BTS Site Specific Documentation

1142 – BORROWDALE

LTE Flexi Multi Radio BTS

1 Site General Information

2 RF Final Site Configuration

3 Antenna System Installation Report

4 Antenna System Commissioning Report

5 BTS Installation Report

6 Transmission Installation Report

7 BTS Commissioning & Integration Report

8 Power System Installation Report

9 Site Inventory

10 Certificates

11 Appendix
LTE Flexi Multi Radio BTS

SITE SPECIFIC DOCUMENTATION

1142 – BORROWDALE

Document Revision History


Version Author Date Approved Version History
1-0 Taworn Pan-on 4 September 2014 First Issue

Number/Version Copyright © Nokia Networks Page


1-0 Company Confidential 2(23)
Paper Copy Uncontrolled
Number/Version Copyright © Nokia Networks Page
1-0 Company Confidential 3(23)
Paper Copy Uncontrolled
1. SITE GENERAL INFORMATION

1.1 Site Details Summary Document

Site Name  BORROWDALE

Site ID 1142

Address  Harare, Zimbabwe

Coordinates S -17.76139 E 31.08583

1.2 Site Access Information

Site Access   REQUIRED

Special Access
Measures
 

Other Comments  Greenfield Site

2G Flexi MultiRadio BTS SSD 4(23)


2. RF FINAL SITE CONFIGURATION

 Insert the document RF Final Site Configuration from the radio network plan
following this section.

2G Flexi MultiRadio BTS SSD 5(23)


3. ANTENNA SYSTEM INSTALLATION REPORT

3.1 Antenna System Configuration


  SECTOR 1 SECTOR 2 SECTOR 3

Antenna Type Code DBXLH-8585B-VTM DBXLH-8585B-VTM DBXLH-8585B-VTM

Number of Antennas 1 2 1 2 1 2

Set Direction 0 ° 120 ° 240 °


Mechanical Tilt 0 ° 0 ° 0 °
Electrical Tilt 900 4 ° 4 ° 4 °
Electrical Tilt 1800 4 ° 4 ° 4
Mounting Height 60 m. AGL 60 m. AGL 60 m. AGL
0
Sector 1 0

0
Sector 1 0
Ant. A Ant. B
+45 -45 +45 -45

-45 +45
Ant. A
Ant. B Ant. A +45 -45
+45
Antenna -45
Support
Structure -45 +45
Ant. A Ant. A
0 0 0 0
240 120 240 -45 120
+45

Sector 3 -45 +45 Sector 2 Sector 3 Sector 2


Ant. A Ant. B
+45 -45

2G Flexi MultiRadio BTS SSD 6(23)


3.2 Antenna Feeder Cable Configuration

Sector 1 Sector 2 Sector 3


-45O +45O -45O +45O -45O +45O
Cable 1 Cable 2 Cable 3 Cable 4 Cable 5 Cable 6
Cable Label 
Item/Description 
Feeder Cable Type: n/a n/a n/a n/a n/a n/a
1. (e.g. 1/2", 7/8”, 1-5/8")

2. Installed Feeder Cable length: n/a n/a n/a n/a n/a n/a

3. Number of Earth kits installed: n/a n/a n/a n/a n/a n/a

4. Number of EMPs installed: n/a n/a n/a n/a n/a n/a


Internal Jumper Cable Lengths
5. a.)* BTS  Feeder Cable n/a n/a n/a n/a n/a n/a
External Jumper Cable Lengths
6. a.)* Feeder Cable  Antenna n/a n/a n/a n/a n/a n/a

b.)* RF Mod  Antenna 3m n/a n/a n/a n/a n/a

c.)* RF Mod  Feeder Cable n/a n/a n/a n/a n/a n/a

d.)* 2G SYS Mod  RF Mod. Fiber 75m. Fiber 75m. Fiber 75m. Fiber 75m. Fiber 75m. Fiber 75m.

e.)* LTE SYS Mod  RF Mod. n/a. n/a n/a n/a n/a n/a

* Complete row relevant to antenna configuration:

2G Flexi MultiRadio BTS SSD 7(23)


3.3 Antenna System Installation Checklist
Checke
Description
d
Antennas mounted according to Standard Procedures and Site Specific Documents ü
Antenna height checked according to Final Site Configuration ü
Antenna forward direction set and checked according to Final Site Configuration ü
Mechanical tilting angle set and checked according to Final Site Configuration ü
Electrical tilting angle set and checked according to Final Site Configuration ü
Antenna mounting clamps & tilting kits checked, all screws tightened ü
Feeder cables installed according to Site Specific Documents ü
Feeder cables grounded at top of support structure close to the antenna ü
Feeder cables grounded at bottom of tower/mast ü
Feeder cables grounded at additional points (d > 80m) where applicable N/A N/A
Feeder cables grounded at the entry point to BTS N/A
Feeder cables secured in position with cable hangers and clamps ü
Feeder cables labelled correctly (at each end) ü
External jumper cable connectors checked and tightened at both ends ü
All external connectors checked for correct sealing ü
All jumper cable connectors checked and tightened at both ends ü
All jumper cables labelled correctly at both ends ü

Notes on Antenna System Installation

2G Flexi MultiRadio BTS SSD 8(23)


4. ANTENNA SYSTEM COMMISSIONING REPORT
4.1 Antenna System VSWR Measurement Results
           
    SECTOR 1 SECTOR 2 SECTOR 3
Cable Label:
Sweeptests Measurement Results:
VSWR for complete Antenna
System (NSN/Netone):
n/a n/a n/a n/a n/a n/a
RL for complete Antenna
System (NSN/Netone):
n/a n/a n/a n/a n/a n/a
Checklist of Printed Sweeptests Results:
Full Antenna Subsystem: n/a n/a n/a n/a n/a n/a

 Copies of Antenna Test Result files are printed after this section.

Note: Feeder less solution no feeder installed on site.


4.2 Antenna Measurement Equipment

Model: Serial Number: Manufacturer: Last Calibration Date:

N.B. Instrument calibration interval shall not exceed 12 month

2G Flexi MultiRadio BTS SSD 9(23)


4.3 Finishing Checklist
Checke
Description
d
All cables restored to normal position for BTS operation ü
All cable connectors properly tightened ü
All external connectors sealed and waterproof ü
Black Plastic Cable Ties placed on all external sealed cable connections (to secure the
ü
PVC tape)
Antenna system configuration table completed in Section 3.1 above ü
Feeder inventory list completed in Section 3.2 above ü
Paper copy of the antenna line test results included following each section ü
All VSWR measurement results are within the defined test limits. ü

Notes on Antenna System Commissioning

2G Flexi MultiRadio BTS SSD 10(23)


5. BTS INSTALLATION REPORT

5.1 BTS Configuration


Installed LTE Flexi BTS Configuration:

1+1+1 Other: __________________

Installed 2G Flexi Multi Radio BTS Configuration:

4+4+4+4+4+4 Other: __________________

2+2+2

Feeder Site / Feeder less Site Configuration:

Feeder

Feeder less

Installed LTE Flexi BTS Hardware Module/s:

FSMF – SYSTEM MODULE

FXEB – 1800 RF MODULE

Installed 2G Flexi Multi Radio Hardware Module/s:

ESMC – SYSTEM MODULE

FXEB – 1800 RF MODULE

FXDB – 900 RF MODULE

FIQB – TRANSMISSION SUBMODULE

FPFC – POWER DISTRIBUTION MODULE

FPMA – POWER MODULE

FPAA – AC/DC SUBMODULE

FPBB – BATTERY

Other: __________________

RF sharing on FXEB

2G Flexi MultiRadio BTS SSD 11(23)


BTS Equipment Installation Type and Location:

BTS EQUIP’T BTS EQUIP’T


BTS EQUIPMENT (ü) INSTALLATION INSTALLATION REMARKS
TYPE (ü) LOCATION (ü)
Shelter
Stack type Outdoor
LTE SYSTEM
MODULE Wall Mounted Tower N/A
Pole Mounted Rooftop
Shelter
Stack type Outdoor
2G SYSTEM
MODULE Wall Mounted Tower N/A
Pole Mounted Rooftop
Shelter
RF MODULE 1 Stack type Outdoor
(Sector 1/2/3) Wall Mounted Tower N/A
Pole Mounted Rooftop
Shelter
RF MODULE 2 Stack type Outdoor
(Sector 4/5/6) Wall Mounted Tower N/A
Pole Mounted Rooftop
Shelter
RF MODULE 3 Stack type Outdoor
1800 Module (FXEB)
(LTE) Wall Mounted Tower
Pole Mounted Rooftop
Shelter
POWER MODULE 1 Stack type Outdoor
FPFC feed 3 x RF
(FPFC) Wall Mounted Tower modules
Pole Mounted Rooftop
Shelter
POWER MODULE 2 Stack type Outdoor
Wall Mounted Tower N/A
Pole Mounted Rooftop
Shelter
POWER MODULE 3 Stack type Outdoor
Wall Mounted Tower N/A
Pole Mounted Rooftop

2G Flexi MultiRadio BTS SSD 12(23)


