
7 Underlayment Nails 30.0 C 1.00 30.00
8 10' Drip Edge 16 ea 2.99 47.84
9 10' Counter Flashing 2 ea 3.99 7.98
10 20' Ridge Vent - ea 42.00 -
11 Turtle Vents 12 ea 7.00 84.00
12 HVAC Flashing 2 ea 9.00 18.00
13 Plumbing Flashing 4 ea 4.00 16.00
14 Subtotal 1,322.65
15 Tax (6.5%) 85.97
16 Roofing Crew 46.1 lhrs 35.00 1,613.50
17 Total 3,022.12

FIGURE 33-39 Bid Worksheet


336 CHAPTER THIRTY-THREE

12. Select Cells D7 through D12, right click on one of the


selected cells, select Paste Special... from the popup
menu to bring up the Paste Special dialogue box, select
the Validation radio button, and click the OK button to
close the Paste Special dialogue box.
13. Repeat this process for Cells H4 through I13.
Next, the data validation for Cells D13 and D14 is set up.
14. Select Cells D13 and D14, click on the Data menu tab,
click on the Data Validation button in the Data Tools
group to bring up the Data Validation dialogue box.
15. Select the Settings tab, select Whole Number from the
Allow: dropdown box, select between from the Data:
dropdown box, type 0 in the Minimum: text box, and
FIGURE 33-40 Settings Tab of the Data Validation Dialogue type 20 in the Maximum: text box.
Box
16. Select the Input Message tab and type Enter a whole
number between 0 and 20. in the Input message: text box.
First, the data validation for Cell D3 is set up. 17. Select the Error tab, type Error in the Title: text box,
type Enter a whole number between 0 and 20. in the
3. Select Cell D3, click on the Data menu tab, click on the Error message: text box, and click the OK button to
Data Validation button in the Data Tools group to close the Data Validation dialogue box.
bring up the Data Validation dialogue box (shown in
The final step is to protect the workbook. This is done in two
Figure 33-40).
steps. First, identify the cells that will be allowed to change.
4. Select the Settings tab, select Whole Number from the Second, protect each of the worksheets in the workbook.
Allow: dropdown box, select between from the Data:
dropdown box, type 3 in the Minimum: text box, and 18. Select Cells D3 through D15 and H4 through I13, right
type 12 in the Maximum: text box. click on one of the selected cells, select Format Cells...
from the popup menu to bring up the Format Cells dia-
5. Select the Input Message tab and type Enter a whole
logue box, select the Protection tab, uncheck the
number between 3 and 12. in the Input message: text
Locked check box, and click the OK button to close the
box. The Title: text box will remain blank.
dialogue box.
6. Select the Error tab, type Error in the Title: text box,
19. Protect the Takeoff worksheet by clicking on the Review
type Enter a whole number between 3 and 12. in the
menu tab and clicking on the Protect Sheet button in
Error message: text box, and click the OK button to
the Changes group (shown in Figure 32-34) to bring up
close the Data Validation dialogue box.
the Protect Sheet dialogue box (shown in Figure 32-35).
Next, the data validation for Cell D6 is set up. 20. Make sure that the Protect worksheet and contents of
7. Select Cell D6, click on the Data menu tab, click on the locked cells check box is checked.
Data Validation button in the Data Tools group to 21. Type 1234 in the Password to unprotect sheet: text box.
bring up the Data Validation dialogue box. 22. Uncheck the Select locked cells check box.
8. Select the Settings tab, select Whole Number from the 23. Make sure that the Select unlocked cells check box is
Allow: dropdown box, select between from the Data: checked.
dropdown box, type 0 in the Minimum: text box, and
24. Make sure that all other check boxes are unchecked.
type 200 in the Maximum: text box.
25. Click on the OK button to bring up the Confirm
9. Select the Input Message tab and type Enter a whole
Password dialogue box.
number between 0 and 200. in the Input message: text
box. 26. Type 1234 in the Reenter password to proceed. text box
and click on the OK button to close the dialogue box
10. Select the Error tab, type Error in the Title: text box,
and protect the worksheet.
type Enter a whole number between 0 and 200. in the
Error message: text box, and click the OK button to 27. Check to make sure only Cells D3 through D15 and H4
close the Data Validation dialogue box. through I13 can be selected by pressing the Down
Arrow key to move through the unlocked cells.
Next, copy the data validation from Cell D6 to Cells D7
28. Protect the Bid and Pricing Data worksheets using the
through D12 and H4 through I13 using the following steps.
same process.
11. Right click on Cell D6 and select Copy from the popup 29. Save the workbook.
menu.
Creating New Forms 337

CONCLUSION 7. What is the purpose of the LOOKUP function?


8. Make a copy of the spreadsheet developed in this chapter.
The steps for planning a new form are to identify the desired Modify the copy to use the plan view area from a takeoff
results, identify input data, solve practice problems, identify software package in lieu of calculating the area. Add the
steps and equations, and sketch spreadsheet layouts. The needed error protection and protect your worksheets.
steps for setting up a new form are the same as for existing
9. Make a copy of the spreadsheet developed in this chap-
forms.
ter and use it to calculate the cost of the roof shown in
Figure 9-11. The roof is constructed of 30-year architec-
tural shingles over 30-pound felt. Ridge vents are used
PROBLEMS and there are four plumbing flashings and one HVAC
1. What are the steps for creating a new form? flashing. The roof slope is 4:12.
2. How can a series be created? 10. Make a copy of the spreadsheet developed in this chap-
ter and use it to calculate the cost of the roof shown in
3. What is the advantage of naming cells?
Figure 9-12. The roof is constructed of 20-year, three-
4. How are cells named? tab shingles over 15-pound felt. Turtle vents are used
5. How do you create a dropdown box? and there are six plumbing flashings and two HVAC
6. What is the purpose of the CONCATENATE function? flashing. The roof slope is 6:12.
C H A P T E R T H I R T Y- F O U R

PROPOSALS
AND BEYOND

In this chapter you will learn how to create a ready-to-sign


proposal and look beyond the Excel spreadsheets presented in
this book.

I n the previous chapter, Excel was used to prepare an esti-


mate for an asphalt shingle roof. It is a simple step to con-
vert this estimate into a ready-to-sign proposal.

FIGURE 34-1 Home: Insert Button


Exercise 34-1
6. Change the width of Columns A and C to 1, of Column
In this exercise you will convert the spreadsheet from B to 10, and of Column D to 25.
Chapter 33 into a ready-to-sign proposal by completing the
following steps: 7. Type the text shown in Table 34-1 into the specified
cells.
1. Open Chapter 33, the workbook you created in the pre- 8. Underline Cells B2 through D2 by selecting the cells
vious chapter. and clicking the Bottom Border button (shown in
2. Save the workbook as Chapter 34.xlsx by selecting the Figure 3-46) in the Font group on the Home menu tab.
File tab (the Microsoft Office button for Excel 2007), If another border is shown in the Borders button, select
clicking on Save As in the left pane to bring up the Save the correct border by clicking on the small arrow to the
As dialogue box, selecting the Excel Exercises folder in right of the Borders button and selecting the Bottom
the left pane (Save in: dropdown box for Excel 2007), Border from the Borders popup.
and typing Chapter 34 in the File Name text box.
Next, you will add a place on the Takeoff worksheet for the TABLE 34-1 Date for Takeoff Worksheet
client and project information using the following steps:
3. Select the Takeoff tab. Cell Data Cell Data
4. Click on the Review menu tab, click on the Unprotect B2 Client Information B11 Project Information
Sheet button in the Changes group to bring up the B3 Name: B12 Name:
Unprotect Sheet dialogue box (shown in Figure 32-37),
B4 Address: B13 Address:
type 1234 in the Password: text box, and click on the OK
button to unprotect the worksheet. B6 City: B15 City:
5. Select Columns A through D, click on the Home menu B7 State: B16 State:
tab, and click on the Insert button in the Cells group B8 Zip Code: B17 Zip Code:
(shown in Figure 34-1) to insert four columns to the left B9 Phone #: B18 Phone #:
of the worksheet.
338
Proposals and Beyond 339

A B C D E F G H I J K L M
1
2 Client Information Roof Information Roof Area
3 Name: Roof Slope: :12 Area Length Width
4 Address: Shingle Type: 1
5 Underlayment: 2
6 City: Ridge(s): ft 3
7 State: No. of Ridges: ea 4
8 Zip Code: Hip(s)/Valley(s): ft 5
9 Phone #: Horiz. Perimeter: ft 6
10 Sloped Perimeter: ft 7
11 Project Information Horiz. Counter: ft 8
12 Name: Sloped Counter: ft 9
13 Address: HVAC Flashings: ea 10
14 Plumbing Flashings: ea
15 City: Vent Type:
16 State:
17 Zip Code: Plan View Area: - sft
18 Phone #: Unit Price: #N/A /sft

FIGURE 34-2 The Takeoff Worksheet

9. Merge and center Cells B2 through D2 by highlighting 21. Save the workbook.
Cells B2 through D2, selecting the Home menu tab, and
The worksheet should now appear as shown in Figure 34-2.
selecting the Merge and Center button in the
Next, you will add a place on the Bid worksheet for the
Alignment group (shown in Figure 3-39).
client, project, and other proposal information using the fol-
10. Underline Cells B11 through D11. lowing steps:
11. Merge and center Cells B11 through D11.
22. Select the Bid tab.
12. Right justify the text in Column B by selecting
23. Click on the Review menu tab, click on the Unprotect
Column B, selecting the Home menu tab, and select-
Sheet button in the Changes group to bring up the
ing the Align Right button in the Alignment group
Unprotect Sheet dialogue box (shown in Figure 32-37),
(shown in Figure 3-32).
type 1234 in the Password: text box, and click the OK
13. Draw a Thick Box Border around Cells B2 through D9 button to unprotect the worksheet.
by selecting Cells B2 through D9, clicking the Home
24. Select Rows 1 through 9, click on the Home menu tab,
menu tab, clicking on the small arrow to the right of the
and click on the Insert button in the Cells group
Borders button in the Font group, and selecting the
(shown in Figure 34-1) to insert nine rows at the top of
Thick Box Border from the Borders popup menu.
the worksheet.
14. Draw a Thick Box Border around Cells B11 through D18.
25. Type the text shown in Table 34-2 into the specified
The next step is to protect the worksheet using the following cells.
steps:
Use the Underline Key to create the underlining. Press the
15. Select Cells D3 through D9 and D12 through D18, right Underline Key 34 times in Cell B30 and 18 times in Cell E30.
click on one of the selected cells, select Format Cells...
26. Merge Cells B2 and C2.
from the popup menu to bring up the Format Cells dia-
logue box (shown in Figure 32-33), select the 27. Merge Cells B3 and C3.
Protection tab, uncheck the Locked check box, and 28. Merge Cells D2 through F2.
click the OK button to close the dialogue box. 29. Merge Cells D3 through F3.
16. Protect the Takeoff worksheet by clicking on the Review
menu tab and clicking on the Protect Sheet button in
the Changes group (shown in Figure 32-34) to bring up
the Protect Sheet dialogue box (shown in Figure 32-35). TABLE 34-2 Data for Bid Worksheet
17. Type 1234 in the Password to unprotect sheet: text box. Cell Data
18. Click on the OK button to bring up the Confirm
Password dialogue box (shown in Figure 32-36). B2 Bill To:
19. Type 1234 in the Reenter password to proceed. text box D2 Ship To:
and click on the OK button to close the dialogue box B28 Half of the payment is due at delivery of materials. The re-
and protect the worksheet. maining payment is due upon completion of the roofing.
20. Check to make sure only Cells D3 through D15 and H4 B30 By:
through I13 can be selected by pressing the Down E30 Date:
Arrow key to move through the unlocked cells.
340 CHAPTER THIRTY-FOUR

TABLE 34-3 Formulas for Bid Worksheet The worksheet should now appear as shown in Figure 34-3.

Cell Data 43. Enter data into Cells D3 through D9 of the Takeoff
worksheet and verify that the data appears in the Bill To:
B3 =IF(Takeoff!D3=““,””,Takeoff!D3) area on the Bid worksheet.
D3 =IF(Takeoff!D12=““,””,Takeoff!D12) 44. Enter data into Cells D12 through D18 of the Takeoff
worksheet and verify that the data appears in the Ship
To: area on the Bid worksheet.
30. Enter the formulas in Table 34-3 into the specified cells.
45. Delete the data in Cells D3 through D9 and Cells D12
31. Copy Cell B3 to Cells B4 through B9.
through D18.
32. Copy Cell D3 to Cells D4 through D9.
46. Exit the workbook. There is no need to save it if you
33. Left justify Cells B2 through F9 by selecting Cells B2 saved the workbook in Step 42.
through F9, selecting the Home menu tab, and selecting
the Align Text Left button in the Alignment group
(shown in Figure 3-30).
34. Draw a Thick Box Border around Cells B2 through C9. AND BEYOND
35. Draw a Thick Box Border around Cells D2 through F9.
During the course of this book you have been introduced to
36. Select Cells A1 through F30 and change the font size to 14 Excel as a powerful tool for estimating. You have seen sample
point by selecting Cells A1 through F30, selecting the worksheets that can be used for the quantity takeoff, devel-
Home menu tab, and then selecting 14 from the Font oped a workbook for use in summarizing an estimate and
dropdown box in the Font group (shown in Figure 3-34). documenting the details of the estimate, incorporated error
37. Merge Cells B28 through F28 and change the font size to 8. checking into spreadsheets, automated repetitive tasks with
38. If needed, adjust the underlining in Cell B30 so that it macros, and set up a workbook to prepare the estimate and
fits in Cells B30 to D30 and the underlining in Cell E30 proposal for an asphalt shingle roof. With little effort, an es-
so that it fits in Cells E30 and F30. timator can develop a spreadsheet to prepare a conceptual
39. Merge Cells B30 through D30. estimate for specific types of construction projects or pre-
pare more complex quantity takeoff spreadsheets. The possi-
40. Merge Cells E30 and F30.
bilities are only limited by the mind and imagination of the
41. Protect the Bid worksheet. estimator. Enjoy the productivity and time-saving features of
42. Save the workbook. using Excel for estimating.

A B C D E F
1
2 Bill To: Ship To:
3
4
5
6
7
8
9
10
11 Materials Quantity Unit Price Total
12 Select Shingle - bundle #N/A #N/A
13 Cap - bundle #N/A #N/A
14 Roofing Nails - lbs 1.39 -
15 Select Underlyment - rolls #N/A #N/A
16 Underlayment Nails - C 1.00 -
17 10' Drip Edge - ea 2.99 -
18 10' Counter Flashing - ea 3.99 -
19 20' Ridge Vent - ea 42.00 -
20 Turtle Vents - ea 7.00 -
21 HVAC Flashing - ea 9.00 -
22 Plumbing Flashing - ea 4.00 -
23 Subtotal #N/A
24 Tax (6.5%) #N/A
25 Roofing Crew #N/A lhr 35.00 #N/A
26 Total #N/A
27
28 Half of the payment is due at delivery of materials. The remaining payment is due upon completion of the roofing.
29
30 By: . Date: .

FIGURE 34-3 The Bid Worksheet


APPENDIX A

REVIEW OF
ESTIMATING MATH

This appendix is provided as a review of the mathematical parallel to the drawing plane, but instead is being projected
equations and concepts needed to perform the quantity takeoff to a horizontal plane. When this occurs the Pythagorean
for those who struggle with math or just want to review the theorem needs to be used to determine the true distance.
necessary mathematical concepts before reading the chapters Let’s look at ways to determine distances.
covering the quantity takeoff. Do not let the math scare you.
The mathematical principles used in estimating are relatively Calculating Distances from Dimensions
simple and can be mastered with a little effort.
To determine distance from the dimensions, we may have to
use two or more dimensions to determine the correct dis-
tance. For example, to find the distance from the corner of

I n estimating we often need to determine lengths, areas,


and volumes in order to determine the quantities of ma-
terials needed to complete the project. In many cases we
need to convert the quantities from one set of units to an-
other set of units. Each of these topics is discussed in this ap-
the building to the center of the door (A) in Figure A-1 one
needs to add the distance from the corner of the building to
the center of the window to the distance from the center of
the window to the center of the door. Similarly, to deter-
mine the distance from the center of the window to the
pendix. Let’s first look at determining lengths. center of the closet wall (B) in Figure A-1 one needs to sub-
tract the distance from the corner of the building to the cen-
ter of the closet wall from the distance from the corner of the
LENGTHS building to the center of the window.
In most cases lengths are determined by calculating the dis- When adding dimensions with feet and inches, the feet
tances based on dimensions shown on the plans or by mea- must be added to the feet, the inches to the inches, and the
suring the distances using a scale, plan measurer, digitizer, fractions of an inch to the fractions of an inch. Before
or takeoff software package. There are cases, such as in a adding the dimensions, one must first make sure that all the
roof-framing plan, where the distances shown on the draw- fractions of an inch have the same denominator (the bot-
ings are not accurate because the building component is not tom portion of the fraction). This is done by multiplying

FIGURE A-1 Calculating Distance from Dimensions

341
342 APPENDIX A

the numerator (the top portion) of a fraction and its de- from the number of feet. Once this is accomplished, the feet
nominator by the same number (which doesn’t change the are subtracted from the feet, the inches from the inches, and
overall value of the fraction) in such a way that each frac- the fraction of an inch from the fraction of an inch, as shown
tion ends up with the same denominator. After you add the in the following example.
dimensions together, if the numerator of the fraction is
greater than the denominator of the fraction, subtract the
denominator from the numerator and add 1 inch to the EXAMPLE A-2
inches portion of the distance. Repeat this until the numer- Determine the distance between the center of the closet wall and
ator is less than the denominator. When the inches portion the center of the window (B) in Figure A-1.
exceeds 12 inches, subtract 12 inches from the inches por-
Solution: The distance is equal to the distance between the corner
tion of the distance and add 1 foot to the feet portion of the of the building and the center of the window (5 feet 5 1>2 inches)
distance. Repeat this until the inches portion of the distance minus the distance between the corner of the building and the cen-
is greater than or equal to 0 and less than 12. ter of the closet wall (2 feet 6 3>4 inches). First, make sure the frac-
tions of an inch have the same denominator. Do this by multiplying
the numerator (the top) and the denominator (the bottom) of 1>2
EXAMPLE A-1 by 2 to get 2>4 as follows:
Determine distance between the corner of the building and the
Distance ⫽ 5¿ 5 1>2– ⫺ 2¿ 6 3>4– ⫽ 5¿ 5 2>4– ⫺ 2¿ 6 3>4–
center of the door (A) in Figure A-1.
Next, make sure that the fraction of an inch in the larger dimension
Solution: The distance is equal to the distance between the corner
is greater than the fraction of an inch in the smaller dimension. In
of the building and the center of the window (5 feet 5 1>2 inches)
this example, this is not the case, so in the larger dimension the de-
plus the distance between the center of the window and the center
nominator (4) must be added to the numerator (2) and 1 sub-
of the door (3 feet 11 3>4 inches). First, convert the fractions of an
tracted from the inches as follows:
inch to a common denominator, in this case 1>4 inch, by multiply-
ing the numerator (the top) and the denominator (the bottom) of Distance ⫽ 5¿ 5 2>4– ⫺ 2¿ 6 3>4– ⫽ 5¿ 4 6>4– ⫺ 2¿ 6 3>4–
1>2 by 2 to get 2>4. The feet, the inches, and the fractions of an inch
Next, make sure the number of inches in the larger dimension is
are added together as follows:
greater than the number of inches in the smaller dimension. In
Distance ⫽ 5¿ 5 1>2– ⫹ 3¿ 11 3>4– ⫽ 5¿ 5 2>4– ⫹ 3¿ 11 3>4– this example, this is not the case, so 12 must be added to the
⫽ 8¿ 16 5>4– inches of the large dimension and 1 subtracted from the feet as
follows:
Next, reduce the fraction of inches to less than 1 inch by adding 1 to
the inches and subtracting 4 from the numerator of the fraction as Distance ⫽ 5¿ 4 6>4– ⫺ 2¿ 6 3>4– ⫽ 4¿ 16 6>4– ⫺ 2¿ 6 3>4–
follows: Now we can subtract the feet from the feet, the inches from the
Distance ⫽ 8¿ 16 5>4¿ ⫽ 8¿ 17 1>4– inches, and the fractions of an inch from the fractions of an inch
as follows:
Finally, reduce the inches portion of the dimension to less than 12
by subtracting 12 from the inches and adding 1 to the feet as fol- Distance ⫽ 4¿ 16 6>4– ⫺ 2¿ 6 3>4– ⫽ 2¿ 10 3>4–
lows: The distance is 2 feet 10 3>4 inches. 䊏
Distance ⫽ 8¿ 17 1>4– ⫽ 9¿ 5 1>4–
The distance is 9 feet 5 1>4 inches. 䊏
SCALING
When determining the distance between the center of Another method of determining the distance on the plans is
the wall and the center of the window (B) in Figure A-1, one scaling the distance. Plans are prepared at reduced scale. The
needs to subtract the smaller dimension (2 feet 6 3>4 inches) length of components on the plans may be determined by
from the larger dimension (5 feet 5 1>2 inches). Before these scaling the length using a scale, plan measurer, digitizer, or
dimensions are subtracted, the fractions of an inch must takeoff package. When scaling drawings it is important to
have the same denominator. This is done by multiplying make sure that the correct scale is used and that the drawings
both the numerator and the denominator of the fraction are to scale. This may be done by scaling a known dimension
with the lower denominator by the same number. Next, one and verifying that the scaled dimension is the same as the di-
must make sure the fraction of an inch in the larger dimen- mension shown on the drawing.
sion is greater than the fraction of an inch in the smaller di- A triangular architect’s scale includes the following
mension. If this is not the case, one adds the number in the scales: 1– ⫽ 1¿ (1 inch on the plans equals 1 foot of the build-
denominator to the number in the numerator of the frac- ing) 1>2– ⫽ 1¿, 1>4– ⫽ 1¿, 1>8– ⫽ 1¿, 3>16– ⫽ 1¿, 3>32– ⫽ 1¿,
tions of an inch and subtracts 1 from the whole number of 3>4– ⫽ 1¿, 3>8– ⫽ 1¿, 1 1>2– ⫽ 1¿, and 3– ⫽ 1¿ along with
inches. One must also make sure that the number of inches a standard 12-inch ruler. Most of the sides have two scales,
in the larger dimension is greater than the number of inches one reading left to right and the other reading right to left,
in the smaller dimensions. If this is not the case, 12 must be with one scale being one-half of the other scale. For exam-
added to the number of inches and 1 must be subtracted ple, the architect scale shown in Figure A-2 includes two
Review of Estimating Math 343

FIGURE A-2 Architect Scale

scales: 1>8– ⫽ 1¿ reading left to right and 1>4– ⫽ 1¿ read-


EXAMPLE A-3
ing right to left. For the 1>8– ⫽ 1¿ scale, the feet are read on
the right side of the scale and the inches on the left side of Determine the length of the wall shown in Figure A-3 using the
the scale. The feet for the 1>8– ⫽ 1¿ scale are the numbers scale at the bottom of the figure. The figure is drawn at a scale of
on the scale closest to the edge and increase in increments of 1>8– ⫽ 1¿.
4 from left to right. For the 1>8– ⫽ 1¿ scale, both the long Solution: The scale is lined up with a foot mark at the right side
and short lines represent a foot. For the 1>4– ⫽ 1¿ scale, the of the drawing, and the left side of the drawing is lined up within
feet are read on the left side of the scale and the inches on the inch marks at the left side of the scale. The feet and inches are
the right side of the scale. The feet for the 1>4– ⫽ 1¿ scale then read off of the scale. The length of the wall is 28 feet 3 inches
are the numbers on the scale furthest from the edge and in- long. 䊏
crease in increments of 2 from right to left. For the
1>4– ⫽ 1¿ scale, the long lines represent a foot and the short A triangular engineer’s scale typically has the following
lines represent a half of a foot. The 1>8– ⫽ 1¿ scale is read scales: 1:10 (1 inch equals 10 feet), 1:20, 1:30, 1:40, 1:50, and
by lining up the feet on the right side of the drawing such 1:60. Each side has only one scale and is read left to right.
that the left side of the drawing falls within the inch marks Inches are not included on the engineer’s scale. The engi-
on the left side of the scale. The feet are then read off the neer’s scale is read by lining up the zero on the left side of the
right side of the scale and the inches off the left side of the drawing and reading the feet on the right side of the scale.
scale.
The 1>4– ⫽ 1¿ scale is read by lining up the feet on the
EXAMPLE A-4
left side of the drawing such that the right side of the draw-
ing falls within the inch marks on the right side of the scale. Determine the length of the building shown in Figure A-4 using the
When reading the 1>4– ⫽ 1¿ scale, care must be taken to line scale at the bottom of the figure. The figure is drawn at a scale of
up with a whole foot mark—the longer marks—rather than 1– ⫽ 20¿.
the short marks, which indicate half a foot for this scale. The Solution: The scale is lined up with the zero; therefore, the feet can
feet are then read off the left side of the scale and the inches be read off of the right side of the scale. The length of the wall is be-
off the right side of the scale. tween 68 and 69 feet. 䊏

FIGURE A-3 Example A-3

FIGURE A-4 Example A-4


344 APPENDIX A

PYTHAGOREAN THEOREM
The Pythagorean theorem is useful when two dimensions at
right angles are used to describe a construction component.
This is commonly found in roof-framing plans, where the
run of the roof joists is shown on the framing plan and there
is a rise in the joist that is calculated from the slope of the
roof. The Pythagorean theorem is also useful for walls that
are constructed at odd angles to the rest of the building, as
we will see in Example A-5.
The Pythagorean theorem equates the length of the hy-
potenuse (C) of a right triangle, a triangle with one 90-de-
gree (right) angle, to the other two sides (A and B) of the tri-
angle. The Pythagorean theorem states that the square of the
hypotenuse equals the sum of the squares of the other two
sides of the triangle and is written as
FIGURE A-6 Example A-5
C2 ⫽ A2 ⫹ B2 (A-1)
where A, B, and C are the lengths of the sides of the triangle Geometric Method
as shown in Figure A-5. It does not matter which of the two
The geometric method breaks complex shapes down into six
sides adjacent to the 90-degree angle is designated A and
simpler geometric shapes: the circle, the square, the rectan-
which is designated B.
gle, the triangle, the trapezoid, and the parallelogram. These
shapes are shown in Figure A-7. The areas of these shapes are
EXAMPLE A-5 calculated as follows.
Determine the length of the diagonal wall in Figure A-6. Circle The area of a circle is calculated from the radius
Solution: Using Eq. (A-1), we get using the equation

C2 ⫽ A2 ⫹ B2 ⫽ (13 ft)2 ⫹ (9 ft)2 ⫽ 250 ft2 Area ⫽ ␲R2 (A-2)

Taking the square root of both sides to solve for C, we get or from the diameter using the equation
C ⫽ (250 ft2)0.5 ⫽ 15.81 ft ⫽ 15 ft 9 3>4 in D2
Area ⫽ ␲ (A-3)
ˇ ˇ

The wall is 15 feet 9 3>4 inches long. 䊏 4


where
AREAS ␲ ⫽ 3.14159
Estimators are often required to calculate areas in order to R ⫽ Radius of the Circle
complete the quantity takeoff. The area of an object is de- D ⫽ Diameter of the Circle
termined by one of two methods: the geometric method
and the coordinate method. Let’s look first at the geomet-
EXAMPLE A-6
ric method.
Find the area of a circle whose radius is 12 inches.
Solution: Using Eq. (A-2), we get
Area ⫽ ␲R2 ⫽ ␲(12 in)2 ⫽ 452 in2 䊏

Rectangle The area of a rectangle is calculated from its


length and width using the equation:
Area ⫽ LW (A-4)
where
L ⫽ Length
W ⫽ Width

EXAMPLE A-7
Find the area of a rectangle whose length is 24 inches and width is
FIGURE A-5 Right Triangle 12 inches.
Review of Estimating Math 345

FIGURE A-7 Basic Shapes

Solution: Using Eq. (A-4), we get


EXAMPLE A-9
Area ⫽ LW ⫽ (24 in)(12 in) ⫽ 288 in2 䊏
Find the area of a triangle whose base is 12 inches and height is
24 inches.
Square A square is a special case of a rectangle in which
the length and the width are equal; therefore, all of the sides Solution: Using Eq. (A-6), we get
are the same length. The area of a square is calculated from its
BH (12 in)(24 in)
length using the equation Area ⫽ ⫽ ⫽ 144 in2 䊏
2 2
Area ⫽ L 2
(A-5)
where Trapezoid A trapezoid is a four-sided figure with two
L ⫽ Length parallel sides. The area of a trapezoid is calculated from the
length of the two parallel sides and the perpendicular dis-
tance between the parallel sides using the equation
EXAMPLE A-8
(B ⫹ C)
Find the area of a square whose length is 12 inches. Area ⫽ D (A-7)
2
Solution: Using Eq. (A-5), we get
where
Area ⫽ L2 ⫽ (12 in)2 ⫽ 144 in2 䊏 B and C ⫽ Lengths of the Parallel Sides
D ⫽ Perpendicular Distance between the Parallel
Triangle The area of a triangle is calculated from its base
Sides
and height using the equation
BH
Area ⫽ (A-6)
2 EXAMPLE A-10

where Find the area of a trapezoid whose parallel sides are 12 and 16
inches long with a distance between the parallel sides of 24 inches.
B ⫽ Base
H ⫽ Height Solution: Using Eq. (A-7), we get

The height of the triangle must be measured perpendicular to (B ⫹ C) (12 in ⫹ 16 in)


Area ⫽ D⫽ (24 in) ⫽ 336 in2 䊏
the base. This is true for all of the triangles shown in Figure A-8. 2 2

FIGURE A-8 Triangles


346 APPENDIX A

FIGURE A-9 Complex Shape

Parallelogram A parallelogram is a four-sided plane fig- shape is determined by breaking the shape down into its
ure with opposite sides parallel. Because both pairs of oppo- basic geometric shapes, determining the area of the basic
site sides are parallel, the opposite sides have the same geometric shapes, and adding their areas as shown in the fol-
length. A parallelogram is a special case of a trapezoid in lowing example.
which B and D are the same length. The area of a parallelo-
gram is determined from the length of one side and the per-
pendicular distance between that side and the side parallel to EXAMPLE A-12
it, using the equation Determine the area of the shape in Figure A-9.
Area ⫽ BD (A-8) Solution: Divide the complex shape into two rectangles and a
square as shown in Figure A-10. The area of the left rectangle is de-
where
termined from Eq. (A-4) as follows:
B ⫽ Length of Each of a Given Pair of Parallel Sides
Area ⫽ LW ⫽ (30 ft)(20 ft) ⫽ 600 ft2
D ⫽ Perpendicular Distance between the Two Sides
That Have Length B The area of the right rectangle is determined from Eq. (A-4) as
follows:
Area ⫽ LW ⫽ (20 ft)(10 ft) ⫽ 200 ft2
EXAMPLE A-11
Find the area of a trapezoid whose parallel sides are 12 inches long The area of the square is determined from Eq. (A-5) as follows:
with a distance between the parallel sides of 24 inches. Area ⫽ L2 ⫽ (30 ft)2 ⫽ 900 ft2
Solution: Using Eq. (A-8), we get The area of the complex shape is determined by summing the areas
Area ⫽ BD ⫽ (12 in)(24 in) ⫽ 288 in 2
䊏 of the smaller shapes as follows:
Area ⫽ 600 ft2 ⫹ 200 ft2 ⫹ 900 ft2 ⫽ 1,700 ft2
Now that we have covered the basic geometric shapes,
let’s look at two complex shapes. The area of a complex The area of the complex shape is 1,700 square feet. 䊏

FIGURE A-10 Complex Shape


Review of Estimating Math 347

FIGURE A-11 Complex Shape

Sometimes it is advantageous to make the shape a part


of a larger shape and subtract the missing pieces as shown in
the following example.

EXAMPLE A-13
Determine the area of the shape in Figure A-9.
Solution: Make the complex shape into a 60-foot by 30-foot rec-
tangle less a 10-foot by 10-foot square as shown in Figure A-11. The
area of the rectangle is determined from Eq. (A-4) as follows: FIGURE A-13 Square-Less-a-Quarter-Circle
Area ⫽ LW ⫽ (60 ft)(30 ft) ⫽ 1,800 ft2
The area of the square is determined from Eq. (A-5) as follows: where
Area ⫽ L2 ⫽ (10 ft)2 ⫽ 100 ft2 ␲ ⫽ 3.14159
R ⫽ Radius of the Circle
The area of the complex shape is determined by subtracting the
area of the square from the area of the rectangle as follows: The use of this equation is shown in the following
Area ⫽ 1,800 ft ⫺ 100 ft ⫽ 1,700 ft
2 2 2 example.

The area of the complex shape is 1,700 square feet, which is the
same as the answer from Example A-12. 䊏 EXAMPLE A-14
Determine the area of the complex shape in Figure A-14.
Another common example of creating a large shape and
subtracting the missing pieces arises in the case of an outside Solution: Divide the shape into two rectangles and a square-less-a-
radius that creates a complex shape as shown in Figure A-12. quarter-circle as shown in Figure A-15.
The area of the left rectangle is determined from Eq. (A-4) as
The area of this shape is calculated by taking the area of a
follows:
square of length R and subtracting the area of a quarter of a
circle as shown in Figure A-13. Area ⫽ LW ⫽ (70 ft)(30 ft) ⫽ 2,100 ft2
The area is calculated by using the equation The area of the right rectangle is determined from Eq. (A-4) as
␲ follows:
Area ⫽ R2a1 ⫺ b (A-9)
4 Area ⫽ LW ⫽ (40 ft)(30 ft) ⫽ 1,200 ft2
The area of the square-less-a-quarter-circle is determined from
Eq. (A-9) as follows:
␲ ␲
Area ⫽ R2 a1 ⫺ b ⫽ (20 ft)2 a1 ⫺ b ⫽ 86 ft2
4 4
The area of the complex shape is determined by summing the areas
of the smaller shapes as follows:
Area ⫽ 2,100 ft2 ⫹ 1,200 ft2 ⫹ 86 ft2 ⫽ 3,386 ft2
FIGURE A-12 Complex Shape The area of the complex shape is 3,386 square feet. 䊏
348 APPENDIX A

FIGURE A-14 Complex Shape

FIGURE A-15 Complex Shape


Review of Estimating Math 349

FIGURE A-16 Complex Shape

Coordinate Method
The coordinate method is used to calculate the area of a
complex shape in which all the sides are straight by using the
coordinates of the intersections of the sides. The area of an
n-sided shape is determined by the following equation:
Area ⫽ 0.5[(X2Y1 ⫹ X3Y2 ⫹ p ⫹ XnYn⫺1 ⫹ X1Yn)
⫺ (X1Y2 ⫹ X2Y3 ⫹ p ⫹ Xn⫺1Yn ⫹ XnY1)] (A-10)
The use of this equation is shown in the following
example.

EXAMPLE A-15
Determine the area of the complex shape in Figure A-16.
Solution: Using the intersection in the lower-left corner as Point 1,
proceeding around the complex shape in a clockwise direction, and
using Eq. (A-10), we get
Area ⫽ 0.5[(0 ⫻ 0 ⫹ 20 ⫻ 30 ⫹ 20 ⫻ 30 ⫹ 30 ⫻ 20 FIGURE A-17 Table for Coordinate Method
⫹ 30 ⫻ 20 ⫹ 60 ⫻ 30 ⫹ 60 ⫻ 30 ⫹ 0 ⫻ 0) ⫺ (0 ⫻ 30
⫹ 0 ⫻ 30 ⫹ 20 ⫻ 20 ⫹ 20 ⫻ 20 ⫹ 30 ⫻ 30 ⫹ 30 ⫻ 30
⫹ 60 ⫻ 0 ⫹ 60 ⫻ 0] ft2
Area ⫽ 0.5[(0 ⫹ 600 ⫹ 600 ⫹ 600 ⫹ 600 ⫹ 1,800 ⫹ 1,800 ⫹ 0)
⫺ (0 ⫹ 0 ⫹ 400 ⫹ 400 ⫹ 900 ⫹ 900 ⫹ 0 ⫹ 0)] ft2
Area ⫽ 0.5[6,000 ⫺ 2,600] ⫽ 0.5[3,400] ⫽ 1,700 ft2
Because Figure A-16 is the same size as Figure A-9, they should have
the same areas, which they do. 䊏

An alternate method for calculating the area using the


coordinate method is to set up the coordinates as shown in
Figure A-17, with the coordinates for the first point at both
the top and bottom.
Starting with the second row, the X-coordinate is mul-
tiplied by the Y-coordinate from the previous row, and the
resultant is entered in the second row of the first column as
shown in Figure A-18. This is repeated for the third
through the last rows. Next, starting with the second row,
the Y-coordinate is multiplied by the X-coordinate from FIGURE A-18 Completed Table for Coordinate Method
350 APPENDIX A

the previous row, and the resultant is entered in the second ␲D 2H


row of the fourth column as shown in Figure A-18. This is Volume ⫽ (A-12)
4
repeated for the third to the last rows. Next, the first and
fourth columns are added as shown in Figure A-18. where
To find the area, the sum of the fourth column is sub- ␲ ⫽ 3.14159
tracted from the sum of the first column and the resultant R ⫽ Radius of the Circle
is divided by two. For the coordinates in Figures A-17 and
D ⫽ Diameter of the Circle
A-18, which correspond to the coordinates of Example A-15,
the area is calculated as follows: H ⫽ Height Measured Perpendicular to the Area of the
Circle
Area ⫽ 0.5(6,000 ⫺ 2,600) ⫽ 0.5(3,400) ⫽ 1,700 ft2
This gives us the same area as was found in Example A-15.
EXAMPLE A-16
Find the volume of a cylinder whose radius is 1 foot and height is
VOLUMES 10 feet.

In addition to determining distances and areas, estimators Solution: Using Eq. (A-11), we get
often must determine volumes. Most volumes are created by Volume ⫽ ␲R2H ⫽ ␲(1 ft)2(10 feet) ⫽ 31.4 ft3 䊏
extending a two-dimensional shape along a line perpendicu-
lar to the plane it occupies, as in the case of a cylinder (circle),
a column (a square or rectangle), or a prism (triangle), or Column
by extending the shape to a point, as is the case with a cone The volume of a column is calculated by multiplying the
or a pyramid. The basic volumetric shapes are shown in Fig- area of a rectangle by the height of the column, where the
ure A-19. The volumes of these shapes are calculated as follows. height of the column is measured perpendicular to the area
of the rectangle. Remember, a square is a special case of a
Cylinder rectangle in which L and W are equal. The volume of a rec-
tangular column is calculated from its length, width, and
The volume of a cylinder is calculated by multiplying the
height using the equation
area of a circle by the height of the cylinder, where the height
of the cylinder is measured perpendicular to the area of the Volume ⫽ LWH (A-13)
circle. The volume of a cylinder is calculated from the radius
by using the equation where
L ⫽ Length
Volume ⫽ ␲R2H (A-11) W ⫽ Width
or from the diameter, which is twice the radius, by using the H ⫽ Height Measured Perpendicular to the Area of the
equation Rectangle

FIGURE A-19 Volumetric Shapes


Review of Estimating Math 351

FIGURE A-20 Pyramids

where
EXAMPLE A-17
L ⫽ Length
Find the volume of a column whose height is 10 feet, length is 2
W ⫽ Width
feet, and width is 1 foot.
H ⫽ Height Measured Perpendicular to the Area of the
Solution: Using Eq. (A-12), we get Rectangle
Volume ⫽ LWH ⫽ (2 ft)(1 ft)(10 ft) ⫽ 20 ft3 䊏 This is true for all of the pyramids shown in Figure A-20,
even though their points are at different locations.
Prism
The volume of a prism is calculated by multiplying the area EXAMPLE A-19
of a triangle by the length of the prism (length is used be-
cause height has already been used to describe the triangle), Find the volume of a pyramid whose height is 12 feet, length is 2 feet,
and width is 1 foot.
where the length of the prism is measured perpendicular to
the area of the triangle. The volume of a prism is calculated Solution: Using Eq. (A-15), we get
from its length, base, and height using the equation (2 ft)(1 ft)(12 ft)
LWH
Volume ⫽ ⫽ ⫽ 8 ft3 䊏
BHL 3 3
Volume ⫽ (A-14)
2 The volume of a cone is calculated from the radius
where using the equation
H ⫽ Height Measured Perpendicular to the Base of the ␲R2H
Triangle Volume ⫽ (A-16)
3
B ⫽ Base
or from the diameter using the equation
L ⫽ Length Measured Perpendicular to the Area of the
Triangle ␲D 2H
Volume ⫽ (A-17)
12
EXAMPLE A-18 where
Find the volume of a prism whose height is 5 feet, length is 20 feet, ␲ ⫽ 3.14159
and base is 3 feet. R ⫽ Radius of the Circle
Solution: Using Eq. (A-14), we get D ⫽ Diameter of the Circle
BHL (3 ft)(5 ft)(20 ft) H ⫽ Height Measured Perpendicular to the Area of the
Volume ⫽ ⫽ ⫽ 150 ft3 䊏 Circle
2 2

