PROJECT:

2 X 660 MW SUPERCRITICAL THERMAL POWER PROJECT (STAGE- I)


FICHTNER Consulting Engineers (India)

Krishnapatnam, Nellore (Dist), Andhra Pradesh Private Limited, (FI) Chennai.


VENDOR DRAWING REVIEW STATUS

AGREEMENT NO.: TPCIL/BTG/SPA200910o Action - I Approved


o Action - II Approved except as noted on drawing. Revise
drawing and resubmit for records.
o Action - III Returned with Comments. Resubmit for approval.
OWNER: o Action - IV Rejected
o Action - V Information received.

THERMAL POWERTECH CORPORATION INDIA LIMITED o Action - VI Information noted Retained for reference and records.
This document has been reviewed as noted with regard to general
conformity with the Contract specifications and requirements. The Vendor /

Hyderabad, India Contractor is responsible for correctness of design calculation and details.
Approval of this document does not relieve the Vendor / Contractor of his
responsibility in carrying out the work correctly and fulfilling the complete
requirements of the contract nor does it limit the purchaser's rights under the
contract.

FI Letter Ref. No. Date:

OWNER’s ENGINEER : CNT 1109171/ PM-6.1/940/1721 05.02.2016

FICHTNER Consulting Engineers (India) Private Limited


Signature Initials: AS

Chennai, India

BTG CONTRACTOR:
DONGFANG ELECTRIC CORPORATION LIMITED
Chengdu, China

Sub Contractor:
Northwest Electric Power Institute Of Commissioning
Xian, China

Document Title:
P e r f o r ma n c e Te s t P ro c e d u re
( B O I L E R E F FI C I E N C Y )

Document No.: DECL-TPCIL-PGT-001 Rev.

Owner’s Doc. No.:


3
DECL’s Doc. No.:

Feb. 4
3 李建 郁翔 王永庆 苏耕
2016
Dec. 29
2 李建 郁翔 王永庆 苏耕
2015

July1 2015 1 李建 吴鹏举 王永庆 苏耕

Nov.4 2014 0 李建 吴鹏举 王永庆 苏耕

Date Rev Prepared by Checked by Reviewed by Approved by Details of Rev


Performance Test Procedure (Boiler efficiency) Rev. 3

Appendix AA:

锅炉效率性能试验程序
Performance Test Procedure
( BOILER EF FICIENCY )

DECL-TPCIL-PGT-001 1 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

1. 前言 Preface
印度科瑞希纳 2×660MW 超临界燃煤电站项目由东方电气股份有限公司( DECL ) 作为
BTG 设备供货方,供货范围包括锅炉及辅机、汽轮机及辅机、发电机及辅机。其中,锅炉、
汽机、发电机由其下属的子公司生产。该电站 1 号机组计划于 2014 年 2 月进入商业运行,2
号机组计划于 2014 年 5 月进入商业运行。由 DECL 在商业运行后 6 个月内进行性能考核试验。
锅炉为超临界参数变压直流炉、一次再热、平衡通风、半露天布置、固态排渣、全钢构
架、全悬吊结构 Π 型锅炉。
DongFang Electric Company Ltd. ( DECL ), as the BTG supplier of Indian Krishnapatnam
2×660MW Super Critical Coal-fired Power Plant Project, supplied the boiler and auxiliaries, steam
turbine and auxiliaries and generator and auxiliaries. Thereinto, the boiler, turbine and generator are
manufactured by the subcompany of DECL. The unit No.1 was scheduled into COD in Feb. 2014
and the unit No.2 was scheduled into COD in May 2014. The performance test will be conducted
by DECL within 6 months after COD separately.
The boiler is a supercritical pressure once-through boiler with the characteristics of single
reheat, balanced draft, semi-outdoor arrangement, dry bottom ash extraction, full steel structure,Π
type and full suspension construction
1.1 锅炉主要参数 Main parameters of boilers
锅炉主要参数(最终与汽轮机的参数相匹配,主要数据见表 1。
Boiler main parameters match the parameters of the steam turbine, Boiler main parameters
are shown in the following Table1.
表1 锅炉主要设计参数
Table 1: Boiler Main Parameters
项目 锅炉主要参数 单位 数值
Item Boiler main parateters Unit Data
蒸汽流量(BMCR/TMCR)
t/h 2105/1900
Boiler Maximum Continuous Rating (BMCR)
过热蒸汽 蒸汽压力(BMCR/TMCR)
MPa(g) 25.5/25.26
Main steam Steam pressure (BMCR/TMCR)
蒸汽温度(BMCR/TMCR)
℃ 570
Steam temperature (BMCR//TMCR)
再热 蒸汽流量(BMCR//TMCR)
t/h 1649/1556
蒸汽 Steam flow (BMCR//TMCR)
Reheated 进口蒸汽压力(BMCR/TMCR)
Mpa(g) 4.94/4.67
steam Inlet steam pressure (BMCR/TMCR)
DECL-TPCIL-PGT-001 2 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

出口蒸汽压力(BMCR/TMCR)
Mpa(g) 4.72/4.47
Outlet steam pressure (BMCR/TMCR)
进口蒸汽温度(BMCR)
℃ 330/324
Inlet steam temperature (BMCR/TMCR)
出口蒸汽温度(BMCR/TMCR)
℃ 603/601
Outlet steam temperature (BMCR)
给水温度(BMCR//TMCR)
℃ 287/283
Feed water temp. (BMCR//TMCR)
注: Notes:
(1)压力单位中“g” 表示表压。 “a” 表示绝对压(以后均同)。In the pressure unit, "g"
means relative pressure and "a" means absolute pressure. (The same below)
1.2 设计煤质 Design coal
锅炉设计煤种如 2 表所示。Design coal data is shown in the table 2.
表2 锅炉设计煤种 Table 2 Design coal
最优煤 最差煤种
符号 设计煤种
单位 种 Worst
Symb Design
名称 Unit Best coal
ol coal
Item coal
收到基碳
Car % 42 45 35
Received based carbon
收到基氢
Har % 3.5 4.2 3
Received based hydrogen
收到基氧
Oar % 10.5 11.1 10.5
Received based oxygen
收到基氮
Nar % 1 1 1.4
Received based nitrogen
收到基硫
Sar % 0.5 0.7 0.5
Received based sulfide
全水分
Mar % 8.5 12.0 8.5
Received based water
灰分
Aar % 34 26 41
Received based ash
挥发份(收到基)
Vdaf % 23 27 22
Received based volatile
高位发热量(收到基)
Q HHV Kcal/kg 4135 4620 3300
GCV
哈氏可磨系数
HGI 45 55 45
HGI

1.3 水文气象条件如表 3 所示。Hydrologic and weather conditions are shown in the table 3.
DECL-TPCIL-PGT-001 3 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

表3 水文气象条件
Table 3:Hydrologic and weather conditions
序号 项 目 单位 特征值
SN Items Unit Data
最高干球温度
1 ℃ 42.2
Maximum dry-bulb temperature
最低干球温度
2 ℃ 18.3
Minimum dry-bulb temperatur
3 日平均气温(最高) ℃ 33
Daily average temperature (max.)
4 日平均气温(最低) ℃ 24.4
Daily average temperature (min.)
5 最大相对湿度 % 84
Maximum relative humidity
6 最小相对湿度 % 46
Minimum relative humidity
7 最大风速 m/s 50
Maximum wind velocity
8 多年平均降水量 mm 1100
Average annual precipitation

2. 试验目的 Purpose
检验与考核锅炉的各项技术经济指标是否达到合同、设计的要求。
To Check and verify whether the performance value of the boilers satisfy the requirement of the
Contract and design.

3. 试验依据 Test guidelines


3.1 试验按照合同要求进行。
The test shall be conducted pursuant to the requirements of the Contract.
3.2 试验依据 ASME PTC 4-2008《锅炉机组性能试验规程》的有关规定执行。
Test is conducted pursuant to related stipulations of ASME PTC 4-2008

4. 试验项目 Test items


4.1 锅炉效率。
Boiler efficiency.

5. 测点布置、测量项目及方法

DECL-TPCIL-PGT-001 4 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Layout of test points, test items and methods


5.1 氧量和烟气温度:用烟气分析仪和 E 型热电偶在空气预热器前后测点采用网格法进
行测量,每个烟道截面网格密度不小于 12×3。烟气含氧量和排烟温度在试验期间
连续测量。最终计算采用试验期间数据的算术平均值。
Oxygen and flue-gas temperature: measurement is made through the grid method with
flue gas analyzer and Type E thermocouple at the test points in the front and back of air
pre-heater with the grid density in each flue duct section not less than 12×3. During the
test, oxygen content and flue-gas temperature adopts the continuous measurement method.
The average value of measurement data will be used for the calculation.
5.2 空预器进、出口空气温度:采用表盘显示值,10~15 分钟记录一次。
Air temperature at inlet and outlet of air pre-heater: adopt the value displayed on the dial,
which is recorded at an interval of 10~15 minutes.
5.3 原煤取样:在给煤机入口落煤管每台磨每 30~40 分钟取样一次,每次采集 1~2 公
斤,封存。
Raw coal sampling: sampling is taken at inlet of coal feeder at an interval of 30~40
minutes, with 1~2 kilos for each time. The coal sampling should be Sealed and kept
properly..
5.4 給煤量采用给煤机电子皮带秤显示值。
The coal feeding quantity adopts the value displayed on the coal feeder.
5.5 石子煤取样:在试验前清空每台磨煤机的石子煤箱,每个试验工况取样一次,试验
结束后对每台磨煤机的石子煤进行称重并取样测量石子煤发热量。
Mill rejects sampling: before the test to empty coal rejects bin and taking sampling one
time for each test. To weigh the mill rejects and test its GCV after test completion.
5.6 飞灰取样:安装飞灰取样器(预热器出口烟道 2 个)取样,试验期间连续取样。
Fly ash sampling: install the fly ash samplers ( 2 pcs) at outlet of air pre-heater ) with
the continuous sampling during the test.
5.7 渣样:在排渣口取样,取一次。
Bottom ash: One time sampling to be taken at the discharge point
5.8 环境条件:在风机入口附近用干湿球温度计测量干湿温度,用电子微压计测量大气
压力,每 30 分钟记录一次。

DECL-TPCIL-PGT-001 5 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Environment conditions: Measure the dry bulb temperature and the wet bulb temperature
with the related thermometer and measure the pressure atmosphere with Electronic
micromanometer at the suction area of the FD fan with an interval of 30 minutes.

5.9 给水、主蒸汽、减温水流量、一、二次风量:采用 DCS 数据每 5 秒钟记录一组。


Feed water flow, main steam flow and desuperheating water flow, primary air flow,
forced draft air flow: recorded by DCS with an interval of 5 seconds .
5.10 金属壁温监测:采用 DCS 数据每 5 秒钟记录。
Measurement of metal tube wall temperature: recorded by DCS with an interval of 5
seconds.

5.11 按照试验工程师要求,由运行人员记录相关运行参数,每 15 分钟记录一次。实验


表格由试验工程师实验前提供。
The related operation data will be recorded by the operators according to the requirement
of DECL test engineers with an interval of 15 minutes. The record form will be issued
by the test engineers before test.