5.2 BTS Installation Checklist
Description Checked
Delivery is complete and undamaged ü
Minimum clearances are met ü
Adapter mechanics are installed (for wall and pole installation) N/A
Plinth is installed according to the instructions ü
Plinth is grounded ü
Transmission sub-module is installed according to the instructions ü
Power supply cable is connected ü
Modules are installed according to the instructions ü
Modules are grounded to the plinth ü
Module back covers are installed ü
Cable entries are installed ü
Antenna cables are connected according to the configuration ü
Internal power cables are connected ü
Transmission cables are connected ü
Optical fibre cables are cleaned and connected ü
External alarm cable is connected N/A
Cables between the modules on the same plinth are routed via internal
ü
cable entries
BTS External cables or cables between the modules on different plinths
ü
are routed via external cable entries
Cables are tied properly ü
Cable connector seals are firmly in place ü
Unused connectors are covered with IP seals ü
BTS is switched on and all units are ready for commissioning ü
Module front covers are installed ü
Site is clean and installation completed ü

Notes on BTS Installation

2G Flexi MultiRadio BTS SSD 13(23)


6. TRANSMISSION INSTALLATION
6.1 Transmission Configuration

SUBMODULE
INTERFACE USED (ü)
INSTALLED (ü)
E1 Interface 1
E1 Interface 2
E1 Interface 3
LTE E1 Interface 4
Gb Ethernet – EIF 1
Fast Ethernet – EIF 2
Fast Ethernet – EIF 3
E1 Interface 1
E1 Interface 2
E1 Interface 3
FIQB (2G) E1 Interface 4
Gb Ethernet – EIF 1
Fast Ethernet – EIF 2
Fast Ethernet – EIF 3

6.2 Transmission Installation Checklist

Description Checked
Transmission Sub module installed properly ü
Transmission cables installed as per specifications ü
Transmission DDF installed as per specifications ü
Transmission cables connected to specified transmission DDF ü

Notes on Transmission Installation

Outdoor and indoor DDF are installed with 10-pair tie-cable between them.

2G Flexi MultiRadio BTS SSD 14(23)


7. BTS COMMISSIONING AND INTEGRATION REPORT
7.1 Site Commissioning Parameters

ITEM VALUE
BTS Name BORROWDALE
BTS ID 911271
BTS IP Address 10.26.17.12
MME Name
MME ID
MME IP
NTP IP 10.26.8.84
Netmask 255.255.255.248
Frequency 1800 (1/1/1)
Tx Power 20W
BTS SW Release Version LN4.0_ENB_1202_902_09

7.2 BTS Commissioning Report

 Insert printed copy of BTS Commissioning Report following this section.

2G Flexi MultiRadio BTS SSD 15(23)


7.3 BTS Integration

Test Handset Details

MODEL SERIAL NUMBER PHONE NUMBER SIM NUMBER

Nokia E72 355239035163265 +263712800794

Voice Call (MOC Call) Success

CELL OK NA INITIALS / DATE COMMENTS

CELL 1 18 March 2015


CELL 2 18 March 2015
CELL 3 18 March 2015

Voice Call (MTC Call) Success

CELL OK NA INITIALS / DATE COMMENTS

CELL 1 18 March 2015


CELL 2 18 March 2015
CELL 3 18 March 2015

PS Call Success

CELL OK NA INITIALS / DATE COMMENTS

CELL 1 18 March 2015


CELL 2 18 March 2015
CELL 3 18 March 2015

2G Flexi MultiRadio BTS SSD 16(23)


8. POWER SYSTEM INSTALLATION REPORT
8.1 BTS Power Supply Configuration
Tap to Existing:

LTE System Module Circuit Breaker:


2G System Module Circuit Breaker: 60A
Input Voltage to System Module: - 54.24
RF Module Circuit Breaker: 60A
Input Voltage to RF Module: - 54.24

Not Applicable

Rectifier Equipment Implementation


Power System 1 / Serial No.
Power System 2 / Serial No.
Power System 3 / Serial No.
PC Serial No.
Rectifier Module type
ELTEK Other: ____________________
Rectifier Serial No. Rectifier 1: Rectifier 1:
Rectifier 2: Rectifier 2:
Rectifier 3: Rectifier 3:
Rectifier 4: Rectifier 4:

Battery Back-up Info


Battery Manufacturer:

No of Battery Banks: Battery Breakers (100A/bank):

Battery Unit Serial


Numbers:

