Sei sulla pagina 1di 70

Busbar Protection

High Impedance Busbar


Protection
Without Busbar Protection

F1 F2

There are fewer faults on busbars than on other parts of the power system.
● No dislocation of system due to accidental operation of busbar protection.
● Slow fault clearance.
Busbar faults at F1 and F2 are cleared by remote time delayed protection on circuits feeding the
faults:
Time Delayed Overcurrent or
Time Delayed Distance Protection

Schneider Electric - Infrastructure Automation – 14/05/2012 3


With Busbar Protection

BUSBAR
ZONE

F1 F2

● Fast clearance by breakers at the busbars


● Where busbars are sectionalised,
Protection can limit the amount of system
disruption for a busbar fault

Schneider Electric - Infrastructure Automation – 14/05/2012 4


Busbar Faults Are Usually Permanent

CAUSES :
● Insulation failures
● Circuit breaker failures
● Falling debris
● Isolators operated outside their ratings
● Safety earths left connected
● Current transformer failures

THEREFORE :
Circuit breakers should be tripped and locked
out by busbar protection

Schneider Electric - Infrastructure Automation – 14/05/2012 5


Busbar Protection must be :

● RELIABLE
● Failure could cause widespread damage to the substation
● STABLE
● False tripping can cause widespread interruption of supplies to
customers
● DISCRIMINATING
● Should trip the minimum number of breakers to clear the fault
● FAST
● To limit damage and possible power system instability

Schneider Electric - Infrastructure Automation – 14/05/2012 6


Methods of Providing Busbar Protection

● Frame to Earth (Leakage) Protection

● Differential Protection : High Impedance


Low Impedance

● Directional Comparison (Blocking Schemes) Protection

Schneider Electric - Infrastructure Automation – 14/05/2012 7


Frame Leakage Protection

Schneider Electric - Infrastructure Automation – 14/05/2012 8


Frame Earth Protection Scheme
● Only an earth fault system

● Involves measuring fault current from switchgear frame to earth

● Switchgear insulated by standing on concrete plinth

● Only one earthing point allowed on switchgear

● C.T. mounted on single earth conductor used to energise instantaneous


relay

● All cable glands must be insulated

Schneider Electric - Infrastructure Automation – 14/05/2012 9


Current Distribution for External Fault
Outgoing feeder
Switchgear frame
IF = I1 + I2

Generator

Busbar
Switchgear frame
bonding bar
Frame-leakage
current
transformer
System
Earth bar earthing
resistor

I1 + I2

I1
Frame insulation I1 I2 Earthing electrode
resistance to earth resistance (< 1Ω)
(> 10Ω)

Schneider Electric - Infrastructure Automation – 14/05/2012 10


Frame Leakage Busbar Protection
Simple, Economical.

Suitable for phase segregated indoor metal clad switchgear. Only E/F
protection required.

Setting of instantaneous E/F relay (64)


= < 0.3 IF(min)
= > 0.1 IF(max)

Disadvantages :
Insulation of switchgear frame and between sections.
Insulation of cable glands to prevent spurious
currents during through faults.

Schneider Electric - Infrastructure Automation – 14/05/2012 11


Frame Leakage Protection
Check Feature
To differentiate between a power system fault and an earth fault from another circuit
within the switchgear.

The check relays pick up for both internal and external faults.

Both check and discriminating relays must operate before tripping can occur.

The various methods of obtaining the check feature are :-

(a) Neutral check provided by a relay energised from a single c.t. in the
power system neutral.
(b) Residual check provided by a relay energised from a residually
connected c.t. on the busbar incomers.
(c) Residual voltage check provided by a voltage relay energised from a
broken delta v.t. supply.

Check relays are normally self-reset in order to avoid having to reset the relay
after each external fault.

Schneider Electric - Infrastructure Automation – 14/05/2012 12


Single Zone Frame - Earth Protection
with Neutral Check
Switchgear frame

G H J K

Frame-earth
fault relay
Neutral check relay

64
64 CH

Trip all breakers


circuit
+

Schneider Electric - Infrastructure Automation – 14/05/2012 13


High Impedance Protection

Schneider Electric - Infrastructure Automation – 14/05/2012 14


High Impedance Protection
This is a versatile and reliable protection system applied to many different
Busbar configurations.