6. 主要试验仪器 Main test instruments


试验使用主要仪表及器具见表 4,所有仪表均需经过有资质的第三方检验单位校验合格,
全部校验合格的试验用仪器和仪表均在试验期间处于校验有效期期内,并经业主方确认。

DECL-TPCIL-PGT-001 6 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

See the table 4 for the main instruments to be used during the test. All instruments shall be
calibricated by a competent third-party, and all the calibricated instruments to be used during
the test shall be within the period of validity and confirmed by the owner before the test.
Table 4:main test instruments
设备名称 数量 型号 测量范围 精度
Instrument Qty. Type Specification Precision class
烟气分析仪 O2 0-21%
2 MRU 0.5
Flue gas analyzer CO 0-1000ppm
热电偶 铠装(E 型)
56 (0-600)℃ I
Thermocouple E
电子微压计
1 EMP-6A 0-6000Pa 0.5
Electronic micromanometer
删除 deleted
通风干湿表
1 DHM2 (10%-100%)RH 0.5
wet and dry bulb thermometer

7. 性能考核指标及保证条件

Performance guarantee value and guarantee conditions


7.1 锅炉效率保证值为 86.5%。
Steam generator efficiency with following conditions ( Guarantee value 86.5% ):
● 100%TMCR
● Firing design coal
● On Gross Calorific value (GCV)basis
● Rated excess air
● At 27 deg.C DBT and 60%RH ambient air conditions
7.2 其它要求
Other requirements
7.2.1 试验所需各种仪器仪表、消耗性材料已准备就绪。各测点已安装完毕,经检查合格;
All instruments and consumable materials required during the test are all in readiness. All
test instruments are installed and qualified.
7.2.2 试验期间,燃用的设计煤种稳定,数量充足,应满足 15 天满负荷运行的需要。
During the test, the design coal should keep stability with sufficient quantity. The coal
quantity should be satisfy 15 days operation with the 100%TMCR condition.
● 高位发热量Q HHV 同设计值偏差在±162.7 kJ/kg 内。
Deviation of Gross Calorific Value from the design value: within ±162.7 kJ/kg

DECL-TPCIL-PGT-001 7 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

● 全水份 Mar 同设计值偏差为±0.25%


Deviation of total moisture (Mar) from the design value: ±0.25%
● 收到基碳 Car 同设计值偏差为±0.3%
Deviation of as-received basis carbon (Car) from the design value: ±0.3%
● 收到基灰份 Aar 同设计值偏差为±0.5%
Deviation of as-received basis ash content (Aar) from the design value: ±0.5%
7.2.3 锅炉参数稳定范围:Stability range of boiler parameters:
短期波动(峰谷差)
序号 名称 长期偏差
Short-term fluctuation
No. Item Long-term deviation
(valley-to-peak)
蒸汽压力
1 4% 3%
Steam pressure
蒸汽流量
2 4% 3%
Steam flow
蒸汽温度
3 20℉ 10℉
Steam temperature
省煤器出口O 2 量
4 O2 leaving boiler /economizer (by 1.0% 0.5%
volume)
过热器、再热器减温喷水流量
5 2%蒸发量 /
Superheat / reheat spray
燃料量
6 10% /
Fuel flow
给水温度
7 20℉ 10℉
Feed water temperature
7.2.4 煤粉细度达到设计值。
Fineness of coal dust meets the design values.
7.2.5 锅炉效率采用热损失法进行计算。
The heat loss method is adopted for calculating the boiler efficiency.
7.2.6 磨的组合方式根据现场实际情况由双方共同协商确定。
The coal mill combination will be finally determined and jointly agreed
according to the actual condition during PG test.
7.2.7 试验前 4 小时进行一次吹灰。
Soot blowing to be conducted prior to 4 hours of the test.
7.2.8 试验期间不吹灰、不打焦、不排污。
Without soot blowing, slagging removing and drainage during the test.

DECL-TPCIL-PGT-001 8 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

7.2.9 试验时不投油助燃。
Without oil support during the test.
7.2.10 锅炉保持工况稳定时间 4 小时。
Boiler shall maintain 4h stabilization operation under test condition during test .
7.2.11 试验期间运行人员在 DECL 的指令下进行机组操作。未得到指令,不得进行任何干
扰运行工况的操作。若遇到危及设备和人身安全的意外情况,运行人员有权按规程进
行紧急处理,并告之试验负责人暂停试验。
The operators can operate the unit under the supervision of DECL. Without the order of
DECL engineer, the operator should not be the abnormal operation which will affect the
test. In the event of emergencies case endangering the equipment and personal safety, the
operators have the right to take emergency measures according to the regulations, and
inform DECL engineers immediately.. DECL will make the decision to continue the test or
not.

8 试验步骤 Test steps


8.1 辅助性试验 Auxiliary test
8.1.1 在锅炉额定负荷下,分别在空气预热器进、出口烟道按等截面原则,每个烟道选取 12
×4 点,分析O 2 值以获得O 2 值分布场,并由此求出取样代表点。
During the Boiler Rated Load condition, 12×4 test points are selected at each flue
according to the equivalent area principle at the inlet/outlet flues of the air pre-heater; the
distribution field of O 2 values is taken by analyzing the O 2 values, so as to get the
representative point of the samples.
8.1.2 在锅炉额定负荷下,测出空气预热器出、入口烟道温度分布场(每个烟道 12×4 点),
并由此求出烟气温度测量代表点(每烟道 3 点)。
During the Boiler Rated Load condition, the temperature distribution field of the
inlet/outlet flues of the air pre-heater is measured (12×3 test points for each flue), so as to
get the representative point of the temperature measurement of flue gas (3 test points for
each flue).
8.2 预备性试验
Preparatory test
在正式试验前,按正式试验的要求,进行一次预备试验,其目的是:

DECL-TPCIL-PGT-001 9 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Prior to the official test, a preparatory test to be conducted in accordance with the
requirements of the official test. The purpose as follows:
8.2.1 确认所有测试仪表、仪器的可靠性与准确性,保证试验顺利进行。
To confirm the reliability and normality of all the test instruments to ensure the smooth
operating of the test.
8.2.4 培训试验人员的测试操作水平。
Train the operators involved in the test to enhance the test operations ability
8.2.5 对正式试验工况进行预验证。
Pre-test the performance guarantee value.
注意:如果预备性试验结束后,经考核试验双方共同确认,预备性试验的试验条件满
足正式试验的要求,将预备性试验作为正式试验处理。
Noted: After the completion of the preparatory test, if the test conditions of the preparatory
test satisfy the requirements of the official test and confirmed by the both parties,
the preparatory test can be treatedas the official test.
8.3 正式试验
Official test
8.2.1 试验前后各方签署锅炉性能试验工况认可书(见附录 A)。
Approval Document for the Performance Test Working Conditions of the Boilers shall be
signed by both parties before and after the test. (See appendix A)
8.2.2 正式试验前,锅炉机组应连续正常运行 3 天以上。正式试验前 12 小时中,前 9 小时
机组运行负荷不低于试验负荷的 75%。正式试验前 3 小时内,应保持预定的试验负荷。
Prior to the official test, the boiler shall keep running normally for 3 days. During the 12
hours before the official test, the operating load of the unit shall not be less than 75% of the
test load for the first 9 hours, and the test load shall be maintained for the latter 3 hours.
8.2.3 试验结束后,锅炉在试验工况下继续稳定运行 1 小时,以便进行试验工况的复核。
After the completion of the test, the boiler continues to run for 1 hour under the test
working conditions in order to review the test conditions.

9 数据处理

Data Processing
9.1 锅炉效率热损失法进行计算,并按标准和双方约定作出修正。
DECL-TPCIL-PGT-001 10 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Heat loss method is taken for calculating the boiler efficiency. Correction to be considered
according to PTC 4 and the agreement of both parties.
9.2 灰平衡比率
Ash balance ratio
炉底大渣份额 Proportion of bottom ash: 10%;
预热器出口飞灰 Portion of fly ash (air pre-heater outlet) 90%。
9.3 热效率试验进行两次,两次偏差应不大于 0.5%,否则应进行第三次试验。
The boiler efficiency test to be conducted two times.The test result is acceptable if the
deviation between them don’t exceed 0.5%.Otherwise,the third test shall be conducted.
9.4 锅炉效率的计算 Calculation of boiler efficiency
9.4.1 锅炉计算效率 Boiler calculated efficiency EFC:
EFC=1-THL %
Where:
THL- Total heat loss %
THL=QpLUbC+QpLDFg+QpLWF+QpLH 2 F+QpLWA+QrLSrc+QpLCO+QpLRs+QpLRa+
QpLPr+QpLALg+QpLNOx+ QpLUN %
Where:
QpLUbC- 灰渣中未燃碳热损失 Heat loss due to unburned carbon in ash %
QpLDFg – 干烟气热损失 Heat loss due to dry gas %
QpLWF –燃料中水分热损失 Heat loss due to moisture in coal %
QpLH 2 F-燃料中H 2 燃烧生成水热损失Heat loss due to H 2 O from combustion of H 2 %
QpLWA-空气中水分热损失 Heat loss due to moisture in air %
QrLSrc –表面辐射与对流热损失 Heat loss due to surface radiation & convection %
QpLCO –烟气中 CO 热损失 Heat loss due to carbon monoxide in flue gas %
QpLRs – 底渣显热热损失 Heat loss due to sensible heat in bottom ash %
QpLRa –飞灰显热热损失 Heat loss due to sensible heat in fly ash %
QpLPr- 磨煤机排出石子煤热损失 Heat loss due to pulverizer rejects %
QpLALg- 漏风引起热损失 Heat loss due to air infiltration loss %
QpLNOx- 形成 NOx 引起的热损失 Heat loss due to NOx formation loss %
QpLUN –不确定热损失 Unaccountable loss %

DECL-TPCIL-PGT-001 11 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

9.4..2 修正后锅炉效率 Corrected Boiler efficiency EF:


EF=EFC+TCV %
Where:
TCV-Total corrected value %
TCV=HHVFC+EADC+CMDC+CHDC+CACDC+ATDC+MIADC+PCFD+FTDC+FGTDC
%
Where:
HHVFC----煤质高位发热量偏差修正 Correcting due to HHVF deviation %
EADC-----过量空气系数偏差修正 Correcting due to excess air deviation %
CMDC-----燃料全水分偏差修正 Correcting due to coal moisture deviation %
CHDC-----燃料氢含量偏差修正 Correcting due to coal hydrogen deviation %
CACDC-----煤的灰分修正 Correcting due to coal ash content deviation %
ATDC----环境温度偏差修正 Correcting due to ambient temperature ( air temperature of APH
inlet ) deviation %
MIADC----空气中水分含量偏差修正 Correcting due to moisture in air deviation %
PCFD----煤粉细度偏差修正 Correcting due to pulverized coal fineness deviation %
FTDC----给水温度偏差修正 Correcting due to feedwater temperature deviation %
FGTDC----空气预热器出口烟温修正 Correcting due to the flue gas temperature at APH
outlet %
9.5 DEC will perform post-test uncertainty analysis according to PTC.