Pyramids and Cones EXAMPLE A-20


For any volumetric shape that is created by extending the Find the volume of a cone whose radius is 1 foot and height is 10 feet.
shape to a point, such as a cone or pyramid, the volume is
Solution: Using Eq. (A-16), we get
one-third of the area of the base of the object times the
height of the object, where the height is measured per- ␲R2 ␲(1 ft)2(10 ft)
Volume ⫽ ⫽ ⫽ 10.5 ft3 䊏
pendicular to the area. For a pyramid with a rectangular 3 3
base, the volume of the pyramid is calculated by using the
equation Volume of a Shape with a Constant Area
LWH The volume of any shape with a constant area over a given
Volume ⫽ (A-15)
3 length is calculated by multiplying the cross-sectional area of
352 APPENDIX A

for which volume can be calculated. For example, the


complex volume created by a building excavation shown
in Figure A-21 can be divided into four pyramids (one at
each corner), four prisms (one along each side), and one
column (located in the center), as shown in Figure A-22.
The volume of the complex shape is calculated by deter-
mining the volumes for the pyramids, prisms, and column
and adding them together. Additional methods of approx-
imating the volume of complex bodies are discussed in
Chapter 16.
FIGURE A-21 Complex Shape

the shape by the length of the object over which the cross- CONVERSION FACTORS
sectional is representative of the shape of the object, using
So far all of the example problems have been in the same
the equation
units, and we have not had to convert units. Typical unit
Volume ⫽ AL (A-18) conversions are given in Table A-1.
The two most common mistakes when converting from
where
one set of units to another set of units are (1) using the
A ⫽ Cross-Sectional Area of the Shape Measured wrong conversion factor and (2) multiplying by the conver-
Perpendicular to the Length sion factor when one should be dividing or vice versa. The
L ⫽ Length best way to avoid these mistakes is to include the units in the
The length should be measured along the centerline of the calculations and make sure the answer is in the correct units
shape, and the cross-sectional area should be measured by canceling out units.
perpendicular to the centerline of the shape. When the cen-
terline of the shape forms a curved line, the volume is an
approximation.
TABLE A-1 Conversion Factors
EXAMPLE A-21 Length Volume
Find the volume of a curb and gutter whose cross-sectional area is
1.7 ft2 and whose length is 200 ft.
1 mile ⫽ 5,280 feet (ft) 1 yd3 ⫽ 27 ft3
1 yard (yd) ⫽ 3 ft 1 ft3 ⫽ 1,728 in3
Solution: Using Eq. (A-18), we get
1 foot ⫽ 12 inches (in) 1 ft3 ⫽ 7.48 gallons
Volume ⫽ AL ⫽ (1.7 ft2)(200 ft) ⫽ 340 ft3 䊏
Area Weight
Complex Volumes 1 acre ⫽ 43,560 ft2 1 ton ⫽ 2,000 pounds (lb)
Like the areas of complex two-dimensional shapes, the 1 yd2 ⫽ 9 ft2 1 hundredweight (cwt) ⫽ 100 lb
volumes of complex three-dimensional bodies can be cal- 1 ft2 ⫽ 144 in2 1 lb ⫽ 16 ounces (oz)
culated by breaking the complex body into simpler shapes

FIGURE A-22 Complex Shape


Review of Estimating Math 353

EXAMPLE A-22
Convert 216 square inches into square feet.
Solution: To convert square inches to square feet, we need to di-
vide the square inches by 144 in2/ft2 as follows:
216 in2 in2 ⫻ ft2
216 in2 ⫽ 2 2 ⫽ 1.5 ⫽ 1.5 ft2
144 in /̌ft
ˇ in2
Two hundred and sixteen square inches equals 1.5 square feet. 䊏

In Example A-22, had we tried to multiply by 144 in2/ft2,


we would have ended up with the following:
in2 in2 ⫻ in2 in4
216 in2 ⫽ 216 in2 ⫻ 144 2
⫽ 31,104 2
⫽ 31,104 2
ft ft ft
FIGURE A-23 A Board Foot
In this case the inches would not cancel out, leaving us
with in4/ft2 as the units for our answer, not the units we
wanted. Likewise, had we used the wrong conversion factor defined as the amount of wood contained in a 12-inch by
and divided by 1,728 in3/ft3, we would have ended up with 12-inch by 1-inch nominal board. Figure A-23 shows the de-
the following: finition of a board foot. The nominal dimensions are the di-
mensions used to describe the board, for example, 2 ⫻ 4 or
216 in2 in2 ⫻ ft3 ft3
216 in2 ⫽ ⫽ 0.125 ⫽ 0.125 2 ⫻ 12. For dimensional lumber, the actual dimensions are
1,728 in3/ft3 in3 in always smaller than the nominal dimensions. A 2 ⫻ 4 typi-
In this case, the inches squared on the top reduce the cally measures 1 1>2 inches by 3 1>2 inches. The units of
ˇ ˇ ˇ ˇ

inches cubed on the bottom to inches, leaving us with ft3/in board feet are inches-feet-squared (in-ft2).
for our units—not the answer we wanted. I cannot empha- The number of board feet in a piece of lumber is calcu-
size this enough. Write your units down and cancel the units lated by using the equation
out to make sure that your answer is in the units you want! (Thickness)(Width)(Lineal Feet)
Board Feet ⫽ (A-19)
12 in>ft
Dimensional Analysis
where the nominal thickness and the nominal width are
In dimensional analysis one writes the equation without the in inches.
numbers to make sure the units cancel out. This is useful for
checking your units without having all of the numbers,
which at times can be confusing. Dimensional analysis on EXAMPLE A-23
Example A-22 is done as follows: Find the number of board feet in a 10-foot long 2 ⫻ 4.
in2
in ⫻ ft
2 2
Solution: Using Eq. (A-19), we get
in2 ⫽ ⫽ ⫽ ft2
(in2/ft2) in2 (Thickness)(Width)(Lineal Feet)
Board Feet ⫽
12 in/ft
Board Feet (2 in)(4 in)(10 ft)
⫽ ⫽ 6.67 in-ft2 ⫽ 6.67 bft
12 in/ft
Lumber, especially random lengths and finish lumber, are
often purchased by the board foot. A board foot (bft) is There are 6.67 board feet in a 10-foot-long 2 ⫻ 4. 䊏
APPENDIX B

SAMPLE JOB COST CODES

last three digits are company specific and are used to collect

T he following is a sample list of standardized job cost


codes for a commercial construction company along
with a list of typical items that would be included in
the cost code. The first two digits of each cost code correspond
to the divisions of the 2010 edition of the MasterFormat. The
cost data in a way that matches the company’s individual work
practices. The cost codes should not be confused with the
numbering of the MasterFormat. For more information on
the MasterFormat visit www.csinet.org/MasterFormat.

Code Description Typical Items

01-000 GENERAL REQUIREMENTS


01-300 Supervision Labor for supervision and supervisor’s truck and tools.
01-500 Temporary Utilities Temporary utility bills including electricity, water, sewer, natural gas,
garbage, and propane. Temporary electrical, sewer, water, and gas
lines and connection fees for temporary utilities.
01-510 Temporary Phone Phone bills including long-distance service, mobile phones, and
temporary phone lines.
01-520 Temporary Facilities Temporary office trailer, office furniture, copier, computers, fax
machine, telephone equipment, first aid supplies, and office supplies.
01-700 Cleanup Labor and supplies for general cleanup.
02-000 EXISTING CONDITIONS
02-400 Demolition Demolition of existing structures.
03-000 CONCRETE
03-200 Rebar Rebar materials used in the construction of building concrete and
masonry.
03-300 Footing and Foundation—Labor Labor, forms, ties, tie wire, equipment, and all other items (except
concrete, rebar, and concrete pump) needed to pour footings and
foundations for buildings.
03-310 Footing and Foundation—Concrete Concrete to pour footings and foundations for buildings.
03-320 Slab/Floor—Labor Labor, forms, ties, tie wire, equipment, and all other items (except
concrete, rebar, and concrete pump) needed to pour building slabs
and floors.
03-330 Slab/Floor—Concrete Concrete to pour building slabs and floors.
03-340 Concrete Pump Concrete pump for placement of building concrete.

354
Sample Job Cost Codes 355

03-400 Pre-cast Concrete Pre-cast concrete used in buildings.


03-500 Light-weight Concrete Light-weight concrete and gypcrete.
04-000 MASONRY
04-200 Masonry Concrete Masonry Unit (CMU) and face brick used in buildings.
05-000 METALS
05-100 Structural Steel Structural steel materials including beams, girders, columns,
lintels (not provided by mason), bracing, and bolts through the
structural steel. Excludes installation and bolts not through the
structural steel.
05-200 Joist and Deck Steel open web joists and metal deck. Excludes installation.
05-500 Metal Fabrications Stairs, handrail, decorative steel, pipe bollards, and other
nonstructural steel. Excludes installation.
05-900 Erection Installation of structural steel, joist, deck, and metal fabrications,
including equipment and welding supplies. Excludes installation of
embeds.
06-000 WOOD, PLASTICS, AND COMPOSITES
06-100 Rough Carpentry Labor, nails, and equipment to install wood framing.
06-110 Lumber Rough carpentry materials including lumber, engineered lumber
(glue-laminated beams, wood I-joists, and so forth), wood siding,
framing hardware, bolts, fasteners, and sill seal. Excludes nails.
06-120 Trusses Pre-manufactured wood trusses.
06-200 Finish Carpentry Labor, nails, and equipment to install metal doors, wood doors,
hardware, wood trim, bathroom accessories, fire extinguishers
and cabinets, and roof specialties when not installed by their
suppliers.
06-210 Wood Trim Wood trim, including base, casing, chair rail, and crown molding.
06-400 Cabinetry and Countertops Furnish and install cabinetry and, if included in the bid,
countertops.
06-410 Countertops Furnish and install countertops when not included with cabinetry
bid.
07-000 THERMAL AND MOISTURE PROTECTION
07-100 Waterproofing Furnish and install waterproofing, dampproofing, and drain board.
07-200 Insulation Furnish and install batt and blown insulation.
07-210 Ridged Insulation Furnish and install ridged insulation.
07-220 Stucco Furnish and install synthetic stucco and Exterior Insulation and
Finish System (EIFS).
07-400 Siding Furnish and install vinyl and aluminum siding, soffit, and fascia.
07-500 Roofing Furnish and install asphalt, metal, built-up, and membrane roofing
including metal trim, asphalt-impregnated felt, ice and water shield,
and flashing not provided by other subcontractors. Install flashings
provided by other subcontractors.
07-600 Sheet Metal Furnish and install flashing (excluding roof flashings) and general
sheet metal.
07-700 Roof Specialties Furnish roof hatches, walkways, skylights, and so forth. May include
installation.
07-710 Rain Gutters Furnish and install rain gutters and down spouts.
07-800 Fireproofing Furnish and install fire caulk and fire collars not provided by other
subcontractors.
07-900 Caulking and Sealants Furnish and install caulking not provided by other subcontractors.
356 APPENDIX B

08-000 OPENINGS
08-100 Metal Doors and Frames Furnish hollow-metal doors and frames.
08-110 Wood Doors Furnish wood doors, wood frames, and prehung residential-grade
doors. Prehung doors include butts and thresholds.
08-300 Overhead Doors Furnish and install sectional and coiling overhead doors and coiling
grilles including all necessary hardware.
08-400 Storefronts Furnish and install glass and aluminum storefronts including all
necessary hardware (cylinders by hardware supplier).
08-500 Windows Vinyl, vinyl-clad, wood, aluminum, and aluminum-clad residential
windows.
08-700 Hardware Furnish hardware for hollow-metal and wood doors and cylinders
for storefront doors.
08-800 Glass and Glazing Furnish and install glazing in hollow-metal doors, wood doors, and
window frames.

09-000 FINISHES
09-200 Drywall Furnish and install drywall, drywall draft stops, and, if included in
the bid, nonstructural metal studs.
09-210 Metal Studs Furnish and install nonstructural metal studs, if not included with
drywall bid.
09-300 Ceramic Tile Furnish and install ceramic tile and marble.
09-500 Acoustical Ceilings Furnish and install acoustical ceiling with grid.
09-600 Flooring Furnish and install carpet, vinyl, vinyl composition tile (VCT), wood
flooring, laminate flooring, and rubber base.
09-700 Wall Coverings Furnish and install fabric and paper wall coverings.
09-900 Paint Furnish and install paints and stains for walls, ceilings, floors, doors,
and trim.

10-000 SPECIALTIES
10-100 Signage Furnish and install interior building signage including room numbers,
bathroom signage, Americans with Disabilities Act (ADA) insignias,
and building directories.
10-200 Toilet Partitions Furnish and install toilet partitions and screens.
10-210 Toilet and Bath Accessories Furnish and install toilet and bath accessories, including toilet paper
holders, soap dispensers, paper towel dispensers, built-in waste
receptacles, sanitary napkin dispensers, sanitary napkin disposal
receptacles, baby changing stations, mirrors, shower enclosures, and
medicine cabinets.
10-400 Fire Extinguishers and Cabinets Furnish and install fire extinguishers and fire extinguisher cabinets.

11-000 EQUIPMENT
11-300 Appliances Residential appliances, including dishwashers, ranges, cooktops,
ovens, refrigerators, ice makers, washers, and dryers.

12-000 FURNISHINGS
12-200 Window Treatments Furnish and install blinds and curtains.

14-000 CONVEYING EQUIPMENT


14-200 Elevators Furnish and install elevators, including excavation for hydraulic
ram.

21-000 FIRE SUPPRESSION


21-100 Fire Sprinklers Furnish and install fire sprinkler systems.
Sample Job Cost Codes 357

22-000 PLUMBING
22-100 Plumbing Furnish and install building water supply and sanitary sewer systems
to five feet outside the building, plumbing fixtures and garbage
disposals. Provide flashing for plumbing roof penetrations.
23-000 HEATING, VENTILATION,
AND AIR-CONDITIONING
23-100 HVAC Furnish and install heating, ventilation, and air-conditioning
systems. Provide flashing for HVAC roof penetrations.
26-000 ELECTRICAL
26-100 Electrical Furnish and install electrical, including power, lighting, and control
systems. Provide flashing for electrical roof penetrations.
27-000 COMMUNICATIONS
27-100 Communications Furnish and install communication (telephone and data). Provide
flashing for communication roof penetrations.
31-000 EARTHWORK
31-100 Clearing and Grubbing Clearing and grubbing of site.
31-200 Grading and Excavation Mass excavation and rough grading of site, including import or
export of soils. Excavation, backfill, and import or export of soils for
structures.
32-000 EXTERIOR IMPROVEMENTS
32-100 Asphalt Furnish and install asphalt pavement, slurry seals, base under
asphalt, prime coat, and tack coat.
32-110 Site Concrete—Labor Labor, forms, ties, tie wire, equipment, and all other items (except
concrete and rebar) needed to pour site concrete, including
sidewalks, driveways, curbs, gutters, waterways, and slabs outside
the building.
32-120 Site Concrete—Concrete Concrete to pour site concrete, including sidewalks, driveways, curbs,
gutters, waterways, and slabs outside the building.
32-130 Rebar Rebar materials used in the construction of site concrete and
retaining walls.
32-300 Fencing Chain link, masonry (including footings), wood, ornamental steel,
and vinyl fencing, including gates.
32-310 Retaining Walls Furnish and install reinforced concrete (excluding rebar materials),
block, or rock retaining walls, including footings.
32-320 Dumpster Enclosures Furnish and install dumpster enclosures, including footings and
foundation, block wall, cap, and gates.
32-330 Signage Furnish and install traffic signs, permanent project signs, and
monuments.
32-340 Outside Lighting1 Furnish and install lighting mounted on poles and buildings to
illuminate the site, including underground wiring.
32-900 Landscaping Finish grading. Top soil import and placement. Furnish and install
irrigation (sprinkler) systems, plants (trees, shrubs, bushes, and
ground cover), sod, and bark.
33-000 UTILITIES
33-100 Water Line Furnish and install site culinary water lines beginning five feet
outside the perimeter of the building, including gravel and bedding
materials.
1
Site lighting is placed here instead of Division 26000 to keep building costs separate from site costs.
358 APPENDIX B

33-300 Sanitary Sewer Furnish and install site sanitary sewer lines beginning five feet
outside the perimeter of the building, including gravel and bedding
materials.
33-400 Storm Drain Furnish and install storm drain, including gravel and bedding
materials.
33-500 Gas Lines Furnish and install site natural gas lines beginning at the low-
pressure side of the gas meter, including any fees charged by the
natural gas provider.
33-700 Power Lines Furnish and install electrical power lines to the meter base, including
transformers located outside the building and any fees charged by
the electrical power provider.
33-800 Telephone Lines Furnish and install phone lines to the building, including any fees
charged by the telephone company.
APPENDIX C

SAMPLE LABOR
PRODUCTIVITY RATES

S
Where possible, estimators should use productivity rates
ample labor productivity rates are shown in the fol- based on the company’s past performance. When this data is
lowing table. These rates are for use in classroom not available, the estimator should consult a current, more
exercises and are based on a review of a number of detailed source of productivity rates.
published productivity rates and personal experience.

Item Productivity

03-000 CONCRETE
0.13–0.20 lhr/sfca Forms, columns, square to 24– ⫻ 24–
0.06–0.09 lhr/lft Forms, footings, 2 ⫻ 12– high
0.09–0.15 lhr/sfca Forms, walls
0.20–0.30 lhr/ea Rebar, 20¿ continuous horizontal, to #6
0.05–0.07 lhr/ea Rebar, dowel, to #6
0.08–0.13 lhr/ea Rebar, ring tie
0.12–0.20 lhr/ea Rebar, vertical, to 12¿ high, to #6
0.05–0.10 lhr/ea Anchor bolt
0.25–0.50 lhr/ea Embed
0.40–0.60 lhr/cyd Concrete placement, columns
0.40–0.50 lhr/cyd Concrete placement, continuous footings
0.40–0.60 lhr/cyd Concrete placement, slabs
0.60–1.00 lhr/cyd Concrete placement, spot footings
0.50–0.70 lhr/cyd Concrete placement, walls
0.010–0.015 lhr/sft Concrete finishing
04-000 MASONRY
0.09–0.14 lhr/sft Concrete masonry unit, including rebar
0.16–0.20 lhr/sft Brick facing
05-000 METALS
0.07–0.10 lhr/lft Steel beams
0.90–1.20 lhr/ea Steel columns

359
360 APPENDIX C

0.04–0.07 lhr/lft Steel joists


0.007–0.014 lhr/sft Metal deck
06-000 WOODS, PLASTICS, AND COMPOSITES
0.03–0.04 lhr/ft Blocking
0.60–1.00 lhr/ea Columns
0.04–0.06 lhr/lft Fascia
1.0–1.5 lhr/ea Girders and beams, to 20¿ long
0.015–0.019 lhr/lft Joists
0.02–0.04 lhr/lft Rafters
0.011–0.016 lhr/sft Sheathing
0.02–0.05 lhr/lft Sills and ledgers
0.04–0.06 lhr/sft Soffit
0.60–1.00 lhr/ea Trusses, to 40¿ span
0.13–0.16 lhr/lft Walls, 16– O.C., to 10¿ high
0.25–0.50 lhr/ea Add for door opening
0.50–0.75 lhr/ea Add for window opening
0.015–0.040 lhr/lft Trim
0.60–1.00 lhr/ea Cabinetry
0.25–0.33 lhr/lft Countertops, plastic laminate
07-000 THERMAL AND MOISTURE PROTECTION
0.20–0.40 lhr/squ Building paper
0.005–0.008 lhr/sft Insulation—batt
0.010–0.016 lhr/sft Insulation—blown
0.05–0.06 lhr/sft Exterior Insulation and Finish System
1.4–2.2 lhr/squ Shingles, asphalt
0.04–0.05 lhr/sft Fascia, aluminum or vinyl
0.04–0.06 lhr/lft Fascia, wood
0.03–0.04 lhr/sft Siding, aluminum or vinyl
0.020–0.035 lhr/sft Siding, wood board
0.011–0.025 lhr/sft Siding, wood sheet
0.04–0.05 lhr/sft Soffit, aluminum or vinyl
0.04–0.06 lhr/sft Soffit, wood
0.010–0.015 lhr/sft Membrane roofing
0.02–0.03 lhr/lft Sheet metal, drip edge
0.04–0.08 lhr/lft Sheet metal, flashings
3.0–5.0 lhr/ea Roof hatch
08-000 OPENINGS
2.0–4.0 lhr/ea Doors, commercial exterior
1.0–2.5 lhr/ea Doors, commercial interior
1.0–2.0 lhr/ea Doors, residential exterior
0.5–1.0 lhr/ea Doors, residential interior
2.0–4.0 lhr/ea Sectional overhead door
1.0–1.5 lhr/ea Add for opener
0.5–1.0 lhr/ea Add for keyless entry
0.10–0.16 lhr/sft Storefront
Sample Labor Productivity Rates 361

