Sei sulla pagina 1di 5

Villages Water Supply System Inc.

│ Block 8 Lot 14 Phase 4 Mansfield Residences, Fil-Am Friendship Hi-way


Barangay Sto. Domingo,  Angeles City, 2009 Pampanga
│ Telefax No.: (045) 435-6513 │ Email: vwssi.corporate@gmail.com

ABSTRACT OF QUOTATION
MALINOVILLE-MINING TRANSMISSION LINE

DONATO BAUZON CRISANTO CORTEZ


WORK ITEM
QTY UM UNIT COST AMOUNT QTY UM AMOUNT

PIPE LAYING (6"-Ø UPVC PIPE) 1,000.00 LM ₱ 190.00 ₱ 190,000.00

PAVEMENT DEMOLITION 400.00 SQ.METER ₱ 450.00 ₱ 180,000.00

CONCRETE PAVEMENT RESTORATION 80.00 CU.METER ₱ 7,500.00 ₱ 600,000.00

INTERCONNECTION TO EXISTING PIPELINES 2.00 UNITS ₱ 6,500.00 ₱ 13,000.00

INSTALLATION OF GATE VALVES (6"-Ø) 2.00 UNITS ₱ 4,000.00 ₱ 8,000.00

INSTALLATION OF GATE VALVES (3"-Ø) 2.00 UNITS ₱ 3,000.00 ₱ 6,000.00

FIRE HYDRANT ASSEMBLY 2.00 UNITS ₱ 4,000.00 ₱ 8,000.00


1.00 LS ₱ 927,500.00
INSTALLATION OF BARRICADES 4.00 UNITS ₱ 1,000.00 ₱ 4,000.00

CULVERT CROSSING (6"-Ø B.I. PIPE) 30.00 MTRS ₱ 2,500.00 ₱ 75,000.00

FABRICATION OF FITTINGS (6"-Ø) 24.00 PCS ₱ 2,000.00 ₱ 48,000.00

INSTALLATION OF C.I. FITTINGS (6"-Ø) 8.00 PCS ₱ 1,200.00 ₱ 9,600.00

CONCRETE CUTTING 1,000.00 LM ₱ 20.00 ₱ 20,000.00

CONCRETE CUTTER RENTAL - ₱ - ₱ -

JACK HAMMER RENTAL - ₱ - ₱ -

TOTAL COST ₱ 1,161,600.00 ₱ 927,500.00

Prepared by: Checked by: Approved by:

ENGR. EDNOR M. LANSANGAN ENGR. ROBERTO V. SUAREZ ENGR. EDWIN R. REYES


Acting Technical Officer VP - Technical Department Chief Executive Officer
Villages Water Supply System Inc.
│ Block 8 Lot 14 Phase 4 Mansfield Residences, Fil-Am Friendship Hi-way
Barangay Sto. Domingo,  Angeles City, 2009 Pampanga
│ Telefax No.: (045) 435-6513 │ Email: vwssi.corporate@gmail.com

BILL OF MATERIALS
Project Site: HANJIN VILLAGES
Descriction: Rehabilitation of messenger wire from pumping station #1 to
pumping station #2.

Quantity Unit Description of item Unit cost


150 meter 8.0mm² THHN copper wire (red) 31.6
150 meter 8.0mm² THHN copper wire (yellow) 31.6
150 meter 8.0mm² THHN copper wire (blue) 31.6
5 pcs 26" secondary rack 3 wire hot dip galvanized 300
15 pcs 3" spool insulator ANSI class 53-2 421.5
15 pcs 1/2"x12" bolt and knot 250
1 pcs 2" galvanized entrance cap (treaded) 235
1 pcs 2"dia x 3m rigid steel conduit 2910
4 bag 40kg cement 265
1 meter³ 3/4" gravel 1097
0.5 meter³ dry sand 982
5 pcs 12mm x 6m Deform Steel Bar 196
6 pcs 10mm x 6m Deform Steel Bar 136
2 kg #12 awg G.I. Wire 70
1 pcs Unistrut Channel 980
1 pcs 3/8" x 3m full treaded round bar 250
1 box 3/8" Grip Anchor 125
***nothing follows***

Total Material Cost Php


Total Construction Cost Php
Contingency Php

Total Cost Php

Prepaired by: Recommending Approval:

Engr. Johnlerie Esguerra Engr. Robert V. Suarez


Cadet Electrical Engineer Vice-President for Technica

Checked by: Approve by:


Engr. Geizy Torno Engr. Edwin R. Reyes
Electrical Engineer Chief Executive Officer
tem Inc.
Friendship Hi-way
Pampanga
rate@gmail.com

BILL OF MATERIALS

Price
4740
4740
4740
1500
6322.5
3750
235
2910
1060
1097
491
980
816
140
980
250
125

34876.5
10462.95
3487.65

48827.1

Recommending Approval:

Engr. Robert V. Suarez


Vice-President for Technical Opr.

Approve by:
Engr. Edwin R. Reyes
Chief Executive Officer