Sei sulla pagina 1di 6

SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.

00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
High Voltage Power Cable (Installed), Continuity and Megger
SATR-P-3212 3-Jul-18 ELECT-
Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. TEST PROCEDURE FOR SHIELD CONTINUITY TEST

Schedule Q
A1 Check and review the test equipment documents for calibration validity. Att. IV
Sec. 7.1
Inspection shall be performed by the project approved Quality Control Schedule Q
A2 Inspector (QCI) and witness point shall be coordinated with the Contractor Att. IV
and Company. Sec. 5.1

Check physical condition of cable for apparent jacket damage. Schedule Q


A3
(NETA ATS, Sec. 7.3.3.1.10) Sec. 1.3

Perform a shield-continuity test to ensure shield is not broken, on each


Schedule Q
A4 shield with a certified and calibrated ohm-meter.
Sec. 1.3
(NETA ATS, Sec. 7.3.3.2.3)

Perform a Core-continuity test to ensure conductor is not broken, on each


SAES-P-104
A5 power cable with a certified and calibrated ohm-meter.
Sec. 3.2
(NEC 110.3 B and Manufacturer's Instructions)

Check the installed cables for test. Ensure the circuit is de-energized,
remove any temporary grounds and disconnect cable from equipment. If
Schedule Q
A6 equipment cannot be disconnected, a reduced voltage should used for the
Sec. 1.3
test.
(NETA ATS, Sec. 7.3.3 & Sec. 5.1.4)

Check for correct cable test voltage. Erect safety barriers and post safety
SAES-P-104
A7 man at cable end remote from the test equipment.
Sec. 3.1
(SA Pre-Commissioning Form # P-042)

Using a four-point, low-resistance ohmmeter, connect both C1 and P1 of


SAES-P-104
A8 the test set to one end of the cable shield.
Sec. 3.2
(NEC 110.3 B and Manufacturer's Instructions)

Connect C1 and P1 of the test set to one end of the cable shield. SAES-P-104
A9
(NEC 110.3 B and Manufacturer's Instructions) Sec. 3.2

Connect the C2 and P2 of the test set to the other end of the cable shield.
NOTE: Observe the correct orientation for the current circuit (C2) and the
SAES-P-104
A10 potential circuit (P2) hook-ups at the opposite end (P2 connection closer
Sec. 3.2
to the specimen than C2). (NEC
110.3 B and Manufacturer's Instructions)

On completion of test, each core shall be grounded to allow residual


SAES-P-104
A11 charge to dissipate.
Sec. 3.1
(S A Pre-Commissioning Form # P-042)

Check and Insulate cable cores from ground. SAES-P-104


A12
(S A Pre-Commissioning Form # P-042) Sec. 3.1
Check conductors are identified as per specifications and drawings. Schedule Q
A13
(NETA ATS, Sec. 7.3.3.1.1) Sec. 1.3

Saudi Aramco: Company General Use


Test Records and Receipt documents are to be carefully presented in
Schedule Q
A14 original.
Sec. 1.3
(NETA ATS, Sec. 5.4.3)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

High Voltage Power Cable (Installed), Continuity and Megger


SATR-P-3212 3-Jul-18 ELECT-
Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.

The integrity of the overall jacket of direct buried cables rated 5 KV and
higher shall be tested by conducting a 5 kV megger test between the
cable insulation metallic shield (and sheath or armor, if any) and ground. SAES-P-104
A15
The DC high potential value shall be 4 kV/1 mm for one minute and not to Sec. 13.4
exceed 10 kV. IEC 60229 shall be used for HV cable jacket integrity
testing.

After single core cables are installed in the ground, a shield to ground test
shall be performed to check the integrity of the outer jacket, at 10 KV of 1 SAES-P-104
A16
minute. (SA Sec. 13.4
Pre-Commissioning Form # P-042)

B. TEST EQUIPMENT AND MATERIALS CRITERIA

Schedule Q
B1 Test shall be performed using a Ductor, DLRO. Att. IV
Sec. 7.1
Schedule Q
B2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7.1

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

C. TEST RESULTS

Cable Identification tag # Cable type Cable length Shield Resistance (Ω) Pass Fail Re-Test Date

D. CONCLUSIONS

Shielding shall exhibit continuity. Investigate any breaks in continuity,


along with any resistance values in excess of 10 ohms per 1000 feet of Schedule Q
D1
cable. Sec. 1.3
(NETA ATS, Sec 7.3.3.2.3 & 7.3.3.3.3)
Test results are acceptable and in accordance with Saudi Aramco
Schedule Q
D2 Engineering Standards and contractual requirements.
Sec. 1.3
(NETA ATS, Sec. 5.4.1.5)

E. INSULATION RESISTANCE (MEGGER) TEST PROCEDURES

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

High Voltage Power Cable (Installed), Continuity and Megger


SATR-P-3212 3-Jul-18 ELECT-
Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.

Perform resistance measurements through bolted connections with a low-


resistance ohmmeter, if applicable, in accordance with NETA ATS Section Schedule Q
E1
7.3.3.1. (NETA Sec. 1.3
ATS, Sec 7.3.3.2.1)

Perform an insulation-resistance test individually on each conductor with


all other conductors and shields grounded. Apply voltage in accordance
Schedule Q
E2 with manufacturer’s published data. In the absence of manufacturer’s
Sec. 1.3
published data, use Table 100.1. (NETA
ATS, Sec 7.3.3.2.2)

Connect megohmmeter between each phase-to-phase and each phase-


SAES-P-104
E3 to-ground.
Sec. 3.1
(S A Pre-Commissioning Form # P-042)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

High Voltage Power Cable (Installed), Continuity and Megger


SATR-P-3212 3-Jul-18 ELECT-
Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.

Measure insulation resistance at one minute following the application of


SAES-P-104
E4 the test voltage.
Sec. 3.1
(S A Pre-Commissioning Form # P-042)

Record the megohm values of each phase-to-ground and between each


SAES-P-104
E5 phase-to-phase, along with the description of the equipment, the voltage
Sec. 13.5
level, humidity, temperature, time, and the date of the test.

Ground each conductor at the completion of the test. SAES-P-104


E6
(S A Pre-Commissioning Form # P-042) Sec. 3.1

Values of insulation resistance less than manufacturer's minimum or KV


+1 in mega ohms should be investigated. Over potential or high potential
SAES-P-104
E7 test should not proceed unless insulation resistance levels equal to or
Sec. 3.1
above the listed minimum values.
(S A Pre-Commissioning Form # P-000)

Cable ends shall be sealed with heat shrinkable end caps after Continuity
SAES-P-104
E8 and Insulation resistance testing of the cable. (NEC
Sec. 3.2
110.3 B and Manufacturer's Instructions)

The testing organization shall furnish a copy or copies of the complete


report to the owner as specified in the acceptance testing contract. Schedule Q
E9
(NETA ATS, Sec. 1.3
Sec. 5.4.3)

F. TEST EQUIPMENT

Test shall be performed using an Insulation Resistance Test Set


SAES-P-104
F1 (Megohmeter) 5000 V dc minimum.
Sec. 3.1
(S A Pre-Commissioning Form # P-042)
Schedule Q
F2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7.1

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

G. TEST RESULTS

Test Voltage level__________ Humidity____________ Temperature_______________ Time/Date of Test____________

Temp. MEASURED INSULATION RESISTANCE (MΩ)


Adjusted
Cable
Insulation Pass Fail Re-Test date
tag #
Resistance A-G B-G C- G A-B B-C C-A
(MΩ)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

High Voltage Power Cable (Installed), Continuity and Megger


SATR-P-3212 3-Jul-18 ELECT-
Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.

H. CONCLUSIONS

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No.

Compare test results with previous test results and with manufacturer data
corrected for temperature variations using manufacturer recommended Schedule Q
H1
correction factors. (NETA ATS, Sec. 1.3
Sec. 7.3.3.3.2.2 and Table 100.1 Notes - Attachment 1)

Insulation-resistance values shall be in accordance with manufacturer’s


published data. Values of insulation resistance less than the Schedule Q
H2
manufacturer’s recommendations should be investigated. Sec. 1.3
(NETA ATS, Sec. 7.3.3.3.2.2)

Test results are acceptable and in accordance with Saudi Aramco


Schedule Q
H3 Engineering Standards and contractual requirements.
Sec. 1.3
(NETA ATS, Sec. 5.4.1.5)

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule G -- Material, Tools and Equipment (MP-LSTK & LSPB Pro Forma, Contract Specific)
2. Schedule Q -- Quality Requirements (MP LSTK & LSPB Pro Forma, Contract Specific)
3. NFPA 70 National Electrical Code (NEC), 2014 Edition
4. Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems- NETA (2009)
5. SAES-P-104 Wiring Methods and Materials, 01 January 2018
6. S A Pre-Commissioning Form # P-000 Testing Guidelines, Issue Date (March 2006)
7. S A Pre-Commissioning Form # P-042 High Voltage Cables (69kV-115kV), Issue Date (March 2006) - supersedes S A Pre-Commissioning
Form # P-005 High Voltage Cables, Issue Date (10/97)
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Name, Title, Department,
Name, Initials and Date:
Company, Initials and Date:

QC Inspector PID Representative


Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use

Potrebbero piacerti anche