0.8–1.0 lhr/ea Windows—residential


0.5–1.0 lhr/ea Hardware, lockset or deadbolt
1.0–2.0 lhr/ea Hardware, panic
0.20–0.40 lhr/ea Hardware, stop
0.40–0.70 lhr/ea Hardware, threshold
1.0–1.50 lhr/ea Hardware, weather stripping
09-000 FINISHES
0.018–0.020 lhr/sft Metal stud wall
0.015–0.020 lhr/sft Drywall, taped and finished
0.08–0.11 lhr/sft Ceramic tile
0.020–0.035 lhr/sft Suspended acoustical ceilings
0.04–0.08 lhr/sft Wood and laminate floors
0.03–0.04 lhr/sft Sheet vinyl
0.015–0.020 lhr/sft Vinyl composition tile
0.25–0.30 lhr/lft Rubber base
0.14–0.17 lhr/syd Carpet and pad
0.004–0.007 lhr/sft Paint, walls, sprayed, per coat
0.006–0.010 lhr/sft Paint, walls, rolled, per coat
0.008–0.015 lhr/lft Paint, trim, brushed, per coat
0.5–1.0 lhr/ea Paint, doors, brushed, per coat
10-000 SPECIALTIES
0.33–0.50 lhr/ea Door signs
0.33–0.67 lhr/ea Grab bar
0.50–1.00 lhr/ea Mirror
0.50–1.00 lhr/ea Paper towel dispenser
3.0–4.0 lhr/ea Shower surround
0.25–0.50 lhr/ea Toilet paper holder
0.25–0.50 lhr/ea Towel bar
2.00–3.00 lhr/ea Fire extinguisher cabinet
21-000 FIRE SUPPRESSION
0.12–0.20 lhr/ft Fire sprinkler, to 1.5– pipe, includes hangars
0.20–0.25 lhr/ft Fire sprinkler, 2– pipe, includes hangars
0.28–0.32 lhr/ft Fire sprinkler, 2.5– pipe, includes hangars
0.32–0.38 lhr/ft Fire sprinkler, 3– pipe, includes hangars
0.14–0.33 lhr/ea Fire sprinkler, to 1.5– fitting
0.33–0.50 lhr/ea Fire sprinkler, 2– fitting
0.40–0.60 lhr/ea Fire sprinkler, 2.5– fitting
0.50–0.75 lhr/ea Fire sprinkler, 3– fitting
0.50–0.80 lhr/ea Fire sprinklers, sprinkler head and drop
3.0–4.0 lhr/ea Fire sprinklers, standpipe
24–32 lhr/ea Fire sprinklers, valve assembly
22-000 PLUMBING
0.8–1.0 lhr/ea Clean–outs
4.0–5.0 lhr/ea Drinking fountain, rough in supply and waste
2.0–2.5 lhr/ea Drinking fountain, finish
362 APPENDIX C

1.0–1.5 lhr/ea Floor drain


8.0–10.0 lhr/ea Kitchen sink, rough in supply and waste
2.5–3.5 lhr/ea Kitchen sink, finish
6.0–8.0 lhr/ea Lavatory, rough in supply and waste
2.5–3.0 lhr/ea Lavatory, finish
3.0–4.0 lhr/ea Roof drain, including wye
7.0–8.0 lhr/ea Shower, rough in supply and waste
6.0–8.0 lhr/ea Shower, finish, including shower door
7.0–8.0 lhr/ea Tub, rough in supply and waste
2.5–4.0 lhr/ea Tub, finish
6.0–8.0 lhr/ea Urinal, rough in supply and waste
5.0–6.0 lhr/ea Urinal, finish
0.5–1.0 lhr/ea Valve, to 2–
6.0–8.0 lhr/ea Water closet, rough in supply and waste
3.0–3.5 lhr/ea Water closet, finish
4.0–6.0 lhr/ea Water heater
23-000 HVAC
0.10–0.13 lhr/lft Duct, to 12⬙ ⫻ 24⬙
0.12–0.15 lhr/lft Duct, 12⬙ ⫻ 30⬙
0.05–0.06 lhr/lft Duct, 4⬙-diameter vent pipe
0.05–0.06 lhr/lft Duct, 6⬙ diameter
0.09–0.10 lhr/lft Duct, 9⬙diameter
0.13–0.15 lhr/lft Duct, 12⬙diameter
0.05–0.07 lhr/lft Duct, 16⬙-wide sheet metal nailed to joists
0.10–0.15 lhr/ea Duct, tee, elbow, transition, or cap, to 12⬙ diameter
0.10–0.15 lhr/ea Duct, tee, elbow, transition, or cap, to 12⬙ ⫻ 12⬙
0.15–0.20 lhr/ea Duct, tee, elbow, transition, or cap, 24⬙ ⫻ 12⬙
0.85–1.00 lhr/ea Diffuser, including drop
6.0–8.0 lhr/ea Furnace and air conditioner, residential, includes plenum
20–26 lhr/ea Package unit
0.30–0.50 lhr/ea Register, including boot or 90-degree elbow
0.30–0.50 lhr/ea Return air grill
1.0–1.5 lhr/ea Thermostat
26-000 ELECTRICAL
0.08–0.10 lhr/lft Conduit, to1⬙, including fittings
0.40–0.60 lhr/ea Junction or metal box
1.5–2.5 lhr/ea Light fixtures, commercial
0.5–1.0 lhr/ea Light fixtures, residential, including wiring
0.20–0.30 lhr/ea Outlet, commercial
0.40–0.60 lhr/ea Outlet, residential, 110v, including wiring
1.0–2.0 lhr/ea Outlet, residential, 220v, including wiring
8.0–14.0 lhr/ea Panel, commercial
6.0–8.0 lhr/ea Panel, residential
0.20–0.30 lhr/ea Switches, commercial
0.40–0.60 lhr/ea Switches, residential, including wiring
0.02–0.03 lhr/lft Wiring, commercial
Sample Labor Productivity Rates 363

27-000 COMMUNICATION
0.08–0.10 lhr/lft Conduit, to 1⬙, including fittings
0.40–0.60 lhr/ea Junction or metal box
0.40–0.60 lhr/ea Phone jack, including wiring
0.40–0.60 lhr/ea Television jack, including wiring
31–000 EARTHWORK
0.08–0.10 lhr/cyd Excavation, machine
0.08–0.10 lhr/cyd Footings excavation, hydraulic excavator
0.15–0.20 lhr/cyd Place and compact
0.02–0.03 lhr/sft Rough grading
32-000 EXTERIOR IMPROVEMENTS
0.15–0.20 lhr/cyd Road base, place and compact
0.02–0.03 lhr/sft Asphalt
0.06–0.09 lhr/lft Forms, to 12⬙ high
0.09–0.15 lhr/sfca Forms, 13⬙to 24⬙ high
15–16 lhr/ton Rebar placement
0.40–0.50 lhr/cyd Concrete placement, curb and gutter
0.40–0.60 lhr/cyd Concrete placement, slab
0.010–0.015 lhr/sft Concrete finishing
0.02–0.03 lhr/sft Finish grade
0.005–0.008 lhr/sft Sod
33-000 UTILITIES
0.15–0.20 lhr/cyd Backfill
0.15–0.20 lhr/cyd Bedding
5.0–7.0 lhr/ea Catch basin
1.0–2.0 lhr/ea Connection to existing manhole or box
0.15–0.20 lhr/lft Pipe, to 4⬙
0.08–0.10 lhr/cyd Trench excavation, hydraulic excavator
ABBREVIATIONS
ea ⫽ each
lft ⫽ linear feet
sfca ⫽ square-foot contact area
sft ⫽ square foot
squ ⫽ square (100 ft2)
syd ⫽ square yard
APPENDIX D

MODEL SCOPES
OF WORK

7. Concrete and rebar is to be provided by the contractor

T he following are sample scopes of work for multiuse


developments (which includes commercial build-
ings, single-family homes, and twin homes) that
may be used as model scopes of work for other projects. Not
all provisions in these scopes of work will apply to all pro-
and installed by the subcontractor.
8. The subcontractor shall ensure that only approved con-
crete mixes from approved suppliers are poured. The
subcontractor shall obtain a list of approved concrete
jects, and some projects will need additional provisions. mixes and suppliers from the project superintendent.
9. Concrete pumping is excluded. The contractor shall pay
for any required concrete pumping. The subcontractor
FOOTINGS AND shall obtain approval to pump concrete prior to doing
FOUNDATIONS so. If the subcontractor fails to obtain approval prior to
pumping concrete, the subcontractor shall pay for the
Provide all labor, materials, equipment, tools, and supervi- cost of pumping the concrete.
sion required to furnish and install all footings and founda-
10. All concrete placed under this contract shall be installed
tions and all appurtenances required for a complete installa-
to avoid thin edges and voids.
tion in accordance with the contract documents, applicable
codes, and governing agencies. The work includes, but is not 11. Any concrete rejected by the owner, contractor, or
limited to, the following: building inspector, or concrete that is rejected because
of failure to meet specified strength, shall be replaced by
1. Installation of all footings, foundations, concrete walls, the subcontractor at its sole expense.
and concrete columns
2. Installation of all embeds, anchor bolts, and sleeves,
hold-downs, and post bases that are to be cast in place. FRAMING
The subcontractor shall supply anchor bolts, hold- Provide all labor, equipment, tools, and supervision required
downs, and post bases. Imbeds and sleeves to be pro- to furnish and install all framing and all appurtenances re-
vided by others. quired for a complete installation in accordance with the
3. Installation of all structural steel anchor bolts that are contract documents, applicable codes, and governing agen-
installed in the concrete footings, foundations, and cies. The work includes, but is not limited to, the following:
columns. Construct plywood templates as required for
proper bolt placement and alignment. All structural 1. The subcontractor shall install all rough carpentry
steel anchor bolts to be provided by others. members, including, but not limited to, sills, studs,
plates, sleepers, columns, posts, beams, girders, floor
4. The subcontractor is to provide window bucks. joists, header joists, stringers, risers, treads, trimmers,
5. The subcontractor shall protect all concrete at all times backing, headers, blocking, lintels, bridging, firestop-
during installation from weather damage, vandalism, ping, rafters, purlins, trusses, floor sheathing, wall
and all other destructive elements. sheathing, roof sheathing, and drops.
6. The subcontractor shall provide layout for the work 2. The subcontractor shall install all exterior drywall, all dry-
contained in this contract. wall sandwiched between wood walls, and all Fiberbond.

364
Model Scopes of Work 365

3. The subcontractor shall install all framing hardware, in- 8. Installation of windowsills.
cluding but not limited to, nails, shots, pins, expansion 9. Installation of bath hardware, including, but not limited
bolts, machine bolts, lag screws, post-to-beam connec- to, medicine cabinets, grab bars, towel bars, towel rings,
tions, joist and beam hinges, and straps. toilet paper holders, and shower rods. All bath hardware
4. The subcontractor shall provide all nails required for shall be fastened into wood backing or installed with
the completion of this contract. All other framing hard- molly bolts.
ware is to be provided by the contractor. 10. The subcontractor is to provide nails, shims, and glue.
5. The subcontractor shall install all exterior doors, sliding All other materials are to be provided by others.
glass doors, and windows. All doors and windows shall 11. The subcontractor shall coordinate the location of re-
be hung true and plumb. Windows that line up shall be quired backing with the project superintendent and the
hung such that the vertical and horizontal lines are framing subcontractor.
straight and true. Doors shall be hung such that they do
not bind or swing open or closed by themselves.
6. The subcontractor shall furnish the forklift and/or
DRYWALL
crane for use in transporting and placing materials in- Provide all labor, materials, equipment, tools, and supervi-
stalled as a part of this contract. sion required to furnish and install all drywall and all appur-
7. The subcontractor shall furnish all tools, saws, cords, tenances required for a complete installation in accordance
and miscellaneous equipment required for the comple- with the contract documents, applicable codes, and gov-
tion of this contract. erning agencies. The work includes, but is not limited to,
8. Contractor shall supply temporary power for the sub- the following:
contractor. 1. Provide and install all interior drywall and associated
9. The subcontractor shall coordinate with the project su- components, including, but not limited to, all trim, acces-
perintendent to: sories, corner and edge trims, and reveals as required by
a. ensure that correct material sizes and quantities are the contract documents and required for a complete job.
ordered; 2. Provide and install fire walls and draft stops as shown
b. ensure prompt and timely material deliveries; on the contract documents.
c. coordinate material distribution and storage; 3. Provide and install fire-rated and moisture-resistant
board and compounds where required by code and the
d. coordinate installation procedures with other trades;
contract documents.
e. set up and maintain inventory control for receiving
4. Furnish and install all rated enclosures, chases, soffits,
and distributing materials;
shafts, and so forth for plumbing, electrical, HVAC
f. spot-check rough openings and backing requirements. ducting and piping, elevators, and other items as re-
quired by the contract documents.
FINISH CARPENTRY 5. The subcontractor shall pre-rock rated enclosures,
chases, soffits, shafts, behind the tub, furnace rooms, and
Provide all labor, materials, equipment, tools, and supervi- so forth prior to rough plumbing, rough HVAC, and
sion required to furnish and install all finish carpentry and rough electrical as directed by the project superintendent.
all appurtenances required for a complete installation in ac-
6. All walls and ceilings are to be taped and textured and
cordance with the contract documents, applicable codes,
ready for paint or wall coverings.
and governing agencies. The work includes, but is not lim-
ited to, the following: 7. The subcontractor is to provide a complete drywall fin-
ish in the furnace room.
1. Installation of all interior doors. All doors shall be hung 8. The subcontractor is to provide a complete drywall fin-
true and plumb. Doors shall be hung such that they do ish in the garage.
not bind or swing open or closed by themselves.
9. Materials shall be stocked by the subcontractor at right
2. Installation of mirrored wardrobe doors and associated angles to the floor trusses/joists and distributed so the
hardware. materials’ weight will not concentrate in any areas that
3. Installation of all interior trim, including, but not lim- may cause damage to the structure.
ited to, base, casing, chair rail, crown mold, wood 10. The subcontractor shall not cover any areas that require
handrail, wood guardrail, and window seats. insulation prior to installation of insulation and will at
4. Installation of fireplace mantels. all times advise the project superintendent of any defi-
5. Installation of wood closet shelving and rods with asso- ciencies in the insulation.
ciated hardware. 11. All drywall shall be screwed into place.
6. Installation of door hardware and door viewers. 12. The subcontractor shall patch around openings of
7. Installation of house numbers. pipes, ductwork, electrical, and other openings in a
366 APPENDIX D

workmanlike manner. Patches in fire-rated walls shall 10. The subcontractor shall caulk the trim metal to the tub.
comply with the applicable fire and building codes. 11. The subcontractor shall rehang doors after installing
13. All vertical and horizontal external corners shall be rein- flooring.
forced with corner bead trim applied in strict accor-
dance with the manufacturer’s recommendations. PAINTING AND STAINING
Vertical corners shall be straight and plumb. Horizontal
corners shall be straight and level. Provide all labor, materials, equipment, tools, and supervi-
14. Joints and screw depressions shall be invisible to the sion required to furnish and install all painting and staining
naked eye when surface is painted. The subcontractor and all appurtenances required for a complete installation in
shall verify that no shadows occur at joints by shining a accordance with the contract documents, applicable codes,
lamp on the face of the finished surface to check for and governing agencies. The work includes, but is not lim-
shadows and bad joints. ited to, the following:
15. After the initial coat of primer has been applied, the 1. Furnish and install all paint and stain for the walls, ceil-
subcontractor shall touch up all areas for screw pops, ings, doors, interior handrails, interior guardrails, and
shadows, rough paper, faulty areas, and areas unaccept- interior trim.
able to the contractor. 2. Prime and seal under wall coverings.
16. Care shall be taken and exercised to minimize dropping 3. Furnish and install concrete floor sealer to interior con-
joint compound on other surfaces. Droppings shall be crete floors as listed on the finish schedule.
scraped loose before they set up in all areas, including 4. Furnish and install all painting required to paint the
closets. garage and furnace/utility room.
17. The subcontractor shall be responsible for the disposal 5. Furnish and install all painting required to paint the ex-
of all drywall scrap materials. The subcontractor shall terior wood siding, trim, soffit, and fascia.
not dispose of drywall scrap materials in the dumpster 6. Furnish and install all painting required to paint the
supplied by the contractor. shutters.
18. Exterior drywall and drywall between the wood framing 7. Furnish and install all painting required to paint the ex-
of the party walls are excluded from this subcontract. terior stairs, stair treads, stair stringers, railings, and
handrails.
FLOOR COVERINGS 8. Furnish and install all painting required to paint the
power meters, gas meters, telephone boxes, cable TV
Provide all labor, materials, equipment, tools, and supervision
boxes, and disconnects.
required to furnish and install all floor coverings and all appur-
tenances required for a complete installation in accordance with 9. Furnish and install all painting required to paint the
the contract documents, applicable codes, and governing agen- vents, roof vents, and roof flashings to match the roof.
cies. The work includes, but is not limited to, the following: The said items are to receive one coat of zinc chromate
primer where needed and one coat of paint.
1. Furnish and install all resilient flooring, including sheet 10. Seal and finish the exposed edges of all metal and wood
vinyl and vinyl tile. doors including the top and bottom when they are visi-
2. Furnish and install all carpeting. ble from stairs, balconies, and so forth.
3. Furnish and install all rubber base. 11. Paint shall be applied to all drywall surfaces by roller.
4. Furnish and install all underlayment. 12. All surfaces of building components (which are installed
5. Furnish and install trim metal where carpet or vinyl by others) shall be inspected and accepted by the paint
meets other flooring materials or the tub. subcontractor prior to start of any work. Application of
6. The subcontractor shall prepare and submit seam dia- subcontractor’s work shall constitute acceptance.
grams for the contractor’s review. Installation of carpet 13. Mask, protect, and cover surfaces and items that do not
shall strictly follow the approved seaming diagram. receive paint, including, but not limited to, door hinges,
7. The subcontractor shall not combine different lots of fire-rating labels, exposed concrete and masonry, fix-
materials within a home or building. This applies to tures, furnaces, equipment, and so forth.
both carpet and vinyl materials. 14. Properly clean and prepare all surfaces before applying
8. The subcontractor shall sweep the floors prior to instal- all material and finishes.
lation of carpet or vinyl. 15. Fill gouges, fill nicks, fill nail holes, caulk joints, and pre-
9. The subcontractor shall be responsible for any minor pare all surfaces, including spot priming, before pro-
float leveling (1/4 inch or less) that may be necessary ceeding with the work.
prior to the installation of floor coverings. The subcon- 16. The subcontractor shall rehang doors after painting.
tractor shall provide and install all items as required for 17. The subcontractor is to include touch-up of paint and
floor preparation. finishes prior to owner’s walkthrough as required by
Model Scopes of Work 367

normal damage, splatters, and marring caused by the sinks, vanities, shower pans, tubs, washer hookups, ice-
process of construction work. Touch-up is to include maker boxes, faucets, floor drains, hose bibs, drain pip-
minor drywall patching. This touch-up is in addition to ing, vent piping, and supply piping.
the touch-up that occurs after the owner’s walkthrough. 2. The subcontractor shall provide a floor drain by laun-
18. The subcontractor is to include four hours of touch-up dry facilities and water heaters.
per residence for touch-up after the owner’s walk- 3. The subcontractor is to connect the water heater to the
through. This touch-up is in addition to the touch-up gas line. The gas line is to be provided by others.
that occurs before the owner’s walkthrough. 4. The subcontractor is to connect the dishwasher to the
plumbing.
FIRE SPRINKLERS 5. The subcontractor shall provide all trenching required
for their work.
Provide all labor, materials, equipment, tools, and supervi- 6. The subcontractor shall provide all block-outs and
sion required to furnish and install all fire sprinklers and all sleeves through floors, walls, and ceilings required for its
appurtenances required for a complete installation in accor- work.
dance with the contract documents, applicable codes, and
7. The subcontractor shall coordinate with the framing
governing agencies. The work includes, but is not limited to,
subcontractor for the location and size of all required
the following:
backing for the plumbing fixtures.
1. Furnish and install all piping, fittings, heads, supports, 8. The subcontractor shall furnish and install fire stops, fire-
seismic bracing, anchors, backflow preventer stations, retardant compound, and/or safing to seal all of the sub-
post indicator valves, fire sprinkler risers, fire depart- contractor’s penetrations through fire-rated assemblies.
ment connections, supervisory tamper/flow switches, 9. The subcontractor shall furnish all pipe flashings and
alarm bell/gong, roof manifold, and so forth. sheet metal jacks for its work. Pipe flashings and sheet
2. The subcontractor shall be responsible for the design metal jacks are to be installed by others.
and adequacy of the fire sprinkling system. The subcon-
tract price includes obtaining approved design draw-
ings, professional engineer’s certification or stamp, and
related permit from the local municipality.
HVAC
3. The subcontractor shall provide trenching, backfill, pip- Provide all labor, materials, equipment, tools, and supervi-
ing, fittings, and connections to 5 feet outside the build- sion required to furnish and install all HVAC and all appur-
ing line. Site utilities are provided by others. tenances required for a complete installation in accordance
4. Furnish and install all access doors required for the fire with the contract documents, applicable codes, and govern-
sprinkling system. ing agencies. The work includes, but is not limited to, the
following:
5. Install all heads in the center of the ceiling tiles.
6. Provide all testing, flushing, and so forth required to 1. Furnish and install all equipment required to complete
comply with the fire marshal’s requirements. the HVAC system, including, but not limited to, furnace,
7. The subcontractor shall furnish and install fire stops, fan coil, and condenser.
fire-retardant compound, and/or safing to seal all of 2. Furnish and install all required ducting, including, but
the subcontractor’s penetrations through fire-rated not limited to, ducting, supply registers, return-air
assemblies. grilles, combustion air ducting, and weather caps.
8. The construction of the fire sprinkling system shall 3. Furnish and install smoke and fire dampers as required
closely follow the construction of the building and shall by code and by the contract documents.
be placed in service as soon as applicable laws permit 4. Furnish and install ducting for clothes dryers.
following completion of each story. 5. Furnish and install ducting to all exhaust fans. The ex-
haust fans are provided and installed by the electrician.
6. Furnish and install a setback thermostat and all re-
PLUMBING quired low-voltage wiring. Provide temporary ther-
Provide all labor, materials, equipment, tools, and supervi- mostats for use during construction.
sion required to furnish and install all plumbing and all 7. The subcontractor is to connect electrical power to fur-
appurtenances required for a complete installation in ac- nace and air-conditioning units from the outlet box or
cordance with the contract documents, applicable codes, disconnect provided by others.
and governing agencies. The work includes, but is not lim- 8. Furnish and install all refrigerant lines. Provide protec-
ited to, the following: tion from nail punchers for all lines.
1. Furnish and install all fixtures and piping, including, 9. Furnish and install all condensate drain lines and piping
but not limited to, water heater, water softener, toilets, for all mechanical equipment.
368 APPENDIX D

