Project # 1 311.60
Project # 2 5,913.00
Project # 3 501.60
The number of hours on the Experience Verification Form(s) must total at least 4,500 hours and the
project dates must indicate that the candidate has at least three (3) years of project management
experience within the eight-year (8) period prior to the application. Candidates must indicate at least
thirty-six (36) unique (non-overlapping) months of project management experience on the
Experience Verification Form(s) to satisfy the three-year (3) requirement.
My Project Details
Initiating 26.24
Planning 65.60
Executing 131.20
Monitoring/Controlling 59.04
Closing 29.52
Project Description:
Big Bang Agro Farm wanted a bio gas plant to sell gas and utilize cow dung and other wastage. I managed the entire project life cycle . Developed
the project plan accounting for cost,requirements, resources and time. Reported on progress to stakeholders. Finally I have sucessfully completed
the project by producing sufficient gas from cow dung.
ject life cycle . Developed
ave sucessfully completed
My Project Details
Initiating 525.60
Planning 1,971.00
Executing 1,642.50
Monitoring/Controlling 1,182.60
Closing 591.30
.
Cleint Details Energypac Power generation Limited
Contact Person Tara Keshore Das
Contact Relationship Project Manager
Contact E-mail tara.pgd@energypac.com
Phone: 8801730010279
Office Address: Scan Cement,Tatki,Rupgonj,Narayanganj
Project Description:
To operate and maintain of 10MW power plant of scan cement by energypac power generation limited. I managed the electrical work of this
project. Identified key stakeholders. Defined the scope with while considering time,cost and resources.Monitored quality and communicated with
stakeholders and maintained 24*7 service. Documented Close out report. Material handed over to both energypac and scan cement's authorized
person
electrical work of this
ty and communicated with
scan cement's authorized
My Project Details
Initiating 42.24
Planning 105.60
Executing 211.20
Monitoring/Controlling 95.04
Closing 47.52
Project Description:
Installation and Commisioning of 9 MVA transformer for Scan Cement Kanchpur Plant. I managed the team through the entire project life cyc
created WBS, schedule,quality and secured the necessary resources, reported on progress to Stakeholders and managed quality, close out.
Trasnformer Installed
m through the entire project life cycle.
and managed quality, close out.
Month Hours
P1 1 months 15 days 311.60
P2 3 years 5 5,913
P3 4 Months 4 502