If CT requirements are met, scheme performance may be predicted by


calculation without heavy current conjunctive tests.

Through Fault Stability


Busbar protection stability limit is based on maximum through fault current.

Generally this value is derived from the rating of the associated switchgear
irrespective of existing fault level, since it can be expected that system will
develop up to limit of rating.

Schneider Electric - Infrastructure Automation – 14/05/2012 15


Basic Circulating Current Scheme
External Fault

Schneider Electric - Infrastructure Automation – 14/05/2012 16


Basic Circulating Current Scheme
Internal Fault

Schneider Electric - Infrastructure Automation – 14/05/2012 17


High Impedance Busbar Protection
Simple system to apply and extend.
High sensitivity for phase and earth
faults.

Extremely stable for external faults.


CT requirements:
Equal ratios
Class ‘X’
May require stabilising resistors,
RST.
May require non-linear resistors
RST (Metrosils).
METROSIL
87

Schneider Electric - Infrastructure Automation – 14/05/2012 18


High Impedance Protection

Add a stabilising resistor which increases the operating


voltage of the protection such that it will not operate for
through faults
Schneider Electric - Infrastructure Automation – 14/05/2012 19
High Impedance Protection
Equivalent circuit

RCT RLY RLX RCT

ZM ZM
R

Schneider Electric - Infrastructure Automation – 14/05/2012 20


Equivalent circuit with 1 CT saturated

RCT RLY RLX RCT


IY

VR CT saturated

VR = IY (RLX + RCT)
VS > VR
Schneider Electric - Infrastructure Automation – 14/05/2012 21
Stabilising resistor calculations

RST + RR is the total resistance required R

IS R = VS
RST
R
{ RR VR
R = VS
IR
IS RST = R – RR

If RR is given in VA then

RR = VA/IS²

Schneider Electric - Infrastructure Automation – 14/05/2012 22


Numeric High Impedance

● The voltage measured by the relay during CT saturation is non


sinusoidal
● The resulting measurement depends upon the analogue circuitry and
digital algorithm
● As part of type testing a Dimensioning factor K is determined
●Vs = K.Is(Rct+Rl)

Schneider Electric - Infrastructure Automation – 14/05/2012 23


Knee-Point Requirements

+10% Vk
Exciting Voltage (VS)

Vk
For High Impedance
+50% Iek Vk>2Vs

●Fast operation
●Dependant upon
maximum through fault

Iek
Exciting Current (Ie)
Schneider Electric - Infrastructure Automation – 14/05/2012 24
Operating Time

● Depends on measurement technique but will always be improved by


increasing the Vk/Vs ratio

Schneider Electric - Infrastructure Automation – 14/05/2012 25


Primary Operating Current (P.O.C)
The value of primary operating current should be around 30% of
minimum fault current available. This ensures sufficient relay
current during internal fault conditions for high speed operation.

Since in each zone of protection there are several CT’s in parallel with
the relay and each other, the combined CT magnetising currents will
increase the primary operating current (P.O.C).

P.O.C. = CT ratio (IR + INLR + nIM)

where :-
IR = Relay setting current
IM = CT magnetising current (one CT at relay
setting voltage)
n = Number of paralleled CT’s
INLR = Non linear resistor current at relay setting
voltage
Schneider Electric - Infrastructure Automation – 14/05/2012 26
Equivalent circuit for Internal fault

RCT RLY RLX RCT


IP
RST
ZM ZM
VS
RR
IM IS IM

VS = IS (RST + RR)
IM = VS/ZM
IP = T (IS + n IM)
Schneider Electric - Infrastructure Automation – 14/05/2012 27
Secondary Voltage at maximum fault level

RCT RLY RLX RCT


IP
RST
ZM ZM
VR
RR

VR < VF = IP/T (RST + RR + RCT + RLY)


VR > VK
VR ≈ 2 √ 2VK (VK – VF)
Schneider Electric - Infrastructure Automation – 14/05/2012 28
Metrosil limitation of relay voltage

IOP Required when peak


relay voltage exceeds
3kV
RST Non linear
VM resistance
(metrosil) V = C Iβ DC
RR
IM IR √2 Vs = C (Irms/0.52)β
AC

Schneider Electric - Infrastructure Automation – 14/05/2012 29


Current Transformers

Schneider Electric - Infrastructure Automation – 14/05/2012 30


CT Wiring Supervision

Open circuit connections between CT’s and relay circuit result in unbalance
currents which may operate the protection.