10. Furnish and install all natural gas lines including gas 12. Furnish and install wiring, jacks, boxes, equipment, and
line service to gas ranges, gas dryers, gas fireplaces, and other items required to complete the intercom/sound
water heaters. system.
11. The subcontractor is to connect gas dryers and gas 13. Furnish and install wiring, jacks, boxes, and other items
ranges to gas lines after appliance installation. required to prewire the home theater system.
12. Connect water heater to gas lines. Water heater to be
provided by others.
13. The subcontractor shall furnish all pipe flashings and EARTHWORK AND UTILITIES—
sheet metal jacks for its work. Pipe flashings and sheet ROADS AND PARKING LOTS
metal jacks are to be installed by others.
Provide all labor, materials, equipment, tools, and supervi-
14. The subcontractor shall provide all block-outs and sleeves sion required to furnish and install all earthwork and utili-
through floors, walls, and ceilings required for its work. ties and all appurtenances required for a complete installa-
15. The subcontractor shall coordinate with the framing tion in accordance with the contract documents, applicable
subcontractor for location and size of all required back- codes, and governing agencies. The work includes, but is not
ing for the HVAC. limited to, the following:
16. The subcontractor shall furnish and install fire stops, fire-
1. Furnish and install sanitary sewer lines, associated
retardant compound, and safing to seal all of the subcon-
manholes, and so forth to complete the sanitary sewer
tractor’s penetrations through fire-rated assemblies.
system.
17. The subcontractor shall work with the contractor to
2. Furnish and install sanitary sewer laterals for all lots.
provide an early operation of the furnace to be used as
The subcontractor shall furnish and install one sewer
temporary heat in the building.
lateral per lot. The sewer laterals shall be constructed
18. The subcontractor shall replace all furnace filters just from the sanitary sewer in the road to a point 10 feet
prior to the building being turned over to the owner. inside the lot boundaries. The locations of the sewer
laterals are to be coordinated with the site superinten-
dent. The subcontractor shall mark the end of each
ELECTRICAL sewer lateral in such a manner that it can be located for
Provide all labor, materials, equipment, tools, and supervi- future connection.
sion required to furnish and install all electrical and all ap- 3. The subcontractor shall make all required connections
purtenances required for a complete installation in accor- to connect the sanitary sewer lines to existing utilities.
dance with the contract documents, applicable codes, and 4. Furnish and install the water lines, fittings, valves, hy-
governing agencies. The work includes, but is not limited to, drants, washouts, boxes, covers, and so forth to com-
the following: plete the water system.
1. Furnish and install all electrical fixtures, switches, meter 5. Furnish and install water laterals, including, but not
bases, breaker boxes, and wiring. limited to, the water meter yoke and meter box for all
2. Provide one meter base per unit and one house meter lots. The subcontractor shall furnish and install one
per apartment building. water meter yoke per lot. The water laterals shall be con-
structed from the water line in the road right-of-way to
3. Furnish and install all exhaust fans. Ducting of the ex-
the water meter locations shown on the plans. Water
haust fans is to be by others.
meters are excluded from this contract.
4. Furnish, install, and provide power to the disconnect for
6. The subcontractor shall make all required connections
the air-conditioner condenser.
to connect the water lines to existing utilities. Utility
5. Furnish, install, and provide power to an electrical box company’s connection, impact, and review fees are ex-
for the furnace. cluded from this subcontract.
6. Provide electrical hookup of the dishwasher and disposal. 7. Furnish and install storm drain piping, catch basins,
7. Install range hood or space-saver microwave. clean-out boxes, manholes, and so forth to complete the
8. Install pigtails on range and electrical clothes dryers. storm drain system.
9. Furnish and install wiring, jacks, boxes, a terminal box, 8. The subcontractor shall construct the detention and re-
and other items required to prewire the telephones. tention ponds shown on the plans.
10. Furnish and install wiring, jacks, boxes, a terminal box, 9. The subcontractor shall excavate and backfill the trench
and other items required to prewire the cable television. required for the placement of power lines. The power
11. Furnish and install wiring, door and window contacts, lines shall be furnished and installed by others.
and an outlet required to prewire the security system. 10. Furnish and install conduits for phone and cable televi-
The key pad, motion detectors, and equipment are pro- sion. The phone and cable television conduits may be
vided and installed by others. placed in a joint trench with the power lines. The phone
Model Scopes of Work 369

and cable television wiring shall be furnished and in- 2. Furnish and install an irrigation system with automatic
stalled by others. controls and pop-up heads. The electrical supply to con-
11. Furnish and install conduits for site lighting. The site trol locations shall be furnished by others. The subcon-
lighting conduits may be placed in a joint trench with tractor shall coordinate with the project superintendent
the power lines. The site lighting and its associated and electrical subcontractor to ensure proper location of
wiring shall be furnished and installed by others the automatic controls and electrical supply.
12. The subcontractor shall clear and grub the site. 3. The subcontractor shall adjust all sprinkler heads and
13. The subcontractor shall provide the rough grade for the set automatic controllers prior to completion of each
roads and parking lots and their associated gutters, side- building or residence.
walks, and curb walls within the road right-of-way. 4. The subcontractor shall place all sleeves, pipes, and con-
14. Furnish and install base for all gutters, sidewalks, and duits required to complete the sprinkling system under
curb walls required for completion of all concrete roads, driveways, walks, curbs, and other hard surfaces
within the road right-of-ways and parking lots. prior to the construction of the said surfaces.
5. Preparation of the soil.
6. Finish grade to ⫾0.1 foot. Rough grade to ⫾0.2 foot to
LANDSCAPING be provided by others.
Provide all labor, materials, equipment, tools, and supervi- 7. Disposal of rock uncovered by installation of the irriga-
sion required to furnish and install all landscaping and all tion system.
appurtenances required for a complete installation in accor- 8. The subcontractor is to warranty all trees and shrubs for
dance with the contract documents, applicable codes, and one year.
governing agencies. The work includes, but is not limited to, 9. The subcontractor is to warranty all hydroseeding and
the following: sod for 90 days.
1. Furnish and install the landscaping including hy- 10. The subcontractor shall maintain the landscape for 90
droseeding, sod, trees, shrubs, and bedding plants. days after final acceptance.
APPENDIX E

GLOSSARY

A B
Absolute Reference All or part of an Excel cell’s reference Bank Cubic Yards The volume of soil in cubic yards before
that does not change as the cell is copied, which is designated it has been excavated in its natural or in situ condition.
by a dollar sign ($) in front of the row and/or column desig- Beam A horizontal member that supports a load and
nation for the cell. transfers the load to girders or columns.
Addenda A construction document, issued before the bid, Bedding Gravel or sand that provides a place for under-
that changes the scope of work for a construction project. ground pipe to rest and may surround the pipe to protect it.
Add-On Costs that are added to the cost of the bid, such as Bid The amount that the contractor charges the owner for
bonds, building permit, and profit and general overhead. the work.
Also known as a markup.
Bid Bond A bond issued by a surety guaranteeing that the
AGC Associated General Contractors of America. bidder, if successful in winning the bid, will execute the con-
AIA American Institute of Architects. tract and provide payment and performance bonds.
Air Handler An HVAC component that combines a heat Bid Documents Forms used for the submission of the bid,
exchanger and a fan. which may include bid forms, bid-bond forms, a schedule of
Alternate Bid Item A bid in which the contractor provides values, and contractor certifications.
alternate or optional pricing for specific bid items in addi- Bid Form The construction document on which the bid or
tion to the base bid. Also known as an optional bid item. price is submitted.
American Standard Beam An I-beam designated with the Bid Instructions A construction document that provides
prefix S. bidders with a set of instructions that must be followed to
American Standard Channel A steel channel designated prepare a complete bid.
with the prefix C. Bid Package The construction documents that define the
Anchor Bolt A bolt used to connect steel or wood to con- scope of work for a construction project, on which bids are
crete or masonry. prepared.
Angle or Angle Iron An L-shaped steel member desig- Billable Hours The number of hours that an employee
nated with the prefix L. can be billed to projects during a year.
Annual Contract A contract for materials that is set up for Block Concrete masonry unit used to construct structural
a period of time (often 1 year), which covers multiple con- walls.
struction projects. Blocking A small piece of wood used to strengthen struc-
ANSI American National Standards Institute. tural members or fill the space between members, as is the
Architect’s Scale A scale or ruler that allows the user to case with fire blocking.
read dimensions from plans drawn at common architectural Boiler A closed vessel used to heat a liquid.
scales. Bond See Bid Bond, Payment Bond, and Performance Bond.
ASTM American Society for Testing and Materials. Bond Beam A horizontal row of concrete blocks or bricks
Avoidable Waste Waste that can be avoided by careful or- reinforced with rebar and grout, used to add structural
dering, storage, and use of materials. strength to a wall.

370
Glossary 371

Bonding Limit The maximum dollar value for a single job Compacted Cubic Yards The volume of soil in cubic yards
and total work in progress a contractor may be bonded for. after it has been excavated, placed, and compacted, and is
Bottom Plate The bottom framing member in a wood used to measure the volume of fill.
wall. Competitive Bidding The bid process in which two or
Brick A masonry unit made from clay or shale. more contractors compete for the bid based on price and/or
Brick Facing A nonbearing layer of brick on the face of a other criteria.
block or wood wall. Also known as brick veneer. Composite Slab A structural slab that derives its strength
Brick Ties Corrugated metal ties used to connect brick ve- from structural steel beams in combination with a concrete
neer to masonry or wood walls. deck.
Brick Veneer A nonbearing layer of brick on the face of a Concrete A mixture of cement, large aggregate, fine aggre-
block or wood wall. Also known as brick facing. gate, and water.
Budget The target cost set for a project or portion of a Concrete Masonry Unit Wall constructed of concrete
project. blocks and mortar.
Building Paper Asphalt-impregnated felt, often used as a Condenser An HVAC component consisting of a com-
vapor barrier. pressor and a heat exchanger, used to cool and compress a
refrigerant.
Bullnose A rounded outside corner.
Continuous Footing A long, narrow footing used to sup-
Burden The costs that must be added to an employee’s
port walls and columns.
wages to determine his or her total cost, which includes cash
equivalents and allowances paid to the employee, payroll Contract A legally binding agreement between the pro-
taxes, unemployment insurance, workers’ compensation in- ject’s owner and a contractor for the work done on a con-
surance, general liability insurance, insurance benefits, re- struction project.
tirement contributions, union payments, vacation, sick Cost Codes A code for the logical grouping of items sepa-
leave, and other benefits paid by the employer. Commonly rated by supplier or installer type. Cost codes are often based
referred to as labor burden. on the MasterFormat.
Butts A common type of hinge. CPVC Chlorinated polyvinyl chloride, a pipe used for
Buyout The process of hiring subcontractors and procur- water lines.
ing materials and equipment for a construction project. Crew Rate The hourly or daily cost of labor and equip-
ment for a construction crew.
C
Cripple Stud A short stud used below windowsills and in
Cell (1) A location on an Excel spreadsheet designated
other areas.
by a row and column. (2) The hollow space in a concrete
masonry unit. Cycle Time The time it takes to complete one cycle of a
repetitive task.
Certifications A construction document that the contrac-
tor signs certifying that it meets specified criteria. D
Change Order A construction document that is issued Damper A blade or louvers in an air duct used to control
after the bid and changes the scope of the work and/or the the airflow.
contract amount for a construction project. Dampproofing A water-resistant material applied to
Channel American Standard Channel, a steel channel des- foundations.
ignated with the prefix C. Davis-Bacon Wages Wage rates that must be used on con-
Check Valve A valve that allows a fluid to flow in one di- tracts with federal funding.
rection only. Design Professional The architect or engineer responsible
Chiller An HVAC unit used to cool water. for the design of a project.
Close-Out Audit A review of all activities completed dur- Dialogue Box A small box in Excel that allows the user to
ing the construction process, including the estimating make choices.
process, which occurs after the project is complete. Diffuser An air distribution component located on the
CMU Concrete masonry unit. ceiling used to direct the airflow into a room.
Coil An HVAC component consisting of a coil of pipes Digitizer A device used to measure distances and areas off
used to transfer heat from the air to a refrigerant or from the of plans.
refrigerant to the air. Also known as a heat exchanger. Dimensional Analysis A mathematical procedure in
Collar Ties A wood member connected to two rafters used which only the units of an equation are written to verify that
to prevent the wall supporting the rafters from spreading the equation produces an answer with the correct units.
apart due to the forces on the rafters. Also known as rafter Direct Costs Costs that can be specifically identified with
ties. the completion of a task. For example, for the task of in-
Column A slender vertical structural member. stalling windows the direct cost includes the material cost for
372 APPENDIX E

the windows (including sales tax and delivery),the labor cost Fire Department Siamese A wye fire hose connection lo-
(including labor burden), and the cost of any equipment cated outside a building and connected to a fire sprinkler
used to install the windows. system for use by the fire department.
Drain Board A material used to allow water to freely drain Flow Alarm An alarm that goes off when flow occurs in a
vertically down the face of a wall. pipe.
Drawings A graphical representation showing the dimen- FOB Free on board. The point where ownership and re-
sions of the project and where different construction materi- sponsibility for materials transfers from the supplier to the
als are used on the project. Also known as plans. contractor.
Dropdown Box A box in Excel that allows the user to se- Folder A location on the computer used to organize files
lect among a list of preset choices with only one choice being and subfolders.
visible until the user selects the arrow to the right side of the Footing A structural member used to transfer the loads
box. from a column or wall to the ground.
Dry Unit Weight The density of the solid portion of a soil, Forms Temporary structures used to support concrete
usually measured in pounds per cubic foot. until it has cured and can support its own weight.
Drywall Preformed sheet of gypsum. Foundation The concrete or masonry structure below the
Drywall Compound The material used to tape the joints first floor of a building, including the footing.
of the drywall. Foundation Wall The wall portion of the foundation,
Durable Wood Wood that is naturally protected against which often acts as a retaining wall.
decay and termites; for example, redwood. Framing Anchor A light-gage metal connector used to
connect two or more wood members together or connect
E
wood members to concrete and masonry.
EIFS Exterior insulation finish system.
Function A computer instruction that selects a value
End Condition The need to add a repetitive member to based upon a specified set of requirements and the values lo-
the beginning of a wall. cated in other cells. For example, the MAX function selects
Engineer’s Scale A scale or ruler that allows the user to read the largest value from a series of cells.
dimensions from plans drawn at common engineering scales. Fusible Link A metal link that melts when exposed to fire
Escutcheon A decorative cover around plumbing and fire conditions, opening a fire sprinkler head or closing a fire
sprinkler pipes. damper.
Estimated Cost The projected cost of the work including FUTA Federal Unemployment Tax Act.
the cost of labor, materials, equipment, and markups. The
estimated cost should not be confused with the bid or selling G
price. Gable-End Truss A nonbearing truss installed over walls
Estimating Estimating is the process of determining the to construct the gable end of the building.
expected quantities and costs of the materials, labor, and General Conditions A construction document that iden-
equipment for a construction project. tifies the relationships among the owner, design profession-
Estimating Software Package High-end software pack- als, and the contractor and addresses provisions that are
ages that combine a spreadsheet with a database. common to the entire project. Typically, this is the standard
Estimator A person responsible for preparing cost esti- document used for many different projects.
mates regardless of his or her job title. General Decision A document containing the Davis-Bacon
Ethics (1) A set of principles or rules by which members of labor rates, which is published by the U.S. Department of
a group agree to abide. (2) A set of values or a guiding phi- Labor.
losophy of a person. General Overhead Costs that cannot be identified with a
Excel A spreadsheet program developed by Microsoft. project, for example, main-office expenses and accounting
costs. Also known as indirect costs.
F Girder A horizontal structural member used to transfer
Fascia A vertical board running perpendicular at the end loads from beams to columns.
of the rafters or trusses. GLB Glue lam beam.
FICA Federal Insurance Contributions Act, which requires Glue Lam Beam A beam constructed by laminating with
the collection of Social Security and Medicare taxes. glue a number of smaller wood members parallel to each
File A uniquely named storage unit containing contents other into a larger beam.
of a computer spreadsheet, drawing, or other computer Grille An HVAC component consisting of horizontal slots
document. used to cover an air duct.
Fillet Weld A triangular weld used to connect two steel Grout A mixture of cement, fine aggregate, and water used
members together at a right angle. to fill the cells of blocks or bricks.
Glossary 373

H Joist Trimmer The joists running parallel to a side of an


Header A horizontal structural member used to transfer opening.
vertical loads from above an opening to the vertical mem-
K
bers located at the sides of the opening.
King Rafters A full-length rafter that runs from the eave of
Heat Exchanger An HVAC component consisting of a coil
the roof to the peak of the roof.
of pipes used to transfer heat from the air to a refrigerant or
from the refrigerant to the air. King Stud A full-length stud located at the side of an
opening.
Hip Rafters The rafters located at the junction of two in-
clined roof planes where the exterior surfaces of the planes L
intersect at an angle greater than 180 degrees. Labor Burden The costs that must be added to an em-
Hold-Down A structural metal connector used to provide ployee’s wages to determine his or her total cost, which in-
resistance against uplift. cludes cash equivalents and allowances paid to the employee,
HVAC Heating, ventilation, and air-conditioning. payroll taxes, unemployment insurance, workers’ compensa-
tion insurance, general liability insurance, insurance bene-
I fits, retirement contributions, union payments, vacation,
Icon A computer image used to represent a command, file, sick leave, and other benefits paid by the employer.
or folder. Labor Hour One employee working 1 hour.
I-Joist An engineered wood joist with an I-shaped cross Labor Hours The total number of labor hours it takes to
section. complete a task.
Included by Reference Documents that are included in Labor Productivity A measure of how fast construction
the contract documents by referencing them in the contract tasks can be performed, which is reported as the number of
documents rather than physically attaching them. units performed during a labor hour or crew day (output) or
Indirect Costs Costs that cannot be identified with a pro- the number of labor hours required to complete one unit of
ject, for example, main-office expenses and accounting costs. work.
Also known as general overhead. Labor Rate The hourly cost of an employee per billable
Indirect Project Costs Costs that can be identified with a hour including wages and labor burden, which is calculated
construction project but are not identifiable with a specific by dividing the annual cost of the employee by the number
task. Most Division 1 (for example, supervision, jobsite of billable hours.
trailer, and temporary utilities) costs fall into this category. Landscape When specifying a page layout for printing, the
Also known as job overhead. paper orientation that has the long side horizontal.
In Situ Soil in its natural condition. Left Click Pressing the button on the left side of the
Invitation to Bid A construction document that invites mouse.
contractors to bid on a project. LHR Labor hours.
Line Set The copper lines used to connect a condenser
J
with a coil in an HVAC system.
Jack Rafters A shortened rafter in a hip roof that is con-
Lintel A structural member used to support the wall above
nected to a hip or valley rafter.
an opening. See also Header.
Jack Stud A short stud used to support a header.
List Box A box in Excel that allows the user to select from a
Jamb The exposed side of a door or window. list of preset choices, with multiple choices being visible in
Job Overhead Costs that can be identified with a con- the box.
struction project but are not identifiable with a specific task. Lookouts Short wood members supporting a roof over-
Most Division 1 (for example, supervision, jobsite trailer, hang.
and temporary utilities) costs fall into this category. Also
Loose Cubic Yards The volume of soil in cubic yards after
known as indirect project costs, which are different than in-
it has been excavated but before it has been placed and com-
direct costs.
pacted, which is used to measure the volume of soil being
Joist A horizontal wood or steel member used to frame a transported.
floor or ceiling.
Lump Sum Bid A bid in which the contractor provides a
Joist Girder A joist used to transfer loads from joists to single price for the construction work.
columns.
Joist Hangar A light-gage metal connector used to con- M
nect joists to joist headers and rim joists. Man Hours See Labor hours.
Joist Header A joist used to transfer loads from joists in- Markup Costs that are added to the cost of the bid, such as
tersecting an opening in a floor or ceiling at a right angle to bonds, building permit, and profit and general overhead.
the joist trimmers. Also known as an add-on.
374 APPENDIX E

