WP -ENG-EXE-17- R0
Scope Allocable for all Granite and Marble flooring and cladding works
a) The slabs/ tiles shall be stacked on edges on regular platforms under cover.
During unloading, care shall be exercised to avoid breakage.
e) The material received at site shall be checked as per Inspection plan IP-ENG-
EXE-17
f) Marble / granite tiles of same type but with distinctly different color or texture
shall be rejected outright.
Procedure
g) Ensure that the laying surface is cleaned. Remove any loose concrete, mortar
or other substances.
h) All chasing for the concealed piping and electrical conducting etc. shall be
carried out before commencement of work.
k) Ensure that the marble / granite tiles to be laid are matched, numbered and
available in the required number for laying on the site.
l) Marble / Granite are dry matched, they are then cut to the exact size
required, and numbered in the sequence and are laid at site in exactly the
same order.
m) For marble works, coat the bottom with sealant before laying. It is good
practice to seal the top also after laying and polishing. This is done due to
a) As per drawing, work should be started by taking right angles for existing
walls.
g) Putty blade is used to rake all joints and fill the joint material neatly as the
Procedure joints will be paper joints.
h) For fixing marble / granite tiles to wall, suitable stainless steel mechanical
anchors shall be used.
a) All surfaces & edges, which will remain exposed after installation, shall be
polished.
b) Cure all tiling works and joint filling works for 3 days.
c) After work is complete, ensure that it is covered with plastic sheet and Plaster
of Paris.
a) Trowels
b) Line dori
c) Tube levels
d) Plumb bobs
e) Measurement Tape
f) Spirit levels 1-2m
g) Sand sieve
h) Aluminum straight edge
i) Right angle
j) Chipping Tools
k) Masons hammer
l) Rubber hammer
m) Leveling threads
n) Tile cutter
o) Angle grinder
p) Masons brushes and buckets
q) Mortar boxes
Procedure
17.5 Inspection methodology for quality assurance
d) Ensure the cement and the sand have been checked / tested prior to tiling.
e) Ensure that the granite / marble is not broken / cracked and joints are well
filled. In case of cracks near the edges, these cracks to be filled using epoxy
compound.
f) After joint filing, ensure that joints are made even using an angle grinder.
g) Tap the tiled surface to check for hollowness. The tiled surface should be
covered with POP and tarpaulin sheets to prevent damage to the tiled
surface.
Process Output Granite / Marble checklist, Material test certificates and Material Inspection report