Supervision is applied by a voltage relay across differential relay circuit.

Supervision relay is time delayed, gives alarm and also shorts out bus wires to
protect differential relay circuit.

Typical effective setting is 25 primary amps or 10% of lowest circuit rating,


whichever is greater.

Schneider Electric - Infrastructure Automation – 14/05/2012 31


CT Wiring Supervision
I1

CT1 I3
RST I2 I4
V R ZM2 ZM3 ZM4
Super
vision RR
relay
I1

Voltage measured by supervisio n relay


V = Ι1 (R + Z M2 + Z M3 + Z M4 )
If supervisio n relay setting = VSP
Out - of - balance current to operate the supervisio n relay
V V V V
Ι = SP + SP + SP + SP
R Z M2 Z M3 Z M4

Schneider Electric - Infrastructure Automation – 14/05/2012 32


Differential Relay Circuit
A
B
Zone bus wires
C
N

95X
95X Bus wire short contacts
95X

95 Supervision
relay

Metrosil
resistors
Stabilising
v v v resistors

87 87 87

Schneider Electric - Infrastructure Automation – 14/05/2012 33


Numeric CT supervision
● Use an additional current stage
● Still requires time delay & latched CT shorting contacts
●Can use auxiliary relay
● May need to use earth fault element to achieve desired sensitivity

Schneider Electric - Infrastructure Automation – 14/05/2012 34


Effect of C.T. Location on Busbar
Protection Performance

Interlocked
Circuit overcurrent
protection relay

Circuit
Circuit protection
protection
Busbar
protection
Busbar
protection

Busbar Interlocked
protection overcurrent
relay

All C.T.s on line side All C.T.s on Busbar side


Overlapping of circuit breaker
C.T.s of circuit breaker

Schneider Electric - Infrastructure Automation – 14/05/2012 35


Low Impedance Busbar
Protection
HV Application: Busbar Protection
Kirchhoff’s Principle applied to a healthy system

ΣI=0

IA I IC
B

IA = IB + IC
IA - IB - IC = 0
Schneider Electric - Infrastructure Automation – 14/05/2012 37
HV Application: Busbar Protection - 2
Kirchhoff’s Principle applied to a system with a fault

ΣI≠0

IA I IC
B

IA ≠ IB + IC
IA - IB - IC ≠ 0 = IF
Schneider Electric - Infrastructure Automation – 14/05/2012 38
MiCOM P746 - Architecture

● The P746 or the 3 P746 are mounted in only one


cubicle.
● This architecture is ideal for the refurbishment of
existing substations

Centralised Solution

Schneider Electric - Infrastructure Automation – 14/05/2012 39


MiCOM P740 Architecture

● The Peripheral Units are installed in individual switchgear bays


distributed around the substation
● The maximum fibre optic length between the
Peripheral Units and the Central Unit is 1 km
● That leads to wiring cost reduction

Distributed Solution

Schneider Electric - Infrastructure Automation – 14/05/2012 40


High Impedance Principle
•Stability is entirely due to introducing a stabilising resistor in-
circuit.
•It is a simple, reliable and circulating current scheme
(CT must have same ratio & must be high accuracy - Class PL)
•The knee point voltage of the CTs needs to be relatively high
•Metrosil may be required
•The CTs are usually not shared with other protection
•The magnetising current can desensitise the scheme
•The scheme is very fast
•Isolator contacts are needed to switch the full CT secondary
current between the zones
•Extending the scheme is quite simple
•Buswire supervision can be offered with Bus wire supervision
relays

Schneider Electric - Infrastructure Automation – 14/05/2012 41


Low Impedance/Biased Principle
•Stability is due to the bias characteristics of the scheme
•CTs can have different ratios,
•Scheme bias characteristic can cater for lesser accuracy CTs
(class 5P)
•CTs with moderate knee point voltages can be used
•Metrosils are never required
•It is easier to share CTs with other protection
•Number of // circuits does not affect the primary operating current
•Tripping is fast
•Isolator contact are not needed to switch heavy currents.
•Expanding the scheme can be complex
•Self supervision and breaker fail protection is easier to integrate
•Numerical scheme offer many fault, event and recording
capabilities
•Some schemes allow for distributed topology