Membrane Roofing A roof constructed of an imperme- Plenum (1) The space between a dropped ceiling and the
able flexible plastic membrane. structure above. (2) The ductwork above a residential furnace.
Metal Deck Formed sheet metal used to support a roof or PO Purchase order. A legally binding agreement used to
floor. order materials or work on a project.
MHR Man hours. See Labor hours. Portrait When specifying a page layout for printing, the
Mono Truss A truss with a single pitch or slope. paper orientation that has the short side horizontal.
Mortar A mixture of cement, lime, fine aggregate, and Post A secondary column.
water used to adhere brick or block together. Pressure-treated Wood Wood that has been treated to
Mullion A member that separates the glazing panels in a prevent rot and insect infestation and/or fire by forcing
window. chemicals into the wood under pressure.
Progress Payment A payment made from the owner to the
N contractor or from the contractor to the subcontractor be-
Nominal In name only. Lumber is often specified in nomi- fore the project is complete as payment for the work com-
nal dimensions, which are larger than the actual dimensions. pleted to a specified date.
Nonresponsive Bid An incomplete bid, which is disre- Project Manual A bid document that contains the invita-
garded. tion to bid, bid instructions, bid documents, bond and con-
tract forms, general and special conditions, technical specifi-
O
cations, and other contract documents.
Optional Bid Item A bid in which the contractor provides
Proposal A letter or document from a contractor to an
alternate or optional pricing for specific bid items in addi-
owner (or from a subcontractor to a contractor) in which
tion to the base bid. Also known as an alternate bid item.
the contractor (subcontractor) proposes to perform a speci-
Oriented Strand Board A panel of wood created by gluing fied scope of work for a set price and set conditions.
wood chips together. PRV Pressure-reducing valve.
OSB Oriented strand board. P-Trap A P-shaped pipe used to prevent sewer gasses from
Output Labor productivity measured in the number of escaping from the sewer system.
units performed during a labor hour or crew day. Purchase Order A legally binding agreement used to order
Overbuild A portion of a roof built over the top of a roof materials or work on a project.
structure, often used to create the appearance of a dormer. PVC Polyvinyl chloride.
P Q
Package Unit An HVAC unit that incorporates the heating Quantity Survey or Quantity Takeoff The process of con-
and cooling equipment into a single unit. verting the building dimensions and details into estimated
Paid-When-Paid Clause Language in a contract that ties quantities.
the payment of the subcontractor to the receipt of payment
from the owner. R
Path The computer location of a file that includes the Rafter A sloped wood member used to frame a roof.
drive designation and all folders from the drive to the file. Rafter Ties A wood member connected to two rafters,
Payment Bond A bond issued by a surety guaranteeing used to prevent the wall supporting the rafters from spread-
that the contractor will pay for the labor, materials, and ing apart due to the forces on the rafters.
equipment used on the project. Raised Slab A slab that does not bear on the ground.
Performance Bond A bond issued by a surety guaranteeing Random Length A bundle of lumber with differing
that the contractor will complete the work and that, should lengths.
they fail to do so, the surety will step in and complete the work. Rate of Progress The speed at which a linear task (for ex-
Pex A plastic pipe used for water lines. ample, paving roads, installing pipes, painting striping on
Pipe Hanger A device used to support a pipe from a struc- roads, installing curbs, and so forth) proceeds.
tural member. Rebar Steel bars used to reinforce concrete and masonry.
Plan Measurer A device that allows the user to measure Register A diffuser combined with a damper to direct and
distances from plans by rolling the wheel of the device along control the flow of air into a room.
a line. Relative Reference All or part of an Excel cell’s reference
Plans A graphical representation showing the dimensions that changes as the cell is copied.
of the project and where different construction materials are Request for Material Quote A written request for pricing
used on the project. on materials.
Plate Steel Flat sheet of structural steel used to make con- Retention Funds withheld from a payment to ensure that
nectors and bearing plates. a contractor completes a construction project.
Glossary 375

Ridge Board A board located at the ridge of a roof used to Slope The relationship between the rise and run of a rafter,
support the rafters. truss, or side of an excavation.
Right Click Pressing the button on the right side of the Soffit The underside of a roof overhang.
mouse. Soils Report A document that describes the soil condi-
Rim Board or Rim Joist The board or joist located at the tions and water table at the construction site.
perimeter of a wood-framed floor or ceiling. Special Conditions A construction document that identi-
Ring Shank Nail A nail with rings around its shank to in- fies conditions, in addition to the general conditions, that
crease its resistance against pullout. apply to a specific project.
Ring Ties Round rebar ties used to tie the vertical rebar to- Specifications (1) The technical specifications. A con-
gether in a round column. struction document that identifies the quality of materials,
Rise (1) The change in height from the supporting mem- installation procedures, and workmanship to be used on the
bers to the ridge for a truss or rafter. (2) The vertical distance project. (2) Incorrectly used to refer to the project manual,
between stairs. which contains the invitation to bid, bid instructions, bid
Roof-Top Unit An HVAC unit that incorporates the heat- documents, bond and contract forms, general and special
ing and cooling equipment into a single package and is de- conditions, and other contract documents, in addition to the
signed to be placed on the roof of a structure. technical specifications.
RTU Roof-top unit. Spread Footing A square or rectangular footing used to
support a column. Sometimes referred to as a spot footing.
Run The distance between the outside of an exterior wall
and the ridge or peak of a roof. Sprinkler Head The portion of a fire sprinkler system that
sprays water to suppress a fire and often includes a fusible
Runner A metal channel used at the top and bottom of a
link or liquid filled vial to release the water.
wall to support the metal studs.
Stirrups U-shaped rebar located near the end of concrete
S beams to resist shear and diagonal tension.
Schedule of Values A list of values used to determine the Structural Brick A masonry unit made from clay or shale
amount of the progress payments. that may be used as structural support.
Scope of Work “The construction and services required Structural Tee A steel shape made by cutting an I-beam in
by the Contract Documents . . . and includes all other half, which is designated with the prefix T.
labor, materials, equipment and services provided or to be Structural Tubing A hollow square or rectangular steel
provided by the Contractor to fulfill the Contractor’s shape.
obligations” (General Conditions of the Contract for
Stud (1) A wood member used to frame walls, most com-
Construction, American Institute of Architects, AIA
monly 2 ⫻ 4s. (2) A metal bolt with one end securely fas-
Document A201-1999, p. 9.)
tened to a deck or steel member, for example, a Nelson stud.
Second-Tier Subcontract A subcontractor to a subcon-
Subcontract A legally binding agreement between the
tractor to the general contractor. The contractual relation-
contractor and a subcontractor for the work done on a con-
ship of second-tier subcontractors passes through a subcon-
struction project.
tractor on the way to the general contractor.
SUTA State Unemployment Tax Act.
Selling Price The amount that the contractor charges the
owner for the work. More commonly known as the bid or Sweating The process of connecting copper pipe using
bid price. heat, flux, and solder.
Shear Panel A structural panel used to resist horizontal Swell The relationship between the bank and the loose
(shear) forces. condition of soil.
Sheathing A panel of wood used to cover walls, floors, and T
roofs. T&G Tongue and groove.
Shrink The relationship between the bank and compacted Tail Joist A short joist that ends at an opening.
condition of soil. Takeoff Software A software package used to measure dis-
Siamese A wye fire hose connection located outside a tances, areas, and volumes from a set of digital plans.
building and connected to a fire sprinkler system for use by Task A discrete segment of the scope of work that con-
the fire department. sumes time and resources.
Sill The bottom horizontal member of a window. Technical Specifications A construction document that
Sill Plate The bottom framing member in contact with identifies the quality of materials, installation procedures,
concrete or masonry. and workmanship to be used on the project. Often referred
Sill Seal A foam material used to prevent air infiltration to as specifications.
between the sill plate and the foundation. Tempered Glass A form of safety glazing in which the
Slab on Grade A slab supported by earthen materials. glass has been heat-treated to resist breakage.
376 APPENDIX E

Text Box A box in Excel where text is typed. Water Content The relationship between the solids and
Thickened Slab An area of a slab-on-grade where the the water in soils, which is the weight of the water (not
thickness has been increased to provide greater strength or volume) expressed as a percentage of the weight of the
to act as a footing. solids.
Ties Round, rectangular, or square rebar ties used to tie the Waterproofing A water-resistant material applied to
vertical rebar together in a column. foundations.
Tongue and Groove Sheeting that has a tongue on one Web Stiffener A piece of steel or wood used to stiffen the
side designed to fit into a groove on the opposite side of an webs of an I-beam or I-joist; prevents the beam’s or joist’s
adjoining sheet. web from buckling.
Top Plate The top horizontal framing members in a wood Welded Wire Fabric A series of wires welded at right an-
wall. gles in a grid to form rolls or sheets of reinforcement for use
Transom A window located above a door. in concrete slabs. Also known as wire mesh.
Truss A wood-framing member composed of multiple Wet Unit Weight The density of soil, both the solids and
structural members, which often form smaller triangles, and the water, usually measured in pound per cubic foot.
which is used to support a floor or roof. Wheel Plan measurer. A device that allows the user to
measure distances from plans by rolling the wheel of the de-
U vice along a line.
Unavoidable Waste Waste that cannot be avoided because Wide-Flange Beam An I-beam with wider flanges than
of the design of the project. an American Standard Beam, which is designated with the
Unit Pricing Bid A bid in which the contractor provides prefix W.
unit pricing for each bid item.
Wire Mesh A series of wires welded at right angles in a
Unit Weight of Water The weight of the water in the soil, grid to form rolls or sheets of reinforcement for use in con-
expressed in pounds per cubic foot. crete slabs. Also known as welded wire fabric.
V Work “The construction and services required by the
Valley Rafters The rafters located at the junction of two Contract Documents . . . and includes all other labor, ma-
inclined roof planes where the exterior surfaces of the planes terials, equipment and services provided or to be provided
intersect at an angle of less than 180 degrees. by the Contractor to fulfill the Contractor’s obligations”
Vapor Barriers Building papers and plastics used to pre- (General Conditions of the Contract for Construction,
vent the infiltration of water vapor. American Institute of Architects, AIA Document A201-
1999, p. 9.)
VAV Box Variable-air-volume box.
Workbook An Excel file containing one or more work-
VCT Vinyl composition tile.
sheets.
V Weld A V-shaped weld used to weld the end of struc-
Worksheet The pages within an Excel workbook or file.
tural steel members together.
WWF Welded wire fabric.
W
Waste Materials lost during the construction project, X
which equals the difference in the quantities of materials or- xlsx File extension for a 2007 or 2010 Excel file.
dered and the calculated quantities of materials to be placed xlsm File extension for a 2007 or 2010 Excel file that con-
on the project. tains macros.
APPENDIX F

INDEX OF DRAWING SETS

(The loose project drawings are provided in a separate pack- West Street Video
age shrink-wrapped to this text.)
Sheet Title Rev. Date
Residential Garage T Title Page 3/24/06
Sheet Title Rev. Date G1 Specifications 3/24/06
1 Title Page 3/24/06 C1 Site Plan 3/24/06
2 Site Plan 3/24/06 C2 Grading Plan 3/24/06
3 Plan Views 3/24/06 A1 Floor Plan 3/24/06
4 Elevations 3/24/06 A2 Exterior Elevations 3/24/06
5 Sections 3/24/06 A3 Exterior Elevations 3/24/06
6 Details 3/24/06 A4 Building Sections 3/24/06
7 Details 3/24/06 A5 Sections 3/24/06
A6 Sections 3/24/06
A7 Reflected Ceiling 3/24/06
Johnson Residence
A8 Interior Elevations 3/24/06
Sheet Title Rev. Date A9 Interior Finishes/Doors & Wind. 3/24/06
T Title Page 3/24/06 A10 Architectural Details 3/24/06
G Specifications 3/24/06 S1 Foundation Plan 3/24/06
A1 Site Plan 3/24/06 S2 Roof-Framing Plan 3/24/06
A2 Floor Plan 3/24/06 S3 Structural Details 3/24/06
A3 Exterior Elevations 3/24/06 S4 Structural Details 3/24/06
A4 Exterior Elevations 3/24/06 P1 Plumbing Plan 3/24/06
A5 Building Sections 3/24/06 P2 Plumbing Details 3/24/06
A6 Finishes and Int. Elevations 3/24/06 FP1 Fire Sprinkler Plan 3/24/06
A7 Details 3/24/06 FP2 Fire Sprinkler Details 3/24/06
A8 Details 3/24/06 M Mechanical Plan 3/24/06
S Structural 3/24/06 E1 Lighting Plan 3/24/06
P Plumbing Plan 3/24/06 E2 Power Plan 3/24/06
M HVAC Plan 3/24/06 E3 One-Line/Panel Boards 3/24/06
E Electrical Plan 3/24/06

377
INDEX

401(k) 245 Anchor bolts 58, 76, 78, 89–90, 117, 364, 370
A Angle 89, 93, 98, 100, 103, 370
Absolute reference, 302–3, 370 Annual contract 370
Accident history 244 ANSI 6, 370
Accounting Appliances 189
style 33 Arbitration 291
system 65, 228, 235, 243, 249, 259 Architect 165, 168, 258
Accrued cost 240 Architect’s
Accuracy 277, 295 estimate 11
Acoustical scale 7, 342–3, 370
ceilings 165–6, 174 Architectural-grade shingles 141
tile 165–6 Area
Addenda 15, 370 calculating 344–50
Add-on 15–6, 261–5, 370, 373 constant 351–2
Adjustment factor 235 method 62
Admixtures 67 ASPE 8–9, 295–6
AGC 289, 292, 370 Asphalt 214–5
Aggregate 67 impregnated felt 136–8, 141
AIA 2, 9, 289, 292, 370 roofing 315
Air-conditioning 181–6, 189, 367–8 Assemblies 8–9
Air Associated General Contractors of America 289, 292
chamber 176 Assumptions 8
entrainment 67 ASTM 6, 370
handler 370 Athletic surfaces 214
infiltration 108 Attachments 283
Alarm Attic 181
check-valve assembly 172 Attorney 289
flow 172 fees 291
Align text left button 31 Auto fill 320
Align text right button 31 Autosum button 43
Allowances 240–2 Average-end method 203–4, 209, 220–2
Alternate bid item 370 modified 204, 209, 220, 222
Alternatives 285, 289 Average function 43–4
Aluminum siding 143 Average-width-length-depth method 203, 209
American Institute of Architects 2, 9, 289, 292, 370 Avoidable waste 370
American Institute of Steel Construction 98
American National Standards Institute 6, 370 B
American Society for Testing and Materials 6, 370 Back charge 290
American Society of Professional Estimators 8–9, 295–6 Backer board 164
American standard beam 98, 370 Backfill 210–1, 225
American standard channel 98, 370 Backing 117, 162, 364–5

378
INDEX 379

Bank 200–2, 210 Bond 270,


cubic yards 370 beam 89–90, 370
Bankruptcy 3 bid 4, 10–1, 282, 370
Base 214–5, 365 capacity 285
plate steel 98 cost 15, 299–300
rubber 168 limits 11, 371
Batten strip 146 payment 4, 263, 270, 374
Beam 78, 98–100, 370 performance 4, 263, 270, 290, 374
American standard 98 schedule 300
wood 364 Borders 28, 34, 307
wide-flange 98 button 34
Bearing walls 110, 117–8 popup menu 34–5
Bedding 223–4, 370 Bottom plate 371
plants 369 Branch lines 172–3
Benefits 240, 245 Brick 371
Bid 370 facing 89, 93–4, 371
best 259 lintels 93
bond 4, 10–1, 282, 370 structural 89–93
checklist 282 ties 371
competitive 10 veneer 89, 93–4, 371
courtesy 264–5 Bridges 214
date 257, 264 Budget 3, 371
deadline 14 Build in mind 56, 59, 66, 293
documents 4, 210, 282, 370 Building
preparation 14 code 67, 115, 261
form 4–5, 282, 370 paper 134–8, 141, 371
instructions 4, 370 permit 15, 261, 263, 270, 285, 299
nonresponsive 282 Bullnose 371
package 4–7, 370 Burden 240–1, 371
planning 10 Butt joint 61–3, 145
preliminary 283 Butts 371
review 16–7 Buyout 17, 289–92, 371
rigging 296
scheduling 10 C
selection 259 Cabinets 124–5
shopping 296 base 181–2
subcontractor 172, 283 medicine 365
submission 16, 282–8 Cable TV 366, 368–9
time 257 Calculations 278
bid-day activities 14–6 Calculator 8
bidding Caret (ˆ) 39
fair 296 Carpentry finish 365
practices 296 Carpet 168, 366
rhythm 264 Cash equivalents 240–2
warming up 264 Casing 365
Billable hours 370 Catalogue cut sheets 282–3
Billing disputes 289 Catalogue of Standard Specifications and Load Tables for Steel
Birds mouth 120 Joists and Joist Girders 101
Block 89–93, 370 Catch basins 368
bond-beam 89–90 Caulk 366
bullnose 90–1 Ceiling
lintel 90–1 dropped 185
Blocking 110–1, 117–8, 364, 370 function 42–3, 366
Block-out 367–8 joists 119, 121
Board feet 108, 110, 113, 353 painting 168
Bodily injury 244 Cell 371
Boiler 370 combining 33
Bold 32 formatting 31
button 32 merging 33
Bolts 98, 100 naming 323–5
expansion 365 unmerge 33
molly 365 Cement powder 67
380 INDEX

Center button 31 chilled water 67


Centerline method 75 columns 364
Ceramic tile 164–5 curb 214–5, 237
Certifications 4, 282, 371 curing 78
Certified payroll 290 design-based specification 67
Chair rail 365 finishing 66, 68, 78
Chair rebar 67 footings 364
Change order 3, 10, 258, 290, 371 forms 66–7, 215
Channel American standard 98, 371 life of 67
Chases 365 reuse 66
Check foundations 364
joint 290 gutter 214–5
valve 172, 371 hot water 68
Chiller 371 ice 67
Chimney 141 masonry unit 371
Circle 344–5 material 67–8
quarter of 346 mixes 364
Circular reference 299, 301 performance-based specification 67
Clarifications 258, 283, 286 placement 66, 68
Cleanouts 177–8 productivity 359
Clean-out boxes 368 protection 68
Cleanup 5, 291 pump 68, 364
Clipboard 27–8 short loads 67
Close-out audit 17, 371 site 215
Closet rod 365 slump 67
CMU 371 stairs 81–2
Coil 371 strength 67
Collar ties 119, 121, 371 truck 68
Color 307 walls 364
Column 69–71, 98–100, 203, 350–2, 371 waste 68
headings 47 weight 81
widths 28, 30 Condenser 367, 371
dialogue box 30–1 Conditional formatting 307–10
minimum 30 button 307
wood 364 rules manager dialogue box 308–9
Combining cells 33 Cone 350–1
Combustion air 367 Conferences 295
Comma style button 33 Confirm password dialogue box 313
Comments 28 Conflict of interest 296
Commercial storefront 155–6 Connectors steel 98, 102
Commitment 295 Constant area 351–2
Communication 17, 257, 357 Construction
productivity 363 cost 263–4
verbal 2–3 documents 230, 289, 295
with field 58–9 methods 2, 58, 293–4
written 2–3 Construction Specifications Canada 9
Compacted 200–2, 210 Construction Specifications Institute 9
cubic yards 371 Contact information 285
Competitive bidding 371 Continuous
Competitors tracking 264–5 footing 371
Completeness 277, 295 improvement 17
Complex Contour lines 206
shape 346–50 Contract 4, 371
volumes 352 alternatives 289
Composite slab 371 annual 228, 230
Composites 355 assignment 289
Compression fitting 176 change order 290
Computers 8 documents 258, 264
Concatenate 329–30 general provisions 291
Conceptual estimate 3–4 inspections 290
Concrete 66–85, 183, 225, 354–5, 371 materials 228, 292
admixtures 67 parties 289
INDEX 381

payment 290 Cross-sectional method 204–9


price 290 Cross tees 165
project identification 289 Crown molding 365
quality 290 CSI 9
quantities 289 Ctrl key 25
retention 290 Curb 369
schedule 290 walls 369
of values 289–90 Current
submittals 290 date button 37
termination 291 time button 37
testing 290 Cushioning 167
voiding 291 Cut 27
Convection 185 button 27
Conversion factors 278, 317, 352–3 Cwt. 229
Conveying equipment 356 Cycle time 235–7, 371
Cooktop 189 Cylinder 350
Coordinate method 349–50
Coordination 290 D
special 293–4 Damage 230
Copper pipe 176 Damper 371
Copy 28 fire 367
button 28 smoke 367
worksheet 25 Dampproofing 134–5, 371
Corner Data
piece siding 143 entry 26–30
trim 146 historical data 64–6, 81, 139–40, 163–4, 168, 228–9, 235, 238,
Cost 257, 259, 296, 317
accrued 240 manufacturer’s 64, 110, 139–40, 163–4, 168, 250–1
actual 228 validation 310–2, 325–6, 335
code 10, 17, 52, 57, 267, 270, 277, 279, 354–8, 371 button 310
construction 263–4 dialogue box 310–1, 325–6
controls 3–4, 16 Database 9, 17
equipment 57, 248–52 Davis-Bacon wages 240, 371
escalation 230 Deck
labor 2, 9, 12–3, 57, 60, 254, 268–70, 318 metal 102
large 277 wood 113
material 2, 12, 57, 60, 267–70, 317–8 Decrease decimal button 34
operating 248, 250 Deflection 81
ownership 248–9 Delays 58, 60, 234
shipping 229, 267 Delete
square foot 279 button 24
storage 267, 230 popup menu 25
total 269–70 Delivery 229
tracking 228 Depreciation 248–50
Counted items 60 Design
Countertops 124–5 information 234
Coverage rate 64, 140 professional 4, 67, 115, 165, 168, 210, 258, 282,
CPVC 176, 371 286, 371
Crane 365 Design-build 283
sizing 98 subcontract 172
Crawl space 181 Desired results 315–6
Crew 13 Detail worksheet 29, 267–70, 272–4, 298, 301, 304
day 233 Detailed
in-house 257 estimate 3–4, 10, 277–8
makeup 255, 293 oriented 3
rate 254–6, 316–7, 371 Detention ponds 368
size 234–5 Dialogue box 371
minimum 290 column 30–1
Cripple stud 371 conditional formatting rules manager 308–9
Cross bracing steel 98 confirm password 313
Cross section 220–1 data validation 310–1, 325–6
area 81 format cells 32, 34, 309, 312
382 INDEX

