Sei sulla pagina 1di 84

G.R. No. 108129 September 23, 1999 damages.

—Our next inquiry is whether damages have been


AEROSPACE CHEMICAL INDUSTRIES, INC., petitioner, properly awarded against petitioner for its unjustified delay in
vs. the performance of its obligation under the contract. Where
COURT OF APPEALS, PHILIPPINE PHOSPHATE there has been breach of contract by the buyer, the seller has
FERTILIZER, CORP., respondents. a right of action for damages. Following this rule, a cause of
action of the seller for damages may arise where the buyer
Civil Law; Contracts; Court finds the appellate court’s refuses to remove the goods, such that buyer has to remove
conclusion that petitioner violated the subject contract amply them.
supported by preponderant evidence.—While we agree with
petitioner that when the findings of the Court of Appeals are Same; Same; Same; Requisites in order that the debtor may
contrary to those of the trial court, this Court may review those be in default.—In order that the debtor may be in default, it is
findings, we find the appellate court’s conclusion that necessary that the following requisites be present: (1) that the
petitioner violated the subject contract amply supported by obligation be demandable and already liquidated; (2) that the
preponderant evidence. Petitioner’s claim was predicated debtor delays performance; and (3) that the creditor requires
merely on the allegations of its employee, Melecio the performance judicially or extrajudicially.
Hernandez, that the storm or force majeure caused the
petitioner’s delay and failure to lift the cargo of sulfuric acid at QUISUMBING, J.:
the designated loadports. In contrast, the appellate court This petition for review assails the Decision 1 dated August 19,
discounted Hernandez’ assertions. For on record, the storm 1992, of the Court of Appeals, which set aside the judgment of
was not the proximate cause of petitioner’s failure to transport the Regional Trial Court of Pasig, Branch 151. The case
its purchases on time. The survey report submitted by a third stemmed from a complaint filed by the buyer (herein
party surveyor, SGS Far East Limited, revealed that the petitioner) against the seller (private respondent) for alleged
vessel, which was unstable, was incapable of carrying the full breach of contract. Although petitioner prevailed in the trial
load of sulfuric acid. Note that there was a premature court, the appellate court reversed and instead found
termination of loading in Basay, Negros Oriental. The vessel petitioner guilty of delay and therefore liable for damages, as
had to undergo several repairs before continuing its voyage to follows:
pick-up the balance of cargo at Sangi, Cebu. Despite repairs, WHEREFORE, the Decision of the court a quo is SET ASIDE
the vessel still failed to carry the whole lot of 500 MT of and a new one rendered, dismissing the complaint with costs
sulfuric acid due to ship defects like listing to one side. Its against the plaintiff (herein petitioner) and, on the
unfortunate sinking was not due to force majeure. It sunk counterclaim, ordering the plaintiff Aerospace Chemical
because it was, based on SGS survey report, unstable and Industries, Inc. to pay the defendant, Philippine Phosphate
unseaworthy. Fertilizer Corporation the sum of P324,516.63 representing
the balance of the maintenance cost and tank rental charges
Same; Same; A party who asserts that a contract of sale has incurred by the defendant for the failure of the plaintiff to haul
been changed or modified has the burden of proving the the rest of the rest of the sulfuric acid on the designated date.
change or modification by clear and convincing evidence; Costs against plaintiff-appellee. 2
Settled is the principle in law that proof of verbal agreements As gleaned from the records, the following are the
offered to vary the terms of written agreements is antecedents:
inadmissible, under the parol evidence rule.—Petitioner On June 27, 1986, petitioner Aerospace Industries, Inc.
claims that private respondent’s employee, Gil Belen, had (Aerospace) purchased five hundred (500) metric tons of
recommended to petitioner to fully utilize the vessel, hence sulfuric acid from private respondent Philippine Phosphate
petitioner’s request for an additional order to complete the Fertilizer Corporation (Philphos). The contract 3 was in letter-
vessel’s 500 MT capacity. This claim has no probative form as follows:
pertinence nor solid basis. A party who asserts that a contract 27 June 1986
of sale has been changed or modified has the burden of AEROSPACE INDUSTRIES INC.
proving the change or modification by clear and convincing 203 E. Fernandez St.
evidence. Repeated requests and additional orders were San Juan, Metro Manila
contained in petitioner’s letters to private respondent. In Attention: Mr. Melecio Hernandez
contrast, Belen’s alleged action was only verbal; it was not Manager
substantiated at all during the trial. Note that, using the vessel Subject : Sulfuric Acid Shipment
to full capacity could redound to petitioner’s advantage, not Gentlemen:
the other party’s. If additional orders were at the instance of This is to confirm our agreement to supply your Sulfuric Acid
private respondent, the same must be properly proved requirement under the following terms and conditions:
together with its relevance to the question of delay. Settled is A. Commodity : Sulfuric Acid in Bulk
the principle in law that proof of verbal agreements offered to B. Concentration : 98-99% H2SO4
vary the terms of written agreements is inadmissible, under C. Quantity : 500 MT-100 MT Ex-Basay
the parol evidence rule. Belen’s purported recommendation 400 MT Ex-Sangi
could not be taken at face value and, obviously, cannot D. Price : US$ 50.00/MT-FOB Cotcot,
excuse petitioner’s default. Basay, Negros Or.
US$ 54.00/MT-FOB Sangi, Cebu
Same; Same; Damages; Where there has been breach of E. Payment : Cash in Philippine currency
contract by the buyer, the seller has a right of action for payable to Philippine Phosphate
Fertilizer Corp. (MAKATI) at addressed letters to private respondent, concerning additional
PCIB selling rate at the time of orders of sulfuric acid to replace its sunken purchases, which
payment at least five (5) days prior letters are hereunder excerpted:
to shipment date. January 26, 1987
F. Shipping Conditions xxx xxx xxx
1. Laycan : July We recently charter another vessel M/T DON VICTOR who
2. Load port : Cotcot, Basay, Negros Or. and will be authorized by us to lift the balance approximately
Atlas Pier, Sangi, Cebu 272.49 MT.
xxx xxx xxx We request your goodselves to grant us for another Purchase
11. Other terms and Conditions: To be mutually agreed upon. Order with quantity of 227.51 MT and we are willing to pay the
Very truly yours, additional order at the prevailing market price, provided the
Philippine Phosphate Fertilizer Corp. lifting of the total 500 MT be centered/confined to only one
Signed: Herman J. Rustia safe berth which is Atlas Pier, Sangi, Cebu. 7
Sr. Manager, Materials & Logistics March 20, 1987
CONFORME: This refers to the remaining balance of the above product
AEROSPACE INDUSTRIES, INC. quantity which were not loaded to the authorized cargo
Signed: Mr. Melecio Hernandez vessel, M/T Sultan Kayumanggi at your load port — Sangi,
Manager Toledo City.
Initially set beginning July 1986, the agreement provided that Please be advised that we will be getting the above product
the buyer shall pay its purchases in equivalent Philippine quantity within the month of April 1987 and we are arranging
currency value, five days prior to the shipment date. Petitioner for a 500 MT Sulfuric Acid inclusive of which the remaining
as buyer committed to secure the means of transport to pick- balance: 272.49 MT an additional product quantity thereof of
up the purchases from private respondent's loadports. Per 227.51 MT. 8
agreement, one hundred metric tons (100 MT) of sulfuric acid Petitioner's letter 9 dated May 15, 1987, reiterated the same
should be taken from Basay, Negros Oriental storage tank, request to private respondent.
while the remaining four hundred metric tons (400 MT) should On January 25, 1988, petitioner's counsel, Atty. Pedro T.
be retrieved from Sangi, Cebu. Santos, Jr., sent a demand letter 10 to private respondent for
On August 6, 1986, private respondent sent an advisory the delivery of the 272.49 MT of sulfuric acid paid by his
letter 4 to petitioner to withdraw the sulfuric acid purchased at client, or the return of the purchase price of three hundred
Basay because private respondent had been incurring seven thousand five hundred thirty (P307,530.00) pesos.
incremental expense of two thousand (P2,000.00) pesos for Private respondent in reply, 11 on March 8, 1988, instructed
each day of delay in shipment. petitioner to lift the remaining 30 MT of sulfuric acid from
On October 3, 1986, petitioner paid five hundred fifty-three Basay, or pay maintenance and storage expenses
thousand, two hundred eighty (P553,280.00) pesos for 500 commencing August 1, 1986.
MT of sulfuric acid. On July 6, 1988, petitioner wrote another letter, insisting on
On November 19, 1986, petitioner chartered M/T Sultan picking up its purchases consisting of 272.49 MT and an
Kayumanggi, owned by Ace Bulk Head Services. The vessel additional of 227.51 MT of sulfuric acid. According to
was assigned to carry the agreed volumes of freight from petitioner it had paid the chartered vessel for the full capacity
designated loading areas. M/T Kayumanggi withdrew only of 500 MT, stating that:
70.009 MT of sulfuric acid from Basay because said vessel With regard to our balance of sulfuric acid — product at your
heavily tilted on its port side. Consequently, the master of the shore tank/plant for 272.49 metric ton that was left by M/T
ship stopped further loading. Thereafter, the vessel underwent Sultana Kayumanggi due to her sinking, we request for an
repairs. additional quantity of 227.51 metric ton of sulfuric acid, 98%
In a demand letter 5 dated December 12, 1986, private concentration.
respondent asked petitioner to retrieve the remaining sulfuric The additional quantity is requested in order to complete the
acid in Basay tanks so that said tanks could be emptied on or shipment, as the chartered vessel schedule to lift the high
before December 15, 1986. Private respondent said that it grade sulfuric acid product is contracted for her full
would charge petitioner the storage and consequential costs capacity/load which is 500 metric tons more or less.
for the Basay tanks, including all other incremental expenses We are willing to pay the additional quantity — 227.51 metric
due to loading delay, if petitioner failed to comply. tons high grade sulfuric acid in the prevailing price of the said
On December 18, 1986, M/T Sultan Kayumanggi docked at product. 12
Sangi, Cebu, but withdrew only 157.51 MT of sulfuric acid. x x x      x x x     x x x
Again, the vessel tilted. Further loading was aborted. Two By telephone, petitioner requested private respondent's
survey reports conducted by the Societe Generale de Shipping Manager, Gil Belen, to get its additional order of
Surveillance (SGS) Far East Limited, dated December 17, 227.51 MT of sulfuric acid at Isabel, Leyte. 13 Belen relayed
1986 and January 2, 1987, attested to these occurrences. the information to his associate, Herman Rustia, the Senior
Later, on a date not specified in the record, M/T Sultan Manager for Imports and International Sales of private
Kayumanggi sank with a total of 227.51 MT of sulfuric acid on respondent. In a letter dated July 22, 1988, Rustia replied:
board.1âwphi1.nêt Subject: Sulfuric Acid Ex-Isabel
Petitioner chartered another vessel, M/T Don Victor, with a Gentlemen:
capacity of approximately 500 MT. 6 On January 26 and Confirming earlier telcon with our Mr. G.B. Belen, we regret to
March 20, 1987, Melecio Hernandez, acting for the petitioner, inform you that we cannot accommodate your request to lift
Sulfuric Acid ex-Isabel due to Pyrite limitation and delayed to a payment of a 2,000-peso incremental expenses per day
arrival of imported Sulfuric Acid from Japan. 14 to defendant for delayed "lifting has not been proven." . . .
On July 25, 1988, petitioner's counsel wrote to private Also, if it were true that plaintiff is indebted to defendant, why
respondent another demand letter for the delivery of the did defendant accept a second additional order after the
purchases remaining, or suffer tedious legal action his client transaction in litigation? Why also, did defendant not send
would commence. plaintiff statements of account until after 3 years?
On May 4, 1989, petitioner filed a complaint for specific All these convince the Court that indeed, defendant must
performance and/or damages before the Regional Trial Court return what plaintiff has paid it for the goods which the latter
of Pasig, Branch 151. Private respondent filed its answer with did not actually receive. 16
counterclaim, stating that it was the petitioner who was remiss On appeal by private respondent, the Court of Appeals
in the performance of its obligation in arranging the shipping reversed the decision of the trial court, as follows:
requirements of its purchases and, as a consequence, should Based on the facts of this case as hereinabove set forth, it is
pay damages as computed below: clear that the plaintiff had the obligation to withdraw the full
Advanced Payment by Aerospace (Oct. 3, 1986) P553,280.00 amount of 500 MT of sulfuric acid from the defendant's
Less Shipments loadport at Basay and Sangi on or before August 15, 1986. As
70.009 MT sulfuric acid P72,830.36 early as August 6, 1986 it had been accordingly warned by
151.51 MT sulfuric acid 176,966.27 (249,796.63) the defendant that any delay in the hauling of the commodity
—————— —————— would mean expenses on the part of the defendant amounting
Balance P303,483.37 to P2,000.00 a day. The plaintiff sent its vessel, the "M/T
Less Charges Sultan Kayumanggi", only on November 19, 1987. The vessel,
Basay Maintenance Expense however; was not capable of loading the entire 500 MT and in
from Aug. 15 to Dec. 15, 1986 fact, with its load of only 227.519 MT, it sank.
(P2,000.00/day x 122 days) P244,000.00 Contrary to the position of the trial court, the sinking of the
Sangi — Tank Rental "M/T Sultan Kayumanggi" did not absolve the plaintiff from its
from Aug. 15, 1986 to Aug. 15, 1987 obligation to lift the rest of the 272.481 MT of sulfuric acid at
(P32,000.00/mo. x 12 mos.) 384,000.00 (628,000.00) the agreed time. It was the plaintiff's duty to charter another
—————— —————— vessel for the purpose. It did contract for the services of a new
Receivable/Counterclaim (P324,516.63) vessel, the "M/T Don Victor", but did not want to lift the
=========== balance of 272.481 MT only but insisted that its additional
Trial ensued and after due proceedings, judgment was order of 227.51 MT be also given by the defendant to
rendered by the trial court in petitioner's favor, disposing as complete 500 MT. apparently so that the vessel may be
follows: availed of in its full capacity.
WHEREFORE, judgment is hereby rendered in favor of xxx xxx xxx
plaintiff and against defendant, directing the latter to pay the We find no basis for the decision of the trial court to make the
former the following sums: defendant liable to the plaintiff not only for the cost of the
1. P306,060.77 — representing the value of the undelivered sulfuric acid, which the plaintiff itself failed to haul, but also for
272.49 metric tons of sulfuric acid plaintiff paid to defendant; unrealized profits as well as exemplary damages and
2. P91,818.23 — representing unrealized profits, both items attorney's fees. 17
with 12% interest per annum from May 4, 1989, when the Respondent Court of Appeals found the petitioner guilty of
complaint was filed until fully paid; delay and negligence in the performance of its obligation. It
3. P30,000.00 — as exemplary damages; and dismissed the complaint of petitioner and ordered it to pay
4. P30,000.00 — as attorney's fees and litigation expenses, damages representing the counterclaim of private respondent.
both last items also with 12% interest per annum from date The motion for reconsideration filed by petitioner was denied
hereof until fully paid. by respondent court in its Resolution dated December 21,
Defendant's counterclaims are hereby dismissed for lack of 1992, for lack of merit.
merit. Petitioner now comes before us, assigning the following
Costs against defendant. 15 errors:
In finding for the petitioner, the trial court held that the I.
petitioner was absolved in its obligation to pick-up the RESPONDENT COURT OF APPEALS ERRED IN NOT
remaining sulfuric acid because its failure was due to force HOLDING PRIVATE RESPONDENT TO HAVE COMMITTED
majeure. According to the trial court, it was private respondent A BREACH OF CONTRACT WHEN IT IS NOT DISPUTED
who committed a breach of contract when it failed to THAT PETITIONER PAID IN FULL THE VALUE OF 500 MT
accommodate the additional order of the petitioner, to replace OF SULFURIC ACID TO PRIVATE RESPONDENT BUT THE
those that sank in the sea, thus: LATTER WAS ABLE TO DELIVER TO PETITIONER ONLY
To begin with, even if we assume that it is incumbent upon the 227.51 M.T.
plaintiff to "lift" the sulfuric acid it ordered from defendant, the II.
fact that  force majeure intervened when the vessel which was RESPONDENT COURT OF APPEALS GRAVELY ERRED IN
previouly (sic) listing, but which the parties, including a HOLDING PETITIONER LIABLE FOR DAMAGES TO
representative of the defendant, did not mind, sunk, has the PRIVATE RESPONDENT ON THE BASIS OF A XEROX
effect of absolving plaintiff from "lifting" the sulfuric acid at the COPY OF AN ALLEGED AGREEMENT TO HOLD
designated load port. But even assuming the plaintiff cannot PETITIONER LIABLE FOR DAMAGES FOR THE DELAY
be held entirely blameless, the allegation that plaintiff agreed WHEN PRIVATE RESPONDENT FAILED TO PRODUCE
THE ORIGINAL IN CONTRAVENTION OF THE RULES ON While we agree with petitioner that when the findings of the
EVIDENCE. Court of Appeals are contrary to those of the trial court, 18 this
III. Court may review those findings, we find the appellate court's
RESPONDENT COURT OF APPEALS ERRED IN FAILING conclusion that petitioner violated the subject contract amply
TO CONSIDER THE UNDISPUTED FACTS THAT supported by preponderant evidence. Petitioner's claim was
PETITIONER'S PAYMENT FOR THE GOODS WAS predicated merely on the allegations of its employee, Melecio
RECEIVED BY PRIVATE RESPONDENT WITHOUT ANY Hernandez, that the storm or  force majeure caused the
QUALIFICATION AND THAT PRIVATE RESPONDENT petitioner's delay and failure to lift the cargo of sulfuric acid at
ENTERED INTO ANOTHER CONTRACT TO SUPPLY the designated loadports. In contrast, the appellate court
PETITIONER 227.519 MT OF SULFURIC ACID IN ADDITION discounted Hernandez' assertions. For on record, the storm
TO THE UNDELIVERED BALANCE AS PROOF THAT ANY was not the proximate cause of petitioner's failure to transport
DELAY OF PETITIONER WAS DEEMED WAIVED BY SAID its purchases on time. The survey report submitted by a third
ACTS OF RESPONDENT. party surveyor, SGS Far East Limited, revealed that the
IV. vessel, which was unstable, was incapable of carrying the full
RESPONDENT COURT OF APPEALS ERRED IN NOT load of sulfuric acid. Note that there was a premature
CONSIDERING THE LAW THAT WHEN THE SALE termination of loading in Basay, Negros Oriental. The vessel
INVOLVES FUNGIBLE GOODS AS IN THIS CASE THE had to undergo several repairs before continuing its voyage to
EXPENSES FOR STORAGE AND MAINTENANCE ARE FOR pick-up the balance of cargo at Sangi, Cebu. Despite repairs,
THE ACCOUNT OF THE SELLER (ARTICLE 1504 CIVIL the vessel still failed to carry the whole lot of 500 MT of
CODE). sulfuric acid due to ship defects like listing to one side. Its
V. unfortunate sinking was not due to  force majeure. It sunk
RESPONDENT COURT OF APPEALS ERRED IN FAILING because it was, based on SGS survey report, unstable and
TO RENDER JUDGMENT FOR PETITIONER AFFIRMING unseaworthy.
THE DECISION OF THE TRIAL COURT. Witness surveyor Eugenio Rabe's incident report, dated
From the assigned errors, we synthesize the pertinent issues December 13, 1986 in Basay, Negros Oriental, elucidated this
raised by the petitioner as follows: point:
1. Did the respondent court err in holding that the petitioner Loading was started at 1500hrs. November 19. At 1600Hrs.
committed breach of contract, considering that: November 20, loading operation was temporarily stopped by
a) the petitioner allegedly paid the full value of its purchases, the vessel's master due to ships stability was heavily tilted to
yet received only a portion of said purchases? port side, ship's had tried to transfer the loaded acid to
b) petitioner and private respondent allegedly had also agreed stbdside but failed to do so, due to their auxiliary pump on
for the purchase and supply of an additional 227.519 MT of board does not work out for acid.
sulfuric acid, hence prior delay, if any, had been waived? xxx xxx xxx
2. Did the respondent court err in awarding damages to Note. Attending surveyor arrived BMC Basay on November
private respondent? 22, due to delayed advice of said vessel Declared quantity
3. Should expenses for the storage and preservation of the loaded onboard based on data's provided by PHILPHOS
purchased fungible goods, namely sulfuric acid, be on seller's representative.
account pursuant to Article 1504 of the Civil Code? On November 26, two representative of shipping company
To resolve these issues, petitioner urges us to review factual arrived Basay to assist the situation, at 1300Hrs repairing
findings of respondent court and its conclusion that the and/or welding of tank number 5 started at 1000Hrs
petitioner was guilty of delay in the performance of its November 27, repairing and/or welding was suspended due to
obligation. According to petitioner, that conclusion is contrary the explosion of tank no. 5. Explosion ripped about two feet of
to the factual evidence. It adds that respondent court the double bottom tank.
disregarded the rule that findings of the trial court are given November 27 up to date no progress of said vessel. 19
weight, with the highest degree of respect. Claiming that While at Sangi, Cebu, the vessel's condition (listing) did not
respondent court's findings conflict with those of the trial improve as the survey report therein noted:
court, petitioner prays that the trial court's findings be upheld Declared quantity loaded on board was based on shore tank
over those of the appellate court. withdrawal due to ship's incomplete tank calibration table.
Petitioner argues that it paid the purchase price of sulfuric Barge displacement cannot be applied due to ship was listing
acid, five (5) days prior to the withdrawal thereof, or on to Stboard side which has been loaded with rocks to control
October 3, 1986, hence, it had complied with the primary her stability. 20
condition set in the sales contract. Petitioner claims its failure These two vital pieces of information were totally ignored by
to pick-up the remaining purchases on time was due to a trial court. The appellate court correctly took these into
storm, a  force majeure, which sank the vessel. It thus claims account, significantly. As to the weather condition in Basay,
exemption from liability to pay damages. Petitioner also the appellate court accepted surveyor Rabe's testimony, thus:
contends that it was actually the private respondent's shipping Q. Now, Mr. Witness, what was the weather condition then at
officer, who advised petitioner to buy the additional 227.51 MT Basay, Negros Oriental during the loading operation of sulfuric
of sulfuric acid, so as to fully utilize the capacity of the vessel acid on board the Sultana Kayumanggi?
it chartered. Petitioner insists that when its ship was ready to A. Fair, sir. 21
pick-up the remaining balance of 272.49 MT of sulfuric acid, Since the third party surveyor was neither petitioner's nor
private respondent could not comply with the contract private respondent's employee, his professional report should
commitment due to "pyrite limitation." carry more weight than that of Melecio Hernandez, an
employee of petitioner. Petitioner, as the buyer, was obligated has been breach of contract by the buyer, the seller has a
under the contract to undertake the shipping requirements of right of action for damages. Following this rule, a cause of
the cargo from the private respondent's loadports to the action of the seller for damages may arise where the buyer
petitioner's designated warehouse. It was petitioner which refuses to remove the goods, such that buyer has to remove
chartered M/T Sultan Kayumanggi. The vessel was them. 25 Article 1170 of the Civil Code provides:
petitioner's agent. When it failed to comply with the necessary Those who in the performance of their obligations are guilty of
loading conditions of sulfuric acid, it was incumbent upon fraud, negligence, or delay and those who in any manner
petitioner to immediately replace M/T Sultan Kayumanggi with contravene the tenor thereof, are liable for damages.
another seaworthy vessel. However, despite repeated Delay begins from the time the obligee judicially or
demands, petitioner did not comply seasonably. extrajudicially demands from the obligor the performance of
Additionally, petitioner claims that private respondent's the obligation. 26 Art. 1169 states:
employee, Gil Belen, had recommended to petitioner to fully Art. 1169. Those obliged to deliver or to do something incur in
utilize the vessel, hence petitioner's request for additional delay from the time the obligee judicially or extrajudicially
order to complete the vessel's 500 MT capacity. This claim demands from them the fulfillment of their obligation.
has no probative pertinence nor solid basis. A party who In order that the debtor may be in default, it is necessary that
asserts that a contract of sale has been changed or modified the following requisites be present: (1) that the obligation be
has the burden of proving the change or modification by clear demandable and already liquidated; (2) that the debtor delays
and convincing evidence. 22 Repeated requests and additional performance; and (3) that the creditor requires the
orders were contained in petitioner's letters to private performance judicially or extrajudicially. 27
respondent. In contrast, Belen's alleged action was only In the present case, private respondent required petitioner to
verbal; it was not substantiated at all during the trial. Note ship out or lift the sulfuric acid as agreed, otherwise petitioner
that, using the vessel to full capacity could redound to would be charged for the consequential damages owing to
petitioner's advantage, not the other party's. If additional any delay. As stated in private respondent's letter to petitioner,
orders were at the instance of private respondent, the same dated December 12, 1986:
must be properly proved together with its relevance to the Subject: M/T "KAYUMANGGI"
question of delay. Settled is the principle in law that proof of Gentlemen:
verbal agreements offered to vary the terms of written This is to reiterate our telephone advice and our letter HJR-
agreements is inadmissible, under the parol evidence 8612-031 dated 2 December 1986 regarding your sulfuric acid
rule. 23 Belen's purported recommendation could not be taken vessel, M/T "KAYUMANGGI".
at face value and, obviously, cannot excuse petitioner's As we have, in various instances, advised you, our Basay
default. wharf will have to be vacated 15th December 1986 as we are
Respondent court found petitioner's default unjustified, and on expecting the arrival of our chartered vessel purportedly to
this conclusion we agree: haul our equipments and all other remaining assets in Basay.
It is not true that the defendant was not in a position to deliver This includes our sulfuric acid tanks. We
the 272.481 MT which was the balance of the original 500 MT regret,  therefore, that if these tanks are not emptied on or
purchased by the plaintiff. The whole lot of 500 MT was ready before the 15th of December, we either have to charge you
for lifting as early as August 15, 1986. What the defendant for the tanks waiting time at Basay and its consequential
could not sell to the plaintiff was the additional 227.51 MT costs  (i.e. chartering of another vessel for its second pick-up
which said plaintiff was ordering, for the reason that the at Basay,  handling,  etc.) as well as all other incremental
defendant was short of the supply needed. The defendant, costs on account of the protracted loading
however, had no obligation to agree to this additional order delay.  28  (Emphasis supplied)
and may not be faulted for its inability to meet the said Indeed the above demand, which was unheeded, justifies the
additional requirements of the plaintiff. And the defendant's finding of delay. But when did such delay begin? The above
incapacity to agree to the delivery of another 227.51 MT is not letter constitutes private respondent's extrajudicial demand for
a legal justification for the plaintiffs refusal to lift the remaining the petitioner to fulfill its obligation, and its dateline is
272.481. significant. Given its date, however, we cannot sustain the
It is clear from the plaintiff's letters to the defendant that it finding of the respondent court that petitioner's delay started
wanted to send the "M/T Don Victor" only if the defendant on August 6, 1986. The Court of Appeals had relied on private
would confirm that it was ready to deliver 500 MT. Because respondent's earlier letter to petitioner of that date for
the defendant could not sell another 227.51 MT to the plaintiff, computing the commencement of delay. But as averred by
the latter did not send a new vessel to pick up the balance of petitioner, said letter of August 6th is not a categorical
the 500 MT originally contracted for by the parties. This, demand. What it showed was a mere statement of fact, that
inspite the representations made by the defendant for the "[F]for your information any delay in Sulfuric Acid withdrawal
hauling thereof as scheduled and its reminders that any shall cost us incremental expenses of P2,000.00 per day."
expenses for the delay would be for the account of the Noteworthy, private respondent accepted the full payment by
plaintiff. 24 petitioner for purchases on October 3, 1986, without
We are therefore constrained to declare that the respondent qualification, long after the August 6th letter. In contrast to the
court did not err when it absolved private respondent from any August 6th letter, that of December 12th was a categorical
breach of contract. demand.
Our next inquiry is whether damages have been properly Records reveal that a tanker ship had to pick-up sulfuric acid
awarded against petitioner for its unjustified delay in the in Basay, then proceed to get the remaining stocks in Sangi,
performance of its obligation under the contract. Where there Cebu. A period of three days appears to us reasonable for a
vessel to travel between Basay and Sangi. Logically, the tenor of its letter-contract with the defendant. 30
computation of damages arising from the shipping delay As pointed out earlier, petitioner is guilty of delay, after private
would then have to be from December 15, 1986, given said respondent made the necessary extrajudicial demand by
reasonable period after the December 12th letter. More requiring petitioner to lift the cargo at its designated loadports.
important, private respondent was forced to vacate Basay When petitioner failed to comply with its obligations under the
wharf only on December 15th. Its Basay expenses incurred contract it became liable for its shortcomings. Petitioner is
before December 15, 1986, were necessary and regular indubitably liable for proven damages.
business expenses for which the petitioner should not be Considering, however, that petitioner made an advance
obliged to pay. payment for the unlifted sulfuric acid in the amount of three
Note that private respondent extended its lease agreement for hundred three thousand, four hundred eighty three pesos and
Sangi, Cebu storage tank until August 31, 1987, solely for thirty seven centavos (P303,483.37), it is proper to set-off this
petitioner's sulfuric acid. It stands to reason that petitioner amount against the rental expenses initially paid by private
should reimburse private respondent's rental expenses of respondent. It is worth noting that the adjustment and
P32,000 monthly, commencing December 15, 1986, up to allowance of private respondent's counterclaim or set-off in
August 31, 1987, the period of the extended lease. Note the present action, rather than by another independent action,
further that there is nothing on record refuting the amount of is encouraged by the law. Such practice serves to avoid
expenses abovecited. Private respondent presented in court circuitry of action, multiplicity of suits, inconvenience,
two supporting documents: first, the lease agreement expense, and unwarranted consumption of the court's
pertaining to the equipment, and second a letter dated June time. 31 The trend of judicial decisions is toward a liberal
15, 1987, sent by Atlas Fertilizer Corporation to private extension of the right to avail of counterclaims or set-
respondent representing the rental charges incurred. Private offs. 32 The rules on counterclaims are designed to achieve
respondent is entitled to recover the payment for these the disposition of a whole controversy involving the conflicting
charges. It should be reimbursed the amount of two hundred claims of interested parties at one time and in one action,
seventy two thousand provided all parties can be brought before the court and the
(P272,000.00) 29 pesos, corresponding to the total amount of matter decided without prejudicing the right of any
rentals from December 15, 1986 to August 31, 1987 of the party. 33 Set-off in this case is proper and reasonable. It
Sangi, Cebu storage tank. involves deducting P272,000.00 (rentals) from P303,483.37
Finally, we note also that petitioner tries to exempt itself from (advance payment), which will leave the amount of
paying rental expenses and other damages by arguing that P31,483.37 refundable to petitioner.
expenses for the preservation of fungible goods must be WHEREFORE, the petition is hereby DENIED. The assailed
assumed by the seller. Rental expenses of storing sulfuric decision of the Court of Appeals in CA G.R. CV No. 33802 is
acid should be at private respondent's account until AFFIRMED, with MODIFICATION that the amount of
ownership is transferred, according to petitioner. However, the damages awarded in favor of private respondent is
general rule that before delivery, the risk of loss is borne by REDUCED to Two hundred seventy two thousand pesos
the seller who is still the owner, is not applicable in this case (P272,000.00). It is also ORDERED that said amount of
because petitioner had incurred delay in the performance of damages be OFFSET against petitioner's advance payment
its obligation. Article 1504 of the Civil Code clearly states: of Three hundred three thousand four hundred eighty three
Unless otherwise agreed, the goods remain at the seller's risk pesos and thirty-seven centavos (P303,483.37) representing
until the ownership therein is transferred to the buyer, but the price of the 272.481 MT of sulfuric acid not lifted. Lastly, it
when the ownership therein is transferred to the buyer the is ORDERED that the excess amount of thirty one thousand,
goods are at the buyer's risk whether actual delivery has been four hundred eighty three pesos and thirty seven centavos
made or not, except that: (P31,483.37) be RETURNED soonest by private respondent
xxx xxx xxx to herein petitioner.1âwphi1.nêt
(2)  Where actual delivery has been delayed through the fault Costs against the petitioner.
of either the buyer or seller the goods are at the risk of the SO ORDERED.
party at fault. (emphasis supplied)
On this score, we quote with approval the findings of the G.R. No. 153004       November 5, 2004
appellate court, thus: SANTOS VENTURA HOCORMA FOUNDATION,
. . . The defendant [herein private respondent] was not remiss INC., petitioner,
in reminding the plaintiff that it would have to bear the said vs.
expenses for failure to lift the commodity for an unreasonable ERNESTO V. SANTOS and RIVERLAND, INC., respondents.
length of time.
But even assuming that the plaintiff did not consent to be so Actions; Compromise Agreements; Judgments; The general
bound, the provisions of Civil Code come in to make it liable rule is that a compromise has upon the parties the effect and
for the damages sought by the defendant. authority of res judicata, with respect to the matter definitely
Art. 1170 of the Civil Code provides: stated therein, or which by implication from its terms should
Those who in the performance of their obligations are guilty of be deemed to have been included therein, and this holds true
fraud, negligence, or delay and those who in any manner even if the agreement has not been judicially approved.—A
contravene the tenor thereof, are liable for damages. compromise is a contract whereby the parties, by making
Certainly, the plaintiff [herein petitioner] was guilty of reciprocal concessions, avoid a litigation or put an end to one
negligence and delay in the performance of its obligation to lift already commenced. It is an agreement between two or more
the sulfuric acid on August 15, 1986 and had contravened the persons, who, for preventing or putting an end to a lawsuit,
adjust their difficulties by mutual consent in the manner which petitioner's Motion for Reconsideration.
they agree on, and which everyone of them prefers in the The facts of this case are undisputed.
hope of gaining, balanced by the danger of losing. The Ernesto V. Santos and Santos Ventura Hocorma Foundation,
general rule is that a compromise has upon the parties the Inc. (SVHFI) were the plaintiff and defendant, respectively, in
effect and authority of res judicata, with respect to the matter several civil cases filed in different courts in the Philippines.
definitely stated therein, or which by implication from its terms On October 26, 1990, the parties executed a Compromise
should be deemed to have been included therein. This holds Agreement4 which amicably ended all their pending
true even if the agreement has not been judicially approved. litigations. The pertinent portions of the Agreement read as
follows:
Same; Same; Same; The compromise agreement as a 1. Defendant Foundation shall pay Plaintiff Santos P14.5
consensual contract becomes binding between the parties Million in the following manner:
upon its execution and not upon its court approval.—In the a. P1.5 Million immediately upon the execution of this
case at bar, the Compromise Agreement was entered into by agreement;
the parties on October 26, 1990. It was judicially approved on b. The balance of P13 Million shall be paid, whether in one
September 30, 1991. Applying existing jurisprudence, the lump sum or in installments, at the discretion of the
compromise agreement as a consensual contract became Foundation, within a period of not more than two (2) years
binding between the parties upon its execution and not upon from the execution of this agreement; provided, however, that
its court approval. From the time a compromise is validly in the event that the Foundation does not pay the whole or
entered into, it becomes the source of the rights and any part of such balance, the same shall be paid with the
obligations of the parties thereto. The purpose of the corresponding portion of the land or real properties subject of
compromise is precisely to replace and terminate the aforesaid cases and previously covered by the notices of
controverted claims. lis pendens, under such terms and conditions as to area,
valuation, and location mutually acceptable to both parties;
Obligations and Contracts; Defaults; Delay as used in Art. but in no case shall the payment of such balance be later than
1169 of the New Civil Code is synonymous to default or mora two (2) years from the date of this agreement; otherwise,
which means delay in the fulfillment of obligations—it is the payment of any unpaid portion shall only be in the form of
non-fulfillment of the obligation with respect to time.—Article land aforesaid;
1169 of the New Civil Code provides: Those obliged to deliver 2. Immediately upon the execution of this agreement (and
or to do something incur in delay from the time the obligee [the] receipt of the P1.5 Million), plaintiff Santos shall cause
judicially or extrajudicially demands from them the fulfillment the dismissal with prejudice of Civil Cases Nos. 88-743,
of their obligation. [Emphasis supplied] Delay as used in this 1413OR, TC-1024, 45366 and 18166 and voluntarily withdraw
article is synonymous to default or mora which means delay in the appeals in Civil Cases Nos. 4968 (C.A.-G.R. No. 26598)
the fulfillment of obligations. It is the non-fulfillment of the and 88-45366 (C.A.-G.R. No. 24304) respectively and for the
obligation with respect to time. In order for the debtor to be in immediate lifting of the aforesaid various notices of lis
default, it is necessary that the following requisites be present: pendens on the real properties aforementioned (by signing
(1) that the obligation be demandable and already liquidated; herein attached corresponding documents, for such lifting);
(2) that the debtor delays performance; and (3) that the provided, however, that in the event that defendant
creditor requires the performance judicially or extrajudicially. Foundation shall sell or dispose of any of the lands previously
subject of lis pendens, the proceeds of any such sale, or any
Same; Same; Damages; Interests; When the debtor knows part thereof as may be required, shall be partially devoted to
the amount and period when he is to pay, interest as the payment of the Foundation's obligations under this
damages is generally allowed as a matter of right.—When the agreement as may still be subsisting and payable at the time
debtor knows the amount and period when he is to pay, of any such sale or sales;
interest as damages is generally allowed as a matter of right. ...
The complaining party has been deprived of funds to which he 5. Failure of compliance of any of the foregoing terms and
is entitled by virtue of their compromise agreement. The goal conditions by either or both parties to this agreement shall
of compensation requires that the complainant be ipso facto and ipso jure automatically entitle the aggrieved
compensated for the loss of use of those funds. This party to a writ of execution for the enforcement of this
compensation is in the form of interest. In the absence of agreement. [Emphasis supplied]5
agreement, the legal rate of interest shall prevail. The legal In compliance with the Compromise Agreement, respondent
interest for loan as forbearance of money is 12% per annum Santos moved for the dismissal of the aforesaid civil cases.
to be computed from default, i.e., from judicial or extrajudicial He also caused the lifting of the notices of lis pendens on the
demand under and subject to the provisions of Article 1169 of real properties involved. For its part, petitioner SVHFI, paid
the Civil Code. P1.5 million to respondent Santos, leaving a balance of P13
million.
QUISUMBING, J.: Subsequently, petitioner SVHFI sold to Development
Subject of the present petition for review on certiorari is the Exchange Livelihood Corporation two real properties, which
Decision,1 dated January 30, 2002, as well as the April 12, were previously subjects of lis pendens. Discovering the
2002, Resolution2 of the Court of Appeals in CA-G.R. CV No. disposition made by the petitioner, respondent Santos sent a
55122. The appellate court reversed the Decision,3 dated letter to the petitioner demanding the payment of the
October 4, 1996, of the Regional Trial Court of Makati City, remaining P13 million, which was ignored by the latter.
Branch 148, in Civil Case No. 95-811, and likewise denied Meanwhile, on September 30, 1991, the Regional Trial Court
of Makati City, Branch 62, issued a Decision6 approving the COMMITTED REVERSIBLE ERROR WHEN IT AWARDED
compromise agreement. LEGAL INTEREST IN FAVOR OF THE RESPONDENTS, MR.
On October 28, 1992, respondent Santos sent another letter SANTOS AND RIVERLAND, INC., NOTWITHSTANDING
to petitioner inquiring when it would pay the balance of P13 THE FACT THAT NEITHER IN THE COMPROMISE
million. There was no response from petitioner. Consequently, AGREEMENT NOR IN THE COMPROMISE JUDGEMENT
respondent Santos applied with the Regional Trial Court of OF HON. JUDGE DIOKNO PROVIDES FOR PAYMENT OF
Makati City, Branch 62, for the issuance of a writ of execution INTEREST TO THE RESPONDENT
of its compromise judgment dated September 30, 1991. The II
RTC granted the writ. Thus, on March 10, 1993, the Sheriff WHETHER OF NOT THE COURT OF APPEALS ERRED IN
levied on the real properties of petitioner, which were formerly AWARDING LEGAL IN[T]EREST IN FAVOR OF THE
subjects of the lis pendens. Petitioner, however, filed RESPONDENTS, MR. SANTOS AND RIVERLAND, INC.,
numerous motions to block the enforcement of the said writ. NOTWITHSTANDING THE FACT THAT THE OBLIGATION
The challenge of the execution of the aforesaid compromise OF THE PETITIONER TO RESPONDENT SANTOS TO PAY
judgment even reached the Supreme Court. All these efforts, A SUM OF MONEY HAD BEEN CONVERTED TO AN
however, were futile. OBLIGATION TO PAY IN KIND – DELIVERY OF REAL
On November 22, 1994, petitioner's real properties located in PROPERTIES OWNED BY THE PETITIONER – WHICH
Mabalacat, Pampanga were auctioned. In the said auction, HAD BEEN FULLY PERFORMED
Riverland, Inc. was the highest bidder for P12 million and it III
was issued a Certificate of Sale covering the real properties WHETHER OR NOT RESPONDENTS ARE BARRED FROM
subject of the auction sale. Subsequently, another auction DEMANDING PAYMENT OF INTEREST BY REASON OF
sale was held on February 8, 1995, for the sale of real THE WAIVER PROVISION IN THE COMPROMISE
properties of petitioner in Bacolod City. Again, Riverland, Inc. AGREEMENT, WHICH BECAME THE LAW AMONG THE
was the highest bidder. The Certificates of Sale issued for PARTIES10
both properties provided for the right of redemption within one The only issue to be resolved is whether the respondents are
year from the date of registration of the said properties. entitled to legal interest.
On June 2, 1995, Santos and Riverland Inc. filed a Complaint Petitioner SVHFI alleges that where a compromise agreement
for Declaratory Relief and Damages7 alleging that there was or compromise judgment does not provide for the payment of
delay on the part of petitioner in paying the balance of P13 interest, the legal interest by way of penalty on account of
million. They further alleged that under the Compromise fault or delay shall not be due and payable, considering that
Agreement, the obligation became due on October 26, 1992, the obligation or loan, on which the payment of legal interest
but payment of the remaining P12 million was effected only on could be based, has been superseded by the compromise
November 22, 1994. Thus, respondents prayed that petitioner agreement.11 Furthermore, the petitioner argues that the
be ordered to pay legal interest on the obligation, penalty, respondents are barred by res judicata from seeking legal
attorney's fees and costs of litigation. Furthermore, they interest on account of the waiver clause in the duly approved
prayed that the aforesaid sales be declared final and not compromise agreement.12 Article 4 of the compromise
subject to legal redemption. agreement provides:
In its Answer,8 petitioner countered that respondents have no Plaintiff Santos waives and renounces any and all other
cause of action against it since it had fully paid its obligation to claims that he and his family may have on the defendant
the latter. It further claimed that the alleged delay in the Foundation arising from and in connection with the aforesaid
payment of the balance was due to its valid exercise of its civil cases, and defendant Foundation, on the other hand,
rights to protect its interests as provided under the Rules. also waives and renounces any and all claims that it may
Petitioner counterclaimed for attorney's fees and exemplary have against plaintiff Santos in connection with such
damages. cases.13 [Emphasis supplied.]
On October 4, 1996, the trial court rendered a Lastly, petitioner alleges that since the compromise
Decision9 dismissing herein respondents' complaint and agreement did not provide for a period within which the
ordering them to pay attorney's fees and exemplary damages obligation will become due and demandable, it is incumbent
to petitioner. Respondents then appealed to the Court of upon respondent Santos to ask for judicial intervention for
Appeals. The appellate court reversed the ruling of the trial purposes of fixing the period. It is only when a fixed period
court: exists that the legal interests can be computed.
WHEREFORE, finding merit in the appeal, the appealed Respondents profer that their right to damages is based on
Decision is hereby REVERSED and judgment is hereby delay in the payment of the obligation provided in the
rendered ordering appellee SVHFI to pay appellants Santos Compromise Agreement. The Compromise Agreement
and Riverland, Inc.: (1) legal interest on the principal amount provides that payment must be made within the two-year
of P13 million at the rate of 12% per annum from the date of period from its execution. This was approved by the trial court
demand on October 28, 1992 up to the date of actual and became the law governing their contract. Respondents
payment of the whole obligation; and (2) P20,000 as posit that petitioner's failure to comply entitles them to
attorney's fees and costs of suit. damages, by way of interest.14
SO ORDERED. The petition lacks merit.
Hence this petition for review on certiorari where petitioner A compromise is a contract whereby the parties, by making
assigns the following issues: reciprocal concessions, avoid a litigation or put an end to one
I already commenced.15 It is an agreement between two or
WHETHER OR NOT THE COURT OF APPEALS more persons, who, for preventing or putting an end to a
lawsuit, adjust their difficulties by mutual consent in the letter on October 28, 1992, to the petitioner, the obligation
manner which they agree on, and which everyone of them was already due and demandable. Furthermore, the
prefers in the hope of gaining, balanced by the danger of obligation is liquidated because the debtor knows precisely
losing.16 how much he is to pay and when he is to pay it.
The general rule is that a compromise has upon the parties The second requisite is also present. Petitioner delayed in the
the effect and authority of res judicata, with respect to the performance. It was able to fully settle its outstanding balance
matter definitely stated therein, or which by implication from only on February 8, 1995, which is more than two years after
its terms should be deemed to have been included the extra-judicial demand. Moreover, it filed several motions
therein.17 This holds true even if the agreement has not been and elevated adverse resolutions to the appellate court to
judicially approved.18 hinder the execution of a final and executory judgment, and
In the case at bar, the Compromise Agreement was entered further delay the fulfillment of its obligation.
into by the parties on October 26, 1990.19 It was judicially Third, the demand letter sent to the petitioner on October 28,
approved on September 30, 1991.20 Applying existing 1992, was in accordance with an extra-judicial demand
jurisprudence, the compromise agreement as a consensual contemplated by law.
contract became binding between the parties upon its Verily, the petitioner is liable for damages for the delay in the
execution and not upon its court approval. From the time a performance of its obligation. This is provided for in Article
compromise is validly entered into, it becomes the source of 117025 of the New Civil Code.
the rights and obligations of the parties thereto. The purpose When the debtor knows the amount and period when he is to
of the compromise is precisely to replace and terminate pay, interest as damages is generally allowed as a matter of
controverted claims.21 right.26 The complaining party has been deprived of funds to
In accordance with the compromise agreement, the which he is entitled by virtue of their compromise agreement.
respondents asked for the dismissal of the pending civil The goal of compensation requires that the complainant be
cases. The petitioner, on the other hand, paid the initial P1.5 compensated for the loss of use of those funds. This
million upon the execution of the agreement. This act of the compensation is in the form of interest.27 In the absence of
petitioner showed that it acknowledges that the agreement agreement, the legal rate of interest shall prevail.28 The legal
was immediately executory and enforceable upon its interest for loan as forbearance of money is 12% per
execution. annum29 to be computed from default, i.e., from judicial or
As to the remaining P13 million, the terms and conditions of extrajudicial demand under and subject to the provisions of
the compromise agreement are clear and unambiguous. It Article 1169 of the Civil Code.30
provides: WHEREFORE, the petition is DENIED for lack of merit. The
... Decision dated January 30, 2002 of the Court of Appeals and
b. The balance of P13 Million shall be paid, whether in one its April 12, 2002 Resolution in CA-G.R. CV No. 55122 are
lump sum or in installments, at the discretion of the AFFIRMED. Costs against petitioner.
Foundation, within a period of not more than two (2) years SO ORDERED.
from the execution of this agreement…22 [Emphasis
supplied.] TITAN-IKEDA CONSTRUCTION & DEVELOPMENT
... CORPORATION, Petitioner, v. PRIMETOWN PROPERTY
The two-year period must be counted from October 26, 1990, GROUP, INC., Respondent.
the date of execution of the compromise agreement, and not
on the judicial approval of the compromise agreement on Appeals; Factual issues are entertained only in petition for
September 30, 1991. When respondents wrote a demand review in exceptional cases such as where the findings of fact
letter to petitioner on October 28, 1992, the obligation was of the Court of Appeals and the trial court are conflicting.—As
already due and demandable. When the petitioner failed to a general rule, only questions of law may be raised in a
pay its due obligation after the demand was made, it incurred petition for review on certiorari. Factual issues are entertained
delay. only in exceptional cases such as where the findings of fact of
Article 1169 of the New Civil Code provides: the CA and the trial court are conflicting.
Those obliged to deliver or to do something incur in delay
from the time the obligee judicially or extrajudicially demands Contracts; Words and Phrases; A contract is a meeting of the
from them the fulfillment of their obligation. [Emphasis minds between two persons whereby one binds himself, with
supplied] respect to the other, to give something or to render some
Delay as used in this article is synonymous to default or mora service.—A contract is a meeting of the minds between two
which means delay in the fulfillment of obligations. It is the persons whereby one binds himself, with respect to the other,
non-fulfillment of the obligation with respect to time.23 to give something or to render some service. This case
In order for the debtor to be in default, it is necessary that the involved two contracts entered into by the parties with regard
following requisites be present: (1) that the obligation be to the project. The parties first entered into a contract for a
demandable and already liquidated; (2) that the debtor delays piece of work when they executed the supplemental
performance; and (3) that the creditor requires the agreement. Petitioner as contractor bound itself to execute
performance judicially or extrajudicially.24 the project for respondent, the owner/developer, in
In the case at bar, the obligation was already due and consideration of a price certain (P130,000,000). The
demandable after the lapse of the two-year period from the supplemental agreement was reciprocal in nature because
execution of the contract. The two-year period ended on the obligation of respondent to pay the entire contract price
October 26, 1992. When the respondents gave a demand depended on the obligation of petitioner to complete the
project (and vice versa). Thereafter, the parties entered into a obligation in due time because of dolo (malice) or culpa
second contract. They agreed to extinguish the supplemental (negligence). A debtor is deemed to have violated his
agreement as evidenced by the October 12, 1995 letter- obligation to the creditor from the time the latter makes a
agreement which was duly acknowledged by their respective demand. Once the creditor makes a demand, the debtor
representatives. incurs mora or delay.

Contracts; Quasi-Contracts; Solutio Indebiti; Requisites; If Same; Construction Contracts; Additional Costs; Unjust
something is received when there is no right to demand it and Enrichment; A claim for the cost of additional work arising
it was unduly delivered through mistake, the obligation to from changes in the scope of work can only be allowed upon
return it arises.—Because petitioner acknowledged that it had the written authority from the developer/owner
been overpaid, it was obliged to return the excess to ordering/allowing the changes in work and written agreement
respondent. Embodying the principle of solutio indebiti, Article of parties with regard to the increase in cost (or price) due to
2154 of the Civil Code provides: Article 2154. If something is the change in work or design modification; A contractor who
received when there is no right to demand it and it was unduly fails to secure the owner’s or developer’s written authority to
delivered through mistake, the obligation to return it arises. changes in the work or written assent to the additional cost to
For the extra-contractual obligation of solutio indebiti to arise, be incurred cannot invoke the principle of unjust enrichment.
the following requisites must be proven: 1. the absence of a —In Powton Conglomerate, Inc. v. Agcolicol, we reiterated
right to collect the excess sums and 2. the payment was that a claim for the cost of additional work arising from
made by mistake. changes in the scope of work can only be allowed upon the:
1. written authority from the developer/owner
Same; Same; Payment by Mistake; Presumptions; It is ordering/allowing the changes in work; and 2. written
presumed that there was a mistake in the payment if agreement of parties with regard to the increase in cost (or
something which had never been due or had already been price) due to the change in work or design
paid was delivered.—With regard to the first requisite, modification.Furthermore: Compliance with the two requisites
because the supplemental agreement had been extinguished of Article 1724, a specific provision governing additional
by the mutual agreement of the parties, petitioner became works, is a condition precedent of the recovery. The absence
entitled only to the cost of services it actually rendered (i.e., of one or the other bars the recovery of additional costs.
that fraction of the project cost in proportion to the percentage Neither the authority for the changes made nor the additional
of its actual accomplishment in the project). It was not entitled price to be paid therefor may be proved by any other evidence
to the excess (or extent of overpayment). On the second for purposes of recovery. (emphasis supplied) Petitioner
requisite, Article 2163 of the Civil Code provides: Article 2163. submitted neither one. In addition, petitioner’s project
It is presumed that there was a mistake in the payment if coordinator Estellita Garcia testified that respondent never
something which had never been due or had already been approved any change order. Thus, under Article 1724 and
paid was delivered; but, he from whom the return is claimed pursuant to our ruling in Powton Conglomerate, Inc., petitioner
may prove that the delivery was made out of liberality or for cannot recover the cost it incurred in effecting the design
any other just cause. (emphasis supplied) modifications. A contractor who fails to secure the owner or
developer’s written authority to changes in the work or written
Same; Same; Same; He who accepts, in good faith, an undue assent to the additional cost to be incurred cannot invoke the
payment of a thing certain and determinate shall only be principle of unjust enrichment.
responsible for the impairment or loss of the same or its
accessories and accessions insofar as he has thereby been Damages; Indemnification for damages comprehends not only
benefited; One who receives payment by mistake in good the loss suffered (actual damages or damnum emergens) but
faith is, as a general rule, only liable to return the thing also the claimant’s lost profits (compensatory damages or
delivered.—Stated simply, respondent erroneously delivered lucrum cessans).—Indemnification for damages comprehends
excess units to petitioner and the latter, pursuant to Article not only the loss suffered (actual damages or damnum
2154, was obliged to the return them to respondent. Article emergens) but also the claimant’s lost profits (compensatory
2160 of the Civil Code provides: Article 2160. He who in good damages or lucrum cessans). For compensatory damages to
faith accepts an undue payment of a thing certain and be awarded, it is necessary to prove the actual amount of the
determinate shall only be responsible for the impairment or alleged loss by preponderance of evidence.
loss of the same or its accessories and accessions insofar as
he has thereby been benefited. If he has alienated it, he shall CORONA, J.:
return the price or assign the action to collect the sum. One This petition for review on certiorari 1 seeks to set aside the
who receives payment by mistake in good faith is, as a decision of the Court of Appeals (CA) in CA-G.R. CV No.
general rule, only liable to return the thing delivered. If he 613532 and its resolution3 denying reconsideration.
benefited therefrom, he is also liable for the impairment or In 1992, respondent Primetown Property Group, Inc. awarded
loss of the thing delivered and its accessories and the contract for the structural works 4 of its 32-storey Makati
accessions. If he sold the thing delivered, he should either Prime Tower (MPT) to petitioner Titan-Ikeda Construction and
deliver the proceeds of the sale or assign the action to collect Development Corporation.5 The parties formalized their
to the other party. agreement in a construction contract 6 dated February 4,
1993.7
Obligations and Contracts; Words and Phrases; “Mora” or Upon the completion of MPT's structural works, respondent
“Delay,” Defined.—Mora or delay is the failure to perform the awarded the P130,000,000 contract for the tower's
architectural works8 (project) to petitioner. Thus, on January [petitioner], in the spirit of cooperation, agreed to hand over
31, 1994, the parties executed a supplemental the construction supervision to [respondent] as requested.
agreement.9 The salient portions thereof were: (emphasis supplied)19
1. the [project] shall cover the scope of work of the detailed Engineers Antonio Co, general construction manager of
construction bid plans and specifications and bid documents respondent, and Luzon Y. Tablante, project manager of
dated 28 September 1993, attached and forming an integral petitioner, signed the letter.
part hereof as Annex A. Integratech’s (ITI’s) Report
2. the contract price for the said works shall be P130 million. In its September 7, 1995 report, ITI estimated that petitioner
3. the payment terms shall be "full swapping" or full payment should have accomplished 48.71% of the project as of the
in condominium units. The condominium units earmarked for October 12, 1995 takeover date.20 Petitioner repudiated this
the [petitioner] are shown in the attached Annex B. figure21 but qualifiedly admitted that it did not finish the
4. the [respondent] shall transfer and surrender to [petitioner] project.22 Records showed that respondent did not merely
the condominium units abovestated in accordance with the take over the supervision of the project but took full control
following schedule: thereof.23
(a) 80% of units — upon posting and acceptance by Petitioner consequently conducted an inventory. 24 On the
[respondent] of the performance bond [and] basis thereof, petitioner demanded from respondent the
(b) 20% or remaining balance — upon completion of the payment of its balance amounting to P1,779,744.85.25
project as provided in the construction contract and On February 19, 1996, petitioner sent a second letter to
simultaneous with the posting by [petitioner] of the respondent demanding P2,023,876.25. This new figure
reglementary guarantee bond. included the cost of materials (P244,331.40) petitioner
5. the contract period shall be fifteen (15) months reckoned advanced from December 5, 1995 to January 26, 1996. 26
from the release of the condominium certificates of title On November 22, 1996, petitioner demanded from
(CCTs) covering eighty percent (80%) of the units transferable respondent the delivery of MPT's management
to [petitioner] as aforesaid[.] certificate27 and the keys to the condominium units and the
Significantly, the supplemental agreement adopted those payment of its (respondent's) balance.28
provisions of the construction contract which it did not Because respondent ignored petitioner's demand, petitioner,
specifically discuss or provide for. 10 Among those carried over on December 9, 1996, filed a complaint for specific
was the designation of GEMM Construction Corporation performance29 in the Housing and Land Use Regulatory Board
(GEMM) as the project's construction manager. 11 (HLURB).
