Delayed on the timeline and milestone MEPFS and Architectural Plan must be
given in the specific area. A lot of incorporated as one since there are a
changes on ducting works and chipping lot of conflict within the plan.
works was made during this conflict
between MEPFS and Architectural.
Chipping works and Tapping on the Survey points and Structural plan are
corbel support since Escalator cannot not followed based on the given plan
be installed on the opening as per by Escalator equipment. Double
actual vs as per plan. Delayed on the checking on the plot points and
installation, manpower distribution on coordination between Structural,
chipping and tapping works. Surveryor and Supplier of the
equipment to provide accurate data
for the dimension of opening
Revision on ducting works providing Based on plan given haunch beam and
Site Instrcution. Delayed on project as per actual condition the haunch
timeline for the specific area and beam was not placed on correct
unusable of the haunch beam location. Structural, TSD and Operation
to coordinate with each other prior
from forming the haunch beam to be
used in MEPFS utility
Delayed installation on escalator that cause subcontractor to raise the concern
Damage ceiling and Chipping works on RFI to consultant all the FCU drain line
walls and tiles (Reworks) due to provision and its tapping point
delayed release of FCU Plan and especially on toilets
Shopdrawings for approval on other
areas not given in the plan
Reworks on ile
Coordinate with TSD to double check
Drop ceiling on hallway due to utility on IFC and use on haunch beam on
conflicts that cause delay and changes crossmain on low ceiling elevation
on utility installation