Sei sulla pagina 1di 4

PROJECT NAME SCOPE ISSUES

Vibration Isolation Spring on CHW/COW Pumps

CITP- MALL Mechanical

Ceiling elevation at Fashion Walk (2nd Floor) and


Wellness Area (3rd Floor)

CITP- MALL Mechanical

Cooling Tower Design Issue

CITP- MALL Mechanical

AHU Equipment and AHU Room provision at


Fashion Walk

CITP- MALL Mechanical

Escalator not feasible on the actual Escalator


Opening provided by Sturctural

CITP- MALL Mechanical

Structural haunch beam at Activity Center


conflict with Ducting and Ceiling Elevation

CITP- MALL Mechanical

Escalator Pit/Pump at Ground Floor Zone 3 in are


CITP- MALL Mechanical not in the same orientation with the equipment

Make up water pump/Bladder Tank provision for


CITP- MALL Mechanical Cooling Tower water supply
CITP- MALL Mechanical Elevator Opening at Service Elevator
CITP- MALL Mechanical Conflict water supply provision on the LPG Tank
Farm

CITP- MALL Mechanical

Excessive sizes on the blackout provided


CITP- MALL Mechanical Mechanical Equipment and its Electrical
provision

CITP- MALL Mechanical

FCU Drain plan at CITP Mall


Combi Fan dimension and its provision
CITP- MALL Mechanical (Structural) at Basement Level
Ball valve stoled on CHWS/R at 2nd Floor AHU
CITP- MALL Mechanical Room
Roofdeck waterproofing and zocalo on Ducting
pentration on slab
CITP- MALL Mechanical

Thermostat of FCU and Room switch location


CITP- MALL Mechanical conflict with Architectural
Dropwall conflict with plumbing utility and
CITP- MALL Mechanical ducting provision (blackout)

Ceiling elevation at Hallway GF to 3F typical


CITP- MALL Mechanical conflict with MEPFS Utilities
CITP- MALL Mechanical VFD and Pump Motor Electrical Specification

CITP- MALL Mechanical

CHWP Pumps storage after delivery


CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
CITP- MALL Mechanical
IMPACT ON PROJECT SITE RESOLUTION/LEARNINGS
Vibration Isolation cannot withstand The design of spring isolation should
the Load of Pump and Inertia Base that consider the pump/motor and inertia
cause irregular noise on pumps base. Secure approval from the
simulation. Also, time was wasted since designer for the reccommended spring
mall started to operate. to be installed on site.

Delayed on the timeline and milestone MEPFS and Architectural Plan must be
given in the specific area. A lot of incorporated as one since there are a
changes on ducting works and chipping lot of conflict within the plan.
works was made during this conflict
between MEPFS and Architectural.

Chiller Operation surges on the Request information from the


condenser side while using 2-3 Chiller consultant since it release new
and Full Load of AHU's/FCU's which Construction Bulletin for the system
cause the Equipment to shutdown due without incorporating the Cooling
to entering and leaving temperature Tower previous design
exceeds to its design temperature level.

Site Instruction of MEPFS Subcontractor Secure a dimension of the equipment


(ICPWI, KALAYAAN and FR Sevilla) and to incorporate with the room provision
delayed in finishing the room since the to check whether the layout is
AHU Equipment Dimension was too convienient
large for the room provision and other
utilities inside was affected.

Chipping works and Tapping on the Survey points and Structural plan are
corbel support since Escalator cannot not followed based on the given plan
be installed on the opening as per by Escalator equipment. Double
actual vs as per plan. Delayed on the checking on the plot points and
installation, manpower distribution on coordination between Structural,
chipping and tapping works. Surveryor and Supplier of the
equipment to provide accurate data
for the dimension of opening

Revision on ducting works providing Based on plan given haunch beam and
Site Instrcution. Delayed on project as per actual condition the haunch
timeline for the specific area and beam was not placed on correct
unusable of the haunch beam location. Structural, TSD and Operation
to coordinate with each other prior
from forming the haunch beam to be
used in MEPFS utility
Delayed installation on escalator that cause subcontractor to raise the concern

Cause leak on roofdeck due to excess Coordinate with Structural Engineer


blackout dimension and rectification on PM/PIC for the exact dimension
slab topping works (offset) for the installation of the utility
and topping works

Damage ceiling and Chipping works on RFI to consultant all the FCU drain line
walls and tiles (Reworks) due to provision and its tapping point
delayed release of FCU Plan and especially on toilets
Shopdrawings for approval on other
areas not given in the plan

Leaking on roofdeck with waterproofing Coordinate with PM/PIC applying


applied due to construction materials waterproofing and then topping works
placed after waterproofing that can including the zocalo (clean the area)
cause damage

Reworks on ile
Coordinate with TSD to double check
Drop ceiling on hallway due to utility on IFC and use on haunch beam on
conflicts that cause delay and changes crossmain on low ceiling elevation
on utility installation

Damage on Pumps/Motr due to storage Provide temporary storage with


after delivery where it was covered roofing to protect equipment from
with blue sack only located at roofdeck having damage and prevent any
trouble prior to installation and testing

Potrebbero piacerti anche