Sei sulla pagina 1di 8

Summary of Projects Total Work Hour

Project # 1 4,665.60
Project # 2 501.60

Total Work Hour 5,167.20

Terms & Conditions:

The number of hours on the Experience Verification Form(s) must total at least 4,500 hours and the
project dates must indicate that the candidate has at least three (3) years of project management
experience within the eight-year (8) period prior to the application. Candidates must indicate at least
thirty-six (36) unique (non-overlapping) months of project management experience on the
Experience Verification Form(s) to satisfy the three-year (3) requirement.
My Project Details

Major overhauling of 3 engines(1026,1027,1028)and


ensuring production of 100% load from three
Project # 2 generator to Scan Cement.
Start Time 1-Jan-16
End Time 1-Jan-19

Job Title Project Manager

Total Duration 3 years


Total Days 864.00
Total Effort Hours 5,184.00

Initiating 414.72
Planning 1,555.20
Executing 1,296.00
Monitoring/Controlling 933.12
Closing 466.56

Total Effort 4,665.60

.
Cleint Details Energypac Power generation Limited
Contact Person Tara Keshore Das
Contact Relationship Project Sponser
Contact E-mail tara.pgd@energypac.com
Phone: 8801730010279
Office Address: Scan Cement,Tatki,Rupgonj,Narayanganj

Project Description:

To overhaul all engines and to produce 10MW power from power plant to scan cement by energypac power generation limited. I managed the
team through entire project lifecycle. Identified key stakeholders. Defined the scope,Created WBS while managing engine overhaul,Secured and
Managed the necessary resources ,Devoloped a schedule to perform overhauling and producing full load, Created yearly Cost baseline, Procured
Spare parts of engine,Monitored quality and Reported on progress to stakeholders,Created Lesson Learned Ripository ,Documented Close out
report. Material handed over to both energypac and scan cement's authorized person. Overhauling Completed and 100 % production has been
ensured to scan cement's for last three years.
limited. I managed the
ne overhaul,Secured and
y Cost baseline, Procured
Documented Close out
% production has been
My Project Details

Project # 3 Installation and commisioning of 9 MVA trasnformer


Start Time 1-Oct-18
End Time 31-Jan-19

Job Title Project Manager

Total Duration 4 Months


Total Days 88.00
Total Effort Hours 528.00

Initiating 42.24
Planning 105.60
Executing 211.20
Monitoring/Controlling 95.04
Closing 47.52

Total Effort 501.60


Cleint Details Energypac Power generation Limited
Contact Person Tara Keshore Das
Contact Relationship Project Sponser
Contact E-mail tara.pgd@energypac.com
Phone: 8801730010279
Office Address: Scan Cement,Tatki,Rupgonj,Narayanganj

Project Description:

Installation and Commisioning of 9 MVA transformer for Scan Cement Kanchpur Plant. I managed the team through the entire project life cyc
created WBS, schedule,quality and secured the necessary resources, reported on progress to Stakeholders and managed quality, close out.
Trasnformer Installed
m through the entire project life cycle.
and managed quality, close out.
Month Hours
P1 3 years 5 4,666
P2 4 Months 4 502

Potrebbero piacerti anche