Sei sulla pagina 1di 1

Sahendra kumar -P no 500327 dated 30-03-20

1) Review of pre-commissioning checklist of power transformer completed.


2) Spare list of Misc package of BPRS completed.
3) BPRS Fire hydrant drg review completed and comments sent to vendor.
4) ISWP supply and erection ordering follow up with procurement done. ordering delayed
due to sap issue. Procurement confirmed that order will be released in this week. UMC of 28
items done.
5) Power system basic transmission and distribution E module 1 completed.
6) Checking of as built GA drawing of 2.2 Kw starter panel completed

7) Heat loss calculation sheet is being reviewed. Windows loss of building are not
considered in this sheet.

8) ABAC module partly completed.

Sahendra kumar -P no 500327 dated 31-03-20

1) Review of pre-commissioning checklist of MV switchgear- completed


2) Study of CRP drawing for understanding panel #1 extension without disturbing
running load- Completed
3) Study of CRP drawing for understanding panel #2 extension without disturbing
running load- completed
4) Preparation of CRP erection plan for feeder#1- completed
5) E-module - Case-3 HV Electrical Flash Incidences- completed

Sahendra kumar -P no 500327 dated 01-04-20

1) Review of BPRS erection & ISWP erection orders- Comments given to Procurement
2) Review of pre-commissioning checklist of Dry type transformer- Completed
3) Preparation of CRP erection plan for feeder#2- Completed
4) Study of GIS panel extension without disturbing running load-completed
5) Preparation of GIS bay extension plan for ISWP Feeder#1-completed
6) E-module - Case-4 HV Electrical Flash Incidences- completed