Petitioner started working on the project in February 1994. While the complaint for specific performance was pending in
On June 30, 1994, respondent executed a deed of the HLURB, respondent sent a demand letter to petitioner
sale12 (covering 114 condominium units and 20 parking slots asking it to reimburse the actual costs incurred in finishing the
of the MPT collectively valued by the parties project (or P69,785,923.47).30 In view of the pendency of the
at P112,416,716.88)13 in favor of petitioner pursuant to the HLURB case, petitioner did not heed respondent's demands.
"full-swapping" payment provision of the supplemental On April 29, 1997, the HLURB rendered a decision in favor of
agreement. petitioner.31 It ruled that the instrument executed on June 30,
Shortly thereafter, petitioner sold some of its units to third 1994 was a deed of absolute sale because the conveyance of
persons.14 the condominium units and parking slots was not subject to
In September 1995, respondent engaged the services of any condition.32 Thus, it ordered respondent to issue MPT’s
Integratech, Inc. (ITI), an engineering consultancy firm, to management certificate and to deliver the keys to the
evaluate the progress of the project. 15 In its September 7, condominium units to petitioner.33 Respondent did not appeal
1995 report,16 ITI informed respondent that petitioner, at that this decision. Consequently, a writ of execution was issued
point, had only accomplished 31.89% of the project (or was 11 upon its finality.34
months and six days behind schedule).17 Undaunted by the finality of the HLURB decision, respondent
Meanwhile, petitioner and respondent were discussing the filed a complaint for collection of sum of money 35 against
possibility of the latter’s take over of the project’s supervision. petitioner in the Regional Trial Court (RTC) of Makati City,
Despite ongoing negotiations, respondent did not obtain Branch 58 on July 2, 1997. It prayed for the reimbursement of
petitioner’s consent in hiring ITI as the project’s construction the value of the project’s unfinished portion amounting
manager. Neither did it inform petitioner of ITI’s September 7, to P66,677,000.36
1995 report. During trial, the RTC found that because respondent modified
On October 12, 1995, petitioner sought to confirm the MPT's architectural design, petitioner had to adjust the
respondent's plan to take over the project. 18 Its letter stated: scope of work.37 Moreover, respondent belatedly informed
The mutual agreement arrived at sometime in the last week of petitioner of those modifications. It also failed to deliver the
August 1995 for [respondent] to take over the construction concrete mix and rebars according to schedule. For this
supervision of the balance of the [project] from [petitioner's] reason, petitioner was not responsible for the project's
[e]ngineering staff and complete [the] same by December 31, delay.38 The trial court thus allowed petitioner to set-off
1995 as promised by [petitioner's] engineer. respondent's other outstanding liabilities with respondent’s
The [petitioner's] accomplished works as of this date of [t]ake excess payment in the project.39 It concluded that respondent
over is of acceptable quality in materials and workmanship. owed petitioner P2,023,876.25.40 In addition, because
This mutual agreement on the take over should not be respondent refused to deliver the keys to the condominium
misconstrued in any other way except that the take over units and the management certificate to petitioner, the RTC
is part of the long range plan of [respondent] that found that petitioner lost rental income amounting to
US$1,665,260.41 The dispositive portion of the RTC decision the necessary materials on time. The CA, however, found that
stated: petitioner incurred delay in the performance of its obligation. It
WHEREFORE, PREMISES CONSIDERED, judgment is relied on ITI's report which stated that petitioner had
hereby rendered dismissing [respondent's] [c]omplaint for lack accomplished only 48.71% of the project as of October 12,
of merit. On the other hand, finding preponderance of 1995.
evidence to sustain [petitioner's] counterclaim, judgment is January 31, 1994 Supplemental Agreement Was
hereby rendered in favor of [petitioner] ordering [respondent] Extinguished
to pay the former: A contract is a meeting of the minds between two persons
1. The unpaid balance of the consideration for [petitioner's] whereby one binds himself, with respect to the other, to give
services in [the project] in the amount of P2,023,867.25 with something or to render some service.50 This case involved two
legal interest from the date of demand until fully paid; contracts entered into by the parties with regard to the project.
2. Compensatory damages in the amount of US$1,665,260 or The parties first entered into a contract for a piece of
its peso equivalent at the current foreign exchange rate work51 when they executed the supplemental agreement.
representing lost rental income due only as of July 1997 and Petitioner as contractor bound itself to execute the project for
the accrued lost earnings from then on until the date of actual respondent, the owner/developer, in consideration of a price
payment, with legal interest from the date of demand until fully certain (P130,000,000). The supplemental agreement was
paid; and reciprocal in nature because the obligation of respondent to
3. Attorney's fees in the amount of P100,000 as acceptance pay the entire contract price depended on the obligation of
fee, P1,000 appearance fee per hearing and 25% of the total petitioner to complete the project (and vice versa).
amount awarded to [petitioner]. Thereafter, the parties entered into a second contract. They
With costs against the [respondent]. agreed to extinguish the supplemental agreement as
SO ORDERED.42 evidenced by the October 12, 1995 letter-agreement which
Respondent appealed the RTC decision to the CA. 43 The was duly acknowledged by their respective representatives. 52
appellate court found that respondent fully performed its While the October 12, 1995 letter-agreement stated that
obligation when it executed the June 30, 1994 deed of respondent was to take over merely the supervision of the
absolute sale in favor of petitioner.44 Moreover, ITI's report project, it actually took over the whole project itself. In fact,
clearly established that petitioner had completed only 48.71% respondent subsequently hired two contractors in petitioner's
of the project as of October 12, 1995, the takeover date. Not stead.53 Moreover, petitioner's project engineer at site only
only did it incur delay in the performance of its obligation but monitored the progress of architectural works undertaken in
petitioner also failed to finish the project. The CA ruled that its condominium units.54 Petitioner never objected to this
respondent was entitled to recover the value of the unfinished arrangement; hence, it voluntarily surrendered its participation
portion of the project under the principle of unjust in the project. Moreover, it judicially admitted in its answer that
enrichment.45 Thus: respondent took over the entire project, not merely its
WHEREFORE, the appealed decision is REVERSED and a supervision, pursuant to its (respondent’s) long-range plans. 55
new one entered dismissing [petitioner's] counterclaims Because the parties agreed to extinguish the supplemental
of P2,023,867.25 representing unpaid balance for [its] agreement, they were no longer required to fully perform their
services in [the project]; US$1,665,260 as accrued lost respective obligations. Petitioner was relieved of its obligation
earnings, and attorney's fees. [Petitioner] is hereby ordered to to complete the project while respondent was freed of its
return to [respondent] the amount of P66,677,000 obligation to pay the entire contract price. However,
representing the value of unfinished [portion of the project], respondent, by executing the June 30, 1994 deed of absolute
plus legal interest thereon until fully paid. Upon payment by sale, was deemed to have paid P112,416,716.88.
[petitioner] of the aforementioned amount, [respondent] is Nevertheless, because petitioner applied part of what it
hereby ordered to deliver the keys and [m]anagement received to respondent’s outstanding liabilities, 56 it admitted
[c]ertificate of the [Makati Prime Tower] paid to [petitioner] as overpayment.
consideration for the [project].46 Because petitioner acknowledged that it had been overpaid, it
Petitioner moved for reconsideration but it was denied. was obliged to return the excess to respondent. Embodying
Hence, this petition. the principle of solutio indebiti, Article 2154 of the Civil Code
Petitioner contends that the CA erred in giving weight to ITI's provides:
report because the project evaluation was commissioned only Article 2154. If something is received when there is no right to
by respondent,47 in disregard of industry practice. Project demand it and it was unduly delivered through mistake, the
evaluations are agreed upon by the parties and conducted by obligation to return it arises.
a disinterested third party.48 For the extra-contractual obligation of solutio indebiti to arise,
We grant the petition. the following requisites must be proven:
Review of Conflicting Factual Findings 1. the absence of a right to collect the excess sums and
As a general rule, only questions of law may be raised in a 2. the payment was made by mistake.57
petition for review on certiorari. Factual issues are entertained With regard to the first requisite, because the supplemental
only in exceptional cases such as where the findings of fact of agreement had been extinguished by the mutual agreement
the CA and the trial court are conflicting.49 of the parties, petitioner became entitled only to the cost of
Here, a glaring contradiction exists between the factual services it actually rendered (i.e.,  that fraction of the project
findings of the RTC and the CA. The trial court found that cost in proportion to the percentage of its actual
respondent contributed to the project's delay because it accomplishment in the project). It was not entitled to the
belatedly communicated the modifications and failed to deliver excess (or extent of overpayment).
On the second requisite, Article 2163 of the Civil Code assign the actions for collection to respondent as required by
provides: Article 2160.
Article 2163. It is presumed that there was a mistake in the Delay In The Completion Of The Project
payment if something which had never been due or had Mora or delay is the failure to perform the obligation in due
already been paid was delivered; but, he from whom the time because of dolo  (malice) or culpa  (negligence).63 A
return is claimed may prove that the delivery was made out of debtor is deemed to have violated his obligation to the creditor
liberality or for any other just cause. (emphasis supplied) from the time the latter makes a demand. Once the creditor
In this instance, respondent paid part of the contract price makes a demand, the debtor incurs mora or delay.64
under the assumption that petitioner would complete the The construction contract65 provided a procedure for
project within the stipulated period. However, after the protesting delay:
supplemental agreement was extinguished, petitioner ceased Article XIV
working on the project. Therefore, the compensation petitioner DELAYS AND ABANDONMENT
received in excess of the cost of its actual accomplishment as 15.1. If at any time during the effectivity of this contract,
of October 12, 1995 was never due. The condominium units [PETITIONER] shall incur unreasonable delay or
and parking slots corresponding to the said excess were slippages of more than fifteen percent (15%) of the
mistakenly delivered by respondent and were therefore not scheduled work program, [RESPONDENT] should
due to petitioner. notify [PETITIONER] in writing to accelerate the work and
Stated simply, respondent erroneously delivered excess units reduce, if not erase, slippage. If after the lapse of sixty (60)
to petitioner and the latter, pursuant to Article 2154, was days from receipt of such notice, [PETITIONER] fails to rectify
obliged to the return them to respondent.58 Article 2160 of the the delay or slippage, [RESPONDENT] shall have the right to
Civil Code provides: terminate this contract except in cases where the same was
Article 2160. He who in good faith accepts an undue payment caused by force majeure. "FORCE MAJEURE" as
of a thing certain and determinate shall only be responsible contemplated herein, and in determination of delay includes,
for the impairment or loss of the same or its accessories and but is not limited to, typhoon, flood, earthquake, coup d'etat,
accessions insofar as he has thereby been benefited. If he rebellion, sedition, transport strike, stoppage of work, mass
has alienated it, he shall return the price or assign the action public action that prevents workers from reporting for work,
to collect the sum. and such other causes beyond [PETITIONER'S]
One who receives payment by mistake in good faith is, as a control.66 (emphasis supplied)
general rule, only liable to return the thing delivered. 59 If he xxx    xxx    xxx
benefited therefrom, he is also liable for the impairment or Respondent never sent petitioner a written demand asking it
loss of the thing delivered and its accessories and to accelerate work on the project and reduce, if not eliminate,
accessions.60 If he sold the thing delivered, he should either slippage. If delay had truly been the reason why respondent
deliver the proceeds of the sale or assign the action to collect took over the project, it would have sent a written demand as
to the other party.61 required by the construction contract. Moreover, according to
The situation is, however, complicated by the following facts: the October 12, 1995 letter-agreement, respondent took over
a) the basis of the valuation (P112,416,716.99) of the the project for the sole reason that such move was part of its
condominium units and parking slots covered by the June 30, (respondent's) long-term plan.
1994 deed of sale is unknown; Respondent, on the other hand, relied on ITI's September 7,
b) the percentage of petitioner's actual accomplishment in the 1995 report. The construction contract named GEMM, not ITI,
project has not been determined and as construction manager.67 Because petitioner did not consent
c) the records of this case do not show the actual number of to the change of the designated construction manager, ITI's
condominium units and parking slots sold by petitioners. September 7, 1995 report could not bind it.
Because this Court is not a trier of facts, the determination of In view of the foregoing, we hold that petitioner did not incur
these matters should be remanded to the RTC for reception of delay in the performance of its obligation.
further evidence. Recovery Of Additional Costs Resulting From Changes
The RTC must first determine the percentage of the project The supplemental agreement was a contract for a stipulated
petitioner actually completed and its proportionate cost. 62 This price.68 In such contracts, the recovery of additional costs
will be the amount due to petitioner. Thereafter, based on the (incurred due to changes in plans or specifications) is
stipulated valuation in the June 30, 1994 deed of sale, the governed by Article 1724 of the Civil Code.
RTC shall determine how many condominium units and Article 1724. The contractor who undertakes to build a
parking slots correspond to the amount due to petitioner. It will structure or any other work for a stipulated price, in conformity
only be the management certificate and the keys to these with plans and specifications agreed upon with the landowner,
units that petitioner will be entitled to. The remaining units, can neither withdraw from the contract nor demand an
having been mistakenly delivered by respondent, will increase in the price on account of higher cost of labor or
therefore be the subject of solutio indebiti. materials, save when there has been a change in plans and
What exactly must petitioner give back to respondent? Under specifications, provided:
Article 2160 in relation to Article 2154, it should return to 1. such change has been authorized by the proprietor in
respondent the condominium units and parking slots in writing; and
excess of the value of its actual accomplishment (i.e., the 2. the additional price to be paid to the contractor has been
amount due to it) as of October 12, 1995. If these properties determined in writing by both parties.
include units and/or slots already sold to third persons, In Powton Conglomerate, Inc. v. Agcolicol,69 we reiterated that
petitioner shall deliver the proceeds of the sale thereof or a claim for the cost of additional work arising from changes in
the scope of work can only be allowed upon the: Court of Makati City, Branch 58 for:
1. written authority from the developer/owner 1. the reception of additional evidence to determine
ordering/allowing the changes in work; and (a) the percentage of the architectural work actually
2. written agreement of parties with regard to the increase in completed by petitioner Titan-Ikeda Construction and
cost (or price) due to the change in work or design Development Corporation as of October 12, 1995 on the
modification. 70 Makati Prime Tower and
Furthermore: (b) the number of condominium units and parking slots sold
Compliance with the two requisites of Article 1724, a by petitioner Titan-Ikeda Construction and Development
specific provision governing additional works, is a Corporation to third persons;
condition precedent of the recovery. The absence of one 2. the computation of petitioner Titan-Ikeda Construction and
or the other bars the recovery of additional costs. Neither the Development Corporation's actual liability to respondent
authority for the changes made nor the additional price to be Primetown Property Group, Inc. or vice-versa, and the
paid therefor may be proved by any other evidence for determination of imposable interests and/or penalties, if any.
purposes of recovery.71 (emphasis supplied) SO ORDERED.
Petitioner submitted neither one. In addition, petitioner’s
project coordinator Estellita Garcia testified that respondent G.R. No. 149734       November 19, 2004
never approved any change order. 72 Thus, under Article 1724 DR. DANIEL VAZQUEZ and MA. LUIZA M.
and pursuant to our ruling in Powton Conglomerate, VAZQUEZ, petitioners,
Inc., petitioner cannot recover the cost it incurred in effecting vs.
the design modifications. A contractor who fails to secure the AYALA CORPORATION, respondent.
owner or developer's written authority to changes in the work
or written assent to the additional cost to be incurred cannot TINGA, J.:
invoke the principle of unjust enrichment. 73 The rise in value of four lots in one of the country's prime
Recovery Of Compensatory Damages residential developments, Ayala Alabang Village in Muntinlupa
Indemnification for damages comprehends not only the loss City, over a period of six (6) years only, represents big money.
suffered (actual damages or damnum emergens) but also the The huge price difference lies at the heart of the present
claimant's lost profits (compensatory damages or lucrum controversy. Petitioners insist that the lots should be sold to
cessans). For compensatory damages to be awarded, it is them at 1984 prices while respondent maintains that the
necessary to prove the actual amount of the alleged loss by prevailing market price in 1990 should be the selling price.
preponderance of evidence.74 Dr. Daniel Vazquez and Ma. Luisa Vazquez1 filed this Petition
The RTC awarded compensatory damages based on the for Review on Certiorari2 dated October 11, 2001 assailing
rental pool rates submitted by petitioner 75 and on the premise the Decision3 of the Court of Appeals dated September 6,
that all those units would have been leased had respondent 2001 which reversed the Decision4 of the Regional Trial Court
only finished the project by December 31, 1995. 76 However, (RTC) and dismissed their complaint for specific performance
other than bare assertions, petitioner submitted no proof that and damages against Ayala Corporation.
the rental pool was in fact able to lease out the units. We thus Despite their disparate rulings, the RTC and the appellate
hold that the "losses" sustained by petitioner were merely court agree on the following antecedents:5
speculative and there was no basis for the award. On April 23, 1981, spouses Daniel Vasquez and Ma. Luisa M.
Remand Of Other Claims Vasquez (hereafter, Vasquez spouses) entered into a
Since respondent did not repudiate petitioner's other claims Memorandum of Agreement (MOA) with Ayala Corporation
stated in the inventory77 in the RTC and CA, it is estopped (hereafter, AYALA) with AYALA buying from the Vazquez
from questioning the validity thereof.78 However, because spouses, all of the latter's shares of stock in Conduit
some of petitioner's claims have been disallowed, we remand Development, Inc. (hereafter, Conduit). The main asset of
the records of this case to the RTC for the computation of Conduit was a 49.9 hectare property in Ayala Alabang,
respondent's liability.79 Muntinlupa, which was then being developed by Conduit
WHEREFORE, the petition is hereby GRANTED. under a development plan where the land was divided into
The March 15, 2002 decision and May 29, 2003 resolution of Villages 1, 2 and 3 of the "Don Vicente Village." The
the Court of Appeals in CA-G.R. CV No. 61353 and the development was then being undertaken for Conduit by G.P.
August 5, 1998 decision of the Regional Trial Court, Branch Construction and Development Corp. (hereafter, GP
58, Makati City in Civil Case No. 97-1501 are hereby SET Construction).
ASIDE. New judgment is entered: Under the MOA, Ayala was to develop the entire property,
1. ordering petitioner Titan-Ikeda Construction and less what was defined as the "Retained Area" consisting of
Development Corporation to return to respondent Primetown 18,736 square meters. This "Retained Area" was to be
Property Group, Inc. the condominium units and parking slots retained by the Vazquez spouses. The area to be developed
corresponding to the payment made in excess of the by Ayala was called the "Remaining Area". In this "Remaining
proportionate (project) cost of its actual accomplishment as of Area" were 4 lots adjacent to the "Retained Area" and Ayala
October 12, 1995, subject to its (petitioner’s) allowable claims agreed to offer these lots for sale to the Vazquez spouses at
as stated in the inventory and the prevailing price at the time of purchase. The relevant
2. dismissing petitioner Titan-Ikeda Construction and provisions of the MOA on this point are:
Development Corporation’s claims for the cost of additional "5.7. The BUYER hereby commits that it will develop the
work (or change order) and damages. 'Remaining Property' into a first class residential subdivision
The records of this case are remanded to the Regional Trial of the same class as its New Alabang Subdivision, and that it
intends to complete the first phase under its amended tax liabilities due or to become due and whether incurred in
development plan within three (3) years from the date of this respect of or measured in respect of the Company's income
Agreement. x x x" prior to Closing or arising out of transactions or state of facts
5.15. The BUYER agrees to give the SELLERS a first option existing prior thereto.
to purchase four developed lots next to the "Retained Area" at 7.2 SELLERS do not know or have no reasonable ground to
the prevailing market price at the time of the purchase." know of any basis for any assertion against the Company as
The parties are agreed that the development plan referred to at closing or any liability of any nature and in any amount not
in paragraph 5.7 is not Conduit's development plan, but fully reflected or reserved against such Audited Financial
Ayala's amended development plan which was still to be Statements referred to above, and those disclosed to BUYER.
formulated as of the time of the MOA. While in the Conduit xxx xxx xxx
plan, the 4 lots to be offered for sale to the Vasquez Spouses 7.6.3 Except as otherwise disclosed to the BUYER in writing
were in the first phase thereof or Village 1, in the Ayala plan on or before the Closing, the Company is not engaged in or a
which was formulated a year later, it was in the third phase, or party to, or to the best of the knowledge of the SELLERS,
Phase II-c. threatened with, any legal action or other proceedings before
Under the MOA, the Vasquez spouses made several express any court or administrative body, nor do the SELLERS know
warranties, as follows: or have reasonable grounds to know of any basis for any such
"3.1. The SELLERS shall deliver to the BUYER: action or proceeding or of any governmental investigation
xxx relative to the Company.
3.1.2. The true and complete list, certified by the Secretary 7.6.4 To the knowledge of the SELLERS, no default or breach
and Treasurer of the Company showing: exists in the due performance and observance by the
xxx Company of any term, covenant or condition of any
D. A list of all persons and/or entities with whom the Company instrument or agreement to which the company is a party or
has pending contracts, if any. by which it is bound, and no condition exists which, with
xxx notice or lapse of time or both, will constitute such default or
3.1.5. Audited financial statements of the Company as at breach."
Closing date. After the execution of the MOA, Ayala caused the suspension
4. Conditions Precedent of work on Village 1 of the Don Vicente Project. Ayala then
All obligations of the BUYER under this Agreement are received a letter from one Maximo Del Rosario of Lancer
subject to fulfillment prior to or at the Closing, of the following General Builder Corporation informing Ayala that he was
conditions: claiming the amount of P1,509,558.80 as the subcontractor of
4.1. The representations and warranties by the SELLERS G.P. Construction...
contained in this Agreement shall be true and correct at the G.P. Construction not being able to reach an amicable
time of Closing as though such representations and settlement with Lancer, on March 22, 1982, Lancer sued G.P.
warranties were made at such time; and Construction, Conduit and Ayala in the then Court of First
xxx Instance of Manila in Civil Case No. 82-8598. G.P.
6. Representation and Warranties by the SELLERS Construction in turn filed a cross-claim against Ayala. G.P.
The SELLERS jointly and severally represent and warrant to Construction and Lancer both tried to enjoin Ayala from
the BUYER that at the time of the execution of this Agreement undertaking the development of the property. The suit was
and at the Closing: terminated only on February 19, 1987, when it was dismissed
xxx with prejudice after Ayala paid both Lancer and GP
6.2.3. There are no actions, suits or proceedings pending, or Construction the total of P4,686,113.39.
to the knowledge of the SELLERS, threatened against or Taking the position that Ayala was obligated to sell the 4 lots
affecting the SELLERS with respect to the Shares or the adjacent to the "Retained Area" within 3 years from the date
Property; and of the MOA, the Vasquez spouses sent several "reminder"
7. Additional Warranties by the SELLERS letters of the approaching so-called deadline. However, no
7.1. With respect to the Audited Financial Statements required demand after April 23, 1984, was ever made by the Vasquez
to be submitted at Closing in accordance with Par. 3.1.5 spouses for Ayala to sell the 4 lots. On the contrary, one of the
above, the SELLER jointly and severally warrant to the letters signed by their authorized agent, Engr. Eduardo Turla,
BUYER that: categorically stated that they expected "development of
7.1.1 The said Audited Financial Statements shall show that Phase 1 to be completed by February 19, 1990, three years
on the day of Closing, the Company shall own the "Remaining from the settlement of the legal problems with the previous
Property", free from all liens and encumbrances and that the contractor."
Company shall have no obligation to any party except for By early 1990 Ayala finished the development of the vicinity of
billings payable to GP Construction & Development the 4 lots to be offered for sale. The four lots were then
Corporation and advances made by Daniel Vazquez for which offered to be sold to the Vasquez spouses at the prevailing
BUYER shall be responsible in accordance with Par. 2 of this price in 1990. This was rejected by the Vasquez spouses who
Agreement. wanted to pay at 1984 prices, thereby leading to the suit
7.1.2 Except to the extent reflected or reserved in the Audited below.
Financial Statements of the Company as of Closing, and After trial, the court a quo rendered its decision, the
those disclosed to BUYER, the Company as of the date dispositive portion of which states:
thereof, has no liabilities of any nature whether accrued, "THEREFORE, judgment is hereby rendered in favor of
absolute, contingent or otherwise, including, without limitation, plaintiffs and against defendant, ordering defendant to sell to
plaintiffs the relevant lots described in the Complaint in the quoted is not an option contract but a right of first refusal there
Ayala Alabang Village at the price of P460.00 per square being no separate consideration therefor. Since petitioners
meter amounting to P1,349,540.00; ordering defendant to refused Ayala Corporation's offer to sell the subject lots at the
reimburse to plaintiffs attorney's fees in the sum of reduced 1990 price of P5,000.00 per square meter, they have
P200,000.00 and to pay the cost of the suit." effectively waived their right to buy the same.
In its decision, the court a quo concluded that the Vasquez In the instant Petition, petitioners allege that the appellate
spouses were not obligated to disclose the potential claims of court erred in ruling that they violated their warranties under
GP Construction, Lancer and Del Rosario; Ayala's the MOA; that Ayala Corporation was not obliged to develop
accountants should have opened the records of Conduit to the "Remaining Property" within three (3) years from the
find out all claims; the warranty against suit is with respect to execution of the MOA; that Ayala was not in delay; and that
"the shares of the Property" and the Lancer suit does not paragraph 5.15 of the MOA is a mere right of first refusal.
affect the shares of stock sold to Ayala; Ayala was obligated to Additionally, petitioners insist that the Court should review the
develop within 3 years; to say that Ayala was under no factual findings of the Court of Appeals as they are in conflict
obligation to follow a time frame was to put the Vasquezes at with those of the trial court.
Ayala's mercy; Ayala did not develop because of a slump in Ayala Corporation filed a Comment on the Petition8 dated
the real estate market; the MOA was drafted and prepared by March 26, 2002, contending that the petition raises questions
the AYALA who should suffer its ambiguities; the option to of fact and seeks a review of evidence which is within the
purchase the 4 lots is valid because it was supported by domain of the Court of Appeals. Ayala Corporation maintains
consideration as the option is incorporated in the MOA where that the subcontract between GP Construction, with whom
the parties had prestations to each other. [Emphasis supplied] Conduit contracted for the development of the property under
Ayala Corporation filed an appeal, alleging that the trial court a Construction Contract dated October 10, 1980, and Lancer
erred in holding that petitioners did not breach their warranties was not disclosed by petitioners during the negotiations.
under the MOA6 dated April 23, 1981; that it was obliged to Neither was the liability for Lancer's claim included in the
develop the land where the four (4) lots subject of the option Audited Financial Statements submitted by petitioners after
to purchase are located within three (3) years from the date of the signing of the MOA. These justify the conclusion that
the MOA; that it was in delay; and that the option to purchase petitioners breached their warranties under the afore-quoted
was valid because it was incorporated in the MOA and the paragraphs of the MOA. Since the Lancer suit ended only in
consideration therefor was the commitment by Ayala February 1989, the three (3)-year period within which Ayala
Corporation to petitioners embodied in the MOA. Corporation committed to develop the property should only be
As previously mentioned, the Court of Appeals reversed the counted thence. Thus, when it offered the subject lots to
RTC Decision. According to the appellate court, Ayala petitioners in 1990, Ayala Corporation was not yet in delay.
Corporation was never informed beforehand of the existence In response to petitioners' contention that there was no action
of the Lancer claim. In fact, Ayala Corporation got a copy of or proceeding against them at the time of the execution of the
the Lancer subcontract only on May 29, 1981 from G.P. MOA on April 23, 1981, Ayala Corporation avers that the facts
Construction's lawyers. The Court of Appeals thus held that and circumstances which gave rise to the Lancer claim were
petitioners violated their warranties under the MOA when they already extant then. Petitioners warranted that their
failed to disclose Lancer's claims. Hence, even conceding that representations under the MOA shall be true and correct at
Ayala Corporation was obliged to develop and sell the four (4) the time of "Closing" which shall take place within four (4)
lots in question within three (3) years from the date of the weeks from the signing of the MOA.9 Since the MOA was
MOA, the obligation was suspended during the pendency of signed on April 23, 1981, "Closing" was approximately the
the case filed by Lancer. third week of May 1981. Hence, Lancer's claims, articulated in
Interpreting the MOA's paragraph 5.7 above-quoted, the a letter which Ayala Corporation received on May 4, 1981, are
appellate court held that Ayala Corporation committed to among the liabilities warranted against under paragraph 7.1.2
develop the first phase of its own amended development plan of the MOA.
and not Conduit's development plan. Nowhere does the MOA Moreover, Ayala Corporation asserts that the warranties under
provide that Ayala Corporation shall follow Conduit's the MOA are not just against suits but against all kinds of
development plan nor is Ayala Corporation prohibited from liabilities not reflected in the Audited Financial Statements. It
changing the sequence of the phases of the property it will cannot be faulted for relying on the express warranty that
develop. except for billings payable to GP Construction and advances
Anent the question of delay, the Court of Appeals ruled that made by petitioner Daniel Vazquez in the amount of
there was no delay as petitioners never made a demand for P38,766.04, Conduit has no other liabilities. Hence,
Ayala Corporation to sell the subject lots to them. According to petitioners cannot claim that Ayala Corporation should have
the appellate court, what petitioners sent were mere reminder examined and investigated the Audited Financial Statements
letters the last of which was dated prior to April 23, 1984 when of Conduit and should now assume all its obligations and
the obligation was not yet demandable. At any rate, the Court liabilities including the Lancer suit and the cross-claim of GP
of Appeals found that petitioners in fact waived the three (3)- Construction.
year period when they sent a letter through their agent, Engr. Furthermore, Ayala Corporation did not make a commitment
Eduardo Turla, stating that they "expect that the development to complete the development of the first phase of the property
of Phase I will be completed by 19 February 1990, three years within three (3) years from the execution of the MOA. The
from the settlement of the legal problems with the previous provision refers to a mere declaration of intent to develop the
contractor."7 first phase of its (Ayala Corporation's) own development plan
The appellate court likewise ruled that paragraph 5.15 above- and not Conduit's. True to its intention, Ayala Corporation did
complete the development of the first phase (Phase II-A) of its 14, 2003 on February 17, 2003.
amended development plan within three (3) years from the We shall first dispose of the procedural question raised by the
execution of the MOA. However, it is not obliged to develop instant petition.
the third phase (Phase II-C) where the subject lots are located It is well-settled that the jurisdiction of this Court in cases
within the same time frame because there is no contractual brought to it from the Court of Appeals by way of petition for
stipulation in the MOA therefor. It is free to decide on its own review under Rule 45 is limited to reviewing or revising errors
the period for the development of Phase II-C. If petitioners of law imputed to it, its findings of fact being conclusive on this
wanted to impose the same three (3)-year timetable upon the Court as a matter of general principle. However, since in the
third phase of the amended development plan, they should instant case there is a conflict between the factual findings of
have filed a suit to fix the time table in accordance with Article the trial court and the appellate court, particularly as regards
119710 of the Civil Code. Having failed to do so, Ayala the issues of breach of warranty, obligation to develop and
Corporation cannot be declared to have been in delay. incurrence of delay, we have to consider the evidence on
Ayala Corporation further contends that no demand was record and resolve such factual issues as an exception to the
made on it for the performance of its alleged obligation. The general rule.15 In any event, the submitted issue relating to
letter dated October 4, 1983 sent when petitioners were the categorization of the right to purchase granted to
already aware of the Lancer suit did not demand the delivery petitioners under the MOA is legal in character.
of the subject lots by April 23, 1984. Instead, it requested The next issue that presents itself is whether petitioners
Ayala Corporation to keep petitioners posted on the status of breached their warranties under the MOA when they failed to
the case. Likewise, the letter dated March 4, 1984 was merely disclose the Lancer claim. The trial court declared they did
an inquiry as to the date when the development of Phase 1 not; the appellate court found otherwise.
will be completed. More importantly, their letter dated June 27, Ayala Corporation summarizes the clauses of the MOA which
1988 through Engr. Eduardo Turla expressed petitioners' petitioners allegedly breached when they failed to disclose the
expectation that Phase 1 will be completed by February 19, Lancer claim:
1990. a) Clause 7.1.1. – that Conduit shall not be obligated to
Lastly, Ayala Corporation maintains that paragraph 5.15 of the anyone except to GP Construction for P38,766.04, and for
MOA is a right of first refusal and not an option contract. advances made by Daniel Vazquez;
Petitioners filed their Reply11 dated August 15, 2002 b) Clause 7.1.2. – that except as reflected in the audited
reiterating the arguments in their Petition and contending financial statements Conduit had no other liabilities whether
further that they did not violate their warranties under the accrued, absolute, contingent or otherwise;
MOA because the case was filed by Lancer only on April 1, c) Clause 7.2. – that there is no basis for any assertion
1982, eleven (11) months and eight (8) days after the signing against Conduit of any liability of any value not reflected or
of the MOA on April 23, 1981. Ayala Corporation admitted that reserved in the financial statements, and those disclosed to
it received Lancer's claim before the "Closing" date. It Ayala;
therefore had all the time to rescind the MOA. Not having d) Clause 7.6.3. – that Conduit is not threatened with any
done so, it can be concluded that Ayala Corporation itself did legal action or other proceedings; and
not consider the matter a violation of petitioners' warranty. e) Clause 7.6.4. – that Conduit had not breached any term,
Moreover, petitioners submitted the Audited Financial condition, or covenant of any instrument or agreement to
Statements of Conduit and allowed an acquisition audit to be which it is a party or by which it is bound.16
conducted by Ayala Corporation. Thus, the latter bought The Court is convinced that petitioners did not violate the
Conduit with "open eyes." foregoing warranties.
Petitioners also maintain that they had no knowledge of the The exchanges of communication between the parties
impending case against Conduit at the time of the execution indicate that petitioners substantially apprised Ayala
of the MOA. Further, the MOA makes Ayala Corporation liable Corporation of the Lancer claim or the possibility thereof
for the payment of all billings of GP Construction. Since during the period of negotiations for the sale of Conduit.
Lancer's claim was actually a claim against GP Construction In a letter17 dated March 5, 1984, petitioner Daniel Vazquez
being its sub-contractor, it is Ayala Corporation and not reminded Ayala Corporation's Mr. Adolfo Duarte (Mr. Duarte)
petitioners which is liable. that prior to the completion of the sale of Conduit, Ayala
Likewise, petitioners aver that although Ayala Corporation Corporation asked for and was given information that GP
may change the sequence of its development plan, it is Construction sub-contracted, presumably to Lancer, a greater
obliged under the MOA to develop the entire area where the percentage of the project than it was allowed. Petitioners gave
subject lots are located in three (3) years. this information to Ayala Corporation because the latter
They also assert that demand was made on Ayala intimated a desire to "break the contract of Conduit with GP."
Corporation to comply with their obligation under the MOA. Ayala Corporation did not deny this. In fact, Mr. Duarte's
Apart from their reminder letters dated January 24, February letter18 dated March 6, 1984 indicates that Ayala Corporation
18 and March 5, 1984, they also sent a letter dated March 4, had knowledge of the Lancer subcontract prior to its
1984 which they claim is a categorical demand for Ayala acquisition of Conduit. Ayala Corporation even admitted that it
Corporation to comply with the provisions of the MOA. "tried to explore…legal basis to discontinue the contract of
The parties were required to submit their respective Conduit with GP" but found this "not feasible when information
memoranda in the Resolution12 dated November 18, 2002. In surfaced about the tacit consent of Conduit to the sub-
compliance with this directive, petitioners submitted their contracts of GP with Lancer."
Memorandum13 dated February 14, 2003 on even date, while At the latest, Ayala Corporation came to know of the Lancer
Ayala Corporation filed its Memorandum14 dated February claim before the date of Closing of the MOA. Lancer's
letter19 dated April 30, 1981 informing Ayala Corporation of its The billings knowingly assumed by Ayala Corporation
unsettled claim with GP Construction was received by Ayala necessarily include the Lancer claim for which GP
Corporation on May 4, 1981, well before the Construction is liable. Proof of this is Ayala Corporation's
"Closing"20 which occurred four (4) weeks after the date of letter23 to GP Construction dated before "Closing" on May 4,
signing of the MOA on April 23, 1981, or on May 23, 1981. 1981, informing the latter of Ayala Corporation's receipt of the
The full text of the pertinent clauses of the MOA quoted Lancer claim embodied in the letter dated April 30, 1981,
hereunder likewise indicate that certain matters pertaining to acknowledging that it is taking over the contractual
the liabilities of Conduit were disclosed by petitioners to Ayala responsibilities of Conduit, and requesting copies of all sub-
Corporation although the specifics thereof were no longer contracts affecting the Conduit property. The pertinent
included in the MOA: excerpts of the letter read:
7.1.1 The said Audited Financial Statements shall show that …
on the day of Closing, the Company shall own the "Remaining In this connection, we wish to inform you that this morning we
Property", free from all liens and encumbrances and that the received a letter from Mr. Maximo D. Del Rosario, President of
Company shall have no obligation to any party except for Lancer General Builders Corporation apprising us of the
billings payable to GP Construction & Development existence of subcontracts that they have with your
Corporation and advances made by Daniel Vazquez for which corporation. They have also furnished us with a copy of their
BUYER shall be responsible in accordance with Paragraph 2 letter to you dated 30 April 1981.
of this Agreement. Since we are taking over the contractual responsibilities of
7.1.2 Except to the extent reflected or reserved in the Audited Conduit Development, Inc., we believe that it is necessary, at
Financial Statements of the Company as of Closing, and this point in time, that you furnish us with copies of all your
those disclosed to BUYER, the Company as of the date subcontracts affecting the property of Conduit, not only with
hereof, has no liabilities of any nature whether accrued, Lancer General Builders Corporation, but all subcontracts with
absolute, contingent or otherwise, including, without limitation, other parties as well…24
tax liabilities due or to become due and whether incurred in Quite tellingly, Ayala Corporation even attached to its Pre-Trial
respect of or measured in respect of the Company's income Brief25 dated July 9, 1992 a copy of the letter26 dated May
prior to Closing or arising out of transactions or state of facts 28, 1981 of GP Construction's counsel addressed to Conduit
existing prior thereto. furnishing the latter with copies of all sub-contract agreements
7.2 SELLERS do not know or have no reasonable ground to entered into by GP Construction. Since it was addressed to
know of any basis for any assertion against the Company as Conduit, it can be presumed that it was the latter which gave
at Closing of any liability of any nature and in any amount not Ayala Corporation a copy of the letter thereby disclosing to
fully reflected or reserved against such Audited Financial the latter the existence of the Lancer sub-contract.
Statements referred to above, and those disclosed to BUYER. The ineluctable conclusion is that petitioners did not violate
xxx xxx xxx their warranties under the MOA. The Lancer sub-contract and
7.6.3 Except as otherwise disclosed to the BUYER in writing claim were substantially disclosed to Ayala Corporation before
on or before the Closing, the Company is not engaged in or a the "Closing" date of the MOA. Ayala Corporation cannot
party to, or to the best of the knowledge of the SELLERS, disavow knowledge of the claim.
threatened with, any legal action or other proceedings before Moreover, while in its correspondence with petitioners, Ayala
any court or administrative body, nor do the SELLERS know Corporation did mention the filing of the Lancer suit as an
or have reasonable grounds to know of any basis for any such obstacle to its development of the property, it never actually
action or proceeding or of any governmental investigation brought up nor sought redress for petitioners' alleged breach
relative to the Company. of warranty for failure to disclose the Lancer claim until it filed
7.6.4 To the knowledge of the SELLERS, no default or breach its Answer27 dated February 17, 1992.
exists in the due performance and observance by the We now come to the correct interpretation of paragraph 5.7 of
Company of any term, covenant or condition of any the MOA. Does this paragraph express a commitment or a
instrument or agreement to which the Company is a party or mere intent on the part of Ayala Corporation to develop the
by which it is bound, and no condition exists which, with property within three (3) years from date thereof? Paragraph
notice or lapse of time or both, will constitute such default or 5.7 provides:
breach."21 [Emphasis supplied] 5.7. The BUYER hereby commits that it will develop the
Hence, petitioners' warranty that Conduit is not engaged in, a 'Remaining Property' into a first class residential subdivision
party to, or threatened with any legal action or proceeding is of the same class as its New Alabang Subdivision, and that it
qualified by Ayala Corporation's actual knowledge of the intends to complete the first phase under its amended
Lancer claim which was disclosed to Ayala Corporation before development plan within three (3) years from the date of this
the "Closing." Agreement….28
At any rate, Ayala Corporation bound itself to pay all billings Notably, while the first phrase of the paragraph uses the word
payable to GP Construction and the advances made by "commits" in reference to the development of the "Remaining
petitioner Daniel Vazquez. Specifically, under paragraph 2 of Property" into a first class residential subdivision, the second
the MOA referred to in paragraph 7.1.1, Ayala Corporation phrase uses the word "intends" in relation to the development
undertook responsibility "for the payment of all billings of the of the first phase of the property within three (3) years from
contractor GP Construction & Development Corporation after the date of the MOA. The variance in wording is significant.
the first billing and any payments made by the company While "commit"29 connotes a pledge to do something,
and/or SELLERS shall be reimbursed by BUYER on closing "intend"30 merely signifies a design or proposition.
which advances to date is P1,159,012.87."22 Atty. Leopoldo Francisco, former Vice President of Ayala
Corporation's legal division who assisted in drafting the MOA, was no parallel commitment made as to the timeframe for the
testified: development of the third phase where the subject lots are
COURT located.
You only ask what do you mean by that intent. Just answer on Lest it be forgotten, the point of this petition is the alleged
that point. failure of Ayala Corporation to offer the subject lots for sale to
ATTY. BLANCO petitioners within three (3) years from the execution of the
Don't talk about standard. MOA. It is not that Ayala Corporation committed or intended to
WITNESS develop the first phase of its amended development plan
A Well, the word intent here, your Honor, was used to within three (3) years. Whether it did or did not is actually
emphasize the tentative character of the period of beside the point since the subject lots are not located in the
development because it will be noted that the sentence refers first phase anyway.
to and I quote "to complete the first phase under its amended We now come to the issue of default or delay in the fulfillment
development plan within three (3) years from the date of this of the obligation.
agreement, at the time of the execution of this agreement, Article 1169 of the Civil Code provides:
your Honor." That amended development plan was not yet in Art. 1169. Those obliged to deliver or to do something incur in
existence because the buyer had manifested to the seller that delay from the time the obligee judicially or extrajudicially
the buyer could amend the subdivision plan originally demands from them the fulfillment of their obligation.
belonging to the seller to conform with its own standard of However, the demand by the creditor shall not be necessary
development and second, your Honor, (interrupted)31 in order that delay may exist:
It is thus unmistakable that this paragraph merely expresses (1) When the obligation or the law expressly so declares; or
an intention on Ayala Corporation's part to complete the first (2) When from the nature and the circumstances of the
phase under its amended development plan within three (3) obligation it appears that the designation of the time when the
years from the execution of the MOA. Indeed, this paragraph thing is to be delivered or the service is to be rendered was a
is so plainly worded that to misunderstand its import is controlling motive for the establishment of the contract; or
deplorable. (3) When demand would be useless, as when the obligor has
More focal to the resolution of the instant case is paragraph rendered it beyond his power to perform.
5.7's clear reference to the first phase of Ayala Corporation's In reciprocal obligations, neither party incurs in delay if the
amended development plan as the subject of the three (3)- other does not comply or is not ready to comply in a proper
year intended timeframe for development. Even petitioner manner with what is incumbent upon him. From the moment
Daniel Vazquez admitted on cross-examination that the one of the parties fulfills his obligation, delay by the other
paragraph refers not to Conduit's but to Ayala Corporation's begins.
development plan which was yet to be formulated when the In order that the debtor may be in default it is necessary that
MOA was executed: the following requisites be present: (1) that the obligation be
Q: Now, turning to Section 5.7 of this Memorandum of demandable and already liquidated; (2) that the debtor delays
Agreement, it is stated as follows: "The Buyer hereby commits performance; and (3) that the creditor requires the
that to develop the remaining property into a first class performance judicially or extrajudicially.33
residential subdivision of the same class as New Alabang Under Article 1193 of the Civil Code, obligations for whose
Subdivision, and that they intend to complete the first phase fulfillment a day certain has been fixed shall be demandable
under its amended development plan within three years from only when that day comes. However, no such day certain was
the date of this agreement." fixed in the MOA. Petitioners, therefore, cannot demand
Now, my question to you, Dr. Vasquez is that there is no performance after the three (3) year period fixed by the MOA
dispute that the amended development plan here is the for the development of the first phase of the property since
amended development plan of Ayala? this is not the same period contemplated for the development
A: Yes, sir. of the subject lots. Since the MOA does not specify a period
Q: In other words, it is not Exhibit "D-5" which is the original for the development of the subject lots, petitioners should
plan of Conduit? have petitioned the court to fix the period in accordance with
A: No, it is not. Article 119734 of the Civil Code. As no such action was filed
Q: This Exhibit "D-5" was the plan that was being followed by by petitioners, their complaint for specific performance was
GP Construction in 1981? premature, the obligation not being demandable at that point.
A: Yes, sir. Accordingly, Ayala Corporation cannot likewise be said to
Q: And point of fact during your direct examination as of the have delayed performance of the obligation.
date of the agreement, this amended development plan was Even assuming that the MOA imposes an obligation on Ayala
still to be formulated by Ayala? Corporation to develop the subject lots within three (3) years
A: Yes, sir.32 from date thereof, Ayala Corporation could still not be held to
As correctly held by the appellate court, this admission is have been in delay since no demand was made by petitioners
crucial because while the subject lots to be sold to petitioners for the performance of its obligation.
were in the first phase of the Conduit development plan, they As found by the appellate court, petitioners' letters which dealt
were in the third or last phase of the Ayala Corporation with the three (3)-year timetable were all dated prior to April
development plan. Hence, even assuming that paragraph 5.7 23, 1984, the date when the period was supposed to expire.
expresses a commitment on the part of Ayala Corporation to In other words, the letters were sent before the obligation
develop the first phase of its amended development plan could become legally demandable. Moreover, the letters were
within three (3) years from the execution of the MOA, there mere reminders and not categorical demands to perform.
More importantly, petitioners waived the three (3)-year period In this regard, we would like to remind you of Articles 5.7 and
as evidenced by their agent, Engr. Eduardo Turla's letter to 5.9 of our Memorandum of Agreement which states
the effect that petitioners agreed that the three (3)-year period respectively:…39
should be counted from the termination of the case filed by Even petitioner Daniel Vazquez' letter40 dated March 5, 1984
Lancer. The letter reads in part: does not make out a categorical demand for Ayala
I. Completion of Phase I Corporation to offer the subject lots for sale on or before April
As per the memorandum of Agreement also dated April 23, 23, 1984. The letter reads in part:
1981, it was undertaken by your goodselves to complete the …and that we expect from your goodselves compliance with
development of Phase I within three (3) years. Dr. & Mrs. our Memorandum of Agreement, and a definite date as to
Vazquez were made to understand that you were unable to when the road to our property and the development of Phase I
accomplish this because of legal problems with the previous will be completed.41
contractor. These legal problems were resolved as of At best, petitioners' letters can only be construed as mere
February 19, 1987, and Dr. & Mrs. Vazquez therefore expect reminders which cannot be considered demands for
that the development of Phase I will be completed by performance because it must appear that the tolerance or
February 19, 1990, three years from the settlement of the benevolence of the creditor must have ended.42
legal problems with the previous contractor. The reason for The petition finally asks us to determine whether paragraph
this is, as you know, that security-wise, Dr. & Mrs. Vazquez 5.15 of the MOA can properly be construed as an option
have been advised not to construct their residence till the contract or a right of first refusal. Paragraph 5.15 states:
surrounding area (which is Phase I) is developed and 5.15 The BUYER agrees to give the SELLERS first option to
occupied. They have been anxious to build their residence for purchase four developed lots next to the "Retained Area" at
quite some time now, and would like to receive assurance the prevailing market price at the time of the purchase.43
from your goodselves regarding this, in compliance with the The Court has clearly distinguished between an option
agreement. contract and a right of first refusal. An option is a preparatory
II. Option on the adjoining lots contract in which one party grants to another, for a fixed
We have already written your goodselves regarding the period and at a determined price, the privilege to buy or sell,
intention of Dr. & Mrs. Vazquez to exercise their option to or to decide whether or not to enter into a principal contract. It
purchase the two lots on each side (a total of 4 lots) adjacent binds the party who has given the option not to enter into the
to their "Retained Area". They are concerned that although principal contract with any other person during the period
over a year has elapsed since the settlement of the legal designated, and within that period, to enter into such contract
problems, you have not presented them with the size, with the one to whom the option was granted, if the latter
configuration, etc. of these lots. They would appreciate being should decide to use the option. It is a separate and distinct
provided with these at your earliest convenience.35 contract from that which the parties may enter into upon the
Manifestly, this letter expresses not only petitioners' consummation of the option. It must be supported by
acknowledgement that the delay in the development of Phase consideration.44
I was due to the legal problems with GP Construction, but In a right of first refusal, on the other hand, while the object
also their acquiescence to the completion of the development might be made determinate, the exercise of the right would be
of Phase I at the much later date of February 19, 1990. More dependent not only on the grantor's eventual intention to enter
importantly, by no stretch of semantic interpretation can it be into a binding juridical relation with another but also on terms,
construed as a categorical demand on Ayala Corporation to including the price, that are yet to be firmed up.45
offer the subject lots for sale to petitioners as the letter merely Applied to the instant case, paragraph 5.15 is obviously a
articulates petitioners' desire to exercise their option to mere right of first refusal and not an option contract. Although
purchase the subject lots and concern over the fact that they the paragraph has a definite object, i.e., the sale of subject
have not been provided with the specifications of these lots. lots, the period within which they will be offered for sale to
The letters of petitioners' children, Juan Miguel and Victoria petitioners and, necessarily, the price for which the subject
Vazquez, dated January 23, 198436 and February 18, lots will be sold are not specified. The phrase "at the
198437 can also not be considered categorical demands on prevailing market price at the time of the purchase" connotes
Ayala Corporation to develop the first phase of the property that there is no definite period within which Ayala Corporation
within the three (3)-year period much less to offer the subject is bound to reserve the subject lots for petitioners to exercise
lots for sale to petitioners. The letter dated January 23, 1984 their privilege to purchase. Neither is there a fixed or
reads in part: determinable price at which the subject lots will be offered for
You will understand our interest in the completion of the roads sale. The price is considered certain if it may be determined
to our property, since we cannot develop it till you have with reference to another thing certain or if the determination
constructed the same. Allow us to remind you of our thereof is left to the judgment of a specified person or
Memorandum of Agreement, as per which you committed to persons.46
develop the roads to our property "as per the original plans of Further, paragraph 5.15 was inserted into the MOA to give
the company", and that petitioners the first crack to buy the subject lots at the price
1. The back portion should have been developed before the which Ayala Corporation would be willing to accept when it
front portion – which has not been the case. offers the subject lots for sale. It is not supported by an
2. The whole project – front and back portions be completed independent consideration. As such it is not governed by
by 1984.38 Articles 1324 and 1479 of the Civil Code, viz:
The letter dated February 18, 1984 is similarly worded. It Art. 1324. When the offeror has allowed the offeree a certain
states: period to accept, the offer may be withdrawn at any time
before acceptance by communicating such withdrawal, except and store room for automobile spare parts;
when the option is founded upon a consideration, as (b) Another building of strong materials for automobile repair
something paid or promised. shop; and
Art. 1479. A promise to buy and sell a determinate thing for a (c) A 5-bedroom house of strong materials for residence of the
price certain is reciprocally demandable. Bacolod Branch Manager of the defendant company.
An accepted unilateral promise to buy or to sell a determinate The term of the lease was five (5) years, to commence from
thing for a price certain is binding upon the promissor if the the time that the building were delivered and placed at the
promise is supported by a consideration distinct from the disposal of the lessee company, ready for immediate
price. occupancy. The contract was renewable for an additional
Consequently, the "offer" may be withdrawn anytime by period of five (5) years. The Manila Motor Company, in
communicating the withdrawal to the other party.47 consideration of the above covenants, agreed to pay to the
In this case, Ayala Corporation offered the subject lots for sale lessors, or their duly authorized representative, a monthly
to petitioners at the price of P6,500.00/square meter, the rental of Three Hundred (P300) pesos payable in advance
prevailing market price for the property when the offer was before the fifth day of each month, and for the residential
made on June 18, 1990.48 Insisting on paying for the lots at house of its branch manager, a monthly rental not to exceed
the prevailing market price in 1984 of P460.00/square meter, Fifty (P50) pesos "payable separately by the Manager".
petitioners rejected the offer. Ayala Corporation reduced the The leased premises were placed in the possession of the
price to P5,000.00/square meter but again, petitioners lessee on the 31st day of October, 1940, from which date, the
rejected the offer and instead made a counter-offer in the period of the lease started to run under their agreement.
amount of P2,000.00/square meter.49 Ayala Corporation This situation, the Manila Motor Co., Inc. and its branch
rejected petitioners' counter-offer. With this rejection, manager enjoying the premises, and the lessors receiving the
petitioners lost their right to purchase the subject lots. corresponding rentals as stipulated, continued until the
It cannot, therefore, be said that Ayala Corporation breached invasion of 1941; and shortly after the Japanese military
petitioners' right of first refusal and should be compelled by an occupation of the Provincial Capital of Bacolod the enemy
action for specific performance to sell the subject lots to forces held and used the properties leased as part of their
petitioners at the prevailing market price in 1984. quarters from June 1, 1942 to March 29, 1945, ousting the
WHEREFORE, the instant petition is DENIED. No lessee therefrom. No payment of rentals were made at any
pronouncement as to costs. time during the said period.
SO ORDERED. Immediately upon the liberation of the said city in 1945, the
American Forces occupied the same buildings that were
G.R. No. L-10394           December 13, 1958 vacated by the Japanese, including those leased by the
CLAUDINA VDA. DE VILLARUEL, ET AL., plaintiffs- plaintiffs, until October 31, 1945. Monthly rentals were paid by
appellees, the said occupants to the owners during the time that they
vs. were in possession, as the same rate that the defendant
MANILA MOTOR CO., INC. and ARTURO company used to pay.
COLMENARES, defendants-appellants. Thereafter, when the United States Army finally gave up the
Hilado and Hilado for appellees. occupancy the premises, the Manila Motor Co., Inc., through
Ozaeta, Gibbs and Ozaeta for appellant company. their branch manager, Rafael B. Grey, decided to exercise
Jose L. Gamboa and Napoleon Garcia for appellant Arturo their option to renew the contract for the additional period of
Colmenares. five (5) years, and the parties, agreed that the seven months
occupancy by the U. S. Army would not be counted as part of
the new 5-year term. Simultaneously with such renewal, the
REYES, J. B. L., J.: company sublet the same buildings, except that used for the
Manila Motor Co., Inc., and Arturo Colmenares interpose this residence of the branch manager, to the other defendant,
appeal against the decision of the Court of First Instance of Arturo Colmenares.
Negros Occidental, in its Civil Case No. 648, ordering the However, before resuming the collection of rentals, Dr. Alfredo
defendant Manila Motor Co., Inc. to pay to the plaintiffs Villaruel, who was entrusted with the same, consulted Atty.