Schneider Electric - Infrastructure Automation – 14/05/2012 42


Low Impedance Requirements

•Key Requirements of Low Impedance Bus Protection

•Stability for External Faults


•Biased Differential Characteristic
•CT Saturation Detection

•Accurate Modelling of the Primary Plant


•CB Status Contacts

•Security and Reliability


•Multiple Tripping Criteria

Schneider Electric - Infrastructure Automation – 14/05/2012 43


Bias Differential Characteristic
Phase and Earth Fault Elements
idiff (t)

Tripping
area

X X
i1 i2
X
X X ID>2 RESTRAIN AREA
i3 in IS
ID>1
ibias (t)

Differential current: idiffnode (t) = i1 + i2 + i3 + … + in


Bias current: ibias(t) = |i1|+ |i2|+ | i3| + … + |in| = Σ|i|

Schneider Electric - Infrastructure Automation – 14/05/2012 44


CT Saturation Internal Fault

3000
3000 / 5/A5 A 3000 / 5 A
9000 A 3000 / 5 A 9000 A
X 10500 A X
20600 A
X
X X X
X
150 / 5 A 1500 / 5 A 500 / 5 A 150 / 5 A
100 A 1400 A 1000 A 100 A

Schneider Electric - Infrastructure Automation – 14/05/2012 45


CT Saturation External Fault

3000
3000 / 5/A5 A 3000 / 5 A
9000 A 3000 / 5 A 9000 A
X 10500 A X
X
X X X
X
500 / 5 A
150 / 5 A 1500 / 5 A 19600 A 150 / 5 A
100 A 1400 A 39.2 x In 100 A
Saturation

Schneider Electric - Infrastructure Automation – 14/05/2012 46


Typical conditions for CT saturation

● Large offset waveform


● Dependant upon fault level and X/R ratio

IA IB

Schneider Electric - Infrastructure Automation – 14/05/2012 47


CT Saturation
● Time-to-saturation is important in the design and application of protective relays
● The time-to-saturation of a CT is determined by the following parameters:
● Fault current magnitude
● Remnant flux in the CT core
● Degree of fault current offset
● Secondary circuit impedance
● Saturation voltage
● Turns ratio

Schneider Electric - Infrastructure Automation – 14/05/2012 48


CT Saturation
Secondary waveforms with increasing remanent flux

Schneider Electric - Infrastructure Automation – 14/05/2012 49


CT Saturation
Secondary waveforms with increasing remanent flux

Schneider Electric - Infrastructure Automation – 14/05/2012 50


CT Saturation
Secondary waveforms with increasing remanent flux

Schneider Electric - Infrastructure Automation – 14/05/2012 51


Low Impedance

Topology Processing

Schneider Electric - Infrastructure Automation – 14/05/2012 52


Topology Processing

The Concept of Nodes (not Zones)


Schneider Electric - Infrastructure Automation – 14/05/2012 53
Topology Useful notations

1st case: Bus coupler Open

Busbar

P742/3 P742/3 P742/3 P742/3

Dead Zone
=
Current Node 2 Dead Zones

P742/3
2nd case: Bus coupler Closed

Feeder

Remark: P742/3 P742/3


No creation of virtual zone
if one CT on the coupling Creation of a Virtual zone

Schneider Electric - Infrastructure Automation – 14/05/2012 54


Topology Processing
BB1

Isolator closed Isolator closed

CB opened CB opened

Dead Zone Dead Zone

PU 1 PU2
not connected not connected

Schneider Electric - Infrastructure Automation – 14/05/2012 55


Topology Processing
BB1

Trip Zone - Isolator Closed Isolator Closed


both breakers
closed to BB 1
Zone 1 = PU1 + PU2
CN1 = Zone 1 only
CB Closed
CB Closed

PU 1 PU 2
connected to BB1 connected to BB1

Schneider Electric - Infrastructure Automation – 14/05/2012


BUS BAR PROTECTION 56
Topology Processing
BB1

Trip Zone 1 -
one breaker
closed
Zone 1 = PU1
CN1 = Zone 1 CB Closed CB Open
only