BANK1 BANK1 BANK1 BANK1


Bat1 ______________ Bat1 ______________ Bat1 ______________ Bat1 ______________
Bat2 ______________ Bat2 ______________ Bat2 ______________ Bat2 ______________
Bat3 ______________ Bat3 ______________ Bat3 ______________ Bat3 ______________
Bat4 ______________ Bat4 ______________ Bat4 ______________ Bat4 ______________
Battery Open Circuit
Voltages:
Bank 1 _________V Bank 2 _________V Bank 3 _______V Bank 4 _________V
Block 1 _________V Block 1 _________V Block 1 _______V Block 1 _________V
Block 2 _________V Block 2 _________V Block 2 _______V Block 2 _________V
Block 3 _________V Block 3 _________V Block 3_ ______V Block 3 _________V
Block 4 _________V Block 4 _________V Block 4 _______V Block 4 _________V

NOTE: Battery Open CCT shall be carried out in warehouse prior delivery of batteries to site. Battery Open
Circuit Voltage below 12.30VDC should not be installed and are to be replaced!

2G Flexi MultiRadio BTS SSD 17(23)


9. SITE INVENTORY

9.1 NSN Supplied Equipment

Description Product Code Serial Number Quantity

LTE/2G BTS Antenna 1 DBXLH-8585B-VTM 14CN103036295 1

LTE/2G BTS Antenna 2 DBXLH-8585B-VTM 14CN103036286 1

LTE/2G BTS Antenna 3 DBXLH-8585B-VTM 14CN103036290 1

LTE System Module - FSMF 472181A EA143363621 1

2G System Module - ESMC

RF Module 1 – FXDB

RF Module 2 – FXDB

RF Module 3 – FXDB

RF Module 1 – FXEB 472501A L6144101065 1

RF Module 2 – FXEB

RF Module 3 – FXEB

Transmission – FIQB

Power Module 1

Power Module 2

Power Module 3

AC/DC Sub module 1

AC/DC Sub module 2

AC/DC Sub module 3

Battery 1

Battery 2

Battery 3

Battery 4

Battery 5

Battery 6

Battery 7

Battery 8

Battery 9

2G Flexi MultiRadio BTS SSD 18(23)


9.2 Changes to Site Inventory

New unit Old unit


NOKIA Fault
Report Number
Name / Version Serial Number Name / Version Serial Number

2G Flexi MultiRadio BTS SSD 19(23)


10. CERTIFICATES
10.1 GSM Flexi MultiradioBTS SITE PUNCH LIST

 Insert printed copy of signed GSM Flexi MultiradioBTS Site Punch List following
this section.

10.2 FAT CERTIFICATE

 Insert printed copy of signed FAT Certificate following this section.

COMPLETED BY:

NAME:_______________________________ SIGNED:_______________________ DATE: ___/___/___


(NSN Representative)

Site Name:  Nokia Siemens Networks 20 (23)


Site ID:
GSM FLEXI MULTIRADIO BTS SITE PUNCH LIST
NETONE – NOKIA SIEMENS NETWORKS
SITE DATA

Item Data
Site ID 1142

Site Name BORROWDALE

Installed by / Date 10 October 2014

Commissioned by / Date 10 October 2014

Integrated by / Date 18 March 2015

PUNCH LIST

Select the correct check number and point to check in Flexi MultiRadio BTS Implementation Check
List. Type the description of point to check and your comments for failure description.
When completed, type what was done.

Check Defect/Failure Description Owner Raised by /date Completed by /


no. date

PUNCH LIST APPROVED BY:

NETONE REPRESENTATIVE:_____________________________________DATE: ____ / ____ / ________


( )

NSN REPRESENTATIVE:_______________________________________DATE: ____ / ____ / ________


( )

Site Name:  Nokia Siemens Networks 21 (23)


Site ID:
FINAL ACCEPTANCE TESTING (FAT)

NETONE – NOKIA SIEMENS NETWORKS

Site Provisional Acceptance certificate for telecom implementation works

INDENT NUMBER: SITE ADDRESS:

SITE ID: 1142

SITE NAME: BORROWDALE

STAGE COMPLETE (Initials/Signature)

GSM FLEXI MULTIRADIO BTS Site Installation

GSM FLEXI MULTIRADIO BTS Site Commissioning

GSM FLEXI MULTIRADIO BTS Site Integration

GSM BTS Site Folder and Attached Documents

Nokia Networks hereby states that the whole of supplies detailed above have been inspected, implemented,
tested and unless otherwise stated conform to the specified requirements in the contract or order identified
above.

NETONE REPRESENTATIVE:_________________________________________DATE: ____ / ____ / ________


( )

NSN REPRESENTATIVE:___________________________________________DATE: ____ / ____ / ________


( )

Site Name:  Nokia Siemens Networks 22 (23)


Site ID:
11. APPENDIX
11.1 BTS Installation Document

 Insert printed copy of BTS Installation Document following this section.

Site Name:  Nokia Siemens Networks 23 (23)


Site ID: