FINAL BILL TOWARDS THE CONSTRUCTION OF RESIDENTIAL BUILDING OF MR. P.J.

MATHEW,
JOINT SECRETARY FINANCE, ISRO AT NO. 77, AGS LAYOUT, AREHALLI, BANGALORE UTTARHALLI TALUK,
BANGALORE
Sl No. Description Unit Previous Present Rate Amount
A Foundation Work Qty Qty
1 Earthwork excavation for foundation in all
types of soil up to a depth of 1.50Mts
including disposing off the surplus
excavated earth as directed etc., complete
with all leads and lifts. Cft 1600 0 3.50 5,600.00
2 Earth work excavation for Column footings ,
Retaining walls, etc., up to 5'depth including
disposing off the surplus excavated earth as
directed etc.,complete with all leads and lifts.
Cft 8640 0 5.00 43,200.00
3 Back filling the foundation trenches and
basement using the available excavated
earth including watering, compacting in
layers etc., complete with all leads and lifts.
Cft 8640 0 2.00 17,280.00
4 Back filling the foundation trenches using
the outside earth including watering,
compacting in layers etc., complete with all
leads and lifts incuding levelling the total site
area Cft 16400 0 5.00 82,000.00
5 Providing and laying PCC 1:4:8 columns, main
walls and floor bedfor leveling course bed
including mixing, compacting in layers, curing
etc., complete with all leads and lifts.
Cft 1538 0 85.00 130,730.00
6 Providing and laying RCC M 20 including
centering, shuttering, framework, machine
mixing, compacting in layers, curing etc. but
excluding cost of steel, complete with all leads
and lifts. 0.00
a Footing Concrete Cft 1423 155.00 220,565.00
b Plinth Beams Cft 271 175.00 47,425.00
c Column concrete Cft 561 185.00 103,785.00
d lintle Beams Cft 326.25 175.00 57,093.75
e Chajjas Cft 192 175.00 33,600.00
f Beams Cft 652 180.00 117,360.00
g Roofslab Concrete Cft 1634 170.00 277,780.00
7 Providing and fabricating and laying in
position Approved TMT reinforcement bars
of various diameter Basic rate 36,000/- per
tonne kgs 10350 760 44.00 488,840.00
8 Providing and constructing side stone
masonary using 1:6 CM including curing
ete., complete
0.00
a) Below plinth beam Cft 543 56.00 30,408.00
b) compound wall Cft 650 100 56.00 42,000.00
9 Providing and constructing using Brick Masonry
including scaffolding, raking the joints, curing
etc. complete. For 4" wall CM 1:4 including
75mm thick reinforced cement concrete band at
every 5th course Basic rate for brick Rs. 4.50/-
0.00
a 9" thick wall Cft 2954.48 95 125.00 381,185.00
b 4" thick wall Sft 1020 120 70.00 79,800.00
10 Door Window Work Ventilators: 0.00
a Main doors with Teak wood frames and shutters
with 125mm X 150mm thick frame and 30mm
thick shutters including all fixtures and
assesories Sft 0 78.75 1,300.00 102,375.00
b Providing and fixing of Doors, windows and
ventilators frames with Honne wood
measuring 75mm X 125 mm thick frame
fixed with MS hold fost and 30mm fully
glazed shutters with all assessories and
including enamel paint etc., complete
Sft 0 975 950.00 926,250.00
11 Providing 12mm thick Plastering 0.00
a In CM 1:6 for ceiling and internal Wall initially
cleaning & watering the surface and grouting if
necessary and then 12 mm plastering for
uniform thickness and smooth sponge finished
Cft 0 10600 25.00 265,000.00
b In CM 1:6 for external Wall initially cleaning &
watering the surface and grouting if necessary
and then 12 mm plastering for uniform thickness
and rough sponge finished
Cft 0 7800 25.00 195,000.00
13 Painting 0.00
b Wall Internal Emulsion two coates of
BERGER or ASIAN with two coats of
ALTECH putty and one coat of primer
including sanding and all leads and lifts to
get even shade without undulations Sft 0 12000 6.00 72,000.00
c Externala wall painting with Berger/Asian (
weather coat/ Apex) in two coats over a coat
of primer including cleaning and all leads
and lifts Sft 0 10600 9.00 95,400.00
MISSELLENEOUS WORKS 0.00
14 Termite control measures using chemical
Chlorpyriphos bearing ISI Certification, in
stages specified by manufacturer of the
chemical with a 10-year guarantee. of the
chemical with a 10-year guarantee.
4,500.00
15 Providing and constructing water storage
sump using brick masonary with CM 1:5
including water proofing and other necessary
curing etc. complete
LTRS 0 8000 9.00 72,000.00
16 Total Electrification and Plumbing
1)Plumbing and sanitary ( part completed) Rs. 300,000.00
2)Electrical works (part completed ) Rs. 300,000.00
E TOTAL 4,491,176.75

for SHREE KRISHNA CONSTRUCTION

B.N.SADAN

Date:24.04.2012
Place:Bangalore