Trip Other End


Intertrip
PU1 PU2 not
connected Local CN=
connected
to BB1 dead zone

Additional Tripping Zones


Schneider Electric - Infrastructure Automation – 14/05/2012 57
Topology Processing
PU3 connected
Dead Zone
to BB1

BB1 BB2

Coupling Open
Zone 1 = PU1+ PU3 Isolator Closed Isolator Closed
Zone 2 = PU2
CN1 = Zone 1
CN2 = Zone 2
Local CN=dead zone
CB Closed CB Closed

PU 1 PU2
connected to
connected to BB2
BB1
Schneider Electric - Infrastructure Automation – 14/05/2012 58
Topology Processing
PU3 connected
to BB1& BB2
BB1 BB2

Coupling Closed
Zone 1 = PU1 + PU3 Isolator Closed Isolator Closed
Zone 2 = PU2 + PU3
CN1 = Zone 1
CN2 = Zone 2
CB Closed CB Closed

PU 1 PU2
connected to BB1 connected to BB1
Schneider Electric - Infrastructure Automation – 14/05/2012 59
Topology Processing
PU3 connected
No CT
to BB1& BB2
BB1 BB2

Coupling Open
Zone 1 = PU1 Isolator Closed Isolator Closed
Zone 2 = PU2
CN1 = Zone 1
CN2 = Zone 2
CB Closed CB Closed

PU 1 PU2
connected to BB1 connected to BB1
Schneider Electric - Infrastructure Automation – 14/05/2012 60
Topology Processing
No CT PU3 connected
to BB1& BB2
BB1 BB2

Coupling Closed
Zone 1 = PU1 Isolator Closed
Zone 2 = PU2 Isolator Closed
CN1 = Zone 1+Zone 2

CB Closed CB Closed

PU 1 PU 2
connected to BB1 connected to BB1
Schneider Electric - Infrastructure Automation – 14/05/2012 61
Topology Processing

BB1

BB2

Zone 1 = PU1
Zone 2 = PU2
CN1 = Zone 1
CN2 = Zone 2

PU 1 PU2
connected to BB1 connected to BB2
Schneider Electric - Infrastructure Automation – 14/05/2012 62
Topology Processing

BB1

BB2

Zone 1 = PU1
Zone 2 = PU2
CN1 = Zone 1 +
Zone 2

PU 1 PU2
connected to BB1 connected to BB2
Schneider Electric - Infrastructure Automation – 14/05/2012 63
Check Zone Supervision

Schneider Electric - Infrastructure Automation – 14/05/2012 64


Check Zone Supervision
● Check Zone element must operate for a bus bar trip command to be issued

Total Idiff = Sum of current node idiff


idiff(t) CZ = Σ (Σ i) 
● Any in-zone fault will be seen as zone differential current

● Any fault will also be seen as a check or total zone differential current

● Under plant discrepancy conditions there will be an equal but opposite current in
an adjacent zone cancelling this error in the check zone value and prevent mal-
operation

Schneider Electric - Infrastructure Automation – 14/05/2012 65


Check Zone
idiff (t)

Tripping
area

X X
i1 i2
X
X X ID>2 RESTRAIN AREA
i3 in IS
ID>1
ibias (t)

Differential current: idiffnode (t) = i1 + i2 + i3 + … + in


Bias current: ibias(t) = |i1|+ |i2|+ | i3| + … + |in| = Σ|i|

Schneider Electric - Infrastructure Automation – 14/05/2012 66


Blocking Schemes

Schneider Electric - Infrastructure Automation – 14/05/2012 67


Busbar Blocking Protection

Incomer

O/C Relay
BLOCK

O/C Relay O/C Relay O/C Relay O/C Relay

Schneider Electric - Infrastructure Automation – 14/05/2012 68


Selection of Relay Current and Time
Delay Settings

10.0

1.0
IDMT incomer
Time IDMT margin
(s) IDMT feeder
0.1 I >3 incomer
t >3 incomer
Time to block
I > feeder
Start
0.01
Current

Schneider Electric - Infrastructure Automation – 14/05/2012 69


Busbar Protection

Potrebbero piacerti anche