Dialogue box (Contd.) Draft stops 365


function argument 42–4 Drain
insert 23–4 board 134, 372
function 41 pipe 176–9
launcher 19 valve 172
macro 305 Drainage system 134
move or copy 26 Drawings 4, 11, 60, 258, 264, 278, 285–6, 316–7, 367, 372,
name manager 324–5 374, 377
new as-built 290
formatting rule 308 Drip edge 141–3
name 323 Driveway 183, 369
open 19–20 excavation 210
options 22, 302 Dropdown box 325–6, 372
page setup 48–9 Dry
paste density 200
name 324 unit weight 200, 372
special 28 Dryer 189, 367–8
picture 37 Drywall 162–4, 364–6, 372
print 46–7 compound 162–3, 372
protect worksheet 313 fasteners 162–3
recent files 21 fire-rated 163, 365
record macro 303 moisture-resistant 365
save as 20–1 patching 366
security options 301–2 scrap 366
trust center 302–3 tape 162–3
unprotect worksheet 313 trim 162–3
warning 25, 33 water-resistant 163
zoom 35 Duplication 277
Diffuser 165, 371 Durable wood 372
Digitally signed 301–2 DWV 176–179
Digitizer 7, 61, 75, 77, 341–2, 371
Dimensional analysis 353, 371 E
Dimensions Earthquakes 117
adding 341–2 Earthwork 9, 200–11, 357, 368–9
subtracting 341–2 productivity 363
Direct Economy 230
costs 371–2 Effective
overhead defined 56 length 61–2
Disconnects 366 width 62
Dishwasher 367–8 Efficiency system 235–7
Disposal 368 EIFS 140–1, 372
Dispute resolution 291 Electrical 183, 189–96, 357, 365, 368
Dollar sign 40 box 190
Door 153, 365–6 junction 190–1
access 367 breaker 189, 192–3
cylinder 155–6 box 368
exterior 365 commercial 190–3
frame 157 conduit 189, 190–3
wood 162 controls 189
jamb 117, 153 disconnect 368
mortising 153 distribution 191
opening 93, 113, 115 fixtures 368
painting 168 fluorescent light 190
predrilled 153, 157 light fixture 165, 189–91
prehung 57, 157 meter 191–2
schedule 153–4, 157 base 368
sliding glass 153, 365 motors 189
stop 155–7 outlet 189–90
swings 153 panel 189–90
wood 153 panelboards 191–3
Double check 278–9 plan 189, 191
Dowels 71 productivity 362
INDEX 383

raceway 190 transportation 248


Romex 189 use 58
starters 189 value 249
switches 189–90, 368 wear 251
transformer 189 items 248–9, 251
wire nuts 190 Error
wireway 192 alert 310–2
wiring 191, 368 canceling 278
commercial 190–3 checking 8, 16
diagram 191 protection 298, 307–14
residential 189–90 Errors 8, 277–9, 335
Elevators 365 identification of 17
E-mail 286, 288 Escalation 267
Embed 364 Escutcheon 174, 372
Employee Estimate
annual cost 245 accuracy 17
class 240, 254 architect’s 11
cost 240 complete 14
death 244 conceptual 3–4
exempt 241 detailed 3–4, 10, 277–8
injury 244 engineer’s 11
occupational illness 244 errors 16
End condition 60–1, 71, 78, 84, 114, 372 final 3–4
Engineer 258 preliminary 3–4, 10
Engineer’s review 279
estimate 11 too high 2
scale 7, 343, 372 too low 2
Environmental inspections 6 types of 3–4
EPDM 146 Estimated cost 372
Equations identifying 315, 317 Estimating 372
Equipment 293–4, 356, 366 art of 3
bucket teeth 250 computerized 8–9
costs 2, 9, 12–3, 57, 248–52, 254, 268–70 database 9, 17
cutting edges 250 department 2
damage 251 fundamental principles 3
depreciation 248–50 inaccuracies 4
different 58 math 2, 341–53
expected life 248 poor 14
filters 248, 250–1 practice 3
fuel 248, 250–1 process 10–7
insurance 248–9, 251 software 8
interest 248–50 package 372
leased 248, 251 tools 7–8
license 248–9, 251 Estimator 2–3, 372
life 248 skills of 2–3
lubricants 248, 250–1 Ethics 295–6, 372
maintenance 251 dilemmas 296
overhaul 251 Ethylene propylene diene monomer 146
owned 248 Excavation
price 13, 15, 248 average-end method 203–4, 209, 220–2
procurement 17, 289 modified 204, 209, 220, 222
quantities 2, 12 average-width-length-depth method 203, 209
rented 248, 251 backfill 210–1, 225
repair 248, 251 base 369
reserve 251 basement 204
sales tax 248 building 208, 210
salvage value 248 clear and grub 369
setup 248 comparison of methods 208–9
storage 248–9, 251 contour lines 206
taxes 248–9, 251 costs 6
tire 248–9, 251 cross sections 203–4
repair 250 cross-sectional method 204–9
384 INDEX

Excavation (Contd.) spread footings 69


cut 203–9 structural steel 100
driveway 210 studs 117
fill 203–8 summary worksheet 271
footing 210–1 trench excavation 222–3
foundation 210–1 waterproofing 135
geometric method 202–3, 209, 222–3, 344–8 Exclusions 15, 258, 283
grade Executable code 301
existing 206 Exhaust fan 184, 367–8
proposed 206 Existing conditions 354
grading data 210 Expense additional 58
gravel underslab 211 Experience modifier 244
grids 204–5 Export 210, 225
rough grade 369 Exterior improvements 214–6, 357
sidewalk 211 productivity 363
site 204 Exterior insulation finish system 140–1, 372
trench 220–3
zero line 205, 207 F
Excel 3, 8, 18–52, 372 F4 key 40
advanced options 26–7 Fan 185
asphalt 215 coil 367
average-end method 222 Fascia 121–4, 143–6, 366, 372
modified 222 Faucets 179, 367
base 215 Federal Insurance Contributions Act
batt insulation 139 242, 372
bedding 224 Federal unemployment tax 242–3
block 92–3 Fence 214
board foot 110 Fiberbond 364
bond cost 263 FICA 242, 372
brick 94 Field measure 155–6
building permit 262 File 372
ceramic tile 165 name button 37
column path button 37
rectangular 70 type 18
round 71 Fillet weld 372
competitor tracking 265 Final estimate 3–4
continuous footing 75–6 Finish carpentry 124
crew rates 255–6 Finishes 162, 356
cycle time 236–7 productivity 361
decking 113 Fire
detail worksheet 269 blocking 111, 117–8, 364
drywall 164 department
equipment costs 251–2 connections 172–3
floor sheathing 112–3 Siamese 172–3, 372, 375
foundation wall 78 prevention 111, 117–8
geometric method 223 sprinkler 367
icon 18–9 drop 173
insulation batt 139 heads 172–4
joists 112 suppression 172–4, 356
labor rate 246–7 productivity 361
metal deck 102 treated wood 162
rafters 122 walls 122, 365
rate of progress 237 Fireplace 368
request for material quote 231 gas 184
roofing mantels 365
felt 138 Fire-rated labels 366
shingles 142 Fit selection 35
siding 144–5 Fittings 368
slab compression 176
on grade with rebar 79–80 Fixtures 366–7
on grade with wire mesh 80 Flashing 141, 146, 366, 368
raised 81 HVAC 183
INDEX 385

pipe 367 wall 76–8, 372


plumbing 177, 179 corners 76
Floor Framing 364–5
covering 366 anchor 110, 372
drains 179, 367 plan 59
function 42–3 floor 109
opening 110–1 joist 100–1
painting 168 roof 123
sheathing 112–3 steel 99
wood 108–13, 166–7 Free on board 229
Flooring Freight 15
carpet 168, 366 Fringe benefits 241
laminate 166–7 Frost wall 84
pad 168 Function 41–5, 372
trim 168 argument dialogue box 42–4
vinyl 167–8, 366 library 41, 44
composition tile 168 Furnace 181–2, 365–8
waste 167 filters 368
wood 108–13, 166–7 Furnishings 356
Flow alarm 172, 372 Fusible link 174, 372
Fly ash 67 FUTA 242–3, 372
FOB 229, 372
Folder 372 G
Font 37, 307 Gable
dialogue box launcher 32 ends 119, 122–3, 142
dropdown box 31 truss 372
size 31–2 roof 141
dropdown box 31–2 Garage 365–6
style 31 Gas
Foolproof 50 line 183–4, 220, 367–8
Footers 36–8 meters 366
Footing 364, 372 Gasket 225
centerline method 75 General
continuous 71–6 conditions 4–5, 372
corners 71–2, 75 decision 240, 372
excavation 210–1 liability insurance 240–2, 244
intersection 71, 75 overhead 372
spot 68 requirements 354
spread 68–9 Geographical area 264
Forklift 365 Geometric method 202–3, 209, 222–3, 344–8
Form layout 298 Girder 98–100, 372
Format wood 110
button 25, 31 Glass 156–7
cells 31 Glazing 154–7
dialogue box 32, 34, 309, 312 safety 154, 156
picture button 37–8 tempered glass 154, 156, 375
popup menu 24 GLB 110, 372
Formatting 28 Glue
Forms 66–9, 71, 76, 78, 81, 372 carpet 168
converting 298–314 lam beam 110, 372
new 315–36 thinset 164
planning 315–9 VCT 168
supporting 78, 81 Go-footer button 38
Formula 8–9, 28, 298–301 Go-header button 38
bar 19, 40 Grab bars 117, 365
copying 301 Grade finish 215
editing 40 Grading 68
selecting between two 317 Grammar 295
testing 278–9, 298, 301 Gravel 68, 223
wrong 278 Gridlines 48
Foundation 364, 372 Grille 165, 181, 185, 367, 372
end condition 78 Groups in Excel 19
386 INDEX

Grout 89–91, 164, 372 furnace 181–2, 365–8


Gutters 214–5, 369 grille 165, 181, 185, 367, 372
Gypcrete 183 heat
Gypsum board 162–4 exchanger 185
pump 184
H heaters 189
Handrail 365–6 humidifying 181
steel 102–3 line sets 181, 373
Hardibacker 164 package unit 185, 374
Hardiplank 145 plenum 182, 185
Hardware 365 productivity 362
butts 157 pump 183
closers 157 radiant heat 183–4
cylinder 157 registers 165, 181–2
doorstop 155–7 residential 181–4
hinges 155–7, 366 return
locksets 157 air 181–2, 185
panic 155–7 manifold 183
pulls 157 rooftop 184
schedule 155 supply 181–2
silencers 157 manifold 183
threshold 155–7 thermostat 183, 185, 367
weather stripping 155–7 trunk line 181–2
Hanger pipe 173, 374 valves 183
Head storefront 155–6 variable-air-volume box 185
Header 36–8, 373 VAV box 185, 376
metal studs 162 vents 181–2
wood 109, 115, 117–8, 364 Heavy Construction Systems Specialists Inc. 8
Header and footer Heavy timber construction 113
button 36 Heavybid 8
tools design menu 37 Height dropdown box 48
Heat High dollar items 10–1
exchanger 373 Highlighter 278
loss 134 Hinges 155–7, 366
temporary 368 Hip
Heating, ventilation and air-conditioning 181–6, 258, 357, 365, rafters 373
367–8, 373 roof 120–2, 136–8, 141–2
air Historical data 64–6, 81, 139–40, 163–4, 168, 228–9, 235, 238, 257,
conditioners 181–6, 189, 367–8 259, 296, 317
ejector 183 Hold down 116–7, 364, 373
filtration 181 Holidays 240–1
handler 185 Hollow metal 153–4, 156
boiler 183, 185 Honesty 296
cap termination 183 Hose bibs 367
chillers 185 Hours
coil 181–2 billable 240, 245, 249
combustion gasses 181 unbillable 245
commercial 184–6 Hundredweight 229
condenser 181 HVAC 181–6, 258, 357, 365, 367–8, 373
controls 184 air
damper 185 conditioners 181–6, 189, 367–8
dehumidifying 181 ejector 183
diffusers 165, 371 filtration 181
ductwork 181, 185 handler 185
electric baseboard 184 boiler 183, 185
exhaust fans 184, 367–8 cap termination 183
expansion tank 183 chillers 185
fan 185 coil 181–2
fin-tube convector 185–6 combustion gasses 181
flashing 183 commercial 184–6
flexible duct 185 condenser 181
INDEX 387

controls 184 Information proprietary 296


damper 185 Input data 317
dehumidifying 181 identifying 316–7
diffusers 165, 371 message 310–1
ductwork 181, 185 Insert
electric baseboard 184 button 23
exhaust fans 184, 367–8 dialogue box 23–4
expansion tank 183 function
fan 185 button 41
fin-tube convector 185–6 dialogue box 41
flashing 183 picture dialogue box 29
flexible duct 185 popup menu 23
furnace 181–2, 365–8 worksheet tab 19, 23
grille 165, 181, 185, 367, 372 Inspections 290, 293–4
heat Instructions to bidders 4, 370
exchanger 185 Insulation 89–90, 138–40, 365
pump 184 batt 138
heaters 189 blown 138–9
humidifying 181 fiberglass 138
line sets 181, 373 paperbacked 138
package unit 185, 374 ridged 140
plenum 182, 185 Insurance
productivity 362 benefits 240, 244–5
pump 183 certificates 290
radiant heat 183–4 dental 244
registers 165, 181–2 disability 244
residential 181–4 equipment 248–9, 251
return health 244
air 181–2, 185 life 244
manifold 183 requirements 290
rooftop 184 workers’ compensation 290
supply 181–2 Insured additional 290
manifold 183 Intercom 368
thermostat 183, 185, 367 Intermediate mullion storefront 155–6
trunk line 181–2 Internal Revenue Service 242, 247
valves 183 International Building Code 152, 156, 161
variable-air-volume box 185 International Code Counsel 152, 156, 161
VAV box 185, 376 Interpolation 206
vents 181–2 Interruptions 234
Hydrants 368 Inventory control 365
Hydroseeding 369 Invitation to bid 4, 373
Invoice 228–9
I Irrigation systems 214–5, 369
Ice and Water Shield 136, 138, 141 IRS 242, 247
Ice-maker boxes 367 Isometric drawing 177
Icon 373 Iteration 262–3, 299–300
If function 44–5
nested 45
I-joist 373
J
Jack
Illegal behavior 296
rafters 373
Imbeds 89–90
stud 373
steel 103
Jamb 373
Import 210, 225
storefront 155–6
Improvement constant 3
J-molding 143, 163
In situ 200, 373
Job
Included by reference 6–7, 373
overhead 373
Increase decimal button 33
title 285
Indirect
Jobsite overhead defined 56
costs 373
Joist 173, 181–2, 373
project costs 373
girder 100–2, 373
Inflation rate 230
388 INDEX

Joist (Contd.) Liquid damages 264


hangar 373 List box 373
header 373 Lists 320
steel 100–2 Loan 248
trimmer 373 Locksets 157
wood 109–12, 364 Logical operators 44
Long-lead 293–4
K Lookouts 122–3, 373
Key Lookup 332–4
shortcut 303 Loose 200–2, 210
word search 41 cubic yards 373
Keyless entry 157 Lost cost factor 244
King Loyalty 296
rafters 373 Lumber 108–26, 355
stud 373 backing 117, 162, 364–5
beam 364
L blocking 110–1, 117–8, 364, 370
Labor 289, 293–4 ceiling joists 119, 121
breaks 236 collar ties 119, 121, 371
burden 240–1, 371, 373 columns 364
markup 245 decks 113
class 234 doors 153
cost 2, 9, 12–3, 57, 60, 254, 268–70, 318 fascia 121
hour 233, 235, 238–9, 254, 268, 293, 315, 318, 373 fire blocking 111, 117–8, 364
tracking 235 fire-treated 162
pricing 13, 15 floor 108–13, 166–7
productivity 9, 233–8, 254, 359–63, 268, 277, 316–9, 373 joist 110–2, 364
factors affecting 233–5 sheathing 112–3
field observations 235–8 squeaks 112
quantities 2, 12 trim 167
rates 9, 240–7, 268, 277, 316–8, 373 framing 156
skill of 2 girder 110, 364
Laminate floors 166–7 gluing 112
Laminated lumber 117 header 109, 115, 117–8, 364
Landscape page orientation 47, 373 I-joist 110
Landscaping 214–6, 369, 373 joist 109
plan 216 ceiling 121
plants 215–6 header 109, 110–1
Lap joint 61, 63, 67, 89, 135 tail 111
Lateral forces 117 trimmers 110–1
Lavatory 176, 179 laminated 117
Layout 364 lintels 364
Learning curve 234 naturally durable 113
Ledger steel 93, 98 package 108
Left click 373 paneling 124
Length 341 plate 109, 113–4, 364
effective 61–2 plywood 112–3, 117–8
Letter post 110, 364
business 285–7 pressure-treated 108, 113, 374
formats 286–7 productivity 360
proposal 282 purlins 364
Lhr 373 rafter 119–22, 364, 374
License requirements 290 common 121
Lien waivers 290 hip 120–1
Light fixtures 165, 189–91 jack 121
Limitations spreadsheet 50 king 121
Line set 181, 373 valley 120–1
Linear components 61 random lengths 108
Link 28 ridge 137–8, 141–2
Lintel 373 board 121
masonry 89 rim board 110
steel 89, 93, 98 ring-shank nail 112, 375
INDEX 389

risers 364 ties 89, 93


roofs 119–24 waste 90
shear panels 117–8, 375 Masterformat 5–6, 9, 55, 354
sheathing 109, 112–3, 364 Material 2, 292–4
roof 123 contract 228, 292
waste 112 costs 2, 12, 57, 60, 267–70,
shelving 124, 365 317–8
sill 108–9, 364 damage 230
plate 109 different 58
window 116 fob 229, 372
sleeper 364 free on board 229
slip-resistant nail 112 improper use 64
stingers 364 installation 5
stud 109, 113–7, 162, 364 invoice 228–9
cripple 116 long-lead 293–4
jack 109, 115–7 loss 64
king 109, 115–6 orders 3–4
precut 114 pricing 12–3, 15, 228–31, 316
treads 364 procurement 17
trim 124, 146 protection 230
trimmers 364 purchase 289
trusses 109, 119, 122–3, 364 quantities 2, 5, 12
tails 122 safety data sheets 290
walls 113–119 scrap 64
corners 114, 116 testing 5
ends 114 theft 230
hold-downs 114, 117 use 4, 58, 65
intersections 114–5 wrong 58, 60
openings 114 Math 2, 341–53
web stiffeners 110, 376 Mediation 291
Lump sum 56 Medicare 242
bid 373 Meeting pre-bid 10
Membrane roofing 146, 374
M Menu tab 19
Macro 278, 298, 301–5 Merge and center button 33
button 303 Merging cells 33
dialogue box 305 Metal
recording 302–4 deck 80, 102, 374
security grid 165
level 301 productivity 359–60
warning 301–2 stud 162
settings 302 header 162
stop recording 304 jack stud 162
Main king stud 162
lines 172–3 opening 162
tees 165 Metals 97–103, 355
Maintenance equipment 251 Method of construction 58
Man hours 239, 373 see labor hours Mhr 374
Manholes 368 Microwave 368
Mantels 365 Miscellaneous steel 103
Manual of Steel Construction 97 Moisture 163, 167
Manufacturer’s data 64, 110, 139–40, 163–4, productivity 360
168, 250–1 protection 134–48, 355
Marking off items 60 Moldings wall 165
Markups 15–6, 261–5, 370, 373 Mono-truss 374
Masonry 89–94, 355 Mortar 89–90, 93, 374
bond beam 89 thickset 164
cells 89 Move after typing 26–7
insulation 89–90 Move or copy
lintels 89 dialogue box 24, 26
openings 90–2 sheet 24
productivity 359 MSDS 290
390 INDEX

Mullion 374 general 15, 263


Multiple cells selecting 25 jobsite defined 56
main office 263
N markup 15, 270–1
Nails 365 project 13–5, 259
Name Overtime 234, 290
box 19, 323 Owner 2, 4, 282
cells 323–5 Ownership cost 248–9
manager
button 324–5 P
dialogue box 324–5 Package unit 185, 374
Naming cells 323–5 Pad 168
National Council on Compensation Insurance 244 Page
National standard books 229, 238 break
Naturally durable wood 108 preview 49
NCCI 244 button 49
Nested if functions 45 setting 49
New view button 49
folder button 22 layout 47
formatting rule dialogue box 308 button 19, 36
name dialogue box 323 view 36
Nominal 374 number button 37
Noncontiguous cells 43 orientation 47
Nonresponsive bid 374 setup dialogue box 48–9
Normal view 49 launcher 48–9
button 38, 49 Paid-when-paid 290, 374
Notice-proceed 290 Paint 168, 365–7
Number Paneling wood 124
dialogue box launcher 34 Panic hardware 155–7
of pages button 37 Paper forms 8
Numbers consecutive 320 Parallelogram 344–6
Parapet wall 146
O Parenthesis 39
Occupational Safety and Health Act 290 Parking lots 368–9
Office trailer rental 56 Partitions
On Center Software 7 fire-rated 163
On-Screen Takeoff 3, 7–8 non-bearing 162
Open dialogue box 19–20 Password 313
Opener overhead door 157 Paste 27–8
Opening 93, 153–7, 356 button 27–8
door 117–8, 113, 143, 145–6 name dialogue box 324
floor 110–1 special 28
productivity 360–1 dialogue box 28
window 117–8, 143, 145–6 popup menu 28
Operation and maintenance manuals 290 Path 374
Operating cost 248, 250 Pattern 307
Operators 39 match 167–8
logical 44 Paving 214, 237
Optional bid item 374 Paydirt 7
Options dialogue box 22, 302 Payment
Order of operation 39 bond 4, 263, 270, 374
Orientation button 47 final 290
Oriented-strand board 112–3, 117–8, progress 290
123–4, 374 terms 283, 286, 290
OSB 112–3, 117–8, 123–4, 374 Payroll taxes 240–2
OSHA 290 Peer review 279
Output 233, 374 Penetrations 141, 146
Overbuild 119, 374 Pennies dropping 279
Overhead 263–5 Pension plan 245
checklist 14–5 Percent style button 33
direct defined 56 Performance bond 4, 263, 270, 290, 374
door 157 Pergo 166
INDEX 391

Perlite 90 Portrait page orientation 47, 374


Permit 367 Post 374
Personal base 110, 364
injury 244 cap 110
title 285 wood 110, 364
Pex 176, 374 Post-bid activities 16–7
Phone quote 15–6, 228 Post-it 14, 282
Picture Power 39
adding 29 lines 220, 368
button 29, 37 meters 366
dialogue box 37 temporary 365
Pipe 237, 367 Pozzolan 67
copper 176 Practice problems 315, 317
CPVC 176, 371 Preliminary estimate 3–4, 10
drain 176–9 Prequalification package 10
hanger 173, 374 Presentations 3
Pex 176, 374 Pressure test 176
steel 98 Pressure-treated wood 108, 113, 374
vent 141, 176–9 Price 259, 277, 283, 286
waste 176–9 breakdown 282
Plan combining 15
and profile 220 extensions 267–76
measurer 7, 61, 75, 77, 190, 317, 341–2, 374, 376 too high 17
view 317 too low 17
Plans 4, 11, 60, 258, 264, 278, 285–6, 316–7, 367, 372, 374, 377 Pricing
framing 59 database 9, 17
Plastic materials 12–3, 15, 228–31, 316
laminate 125 Primer 366
sheet 138 Print 37, 46–9
tubing 183 button 46
Plastics 355 dialogue box 46–7
Plate entire workbook 46
wood 109, 113–4, 364 gridlines 48
steel 98, 100, 374 landscape 47
Plenum 374 number of copies 46
Plumbing 176–9, 258, 357, 365, 367 portrait 47
air chamber 176 range 46
bushing 179 scale 35
cleanouts 177–8 to fit 48
equipment 179 selection 46
faucet 179, 367 setting
flashing 179 page breaks 49
floor drain 179, 367 scale 48–9
flush valve 179 settings 46
lavatory 176, 179 titles button 47–8
pressure reducing valve 176, 374 Printer 8
productivity 361–2 properties 46
p-traps 176–7, 179, 374 selection 46
sanitary tee 179 Prism 203, 350–2
shutoff valve 172, 176, 179 Production
sink 176, 179, 367 daily 238
stub-out fitting 176 time 237
test cap 179 Productivity
toilet 176, 179, 367 communication 363
flange 179 concrete 359
urinal 176, 179 earthwork 363
water electrical 362
closet 176, 179 exterior improvements 363
heater 176 finishes 361
Plywood templates 364 fire suppression 361
PO 3, 17, 291–3, 374 HVAC 362
Polyvinyl chloride 146, 374 labor 9, 233–8, 254, 359–63, 268, 277, 316–9, 373
392 INDEX

Productivity (Contd.) R
factors affecting 233–5 Radiant heat 183–4
field observations 235–8 Rafter 119–22, 364, 374
masonry 359 ties 374
metals 359–60 Raised slab 374
openings 360–1 Random length 374
plumbing 361–2 Range 189, 368
rates 13 hood 368
specialties 361 Rate of progress 237, 374
thermal and moisture protection 360 Rebar 66–7, 69, 71, 76, 78, 89–90, 374
utilities 363 dowels 68–9
woods 360 epoxy coated 67
Profit 263–5, 270–1, 277 shop fabricated 67
margin 2 size 67
markup 15 ties 68–9
Progress payment 4, 283, 374 weight of 67
Project Recent files dialogue box 21
buyout 17, 289–92, 371 Record macro dialogue box 303
layout 235 Rectangle 344–6
location 289 Redlining 59
management team 17 Redwood 108, 113
managers 2, 17 Reference
manual 4–7, 11, 258, 264, 286 absolute 40, 302–3, 370
overhead 13–5, 259 books 64
size 233–4, 259, 264 relative 40, 302–4, 374
type 264 Register 374
Property damage 244 Reimbursements 242
Proposal 257, 282–5, 338–40, 374 Reinforcing 67
Protect worksheet lap 67
button 313 Relationships working 296
dialogue box 313 Relative reference 40, 302–4, 374
Protection of work 235, 290, 364 Repair multiplier 250
PRV 176, 374 Repetitive members 60
P-trap 176–7, 179, 374 Request
Public agencies 4 for materials quote 228–9, 268–70, 291, 374
Purchase order 3, 17, 291–3, 374 for proposal 257
log 291–2 for quote 11–2, 257–8
Purlins 364 Resilient floor 366
PVC 146, 374 Retaining walls 214
Pyramid 203, 350–2 Retention 290, 374
Pythagorean theorem 119–20, 122–4, 341, 344 ponds 368
rate 283
Q Retirement contributions 240, 245
Quality 4, 9, 259, 290, 295 Return line 185
actual 228 RFP 257
survey 56, 374 RFQ 11–2, 257–8
takeoff 4, 12–3, 228, 277, 374 Ridge board 375
defined 56 Right click 375
fundamentals 56–65 Rim
package 7–8, 61, 75, 77, 190 board 375
performing 56–7 joist 375
quick-and-dirty 278 Ring-shank nail 112, 375
software package 317, 341–2, 375 Ring ties 375
Quantity-from-quantity goods 64 Rise 120, 375
Quick Riser pipe 172–3
access toolbar 19, 46 Risk 12, 264–5, 277
customizing 46 Roads 368, 368–9
print 46 Rock ballast 146
Quotes Rod threaded 173
e-mailed 15 Roll goods 61–3
faxed 15 Romex 189
phone 15–6, 228 Roof 344
INDEX 393

framing plan 123 Security 230, 249


hip 120–2, 136–8, 141–2 options dialogue box 301–2
joist 344 systems 368
lookouts 122–3, 373 Seismic straps 58
overhang 120, 122 Selecting multiple cells 25
ridge 137–8, 141–2 Self-adhering bitumen 136
sheathing 123 Selling price 375
shingle 141–3 Series 320
cap 141–2 Setting page breaks 49
exposure 141 Severe weather 285
slope 120–1, 124 Sewer
span 120 gas 176
starter row 141–2 lines 368
valley 136–8, 142 Shafts 365
waste 123, 136 Shear panel 117–8, 375
Roofing Sheathing 118–9, 375
asphalt shingle 315 wood 109, 112–3, 364
membrane 146 Sheet
Roof-top unit 375 goods 61–3
Rough carpentry 108–26 metal 182
Round function 41–2 name button 37
Rounddown function 42 tabs 19
Rounding 60–1, 63 vinyl 167–8, 366
Roundup function 42 Shelving 124, 365
Row and column method 63 Shift key 25
Row heights 31 Shimming 117
Rows repeating at top of page 47–8 Shingles 141–3
RTU 375 Shipped lapped 145
Rubber base 168, 366 Shipping cost 229, 267
Run 120, 375 Shop drawings 97
Runner 162, 375 Shortcut key 303
Shower pans 367
S shrinkage 200–2, 225, 375
Safety 235, 244, 290 percentage 201–2, 210
glazing 154, 156 Shrubs 369
meetings 290 Shutoff valve 172, 176, 179
plan 290 Shutter 366
regulations 220 Siamese connection 172–3, 372, 375
Sag 80–1 Sick leave 240–1, 245
Sales tax 15, 229–30, 248, 267 Sidelight 156
Sample Sidewalk 183, 369
durations garage 294 excavation 211
takeoff garage 82–5, 125–6, 146–8, 157, 169, 193–6, 210–1, 216, Siding 143–6, 366
272–6, 294 aluminum 143
Samples 282 board 145
Sand 223 sheet wood 146
Sanitary sewer 220 vinyl 143
Save as dialogue box 20–1 waste 143
Scale 7, 61, 190, 341–3, 370 wood 145
to fit 48 Significance 42–3
Scaling 342–3 Sill 108–9, 375
Schedule 57, 66, 259, 264, 282, 285, 290, 293–4 plate 375
durations 293–4 Seal 108, 113, 375
of values 4, 6, 14, 282–3, 289–90, 375 storefront 155–6
Scope of work 2, 4–5, 10, 14, 257–9, 283, 285, 289, 375 Sink 176, 179, 367
model 364–9 Siphoned 177
Scrap 64 Site lighting 369
Screws 365 Slab
Scroll bar 19 composite 81
Seaming diagram 366 on grade 78–80, 375
Search key word 41 raised 80–1
Second-tier subcontract 375 Sleeper 364
394 INDEX

Sleeves 364, 367–9 nosing 167


Slope 120–1, 124, 375 steel 102–3
Social security 242 stringers
Sod 369 steel 98
Soffit 143–6, 365–6, 375 wood 118
vented 143 Standardized form 277
Soil Starter strip 143
bank 200–202, 210 State unemployment tax 242–3
characteristics 200 Status bar 19
compacted 200–2, 210 Steel 97–103
compaction 200 angles 89, 93, 98, 100, 103
conditions 220 base plate 98
dry bolts 98
density 200 connections 97–9, 101–2
unit weight 200, 372 dimensioning 97
excavation 200 fabrication 97
export 210, 225 framing plan 99
import 210, 225 handrails 102–3
in situ 200, 373 imbeds 103
loose 200–2, 210 Joist Institute 100–1
report 6, 210, 375 joists 100–2
shrinkage 200–2, 225, 375 ledger 93, 98
percentage 201–2, 210 lintels 89, 93, 98
swell 200–2, 225, 375 miscellaneous 103
percentage 200, 202, 210 pipe 98
transportation 200 plate 98, 100, 374
unit weight of water 200, 376 prime 97
water content 200 shapes 97–8
wet stairs 102–3
density 200 structural 90
unit weight 200, 376 timber brackets 103
Soldered 176 truss 102–3
Solvent weld 176 types of 97
Sonotube 66 welds 102
Sound Steps identifying 315, 317–8
attenuation 167 Stick framed 119, 122
system 368 Stirrups 78, 375
Spaced joint 63 Storage costs 267, 230, 248–9, 251
Spacing 60–1 Storefronts 153, 155–6
Special conditions 5, 375 Storm drain 220, 368
Specialization 234, 264 Striping 237
Specialties 356 Structural
productivity 361 brick 375
Specifications 5, 11, 229, 285, 290, engineer 67, 97
316–7, 375 steel 90
sample 283–4 tee 98, 375
Spelling 285, 288, 295 ties 89, 93
Splice 63 tubing 98, 375
Spot footings 68 Stucco 140
Spread footings 68–9, 375 Stud 109, 113–7, 162, 181, 364, 375
Spreadsheet 8–9, 18, 278 Subcontract 3, 17, 258–9, 289–91, 375
layout 315, 318–9 design-build 172
limitations 50 pricing 257–9
setup 319 Subcontractor 4, 11–2, 17, 286
testing 8, 49–50 bid 172, 269–70
Sprinkler head 375 past experience 15
Sprinkling system 369 performance 259
Square 344–6 pricing 14–5
root 39 selection 14–5
Stain 366–7 Subgrade 68
Stairs 366 Subject line 285
concrete 81–2 Submittals 5, 290
INDEX 395

Sum function 43 Thickened slab 376


Summary worksheet 12–3, 50, 52, 267, 269–71, 275–6, 298–9 Thickset mortar 164
Superintendents 17 Thinset glue 164
Suppliers 228–9, 286 Threaded rod 173
Supply Threshold 155–7
line 185 Ties 376
registers 367 Tile
Surety 4, 11 acoustical 165–6
SUTA 242–3, 375 ceramic 164–5
Swamp cooler 184 grout 164
Sweated 176 Timber brackets 103
Sweating 375 Timberline Precision Estimating 8
Swell 200–2, 225, 375 Time curing 294
percentage 200, 202, 210 Toilet 176, 179, 367
Synthetic stucco 140 paper holder 365
System efficiency 235–7 Tongue and grove 112, 167, 376
Top plate 376
T Topsoil 215–6
T&G 112, 123, 375 Towel
T1–11 143 bars 365
Tabs sheet 19 rings 365
Tackless fastening strips 168 Tracking
Tail joist 375 competitors 264–5
Takeoff 4, 9, 259, 290, 295 worksheet 37
defined 56 Trade
fundamentals 56–65 journals 295
package 7–8, 61, 75, 77, 190 magazines 230
performing 56–7 publications 295
quick-and-dirty 278 Transom 156, 376
software package 317, 341–2, 375 profile 155–6
Task 293, 375 Transpose 28
assignment 10 Trapezoid 344–5
linear 237 Travel time 237
relationships 293–4 Trees 369
repetitive 235 Trenching 220, 367–8
Tax Triangle 344–5
advisor 242 Trim 124, 146, 365–6
equipment 248–9, 251 Trimble 7
property 249 Truss 376
Technical specifications 5, 11, 229, 285, 290, wood 109, 119, 122–3, 364
316–7, 375 steel 102–3
Tee Trust 296
suspended ceilings 165 center dialogue box 302–3
steel 98 Trusted sources 301
Telephone 368–9 Tubing steel 98
boxes 366 Tubs 365–7
lines 220 Typographical errors 285, 288
Tempered glass 154, 156, 375 Tyvek 89
Templates 364
Temporary fencing 230 U
Testing 290 U.S. Department of Labor 240
spreadsheets 49–50 Unavoidable waste 376
Text Uncertainty 264
box 376 Underground service 172
button 329 Underlayment 141, 167, 366
string 329 Unemployment
wrapping 33 claims history 243
Theater system 368 insurance 240–3
Theft 290 Unethical behavior 296
Thermal protection 134–48, 355 Uniform Building Code 261
productivity 360 Union 245
Thermostat 183, 185, 367 contracts 240
396 INDEX

Union (Contd.) raise 240


dues 245 weekends 240
payments 240, 245 Walks 369
Unit 278, 315–7 Wall 366
pricing bid 376 bearing 110, 113, 122
weight of water 200, 376 coverings 365–6
Unmerge 33 fire 122
Unprotect worksheet foundation 76–8
button 313 moldings 165
dialogue box 313 painting 168
Use relative reference button 303 wood 113–9
Utilities 172, 220–5, 357–8, 368–9 Warning dialogue box 25, 33
productivity 363 Warranty 290
Utility Washer hookups 367
boxes 220, 224 Washout 368
conduit 224 Waste 63–5, 68, 376
lines 224–5 actual 68
manhole 220, 224 percentage 64–5
pipe 224 avoidable 4
room 366 control of 64
valves 224 definition 64
wire 224 tracking 64
controlling 68
V factor 64
V weld 376 flooring 167
Vacation 240–1, 245 pipe 176–9
Validation 28 roof 123, 136
Valley 136–8, 142 unavoidable 4, 63
rafters 376 definition 64
Valve 183, 368 wood sheathing 112
check 172, 371 Water
drain 172 closet 176, 179
flush 179 content 200, 376
pressure reducing 176, 374 heater 176, 367–8
shutoff 172, 176, 179 infiltration 134
utility 224 lines 220, 368
Vandalism 290, 364 main 172
Vanities 367 meter 368
Vapor barriers 135–8, 167, 376 softener 367
Variable-air-volume box 185 supply 176–7
Variables 39 table 6
VAV box 185, 376 Waterproofing 134–5, 376
VCT 168, 376 Weather 234–5
Vendors 4, 12 barrier 89, 93
Vent 366 caps 367
pipes 141, 176–9 stripping 155–7
Ventilation 181–6 Web stiffener 110, 376
Vinyl Weld field 97
composition tile 168, 366 Welded wire fabric 66–7, 78, 80, 376
flooring 167–8, 366 Welds 100, 102
siding 143 Wet
Viruses 301 density 200
Vlookup 332–4 pipe fire sprinklers 172
Volumes 350 unit weight 200, 376
Volumetric goods 63–4 Wheel 7, 61, 75, 77, 190, 317, 341–2,
374, 376
W Wide-flange beam 98, 376
Wage rate 240 Width
Wages 240–1 dropdown box 48
bonus 240 effective 62
overtime 240 Wind forces of 117
INDEX 397

Window 153–5, 365 random lengths 108


bucks 364 ridge 137–8, 141–2
fixed panels 154 board 121
opening 93, 115–6 rim board 110
operable 154 ring-shank nail 112, 375
safety glazing 154, 156 risers 364
schedule 153–4 roofs 119–24
seats 365 shear panels 117–8, 375
sills 365 sheathing 109, 112–3, 364
sliding residential 154 roof 123
tempered glass 154, 156, 375 waste 112
WinEst 8 shelving 124, 365
WinEstimator Inc. 8 sill 108–9, 364
Wire mesh 66–7, 78, 80, 376 plate 109
Wiring window 116
diagram 191 sleeper 364
low voltage 183, 367 slip-resistant nail 112
Wood 108–26, 355 stingers 364
backing 117, 162, 364–5 stud 109, 113–7, 162, 364
beam 364 cripple 116
blocking 110–1, 117–8, 364, 370 jack 109, 115–7
ceiling joists 119, 121 king 109, 115–6
collar ties 119, 121, 371 precut 114
columns 364 treads 364
decks 113 trim 124, 146
doors 153 trimmers 364
fascia 121 trusses 109, 119, 122–3, 364
fire blocking 111, 117–8, 364 tails 122
fire-treated 162 walls 113–119
floor 108–13, 166–7 corners 114, 116
joist 110–2, 364 ends 114
sheathing 112–3 hold-downs 114, 117
squeaks 112 intersections 114–5
trim 167 openings 114
framing 156 web stiffeners 110, 376
girder 110, 364 Word processing 3, 8
gluing 112 Work 376
header 109, 115, 117–8, 364 complexity 259
I-joist 110 duplication 258
joist 109 ethic 295–6
ceiling 121 package 57–8, 257–9
header 109, 110–1 protection of 290
tail 111 scope of 2, 4–5, 10, 14, 257–9, 283, 285, 289, 375
trimmers 110–1 model 364–9
laminated lumber 117 Workbook 376
lintels 364 creating 18
naturally durable 113 macro-enabled 304
package 108 management 18–22
paneling 124 new 19
plate 109, 113–4, 364 opening 18–20
plywood 112–3, 117–8 saving 20
post 110, 364 Workers’ compensation insurance 240–2, 244
pressure-treated 108, 113, 374 Workmanship 5
productivity 360 Worksheet 376
purlins 364 adding 23
rafter 119–22, 364, 374 copying 24
common 121 default number of 22–3
hip 120–1 deleting 24–5
jack 121 detail 26
king 121 formatting 30–9
valley 120–1 organizing 25–6
398 INDEX

Worksheet (Contd.) Z
protecting 312–4, 335 zoom 34–5
referencing 328–9 button 35
renaming 25 controls 19
summary 12–3, 26, 50, 52 dialogue box 35
testing 306–7 level 35
tracking 37 selection button 35
working with 22–6 slider 34–5
Wrap text button 33 to fit 35
Wrapping 33
Writing formulas 39–41
WWF 66–7, 78, 80, 376

X
xls 18
xlsm 18, 304, 376
xlsx 18, 376

Potrebbero piacerti anche