DECL-TPCIL-PGT-001 12 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

附录 A Appendix A
锅炉性能试验工况认可书
Approval Document for the Performance Test Working Conditions of the Boilers
业主: Owner:
锅炉试验机组:印度科瑞希纳 2×660MW 超临界燃煤电站 号机组
Boiler test unit:No. Unit for Indian Krishnapatnam 2×660MW Super Critical Coal-fired
Power Plant
试验地点 Location for test::
试验工况 Test working conditions: 试验日期 Test date:
制造厂:DONGFANG BOILER GROUP CO., LTD.
1.锅炉机组的系统及运行状态满足试验条件;
The boiler system and operating state meet the test conditions;
2.试验用仪器、仪表已全部经过校验合格、工作正常、有效,可以用于
本次试验;
All instruments and meters required by the test are all checked and qualified
试验开始确认 after verification, suitable for this test;
Confirmation 3.试验人员全部到位,能够胜任试验工作;
at start time of All staff involved in the test are in readiness and qualified to conduct this test;
the test 4.各方均同意开始进行试验。
Various parties agree to undertake this test.
试验开始时间:Start time of the test:
确认签字:Confirmed by signature:
业主:Owner: 制造厂家:Manufacturer:
DEC:
1.试验时间满足试验要求;
The test time meets the test requirements;
2.试验数据完整、准确、真实、有效。各方均保留一份原始数据文件一
试验结束确认
套备案;
The data of the test is complete, accurate, true and effective. Various parties
maintain one document of original data for records;

DECL-TPCIL-PGT-001 13 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

3.各方均同意结束本次试验测试。
Various parties agree to complete this test
试验结束时间:End time of the test:
确认签字:Confirmed by signature:
业主:Owner: 制造厂家:Manufacturer:
DEC:

DECL-TPCIL-PGT-001 14 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

附录 B DCS 存盘清单

Appendix B List of DCS format storage


点号 名称(中文) 名称(英文)
point ID Name(chinese) Name(english)
发电机有功功率 LOAD of generators
10HFC10AD001CE A 磨煤机电流 MILL A CURRENT
10HFY01AI003 A 给煤机瞬时煤量反馈信号 COAL FEEDER A FEEDING RATE FEEDBACK
10HFE51CF101 磨煤机 A 入口一次风风量 1 MILL A INLET PA FLOW 1
10HFE51CP101 磨煤机 A 入口一次风压力 MILL A INLET PA PRESS.
10HFE51CF102 磨煤机 A 入口一次风风量 2 MILL A INLET PA FLOW 2
10HFC10CT301 A 磨煤机分离器出口温度 1 MILL A CLASSIFIER OUTLET TEMP.1
10HFC10CT304 A 磨煤机分离器出口温度 4 MILL A CLASSIFIER OUTLET TEMP.4
10HFC10CT302 A 磨煤机分离器出口温度 2 MILL A CLASSIFIER OUTLET TEMP.2
10HFC10CT305 A 磨煤机分离器出口温度 5 MILL A CLASSIFIER OUTLET TEMP.5
10HFC10CT303 A 磨煤机分离器出口温度 3 MILL A CLASSIFIER OUTLET TEMP.3
10HFC10CT306 A 磨煤机分离器出口温度 6 MILL A CLASSIFIER OUTLET TEMP.6
10HFE51CT101 磨煤机 A 入口一次风温度 1 MILL A INLET PA TEMP. 1
10HFE51CT102 磨煤机 A 入口一次风温度 2 MILL A INLET PA TEMP. 2
10HFC20AD001CE B 磨煤机电流 MILL B CURRENT
10HFY02AI003 B 给煤机瞬时煤量反馈信号 COAL FEEDER B FEEDING RATE FEEDBACK
10HFE52CF101 磨煤机 B 入口一次风风量 1 MILL B INLET PA FLOW 1
10HFE52CP101 磨煤机 B 入口一次风压力 MILL B INLET PA PRESSURE.
10HFE52CF102 磨煤机 B 入口一次风风量 2 MILL B INLET PA FLOW 2
10HFC20CP103 B 磨煤机分离器出口压力 MILL B CLASSIFIER OUTLET PRESSURE
10HFC20CT301 B 磨煤机分离器出口温度 1 MILL B CLASSIFIER OUTLET TEMP.1
10HFC20CT304 B 磨煤机分离器出口温度 4 MILL B CLASSIFIER OUTLET TEMP.4
10HFC20CT302 B 磨煤机分离器出口温度 2 MILL B CLASSIFIER OUTLET TEMP.2
10HFC20CT305 B 磨煤机分离器出口温度 5 MILL B CLASSIFIER OUTLET TEMP.5
10HFC20CT303 B 磨煤机分离器出口温度 3 MILL B CLASSIFIER OUTLET TEMP.3
10HFC20CT306 B 磨煤机分离器出口温度 6 MILL B CLASSIFIER OUTLET TEMP.6
10HFE52CT101 磨煤机 B 入口一次风温度 1 MILL B INLET PA TEMP. 1
10HFE52CT102 磨煤机 B 入口一次风温度 2 MILL B INLET PA TEMP. 2
10HFC30AD001CE C 磨煤机电流 MILL C CURRENT
10HFY03AI003 C 给煤机瞬时煤量反馈信号 COAL FEEDER C FEEDING RATE FEEDBACK
10HFE53CF101 磨煤机 C 入口一次风风量 1 MILL C INLET PA FLOW 1
10HFE53CP101 磨煤机 C 入口一次风压力 MILL C INLET PA PRESSURE.
10HFE53CF102 磨煤机 C 入口一次风风量 2 MILL C INLET PA FLOW 2
10HFC30CP103 C 磨煤机分离器出口压力 MILL C CLASSIFIER OUTLET PRESSURE
10HFC30CT301 C 磨煤机分离器出口温度 1 MILL C CLASSIFIER OUTLET TEMP.1
10HFC30CT304 C 磨煤机分离器出口温度 4 MILL C CLASSIFIER OUTLET TEMP.4
10HFC30CT302 C 磨煤机分离器出口温度 2 MILL C CLASSIFIER OUTLET TEMP.2
10HFC30CT305 C 磨煤机分离器出口温度 5 MILL C CLASSIFIER OUTLET TEMP.5
DECL-TPCIL-PGT-001 15 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

10HFC30CT303 C 磨煤机分离器出口温度 3 MILL C CLASSIFIER OUTLET TEMP.3


10HFC30CT306 C 磨煤机分离器出口温度 6 MILL C CLASSIFIER OUTLET TEMP.6
10HFE53CT101 磨煤机 C 入口一次风温度 1 MILL C INLET PA TEMP. 1
10HFE53CT102 磨煤机 C 入口一次风温度 2 MILL C INLET PA TEMP. 2
10HFC40AD001CE D 磨煤机电流 MILL D CURRENT
10HFY04AI003 D 给煤机瞬时煤量反馈信号 COAL FEEDER D FEEDING RATE FEEDBACK
10HFE54CF101 磨煤机 D 入口一次风风量 1 MILL D INLET PA FLOW 1
10HFE54CP101 磨煤机 D 入口一次风压力 MILL D INLET PA PRESSURE.
10HFE54CF102 磨煤机 D 入口一次风风量 2 MILL D INLET PA FLOW 2
10HFC40CP103 D 磨煤机分离器出口压力 MILL D CLASSIFIER OUTLET PRESSURE
10HFC40CT301 D 磨煤机分离器出口温度 1 MILL D CLASSIFIER OUTLET TEMP.1
10HFC40CT304 D 磨煤机分离器出口温度 4 MILL D CLASSIFIER OUTLET TEMP.4
10HFC40CT302 D 磨煤机分离器出口温度 2 MILL D CLASSIFIER OUTLET TEMP.2
10HFC40CT305 D 磨煤机分离器出口温度 5 MILL D CLASSIFIER OUTLET TEMP.5
10HFC40CT303 D 磨煤机分离器出口温度 3 MILL D CLASSIFIER OUTLET TEMP.3
10HFC40CT306 D 磨煤机分离器出口温度 6 MILL D CLASSIFIER OUTLET TEMP.6
10HFE54CT101 磨煤机 D 入口一次风温度 1 MILL D INLET PA TEMP. 1
10HFE54CT102 磨煤机 D 入口一次风温度 2 MILL D INLET PA TEMP. 2
10HFC50AD001CE E 磨煤机电流 MILL E CURRENT
10HFY05AI003 E 给煤机瞬时煤量反馈信号 COAL FEEDER E FEEDING RATE FEEDBACK
10HFE55CF101 磨煤机 E 入口一次风风量 1 MILL E INLET PA FLOW 1
10HFE55CP101 磨煤机 E 入口一次风压力 MILL E INLET PA PRESSURE.
10HFE55CF102 磨煤机 E 入口一次风风量 2 MILL E INLET PA FLOW 2
10HFC50CT301 E 磨煤机分离器出口温度 1 MILL E CLASSIFIER OUTLET TEMP.1
10HFC50CT304 E 磨煤机分离器出口温度 4 MILL E CLASSIFIER OUTLET TEMP.4
10HFC50CT302 E 磨煤机分离器出口温度 2 MILL E CLASSIFIER OUTLET TEMP.2
10HFC50CT305 E 磨煤机分离器出口温度 5 MILL E CLASSIFIER OUTLET TEMP.5
10HFC50CT303 E 磨煤机分离器出口温度 3 MILL E CLASSIFIER OUTLET TEMP.3
10HFC50CT306 E 磨煤机分离器出口温度 6 MILL E CLASSIFIER OUTLET TEMP.6
10HFE55CT101 磨煤机 E 入口一次风温度 1 MILL E INLET PA TEMP. 1
10HFE55CT102 磨煤机 E 入口一次风温度 2 MILL E INLET PA TEMP. 2
10HFY01PI001 A 给煤机累积给煤量 COAL FEEDER A WEIGHT DATA LOGGING
10HFY02PI001 B 给煤机累积给煤量 COAL FEEDER B WEIGHT DATA LOGGING
10HFY03PI001 C 给煤机累积给煤量 COAL FEEDER C WEIGHT DATA LOGGING
10HFY04PI001 D 给煤机累积给煤量 COAL FEEDER D WEIGHT DATA LOGGING
10HFY05PI001 E 给煤机累积给煤量 COAL FEEDER E WEIGHT DATA LOGGING
10HFY06PI001 F 给煤机累积给煤量 COAL FEEDER F WEIGHT DATA LOGGING
10HFY07PI001 G 给煤机累积给煤量 COAL FEEDER G WEIGHT DATA LOGGING
10HFY08PI001 H 给煤机累积给煤量 COAL FEEDER H WEIGHT DATA LOGGING
10HFC60AD001CE F 磨煤机电流 MILL F CURRENT
10HFY06AI003 F 给煤机瞬时煤量反馈信号 COAL FEEDER F FEEDING RATE FEEDBACK
10HFE56CF101 磨煤机 F 入口一次风风量 1 MILL F INLET PA FLOW 1
10HFE56CP101 磨煤机 F 入口一次风压力 MILL F INLET PA PRESSURE.

DECL-TPCIL-PGT-001 16 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

10HFE56CF102 磨煤机 F 入口一次风风量 2 MILL F INLET PA FLOW 2


10HFC60CP103 F 磨煤机分离器出口压力 MILL F CLASSIFIER OUTLET PRESSURE
10HFC60CT301 F 磨煤机分离器出口温度 1 MILL F CLASSIFIER OUTLET TEMP.1
10HFC60CT304 F 磨煤机分离器出口温度 4 MILL F CLASSIFIER OUTLET TEMP.4
10HFC60CT302 F 磨煤机分离器出口温度 2 MILL F CLASSIFIER OUTLET TEMP.2
10HFC60CT305 F 磨煤机分离器出口温度 5 MILL F CLASSIFIER OUTLET TEMP.5
10HFC60CT303 F 磨煤机分离器出口温度 3 MILL F CLASSIFIER OUTLET TEMP.3
10HFC60CT306 F 磨煤机分离器出口温度 6 MILL F CLASSIFIER OUTLET TEMP.6
10HFE56CT101 磨煤机 F 入口一次风温度 1 MILL F INLET PA TEMP. 1
10HFE56CT102 磨煤机 F 入口一次风温度 2 MILL F INLET PA TEMP. 2
10HFC70AD001CE G 磨煤机电流 MILL G CURRENT
10HFY07AI003 G 给煤机瞬时煤量反馈信号 COAL FEEDER G FEEDING RATE FEEDBACK
10HFE57CF101 磨煤机 G 入口一次风风量 1 MILL G INLET PA FLOW 1
10HFE57CP101 磨煤机 G 入口一次风压力 MILL G INLET PA PRESSURE.
10HFE57CF102 磨煤机 G 入口一次风风量 2 MILL G INLET PA FLOW 2
10HFC70CP103 G 磨煤机分离器出口压力 MILL G CLASSIFIER OUTLET PRESSURE
10HFC70CT301 G 磨煤机分离器出口温度 1 MILL G CLASSIFIER OUTLET TEMP.1
10HFC70CT304 G 磨煤机分离器出口温度 4 MILL G CLASSIFIER OUTLET TEMP.4
10HFC70CT302 G 磨煤机分离器出口温度 2 MILL G CLASSIFIER OUTLET TEMP.2
10HFC70CT305 G 磨煤机分离器出口温度 5 MILL G CLASSIFIER OUTLET TEMP.5
10HFC70CT303 G 磨煤机分离器出口温度 3 MILL G CLASSIFIER OUTLET TEMP.3
10HFC70CT306 G 磨煤机分离器出口温度 6 MILL G CLASSIFIER OUTLET TEMP.6
10HFE57CT101 磨煤机 G 入口一次风温度 1 MILL G INLET PA TEMP. 1
10HFE57CT102 磨煤机 G 入口一次风温度 2 MILL G INLET PA TEMP. 2
10HFC80AD001CE H 磨煤机电流 MILL H CURRENT
10HFY08AI003 H 给煤机瞬时煤量反馈信号 COAL FEEDER H FEEDING RATE FEEDBACK
10HFE58CF101 磨煤机 H 入口一次风风量 1 MILL H INLET PA FLOW 1
10HFE58CP101 磨煤机 H 入口一次风压力 MILL H INLET PA PRESSURE.
10HFE58CF102 磨煤机 H 入口一次风风量 2 MILL H INLET PA FLOW 2
10HFC80CP103 H 磨煤机分离器出口压力 MILL H CLASSIFIER OUTLET PRESSURE
10HFC80CT301 H 磨煤机分离器出口温度 1 MILL H CLASSIFIER OUTLET TEMP.1
10HFC80CT304 H 磨煤机分离器出口温度 4 MILL H CLASSIFIER OUTLET TEMP.4
10HFC80CT302 H 磨煤机分离器出口温度 2 MILL H CLASSIFIER OUTLET TEMP.2
10HFC80CT305 H 磨煤机分离器出口温度 5 MILL H CLASSIFIER OUTLET TEMP.5
10HFC80CT303 H 磨煤机分离器出口温度 3 MILL H CLASSIFIER OUTLET TEMP.3
10HFC80CT306 H 磨煤机分离器出口温度 6 MILL H CLASSIFIER OUTLET TEMP.6
10HFE58CT101 磨煤机 H 入口一次风温度 1 MILL H INLET PA TEMP. 1
10HFE58CT102 磨煤机 H 入口一次风温度 2 MILL H INLET PA TEMP. 2
10HFD10AA001ZZ 一次风机 A 动叶位置反馈 PAF A BLADE POS.FEEDBACK
10HFD10AN001CE 一次风机 A 电流 PA FAN A CURRENT
10HLB10AA001ZZ 送风机 A 动叶位置反馈 FDF A BLADE POS.
10HLB10AN001CE 送风机 A 电流 FD FAN A CURRENT
10ZZZ10CQ101 烟囱出口烟气 CO2 含量 CHIMNEY OUTLET GAS CO2 CONTENT

DECL-TPCIL-PGT-001 17 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

10ZZZ10CQ102 烟囱出口烟气 CO 含量 CHINNEY OUTLET GAS CO CONTENT


10ZZZ10CQ103 烟囱出口烟气 SOX 含量 CHIMNEY OUTLET GAS SOX CONTENT
10ZZZ10CQ104 烟囱出口烟气 NOX 含量 CHIMNEY OUTLET GAS NOX CONTENT
10ZZZ10CQ105 烟囱出口烟气含尘量 CHIMNEY OUTLET GAS OPACITY
10HNC10AA001ZZ 引风机 A 动叶位置反馈 IDF A MOVABLE VANE POS.引风机为静叶调节
10HNC10AN001CE 引风机 A 电流 ID FAN A CURRENT
10HLA40CF101 锅炉 A 侧热二次风风量 1 BOILER SIDE A HOT SA FLOW 1
10HLA40CP101 锅炉 A 侧二次风箱入口压力 1 BOILER SIDE A SA WIND BOX INLET PRESSURE. 1
10HNA10CQ104 后烟井 A 侧烟气含碳量 1 BACK PASS A CO CONTENT 1
10HFE10CP102 空预器 A 入口一次风压力 APH A INLET PA PRESSURE.
10HFE12CP101 空预器 A 出口一次风压力 APH A OUTLET PA PRESSURE.
10HFE10CP101 一次风机 A 出口压力 PAF A OUTLET PRESSURE.
10HFE11CP101 冷一次风母管压力 1 COLD PA HEADER PRESSURE. 1
10HFE12CP102 热一次风母管压力 1 HOT PA HEADER PRESSURE.1
10HLA40CF102 锅炉 A 侧热二次风风量 2 BOILER SIDE A HOT SA FLOW 2
10HLA40CP102 锅炉 A 侧二次风箱入口压力 2 BOILER SIDE A SA WIND BOX INLET PRESSURE. 2
10HNA10CQ105 后烟井 A 侧烟气含碳量 2 BACK PASS A CO CONTENT 2
10HLA10CP102 空预器 A 入口二次风压力 APH A INLET SA PRESSURE.
10HLA40CP103 空预器 A 出口二次风压力 APH A OUTLET SA PRESSURE.
10HLA10CP101 送风机 A 出口压力 FDF A OUTLET PRESSURE.
10HFE11CP102 冷一次风母管压力 2 COLD PA HEADER PRESSURE. 2
10HFE12CP103 热一次风母管压力 2 HOT PA HEADER PRESSURE.2
10HLA40CF103 锅炉 A 侧热二次风风量 3 BOILER SIDE A HOT SA FLOW 3
10HNA10CP101 后烟井 A 侧出口烟气压力 BACK PASS A OUTLET FLUE GAS PRESSURE.
10HNA10CP102 空预器 A 出口烟气压力 APH A OUTLET GAS PRESSURE.
10HNA10CP103 引风机 A 入口烟气压力 IDF A INLET GAS PRESSURE.
10HNA10CP104 引风机 A 出口烟气压力 IDF A OUTLET GAS PRESSURE.
10HFE11CP103 冷一次风母管压力 3 COLD PA HEADER PRESSURE. 3
10HFE12CP104 热一次风母管压力 3 HOT PA HEADER PRESSURE.3
10HBC72CP101 炉膛左侧负压 1 FURNACE LEFT NEGATIVE PRESSURE 1
10HNA10CQ106 静电除尘器 A 出口烟气含尘量 ESP A OUTLET GAS OPACITY
10HBC72CP102 炉膛左侧负压 2 FURNACE LEFT NEGATIVE PRESSURE 2
锅炉左侧后竖井低过入口烟 BOILER LEFT BACK PASS PRIMARY SH. INLET GAS
气压力 PRESSURE
锅炉左侧后竖井低再入口烟 BOILER LEFT BACK PASS PRIMARY RH. INLET GAS
10HBC72CP104 气压力 PRESSURE
锅炉左侧后竖井省煤器入口
10HBC72CP105 烟气压力 BOILER LEFT BACK PASS ECO. INLET GAS PRESSURE
锅炉左侧后竖井省煤器出口
10HBC72CP106 烟气压力 BOILER LEFT BACK PASS ECO. OUTLET GAS PRESSURE
锅炉左侧后竖井低再出口烟 BOILER LEFT BACK PRIMARY RH. OUTLET GAS
10HBC72CP107 气压力 PRESSURE
10HFD10AA001AO 一次风机 A 动叶控制指令 PAF A BLADE CTRL CMD
10HLB10AA001AO 送风机 A 动叶控制指令 FDF A BLADE CTRL CMD
DECL-TPCIL-PGT-001 18 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

10HNC10AA001AO 引风机 A 动叶控制指令 IDF A BLADE CTRL CMD


10HLA10CT311 送风机 A 入口温度 FDF A INLET TEMP.
10HNA10CT303 引风机 A 入口烟气温度 IDF A INLET GAS TEMP.
10HNA10CT304 引风机 A 出口烟气温度 IDF A OUTLET GAS TEMP.
10HLA10CT302 空预器 A 入口二次风温度 1 APH A INLET SA TEMP. 1
10HNA10CT301 空预器 A 出口烟气温度 1 APH A OUTLET GAS TEMP. 1
10HLA10CT303 空预器 A 入口二次风温度 2 APH A INLET SA TEMP. 2
10HNA10CT302 空预器 A 出口烟气温度 2 APH A OUTLET GAS TEMP. 2
10HFE10CT301 一次风机 A 入口温度 PAF A INLET TEMP.
10HFE10CT302 一次风机 A 出口温度 PAF A OUTLET TEMP.
10HFE10CT303 空预器 A 入口一次风温度 APH A INLET PA TEMP.
10HLA10CT301 送风机 A 出口温度 FDF A OUTLET TEMP.
锅炉左侧后竖井低过入口烟 BOILER LEFT BACK PASS PRIMARY SH. INLET GAS
10HBC72CT101 气温度 1 TEMP 1
锅炉左侧后竖井低再入口烟 BOILER LEFT BACK PASS PRIMARY RH. INLET GAS
10HBC72CT103 气温度 1 TEMP 1
锅炉左侧后竖井省煤器入口
10HBC72CT105 烟气温度 1 BOILER LEFT BACK PASS ECO. INLET GAS TEMP 1
锅炉左侧后竖井省煤器出口
10HBC72CT107 烟气温度 1 BOILER LEFT BACK PASS ECO. OUTLET GAS TEMP 1
锅炉左侧后竖井低再出口烟 BOILER LEFT BACK PASS PRIMARY RH. OUTLET GAS
10HBC72CT109 气温度 1 TEMP 1
10HLA40CT101 锅炉 A 侧二次风箱入口温度 1 BOILER SIDE A SA WIND BOX INLET TEMP.1
锅炉左侧后竖井低过入口烟 BOILER LEFT BACK PASS PRIMARY SH. INLET GAS
10HBC72CT102 气温度 2 TEMP 2
锅炉左侧后竖井低再入口烟 BOILER LEFT BACK PASS PRIMARY RH. INLET GAS
10HBC72CT104 气温度 2 TEMP 2
锅炉左侧后竖井省煤器入口
10HBC72CT106 烟气温度 2 BOILER LEFT BACK PASS ECO. INLET GAS TEMP 2
锅炉左侧后竖井省煤器出口
10HBC72CT108 烟气温度 2 BOILER LEFT BACK PASS E CO. OUTLET GAS TEMP 2
锅炉左侧后竖井低再出口烟 BOILER LEFT BACK PASS P RIMARY RH. OUTLET GAS
10HBC72CT110 气温度 2 TEMP 2
10HLA40CT102 锅炉 A 侧二次风箱入口温度 2 BOILER SIDE A SA WIND BOX INLET TEMP.2
10HFE12CT101 空预器 A 出口一次风温度 APH A PA OUTLET TEMP.
10HLA40CT103 空预器 A 出口二次风温度 APH A SA OUTLET TEMP.
10HNA10CT101 后烟井 A 侧出口烟气温度 REAR GAS WALL SIDE A OUTLET TEMP.
10HFD20AA001ZZ 一次风机 B 动叶位置反馈 PAF B MOVABLE VANE POS.
10HFD20AN001CE 一次风机 B 电流 PA FAN B CURRENT
10HLB20AA001ZZ 送风机 B 动叶位置反馈 FDF B BLADE POS.
10HLB20AN001CE 送风机 B 电流 FD FAN B CURRENT
10HNC20AA001ZZ 引风机 B 动叶位置反馈 IDF B BLADE POS.
10HNC20AN001CE 引风机 B 电流 ID FAN B CURRENT
10HLA50CF101 锅炉 B 侧热二次风风量 1 BOILER SIDE B SA FLOW 1