Villaruel the sum of (a) P11,900 with legal rest from May 18, Luis Hilado on whether they (the lessors) had the right to
1953, on which date, the court below declared invalid the collect, from the defendant company, rentals corresponding to
continued operation of the Debt Moratorium, under the first the time during which the Japanese military forces had control
cause of action; (b) P38,395 with legal interest from the date over the leased premises. Upon being advised that they had
of filing of the original complaint on April 26, 1947, on the such a right, Dr. Villaruel demanded payment thereof, but the
second cause of action; and against both the Manila Motor defendant company refused to pay. As a result, Dr. Villaruel
Co., Inc. and its co-defendant, Arturo Colmenares, the sum of gave notice seeking the rescission of the contract of lease
P30,000 to be paid, jointly and severally, with respect to the and the payment of rentals from June 1, 1942 to March 31,
third cause of action. 1945 totalling P11,900. This was also rejected by the
On May 31, 1940, the plaintiffs Villaruel and the defendant defendant company in its letter to Villaruel, dated July 27,
Manila Motor Co., Inc. entered into a contract (Exhibit "A") 1946.
whereby, the former agreed to convey by way of lease to the Sometime on that same month of July, Rafael B. Grey offered
latter the following described premises; to pay to Dr. Villaruel the sum of P350, for which, tenderer
(a) Five hundred (500) square meters of floor space of a requested a receipt that would state that it was in full payment
building of strong materials for automobile showroom, offices, for the said month. The latter expressed willingness to accept
the tendered amount provided, however, that his acceptance sustained under the circumstances. This action was
should be understood to be without prejudice to their demand inceptionally instituted for the rescission of the contract of
for the rescission of the contract, and for increased rentals lease and for the recovery of unpaid rentals before and after
until their buildings were returned to them. Later, Dr. Villaruel liberation. When the leased buildings were destroyed, the
indicated his willingness to limit the condition of his plaintiffs-lessors demanded from the defendants-lessees,
acceptance to be that "neither the lessee nor the lessors instead, the value of the burned premises, basing their right to
admit the contention of the other by the mere fact of do so on defendants' alleged default in the payment of post-
payment". As no accord could still be reached between the liberation rentals (which was also their basis in formerly
parties as to the context of the receipt, no payment was seeking for rescission). This cannot be considered as already
thereafter tendered until the end of November, 1946. On altering the theory of the case which is merely a change in the
December 4, 1946 (the day after the defendant company relief prayed for, brought about by circumstances occurring
notified Dr. Villaruel by telegram, that it cancelled the power of during the pendency of the action, and is not improper.
attorney given to Grey, and that it now authorized Arturo (Southern Pacific Co. vs. Conway, 115 F. 2d 746; Suburban
Colmenares, instead, to pay the rent of P350 each month), Improvement Company vs. Scott Lumber Co., 87 A.L.R. 555,
the Manila Motor Co., Inc. remitted to Dr. Villaruel by letter, 59 F. 2d 711). The filing of the supplements complaint can
the sum of P350.00. For this payment, the latter issued a well be justified also under section 2, Rule 17 of the Rules of
receipt stating that it was "without prejudice" to their demand Court (on amendments) "to the end that the real matter in
for rents in arrears and for the rescission of the contract of dispute and all matters in the action in dispute between the
lease. parties may, as far as possible be completely determined in a
After it had become evident that the parties could not settle single proceedings". It is to be noted furthermore, that the
their case amicably, the lessors commenced this action on admission or rejection of this kind of pleadings is within the
April 26, 1947 with the Court of First Instance of Negros sound discretion of the court that will not be disturbed on
Occidental against the appellants herein. During the appeal in the absence of abuse thereof (see Sec. 5, Rule 17,
pendency of the case, a fire originating from the projection Rules of Court), especially so, as in this case, where no
room of the City Theatre, into which Arturo Colmenares, (the substantial procedural prejudice is caused to the adverse
sublessee) had converted the former repair shop of the party.
Manila Motor Co. Inc., completely razed the building, It is urged that the dismissal of the first and second causes of
engulfing also the main building where Colmenares had action on February 5, 1951 had the effect of a dismissal "with
opened a soda fountain and refreshment parlor, and made prejudice" as the court did not make any qualification in its
partitions for store spaces which he rented to other persons. dismissal order. Appellants, apparently, lost sight of the fact
Because of the aforesaid occurrence, plaintiffs demanded that the dismissal was premised on the existence of the "Debt
reimbursement from the defendants, but having been refused, Moratorium" which suspended the enforcement of the
they filed a supplemental complaint to include as their third obligation up to a certain time. The reference thereto by the
cause of action, the recovery of the value of the burned lower court amounted to a dismissal "without prejudice", since
buildings. in effect it ruled that the plaintiffs could not, at the time they
Defendants filed their amended answer and also moved for sought it, enforce their right of action against the defendants,
the dismissal of the plaintiffs' first and second causes of action but plaintiffs must wait until the moratorium was lifted. In this
invoking the Debt Moratorium that was then in force. The way, the court qualified its dismissal.
dismissal was granted by the trial court on February 5, 1951, Taking up the case on its merits, it is readily seen that the key
but hearing was set as regards the third cause of action. to the entire dispute is the question whether the defendant-
On August 11, 1952, the defendant company filed a motion for appellant Manila Motor Co., Inc. should be held liable for the
summary judgment dismissing the plaintiffs, third cause of rentals of the premises leased corresponding to the lapse of
action, to which plaintiffs registered objection coupled with a time that they were occupied as quarters or barracks by the
petition for reconsideration of the order of the court dismissing invading Japanese army, and whether said appellant was
the first and second causes of action. Pending the resolution placed in default by its refusal to comply with the demand to
of this incident, plaintiffs, on October 2, 1953, called the pay such rents. For if the Motor Company was not so liable,
court's attention to the decision in the case of Rutter vs. then it never was in default nor was it chargeable for the
Esteban (93 Phil., 68; 49 Off. Gaz. [5] 1807) invalidating the accidental lose of the buildings, nor for any damages except
continued effectivity of the Moratorium Law (R. A. 342). On the rental at the contract rate from its reoccupation of the
November 25, 1953, the trial court denied the defendant premises leased until the same were accidentally destroyed
company's motion for summary judgment and set aside its by fire on March 2, 1948.
previous order dismissing the first and second causes of The appellees contended, and the court below has held, that
action. The case was accordingly heard and thereafter, the ouster of the least company by the Japanese occupation
judgment was rendered in plaintiffs' favor in the terms set in forces from 1942 until liberation, while operating to deprive
the opening paragraph of this decision. Thereafter, the the lessee of the enjoyment of the thing leased, was,
defendants regularly appealed to this Court. nevertheless, a mere act of trespass ("perturbacion de mero
The defendants-appellants raise a number of procedural hecho") that, under the Spanish Civil Code of 1889 (in force
points. The first of these relates to their contention that the here until 1950), did not exempt the lessee from the duty to
supplemental complaint which included a third cause of pay rent. We find that contention and ruling erroneous and
action, should not have been admitted, as it brought about a untenable.
change in the original theory of the case and that it raised new The pertinent articles of the Civil Code of Spain of 1889
issues not theretofore considered. This argument cannot be provide:
ART. 1554. It shall be the duty of the lessor; No. 324) to the effect that —
1. To deliver to the lessee the thing which is the subject matter The measure of permissible devastation is found in the strict
of the contract; necessities of war. As an end in itself, as a separate measure
2. To make thereon, during the lease, all repairs necessary in of war, devastation is not sanctioned by the law of war. There
order to keep it in serviceable condition for the purpose for must be some reasonably close connection between the
which it was intended; destruction of property and the overcoming of the enemy's
3. To maintain the lessee in the peaceful enjoyment of the army. Thus the rule requiring respect for private property is
lease during the entire term of the contract. not violated through damage resulting from operations,
ART. 1560. The lessor shall not be liable for any act of mere movements, or combats of the army; that is, real estate may
disturbance of a third person of the use of the leased be utilized for marches, camp sites, construction of trenches,
property; but the lessee shall have a direct action against the etc. Buildings may be used for shelter for troops, the sick and
trespasser. wounded, for animals, for reconnaissance, cover defense, etc.
It the third person, be it the Government or a private Fence, woods, crops, buildings, etc., may be demolished, cut
individual, has acted in reliance upon a right, such action shall down, and removed to clear a field of fire, to construct
not be deemed a mere act of disturbance. (Emphasis bridges, to furnish fuel if imperatively needed for the army.
supplied) (Emphasis supplied)
Under the first paragraph of article 1560 the lessor does not Reference may also be made to Rule 336:
answer for a mere act of trespass ( perturbacion de mero What may be requisitioned. — Practically everything may be
hecho) as distinguished from trespass under color of title requisitioned under this article (art. LII of the regulations
( perturbacion de derecho). As to what would constitute a above quoted) that is necessary for the maintenance of the
mere act of trespass, this Court in the case of Goldstein vs. army and not of direct military use, such as fuel, food, forage,
Roces (34 Phil. 562), made this pronouncement: clothing, tobacco, printing presses, type, leather, cloth,
Si el hecho perturbador no va acompañado ni precedido de etc. Billeting of troops for quarters and subsistence is also
nada que revele una intencion propiamente juridica en el que authorized. (Emphasis supplied)
lo realiza, de tal suerte que el arrendatario solo pueda And Forest and Tucker state:
apreciar el hecho material desnudo de toda forma o The billegerent occupant may destroy or appropriate public
motivacion de derecho, entendemos que se trata de una property which may have a hostile purpose, as forts, arms,
perturbacion de mero hecho. armories, etc. The occupying force may enjoy the income
Upon the basis of the distinction thus established between from the public sources. Strictly private property should be
the  perturbacion de hecho and the  perturbacion de derecho, inviolable, except so far as the necessity of war requires
it is demonstrable that the ouster of the appellant by the contrary action. (Forest and Tucker, International Law, 9th
Japanese occupying forces belongs to the second class of Ed., p. 277) (Emphasis supplied)
disturbances, de derecho. For under the generally accepted The distinction between confiscation and temporary
principles of international law (and it must be remembered sequestration of private property by a belligerent occupant
that those principles are made by our Constitution a part of was also passed upon by this Court in Haw Pia vs. China
the law of our nation 1) a belligerent occupant (like the Banking Corporation, 80 Phil. 604, wherein the right of Japan
Japanese in 1942-1945) may legitimately billet or quarter its to sequester or take temporary control over enemy private
troops in privately owned land and buildings for the duration of property in the interest of its military effort was expressly
its military operations, or as military necessity should demand. recognized.
The well known writer Oppenheim, discoursing on the laws of We are thus forced to conclude that in evicting the lessee,
war on land, says upon this topic; Manila Motor Co., Inc. from the leased buildings and
Immovable private enemy property may under no occupying the same as quarters for troops, the Japanese
circumstances or conditions be appropriated by an invading authorities acted pursuant to a right recognized by
belligerent. Should he confiscate and sell private land or international and domestic law. Its act of dispossession,
buildings, the buyer would acquire no right whatever to the therefore, did not constitute perturbacion de hecho but
property. Article 46 of the Hague Regulations expressly a  perturbacion de derecho  for which the lessors Villaruel (and
enacts that "private property may not be confiscated." But not the appellants lessees) were liable (Art. 1560, supra) and
confiscation differs from the temporary use of private land and for the consequences of which said lessors must respond,
building for all kinds of purposes demanded by the since the result of the disturbance was the deprivation of the
necessities of war. What has been said above with regard to lessee of the peaceful use and enjoyment of the property
utilization of public buildings applied equally to private leased. Wherefore, the latter's corresponding obligation to pay
buildings. If necessary, they maybe converted into hospital rentals ceased during such deprivation.
barracks, and stables without compensation for the The Supreme Court of Spain, in its Sentencia of 6 December
proprietors, and they may also be converted into fortifications. 1944, squarely declared the resolutory effect of the military
A humane belligerent will not drive the wretched inhabitants sequestration of properties under lease upon the lessee's
into the street if he can help it. But under the pressure of obligation to pay rent (Jurisprudencia Civil, Segunda Serie,
necessity he may be obliged to do this, and he is certainly not Tomo 8, pp. 583, 608):.
prohibited from doing it. (Emphasis supplied) (Oppenheim & Considerando que para resolver acerca de la procedencia del
Lauterpach, International Law, Vol. II, p. 312, 1944 Ed.) presente recurso es preciso partir de las bases de hecho
The view thus expressed is concurred in by other writers. sentadas en la sentencia recurrida, y no impugnadas al
Hyde (International Law, Vol. 3, p. 1893, 2nd Rev. Ed.) quotes amparo del numero 7. del articulo 1.692 de la Ley de
the U. S. War Department 1940 Rules of Land Warfare (Rule Enjuiciamiento civil, es decir, de que hallandose vigente el
contrato de arrendamiento celebrado entre actor y and court personnel, would face "severest penalties" for such
demandada, en fecha que no se precisa, entre los dias del 18 defiance of the invader.
al 31 de julio de 1936, los locales objeto de dicho contrato de The present case is distinguishable from Lo Ching vs.
arrendamiento, y en los que no funcionaba de tiempo anterior Archbishop of Manila (81 Phil., 601) in that the act of the
la industria para cuyo ejercicio se arrendaron, fueron Japanese military involved in the latter case clearly went
requisados por el Ejercito Nacional, con motivo de la guerra beyond the limits set by the Hague Conventions, in seizing
civil, para que se instalara en los mismos la Junta de the property and delivering it to another private party; and
Donativos al Ejercito del Sur, aun cundo en dicha incautacion, from Reyes vs. Caltex (Phil.) Inc., 84 Phil. 654, in that the
que se hizo a la propiedad de la finca, no se observaron las rights of the military occupant under international law were not
formalidades legales, a causa de las circunstancias raised or put in issue in said case; and moreover, the lessee
extraordinarias por que a la sazon atravesaba Sevilla, hecho there, by failing to rescind the lease upon seizure of the
que no consta se hiciera saber por los arrendatarios premises by the Japanese military, despite the stipulated
demandados al actor, pero que fue notorio en aquella capital, power to do so, resumed business and decided to hold unto
donde residia el actor, que de el debio tener conocimiento. Se the long term lease for the balance of its 20-year period,
estima igualmente por la Sala que el hecho de que la starting from December 23, 1940. In the case before us, the
industria no funcionara en el local no tuvo influencia alguna occupation of the leased property by the Japanese army
sobre su incautacion por el Ejercito. covered the major portion of the five-year contractual period,
Considerando que sobre tales bases de hecho es de without any option to rescind by the lessee.
desestimar el primer motivo del recurso: violacion de los The lessor's position is not improved by regarding the military
articulos 1.254, 1.278 y 1.091 del Codigo civil, que sancionan, seizure of the property under lease as a case of  force
en terminos generales, la eficacia de los contratos, puesto majeure or fortuitous event. Ordinarily, a party may not be
que en el presente caso de los que se trata en definitiva es de held responsible therefor, despite the fact that it prevented
determinar si por virtud de fuerza mayor, la requisa a que se compliance of its obligations. But lease being a contract that
hace referencia, ajena, por lo tanto, a culpa, asi del calls for prestations that are both reciprocal and repetitive
arrendatario como del arrendador, se vio aquel privado del (tractum successivum), the obligations of either party are not
posible disfrute de la finca arrendada, y de si por virtud de discharged at any given moment, but must be fulfilled all
esta circunstancia esta o no exento de la obligacion de throughout the term of the contract. As a result, any
abonar la renta pactada durante el tiempo que subsistio la substantial failure by one party to fulfill its commitments at any
incautacion; y es indudable la afirmativa en cuanto al primer time during the contract period gives rise to a failure of
extremo, puesto que la sentencia recurrida establece que el consideration (causa) for the obligations of the other party and
hecho de que no funcionase la industria y estuvieran los excuses the latter from the correlative performance, because
locales cerrados no actuo como causa de la requisa de estos the causa in lease must exist not only at the perfection but
por el Ejercito. throughout the term of the contract. No lessee would agree to
Considerando que la sentencia recurrida, en cuanto no da pay rent for premises he could not enjoy. As expressed by
lugar al pago de las rentas correspondientes al tiempo que Marcel Planiol (quoted in 4 Castan, Derecho Civil, 7th Edition,
duro la incautacion, lejos de infringir, por aplicacion indebida, p. 264) —
el art. 1.568 del Codigo civil, se ajusta la orientacion marcada Como la obligacion del arrendador es sucesiva y se renueva
en el mismo, puesto que este precepto legal dispone que el todos los dias, la subsistencia del arrendamiento se hace
arrendatario tiene accion contra el tercero perturbador de imposible cuando, por cualquier razon, el arrendador no
mero hecho en la posesion de la finca arrendada, pero no puede ya procurar al arrendatario el disfrute de la cosa.
contra la Administracion o contra los que obran en virtud de This effect of the failure of reciprocity appears whether the
un derecho que les corresponde; y aqui la perturbacion que failure is due to fault or to fortuitous event; the only difference
experimento el arrendador en su posesion, como being that in case of fault, the other party is entitled to rescind
consecuencia de la requisa, no puede calificarse como de the contract in toto, and collect damages, while in casual non-
mero hecho, conforme al citado articulo, puesto que la finca performance it becomes entitled only to a suspension pro
fue requisada por la autoridad militar para fines de guerra, de tanto of its own commitments. This rule is recognized in par. 2
donde se sigue que el arrendatario tenia que soportar la of Art. 1558, authorizing the lessee to demand reduction of
privacion de su tenencia material a traves del arrendador, con the rent in case of repairs depriving him of the possession of
quien ha de entenderse la requisa de la cosa arrendada. part of the property; and in Art. 1575, enabling the lessee of
In addition, the text of Art. 1560, in its first paragraph ( jam rural property to demand reduction of the rent if more than
quot.) assumes that in case of mere disturbance one-half of the fruits are lost by extraordinary fortuitous event.
( perturbacion de mero hecho) "the lessee shall have a direct Of course, where it becomes immediately apparent that the
action against the trespasser." This assumption evidently loss of possession or enjoyment will be permanent, as in the
does not contemplate the case of dispossession of the lessee case of accidental destruction of a leased building, the lease
by a military occupant, as pointed out by Mr. Chief Justice contract terminates.
Paras in his dissenting opinion in Reyes vs. Caltex (Phil.) Inc., Applying these principles, the Sentencia of December 1944,
84 Phil. 669; for the reason that the lessee could not have a already adverted to, ruled as follows:
direct action against the military occupant. It would be most Considerando que privado el arrendador, por tal hecho, del
unrealistic to expect that the occupation courts, place under disfrute de esta, es manifiesta la imposibilidad en que se vio
the authority of the occupying belligerent, should entertain at de cumplir la tercera de las obligaciones que el impone el
the time a suit for forcible entry against the Japanese army. articulo 1.554 del Codigo Civil, obligacion (la de mantener al
The plaintiffs, their lawyers, and in all probability, the Judge arrendatario en el disfrute de la cosa arrendada) que ha de
entenderse reciproca de la de pago de renta pactada, que It is accordingly laid down in the Pandects, on the authority of
impone al arrendatario el numero primero del art. 1.555 de Julian, "If anyone has let an estate, that, even if anything
dicho Cuerpo legal, y por ello no puede ser exigida. happens by vis major, he must make it good, he must stand
Considerando que, aunque no sean estrictamente aplicables by his contract," si quis fundum locaverit, ut, etiamsi quid vi
al caso los articulos 1.124, 1.556 y 1.568, que se citan como majore accidisset, hoc ei praestaretur, pacto standum esse;
infringidos por el recurrente, suponiendo que a ellos ha Dig. 19, 2, 9, 2; and on the authority of Ulpian, that "A lease
entendido referirse la Audiencia (lo que impediria, en todo does not change the ownership," non solet locatio dominiun
caso, la estimacion del recurso por este motivo, ya que mutare; Dig. 19, 2, 39; and that the lessee has a right of
dichos articulos no se citan en la sentencia de instancia), es action, if he cannot enjoy the thing which he has hired, si re
evidente que ellos proclaman la reciprocidad de las quam conduxit frui non liceat, whether because his
obligaciones entre arrendatario y arrendador, y en este possession, either of the whole or of part of the field, is not
sentido, tratandose de un incumplimiento inculpable made good, or a house, or stable or sheepfold, is not
decontrato, pueden servir, como tambien el 1.558, en cuanto repaired; and the landlord ought to warrant the tenant,
preven la reduccion de rentas o posible restriccion del dominum colono praestare debere, against every irresistible
contrato cuando el arrendatario se ve privado, por obras force, omnim vim cui resisti non potest, such as floods, flocks
realizadas en la finca arrendada, del disfrute de este, de of birds, or any like cause, or invasion of enemies; and if the
fundamento, con los demas preceptos invocados, a una whole crop should be destroyed by a heavy rainfall, or the
extencion de renta mientras subsiste la imposibilidad de olives should be spoiled by blight, or by extraordinary heat of
utilizar la cosa arrendada, sobre todo cuando los articulos 157 the sun, solis fervore non assueto, it would be the loss of the
y 158 del Reglamento de Requisas de 13 de enero de 1921 landlord, damnum domini futurum; and so if the field falls in by
estatuyen claramente que las requisas de edificio se hacen a an earthquake, for there must be made good to the tenant a
la propiedad, y es el propietario el que puede pedir field that he can enjoy, oportere enim agrum praestari
indemnization, uno de cuyos elementos es el precio del conductori, ut frui possit; but if any loss arises from defects in
alquiler que le sea satisfecho por el inmueble incautado. the thing itself, si qua tamen vitia ex ipsa re oriantur, as if wine
We are aware that the rule in the common law is otherwise, turns sour, or standing corn is spoiled by worms or weeds, or
due to its regarding a lease as a conveyance to the lessee of if nothing extraordinary happens, si vero nihil extra
a temporary estate or title to the leased property so that loss consuetudinem acciderit, it is the loss of the tenant, damnum
of possession due to war or other fortuitous event leaves the coloni esse. Dig. 19, 2; 15, 1, 2. (Emphasis supplied)
tenant liable for the rent in the absence of stipulation. The In short, the law applies to leases the rule enunciated by the
fundamental difference between the common law and the civil Canonists and the Bartolist School of Post glossatorse, that
law concepts has been outlined by the United States "contractus qui tractum successivum habent et dependentiam
in Viterbo vs. Friedlander, 30 L. Ed. (U.S.) pp. 776, 778, in de futuro, sub conditione rebus sic stantibus intelliguntur,"
this wise: they are understood entered subject to the condition that
But as to the nature and effect of a lease for years, at a things will remain as they are, without material change.
certain rent which the lessee agrees to pay, and containing no It is also worthy of note that the lessors, through Dr. Javier
express covenant on the part of the lessor, the two systems Villaruel, agreed after liberation to a renewal of the contract of
differ materially. The common law regards such a lease as the lease for another five years (from June 1, 1946 to May 31 of
grant of an estate for years, which the lessee takes a title in, 1951) without making any reservation regarding the alleged
and is bound to pay the stipulated rent for, notwithstanding liability of the lessee company for the rentals corresponding to
any injury by flood, fire or external violence, at least unless the period of occupancy of the premises by the Japanese
the injury is such a destruction of the land as to amount to an army, and without insisting that the non-payment of such
eviction; and by that law the lessor is under no implied rental was a breach of the contract of lease. This passivity of
covenant to repair, or even that the premises shall be fit for the lessors strongly supports the claim of the lessees that the
the purpose for which they are leased. Fowler vs. Bott, 6 rentals in question were verbally waived. The proffered
Mass. 63; 3 Kent, Com. 465, 466; Broom, Legal Maxims, 3d explanation is that the lessors could not refuse to renew the
ed. 213, 214; Doupe vs. Genin, 45 N. Y. 119; Kingbury vs. lease, because the privilege of renewal had been granted to
Westfall, 61 N. Y. 356. Naumberg vs. Young, 15 Vroom, the lessees in the original contract. Such excuse is untenable:
331; Bowe vs. Hunking, 135 Mass. 380; Manchester if the lessors deemed that the contract had been breached by
Warehouse Co. vs. Carr, L.R. 5 C.P.D. 507. the lessee's non-payment of the occupation rents how could
The civil law, on the other hand, regards a lease for years as they admit the lessee's right to renew a contract that the
a mere transfer of the use and enjoyment of the property; and lessee itself had violated?
holds the landlord bound, without any express covenant, to But this is not all. The lessors accepted payment of current
keep it in repair and otherwise fit for use and enjoyment for rentals from October 1945 to June 1946. It was only in July
the purpose for which it is leased, even when the need of 1946 that they insisted upon collecting also the 1942-1945
repair or the unfitness is caused by an inevitable accident, rents, and refused to accept further payments tendered by the
and if he does not do so, the tenant may have the lease lessee unless their right to collect the occupation rental was
annulled, or the rent abated. Dig. 19, 2, 9, 2; 19, 2, 15, 1, 2; recognized or reserved. After refusing the rents from July to
19, 2, 25, 2; 19, 2, 39; 2 Gomez, Variae Resolutiones c. 3, November 1946, unless the lessee recognized their right to
secs. 1-3, 18, 19: Gregorio Lopez in 5 Partidas, tit. 8, 11. 8, occupation rentals, the appellees (lessors) demanded
22; Domat, Droit Civil, pt. 1, lib. 1, tit. 4, sec. 1, no. 1; sec. 3 rescission of the contract and a rental of P1,740 monthly in
nos. 1, 3, 6, Pothier, Contract de Louage, nos. 3, 6, 11, 22, lieu of the stipulated P350 per month. (Exhibit "C").
53, 103, 106, 139-155. This attitude of the lessors was doubly wrongful: first, because
as already shown, the dispossession by the Japanese army being undisputed that, from December 1946 up to March 2,
exempted the lessee from his obligation to pay rent for the 1948, when the commercial buildings were burned, the
period of its ouster; and second, because even if the lessee defendants-appellants have paid the contract rentals at the
had been liable for that rent, its collection in 1946 was barred rate of P350 per month. But the failure to consign did not
by the moratorium order, Executive Order No. 32, that eradicate the default (mora) of the lessors nor the risk of loss
remained in force until replaced by Rep. Act 342 in 1948. To that lay upon them. (3 Castan, Der. Civ., 8th Ed., p. 145; 4
apply the current rentals to the occupation obligations would Puig Peña, Der. Civ., part. 1, p. 234; Diaz Pairo, Teoria Gen.
amount to enforcing them contrary to the moratorium decreed de las Obligaciones [3rd Ed.], Vol. 1, pp. 192-193).
by the government. In view of the foregoing, we hold:lawphil.net
Clearly, then, the lessor' insistence upon collecting the (a) That the dispossession of the lessee from the premises by
occupation rentals for 1942-1945 was unwarranted in law. the Japanese army of occupation was not an act of mere
Hence, their refusal to accept the current rentals without trespass (  perturbacion de mero hecho) but one de derecho
qualification placed them in default (mora creditoris or chargeable to the lessors;
accipiendi) with the result that thereafter, they had to bear all (b) That such dispossession, though not due to fault of lessors
supervening risks of accidental injury or destruction of the or lessee, nevertheless resulted in the exemption of the
leased premises. While not expressly declared by the Code of lessee from its obligation to pay rent during the period that it
1889, this result is clearly inferable from the nature and was deprived of the possession and enjoyment of the
effects of mora, and from Articles 1185, 1452 [par. 3] and premises leased;
1589). (c) That the insistence of the lessors to collect such rentals
ART. 1185. When the obligation to deliver a certain and was unwarranted;
determinate thing arises from the commission of a crime or (d) That the lessors were not justified in refusing to accept the
misdemeanor the obligor shall not be exempted from the tender of current rentals unless the lessee should recognize
payment of its value, whatever the cause of its loss may have their right to the rents corresponding to the period that the
been, unless, having offered the thing to the person entitled to lessee was not in possession;
receive it, the latter should have refused without reason to (e) That by their improper refusal to accept the current rents
accept it. tendered by the lessee, the lessors incurred in default (mora)
Art. 1452. . . . . and they must shoulder the subsequent accidental loss of the
If fungible things should be sold for a price fixed with relation premises leased;
to weight, number, or measure, they shall not be at the (f) That the mora of the lessors was not cured by the failure of
purchaser's risk until they have been weighed, counted, or the lessee to make the consignation of the rejected payments,
measured, unless the purchaser should be in default. but the lessee remained obligated to pay the amounts
ART. 1589. If the person who contracted to do the work bound tendered and not consigned by it in court.
himself to furnish the materials, he shall bear the loss in case Consequently, it was reversible error to sentence the
of the destruction of the work before it is delivered, unless its appellants to pay P2,165 a month as reasonable value of the
acceptance has been delayed by the default of the other occupation of the premises from July 1946, and the value of
party. the destroyed buildings amounting to P30,000.
While there is a presumption that the loss of the thing leased Wherefore, the decision appealed from is modified in the
is due to the fault of the lessee (Civil Code of 1889, Art. 1563), sense that the appellant Manila Motor Company should pay to
it is noteworthy that the lessor have not invoked that the appellees Villaruel only the rents for the leased premises
presumption either here or in the court below. On the contrary, corresponding to the period from July up to November 1946,
the parties and the trial court have all proceeded and at the rate of P350 a month, or a total of P1,750. Costs
discussed the issues taking for granted that the destruction of against appellees in both instances. So ordered.
the leased buildings was purely fortuitous. We see no reason
for departing from that assumption and further prolonging this G.R. No. 101163 January 11, 1993
litigation.. STATE INVESTMENT HOUSE, INC., petitioner,
That the lessee and sublessee did not consign or deposit in vs.
court the rentals tendered to and improperly rejected by the COURT OF APPEALS and NORA B. MOULIC, respondents.
lessors, did not render the debtor liable for default (mora Escober, Alon & Associates for petitioner.
solvendi) nor answerable for fortuitous events because, as Martin D. Pantaleon for private respondents.
explained by the Supreme Court of Spain in its Sentencia of 5
June 1944 —
Al exigir el art. 1176 del Codigo Civil la consignacion para BELLOSILLO, J.:
liberar al deudor no quiere decir que necesariamente haya de The liability to a holder in due course of the drawer of checks
practicarse, y no baste el ofrecimiento de pago que de issued to another merely as security, and the right of a real
aquella no fuere seguido, a efectos de exclusion de las estate mortgagee after extrajudicial foreclosure to recover the
consecuencias de la mora solvendi. (8 Manresa, balance of the obligation, are the issues in this Petition for
Comentarios, 5th Ed., Vol. 1, p. 136). Review of the Decision of respondent Court of Appeals.
In other words, the only effect of the failure to consign the Private respondent Nora B. Moulic issued to Corazon
rentals in court was that the obligation to pay them subsisted Victoriano, as security for pieces of jewelry to be sold on
(P.N.B. vs. Relativo, 92 Phil., 203) and the lessee remained commission, two (2) post-dated Equitable Banking
liable for the amount of the unpaid contract rent, Corporation checks in the amount of Fifty Thousand Pesos
corresponding to the period from July to November, 1946; it (P50,000.00) each, one dated 30 August 1979 and the other,
30 September 1979. Thereafter, the payee negotiated the such, it holds the instruments free from any defect of title of
checks to petitioner State Investment House. Inc. (STATE). prior parties, and from defenses available to prior parties
MOULIC failed to sell the pieces of jewelry, so she returned among themselves; STATE may, therefore, enforce full
them to the payee before maturity of the checks. The checks, payment of the checks.4
however, could no longer be retrieved as they had already MOULIC cannot set up against STATE the defense that there
been negotiated. Consequently, before their maturity dates, was failure or absence of consideration. MOULIC can only
MOULIC withdrew her funds from the drawee bank. invoke this defense against STATE if it was privy to the
Upon presentment for payment, the checks were dishonored purpose for which they were issued and therefore is not a
for insufficiency of funds. On 20 December 1979, STATE holder in due course.
allegedly notified MOULIC of the dishonor of the checks and That the post-dated checks were merely issued as security is
requested that it be paid in cash instead, although MOULIC not a ground for the discharge of the instrument as against a
avers that no such notice was given her. holder in due course. For the only grounds are those outlined
On 6 October 1983, STATE sued to recover the value of the in Sec. 119 of the Negotiable Instruments Law:
checks plus attorney's fees and expenses of litigation. Sec. 119. Instrument; how discharged. — A negotiable
In her Answer, MOULIC contends that she incurred no instrument is discharged: (a) By payment in due course by or
obligation on the checks because the jewelry was never sold on behalf of the principal debtor; (b) By payment in due
and the checks were negotiated without her knowledge and course by the party accommodated, where the instrument is
consent. She also instituted a Third-Party Complaint against made or accepted for his accommodation; (c) By the
Corazon Victoriano, who later assumed full responsibility for intentional cancellation thereof by the holder; (d) By any other
the checks. act which will discharge a simple contract for the payment of
On 26 May 1988, the trial court dismissed the Complaint as money; (e) When the principal debtor becomes the holder of
well as the Third-Party Complaint, and ordered STATE to pay the instrument at or after maturity in his own right.
MOULIC P3,000.00 for attorney's fees. Obviously, MOULIC may only invoke paragraphs (c) and (d)
STATE elevated the order of dismissal to the Court of as possible grounds for the discharge of the instrument. But,
Appeals, but the appellate court affirmed the trial court on the the intentional cancellation contemplated under paragraph (c)
ground that the Notice of Dishonor to MOULIC was made is that cancellation effected by destroying the instrument
beyond the period prescribed by the Negotiable Instruments either by tearing it up,5 burning it,6 or writing the word
Law and that even if STATE did serve such notice on "cancelled" on the instrument. The act of destroying the
MOULIC within the reglementary period it would be of no instrument must also be made by the holder of the instrument
consequence as the checks should never have been intentionally. Since MOULIC failed to get back possession of
presented for payment. The sale of the jewelry was never the post-dated checks, the intentional cancellation of the said
effected; the checks, therefore, ceased to serve their purpose checks is altogether impossible.
as security for the jewelry. On the other hand, the acts which will discharge a simple
We are not persuaded. contract for the payment of money under paragraph (d) are
The negotiability of the checks is not in dispute. Indubitably, determined by other existing legislations since Sec. 119 does
they were negotiable. After all, at the pre-trial, the parties not specify what these acts are, e.g., Art. 1231 of the Civil
agreed to limit the issue to whether or not STATE was a Code7 which enumerates the modes of extinguishing
holder of the checks in due course.1 obligations. Again, none of the modes outlined therein is
In this regard, Sec. 52 of the Negotiable Instruments Law applicable in the instant case as Sec. 119 contemplates of a
provides — situation where the holder of the instrument is the creditor
Sec. 52. What constitutes a holder in due course. — A holder while its drawer is the debtor. In the present action, the payee,
in due course is a holder who has taken the instrument under Corazon Victoriano, was no longer MOULIC's creditor at the
the following conditions: (a) That it is complete and regular time the jewelry was returned.
upon its face; (b) That he became the holder of it before it was Correspondingly, MOULIC may not unilaterally discharge
overdue, and without notice that it was previously dishonored, herself from her liability by the mere expediency of
if such was the fact; (c) That he took it in good faith and for withdrawing her funds from the drawee bank. She is thus
value; (d) That at the time it was negotiated to him he had no liable as she has no legal basis to excuse herself from liability
notice of any infirmity in the instrument or defect in the title of on her checks to a holder in due course.
the person negotiating it. Moreover, the fact that STATE failed to give Notice of
Culled from the foregoing, a prima facie presumption exists Dishonor to MOULIC is of no moment. The need for such
that the holder of a negotiable instrument is a holder in due notice is not absolute; there are exceptions under Sec. 114 of
course.2 Consequently, the burden of proving that STATE is the Negotiable Instruments Law:
not a holder in due course lies in the person who disputes the Sec. 114. When notice need not be given to drawer. — Notice
presumption. In this regard, MOULIC failed. of dishonor is not required to be given to the drawer in the
The evidence clearly shows that: (a) on their faces the post- following cases: (a) Where the drawer and the drawee are the
dated checks were complete and regular: (b) petitioner bought same person; (b) When the drawee is a fictitious person or a
these checks from the payee, Corazon Victoriano, before their person not having capacity to contract; (c) When the drawer is
due dates;3 (c) petitioner took these checks in good faith and the person to whom the instrument is presented for payment:
for value, albeit at a discounted price; and, (d) petitioner was (d) Where the drawer has no right to expect or require that the
never informed nor made aware that these checks were drawee or acceptor will honor the instrument; (e) Where the
merely issued to payee as security and not for value. drawer had countermanded payment.
Consequently, STATE is indeed a holder in due course. As Indeed, MOULIC'S actuations leave much to be desired. She
did not retrieve the checks when she returned the jewelry. event of foreclosure, the vendor "shall have no further action
She simply withdrew her funds from her drawee bank and against the purchaser to recover any unpaid balance of the
transferred them to another to protect herself. After price. Any agreement to the contrary will be void".16
withdrawing her funds, she could not have expected her It is clear then that in the absence of a similar provision in Act
checks to be honored. In other words, she was responsible for No. 3135, as amended, it cannot be concluded that the
the dishonor of her checks, hence, there was no need to creditor loses his right recognized by the Rules of Court to
serve her Notice of Dishonor, which is simply bringing to the take action for the recovery of any unpaid balance on the
knowledge of the drawer or indorser of the instrument, either principal obligation simply because he has chosen to
verbally or by writing, the fact that a specified instrument, extrajudicially foreclose the real estate mortgage pursuant to
upon proper proceedings taken, has not been accepted or a Special Power of Attorney given him by the mortgagor in the
has not been paid, and that the party notified is expected to contract of mortgage.17
pay it.8 The filing of the Complaint and the Third-Party Complaint to
In addition, the Negotiable Instruments Law was enacted for enforce the checks against MOULIC and the VICTORIANO
the purpose of facilitating, not hindering or hampering spouses, respectively, is just another means of recovering the
transactions in commercial paper. Thus, the said statute unpaid balance of the debt of the VICTORIANOs.
should not be tampered with haphazardly or lightly. Nor In fine, MOULIC, as drawer, is liable for the value of the
should it be brushed aside in order to meet the necessities in checks she issued to the holder in due course, STATE,
a single case.9 without prejudice to any action for recompense she may
The drawing and negotiation of a check have certain effects pursue against the VICTORIANOs as Third-Party Defendants
aside from the transfer of title or the incurring of liability in who had already been declared as in default.
regard to the instrument by the transferor. The holder who WHEREFORE, the petition is GRANTED. The decision
takes the negotiated paper makes a contract with the parties appealed from is REVERSED and a new one entered
on the face of the instrument. There is an implied declaring private respondent NORA B. MOULIC liable to
representation that funds or credit are available for the petitioner STATE INVESTMENT HOUSE, INC., for the value
payment of the instrument in the bank upon which it is of EBC Checks Nos. 30089658 and 30089660 in the total
drawn.10 Consequently, the withdrawal of the money from the amount of P100,000.00, P3,000.00 as attorney's fees, and the
drawee bank to avoid liability on the checks cannot prejudice costs of suit, without prejudice to any action for recompense
the rights of holders in due course. In the instant case, such she may pursue against the VICTORIANOs as Third-Party
withdrawal renders the drawer, Nora B. Moulic, liable to Defendants.
STATE, a holder in due course of the checks. Costs against private respondent.
Under the facts of this case, STATE could not expect payment SO ORDERED.
as MOULIC left no funds with the drawee bank to meet her
obligation on the checks,11 so that Notice of Dishonor would G.R. No. L-42283 March 18, 1985
be futile. BUENAVENTURA ANGELES, ET AL., plaintiffs-appellees,
The Court of Appeals also held that allowing recovery on the vs.
checks would constitute unjust enrichment on the part of URSULA TORRES CALASANZ, ET AL., defendants-
STATE Investment House, Inc. This is error. appellants.
The record shows that Mr. Romelito Caoili, an Account
Assistant, testified that the obligation of Corazon Victoriano
and her husband at the time their property mortgaged to GUTIERREZ, JR., J.:
STATE was extrajudicially foreclosed amounted to P1.9 This is an appeal from the decision of the Court of First
million; the bid price at public auction was only P1 Instance of Rizal, Seventh Judicial District, Branch X,
million.12 Thus, the value of the property foreclosed was not declaring the contract to sell as not having been validly
even enough to pay the debt in full. cancelled and ordering the defendants-appellants to execute
Where the proceeds of the sale are insufficient to cover the a final deed of sale in favor of the plaintiffs-appellees, to pay
debt in an extrajudicial foreclosure of mortgage, the P500.00 attorney's fees and costs.
mortgagee is entitled to claim the deficiency from the The facts being undisputed, the Court of Appeals certified the
debtor.13 The step thus taken by the mortgagee-bank in case to us since only pure questions of law have been raised
resorting to an extra-judicial foreclosure was merely to find a for appellate review.
proceeding for the sale of the property and its action cannot On December 19, 1957, defendants-appellants Ursula Torres
be taken to mean a waiver of its right to demand payment for Calasanz and Tomas Calasanz and plaintiffs-appellees
the whole debt.14 For, while Act 3135, as amended, does not Buenaventura Angeles and Teofila Juani entered into a
discuss the mortgagee's right to recover such deficiency, it contract to sell a piece of land located in Cainta, Rizal for the
does not contain any provision either, expressly or impliedly, amount of P3,920.00 plus 7% interest per annum.
prohibiting recovery. In this jurisdiction, when the legislature The plaintiffs-appellees made a downpayment of P392.00
intends to foreclose the right of a creditor to sue for any upon the execution of the contract. They promised to pay the
deficiency resulting from foreclosure of a security given to balance in monthly installments of P 41.20 until fully paid, the
guarantee an obligation, it so expressly provides. For installments being due and payable on the 19th day of each
instance, with respect to pledges, Art. 2115 of the Civil month. The plaintiffs-appellees paid the monthly installments
Code15 does not allow the creditor to recover the deficiency until July 1966, when their aggregate payment already
from the sale of the thing pledged. Likewise, in the case of a amounted to P4,533.38. On numerous occasions, the
chattel mortgage, or a thing sold on installment basis, in the defendants-appellants accepted and received delayed
installment payments from the plaintiffs-appellees. SIXTH.—In case the party of the SECOND PART fails to
On December 7, 1966, the defendants-appellants wrote the satisfy any monthly installments, or any other payments
plaintiffs-appellees a letter requesting the remittance of past herein agreed upon, he is granted a month of grace within
due accounts. which to make the retarded payment, together with the one
On January 28, 1967, the defendants-appellants cancelled corresponding to the said month of grace; it is understood,
the said contract because the plaintiffs-appellees failed to however, that should the month of grace herein granted to the
meet subsequent payments. The plaintiffs' letter with their party of the SECOND PART expired; without the payments
plea for reconsideration of the said cancellation was denied corresponding to both months having been satisfied, an
by the defendants-appellants. interest of 10% per annum will be charged on the amounts he
The plaintiffs-appellees filed Civil Case No. 8943 with the should have paid; it is understood further, that should a period
Court of First Instance of Rizal, Seventh Judicial District, of 90 days elapse, to begin from the expiration of the month
Branch X to compel the defendants-appellants to execute in of grace herein mentioned, and the party of SECOND PART
their favor the final deed of sale alleging inter alia that after has not paid all the amounts he should have paid with the
computing all subsequent payments for the land in question, corresponding interest up to that date, the party of the FIRST
they found out that they have already paid the total amount of PART has the right to declare this contract cancelled and of
P4,533.38 including interests, realty taxes and incidental no effect, and as consequence thereof, the party of the FIRST
expenses for the registration and transfer of the land. PART may dispose of the parcel of land covered by this
The defendants-appellants alleged in their answer that the contract in favor of other persons, as if this contract had never
complaint states no cause of action and that the plaintiffs- been entered into. In case of such cancellation of the contract,
appellees violated paragraph six (6) of the contract to sell all the amounts paid in accordance with this agreement
when they failed and refused to pay and/or offer to pay the together with all the improvements made on the premises,
monthly installments corresponding to the month of August, shall be considered as rents paid for the use and occupation
1966 for more than five (5) months, thereby constraining the of the above mentioned premises, and as payment for the
defendants-appellants to cancel the said contract. damages suffered by failure of the party of the SECOND
The lower court rendered judgment in favor of the plaintiffs- PART to fulfill his part of the agreement; and the party of the
appellees. The dispositive portion of the decision reads: SECOND PART hereby renounces all his right to demand or
WHEREFORE, based on the foregoing considerations, the reclaim the return of the same and obliges himself to
Court hereby renders judgment in favor of the plaintiffs and peacefully vacate the premises and deliver the same to the
against the defendants declaring that the contract subject party of the FIRST PART. (Emphasis supplied by appellant)
matter of the instant case was NOT VALIDLY cancelled by the xxx xxx xxx
defendants. Consequently, the defendants are ordered to The defendants-appellants argue that the plaintiffs-appellees
execute a final Deed of Sale in favor of the plaintiffs and to failed to pay the August, 1966 installment despite demands
pay the sum of P500.00 by way of attorney's fees. Costs for more than four (4) months. The defendants-appellants
against the defendants. point to Jocson v. Capitol Subdivision (G.R. No. L-6573,
A motion for reconsideration filed by the defendants- February 28, 1955) where this Court upheld the right of the
appellants was denied. subdivision owner to automatically cancel a contract to sell on
As earlier stated, the then Court of Appeals certified the case the strength of a provision or stipulation similar to paragraph 6
to us considering that the appeal involves pure questions of of the contract in this case. The defendants-appellants also
law. argue that even in the absence of the aforequoted provision,
The defendants-appellants assigned the following alleged they had the right to cancel the contract to sell under Article
errors of the lower court: 1191 of the Civil Code of the Philippines.
First Assignment of Error The plaintiffs-appellees on the other hand contend that
THE LOWER COURT ERRED IN NOT HOLDING THE the Jocson ruling does not apply. They state that paragraph 6
CONTRACT TO SELL (ANNEX "A" OF COMPLIANCE) AS of the contract to sell is contrary to law insofar as it provides
HAVING BEEN LEGALLY AND VALIDLY CANCELLED. that in case of specified breaches of its terms, the sellers
Second Assignment of Error have the right to declare the contract cancelled and of no
EVEN ASSUMING ARGUENDO THAT THE SAID effect, because it granted the sellers an absolute and
CONTRACT TO SELL HAS NOT BEEN LEGALLY AND automatic right of rescission.
VALIDLY CANCELLED, THE LOWER COURT ERRED IN Article 1191 of the Civil Code on the rescission of reciprocal
ORDERING DEFENDANTS TO EXECUTE A FINAL DEED obligations provides:
OF SALE IN FAVOR OF THE PLAINTIFF. The power to rescind obligations is implied in reciprocal ones,
Third Assignment of Error in case one of the obligors should not comply with what is
THE LOWER COURT ERRED IN ORDERING DEFENDANTS incumbent upon him.
TO PAY PLAINTIFFS THE SUM OF P500.00 AS The injured party may choose between the fulfillment and the
ATTORNEY'S FEES. rescission of the obligation, with the payment of damages in
The main issue to be resolved is whether or not the contract either case. He may also seek rescission, even after he has
to sell has been automatically and validly cancelled by the chosen fulfillment, if the latter should become impossible.
defendants-appellants. xxx xxx xxx
The defendants-appellants submit that the contract was Article 1191 is explicit. In reciprocal obligations, either party
validly cancelled pursuant to paragraph six of the contract the right to rescind the contract upon the failure of the other to
which provides: perform the obligation assumed thereunder. Moreover, there
xxx xxx xxx is nothing in the law that prohibits the parties from entering
into an agreement that violation of the terms of the contract violated Section two of the contract to sell which provides:
would cause its cancellation even without court intervention SECOND.—That in consideration of the agreement of sale of
(Froilan v. Pan Oriental Shipping, Co., et al., 12 SCRA 276)— the above described property, the party of the SECOND PART
Well settled is, however, the rule that a judicial action for the obligates himself to pay to the party of the FIRST PART the
rescission of a contract is not necessary where the contract Sum of THREE THOUSAND NINE HUNDRED TWENTY
provides that it may be revoked and cancelled for violation of ONLY (P3,920.00), Philippine Currency, plus interest at the
any of its terms and conditions' (Lopez v. Commissioner of rate of 7% per annum, as follows:
Customs, 37 SCRA 327, and cases cited therein) (a) The amount of THREE HUNDRED NINETY TWO only
Resort to judicial action for rescission is obviously not (P392.00) when this contract is signed; and
contemplated . . . The validity of the stipulation can not be (b) The sum of FORTY ONE AND 20/100 ONLY (P4l.20) on or
seriously disputed. It is in the nature of a facultative resolutory before the 19th day of each month, from this date until the
condition which in many cases has been upheld by this Court. total payment of the price above stipulated, including interest.
(Ponce Enrile v. Court of Appeals, 29 SCRA 504). because they failed to pay the August installment, despite
The rule that it is not always necessary for the injured party to demand, for more than four (4) months.
resort to court for rescission of the contract when the contract The breach of the contract adverted to by the defendants-
itself provides that it may be rescinded for violation of its appellants is so slight and casual when we consider that apart
terms and conditions, was qualified by this Court in University from the initial downpayment of P392.00 the plaintiffs-
of the Philippines v. De los Angeles, (35 SCRA 102) where we appellees had already paid the monthly installments for a
explained that: period of almost nine (9) years. In other words, in only a short
Of course, it must be understood that the act of a party in time, the entire obligation would have been paid. Furthermore,
treating a contract as cancelled or resolved on account of although the principal obligation was only P 3,920.00
infractions by the other contracting party must be made excluding the 7 percent interests, the plaintiffs- appellees had
known to the other and is always provisional, being ever already paid an aggregate amount of P 4,533.38. To sanction
subject to scrutiny and review by the proper court. If the other the rescission made by the defendants-appellants will work
party denies that rescission is justified, it is free to resort to injustice to the plaintiffs- appellees. (See J.M. Tuazon and
judicial action in its own behalf, and bring the matter to court. Co., Inc. v. Javier, 31 SCRA 829) It would unjustly enrich the
Then, should the court, after due hearing, decide that the defendants-appellants.
resolution of the contract was not warranted, the responsible Article 1234 of the Civil Code which provides that:
party will be sentenced to damages; in the contrary case, the If the obligation has been substantially performed in good
resolution will be affirmed, and the consequent indemnity faith, the obligor may recover as though there had been a
awarded to the party prejudiced. strict and complete fulfillment, less damages suffered by the
In other words, the party who deems the contract violated obligee.
many consider it resolved or rescinded, and act accordingly, also militates against the unilateral act of the defendants-
without previous court action, but it proceeds at its own risk. appellants in cancelling the contract.
For it is only the final judgment of the corresponding court that We agree with the observation of the lower court to the effect
will conclusively and finally settle whether the action taken that:
was or was not correct in law. ... . Although the primary object of selling subdivided lots is
We see no conflict between this ruling and the previous business, yet, it cannot be denied that this subdivision is
jurisprudence of this Court invoked by respondent declaring likewise purposely done to afford those landless, low income
that judicial action is necessary for the resolution of a group people of realizing their dream of a little parcel of land
reciprocal obligation; (Ocejo, Perez & Co. v. International which they can really call their own.
Banking Corp., 37 Phil. 631; Republic v. Hospital de San Juan The defendants-appellants cannot rely on paragraph 9 of the
de Dios, et al., 84 Phil. 820) since in every case where the contract which provides:
extrajudicial resolution is contested only the final award of the NINTH.-That whatever consideration of the party of the FIRST
court of competent jurisdiction can conclusively settle whether PART may concede to the party of the SECOND PART, as not
the resolution was proper or not. It is in this sense that judicial exacting a strict compliance with the conditions of paragraph
action will be necessary, as without it, the extrajudicial 6 of this contract, as well as any other condonation that the
resolution will remain contestable and subject to judicial party of the FIRST PART may give to the party of the
invalidation, unless attack thereon should become barred by SECOND PART with regards to the obligations of the latter,
acquiescence, estoppel or prescription. should not be interpreted as a renunciation on the part of the
The right to rescind the contract for non-performance of one party of the FIRST PART of any right granted it by this
of its stipulations, therefore, is not absolute. In Universal Food contract, in case of default or non-compliance by the party of
Corp. v. Court of Appeals (33 SCRA 1) the Court stated that— the SECOND PART.
The general rule is that rescission of a contract will not be The defendants-appellants argue that paragraph nine clearly
permitted for a slight or casual breach, but only for such allows the seller to waive the observance of paragraph 6 not
substantial and fundamental breach as would defeat the very merely once, but for as many times as he wishes.
object of the parties in making the agreement. (Song Fo & Co. The defendants-appellants' contention is without merit. We
v. Hawaiian-Philippine Co., 47 Phil. 821, 827) The question of agree with the plaintiffs-appellees that when the defendants-
whether a breach of a contract is substantial depends upon appellants, instead of availing of their alleged right to rescind,
the attendant circumstances. (Corpus v. Hon. Alikpala, et al., have accepted and received delayed payments of
L-23707 & L-23720, Jan. 17, 1968). ... . installments, though the plaintiffs-appellees have been in
The defendants-appellants state that the plaintiffs-appellees arrears beyond the grace period mentioned in paragraph 6 of
the contract, the defendants-appellants have waived and are ... (W)hile generally, stipulations in a contract come about
now estopped from exercising their alleged right of rescission. after deliberate drafting by the parties thereto. . . . there are
In De Guzman v. Guieb  (48 SCRA 68), we held that: certain contracts almost all the provisions of which have been
xxx xxx xxx drafted only by one party, usually a corporation. Such
But defendants do not deny that in spite of the long contracts are called contracts of adhesion, because the only
arrearages, neither they nor their predecessor, Teodoro de participation of the party is the signing of his signature or his
Guzman, even took steps to cancel the option or to eject the "adhesion" thereto. Insurance contracts, bills of
appellees from the home-lot in question. On the contrary, it is lading, contracts of sale of lots on the installment plan fall into
admitted that the delayed payments were received without this category. (Paras, Civil Code of the Philippines, Seventh
protest or qualification. ... Under these circumstances, We ed., Vol. 1, p. 80.) (Emphasis supplied)
cannot but agree with the lower court that at the time While it is true that paragraph 2 of the contract obligated the
appellees exercised their option, appellants had already plaintiffs-appellees to pay the defendants-appellants the sum
forfeited their right to invoke the above-quoted provision of P3,920.00 plus 7% interest per annum, it is likewise true
regarding the nullifying effect of the non-payment of six that under paragraph 12 the seller is obligated to transfer the
months rentals by appellees by their having accepted without title to the buyer upon payment of the P3,920.00 price sale.
qualification on July 21, 1964 the full payment by appellees of The contract to sell, being a contract of adhesion, must be
all their arrearages. construed against the party causing it. We agree with the
The defendants-appellants contend in the second assignment observation of the plaintiffs-appellees to the effect that "the
of error that the ledger of payments show a balance of terms of a contract must be interpreted against the party who
P671,67 due from the plaintiffs-appellees. They submit that drafted the same, especially where such interpretation will
while it is true that the total monthly installments paid by the help effect justice to buyers who, after having invested a big
plaintiffs-appellees may have exceeded P3,920.00, a amount of money, are now sought to be deprived of the same
substantial portion of the said payments were applied to the thru the prayed application of a contract clever in its
interests since the contract specifically provides for a 7% phraseology, condemnable in its lopsidedness and injurious in
interest per annum on the remaining balance. The its effect which, in essence, and in its entirety is most unfair to
defendants-appellants rely on paragraph 2 of the contract the buyers."
which provides: Thus, since the principal obligation under the contract is only
SECOND.—That in consideration of the agreement of sale of P3,920.00 and the plaintiffs-appellees have already paid an
the above described property, the party of the SECOND PART aggregate amount of P4,533.38, the courts should only order
obligates himself to pay to the party of the FIRST PART the the payment of the few remaining installments but not uphold
Sum of THREE THOUSAND NINE HUNDRED TWENTY the cancellation of the contract. Upon payment of the balance
ONLY (P 3,920.00), Philippine Currency, plus interest at the of P671.67 without any interest thereon, the defendants-
rate of 7% per annum ... . (Emphasis supplied) appellants must immediately execute the final deed of sale in
The plaintiffs-appellees on the other hand are firm in their favor of the plaintiffs-appellees and execute the necessary
submission that since they have already paid the defendants- transfer documents as provided in paragraph 12 of the
appellants a total sum of P4,533.38, the defendants- contract. The attorney's fees are justified.
appellants must now be compelled to execute the final deed WHEREFORE, the instant petition is DENIED for lack of
of sale pursuant to paragraph 12 of the contract which merit. The decision appealed from is AFFIRMED with the
provides: modification that the plaintiffs-appellees should pay the
TWELFTH.—That once the payment of the sum of P3,920.00, balance of SIX HUNDRED SEVENTY ONE PESOS AND
the total price of the sale is completed, the party to the FIRST SIXTY-SEVEN CENTAVOS (P671.67) without any interests.
PART will execute in favor of the party of the SECOND PART, Costs against the defendants-appellants.
the necessary deed or deeds to transfer to the latter the title SO ORDERED.
of the parcel of land sold, free from all hens and
encumbrances other than those expressly provided in this G.R. No. 129018      November 15, 2001
contract; it is understood, however, that au the expenses CARMELITA LEAÑO, assisted by her husband
which may be incurred in the said transfer of title shall be paid GREGORIO CUACHON, petitioner,
by the party of the SECOND PART, as above stated. vs.
Closely related to the second assignment of error is the COURT OF APPEALS and HERMOGENES
submission of the plaintiffs-appellees that the contract herein FERNANDO, respondents.
is a contract of adhesion. PARDO, J.:
We agree with the plaintiffs-appellees. The contract to sell The Case
entered into by the parties has some characteristics of a The case is a petition for review on certiorari of the
contract of adhesion. The defendants-appellants drafted and decision1 of the Court of Appeals affirming that of the Regional
prepared the contract. The plaintiffs-appellees, eager to Trial Court, Malolos, Branch 72 ordering petitioner Leaño to
acquire a lot upon which they could build a home, affixed their pay respondent Hermogenes Fernando the sum of
signatures and assented to the terms and conditions of the P183,687.70 corresponding to her outstanding obligations
contract. They had no opportunity to question nor change any under the contract to sell, with interest and surcharges due
of the terms of the agreement. It was offered to them on a thereon, attorney's fees and costs.1âwphi1.nêt
"take it or leave it" basis. In Sweet Lines, Inc. v. Teves (83 The Facts
SCRA 36 1), we held that: On November 13, 1985, Hermogenes Fernando, as vendor
xxx xxx xxx and Carmelita Leaño, as vendee executed a contract to sell
involving a piece of land, Lot No. 876-B, with an area of 431 "2. Ordering the plaintiff to pay to the defendant the sum of
square meters, located at Sto. Cristo, Baliuag, Bulacan. 3 P103,090.70 corresponding to her outstanding obligations
In the contract, Carmelita Leaño bound herself to pay under the contract to sell (Exhibit "A" – Exhibit "B") consisting
Hermogenes Fernando the sum of one hundred seven of the principal of said obligation together with the interest and
thousand and seven hundred and fifty pesos (P107,750.00) surcharges due thereon as of February 28, 1994, plus interest
as the total purchase price of the lot. The manner of paying thereon at the rate of 18% per annum in accordance with the
the total purchase price was as follows: provision of said contract to be computed from March 1, 1994,
"The sum of TEN THOUSAND SEVEN HUNDRED SEVENTY until the same becomes fully paid;
FIVE (P10,775.00) PESOS, shall be paid at the signing of this "3. Ordering the defendant to pay to plaintiff the amount of
contract as DOWN PAYMENT, the balance of NINETY SIX P10,000 as and by way of attorney's fees;
THOUSAND NINE HUNDRED SEVENTY FIVE PESOS "4. Ordering the defendant to pay to plaintiff the costs of the
(P96,975.00) shall be paid within a period of TEN (10) years suit in Civil Case No. 1680 aforementioned.
at a monthly amortization of P1,747.30 to begin from "SO ORDERED.
December 7, 1985 with interest at eighteen per cent (18%) "Malolos, Bulacan, February 6, 1995.
per annum based on balances."4
The contract also provided for a grace period of one month
within which to make payments, together with the one "(sgd.) DANILO A. MANALASTAS
corresponding to the month of grace. Should the month of Judge"17
grace expire without the installments for both months having On February 21, 1995, respondent Fernando filed a motion
been satisfied, an interest of 18% per annum will be charged for reconsideration18 and the supplement19 thereto. The trial
on the unpaid installments.5 court increased the amount of P103,090.70 to P183,687.00
Should a period of ninety (90) days elapse from the expiration and ordered petitioner Leaño ordered to pay attorney's fees. 20
of the grace period without the overdue and unpaid According to the trial court, the transaction between the
installments having been paid with the corresponding parties was an absolute sale, making petitioner Leaño the
interests up to that date, respondent Fernando, as vendor, owner of the lot upon actual and constructive delivery thereof.
was authorized to declare the contract cancelled and to Respondent Fernando, the seller, was divested of ownership
dispose of the parcel of land, as if the contract had not been and cannot recover the same unless the contract is rescinded
entered into. The payments made, together with all the pursuant to Article 1592 of the Civil Code which requires a
improvements made on the premises, shall be considered as judicial or notarial demand. Since there had been no
rents paid for the use and occupation of the premises and as rescission, petitioner Leaño, as the owner in possession of
liquidated damages.6 the property, cannot be evicted.
After the execution of the contract, Carmelita Leaño made On the issue of delay, the trial court held:
several payments in lump sum. 7 Thereafter, she constructed a "While the said contract provides that the whole purchase
house on the lot valued at P800,000.00. 8 The last payment price is payable within a ten-year period, yet the same
that she made was on April 1, 1989. contract clearly specifies that the purchase price shall be
On September 16, 1991, the trial court rendered a decision in payable in monthly installments for which the corresponding
an ejectment case9 earlier filed by respondent Fernando penalty shall be imposed in case of default. The plaintiff
ordering petitioner Leaño to vacate the premises and to pay certainly cannot ignore the binding effect of such stipulation
P250.00 per month by way of compensation for the use and by merely asserting that the ten-year period for payment of
occupation of the property from May 27, 1991 until she the whole purchase price has not yet lapsed. In other words,
vacated the premises, attorney's fees and costs of the the plaintiff has clearly defaulted in the payment of the
suit.10 On August 24, 1993, the trial court issued a writ of amortizations due under the contract as recited in the
execution which was duly served on petitioner Leaño. statement of account (Exhibit "2") and she should be liable for
On September 27, 1993, petitioner Leaño filed with the the payment of interest and penalties in accordance with the
Regional Trial Court of Malolos, Bulacan a complaint for stipulations in the contract pertaining thereto."21
specific performance with preliminary injunction. 11 Petitioner The trial court disregarded petitioner Leaños claim that she
Leaño assailed the validity of the judgment of the municipal made a downpayment of P10,000.00, at the time of the
trial court12 for being violative of her right to due process and execution of the contract.
for being contrary to the avowed intentions of Republic Act The trial court relied on the statement of account 22 and the
No. 6552 regarding protection to buyers of lots on summary23 prepared by respondent Fernando to determine
installments. Petitioner Leaño deposited P18,000.00 with the petitioner Leaño's liability for the payment of interests and
clerk of court, Regional Trial Court, Bulacan, to cover the penalties.
balance of the total cost of Lot 876-B.13 The trial court held that the consignation made by petitioner
On November 4, 1993, after petitioner Leaño posted a cash Leaño in the amount of P18,000.00 did not produce any legal
bond of P50,000.00,14 the trial court issued a writ of effect as the same was not done in accordance with Articles
preliminary injunction15 to stay the enforcement of the decision 1176, 1177 and 1178 of the Civil Code.
of the municipal trial court.16 In time, petitioner Leaño appealed the decision to the Court of
On February 6, 1995, the trial court rendered a decision, the Appeals.24 On January 22, 1997, Court of Appeals
dispositive portion of which reads: promulgated a decision affirming that of the Regional Trial
"WHEREFORE, judgment is hereby rendered as follows: Court in toto.25 On February 11, 1997, petitioner Leaño filed a
"1. The preliminary injunction issued by this court per its order motion for reconsideration.26 On April 18, 1997, the Court of
dated November 4, 1993 is hereby made permanent; Appeals denied the motion.27
Hence, this petition.28 property equivalent to fifty percent of the total payments made
The Issues and, after five years of installments, an additional five percent
The issues to be resolved in this petition for review are (1) every year but not to exceed ninety percent of the total
whether the transaction between the parties in an absolute payment made:  Provided, That the actual cancellation of the
sale or a conditional sale; (2) whether there was a proper contract shall take place after thirty days from receipt by the
cancellation of the contract to sell; and (3) whether petitioner buyer of the notice of cancellation or the demand for
was in delay in the payment of the monthly amortizations. rescission of the contract by a notarial act and upon full
The Court's Ruling payment of the cash surrender value to the buyer." [Emphasis
Contrary to the findings of the trial court, the transaction supplied]
between the parties was a conditional sale not an absolute The decision in the ejectment case 37 operated as the notice of
sale. The intention of the parties was to reserve the ownership cancellation required by Sec. 3(b). As petitioner Leaño was
of the land in the seller until the buyer has paid the total not given then cash surrender value of the payments that she
purchase price. made, there was still no actual cancellation of the contract.
Consider the following: Consequently, petitioner Leaño may still reinstate the contract
First, the contract to sell makes the sale, cession and by updating the account during the grace period and before
conveyance "subject to conditions" set forth in the contract to actual cancellation.38
sell.29 Should petitioner Leaño wish to reinstate the contract, she
Second, what was transferred was the possession of the would have to update her accounts with respondent Fernando
property, not ownership. The possession is even limited by in accordance with the statement of account39 which amount
the following: (1) that the vendee may continue therewith "as was P183,687.00.40
long as the VENDEE complies with all the terms and On the issue of whether petitioner Leaño was in delay in
conditions mentioned, and (2) that the buyer may not sell, paying the amortizations, we rule that while the contract
cede, assign, transfer or mortgage or in any way encumber provided that the total purchase price was payable within a
any right, interest or equity that she may have or acquire in ten-year period, the same contract specified that the purchase
and to the said parcel of land nor to lease or to sublease it or price shall be paid in monthly installments for which the
give possession to another person without the written consent corresponding penalty shall be imposed in case of default.
of the seller.30 Petitioner Leaño cannot ignore the provision on the payment
Finally, the ownership of the lot was not transferred to of monthly installments by claiming that the ten-year period
Carmelita Leaño. As the land is covered by a torrens title, the within which to pay has not elapsed.
act of registration of the deed of sale was the operative act Article 1169 of the Civil Code provides that in reciprocal
that could transfer ownership over the lot. 31 There is not even obligations, neither party incurs in delay if the other does not
a deed that could be registered since the contract provides comply or is not ready to comply in a proper manner with what
that the seller will execute such a deed "upon complete is incumbent upon him. From the moment one of the parties
payment by the VENDEE of the total purchase price of the fulfills his obligation, delay by the other begins.1âwphi1.nêt
property" with the stipulated interest.32 In the case at bar, respondent Fernando performed his part of
In a contract to sell real property on installments, the full the obligation by allowing petitioner Leaño to continue in
payment of the purchase price is a positive suspensive possession and use of the property. Clearly, when petitioner
condition, the failure of which is not considered a breach, Leaño did not pay the monthly amortizations in accordance
casual or serious, but simply an event that prevented the with the terms of the contract, she was in delay and liable for
obligation of the vendor to convey title from acquiring any damages.41 However, we agree with the trial court that the
obligatory force.33 The transfer of ownership and title would default committed by petitioner Leaño in respect of the
occur after full payment of the price.34 obligation could be compensated by the interest and
In the case at bar, petitioner Leaño's non-payment of the surcharges imposed upon her under the contract in
installments after April 1, 1989, prevented the obligation of question.42
respondent Fernando to convey the property from arising. In It is a cardinal rule in the interpretation of contracts that if the
fact, it brought into effect the provision of the contract on terms of a contract are clear and leave no doubt upon the
cancellation. intention of the contracting parties, the literal meaning of its
Contrary to the findings of the trial court, Article 1592 of the stipulation shall control.43 Thus, as there is no ambiguity in the
Civil Code is inapplicable to the case at bar. 35 However, any language of the contract, there is no room for construction,
attempt to cancel the contract to sell would have to comply only compliance.
with the provisions of Republic Act No. 6552, the "Realty The Fallo
Installment Buyer Protection Act." IN VIEW WHEREOF, we DENY the petition and AFFIRM the
R.A. No. 6552 recognizes in conditional sales of all kinds of decision of the Court of Appeals44 in toto.
real estate (industrial, commercial, residential) the right of the No costs.
seller to cancel the contract upon non-payment of an SO ORDERED.
installment by the buyer, which is simply an event that
prevents the obligation of the vendor to convey title from G.R. No. 127695       December 3, 2001
acquiring binding force.36 The law also provides for the rights HEIRS OF LUIS BACUS, namely: CLARA RESMA BACUS,
of the buyer in case of cancellation. Thus, Sec. 3 (b) of the ROQUE R. BACUS, SR., SATURNINO R. BACUS,
law provides that: PRISCILA VDA. DE CABANERO, CARMELITA B. SUQUIB,
"If the contract is cancelled, the seller shall refund to the BERNARDITA B. CARDENAS, RAUL R. BACUS,
buyer the cash surrender value of the payments on the MEDARDO R. BACUS, ANSELMA B. ALBAN, RICARDO R.
BACUS, FELICISIMA B. JUDICO, and DOMINICIANA B. refused. They further alleged that private respondents did not
TANGAL, petitioners, deposit the money as required by the Lupon and instead
vs. presented a bank certification which cannot be deemed legal
HON. COURT OF APPEALS and SPOUSES FAUSTINO tender.
DURAY and VICTORIANA DURAY, respondents. On October 30, 1990, private respondents manifested in court
QUISUMBING, J.: that they caused the issuance of a cashier's check in the
This petition assails the decision dated November 29, 1996, amount of P650,0006 payable to petitioners at anytime upon
of the Court of Appeals in CA-G.R. CV No. 37566, affirming demand.
the decision dated August 3, 1991, of the Regional Trial Court On August 3, 1991, the Regional Trial Court ruled in favor of
of Cebu City, Branch 6, in Civil Case No. CEB-8935. private respondents, the dispositive portion of which reads:
The facts, as culled from the records, are as follows: Premises considered, the court finds for the plaintiffs and
On June 1, 1984, Luis Bacus leased to private respondent orders the defendants to specifically perform their obligation in
Faustino Duray a parcel of agricultural land in Bulacao, the option to buy and to execute a document of sale over the
Talisay, Cebu. Designated as Lot No. 3661-A-3-B-2, it had an property covered by Transfer Certificate of Title # T-63269
area of 3,002 square meters, covered by Transfer Certificate upon payment by the plaintiffs to them in the amount of Six
of Title No. 48866. The lease was for six years, ending May Hundred Seventy-Five Thousand Six Hundred Seventy-Five
31, 1990. The contract contained an option to buy clause. (P675,675.00) Pesos within a period of thirty (30) days from
Under said option, the lessee had the exclusive and the date this decision becomes final.
irrevocable right to buy 2,000 square meters of the property SO ORDERED.7
within five years from a year after the effectivity of the Unsatisfied, petitioners appealed to the respondent Court of
contract, at P200 per square meter. That rate shall be Appeals which denied the appeal on November 29, 1996, on
proportionately adjusted depending on the peso rate against the ground that the private respondents exercised their option
the US dollar, which at the time of the execution of the to buy the leased property before the expiration of the
contract was fourteen pesos.1 contract of lease. It held:
Close to the expiration of the contract, Luis Bacus died on . . . After a careful review of the entire records of this case, we
October 10, 1989. Thereafter, on March 15, 1990, the Duray are convinced that the plaintiffs-appellees validly and
spouses informed Roque Bacus, one of the heirs of Luis effectively exercised their option to buy the subject property.
Bacus, that they were willing and ready to purchase the As opined by the lower court, "the readiness and
property under the option to buy clause. They requested preparedness of the plaintiff on his part, is manifested by his
Roque Bacus to prepare the necessary documents, such as a cautionary letters, the prepared bank certification long before
Special Power of Attorney authorizing him to enter into a the date of May 31, 1990, the final day of the option, and his
contract of sale,2 on behalf of his sisters who were then filing of this suit before said date. If the plaintiff-appellee
abroad. Francisco Duray had no intention to purchase the property, he
On March 30, 1990, due to the refusal of petitioners to sell the would not have bothered to write those letters to the
property, Faustino Duray's adverse claim was annotated by defendant-appellants (which were all received by them) and
the Register of Deeds of Cebu, at the back of TCT No. 63269, neither would he be interested in having his adverse claim
covering the segregated 2,000 square meter portion of Lot annotated at the back of the T.C.T. of the subject property, two
No. 3661-A-3-B-2-A.3 (2) months before the expiration of the lease. Moreover, he
Subsequently, on April 5, 1990, Duray filed a complaint for even went to the extent of seeking the help of the Lupon
specific performance against the heirs of Luis Bacus with Tagapamayapa to compel the defendants-appellants to
the Lupon Tagapamayapa of Barangay Bulacao, asking that recognize his right to purchase the property and for them to
he be allowed to purchase the lot specifically referred to in the perform their corresponding obligation.8
lease contract with option to buy. At the hearing, Duray xxx      xxx      xxx
presented a certification4 from the manager of Standard We therefore find no merit in this appeal.
Chartered Bank, Cebu City, addressed to Luis Bacus, stating WHEREFORE, the decision appealed from is hereby
that at the request of Mr. Lawrence Glauber, a bank client, AFFIRMED.9
arrangements were being made to allow Faustino Duray to Hence, this petition where petitioners aver that the Court of
borrow funds of approximately P700,000 to enable him to Appeals gravely erred and abused its discretion in:
meet his obligations under the contract with Luis Bacus.5 I. . . . UPHOLDING THE TRIAL COURT'S RULING IN THE
Having failed to reach an agreement before the Lupon, on SPECIFIC PERFORMANCE CASE BY ORDERING
April 27, 1990, private respondents filed a complaint for PETITIONERS (DEFENDANTS THEREIN) TO EXECUTE A
specific performance with damages against petitioners before DOCUMENT OF SALE OVER THE PROPERTY IN
the Regional Trial Court, praying that the latter, (a) execute a QUESTION (WITH TCT NO. T-63269) TO THEM IN THE
deed of sale over the subject property in favor of private AMOUNT OF P675,675.00 WITHIN THIRTY (30) DAYS
respondents; (b) receive the payment of the purchase price; FROM THE DATE THE DECISION BECOMES FINAL;
and (c) pay the damages. II. . . . DISREGARDING LEGAL PRINCIPLES, SPECIFIC
On the other hand, petitioners alleged that before Luis Bacus' PROVISIONS OF LAW AND JURISPRUDENCE IN
death, private respondents conveyed to them the former's UPHOLDING THE DECISION OF THE TRIAL COURT TO
lack of interest to exercise their option because of THE EFFECT THAT PRIVATE RESPONDENTS HAD
insufficiency of funds, but they were surprised to learn of EXERCISED THEIR RIGHT OF OPTION TO BUY ON TIME;
private respondents' demand. In turn, they requested private THUS THE PRESENTATION OF THE CERTIFICATION OF
respondents to pay the purchase price in full but the latter THE BANK MANAGER OF A BANK DEPOSIT IN THE NAME
OF ANOTHER PERSON FOR LOAN TO RESPONDENTS make actual payment. Only upon petitioners' actual execution
WAS EQUIVALENT TO A VALID TENDER OF PAYMENT and delivery of the deed of sale were they required to pay. As
AND A SUFFICIENT COMPLAINCE (SIC) OF A CONDITION earlier stated, the latter was contingent upon the former.
FOR THE EXERCISE OF THE OPTION TO BUY; AND In Nietes vs. Court of Appeals, 46 SCRA 654 (1972), we held
III. . . . UPHOLDING THE TRIAL COURT'S RULING THAT that notice of the creditor's decision to exercise his option to
THE PRESENTATION OF A CASHER'S (SIC) CHECK BY buy need not be coupled with actual payment of the price, so
THE RESPONDENTS IN THE AMOUNT OF P625,000.00 long as this is delivered to the owner of the property upon
EVEN AFTER THE TERMINATION OF THE TRIAL ON THE performance of his part of the agreement. Consequently,
MERITS WITH BOTH PARTIES ALREADY HAVING RESTED since the obligation was not yet due, consignation in court of
THEIR CASE, WAS STILL VALID COMPLIANCE OF THE the purchase price was not yet required.
CONDITION FOR THE PRIVATE RESPONDENTS' Consignation is the act of depositing the thing due with the
(PLAINTIFFS THEREIN) EXERCISE OF RIGHT OF OPTION court or judicial authorities whenever the creditor cannot
TO BUY AND HAD A FORCE OF VALID AND FULL TENDER accept or refuses to accept payment and it generally requires
OF PAYMENT WITHIN THE AGREED PERIOD.10 a prior tender of payment. In instances, where no debt is due
Petitioners insist that they cannot be compelled to sell the and owing, consignation is not proper. 14 Therefore, petitioners'
disputed property by virtue of the nonfulfillment of the contention that private respondents failed to comply with their
obligation under the option contract of the private obligation under the option to buy because they failed to
respondents. actually deliver the purchase price or consign it in court before
Private respondents first aver that petitioners are unclear if the contract expired and before they execute a deed, has no
Rule 65 or Rule 45 of the Rules of Court govern their petition, leg to stand on.
and that petitioners only raised questions of facts which this Corollary, private respondents did not incur in delay when
Court cannot properly entertain in a petition for review. They they did not yet deliver payment nor make a consignation
claim that even assuming that the instant petition is one under before the expiration of the contract. In reciprocal obligations,
Rule 45, the same must be denied for the Court of Appeals neither party incurs in delay if the other does not comply or is
has correctly determined that they had validly exercised their not ready to comply in a proper manner with what is
option to buy the leased property before the contract expired. incumbent upon him. Only from the moment one of the parties
In response, petitioners state that private respondents erred in fulfills his obligation, does delay by the other begin. 15
initially classifying the instant petition as one under Rule 65 of In this case, private respondents, as early as March 15, 1990,
the Rules of Court. They argue that the petition is one under communicated to petitioners their intention to buy the property
Rule 45 where errors of the Court of Appeals, whether and they were at that time undertaking to meet their obligation
evidentiary or legal in nature, may be reviewed. before the expiration of the contract on May 31, 1990.
We agree with private respondents that in a petition for review However, petitioners refused to execute the deed of sale and
under Rule 45, only questions of law may be it was their demand to private respondents to first deliver the
raised.11 However, a close reading of petitioners' arguments money before they would execute the same which prompted
reveal the following legal issues which may properly be private respondents to institute a case for specific
entertained in the instant petition: performance in the Lupong Tagapamayapa and then in the
a) When private respondents opted to buy the property RTC. On October 30, 1990, after the case had been
covered by the lease contract with option to buy, were they submitted for decision but before the trial court rendered its
already required to deliver the money or consign it in court decision, private respondents issued a cashier's check in
before petitioner executes a deed of transfer? petitioners' favor purportedly to bolster their claim that they
b) Did private respondents incur in delay when they did not were ready to pay the purchase price. The trial court
deliver the purchase price or consign it in court on or before considered this in private respondents' favor and we believe
the expiration of the contract? that it rightly did so, because at the time the check was
On the first issue, petitioners contend that private respondents issued, petitioners had not yet executed a deed of sale nor
failed to comply with their obligation because there was expressed readiness to do so. Accordingly, as there was no
neither actual delivery to them nor consignation in court or compliance yet with what was incumbent upon petitioners
with the Municipal, City or Provincial Treasurer of the under the option to buy, private respondents had not incurred
purchase price before the contract expired. Private in delay when the cashier's check was issued even after the
respondents' bank certificate stating that arrangements were contract expired.
being made by the bank to release P700,000 as a loan to WHEREFORE, the instant petition is DENIED. The decision
private respondents cannot be considered as legal tender that dated November 29, 1996 of the Court of Appeals is hereby
may substitute for delivery of payment to petitioners nor was it AFFIRMED.
a consignation. Costs against petitioners.
Obligations under an option to buy are reciprocal SO ORDERED.
obligations.12 The performance of one obligation is
conditioned on the simultaneous fulfillment of the other G.R. No. 115117        June 8, 2000
obligation.13 In other words, in an option to buy, the payment INTEGRATED PACKAGING CORP., petitioner,
of the purchase price by the creditor is contingent upon the vs.
execution and delivery of a deed of sale by the debtor. In this COURT OF APPEALS and FIL-ANCHOR PAPER CO.,
case, when private respondents opted to buy the property, INC., respondents.
their obligation was to advise petitioners of their decision and QUISUMBING, J.:
their readiness to pay the price. They were not yet obliged to This is a petition to review the decision of the Court of
Appeals rendered on April 20, 1994 reversing the judgment of contract with Philacor. Unfortunately, petitioner failed to fully
the Regional Trial Court of Caloocan City in an action for comply with its contract with Philacor for the printing of books
recovery of sum of money filed by private respondent against VIII, IX, X and XI. Thus, Philacor demanded compensation
petitioner. In said decision, the appellate court decreed: from petitioner for the delay and damage it suffered on
WHEREFORE, in view of all the foregoing, the appealed account of petitioner's failure.
judgment is hereby REVERSED and SET ASIDE. Appellee On August 14, 1981, private respondent filed with the
[petitioner herein] is hereby ordered to pay appellant [private Regional Trial Court of Caloocan City a collection suit against
respondent herein] the sum of P763,101.70, with legal interest petitioner for the sum of P766,101.70, representing the unpaid
thereon, from the date of the filing of the Complaint, until fully purchase price of printing paper bought by petitioner on credit.
paid. In its answer, petitioner denied the material allegations of the
SO ORDERED.1 complaint. By way of counterclaim, petitioner alleged that
The RTC judgment reversed by the Court of Appeals had private respondent was able to deliver only 1,097 reams of
disposed of the complain as follows: printing paper which was short of 2,875 reams, in total
WHEREFORE, judgment is hereby rendered: disregard of their agreement; that private respondent failed to
Ordering plaintiff [herein private respondent] to pay defendant deliver the balance of the printing paper despite demand
[herein petitioner] the sum of P27,222.60 as compensatory therefor, hence, petitioner suffered actual damages and failed
and actual damages after deducting P763,101.70 (value of to realize expected profits; and that petitioner's complaint was
materials received by defendant) from P790,324.30 prematurely filed.
representing compensatory damages as defendant's After filing its reply and answer to the counterclaim, private
unrealized profits; respondent moved for admission of its supplemental
Ordering plaintiff to pay defendant the sum of P100,000.00 as complaint, which was granted. In said supplemental
moral damages; complaint, private respondent alleged that subsequent to the
Ordering plaintiff to pay the sum of P30,000.00 for attorney's enumerated purchase invoices in the original complaint,
fees; and to pay the costs of suit. petitioner made additional purchases of printing paper on
SO ORDERED.2 credit amounting to P94,200.00. Private respondent also
The facts, as culled from the records, are as follows: averred that petitioner failed and refused to pay its
Petitioner and private respondent executed on May 5, 1978, outstanding obligation although it made partial payments in
an order agreement whereby private respondent bound itself the amount of P97,200.00 which was applied to back
to deliver to petitioner 3,450 reams of printing paper, coated, 2 accounts, thus, reducing petitioner's indebtedness to
sides basis, 80 lbs., 38" x 23", short grain, worth P763,101.70.
P1,040,060.00 under the following schedule: May and June On July 5, 1990, the trial court rendered judgment declaring
1978 — 450 reams at P290.00/ream; August and September that petitioner should pay private respondent the sum of
1978 — 700 reams at P290/ream; January 1979 — 575 P763,101.70 representing the value of printing paper
reams at P307.20/ream; March 1979 — 575 reams at delivered by private respondent from June 5, 1980 to July 23,
P307.20/ream; July 1979 — 575 reams at 307.20/ream; and 1981. However, the lower court also found petitioner's
October 1979 — 575 reams at P307.20/ream. In accordance counterclaim meritorious. It ruled that were it not for the failure
with the standard operating practice of the parties, the or delay of private respondent to deliver printing paper,
materials were to be paid within a minimum of thirty days and petitioner could have sold books to Philacor and realized profit
maximum of ninety days from delivery. of P790,324.30 from the sale. It further ruled that petitioner
Later, on June 7, 1978, petitioner entered into a contract with suffered a dislocation of business on account of loss of
Philippine Appliance Corporation (Philacor) to print three contracts and goodwill as a result of private respondent's
volumes of "Philacor Cultural Books" for delivery on the violation of its obligation, for which the award of moral
following dates: Book VI, on or before November 1978; Book damages was justified.
VII, on or before November 1979 and; Book VIII, on or before On appeal, the respondent Court of Appeals reversed and set
November 1980, with a minimum of 300,000 copies at a price aside the judgment of the trial court. The appellate court
of P10.00 per copy or a total cost of P3,000,000.00. ordered petitioner to pay private respondent the sum of
As of July 30, 1979, private respondent had delivered to P763,101.70 representing the amount of unpaid printing
petitioner 1,097 reams of printing paper out of the total 3,450 paper delivered by private respondent to petitioner, with legal
reams stated in the agreement. Petitioner alleged it wrote interest thereon from the date of the filing of the complaint
private respondent to immediately deliver the balance until fully paid.4 However, the appellate court deleted the
because further delay would greatly prejudice petitioner. From award of P790,324.30 as compensatory damages as well as
June 5, 1980 and until July 23, 1981, private respondent the award of moral damages and attorney's fees, for lack of
delivered again to petitioner various quantities of printing factual and legal basis.
paper amounting to P766,101.70. However, petitioner Expectedly, petitioner filed this instant petition contending that
encountered difficulties paying private respondent said the appellate court's judgment is based on erroneous
amount. Accordingly, private respondent made a formal conclusions of facts and law. In this recourse, petitioner
demand upon petitioner to settle the outstanding account. On assigns the following errors:
July 23 and 31, 1981 and August 27, 1981, petitioner made [I]
partial payments totalling P97,200.00 which was applied to its THE COURT OF APPEALS ERRED IN CONCLUDING THAT
back accounts covered by delivery invoices dated September PRIVATE RESPONDENT DID NOT VIOLATE THE ORDER
29-30, 1980 and October 1-2, 1980.3 AGREEMENT.
Meanwhile, petitioner entered into an additional printing [II]
THE COURT OF APPEALS ERRED IN CONCLUDING THAT establish that it had paid for the printing paper covered by the
RESPONDENT IS NOT LIABLE FOR PETITIONER'S delivery invoices on time. Consequently, private respondent
BREACH OF CONTRACT WITH PHILACOR. has the right to cease making further delivery, hence the
[III] private respondent did not violate the order agreement. On
THE COURT OF APPEALS ERRED IN CONCLUDING THAT the contrary, it was petitioner which breached the agreement
PETITIONER IS NOT ENTITLED TO DAMAGES AGAINST as it failed to pay on time the materials delivered by private
PRIVATE RESPONDENT. 5 respondent. Respondent appellate court correctly ruled that
In our view, the crucial issues for resolution in this case are as private respondent did not violate the order agreement.
follows: On the second assigned error, petitioner contends that private
(1) Whether or not private respondent violated the order respondent should be held liable for petitioner's breach of
agreement, and; contract with Philacor. This claim is manifestly devoid of merit.
(2) Whether or not private respondent is liable for petitioner's As correctly held by the appellate court, private respondent
breach of contract with Philacor. cannot be held liable under the contracts entered into by
Petitioner's contention lacks factual and legal basis, hence, petitioner with Philacor. Private respondent is not a party to
bereft of merit. said agreements. It is also not a contract pour autrui.
Petitioner contends, firstly, that private respondent violated Aforesaid contracts could not affect third persons like private
the order agreement when the latter failed to deliver the respondent because of the basic civil law principle of relativity
balance of the printing paper on the dates agreed upon. of contracts which provides that contracts can only bind the
The transaction between the parties is a contract of sale parties who entered into it, and it cannot favor or prejudice a
whereby private respondent (seller) obligates itself to deliver third person, 10 even if he is aware of such contract and has
printing paper to petitioner (buyer) which, in turn, binds itself acted with knowledge thereof. 11
to pay therefor a sum of money or its equivalent (price).6 Both Indeed, the order agreement entered into by petitioner and
parties concede that the order agreement gives rise to a private respondent has not been shown as having a direct
reciprocal obligations7 such that the obligation of one is bearing on the contracts of petitioner with Philacor. As pointed
dependent upon the obligation of the other. Reciprocal out by private respondent and not refuted by petitioner, the
obligations are to be performed simultaneously, so that the paper specified in the order agreement between petitioner
performance of one is conditioned upon the simultaneous and private respondent are markedly different from the paper
fulfillment of the other.8 Thus, private respondent undertakes involved in the contracts of petitioner with
to deliver printing paper of various quantities subject to Philacor. 12 Furthermore, the demand made by Philacor upon
petitioner's corresponding obligation to pay, on a maximum petitioner for the latter to comply with its printing contract is
90-day credit, for these materials. Note that in the contract, dated February 15, 1984, which is clearly made long after
petitioner is not even required to make any deposit, down private respondent had filed its complaint on August 14, 1981.
payment or advance payment, hence, the undertaking of This demand relates to contracts with Philacor dated April 12,
private respondent to deliver the materials is conditional upon 1983 and May 13, 1983, which were entered into by petitioner
payment by petitioner within the prescribed period. Clearly, after private respondent filed the instant case.lawphi1
petitioner did not fulfill its side of the contract as its last To recapitulate, private respondent did not violate the order
payment in August 1981 could cover only materials covered agreement it had with petitioner. Likewise, private respondent
by delivery invoices dated September and October 1980. could not be held liable for petitioner's breach of contract with
There is no dispute that the agreement provides for the Philacor. It follows that there is no basis to hold private
delivery of printing paper on different dates and a separate respondent liable for damages. Accordingly, the appellate
price has been agreed upon for each delivery. It is also court did not err in deleting the damages awarded by the trial
admitted that it is the standard practice of the parties that the court to petitioner.
materials be paid within a minimum period of thirty (30) days The rule on compensatory damages is well established. True,
and a maximum of ninety (90) days from each indemnification for damages comprehends not only the loss
delivery.9 Accordingly, the private respondent's suspension of suffered, that is to say actual damages (damnum emergens),
its deliveries to petitioner whenever the latter failed to pay on but also profits which the obligee failed to obtain, referred to
time, as in this case, is legally justified under the second as compensatory damages (lucrum cessans). However, to
paragraph of Article 1583 of the Civil Code which provides justify a grant of actual or compensatory damages, it is
that: necessary to prove with a reasonable degree of certainty,
When there is a contract of sale of goods to be delivered by premised upon competent proof and on the best evidence
stated installments, which are to be separately paid for, and obtainable by the injured party, the actual amount of
the seller makes defective deliveries in respect of one or more loss. 13 In the case at bar, the trial court erroneously
installments, or the buyer neglects or refuses without just concluded that petitioner could have sold books to Philacor at
cause to take delivery of or  pay for one or more installments, the quoted selling price of P1,850,750.55 and by deducting
it depends in each case on the terms of the contract and the the production cost of P1,060,426.20, petitioner could have
circumstances of the case, whether the breach of contract is earned profit of P790,324.30. Admittedly, the evidence relied
so material as to justify the injured party in refusing to upon by the trial court in arriving at the amount are mere
proceed further and suing for damages for breach of the estimates prepared by petitioner. 14 Said evidence is highly
entire contract, or whether the breach is severable, giving rise speculative and manifestly hypothetical. It could not provide
to a claim for compensation but not to a right to treat the sufficient legal and factual basis for the award of P790,324.30
whole contract as broken. (Emphasis supplied) as compensatory damages representing petitioner's self-
In this case, as found a quo petitioner's evidence failed to serving claim of unrealized profit.
Further, the deletion of the award of moral damages is proper, document or paper executed in the exercise of their
since private respondent could not be held liable for breach of authority.1âwphi1.nêt
contract. Moral damages may be awarded when in a breach In the exercise of the above authority, on January 20, 1989,
of contract the defendant acted in bad faith, or was guilty of the heirs of the late Francisco Q. Laforteza represented by
gross negligence amounting to bad faith, or in wanton Roberto Z. Laforteza and Gonzalo Z. Laforteza, Jr. entered
disregard of his contractual obligation. 15 Finally, since the into a Memorandum of Agreement (Contract to Sell) with the
award of moral damages is eliminated, so must the award for plaintiff 2 over the subject property for the sum of SIX
attorney's fees be also deleted. 16 HUNDRED THIRTY THOUSAND PESOS (P630,000.00)
WHEREFORE, the instant petition is DENIED. The decision payable as follows:
of the Court of Appeals is AFFIRMED. Costs against (a) P30,000.00 as earnest money, to be forfeited in favor of
petitioner. the defendants if the sale is not effected due to the fault of the
SO ORDERED. plaintiff;
(b) P600,000.00 upon issuance of the new certificate of title in
G.R. No. 137552        June 16, 2000 the name of the late Francisco Q. Laforteza and upon
ROBERTO Z. LAFORTEZA, GONZALO Z. LAFORTEZA, execution of an extra-judicial settlement of the decedent's
MICHAEL Z. LAFORTEZA, DENNIS Z. LAFORTEZA, and estate with sale in favor of the plaintiff (Par. 2, Exh. "E",
LEA Z. LAFORTEZA, petitioners, record, pp. 335-336).
vs. Significantly, the fourth paragraph of the Memorandum of
ALONZO MACHUCA, respondent. Agreement (Contract to Sell) dated January 20, 1989 (Exh.
GONZAGA-REYES, J.: "E", supra.) contained a provision as follows:
This Petition for Review on Certiorari  seeks the reversal of . . . . Upon issuance by the proper Court of the new title, the
the Decision of the Court of Appeals 1 in CA G.R. CV No. BUYER-LESSEE shall be notified in writing and said BUYER-
147457 entitled "ALONZO MACHUCA versus ROBERTO Z. LESSEE shall have thirty (30) days to produce the balance of
LAFORTEZA, GONZALO Z. LAFORTEZA, LEA ZULUETA- P600,000.00 which shall be paid to the SELLER-LESSORS
LAFORTEZA, MICHAEL Z. LAFORTEZA, and DENNIS Z. upon the execution of the Extrajudicial Settlement with sale.
LAFORTEZA". On January 20, 1989, plaintiff paid the earnest money of
The following facts as found by the Court of Appeals are THIRTY THOUSAND PESOS (P30,000.00), plus rentals for
undisputed: the subject property (Exh. "F", Plaintiff, record, p. 339).
The property involved consists of a house and lot located at On September 18, 1998 3 , defendant heirs, through their
No. 7757 Sherwood Street, Marcelo Green Village, counsel wrote a letter (Exh. 1, Defendants, record, p. 370) to
Parañaque, Metro Manila, covered by Transfer Certificate of the plaintiff furnishing the latter a copy of the reconstituted title
Title (TCT) No. (220656) 8941 of the Registered of Deeds of to the subject property, advising him that he had thirty (3)
Parañaque (Exhibit "D", Plaintiff, record, pp. 331-332). The days to produce the balance of SIX HUNDRED PESOS (sic)
subject property is registered in the name of the late (P600,000.00) under the Memorandum of Agreement which
Francisco Q. Laforteza, although it is conjugal in nature plaintiff received on the same date.
(Exhibit "8", Defendants, record pp. 331-386). On October 18, 1989, plaintiff sent the defendant heirs a letter
On August 2, 1988, defendant Lea Zulueta-Laforteza requesting for an extension of the THIRTY (30) DAYS
executed a Special Power of Attorney in favor of defendants deadline up to November 15, 1989 within which to produce
Roberto Z. Laforteza and Gonzalo Z. Laforteza, Jr., appointing the balance of SIX HUNDRED THOUSAND PESOS
both as her Attorney-in-fact authorizing them jointly to sell the (P600,000.00) (Exh. "G", Plaintiff, record, pp. 341-342).
subject property and sign any document for the settlement of Defendant Roberto Z. Laforteza, assisted by his counsel Atty.
the estate of the late Francisco Q. Laforteza (Exh. "A", Romeo L. Gutierrez, signed his conformity to the plaintiff's
Plaintiff, record, pp. 323-325). letter request (Exh. "G-1 and "G-2", Plaintiff, record, p. 342).
Likewise on the same day, defendant Michael Z. Laforteza The extension, however, does not appear to have been
executed a Special Power of Attorney in favor of defendants approved by Gonzalo Z. Laforteza, the second attorney-in-fact
Roberto Z. Laforteza and Gonzalo Laforteza, Jr., likewise, as his conformity does not appear to have been secured.
granting the same authority (Exh. "B", record, pp. 326-328) On November 15, 1989, plaintiff informed the defendant heirs,
Both agency instruments contained a provision that in any through defendant Roberto Z. Laforteza, that he already had
document or paper to exercise authority granted, the the balance of SIX HUNDRED THOUSAND PESOS
signature of both attorneys- in-fact must be affixed. (P600,000.00) covered by United Coconut Planters Bank
On October 27, 1988, defendant Dennis Z. Laforteza Manager's Check No. 000814 dated November 15, 1989
executed a Special Power of Attorney in favor of defendant (TSN, August 25, 1992, p. 11; Exhs. "H", record, pp. 343-344;
Roberto Z. Laforteza for the purpose of selling the subject "M", records p. 350; and "N", record, p. 351). However, the
property (Exh. "C", Plaintiff, record, pp. 329-330). A year later, defendants, refused to accept the balance (TSN, August 24,
on October 30, 1989, Dennis Z. Laforteza executed another 1992, p. 14; Exhs. "M-1", Plaintiff, record, p. 350; and "N-1",
Special Power of Attorney in favor of defendants Roberto Z. Plaintiff, record, p. 351). Defendant Roberto Z. Laforteza had
Laforteza and Gonzalo Laforteza, Jr. naming both attorneys- told him that the subject property was no longer for sale (TSN,
in-fact for the purpose of selling the subject property and October 20, 1992, p. 19; Exh. "J", record, p. 347).
signing any document for the settlement of the estate of the On November 20, 1998 4 , defendants informed plaintiff that
late Francisco Q. Laforteza. The subsequent agency they were canceling the Memorandum of Agreement
instrument (Exh, "2", record, pp. 371-373) contained similar (Contract to Sell) in view of the plaintiff's failure to comply with
provisions that both attorneys-in-fact should sign any his contractual obligations (Exh. "3").
Thereafter, plaintiff reiterated his request to tender payment of Appeals erred in ruling that rescission of the contract was
the balance of SIX HUNDRED THOUSAND PESOS already out of the question. Rescission implies that a contract
(P600,000.00). Defendants, however, insisted on the of sale was perfected unlike the Memorandum of Agreement
rescission of the Memorandum of Agreement. Thereafter, in question which as previously stated is allegedly only an
plaintiff filed the instant action for specific performance. The option contract.
lower court rendered judgment on July 6, 1994 in favor of the Petitioner adds that at most, the Memorandum of Agreement
plaintiff, the dispositive portion of which reads: (Contract to Sell) is a mere contract to sell, as indicated in its
WHEREFORE, judgment is hereby rendered in favor of title. The obligation of the petitioners to sell the property to the
plaintiff Alonzo Machuca and against the defendant heirs of respondent was conditioned upon the issuance of a new
the late Francisco Q. Laforteza, ordering the said defendants. certificate of title and the execution of the extrajudicial
(a) To accept the balance of P600,000.00 as full payment of partition with sale and payment of the P600,000.00. This is
the consideration for the purchase of the house and lot why possession of the subject property was not delivered to
located at No. 7757 Sherwood Street, Marcelo Green Village, the respondent as the owner of the property but only as the
Parañaque, Metro Manila, covered by Transfer Certificate of lessee thereof. And the failure of the respondent to pay the
Title No. (220656) 8941 of the Registry of Deeds of Rizal purchase price in full prevented the petitioners' obligation to
Parañaque, Branch; convey title from acquiring obligatory force.
(b) To execute a registrable deed of absolute sale over the Petitioners also allege that assuming for the sake of argument
subject property in favor of the plaintiff; that a contract of sale was indeed perfected, the Court of
(c) Jointly and severally to pay the plaintiff the sum of Appeals still erred in holding that respondent's failure to pay
P20,000.00 as attorney's fees plus cost of suit. the purchase price of P600,000.00 was only a "slight or
SO ORDERED. (Rollo, pp. 74-75). 5 casual breach".
Petitioners appealed to the Court of Appeals, which affirmed The petitioners also claim that the Court of Appeals erred in
with modification the decision of the lower court; the ruling that they were not ready to comply with their obligation
dispositive portion of the Decision reads: to execute the extrajudicial settlement. The Power of Attorney
WHEREFORE, the questioned decision of the lower court is to execute a Deed of Sale made by Dennis Z. Laforteza was
hereby AFFIRMED with the MODIFICATION that defendant sufficient and necessarily included the power to execute an
heirs Lea Zulueta-Laforteza, Michael Z. Laforteza, Dennis Z. extrajudicial settlement. At any rate, the respondent is
Laforteza and Roberto Z. Laforteza including Gonzalo Z. estopped from claiming that the petitioners were not ready to
Laforteza, Jr. are hereby ordered to pay jointly and severally comply with their obligation for he acknowledged the
the sum of FIFTY THOUSAND PESOS (P50,000.00) as moral petitioners' ability to do so when he requested for an
damages. extension of time within which to pay the purchase price. Had
SO ORDERED. 6 he truly believed that the petitioners were not ready, he would
Motion for Reconsideration was denied but the Decision was not have needed to ask for said extension.
modified so as to absolve Gonzalo Z. Laforteza, Jr. from Finally, the petitioners allege that the respondent's
liability for the payment of moral damages. 7 Hence this uncorroborated testimony that third persons offered a higher
petition wherein the petitioners raise the following issues: price for the property is hearsay and should not be given any
I. WHETHER THE TRIAL AND APPELLATE COURTS evidentiary weight. Thus, the order of the lower court
CORRECTLY CONSTRUED THE MEMORANDUM OF awarding moral damages was without any legal basis.
AGREEMENT AS IMPOSING RECIPROCAL OBLIGATIONS. The appeal is bereft of merit.
II. WHETHER THE COURTS A QUO  CORRECTLY RULED A perusal of the Memorandum Agreement shows that the
THAT RESCISSION WILL NOT LIE IN THE INSTANT CASE. transaction between the petitioners and the respondent was
III. WHETHER THE RESPONDENT IS UNDER ESTOPPEL one of sale and lease. The terms of the agreement read:
FROM RAISING THE ALLEGED DEFECT IN THE SPECIAL 1. For and in consideration of the sum of PESOS: SIX
POWER OF ATTORNEY DATED 30 OCTOBER 1989 HUNDRED THIRTY THOUSAND (P630,000.00) payable in a
EXECUTED BY DENNIS LAFORTEZA. manner herein below indicated, SELLER-LESSOR hereby
IV. SUPPOSING EX GRATIA ARGUMENTI  THE agree to sell unto BUYER-LESSEE the property described in
MEMORANDUM OF AGREEMENT IMPOSES RECIPROCAL the first WHEREAS of this Agreement within six (6) months
OBLIGATIONS, WHETHER THE PETITIONERS MAY BE from the execution date hereof, or upon issuance by the Court
COMPELLED TO SELL THE SUBJECT PROPERTY WHEN of a new owner's certificate of title and the execution of
THE RESPONDENT FAILED TO MAKE A JUDICIAL extrajudicial partition with sale of the estate of Francisco
CONSIGNATION OF THE PURCHASE PRICE? Laforteza, whichever is earlier;
V. WHETHER THE PETITIONERS ARE IN BAD FAITH SO 2. The above-mentioned sum of PESOS: SIX HUNDRED
TO AS MAKE THEM LIABLE FOR MORAL DAMAGES? 8 THIRTY THOUSAND (P630,000.00) shall be paid in the
The petitioners contend that the Memorandum of Agreement following manner:
is merely a lease agreement with "option to purchase". As it P30,000.00 — as earnest money and as consideration for this
was merely an option, it only gave the respondent a right to Agreement, which amount shall be forfeited in favor of
purchase the subject property within a limited period without SELLER-LESSORS if the sale is not effected because of the
imposing upon them any obligation to purchase it. Since the fault or option of BUYER-LESSEE;
respondent's tender of payment was made after the lapse of P600,000.00 — upon the issuance of the new certificate of
the option agreement, his tender did not give rise to the title in the name of the late Francisco Laforteza and upon the
perfection of a contract of sale. execution of an Extrajudicial Settlement of his estate with sale
It is further maintained by the petitioners that the Court of in favor of BUYER-LESSEE free from lien or any
encumbrances. the lost title was not yet replaced and the extrajudicial partition
3. Parties reasonably estimate that the issuance of a new title was not yet executed, the respondent would no longer be
in place of the lost one, as well as the execution of required to pay rentals and would continue to occupy and use
extrajudicial settlement of estate with sale to herein BUYER- the premises until the subject condition was complied with the
LESSEE will be completed within six (6) months from the petitioners.
execution of this Agreement. It is therefore agreed that during The six-month period during which the respondent would be
the six months period, BUYER-LESSEE will be leasing the in possession of the property as lessee, was clearly not a
subject property for six months period at the monthly rate of period within which to exercise an option. An option is a
PESOS: THREE THOUSAND FIVE HUNDRED contract granting a privilege to buy or sell within an agreed
(P3,500.00). Provided however, that if the issuance of new time and at a determined price. An option contract is a
title and the execution of Extrajudicial Partition is completed separate and distinct contract from that which the parties may
prior to the expiration of the six months period, BUYER- enter into upon the consummation of the option. 13 An option
LESSEE shall only be liable for rentals for the corresponding must be supported by consideration.14 An option contract is
period commencing from his occupancy of the premises to the governed by the second paragraph of Article 1479 of the Civil
execution and completion of the Extrajudicial Settlement of Code 15 , which reads:
the estate, provided further that if after the expiration of six (6) Art. 1479. . . .
months, the lost title is not yet replaced and the extra judicial An accepted unilateral promise to buy or to sell a determinate
partition is not executed, BUYER-LESSEE shall no longer be thing for a price certain is binding upon the promissor if the
required to pay rentals and shall continue to occupy, and use promise is supported by a consideration distinct from the
the premises until subject condition is complied by SELLER- price.
LESSOR; In the present case, the six-month period merely delayed the
4. It is hereby agreed that within reasonable time from the demandability of the contract of sale and did not determine its
execution of this Agreement and the payment by BUYER- perfection for after the expiration of the six-month period,
LESSEE of the amount of P30,000.00 as herein above there was an absolute obligation on the part of the petitioners
provided, SELLER-LESSORS shall immediately file the and the respondent to comply with the terms of the sale. The
corresponding petition for the issuance of a new title in lieu of parties made a "reasonable estimate" that the reconstitution
the lost one in the proper Courts. Upon issuance by the the lost title of the house and lot would take approximately six
proper Courts of the new title, the BUYER-LESSEE shall have months and thus presumed that after six months, both parties
thirty (30) days to produce the balance of P600,000.00 which would be able to comply with what was reciprocally incumbent
shall be paid to the SELLER-LESSORS upon the execution of upon them. The fact that after the expiration of the six-month
the Extrajudicial Settlement with sale. 9 period, the respondent would retain possession of the house
A contract of sale is a consensual contract and is perfected at and lot without need of paying rentals for the use therefor,
the moment there is a meeting of the minds upon the thing clearly indicated that the parties contemplated that ownership
which is the object of the contract and upon the over the property would already be transferred by that time.
price. 10 From that moment the parties may reciprocally The issuance of the new certificate of title in the name of the
demand performance subject to the provisions of the law late Francisco Laforteza and the execution of an extrajudicial
governing the form of contracts. 11 The elements of a valid settlement of his estate was not a condition which determined
contract of sale under Article 1458 of the Civil Code are (1) the perfection of the contract of sale. Petitioners' contention
consent or meeting of the minds; (2) determinate subject that since the condition was not met, they no longer had an
matter and (3) price certain money or its equivalent. 12 obligation to proceed with the sale of the house and lot is
In the case at bench, there was a perfected agreement unconvincing. The petitioners fail to distinguish between a
between the petitioners and the respondent whereby the condition imposed upon the perfection of the contract and a
petitioners obligated themselves to transfer the ownership of condition imposed on the performance of an obligation.
and deliver the house and lot located at 7757 Sherwood St., Failure to comply with the first condition results in the failure
Marcelo Green Village, Parañaque and the respondent to pay of a contract, while the failure to comply with the second
the price amounting to six hundred thousand pesos condition only gives the other party the option either to refuse
(P600,000.00). All the elements of a contract of sale were to proceed with the sale or to waive the condition. Thus, Art.
thus present. However, the balance of the purchase price was 1545 of the Civil Code states:
to be paid only upon the issuance of the new certificate of title Art. 1545. Where the obligation of either party to a contract of
in lieu of the one in the name of the late Francisco Laforteza sale is subject to any condition which is not performed, such
and upon the execution of an extrajudicial settlement of his party may refuse to proceed with the contract or he may
estate. Prior to the issuance of the "reconstituted" title, the waive performance of the condition. If the other party has
respondent was already placed in possession of the house promised that the condition should happen or be performed,
and lot as lessee thereof for six months at a monthly rate of such first mentioned party may also treat the nonperformance
three thousand five hundred pesos (P3,500.00). It was of the condition as a breach of warranty.
stipulated that should the issuance of the new title and the Where the ownership in the things has not passed, the buyer
execution of the extrajudicial settlement be completed prior to may treat the fulfillment by the seller of his obligation to
expiration of the six-month period, the respondent would be deliver the same as described and as warranted expressly or
liable only for the rentals pertaining to the period commencing by implication in the contract of sale as a condition of the
from the date of the execution of the agreement up to the obligation of the buyer to perform his promise to accept and
execution of the extrajudicial settlement. It was also expressly pay for the thing. 16
stipulated that if after the expiration of the six month period, In the case at bar, there was already a perfected contract. The
condition was imposed only on the performance of the nearly eight months after the execution of the Memorandum
obligations contained therein. Considering however that the of Agreement when the petitioners informed the respondent
title was eventually "reconstituted" and that the petitioners that they already had a copy of the reconstituted title and
admit their ability to execute the extrajudicial settlement of demanded the payment of the balance of the purchase price.
their father's estate, the respondent had a right to demand The respondent could not therefore be considered in delay for
fulfillment of the petitioners' obligation to deliver and transfer in reciprocal obligations, neither party incurs in delay if the
ownership of the house and lot. other party does not comply or is not ready to comply in a
What further militates against petitioners' argument that they proper manner with what was incumbent upon him. 24
did not enter into a contract or sale is the fact that the Even assuming for the sake of argument that the petitioners
respondent paid thirty thousand pesos (P30,000.00) as were ready to comply with their obligation, we find that
earnest money. Earnest money is something of value to show rescission of the contract will still not prosper. The rescission
that the buyer was really in earnest, and given to the seller to of a sale of an immovable property is specifically governed by
bind the bargain.17 Whenever earnest money is given in a Article 1592 of the New Civil Code, which reads:
contract of sale, it is considered as part of the purchase price In the sale of immovable property, even though it may have
and proof of the perfection of the contract. 18 been stipulated that upon failure to pay the price at the time
We do not subscribe to the petitioners' view that the agreed upon the rescission of the contract shall of right take
Memorandum Agreement was a contract to sell. There is place, the vendee may pay, even after the expiration of the
nothing contained in the Memorandum Agreement from which period, as long as no demand for rescission of the contract
it can reasonably be deduced that the parties intended to has been made upon him either judicially or by a notarial act.
enter into a contract to sell, i.e. one whereby the prospective After the demand, the court may not grant him a new term. 25
seller would explicitly reserve the transfer of title to the It is not disputed that the petitioners did not make a judicial or
prospective buyer, meaning, the prospective seller does not notarial demand for rescission.1avvphi1 The November 20,
as yet agree or consent to transfer ownership of the property 1989 letter of the petitioners informing the respondent of the
subject of the contract to sell until the full payment of the automatic rescission of the agreement did not amount to a
price, such payment being a positive suspensive condition, demand for rescission, as it was not notarized. 26 It was also
the failure of which is not considered a breach, casual or made five days after the respondent's attempt to make the
serious, but simply an event which prevented the obligation payment of the purchase price. This offer to pay prior to the
from acquiring any obligatory force. 19 There is clearly no demand for rescission is sufficient to defeat the petitioners'
express reservation of title made by the petitioners over the right under article 1592 of the Civil Code. 27 Besides, the
property, or any provision which would impose non-payment Memorandum Agreement between the parties did not contain
of the price as a condition for the contract's entering into a clause expressly authorizing the automatic cancellation of
force. Although the memorandum agreement was also the contract without court intervention in the event that the
denominated as a "Contract to Sell", we hold that the parties terms thereof were violated. A seller cannot unilaterally and
contemplated a contract of sale. A deed of sale is absolute in extrajudicially rescind a contract or sale where there is no
nature although denominated a conditional sale in the express stipulation authorizing him to extrajudicially
absence of a stipulation reserving title in the petitioners until rescind. 28 Neither was there a judicial demand for the
full payment of the purchase price. 20 In such cases, rescission thereof. Thus, when the respondent filed his
ownership of the thing sold passes to the vendee upon actual complaint for specific performance, the agreement was still in
or constructive delivery thereof. 21 The mere fact that the force inasmuch as the contract was not yet rescinded. At any
obligation of the respondent to pay the balance of the rate, considering that the six-month period was merely an
purchase price was made subject to the condition that the approximation of the time if would take to reconstitute the lost
petitioners first deliver the reconstituted title of the house and title and was not a condition imposed on the perfection of the
lot does not make the contract a contract to sell for such contract and considering further that the delay in payment
condition is not inconsistent with a contract of sale. 22 was only thirty days which was caused by the respondents
The next issue to be addressed is whether the failure of the justified but mistaken belief that an extension to pay was
respondent to pay the balance of the purchase price within granted to him, we agree with the Court of Appeals that the
the period allowed is fatal to his right to enforce the delay of one month in payment was a mere casual breach
agreement. that would not entitle the respondents to rescind the contract.
We rule in the negative. Rescission of a contract will not be permitted for a slight or
Admittedly, the failure of the respondent to pay the balance of casual breach, but only such substantial and fundamental
the purchase price was a breach of the contract and was a breach as would defeat the very object of the parties in
ground for rescission thereof. The extension of thirty (30) days making the agreemant. 29
allegedly granted to the respondent by Roberto Z. Laforteza Petitioners' insistence that the respondent should have
(assisted by his counsel Attorney Romeo Gutierrez) was consignated the amount is not determinative of whether
correctly found by the Court of Appeals to be ineffective respondent's action for specific performance will lie.
inasmuch as the signature of Gonzalo Z. Laforteza did not Petitioners themselves point out that the effect of cansignation
appear thereon as required by the Special Powers of is to extinguish the obligation. It releases the debtor from
Attorney. 23 However, the evidence reveals that after the responsibility therefor. 30 The failure of the respondent to
expiration of the six-month period provided for in the contract, consignate the P600,000.00 is not tantamount to a breach of
the petitioners were not ready to comply with what was the contract for by the fact of tendering payment, he was
incumbent upon them, i.e. the delivery of the reconstituted title willing and able to comply with his obligation.
of the house and lot. It was only on September 18, 1989 or The Court of Appeals correctly found the petitioners guilty of
bad faith and awarded moral damages to the respondent. As agreement.
found by the said Court, the petitioners refused to comply The contract of the parties is in writing. It is found principally in
with, their obligation for the reason that they were offered a the documents, Exhibits F and G. The First mentioned exhibit
higher price therefor and the respondent was even offered is a letter addressed by the administrator of the Hawaiian-
P100,000.00 by the petitioners' lawyer, Attorney Gutierrez, to Philippine Co. to Song Fo & Company on December 13,
relinquish his rights over the property. The award of moral 1922. It reads:
damages is in accordance with Article 1191 31 of the Civil
Code pursuant to Article 2220 which provides that moral
damages may be awarded in case of breach of contract SILAY, OCC. NEGROS, P.I.
where the defendant acted in bad faith. The amount awarded        December 13, 1922
depends on the discretion of the court based on the
circumstances of each Messrs. SONG FO AND CO.
case. 32 Under the circumstances, the award given by the Iloilo, Iloilo.
Court of Appeals amounting to P50,000.00 appears to us to DEAR SIRS: Confirming our conversation we had today with
be fair and reasonable. your Mr. Song Fo, who visited this Central, we wish to state as
ACCORDINGLY, the decision of the Court of Appeals in CA follows:
G.R. CV No. 47457 is AFFIRMED and the instant petition is He agreed to the delivery of 300,000 gallons of molasses at
hereby DENIED. the same price as last year under the same condition, and the
No pronouncement as to costs. same to start after the completion of our grinding season. He
SO ORDERED. requested if possible to let you have molasses during
January, February and March or in other words, while we are
G.R. No. 23769      September 16, 1925 grinding, and we agreed with him that we would to the best of
SONG FO & COMPANY, plaintiff-appellee, our ability, altho we are somewhat handicapped. But we
vs. believe we can let you have 25,000 gallons during each of the
HAWAIIAN PHILIPPINE CO., defendant-appellant. milling months, altho it interfere with the shipping of our own
Hilado and Hilado, Ross, Lawrence and Selph and Antonio T. and planters sugars to Iloilo. Mr. Song Fo also asked if we
Carrascoso, Jr., for appellant. could supply him with another 100,000 gallons of molasses,
Arroyo, Gurrea and Muller for appellee. and we stated we believe that this is possible and will do our
best to let you have these extra 100,000 gallons during the
MALCOLM, J.: next year the same to be taken by you before November 1st,
In the court of First Instance of Iloilo, Song Fo & Company, 1923, along with the 300,000, making 400,000 gallons in all.
plaintiff, presented a complaint with two causes of action for Regarding the payment for our molasses, Mr. Song Fo gave
breach of contract against the Hawaiian-Philippine Co., us to understand that you would pay us at the end of each
defendant, in which judgment was asked for P70,369.50, with month for molasses delivered to you.
legal interest, and costs. In an amended answer and cross- Hoping that this is satisfactory and awaiting your answer
complaint, the defendant set up the special defense that since regarding this matter, we remain.
the plaintiff had defaulted in the payment for the molasses Yours very truly,
delivered to it by the defendant under the contract between
the parties, the latter was compelled to cancel and rescind the
said contract. The case was submitted for decision on a HAWAIIAN-PHILIPPINE COMPANY
stipulation of facts and the exhibits therein mentioned. The    BY R. C. PITCAIRN
judgment of the trial court condemned the defendant to pay to     Administrator.
the plaintiff a total of P35,317.93, with legal interest from the
date of the presentation of the complaint, and with costs.
From the judgment of the Court of First Instance the Exhibit G is the answer of the manager of Song Fo &
defendant only has appealed. In this court it has made the Company to the Hawaiian-Philippine Co. on December 16,
following assignment of errors: "I. The lower court erred in 1922. This letter reads:
finding that appellant had agreed to sell to the appellee
400,000, and not only 300,000, gallons of molasses. II. The December 16th, 1922.
lower court erred in finding that the appellant rescinded
without sufficient cause the contract for the sale of molasses
executed by it and the appellee. III. The lower court erred in Messrs. HAWAIIAN-PHILIPPINE CO.,
rendering judgment in favor of the appellee and not in favor of          Silay, Neg. Occ., P.I.
the appellant in accordance with the prayer of its answer and DEAR SIRS: We are in receipt of your favours dated the 9th
cross-complaint. IV. The lower court erred in denying and the 13th inst. and understood all their contents.
appellant's motion for a new trial." The specified errors raise In connection to yours of the 13th inst. we regret to hear that
three questions which we will consider in the order suggested you mentioned Mr. Song Fo the one who visited your Central,
by the appellant. but it was not for he was Mr. Song Heng, the representative
1. Did the defendant agree to sell to the plaintiff 400,000 and the manager of Messrs. Song Fo & Co.
gallons of molasses or 300,000 gallons of molasses? The trial With reference to the contents of your letter dated the 13th
court found the former amount to be correct. The appellant inst. we confirm all the arrangements you have stated and in
contends that the smaller amount was the basis of the order to make the contract clear, we hereby quote below our
old contract as amended, as per our new arrangements. Company dated April 2, 1923, is of a similar tenor. Exhibit P, a
(a) Price, at 2 cents per gallon delivered at the central. communication sent direct by the Hawaiian-Philippine Co. to
(b) All handling charges and expenses at the central and at Song Fo & Company on April 2, 1923, by which the Hawaiian-
the dock at Mambaguid for our account. Philippine Co. gave notice of the termination of the contract,
(c) For services of one locomotive and flat cars necessary for gave as the reason for the rescission, the breach by Song Fo
our six tanks at the rate of P48 for the round trip dock to & Company of this condition: "You will recall that under the
central and central to dock. This service to be restricted to arrangements made for taking our molasses, you were to
one trip for the six tanks. meet our accounts upon presentation and at each delivery."
Yours very truly, Not far removed from this statement, is the allegation of
plaintiff in its complaint that "plaintiff agreed to pay defendant,
at the end of each month upon presentation accounts."
   SONG FO & COMPANY Resolving such ambiguity as exists and having in mind
By __________________________ ordinary business practice, a reasonable deduction is that
             Manager. Song Fo & Company was to pay the Hawaiian-Philippine Co.
upon presentation of accounts at the end of each month.
We agree with appellant that the above quoted Under this hypothesis, Song Fo & Company should have paid
correspondence is susceptible of but one interpretation. The for the molasses delivered in December, 1922, and for which
Hawaiian-Philippine Co. agreed to deliver to Song Fo & accounts were received by it on January 5, 1923, not later
Company 300,000 gallons of molasses. The Hawaiian- than January 31 of that year. Instead, payment was not made
Philippine Co. also believed it possible to accommodate Song until February 20, 1923. All the rest of the molasses was paid
Fo & Company by supplying the latter company with an extra for either on time or ahead of time.
100,000 gallons. But the language used with reference to the The terms of payment fixed by the parties are controlling. The
additional 100,000 gallons was not a definite promise. Still time of payment stipulated for in the contract should be
less did it constitute an obligation. treated as of the essence of the contract. Theoretically,
If Exhibit T relied upon by the trial court shows anything, it is agreeable to certain conditions which could easily be
simply that the defendant did not consider itself obliged to imagined, the Hawaiian-Philippine Co. would have had the
deliver to the plaintiff molasses in any amount. On the other right to rescind the contract because of the breach of Song Fo
hand, Exhibit A, a letter written by the manager of Song Fo & & Company. But actually, there is here present no outstanding
Company on October 17, 1922, expressly mentions an fact which would legally sanction the rescission of the contract
understanding between the parties of a contract for P300,000 by the Hawaiian-Philippine Co.
gallons of molasses. The general rule is that rescission will not be permitted for a
We sustain appellant's point of view on the first question and slight or casual breach of the contract, but only for such
rule that the contract between the parties provided for the breaches as are so substantial and fundamental as to defeat
delivery by the Hawaiian-Philippine Co. to song Fo & the object of the parties in making the agreement. A delay in
Company of 300,000 gallons of molasses. payment for a small quantity of molasses for some twenty
2. Had the Hawaiian-Philippine Co. the right to rescind the days is not such a violation of an essential condition of the
contract of sale made with Song Fo & Company? The trial contract was warrants rescission for non-performance. Not
judge answers No, the appellant Yes. only this, but the Hawaiian-Philippine Co. waived this
Turning to Exhibit F, we note this sentence: "Regarding the condition when it arose by accepting payment of the overdue
payment for our molasses, Mr. Song Fo (Mr. Song Heng) accounts and continuing with the contract. Thereafter, Song
gave us to understand that you would pay us at the end of Fo & Company was not in default in payment so that the
each month for molasses delivered to you." In Exhibit G, we Hawaiian-Philippine co. had in reality no excuse for writing its
find Song Fo & Company stating that they understand the letter of April 2, 1923, cancelling the contract. (Warner, Barnes
contents of Exhibit F, and that they confirm all the & Co. vs. Inza [1922], 43 Phil., 505.)
arrangements you have stated, and in order to make the We rule that the appellant had no legal right to rescind the
contract clear, we hereby quote below our old contract as contract of sale because of the failure of Song Fo & Company
amended, as per our new arrangements. (a) Price, at 2 cents to pay for the molasses within the time agreed upon by the
per gallon delivered at the central." In connection with the parties. We sustain the finding of the trial judge in this respect.
portion of the contract having reference to the payment for the 3. On the basis first, of a contract for 300,000 gallons of
molasses, the parties have agree on a table showing the date molasses, and second, of a contract imprudently breached by
of delivery of the molasses, the amount and date thereof, the the Hawaiian-Philippine Co., what is the measure of
date of receipt of account by plaintiff, and date of payment. damages? We again turn to the facts as agreed upon by the
The table mentioned is as follows: parties.
The first cause of action of the plaintiff is based on the greater
Some doubt has risen as to when Song Fo & Company was expense to which it was put in being compelled to secure
expected to make payments for the molasses delivered. molasses from other sources. Three hundred thousand
Exhibit F speaks of payments "at the end of each month." gallons of molasses was the total of the agreement, as we
Exhibit G is silent on the point. Exhibit M, a letter of March 28, have seen. As conceded by the plaintiff, 55,006 gallons of
1923, from Warner, Barnes & Co., Ltd., the agent of the molasses were delivered by the defendant to the plaintiff
Hawaiian-Philippine Co. to Song Fo & Company, mentions before the breach. This leaves 244,994 gallons of molasses
"payment on presentation of bills for each delivery." Exhibit O, undelivered which the plaintiff had to purchase in the open
another letter from Warner, Barnes & Co., Ltd. to Song Fo & market. As expressly conceded by the plaintiff at page 25 of
its brief, 100,000 gallons of molasses were secured from the and MANUEL NIETO, JR., defendants-appellees.
Central North Negros Sugar Co., Inc., at two centavos a Felipe Torres and Associates for plaintiffs-appellants.
gallon. As this is the same price specified in the contract V.E. Del Rosario & Associates for defendant-appellee M.
between the plaintiff and the defendant, the plaintiff Nieto, Jr.
accordingly suffered no material loss in having to make this A.R. Naravasa & Pol Tiglao, Jr. for defendant-appellee
purchase. So 244,994 gallons minus the 100,000 gallons just Interphil Promotions, Inc.
mentioned leaves as a result 144,994 gallons. As to this RESOLUTION
amount, the plaintiff admits that it could have secured it and
more from the Central Victorias Milling Company, at three and
one-half centavos per gallon. In other words, the plaintiff had FERNAN, J.:
to pay the Central Victorias Milling company one and one-half This is an appeal interposed by Solomon Boysaw and Alfredo
centavos a gallon more for the molasses than it would have Yulo, Jr., from the decision dated July 25, 1963 and other
had to pay the Hawaiian-Philippine Co. Translated into pesos rulings and orders of the then Court of First Instance [CFI] of
and centavos, this meant a loss to the plaintiff of Rizal, Quezon City, Branch V in Civil Case No. Q-5063,
approximately P2,174.91. As the conditions existing at the entitled "Solomon Boysaw and Alfredo M. Yulo, Jr., Plaintiffs
central of the Hawaiian-Philippine Co. may have been versus Interphil Promotions, Inc., Lope Sarreal, Sr. and
different than those found at the Central North Negros Sugar Manuel Nieto, Jr., Defendants," which, among others, ordered
Co., Inc., and the Central Victorias Milling Company, and as them to jointly and severally pay defendant-appellee Manuel
not alone through the delay but through expenses of Nieto, Jr., the total sum of P25,000.00, broken down into
transportation and incidental expenses, the plaintiff may have P20,000.00 as moral damages and P5,000.00 as attorney's
been put to greater cost in making the purchase of the fees; the defendants-appellees Interphil Promotions, Inc. and
molasses in the open market, we would concede under the Lope Sarreal, Sr., P250,000.00 as unrealized profits,
first cause of action in round figures P3,000. P33,369.72 as actual damages and P5,000.00 as attorney's
The second cause of action relates to lost profits on account fees; and defendant-appellee Lope Sarreal, Sr., the additional
of the breach of the contract. The only evidence in the record amount of P20,000.00 as moral damages aside from costs.
on this question is the stipulation of counsel to the effect that The antecedent facts of the case are as follows:
had Mr. Song Heng, the manager of Song Fo & Company, On May 1, 1961, Solomon Boysaw and his then Manager,
been called as a witness, he would have testified that the Willie Ketchum, signed with Interphil Promotions, Inc.
plaintiff would have realized a profit of P14,948.43, if the represented by Lope Sarreal, Sr., a contract to engage
contract of December 13, 1922, had been fulfilled by the Gabriel "Flash" Elorde in a boxing contest for the junior
defendant. Indisputably, this statement falls far short of lightweight championship of the world.
presenting proof on which to make a finding as to damages. It was stipulated that the bout would be held at the Rizal
In the first place, the testimony which Mr. Song Heng would Memorial Stadium in Manila on September 30, 1961 or not
have given undoubtedly would follow the same line of thought later than thirty [30] days thereafter should a postponement
as found in the decision of the trial court, which we have be mutually agreed upon, and that Boysaw would not, prior to
found to be unsustainable. In the second place, had Mr. Song the date of the boxing contest, engage in any other such
Heng taken the witness-stand and made the statement contest without the written consent of Interphil Promotions,
attributed to him, it would have been insufficient proof of the Inc.
allegations of the complaint, and the fact that it is a part of the On May 3, 1961, a supplemental agreement on certain details
stipulation by counsel does not change this result. And lastly, not covered by the principal contract was entered into by
the testimony of the witness Song Heng, it we may dignify it Ketchum and Interphil. Thereafter, Interphil signed Gabriel
as such, is a mere conclusion, not a proven fact. As to what "Flash" Elorde to a similar agreement, that is, to engage
items up the more than P14,000 of alleged lost profits, Boysaw in a title fight at the Rizal Memorial Stadium on
whether loss of sales or loss of customers, or what not, we September 30, 1961.
have no means of knowing. On June 19, 1961, Boysaw fought and defeated Louis Avila in
We rule that the plaintiff is entitled to recover damages from a ten-round non-title bout held in Las Vegas, Nevada, U.S.A.
the defendant for breach of contract on the first cause of [pp. 26-27, t.s.n., session of March 14, 1963].
action in the amount of P3,000 and on the second cause of On July 2, 1961, Ketchum on his own behalf and on behalf of
action in no amount. Appellant's assignments of error are his associate Frank Ruskay, assigned to J. Amado Araneta
accordingly found to be well taken in part and not well taken in the managerial rights over Solomon Boysaw.
part. Presumably in preparation for his engagement with Interphil,
Agreeable to the foregoing, the judgment appealed from shall Solomon Boysaw arrived in the Philippines on July 31, 1961.
be modified and the plaintiff shall have and recover from the On September 1, 1961, J. Amado Araneta assigned to Alfredo
defendant the sum of P3,000, with legal interest form October J. Yulo, Jr. the managerial rights over Boysaw that he earlier
2, 1923, until payment. Without special finding as to costs in acquired from Ketchum and Ruskay. The next day, September
either instance, it is so ordered. 2, 1961, Boysaw wrote Lope Sarreal, Sr. informing him of his
arrival and presence in the Philippines.
G.R. No. L-22590 March 20, 1987 On September 5, 1961, Alfredo Yulo, Jr. wrote to Sarreal
SOLOMON BOYSAW and ALFREDO M. YULO, informing him of his acquisition of the managerial rights over
JR., plaintiffs-appellants, Boysaw and indicating his and Boysaw's readiness to comply
vs. with the boxing contract of May 1, 1961. On the same date,
INTERPHIL PROMOTIONS, INC., LOPE SARREAL, SR., on behalf of Interphil Sarreal wrote a letter to the Games and
Amusement Board [GAB] expressing concern over reports court's permission, took no further part in the proceedings.
that there had been a switch of managers in the case of After the lower court rendered its judgment dismissing the
Boysaw, of which he had not been formally notified, and plaintiffs' complaint, the plaintiffs moved for a new trial. The
requesting that Boysaw be called to an inquiry to clarify the motion was denied, hence, this appeal taken directly to this
situation. Court by reason of the amount involved.
The GAB called a series of conferences of the parties From the errors assigned by the plaintiffs, as having been
concerned culminating in the issuance of its decision to committed by the lower court, the following principal issues
schedule the Elorde-Boysaw fight for November 4, 1961. The can be deduced:
USA National Boxing Association which has supervisory 1. Whether or not there was a violation of the fight contract of
control of all world title fights approved the date set by the May 1, 1961; and if there was, who was guilty of such
GAB violation.
Yulo, Jr. refused to accept the change in the fight date, 2. Whether or not there was legal ground for the
maintaining his refusal even after Sarreal on September 26, postponement of the fight date from September 1, 1961, as
1961, offered to advance the fight date to October 28, 1961 stipulated in the May 1, 1961 boxing contract, to November
which was within the 30-day period of allowable 4,1961,
postponements provided in the principal boxing contract of 3. Whether or not the lower court erred in the refusing a
May 1, 1961. postponement of the July 23, 1963 trial.
Early in October 1961, Yulo, Jr. exchanged communications 4. Whether or not the lower court erred in denying the
with one Mamerto Besa, a local boxing promoter, for a appellant's motion for a new trial.
possible promotion of the projected Elorde-Boysaw title bout. 5. Whether or not the lower court, on the basis of the
In one of such communications dated October 6, 1961, Yulo evidence adduced, erred in awarding the appellees damages
informed Besa that he was willing to approve the fight date of of the character and amount stated in the decision.
November 4,1961 provided the same was promoted by Besa. On the issue pertaining to the violation of the May 1, 1961
While an Elorde-Boysaw fight was eventually staged, the fight fight contract, the evidence established that the contract was
contemplated in the May 1, 1961 boxing contract never violated by appellant Boysaw himself when, without the
materialized. approval or consent of Interphil, he fought Louis Avila on June
As a result of the foregoing occurrences, on October 12, 19, 1961 in Las Vegas Nevada. Appellant Yulo admitted this
1961, Boysaw and Yulo, Jr. sued Interphil, Sarreal, Sr. and fact during the trial. [pp. 26-27, t.s.n., March 14, 1963].
Manuel Nieto, Jr. in the CFI of Rizal [Quezon City Branch] for While the contract imposed no penalty for such violation, this
damages allegedly occasioned by the refusal of Interphil and does not grant any of the parties the unbridled liberty to
Sarreal, aided and abetted by Nieto, Jr., then GAB Chairman, breach it with impunity. Our law on contracts recognizes the
to honor their commitments under the boxing contract of May principle that actionable injury inheres in every contractual
1,1961. breach. Thus:
On the first scheduled date of trial, plaintiff moved to disqualify Those who in the performance of their obligations are guilty of
Solicitor Jorge Coquia of the Solicitor General's Office and fraud, negligence or delay, and those who in any manner
Atty. Romeo Edu of the GAB Legal Department from contravene the terms thereof, are liable for damages. [Art.
appearing for defendant Nieto, Jr. on the ground that the latter 1170, Civil Code].
had been sued in his personal capacity and, therefore, was Also:
not entitled to be represented by government counsel. The The power to rescind obligations is implied, in reciprocal ones,
motion was denied insofar as Solicitor General Coquia was in case one of the obligors should not comply with what is
concerned, but was granted as regards the disqualification of incumbent upon him. [Part 1, Art. 1191, Civil Code].
Atty. Edu. There is no doubt that the contract in question gave rise to
The case dragged into 1963 when sometime in the early part reciprocal obligations. "Reciprocal obligations are those which
of said year, plaintiff Boysaw left the country without informing arise from the same cause, and in which each party is a
the court and, as alleged, his counsel. He was still abroad debtor and a creditor of the other, such that the obligation of
when, on May 13, 1963, he was scheduled to take the witness one is dependent upon the obligation of the other. They are to
stand. Thus, the lower court reset the trial for June 20, 1963. be performed simultaneously, so that the performance of one
Since Boysaw was still abroad on the later date, another is conditioned upon the simultaneous fulfillment of the other"
postponement was granted by the lower court for July 23, [Tolentino, Civil Code of the Philippines, Vol. IV, p. 175.1
1963 upon assurance of Boysaw's counsel that should The power to rescind is given to the injured party. "Where the
Boysaw fail to appear on said date, plaintiff's case would be plaintiff is the party who did not perform the undertaking
deemed submitted on the evidence thus far presented. which he was bound by the terms of the agreement to
On or about July 16, 1963, plaintiffs represented by a new perform 4 he is not entitled to insist upon the performance of
counsel, filed an urgent motion for postponement of the July the contract by the defendant, or recover damages by reason
23, 1963 trial, pleading anew Boysaw's inability to return to of his own breach " [Seva vs. Alfredo Berwin 48 Phil. 581,
the country on time. The motion was denied; so was the Emphasis supplied].
motion for reconsideration filed by plaintiffs on July 22, 1963. Another violation of the contract in question was the
The trial proceeded as scheduled on July 23, 1963 with assignment and transfer, first to J. Amado Araneta, and
plaintiff's case being deemed submitted after the plaintiffs subsequently, to appellant Yulo, Jr., of the managerial rights
declined to submit documentary evidence when they had no over Boysaw without the knowledge or consent of Interphil.
other witnesses to present. When defendant's counsel was The assignments, from Ketchum to Araneta, and from Araneta
about to present their case, plaintiff's counsel after asking the to Yulo, were in fact novations of the original contract which,
to be valid, should have been consented to by Interphil. On the validity of the fight postponement, the violations of the
Novation which consists in substituting a new debtor in the terms of the original contract by appellants vested the
place of the original one, may be made even without the appellees with the right to rescind and repudiate such contract
knowledge or against the will of the latter, but not without the altogether. That they sought to seek an adjustment of one
consent of the creditor. [Art. 1293, Civil Code, emphasis particular covenant of the contract, is under the
supplied]. circumstances, within the appellee's rights.
That appellant Yulo, Jr., through a letter, advised Interphil on While the appellants concede to the GAB's authority to
September 5, 1961 of his acquisition of the managerial rights regulate boxing contests, including the setting of dates
over Boysaw cannot change the fact that such acquisition, thereof, [pp. 44-49, t.s.n., Jan. 17, 1963], it is their contention
and the prior acquisition of such rights by Araneta were done that only Manuel Nieto, Jr. made the decision for
without the consent of Interphil. There is no showing that postponement, thereby arrogating to himself the prerogatives
Interphil, upon receipt of Yulo's letter, acceded to the of the whole GAB Board.
"substitution" by Yulo of the original principal obligor, who is The records do not support appellants' contention. Appellant
Ketchum. The logical presumption can only be that, with Yulo himself admitted that it was the GAB Board that set the
Interphil's letter to the GAB expressing concern over reported questioned fight date. [pp. 32-42, t.s.n., Jan. 17, 1963]. Also, it
managerial changes and requesting for clarification on the must be stated that one of the strongest presumptions of law
matter, the appellees were not reliably informed of the is that official duty has been regularly performed. In this case,
changes of managers. Not being reliably informed, appellees the absence of evidence to the contrary, warrants the full
cannot be deemed to have consented to such changes. application of said presumption that the decision to set the
Under the law when a contract is unlawfully novated by an Elorde-Boysaw fight on November 4, 1961 was a GAB Board
applicable and unilateral substitution of the obligor by another, decision and not of Manuel Nieto, Jr. alone.
the aggrieved creditor is not bound to deal with the substitute. Anent the lower court's refusal to postpone the July 23, 1963
The consent of the creditor to the change of debtors, whether trial, suffice it to say that the same issue had been raised
in expromision or delegacion is an, indispensable before Us by appellants in a petition for certiorari and
requirement . . . Substitution of one debtor for another may prohibition docketed as G.R. No. L-21506. The dismissal by
delay or prevent the fulfillment of the obligation by reason of the Court of said petition had laid this issue to rest, and
the inability or insolvency of the new debtor, hence, the appellants cannot now hope to resurrect the said issue in this
creditor should agree to accept the substitution in order that it appeal.
may be binding on him. On the denial of appellant's motion for a new trial, we find that
Thus, in a contract where x is the creditor and y is the debtor, the lower court did not commit any reversible error.
if y enters into a contract with z, under which he transfers to z The alleged newly discovered evidence, upon which the
all his rights under the first contract, together with the motion for new trial was made to rest, consists merely of
obligations thereunder, but such transfer is not consented to clearances which Boysaw secured from the clerk of court prior
or approved by x, there is no novation. X can still bring his to his departure for abroad. Such evidence cannot alter the
action against y for performance of their contract or damages result of the case even if admitted for they can only prove that
in case of breach. [Tolentino, Civil Code of the Boysaw did not leave the country without notice to the court or
Philippines, Vol. IV, p. 3611. his counsel.
From the evidence, it is clear that the appellees, instead of The argument of appellants is that if the clearances were
availing themselves of the options given to them by law of admitted to support the motion for a new trial, the lower court
rescission or refusal to recognize the substitute obligor Yulo, would have allowed the postponement of the trial, it being
really wanted to postpone the fight date owing to an injury that convinced that Boysaw did not leave without notice to the
Elorde sustained in a recent bout. That the appellees had the court or to his counsel. Boysaw's testimony upon his return
justification to renegotiate the original contract, particularly the would, then, have altered the results of the case.
fight date is undeniable from the facts aforestated. Under the We find the argument without merit because it confuses the
circumstances, the appellees' desire to postpone the fight evidence of the clearances and the testimony of Boysaw. We
date could neither be unlawful nor unreasonable. uphold the lower court's ruling that:
We uphold the appellees' contention that since all the rights The said documents [clearances] are not evidence to offset
on the matter rested with the appellees, and appellants' the evidence adduced during the hearing of the defendants. In
claims, if any, to the enforcement of the contract hung entirely fact, the clearances are not even material to the issues raised.
upon the former's pleasure and sufferance, the GAB did not It is the opinion of the Court that the 'newly discovered
act arbitrarily in acceding to the appellee's request to reset the evidence' contemplated in Rule 37 of the Rules of Court, is
fight date to November 4, 1961. It must be noted that such kind of evidence which has reference to the merits of the
appellant Yulo had earlier agreed to abide by the GAB ruling. case, of such a nature and kind, that if it were presented, it
In a show of accommodation, the appellees offered to would alter the result of the judgment. As admitted by the
advance the November 4, 1961 fight to October 28, 1961 just counsel in their pleadings, such clearances might have
to place it within the 30- day limit of allowable postponements impelled the Court to grant the postponement prayed for by
stipulated in the original boxing contract. them had they been presented on time. The question of the
The refusal of appellants to accept a postponement without denial of the postponement sought for by counsel for plaintiffs
any other reason but the implementation of the terms of the is a moot issue . . . The denial of the petition for certiorari and
original boxing contract entirely overlooks the fact that by prohibition filed by them, had he effect of sustaining such
virtue of the violations they have committed of the terms ruling of the court . . . [pp. 296-297, Record on Appeal].
thereof, they have forfeited any right to its enforcement. The testimony of Boysaw cannot be considered newly
discovered evidence for as appellees rightly contend, such action has been erroneously filed, such litigant may be
evidence has been in existence waiting only to be elicited penalized for costs.
from him by questioning. The grant of moral damages is not subject to the whims and
We cite with approval appellee's contention that "the two caprices of judges or courts. The court's discretion in granting
qualities that ought to concur or dwell on each and every of or refusing it is governed by reason and justice. In order that a
evidence that is invoked as a ground for new trial in order to person may be made liable to the payment of moral damages,
warrant the reopening . . . inhered separately on two the law requires that his act be wrongful. The adverse result
unrelated species of proof" which "creates a legal monstrosity of an action does not per se make the act wrongful and
that deserves no recognition." subject the actor to the payment of moral damages. The law
On the issue pertaining to the award of excessive damages, it could not have meant to impose a penalty on the right to
must be noted that because the appellants wilfully refused to litigate; such right is so precious that moral damages may not
participate in the final hearing and refused to present be charged on those who may exercise it erroneously. For
documentary evidence after they no longer had witnesses to these the law taxes costs. [Barreto vs. Arevalo, et. al. No. L-
present, they, by their own acts prevented themselves from 7748, Aug. 27, 1956, 52 O.G., No. 13, p. 5818.]
objecting to or presenting proof contrary to those adduced for WHEREFORE, except for the award of moral damages which
the appellees. is herein deleted, the decision of the lower court is hereby
On the actual damages awarded to appellees, the appellants affirmed.
contend that a conclusion or finding based upon the SO ORDERED.
uncorroborated testimony of a lone witness cannot be
sufficient. We hold that in civil cases, there is no rule requiring G.R. No. L-28602 September 29, 1970
more than one witness or declaring that the testimony of a UNIVERSITY OF THE PHILIPPINES, petitioner,
single witness will not suffice to establish facts, especially vs.
where such testimony has not been contradicted or rebutted. WALFRIDO DE LOS ANGELES, in his capacity as JUDGE
Thus, we find no reason to disturb the award of P250,000.00 of the COURT OF FIRST INSTANCE IN QUEZON CITY, et
as and for unrealized profits to the appellees. al., respondents.
On the award of actual damages to Interphil and Sarreal, the Office of the Solicitor General Antonio P. Barredo, Solicitor
records bear sufficient evidence presented by appellees of Augusto M. Amores and Special Counsel Perfecto V.
actual damages which were neither objected to nor rebutted Fernandez for petitioner.
by appellants, again because they adamantly refused to Norberto J. Quisumbing for private respondents.
participate in the court proceedings.
The award of attorney's fees in the amount of P5,000.00 in
favor of defendant-appellee Manuel Nieto, Jr. and another REYES, J.B.L., J.:
P5,000.00 in favor of defendants-appellees Interphil Three (3) orders of the Court of First Instance of Rizal
Promotions, Inc. and Lope Sarreal, Sr., jointly, cannot also be (Quezon City), issued in its Civil Case No. 9435, are sought to
regarded as excessive considering the extent and nature of be annulled in this petition for certiorari and prohibition, filed
defensecounsels' services which involved legal work for by herein petitioner University of the Philippines (or UP)
sixteen [16] months. against the above-named respondent judge and the
However, in the matter of moral damages, we are inclined to Associated Lumber Manufacturing Company, Inc. (or
uphold the appellant's contention that the award is not ALUMCO). The first order, dated 25 February 1966, enjoined
sanctioned by law and well- settled authorities. Art. 2219 of UP from awarding logging rights over its timber concession
the Civil Code provides: (or Land Grant), situated at the Lubayat areas in the
Art. 2219. Moral damages may be recovered in the following provinces of Laguna and Quezon; the second order, dated 14
analogous cases: January 1967, adjudged UP in contempt of court, and directed
1) A criminal offense resulting in physical injuries; Sta. Clara Lumber Company, Inc. to refrain from exercising
2) Quasi-delict causing physical injuries; logging rights or conducting logging operations on the
3) Seduction, abduction, rape or other lascivious acts; concession; and the third order, dated 12 December 1967,
4) Adultery or concubinage; denied reconsideration of the order of contempt.
5) Illegal or arbitrary detention or arrest; As prayed for in the petition, a writ of preliminary injunction
6) Illegal search; against the enforcement or implementation of the three (3)
7) Libel, slander or any other form of defamation; questioned orders was issued by this Court, per its resolution
8) Malicious prosecution; on 9 February 1968.
9) Acts mentioned in Art. 309. The petition alleged the following:
10) Acts and actions referred to in Arts., 21, 26, 27, 28, 29, 30, That the above-mentioned Land Grant was segregated from
32, 34 and 35. the public domain and given as an endowment to UP, an
The award of moral damages in the instant case is not based institution of higher learning, to be operated and developed for
on any of the cases enumerated in Art. 2219 of the Civil Code. the purpose of raising additional income for its support,
The action herein brought by plaintiffs-appellants is based on pursuant to Act 3608;
a perceived breach committed by the defendants-appellees of That on or about 2 November 1960, UP and ALUMCO
the contract of May 1, 1961, and cannot, as such, be entered into a logging agreement under which the latter was
arbitrarily considered as a case of malicious prosecution. granted exclusive authority, for a period starting from the date
Moral damages cannot be imposed on a party litigant of the agreement to 31 December 1965, extendible for a
although such litigant exercises it erroneously because if the further period of five (5) years by mutual agreement, to cut,
collect and remove timber from the Land Grant, in Jose Rico, the court, in an order dated 14 January 1967,
consideration of payment to UP of royalties, forest fees, etc.; declared petitioner UP in contempt of court and, in the same
that ALUMCO cut and removed timber therefrom but, as of 8 order, directed Sta. Clara Lumber Company, Inc., to refrain
December 1964, it had incurred an unpaid account of from exercising logging rights or conducting logging
P219,362.94, which, despite repeated demands, it had failed operations in the concession.
to pay; that after it had received notice that UP would rescind The UP moved for reconsideration of the aforesaid order, but
or terminate the logging agreement, ALUMCO executed an the motion was denied on 12 December 1967.
instrument, entitled "Acknowledgment of Debt and Proposed Except that it denied knowledge of the purpose of the Land
Manner of Payments," dated 9 December 1964, which was Grant, which purpose, anyway, is embodied in Act 3608 and,
approved by the president of UP, and which stipulated the therefore, conclusively known, respondent ALUMCO did not
following: deny the foregoing allegations in the petition. In its answer,
3. In the event that the payments called for in Nos. 1 and 2 of respondent corrected itself by stating that the period of the
this paragraph are not sufficient to liquidate the foregoing logging agreement is five (5) years - not seven (7) years, as it
indebtedness of the DEBTOR in favor of the CREDITOR, the had alleged in its second amended answer to the complaint in
balance outstanding after the said payments have been Civil Case No. 9435. It reiterated, however, its defenses in the
applied shall be paid by the DEBTOR in full no later than June court below, which maybe boiled down to: blaming its former
30, 1965; general manager, Cesar Guy, in not turning over management
xxx xxx xxx of ALUMCO, thereby rendering it unable to pay the sum of
5. In the event that the DEBTOR fails to comply with any of its P219,382.94; that it failed to pursue the manner of payments,
promises or undertakings in this document, the DEBTOR as stipulated in the "Acknowledgment of Debt and Proposed
agrees without reservation that the CREDITOR shall have the Manner of Payments" because the logs that it had cut turned
right and the power to consider the Logging Agreement dated out to be rotten and could not be sold to Sta. Clara Lumber
December 2, 1960 as rescinded without the necessity of any Company, Inc., under its contract "to buy and sell" with said
judicial suit, and the CREDITOR shall be entitled as a matter firm, and which contract was referred and annexed to the
of right to Fifty Thousand Pesos (P50,000.00) by way of and "Acknowledgment of Debt and Proposed Manner of
for liquidated damages; Payments"; that UP's unilateral rescission of the logging
ALUMCO continued its logging operations, but again incurred contract, without a court order, was invalid; that petitioner's
an unpaid account, for the period from 9 December 1964 to supervisor refused to allow respondent to cut new logs unless
15 July 1965, in the amount of P61,133.74, in addition to the the logs previously cut during the management of Cesar Guy
indebtedness that it had previously acknowledged. be first sold; that respondent was permitted to cut logs in the
That on 19 July 1965, petitioner UP informed respondent middle of June 1965 but petitioner's supervisor stopped all
ALUMCO that it had, as of that date, considered as rescinded logging operations on 15 July 1965; that it had made several
and of no further legal effect the logging agreement that they offers to petitioner for respondent to resume logging
had entered in 1960; and on 7 September 1965, UP filed a operations but respondent received no reply.
complaint against ALUMCO, which was docketed as Civil The basic issue in this case is whether petitioner U.P. can
Case No. 9435 of the Court of First Instance of Rizal (Quezon treat its contract with ALUMCO rescinded, and may disregard
City), for the collection or payment of the herein before stated the same before any judicial pronouncement to that effect.
sums of money and alleging the facts hereinbefore specified, Respondent ALUMCO contended, and the lower court, in
together with other allegations; it prayed for and obtained an issuing the injunction order of 25 February 1966, apparently
order, dated 30 September 1965, for preliminary attachment sustained it (although the order expresses no specific findings
and preliminary injunction restraining ALUMCO from in this regard), that it is only after a final court decree
continuing its logging operations in the Land Grant. declaring the contract rescinded for violation of its terms that
That before the issuance of the aforesaid preliminary U.P. could disregard ALUMCO's rights under the contract and
injunction UP had taken steps to have another concessionaire treat the agreement as breached and of no force or effect.
take over the logging operation, by advertising an invitation to We find that position untenable.
bid; that bidding was conducted, and the concession was In the first place, UP and ALUMCO had expressly stipulated in
awarded to Sta. Clara Lumber Company, Inc.; the logging the "Acknowledgment of Debt and Proposed Manner of
contract was signed on 16 February 1966. Payments" that, upon default by the debtor ALUMCO, the
That, meantime, ALUMCO had filed several motions to creditor (UP) has "the right and the power to consider, the
discharge the writs of attachment and preliminary injunction Logging Agreement dated 2 December 1960 as rescinded
but were denied by the court; without the necessity of any judicial suit." As to such special
That on 12 November 1965, ALUMCO filed a petition to enjoin stipulation, and in connection with Article 1191 of the Civil
petitioner University from conducting the bidding; on 27 Code, this Court stated in Froilan vs. Pan Oriental Shipping
November 1965, it filed a second petition for preliminary Co., et al.,  L-11897, 31 October 1964, 12 SCRA 276:
injunction; and, on 25 February 1966, respondent judge there is nothing in the law that prohibits the parties from
issued the first of the questioned orders, enjoining UP from entering into agreement that violation of the terms of the
awarding logging rights over the concession to any other contract would cause cancellation thereof, even without court
party. intervention. In other words, it is not always necessary for the
That UP received the order of 25 February 1966 after it had injured party to resort to court for rescission of the contract.
concluded its contract with Sta. Clara Lumber Company, Inc., Of course, it must be understood that the act of party in
and said company had started logging operations. treating a contract as cancelled or resolved on account of
That, on motion dated 12 April 1966 by ALUMCO and one infractions by the other contracting party must be made
known to the other and is always provisional, being ever convenido, que puede ejercitarse, ya en la via judicial,  ya
subject to scrutiny and review by the proper court. If the other fuera de ella, por declaracion del acreedor, a reserva, claro
party denies that rescission is justified, it is free to resort to es, que si la declaracion de resolucion hecha por una de las
judicial action in its own behalf, and bring the matter to court. partes se impugna por la otra, queda aquella sometida el
Then, should the court, after due hearing, decide that the examen y sancion de los Tribunale, que habran de declarar,
resolution of the contract was not warranted, the responsible en definitiva, bien hecha la resolucion o por el contrario, no
party will be sentenced to damages; in the contrary case, the ajustada a Derecho. (Sent. TS of Spain, 16 November 1956;
resolution will be affirmed, and the consequent indemnity Jurisp. Aranzadi, 3, 447).
awarded to the party prejudiced. La resolucion de los contratos sinalagmaticos, fundada en el
In other words, the party who deems the contract violated incumplimiento por una de las partes de su respectiva
may consider it resolved or rescinded, and act accordingly, prestacion, puedetener lugar con eficacia" 1. o Por la
without previous court action, but it  proceeds at its own risk. declaracion de voluntad de la otra hecha extraprocesalmente,
For it is only the final judgment of the corresponding court that si no es impugnada en juicio luego con exito. y 2. 0 Por la
will conclusively and finally settle whether the action taken demanda de la perjudicada, cuando no opta por el
was or was not correct in law. But the law definitely does not cumplimientocon la indemnizacion de danos y perjuicios
require that the contracting party who believes itself injured realmente causados, siempre quese acredite, ademas, una
must first file suit and wait for a judgment before taking actitud o conducta persistente y rebelde de laadversa o la
extrajudicial steps to protect its interest. Otherwise, the party satisfaccion de lo pactado, a un hecho obstativo que de un
injured by the other's breach will have to passively sit and modoabsoluto, definitivo o irreformable lo impida, segun el
watch its damages accumulate during the pendency of the art. 1.124, interpretado por la jurisprudencia de esta Sala,
suit until the final judgment of rescission is rendered when the contenida en las Ss. de 12 mayo 1955 y 16 Nov. 1956, entre
law itself requires that he should exercise due diligence to otras, inspiradas por el principio del Derecho intermedio,
minimize its own damages (Civil Code, Article 2203). recogido del Canonico, por el cual fragenti fidem, fides non
We see no conflict between this ruling and the previous est servanda. (Ss. de 4 Nov. 1958 y 22 Jun. 1959.) (Emphasis
jurisprudence of this Court invoked by respondent declaring supplied).
that judicial action is necessary for the resolution of a In the light of the foregoing principles, and considering that
reciprocal obligation,1 since in every case where the the complaint of petitioner University made out a prima
extrajudicial resolution is contested only the final award of the facie case of breach of contract and defaults in payment by
court of competent jurisdiction can conclusively settle whether respondent ALUMCO, to the extent that the court below
the resolution was proper or not. It is in this sense that judicial issued a writ of preliminary injunction stopping ALUMCO's
action will be necessary, as without it, the extrajudicial logging operations, and repeatedly denied its motions to lift
resolution will remain contestable and subject to judicial the injunction; that it is not denied that the respondent
invalidation, unless attack thereon should become barred by company had profited from its operations previous to the
acquiescence, estoppel or prescription. agreement of 5 December 1964 ("Acknowledgment of Debt
Fears have been expressed that a stipulation providing for a and Proposed Manner of Payment"); that the excuses offered
unilateral rescission in case of breach of contract may render in the second amended answer, such as the misconduct of its
nugatory the general rule requiring judicial action (v. Footnote, former manager Cesar Guy, and the rotten condition of the
Padilla, Civil Law, Civil Code Anno., 1967 ed. Vol. IV, page logs in private respondent's pond, which said respondent was
140) but, as already observed, in case of abuse or error by in a better position to know when it executed the
the rescinder the other party is not barred from questioning in acknowledgment of indebtedness, do not constitute on their
court such abuse or error, the practical effect of the stipulation face sufficient excuse for non-payment; and considering that
being merely to transfer to the defaulter the initiative of whatever prejudice may be suffered by respondent ALUMCO
instituting suit, instead of the rescinder. is susceptibility of compensation in damages, it becomes plain
In fact, even without express provision conferring the power of that the acts of the court a quo in enjoining petitioner's
cancellation upon one contracting party, the Supreme Court of measures to protect its interest without first receiving
Spain, in construing the effect of Article 1124 of the Spanish evidence on the issues tendered by the parties, and in
Civil Code (of which Article 1191 of our own Civil; Code is subsequently refusing to dissolve the injunction, were in grave
practically a reproduction), has repeatedly held that, a abuse of discretion, correctible by certiorari, since appeal was
resolution of reciprocal or synallagmatic contracts may be not available or adequate. Such injunction, therefore, must be
made extrajudicially unless successfully impugned in court. set aside.
El articulo 1124 del Codigo Civil establece la facultad de For the reason that the order finding the petitioner UP in
resolver las obligaciones reciprocas para el caso de que uno contempt of court has open appealed to the Court of Appeals,
de los obligados no cumpliese lo que le incumbe, facultad and the case is pending therein, this Court abstains from
que, segun jurisprudencia de este Tribunal, surge making any pronouncement thereon.
immediatamente despuesque la otra parte incumplio su WHEREFORE, the writ of certiorari applied for is granted, and
deber, sin necesidad de una declaracion previa de los the order of the respondent court of 25 February 1966,
Tribunales. (Sent. of the Tr. Sup. of Spain, of 10 April 1929; granting the Associated Lumber Company's petition for
106 Jur. Civ. 897). injunction, is hereby set aside. Let the records be remanded
Segun reiterada doctrina  de esta Sala, el Art. 1124 regula la for further proceedings conformably to this opinion.
resolucioncomo una "facultad" atribuida a la parte perjudicada
por el incumplimiento del contrato, la cual tiene derecho do G.R. No. 47206 September 27, 1989
opcion entre exigir el cumplimientoo la resolucion de lo GLORIA M. DE ERQUIAGA, administratrix of the estate of
the late SANTIAGO DE ERQUIAGA & HON. FELICIANO S. As recited by the Court of Appeals in its decision under
GONZALES, petitioners, review, the following developments occurred thereafter:
vs. On March 30, 1970, private respondent Santiago de Erquiaga
HON. COURT OF APPEALS, AFRICA VALDEZ VDA. DE filed a complaint for rescission with preliminary injunction
REYNOSO, JOSES V. REYNOSO, JR., EERNESTO , against Jose L. Reynoso and Erquiaga Development
SYLVIA REYNOSO, LOURDES REYNOSO, CECILE Corporation, in the Court of First Instance of Sorsogon,
REYNOSO, EDNA REYNOSO, ERLINDA REYNOSO & Branch I (Civil Case No. 2446).** After issues have been
EMILY REYNOSO, respondents. joined and after trial on the merits, the lower court rendered
Agrava, Lucero, Gineta & Roxas for petitioners. judgment (on September 30, 1972),*** the dispositive portion
Bausa, Ampil, Suarez, Parades & Bausa for private of which reads as follows:
respondents. In view of the foregoing, judgment is hereby rendered in favor
of the plaintiff and against the defendant Jose L. Reynoso,
rescinding the sale of 3,100 paid up shares of stock of the
GRINO-AQUINO, J.: Erquiaga Development Corporation to the defendant, and
This is a case that began in the Court of First Instance of ordering:
Sorsogon in 1970. Although the decision dated September 30, (a) The defendant to return and reconvey to the plaintiff the
1972 of the trial court (pp. 79-106, Rollo) became final and 3,100 paid up shares of stock of the Erquiaga Development
executory because none of the parties appealed, its execution Corporation which now stand in his name in the books of the
has taken all of the past seventeen (17) years with the end corporation;
nowhere in sight. The delay in writing finis to this case is (b) The defendant to render a full accounting of the fruits he
attributable to several factors, not the least of which is the received by virtue of said 3,100 paid up shares of stock of the
intransigence of the defeated party. Now, worn down by this Erquiaga Development Corporation, as well as to return said
attrital suit, both have pleaded for a decision to end this case. fruits received by him to plaintiff Santiago de Erquiaga;
Assailed in this petition for review are: (c) The plaintiff to return to the defendant the amount of
(a) the decision of the Court of Appeals dated May 31, 1976 in P100,000.00 plus legal interest from November 4,1968, and
CA-G.R. No. SP 04811, entitled "Africa Valdez Vda. de the amount of P310,000.00 plus legal interest from December
Reynoso et al. vs. Hon. Feliciano S. Gonzales and Santiago 17, 1968, until paid;
de Erquiaga" (pp. 275-290, Rollo); (d) The defendant to pay the plaintiff as actual damages the
(b) its resolution dated August 3, 1976, denying the motion for amount of P12,000.00;
reconsideration (p. 298, Rollo); (e) The defendant to pay the plaintiff the amount of
(c) its resolution of August 24, 1977, ordering entry of P50,000.00 as attorney's fees; and
judgment (p. 316, Rollo); and (f) The defendant to pay the costs of this suit and expenses of
(d) its resolution of October 4, 1977, denying the motion to set litigation. (Annex A-Petition.)
aside the entry of judgment. The parties did not appeal therefrom and it became final and
Santiago de Erquiaga was the owner of 100% or 3,100 paid- executory.
up shares of stock of the Erquiaga Development Corporation On March 21, 1973, the CFI of Sorsogon issued an Order,
which owns the Hacienda San Jose in Irosin, Sorsogon (p. pertinent portions of which reads:
212, Rollo). On November 4,1968, he entered into an It will be noted that both parties having decided not to appeal,
Agreement with Jose L. Reynoso to sell to the latter his 3,100 the decision has become final and executory.
shares (or 100%) of Erquiaga Development Corporation for Nevertheless, the Court finds merit in the contention of the
P900,000 payable in installments on definite dates fixed in the plaintiff that the payment to the defendant of the total sum of
contract but not later than November 30, 1968. Because P410,000.00 plus the interest, should be held in abeyance
Reynoso failed to pay the second and third installments on pending rendition of the accounting by the defendant of the
time, the total price of the sale was later increased to fruits received by him on account of the 3,100 shares of the
P971,371.70 payable on or before December 17, 1969. The capital stock of Erquiaga Development Corporation. The
difference of P71,371.70 represented brokers' commission same may be said with respect to the sums due the plaintiff
and interest (CFI Decision, pp. 75, 81, 90, 99,Rollo). from the defendant for damages and attorney's fees. Indeed it
As of December 17, 1968, Reynoso was able to pay the total is reasonable to suppose, as contended by the plaintiff, that
sum of P410,000 to Erquiaga who thereupon transferred all when such accounting is made and the accounting, as urged
his shares (3,100 paid-up shares) in Erquiaga Development by plaintiff, should refer not only to the dividends due from the
Corporation to Reynoso, as well as the possession of the shares of stock but to the products of the hacienda which is
Hacienda San Jose, the only asset of the corporation (p. 100, the only asset of the Erquiaga Development Corporation,
Rollo). However, as provided in paragraph 3, subparagraph certain sums may be found due to the plaintiff from the
(c) of the contract to sell, Reynoso pledged 1,500 shares in defendant which may partially or entirely off set (sic) the
favor of Erquiaga as security for the balance of his obligation amount adjudged against him in the decision.
(p. 100, Rollo). Reynoso failed to pay the balance of It is the sense of the court that the fruits referred to in the
P561,321.70 on or before December 17, 1969, as provided in decision include not only the dividends received, if any, on the
the promissory notes he delivered to Erquiaga. So, on March 3,100 shares of stocks but more particularly the products
2, 1970, Erquiaga, through counsel, formally informed received by the defendant from the hacienda. The hacienda
Reynoso that he was rescinding the sale of his shares in the and the products thereon produced constitute the physical
Erquiaga Development Corporation (CFI Decision, pp. 81- assets of the Erquiaga Development Corporation represented
100, Rollo). by the shares of stock and it would be absurd to suppose that
any accounting could be made by the defendant without (Annex D, Id.).
necessarily taking into account the products received which In an Omnibus Motion, dated July 25,1975, filed by Erquiaga,
could be the only basis for determining whether dividends are and over the objections interposed thereto by herein
due or not on account of the investment. The hacienda and its petitioners (Reynosos), the CFI of Sorsogon issued an Order,
natural fruits as represented by the shares of stock which the dated October 9, 1975, the dispositive portion of which reads:
defendant received as manager and controlling stockholder of WHEREFORE, in view of the foregoing, on the first count, the
the Erquiaga Development Corporation can not be divorced defendants are directed (to deliver) to the plaintiff or his
from the certificates of stock in order to determine whether the counsel within five (5) days from receipt of this order the
defendant has correctly reported the income of the 1,600 shares of stock of the Erquiaga Development
corporation or concealed part of it for his personal advantage. Corporation which are in their possession. Should the
It is hardly necessary for the Court to restate an obvious fact defendants refuse or delay in delivering such shares of stock,
that on both legal and equitable grounds, the Erquiaga as prayed for, the plaintiff is authorized:
Development Corporation and defendant Jose Reynoso are (a) To call and hold a special meeting of the stockholders of
one and the same persons as far as the obligation to account the Erquiaga Development Corporation to elect the members
for the products of the hacienda is concerned,' (pp. 4-6, of the Board of Directors;
Annex 1, Answer.) (b) In the said meeting the plaintiff is authorized to vote not
In the same Order, the CFI of Sorsogon appointed a receiver only the 1,500 shares of stock in his name but also the 1,600
upon the filing of a bond in the amount of P100,000.00. The shares in the name and possession of the defendants;
reasons of the lower court for appointing a receiver 'were that (c) The question as to who shall be elected members of the
the matter of accounting of the fruits received by defendant Board of Directors and officers of the board is left to the
Reynoso as directed in the decision will take time; that plaintiff discretion of the plaintiff;
Erquiaga has shown sufficient and justifiable ground for the (d) The members of the board and the officers who are
appointment of a receiver in order to preserve the Hacienda elected are authorized to execute any and all contracts or
which has obviously been mismanaged by the defendant to a agreements under such conditions as may be required by the
point where the amortization of the loan with the Development Development Bank for the purpose of restructuring the loan of
Bank of the Philippines has been neglected and the arrears in the Erquiaga Development Corporation with the said bank.
payments have risen to the amount of P503,510.70 as of On the second count, the prayer to strike out all expenses
October 19, 1972, and there is danger that the Development alleged[ly] incurred by the defendants in the production of the
Bank of the Philippines may institute foreclosure proceedings fruits of Hacienda San Jose and declaring the obligation of the
to the damage and prejudice of the plaintiff.' (p. 7, Id.) plaintiff under paragraph (c) of the judgment to pay the
On April 26, 1973, defendant Jose L. Reynoso died and he defendant the sum of P410,000.00 with interest as fully
was substituted by his surviving spouse Africa Valdez Vda. de compensated by the fruits earned by the defendants from the
Reynoso and children, as party defendants. property, as well as the issuance of a writ of execution against
Defendants filed a petition for  certiorari with a prayer for a writ the defendants to pay the plaintiffs P62,000.00 under
of preliminary injunction seeking the annulment of the paragraphs (e) and (d) and costs of litigation under paragraph
aforementioned Order of March 21, 1973. On June 28, 1973, (f) of the judgment of September 30, 1972, is denied.
the Court of Appeals rendered judgment dismissing the The defendants are once more directed to comply with the
petition with costs against the petitioners, ruling that said order of February 12, 1975, by answering the interrogatories
Order is valid and the respondent court did not commit any propounded by counsel for the plaintiff and allowing said
grave abuse of discretion in issuing the same (Annex 2, counsel or his representative to inspect, copy and photograph
Id.). Petitioners brought the case up to the Supreme Court on the documents mentioned by the plaintiff during reasonable
a petition for review on certiorari which was denied by said hours of any working day within twenty (20) days from receipt
tribunal in a Resolution dated February 5, 1974 (Annex 3, Id.). of this order, should the defendants persist in their refusal or
Petitioners' motion for reconsideration thereof was likewise failure to comply with the order, the plaintiff may inform the
denied by the Supreme Court on March 29,1974. court seasonably so that the proper action may be taken.
