Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PROJECT TITLE
Mechanical Piping Work Package-3
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
CONTENT
1. PURPOSE ..................................................................................................... 1
2. SCOPE .......................................................................................................... 2
3. REFERENCES .............................................................................................. 2
4. ORGANIZATION CHART.............................................................................. 2
5. RESPONSIBILITIES ..................................................................................... 3
6. METHOD OF WORKS .................................................................................. 3
7. SAFETY ........................................................................................................ 7
Page 1 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
1. PURPOSE
This document provides the general specification and technical reference for Installation
Rotating Equipment and Static Equipment work at RANTAU DEDAP GEOTHERMAL
POWERPLANT PROJECT 2X49.2 MW of PT SUPREME ENERGY RANTAU DEDAP
(SERD). This specification shall be applied as reference during lifting, installation and testing
2. SCOPE
Scope of this method statement covers the following activities.
• Preparation
• Lifting
• Installation
• Inspection
• Testing
3. REFERENCES
3.1. RDPRD01-ENG-CSPC-1211-A Spec for Rotating Equipment
3.2. RD-PRD01-ENG-CSPC-1210-A Spec for Static Equipment Installation
3.3. API 686 Recommended Practice for Machinery Installation and Installation Design
3.4. RD-PRD01-SCM-CPRO-1011: Warehousing Procedure
3.5. Other related Specifications
Page 2 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
4. ORGANIZATION CHART
Site Manager
HSE Coordinator
Supervisor HSE
QC COORDINATOR Mechanical Superintendent Mech. Engineer
QC Inspector Supervisor
Foreman
5. RESPONSIBILITIES
The following ETI site personal shall be involved as responsible for the equipment erection.
5.1. Site Manager
Page 3 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
5.6. QC Mechanical
QC Inspectors in conjunction with the QC Engineer are responsible for the inspection in
accordance with specification and procedure of the equipment erection and the compilation
of equipment reports and records as per required ITP.
5.7. Surveyor
The surveyor is responsible for checking elevations and verticality as per construction
drawing.
5.8. Foreman
Foreman is responsible to execute all work start from preparation until completion jobs with
good quality and safe manner.
6. METHODS of WORKS
6.1. Equipment Receives
6.1.1. All equipment received at site shall be inspected in accordance with vendor’s instruction
for site storage, installation and preservation.
6.1.2. Equipment shall be off loaded from trailer using the vendor recommended lifting point
and approved techniques.
Page 4 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
6.1.3. All loose items that are not required for immediate installation shall be suitably identified
and retained in the stores.
6.1.4. Protective covers on all equipment’s shall be removed if they appear damage and
equipment inspected before replacing the cover, if any damage has occurred,
Discrepancy report shall be issued with photograph showing damages as necessary.
6.1.5. Preservation of rotary equipment will be maintained during storage period, by shaft
rotation as per vendor manual.
6.3.2. Proceed to the site and check the equipment foundation, study the GA Drawing of the
equipment and check the foundation, elevation and ensure the right orientation during
installation.
6.3.3. Ensure all mobile equipment and any electrical equipment are inspected prior to
mobilization on site.
6.3.4. Prepare all the equipment and lifting tackle required for the lifting and installation work
inspected by REKIND
6.3.5. Ensure all the preparation work are done before any lifting works commences
Page 5 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
6.3.6. Ensure all lifting plan and mobile crane movement plan are being approved REKIND
attached to the PTW
6.3.7. Survey and mark the location of the crane out rigger position and trailer parking area
6.3.8. Hard barricade with warning signage will be set up prior to any lifting work.
Page 6 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
Page 7 of 8
METHOD STATEMENT FOR
PT. ENVIRONMATE TECHNOLOGY
INSTALLATION STATIC & ROTATING
INTERNATIONAL
EQUIPMENT
7. SAFETY
7.1. Job safety analysis attached.
7.2. All workers shall conduct orientation course.
7.3. Work at height full body harness shall be used with 100%Tie off.
7.4. Make sure access completely safe on scaffolding with green tag.
7.5. Hot work, A Gas/Oxygen level check through the use of gas detector shall be used prior
to any hot work (welding-gas cutting).
7.6. Confined space ventilation using air mover is required for any vessel prior to entry for any
internal activity.
7.7. 24V or 12V power lighting shall be used as required.
7.8. Working area shall be barricaded. (Crane operation area, erection or dismantling of
Scaffolding)
7.9. All warning signs shall be fixed in proper location to ensure personnel safety.
7.10. Rigging operation will be done under control of Rigging Engineer, all using rigging study or
lift plan as required for each lift.
Page 8 of 8