DECL-TPCIL-PGT-001 19 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

10HLA50CP101 锅炉 B 侧二次风箱入口压力 1 BOILER SIDE B SA WIND BOX INLET PRESSURE. 1


10HNA20CQ104 后烟井 B 侧烟气含碳量 1 BACK PASS B CO CONTENT 1
10HFE20CP102 空预器 B 入口一次风压力 APH B INLET PA AIR PRESSURE.
10HFE22CP101 空预器 B 出口一次风压力 APH B OUTLET PA PRESSURE.
10HFE20CP101 一次风机 B 出口压力 PAF B OUTLET PRESSURE.
10HLA50CF102 锅炉 B 侧热二次风风量 2 BOILER SIDE B SA FLOW 2
10HLA50CP102 锅炉 B 侧二次风箱入口压力 2 BOILER SIDE B SA WIND BOX INLET PRESSURE. 2
10HNA20CQ105 后烟井 B 侧烟气含碳量 2 BACK PASS B CO CONTENT 2
10HLA20CP102 空预器 B 入口二次风压力 APH B INLET SA PRESSURE.
10HLA50CP103 空预器 B 出口二次风压力 APH B OUTLET SA PRESSURE.
10HLA20CP101 送风机 B 出口压力 FAF B OUTLET PRESSURE.
10HLA50CF103 锅炉 B 侧热二次风风量 3 BOILER SIDE B SA FLOW 3
10HNA20CP101 后烟井 B 侧出口烟气压力 BACK PASS B OUTLET PRESSURE.
10HNA20CP102 空预器 B 出口烟气压力 APH B OUTLET GAS PRESSURE.
10HNA20CP103 引风机 B 入口烟气压力 IDF B INLET GAS PRESSURE.
10HNA20CP104 引风机 B 出口烟气压力 IDF B OUTLET GAS PRESSURE.
10HBC71CP101 炉膛右侧负压 1 FURNACE RIGHT NEGATIVE PRESSURE 1
10HBC71CP102 炉膛右侧负压 2 FURNACE RIGHT NEGATIVE PRESSURE 2
锅炉右侧后竖井低过入口烟 BOILER RIGHT BACK PASS PRIMARY SH. INLET GAS
10HBC71CP103 气压力 PRESSURE
锅炉右侧后竖井低再入口烟 BOILER RIGHT BACK PASS PRIMARY RH. INLET GAS
10HBC71CP104 气压力 PRESSURE
锅炉右侧后竖井省煤器入口 BOILER RIGHT BACK PASS ECO. INLET GAS
10HBC71CP105 烟气压力 PRESSURE
锅炉右侧后竖井省煤器出口 BOILER RIGHT BACK PASS ECO. OUTLET GAS
10HBC71CP106 烟气压力 PRESSURE
锅炉右侧后竖井低再出口烟 BOILER RIGHT BACK PASS PRIMARY RH. OUTLET GAS
10HBC71CP107 气压力 PRESSURE
10HFD20AA001AO 一次风机 B 动叶控制指令 PAF B BLADE CTRL CMD
10HLB20AA001AO 送风机 B 动叶控制指令 FDF B BLADE CTRL CMD
10HNC20AA001AO 引风机 B 动叶控制指令 IDF B BLADE CTRL CMD
10HLA20CT311 送风机 B 入口温度 FDF B INLET TEMP
10HNA20CT303 引风机 B 入口烟气温度 IDF B INLET GAS TEMP.
10HNA20CT304 引风机 B 出口烟气温度 IDF B OUTLET GAS TEMP.
10HLA20CT302 空预器 B 入口二次风温度 1 APH B INLET SA TEMP. 1
10HNA20CT301 空预器 B 出口烟气温度 1 APH B OUTLET GAS TEMP. 1
10HLA20CT303 空预器 B 入口二次风温度 2 APH B INLET SA TEMP. 2
10HNA20CT302 空预器 B 出口烟气温度 2 APH B OUTLET GAS TEMP. 2
10HFE20CT301 一次风机 B 入口温度 PAF B INLET TEMP.
10HFE20CT302 一次风机 B 出口温度 PAF B OUTLET TEMP.
10HFE20CT303 空预器 B 入口一次风温度 APH B INLET PA TEMP.
10HLA20CT301 送风机 B 出口温度 FDF B OUTLET TEMP.
锅炉右侧后竖井低过入口烟 BOILER RIGHT BACK PASS PRIMARY SH. INLET GAS
10HBC71CT101 气温度 1 TEMP 1

DECL-TPCIL-PGT-001 20 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

锅炉右侧后竖井低再入口烟 BOILER RIGHT BACK PASS PRIMARY RH. INLET GAS


10HBC71CT103 气温度 1 TEMP 1
锅炉右侧后竖井省煤器入口
10HBC71CT105 烟气温度 1 BOILER RIGHT BACK PASS ECO. INLET GAS TEMP 1
锅炉右侧后竖井省煤器出口 BOILER RIGHT BACK PASS ECO. OUTLET GAS TEMP
10HBC71CT107 烟气温度 1 1
锅炉右侧后竖井低再出口烟 BOILER RIGHT BACK PASS PRIMARY RH. OUTLET GAS
10HBC71CT109 气温度 1 TEMP 1
10HLA50CT101 锅炉 B 侧二次风箱入口温度 1 BOILER SIDE B SA WIND BOX INLET TEMP.1
锅炉右侧后竖井低过入口烟 BOILER RIGHT BACK PASS PRIMARY SH. INLET GAS
10HBC71CT102 气温度 2 TEMP 2
锅炉右侧后竖井低再入口烟 BOILER RIGHT BACK PASS PRIMARY RH. INLET GAS
10HBC71CT104 气温度 2 TEMP 2
锅炉右侧后竖井省煤器入口
10HBC71CT106 烟气温度 2 BOILER RIGHT BACK PASS ECO. INLET GAS TEMP 2
锅炉右侧后竖井省煤器出口 BOILER RIGHT BACK PASS ECO. OUTLET GAS TEMP
10HBC71CT108 烟气温度 2 2
锅炉右侧后竖井低再出口烟 BOILER RIGHT BACK PASS PRIMARY RH. OUTLET GAS
10HBC71CT110 气温度 2 TEMP 2
10HLA50CT102 锅炉 B 侧二次风箱入口温度 2 BOILER SIDE B SA WIND BOX INLET TEMP.2
10HFE22CT101 空预器 B 出口一次风温度 APH B PA OUTLET TEMP.
10HLA50CT103 空预器 B 出口二次风温度 APH B SA OUTLET TEMP.
10HNA20CT101 后烟井 B 侧出口烟气温度 BACK PASS SIDE B OUTLET TEMP.
10CFC23AI001 炉膛出口温度 1 FURNACE OUTLET GAS TEMP 1
10CFC23AI002 炉膛出口温度 2 FURNACE OUTLET GAS TEMP 2
10CFC23AI003 炉膛出口温度 3 FURNACE OUTLET GAS TEMP 3
10CFC23AI004 炉膛出口温度 4 FURNACE OUTLET GAS TEMP 4
10CFC23AI005 炉膛出口温度 5 FURNACE OUTLET GAS TEMP 5
10CFC23AI006 炉膛出口温度 6 FURNACE OUTLET GAS TEMP 6
10CFC23AI007 炉膛出口温度 7 FURNACE OUTLET GAS TEMP 7
10CFC23AI008 炉膛出口温度 8 FURNACE OUTLET GAS TEMP 8
10CFC23AI009 炉膛出口温度 9 FURNACE OUTLET GAS TEMP 9
10CFC23AI010 炉膛出口温度 10 FURNACE OUTLET GAS TEMP 10
10CFC23AI011 炉膛出口温度 11 FURNACE OUTLET GAS TEMP 11
10CFC23AI012 炉膛出口温度 12 FURNACE OUTLET GAS TEMP 12
10CFC23AI013 炉膛出口温度 13 FURNACE OUTLET GAS TEMP 13
10CFC23AI014 炉膛出口温度 14 FURNACE OUTLET GAS TEMP 14
10CFC23AI015 炉膛出口温度 15 FURNACE OUTLET GAS TEMP 15
10CFC23AI016 炉膛出口温度 16 FURNACE OUTLET GAS TEMP 16
10CFC24AI001 省煤器出口烟气温度 1 ECONOMIZER OUTLET GAS TEMP 1
10CFC24AI002 省煤器出口烟气温度 2 ECONOMIZER OUTLET GAS TEMP 2
10CFC24AI003 省煤器出口烟气温度 3 ECONOMIZER OUTLET GAS TEMP 3
10CFC24AI004 省煤器出口烟气温度 4 ECONOMIZER OUTLET GAS TEMP 4
10HAG10CL101 汽水分离器储水罐液位 1 STEAM-WATER SEPARATOR STORAGE TANK WATER

DECL-TPCIL-PGT-001 21 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

LEVEL 1
10HAG10CP101 汽水分离器出口压力 1 STEAM-WATER SEPARATOR OUTLET PRESSURE 1
10HAH60CP101 高温过热器出口集箱压力 1 FINAL SH OUTLET HEADER PRESSURE 1
10HAH60CP104 高温过热器出口集箱压力 4 FINAL SH OUTLET HEADER PRESSURE 4
10HAG30CF101 再循环泵出口母管流量 BCP PUMP OUTLET HEADER FLOW
锅炉启动扩容器疏水泵出口 BOILER FLASH TANK DRAIN PUMP OUTLET HEADER
10LCL10CP101 母管压力 PRESSURE
10HAG10CL102 汽水分离器储水罐液位 2 STEAM-WATER SEPARATOR STORAGE TANK LEVEL 2
10HAG10CP102 汽水分离器出口压力 2 STEAM-WATER SEPARATOR OUTLET PRESSURE 2
10HAH60CP102 高温过热器出口集箱压力 2 FINAL SH OUTLET HEADER PRESSURE 2
10HAH60CP105 高温过热器出口集箱压力 5 FINAL SH OUTLET HEADER PRESSURE 5
10HAG10CL103 汽水分离器储水罐液位 3 STEAM-WATER SEPARATOR STORAGE TANK LEVEL 3
10HAG10CP103 汽水分离器储水罐压力 STEAM-WATER SEPARATOR STORAGE TANK PRESSURE
10HAH60CP103 高温过热器出口集箱压力 3 FINAL SH OUTLET HEADER PRESSURE 3
10LAD20CP101 再热器减温水总管给水压力 RH DSH WATER MAIN PIPE PRESSURE
锅炉扩容器疏水母管电动调
10LCL20AA001ZZ 节阀位置反馈 BOILER FLASH TANK DRAIN MCV POS.
再热器 A 侧减温器减温水流量
10LAD21CF101 1 RH SIDE A DSH WATER FLOW 1
10LAD32CF101 A 侧过热器一级减温水流量 1 SIDE A PRIMARY SH. DSH WATER FLOW 1
10LAD41CF101 A 侧过热器二级减温水流量 1 SIDE A SECONDARY SH. DSH WATER FLOW 1
10LBA10CP101 主蒸汽压力 1 MAIN STEAM PRESSURE 1
10LAC40CF101 锅炉主给水流量 1 BOILER FEED WATER FLOW 1
10HNA10CQ101 后烟井 A 侧烟气含氧量 1 BACK PASS A O2 CONTENT 1
10LBC31CP101 低温再热器入口 A 侧蒸汽压力 PRIMARY RH INLET SIDE A STEAM PRESSURE
10LBA01CP101 高旁阀 1 后压力 HP BYPASS VALVE 1 DOWNSTREAM PRESSURE
再热器 A 侧减温器减温水流量
10LAD21CF102 2 RH SIDE A DSH WATER FLOW 2
10LAD32CF102 A 侧过热器一级减温水流量 2 SIDE A PRIMARY SH. DSH WATER FLOW 2
10LAD41CF102 A 侧过热器二级减温水流量 2 SIDE A SECONDARY SH. DSH WATER FLOW 2
10LBA10CP102 主蒸汽压力 2 MAIN STEAM PRESSURE 2
10LAC40CF102 锅炉主给水流量 2 BOILER FEED WATER FLOW 2
10HNA10CQ102 后烟井 A 侧烟气含氧量 2 BACK PASS A O2 CONTENT 2
10LBB01CP101 低旁阀 A 后压力 LP BYPASS VALVE A DOWNSTREAM PRESSURE
再热器 A 侧减温器减温水流量
10LAD21CF103 3 RH SIDE A DSH WATER FLOW 3
10LAD32CF103 A 侧过热器一级减温水流量 3 SIDE A PRIMARY SH. DSH WATER FLOW 3
10LAD41CF103 A 侧过热器二级减温水流量 3 SIDE A SECONDARY SH. DSH WATER FLOW 3
10LBA10CP103 主蒸汽压力 3 MAIN STEAM PRESSURE 3
10LAC40CF103 锅炉主给水流量 3 BOILER FEED WATER FLOW 3
10LCC12CF101 低旁 A 减温水流量 LP BYPASS A SPRAY WATER FLOW
10LCC12CP101 低旁 A 喷水压力 LP BYPASS A SPRAY WATER PRESSURE
10HNA10CQ103 空预器 A 出口烟气含氧量 APH A OUTLET GAS O2 CONTENT
10LAD22CF101 再热器 B 侧减温器减温水流量 RH SIDE B DSH WATER FLOW 1
DECL-TPCIL-PGT-001 22 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

1
10LAD31CF101 B 侧过热器一级减温水流量 1 SIDE B PRIMARY SH. DSH WATER FLOW 1
10LAD42CF101 B 侧过热器二级减温水流量 1 SIDE B SECONDARY SH. DSH WATER FLOW 1
TURBINE STEAM PRESSURE 1 DOWNSTREAM GOVERNING
10MAA10CP101 汽机调节级压力 1 STAGE
10LAC71DP101 锅炉主给水调节阀差压 1 BOILER FEED WATER CONTROL VALVE DP 1
10HNA20CQ101 后烟井 B 侧烟气含氧量 1 BACK PASS B O2 CONTENT 1
10LBC32CP101 低温再热器入口 B 侧蒸汽压力 PRIMARY RH INLET SIDE B STEAM PRESSURE
10LBA01CP102 高旁阀 2 后压力 HP BYPASS VALVE 2 DOWNSTREAM PRESSURE
再热器 B 侧减温器减温水流量
10LAD22CF102 2 RH SIDE B DSH WATER FLOW 2
10LAD31CF102 B 侧过热器一级减温水流量 2 SIDE B PRIMARY SH. DSH WATER FLOW 2
10LAD42CF102 B 侧过热器二级减温水流量 2 SIDE B SECONDARY SH. DSH WATER FLOW 2
TURBINE STEAM PRESSURE 2 DOWNSTREAM GOVERNING
10MAA10CP102 汽机调节级压力 2 STAGE
10LAC71DP102 锅炉主给水调节阀差压 2 BOILER FEED WATER CONTROL VALVE DP 2
10HNA20CQ102 后烟井 B 侧烟气含氧量 2 BACK PASS B O2 CONTENT 2
10LBB02CP101 低旁阀 B 后压力 LP BYPASS VALVE B DOWNSTREAM PRESSURE
再热器 B 侧减温器减温水流量
10LAD22CF103 3 RH SIDE B DSH WATER FLOW 3
10LAD31CF103 B 侧过热器一级减温水流量 3 SIDE B PRIMARY SH. DSH WATER FLOW 3
10LAD42CF103 B 侧过热器二级减温水流量 3 SIDE B SECONDARY SH. DSH WATER FLOW 3
TURBINE STEAM PRESSURE 3 DOWNSTREAM GOVERNING
10MAA10CP103 汽机调节级压力 3 STAGE
10LCC13CF101 低旁 B 减温水流量 LP BYPASS B SPRAY WATER FLOW
10LCC13CP101 低旁 B 喷水压力 LP BYPASS B SPRAY WATER PRESSURE
10HNA20CQ103 空预器 B 出口烟气含氧量 APH B OUTLET GAS O2 CONTENT
高温过热器出口 A 侧蒸气温度
10LBA11CT101 1 FINAL SH OUTLET SIDE A STEAM TEMP 1
高温再热器出口 A 侧蒸汽温度
10LBB11CT101 1 FINAL RH SIDE A OUTLET PIPE STEAM TEMP 1
10LBA01CT101 高旁阀 1 后温度 1 HP BYPASS VALVE 1 DOWNSTREAM TEMP 1
10LBA01CT104 高旁阀 2 后温度 1 HP BYPASS VALVE 2 DOWNSTREAM TEMP 1
屏式过热器出口 A 侧蒸汽温度
10HAH40CT103 1 PLATEN SH OUTLET SIDE A STEAM TEMP 1
高温过热器入口 A 侧蒸汽温度
10HAH50CT106 1 FINAL SH INLET SIDE A STEAM TEMP 2
高温再热器入口 A 侧蒸汽温度
10HAJ20CT101 1 RH. INLET SIDE A STEAM TEMP 1
高温过热器出口 A 侧蒸气温度
10LBA11CT102 2 FINAL SH OUTLET SIDE A STEAM TEMP 2
高温再热器出口 A 侧蒸汽温度
10LBB11CT102 2 FINAL RH SIDE A OUTLET PIPE STEAM TEMP 2
10LBA01CT102 高旁阀 1 后温度 2 HP BYPASS VALVE 1 DOWNSTREAM TEMP 2

DECL-TPCIL-PGT-001 23 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

10LBA01CT105 高旁阀 2 后温度 2 HP BYPASS VALVE 2 DOWNSTREAM TEMP 2


屏式过热器出口 A 侧蒸汽温度
10HAH50CT101 2 SECONDARY SH OUTLET SIDE A STEAM TEMP 2
高温过热器入口 A 侧蒸汽温度
10HAH50CT105 2 FINAL SH INLET SIDE A STEAM TEMP 1
高温再热器入口 A 侧蒸汽温度
10HAJ20CT102 2 RH. INLET SIDE A STEAM TEMP 2
高温过热器出口 A 侧蒸气温度
10LBA11CT103 3 FINAL SH OUTLET SIDE A STEAM TEMP 3
高温再热器出口 A 侧蒸汽温度
10LBB11CT103 3 FINAL RH SIDE A OUTLET PIPE STEAM TEMP 3
10LBA01CT103 高旁阀 1 后温度 3 HP BYPASS VALVE 1 DOWNSTREAM TEMP 3
10LBA01CT106 高旁阀 2 后温度 3 HP BYPASS VALVE 2 DOWNSTREAM TEMP 3
顶棚过热器出口集箱 A 侧蒸汽
10HAH10CT101 温度 ROOF OUTLET HEADER SIDE A STEAM TEMP
10HAH30CT101 低温过热器进口 A 侧蒸汽温度 PRIMARY SH INLET SIDE A STEAM TEMP
10HAH40CT101 低温过热器出口 A 侧蒸汽温度 PRIMARY SH OUTLET SIDE A STEAM TEMP
10HAH40CT104 屏式过热器入口 A 侧蒸汽温度 PLATEN SH INLET SIDE A STEAM TEMP
10HAJ10CT101 低温再热器出口 A 侧蒸汽温度 PRIMARY RH OUTLET HADER SIDE A STEAM TEMP
10LBC31CT101 低温再热器入口 A 侧蒸汽温度 PRIMARY RH INLET SIDE A STEAM TEMP
10LBB01CT101 低旁阀 1 后温度 LP BYPASS VALVE 1 DOWNSTREAM TEMP
10HAC10CT101 省煤器出口给水温度 ECONOMIZER OUTLET FEED WATER TEMP
10LAC40CT111 锅炉给水泵出口母管温度 BFP DISCHARGE HEADER TEMP
高温过热器出口 B 侧蒸气温度
10LBA12CT101 1 FINAL SH OUTLET SIDE B STEAM TEMP 1
高温再热器出口 B 侧蒸汽温度
10LBB12CT101 1 FINAL RH SIDE B OUTLET PIPE STEAM TEMP 1
10LAC40CT107 锅炉最终给水温度 1 BOILER FINAL FEED WATER TEMP 1
10HAD30CT101 水冷壁出口集箱给水温度 1 OPEN PASS WALL OUTLET FEED WATER TEMP 1
屏式过热器出口 B 侧蒸汽温度
10HAH40CT105 1 PLATEN SH OUTLET SIDE B STEAM TEMP 1
高温过热器入口 B 侧蒸汽温度
10HAH50CT103 1 FINAL SH INLET SIDE B STEAM TEMP 1
高温再热器入口 B 侧蒸汽温度
10HAJ20CT103 1 RH. INLET SIDE B STEAM TEMP 1
高温过热器出口 B 侧蒸气温度
10LBA12CT102 2 FINAL SH OUTLET SIDE B STEAM TEMP 2
高温再热器出口 B 侧蒸汽温度
10LBB12CT102 2 FINAL RH B SIDE OUTLET PIPE STEAM TEMP 2
10LAC40CT108 锅炉最终给水温度 2 BOILER FINAL FEED WATER TEMP 2
10HAD30CT102 水冷壁出口集箱给水温度 2 OPEN PASS WALL OUTLET FEED WATER TEMP 2
屏式过热器出口 B 侧蒸汽温度
10HAH50CT102 2 PLATEN SH OUTLET SIDE B STEAM TEMP 2
10HAH50CT104 高温过热器入口 B 侧蒸汽温度 FINAL SH INLET SIDE B STEAM TEMP 2

DECL-TPCIL-PGT-001 24 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

2
高温再热器入口 B 侧蒸汽温度
10HAJ20CT104 2 RH. INLET SIDE B STEAM TEMP 2
高温过热器出口 B 侧蒸气温度
10LBA12CT103 3 FINAL SH OUTLET SIDE B STEAM TEMP 3
高温再热器出口 B 侧蒸汽温度
10LBB12CT103 3 FINAL RH SIDE B OUTLET PIPE STEAM TEMP 3
10LAC40CT109 锅炉最终给水温度 3 BOILER FINAL FEED WATER TEMP 3
10HAD30CT103 水冷壁出口集箱给水温度 3 OPEN PASS WALL OUTLET FEED WATER TEMP 3
顶棚过热器出口集箱 B 侧蒸汽
10HAH10CT102 温度 ROOF OUTLET HEADER SIDE B STEAM TEMP
10HAH30CT102 低温过热器进口 B 侧蒸汽温度 PRIMARY SH INLET SIDE B STEAM TEMP
10HAH40CT102 低温过热器出口 B 侧蒸汽温度 PRIMARY SH OUTLET SIDE B STEAM TEMP
10HAH40CT106 屏式过热器入口 B 侧蒸汽温度 PLATEN SH INLET SIDE B STEAM TEMP
10HAJ10CT102 低温再热器出口 B 侧蒸汽温度 PRIMARY RH OUTLET HADER SIDE B STEAM TEMP
10LBC32CT101 低温再热器入口 B 侧蒸汽温度 PRIMARY RH INLET SIDE B STEAM TEMP
10LBB02CT101 低旁阀 B 后温度 LP BYPASS VALVE B DOWNSTREAM TEMP

DECL-TPCIL-PGT-001 25 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Appendix C Boiler efficiency correction curve ( Total moisture in coal )


( y=0.175x-1.4875 )

Appendix D Boiler efficiency correction curve ( Hydrogen in coal )


( y=1.1667x-4.08333 )

DECL-TPCIL-PGT-001 26 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Appendix E Boiler efficiency correction curve ( Air absolute humidity )


( y=9.0x-0.117 )

Appendix F Boiler efficiency correction curve ( Air temperature at APH inlet )


( y=0.03386x-1.1221218 )

DECL-TPCIL-PGT-001 27 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Appendix G Boiler efficiency correction curve ( Feed water inlet temperature )


(y=0.01x-2.83)

Appendix H Boiler efficiency correction curve( The fineness of Coal )


( y =1.473923×10-4x3-7.1145133×10-3x2+0.1282937x-0.8637756)

DECL-TPCIL-PGT-001 28 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Appendix I Boiler efficiency correction curve ( The flue gas temperature at APH outlet )
( y=0.05556x-7.8333 )

Appendix L: Boiler efficiency correction curve ( Excess Air at Furnace Outlet )


( y =2.19047x2-3.10761x+0.61697 )

DECL-TPCIL-PGT-001 29 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Appendix K: Boiler efficiency correction curve ( The Ash in Coal )


( y=0.016x-0.544 )

Appendix J Boiler efficiency correction curve ( HHVF of the Coal )


( y=-0.000291x+5.0375509 )

DECL-TPCIL-PGT-001 30 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

APPENDIX J: Other Record Table

Original Data 1
test conditions :
date: / / time: ~
Atmospheric conditions
time atmospheric pressure ambient temperature relative humidity
×10hPa ℃ %
:
:

:
:
:
:
:
:

:
:
:

DECL-TPCIL-PGT-001 31 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

APPENDIX J: Other Record Table


Original Data 2-1
test conditions :
date: / / time: ~
APH INLET O2/CO/NOx (A SIDE)
Top Bottom
1 2 3 4
O2 CO NO O2 CO NO O2 CO NO O2 CO NO
% ppm ppm % ppm ppm % ppm ppm % ppm ppm
A 1
2
3
4
5
6
7
8
9
10
B 11

DECL-TPCIL-PGT-001 32 / 35
Performance Test Procedure (Boiler efficiency) Rev. 3

APPENDIX J: Other Record Table


Original Data 2-2
test conditions :
date: / / time: ~
APH INLET O2/CO/NOx (B SIDE)
Top Bottom
1 2 3 4
O2 CO NO O2 CO NO O2 CO NO O2 CO NO
% ppm ppm % ppm ppm % ppm ppm % ppm ppm
A 1
2
3
4
5
6
7
8
9
10
B 11

DECL-TPCIL-PGT-001 33 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

APPENDIX J: Other Record Table


Original Data 3-1
test conditions :
date: / / time: ~
APH OUTLET O2/CO/NOx/ GAS TEMP (A SIDE)
Top Bottom

1 2 3 4
A O2 CO NO T O2 CO NO T O2 CO NO T O2 CO NO T
% ppm ppm ℃ % ppm ppm ℃ % ppm ppm ℃ % ppm ppm ℃
1
2
3
4
5
6
7
8
9
B 10

DECL-TPCIL-PGT-001 34 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

APPENDIX J: Other Record Table


Original Data 3-2
test conditions :
date: / / time: ~
APH OUTLET O2/CO/NOx/ GAS TEMP (B SIDE)

Top Bottom
1 2 3 4
A O2 CO NO T O2 CO NO T O2 CO NO T O2 CO NO T
% ppm ppm ℃ % ppm ppm ℃ % ppm ppm ℃ % ppm ppm ℃
1
2
3
4
5
6
7
8
9
B 10

DECL-TPCIL-PGT-001 35 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Sample Calculation of Boiler Efficiency

单位
内容Title 符号symbol Formula sample Formula
unit

碳C(ar) MpCF % analysis


氢H(ar) MpH2F % analysis
氧O(ar) MpO2F % analysis
氮N(ar) MpN2F % analysis
硫S(ar) MpSF % analysis
水分Mt(ar) MpWF % analysis
灰分A(ar) MpAsF % analysis
挥发分V(ar) MpVm % analysis
固定碳FC(ar) MpFc % analysis
高位热值HHVF(ar) HHVF KJ/Kg analysis

飞灰中未燃尽碳Unburned Carbon in fly ash MpCRsf % analysis

炉渣中未燃尽碳Unburned Carbon in bottom ash MpCRsb % analysis

飞灰比例The proportion of fly ash MpRsf design

炉渣比例 The proportion of bottom ash MpRsb design

灰渣中的未燃尽碳Unburned Carbon in the residue MpCRs % ASME 5.10-6

DECL-TPCIL-PGT-001 36 / 35
Performance Test Procedure (Boiler efficiency) Rev. 3

灰渣质量Mass of Residue MFrRs kg/kg ASME 5.10-1

燃料中未燃尽碳Unburned Carbon in Fuel MpUbc % ASME 5.10-8

已燃碳Carbon Burned MpCb % ASME 5.10-9

灰渣中未燃碳造成的损失Loss Due to Unburned Carbon


QpLUbc % MpUbc*HHVCRs/HHVF ASME 5.14-8
in Residue

燃烧空气性质 Air property

理论空气量Theoretical Air MFrThACr kg/kg ASME 5.11-6

燃料燃烧干烟气产物摩尔数moles of dry products from


the combustion MoDPc mol/kg ASME 5.11-12
of fuel

排烟干烟气中氧浓度 oxygen concentration in the flue measure


DVpO2 %
gas AH(En/Lv) measure

ASEM 5.11-11
过量空气率Excess Air AH(En/Lv) XpA %

ASME 5.11-29
干空气量Dry Air AH(En/Lv) MFrDA kg/kg

空气相对湿度relative humidity Rhm % measure

DECL-TPCIL-PGT-001 37 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

大气压力atmosphere press Pa Pa measure

℃ measure
干球温度dry balltemperature Tdb

干球温度下水蒸汽饱和压力vapour saturation press of


PsWvTdb Pa ASME 5.11-4
Tdb

空气绝对湿度absolute humidity MFrWDA kg/kg ASEM 5.11-1

烟气产物 Gas products

燃料水分带入的水分量Moisture From H2O(water) in Fuel MFrWF kg/kg MFrWF= MpWF/100 calculation

燃料中氢燃烧产生的水分Moisture From the Combustion


MFrWH2F kg/kg 8.937* MpH2F/100 ASME 5.12-3
of Hydrogen in the Fuel

MfrWA1= MfrThACr1* MFrWDA calculation


空气中的水分Moisture in Air (En/Lv) MFrWA kg/kg
calculation
MfrWA2= MfrThACr2* MFrWDA

calculation
烟气中总水分Total Moisture in Flue Gas (En/Lv) MFrWFg kg/kg MFrWFg= MFrWF+ MFrWH2F+ MFrWA
calculation

(100-MpAsF-MpUbC-MFrSc*MpSF)/100H
来自燃料的湿烟气量Wet Gas From Fuel MFrFgF kg/kg ASME 5.12-1
HVF
MFrFg=MFrFgF+ MFrWFg+ MfrWA+ calculation
湿烟气总量Total Wet Flue Gas Weight (En/Lv) MFrFg kg/kg MFrWH2F+ MFrWF
calculation
干烟气总量Dry Flue Gas Weight (En/Lv) MFrDFg kg/kg MFrDFg1=MqFgz1- MqWFgz1 calculation

DECL-TPCIL-PGT-001 38 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

calculation
MFrDFg2=MqFgz2- MqWFgz2
℃ measure
排烟温度gas temperature leaving the air heater TFgLv
K TFgLv2= TFgLv1+273.15 calculation
预热器进口风温
Preheater inlet air temperature

进入空气预热器二次风温Temp of secondary air in air


TA2 ℃ measure
preheater inlet
进入空气预热器一次风温Temp of primary air in air
TA1 ℃ measure
preheater inlet
进入空气预热器二次风量Flow of secondary air in air
MFrA2 t/h measure
preheater inlet
进 入 空 气 预 热 器 一 次 风 量 Flow of primary air in air
MFrA1 t/h measure
preheater inlet
TmnAEn1= (TA2* MFrA2+ MFrA1*
℃ calculation
进入系统空气平均温度Average Entering Air Temperature TMnAEn TA1)/( MFrA1+ MFrA2)
K TmnAEn2= TmnAEn1+273.15 calculation
空气预热器“0”漏风修正排烟温度
Corrected APH “0” air infiltration exhaust temperature
75=112.9/(112.9+37.6)*100/100
一次风漏风率Priamry air leakage rate AL1 % design

25=37.6/(112.9+37.6) *100/100
二次风漏风率Sendary air leakage rate AL2 % design

TAEn1=(AL1/100*TA1)+ (AL2/100*TA2)
让 锅 炉 漏 风 加 权 平 均 温 度 值 Weighted average ℃ calculation
TAEn
temperature of air leakage TAEn 2 = TAEn1+273.15
K calculation

DECL-TPCIL-PGT-001 39 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

(-131.0558+0.458*TAEn2-0.107*10-3*TA
Calculation
漏风温度下干空气焓值Enthalpy of dry air under air En2^2+0.1779*10-6*TAEn2^3-0.9249*10-1
HDAEn kJ/kg 1 asper ASME
leakage temperature *TAEn2^4+0.1682*10-13*TAEn2^5)
formula
*2.326
(-239.4034+0.827*TAEn2-0.1798*10-3*T
Calculation
漏 风 温 度 下 水 蒸 汽 焓 值 Enthalpy of steam under air AEn2^2+0.3935*10-6*TAEn2^3-0.2416*10
HWvEn kJ/kg -9 asper ASME
leakage temperature *TAEn2^4+0.6069*10-13*TAEn2^5)
formula
*2.326
(1-MFrWDA/(1+MFrWDA))*HDAEn+
漏风温度下湿空气焓值Enthalpy of wet air under air
HAEn kJ/kg MFrWDA/(1+ MFrWDA)*HWvEn calculation
leakage temperature

(-131.0658+0.458*TFgLv2-0.107*10-3*T
Calculation
排烟温度下干空气焓值Enthalpy of dry air under exhaust FgLv2^2+0.1779*10-6*TFgLv2^3-0.9249*1
HDATFgLv kJ/kg asper ASME
temperature 0-11*TFgLv2^4+0.1682*10-13*TFgLv2^5)
formula
*2.326
(-239.4034+0.827*TFgLv2-0.1798*10-3*
Calculation
排烟温度下水蒸气焓值Enthalpy of water steam under TFgLv2^2+0.3935*10-6*TFgLv2^3-0.2416*
HWvLv kJ/kg asper ASME
exhaust temperature 10-9*TFgLv2^4+0.6069*10-13*TFgLv2^5)
formula
*2.326
排烟温度下湿空气焓值Enthalpy of wet air under exhaust (1-MFrWDA/(1+MFrWDA))*HDATFgLv+
HATFgLv kJ/kg calculation
temperature MFrWDA/(1+ MFrWDA)* HWvLv

kJ/(kg· (HATFgLv-HAEn)/(TFgLv-TAEn)
湿空气平均比热容Wet air mean specific heat capacity MnCpA calculation
K)

(-123.1899+0.4066*TFgLv2+0.5795*10-5
Calculation
排烟温度下干烟气焓值Enthalpy of dry flue gas under *TFgLv2^2+0.6331*10-7*TFgLv2^3-0.2924
HDFgLv kJ/kg asper ASME
exhaust temeperature *10-10*
formula
TFgLv2^4+0.2491*10-14*TFgLv2^5)*2.326

DECL-TPCIL-PGT-001 40 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

湿烟气中蒸气质量份额Steam mass ration of wet flue gas


MFrWFg % MFrWFg/MFrFg calculation
AH(En)

排烟温度下湿烟气焓值Enthalpy of wet flue gas under


HFgLv kJ/kg calculation
exhaust temeperature

cyclic iterative
假设“0”漏风排烟温度Assemed “0”air infitration exhaust ℃ assumed
TFgLvC calculation
temeperature TFgLvC2= TFgLvC1+273.15
K calculation

(-123.1899+0.4066*TFgLv2+0.5795*10-5
Calculation
假设“0”漏风排烟温度下干烟气焓Enthalpy of dry flue gas *TFgLv2^2+0.6331*10-7*TFgLv2^3-0.2924
HDFgLvC kJ/kg asper ASME
under assumed “0”air infitration exhaust temeperature *10-10*TFgLv2^4+0.2491*10-14*TFgLv2^5)
formula
*2.326

(-239.4034+0.827*TFgLv2-0.1798*10-3*
Calculation
假 设 “0” 漏 风 排 烟 温 度 下 水 蒸 汽 焓 Enthalpy of steam TFgLv2^2+0.3935*10-6*TFgLv2^3-0.2416*
HWvLvC kJ/kg asper ASME
under assumed “0”air infitration exhaust temeperature 10-9*TFgLv2^4+0.6069*10-13*TFgLv2^5)
formula
*2.326

假设“0”漏风排烟温度下湿烟气焓Enthalpy of wet flue gas


HFgLvC kJ/kg calculation
under assumed “0”air infitration exhaust temeperature

湿 烟 气 平 均 比 热 容 Wet flue gas mean specific heat kJ/(kg·


MnCpFg calculation
capacity K)

“0”漏风修正的排烟温度Corrected “0”air infitration flue ℃ ASME 5.13-6


TFgLvCr
gas temperature

K TFgLvCr1+273.15

DECL-TPCIL-PGT-001 41 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

损失计算 loss calculation

(-123.1899+0.4066*TFgLv2+0.5795*10-5
Calculation
排烟温度下的干烟气焓Enthalpy of dry flue gas under *TFgLv2^2+0.6331*10-7*TFgLv2^3-0.2924
HDFgLvCr kJ/kg asper ASME
flue gas exhaust temperature *10-10*TFgLv2^4+0.2491*10-14*TFgLv2^5)
formula
*2.326

干烟气热损失Dry Gas Loss QpLDFg % 100MqDFg*HDFgLyCr ASME 5.14-3

排 烟 温 度 下 蒸 汽 焓 Enthalpy of steam under flue gas


HStLvCr kJ/kg ASME 5.19-6
exhaust temperature

基准温度下的饱和汽焓Enthalpy of saturated vapor under 1


HWv kJ/kg HWRe=2.326*(TRe-32) ASME 5.14.2.1
reference temperature
H 2 燃烧生成水造成的损失Loss due to Water Formed from
QpLH2F % ASME5.14-4
the Combustion of H2 in the fule

燃料中的水分造成的损失Loss Due to Water (H2O) In the


QpLWF % ASME 5.14-5
Fuel

(0.4408 * (1.8*TFgLvCr-459.67) + 2.381 *


Calculation
排烟温度下水蒸汽焓Enthalpy of water steam under flue 10^-5 *(1.8*TFgLvCr-459.67)^2 +
HWLvCr kJ/kg asper ASME
gas exhaust temperature 9.638*10^-9 * (1.8*TFgLvCr-459.67)^3 –
formula
34.1)*2.326

空气中水分引起的损失Loss Due to Moisture in Air QpLWA % ASME 5.14-7

空气预热器入口CO测量值Measured CO at APH inlet DVpCOEn % measure

空气预热器入口干烟气摩尔数Mole number of APH inlet


MoDFgEn mol/kg calculation
dry flue gas

DECL-TPCIL-PGT-001 42 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

烟气中CO引起的损失 Loss Due to Carbon Monoxide in DvpCO*MoDFgLv*28.01*10111*100/HHV


QpLCO % ASME 5.14-10
flue Gas F

表面辐射与对流引起的损失Loss Due to Surface Radiation


QpLSrc % design
and Convection
he formula is from
ASME 5-19.3
(Enthalpy of Dry
排烟温度下飞灰焓 Enthalpy of fly ash under exhaust (0.16 * MOLT + 1.09*10^-4 * MOLT^2 –
HRsf kJ/kg residue) ,
temperature 2.843 * 10 ^ -8 * MOLT^3 – 12.95)*2.326
transferred from
English Unit to
Metric Unit.

炉渣焓 residue enthalpy HRsb kJ/kg ASME5.14.5

飞灰显热引起的损失 Loss Due Sensible Heat of Fly Ash


QpLRsf % MpRsf*MFrRs*HRsf/HHVF ASME5.14-14
Residue

底渣显热引起的损失 Loss Due Sensible Heat of Bottom


QpLRs % MpRsb*MFrRs*HRsb/HHVF ASME5.14-14
Residue

漏风热损失 design
QpLALg %
Loss due to air infiltration Include in QpLUN

磨煤机排出石子煤质量流量 MrPr Kg/s measure

磨煤机排出石子煤高位发热量 HHVPr kJ/kg analysis

DECL-TPCIL-PGT-001 43 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

磨煤机出口温度 TPr ℃ measure

K TPr+273.15

磨煤机排出石子煤携带的显热 HPr kJ/kg ASME5.14.5

锅炉燃料量 MrF Kg/s measure

磨煤机排出石子煤质量 MqPr kg/kJ MrPr/MrF*HHVF ASME5.14-12

磨煤机排出石子煤热损失
QpLPr % 100*MqPr*(HHVPr+HPr) ASME5.14-11
Loss due to pulverizer rejects

氮氧化物生成热损失
% ASME 5.14.8
Heat loss due to NO X

不明确损失
QpLUN % design
Unaccountable loss

QpL= QpLUbc+ QpLDFg+ QpLH2F+


QpLWF+ QpLWA+ QpLCO+ QpLSrc+ Calculation
损失总和summation of losses QpL
% QpLRs+ QpLRsf ASME 5.14
+QpLPr+QpLALg+QpLNOX+ QpLUN

Calculation of Heat Credits

TMnAEn TmnAEn1= (TA2* MFrA2+ MFrA1* calculation


进入系统空气平均温度Average Entering Air Temperature ℃

DECL-TPCIL-PGT-001 44 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

TA1)/( MFrA1+ MFrA2)

K TmnAEn2= TmnAEn1+273.15 calculation

( -131.0558+0.458* TMnAEn
Enthalpy of Dry Air at the Average air temperature entering 2-0.107*10-3* TMnAEn ^2+0.1779*10-6*
HDAEn KJ / Kg ASME 5-19.10
the steam Generator TMnAEn ^3-0.9249*10-11* TMnAEn
^4+0.1682*10-13* TMnAEn^5)
MFrDAEn*HDAEn*100/HHVF
Credit Due toEnetring Dry Air QpBDA % ASME 5.15-1

Enthalpy of Water vapour at the Average air temperature


HWvEn KJ / Kg ASME 5-19.4
entering the steam Generator

Credit Due to Moisture in Entering air QpBWA % MFrWAEn*HWvEn*MqDA*100/HHVF ASME 5.15-2

Temperature of Fuel entering the steam generator TFEn℃ ℃

Temperature of Fuel entering the steam generator TFEn ℉ οF = ℃ × 1.8 + 32 Tdb

(0.152*TFEN+1.95*10^-4*TFEN^2-12.86)
固定碳焓 Enthalpy of fixed carbon HFc kJ/kg ASME 5.19-9
*2.326
(380.152*TFEN+2.25*10^-4*TFEN^2-30.5
一次挥发分焓 Enthalpy of primary volatile matter HVm1 kJ/kg ASME 5.19-10
94)*2.326
(0.7*TFEN+1.7*10^-4*TFEN^2-54.908)*2.
二次挥发分焓 Enthalpy of secondary volatile matter HVm2 kJ/kg ASME 5.19-11
326

灰焓 Enthalpy of ash HRs kJ/kg (0.17*T+0.8*10^-4*T^2-18.564)*2.326 ASME 5.19-12

水分焓 Enthalpy of water HW kJ/kg (TFEN-77)*2.326 ASME 5.19-13

Mass fraction of Volatile matter of coal on a dry and ash MFrVmCr Kg / Kg MFrVmCr = MFrVm / (1-MFrAsF – MFrWF) ASME 5.19-15

DECL-TPCIL-PGT-001 45 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

free basis

As
二次挥发分 Mass fraction of secondary volatile matter MFrVm2 Kg / Kg 0.1*(1-MpAsF-MpWF) ASME 5.19-18 MFrVmCr >
0.1

Mass fraction of primary volatile matter MFrVm1 Kg / Kg MFrVm1 = MFrVm – MFrVm2 ASME 5.19-19

As per
ASME
5-19.6
Hcoal = MFrFc*HFc + MFrVm1*HVm1 +
Enthalpy of the fuel at the temperature of fuel entering the based on
HFEn KJ / Kg MFrVm2*HVm2 + MFrWF*HW + ASME 5.19-8
steam generator the
MFrAsF*HRs,
proximate
analysis of
the coal.

Credit Due to Sensible heat in fuel QpBF ^% HFEn*100/HHVF ASME 5.15-3

Total Heat Credits QpB % QpBDA+QpBWA+QpBF calculation

锅炉效率Boiler Efficiency EFC % 1-QpL+QpB calculation

Boiler Efficiency Corrections losses

Refer from
Correcting due to Ambient Temperature ATDC %
corrections curves
Refer from
Correcting due to Fuel HHVF HHVFC %
corrections curves
Refer from
Correcting due to coal moisture CMDC %
corrections curves

DECL-TPCIL-PGT-001 46 / 47
Performance Test Procedure (Boiler efficiency) Rev. 3

Refer from
Correcting due to Feed Water Temperature FTDC %
corrections curves
Refer from
Correcting due to excess air EADC %
corrections curves
Refer from
Correcting due to coal hydrogen CHDC %
corrections curves
Refer from
Correcting due to coal ash content CACDC %
corrections curves
Refer from
Correcting due to moisture in air MIADC %
corrections curves
Refer from
Correcting due to pulverized coal fineness PCFD %
corrections curves
Refer from
Correcting due to the fiue gas temperature at AH outlet FGTDC %
corrections curves
ATDC+HHVFC+CMDC+FTDC+EADC+CHDC+
Sum of Corrections TCV %
CACDC+MIADC+PCFD+FGTDC

Corrected Boiler Efficiency EF % EFC+TCV

DECL-TPCIL-PGT-001 47 / 47