Upon motion of Erquiaga, the CFI of Sorsogon issued an (Annex J, Id.)
order, dated February 12,1975, dissolving the receivership Hence, the present petition for certiorari, prohibition and
and ordering the delivery of the possession of the Hacienda mandamus instituted by the substituted defendants, heirs of
San Jose to Erquiaga, the filing of bond by said Erquiaga in the deceased defendant Jose L. Reynoso against the CFI of
the amount of P410,000.00 conditioned to the payment of Sorsogon and (plaintiff) Santiago de Erquiaga. (pp. 276- 281,
whatever may be due to the substituted heirs of deceased Rollo.)
defendant Reynoso (petitioners herein) after the approval of On May 31, 1976, the Court of Appeals rendered judgment
the accounting report submitted by Reynoso. Said order holding that:
further directed herein petitioners to allow counsel for IN VIEW OF ALL THE FOREGOING, this court finds that the
Erquiaga to inspect, copy and photograph certain documents respondent court had acted with grave abuse of discretion or
related to the accounting report (Annex B, Petition). in excess of jurisdiction in issuing the assailed order of
On March 3,1975, the CFI of Sorsogon approved the October 9, 1975 (Annex A, Petition) insofar only as that part of
P410,000.00 bond submitted by Erquiaga and the the Order (1) giving private respondent voting rights on the
possession, management and control of the hacienda were 3,100 shares of stock of the Erquiaga Development
turned over to Erquiaga (Annex C, Petition). Petitioners Corporation without first divesting petitioners of their title
(Reynosos) filed their motion for reconsideration which the thereto and ordering the registration of the same in the
CFI of Sorsogon denied in an Order, dated June 23, 1975 corporation books in the name of private respondent,
pursuant to Section 10, Rule 39 of the Revised Rules of 4. Reynoso has not paid the judgment of Pl2,000 as actual
Court; (2) authorizing corporate meetings and election of damages in favor of Erquiaga, under paragraph (d) of the
members of the Board of Directors of said corporation and (3) judgment;
refusing to order the reimbursement of the purchase price of 5. .Reynoso has not paid the sum of P50,000 as attorney's
the 3,100 shares of stock in the amount of P410,000.00 plus fees to Erquiaga under paragraph (e) of the judgment; and
interests awarded in said final decision of September 30, 6. Reynoso has not paid the costs of suit and expenses of
1972 and the set-off therewith of the amount of P62,000.00 as litigation as ordered in paragraph (f) of the final judgment.
damages and attorney's fees in favor of herein private The petitioner alleges, in her petition for review, that:
respondent are concerned. Let writs of certiorari and I. The decision of the Court of Appeals requiring the petitioner
prohibition issue against the aforesaid acts, and the writ of to pay the private respondents the sum of P410,000 plus
preliminary injunction heretofore issued is hereby made interest, without first awaiting Reynoso's accounting of the
permanent only insofar as (1), (2) and (3) above are fruits of the Hacienda San Jose, violates the law of the case
concerned. As to all other matters involved in said Order of and Article 1385 of the Civil Code, alters the final order dated
October 9, 1975, the issuance of writs prayed for in the February 12, 1975 of the trial court, and is inequitous.
petition are not warranted and therefore denied. II. The Court of Appeals erroneously applied the Corporation
FINALLY, to give effect to all the foregoing, with a view of Law.
putting an end to a much protracted litigation and for the best III. The Court of Appeals erred in ordering entry of its
interest of the parties, let a writ of mandamus issue, judgment.
commanding the respondent Judge to order (1) the Clerk of We address first the third assignment of error for it will be
Court of the CFI of Sorsogon to execute the necessary deed futile to discuss the first and second if, after all, the decision
of conveyance to effect the transfer of ownership of the entire complained of is already final, and the entry of judgment
3,100 shares of stock of the Erquiaga Development which the Court of Appeals directed to be made in its
Corporation to private respondent Santiago Erquiaga in case resolution of August 24,1977 (p. 316, Rollo) was proper. After
of failure of petitioners to comply with the Order of October 9, examining the records, we find that the Court of Appeals'
1975 insofar as the delivery of the 1,600 shares of stock to decision is not yet final. The entry of judgment was
private respondent is concerned, within five (5) days from improvident for the Court of Appeals, in its resolution of
receipt hereof; and (2) upon delivery by petitioners or transfer December 13, 1976, suspended the proceedings before it
by the Clerk of Court of said shares of stock to private "pending the parties' settlement negotiations" as prayed for in
respondent, as the case may be, to issue a writ of execution their joint motion (p. 313, Rollo). Without however giving them
ordering private respondent to pay petitioners the amount of an ultimatum or setting a deadline for the submission of their
P410,000.00 plus interests in accordance with the final compromise agreement, the Court of Appeals, out of the blue,
decision of September 30, 1972 in Civil Case No. 2448, issued a resolution on August 24, 1977 ordering the Judgment
setting-off therewith the amount of P62,000.00 adjudged in Section of that Court to enter final judgment in the case (p.
favor of private respondent, and against petitioners' 316, Rollo).
predecessor-in-interest, Jose L. Reynoso, in the same We hold that the directive was precipitate and premature.
decision, as damages and attorney's fees. (pp. 289-290, Erquiaga received the order on September 2, 1977 and filed
Rollo.) on September 12, 1977 (p. 317, Rollo) a motion for
It may be seen from the foregoing narration of facts that as of reconsideration which the Court of Appeals denied on October
the time the Court of Appeals rendered its decision on May 4, 1977 (p. 322, Rollo). The order of denial was received on
31, 1976 (now under review) only the following have been October 14, 1977 (p. 7, Rollo). On October 28, 1977,
done by the parties in compliance with the final judgment in Erquiaga filed in this Court a timely motion for extension of
the main case (Civil Case No. 2446): time to file a petition for review, and the petition was filed
1. The Hacienda San Jose was returned to Erquiaga on within the extension granted by this Court.
March 3, 1975 upon approval of Erquiaga's surety bond of We now address the petitioners' first and second assignments
P410,000 in favor of Reynoso; of error.
2. Reynoso has returned to Erquiaga only the pledged 1,500 After deliberating on the petition for review, we find no
shares of stock of the Erquiaga Development Corporation, reversible error in the Court of Appeals' decision directing the
instead of 3,100 shares, as ordered in paragraph (a) of the clerk of court of the trial court to execute a deed of
final judgment. conveyance to Erquiaga of the 1,600 shares of stock of the
What the parties have not done yet are: Erquiaga Development Corporation still in Reynoso's name
1. Reynoso has not returned 1,600 shares of stock to and/or possession, in accordance with the procedure in
Erquiaga as ordered in paragraph (a,) of the decision; Section 10, Rule 39 of the Rules of Court. Neither did it err in
2. Reynoso has not rendered a full accounting of the fruits he annulling the trial court's order: (1) allowing Erquiaga to vote
has received from Hacienda San Jose by virtue of the 3,100 the 3,100 shares of Erquiaga Development Corporation
shares of stock of the Erquiaga Development Corporation without having effected the transfer of those shares in his
delivered to him under the sale, as ordered in paragraph (b) of name in the corporate books; and (2) authorizing Erquiaga to
the decision; call a special meeting of the stockholders of the Erquiaga
3. Erquiaga has not returned the sum of P100,000 paid by Development Corporation and to vote the 3,100 shares,
Reynoso on the sale, with legal interest from November 4, without the pre-requisite registration of the shares in his
1968 and P310,000 plus legal interest from December 17, name. It is a fundamental rule in Corporation Law (Section 35)
1968, until paid (total: P410,000) as ordered in paragraph (c) that a stockholder acquires voting rights only when the shares
of the decision; of stock to be voted are registered in his name in the
corporate books. stock of the Erquiaga Development Corporation should be
Until registration is accomplished, the transfer, though valid computed as provided in the final judgment in Civil Case No.
between the parties, cannot be effective as against the 2446 up to September 30,1972, the date of said judgment.
corporation. Thus, the unrecorded transferee cannot enjoy the Since Reynoso's judgment liability to Erquiaga for attorney's
status of a stockholder; he cannot vote nor be voted for, and fees and damages in the total sum of P62,000 should be set
he will not be entitled to dividends. The Corporation will be off against the price of P410,000 that Erquiaga is obligated to
protected when it pays dividend to the registered owner return to Reynoso, the balance of the judgment in favor of
despite a previous transfer of which it had no knowledge. The Reynoso would be only P348,000 which should earn legal
purpose of registration therefore is two-fold; to enable the rate of interest after September 30,1972, the date of the
transferee to exercise all the rights of a stockholder, and to judgment. However, the payment of said interest by Erquiaga
inform the corporation of any change in share ownership so should await Reynoso's accounting of the fruits received by
that it can ascertain the persons entitled to the rights and him from the Hacienda San Jose. Upon payment of P348,000
subject to the liabilities of a stockholder. (Corporation Code, by Erquiaga to Reynoso, Erquiaga's P410,000 surety bond
Comments, Notes and Selected cases by Campos & Lopez- shall be deemed cancelled. In all other respects, the decision
Campos, p. 838,1981 Edition.) of the Court of Appeals in CA-G.R. No, 04811-SP is affirmed.
The order of respondent Court directing Erquiaga to return the No pronouncement as to costs.
sum of P410,000 (or net P348,000 after deducting P62,000 SO ORDERED.
due from Reynoso under the decision) as the price paid by
Reynoso for the shares of stock, with legal rate of interest, G.R. No. 73893
and the return by Reynoso of Erquiaga's 3,100 shares with MARGARITA SURIA AND GRACIA R. JOVEN, petitioners,
the fruits(construed to mean not only dividends but also fruits vs.
of the corporation's Hacienda San Jose) is in full accord with HON. INTERMEDIATE APPELLATE COURT, HON. JOSE
Art. 1385 of the Civil Code which provides: MAR GARCIA (Presiding Judge of the RTC of Laguna,
ART. 1385. Rescission creates the obligation to return the Branch XXIV, Biñan, Laguna), and SPOUSES HERMINIO
things which were the object of the contract, together with A. CRISPIN and NATIVIDAD C. CRISPIN, respondents.
their fruits, and the price with its interest; consequently, it can De Castro & Cagampang Law Offices for petitioners.
be carried out only when he who demands rescission can Nelson A. Loyola for private respondents.
return whatever he may be obliged to restore. RESOLUTION
Neither shall rescission take place when the things which are
the object of the contract are legally in the possession of third
persons who did not act in bad faith. GUTIERREZ, JR., J.:
In this case, indemnity for damages may be demanded from This is a petition for review on certiorari of the decision of the
the person causing the loss. Court of Appeals dismissing for lack of merit the petition for
The Hacienda San Jose and 1,500 shares of stock have certiorari filed therein.
already been returned to Erquiaga. Therefore, upon the As factual background, we quote from the Court of Appeals'
conveyance to him of the remaining 1,600 shares, Erquiaga decision:
(or his heirs) should return to Reynoso the price of P410,000 The factual and procedural antecedents of this case may be
which the latter paid for those shares. Pursuant to the briefly stated as follows:
rescission decreed in the final judgment, there should be On June 20, 1983, private-respondents filed a complaint
simultaneous mutual restitution of the principal object of the before the Regional Trial Court of Laguna, Branch XXIV, for
contract to sell (3,100 shares) and of the consideration paid rescission of contract and damages, alleging among others:
(P410,000). This should not await the mutual restitution of 1. x x x
the  fruits, namely: the legal interest earned by Reynoso's 2. That on March 31, 1975, plaintiffs being the owners of a
P410,000 while in the possession of Erquiaga and its parcel of land situated at Barrio San Antonio, San Pedro,
counterpart: the fruits of Hacienda San Jose which Reynoso Laguna, entered into a contract denominated as DEED OF
received from the time the hacienda was delivered to him on SALE WITH MORTGAGE, with herein defendants, a true
November 4,1968 until it was placed under receivership by copy of said contract (which is made an integral part hereof) is
the court on March 3, 1975. However, since Reynoso has not hereto attached as ANNEX ."A":
yet given an accounting of those fruits, it is only fair that 3. x x x
Erquiaga's obligation to deliver to Reynoso the legal interest 4. That the defendants violated the terms and conditions of
earned by his money, should await the rendition and approval the contract by failing to pay the stipulated installments and in
of his accounting. To this extent, the decision of the Court of fact only one installment due in July 1975 (paid very late in
Appeals should be modified. For it would be inequitable and the month of September, 1975) was made all the others
oppressive to require Erquiaga to pay the legal interest remaining unsettled to the present time;
earned by Reynoso's P410,000 since 1968 or for the past 20 5. That repeated verbal and written demands were made by
years (amounting to over P400,000 by this time) without first plaintiff upon the defendants for the payment of the
requiring Reynoso to account for the fruits of Erquiaga's installments, some of said written demands having been
hacienda which he allegedly squandered while it was in his made on September 24, 1981, February 7, 1982, February
possession from November 1968 up to March 3, 1975. 24, 1983, March 13, 1983, and April 12, 1983, but defendants
WHEREFORE, the petition for review is granted. The for no justifiable reason failed to comply with the demands of
payment of legal interest by Erquiaga to Reynoso on the price plaintiffs;
of P410,000 paid by Reynoso for Erquiaga's 3,100 shares of 6. x x x
On November 14, 1983, petitioners filed their answer with jurisprudence and the hypothetically admitted allegations of
counterclaim. the complaint, and for that reason it denied the motion to
On July 16, 1984, petitioners filed a motion to disniiss dismiss in its said order of November 26, 1984.
complaint, alleging that: The instant Motion for Reconsideration is therefore denied for
1. That plaintiffs are not entitled to the subsidiary remedy of lack of merit. (Pp, 29-32, Rollo)
rescission because of the presence of remedy of The questions raised by petitioner are as follows:
foreclosure in the Deed of Sale with Mortgage (Annex "A", I
Complaint); IN A DEED OF SALE, WHICH IS COUPLED WITH A
2. That, assuming arguendo that rescission were a proper MORTGAGE TO SECURE PAYMENT OF THE BALANCE OF
remedy, it is apparent in the face of the Complaint that the THE PURCHASE PRICE, MAY THE SELLER RESORT TO
plaintiffs failed to comply with the requirements of law, hence THE REMEDY OF RESCISSION UNDER ARTICLE 1191 OF
the rescission was ineffective, illegal, null and void, and THE CIVIL CODE WHICH PROVIDES FOR THE
invalid. SUBSIDIARY AND EQUITABLE REMEDY OF RESCISSION
On July 26, 1984, private-respondents filed their opposition to IN CASE OF BREACH OF RECIPROCAL OBLIGATIONS?
the above motion. Otherwise stated,
In the meantime, on August 6, 1984, petitioners formerly IS THE SUBSIDIARY AND EQUITABLE REMEDY OF
offered to pay private-respondents all the outstanding balance RESCISSION AVAILABLE IN THE PRESENCE OF A
under the Deed of Sale with Mortgage, which offer was REMEDY OF FORECLOSURE IN THE LIGHT OF THE
rejected by private respondents on August 7, 1984. EXPRESS PROVISION OF ARTICLE 1383 OF THE CIVIL
On November 26, 1984, the respondent-Court denied the CODE THAT: 'THE ACTION FOR RESCISSION IS
motion to dismiss. The order reads: SUBSIDIARY; IT CANNOT BE INSTITUTED EXCEPT WHEN
Defendants through counsel filed a Second Motion to Dismiss THE PARTY SUFFERING DAMAGE HAS NO OTHER LEGAL
dated July 24, 1984 based on an affirmative defense raised in MEANS TO OBTAIN REPARATION FOR THE SAME?
their answer, that is, that the complaint fails to state a cause x x x      x x x     x x x
of action for rescission against defendants because (1) — II
plaintiffs are not entitled to the subsidiary remedy of MAY THE SELLER LEGALLY DEMAND RESCISSION OF
rescission because of the presence of the remedy of THE DEED OF SALE WITH MORTGAGE WITHOUT
foreclosure in the Deed of Sale with Mortgage (Annex "A", OFFERING TO RESTORE TO THE BUYER WHAT HE HAS
Complaint) and (2) — assuming arguendo that rescission PAID, AS REQUIRED BY ARTICLE 1385, OR COMPLYING
were a proper remedy, it is apparent from the face of the WITH THE REQUIREMENTS OF THE MACEDA LAW
Complaint that the plaintiffs failed to comply with the (REPUBLIC ACT 6552) GRANTING THE BUYER A GRACE
requirements of law, hence the rescission was ineffective, PERIOD TO PAY WITHOUT INTEREST, AND, IN CASE OF
illegal, null and void, and invalid. CANCELLATION IN CASE THE BUYER STILL COULD NOT
After a careful perusal of the allegations of the complaint PAY WITHIN THE GRACE PERIOD, REQUIRING THE
considered in the light of existing applicable law and SELLER TO ORDER PAYMENT OF THE CASH
jurisprudence touching on the matters in issue, and mindful of SURRENDER VALUE BEFORE THE CANCELLATION MAY
the settled rule that in a motion to dismiss grounded on lack of LEGALLY TAKE EFFECT (SEC. 3[b], LAST PAR., REP. ACT
cause of action the allegations of the complaint must be 6552)?
assumed to be true, the Court finds and holds that the motion The petition was denied in a minute resolution on June 13,
to dismiss dated July 24, 1984 filed by defendants lacks merit 1986 but was given due course on September 29, 1986 on a
and therefore denied the same. motion for reconsideration.
SO ORDERED. The petition is impressed with merit.
On January 31, 1985, petitioners filed a motion for The respondent court rejected the petitioners' reliance on
reconsideration to which private-respondents filed their paragraph (H) of the contract which grants to the vendors
opposition on February 11, 1985. On February 19, 1985, mortgagees the right to foreclose "in the event of the failure of
petitioners filed their reply. the vendees-mortgagors to comply with any provisions of this
On March 13, 1985, the respondent-Court denied the motion mortgage." According to the appellate court, this stipulation
for reconsideration. The order reads in part: merely recognizes the right of the vendors to foreclose and
x x x      x x x     x x x realize on the mortgage but does not preclude them from
Perusing the grounds invoked by the defendants in their availing of other remedies under the law, such as rescission of
Motion for Reconsideration and Reply as well as the contract and damages under Articles 1191 and 1170 of the
objections raised by plaintiffs in their opposition, and it Civil Code in relation to Republic Act No. 6552.
appearing that in its Order dated November 26, 1984, the The appellate court committed reversible error. As will be
Court has sufficiently, althou (sic) succinctly stated its reason explained later, Art. 1191 on reciprocal obligations is not
for denying the motion to dismiss dated July 16, 1984, that is, applicable under the facts of this case. Moreover, Art. 1383 of
for lack of merit, the Court finds no overriding reason or the Civil Code provides:
justification from the grounds invoked in the said Motion for The action for rescission is subsidiary; it cannot be instituted
Reconsideration for it to reconsider, change, modify, or set except when the party suffering damage has no other legal
aside its Order dated November 26, 1984. The Court still means to obtain reparation for the same.
believes that the two (2) grounds invoked by defendants in The concurring opinion of Justice J.B.L. Reyes in Universal
their Motion to Dismiss dated July 16, 1984 are not Food Corp. v. Court of Appeals (33 SCRA 22) was cited by
meritorious when considered in the light of prevailing law and the appellate court.
In that case, Justice J.B.L. Reyes explained: the place of a cash payment. In other words, the relationship
x x x      x x x     x x x between the parties is no longer one of buyer and seller
... The rescission on account of breach of stipulations is not because the contract of sale has been perfected and
predicated on injury to economic interests of the party plaintiff consummated. It is already one of a mortgagor and a
but on the breach of faith by the defendant, that violates the mortgagee. In consideration of the petitioners'promise to pay
reciprocity between the parties. It is not a subsidiary action, on installment basis the sum they owe the respondents, the
and Article 1191 may be scanned without disclosing anywhere latter have accepted the mortgage as security for the
that the action for rescission thereunder is subordinated to obligation.
anything other than the culpable breach of his obligations by The situation in this case is, therefore, different from that
the defendant. This rescission is a principal action retaliatory envisioned in the cited opinion of Justice J.B.L. Reyes. The
in character, it being unjust that a party be held bound to fulfill petitioners' breach of obligations is not with respect to the
his promises when the other violates his. As expressed in the perfected contract of sale but in the obligations created by the
old Latin aphorism: "Non servanti fidem, non est fides mortgage contract. The remedy of rescission is not a principal
servanda," Hence, the reparation of damages for the breach action retaliatory in character but becomes a subsidiary one
is purely secondary. which by law is available only in the absence of any other
On the contrary, in the rescission by reason of lesion or legal remedy. (Art. 1384, Civil Code).
economic prejudice, the cause of action is subordinated to the Foreclosure here is not only a remedy accorded by law but,
existence of that prejudice, because it is the raison d 'etre as as earlier stated, is a specific provision found in the contract
well as the measure of the right to rescind. Hence, where the between the parties.
defendant makes good the damages caused, the action The petitioners are correct in citing this Court's ruling
cannot be maintained or continued, as expressly provided in in Villaruel v. Tan King (43 Phil. 251) where we Stated:
Articles 1383 and 1384. But the operation of these two articles At the outset it must be said that since the subject-matter of
is limited to the cases of rescission for lesion enumerated in the sale in question is real property, it does not come strictly
Article 1381 of the Civil Code of the Philippines, and does not within the provisions of article 1124 of the Civil Code, but is
apply to cases under Article 1191. rather subjected to the stipulations agreed upon by the
It is probable that the petitioner's confusion arose from the contracting parties and to the provisions of Article 1504 of the
defective technique of the new Code that terms both Civil Code.
instances as "rescission" without distinctions between them; The "pacto comisorio" of "ley comisoria" is nothing more than
unlike the previous Spanish Civil Code of 1889, that a condition subsequent of the contract of purchase and sale.
differentiated "resolution" for breach of stipulations from Considered carefully, it is the very condition subsequent that
"rescission" by reason of lesion or damage. But the is always attached to all bilateral obligations according to
terminological vagueness does not justify confusing one case article 1124; except that when applied to real property it is not
with the other, considering the patent difference in causes and within the scope of said article 1124, and it is subordinate to
results of either action. the stipulations made by the contracting parties and to the
According to the private respondents, the applicable law is provisions of the article on which we are now commenting"
Article 1191 of the Civil Code which provides: (article 1504). (Manresa, Civil Code, volume 10, page 286,
The power to rescind obligations is implied in reciprocal ones, second edition.)
in case one of the obligors should not comply with what is Now, in the contract of purchase and sale before us, the
incumbent upon him. parties stipulated that the payment of the balance of one
The injured party may choose between the fulfilment and the thousand pesos (P1,000) was guaranteed by the mortgage of
rescission of the obligation, with the payment of damages in the house that was sold. This agreement has the two-fold
either case. He may also seek rescission, even after he has effect of acknowledging indisputably that the sale had been
chosen fulfiument, if the latter should become impossible. consummated, so much so that the vendee was disposing of
The court shall decree the rescission claimed, unless there be it by mortgaging it to the vendor, and of waiving the pacto
just cause authorizing the fixing of a period. comisorio,  that is, the resolution of the sale in the event of
This is understood to be without prejudice to the rights of third failure to pay the one thousand pesos (P1,000) such waiver
persons who have acquired the thing, in accordance with being proved by the execution of the mortgage to guarantee
articles 1385 and 1388 and the Mortgage Law. the payment, and in accord therewith the vendor's adequate
There is no dispute that the parties entered into a contract of remedy, in case of nonpayment, is the foreclosure of such
sale as distinguished from a contract to sell. mortgage. (at pp. 255-256).
By the contract of sale, the vendor obligates himself to x x x      x x x     x x x
transfer the ownership of and to deliver a determinate thing to There is, therefore, no cause for the resolution of the sale as
the buyer, who in turn, is obligated to pay a price certain in prayed for by the plaintiff. His action, at all events, should
money or its equivalent (Art. 1458, Civil Code). From the have been one for the foreclosure of the mortgage, which is
respondents' own arguments, we note that they have fully not the action brought in this case.
complied with their part of the reciprocal obligation. As a Article 1124 of the Civil Code, as we have seen, is not
matter of fact, they have already parted with the title as applicable to this case. Neither is the doctrine enunciated in
evidenced by the transfer certificate of title in the petitioners' the case of Ocejo, Perez & Co. v. International Banking
name as of June 27, 1975. Corporation (37 Phil. 631), which plaintiff alleges to be
The buyer, in tum, fulfilled his end of the bargain when he applicable, because that principle has reference to the sale of
executed the deed of mortgage. The payments on an personal property. (at p. 257)
installment basis secured by the execution of a mortgage took The petitioners have offered to pay au past due accounts.
Considering the lower purchasing value of the peso in terms installments of THREE HUNDRED FIFTY THOUSAND
of prices of real estate today, the respondents are correct in PESOS (P350,000.00), the first to be due and payable on
stating they have suffered losses. However, they are also to June 15, 1983, and every quarter thereafter, until the whole
blame for trusting persons who could not or would not comply amount is fully paid, by these presents promise to sell to said
with their obligations in time. They could have foreclosed on BUYER the two (2) parcels of agricultural land including the
the mortgage immediately when it fell due instead of waiting rice mill and the piggery which are the most notable
all these years while trying to enforce the wrong remedy. improvements thereon, situated at Barangay Puri, San
WHEREFORE, the petition is hereby GRANTED. The Antonio Quezon, . . .
Intermediate Appellate Court's decision dated November 8, 2. That upon the payment of the total purchase price by
1985 and the resolution dated December 6, 1985 and the BUYER the SELLERS bind themselves to deliver to the
February 28, 1986 are REVERSED and SET ASIDE. The former a good and sufficient deed of sale and conveyance for
petitioners are ordered to pay the balance of their the described two (2) parcels of land, free and clear from all
indebtedness under the Deed of Absolute Sale with Mortgage liens and encumbrances.
with legal interests from the second installment due on 3. That immediately upon the execution of this document,
October 24, 1975 until fully paid, failing which the respondents the SELLERS shall deliver, surrender and transfer possession
may resort to foreclosure. of the said parcels of land including all the improvements that
SO ORDERED. may be found thereon, to the BUYER, and the latter shall take
over from the SELLER the possession, operation, control and
G.R. No. 97347 July 6, 1999 management of the RICEMILL and PIGGERY found on the
JAIME G. ONG, petitioner, aforesaid parcels of land.
vs. 4. That all payments due and payable under this contract shall
THE HONORABLE COURT OF APPEALS, SPOUSES be effected in the residence of the SELLERS located at
MIGUEL K. ROBLES and ALEJANDRO M. Barangay Puri, San Antonio, Quezon unless another place
ROBLES, respondents. shall have been subsequently designated by both parties in
writing.
YNARES-SANTIAGO, J.: xxx xxx xxx 1
Before us is a petition for review on certiorari from the On May 15, 1983, petitioner Ong took possession of the
judgment rendered by the Court of Appeals which, except as subject parcels of land together with the piggery, building,
to the award of exemplary damages, affirmed the decision of ricemill, residential house and other improvements thereon.
the Regional Trial Court of Lucena City, Branch 60, setting Pursuant to the contract they executed, petitioner paid
aside the "Agreement of Purchase and Sale" entered into by respondent spouses the sum of P103,499.91 2 by depositing
herein petitioner and private respondent spouses in Civil Case it with the United Coconut Planters Bank. Subsequently,
No. 85-85.1âwphi1.nêt petitioner deposited sums of money with the Bank of
Philippine Islands (BPI), 3 in accordance with their stipulation
On May 10, 1983, petitioner Jaime Ong, on the one hand, and that petitioner pay the loan of respondents with BPI.
respondent spouses Miguel K. Robles and Alejandra Robles, To answer for his balance of P1,400,000.00 petitioner issued
on the other hand, executed an "Agreement of Purchase and four (4) post-dated Metro Bank checks payable to respondent
Sale" respecting two parcels of land situated at Barrio Puri, spouses in the amount of P350,0000.00 each, namely: Check
San Antonio, Quezon. The terms and conditions of the No. 157708 dated June 15, 1983, 4 Check No. 157709 dated
contract read:" September 15, 1983, 5 Check No. 157710 dated December
1. That for and in consideration of the agreed purchase price 15, 1983 6 and Check No. 157711 dated March 15,
of TWO MILLION PESOS (P2,000,000.00), Philippine 1984. 7 When presented for payment, however, the checks
currency, the mode and manner of payment is as follows: were dishonored due to insufficient funds. Petitioner promised
A. The initial payment of SIX HUNDRED THOUSAND PESOS to replace the checks but failed to do so. To make matters
(P600,000.00) as verbally agreed by the parties, shall be worse, out of the P496,500.00 loan of respondent spouses
broken down as follows: with the Bank of the Philippine Islands, which petitioner, as
1. P103,499.91 shall be paid, and as already paid by per agreement, should have paid, petitioner only managed to
the BUYER to the SELLERS on March 22, 1983, as stipulated dole out no more than P393,679.60. When the bank
under the Certification of undertaking dated March 22, 1983 threatened to foreclose the respondent spouses' mortgage,
and covered by a check of even date. they sold three transformers of the rice mill worth P51,411.00
2. That the sum of P496,500.09 shall be paid directly by to pay off their outstanding obligation with said bank, with the
the BUYER to the Bank of Philippine Islands to answer for the knowledge and conformity of petitioner. 8 Petitioner, in return,
loan of the SELLERS which as of March 15, 1983 amounted voluntarily gave the spouses authority to operate the rice
to P537,310.10, and for the interest that may accrued (sic) mill. 9 He, however, continued to be in possession of the two
from March 15, 1983, up to the time said obligation of parcels of land while private respondents were forced to use
the SELLERS with the said bank has been settled, provided the rice mill for residential purposes.
however that the amount in excess of P496,500.09, shall be On August 2, 1985, respondent spouses, through counsel,
chargeable from the time deposit of the SELLERS with the sent petitioner a demand letter asking for the return of the
aforesaid bank. properties. Their demand was left unheeded, so, on
B. That the balance of ONE MILLION FOUR HUNDRED September 2, 1985, they filed with the Regional Trial Court of
THOUSAND (P1,400,000.00) PESOS shall be paid by Lucena City, Branch 60, a complaint for rescission of contract
the BUYER to the SELLERS in four (4) equal quarterly and recovery of properties with damages. Later, while the
case was still pending with the trial court, petitioner introduced Rescission, as contemplated in Articles 1380, et seq., of the
major improvements on the subject properties by constructing New Civil Code, is a remedy granted by law to the contracting
a complete fence made of hollow blocks and expanding the parties and even to third persons, to secure the reparation of
piggery. These prompted the respondent spouses to ask for a damages caused to them by a contract, even if this should be
writ of preliminary injunction. 10 The trial court granted the valid, by restoration of things to their condition at the moment
application and enjoined petitioner from introducing prior to the celebration of the contract. 14 It implies a contract,
improvements on the properties except for repairs. 11 which even if initially valid, produces a lesion or a pecuniary
On June 1, 1989 the trial court rendered a decision, the damage to someone. 15
dispositive portion of which reads as follows: On the other hand, Article 1191 of the New Civil Code refers
IN VIEW OF THE FOREGOING, judgment is hereby to rescission applicable to reciprocal obligations. Reciprocal
rendered: obligations are those which arise from the same cause, and in
a) Ordering that the contract entered into by plaintiff spouses which each party is a debtor and a creditor of the other, such
Miguel K. Robles and Alejandra M. Robles and the defendant, that the obligation of one is dependent upon the obligation of
Jaime Ong captioned "Agreement of Purchase and Sale," the other. 16 They are to be performed simultaneously such
marked as Exhibit "A" set aside; that the performance of one is conditioned upon the
b) Ordering defendant, Jaime Ong to deliver the two (2) simultaneous fulfillment of the other. Rescission of reciprocal
parcels of land which are the subject matter of Exhibit "A" obligations under Article 1191 of the New Civil Code should
together with the improvements thereon to the spouses be distinguished from rescission of contracts under Article
Miguel K. Robles and Alejandro M. Robles; 1383. Although both presuppose contracts validly entered into
c) Ordering plaintiff spouses, Miguel Robles and Alejandra and subsisting and both require mutual restitution when
Robles to return to Jaime Ong the sum of P497,179.51; proper, they are not entirely identical.
d) Ordering defendant Jaime Ong to pay the plaintiffs the sum While Article 1191 uses the term "rescission," the original term
of P100,000.00 as exemplary damages; and which was used in the old Civil Code, from which the article
e) Ordering defendant Jaime Ong to pay the plaintiffs spouses was based, was "resolution. 17" Resolution is a principal
Miguel K. Robles and Alejandra Robles the sum of action which is based on breach of a party, while rescission
P20,000.00 as attorney's fees and litigation expenses. under Article 1383 is a subsidiary action limited to cases of
The motion of the plaintiff spouses Miguel K. Roles and rescission for lesion under Article 1381 of the New Civil Code,
Alejandra Robles for the appointment of receivership is which expressly enumerates the following rescissible
rendered moot and academic. contracts:
SO ORDERED. 12 1. Those which are entered into by guardians whenever the
From this decision, petitioner appealed to the Court of wards whom they represent suffer lesion by more than one
Appeals, which affirmed the decision of the Regional Trial fourth of the value of the things which are the object thereof;
Court but deleted the award of exemplary damages. In 2. Those agreed upon in representation of absentees, if the
affirming the decision of the trial court, the Court of Appeals latter suffer the lesion stated in the preceding number;
noted that the failure of petitioner to completely pay the 3. Those undertaken in fraud of creditors when the latter
purchase price is a substantial breach of his obligation which cannot in any manner collect the claims due them;
entitles the private respondents to rescind their contract under 4. Those which refer to things under litigation if they have
Article 1191 of the New Civil Code. Hence, the instant petition. been entered into by the defendant without the knowledge
At the outset, it must be stated that the issues raised by the and approval of the litigants or of competent judicial authority;
petitioner are generally factual in nature and were already 5. All other contracts specially declared by law to be subject to
passed upon by the Court of Appeals and the trial court. Time rescission.
and again, we have stated that it is not the function of the Obviously, the contract entered into by the parties in the case
Supreme Court to assess and evaluate all over again the at bar does not fall under any of those mentioned by Article
evidence, testimonial and documentary, adduced by the 1381. Consequently, Article 1383 is inapplicable.
parties to an appeal, particularly where, such as in the case at May the contract entered into between the parties, however,
bench, the findings of both the trial court and the appellate be rescinded based on Article 1191?
court on the matter coincide. There is no cogent reason A careful reading of the parties' "Agreement of Purchase and
shown that would justify the court to discard the factual Sale" shows that it is in the nature of a contract to sell, as
findings of the two courts below and to superimpose its distinguished from a contract of sale. In a contract of sale, the
own. 13 title to the property passes to the vendee upon the delivery of
The only pertinent legal issues raised which are worthy of the thing sold; while in a contract to sell, ownership is, by
discussion are (1) whether the contract entered into by the agreement, reserved in the vendor and is not to pass to the
parties may be validly rescinded under Article 1191 of the vendee until full payment of the purchase price. 18 In a
New Civil Code; and (2) whether the parties had novated their contract to sell, the payment of the purchase price is a
original contract as to the time and manner of payment. positive suspensive condition, the failure of which is not a
Petitioner contends that Article 1191 of the New Civil Code is breach, casual or serious, but a situation that prevents the
not applicable since he has already paid respondent spouses obligation of the vendor to convey title from acquiring an
a considerable sum and has therefore substantially complied obligatory force. 19
with his obligation. He cites Article 1383 instead, to the effect Respondents in the case at bar bound themselves to deliver a
that where specific performance is available as a remedy, deed of absolute sale and clean title covering the two parcels
rescission may not be resorted to. of land upon full payment by the buyer of the purchase price
A discussion of the aforesaid articles is in order. of P2,000,000.00. This promise to sell was subject to the
fulfillment of the suspensive condition of full payment of the purchase price in the sum of P496,500.00 would be directly
purchase price by the petitioner. Petitioner, however, failed to deposited by petitioner to the Bank of Philippine Islands to
complete payment of the purchase price. The non-fulfillment answer for the loan of respondent spouses, petitioner only
of the condition of full payment rendered the contract to sell managed to deposit P393,679.60. When the bank threatened
ineffective and without force and effect. It must be stressed to foreclose the properties, petitioner apparently could not
that the breach contemplated in Article 1191 of the New Civil even raise the sum needed to forestall any action on the part
Code is the obligor's failure to comply with an of the bank. Consequently, he authorized respondent spouses
obligation. 20 Failure to pay, in this instance, is not even a to sell the three (3) transformers. However, although the
breach but merely an event which prevents the vendor's parties agreed to credit the proceeds from the sale of the
obligation to convey title from acquiring binding transformers to petitioner's obligation, he was supposed to
force. 21 Hence, the agreement of the parties in the case at reimburse the same later to respondent spouses. This can
bench may be set aside, but not because of a breach on the only mean that there was never an intention on the part of
part of petitioner for failure to complete payment of the either of the parties to novate petitioner's manner of payment.
purchase price. Rather, his failure to do so brought about a Petitioner contends that the parties verbally agreed to novate
situation which prevented the obligation of respondent the manner of payment when respondent spouses proposed
spouses to convey title from acquiring an obligatory force. to operate the rice mill on the condition that they will account
Petitioner insists, however, that the contract was novated as for its earnings. We find that this is unsubstantiated by the
to the manner and time of payment. evidenced on the record. The tenor of his letter dated August
We are not persuaded. Article 1292 of the New Civil Code 12, 1984 to respondent spouses, in fact, shows that petitioner
states that, "In order that an obligation may be extinguished had a "little misunderstanding" with respondent spouses
by another which substitutes the same, it is imperative that it whom he was evidently trying to appease by authorizing them
be so declared in unequivocal terms, or that the old and the to continue temporarily with the operation of the rice mill.
new obligations be on every point incompatible with each Clearly, while petitioner might have wanted to novate the
other." original agreement as to his manner of payment, the records
Novation is never presumed, it must be proven as a fact either are bereft of evidence that respondent spouses willingly
by express stipulation of the parties or by implication derived agreed to modify their previous arrangement.
from an irreconcilable incompatibility between the old and the In order for novation to take place, the concurrence of the
new obligation. 22 Petitioner cites the following instances as following requisites is indispensable: (1) there must be a
proof that the contract was novated: the retrieval of the previous valid obligation; (2) there must be an agreement of
transformers from petitioner's custody and their sale by the the parties concerned to a new contract; (3) there must be the
respondents to MERALCO on the condition that the proceeds extinguishment of the old contract; and (4) there must be the
thereof be accounted for by the respondents and deducted validity of the new contract. 25 The aforesaid requisites are
from the price of the contract; the take-over by the not found in the case at bench. The subsequent acts of the
respondents of the custody and operation of the rice mill; and parties hardly demonstrate their intent to dissolve the old
the continuous and regular withdrawals by respondent Miguel obligation as a consideration for the emergence of the new
Robles of installment sums per vouchers (Exhs. "8" to "47") one. We repeat to the point of triteness, novation is never
on the condition that these installments be credited to presumed, there must be an express intention to novate.
petitioner's account and deducted from the balance of the As regards the improvements introduced by petitioner to the
purchase price. premises and for which he claims reimbursement, we see no
Contrary to petitioner's claim, records show that the parties reason to depart from the ruling of the trial court and the
never even intended to novate their previous agreement. It is appellate court that petitioner is a builder in bad faith. He
true that petitioner paid respondents small sums of money introduced the improvements on the premises knowing fully
amounting to P48,680.00, in contravention of the manner of well that he has not paid the consideration of the contract in
payment stipulated in their contract. These installments were, full and over the vigorous objections of respondent spouses.
however, objected to by respondent spouses, and petitioner Moreover, petitioner introduced major improvements on the
replied that these represented the interest of the principal premises even while the case against him was pending before
amount which he owed them. 23 Records further show that the trial court.
petitioner agreed to the sale of MERALCO transformers by The award of exemplary damages was correctly deleted by
private respondents to pay for the balance of their subsisting the Court of Appeals in as much as no moral, temperate,
loan with the Bank of Philippine Islands. Petitioner's letter of liquidated or compensatory damages in addition to exemplary
authorization reads: damages were awarded.
xxx xxx xxx WHEREFORE, the decision rendered by the Court of Appeals
Under this authority, it is mutually understood that whatever is hereby AFFIRMED with the MODIFICATION that
payment received from MERALCO as payment to the respondent spouses are ordered to return to petitioner the
transfromers will be considered as partial payment of the sum of P48,680.00 in addition to the amounts already
undersigned's obligation to Mr. and Mrs. Miguel K. Robles. awarded. Costs against petitioner.1âwphi1.nêt
The same will be utilized as partial payment to existing loan
with the Bank of Philippine Islands. SO ORDERED.
It is also mutually understood that this payment to the Bank of
Philippine Islands will be reimbursed to Mr. and Mrs. Miguel K. G.R. No. 133632        February 15, 2002
Robles by the undersigned. [Emphasis supplied] 24 BPI INVESTMENT CORPORATION, petitioner,
It should be noted that while it was. agreed that part of the vs.
HON. COURT OF APPEALS and ALS MANAGEMENT & 52093 against BPIIC. They alleged, among others, that they
DEVELOPMENT CORPORATION, respondents. were not in arrears in their payment, but in fact made an
DECISION overpayment as of June 30, 1984. They maintained that they
QUISUMBING, J.: should not be made to pay amortization before the actual
This petition for certiorari assails the decision dated February release of the ₱500,000 loan in August and September 1982.
28, 1997, of the Court of Appeals and its resolution dated April Further, out of the ₱500,000 loan, only the total amount of
21, 1998, in CA-G.R. CV No. 38887. The appellate court ₱464,351.77 was released to private respondents. Hence,
affirmed the judgment of the Regional Trial Court of Pasig applying the effects of legal compensation, the balance of
City, Branch 151, in (a) Civil Case No. 11831, for foreclosure ₱35,648.23 should be applied to the initial monthly
of mortgage by petitioner BPI Investment Corporation (BPIIC amortization for the loan.
for brevity) against private respondents ALS Management and On August 31, 1988, the trial court rendered its judgment in
Development Corporation and Antonio K. Civil Case Nos. 11831 and 52093, thus:
Litonjua,1 consolidated with (b) Civil Case No. 52093, for WHEREFORE, judgment is hereby rendered in favor of ALS
damages with prayer for the issuance of a writ of preliminary Management and Development Corporation and Antonio K.
injunction by the private respondents against said petitioner. Litonjua and against BPI Investment Corporation, holding that
The trial court had held that private respondents were not in the amount of loan granted by BPI to ALS and Litonjua was
default in the payment of their monthly amortization, hence, only in the principal sum of P464,351.77, with interest at 20%
the extrajudicial foreclosure conducted by BPIIC was plus service charge of 1% per annum, payable on equal
premature and made in bad faith. It awarded private monthly and successive amortizations at P9,283.83 for ten
respondents the amount of ₱300,000 for moral damages, (10) years or one hundred twenty (120) months. The
₱50,000 for exemplary damages, and ₱50,000 for attorney’s amortization schedule attached as Annex "A" to the "Deed of
fees and expenses for litigation. It likewise dismissed the Mortgage" is correspondingly reformed as aforestated.
foreclosure suit for being premature. The Court further finds that ALS and Litonjua suffered
The facts are as follows: compensable damages when BPI caused their publication in
Frank Roa obtained a loan at an interest rate of 16 1/4% per a newspaper of general circulation as defaulting debtors, and
annum from Ayala Investment and Development Corporation therefore orders BPI to pay ALS and Litonjua the following
(AIDC), the predecessor of petitioner BPIIC, for the sums:
construction of a house on his lot in New Alabang Village, a) P300,000.00 for and as moral damages;
Muntinlupa. Said house and lot were mortgaged to AIDC to b) P50,000.00 as and for exemplary damages;
secure the loan. Sometime in 1980, Roa sold the house and c) P50,000.00 as and for attorney’s fees and expenses of
lot to private respondents ALS and Antonio Litonjua for litigation.
₱850,000. They paid ₱350,000 in cash and assumed the The foreclosure suit (Civil Case No. 11831) is hereby
₱500,000 balance of Roa’s indebtedness with AIDC. The DISMISSED for being premature.
latter, however, was not willing to extend the old interest rate Costs against BPI.
to private respondents and proposed to grant them a new SO ORDERED.2
loan of ₱500,000 to be applied to Roa’s debt and secured by Both parties appealed to the Court of Appeals. However,
the same property, at an interest rate of 20% per annum and private respondents’ appeal was dismissed for non-payment
service fee of 1% per annum on the outstanding principal of docket fees.
balance payable within ten years in equal monthly On February 28, 1997, the Court of Appeals promulgated its
amortization of ₱9,996.58 and penalty interest at the rate of decision, the dispositive portion reads:
21% per annum per day from the date the amortization WHEREFORE, finding no error in the appealed decision the
became due and payable. same is hereby AFFIRMED in toto.
Consequently, in March 1981, private respondents executed a SO ORDERED.3
mortgage deed containing the above stipulations with the In its decision, the Court of Appeals reasoned that a simple
provision that payment of the monthly amortization shall loan is perfected only upon the delivery of the object of the
commence on May 1, 1981. contract. The contract of loan between BPIIC and ALS &
On August 13, 1982, ALS and Litonjua updated Roa’s Litonjua was perfected only on September 13, 1982, the date
arrearages by paying BPIIC the sum of ₱190,601.35. This when BPIIC released the purported balance of the ₱500,000
reduced Roa’s principal balance to ₱457,204.90 which, in loan after deducting therefrom the value of Roa’s
turn, was liquidated when BPIIC applied thereto the proceeds indebtedness. Thus, payment of the monthly amortization
of private respondents’ loan of ₱500,000. should commence only a month after the said date, as can be
On September 13, 1982, BPIIC released to private inferred from the stipulations in the contract. This, despite the
respondents ₱7,146.87, purporting to be what was left of their express agreement of the parties that payment shall
loan after full payment of Roa’s loan. commence on May 1, 1981. From October 1982 to June
In June 1984, BPIIC instituted foreclosure proceedings 1984, the total amortization due was only ₱194,960.43.
against private respondents on the ground that they failed to Evidence showed that private respondents had an
pay the mortgage indebtedness which from May 1, 1981 to overpayment, because as of June 1984, they already paid a
June 30, 1984, amounted to Four Hundred Seventy Five total amount of ₱201,791.96. Therefore, there was no basis
Thousand Five Hundred Eighty Five and 31/100 Pesos for BPIIC to extrajudicially foreclose the mortgage and cause
(₱475,585.31). A notice of sheriff’s sale was published on the publication in newspapers concerning private
August 13, 1984. respondents’ delinquency in the payment of their loan. This
On February 28, 1985, ALS and Litonjua filed Civil Case No. fact constituted sufficient ground for moral damages in favor
of private respondents. the money. In reciprocal obligations, neither party incurs in
The motion for reconsideration filed by petitioner BPIIC was delay if the other does not comply or is not ready to comply in
likewise denied, hence this petition, where BPIIC submits for a proper manner with what is incumbent upon him. Therefore,
resolution the following issues: private respondents conclude, they did not incur in delay
I. WHETHER OR NOT A CONTRACT OF LOAN IS A when they did not commence paying the monthly amortization
CONSENSUAL CONTRACT IN THE LIGHT OF THE RULE on May 1, 1981, as it was only on September 13, 1982 when
LAID DOWN IN BONNEVIE VS. COURT OF APPEALS, 125 petitioner fully complied with its obligation under the loan
SCRA 122. contract.
II. WHETHER OR NOT BPI SHOULD BE HELD LIABLE FOR We agree with private respondents. A loan contract is not a
MORAL AND EXEMPLARY DAMAGES AND ATTORNEY’S consensual contract but a real contract. It is perfected only
FEES IN THE FACE OF IRREGULAR PAYMENTS MADE BY upon the delivery of the object of the contract.5 Petitioner
ALS AND OPPOSED TO THE RULE LAID DOWN misapplied Bonnevie. The contract in Bonnevie  declared by
IN SOCIAL SECURITY SYSTEM VS. COURT OF APPEALS, this Court as a perfected consensual contract falls under the
120 SCRA 707. first clause of Article 1934, Civil Code. It is an accepted
On the first issue, petitioner contends that the Court of promise to deliver something by way of simple loan.
Appeals erred in ruling that because a simple loan is In Saura Import and Export Co. Inc. vs. Development Bank of
perfected upon the delivery of the object of the contract, the the Philippines, 44 SCRA 445, petitioner applied for a loan of
loan contract in this case was perfected only on September ₱500,000 with respondent bank. The latter approved the
13, 1982. Petitioner claims that a contract of loan is a application through a board resolution. Thereafter, the
consensual contract, and a loan contract is perfected at the corresponding mortgage was executed and registered.
time the contract of mortgage is executed conformably with However, because of acts attributable to petitioner, the loan
our ruling in Bonnevie v. Court of Appeals, 125 SCRA 122. In was not released. Later, petitioner instituted an action for
the present case, the loan contract was perfected on March damages. We recognized in this case, a perfected consensual
31, 1981, the date when the mortgage deed was executed, contract which under normal circumstances could have made
hence, the amortization and interests on the loan should be the bank liable for not releasing the loan. However, since the
computed from said date. fault was attributable to petitioner therein, the court did not
Petitioner also argues that while the documents showed that award it damages.
the loan was released only on August 1982, the loan was A perfected consensual contract, as shown above, can give
actually released on March 31, 1981, when BPIIC issued a rise to an action for damages. However, said contract does
cancellation of mortgage of Frank Roa’s loan. This finds not constitute the real contract of loan which requires the
support in the registration on March 31, 1981 of the Deed of delivery of the object of the contract for its perfection and
Absolute Sale executed by Roa in favor of ALS, transferring which gives rise to obligations only on the part of the
the title of the property to ALS, and ALS executing the borrower.6
Mortgage Deed in favor of BPIIC. Moreover, petitioner claims, In the present case, the loan contract between BPI, on the
the delay in the release of the loan should be attributed to one hand, and ALS and Litonjua, on the other, was perfected
private respondents. As BPIIC only agreed to extend a only on September 13, 1982, the date of the second release
₱500,000 loan, private respondents were required to reduce of the loan. Following the intentions of the parties on the
Frank Roa’s loan below said amount. According to petitioner, commencement of the monthly amortization, as found by the
private respondents were only able to do so in August 1982. Court of Appeals, private respondents’ obligation to pay
In their comment, private respondents assert that based on commenced only on October 13, 1982, a month after the
Article 1934 of the Civil Code,4 a simple loan is perfected perfection of the contract.7
upon the delivery of the object of the contract, hence a real We also agree with private respondents that a contract of loan
contract. In this case, even though the loan contract was involves a reciprocal obligation, wherein the obligation or
signed on March 31, 1981, it was perfected only on promise of each party is the consideration for that of the
September 13, 1982, when the full loan was released to other.8 As averred by private respondents, the promise of
private respondents. They submit that petitioner BPIIC to extend and deliver the loan is upon the consideration
misread Bonnevie.  To give meaning to Article 1934, according that ALS and Litonjua shall pay the monthly amortization
to private respondents, Bonnevie  must be construed to mean commencing on May 1, 1981, one month after the supposed
that the contract to extend the loan was perfected on March release of the loan. It is a basic principle in reciprocal
31, 1981 but the contract of loan itself was only perfected obligations that neither party incurs in delay, if the other does
upon the delivery of the full loan to private respondents on not comply or is not ready to comply in a proper manner with
September 13, 1982. what is incumbent upon him.9 Only when a party has
Private respondents further maintain that even performed his part of the contract can he demand that the
granting, arguendo, that the loan contract was perfected on other party also fulfills his own obligation and if the latter fails,
March 31, 1981, and their payment did not start a month default sets in. Consequently, petitioner could only demand
thereafter, still no default took place. According to private for the payment of the monthly amortization after September
respondents, a perfected loan agreement imposes reciprocal 13, 1982 for it was only then when it complied with its
obligations, where the obligation or promise of each party is obligation under the loan contract. Therefore, in computing
the consideration of the other party. In this case, the the amount due as of the date when BPIIC extrajudicially
consideration for BPIIC in entering into the loan contract is the caused the foreclosure of the mortgage, the starting date is
promise of private respondents to pay the monthly October 13, 1982 and not May 1, 1981.
amortization. For the latter, it is the promise of BPIIC to deliver Other points raised by petitioner in connection with the first
issue, such as the date of actual release of the loan and Additionally, petitioner is ORDERED to pay private
whether private respondents were the cause of the delay in respondents ₱25,000 as nominal damages. Costs against
the release of the loan, are factual. Since petitioner has not petitioner.
shown that the instant case is one of the exceptions to the SO ORDERED.
basic rule that only questions of law can be raised in a petition
for review under Rule 45 of the Rules of Court,10 factual G.R. No. 129107      September 26, 2001
matters need not tarry us now. On these points we are bound ALFONSO L. IRINGAN, petitioner,
by the findings of the appellate and trial courts. vs.
On the second issue, petitioner claims that it should not be HON. COURT OF APPEALS and ANTONIO PALAO,
held liable for moral and exemplary damages for it did not act represented by his Attorney-in-Fact, FELISA P. DELOS
maliciously when it initiated the foreclosure proceedings. It SANTOS, respondents.
merely exercised its right under the mortgage contract QUISUMBING, J.:
because private respondents were irregular in their monthly This petition assails the Decision 1 dated April 30, 1997 of the
amortization.1âwphi1 It invoked our ruling in Social Security Court of Appeals in CA G.R. CV No. 39949, affirming the
System vs. Court of Appeals, 120 SCRA 707, where we said: decision of the Regional Trial Court and deleting the award of
Nor can the SSS be held liable for moral and temperate attorney's fee.
damages. As concluded by the Court of Appeals "the The facts of the case are based on the records.
negligence of the appellant is not so gross as to warrant moral On March 22, 1985, private respondent Antonio Palao sold to
and temperate damages," except that, said Court reduced petitioner Alfonso Iringan, an undivided portion of Lot No. 992
those damages by only P5,000.00 instead of eliminating of the Tuguegarao Cadastre, located at the Poblacion of
them. Neither can we agree with the findings of both the Trial Tuguegarao and covered by Transfer Certificate of Title No. T-
Court and respondent Court that the SSS had acted 5790. The parties executed a Deed of Sale 2 on the same date
maliciously or in bad faith. The SSS was of the belief that it with the purchase price of P295,000.00, payable as follows:
was acting in the legitimate exercise of its right under the (a) P10,000.00 - upon the execution of this instrument, and for
mortgage contract in the face of irregular payments made by this purpose, the vendor acknowledges having received the
private respondents and placed reliance on the automatic said amount from the vendee as of this date;
acceleration clause in the contract. The filing alone of the (b) P140,000.00 - on or before April 30, 1985;
foreclosure application should not be a ground for an award of (c) P145,000.00 - on or before December 31, 1985. 3
moral damages in the same way that a clearly unfounded civil When the second payment was due, Iringan paid only
action is not among the grounds for moral damages. P40,000. Thus, on July 18, 1985, Palao sent a letter 4 to
Private respondents counter that BPIIC was guilty of bad faith Iringan stating that he considered the contract as rescinded
and should be liable for said damages because it insisted on and that he would not accept any further payment considering
the payment of amortization on the loan even before it was that Iringan failed to comply with his obligation to pay the full
released. Further, it did not make the corresponding deduction amount of the second installment.
in the monthly amortization to conform to the actual amount of On August 20, 1985, Iringan through his counsel Atty. Hilarion
loan released, and it immediately initiated foreclosure L. Aquino,5 replied that they were not opposing the revocation
proceedings when private respondents failed to make timely of the Deed of Sale but asked for the reimbursement of the
payment. following amounts:
But as admitted by private respondents themselves, they (a) P50,000.00 - cash received by you;
were irregular in their payment of monthly amortization. (b) P3,200.00 - geodetic engineer's fee;
Conformably with our ruling in  SSS,  we can not properly (c) P500.00 - attorney's fee;
declare BPIIC in bad faith. Consequently, we should rule out (d) the current interest on P53,700.00.6
the award of moral and exemplary damages.11 In response, Palao sent a letter dated January 10, 1986, 7 to
However, in our view, BPIIC was negligent in relying merely Atty. Aquino, stating that he was not amenable to the
on the entries found in the deed of mortgage, without reimbursements claimed by Iringan.
checking and correspondingly adjusting its records on the On February 21, 1989, Iringan, now represented by anew
amount actually released to private respondents and the date counsel - Atty. Carmelo Z. Lasam, proposed that the P50,000
when it was released. Such negligence resulted in damage to which he had already paid Palao be reimbursed 8 or Palao
private respondents, for which an award of nominal damages could sell to Iringan, an equivalent portion of the land.
should be given in recognition of their rights which were Palao instead wrote Iringan that the latter's standing
violated by BPIIC.12 For this purpose, the amount of ₱25,000 obligation had reached P61,600, representing payment of
is sufficient. arrears for rentals from October 1985 up to March 1989. 9 The
Lastly, as in SSS  where we awarded attorney’s fees because parties failed to arrive at an agreement.
private respondents were compelled to litigate, we sustain the On July 1, 1991, Palao filed a Complaint 10 for Judicial
award of ₱50,000 in favor of private respondents as attorney’s Confirmation of Rescission of Contract and Damages against
fees. Iringan and his wife.
WHEREFORE, the decision dated February 28, 1997, of the In their Answer,11 the spouses alleged that the contract of sale
Court of Appeals and its resolution dated April 21, 1998, are was a consummated contract, hence, the remedy of Palao
AFFIRMED WITH MODIFICATION as to the award of was for collection of the balance of the purchase price and not
damages. The award of moral and exemplary damages in rescission. Besides, they said that they had always been
favor of private respondents is DELETED, but the award to ready and willing to comply with their obligations in
them of attorney’s fees in the amount of ₱50,000 is UPHELD. accordance with said contract.
In a Decision12 dated September 25, 1992, the Regional Trial Clearly, a judicial or notarial act is necessary before a valid
Court of Cagayan, Branch I, ruled in favor of Palao and rescission can take place, whether or not automatic rescission
affirmed the rescission of the contract. It disposed, has been stipulated. It is to be noted that the law uses the
WHEREFORE, the Court finds that the evidence phrase "even though"20 emphasizing that when no stipulation
preponderates in favor of the plaintiff and against the is found on automatic rescission, the judicial or notarial
defendants and judgment is hereby rendered as follows: requirement still applies.
(a) Affirming the rescission of the contract of sale; On the first issue, both the trial and appellate courts affirmed
(b) Cancelling the adverse claim of the defendants annotated the validity of the alleged mutual agreement to rescind based
at the back of TCT No. T-5790; on Article 1191 of the Civil Code, particularly paragraphs 1
(c) Ordering the defendants to vacate the premises; and 2 thereof.
(d) Ordering the defendants to pay jointly and severally the Article 1191. The power to rescind obligations is implied
sum of P100,000.00 as reasonable compensation for use of in reciprocal ones, in case one of the obligors should not
the property minus 50% of the amount paid by them; and to comply with what is incumbent upon him.
pay P50,000.00 as moral damages; P10,000.00 as exemplary The injured party may choose between the fulfillment and
damages; and P50,000.00 as attorney's fee; and to pay the the rescission of the obligation, with payment of
costs of suit. damages in either case. He may also seek rescission,
SO ORDERED.13 even after he has chosen fulfillment, if the latter should
As stated, the Court of Appeals affirmed the above decision. become impossible. [Emphasis ours.]
Hence, this petition for review. The court shall decree the rescission claimed, unless there be
Iringan avers in this petition that the Court of Appeals erred: just cause authorizing the fixing of a period.
1. In holding that the lower court did not err in affirming the This is understood to be without prejudice to the rights of third
rescission of the contract of sale; and persons who have acquired the thing, in accordance with
2. In holding that defendant was in bad faith for "resisting" articles 1385 and 1388 and the Mortgage Law.
rescission and was made liable to pay moral and exemplary But in our view, even if Article 1191 were applicable, petitioner
damages.14 would still not be entitled to automatic rescission. In Escueta
We find two issues for resolution: (1) whether or not the v. Pando,21 we ruled that under Article 1124 (now Article 1191)
contract of sale was validly rescinded, and (2) whether or not of the Civil Code, the right to resolve reciprocal obligations, is
the award of moral and exemplary damages is proper. deemed implied in case one of the obligors shall fail to comply
On the first issue, petitioner contends that no rescission was with what is incumbent upon him. But that right must be
effected simply by virtue of the letter15 sent by respondent invoked judicially. The same article also provides: "The Court
stating that he considered the contract of sale rescinded. shall decree the resolution demanded, unless there should be
Petitioner asserts that a judicial or notarial act is necessary grounds which justify the allowance of a term for the
before one party can unilaterally effect a rescission. performance of the obligation."
Respondent Palao, on the other hand, contends that the right This requirement has been retained in the third paragraph of
to rescind is vested by law on the obligee and since petitioner Article 1191, which states that "the court shall decree the
did not oppose the intent to rescind the contract, Iringan in rescission claimed, unless there be just cause authorizing the
effect agreed to it and had the legal effect of a mutually fixing of a period."
agreed rescission. Consequently, even if the right to rescind is made available to
Article 1592 of the Civil Code is the applicable provision the injured party,22 the obligation is not ipso facto erased by
regarding the sale of an immovable property. the failure of the other party to comply with what is incumbent
Article 1592. In the sale of immovable property, even though it upon him. The party entitled to rescind should apply to the
may have been stipulated that upon failure to pay the price at court for a decree of rescission. 23 The right cannot be
the time agreed upon the rescission of the contract shall of exercised solely on a party's own judgment that the other
right take place, the vendee may pay, even after the committed a breach of the obligation. 24 The operative act
expiration of the period, as long as no demand for rescission which produces the resolution of the contract is the decree of
of the contract has been made upon him either judicially or by the court and not the mere act of the vendor. 25 Since a judicial
a notarial act. After the demand, the court may not grant him or notarial act is required by law for a valid rescission to take
a new term. (Italics supplied) place, the letter written by respondent declaring his intention
Article 1592 requires the rescinding party to serve judicial or to rescind did not operate to validly rescind the contract.
notarial notice of his intent to resolve the contract. 16 Notwithstanding the above, however, in our view when private
In the case of Villaruel v. Tan King,17  we ruled in this wise, respondent filed an action for Judicial Confirmation of
...since the subject-matter of the sale in question is real Rescission and Damages26 before the RTC, he complied with
property, it does not come strictly within the provisions of the requirement of the law for judicial decree of rescission.
article 1124 (now Article 1191) of the Civil Code, but is rather The complaint27 categorically stated that the purpose was 1)
subjected to the stipulations agreed upon by the contracting to compel appellants to formalize in a public document, their
parties and to the provisions of article 1504 (now Article 1592) mutual agreement of revocation and rescission; and/or 2) to
of the Civil Code."18 have a judicial confirmation of the said revocation/rescission
Citing Manresa, the Court said that the requirement of then under terms and conditions fair, proper and just for both
Article 1504, "refers to a demand that the vendor makes upon parties.28 In Luzon Brokerage Co., Inc.  v. Maritime Building
the vendee for the latter to agree to the resolution of the Co., Inc.,29 we held that even a crossclaim found in the
obligation and to create no obstacles to this contractual mode Answer could constitute a judicial demand for rescission that
of extinguishing obligations."19 satisfies the requirement of the law.30
Petitioner contends that even if the filing of the case were RJH TRADING, represented by RAMON J. HIBIONADA,
considered the judicial act required, the action should be proprietor, respondents.
deemed prescribed based on the provisions of Article 1389 of Saleto J. Erames and Edilberto V. Logronio for petitioners.
the Civil Code.31 Eugenio O. Original for private respondent.
This provision of law applies to rescissible contracts, 32 as SYLLABUS
enumerated and defined in Articles 1380 33 and 1381.34 We 1. CIVIL LAW; CONTRACT TO SELL; EFFECT OF
must stress however, that the "rescission" in Article 1381 is VENDEE'S FAILURE TO COMPLY WITH POSITIVE
not akin to the term "rescission" in Article 1191 and Article SUSPENSIVE CONDITION; CASE AT BAR. — The petitioner
1592.35 In Articles 1191 and 1592, the rescission is a principal corporation's obligation to sell is unequivocally subject to a
action which seeks the resolution or cancellation of the positive suspensive condition, i.e., the private respondent's
contract while in Article 1381, the action is a subsidiary one opening, making or indorsing of an irrevocable and
limited to cases of rescission for lesion as enumerated in said unconditional letter of credit. The former agreed to deliver the
article.36 scrap iron only upon payment of the purchase price by means
The prescriptive period applicable to rescission under Articles of an irrevocable and unconditional letter of credit. Otherwise
1191 and 1592, is found in Article 1144, 37 which provides that stated, the contract is not one of sale where the buyer
the action upon a written contract should be brought within ten acquired ownership over the property subject to the resolutory
years from the time the right of action accrues. The suit was condition that the purchase price would be paid after delivery.
brought on July 1, 1991, or six years after the default. It was Thus, there was to be no actual sale until the opening, making
filed within the period for rescission. Thus, the contract of sale or indorsing of the irrevocable and unconditional letter of
between the parties as far as the prescriptive period applies, credit. Since what obtains in the case at bar is a mere
can still be validly rescinded. promise to sell, the failure of the private respondent to comply
On the issue of moral and exemplary damages, petitioner with the positive suspensive condition cannot even be
claims that the Court of Appeals erred in finding bad faith on considered a breach — casual or serious — but simply an
his part when he resisted the rescission 38 and claimed he was event that prevented the obligation of petitioner corporation to
ready to pay but never actually paid respondent, convey title from acquiring binding force. In Luzon Brokerage
notwithstanding that he knew that appellee's principal Co., Inc. vs. Maritime Building Co., Inc., this Court stated: ". . .
motivation for selling the lot was to raise money to pay his The upshot of all these stipulations is that in seeking the
SSS loan.39 Petitioner would have us reverse the said CA ouster of Maritime for failure to pay the price as agreed upon,
findings based on the exception 40 that these findings were Myers was not rescinding (or more properly, resolving) the
made on a misapprehension of facts. contract, but precisely enforcing it according to its express
The records do not support petitioner's claims. First, per the terms. In its suit Myers was not seeking restitution to it of the
records, petitioner knew respondent's reason for selling his ownership of the thing sold (since it was never disposed of),
property. As testified to by petitioner 41 and in the such restoration being the logical consequence of the
deposition42 of respondent, such fact was made known to fulfillment of a resolutory condition, express or implied (Article
petitioner during their negotiations as well as in the letters 1190); neither was it seeking a declaration that its obligation
sent to petitioner by Palao.43 Second, petitioner adamantly to sell was extinguished. What it sought was a judicial
refused to formally execute an instrument showing their declaration that because the suspensive condition (full and
mutual agreement to rescind the contract of sale, punctual payment) had not been fulfilled, its obligation to sell
notwithstanding that it was petitioner who plainly breached the to Maritime never arose or never became effective and,
terms of their contract when he did not pay the stipulated therefore, it (Myers) was entitled to repossess the property
price on time, leaving private respondent desperate to find object of the contract, possession being a mere incident to its
other sources of funds to payoff his loan. Lastly, petitioner did right of ownership. It is elementary that, as stated by Castan,
not substantiate by clear and convincing proof, his allegation -- 'b) Si la condicion suspensiva llega a faltar, la obligacion se
that he was ready and willing to pay respondent. We are more tiene por no existente, y el acreedor pierde todo derecho,
inclined to believe his claim of readiness to pay was an incluso el de utilizar las medidas conservativas.'(3 Castan,
afterthought intended to evade the consequence of his Derecho Civil, 7a Ed., p. 107). (Also Puig Peña, Der. Civ., T.
breach. There is no record to show the existence of such IV (1), p. 113).'"
amount, which could have been reflected, at the very least, in 2. ID.; ID.; ID.; RESCISSION. — The obligation of the
a bank account in his name, if indeed one existed; or, petitioner corporation to sell did not arise; it therefore cannot
alternatively, the proper deposit made in court which could be compelled by specific performance to comply with its
serve as a formal tender of payment. 44 Thus, we find the prestation. In short, Article 1191 of the Civil Code does not
award of moral and exemplary damages proper.1âwphi1.nêt apply; on the contrary, pursuant to Article 1597 of the Civil
WHEREFORE, the petition is DENIED. The assailed decision Code, the petitioner corporation may totally rescind, as it did
dated April 30, 1997 of the Court of Appeals in CA G.R. CV in this case, the contract. Said Article provides: "ART. 1597.
No. 39949, affirming the Regional Trial Court decision and Where the goods have not been delivered to the buyer, and
deleting the award of attorney's fees, is hereby AFFIRMED. the buyer has repudiated the contract of sale, or has
Costs against the petitioner. manifested his inability to perform his obligations, thereunder,
SO ORDERED. or has committed a breach thereof, the seller may totally
rescind the contract of sale by giving notice of his election so
G.R. No. 83851. March 3, 1993. to do to the buyer."
VISAYAN SAWMILL COMPANY, INC., and ANG TAY, 3. ID.; ID.; IN CASE AT BAR, VENDOR'S CONSENT TO
petitioners, vs. THE HONORABLE COURT OF APPEALS and DIGGING UP AND GATHERING OF SCRAP IRON NOT
CONSTRUED AS DELIVERY THEREOF; REASONS of and to deliver a determinate thing and the other to pay
THEREFOR. — Paragraph 6 of the Complaint reads: "6. That therefor a price certain in money or its equivalent." Article
on May 17, 1983 Plaintiff with the consent of defendant Ang 1475 gives the significance of this mutual undertaking of the
Tay sent his men to the stockyard of Visayan Sawmill Co., Inc. parties, thus: "The contract of sale is perfected at the moment
at Cawitan, Sta. Catalina, Negros Oriental to dig and gather there is a meeting of minds upon the thing which is the object
the scrap iron and stock the same for weighing." This of the contract and upon the price. From that moment, the
permission or consent can, by no stretch of the imagination, parties may reciprocally demand performance, subject to the
be construed as delivery of the scrap iron in the sense that, as provisions of the law governing the form of contracts." Thus,
held by the public respondent, citing Article 1497 of the Civil when the parties entered into the contract entitled "Purchase
Code, petitioners placed the private respondent in control and and Sale of Scrap Iron" on May 1, 1983, the contract reached
possession thereof. In the first place, said Article 1497 falls the stage of perfection, there being a meeting of the' minds
under the Chapter Obligations of the Vendor, which is found in upon the object which is the subject matter of the contract and
Title VI (Sales), Book IV of the Civil Code. As such, therefore, the price which is the consideration. Applying Article 1475 of
the obligation imposed therein is premised on an existing the Civil Code, from that moment, the parties may reciprocally
obligation to deliver the subject of the contract. In the instant demand performance of the obligations incumbent upon them,
case, in view of the private respondent's failure to comply with i.e., delivery by the vendor and payment by the vendee.
the positive suspensive condition earlier discussed, such an 2. ID.; ID.; DELIVERY; HOW ACCOMPLISHED; CASE AT
obligation had not yet arisen. In the second place, it was a BAR. — From the time the seller gave access to the buyer to
mere accommodation to expedite the weighing and hauling of enter his premises, manifesting no objection thereto but even
the iron in the event that the sale would materialize. The sending 18 or 20 people to start the operation, he has placed
private respondent was not thereby placed in possession of the goods in the control and possession of the vendee and
and control over the scrap iron. Thirdly, We cannot even delivery is effected. For according to Article 1497, "The thing
assume the conversion of the initial contract or promise to sell sold shall be understood as delivered when it is placed in the
into a contract of sale by the petitioner corporation's alleged control and possession of the vendee." Such action or real
implied delivery of the scrap iron because its action and delivery (traditio) is the act that transfers ownership. Under
conduct in the premises do not support this conclusion. Article 1496 of the Civil Code, "The ownership of the thing
Indeed, petitioners demanded the fulfillment of the suspensive sold is acquired by the vendee from the moment it is delivered
condition and eventually cancelled the contract. to him in any of the ways specified in Articles 1497 to 1501, or
4. ID.; CONTRACTS; DAMAGES; MORAL DAMAGES; in any other manner signifying an agreement that the
PURPOSE OF AWARD THEREOF; EXEMPLARY possession is transferred from the vendor to the vendee."
DAMAGES. — In contracts, such as in the instant case, moral 3. ID.; ID.; PROVISION IN CONTRACT REGARDING MODE
damages may be recovered if defendants acted fraudulently OF PAYMENT NOT ESSENTIAL REQUISITE THEREOF;
and in bad faith, while exemplary damages may only be WHEN PROVISION CONSIDERED A SUSPENSIVE
awarded if defendants acted in a wanton, fraudulent, reckless, CONDITION. — a provision in the contract regarding the
oppressive or malevolent manner. In the instant case, the mode of payment, like the requirement for the opening of the
refusal of the petitioners to deliver the scrap iron was founded Letter of Credit in this case, is not among the essential
on the non-fulfillment by the private respondent of a requirements of a contract of sale enumerated in Articles 1305
suspensive condition. It cannot, therefore, be said that the and 1474, the absence of any of which will prevent the
herein petitioners had acted fraudulently and in bad faith or in perfection of the contract from happening. Likewise, it must be
a wanton, reckless, oppressive or malevolent manner. What emphasized that not every provision regarding payment
this Court stated in Inhelder Corp. vs. Court of Appeals needs should automatically be classified as a suspensive condition.
to be stressed anew: "At this juncture, it may not be amiss to To do so would change the nature of most contracts of sale
remind Trial Courts to guard against the award of exhorbitant into contracts to sell. For a provision in the contract regarding
(sic) damages that are way out of proportion to the the payment of the price to be considered a suspensive
environmental circumstances of a case and which, time and condition, the parties must have made this clear in certain and
again, this Court has reduced or eliminated. Judicial discretion unambiguous terms, such as for instance, by reserving or
granted to the Courts in the assessment of damages must withholding title to the goods until full payment by the buyer.
always be exercised with balanced restraint and measured This was a pivotal circumstance in the Luzon Brokerage case
objectivity." For, indeed, moral damages are emphatically not where the contract in question was replete with very explicit
intended to enrich a complainant at the expense of the provisions such as the following: "Title to the properties
defendant. They are awarded only to enable the injured party subject of this contract remains with the Vendor and shall
to obtain means, diversion or amusements that will serve to pass to, and be transferred in the name of the Vendee only
obviate the moral suffering he has undergone, by reason of upon complete payment of the full price . . .;" 10 the Vendor
the defendant's culpable action. Its award is aimed at the (Myers) will execute and deliver to the Vendee a definite and
restoration, within the limits of the possible, of the spiritual absolute Deed of Sale upon full payment of the Vendee . . .;
status quo ante, and it must be proportional to the suffering and "should the Vendee fail to pay any of the monthly
inflicted. installments, when due, or otherwise fail to comply with any of
ROMERO, J., dissenting: the terms and conditions herein stipulated, then this Deed of
1. CIVIL LAW; CONTRACT OF SALE; DEFINED; WHEN Conditional Sale shall automatically and without any further
PERFECTED; CASE AT BAR. — Article 1458 of the Civil formality, become null and void." It is apparent from a careful
Code has this definition: "By a contract of sale, one of the reading of Luzon Brokerage, as well as the cases which
contracting parties obligates himself to transfer the ownership preceded it and the subsequent ones applying its doctrines,
that the mere insertion of the price and the mode of payment Second, the Court found in Sycip that time was of the
among the terms and conditions of the agreement will not essence for the seller who was anxious to sell to other buyers
necessarily make it a contract to sell. The phrase in the should the offeror fail to open the Letter of Credit within the
contract "on the following terms and conditions" is standard stipulated time. In contrast, there are no indicia in this case
form which is not to be construed as imposing a condition, that can lead one to conclude that time was of the essence for
whether suspensive or resolutory, in the sense of the petitioner as would make the eleven-day delay a fundamental
happening of a future and uncertain event upon which an breach of the contract.
obligation is made to depend. There must be a manifest 6. ID.; OBLIGATIONS AND CONTRACTS; RESCISSION
understanding that the agreement is in what may be referred UNDER ARTICLE 1191 OF THE CIVIL CODE; WHEN
to as "suspended animation" pending compliance with PROPER; DELAY IN PAYMENT FOR TWENTY DAYS NOT
provisions regarding payment. The reservation of title to the CONSIDERED A SUBSTANTIAL BREACH OF CONTRACT;
object of the contract in the seller is one such manifestation. CASE AT BAR. — The right to rescind pursuant to Article
Hence, it has been decided in the case of Dignos v. Court of 1191 is not absolute. Rescission will not be permitted for slight
Appeals that, absent a proviso in the contract that the title to or casual breach of the contract. Here, petitioners claim that
the property is reserved in the vendor until full payment of the the breach is so substantial as to justify rescission . . . I am
purchase price or a stipulation giving the vendor the right to not convinced that the circumstances may be characterized
unilaterally rescind the contract the moment the vendee fails as so substantial and fundamental as to defeat the object of
to pay within the fixed period, the transaction is an absolute the parties in making the agreement. None of the alleged
contract of sale and not a contract to sell. defects in the Letter of Credit would serve to defeat the object
4. ID.; ID.; CONTRACT OF SALE DISTINGUISHED FROM of the parties. It is to be stressed that the purpose of the
CONTRACT TO SELL; EFFECT OF NON-PAYMENT OF opening of a Letter of Credit is to effect payment. The above-
PURCHASE PRICE; EFFECT OF DELIVERY ON mentioned factors could not have prevented such payment. It
OWNERSHIP OF OBJECT OF CONTRACT. — In a contract is also significant to note that petitioners sent a telegram to
of sale, the non-payment of the price is a resolutory condition private respondents on May 23, 1983 cancelling the contract.
which extinguishes the transaction that, for a time, existed This was before they had even received on May 26, 1983 the
and discharges the obligations created thereunder. On the notice from the bank about the opening of the Letter of Credit.
other hand, "the parties may stipulate that ownership in the How could they have made a judgment on the materiality of
thing shall not pass to the purchaser until he has fully paid the the provisions of the Letter of Credit for purposes of
price." In such a contract to sell, the full payment of the price rescinding the contract even before setting eyes on said
is a positive suspensive condition, such that in the event of document? To be sure, in the contract, the private
non-payment, the obligation of the seller to deliver and respondents were supposed to open the Letter of Credit on
transfer ownership never arises. Stated differently, in a May 15, 1983 but, it was not until May 26, 1983 or eleven (11)
contract to sell, ownership is not transferred upon delivery of days later that they did so. Is the eleven-day delay a
property but upon full payment of the purchase price. substantial breach of the contract as could justify the
Consequently, in a contract of sale, after delivery of the object rescission of the contract? In Song Fo and Co. v. Hawaiian-
of the contract has been made, the seller loses ownership and Philippine Co., it was held that a delay in payment for twenty
cannot recover the same unless the contract is rescinded. But (20) days was not a violation of an essential condition of the
in the contract to sell, the seller retains ownership and the contract which would warrant rescission for non-performance.
buyer's failure to pay cannot even be considered a breach, In the instant case, the contract is bereft of any suggestion
whether casual or substantial, but an event that prevented the that time was of the essence. On the contrary, it is noted that
seller's duty to transfer title to the object of the contract. petitioners allowed private respondents' men to dig and
5. ID.; ID.; CASE OF SYCIP V. NATIONAL COCONUT remove the scrap iron located in petitioners' premises
CORPORATION, ET AL., G.R. NO. L-6618, APRIL 28, 1956, between May 17, 1983 until May 30, 1983 or beyond the May
DISTINGUISHED FROM CASE AT BAR. — Worthy of 15, 1983 deadline for the opening of the Letter of Credit.
mention before concluding is Sycip v. National Coconut Hence, in the absence of any indication that the time was of
Corporation, et al. since, like this case, it involves a failure to the essence, the eleven-day delay must be deemed a casual
open on time the Letter of Credit required by the seller. In breach which cannot justify a rescission.
Sycip, after the buyer offered to buy 2,000 tons of copra, the DECISION
seller sent a telegram dated December 19, 1946 to the buyer DAVIDE, JR., J p:
accepting the offer but on condition that the latter opens a By this petition for review under Rule 45 of the Rules of Court,
Letter of Credit within 48 hours. It was not until December 26, petitioners urge this Court to set aside the decision of public
1946, however, that the Letter of Credit was opened. The respondent Court of Appeals in C.A.-G.R. CV No. 08807, 1
Court, speaking through Justice Bengzon, held that because promulgated on 16 March 1988, which affirmed with
of the delay in the opening of the Letter of Credit; the seller modification, in respect to the moral damages, the decision of
was not obliged to deliver the goods. Two factors distinguish the Regional Trial Court (RTC) of Iloilo in Civil Case No.
Sycip from the case at bar. First, while there has already been 15128, an action for specific performance and damages, filed
a perfected contract of sale in the instant case, the parties in by the herein private respondent against the petitioners. The
Sycip were still undergoing the negotiation process. The dispositive portion of the trial court's decision reads as
seller's qualified acceptance in Sycip served as a counter follows:
offer which prevented the contract from being perfected. Only "IN VIEW OF THE ABOVE FINDINGS, judgment is hereby
an absolute and unqualified acceptance of a definite offer rendered in favor of plaintiff and against the defendants
manifests the consent necessary to perfect a contract. ordering the latter to pay jointly and severally plaintiff, to wit:
1) The sum of Thirty-Four Thousand Five Hundred Eighty In reply to those telegrams, defendants-appellants' lawyer, on
Three and 16/100 (P34,583.16), as actual damages; July 20, 1983 informed plaintiff-appellee's lawyer that
2) The sum of One Hundred Thousand (P100,000.00) Pesos, defendant-appellant corporation is unwilling to continue with
as moral damages; the sale due to plaintiff-appellee's failure to comply with
3) The sum of Ten Thousand (P10,000.00) Pesos, as essential pre-conditions of the contract.
exemplary damages; On July 29, 1983, plaintiff-appellee filed the complaint below
4) The sum of TWENTY Five Thousand (P25,000.00) Pesos, with a petition for preliminary attachment. The writ of
as attorney's fees; and attachment was returned unserved because the defendant-
5) The sum of Five Thousand (P5,000.00) Pesos as actual appellant corporation was no longer in operation and also
litis expenses." 2 because the scrap iron as well as other pieces of machinery
The public respondent reduced the amount of moral damages can no longer be found on the premises of the corporation." 3
to P25,000.00. In his complaint, private respondent prayed for judgment
The antecedent facts, summarized by the public respondent, ordering the petitioner corporation to comply with the contract
are as follows: by delivering to him the scrap iron subject thereof; he further
"On May 1, 1983, herein plaintiff-appellee and defendants- sought an award of actual, moral and exemplary damages,
appellants entered into a sale involving scrap iron located at attorney's fees and the costs of the suit. 4
the stockyard of defendant-appellant corporation at Cawitan, In their Answer with Counterclaim, 5 petitioners insisted that
Sta. Catalina, Negros Oriental, subject to the condition that the cancellation of the contract was justified because of
plaintiff-appellee will open a letter of credit in the amount of private respondent's non-compliance with essential pre-
P250,000.00 in favor of defendant-appellant corporation on or conditions, among which is the opening of an irrevocable and
before May 15, 1983. This is evidenced by a contract entitled unconditional letter of credit not later than 15 May 1983.
`Purchase and Sale of Scrap Iron' duly signed by both parties. During the pre-trial of the case on 30 April 1984, the parties
On May 17, 1983, plaintiff-appellee through his man (sic), defined the issues to be resolved; these issues were
started to dig and gather and (sic) scrap iron at the defendant- subsequently embodied in the pre-trial order, to wit:
appellant's (sic) premises, proceeding with such endeavor "1. Was the contract entitled Purchase and Sale of Scrap Iron,
until May 30 when defendants-appellants allegedly directed dated May 1, 1983 executed by the parties cancelled and
plaintiff-appellee's men to desist from pursuing the work in terminated before the Complaint was filed by anyone of the
view of an alleged case filed against plaintiff-appellee by a parties; if so, what are the grounds and reasons relied upon
certain Alberto Pursuelo. This, however, is denied by by the cancelling parties; and were the reasons or grounds for
defendants-appellants who allege that on May 23, 1983, they cancelling valid and justified?
sent a telegram to plaintiff-appellee cancelling the contract of 2. Are the parties entitled to damages they respectively claim
sale because of failure of the latter to comply with the under the pleadings?" 6
conditions thereof. On 29 November 1985, the trial court rendered its judgment,
On May 24, 1983, plaintiff-appellee informed defendants- the dispositive portion of which was quoted earlier.
appellants by telegram that the letter of credit was opened Petitioners appealed from said decision to the Court of
May 12, 1983 at the Bank of the Philippine Islands main office Appeals which docketed the same as C.A.-G.R. CV No.
in Ayala, but then (sic) the transmittal was delayed. 08807. In their Brief, petitioners, by way of assigned errors,
On May 26, 1983, defendants-appellants received a letter alleged that the trial court erred:
advice from the Dumaguete City Branch of the Bank of the "1. In finding that there was delivery of the scrap iron subject
Philippine Islands dated May 26, 1983, the content of which is of the sale;
quited (sic) as follows: 2. In not finding that plaintiff had not complied with the
'Please be advised that we have received today cable advise conditions in the contract of sale;
from our Head Office which reads as follows: 3. In finding that defendants-appellants were not justified in
'Open today our irrevocable Domestic Letter of Credit No. cancelling the sale;
01456-d fot (sic) P250,000.00 favor ANG TAY c/o Visayan 4. In awarding damages to the plaintiff as against the
Sawmill Co., Inc. Dumaguete City, Negros Oriental Account of defendants-appellants;
ARMACO-MARSTEEL ALLOY CORPORATION 2nd Floor 5. In not awarding damages to defendants-appellants." 7
Alpap 1 Bldg., 140 Alfaro stp (sic) Salcedo Village, Makati, Public respondent disposed of these assigned errors in this
Metro Manila Shipments of about 500 MT of assorted steel wise:
scrap marine/heavy equipment expiring on July 24, 1983 "On the first error assigned, defendants-appellants argue that
without recourse at sight draft drawn on Armaco Marsteel there was no delivery because the purchase document states
Alloy Corporation accompanied by the following documents: that the seller agreed to sell and the buyer agreed to buy 'an
Certificate of Acceptance by Armaco-Marsteel Alloy undetermined quantity of scrap iron and junk which the seller
Corporation shipment from Dumaguete City to buyer's will identify and designate.' Thus, it is contended, since no
warehouse partial shipment allowed/transhipment (sic) not identification and designation was made, there could be no
allowed'. delivery. In addition, defendants-appellants maintain that their
For your information'. obligation to deliver cannot be completed until they furnish the
On July 19, 1983, plaintiff-appellee sent a series of telegrams cargo trucks to haul the weighed materials to the wharf.
stating that the case filed against him by Pursuelo had been The arguments are untenable. Article 1497 of the Civil Code
dismissed and demanding that defendants-appellants comply states:
with the deed of sale, otherwise a case will be filed against 'The thing sold shall be understood as delivered when it is
them. placed in the control and possession of the vendee.'
In the case at bar, control and possession over the subject There is no need to discuss the fourth and fifth assigned
matter of the contract was given to plaintiff-appellee, the errors since these are merely corollary to the first three
buyer, when the defendants-appellants as the sellers allowed assigned errors." 8
the buyer and his men to enter the corporation's premises and Their motion to reconsider the said decision having been
to dig-up the scrap iron. The pieces of scrap iron then (sic) denied by public respondent in its Resolution of 4 May 1988,
placed at the disposal of the buyer. Delivery was therefore 9 petitioners filed this petition reiterating the abovementioned
complete. The identification and designation by the seller assignment of errors.
does not complete delivery. There is merit in the instant petition.
On the second and third assignments of error, defendants- Both the trial court and the public respondent erred in the
appellants argue that under Articles 1593 and 1597 of the appreciation of the nature of the transaction between the
Civil Code, automatic rescission may take place by a mere petitioner corporation and the private respondent. To this
notice to the buyer if the latter committed a breach of the Court's mind, what obtains in the case at bar is a mere
contract of sale. contract to sell or promise to sell, and not a contract of sale.
Even if one were to grant that there was a breach of the The trial court assumed that the transaction is a contract of
contract by the buyer, automatic rescission cannot take place sale and, influenced by its view that there was an "implied
because, as already (sic) stated, delivery had already been delivery" of the object of the agreement, concluded that Article
made. And, in cases where there has already been delivery, 1593 of the Civil Code was inapplicable; citing Guevarra vs.
the intervention of the court is necessary to annul the Pascual 10 and Escueta vs. Pando, 11 it ruled that rescission
contract. under Article 1191 of the Civil Code could only be done
As the lower court aptly stated: judicially. The trial court further classified the breach
'Respecting these allegations of the contending parties, while committed by the private respondent as slight or casual,
it is true that Article 1593 of the New Civil Code provides that foreclosing, thereby, petitioners' right to rescind the
with respect to movable property, the rescission of the sale agreement.
shall of right take place in the interest of the vendor, if the Article 1593 of the Civil Code provides:
vendee fails to tender the price at the time or period fixed or "ARTICLE 1593. With respect to movable property, the
agreed, however, automatic rescission is not allowed if the rescission of the sale shall of right take place in the interest of
object sold has been delivered to the buyer (Guevarra vs. the vendor, if the vendee, upon the expiration of the period
Pascual, 13 Phil. 311; Escueta vs. Pando, 76 Phil 256), the fixed for the delivery of the thing, should not have appeared to
action being one to rescind judicially and where (sic) Article receive it, or, having appeared, he should not have tendered
1191, supra, thereby applies. There being already an implied the price at the same time, unless a longer period has been
delivery of the items, subject matter of the contract between stipulated for its payment."
the parties in this case, the defendant having surrendered the Article 1191 provides:
premises where the scraps (sic) were found for plaintiff's men "ARTICLE 1191. The power to rescind obligations is implied in
to dig and gather, as in fact they had dug and gathered, this reciprocal ones, in case one of the obligors should not comply
Court finds the mere notice of resolution by the defendants with what is incumbent upon him.
untenable and not conclusive on the rights of the plaintiff The injured party may choose between the fulfillment and the
(Ocejo Perez vs. Int. Bank, 37 Phi. 631). Likewise, as early as rescission of the obligation, with the payment of damages in
in the case of Song Fo vs. Hawaiian Philippine Company, it either case. He may also seek rescission, even after he has
has been ruled that rescission cannot be sanctioned for a chosen fulfillment, if the latter should become impossible.
slight or casual breach (47 Phil. 821).' The court shall decree the rescission claimed, unless there be
In the case of Angeles vs. Calasanz (135 (1935) SCRA 323), just cause authorizing the fixing of a period."
the Supreme Court ruled: xxx xxx xxx
'Article 1191 is explicit. In reciprocal obligations, either party Sustaining the trial court on the issue of delivery, public
has the right to rescind the contract upon failure of the other respondent cites Article 1497 of the Civil Code which
to perform the obligation assumed thereunder. provides:
Of course, it must be understood that the right of a party in "ARTICLE 1497. The thing sold shall be understood as
treating a contract as cancelled or resolved on account of delivered, when it is placed in the control and possession of
infractions by the other contracting party must be made the vendee."
known to the other and is always provisional, being ever In the agreement in question, entitled PURCHASE AND SALE
subject to scrutiny and review by the proper court.' OF SCRAP IRON, 12 the seller bound and promised itself to
Thus, rescission in cases falling under Article 1191 of the Civil sell the scrap iron upon the fulfillment by the private
Code is always subject to review by the courts and cannot be respondent of his obligation to make or indorse an irrevocable
considered final. and unconditional letter of credit in payment of the purchase
In the case at bar, the trial court ruled that rescission is price. Its principal stipulation reads, to wit:
improper because the breach was very slight and the delay in xxx xxx xxx
opening the letter of credit was only 11 days. "Witnesseth:
'Where time is not of the essence of the agreement, a slight That the SELLER agrees to sell, and the BUYER agrees to
delay by one party in the performance of his obligation is not a buy, an undetermined quantity of scrap iron and junk which
sufficient ground for rescission of the agreement. Equity and the SELLER will identify and designate now at Cawitan, Sta.
justice mandates (sic) that the vendor be given additional (sic) Catalina, Negros Oriental, at the price of FIFTY CENTAVOS
period to complete payment of the purchase price.' (Taguda (P0.50) per kilo on the following terms and conditions:
vs. Vda. de Leon, 132 SCRA (1984), 722).' 1. Weighing shall be done in the premises of the SELLER at
Cawitan, Sta. Catalina, Neg. Oriental. reference to the opening on that date of a letter of credit in
2. To cover payment of the purchase price, BUYER will open, favor of petitioner Ang Tay c/o Visayan Sawmill Co. Inc.,
make or indorse an irrevocable and unconditional letter of drawn without recourse on ARMACO-MARSTEEL ALLOY
credit not later than May 15, 1983 at the Consolidated Bank CORPORATION and set to expire on 24 July 1983, which is
and Trust Company, Dumaguete City, Branch, in favor of the indisputably not in accordance with the stipulation in the
SELLER in the sum of TWO HUNDRED AND FIFTY contract signed by the parties on at least three (3) counts: (1)
THOUSAND PESOS (P250,000.00), Philippine Currency. it was not opened, made or indorsed by the private
3. The SELLER will furnish the BUYER free of charge at least respondent, but by a corporation which is not a party to the
three (3) cargo trucks with drivers, to haul the weighed contract; (2) it was not opened with the bank agreed upon;
materials from Cawitan to the TSMC wharf at Sta. Catalina for and (3) it is not irrevocable and unconditional, for it is without
loading on BUYER's barge. All expenses for labor, loading recourse, it is set to expire on a specific date and it stipulates
and unloading shall be for the account of the BUYER. certain conditions with respect to shipment. In all probability,
4. SELLER shall be entitled to a deduction of three percent private respondent may have sold the subject scrap iron to
(3%) per ton as rust allowance." (Emphasis supplied). ARMACO-MARSTEEL ALLOY CORPORATION, or otherwise
The petitioner corporation's obligation to sell is unequivocally assigned to it the contract with the petitioners. Private
subject to a positive suspensive condition, i.e., the private respondent's complaint fails to disclose the sudden entry into
respondent's opening, making or indorsing of an irrevocable the picture of this corporation.
and unconditional letter of credit. The former agreed to deliver Consequently, the obligation of the petitioner corporation to
the scrap iron only upon payment of the purchase price by sell did not arise; it therefore cannot be compelled by specific
means of an irrevocable and unconditional letter of credit. performance to comply with its prestation. In short, Article
Otherwise stated, the contract is not one of sale where the 1191 of the Civil Code does not apply; on the contrary,
buyer acquired ownership over the property subject to the pursuant to Article 1597 of the Civil Code, the petitioner
resolutory condition that the purchase price would be paid corporation may totally rescind, as it did in this case, the
after delivery. Thus, there was to be no actual sale until the contract. Said Article provides:
opening, making or indorsing of the irrevocable and "ARTICLE 1597. Where the goods have not been delivered to
unconditional letter of credit. Since what obtains in the case at the buyer, and the buyer has repudiated the contract of sale,
bar is a mere promise to sell, the failure of the private or has manifested his inability to perform his obligations,
respondent to comply with the positive suspensive condition thereunder, or has committed a breach thereof, the seller may
cannot even be considered a breach — casual or serious — totally rescind the contract of sale by giving notice of his
but simply an event that prevented the obligation of petitioner election so to do to the buyer."
corporation to convey title from acquiring binding force. In The trial court ruled, however, and the public respondent was
Luzon Brokerage Co., Inc. vs. Maritime Building Co., Inc., 13 in agreement, that there had been an implied delivery in this
this Court stated: case of the subject scrap iron because on 17 May 1983,
" . . . The upshot of all these stipulations is that in seeking the private respondent's men started digging up and gathering
ouster of Maritime for failure to pay the price as agreed upon, scrap iron within the petitioner's premises. The entry of these
Myers was not rescinding (or more properly, resolving) the men was upon the private respondent's request. Paragraph 6
contract, but precisely enforcing it according to its express of the Complaint reads:
terms. In its suit Myers was not seeking restitution to it of the "6. That on May 17, 1983 Plaintiff with the consent of
ownership of the thing sold (since it was never disposed of), defendant Ang Tay sent his men to the stockyard of Visayan
such restoration being the logical consequence of the Sawmill Co., Inc. at Cawitan, Sta. Catalina, Negros Oriental to
fulfillment of a resolutory condition, express or implied (article dig and gather the scrap iron and stock the same for
1190); neither was it seeking a declaration that its obligation weighing." 14
to sell was extinguished. What it sought was a judicial This permission or consent can, by no stretch of the
declaration that because the suspensive condition (full and imagination, be construed as delivery of the scrap iron in the
punctual payment) had not been fulfilled, its obligation to sell sense that, as held by the public respondent, citing Article
to Maritime never arose or never became effective and, 1497 of the Civil Code, petitioners placed the private
therefore, it (Myers) was entitled to repossess the property respondent in control and possession thereof. In the first
object of the contract, possession being a mere incident to its place, said Article 1497 falls under the Chapter 15 Obligations
right of ownership. It is elementary that, as stated by Castan, of the Vendor, which is found in Title VI (Sales), Book IV of the
— Civil Code. As such, therefore, the obligation imposed therein
'b) Si la condicion suspensiva llega a faltar, la obligacion se is premised on an existing obligation to deliver the subject of
tiene por no existente, y el acreedor pierde todo derecho, the contract. In the instant case, in view of the private
incluso el de utilizar las medidas conservativas.' (3 Cast n, respondent's failure to comply with the positive suspensive
Derecho Civil, 7a Ed., p. 107). (Also Puig Peña, Der. Civ., T. condition earlier discussed, such an obligation had not yet
IV (1), p. 113)'." arisen. In the second place, it was a mere accommodation to
In the instant case, not only did the private respondent fail to expedite the weighing and hauling of the iron in the event that
open, make or indorse an irrevocable and unconditional letter the sale would materialize. The private respondent was not
of credit on or before 15 May 1983 despite his earlier thereby placed in possession of and control over the scrap
representation in his 24 May 1983 telegram that he had iron. Thirdly, We cannot even assume the conversion of the
opened one on 12 May 1983, the letter of advice received by initial contract or promise to sell into a contract of sale by the
the petitioner corporation on 26 May 1983 from the Bank of petitioner corporation's alleged implied delivery of the scrap
the Philippine Islands Dumaguete City branch explicitly makes iron because its action and conduct in the premises do not
support this conclusion. Indeed, petitioners demanded the That the SELLER agrees to sell, and the BUYER agrees to
fulfillment of the suspensive condition and eventually buy, an undetermined quantity of scrap iron and junk which
cancelled the contract. the SELLER will identify and designate now at Cawitan, Sta.
All told, Civil Case No. 15128 filed before the trial court was Catalina, Negros Oriental, at the price of FIFTY CENTAVOS
nothing more than the private respondent's preemptive action (P.50) per kilo on the following terms and conditions:
to beat the petitioners to the draw. 1. Weighing shall be done in the premises of the SELLER at
One last point. This Court notes the palpably excessive and Cawitan, Sta. Catalina, Negros Oriental.
unconscionable moral and exemplary damages awarded by 2. To cover payment of the purchase price BUYER will open,
the trial court to the private respondent despite a clear make or indorse an irrevocable and unconditional letter of
absence of any legal and factual basis therefor. In contracts, credit not later than May 15, 1983 at the Consolidated Bank
such as in the instant case, moral damages may be recovered and Trust Company, Dumaguete City Branch, in favor of the
if defendants acted fraudulently and in bad faith, 16 while SELLER in the sum of TWO HUNDRED AND FIFTY
exemplary damages may only be awarded if defendants acted THOUSAND PESOS (P250,000.00), Philippine currency.
in a wanton, fraudulent, reckless, oppressive or malevolent 3. The SELLER will furnish the BUYER free of charge at least
manner. 17 In the instant case, the refusal of the petitioners to three (3) cargo trucks with drivers, to haul the weighed
deliver the scrap iron was founded on the non-fulfillment by materials from Cawitan to the TSMC wharf at Sta. Catalina for
the private respondent of a suspensive condition. It cannot, loading on BUYER'S barge. All expenses for labor, loading
therefore, be said that the herein petitioners had acted and unloading shall be for the account of the BUYER.
fraudulently and in bad faith or in a wanton, reckless, 4. SELLER shall be entitled to a deduction of three percent
oppressive or malevolent manner. What this Court stated in (3%) per ton as rust allowance.
Inhelder Corp. vs. Court of Appeals 18 needs to be stressed xxx xxx xxx
anew: On May 17, 1983, the workers of private respondents were
"At this juncture, it may not be amiss to remind Trial Courts to allowed inside petitioner company's premises in order to
guard against the award of exhorbitant (sic) damages that are gather the scrap iron. However, on May 23, 1983, petitioner
way out of proportion to the environmental circumstances of a company sent a telegram which stated:
case and which, time and again, this Court has reduced or "RAMON HIBIONADA
eliminated. Judicial discretion granted to the Courts in the RJH TRADING
assessment of damages must always be exercised with 286 QUEZON STREET
balanced restraint and measured objectivity." ILOILO CITY
For, indeed, moral damages are emphatically not intended to DUE YOUR FAILURE TO COMPLY WITH CONDITIONS
enrich a complainant at the expense of the defendant. They BEFORE DEADLINE OUR CONTRACT FOR PURCHASE
are awarded only to enable the injured party to obtain means, SCRAP IRON CANCELLED
diversion or amusements that will serve to obviate the moral VISAYAN SAWMILL CO., INC."
suffering he has undergone, by reason of the defendant's Hibionada wired back on May 24, 1983 the following:
culpable action. Its award is aimed at the restoration, within "ANG TAY VISAYAN SAWMILL
the limits of the possible, of the spiritual status quo ante, and DUMAGUETE CITY
it must be proportional to the suffering inflicted. 19 LETTER OF CREDIT AMOUNTING P250,000.00 OPENED
WHEREFORE, the instant petition is GRANTED. The MAY 12, 1983 BANK OF PI MAIN OFFICE AYALA AVENUE
decision of public respondent Court of Appeals in C.A.-G.R. MAKATI METRO MANILA BUT TRANSMITTAL IS DELAYED
CV No. 08807 is REVERSED and Civil Case No. 15128 of the PLEASE CONSIDER REASON WILL PERSONALLY
Regional Trial Court of Iloilo is ordered DISMISSED. FOLLOW-UP IN MANILA THANKS REGARDS.
Costs against the private respondent. RAMON HIBIONADA"
SO ORDERED. On May 26, 1983, petitioner company received the following
Narvasa, C .J ., Cruz, Feliciano, Padilla, Bidin and Bellosillo, advice from the Dumaguete City Branch of The Bank of
JJ ., concur. Philippine Islands: cdll
Gutierrez, Jr., J ., On terminal leave. "Opened today our Irrevocable Domestic Letter of Credit 2-
Melo and Quiason, JJ ., No part. 01456-4 for P250,000.00 in favor ANG TAY c/o Visayan
Separate Opinions Sawmill Co., Inc. Dumaguete City Negros Oriental Account of
ROMERO, J., dissenting: ARMACO-MARSTEEL ALLOW (sic) CORPORATION 2nd
I vote to dismiss the petition. Floor Alpap 1 Bldg., 140 Alfaro st. Salcedo Village Makati
Petitioner corporation, Visayan Sawmill Co., Inc., entered into Metro Manila Shipments of about 500 MT of assorted steel
a contract on May 1, 1983 with private respondent RJH scrap marine/heavy equipment expiring on July 23, 1983
Trading Co. represented by private respondent Ramon J. without recourse at slight draft drawn on Armaco-Marsteel
Hibionada. The contract, entitled "PURCHASE AND SALE OF Alloy Corporation accompanied by the following documents:
SCRAP IRON," stated: Certificate of acceptance by Armaco-Marsteel Allow (sic)
This contract for the Purchase and Sale of Scrap Iron, made Corporation shipment from Dumaguete City to buyer's
and executed at Dumaguete City, Phil., this 1st day of May, warehouse partial shipment allowed/transhipment not
1983 by and between: allowed."
VISAYAN SAWMILL CO., INC., . . . hereinafter called the Subsequently, petitioners' counsel sent another telegram to
SELLER, and private respondents stating that:
RAMON J. HIBIONADA, . . . hereinafter called the BUYER, "VISAYAN SAWMILL COMPANY UNWILLING TO CONTINUE
witnesseth: SALE OF SCRAP IRON TO HIBIONADA DUE TO NON
COMPLIANCE WITH ESSENTIAL PRE CONDITIONS" immaterial to the transfer of the right of ownership. In a
Consequently, private respondents filed a complaint for contract of sale, the non-payment of the price is a resolutory
specific performance and damages with the Regional Trial condition which extinguishes the transaction that, for a time,
Court (RTC) of Iloilo (Branch XXXV) which decided in favor of existed and discharges the obligations created thereunder. 4
private respondents. The RTC decision having been affirmed On the other hand, "the parties may stipulate that ownership
by the Court of Appeals, the present petition was filed. in the thing shall not pass to the purchaser until he has fully
Finding the petition meritorious, the ponencia reversed the paid the price." 5 In such a contract to sell, the full payment of
decision of the Court of Appeals. Based on its appreciation of the price is a positive suspensive condition, such that in the
the contract in question, it has arrived at the conclusion that event of non-payment, the obligation of the seller to deliver
herein contract is not a contract of sale but a contract to sell and transfer ownership never arises. Stated differently, in a
which is subject to a positive suspensive condition, i.e., the contract to sell, ownership is not transferred upon delivery of
opening of a letter of credit by private respondents. Since the property but upon full payment of the purchase price. 6
condition was not fulfilled, the obligation of petitioners to Consequently, in a contract of sale, after delivery of the object
convey title did not arise. The lengthy decision of Luzon of the contract has been made, the seller loses ownership and
Brokerage Co., Inc. v. Maritime Co. Inc. 1 penned by Justice cannot recover the same unless the contract is rescinded. But
J.B.L. Reyes, was cited as authority on the assumption that in the contract to sell, the seller retains ownership and the
subject contract is indeed a contract to sell but which will be buyer's failure to pay cannot even be considered a breach,
shown herein as not quite accurate. whether casual or substantial, but an event that prevented the
Evidently, the distinction between a contract to sell and a seller's duty to transfer title to the object of the contract.
contract of sale is crucial in this case. Article 1458 of the Civil At the outset, it must be borne in mind that a provision in the
Code has this definition: "By a contract of sale, one of the contract regarding the mode of payment, like the requirement
contracting parties obligates himself to transfer the ownership for the opening of the Letter of Credit in this case, is not
of and to deliver a determinate thing and the other to pay among the essential requirements of a contract of sale
therefor a price certain in money or its equivalent." enumerated in Articles 1305 7 and 1474, 8 the absence of any
Article 1475 gives the significance of this mutual undertaking of which will prevent the perfection of the contract from
of the parties, thus: "The contract of sale is perfected at the happening. Likewise, it must be emphasized that not every
moment there is a meeting of minds upon the thing which is provision regarding payment should automatically be
the object of the contract and upon the price. From that classified as a suspensive condition. To do so would change
moment, the parties may reciprocally demand performance, the nature of most contracts of sale into contracts to sell. For
subject to the provisions of the law governing the form of a provision in the contract regarding the payment of the price
contracts." to be considered a suspensive condition, the parties must
Thus, when the parties entered into the contract entitled have made this clear in certain and unambiguous terms, such
"Purchase and Sale of Scrap Iron" on May 1, 1983, the as for instance, by reserving or withholding title to the goods
contract reached the stage of perfection, there being a until full payment by the buyer. 9 This was a pivotal
meeting of the' minds upon the object which is the subject circumstance in the Luzon Brokerage case where the contract
matter of the contract and the price which is the consideration. in question was replete with very explicit provisions such as
Applying Article 1475 of the Civil Code, from that moment, the the following: "Title to the properties subject of this contract
parties may reciprocally demand performance of the remains with the Vendor and shall pass to, and be transferred
obligations incumbent upon them, i.e., delivery by the vendor in the name of the Vendee only upon complete payment of the
and payment by the vendee. full price . . .;" 10 the Vendor (Myers) will execute and deliver
Petitioner, in its petition, admits that "[b]efore the opening of to the Vendee a definite and absolute Deed of Sale upon full
the letter of credit, buyer Ramon Hibionada went to Mr. Ang payment of the Vendee . . .; 11 and "should the Vendee fail to
Tay and informed him that the letter of credit was forthcoming pay any of the monthly installments, when due, or otherwise
and if it was possible for him (buyer) to start cutting and fail to comply with any of the terms and conditions herein
digging the scrap iron before the letter of credit arrives and stipulated, then this Deed of Conditional Sale shall
the former (seller) manifested no objection, and he automatically and without any further formality, become null
immediately sent 18 or 20 people to start the operation." 2 and void." 12
From the time the seller gave access to the buyer to enter his It is apparent from a careful reading of Luzon Brokerage, as
premises, manifesting no objection thereto but even sending well as the cases which preceded it 13 and the subsequent
18 or 20 people to start the operation, he has placed the ones applying its doctrines, 14 that the mere insertion of the
goods in the control and possession of the vendee and price and the mode of payment among the terms and
delivery is effected. For according to Article 1497, "The thing conditions of the agreement will not necessarily make it a
sold shall be understood as delivered when it is placed in the contract to sell. The phrase in the contract "on the following
control and possession of the vendee." 3 terms and conditions" is standard form which is not to be
Such action or real delivery (traditio) is the act that transfers construed as imposing a condition, whether suspensive or
ownership. Under Article 1496 of the Civil Code, "The resolutory, in the sense of the happening of a future and
ownership of the thing sold is acquired by the vendee from the uncertain event upon which an obligation is made to depend.
moment it is delivered to him in any of the ways specified in There must be a manifest understanding that the agreement
Articles 1497 to 1501, or in any other manner signifying an is in what may be referred to as "suspended animation"
agreement that the possession is transferred from the vendor pending compliance with provisions regarding payment. The
to the vendee." reservation of title to the object of the contract in the seller is
That payment of the price in any form was not yet effected is one such manifestation. Hence, it has been decided in the
case of Dignos v. Court of Appeals 15 that, absent a proviso substantial as to justify rescission, not only because the Letter
in the contract that the title to the property is reserved in the of Credit was not opened on May 15, 1983 as stipulated in the
vendor until full payment of the purchase price or a stipulation contract but also because of the following factors: (1) the
giving the vendor the right to unilaterally rescind the contract Letter of Credit, although opened in favor of petitioners was
the moment the vendee fails to pay within the fixed period, the made against the account of a certain Marsteel Alloy
transaction is an absolute contract of sale and not a contract Corporation, instead of private respondent's account; (2) the
to sell. 16 Letter of Credit referred to "assorted steel scrap" instead of
In the instant case, nowhere in the contract did it state that the "scrap iron and junk" as provided in the contract; (3) the Letter
petitioners reserve title to the goods until private respondents of Credit placed the quantity of the goods at "500 MT" while
have opened a letter of credit. Nor is there any provision the contract mentioned "an undetermined quantity of scrap
declaring the contract as without effect until after the iron and junk"; (4) no amount from the Letter of Credit will be
fulfillment of the condition regarding the opening of the letter released unless accompanied by a Certificate of Acceptance;
of credit. and (5) the Letter of Credit had an expiry date.
Examining the contemporaneous and subsequent conduct of I am not convinced that the above circumstances may be
the parties, which may be relevant in the determination of the characterized as so substantial and fundamental as to defeat
nature and meaning of the contract, 17 it is significant that in the object of the parties in making the agreement. 21 None of
the telegram sent by petitioners to Hibionada on May 23, the alleged defects in the Letter of Credit would serve to
1983, it stated that "DUE [TO] YOUR FAILURE TO COMPLY defeat the object of the parties. It is to be stressed that the
WITH CONDITIONS BEFORE DEADLINE OUR CONTRACT purpose of the opening of a Letter of Credit is to effect
FOR PURCHASE SCRAP IRON CANCELLED." And in some payment. The above-mentioned factors could not have
of the pleadings in the course of this litigation, petitioners prevented such payment. It is also significant to note that
referred to the transaction as a contract of sale. 18 petitioners sent a telegram to private respondents on May 23,
In light of the provisions of the contract, contemporaneous 1983 cancelling the contract. This was before they had even
and subsequent acts of the parties and the other relevant received on May 26, 1983 the notice from the bank about the
circumstances surrounding the case, it is evident that the opening of the Letter of Credit. How could they have made a
stipulation for the buyer to open a Letter of Credit in order to judgment on the materiality of the provisions of the Letter of
cover the payment of the purchase price does not bear the Credit for purposes of rescinding the contract even before
marks of a suspensive condition. The agreement between the setting eyes on said document?
parties was a contract of sale and the "terms and conditions" To be sure, in the contract, the private respondents were
embodied therein which are standard form, are clearly supposed to open the Letter of Credit on May 15, 1983 but, it
resolutory in nature, the breach of which may give either party was not until May 26, 1983 or eleven (11) days later that they
the option to bring an action to rescind and/or seek damages. did so. Is the eleven-day delay a substantial breach of the
Contrary to the conclusions arrived at in the ponencia, the contract as could justify the rescission of the contract?
transaction is not a contract to sell but a contract of sale. In Song Fo and Co. v. Hawaiian-Philippine Co. 22 it was held
However, the determination of the nature of the contract does that a delay in payment for twenty (20) days was not a
not settle the controversy. A breach of the contract was violation of an essential condition of the contract which would
committed and the rights and liabilities of the parties must be warrant rescission for non-performance. In the instant case,
established. The ponencia, notwithstanding its conclusion that the contract is bereft of any suggestion that time was of the
no contract of sale existed, proceeded to state that petitioner essence. On the contrary, it is noted that petitioners allowed
company may rescind the contract based on Article 1597 of private respondents' men to dig and remove the scrap iron
the Civil Code which expressly applies only to a contract of located in petitioners' premises between May 17, 1983 until
sale. It provides: May 30, 1983 or beyond the May 15, 1983 deadline for the
"ARTICLE 1597. Where the goods have not been delivered to opening of the Letter of Credit. Hence, in the absence of any
the buyer, and the buyer has repudiated the contract of sale, indication that the time was of the essence, the eleven-day
or has manifested his inability to perform his obligations, delay must be deemed a casual breach which cannot justify a
thereunder, or has committed a breach thereof, the seller may rescission.
totally rescind the contract of sale by giving notice of his Worthy of mention before concluding is Sycip v. National
election so to do to the buyer." (Emhasis supplied). Coconut Corporation, et al. 23 since, like this case, it involves
The ponencia was then confronted with the issue of delivery a failure to open on time the Letter of Credit required by the
since Article 1597 applies only "[w]here the goods have not seller. In Sycip, after the buyer offered to buy 2,000 tons of
yet been delivered." In this case, as aforestated, the workers copra, the seller sent a telegram dated December 19, 1946 to
of private respondents were actually allowed to enter the the buyer accepting the offer but on condition that the latter
petitioners' premises, thus, giving them control and opens a Letter of Credit within 48 hours. It was not until
possession of the goods. At this juncture, it is even December 26, 1946, however, that the Letter of Credit was
unnecessary to discuss the issue of delivery in relation to the opened. The Court, speaking through Justice Bengzon, held
right of rescission nor to rely on Article 1597. In every contract that because of the delay in the opening of the Letter of
which contains reciprocal obligations, the right to rescind is Credit; the seller was not obliged to deliver the goods.
always implied under Article 1191 of the Civil Code in case Two factors distinguish Sycip from the case at bar. First, while
one of the parties fails to comply with his obligations. 19 there has already been a perfected contract of sale in the
The right to rescind pursuant to Article 1191 is not absolute. instant case, the parties in Sycip were still undergoing the
Rescission will not be permitted for slight or casual breach of negotiation process. The seller's qualified acceptance in Sycip
the contract. 20 Here, petitioners claim that the breach is so served as a counter offer which prevented the contract from
being perfected. Only an absolute and unqualified acceptance
of a definite offer manifests the consent necessary to perfect
a contract. 24 Second, the Court found in Sycip that time was
of the essence for the seller who was anxious to sell to other
buyers should the offeror fail to open the Letter of Credit
within the stipulated time. In contrast, there are no indicia in
this case that can lead one to conclude that time was of the
essence for petitioner as would make the eleven-day delay a
fundamental breach of the contract.
In sum, to my mind, both the trial court and the respondent
Court of Appeals committed no reversible error in their
appreciation of the agreement in question as a contract of
sale and not a contract to sell, as well as holding that the
breach of the contract was not substantial and, therefore,
petitioners were not justified in law in rescinding the
agreement.
PREMISES CONSIDERED, the Petition must be DISMISSED
and the decision of the Court of Appeals AFFIRMED.
AEROSPACE CHEMICAL Vs CA Case Digest On this score, we quote with approval the findings of the
AEROSPACE CHEMICAL Vs CA  appellate court, thus: The defendant [herein private
g.r.no. 108129 September 23, 1999  respondent] was not remiss in reminding the plaintiff that it
would have to bear the said expenses for failure to lift the
commodity for an unreasonable length of time.But even
FACTS: On June 27, 1986, petitioner Aerospace Industries, assuming that the plaintiff did not consent to be so bound, the
Inc. (Aerospace) purchased five hundred (500) metric tons of provisions of Civil Code come in to make it liable for the
sulfuric acid from private respondent Philippine Phosphate damages sought by the defendant.
Fertilizer Corporation (Philphos). Initially set beginning July
1986, the agreement provided that the buyer shall pay its Santos Ventura Hocorma Foundation, Inc. vs. Ernesto V.
purchases in equivalent Philippine currency value, five days Santos
prior to the shipment date. Petitioner as buyer committed to G.R. No. 153004 (November 5, 2004)
secure the means of transport to pick-up the purchases from FACTS:
private respondent's loadports. Per agreement, one hundred On October 26, 1990, the parties executed a Compromise
metric tons (100 MT) of sulfuric acid should be taken from Agreement wherein Foundation shall pay Santos P14.5
Basay, Negros Oriental storage tank, while the remaining four Million in the following manner: (a) P1.5 Million immediately
hundred metric tons (400 MT) should be retrieved from Sangi, upon the execution of this agreement; and (b) the balance of
Cebu. On December 18, 1986, M/T Sultan Kayumanggi P13 Million shall be paid, whether in lump sum or in
docked at Sangi, Cebu, but withdrew only 157.51 MT of installments, at the discretion of the Foundation, within a
sulfuric acid. Again, the vessel tilted. Further loading was period of not more than two (2) years from the execution of
aborted. Two survey reports conducted by the Societe this agreement.
Generale de Surveillance (SGS) Far East Limited, dated In compliance with the Compromise Agreement, respondent
December 17, 1986 and January 2, 1987, attested to these Santos moved for the dismissal of the aforesaid civil cases.
occurrences. Later, on a date not specified in the record, M/T He also caused the lifting of the notices of lis pendens on the
Sultan Kayumanggi sank with a total of 227.51 MT of sulfuric real properties involved. For its part, petitioner SVHFI, paid
acid on board. Petitioner chartered another vessel, M/T Don P1.5 million to respondent Santos, leaving a balance of P13
Victor, with a capacity of approximately 500 MT.6 [TSN, million. Subsequently, petitioner SVHFI sold to Development
September 1, 1989, pp. 28-29.] On January 26 and March 20, Exchange Livelihood Corporation two real properties, which
1987, Melecio Hernandez, acting for the petitioner, addressed were previously subjects of lis pendens. Discovering the
letters to private respondent, concerning additional orders of disposition made by the petitioner, respondent Santos sent a
sulfuric acid to replace its sunken purchases.  letter to the petitioner demanding the payment of the
remaining P13 million, which was ignored by the latter.
Respondent Santos sent another letter to petitioner inquiring
ISSUE: Should expenses for the storage and preservation of when it would pay the balance of P13 million. There was no
the purchased fungible goods, namely sulfuric acid, be on response from petitioner. Consequently, respondent Santos
seller's account pursuant to Article 1504 of the Civil Code?  applied with the Regional Trial Court of Makati City for the
issuance of a writ of execution.
On June 2, 1995, Santos and Riverland Inc. filed a Complaint
RULING: Petitioner tries to exempt itself from paying rental for Declaratory Relief and Damages alleging delay on the part
expenses and other damages by arguing that expenses for of SVHFI in paying the balance. They further alleged that
the preservation of fungible goods must be assumed by the under the Compromise Agreement, the obligation became
seller. Rental expenses of storing sulfuric acid should be at due on October 26, 1992, but payment of the remaining
private respondent's account until ownership is transferred, balance was effected only on November 22, 1994. Thus,
according to petitioner. However, the general rule that before respondents prayed that petitioner be ordered to pay legal
delivery, the risk of loss is borne by the seller who is still the interest on the obligation, penalty, attorney’s fees and costs of
owner, is not applicable in this case because petitioner had litigation. SVHFI alleged that the legal interest on account of
incurred delay in the performance of its obligation. Article fault or delay was not due and payable, considering that the
1504 of the Civil Code clearly states: "Unless otherwise obligation had been superseded by the compromise
agreed, the goods remain at the seller's risk until the agreement. Moreover, SVHFI argued that absent a stipulation,
ownership therein is transferred to the buyer, but when the Santos must ask for judicial intervention for purposes of fixing
ownership therein is transferred to the buyer the goods are at the period.
the buyer's risk whether actual delivery has been made or not, ISSUE:
except that: (2) Where actual delivery has been delayed Whether or not SVHFI incurred in delay based on the
through the fault of either the buyer or seller the goods are at compromise agreement and thereby liable for legal interest
the risk of the party at fault."  RULING:
Yes. SVHFI is liable for legal interest as penalty on account of
delay. The general rule is that a compromise has upon the
parties the effect and authority of res judicata, with respect to
the matter definitely stated therein, or which by implication
from its terms should be deemed to have been included
therein. This holds true even if the agreement has not been
judicially approved. Article 1169 of the New Civil Code FACTS:
provides that those obliged to deliver or to do something incur       On April 23, 1981, spouses Vasquez entered into a MOA
in delay from the time the obligee judicially or extrajudicially with Ayala Corp. with Ayala buying from the Vazquez spouses
demands from them the fulfillment of their obligation. all of the latter's shares of stock in Conduit Development, Inc.
In order for the debtor to be in default, it is necessary that the The main asset was a property in Ayala Alabang which was
following requisites be present: (1) that the obligation be then being developed by Conduit under a development plan
demandable and already liquidated; (2) that the debtor delays where the land was divided into Villages 1, 2 and 3. The
performance; and (3) that the creditor requires the development was then being undertaken by G.P. Construction
performance judicially or extrajudicially. and Development Corp. Under the MOA, Ayala was to
In the case at bar, the obligation was already due and develop the entire property, less what was defined as the
demandable after the lapse of the two-year period from the "Retained Area". This "Retained Area" was to be retained by
execution of the contract. The Compromise Agreement was the Vazquez spouses. The area to be developed by Ayala was
entered into by the parties on October 26, 1990. It was called the "Remaining Area". In this "Remaining Area" were 4
judicially approved on September 30, 1991. Applying existing lots adjacent to the "Retained Area" and Ayala agreed to offer
jurisprudence, the compromise agreement as a consensual these lots for sale to the spouses at the prevailing price at the
contract became binding between the parties upon its time of purchase. After the execution of the MOA, Ayala
execution and not upon its court approval. From the time a caused the suspension of work on Village 1 of the project.
compromise is validly entered into, it becomes the source of Ayala then received a letter from Lancer General Builder
the rights and obligations of the parties thereto. Hence, the Corp. in which the latter was claiming a certain amount as
two-year period must be counted from October 26, 1990. subcontractor. G.P. Construction not being able to reach an
Verily, the petitioner is liable for damages for the delay in the amicable settlement with Lancer, Lancer sued G.P.
performance of its obligation. This is provided for in Article Construction, Conduit and Ayala in the court. G.P.
1170 of the New Civil Code. Construction and Lancer both tried to enjoin Ayala from
undertaking the development of the property. The suit was
TITAN-IKEDA VS. PRIMETOWN  terminated only on 1987. Taking the position that Ayala was
G.R No. 158768. February 12, 2008  obligated to sell the 4 lots adjacent to the "Retained Area"
within 3 years from the date of the MOA, the Vasquez
spouses sent several "reminder" letters of the approaching
FACTS: The respondent Primetown Property Corporation so-called deadline. However, no demand after 1984, was ever
entered into contract weith the petitioner Titan-Ikeda made by the Vasquez spouses for Ayala to sell the 4 lots. On
Construction Corporation for the structural works of a 32- the contrary, one of the letters signed by their authorized
storey prime tower. After the construction of the tower, agent categorically stated that they expected development of
respondent again awarded to the petitioner the amount of P Phase 1 to be completed 3 years from the settlement of the
130,000,000.00 for the tower’s architectural design and legal problems with the previous contractor. By early 1990,
structure. Howevere, in 1994, the respondent entered inot a Ayala finished the development of the vicinity. The 4 lots were
contract of sale of the tower in favor of the petitioner in a then offered to be sold to the Vasquez spouses at the
manner called full-swapping. Since the respondent had prevailing price in 1990. This was rejected by the Vasquez
allegedly constructed almost one third of the project as weel spouses who wanted to pay at 1984 prices, thereby leading to
as selling some units to third persons unknown to the the suit below.
petitioner. Integrated Inc. took over the project, thus the ISSUE:
petitioner is demanding for the return of its advanced payment       Whether or not respondent incurred default or delay in the
in the amount of P2, 000,000.00 as weel as the keys of the fulfillment of its obligation.
unit.  HELD:
      No. In order that the debtor may be in default it is
necessary that the following requisites be present: (1) that the
ISSUE: Whether or not the petitioner is entitled to damages.  obligation be demandable and already liquidated; (2) that the
debtor delays performance; and (3) that the creditor requires
the performance judicially or extrajudicially. Under Article 1193
RULING: No, because in a contract necessarily that there is a of the Civil Code, obligations for whose fulfillment a day
meeting of the minds of the parties in which this will be the certain has been fixed shall be demandable only when that
binding law upon them. Thus, in a reciprocal obligation. Both day comes. However, no such day certain was fixed in the
parties are obliged to perform their obligation simultaneously MOA. Petitioners, therefore, cannot demand performance
and in good faith. In this case, petitioner, Titan-Ikeda can not after the 3 year period fixed by the MOA for the development
recover damages because it was found out there was no of the first phase of the property since this is not the same
solutio indebiti or mistake in payment in this case since the period contemplated for the development of the subject lots.
latter is just entitled to the actual services it rendered to the Since the MOA does not specify a period for the development
respondent and thus it is ordered to return the condominium of the subject lots, petitioners should have petitioned the court
units to the respondent. to fix the period in accordance with Article 1197 of the Civil
Code. As no such action was filed by petitioners, their
Vasquez v Ayala Corporation complaint for specific performance was premature, the
GR No. 149734 obligation not being demandable at that point. Accordingly,
Tinga, J.: Ayala Corp. cannot likewise be said to have delayed
performance of the obligation. Even assuming that the MOA December 1946 up to March 2, 1948, when the commercial
imposes an obligation on Ayala Corp. to develop the subject buildings were burned, the defendants appellants have paid
lots, within 3 years from date thereof, Ayala Corp. could still the contract rentals at the rate of P350 per month. But the
not be held to have been in delay since no demand was made failure to consign did not eradicate the default (mora) of the
by petitioners for the performance of its obligation. Moreover, lessors nor the risk of loss that lay upon them.
the letters were mere reminders and not categorical demands
to perform. These letters were sent before the obligation could STATE INVESTMENT HOUSE INC vs. COURT OF
become legally demandable. More importantly, petitioners APPEALS Case Digest
waived the 3 year period as evidenced by their agent's letter
to the effect that petitioners agreed that the 3 year period G.R. No. 115548 March 5, 1996 
should be counted from the termination of the case filed by
Lancer. STATE INVESTMENT HOUSE INC vs. COURT OF
APPEALS
CLAUDINA VDA. DE VILLARUEL, ET AL. VS. MANILA
MOTOR CO., INC. 104 PHIL. 926 FACTS:

FACTS: On May 31, 1940, the plaintiffs Villaruel and On October 15, 1969, Contract to Sell No. 36 was executed
defendant Manila Motor Co. Inc. entered into a contract by the Spouses Canuto and Ma. Aranzazu Oreta, and the
whereby the defendant agreed to lease plaintiffs building Solid Homes, Inc. (SOLID), involving a parcel of land
premises. On October 31, 1940, the leased premises were identified as Block No. 8, Lot No. 1, Phase of the Capitol Park
placed in the possession of the defendant until the invasion of Homes Subdivision, Quezon City, containing 511 square
1941. The Japanese military occupied and used the property meters for a consideration of P39,347.00. Upon signing of the
leased as part of their quarters from June, 1942 to March, contract, the spouses  Oreta made payment amounting to
1945, in which no payment of rentals were made. Upon the P7,869.40, with the agreement that the balance shall
liberation of the said city, the American forces occupied the be payable in monthly installments of P451.70, at 12%
same buildings that were vacated by the Japanese. When the interest per annum.
United States gave up the occupancy of the premises,
defendant decided to exercise their option to renew the On November 4, 1976, SOLID executed several real estate
contract, in which they agreed. However, before resuming the mortgage contracts in favor of State Investment Homes, (sic)
collection of rentals, Dr. Alfredo Villaruel upon advice Inc. (STATE) over its subdivided parcels of land, one of which
demanded payment of rentals corresponding to the time the is the subject lot.
Japanese military occupied the leased premises, but the
defendant refused to pay. As a result plaintiff gave notice For Failure of SOLID to comply with its mortgage obligations
seeking the rescission of the contract and the payment of contract, STATE extrajudicially foreclosed the mortgaged
rentals from June, 1942 to March, 1945; this was rejected by properties including the subject lot on April 6, 1983, with
the defendant. Despite the fact the defendant under new the corresponding certificate of sale issued therefor to STATE
branch manager paid to plaintiff the sum of P350 for the rent, annotated at the back of the titles covering the said properties
the plaintiff still demanded for rents in arrears and for the on October 13, 1983.
rescission of the contract of lease. The plaintiff commenced
an action before the CFC of Neg. Occidental against On June 23, 1984; SOLID thru a Memorandum of Agreement
defendant company. During the pendency of the case, the negotiated for the deferment of consolidation of ownership
leased building was burned down. Because of the occurrence, over the foreclosed properties by committing to redeem
plaintiffs demanded reimbursement from the defendants, but the properties from STATE.
having been refused, they filed a supplemental complaint to
include a 3rd cause of action, the recovery of the value of the On August 15, 1988, the spouses filed a complaint before the
burned building. The trial court rendered judgment in favor of Housing and Land Use Regulatory Board, HLRB, against the
the plaintiff. Hence the defendants appeal. developer SOLID and STATE for failure on the part of SOLID
ISSUE: Is Manila Motor Co. Inc. liable for the loss of the "to execute the necessary absolute deed of sale as well as to
leased premises? deliver title to said property . . . in violation of the contract to
RULING: No. Clearly, the lessor’s insistence upon collecting sell . . .," despite full payment of the purchase price as of
the occupation rentals for 1942-1945 was unwarranted in law. January 7, 1981. In its Answer, SOLID, by way of alternative
Hence, their refusal to accept the current rentals without defense, alleged that the obligations under the Contract to
qualification placed them in default (mora creditoris or Sell has become so difficult . . . the herein respondents
accipiendi) with the result that thereafter, they had to bear all be partially released from said obligation by substituting
supervening risks of accidental injury or destruction of the subject lot with another suitable residential lot from another
leased premises. While not expressly declared by the Code of subdivision which respondents own/operates". Upon the
1889, this result is clearly inferable from the nature and other hand, STATE, to which the subject lot was mortgaged,
effects of mora. In other words, the only effect of the failure to averred that unless SOLID pays the redemption price of
consign the rentals in court was that the obligation to pay P125,1955.00, (sic) it has "a right to hold on and not release
them subsisted and the lessee remained liable for the amount the foreclosed properties.
of the unpaid contract rent, corresponding to the period from
July to November, 1946; it being undisputed that, from
In Sunshine Finance and Investment Corp. v. Intermediate
ISSUES:  Appellate Court,  the Court noting petitioner therein to be a
financing corporation, deviated from the general rule that a
1.) WON Sps. Oreta’s unregistered rights over the subject purchaser or mortgagee of a land is not required to look
property are superior to the registered mortgage rights of further that what appears on theface of the Torrens Title. 
petitioner State Investment House, Inc. (STATE) 
2.) WON the CA erred in not applying the settled rule that
persons dealing with property covered by torrens certificate of The above-enunciated rule should apply in this case as
title are not required to go beyond what appears on the face petitioner admits of being a financing 
of the title. institution. We take judicial notice of the uniform practice of
financing institutions to investigate, examine and assess the
HELD:  real property offered as security for any loan
application especially where, as in this case, the subject
1.) YES! STATE's registered mortgage right over the property property is a subdivision lot located at Quezon City, M.M. It is
is inferior to that of respondents spouses' unregistered right. a settled rule that a purchaser or mortgagee cannot close its
The unrecorded sale between respondents-spouses and eyes to facts which should put a reasonable man upon his
SOLID is preferred for the reason that if the original owner guard, and then claim that he acted in good faith under the
(SOLID, in this case) had parted with his ownership of the belief that there was no defect in the title of the vendor or
thing sold then he no longer had ownership and free disposal mortgagor. Petitioner's constructive knowledge of the defect in
of that thing so as to be able to mortgage it again. the title of the subject property, or lack of such knowledge due
Registration of the mortgage is of no moment since it is to its negligence, takes the place of registration of the rights of
understood to be without prejudice to the better right of third respondents-spouses. Respondent Court thus correctly ruled
parties. that petitioner was not a purchaser or mortgagee in good
faith; hence petitioner can not solely rely on what merely
2.) NO! As a general rule, where there is nothing in the appears on the face of the Torrens Title.
certificate of title to indicate any cloud or vice in the ownership
of the property, or any encumbrance thereon, the purchaser is Angeles V Calasanz
not required to explore further than what the Torrens Title
upon its face indicates in quest for any hidden defect or FACTS:
inchoate right that may subsequently defeat his right thereto. Ursula and Tomas Calasanz sold a piece of land to
Buenaventura Angeles and Teofila Juani covered by a
This rule, however, admits of an exception as where the contract to sell. Angeles paid a down payment upon the
purchaser or mortgagee, has knowledge of a defect or lack of execution of the contract and started paying the balance in
monthly installments for nine years with only a few remaining
title in his vendor, or that he was aware of sufficient facts to
installments left to pay. Although Calasanz accepted late
induce a reasonably prudent man to inquire into the status of payments before, Angeles was now five months late.
the title of the property in litigation. 7 In this case, petitioner Calasanz demanded payment of past due accounts, but did
not receive any. Eventually, Calansanz canceled the said
was well aware that it was dealing with SOLID, a business contract and Angeles asked for reconsideration, but was
entity engaged in the business of selling subdivision lots. In denied.
A provision in the contract to sell gave Calasanz the right to
fact, the OAALA found that at the time the lotwas mortgaged,
cancel the contract and consider the amounts paid as rent for
respondent State Investment House Inc., [now petitioner] had the property. However, the lower court ruled that the contract
been aware of the lot's location and that the said lot formed was not validly canceled and ordered Calasanz to execute a
final Deed of Sale in favor of Angeles.
part of Capital Park/Homes Subdivision."   ISSUE:
Was the contract to sell validly canceled?
RULING:
No. The act of a party in treating a contract as canceled or
resolved on account of infractions by the other must be made
known to the other and is always provisional, being ever
subject to scrutiny and review by the proper court. If the other at bar, respondent Fernando performed his part of the
party denies that rescission is justified, it is free to bring the obligation by allowing petitioner Leano to continue in
matter to court. Then, should the court decide that the possession and use of the property. Clearly, when petitioner
resolution of the contract was not warranted, the responsible Leano did not pay the monthly amortizations in accordance
party will be sentenced to damages; in the contrary case, the with the terms of the contract, she was in delay and liable for
resolution will be affirmed and indemnity awarded to the party damages. However, we agree with the trial court that the
prejudiced. default committed by petitioner Leano in respect of the
The right to rescind the contract for non-performance of one obligation could be compensated by the interest and
of its stipulations is not absolute. The general rule is that surcharges impo!ed upon her under the contract in question.
rescission of a contract will not be permitted for a slight or
casual breach, but only for such substantial and fundamental Heirs of Luis Bacus Vs. CA
breach as would defeat the very object of the parties in Facts: Bacus leased a parcel of land to Faustino Duray in
making the agreement. The question of whether a breach of a Cebu. The lease was for 6 years ending in 1990, the contract
contract is substantial depends upon the attendant contained an option to buy clause. Under such option the
circumstances. lessee had the exclusive and irrevocable right to buy 2000 sq
The breach of the contract alleged by Calasanz is so slight meters within 5 years after the effectivity of the contract.
considering that Angeles had already paid monthly Close to the expiration of the contract, Bacus died after Duray
installments for almost nine years. In only a short time, the informed the heirs of Bacus that they are willing to purchase
entire obligation would have been paid. the property under the option to buy clause. The heirs refused
To mitigate the unilateral act of Calasanz in cancelling the to sell, thus Duray filed a complaint for specific performance
contract, Article 1234 of the Civil Code provides that: If the against the heirs of Bacus. RTC ruled in favor of Duray, CA
obligation has been substantially performed in good faith, the affirmed.
obligor may recover as though there had been a strict and Issue: W/o the heirs of Bacus be compelled to sell the portion
complete fulfillment, less damages suffered by the obligee. of the lot under the option to buy clause.
Held: Yes. Obligation under an option to buy is a reciprocal
CARMELITA LEANO Vs. COURT OF APPEALS obligation. The performance of one obligation is conditioned
G.R. No. 129018  on the simultaneous fulfillment of the other obligation. The
NOVEMBER 15- 2001 payment of the purchase price is contingent upon the
execution and delivery of the deed of sale by the debtor.
FACTS: When Duray exercised their option to buy, their obligation was
Hermogenes Fernando, as vendor and Carmelita Leano, as to advise the Bacus’ heirs of their decision and readiness to
vendee executed a contract tosell involving a piece of land. In pay the price. Upon the actual execution of Bacus were they
the contract, Leano bound herself to pay Fernando P10,775 required to pay. Duray did not incur delay when they did not
at the signing of the contract with the balance of P96,965.00 yet deliver the payment nor make a consignation before the
to be paid within a period of TEN(10) years at a monthly expiration of the contract.
amortization of P1747.30. The contract also provided for a
grace periodof one month within which to make payments, Laforteza vs. Machuca
together with the one corresponding to the monthof
grace. Should the month of grace expire without the Facts:
installments for both months having beensatisfied, an interest
of 18% per annum will be charged on the unpaid installments. Roberto Laforteza and Gonzalo Laforteza, Jr., in their
capacities as attorneys-in-fact of Dennis Laforteza, entrered
ISSUE; into a MOA (Contract to Sell) with Alonzo Machuca over a
Whether petitioner was in delay in the payment of the monthly house and lot registered in the name of the late Francisco
amortizations. Laforteza. Machuca was able to pay the earnest money but
however failed to pay the balance on time. Upon a request of
RULING; an extension of time, Machuca informed petitioner heirs that
On the issue of whether petitioner Leano was in delay in the balance was already covered, but petitioners refused to
paying the amortizations, we rule that while the contract accept the balance and told Machuca that the subject
provides that the total purchase price was payable within property is no longer for sale. The petitioners contend that the
a ten/year period, the same contract specified that the Memorandum of Agreement is merely a lease agreement with
purchase price shall be paid in monthly installments for which “option to purchase”; hence, it only gave the respondent a
the corresponding penalty shall be imposed in case right to purchase the subject property within a limited period
of default. Petitioner Leano cannot ignore the provision on the without imposing upon them any obligation to purchase it. And
payment of monthly installments by claiming that the ten/year since the respondent’s tender of payment was made after the
period within which to pay has not elapsed. lapse of the option agreement, his tender did not give rise to
the perfection of a contract of sale.
Article 1169 of the Civil Code provides that in reciprocal
obligations, neither party incurs in delay if the other does not
comply or if not ready to comply in a proper manner with what
is incumbent upon him. From the moment one of the parties Issue:
fulfills his obligation, delay by the other begins. In the case (1) WON the tender of payment after the lapse of the option
agreement gave rise to the perfection of a contract of sale. Article 1170 of the Civil Code provides “Those who in the
performance of their obligations are guilty of fraud,
(2) WON the six-moth period during which the respondent negligence, or delay, and those who in  any manner
would be in possession of the property as lessee was a period contravene the tenor thereof, are liable for damages”
within which to exercise an option. The failure of HPC to deliver the rest of the molasses
constitutes a breach of contract by contravention of tenor and
Held: is thus liable for damages. The bases for damages is the cost
(1) It did. A perusal of the Memorandum Agreement shows in excess of the agreed price in the contract when SFC was
that the transaction between the petitioners and the made to acquire the needed molasses from another supplier
respondent was one of sale and lease. and the expenses related to the transportation of the same.
 A contract of sale is a consensual contract and is perfected at Loss of profits would have been included as part of damages
the moment there is a meeting of the minds upon the thing had SFC been able to substantiate such a claim.
which is the object of the contract and upon the price. From As to the second question, no, HPC has no right to rescind
that moment the parties may reciprocally demand the contract.
performance subject to the provisions of the law governing the The court provided that the general rule is that rescission
form of contracts. In the case at bench, all the elements of a will not be permitted for a slight or casual breach of the
contract of sale were thus present. contract, but only for such breaches as are so substantial
(1) The six-month period during which the respondent would and fundamental as to defeat the object of the parties in
be in possession of the property as lessee, was clearly not a making the agreement.
period within which to exercise an option. An option is a It should be noted that the time of payment stipulated for in
contract granting a privilege to buy or sell within an agreed the contract should be treated as of the essence of the
time and at a determined price. An option contract is a contract. There was only a slight breach of contract when the
separate and distinct contract from that which the parties may payment was delayed for 20 days and does not violate
enter into upon the consummation of the option. An option essential condition of the contract which warrants rescission
must be supported by consideration.   An option contract is for non-performance. Furthermore, HPC accepted the
governed by the second paragraph of Article 1479 of the Civil payment of the overdue accounts and continued with the
Code, which reads: contract, waiving its right to rescind the same.
Art. 1479… . Petition of partly granted, and the judgment appealed is
An accepted unilateral promise to buy or to sell a determinate modified. Plaintiff shall have and recover from the defendant
thing for a price certain is binding upon the promissor if the the sum of P3,000, with legal interest from date of judgment,
promise is supported by a consideration distinct from the no special costs.
price.
In the present case, the six-month period merely delayed the
demandability of the contract of sale and did not determine its
perfection for after the expiration of the six-month period, Boysaw vs. Interphil Promotions
there was an absolute obligation on the part of the petitioners
and the respondent to comply with the terms of the sale. Summary: A boxer signed an agreement with a promotions
agency to arrange and promote a boxing match with Flash
Song Fo & Company V. Hawaiian Philippine Co. Elorde. The boxer violated the terms of the contract, but in
spite of these, the agency proceeded except it negotiated for
G.R. No. 23769 – September 16, 1925 a new date for the match. Eventually, the match as originally
FACTS: stated in the contract did not materialize. Boxer and manager
Hawaiian-Philippine Co (HPC) entered into a contract with is now suing the promotion agency for breach of contract.
Song Fo and Co (SFC) where it would deliver molasses to the
latter evidenced by a letter containing their contract. The Rule of Law: Where one party did not perform the
same states that Mr. Song Fo agreed to the delivery of undertaking which he was bound by the terms of the
300,000 gallons of molasses and the same requested for an agreement to perform, he is not entitled to insist upon the
additional 100,000 molasses which the HPC promised that it performance of the contract by the other party, or recover
will do its best to comply with the additional shipment. damages by reason of his own breach.
However, the HPC was only able to deliver 55,006 gallons.
SFC thereafter filed a complaint with two causes of action for Facts: Solomon Boysaw (P), signed with Interphil
breach of contract against the HPC and asked for Promotions, Inc. (D), a contract to engage Gabriel "Flash"
P70,369.50. HPC answered that there was a delay in the Elorde in a boxing contest for the junior lightweight
payment from championship of the world. Thereafter, Interphil (D) signed
SFC and that HPC has the right to rescind the contract Gabriel "Flash" Elorde to a similar agreement—that is, to
because of the same· The trial court condemned HPC to pay engage Boysaw in a title fight.
SFC a total of P35,317.93, with legal interest.
ISSUES: The managerial rights over Boysaw (P) was assigned and
1. Whether or not SFC is entitled to damages eventually reassigned to Alfredo Yulo, Jr. (P) without the
2. Whether or not HPC has a right to rescind the contract? consent of Interphil (D) in violation of their contract. When
RULING: informed of the change, Interphil (D) referred the matter to the
As to the first question, yes, SFC is entitled to damages. Games and Amusement Board culminating to a decision by
the board to approve a new date for the match. Yulo (P)
protested against the new date even when another proposed UNIVERSITY OF THE PHILIPPINES VS. DE LOS
date was within the 30-day allowable postponements. ANGELES
35 SCRA 102
Boysaw (P) and Yulo (P) filed for breach of contract when the
fight contemplated in the original boxing contract did not FACTS:
materialize. On November 2, 1960, UP and ALUMCO entered into a
logging agreement whereby the latter was granted exclusive
Issues: May the offending party in a reciprocal obligation authority to cut, collect and remove timber from the Land
compel the other party for specific performance? Grant for a period starting from the date of agreement to
December 31, 1965, extendible for a period of 5 years by
Ruling: No. Evidence established that the contract was mutual agreement.
violated by Boysaw (P) when, without the approval or consent
of Interphil (D), he fought a boxing match in Las Vegas. On December 8, 1964, ALUMCO incurred an unpaid account
Another violation was the assignment and transfer of the of P219,362.94. Despite repeated demands, ALUMCO still
managerial rights over Boysaw (P) without the knowledge or failed to pay, so UP sent a notice to rescind the logging
consent of Interphil (D). agreement. On the other hand, ALUMCO executed an
instrument entitled “Acknowledgment of Debt and Proposed
While the contract imposed no penalty for such violation, this Manner of Payments. It was approved by the president of UP,
does not grant any of the parties the unbridled liberty to which
breach it with impunity. Our law on contracts recognizes the stipulated the following:
principle that actionable injury inheres in every contractual
breach. 3. In the event that the payments called for are not sufficient
to liquidate the foregoing indebtedness, the balance
Those who in the performance of their obligations are guilty of outstanding after the said payments have been applied shall
fraud, negligence or delay, and those who in any manner be paid by the debtor in full no later than June 30, 1965.
contravene the terms thereof, are liable for damages.
   —Article 1170, Civil Code. 5. In the event that the debtor fails to comply with any of its
promises, the Debtor agrees without reservation that Creditor
The power to rescind obligations is implied, in reciprocal ones, shall have the right to consider the Logging Agreement
in case one of the obligors should not comply with what is rescinded,
incumbent upon him. without the necessity of any judicial suit…
   —Article 1191, Civil Code.

The contract in question gave rise to reciprocal obligations. ALUMCO continued its logging operations, but again incurred
Reciprocal obligations are those which arise from the same an unpaid account. On July 19,1965, UP informed ALUMCO
cause, and in which each party is a debtor and a creditor of that it had, as of that date, considered rescinded and of no
the other, such that the obligation of one is dependent upon further legal effect the logging agreement, and that UP had
the obligation of the other. They are to be performed already taken steps to have another concessionaire take over
simultaneously, so that the performance of one is conditioned the logging operation. ALUMCO filed a petition to enjoin UP
upon the simultaneous fulfillment of the other. from conducting the bidding. The lower court ruled in favor of
   —Tolentino, Civil Code of the Philippines, Vol. IV, p. 175. ALUMCO, hence, this appeal.
The power to rescind is given to the injured party.
Where the plaintiff is the party who did not perform the ISSUE:
undertaking which he was bound by the terms of the Can petitioner UP treat its contract with ALUMCO rescinded,
agreement to perform, he is not entitled to insist upon the and may disregard the same before any judicial
performance of the contract by the defendant, or recover pronouncement to that effect?
damages by reason of his own breach.
   —Seva vs. Alfredo Berwin, 48 Phil. 581. RULING:

Under the law, when a contract is unlawfully novated by an Yes. In the first place, UP and ALUMCO had expressly
applicable and unilateral substitution of the obligor by another, stipulated that upon default by the debtor, UP has the right
the aggrieved creditor is not bound to deal with the substitute. and the power to consider the Logging
However, from the evidence, it is clear that the Interphil (D), Agreement of December 2, 1960 as rescinded without the
instead of availing themselves of the options given to them by necessity of any judicial suit. As to such special stipulation
law of rescission or refusal to recognize the substitute obligor, and in connection with Article 1191 of the Civil Code, the
really wanted to postpone the fight date owing to an injury that Supreme Court, stated in Froilan vs. Pan Oriental Shipping
Elorde sustained in a recent bout. That Interphil (D) had Co:
justification to renegotiate the original contract, particularly the
fight date is undeniable from the facts. Under the “There is nothing in the law that prohibits the parties from
circumstances, Interphil's (D) desire to postpone the fight date entering into agreement that violation of the terms of the
could neither be unlawful nor unreasonable. contract would cause cancellation thereof, even without court
intervention. In other words, it is not always CFI order. The CA dismissed the petition. The SC affirmed.
necessary for the injured party to resort to court for rescission Upon Erquiaga’s motion, the CFI issued an order on February
of the contract.” 12, 1975: (a) dissolving the receivership and ordering the
delivery of the possession of the Hacienda San Jose to
Erquiaga, (b) ordering Erquiaga to file a P410,000 bond
De Erquiaga V CA conditioned to the payment of whatever may be due to the
Reynoso heirs after the approval of Reynoso’s accounting
G.R. No. 47206, September 27, 1989, 178 SCRA 1 report; and (c) allowing Erquiaga’s counsel to inspect, copy
FACTS: and photograph certain documents related to the accounting
Santiago de Erquiaga was the owner of 100% or 3,100 paid- report.
up shares of stock of the Erquiaga Development Corporation The CFI approved Erquiaga’s submitted bond and turned over
(EDC) which owns the Hacienda San Jose in Irosin, the possession, management and control of the hacienda to
Sorsogon. him. Upon Erquiaga’s Omnibus Motion, opposed by
On November 4, 1968, he entered into an Agreement with Reynosos, the CFI ordered the latter to deliver to Erquiaga
Jose L. Reynoso to sell to the latter his 3,100 shares (or within 5 days from receipt of the order the 1,600 shares which
100%) of EDC for P900,000, payable in installments on are in their possession. The CFI also denied the prayer to (a)
definite dates fixed in the contract but not later than strike out all expenses allegedly incurred by Reynosos in the
November 30, 1968. production of the fruits of Hacienda San Jose; (b) declare
Reynoso failed to pay the second and third installments on Erquiaga’s obligation to pay Reynosos P410,000 with interest
time. Thus, the total price of the sale was increased to as fully compensated by the fruits earned by Reynosos from
P971,371.70 payable on or before December 17, 1969. The the property; and (c) issue a writ of execution against
increase represented brokers’ commission and interest. Reynosos to pay Erquiaga P62,000.
As of December 17, 1968, Reynoso was able to pay Reynosos filed a petition for certiorari against the last order.
P410,000 to Erquiaga who thereupon transferred all his The CA ruled in their favor, holding that the CFI acted with
shares to Reynoso, as well as the possession of the Hacienda GADALEJ in refusing to order the reimbursement of the
San Jose, EDC’s only asset. However, as provided in P410,000 purchase price plus interests awarded in the final
paragraph 3, subparagraph (c) of the contract to sell, decision and the setoff therewith of P62,000 as damages and
Reynoso pledged 1,500 shares in favor of Erquiaga as attorney’s fees in Erquiaga’s favor. Thus, the CA directed
security for the balance of his obligation. Erquiaga to return P410,000 (or net P348,000 after deducting
Reynoso failed to pay the balance of P561,321.70 on or P62,000 due from Reynoso) as the price paid by Reynoso for
before December 17, 1969, as provided in the promissory the shares of stock, with legal rate of interest, and the return
notes he delivered to Erquiaga. So, on March 2, 1970, by Reynoso of Erquiaga’s 3,100 shares with the fruits.
Erquiaga, through counsel, formally informed Reynoso that he At the time of the CA decision:
was rescinding the sale of his shares in EDC. o Hacienda San Jose was returned to Erquiaga;
Erquiaga filed a complaint for rescission with preliminary o Reynoso has returned to Erquiaga only the pledged 1,500
injunction against Reynoso and EDC, in CFI Sorsogon, shares of stock;
Branch I. The CFI ruled in favor of Erquiaga, rescinded the o Reynoso has not complied with (b) and (c) of the decision;
sale, and ordered Reynoso to: (a) return and reconvey to o Erquiaga has not returned P410k required by the decision.
Erquiaga the 3,100 paid up shares of stock of the EDC; (b) Erquiaga alleged that the CA decision of requiring him to pay
render a full accounting of the fruits he received by virtue of Reynosos P410,000 plus interest, without first awaiting
said shares, and to return said fruits received by him to Reynoso’s accounting of the fruits of the Hacienda San Jose,
Erquiaga; (c) and pay Erquiaga P12,000 as actual damages, violates the law of the case and Art. 1385, CC, alters the final
P50,000 as attorney’s fees, the costs of this suit and order dated February 12, 1975 of the trial court, and is
expenses of litigation (P62,000). Erquiaga was ordered to inequitous.
return to Reynoso P100,000 plus legal interest from ISSUE:
November 4, 1968, and P310,000 plus legal interest from WON Erquiaga’s allegation has merit
December 17, 1968, until paid (P410,000 total). HELD:
The CFI decision became final and executory. However, it NO. The CA order is in full accord with Art. 1385, CC:
issued another order holding in abeyance Erquiaga’s payment “ART. 1385. Rescission creates the obligation to return the
of P410,000 plus interest, pending Reynoso’s accounting of things which were the object of the contract, together with
the fruits he received on account of the shares. In the same their fruits, and the price with its interest; consequently, it can
order, the CFI appointed a receiver since (a) the accounting of be carried out only when he who demands rescission can
the fruits received by Reynoso would take time; and (b) return whatever he may be obliged to restore.
Erquiaga has shown sufficient and justifiable ground for the “Neither shall rescission take place when the things which are
appointment of a receiver ‘in order to preserve the Hacienda the object of the contract are legally in the possession of third
which has obviously been mismanaged by Reynoso (arrears persons who did not act in bad faith.
in DBP loan amounting to P503,510.70 and danger of “In this case, indemnity for damages may be demanded from
foreclosure to Erquiaga’s damage). the person causing the loss.”
On April 26, 1973, Jose L. Reynoso died and he was The Hacienda San Jose and 1,500 shares of stock have
substituted by his surviving spouse Africa Valdez Vda. de already been returned to Erquiaga. Therefore, upon the return
Reynoso and children, as defendants. The Reynoso heirs to him of the remaining 1,600 shares, Erquiaga should return
(Reynosos) filed a petition for certiorari in the CA against the to Reynoso P410,000 which the latter paid for those shares.
Pursuant to the rescission decreed in the final judgment, there ISSUE
should be simultaneous mutual restitution of the principal Whether or not the seller can resort to the remedy of
object of the contract to sell (3,100 shares) and of the rescission under Art 1191 which provides that the subsidiary
consideration paid (P410,000). This should not await the and equitable remedy of rescission in case of breach of
mutual restitution of the fruits, namely: the legal interest reciprocal obligation.
earned by Reynoso’s P410,000 while in the possession of HELD 
Erquiaga, and its counterpart: the fruits of Hacienda San Jose The petition is hereby GRANTED. The Intermediate Appellate
which Reynoso received from the time the hacienda was Court’s decision is REVERSED and SET ASIDE. The
delivered to him on November 4, 1968 until it was placed petitioners are ordered to pay the balance of their
under receivership by the court on March 3, 1975. indebtedness under the Deed of Absolute Sale with Mortgage
However, since Reynoso has not yet given an accounting of with legal interests from the second installment due on
those fruits, it is only fair that Erquiaga’s obligation to deliver October 24, 1975 until fully paid,
to Reynoso the legal interest earned by his money, should 1.) There is no dispute that the parties entered into a contract
await the rendition and approval of his accounting. To this of sale as distinguished from a contract to sell. By the contract
extent, the decision of the Court of Appeals should be of sale, the vendor obligates himself to transfer the ownership
modified. For it would be inequitable and oppressive to of and to deliver a determinate thing to the buyer, who in turn,
require Erquiaga to pay the legal interest earned by is obligated to pay a price certain in money or its equivalent
Reynoso’s P410,000 since 1968 or for the past 20 years (Art. 1458, Civil Code). From the respondents’ own
(amounting to over P400,000 by this time) without first arguments, we note that they have fully complied with their
requiring Reynoso to account for the fruits of Erquiaga’s part of the reciprocal obligation. 2.) The petitioners’ breach of
hacienda which he allegedly squandered while it was in his obligations is not with respect to the perfected contract of sale
possession from November 1968 up to March 3, 1975. but in the obligations created by the mortgage contract. The
remedy of rescission is not a principal action retaliatory in
character but becomes a subsidiary one which by law is
Margarita Suria vs Court of Appeals & Herminom/ available only in the absence of any other legal remedy. The
Natividad Crispin relationship between the parties is no longer one of buyer and
seller because the contract of sale has been perfected and
consummated. It is already one of a mortgagor and a
FACTS mortgagee. In consideration of the petitioners’ promise to pay
That on March 31, 1975, plaintiffs being the owners of a on installment basis the sum they owe the respondents, the
parcel of land situated at Barrio San Antonio, San Pedro, latter have accepted the mortgage as security for the
Laguna, entered into a contract denominated as DEED OF obligation. 3)The petitioners have offered to pay au past due
SALE WITH MORTGAGE, with herein defendants, a true accounts. Considering the lower purchasing value of the peso
copy of said contract. in terms of prices of real estate today, the respondents are
That the defendants violated the terms and conditions of the correct in stating they have suffered losses. However, they
contract by failing to pay the stipulated installments and in fact are also to blame for trusting persons who could not or would
only one installment due in July 1975 (paid very late in the not comply with their obligations in time. They could have
month of September, 1975) was made all the others foreclosed on the mortgage immediately when it fell due
remaining unsettled to the present time; instead of waiting all these years while trying to enforce the
That repeated verbal and written demands were made by wrong remedy.
plaintiff upon the defendants for the payment of the
installments, some of said written demands having been
made on September 24, 1981, February 7, 1982, February
24, 1983, March 13, 1983, and April 12, 1983, but defendants
for no justifiable reason failOn November 14, 1983, petitioners
filed their answer with counterclaim.
On July 16, 1984, petitioners filed a motion to dismiss
complaint, alleging that:That plaintiffs are not entitled to the
subsidiary remedy of rescission because of the presence of
remedy of foreclosure in the Deed of Sale with Mortgage ,
secondly that, assuming arguendo that rescission were a
proper remedy, it is apparent in the face of the Complaint that
the plaintiffs failed to comply with the requirements of law,
hence the rescission was ineffective, illegal, null and void, and
invalid.
On July 26, 1984, private-respondents filed their opposition to
the above motion.In the meantime, on August 6, 1984,
petitioners formerly offered to pay private-respondents all the
outstanding balance under the Deed of Sale with Mortgage,
which offer was rejected by private respondents on August 7,
1984. On November 26, 1984, the respondent-Court denied
the motion to dismiss.
Ong v. CA A careful reading of the parties' "Agreement of Purchase and
Facts: Sale" shows that it is in the nature of a contract to sell, as
Petitioner Jaime Ong, on the one hand, and respondent distinguished from a contract of sale. In a contract of sale, the
spouses Miguel K. Robles and Alejandra Robles, on the other title to the property passes to the vendee upon the delivery of
hand, executed an "Agreement of Purchase and Sale" the thing sold; while in a contract to sell, ownership is, by
respecting two parcels of land situated at Barrio Puri, San agreement, reserved in the vendor and is not to pass to the
Antonio, Quezon. On May 15, 1983, petitioner Ong took vendee until full payment of the purchase price. In a contract
possession of the subject parcels of land together with the to sell, the payment of the purchase price is a positive
piggery, building, ricemill, residential house and other suspensive condition, the failure of which is not a breach,
improvements thereon. casual or serious, but a situation that prevents the obligation
For failure of the vendee to pay the price as agreed upon, a of the vendor to convey title from acquiring an obligatory
complaint for rescission of contract and recovery of properties force. The non-fulfillment of the condition of full payment
with damages. Later, while the case was still pending with the rendered the contract to sell ineffective and without force and
trial court, petitioner introduced major improvements on the effect. It must be stressed that the breach contemplated in
subject properties. These prompted the respondent spouses Article 1191 of the New Civil Code is the obligor's failure to
to ask for a writ of preliminary injunction. The trial court comply with an obligation. Failure to pay, in this instance, is
granted the application and enjoined petitioner from not even a breach but merely an event which prevents the
introducing improvements on the properties except for repairs. vendor's obligation to convey title from acquiring binding
Eventually, the trial court ordered the rescission of the force. Hence, the agreement of the parties in the case at
contract. bench may be set aside, but not because of a breach on the
Issues: part of petitioner for failure to complete payment of the
(1) whether the contract entered into by the parties may be purchase price. Rather, his failure to do so brought about a
validly rescinded under Article 1191 of the New Civil Code situation which prevented the obligation of respondent
(2) whether the parties had novated their original contract as spouses to convey title from acquiring an obligatory force.
to the time and manner of payment Novation is never presumed, it must be proven as a fact either
Held: by express stipulation of the parties or by implication derived
Article 1191 of the New Civil Code refers to rescission from an irreconcilable incompatibility between the old and the
applicable to reciprocal obligations. Reciprocal obligations are new obligation. In order for novation to take place, the
those which arise from the same cause, and in which each concurrence of the following requisites is indispensable: (1)
party is a debtor and a creditor of the other, such that the there must be a previous valid obligation; (2) there must be an
obligation of one is dependent upon the obligation of the agreement of the parties concerned to a new contract; (3)
other. They are to be performed simultaneously such that the there must be the extinguishment of the old contract; and (4)
performance of one is conditioned upon the simultaneous there must be the validity of the new contract. The aforesaid
fulfillment of the other. requisites are not found in the case at bench. The subsequent
acts of the parties hardly demonstrate their intent to dissolve
the old obligation as a consideration for the emergence of the
new one.

BPI Investment V CA.

obligations and contracts: Reciprocal Obligations: It is a basic


principle in reciprocal obligations that neither party incurs in
delay, if the other does not comply or is not ready to comply in purchase price of as follows:(a) upon the execution of this
a proper manner with what is incumbent upon him. instrument on or before April 30, on or before December 31,
1985.
FACTS:
When the second payment was due, Iringan paid only Thus,
Frank Roa obtained a loan at 16 1/4% interest rate per annum Palao sent a letter to Iringan stating that he considered the
from Ayala Investment and Development Corporation. For contract as rescinded and that he would not accept any
further payment considering that Iringan failed to comply with
security, Roa's house and lot were mortgaged. Later, Roa sold
his obligation to pay the full amount of the second installment.
the house and lot to ALS and Antonio Litonjua, who assumed Iringan through his counsel Atty. Hilarion L. Aquino, replied
Roa's debt to Ayala Investment. Ayala Investment, however, that they were not opposing the revocation of the Deed of
granted a new loan to be applied to Roa's debt, secured by Sale but asked for the reimbursement of the following
the same property at a different interest rate of 20% per amounts:(a) cash P3,200.00 geodetic engineers P500.00
annum. attorneys the current interest on P53,700.00. In response,
Palao sent a letter dated January 10, 1986 to Atty. Aquino,
When ALS and Litonjua failed to pay, BPIIC, successor to stating that he was not amenable to the reimbursements
Ayala Investment, filed for foreclosure of mortgage. claimed Iringan.

ISSUE: On February 21, 1989, Iringan, now represented a new


counsel Atty. Carmelo Z. Lasam, proposed that the which he
had already paid Palao be reimbursed or Palao could sell to
 W/N a contract of loan is a consensual contract Iringan, an equivalent portion of the land. Palao instead wrote
Iringan that the latters standing obligation had reached
P61,600, representing payment of arrears for rentals from
HELD:
October 1985 up to March The parties failed to arrive at an
agreement. On July 1, 1991, Palao filed a for Judicial
A loan contract is not a consensual contract but a real Confirmation of Rescission of Contract and Damages against
contract. It is perfected upon delivery of the object of the Iringan and his wife.
contract. Although a perfected consensual contract can give
rise to an action for damages, it does not constitute a real ISSUE:
contract which requires delivery for perfection. A perfected
real contract gives rise only to obligations on the part of the Whether or not the contract of sale was validly rescinded.
borrower.
RULING:
In the present case, the loan contract was only perfected on
the date of the second release of the loan. Article 1592 of the Civil Code is the applicable provision
regarding the sale of an immovable property. Article 1592. In
A contract of loan involves a reciprocal obligation, wherein the the sale of immovable property, even though it may have
obligation or promise of each party is the consideration for been stipulated that upon failure to pay the price at the time
that of the other. It is a basic principle in reciprocal obligations agreed upon the rescission of the contract shall of right take
that neither party incurs in delay, if the other does not comply place, the vendee may pay, even after the expiration of the
or is not ready to comply in a proper manner with what is period, as long as no demand for rescission of the contract
has been made upon him either judicially or a notarial
incumbent upon him. Only when a party has performed his
act.After the demand, the court may not grant him a new term.
part of the contract can he demand that the other party also Article 1592 requires the rescinding party to serve judicial or
fulfills his own obligation and if the latter fails, default sets in. notarial notice of his intent to resolve the contract.
DECISION: Article 1191. The power to rescind obligations is implied in
reciprocal ones, in case one of the obligors should not comply
The payment of amortization should accrue from the time with what is incumbent upon him. The injured party may
BPIIC released the loan amount to ALS and Litonjua because choose between the fulfillment and the rescission of the
it was only at that time (the delivery of the amount -- the obligation, with payment of damages in either case. He may
object of the contract) that the loan contract was perfected. also seek rescission, even after he has chosen fulfillment, if
the latter should become impossible. The court shall decree
Iringan v. Court of Appeals the rescission claimed, unless there be just cause authorizing
G.R. No. 129107, the fixing of a period.
September 26, 2001,
366 SCRA 41 This is understood to be without prejudice to the rights of third
persons who have acquired the thing, in accordance with
FACTS: articles 1385 and 1388 and the Mortgage Law.

Private respondent Antonio Palao sold to petitioner Alfonso But in our view, even if Article 1191 were applicable, petitioner
Iringan, an undivided portion of Lot No. 992 of the would still not be entitled to automatic rescission. In Escueta
Tuguegarao Cadastre, located at the Poblacion of v. Pando, we ruled that under Article 1124 (now Article 1191)
Tuguegarao and covered Transfer Certificate of Title No. The of the Civil Code, the right to resolve reciprocal obligations, is
parties executed a Deed of on the same date with the deemed implied in case one of the obligors shall fail to comply
with what is incumbent upon him. But that right must be Yes. The reasons or grounds for cancelling the contract are
invoked judicially. The same article also provides: The Court valid and justified. Both the trial court and the public
shall decree the resolution demanded, unless there should be respondent erred in the appreciation of the nature of the
grounds, which justify the allowance of a term for the transaction between the petitioner corporation and the private
performance of the obligation. This requirement has been respondent. To this Court’s mind, what obtains in the case at
retained in the third paragraph of Article 1191, which states bar is a mere contract to sell or promise to sell, and not a
that the court shall decree the rescission claimed, unless
contract of sale.
there be just cause authorizing the fixing of a period.
The injured party may choose between the fulfillment and the
Consequently, even if the right to rescind is made available to rescission of the obligation, with the payment of damages in
the injured party, the obligation is not ipso facto erased the either case. He may also seek rescission, even after he has
failure of the other party to comply with what is incumbent chosen fulfillment, if the latter should become impossible. The
upon him. The party entitled to rescind should apply to the Civil Code provides:
court for a decree of rescission.The right cannot be exercised Article 1593. With respect to movable property, the rescission
solely on a own judgment that the other committed a breach of the sale shall of right take place in the interest of the
of the obligation.The operative act which produces the vendor, if the vendee, upon the expiration of the period fixed
resolution of the contract is the decree of the court and not the for the delivery of the thing, should not have appeared to
mere act of the vendor. Since a judicial or notarial act is receive it, or, having appeared, he should not have tendered
required law for a valid rescission to take place, the letter the price at the same time, unless a longer period has been
written respondent declaring his intention to rescind did not stipulated for its payment.
operate to validly rescind the contract. Article 1191. The power to rescind obligations is implied in
reciprocal ones, in case one of the obligors should not comply
Visayan Sawmill V CA with what is incumbent upon him.
In this case, there was to be no actual sale until the opening,
G.R. No. 83851 (March 3, 1993) making or indorsing of the irrevocable and unconditional LOC.
FACTS: Since what obtains here is a mere promise to sell, RJH’s
On May 1, 1983, RJH Trading and Visayan Sawmill Company failure to comply with the positive suspensive condition cannot
(VSC) entered into a sale involving scrap iron located at even be considered a breach casual or serious but simply an
VSC’s stockyard at Negros Oriental, subject to the condition event that prevented the obligation of petitioner corporation to
that RJH will open a Letter of Credit (LOC) of P250,000 in convey title from acquiring binding force. Consequently, the
favor of VSC on or before May 15, 1983. This is evidenced by obligation of the petitioner corporation to sell did not arise; it
a contract entitled `Purchase and Sale of Scrap Iron’ duly therefore cannot be compelled by specific performance to
signed by both parties. On May 17, 1983, RJH through his comply with its prestation. In short, Article 1191 of the Civil
men started to dig and gather and scrap iron at the VSC’s Code does not apply; on the contrary, pursuant to Article 1597
premises, proceeding until May 30 when VSC allegedly of the Civil Code, the petitioner corporation may totally
directed RJH’s men to desist from pursuing the work in view rescind, as it did in this case, the contract.
of an alleged case filed against RJH by Alberto Pursuelo. VSC
denied this, alleging that on May 23, 1983, they sent a
telegram to RJH cancelling the contract of sale because of the
failure of the latter to comply with the conditions thereof. On
May 24, 1983, RJH informed VSC that the LOC was opened
May 12, 1983 at BPI main office in Ayala, but then the
transmittal was delayed.
On May 26, 1983, VSC received a letter advice from BPI
Dumaguete stating that an irrevocable domestic LOC
P250,000 was opened in favor of Ang Tay c/o VSC on
account of Armaco-Armsteel Alloy Corporation. On July 19,
1983, RJH Trading sent a series of telegrams stating that the
case filed against him by Pursuelo had been dismissed and
demanding that VSC comply with the deed of sale, otherwise
a case will be filed against them. On July 20, 1983, VSC
informed RJH that they were unwilling to continue with the
sale due to RJH’s failure to comply with essential pre-
conditions of the contract. On July 29, 1983, RJH filed the
complaint, praying for judgment ordering VSC to comply with
the contract by delivering to him the scrap iron subject
thereof. VSC insisted that the cancellation of the contract was
justified because of RJH’s noncompliance with essential pre-
conditions. The RTC ruled in RJH’s favor. The CA affirmed.
Hence, this appeal.
ISSUE:
Whether or not the reasons or grounds for cancelling the
contract valid and justified.
RULING:

Potrebbero piacerti anche