Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
High Voltage Power Cable (Installed), Continuity and Megger
SATR-P-3212 3-Jul-18 ELECT-
Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Schedule Q
A1 Check and review the test equipment documents for calibration validity. Att. IV
Sec. 7.1
Inspection shall be performed by the project approved Quality Control Schedule Q
A2 Inspector (QCI) and witness point shall be coordinated with the Contractor Att. IV
and Company. Sec. 5.1
Check the installed cables for test. Ensure the circuit is de-energized,
remove any temporary grounds and disconnect cable from equipment. If
Schedule Q
A6 equipment cannot be disconnected, a reduced voltage should used for the
Sec. 1.3
test.
(NETA ATS, Sec. 7.3.3 & Sec. 5.1.4)
Check for correct cable test voltage. Erect safety barriers and post safety
SAES-P-104
A7 man at cable end remote from the test equipment.
Sec. 3.1
(SA Pre-Commissioning Form # P-042)
Connect C1 and P1 of the test set to one end of the cable shield. SAES-P-104
A9
(NEC 110.3 B and Manufacturer's Instructions) Sec. 3.2
Connect the C2 and P2 of the test set to the other end of the cable shield.
NOTE: Observe the correct orientation for the current circuit (C2) and the
SAES-P-104
A10 potential circuit (P2) hook-ups at the opposite end (P2 connection closer
Sec. 3.2
to the specimen than C2). (NEC
110.3 B and Manufacturer's Instructions)
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.
The integrity of the overall jacket of direct buried cables rated 5 KV and
higher shall be tested by conducting a 5 kV megger test between the
cable insulation metallic shield (and sheath or armor, if any) and ground. SAES-P-104
A15
The DC high potential value shall be 4 kV/1 mm for one minute and not to Sec. 13.4
exceed 10 kV. IEC 60229 shall be used for HV cable jacket integrity
testing.
After single core cables are installed in the ground, a shield to ground test
shall be performed to check the integrity of the outer jacket, at 10 KV of 1 SAES-P-104
A16
minute. (SA Sec. 13.4
Pre-Commissioning Form # P-042)
Schedule Q
B1 Test shall be performed using a Ductor, DLRO. Att. IV
Sec. 7.1
Schedule Q
B2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7.1
C. TEST RESULTS
Cable Identification tag # Cable type Cable length Shield Resistance (Ω) Pass Fail Re-Test Date
D. CONCLUSIONS
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.
Cable ends shall be sealed with heat shrinkable end caps after Continuity
SAES-P-104
E8 and Insulation resistance testing of the cable. (NEC
Sec. 3.2
110.3 B and Manufacturer's Instructions)
F. TEST EQUIPMENT
G. TEST RESULTS
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.
H. CONCLUSIONS
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.
Compare test results with previous test results and with manufacturer data
corrected for temperature variations using manufacturer recommended Schedule Q
H1
correction factors. (NETA ATS, Sec. 1.3
Sec. 7.3.3.3.2.2 and Table 100.1 Notes - Attachment 1)
REMARKS:
REFERENCE DOCUMENTS:
1. Schedule G -- Material, Tools and Equipment (MP-LSTK & LSPB Pro Forma, Contract Specific)
2. Schedule Q -- Quality Requirements (MP LSTK & LSPB Pro Forma, Contract Specific)
3. NFPA 70 National Electrical Code (NEC), 2014 Edition
4. Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems- NETA (2009)
5. SAES-P-104 Wiring Methods and Materials, 01 January 2018
6. S A Pre-Commissioning Form # P-000 Testing Guidelines, Issue Date (March 2006)
7. S A Pre-Commissioning Form # P-042 High Voltage Cables (69kV-115kV), Issue Date (March 2006) - supersedes S A Pre-Commissioning
Form # P-005 High Voltage Cables, Issue Date (10/97)
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
indicates compliance with appropriate standards or performance in a specified manner.
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED