Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Fiive-Yeaar Annuual
Cap
Transmmission
pabilityy Statem
(2009-2013)
ment 200099
Issue:
I 20009
Page | 1
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Preface
This Transmission Capability Statement is provided by the Oman Electricity Transmission Company
according to Transmission and Dispatch Licence Condition number 27 and in accordance to the Grid
Code / Planning Code. The Statement describes in detail the transmission system capability over the
coming five years 2009-2013. The Statement provides up-to-date transmission system data in order to
identify those parts of the system, which offer the opportunity for future development of existing and
potential users of the system.
In this Capability Statement the results of load flow and short circuit analysis are presented based on the
planned system reinforcement to meet the demand forecast provided by Oman Power and Water
Procurement Company and the distribution companies. The Statement presents complete solutions of
all problems reported in the previous Five Year Capability Statement (2008-2012). By the end of the
period covered by the present Statement, problems of line and transformer loadings, voltage, and fault
current issues will be completely removed. Significant improvement has been introduced in the OETC
grid model, e.g. updated project schedule, generation data, system data and control settings.
The existing and planned development in the generation and is transmission system is described and a
new section for transmission system derogations is also included in the Statement.
Page | 2
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Contents
Preface 2
List of Figures 5
List of Tables 6
Document History and Status 7
1. Executive Summary 8
2. Introduction 9
3. Technical Requirements for Compliance with the Grid Code and Licence 22
3.1. System Frequency 25
3.2. System Voltage 26
3.3. Security of Supply 26
4. OETC System Design and Planning Standards 27
4.1 Oman Electrical Standard OES 11 27
4.2 Oman Electrical Standard OES 25A and 25B 27
4.3 Oman Electrical Standard OES 27 27
4.4 Oman Electrical Standard OES 32 27
4.5 Other Standards 28
5. OETC Transmission System 28
5.1 Existing 220/132 kV Transmission System 28
5.2 Future System Development Projects 30
5.2.1 Projects expected to be completed to meet the 2009 peak demand 30
5.2.2 Projects expected to be completed to meet the 2010 peak demand 30
5.2.3 Projects expected to be completed to meet the 2011 peak demand 31
5.2.4 Projects expected to be completed to meet the 2012 peak demand 32
5.2.5 Projects expected to be completed to meet the 2013 peak demand 32
5.3 Summary 33
6. Existing and Planned Developments in Generation 39
6.1 Existing Generation 39
6.2 Planned Retirements of Existing Plant 43
6.3 Planned Future Generation (2009 – 2013) 43
6.4 Non-Contracted Generating Capacity 44
6.5 Interconnections 46
6.5.1 Interconnection with the UAE and the rest of the GCC Grid 46
6.5.2 Interconnection with PDO 47
6.6 Economic Dispatch 47
6.7 Spinning Reserve 47
7. Demand Forecast and Generation Availability 48
Page | 3
Five-Year Annual Transmission Capability Statement (2009 - 2013)
10. Derogations 76
Appendix A Review of Future Developments 80
A.1 Summery to projects to be completed annually between 2009-2013 peak demand 80
A.2 Projects expected to be completed to meet the 2009 peak demand 80
A.3 Projects expected to be completed to meet the 2010 peak demand 81
A.4 Projects expected to be completed to meet the 2011 peak demand 84
A.5 Projects expected to be completed to meet the 2012 peak demand 88
A.6 Projects expected to be completed to meet the 2013 peak demand 92
Appendix B Transmission System data 94
B.1 Substations Loads and Capacitor data 94
B.2 Overhead Line Circuit Capacities and Parameters 94
B.3 Transformer data 94
Appendix C Power System Studies 109
C.1 Summary of Load Flow Study results 109
C.2 Summary of Fault Level Study results 109
C.3 Diagrames of the model for the Load Flow Study Results 109
Page | 4
Five-Year Annual Transmission Capability Statement (2009 - 2013)
List of Figures
Figure 1: OETC existing transmission system in 2009 34
Figure 2: Expected development by 2010 35
Figure 3: Expected development by 2011 36
Figure 4: Expected development by 2012 37
Figure 5: Expected development by 2013 38
Figure 6: OETC System Load on 2008 Peak Day (31/5/2008) 48
Figure 7: OETC System Load on 2008 Minimum Load Day (18/1/2008) 49
Figure 8: Reduction of number of out-of-firm transmission lines during 2009-2013 62
Figure 9: Reduction of number of out-of-firm transformers during 2009-2013 63
Figure 10: Transmission power losses at peak demand of the years 2009-2013 64
Figure 11: Trend in peak load growth over the period 2009-2013 65
Figure 12: Future OETC Transmission System (2013) 70
Figure C.1 OETC Transmission System 2009 Max. Load Flow Condition 135
Figure C.2 OETC Transmission System 2010 Max. Load Flow Condition 136
Figure C.3 OETC Transmission System 2011 Max. Load Flow Condition 137
Figure C.4 OETC Transmission System 2012 Max. Load Flow Condition 138
Figure C.5 OETC Transmission System 2013 Max. Load Flow Condition 139
Page | 5
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Tables
Table1: Summary of Planned Developments on OETC Transmission System (2009 - 2013) 10
Table 2: Existing and Committed Future Generating Capacity 41
Table 3: New Contracted and Planned Generating Capacity 44
Table 4: Non-Contracted Generating Capacity 45
Table 5: Centrally Dispatched Generating Capacity on OETC Transmission System 46
Table 6: Historic Growth in Peak Demand and Transmission Losses (2003 – 2008) 48
Table 7: Expected oad Transfers amounge Grid Supply Points (2009 - 2013) 51
Table 8: OETC Transmission System Demand Forecast by Grid Station 53
Table 9: Comparison of Demand Forecast with Available Generating Capacity including Planned Retirements 56
Table 10: Comparison of Demand Forecast with Available Generating Capacity with Retirements Postponed and
Non-Contracted Generation in service 57
Table 11: Summary of Connected Generation used in Load Flow Studies of Maximum Demand 59
Table 12: Summary of Connected Generation used in Load Flow Studies of Minimum Demand 60
Table 13: Estimated Power Surplus and Power Deficit on an Area Basis (2009 - 2013) 71
Table 14: Available Grid Station Capacity of more than 10 MVA in 2013 75
Table 15: Expected Over head lines/ cables which will not comply with N-1 criterion at peak demand in 2009 78
Table 16: Expected Grid stations/ Transformers 132/33 kV which will not comply with N-1 criterion at peak
demand in 2009 79
Table B.1: Load and Capacitor Data for Grid Stations (2009 - 2013) 95
Table B.2: 2009 Branch Data Listing 98
Table B.3: Progressive Changes to Branch Circuit Data for 2010-2013 100
Table B.4: Grid Stations Transformer Data at peak 2009 103
Table B.5: Grid Stations Transformer Data from 2010 to 2013 105
Table C.1: Transformer Loading (%) at Grid Station (2009-2013) 110
Table C.2: Available Capacity at Grid Stations (2009 – 2013) for Connection of New Demand 113
Table C.3: Overhead Line and Cable Circuit Loading (%) at Peak Demand (2009-2013) 116
Table C.4: Transmission System Voltage Profile at Peak and Minimum Demand (2009 - 2013) 120
Table C.5: Estimation of Transmission Losses at Peak Demand (2009-2013) 125
Table C.6: Maximum 3-Phase Short Circuit Fault Levels 126
Table C.7: Maximum 1- Phase Short Circuit Fault Levels 131
Page | 6
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 7
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Distribution of Copies
Revision Copy no Quantity Date Issued to
v.0 1 1 Eng. Ali Al Hadabi
1 1 Eng. Rashid Al Badwawi
1 1 Eng. Thani Al -Khusabi
1 1 Dr.Hilal Al Nasssri
1 1 Dr. Bhowmick
1 1 Eng: Younis Al Rewahi
1 1 Eng: Mohamed Al Mazroui
1 1 Eng: Masoud Al Reyami
1 1 Eng: El Tayeb Bashir
1 1 Mrs. Lubna Al Mahrouqi
1 1 Eng: K.S Babu
1 1 Mrs. Celia Whitaker
V.1 Revised meeting( All above members)
V.2 1 1 31/3/2009 Sent to AER for approval
19/5/2009 Comment from AER
18/5/2009 Meeting with AER
Revision of Projects
New List of projects sent to Discos
Receiving Comments from Discos
Revising of projects and analysing them in the model
20/6/2009 Start new analysis
23/6/2009 Requesting AER to extend the submission date
24/6/2009 Receiving letter from AER for extension
28/6/2009 Draft Submission
1/7/2009 Sent to SKM for review
10/7/2009 final revised document from SKM
11/7/2009 OETC review the comments and updates SKM Comments
13/7/2009 OETC Sent the updates to SKM
15/7/2009 Final comments are dealt with by OETC
15/7/2009 OETC received certification letter for the 5 Year
Statement and Model from SKM
18/7/2009 Sent to AER for final revised approval
26/7/2009 Recived from AER for minor changes
29/7/2009 Sent back to AER
1/8/2009 Final version submitted for approval
Author: Strategic Planning and Projects / Strategic Planning and Study Section
Document version: v.2 "As submitted to the Authority for Approval, March 2009"
Page | 8
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The Statement includes data for the generators, loads, overhead line and cable circuits, transformers and
capacitors used in the development of transmission system models for the power system studies undertaken with
OETC’s DIgSILENT power system analysis software, version 14, in preparation of this Capability Statement.
The Statement also includes the results of power system analysis of the transmission system that defines system
performance when operating under the extremes of peak and minimum demand in each of the five years. From
this analysis an assessment has been made of the opportunities for the connection of new generation and new
demand on the system.
Table 1 lists the schedule for committed and planned system development projects on the 220/132 kV
transmission system, although it should be noted that not all of the projects listed have full authorisation at this
time. Implementation of these system development projects will increase the number of 220/132 kV grid stations
from six to fourteen before the summer peak of 2013, with an additional installed firm grid substation capacity of
5,000 MVA. The number of 132/33 kV grid stations will also increase from the thirty one in service at the
beginning of 2009 to forty nine (49) by the summer peak of 2013.
During the next five years the company is introducing direct voltage transformation from 220 kV to 33 kV and
from 132 kV to 11 kV on the transmission system with respective 220/33 kV and 132/11 kV substations for the
major residential/tourism developments at Blue City and Azaiba Coast (Wave Project).
It is also one of OETC’s strategic planning concepts to complete a 220 kV double circuit ring around northern
Oman. By the summer of 2010 the proposed 220 kV connection between the Sohar Interconnector Station (SIS)
and Al-Wasit in Mahadah will be completed to link the main load centre in Oman (Muscat) with the UAE and the
rest of the GCC Grid via Sohar and the rapidly developing Sohar port and industrial area. By the first quarter of
2012 the 220 kV transmission system will also be extended from Misfah in the Muscat area to Jahloot and further
eastwards to Sur. In addition, OETC plans to upgrade the line between Mahadah to Ibri to 220 kV to support the
voltage and meet the expected load growth.
Beyond the period covered by this Statement, i.e. by the end of 2014, the 220 kV ring will be completed with the
connection of Misfah Switching Station to Nizwa University Grid Station. The proposed 1,000 MW power plant
at Duqum is scheduled for connection to the transmission system at some stage from 2015 onwards.
In accordance with Condition 27 of OETC’s Transmission Licence the power flow studies presented in this
Capability Statement are based on demand forecast data provided by Oman Power and Water Procurement
Company (OPWP) which it has used in its Seven-Year Statement (2009 – 2015). The forecast has been
disaggregated by grid station, according to available DISCO data, for detailed power system analysis.
Page | 9
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Project
Description Status Details Purpose
No.
Peak 2009
132/33 kV GSP at Adam, 132 kV Load transfer from Nizwa and feeds
2 x 40 MVA transformers, 47
1 double circuit line Adam - Manah Energized loads with voltage problems (66 km
km 132 kV SCCT line
Power Station from Nizwa)
Project
Description Status Details Purpose
No.
Peak 2010
New 132/33 kV GSP at Muladah 2 x 125 MVA transformers, New Muladah (MIS) will take load
3 on same site of MIS 220/132 kV Energized 132/33 kV at Muladah Grid transfer from Old Muladah (11km)
grid station Station 220/132kV and Khabourah (53km)
Page | 10
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Cont:
2010
220 kV DCCT line from Barka Under construction, due in Reinforcement of OETC system
6 11km, 220 kV DCCT line
Power station to Filaj service Sep'09 between Barka P/Stn and Filaj
Page | 11
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Cont:2010
Page | 12
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Cont:2010
Page | 13
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Peak 2011
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Cont:2011
Dedicated to supply Sohar Industrial Area
Second phase of 220/132 kV GSP at Sohar
28 Floated. Due in service Q4_10 2 x 500 MVA transformers loads and provide load relief to Sohar
Port Industrial Area (SIA2)
Industrial Area 'A' grid station
Upgrade Dank grid station from 2 x 15 MVA to Proposed scheme. Target 2 x 63 MVA transformers bay shafting Ibri Increases capacity at Dank to ensure (N-1)
29
2 x 63 MVA transformers date Q4_10 transformers met.
Page | 15
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Peak
2012
Phase 1 (2010): 60 MVA supplied at 132 kV
from Yitti (5km away). Phase 2 (2011): With
132/33 kV GSP at Yankit connected to new 220 kV established at Jahloot supply to
2 x 125 MVA transformers 45km 132 kV
35 132 kV busbars at Jahloot grid station via 132 Expected to be in Q2'12 Yankit taken from Yitti at 132 kV. Seefa
DCCT line
kV DCCT line Resort (15km from Yankit) supplied from
Yankit. This project not confirmed waiting
conformation form the developer.
To meet load growth requirements and
220/132 kV GSP at Jahloot connected to Adding 2 x 500MVA with 70km of 220kV
36 Expected to be in Q2'12 improve voltage profile and to be linked with
Misfah grid station via 220 kV DCCT line O/H line between Misfah and Jahloot
Sur area.
Required to support voltage in Sur and BB
220/132 kV grid station at Sur connected to
2 x 500 MVA transformers 160km 220 kV Ali areas. And to meet load growth ( OETC
37 Jahloot grid station via a 220 kV DCCT line Expected to be in Q2'12
DCCT line studying to construct this line as 400kV and
when 220 kV bus established at Jahloot
operated as 220kV)
Upgrade of Mudhabi grid station from 2 x 63 To meet load growth requirements and to
38 Expected to be in Q2_12 2 x 125 MVA transformers
MVA to 2 x 125 MVA transformers maintain N-1
Upgrade of Izki grid station from 2 x 40 MVA to To meet load growth requirements and to
39 Expected to be in Q2_12 2 x 125 MVA transformers
2 x 125 MVA transformers maintain N-1
Upgrade of Rustaq grid station from 2 x 63 To meet load growth requirements and to
40 Expected to be in Q2_12 2 x 125 MVA transformers
MVA to 2 x 125 MVA transformers maintain N-1
Upgrade of Sumail grid station from 2 x 63 To meet load growth requirements and to
41 Expected to be in Q2_12 2 x 125 MVA transformers
MVA to 2 x 125 MVA Tx. maintain N-1
Load transfer and to met load growth
42 132/33 kV GSP at Al Kamil Expected to be in Q2_12 2 x 125 MVA transformers
requirements in the area.
2 x 125 MVA transformers connected to Load transfer and to met load growth
43 132/33 kV GSP at Nizwa (University) Expected to be in Q2_12
LILO of Izki - Nizwa 132kV lines. requirements in the area.
To increase Voltage profile for the long 33kV
2 x 63MVA transformers connected to Al
44 132/33 kV GSP at Al Roudha Expected to be in Q2_12 lines (60km), Load transfer and to met load
Modhabi through 40km 132kV lines.
growth requirements in the area.
Construction of new 220kV Grid station at New 220kV GIS interconnection Grid for
45 Expected to be in Q212 To connect the new IPP to the Grid.
Misfah new IPP at Misfah
To meet N-1 , cater load growth and to
46 Upgrading of Ghoubrah 132kV Expected to be in Q2'12 2 x 125MVA Transformers connect the new IPP
Page | 16
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Cont:2012
New 220kV GIS switch gear at Sohar with
Construction of new 220kV lines between SPS To connect the new IPP from Sohar to SIS
48 Expected to be in Q1'12 6 km 2500mm2 cable and 36km 220kV
and SIS grid stations.(For new IPP at Sohar) Grid station.
DCCT line
To connect the new IPP to the Grid. This
Construction of new 220kV Grid Station at New 220kV GIS interconnection Grid for
49 Expected to be in Q1'12 project is linked with new Barka 220kV and
Barka for the new IPP new IPP to Misfah
Misfah grid.
Construction of new 220kV Grid Station at New 220kV GIS interconnection Grid for
50 Expected to be in Q1'12 To connect the new IPP to the Grid.
Sohar for the new IPP new IWPP to SIS
2 x 125MVA , 25km 132kV lines between Load transfer from Jahloot and to be as
51 New grid at Amerat area Expected to be in Q2'12
MSQ and Jahloot Lines (LILO) voltage support in Amerat area
2 x 125MVA , 10km 132kV from Sohar
52 New Grid station at Multaqa (Sohar) Expected to be in Q2'12 load transfer from Sohar Grid.(77.7MW)
grid station
2 x 125MVA transformers connected to To cater the expected load growth in the
53 New Grid at Al-Ghala area (Muscat) Expected to be in Q2’12
Airport Heights grid station area and load transfer
2 x 125MVA, connected to the existing To meet N-1, load transfer from existing
54 New grid at Buraimi Expected to be in Q2'12 Mahadah-Buraimi 132kV LILO with Buraimi Grid(64.2MW), and new load at the
additional around 4km area.
2 x 125MVA , 10km 132kV from SIA-2
New Grid at Sohar Special Economic To cater the new load requirement for this
55 Expected to be in Q2'12 grid station by using 2500mm2
Zone(SSEZ) area.
underground cable
To cater the load growth at Ras Al Had area
and to solve the issue of voltage drop,
56 Aijah (Sur-2) Expected to be in Q212 2 x 125MVA, 25km 132kV from Sur grid currently this area is fed by 33Kv feeders
from Sur grid 60km and load transfer(40MW)
from existing Sur Grid
Page | 17
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table1 (continued): Summary of Planned Developments on OETC Transmission System (2009 - 2013)
Project
Description Status Details Purpose
No.
Peak 2013
Page | 18
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In order to model future system development as accurately as possible the distribution companies are
required by the Grid Code to provide OETC with information that identifies their load transfer plans,
including the load to be transferred, the timing and the grid stations involved, data that is also provided to
OPWP for its own forecast of generation requirements. From the individual demand forecasts of the
distribution companies, OETC has developed its own demand forecast for the transmission system as a
whole, including the load transfers between grid stations that are then incorporated into the power system
models for each year.
The forecast average annual growth in system demand of almost 12 % over the period 2009 –2013 drives
many of the planned grid station reinforcements with a large portion of the additional demand supplied to
the distribution companies through the 132/33 kV grid stations. To meet security of supply requirements
and provide load relief to the heavier loaded grid stations it will be necessary to transfer excess load to the
new or existing, but lightly-loaded grid stations. Comparison of the demand forecast with generation
availability as defined in the OPWP Seven-Year Statement (2009-2015) shows a potential shortfall in
generation capacity at system peak in 2010 and 2011. To meet the shortfall caused by planned plant
retirements at Ghubrah and Wadi Jizzi it is assumed that power will be imported from direct customer
generation. In addition the new generating capacity from Barka Phase-2 (SMN), Barka Phase-3 and Sohar
Phase-2 will be required to meet future growth and avoid a further shortfall in generating capacity.
As the demand grows there is a greater need to extend the 220 kV transmission system so that bulk power
is transmitted at this voltage rather than 132 kV in order to avoid overloads, improve voltages and reduce
power losses. Consequently it is OETC’s objective to operate 220 kV as the main transmission voltage
and use 132kV for sub-transmission and at some future date consider the introduction of 400 kV for the
transmission of bulk power over long distances.
From Table 1 a total of 64 transmission projects are planned over a three year period, most of which are
designed to increase the transmission system capacity so that it can meet future growth in demand and
satisfy the security criteria. This is a major programme of capital investment in its infrastructure that will
be spread across the whole network to improve transmission system performance across northern Oman
and power system studies presented in this Statement confirm that the planned investment in 220 kV grid
stations and transmission circuits will provide substantial spare capacity on the 220 kV transmission
system to well beyond 2013.
The major technical issue identified in the studies was with high short-circuit fault levels on the 132 kV
busbars at 4 grid stations in the Muscat area. The grid stations at Ghubrah, Bousher, Rusail and Madinat
Sultan Qaboos (MSQ) were all shown in earlier studies (OETC Five Year Capability Statement 2008-
2012) to have high 132 kV fault levels. Accordingly, OETC has taken appropriate remedial action to
address this problem by implementing in the short–term, measures to split the 132 kV busbars at Rusail
and Ghubrah.
Page | 19
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In 2009, the 132 kV busbars were split at Rusail, but practical difficulties at Ghubrah prevented its
implementation and the action to split the 132 kV busbars there has been postponed to be implemented
later. Until then operating restrictions are being applied to avoid performing any works near switchgear
at Ghubrah Power Station. Splitting the 132 kV busabrs at these power stations significantly reduces the
fault level on the 132 kV transmission system in the Muscat area and temporarily solves the short circuit
problem at zero cost.
In 2012 Rusail will no longer need splitting due to the network development and reconfiguration works
completed to facilitate the addition of new IPPs, and therefore the Rusail busbars will be returned to
normal operation. In 2013, with the completion of transmission system developments required to facilitate
the introduction of new IWPP at Ghubrah, splitting of the busbars will no longer be required.
Load flow studies have confirmed that with the exception of the 132 kV bus-bars at Al Hail, the voltage
levels across the transmission system can be maintained within the +/-10 % limits defined in the Grid
Code. In the case of Al Hail, the 132/33 kV grid station is currently supplied via a single circuit line from
Dank, but by the end of 2010 this will be upgraded to a double circuit connection
At Al Hail and at other remote locations, such as Sur at the eastern end of the transmission system, there
is a strong case for the deployment of reactive compensation as a cost effective means of improving the
system voltage. Similarly, with the demand in the Muscat area continuing to grow there are occasions
when some grid stations in the Muscat area suffer reduced voltages at times of heavy load. To overcome
this problem, Muscat Electricity Distribution Company (MEDC) have agreed to install new capacitor
banks on the 33 kV busbars at Bousher, MSQ, Muttrah, Qurum, and Jahloot grid stations and studies
presented in the report have confirmed that their addition by the summer of 2010 will produce a
significant improvement in the voltage profile across the Muscat area.
Consequently, OETC has written to the distribution companies to request that they add more capacitor
banks at the distribution voltage level to operate within the recommended power factor as an additional
measure for improving system efficiency for the 2010 and 2011 system peaks.
The voltage problems experienced in the Al Dahirah area has led OETC to review its plans for system
reinforcement to this area with the 220 kV system extended from Mahadah (Al Wasit) to Ibri, with Ibri
scheduled upgraded before the 2011 peak. When this work is completed, the transmission system in this
area will be fully compliant with the voltage requirements set by the Grid Code and the (N-1) security
requirements set by Licence Condition 26.
OETC has floated a reactive power and voltage study in coordination with the distribution companies and
a detailed study of the short circuit issue is also in progress to formulate long term plans for dealing with
the fault level issue beyond 2013.
The Statement has reviewed the opportunities for the connection of new generation and new demand and
identified those grid stations with substantial spare capacity where it should be possible to connect new
demand to the system. A review of the balance between generation and demand has shown that the
Page | 20
Five-Year Annual Transmission Capability Statement (2009 - 2013)
construction of a new 500 MW power plant at Ghubrah in 2013 to supplement the existing generation at
Ghubrah and the Barka Phase 2 and Phase 3 power plants will produce a generation surplus in the Greater
Muscat area.
Section 2 of the Statement provides an introduction to the document, identifying the main related
documentation and the key changes that have taken place on the transmission system since the previous
issue of the Statement.
Section 3 identifies the technical requirements of the Grid Code and the Transmission Licence with
specific attention to system voltage, frequency and security of supply.
Section 4 describes the main engineering standards used by OETC in its planning and design of the
transmission system.
Section 5 describes the existing transmission system and summarises the planned developments in each
year over the period 2009 to 2013.
Section 6 identifies the existing and planned developments in generation and describes the
interconnections both inside Oman and internationally, i.e. PDO and the UAE respectively.
Section 7 presents the demand forecast and compares this with the generation capacity available.
Section 8 discusses transmission system performance and presents the results of load flow and short-
circuits studies that show the performance of the transmission system at both peak and minimum demand
in each year from 2009 to 2013.
Section 9 identifies the development opportunities for the connection of new demand and new generating
plant to the transmission system.
Section 10 presents the areas of the network where network components will be operating above firm
capacity during the period 2009 - 2013 and identifies the need for new or renewed derogations from
application of the N-1 security criterion, as appropriate.
Page | 21
Five-Year Annual Transmission Capability Statement (2009 - 2013)
2. Introduction
2.1 Licence conditions, Codes and Standards
This Transmission System Five-Year Capability Statement covers the period 2009 – 2013 which has been
prepared by the Oman Electricity Transmission Company S.A.O.C. (OETC) in accordance with the
requirements set down under Licence Condition 27 of the Electricity Transmission and Dispatch Licence
granted to the Company on 1 May 2005 by the Authority of Electricity Regulation (AER). The Licence
has been granted under the powers invested in the Authority by Article (2) of the Law for the Regulation
and Privatisation of the Electricity and Related Water Sector promulgated by Royal Decree 78/2004.
The purpose of the Statement is to provide up-to-date transmission system data for potential and existing
users of the transmission system so they can identify those parts of the transmission system which offer
the opportunity for future development. The Statement is required to be updated annually so that users
and potential users of the transmission system are furnished with the latest information.
Potential users of the transmission system should be aware of the following main documents that
influence the planning and future development of the transmission system infrastructure:
ii) The Electricity Transmission and Dispatch Licence granted to OETC, notably Licence
Condition 26, which defines the requirements for the Security Standards and the
maintaining of an Efficient and Economic Transmission System.
iii) The approved Transmission Security Standards prepared in accordance with Condition 26
of OETC’s Transmission and Dispatch Licence.
iv) The Statement of Charges for Connection to the OETC Electricity Transmission System.
v) The Statement of Charges for the Use of the OETC Electricity Transmission System.
Since the issue of the previous Capability Statement, covering the period 2008 – 2012, the following
projects have been completed and are currently being energized in time to meet 2009 system peak
demand:
i. Construction of the 132/33 kV Manah to Adam double circuit overhead line and
associated Grid Station at Adam.
ii. Upgrading of the 132/33 kV substations at Nizwa and Bahla. The works undertaken
were for replacement of the two 63 MVA transformers at Nizwa grid station with two
Page | 22
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The following projects are in the final stage and will be in service by the end of 2009.
ii. Installation of two 125 MVA transformers at Liwa Grid Station. The double circuit 132
kV Wadi Jizzi – Liwa - Shinas transmission line has been already energiesd.
iii. Installation of two 125 MVA transformers at the 220/132 kV Muladah Grid Station.
In addition to the transmission system developments, three new, large industrial customers have been
connected directly to the transmission system in the Sohar area:
ii. Aromatics industrial load has been connected to the same grid station at 132 kV.
Since the issue of the Transmission System Capability Statement for 2008 – 2012 there have been a
number of improvements in the data and the power system modelling upon which the studies that are
discussed in the Statement are based. The most significant of these are:
i. The Statement presents complete solutions of all problems reported in the previous
Five Year Capability Statement (2008-2012). By the end of the period covered by
the present Statement, problems of line and transformer loadings, voltage, and
fault current issues will be completely removed.
ii. The OETC demand forecast is based on the data provided by OPWP and distribution
companies which should make for a more accurate forecast.
iii. A review of power system model resulted in more appropriate settings being used for the
transformers tap changers and the terminal voltages of generating units.
Page | 23
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The improvements in the demand forecast and the power system modelling should result in similar
improvements being achieved in the accuracy of the power system studies upon which network
development planning is based.
Page | 24
Five-Year Annual Transmission Capability Statement (2009 - 2013)
3. Technical requirements for compliance with the Grid Code and Licence
In order to comply with Condition 26 of the Electricity Transmission and Dispatch Licence the
transmission system must be planned, designed and operated to provide a secure, efficient and economic
supply of electricity that is of an acceptable quality to its users.
Whilst Condition 26 specifically sets out the Security of Supply requirements, the most important
characteristics that determine the quality of supply are frequency and voltage. The requirements for
maintaining transmission system frequency and voltage within specified operating limits are set out in the
Grid Code, and most clearly defined under conditions ASC4.1 and ASC4.2 respectively of the Ancillary
Services Code.
Other issues that relate to the planning of an economic and cost effective transmission system that
provides a voltage supply of acceptable quality, such as standardisation of equipment ratings, limitation of
system losses, and the control and limitation of disturbing factors that affect the voltage waveform are
covered by relevant Omani and/or International Standards.
a) During normal operating conditions, the nominal system frequency of the transmission
system shall be 50.00Hz and will be controlled normally between 49.95Hz and 50.05Hz.
b) During exceptional steady state conditions, frequency deviations will not exceed 49.90Hz
to 50.10Hz unless disturbed circumstances prevail.
c) Under disturbed conditions, system frequency could rise transiently to 51.50 Hz or fall to
48.0 Hz, but not exceed these limits.
As ASC4.1 points out, the frequency of the total system is responsive to changes in the balance between
the active power demand and total available generation capacity. OETC must therefore ensure that
sufficient generation capacity and demand is available and connected to the system at all times to respond
automatically to active power imbalances and correct any frequency change.
Page | 25
Five-Year Annual Transmission Capability Statement (2009 - 2013)
a) The voltage on the 220 kV and 132 kV parts of the Transmission System at each site with a
user connection will remain within the limits of ±10% of the nominal voltage level.
During some system disturbances, such as where short circuits occur, the voltage could collapse
transiently to zero at the point of fault until the fault is cleared.
Voltage regulation requires both active and reactive power flows across the transmission system to be
carefully controlled. The physical characteristics of the plant on the transmission system also give rise to
the generation and absorption of reactive power. Reactive power flows across the transmission system
can give rise to substantial voltage differences and it is therefore necessary to maintain reactive power
balances between sources of capacity and demand on a “zone” basis.
Unlike frequency, which is consistent across an interconnected transmission system, voltages at different
points on an interconnected system are determined by the local sources of demand and capacity, by the
prevailing network configuration and by the reactive power flows across the network.
The management of voltage requires control of reactive power and this can be provided by centrally
dispatched generators, transformer tap-changers, by the connection of capacitor banks at 33 kV or below,
or by means of static compensation.
The Transmission System taken over by OETC in 2005 had several components that failed to meet the
(N-1) criterion, and the Licence recognised that it might take two years, but at system peak 2012 and 2013
all grid stations and overhead lines will meet most of required standards and criteria to bring the whole
system into full compliance. To date some of these out of firm situations have been addressed, but
equally the steep growth in demand has caused further circuits / transformers to become out of firm.
Section 10 summarizes the system grid condition.
Page | 26
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In addition to the technical requirements of the Transmission Licence and the Grid Code, the principal
electrical standards used by OETC in its planning and design of the 220 kV and 132 kV transmission
systems are:
Page | 27
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The transmission system was first established under the Ministry of Housing, Electricity and Water
(MHEW) in 1983 and underwent rapid expansion during the 1990s. Consequently much of it has less
than 15 years service experience. After the electrical sector was unbundled, the OETC took over the
operation of the transmission system on 1 May 2005. The present OETC transmission system consists of:
The OETC transmission system is also interconnected with the PDO transmission network at 132 kV via
a single circuit overhead line that runs between Nizwa on the OETC system and Nahda on the PDO
system. Under normal conditions the power transfer across the interconnection is forecast to be
negligible, but in the event of an emergency on either network the interconnection can facilitate a power
transfer of up to 60 MW to address the shortfall. The energy transfer between OETC and PDO is
managed such that annually the net energy transfer is around zero.
The transmission system is supplied with electricity generated from eight gas-based power stations
located at Ghubrah, Rusail, Wadi Jizzi, Manah, Al Kamil, Barka AES & Barka SMN (phase 2) and Sohar.
Page | 28
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In addition the transmission system may be supplied from direct customers, such as Sohar Aluminium
and OMIFCO and some more additional generating units have been added at Barka. .
Three Distribution Licence holders, i.e. Muscat Electricity Distribution Company(MEDC), Mazoon
Electricity Company (MZEC) and Majan Electricity Company (MJEC), take the bulk of the power
transmitted through the main grid, from the 220/132/33 kV and 132/33 kV grid stations.
In addition to the three distribution companies, eleven large private customers are directly connected to
the transmission system. Seven of these are connected to the transmission system in the Sohar Industrial
Area. The existing private customers are:
220 kV Connections
i. Sohar Aluminium
ii. Shadeed
132 kV Connections
iii. PDO
iv. OMCO
v. Aromatics
vii. OMIFCO
The following new customers will be directly connected during the period covered by the Statement:
Zoom will be connected with the new 220kV Sur grid station in 2010.
VALE will be supplied via a single circuit connection to the existing SIA-1 substation,
with the second circuit connected from the new 220kV SIA-2 station by the end of 2010.
Page | 29
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In 2008 the system gross peak demand of 3,139 MW which occurred at 15:00 hours on 31 May, an
increase of 13.2 % on the 2007 peak demand. During 2008, the energy imported to the system from
connected generating plant was 14,017.1 GWh, whilst that exported to private customers and the
distribution companies was 13,837.6 GWh, resulting in system energy losses of 179.5 GWh, which
equates to an system energy loss of 1.3 %.
The new projects scheduled for completion in time to meet the summer peak demand in 2010 are at
various stages of development and the major projects for which a consultant has been appointed for
construction are:
iv) Construction of the132/33kV grid station at Saham and the associated 132 kV transmission
system.
v) Installation of two 125 MVA transformers at Liwa Grid Station. The double circuit 132 kV
Wadi Jizzi – Liwa - Shinas transmission line has been already energised.
vi) Installation of two 125 MVA transformers at the 220/132 kV Muladah Grid Station.
A number of grid stations cannot maintain (N-1) security of supply and additional transformer capacity is
being provided to meet the 2010 peak at MSQ (125MVA), Ghubrah (40MVA), Bousher (125MVA),
Page | 30
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Mawalih (125MVA) and Seeb Main (63MVA) until new grid stations are available to provide load relief
in the future. At MSQ and Mawalih the third 125 MVA transformer installed in 2010 will be further
reinforced in 2011 as part of the process to establish a second grid station within the boundary of each
site. At Bousher, two 125 MVA transformers will be installed to meet peak 2010.
The replacement of overhead lines with underground cables in the Muscat area is also planned for
completion in time for the 2010 peak.
The major transmission system developments that are expected to come into service between the summers
of 2010 and 2011 to meet the summer peak in 2011 are planned for the coastal areas to the east of Muscat.
Other major projects scheduled for that period are a second 220/132 kV grid supply point in the Sohar
Industrial Area (i.e. Sohar Industrial Area ‘B’), a new 220/33 kV grid station at Blue City, the new
220 kV double circuit line between SIS (Seh Al Makarim) and Mahadah (Al Wasit) grid stations and the
upgrade of the 132 kV double circuit line between Mahadah (Al Wasit) and Buraimi. In addition, the
220 kV system will be extended into the Al Dahirah area by the construction of a new 220 kV 120 km
double circuit overhead transmission line from Mahadah to Ibri, where a new 220/132 kV 2 x 500 MVA
grid station will be established. This project will help in transferring the flow of the bulk electric power
to the more efficient 220 kV system, thus improving the voltage profiles in this area, and reducing power
losses. By summer 2011 the 132 kV single circuit connection between Dank and Al Hail will be
upgraded to a double circuit connection. This work is a priority as it is required to meet the (N-1) security
requirements and OETC is striving to advance the completion date for this project by combining it in the
same tender as the project for upgrading the 132 kV line between Mahadah (Al Wasit) and Buraimi grid
stations.
The other major project to be commissioned before the 2011 summer peak that has been floated for
consultancy services is the construction of a new 132 kV 30 km double circuit overhead line from Jahloot
to Quriyat, with a new 132/33 kV, 2 x 125 MVA grid station to be established at Quriyat.
Page | 31
Five-Year Annual Transmission Capability Statement (2009 - 2013)
5.2.4 Projects expected to be completed in time to meet the 2012 peak demand
In the Muscat area, the main development is the further reinforcement of transformer capacity at MSQ,
Bousher and Mawalih. The addition of a fourth 125 MVA transformers will enable OETC to establish
two grid stations on each site by converting the temporary transformers installed for 2010 into permanent
fixtures. The new grid stations (i.e. MSQ-2, Bousher-2 and Mawalih-2) will provide load relief for each
of the existing grid stations. These projects are expected to be completed to meet the 2012 peak demand.
Figure 4 shows in geo-schematic form the system development plan to meet the 2012 peak demand.
The main investment to meet the 2012 peak is in the extension of the 220 kV transmission system from
Barka (i.e. Barka – 2) to Misfah and on to Wadi Adai where the grid station would be upgraded 220 kV.
The 220 kV transmission system will be extended from Misfah to Jahloot and on to Sur, a total distance
of approximately 300 km. To cater for future growth in demand, consideration is being given to
constructing these lines for operation at 400 kV, but operating initially at 220kV. This option will be
discussed with the consultant in due course.
The other major projects planned for completion before summer 2012 are the new 220/132 kV, 2 x
500 MVA grid stations to be established at Sur, Wadi Adai and Jahloot. The consultancy services for
these projects have been floated and the work is in progress. The new IPPs at Barka and Sohar will be
connected to the 220 kV transmission system through new 220 kV GIS substations at Barka (Barka-2)
and Sohar (SPS-2). SPS-2 will be connected to SIS (Sohar Interconnector Station) at 220 kV via a double
circuit connection over a distance of around 40 km. However, part of the route near the power station
will have to be run underground because of expected difficulties in obtaining a right of way for another
overhead line circuit. Other projects that are required to meet the 2012 peak are the construction of new
132/33 kV grid stations at Yankit, Al Amerat, Ghala, Nizwa University, Al-Kamil, Al-Roudah, Multaqa
(Sohar area) Free Zone and Buraimi-2Further upgrading projects are also required at Mudaibi, Izki,
Rustaq and Sumail.
5.2.5 Projects expected to be completed in time to meet the 2013 peak demand
Figure 5 shows in geo-schematic form the system arrangement to meet the 2013 peak demand.
Major projects expected to be connected to the transmission system by summer 2013are construction of
new 132/33 kV grid stations at Al Khaudh (Muscat), Barka Main - 2which is required to supply the Blue
City demand and Dreez which will be connected to Ibri. Further upgrading is planned for the Manah -
Nizwa 132kV lines and the Mahadah 132/33 kV transformers from 30MVA to 63MVA.
To address the fault level issues at Ghubrah power station a number of design options are under
evaluation to determine the most appropriate long term solution for the site.
Page | 32
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The ambitious nature of the development programme planned for the period 2009 - 2012 is recognised
and for the purpose of this Statement a conservative view has therefore been taken for developments in
2013 on the assumption that some projects may suffer slippage due to unforeseen circumstances and
completion that was planned for 2012 could slip into 2013.
5.3 Summary
Table 1 in the Executive Summary has summarised the development plans for the OETC Transmission
System on a project by project basis at the time of this Statement. The table identifies the projects to
which OETC are already committed and those projects that are considered likely to proceed.
The power system studies presented later in this Capability Statement to show the expected performance
of the transmission system over the period 2009-2013 have been performed on the basis that the
committed and planned development projects in Table 1 and detailed in Appendix A will proceed as
planned and be completed on schedule. The system studies are used to identify areas of the transmission
system where there are opportunities for connecting new demand and new generation and where
constraints should be applied to further development.
Page | 33
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 34
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Legend
UAE Al Batinah North 220kv Grid Station
SRC
220kv Double Circuit
Shinas Liwa
800mm2 XLPE
SPS
2.2km
CABLE
SIA-1 220kv Double Circuit Cable
20 km
YEW x 2
2500mm2 XLPE
132kv Grid Station
CABLE
G
3km 2500mm2 132kv Double Circuit
YEW x 2
XLPE
CABLE
Auha Smelter
13km 3km
0.5km 132kv Single Circuit wooden pole
G
28 km
ARCURIA x
AR 47k
Sohar Power Station
4k
m Aluminium G
41 km
CU m 2
2
RIA
x2 Mhadah x 2 Oman Gulf
YEW
(Alwasit) G 28km 132 kv Double Circuit Cable
33km
ELM 33 km YEW x 2
Bureimi x1 YE
ELM
x1
SIS 30 W x
Wadi Al km 2
37km
225
12
Jizzi 1k
m Al
AAA
Al Bureimi
YE
W
Ba
40 ti
C
x2
Saham km na
Wadi Sa’a YE
W
h So
x2
uth
Khaburah 54
km
Barka G Wave
Muladah Seeb Main G Ghoubrah
11 km
Barka
XL
MIS YE m
ARCURIA x 2
10 2 1 c L E
km Cu
W
km
43km x1 Mawalih
mm CAB
12 km YEW AlFalaj
6.3
x
YEW15km
240 ZTACIR
2
x 2m
k
00
8 km
22
Wadi
20
W
x2
Al Dhahirah MSQ Wadi
x2
YE
km
x2
Filaj
5
m
64km Adai Kabir
YE
3k
Ad Dhahirah 2.25 km
AA
10km 28 km
25
W
8.2km
ARC
G
YE
Dank URIA YEW x 2 240 ZTACIR
AC
28
46 km
ARCURIA x 2
22 52k Yitti
km
AR
29km
5A m Rustaq YE
CU
W
x2
AA Alhayl
km
RIA
C 43 km
40
ARCURIA x 2 28km YE
2
x2
W
x
W
22
x2
km
54 AAA
YE
x2
5
Jahloot
km C
35
W
Airport
YE
High
Ibri Al-Dakhiliah Sumail
KSA
Muscat
km
x2
61
W
YE
120k
m
Bahla
YEW
x 32 Izki Al-Sharqiyah
2 YE km Nizwa
33 km
W
x2
x2
YEW
19
YE
km
.7
W
x2
Manah
G
63 OMIFCO G
YEW x 2
km
km
x1
YE
Mudhirib
47km
W
M
67
Mudaybi
3k
EL
x
2
m
60km
Sur
YEW x 2
YE
Adam W
x2
Al Wusta Alkamil 73
km
51
km G
Nahada YEW x 2
PDO
YE
55
W
km
x
2
JBB Ali
Page | 35
Five-Year Annual Transmission Capability Statement (2009 - 2013)
SRC Legend
Al Batinah
800mm2 XLPE
UAE 220kv Grid Station
2.2km
Shinas North SIA-2 SIA-1
220kv Double Circuit
Liwa 2.5km
2500mm2 XLPE SPS 220kv Double Circuit Cable
20 km
2500mm2 XLPE
G 220kv Double Circuit Cable future
YEW x 2 2500mm2 XLPE 3km
Auha 2500mm2 0.5km
28 km
13km 132kv Grid Station
Smelter
Sohar
XLPE
3km G
YEW x 2
4
AR 7km
ARCURIA x 2
CU Aluminium 132kv Double Circuit
41 km
RIA
Mhadah km Oman Gulf
x2 24 132kv Single Circuit wooden pole
2
x
SIS
W
(Alwasit) G 28km
YE
33km 132kv Double Circuit Cable
YEW x 2
ELM x1
YEW x 2 Wadi Al 30 Power Station G
Bureimi 33 km x2 YE k m
Jizzi A RCU
RIA W
x2
12
6 6 km 0.4
YE
37
km
W
40
km
km AR
x2
Saham YE CU
W
Al Bureimi Wadi Sa’a x2
RIA
x2
BLE
Barka
CA
Muladah
G Seeb Main
2000
XLPE
6 km
8k
mm2 BLE
Barka
MIS
11 km
mm2
YE m km
ru
ARCURIA x 2
W x2
CA
km
km
Main x2
Qu 9.7 YE
W
1c Cu
12 km 43km
5 km
2500
51 mm
.3k 00
Al Dhahirah Mawalih 25 LPE
YEW
240 ZTACIR
m 2 X BLE
XL
YEW x 2
2
YEW W
8 km
YE 2
6. W x
AR x CA AlFalaj
PE
2
CU k m
YE
m
R
10
x2
x2
IA Wadi
km
3k
x2 ARCURIA x 2
m
W
15km
Al Batinah MSQ Adai
x2
Bawsher
3k
YE
13
39.2km 13.1km
25
8.2km Wadi
G
W
4
YE
6 km YEW x 1
15 km
YEW x 2
10 km
South Filaj
Ad Dhahirah x2 28
Rusail
A
YEW km 9k
m
RC
52 2 x2
Yitti
AR
RIA
U
km Rustaq
x2
CU
RI
YE
Nakhal
C
AR
A
W x2
UR
x2 Alhayl
x
YE
YEW
W
km
10 km
x2
km
YE
2
Airport W 43 km
IA
x2
40
2
35
m
x
6k
x2
High
W
YE
YE
3
YE
Jahloot
54
W
x2
km
MISFAH
Al-Dakhiliah
30 W x 2
Sumail
YE
km
KSA Ibri Muscat
km
61
x2
W
Bahla Quriat
YE
120k
m
32 Izki
YE
W
km Al-Sharqiyah
Nizwa
3 3 km
x2
YEW x2
x2 YEW
19
km
.7
YE
W
x2 Manah
G 63
km
OMIFCO G
km
47km
YEW x 2
YE
Mudhirib
W
67
x1
Mudaybi
3k
x
M
2
EL
m
60km
Sur
Adam YEW x 2
YE 51
W km
x2 Alkamil km
73
G YEW
x2
Al Wusta Nahada
PDO
YE
55
W
km
x
2
JBB Ali
Page | 36
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 37
Five-Year Annual Transmission Capability Statement (2009 - 2013)
10
km
25
00
m
m
2
XL
PE
x2
W
YE
YE
W
x2
YE
W
x2
AR
CU
RI
YE Ax
W 2
x2
km
8k
.2
m3
m
2
m 9.7 k 500 mPmE
Y
E
ru
W
x 2 2 XL
Qu
x
E
BL
2
W
51 YE CA
.3k
m 10
km
39
. 2k
A
m
R
C
U
A
R
RI
C
U
A
Y
IA
E
x
W
x
2
22
2
x
28
2
km
km
YE
YE
W
km
x2
W
40
x
x
5k
EW
2
m
Y
54
km
YE
W
x
2
2
x
W
YE
YE
W
x2
19 m
.7
k
YE
W
x2
YE
W
x2
55
km
Figure 5: Expected development by 2013.
Page | 38
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 39
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 2 lists on a yearly basis the existing and committed future generating capacity over the period 2009 - 2013. The
table presents the gross and net maximum capacity for each generating unit at each power station and takes account of the
desalination load where appropriate.
Page | 40
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 2: Existing and committed future generating capacity
Power Station Net Generating Capacity (MW)
Type Unit 2009 2010 2011 2012 2013
Al-Ghubrah Power & Desalination Plant Steam Turbine ST 3 8.3 0.0 0.0 0.0 0.0
Steam Turbine ST 4 39.2 39.2 39.2 39.2 0.0
Steam Turbine ST 5 31.8 31.8 31.8 31.8 31.8
Steam Turbine ST 6 30.2 30.2 30.2 30.2 30.2
Gas Turbine GT1 17.8 17.0 17.0 17.0 0.0
Gas Turbine GT2 17.1 17.0 17.0 17.0 0.0
Gas Turbine GT3 17.8 17.0 17.0 17.0 0.0
Gas Turbine GT4 16.4 0.0 0.0 0.0 0.0
Gas Turbine GT5 15.4 0.0 0.0 0.0 0.0
Gas Turbine GT6 17.1 0.0 0.0 0.0 0.0
Gas Turbine GT7 17.3 0.0 0.0 0.0 0.0
Gas Turbine GT8 17.2 0.0 0.0 0.0 0.0
Gas Turbine GT9 17.1 0.0 0.0 0.0 0.0
Gas Turbine GT10 27.4 27.4 27.4 27.4 27.4
Gas Turbine GT11 27.4 27.4 27.4 27.4 27.4
Gas Turbine GT12 95.7 95.7 95.7 95.7 95.7
Gas Turbine GT13 96.4 96.4 96.4 96.4 96.4
Gen sub-total 509.6 398.9 398.9 398.9 308.8
Desalination load 28 28 28 28 20
Net Generation 481.6 370.9 370.9 370.9 288.8
Rusail Power Plant Gas Turbine GT 1 80.6 80.6 80.6 80.6 80.6
Gas Turbine GT 2 80.6 80.6 80.6 80.6 80.6
Gas Turbine GT 3 80.6 80.6 80.6 80.6 80.6
Gas Turbine GT 4 83.9 83.9 83.9 83.9 83.9
Gas Turbine GT 5 83.9 83.9 83.9 83.9 83.9
Gas Turbine GT 6 83.9 83.9 83.9 83.9 83.9
Gas Turbine GT 7 95.9 95.9 95.9 95.9 95.9
Gas Turbine GT 8 94.9 94.9 94.9 94.9 94.9
Net Generation 684.4 684.4 684.4 684.4 684.4
Wadi Al-Jizzi Power Plant Gas Turbine GT3 17.6 17.6 17.6 0.0 0.0
Gas Turbine GT4 27.8 27.8 27.8 27.8 27.8
Gas Turbine GT5 23.6 23.6 23.6 23.6 23.6
Gas Turbine GT6 27.1 27.1 27.1 0.0 0.0
Gas Turbine GT7 26.0 26.0 26.0 0.0 0.0
Gas Turbine GT8 26.6 26.6 26.6 26.6 26.6
Gas Turbine GT9 26.7 26.7 26.7 26.7 26.7
Gas Turbine GT10 27.4 27.4 27.4 27.4 27.4
Gas Turbine GT11 28.3 28.3 28.3 28.3 28.3
Gas Turbine GT12 29.3 29.3 29.3 29.3 29.3
Gas Turbine GT13 30.0 30.0 30.0 30.0 30.0
Net Generation 290.2 290.2 290.2 219.5 219.5
Page | 41
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 42
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In 2010, it is planned to retire the existing units ST3 (8.3 MW) and GT4-9 (100.5 MW). Also, in
2013 ST4 (39.2 MW) and GT1-3 (51 MW) will be retired.
The two Frame 6B gas turbines and the Frame 5P gas turbine have had their retirement delayed until
2012, when the gross generation capacity at Wadi Jizzi will be reduced from 290 MW to 219 MW.
Page | 43
Five-Year Annual Transmission Capability Statement (2009 - 2013)
is connected in order to represent the worst case scenario for the system as a whole, but is making plans to
connect the larger capacity if that is selected. The generation development assumed at Sohar-2 in the
studies used in this Capability Statement are for the first stage increasing system generating capacity by
375MW in 2011 and second stage a further 275 MW in 2012. The project is currently at the consultancy
services stage.
Table 3 summarises the net capacity of the additional future generating plant over the period 2009 to 2013
assumed in this Capability Statement. The table shows that an additional 1800 MW of generating
capacity from these plants is planned to be in service before the 2013 peak.
Sohar Phase II
Phase 1 500
Page | 44
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The interconnected system and the private customer generating plants can with the customer’s agreement
be made available to support the contracted generation under emergency conditions in order to avoid
power cuts in northern Oman because of a shortfall in the contracted generation. These generators are
termed “non-contracted” generating plants. Table 4 shows the non-contracted generating capacity
PDO 60 60 60 60 60
Table 5 summarises the Centrally Dispatched Net Generation Capacity available over the period 2008 –
2013, with the new generation at Barka Phase III, Sohar II and the new Ghubrah 500 MW plant in
service with the planned retirement of generating units at Al Ghubrah and Wadi Al-Jizzi taken into
account.
Page | 45
Five-Year Annual Transmission Capability Statement (2009 - 2013)
6.5 Interconnections
6.5.1 Interconnection with the UAE and the rest of the GCC Grid
The 220 kV transmission interconnection with the United Arab Emirates (UAE) was completed in the
first quarter of 2007. The interconnection connects Mahadah Grid (Al Wasit) to Al Oha Grid Station in
Al Ain in the UAE. However, contractual issues have to date prevented the interconnection from coming
into service. Nevertheless it is reasonable to expect that these will be resolved and that the
interconnection can provide power to Oman in the event of a possible shortfall in generation.
The interconnection is via a 220 kV double circuit overhead transmission line with twin “Arcuria” (2 x
700mm2) AAAC conductors per phase, with a conductor thermal rating of 2000 Amps (i.e. 762 MVA per
circuit).
Page | 46
Five-Year Annual Transmission Capability Statement (2009 - 2013)
In the longer term the principal technical benefit to be obtained from connecting Oman to the GCC Grid
is in a reduced spinning reserve requirement, which will be shared between the members of the
GCC Grid. However, in the shorter term the interconnection will allow Oman to import power from the
GCC Grid to meet any potential generation shortfall. An import capacity of up to 200 MW will be
available from the GCC Grid according to OPWP in its Seven-Year Statement (2009-2015).
Under circumstances where the system frequency is seen to stray outside the specified limits, LDC will
issue dispatch instructions to Generators based on Merit Order to rectify the situation.
Page | 47
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 6: Historic growth in peak demand and transmission losses (2003 – 2008)
System Max Demand (MW) based on gross demand 2232 2371 2495 2613 2773 3139
Annual growth rate based on gross demand (%) --- 6.2 5.2 4.7 6.1 13
System Max Demand (MW) based on net demand 2139 2294 2395 2505 2662 3033
Transmission System Losses (%) 1.64 1.66 1.67 1.47 1.50 2.0
*estimated
Page | 48
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Minimum demand generally occurs on the transmission system during night-time in December/January
when electricity consumption in all major load categories is reduced. In 2008 the system minimum
demand was 586 MW and this occurred on 18 January 2008 at 04:00 AM. The 2008 system minimum
demand was 18.67 % of the 2008 system peak demand. The 24-hour profile for the day of minimum
demand is shown in Figure 7.
1200
1000
800
Load (MW)
600 Load
400
200
0
00
00
00
00
00
0
:0
:0
:0
:0
:0
:0
:0
:0
0:
2:
4:
6:
8:
10
12
14
16
18
20
22
24
Time (hr)
Under clause 3 of Condition 27 of the OETC Transmission and Dispatch Licence it is stated that:
“The Licensee shall, when preparing the Capability Statement …. ensure that the forecasts of electricity
flows and loading on each part of the Transmission System are consistent with the prevailing electricity
demand forecasts prepared and used by the OPWP for the purposes of the Statement of future capacity
requirements required by Condition 5 of the OPWP licence”.
The OPWP demand forecast is based on data supplied to them by the three distribution companies (i.e.
Muscat EDC, Mazoon EC and Majan EC) and includes demand forecasts for the major customers that
are, or will be, directly connected to the OETC transmission system at either 220 kV or 132 kV in their
respective supply areas. The distribution company forecasts are provided in terms of:
Page | 49
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The forecasts supplied to OPWP relate to the totals for each distribution company and do not indicate
how this load is allocated to the individual grid supply points. The forecast data provided to OPWP does,
however, include major future connections and the cumulative increase in load over the seven-year period
covered by the OPWP Statement. OPWP has then reviewed this data and taken a view as to the
probability that the individual schemes will proceed and if so, the rate at which their load will develop.
The outcome of this review is presented as the OPWP Demand Forecast in its Seven-Year Statement.
The OPWP Demand Forecast was therefore taken as the starting point for developing the demand forecast
presented in this OETC Capability Statement. The OETC forecast, however, is required to identify the
future demand at individual grid stations at the system peak for each year over the period 2009 to 2013,
since this information is required for the power flow studies.
Analysis of the demand forecast data used by OPWP in developing its Seven-Year Statement (2008 –
2014) identified basic annual percentage rates of 5, 6 and 7 % respectively for the growth in peak demand
(excluding major projects) in the Mazoon EC, Muscat EDC and Majan DC supply areas. These rates
have been applied to the grid station demands in the respective supply areas as noted by the OETC Load
Dispatch Centre at the 2008 system peak (i.e. on 31 May, 1500hours). The demand associated with major
industrial and tourism projects as assessed by OPWP (with diversity taken into account) was then
superimposed on to the steady growth in the basic demand to produce a basic forecast. Section 5
identified a number of new grid supply points that are scheduled to come into service to meet the summer
peak demands from 2009 onwards. These gird stations will provide load relief to the more heavily loaded
grid stations and in some cases supply new loads.
The distribution companies’ plans for load transfers from existing grid stations that are heavily loaded to
new grid stations are one of the most important elements of the demand forecast. Table 7 summarises the
load transfers adopted in the studies based on consideration of what is required and what OETC has
considered viable. OETC, however, acknowledges that this aspect of the forecast needs to be improved in
future and believes that it would be helpful if the distribution companies were to give greater
consideration to feasible load transfers when planning their distribution networks, and to develop
proposals for load transfers in coordination with OETC.
Page | 50
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 51
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Continue Table 7: Expected Load Transfers between Grid Supply Points (2009-2013).
Majan Area
Ibri Dreez 20
Al Hail Dreez 20
Buraimi Buraimi‐2 50
Shinas Liwa 45
Sohar Sohar Temp. 27
Sohar Liwa 30
Sohar Saham 40
Sohar Free Zone 60
Khabourah Saham 60
Total 27 175 0 110 40
Page | 52
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 53
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 54
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 55
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 9 compares the total demand forecast with the available generating capacity from Table 5 and
shows that with no additional non-contracted generating capacity connected and zero power import over
the cross-border interconnection with the UAE, then there will be a shortfall in generating capacity in
Oman in 2010, 2012 and 2013 should the planned retirements at Ghubrah and Wadi Jizzi go ahead as
planned.
Table 9: Comparison of Demand Forecast with Available Generating Capacity including Planned
Retirements
Table 10 compares the total demand forecast with the available generating capacity from Table 5 and
shows that with the non-contracted generating capacity connected, zero power import over the cross-
border interconnection with the UAE, and the initial tranche of plant retirements at Ghubrah postponed to
2011.
Page | 56
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 10: Comparison of Demand Forecast with Available Generating Capacity with Retirements
Postponed and Non-Contracted Generation in service
Page | 57
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The transmission system data used in the power system studies to determine the system performance over
the period from 2009 to 2013 is presented in Appendix B of this document.
The system data described and presented in Appendix B has been used in a series of load flow studies to
establish the performance of the OETC transmission system at peak demand in each year from 2009 to
2013 inclusive. The studies were undertaken on the basis that all circuits and plant will be available at
system peak in each of the five years and that the system will be developed in accordance with the plans
described in Section 5 of the Statement. The studies also assume that the demand will grow in
accordance with the Demand Forecast, which is consistent with that produced by the OPWP and
distribution companies, and that sufficient generation will be available from both Contracted and Non-
Contracted Generating Plants to meet each annual system peak as indicated in the OPWP latest 7 Year
Statement (2009-2015).
Table 11 shows the generating plant power assumed to be in service at peak load in each year of the study
from 2009 to 2013. Under peak load conditions it is assumed that capacitive support will be fully
switched on, i.e. capacitor banks at 33 kV grid stations are raised to provide maximum reactive power and
voltage support. In the studies the generator terminal voltage and generator-transformer taps are set to
control the voltage on the transmission system at the target busbar to within the allowable limits.
A second series of load flow studies were undertaken with the transmission system supplying minimum
demand. The minimum demand case identifies where there is a risk of the busbar voltages rising above
the voltage limits defined in the Grid Code and where additional generation has to be operated to absorb
excess reactive power, since there are no reactors connected to the system. In 2008 the system minimum
demand was approximately 18% of peak demand and under this condition the generation has been
reduced to a level that provides the necessary margin of reserve capacity that is consistent with the
operational practices adopted by LDC to handle minimum load conditions.
Table 12 shows the generating plant assumed to be in service at minimum load in each year of the study.
For 2009, real data are listed in the table. These actual values have been obtained from the LDC Daily
Report of the 2009 minimum load which occurred on 17 January 2009. The total generation was 623 MW
on that date. Under minimum load conditions it is assumed that all capacitor banks will be switched out.
Page | 58
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 11: Summary of Connected Generation used in load flow studies of maximum demand
Total Gen
(MW) 4359.9 836.5 3563.4 4412.2 437.2 3975.0 5291.2 694.0 4597.2 5770.4 717.0 5053.4 6179.3 673.4 5505.9
Grid Load
(MW) 3324.2 3718.5 4325.8 4800.8 5222.9
Page | 59
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 12: Summary of Connected Generation used in load flow studies of minimum demand
Total Gen (MW) 1113 489.6 623.4 1415.3 543.1 872.2 1525.2 328.7 1196.5 1621.1 329.5 1291.6 2157.1 703.4 1453.7
Grid Load
542 762 1076 1167 1291
(MW)
Page | 60
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The key results of the load flow and fault level studies on the OETC transmission system are presented in
detail in Appendix C for each year over the period 2009 to 2013. System diagrams showing the results of
the peak demand load flows have also been produced and are available in Appendix C.
The Transformers percentage loading of all grid stations at system peak demand are as per Table C.1.
Available spare capacity at each grid station in relation to firm capacity at system peak demand can
be seen in Table C.2. It should be noted that although spare MVA capacities are available at some
individual grid stations, there is no guarantee that all can be exploited simultaneously. Lack of
available generation and/or voltage level limits may restrict simultaneous utilization of all spare
MVA capacities.
Percentage loading of each overhead line and underground cable in the transmission system at system
peak demand is as per Table C.3.
Voltage profile at each 220 kV, 132 kV and 33 kV bus-bar at maximum and minimum load, Table
C.4.
Annual transmission losses at peak demand are as shown Table C.5.
Maximum 3-phase and single-phase to earth short-circuit fault levels are as shown in Table C.6 and
Table C.7 respectively.
The principal findings from the power system studies are:
Page | 61
Fiive-Year Annuall Transmission Capability
C Statem
ment (2009 - 20113)
d) One of the seeven 220 kV double circuuit lines, that between Barrka power staation and Filaj aj grid
station (ciircuits #1 andd #2), is show
wn to be operrating above firm capacityy at the 20099 peak
demand. However, onnce this line is i reinforced with a seconnd double circcuit line the out
o of
firm conddition will be eliminated and the four circuits
c will be
b operating within
w N-1 att peak
demand between
b 20100 and 2013. The
T SPS-SIS 220 kV line will be operaating slightly over-
firm at thee 2011 peak, but OETC is planning to construct
c new
w circuits (3 & 4) betweenn SPS-
2 and SISS to reinforce the 220 kV transmission
t c
capacity betw
ween SPS andd SIS 220 kV V lines
when the new IPP is coonnected at Soohar II.
e) The number of
o 132 kV doouble circuit liines operatingg above firm capacity oveer the period 2009-
2
2013 will be as followss:
• 2009 – 10
• 2010 – 6
• 2011 – 5
• 2012 – 0
• 2013 – 0
Figure 8 shows the reeduction in thhe number off out-of-firm double circuuit lines durinng the
study periiod 2009-20133. There will be no overloaaded lines thrroughout this period.
10
9
8
7
6
5
4
3
2
1
0
2009 2010 2011 2012 201
13
Pagge | 62
Fiive-Year Annuall Transmission Capability
C Statem
ment (2009 - 20113)
f) The number of
o out-of-firm
m grid stationss during the period
p 2009 too 2013 are:
2009 – 19
9
2010 – 21
2011 – 17
7
2012 – 5
2013 – 0
This is sho
own graphicaally in Figure 9.
25
20
15
10
0
2009 2010 2011
1 20
012 2013
Voltaage Issues
g) The voltage at the 220 kV V and 132 kV V busbars wiill be maintaained within the
t ±10 % vooltage
limit at th
he extremes of
o maximum and a minimum m demand durring years 20009-2013, witth one
exception. At the Al Hail
H 132 kV bus, b the voltaage at peak demand will fallfa to 0.88 peer unit
in 2009 an nd to 0.87 perr unit in 20100 unless new capacitor bannks are addedd to supplement the
existing capacitor bankks and providee voltage suppport at Al Haail.
h) The 33 kV busbar
b voltagges at all gridd stations wiill be maintained within ± 6 % of nominal
voltage du
uring these extreme
e load conditions ofo maximum and minimum m demand, i.e. all
33kV busbbars will be within
w the accceptable operaating range sppecified in thee Grid Code.
Pagge | 63
Fiive-Year Annuall Transmission Capability
C Statem
ment (2009 - 20113)
2.5
1.5
0.5
0
2009 2010 2011 20
012 2
2013
Pagge | 64
Fiive-Year Annuall Transmission Capability
C Statem
ment (2009 - 20113)
6
6000
5
5000
4
4000
3
3000
2
2000
1
1000
0
20
009 2010 2011 2012 2013
3
Figure 11: Trennd in peak loaad growth oveer the period 2009-2013.
2
l) The developm
T ments propossed for the trransmission system
s that were
w identifieed in Table 1 will
p
provide an eff
ffective solutioon to the volttage problemss at peak dem
mand.
Pagge | 65
Five-Year Annual Transmission Capability Statement (2009 - 2013)
a) All of the 220 kV busbars have fault levels within the corresponding switchgear ratings over the
period 2009-2013.
b) All the 132 kV buses, except Ghubrah in 2009, have fault levels within the corresponding
switchgear ratings. However, by splitting the busbars for 2010 the fault level is reduced to
within the switchgear rating.
c) The 3-phase short-circuit level at all 33 kV busbars except Rusail, does not exceed the
switchgear rating. At Rusail the fault level marginally exceeds switchgear rating in 2009 and
even less so in 2010.
a) In 2009 the single-phase fault levels at all buses on the transmission system are within the
switchgear rating except at the Ghubrah and MSQ 132 kV busbars, due to delay in splitting
Ghubrah busbars
b) In the years 2010 to 2013 the fault levels across the transmission system are within the
corresponding switchgear short-circuit ratings. During 2010-2012 busbar splitting at Ghubrah
(or MSQ) in addition to Rusail will be adopted. In 2013 fault current limiters will be installed at
Ghubrah, thus limiting short-circuit currents to be within switchgear rating. This will provide a
long-term permanent solution in the OETC Transmission System. In this case, there will be no
need to apply the splitting technique at any busbars in the system. Both Rusail and Ghubrah
Busbars will be operating normally without the need for splitting.
Page | 66
Five-Year Annual Transmission Capability Statement (2009 - 2013)
9. Development Opportunities
From the results of the load flow and fault level studies, and from analysis of the magnitude and location
of generation and demand on the transmission system it is possible to give some indication as to where
future generation and demand can be connected to the transmission system without causing or
exacerbating any critical technical issues.
Figure 12 shows the connectivity of the OETC transmission in 2013 as it extends over the northern
regions of Oman, a distance of around 500km from Shinas in the North West to JBB Ali in the south-east.
To assess how generation and load is distributed over the transmission system the whole supply area has
been split into seven geographic areas:
a) Central Muscat
b) Outer Muscat
c) North Coast
d) Sohar
e) Border and Interior
f) Nizwa
g) Sur.
The Central Muscat area, although geographically the smallest area, is by far the most heavily populated,
with the highest demand and with the greatest amount of connected generation, even though much of the
generation currently operating at Ghubrah is the oldest on the system and the most inefficient.
The Sohar area is rapidly developing around the new port with new industry seeking connections to the
OETC transmission system or the distribution system of the Majan Electricity Company. Some of the
larger industrial customers in this area also operate their own generating plant and on occasions supply
power to the transmission system on a non-contracted basis.
Page | 67
Five-Year Annual Transmission Capability Statement (2009 - 2013)
The North Coast area covers the coastal strip between Barka on the western outskirts of the Muscat area
and Sohar. This area is likely to develop as Sohar port grows, since the main road link between Muscat
and Sohar runs through it. It also has been chosen for the Blue City Development which is a major
residential and tourist development.
The Outer Muscat area is also being developed as a major tourism area along the coast just south of
Muscat, with resorts being developed at Yitti and Yankit. However, the generation in Outer Muscat is
located at Barka, around 140km from the resorts.
The transmission system in the Border area provides the interconnection with the UAE and supplies a
number of grid stations that feed the Majan distribution system to supply a number of small towns and
villages in this remote area. The power station at Wadi Jizzi is located in the north of the area and over
160km from the grid stations at Ibri and Al Hail where the voltage quality is poor. However, the
development plan for the period 2009 – 2013 will see the extension of the 220 kV system from Al Wasit
to Ibri and this should produce a marked improvement in the voltage quality.
The other areas, Nizwa and Sur, are provincial load centres that are exhibiting moderate growth. In both
areas there is a local power station connected to the transmission system, and in the Sur area a private
customer has installed generation that can provide support when required again on a non-contracted basis.
Table 13 compares the generation capacity installed in each of the seven areas with the forecast demand
at the grid station at the annual system peak over the period 2009 to 2013. From the table it can be seen
that there is a surplus of generating capacity in the Outer Muscat area across the period with the
commissioning of Barka Phase 2 in 2009 and new IPP at Barka (Barka -3) in 2011/2012. The power
balance in Central Muscat area is shown to be in deficit over the period from 2009 to 2013.
At Nizwa, the minor surplus in generation in 2009 becomes a deficit by 2011 as the demand grows From
2011 to 2013 there will be a modest, but increasing shortage of generation in the Nizwa area, so there
may be a need for new generation in that area in future.
At Sohar a generation surplus is forecast to 2013 and the magnitude of the surplus suggests it could
remain in surplus for some time after 2013. The load forecast shows there will continue to be high
growth in industrial demand in the Sohar area.
The major power deficit on the transmission system is in the North Coastal area where it increases from
413 MW in summer 2009 peak to 709 MW in 2013. No generation is connected to the transmission
system in this area, which stretches about 180km from east to west, and this area could obtain some
benefit from generation at a central location.
The Border & Interior and the Sur areas will experience an increasing deficit in generating capacity over
the period. By 2013, the deficiency in the two areas will be around 567 MW and 256 MW respectively.
In the Interior the 132 kV transmission system experiences poor voltage levels at peak demand and new
generation could provide the necessary voltage support, although reactive compensation would probably
Page | 68
Five-Year Annual Transmission Capability Statement (2009 - 2013)
be more cost effective. At Sur the voltage problems will be addressed by extending the 220 kV
transmission systems from Jahloot to Sur in 2012.
Table 14 lists the grid stations where spare grid transformer capacity of more than 10 MVA is available1
to supply new demand, on the same area basis as that presented in sub-section 9.1. The MVA figure
quoted refers to the available capacity in 2013.
1
The available capacity was determined in relation to the firm capacity of the substation.
Page | 69
Five-Year Annual Transmission Capability Statement (2009 - 2013)
10
km
25
00
m
m
2
XL
EP
x2
W
YE
YE
W
x2
YE
W
x2
AR
CU
RI
YE Ax
W 2
x2
km
8k
.2
m 3 m2
m
m 9.7 k 500mPE
YE
ru
W
x2 2
Qu
L
x
E X
BL
2
W
51 YE CA
.3k
m 10
km
39
.2k
A
m
R
C
U
AR
R
C
IA
U
R
YE
IA
x
W
x
22
2
x
28
2
km
km
YE
YE
W
km
x2
W
40
x
x
5k
W
2
m
YE
54
km
YE
W
x
2
2
x
W
YE
YE
W
x2
19 m
.7
k
YE
W
x2
YE
W
x2
55
km
Figure 12: Future OETC Transmission System (2013).
Page | 70
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 13: Estimated power surplus and power deficit on an area basis (2009 - 2013)
Page | 71
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 13(continued): Estimated power surplus and power deficit on an area basis (2009 - 2013)
Outer Muscat
Barka phase-1 Power Plant 459 459 459 459 459
Barka phase-2 Power Plant 714 712 711 711 710
New Barka Power Plant 375 650 650
Total Generation MW) 1173 1171 1545.2 1820.2 1819.2
Barka Main 157.0 169.5 135.3 88.0 89.3
Barka Main-2 70.0
Jahloot 94.2 101.2 76.9 53.9 58.0
Amerat 70.0 96.3
Misfah 80.0 81.0 90.7
Mobella 72.3 78.1 86.2 91.4 96.0
Quriyat 30.0 32.8 36.7
Sumail 68.4 78.0 87.3 93.0 98.1
Yankit 33.0 35.5
Yitti 35.0 38.7 42.9 48.1
Total Load (MW) 392 462 534 586 719
Power Surplus (MW) 781 709 1011 1234 1100
North Coast
Total Generation (MW) 0 0 0 0 0
Blue City 20.0 50.0 120.0
Nakhal 41.0 71.4 102.1
Khabourah 126.0 77.3 85.1 88.9 92.9
MIS 80.0 89.6 95.4 103.1
Muladha 204.8 134.0 140.7 149.8 85.8
Rustaq 82.1 89.5 95.3 101.5 105.5
Saham 83.0 94.2 98.0 99.9
Total Load (MW) 413 464 566 655 709
Power Surplus (MW) -413 -464 -566 -655 -709
Page | 72
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 13(continued): Estimated power surplus and power deficit on an area basis (2009 - 2013)
Sohar
Sohar I Power Plant 621 621 621 621 621
Sohar II Power Plant 375 650 650
Total Generation MW) 621 621 996 1271 1271
Sohar Ind'l A 86.8 88.1 89.4 90.8 92.2
Sohar Grid 178.0 123.2 134.3 84.3 88.6
Sohar Temporary 27.0 27.4 27.8 28.2 28.7
Sohar Industrial Area-A (132 kV) 30.0 30.0 50.0 50.0 50.0
Sohar Industrial Area-A (220 kV) 50.0 50.0 120.0 120.0 120.0
Sohar Industrial Area-B (220 kV) 70 120 140
Total Load (MW) 372 319 492 493 519
Power Surplus (MW) 249 302 504 778 752
Border & Interior
Wadi Jizzi Power Plant 290.2 290.2 290.2 219.5 219.5
Total Generation MW) 290.2 290.2 290.2 219.5 219.5
Al Hail 30.7 32.1 36.4 39.3 22.5
Al Wasit 22.1 24.0 27.2 29.4 31.7
Dreez 46.2
Shinas 75.9 37.0 42.0 45.3 48.9
Buraimi 96.4 110.8 125.8 85.8 92.7
Dank 19.1 19.9 22.6 24.5 26.4
Ibri 90.5 95.9 108.9 117.6 103.5
Moltaqa 87.2 88.1
Free Zone 70.0 74.2
Buraimi-2 70.0 75.6
Liwa 75.0 85.1 91.9 96.5
Wadi Sa'a 18.0 30.0 40.0 50.0
Garamco(132 Liwa) 20.0 30.0 30.0 30.0
Total Load (MW) 335 433 508 731 786
Power Surplus (MW) -44 -143 -218 -512 -567
Page | 73
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 13(continued): Estimated power surplus and power deficit on an area basis (2009 - 2013)
Nizwa
Manah Power Plant 279.3 279.3 279.3 279.3 279.3
Total Generation MW) 279.3 279.3 279.3 279.3 279.3
Adam 20.0 22.8 25.5 27.2 30.6
Bahla 65.0 74.1 83.0 88.4 99.4
Izki 57.0 65.0 72.8 57.5 64.7
Nizwa 98.3 112.1 125.6 83.7 94.2
Nizwa University 70.0 78.8
Total Load (MW) 240 274 307 327 368
Power Surplus (MW) 39 5 -28 -47 -88
Sur
Al Kamil Power Plant 282.3 282.2 282.2 282.1 282.1
Total Generation MW) 282.3 282.2 282.2 282.1 282.1
JBB Ali 92.3 105.3 117.9 105.6 74.0
Mudhaibi 62.7 71.5 80.1 70.3 79.0
Mudharib 91.2 104.0 116.4 84.0 94.5
Sur 91.2 104.0 116.4 84.0 94.5
Al Rawdah 15.0 15.2
Al Kamail 30.0 70.3
Al Ayjah 40.0 40.4
Zoom Load 70 70 70
Total Load (MW) 337.4 384.7 500.8 498.8 537.9
Power Surplus (MW) -55 -102 -219 -217 -256
Colour Key:
Generation deficit
Not in service
Page | 74
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 14: Available Grid Station Capacity of more than 10 MVA in 2013
Dank (33.1 MVA); Shinas (13.6 MVA); Liwa ( 13.5MVA); Ibri (12.7MVA);
Border and Interior Bureimi-A (25.6MVA); Bureimi-B (38MVA); Al Hail (13.5MVA); Al Wasit
(26.9MVA)
Izki (47.9 MVA); Nizwa University (31.6 MVA); Nizwa (14.6 MVA);
Nizwa
Bahla (21.4MVA)
Page | 75
Five-Year Annual Transmission Capability Statement (2009 - 2013)
10. Derogation
The load flow studies summarised in Appendix C and discussed in Sections 8 and 9 of this Statement
indicate a number of out-of firm grid stations and circuits in the early years of the Statement. In this final
section we review each station / circuit which is currently failing to meet the N-1 criterion; we describe
the development activities that OETC is undertaking or planning to undertake to address this non-
compliance; and we indicate the expected time by which, in each instance, full N-1 compliance should be
achieved.
It should be noted that the N-1 situation on the transmission system will change in future as demand on
the system increases and as the system configuration changes. It is possible that further N-1 non-
compliances might arise in the future until the overall system becomes substantially more robust through
interconnection. OETC will keep this situation under review, and the non-compliance status will be
updated in the 2010 Capability Statement.
As indicated in sections 8 and 9 and summarized in tables 15 and 16, there are some grid stations and
overhead lines which do not comply with the N-1 criterion. The implicit derogations from the N-1
standard expired on 31st January 2009. It will be necessary therefore for a further location and duration
specific derogations to be put in place by the Authority for each of the out of firm stations noted in table
15, and for each of the out of firm circuits noted in table 16.
The following points should be noted:
1- The loading values show in tables C1 and C3 (Appendix C), are those at the peak load conditions. The
system peak lasts only for a period of less than one hour in one day during the relevant year. (For
example refer to Figure 6 of 2008 daily load curve peak day.)
2- According to the most recent OPWP 7-year statement (2009-2015) which has been approved by AER,
there are two forecast cases: (i) base case, and (ii) high case. The difference between the high and basic
case in 2009 is 64 MW at the peak. This difference increases in the subsequent years and reaches
622 MW in 2013, indicating uncertainty in the forecast over the coming years especially with regards
to new industrial loads. OETC supports OPWP’s view that the likelihood of the high case demands
being realized is heavily dependent on the rate of recovery of the current global economic and
financial conditions. OETC intends to monitor closely, in coordination with OPWP, the situation in
order to assess the probability associated with the high case projection.
3- It is not prudent to invest in uncertain expansion. OETC will, of course, initiate new projects as new
demand becomes more certain. Therefore, in Tables 15 and 16 we concentrate on covering N-1
conditions at the peak in 2009.
4- The modelling reflects all load transfer schemes that have been formally accepted by the relevant
distribution company and included in their load forecasts. In addition, the modelling includes certain
load transfer schemes, which are not yet confirmed by the distribution company concerned, but which
Page | 76
Five-Year Annual Transmission Capability Statement (2009 - 2013)
in the view of OETC are technically feasible and where no technical impediment to implementation
exists.
OETC has adopted a three-fold approach to addressing these out of firm situations:
1) Reinforcement plans: strategic upgrading to add new circuits and/or to increase the capacity of
grid stations within a minimum of two to five years. This will not just solve the problem; but it
will also strengthen the transmission system for future development. This type of solution can only
be applied as a longer term solution because of the time taken to implement. Reinforcement is the
most robust long term solution for secure system development, but may not necessarily be the least
cost solution to address the immediate out of firm conditions on the network.
2) Installing temporary transformers at heavily loaded grid stations, such as MSQ, Bousher, Mawalih,
and Seeb Main. These will provide a temporary solution to the out-of-firm problems at the heavily
loaded grid stations until a permanent solution is put in place.
3) Load Transfer: through agreement with distribution companies, load can be transferred from
heavily loaded grid stations to more lightly loaded grid stations over the next three years. This
would reduce the loading issues and balance the system during peak time. This is a mid-term
solution which could be implemented with the cooperation of distribution companies in certain
cases. Given the uncertainty of mid-term load forecasts in Oman at present, this is in some
circumstances the most appropriate and economic action to address out of firm conditions on the
network.
Tables 15 and 16 indicate a number of locations on the system where, at present, the out of firm condition
of certain circuits or transformers is shown to exist to 2013 and possibly beyond. In respect of these
currently unresolved out-of-firm conditions, OETC intends to hold further in-depth discussions with
relevant system users, and particularly with the distribution companies, over the coming months to
explore all possible options and to agree the most suitable option in each case. In this way, it is OETC's
objective that the 2010 Capability Statement will forecast full resolution of the out-of-firm conditions by
the end of the next Capability Statement period.
Page | 77
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 15: Expected Over head lines/ cables which will not comply with N-1 criterion at peak demand in 2009
Indicative Date
Circuit Circuit
Receive Voltage No. of Circuit Conductor Loading for full
No Send Bus length Rating Proposed solution Mitigation
Bus (kV) circuits Type Size/Type (%) Compliance
(km) (MVA)
against N-1
Construction of new
220kV line between SIS
9 Wadi Jizzi Al Wasit 132 2 OHL ELM x 2 33 163 68.54 End Q3 2010
and Mahadah ( In
progress)
Construction of new
10 Wadi Jizzi Shinas 132 1 OHL ELM x 1 45.6 82 105.20 Q3 2009
double-circuit line
Design required for
Wadi
11 Wadi Kabir 132 2 OHL YEW x 1 8 130 54.81 Q2 2011 upgrading to twin
Adai
conductor (Q4 2010)
* This project was planned to upgrade the conductors but Government requirements may now mean that undergrounding is necessary. Await final government decision and review project if necessary.
Page | 78
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table 16: Expected Grid stations/ Transformers 132/33 kV which will not comply with N-1 criterion at peak demand in 2009.
Total Substation
Transformer Firm Loading Indicative Date for full
No. Location Proposed Solution Mitigation
Capacity Capacity (%) Compliance against N-1
(MVA) (MVA)
Page | 79
Five-Year Annual Transmission Capability Statement (2009 - 2013)
An important change to the Omani electricity sector is the new interconnector between Oman and the
UAE (GCC link). The work on the interconnector was completed in the first quarter of 2008, but the
circuits will not come into use until the GCC Intergovernmental Agreements are signed. A further
development is the Mahadah to SIS interconnection through a 220kV double circuit. There are a
significant number of projects required to meet the annual peak demands over the period of this Statement
(2009-2013). These projects are considered below under the following categories:
• Projects that are at the tender evaluation stage prior to appointment of the preferred
EPC Contractor.
• Projects for future developments which represent the least cost options to address
problems with system growth, voltage profile, N-1 security criteria transmission system
reinforcement.
The entire programme of ongoing and future projects which are planned for implementation over the
period 2009 to 2013 are listed and described below. It should be noted that the project numbers referred
to in the Appendix are identical to those in Table 1 of the Executive Summary, and it should also be noted
that not all of the projects described have full authorisation at this time.
This project is in its final stage of construction and was completed on 10 June 2009.
Page | 80
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Project #2: Upgrade of the transformer capacity at Nizwa and Bahla grid stations
The 132/33 kV grid stations at Nizwa (2 x 63 MVA) and Bahla (2 x 40 MVA) were both loaded
above firm capacity at peak demand in 2008 and to address this situation both grid stations will
have their existing transformers replaced with 2 x 125 MVA transformers. One 125MVA
transformer at each grid station was energised in May 2009.
The new 132/33kV, 2 x 125 MVA GSP at Muladha in South Batinah is being constructed on the
same site as the MIS 220/132 kV interconnection grid station. One transformer at this new GSP
station was energised on 11 April 2009. This GSP will provide load relief to the existing Muladha
(11km from MIS) and Khabourah substations (53km from MIS).
Project #6: New 220 kV double circuit line between Barka Power Station and Filaij
(circuits 3 and 4)
The capacity of the existing 220 kV double circuit line between Barka Power Station and Filaij
220/132 kV grid station needs to be reinforced in order to satisfy the N-1 security criterion when
the Barka power station phase 2 development is commissioned in 2009. To reinforce the
Page | 81
Five-Year Annual Transmission Capability Statement (2009 - 2013)
connection a second 220 kV double circuit line between Barka Power Station and Filaij was
scheduled to be commissioned at the end of 2009. The contract has been awarded and is in
progress. This project has been delayed due to routing problems and a longer than expected
delivery time for the 220 kV circuit breakers.
Page | 82
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Project #12: Replacing portion of existing 220kV & 132kV OHL by Underground cables
near existing & planned residential Area in Muscat
Replacement of the existing 220kV & 132kV overhead lines with underground cables near
existing and planned residential areas within the Muscat governorate is required for
environmental reasons. When the transmission towers were established around fifteen years ago
the Muscat area was not so heavily residential, but with urban development has come increased
health and safety considerations. Undergrounding will also assist in eliminating or at least
reducing the voltage drop issues that occur with overhead lines. The project is scheduled to be
completed by the second quarter of 2010.
A new 132/33 kV 40 MVA transformer will be installed temporarily at Ghubrah by the second
quarter of 2010 to support the existing 40MVA transformers by providing load relief of up to
30MW to meet N-1. The transformer will be in service until the capacity is upgraded to 2 x
125MVA to meet the 2012 peak.
A 132/33 kV 63 MVA transformer will be installed temporarily at Seeb Main by the second
quarter of 2010 to support the existing 63 MVA transformers by providing load relief of up to
30MW to meet N-1. As with Project #17, the transformer will be in service until the capacity is
upgraded to 2 x 125MVA at some later date.
Page | 83
Five-Year Annual Transmission Capability Statement (2009 - 2013)
A third 132/33 kV 125 MVA grid transformer will be installed at MSQ to shift around 60MW
from the existing two transformers in order to meet N-1. The work is scheduled for completion in
the second quarter of 2010.
A third 132/33 kV 125 MVA grid transformer will be by installed at Mawilah to shift around
60MW from the existing two transformers in order to meet N-1. The work is scheduled for
completion in the second quarter of 2010.
Page | 84
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Project #21: New 132/33kV grid supply point at Misfah and 132 kV connection
The new 132/33 kV 2 x 125 MVA grid station at Misfah is scheduled to come into service in the
first quarter of 2011 to accept load transfers from Rusail, and meet future load growth and
support the system voltage. The existing 132 kV Rusail – Wadi Adai double circuit line will be
looped in and out of Misfah.
Project #22: Upgrade of the 132 kV connection between Dank and Al Hail
The existing connection to Al Hail is by a 132 kV 52km single circuit overhead line from Dank
which is not compliant with the N-1 security requirements and therefore in contravention of
Licence Condition 26. Al Hail also suffers the worst voltage conditions on the OETC
transmission system because of its remote location on the system and its single circuit connection.
Upgrading the connection to a double circuit is considered a high priority scheme and is required
at the earliest date. OETC has taken action to that effect and as a result the work is scheduled for
completion in the first quarter of 2011.
Project #24: Upgrade of the 132 kV double circuit line between Al Wasit and Buraimi
The existing 132 kV, 33 km double circuit line between Al Wasit and Buraimi was operating
over-firm under 2008 peak load conditions, with each circuit loaded at 80% of thermal rating. To
increase the capacity of the single ‘Elm’ conductor per phase to be replaced with twin ‘Yew’
conductor, but to carry the extra weight of the conductor the line will be rebuilt with steel lattice
towers. Approximately 6km of the route will be by underground cable to avoid environmental
impact and related health and safety issues, the cable size chosen to match the capacity of the
upgraded conductor. The work is scheduled to be completed by the fourth quarter of 2010.
Project #25: 220 kV double circuit line between SIS (Seh Al Makarim) and Al Wasit
With the completion of this project, a double circuit 220 kV connection will be established across
northern Oman from MSQ grid station in Muscat to the 220 kV interconnection with the UAE at
Mahadah (Al Wasit). This will strengthen the network and improve the effectiveness of the
cross-border interconnector. This work is scheduled to be completed during the third quarter of
2010. The EPC contract is awarded.
The electricity supply to the new Blue City development in the South Batinah region will be fed
from a new 220/33 kV grid supply point connected between the MIS and Filayj grid stations by
Page | 85
Five-Year Annual Transmission Capability Statement (2009 - 2013)
routing the 220kV MIS – Filayj double circuit connection through the new grid station in a line-
in-line-out (LILO) arrangement. The diversion will require two 220 kV double circuit overhead
lines over part of the route and four 220 kV 2500mm2 cable circuits over the last 6 km of the
route as it reaches the Blue City grid supply point. The project is dedicated to supply the Blue
City project as requested by Mazoon Electricity Company and is currently in the design stage
with the EPC tender ready to be floated when confirmation to proceed is received from Mazoon.
At present the grid station is due in service during the first quarter of 2011.
The Muttrah area is currently supplied from the existing Al Falaj and Wadi Kabir grid stations,
which were both operating above firm capacity under 2008 peak load conditions. The work is
scheduled to be completed during the fourth quarter of 2010.
The new grid station at Muttrah is preferred to the alternative of reinforcement of the existing Al
Falaj and Wadi Kabir grid stations although it may be more complex and costly to undertake due
to constraints on available building land due to the mountainous nature of the terrain.
Project #28: Second phase of development at Sohar Industrial Area 220/132 kV grid
station:
This project is required in order to meet the expected industrial demand growth in Sohar
industrial area. In addition this project will support and ensure that the existing Sohar Industrial
Area 220/132/33 kV grid station which developed in the first phase meets the N-1 security
requirements. This grid station is scheduled for the final quarter of 2010. This project was
proposed to be 220kV/132kV/33kV but after confirmation from Majan, the grid will be
constructed as 220kV/132kV system and it is designed to accept 33kV if required in the future.
Currently there is one customer to be fed from this grid station, confirmed at around 90MW as a
first stage, later rising to 170MW.
Page | 86
Five-Year Annual Transmission Capability Statement (2009 - 2013)
This project will be done in addition to project # 16 where a fourth transformer will be installed at
MSQ (MSQ-2) as part of the scope of this project. By this project MSQ-1 will meet N-1 and will
be fine for the expected load in the area. This project is expected to be in service by Q2 2011.
This project will be done in addition to project # 17 where a fourth transformer will be installed at
Mawalih ( Mawalih-2) as part of the scope of this project. By this project Mawalih-1 will meet N-
1 and will be fine for the expected load in the area. This project is expected to be in service by Q2
2011.
Project #32: Upgrade of Ibri grid station from 2 x 63MVA to 125MVA transformers
The existing 2 x 63 MVA, 132/33 kV grid supply point at Ibri in the Dhahirah region was
overloaded during the 2008 summer peak. The favoured option for this project is to replace the
two 63 MVA transformers with 2 x 125 MVA transformers. The award of the Consultancy
Contract was done in last October 2008 and the project is scheduled to be completed by Q2 2010.
Project #33: Construct 132/33 kV grid station at Nakhal area with associated transmission
system:
Construct 132/33kV Nakhal new grid stations and connect it with Al-Falij via 132kV lines. This
project will assist with the new load growth in the area and also support the voltage. The load at
Nakhal is now fed by two 33kV feeders from Barka main grid station which is fully loaded. This
project will release load from Barka main. This project is expected to be completed by final
quarter of 2010 and so will meet the peak of year 2011.
Page | 87
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Dakhliah) through Misfah –Nizwa university 220kV system later on .This project is expected to
be completed on second quarter of 2011 before the 2011 peak.
A.5 Projects expected to be completed in time to meet the 2012 peak demand:
In the second phase, with the 220 kV system extended to Jahloot and a 132 kV GSP established at
Yitti, a 132 kV double circuit line would be built to supply Yankit from Yitti. The proposed new
resort at Seefa, only 15km from Yankit, would be supplied from Yankit at 33 kV. A number of
options are still being considered by OETC before tender documents are finalised and issued for
the appointment of a consultant. The project is expected to be completed by Q2’12. In addition
confirmation of requirements has been requested from Muscat Distribution Company.
Project #36: 220/132 kV Grid Supply Point at Jahloot connected to Misfah Grid Station via
220kV DCCT line:
Extension of 220 kV transmission system from Misfah to Jahloot with a 220 kV, ≈ 100km double
circuit line to the new grid station will eliminate voltage problems in the Jahloot area and
strengthen the supply to this provincial expected load centre. The Existing Jahloot grid station
will be connected to the proposed 220/132kV system by installing 2 x 500MVA transformers.
This project will feed the Yitti and Quriat grid stations and the 220kV system will be extended to
Sur. This project expected to be completed by the end of the second quarter of 2012.
Page | 88
Five-Year Annual Transmission Capability Statement (2009 - 2013)
This project is to upgrade the two transformers of Mudaibi grid stations from 63MVA to
125MVA. The project will have an impact on reducing the overloading on the grid stations and
also will support the voltage in the area. This project is expected to be completed by second
quarter of 2012.
Construct of a new 132/33kV GSP at Nizwa to meet the load requirement in the area. It will also
facilitate the Duqm project, if that development proceeds. The project will be in by second
quarter of 2012.
Page | 89
Five-Year Annual Transmission Capability Statement (2009 - 2013)
This project will be constructed to connect the new IPP power at Barka this station will be
connected to the proposed Barka-2 as interconnect grid for other links ( Wadi Adai, Jahloot and
Nizwa University (Duqm project)). This grid will be connected through 220kV overhead lines
30km of high rating conductors to curry around 750MW and around 6km of 2500mm2 cables due
to difficulties of rout between Barka and Filaj. The consultancy tender is in progress. This project
expected to be in service Q1’2012.
Currently this grid is 2 x 42MVA and not meeting N-1; the proposed new scheme will be 2 x
125MVA transformers with the GIS outside the Ghoubrah power plant area to connect the new
proposed IPP for Ghoubrah. By construction of this project Ghoubrah will meet N-1 and
accommodate the new growth in coastal area on Bousher. This project expected to be in serves by
end of Q2 2012.
This grid will be connected through 220kV overhead lines 45km from Misfah grid. The proposed
grid will be connected to the existing 132/33kV grid at Wadi Adai. The route for this grid is high
terrain. By construction of this grid all stressed 132kV lines between MSQ and Wadi Adai will be
released and the voltage will be improved in the area. The consultancy tender is in progress. This
project is expected to be in service by Q1’2012.
Project #48: Construction of new 220kV lines between SPS and SIS grid stations:
This project will be constructed to connect the new IPP power at Sohar by construction of 220kV
over head lines 36km and around 6km underground cables these lines will be connected to the
proposed Sohar-2 (SPS-2) as interconnect grid station. These lines will be designed as high rating
conductors to carry around 750MW and. The consultancy tender is in progress. This project
expected to be in service Q1’2012.
This grid will be used for the new IPP at Barka (Phase-3). The grid will be as interconnection bus
for the new IPP and for the new proposed 220kV lines which will be connected to Misfah. The
proposed Bus will be connected to the existing through two bus section CBs and are kept open if
all machines are running to avoid high short circuit effect on the existing grid, by using proper
inter locking scheme. This project will be in line with Misfah and Wadi Adai projects. This
project expected to be in service at Q1’2012.
Page | 90
Five-Year Annual Transmission Capability Statement (2009 - 2013)
This grid will be used for the new IPP at Sohar (Phase-2). The grid will be as interconnection bus
for the new IPP and for the new proposed 220kV lines which will be connected to SIS. The
proposed bus will be connected to the existing through two bus section CBs and kept open if all
machines are running to avoid high short circuit effect on the existing grid, by using proper inter-
locking scheme. This project will be in line with Misfah and Wadi Adai projects. This project
expected to be in service at Q1’2012.
This project will be as new grid 132/33kV with 2 x125MVA connected as LILO between MSQ-
Jahloot 132kV lines. This grid will support the low voltage in Al Amerat area which currently fed
from Jahloot. This grid will release load from Jahloot around 40MW and can be used to transfer
load from Wadi Adai through three number of 33kV lines. The location of this grid will be
finalized by MEDC. This project expected to be in service Q2’2012.
This project will be as new grid 132/33kV with 2 x125MVA connected to Sohar grid around
10km. This grid will relief load from Sohar Grid and to cater for load growth in the area.. The
location of this grid will be finalized by Majan Company. This project expected to be in service
Q2’2012.
This project will be as new grid 132/33kV with 2 x125MVA connected to Airport Heights grid
around 10km. This grid will release load from Bousher Grid and cater for load growth in the area.
The location of this grid will be finalized by MEDC. This project expected to be in service
Q2’2012.
This project will be as new grid 132/33kV (Burimai-2) with 2 x125MVA connected to the lines
between Mahadah and the existing Al Buraimi grid as LILO for an around 4km. This grid will
release load from Buraimi Grid and to cater for load growth in the area.. The location of this grid
will be finalized by Majan Co. This project is expected to be in service by Q2’2012.
Page | 91
Five-Year Annual Transmission Capability Statement (2009 - 2013)
This project will be as new grid 132/33kV Free Zone with 2 x125MVA connected proposed SIA-
2 grid station (220/132kV) around 7km underground cable from SIA-2. This grid will release
load from Liwa Grid and cater for the load growth in the area. The location of this grid will be
finalized by Majan Company. This project expected to be in service Q2’2012.
This project will be connected to existing upgraded Sur grid station which includes the
construction of a new 132kV/33kV grid station in the Al Aijah area to meet the new tourism load
in the Ras Al Had area, and to support the voltage with 25km over head lines. Currently the load
is supplied through 33kV lines of around 60km from the existing Sur grid station 132kV/33kV.
This project is included in the price control as Sur-2 station, but after discussion with Mazoon
Company, it has been decided to build new grid station in a location selected by Mazoon
Company. The route survey has been started to save time and to assist in the selection of the
proper location for this grid station. This project expected to be completed by the end of the
second quarter of 2012.
Project #57: Adding 2 new 132kV lines between Barka Main and Filaj:
This project will be as new 132kV overhead lines( 3 and 4) connected between Filaj and Barka
Main around 11km steel towers. By construction of these lines the other existing lines (1and 2)
will meet N-1. This project expected to be in service Q2’2012.
These lines are constructed as single conductor which is not N-1. By construction of these lines
the N-1 criteria will be met. This project expected to be in service Q2’2012.
New grid station will be constructed at Adreez area as 132/33 kV 2 x 63MVA transformers and it
will be connected to Ibri grid station 30km on steel tower. This grid will support the low voltage
in distribution system in the area and to release load from Ibri and Al Hail. This project expected
to be in service at Q1’2013.
Page | 92
Five-Year Annual Transmission Capability Statement (2009 - 2013)
New grid station will be constructed at Al Khoudh area Muscat) area as 132/33kV 2 x 125MVA
transformers and it will be connected to Al Mawalih grid station 10km on steel tower/cable. This
grid will release load from Mawalih and Seeb Main grid stations. This project expected to be in
service at Q1’2013.
This project will be by adding two 125MVA transformers to the existing grid, which will be
connected to the 132kV bus bar and the 33kV side will be as two groups to avoid short circuit and
complication of the operation of these transformers. This grid will release load from Existing
Barka Main grid. This project expected to be in service at Q1’2013.
The existing lines are not N-1 , and these lines are owned by United Power Company(UPC), and
need to be confirmed and addressed to them either by upgrading the conductor or by adding new
circuits. This project expected to be in service at Q1’2003.
The existing grid station is 30MVA it will be upgraded to 63MVA to meet the N-1 and to cater
for the load growth in the area. Normally the growth in this area is very slow which can be
overcome by using this capacity of transformers. This project expected to be in service by end of
Q1’2013
The short circuit current for the existing Goubrah grid station are more than the rated (26.2kA and
31.5kA). To address the fault level issues at Ghubrah power station a number of design options
are under evaluation to determine the most appropriate long term solution for the site. OETC is
looking seriously to add additional fault current limiter elements for each out going circuits. This
option will be studied by third party to select the proper technology used and selecting the best to
avoid any complication or any system stability problems which may will occur. By installing this
equipment the short circuit current will be reduced on (Bousher and MSQ). This project expected
to be in service by end of Q1’2013.
Page | 93
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Although the thermal rating of an overhead line is affected by climatic conditions, for the purpose of
assessing spare capacity on the transmission system the key climatic condition that limits the circuit rating
is the summer rating when the temperature is at its highest and the solar radiation is at its peak. This also
corresponds to when the electricity demand is at or near to its peak.
The circuit data presented in Table B.2 for the first year of the Statement period (2009) comprises the
voltage, resistance, reactance, susceptance and thermal rating of the line and cable circuits. It also shows
the circuit length and the type of overhead conductor or underground cable for each circuit.
Table B.3 shows the changes to the circuit data required in each of the other four years covered by the
Statement.
2
The 33 kV busbars at the grid supply points and the capacitors connected to them are owned and operated by the distribution companies.
Page | 94
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table B.1: Load and Capacitor Data for Grid Stations (2009 - 2013)
Page | 95
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table B.1 (continued): Load and Capacitor Data for Grid Stations (2009 - 2013)
Page | 96
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table B.1 (continued): Load and Capacitor Data for Grid Stations (2009 - 2013)
Sohar Industrial Area-A (132 kV) 30 14.5 0 30 14.5 0 50 24.2 0 50 24.2 0 50 24.2 0
Sohar Industrial Area-A (220 kV) 50 24.2 0 50 24.2 0 120 58.1 0 120 58.1 0 120 58.1 0
Sohar Industrial Area-B (132 kV) 70 33.9 0 120 58.1 0 140 67.8 0
Garamco (132 kV liwa) 20 9.7 0 30 14.5 0 30 14.5 0 30 14.5 0
Zoom Load (Sur Area) 70 33.9 0 70 33.9 0 70 33.9 0
Transport (Muscat) 20 9.7 0 20 9.7 0 20 9.7 0
GRAND TOTAL (MW) 3324.5 1755.6 390.0 3718.6 1958.0 650.0 4325.9 2265.2 630.0 4800.8 2497.8 670.0 5222.9 2717.4 790.0
Page | 97
Five-Year Annual Transmission Capability Statement (2009 - 2013)
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Al Wasit Al Oha (UAE) 220 2 ARCURIA x 2 46.7 0.0025 0.0310 0.0863 762 − − − − − −
Barka Power station Filaj 220 2 ARCURIA x 2 10 0.0005 0.0066 0.0185 762 − − − − − −
MIS SIS 220 2 ARCURIA x 2 107 0.0057 0.0710 0.1978 762 2500mm2 XLPE cable 0.1 0.000005 0.0001 0.0002
762
SPS SIS 220 2 ARCURIA x 2 38 0.0020 0.0252 0.0703 762 2500mm2 XLPE cable 3 0.0002 0.0020 0.0055
762
SPS Sohar Industrial Area 'A' 220 2 − − − − − − 2500mm2 XLPE cable 3 0.0002 0.0020 0.0055
762
Barka Main Filaj 132 2 YEW x 2 6.3 0.0015 0.0102 0.0044 261 − − − − − −
Ghubrah Boushar 132 2 240 ZTACIR 2.2 0.0018 0.0052 0.0011 261 800mm2 XLPE cable 0.5 0.000414 0.00119 0.000242 261
Ghubrah MS Qaboos 132 2 YEW x 2 6.1 0.0015 0.0099 0.0042 261 800mm2 XLPE cable 0.3 0.0001 0.0005 0.0002 261
Ghubrah MS Qaboos 132 2 YEW x 2 6.6 0.0016 0.0107 0.0046 261 800mm2 XLPE cable 1 0.0002 0.0016 0.0032 261
Mawellah Seeb Main 132 2 240 ACSR 7.8 0.0066 0.0184 0.0038 101 − − − − − −
Mawellah Rusail 132 2 240 ZTACIR 8 0.0066 0.0191 0.0039 261 800mm2 XLPE cable 0.3 0.0002 0.0007 0.0001 261
Mabalah Barka Main 132 2 YEW x 2 11.6 0.0029 0.0188 0.0080 261 − − − − − −
Page | 98
Five-Year Annual Transmission Capability Statement (2009 - 2013)
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
MS Qaboos Jahloot 132 2 YEW x 2 44 0.0108 0.0712 0.0305 261 800mm2 XLPE cable 0.1 0.00002 0.0002 0.0001 261
MS Qaboos Wadi Adai 132 2 YEW x 2 8.2 0.0020 0.0133 0.0057 261 800mm2 XLPE cable 0.2 0.00005 0.0003 0.0001 261
Rusail Wadi Adai 132 2 YEW x 2 46.5 0.0114 0.0753 0.0322 261 800mm2 XLPE cable 0.5 0.0001229 0.0008095 0.0003467 261
SIS Sohar Grid 132 2 YEW x 2 27.5 0.0068 0.0445 0.0191 261 − − − − − −
Sohar Grid Wadi Jizzi 132 2 YEW x 2 24.7 0.0061 0.0400 0.0171 261 − − − − − −
Sohar Grid_ ext Wadi Jizzi 132 2 YEW x 2 0.1 0.0000 0.0002 0.0001 261 − − − − − −
Sohar Industrial Sohar
132 2 − − − − − − 800mm2 XLPE cable 2.2 0.0005 0.0036 0.0015 261
Area 'A' Refinery Co.
Sumail Izki 132 2 YEW x 2 61 0.0150 0.0988 0.0423 261 − − − − − −
Wadi Adai Al Falaj 132 2 YEW x 2 3 0.0007 0.0049 0.0021 261 800mm2 XLPE cable 0.3 0.0001 0.0005 0.0002 261
Wadi Jizzi Al Wasit 132 2 ELM x 2 36.7 0.0205 0.0667 0.0243 163 − − − − − −
Wadi Kabir Wadi Adai 132 2 YEW x1 6 0.0029 0.0136 0.0030 130 800mm2 XLPE cable 1.1 0.0005 0.0025 0.0006 130
Page | 99
Five-Year Annual Transmission Capability Statement (2009 - 2013)
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Filaj MS Qaboos 220 2 ARCURIA x 2 59 0.0031 0.0391 0.1091 760 − − − − − −
Mawellah Seeb Main 132 2 240 ACSR 8 0.0068 0.0189 0.0039 101 − − − − − −
Ghubrah Boushar 132 2 240 ZTACIR 4 0.0033 0.0095 0.0019 261 800mm2 XLPE cable 0.5 0.000414 0.00119 0.000242 261
Ghubrah MS Qaboos 132 2 YEW x 2 7 0.0018 0.0116 0.0050 261 800mm2 XLPE cable 0.3 0.0001 0.0005 0.0002 261
Ghubrah MS Qaboos 132 2 YEW x 2 7 0.0018 0.0116 0.0050 261 800mm2 XLPE cable 1 0.0002 0.0016 0.0032 261
2010 Additions
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Filaj Airport Heights 220 2 ARCURIA x 2 28 0.0015 0.0186 0.0518 762 − − − − − −
Barka Power station Filaj 220 2 ARCURIA x 2 11 0.0006 0.0073 0.0203 762 − − − − − −
Airport Heights Wave 132 2 − − − − − − 2000mm2 XLPE cable 10 0.0025 0.0162 0.0069 261
Ghubrah Boushar 132 2 − − − − − − 2500mm2 XLPE cable 2.25 0.0006 0.0036 0.0016 261
Ghubrah MS Qaboos 132 2 − − − − − − 2500mm2 XLPE cable 4.8 0.0012 0.0078 0.0033 261
Ghubrah MS Qaboos 132 2 − − − − − − 2500mm2 XLPE cable 4.35 0.0011 0.0070 0.0030 261
Page | 100
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table B.3 (continued): Progressive Changes to Branch Circuit Data for 2010-2013
2011 Deletions
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Filaj MIS 220 2 ARCURIA x 2 64 0.0034 0.0424 0.1183 762 − − − − − −
Rusail Wadi Adai 132 2 YEW x 2 46 0.0113 0.0745 0.0319 261 800mm2 XLPE cable 0.5 0.0001229 0.0008095 0.0003467
261
Rusail Boushar 132 2 240 ZTACIR 31.5 0.0261 0.0750 0.0153 261 800mm2 XLPE cable 0.5 0.000414 0.00119 0.000242 261
2011 Additions
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Al Wasit SIS 220 2 ARCURIA x 2 66 0.0035 0.0438 0.1220 762 − − − − − −
Filaj Blue City 220 2 ARCURIA x 2 39.2 0.0021 0.0260 0.0725 762 2500mm2 XLPE cable 6 0.0003 0.0040 0.0111
762
Blue City MIS 220 2 ARCURIA x 2 51.3 0.0027 0.0340 0.0948 762 2500mm2 XLPE cable 6 0.0003 0.0040 0.0111
762
SPS Sohar Industrial Area 'B' 220 2 − − − − − − 2500mm2 XLPE cable 3 0.0002 0.0020 0.0055
762
Al Wasit Ibri 220 2 ARCURIA x 2 134 0.0071 0.0889 0.2477 762 − − − − − −
MS Qaboos Qurum 132 2 YEW x 2 10 0.0025 0.0162 0.0069 261 2500mm2 XLPE cable 0.3 0.0001 0.0005 0.0002
261
Qurum Muttrah 132 2 YEW x 2 9.7 0.0024 0.0157 0.0067 261 2500mm2 XLPE cable 3.2 0.0008 0.0052 0.0022
261
Al Wasit Buraimi 132 2 YEW x 2 33 0.0081 0.0534 0.0229 261 − − − − − −
Mawellah Rusail 132 2 240 ZTACIR 8 0.0066 0.0191 0.0039 261 800mm2 XLPE cable 0.3 0.0002 0.0007 0.0001 261
Airport Height Bousher 132 2 240 ZTACIR 15 0.0124 0.0357 0.0073 261 − − − − − −
Page | 101
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table B.3 (continued): Progressive Changes to Branch Circuit Data for 2010-2013
2012 Deletions
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Rusail Mabalah 132 2 YEW x2 13.1 0.0032 0.0212 0.0091 261 − − − − − −
Izki Nizwa 132 2 YEW x2 33 0.0081 0.0534 0.0229 261 − − − − − −
Misfah Wadi Adai 132 2 YEW x2 36 0.0088 0.0583 0.0250 261 − − − − − −
Wadi Kabir Wadi Adai 132 2 YEW x1 6 0.0029 0.0136 0.0030 130 800mm2 XLPE cable 1.1 0.0005 0.0025 0.0006 130
Al Wasit Buraimi 132 2 YEW x2 33 0.0081 0.0534 0.0229 261 − − − − − −
MS Qaboos Jahloot 132 2 YEW x2 44 0.0108 0.0712 0.0305 261 800mm2 XLPE cable 0.1 0.00002 0.0002 0.0001 261
2012 Additions
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Jahloot Sur 220 2 ARCURIA x 2 160 0.0085 0.1061 0.2958 762 − − − − − −
IPP Barka Misfah 220 2 ARCURIA x 2 35 0.0019 0.0232 0.0647 762 − − − − − −
IPP Sohar SIS 220 2 ARCURIA x 2 38 0.0020 0.0252 0.0703 762 2500mm2 XLPE cable 3 0.0002 0.0020 0.0055 762
Misfah Wadi Adai 220 2 ARCURIA x 2 36 0.0019 0.0239 0.0666 762 − − − − − −
Misfah Jahloot 220 2 ARCURIA x 2 65 0.0035 0.0431 0.1202 762 − − − − − −
Airport Height Ghala 132 2 YEW x2 10 0.0025 0.0162 0.0069 261
SIA-2 Free Zone 132 2 − − − − − − 2500mm2 XLPE cable 10 0.0025 0.0162 0.0069 261
Sohar Multaqa 132 2 YEW x2 10 0.0025 0.0162 0.0069 261 − − − − − −
Al Wasit New Buraimi 132 2 YEW x2 20 0.0049 0.0324 0.0139 261 − − − − − −
New Buraimi Buraimi 132 2 YEW x2 13 0.0032 0.0210 0.0090 261 − − − − − −
MS Qaboos Amerat 132 2 YEW x2 22 0.0054 0.0356 0.0153 261 − − − − − −
Amerat Jahloot 132 2 YEW x2 22 0.0054 0.0356 0.0153 261 − − − − − −
Wadi Kabir Wadi Adai 132 2 YEW x2 6 0.0015 0.0097 0.0042 261 − − − − − −
Barka Main Filaj 132 2 YEW x2 6.3 0.0015 0.0102 0.0044 261 − − − − − −
Yitti Yankit 132 2 YEW x2 5 0.0012 0.0081 0.0035 261 − − − − − −
Sur Ayjah 132 2 YEW x2 20 0.0049 0.0324 0.0139 261 − − − − − −
Mudhabi Raoudha 132 2 YEW x2 40 0.0098 0.0648 0.0277 261 − − − − − −
Nizwa Nizwa university 132 2 YEW x2 16 0.0039 0.0259 0.0111 261 − − − − − −
Nizwa university Izki 132 2 YEW x2 16 0.0039 0.0259 0.0111 261 − − − − − −
2013 Additions
From To Voltage No. Conductor Length pu on 100 MVA base Rating Conductor Length pu on 100 MVA base Rating
Substation Substation (kV) Circuits type (OHL) Km R[pu] X[pu] B[pu] (MVA) type (Cable) Km R[pu] X[pu] B[pu] (MVA)
Ibri Drezz 132 2 YEW x2 30 0.0074 0.0486 0.0208 261 − − − − − −
Manah Nizwa 132 1 YEW x2 19.7 0.0048 0.0319 0.0137 261 − − − − − −
Mawallih Al Khoud 132 2 YEW x2 10 0.0025 0.0162 0.0069 261 − − − − − −
Page | 102
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Peak 2009
No. of Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance Copper
Substation Units (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) Loss (kW)
Al Wasit 2 315 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23 856.8
Filaj 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.25 750
MS Qaboos 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.3 750
SIP-1 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.075 750
SIS 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.075 750
MIS 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.075 750
Al Falaj 2 125 132/33 YNd5 HV 1.67 4 1 13 5 -15 19.56 340
Al Hail 2 40 132/33 YNd11 HV 1.25 5 1 17 5 -15 11.92 160
Al Wasit 2 30 132/33 YNd11 HV 1.67 4 1 13 5 -15 12.33 135
Bahla 2 125 132/33 YNd5 HV 1.1 6 1 19 5.5 -15.54 18 340
Barka Main 2 125 132/33 YNd5 HV 1.67 4 1 13 5 -15 17 340
Boushar 2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26 340
Buraimi 2 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.82 220
Dank 2 15 132/33 YNd11 HV 1.25 5 1 17 5 -15 11.97 200
Ghubrah 2 42 132/33 YNd5 HV 1.35 5 1 19 5.4 -15.54 13.2 160
Ibri 2 63 132/33 YNd11 HV 1.25 5 1 17 5 -15 10.9 220
Izki 2 40 132/33 YNd5 HV 1.11 6 1 19 5.5 -15.54 10 150
Jahloot 2 125 132/33 YNd5 HV 1.1 6 1 21 5.55 -15.4 19.03 420
JBB Ali 2 125 132/33 YNd5 HV 1.11 6 1 21 5.55 -15.4 17.84 340
Khaburah 2 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 17.78 340
Mawalih 2 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.7 445
Mudarib 2 125 132/33 YNd5 HV 1.11 6 1 21 5.55 -15.4 17.81 340
Muladah (old) 2 125 132/33 YNd5 HV 1.67 4 1 13 5 -15 17 340
Page | 103
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Wadi Adai 2 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 17.94 340
Wadi Kabir 2 125 132/33 YNd5 HV 1.11 6 1 19 5.57 -15.54 18.8 340
Page | 104
Five-Year Annual Transmission Capability Statement (2009 - 2013)
2010 Changes
No. of Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance Copper
Substation
Units (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) Loss (kW)
Deletions
Seeb 2 63 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 16.97 220
Additions
Airport Hight 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23 750
Boushar-2 2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26 340
Liwa 2 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 18.45 340
Saham 2 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 18.45 340
MIS 2 125 132/33 YNd11 HV 1.11 6 1 20 5.55 -15.54 18 340
Airport Hight 2 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 18 340
Azaiba Coast 3 50 132/11 YNd1 HV 1.11 6 1 19 5.55 -15.54 31.5 220
Seeb 2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26 340
Wadi Sa'a 2 63 132/33 YNd11 HV 1.25 6 1 17 5 -15 10.9 220
Yitti 2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26 340
Page | 105
Five-Year Annual Transmission Capability Statement (2009 - 2013)
2011 Changes
No. of Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance Copper
Substation
Units (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) Loss (kW)
Deletions
Dank 2 15 132/33 YNd11 HV 1.25 6 1 17 5 -15 11.97 200
Ibri 2 63 132/33 YNd11 HV 1.25 6 1 17 5 -15 10.9 220
Additions
Sohar industrial area-2 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.075 750
Blue City 2 160 220/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.5 750
Ibri 2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 17.5 750
MSQ-2 2 125 132/33 YNd5 HV 1.67 4 1 13 5 -15 17.44 340
Mawallah-2 2 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.7 445
Qurum 2 125 132/33 YNd5 HV 1.67 4 1 13 5 -15 17 340
Page | 106
Five-Year Annual Transmission Capability Statement (2009 - 2013)
2012 Changes
No. of Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance Copper
Substation
Units (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) Loss (kW)
Deletions
Mudaibi 2 63 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.4 15.21 220
Page | 107
Five-Year Annual Transmission Capability Statement (2009 - 2013)
2013 Changes
No. of Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance Copper
Substation
Units (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) Loss (kW)
Deletions
Page | 108
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.2 – Available capacity at Grid Stations (2009 – 2013) for connection of new demand
Table C.3 – Overhead line and cable circuit loadings at peak demand (2009 – 2013)
Table C.4 – Transmission system voltage profile at peak and minimum demand (2009 – 2013)
Table C.6 – Maximum 3-Phase Short Circuit Fault Levels (2009 – 2013)
Table C.7 – Maximum Single-Phase Short Circuit Fault Levels (2009 – 2013).
C.3 Diagrames of the model for the Load Flow Study Results
The result of peak demand load flow studies for the years 2009 through to 2013 are presented as Figures
C.1 to C.5 respectively.
Page | 109
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 110
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 111
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 112
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.2: Available Capacity at Grid Stations (2009 – 2013) for Connection of New Demand
Total Available capacity (MVA)
Substation
Transformer
Location Firm Capacity
Capacity 2009 2010 2011 2012 2013
(MVA)
(MVA)
220/132 kV Transformers
Airport Heights 2 x 500 500 414.3 314.1 213.2 258.1
Al Wasit 2 x 315 315 298.2 166.3 94.6 122.8 5.7
Filaj 2 x 500 500 63.9 54.0 56.4 175.3 89.7
Jahloot 2 x 500 500 312.8 304.7
-
MS Qaboos 2 x 500 500 101.0 -31.3 138.4 192.4 150.6
MIS 2 x 500 500 219.6 198.6 181.4 206.5 212.0
SIS 2 x 500 500 130.0 46.7 205.8 55.9 120.1
Sohar Industrial Port 'A' 2 x 500 500 364.2 394.6 362.3 363.9 365.1
Sohar Industrial Port 'B' 2 x 500 500 422.7 303.9 275.5
Ibri 2 x 500 500 192.4 220.2 190.1
Wadi Adai 2 x 500 500 219.8 305.4
Sur 2 x 500 500 336.6 268.4
220/33 kV Transformers
Blue City 2 x 160 160 137.1 103.7 20.2
132/33 kV Transformers
Adam 2 x 40 40 17.0 13.4 10.6 8.3 5.4
Airport Heights 2 x 125 125 66.1 59.8 53.2 42.6
Al Falaj 2 x 125 125 -73.2 -39.2 16.5 14.7 13.8
Al Hail 2 x 40 40 1.2 0.0 -4.5 -7.2 13.5
Al Wasit 2 x 30 30 2.8 1.6 -1.0 -4.8
Al Wasit (upgrading) 2 x 63 63 26.9
Al Kamil 2 x 125 125 90.6 43.5
Al Raoudha 2 x 125 125 106.6 88.5
Al Koudh 2 x 125 125 54.6
Ayjah 2 x 125 125 78.8 78.3
Amerat 2 x 125 125 41.4 9.8
Bahla 2 x 125 125 43.7 30.5 20.1 14.0 21.4
Barka Main-A 2 x 125 125 -58.0 -68.8 -22.5 35.2 31.5
Barka Main-B 2 x 125 125 41.9
-
Bousher-A 2 x 125 125 118.8 -7.7 -12.0 22.1 17.7
Bousher-B 2 x 125 125 6.9 19.4 59.7 57.0
Bureimi-A 2 x 125 125 8.0 -7.8 -18.0 29.6 25.6
Bureimi-B 2 x 125 125 40.5 38.0
Page | 113
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.2 (continued): Available Capacity at Grid Stations (2009 – 2013) for Connection of New Demand
Total Available capacity (MVA)
Substation
Transformer
Location Firm Capacity
Capacity 2009 2010 2011 2012 2013
(MVA)
(MVA)
Dank 2 x 15 15 -7.3 -8.2
Dank (upgrading) 2 x 63 63 37.4 35.6 33.1
Dreez 2 x 63 63 7.4
Free Zone 2 x 125 125 46.1 40.4
Ghubrah 2 x 42 42 -3.6 8.5 17.7
Ghubrah (upgrading) 2 x 125 125 64.4 4.5
Ghubrah Temporary 1 x 40 40 -32.1 -32.3
Ghala 2 x 125 125 43.2 27.3
Ibri 2 x 63 63 -49.4 -57.6
Ibri (upgrading) 2 x 125 125 -2.5 -9.4 12.7
Izki 2 x 40 40 -31.4 -42.9 -52.9
Izki (upgrading) 2 x 125 125 56.3 47.9
Jahloot 2 x 125 125 8.5 18.6 45.0 68.6 64.1
JBB Ali 2 x 125 125 9.0 -9.1 -21.5 -0.5 37.5
Khaborah 2 x 125 125 -15.5 46.4 35.8 34.2 27.1
Liwa 2 x 125 125 38.4 27.4 17.8 13.5
MS Qaboos Temporary 1 x 125 125 -19.9
MS Qaboos-A 2 x 125 125 -85.0 0.2 42.8 38.5 38.6
MS Qaboos-B 2 x 125 125 25.2 16.8 9.1
Mawalleh Temporary 1 x 125 125 -11.5
Mawalleh-A 2 x 125 125 -68.0 32.6 47.2 42.9 36.9
Page | 114
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.2 (continued): Available Capacity at Grid Stations (2009 – 2013) for Connection of New Demand
Total Available capacity (MVA)
Transformer Substation
Capacity Firm Capacity 2009 2010 2011 2012 2013
Location
(MVA) (MVA)
Mawalleh-B 2 x 125 125 35.6 21.5 46.6
Mobalah 2 x 125 125 35.8 43.7 36.2 32.2 25.0
Mudaibi 2 x 63 63 -16.4 -29.6 -41.2
Mudaibi (upgrading) 2 X 125 125 40.7 29.8
Mudarib 2 X 125 125 7.4 -11.1 -26.1 23.2 9.1
Muladah 2 x 125 125 -113.8 -19.2 -26.4 -33.7 37.1
Multaqa 2 x 125 125 24.7 22.3
Muttrah 2 x 125 125 19.8 14.9 14.8
Misfah 2 x 125 125 31.0 33.5 18.6
MIS 2 x 125 125 29.0 17.4 12.5 17.8
Nakhal 2 x 125 125 76.8 41.4 18.3
Nizwa 2 x 125 125 5.0 -14.5 -29.7 24.6 14.6
Nizwa University 2 x 125 125 40.9 31.6
Quriyat 2 x 125 125 88.5 86.0 80.7
Qurum 2 x 125 125 53.6 11.9 3.4
Rusail 4 x 75 225 75.5 41.5 86.1 87.3 75.1
Rustaq 2 x 63 63 -40.3 -53.9 -61.6
Rustaq (upgrading) 2 x 125 125 17.8 11.3
Saham 2 x 125 125 29.6 12.4 11.9 5.5
Seeb Main Temporary 1 x 63 63 -34.2
Seeb Main 2 x 63 63 -78.7
Seeb Main (upgrading) 2 x 125 125 48.0 -4.3 6.8 31.9
Shinas 2 x 63 63 -19.4 24.1 20.2 17.2 13.6
Sohar 2 x 125 125 -76.6 -2.2 -17.0 40.8 35.7
Sohat Temporary 1 x 60 60 -4.1 -2.8 -4.6 -4.8 -6.8
Sohar Industrial Area 'A' 2 x 125 125 24.8 25.8 20.1 22.3 20.0
Sumail 2 x 63 63 -21.2 -33.1 -44.3
Sumail (upgrading) 2 x 125 125 19.4 10.7
Sur 2 x 125 125 10.8 11.7 -8.7 29.5 16.8
Wadi Adai 2 x 125 125 -5.3 -2.7 27.6 37.4 37.0
Wadi Kabir 2 x 125 125 -17.8 -45.7 14.1 11.8 10.3
Wadi Sa'a 2 x 63 63 41.2 29.3 16.2 6.6
Yankit 2 x 125 125 85.2 81.4
Yitti 2 x 125 125 82.4 77.8 73.4 66.0
132/11 kV Transformers
Azaiba Coast (Wave Project) 3 x 50 100 64.0 60.1 57.1 51.5
Color Key:
Transformers not in
service
Page | 115
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.3: Overhead Line and Cable Circuit Loading (%) at Peak Demand (2009-2013)
Al Kamil JBB Ali 132 2 261 22.26 25.67 28.11 24.07 16.79
Al Kamil Mudharib 132 2 261 19.07 20.13 30.42 23.22 30.39
Al Kamil Sur 132 2 261 21.90 21.71 38.65 7.11 5.67
Al Wasit Buraimi 132 2 82 70.31 79.98
Al Wasit Buraimi 132 2 261 26.93
Al Wasit Buraimi-2 132 2 261 33.60 34.86
Buraimi-2 Buraimi 132 2 261 17.97 18.72
Page | 116
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.3 (continued): Overhead Line and Cable Circuit Loading (%) at Peak Demand (2009-2013)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Send Bus Receive Bus Rating
(kV) circuits 2009 2010 2011 2012 2013
(MVA)
Barka Main Filaj 132 2 261 66.19 87.61 70.22
Barka Main Filaj 132 4 261 17.48 26.17
Dank Al Wasit 132 2 89 51.00
Dank Al Hail 132 1 89 43.52 46.08
Dank Al Hail 132 2 261 8.53 9.06 5.84
Filaj Muladha 132 2 261 17.90 8.48 12.65 12.69 6.20
Ghubrah Boushar 132 2 261 43.35
Ghubrah Boushar 132 2 261 35.73 33.24 17.92 32.22
Ghubrah MS Qaboos 132 4 261 24.92
Ghubrah MS Qaboos 132 4 261 12.64 13.51 38.58 42.52
Ibri Dank 132 2 89 19.53 54.23 37.74 40.17 29.44
Ibri Dreez 132 2 261 10.64
Izki Mudabi 132 2 261 18.91 27.67 52.59 16.09 12.42
Izki Nizwa 132 2 261 18.42 21.02 38.15
Manah Nizwa 132 2 261 59.89 61.35 60.67 47.81
Manah Nizwa 132 3 261 38.96
Mawellah Seeb Main 132 2 101 70.42
Mawellah Seeb Main 132 2 261 24.09 24.81 22.67 17.87
Mawellah Rusail 132 2 261 66.67 55.57
Mawellah Rusail 132 4 261 28.64 29.15 32.09
Mawellah Al Khoudh 132 2 261 13.51
MIS Khabourah 132 2 261 12.37 11.98 4.53 4.36 4.02
Mabalah Barka Main 132 2 261 34.50 53.51 43.37 17.81 19.20
MS Qaboos Jahloot 132 2 261 22.35 27.90 29.85
MS Qaboos Amerat 132 2 261 13.07 22.07
Amerat Jahloot 132 2 261 5.45
MS Qaboos Wadi Adai 132 2 261 60.02 55.24 45.77 6.59 26.09
Mudhabi Mudharib 132 2 261 5.37 12.83 37.16 6.22 8.97
Muladha MIS 132 2 261 47.42 49.80 44.41 38.62 32.09
Page | 117
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.3 (continued): Overhead Line and Cable Circuit Loading (%) at Peak Demand (2009-2013)
Page | 118
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.3 (continued): Overhead Line and Cable Circuit Loading (%) at Peak Demand (2009-2013)
Page | 119
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.4: Transmission System Voltage Profile at Peak Demand (2009 - 2013)
Page | 120
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.4 (continued): Transmission System Voltage Profile at Peak Demand (2009 - 2013)
Busbar Voltage at Peak Demand (per unit)
Location
2009 2010 2011 2012 2013
132 kV Busbars
Ayjah 1.00 1.00
Al Rawdh 0.96 0.96
Adam 1.00 0.99 1.00 0.99 1.02
Amerat 0.98 0.99
Al Falaj 0.94 0.97 0.98 0.98 0.99
Al Hayl 0.88 0.87 0.93 0.95 0.97
Al Kamil Power Station 0.95 0.95 0.98 1.01 1.01
Al Wasit 0.96 0.99 1.05 1.00 1.05
Al Khoudh 0.99
Airport Heights 0.99 0.99 1.00 0.96
Azaiba Coast 0.98 0.98 1.00 0.96
Bahla 0.95 0.93 0.94 0.95 0.99
Barka Main 0.94 0.97 0.98 1.00 0.98
Bousher 0.94 0.96 0.98 1.00 1.01
Buraimi A 0.92 0.95 1.03 0.98 1.03
Buraimi B 0.99 1.03
Dank 0.91 0.91 0.94 0.96 0.96
Dreez 0.96
Filaj 0.95 0.98 0.99 1.00 0.99
Free Zone 1.03 1.02
Ghoubrah 0.95 1.01
Ghubrah-A 0.96 0.98 1.00
Ghubrah-B 0.98 0.98 0.99
Ghala 1.00 0.95
Ibri 0.91 0.90 0.97 1.00 0.97
Izki 0.94 0.93 0.94 0.97 0.98
Jahloot 0.92 0.96 0.96 0.98 0.97
JBB Ali 0.92 0.91 0.94 0.98 0.98
Khaborah 0.96 1.00 0.98 1.00 0.98
Liwa 1.00 1.02 0.99 1.02
MS Qaboos 0.95 0.98 0.98 0.98 1.00
Manah Power Stataion 1.00 0.99 1.01 1.00 1.03
Mawalleh 0.96 0.99 1.00 1.04 0.99
MIS 0.95 0.97 0.98 1.00 0.99
Mobella 0.95 0.97 0.98 1.00 0.98
Misfah 1.00 1.05 1.00
Mudaibi 0.92 0.91 0.91 0.96 0.96
Mudarib 0.92 0.91 0.92 0.97 0.97
Muladah 0.94 0.96 0.97 0.99 0.98
Muttrah 0.97 0.97 0.99
Multaqa 1.02 1.01
Nakhal 0.99 1.00 0.98
Page | 121
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.4 (continued): Transmission System Voltage Profile at Peak Demand (2009 - 2013)
Page | 122
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.4 (continued): Transmission System Voltage Profile at Peak Demand (2009 - 2013)
Page | 123
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Table C.4 (continued): Transmission System Voltage Profile at Peak Demand (2009 - 2013)
Busbar Voltage at Peak Demand (per unit)
Location
2009 2010 2011 2012 2013
Multaqa 0.99 0.99
Nakhal 1.00 1.00 1.00
Nizwa 0.99 1.00 0.98 1.00 0.99
Nizwa University 1.00 0.99
Qurum 1.00 1.01 0.99
Quriyat 1.00 1.00 0.99
Rusail 1.00 0.99 0.99 1.00 1.00
Rustaq 1.00 0.99 0.99 1.00 1.00
Saham 1.00 0.99 1.00 0.99
Seeb Main 0.98 0.99 0.99 1.00 0.99
Shinas 1.00 1.01 1.00 1.00 0.99
Sohar 0.99 1.00 1.00 1.00 1.00
Sohar Industrial Area 'A' 1.00 1.00 1.00 1.00 0.99
Sumail 0.98 0.99 0.98 1.00 0.99
Sur 0.98 1.00 1.00 1.00 1.00
Wadi Adai 0.99 1.00 0.99 1.00 1.00
Wadi Kabir 0.98 0.99 1.00 1.00 0.99
Wadi Sa'a 0.99 1.00 0.99 1.00
Yankit 0.99 1.00
Yitti 0.99 0.99 0.99 0.99
11 kV busbars
Azaiba Coast 0.99 0.99 0.99 0.99
Colour Key:
Substation
not in
service
Page | 124
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 125
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 127
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 130
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 132
Five-Year Annual Transmission Capability Statement (2009 - 2013)
Page | 134
Five-Year Annual Transmission Capability Statement (2009 - 2013)
seb33_load
DIgSILENT
AES Barka P/S
brk GT1-3 Ph-2 brk ST1-2 Ph-2 brk GT1-2 brk ST1 109.60
32.85
1.00 56.15
~ ~ ~ ~ -144.74
G G G G Seeb 3..
Sohar Aluminum
363.30 264.02 221.40 203.90 -170.35
135.04 102.05 91.80 82.23 123.85 -73.58
73.83 69.76 75.37 78.52 0.94 37.94
brk ST1-3 P2 TX
brk GT1-2 TX
sps GT1-3 sps ST1 maw33_load
Seeb 63M..
brk ST1 TX
3 3 170.35
~ ~ 73.58
G G 12 11 12 11 3 79.13
Al Fal..
110.02 161.50
75.47 63.83 4 4 4
371.70 217.17 112.01
0.99
Wadi Adai..
-76.15
-22.97
259.46
84.41
203.90
130.10 24.15 982.69 6.00 6.00 25.00 31.20
0.41 0.41 Seeb132k.. Seeb Main Mawalla..
256.68 3.07 3.07 12.81 15.98
105.35 87.95 1.00 1.00
Shinas13.. 67.57 0.415 busbar.. -114.74
0.415 busbar.. -114.74
-0.00 119.20 -0.00
124.79 33.19 -19.65 54.31 -19.65 32.71
0.95 1.01 0.99
-110.02 -161.50 0.00 -143.40 -169.90
12.40 -143.55 -47.56
-120.92
Al Fa..
Shinas
17.85
76.15
1.05
8.87
22.97
sps GT1-3 TX
3 Wadi Ad..
sps ST1 TX
68.24 Ax Barka ph-2Ax Barka phase 1Dsl Barka ph
Dsl1 Barka ph2
Shinas 63MVA..
-119.20 0.00
Mawallah..
Mawallah..
6 0.00 169.90
Filaj-MI.. -0.00
0.00 87.04
-146.11
5 0.00 3
Wadi Ad..
-17.33 0.42 0.00
68.24 8 0.00 4 4
0.415 busbar.. 1.01 -0.00
-113.55 -0.00
227.42 0.00
Shinas3.. 1.03 204.98 -979.58 110.70 162.03
alf cap2(1) alf33_load alf cap2
32.83
0.99
23.11 167.36
72.32
31.00
15.88
6.00
3.07
370.17
220.27
-3.80
13.81
-221.94
67.57
Filaj 76.69
70.15
AlMawalih 87.54
76.99
0.41
0.99
35.38 75.90 0.00 0.00 0.00
12.39 28.30
Filaj 220.. Mawalla.. 0.415 busbar.. -113.40 0.41
56.92 -19.80 -19.80 0.00 0.99
shns 0.2MVA
SPS-SIP-A 220kV
214.56 126.31 26.84 74.22
3 0.98 0.96 52.05 37.94
22.06 408.53 366.07 12.89 -272.73 Wadi Ad..
4 4 115.47 110.27 -164.23
-0.00 43.59 26.10 66.45
0.00
shns cap1 shns cap2 0.00 124.22
Filaj 500MVA x 2
shns33_load Ax Sohar 0.94 -288.68
SIP-A 500MVA x 2
13.56
MIS-SIS ..
125.62
-51.28 -204.23 0.95
15 325.14 16.50
SIS-SPS 2..
-83.14 -9.22 40.46
6.60 13.81 66.07
MIS 220.. Filaj-Bark..
Rusail-..
-117.01
-67.08
13.56
sip220_load
213.64
0.97 -323.83
Rusail P/S
SIP-A132.. Sohar Ind Port-A 255.50
92.36
28.02
19.44 124.75
0.95
15.02
Barka Main -32.94
66.07 rsl_GT1-2 rsl_GT6 rsl_GT3 rsl_GT4-5 rsl_GT7 rsl_GT8
MIS 500MVA x2
Barka 1.. Rusail-M..
134.09 ~ ~ ~ ~ ~ ~
1.02 0.00 87.01 30.00 15 G G G G G G
21.68 -0.31 52.86 14.53
0.06 40.09 -126.03
157.40 166.44
-41.32
9
123.22
Barka ..
0.93
4 10.73 126.03
Mobalah-.. 41.32
219.19 125.42
rsl GT1-2 TX
rsl GT4-5 TX
rsl GT8 TX
sip132_load 56.82
rsl GT6 TX
rsl GT3 TX
rsl GT7 TX
1.00 0.95
20.40 316.54 48.53 206.58
190.37 -37.41 15.95 107.99
37.13 12.37 47.20
SIS 500MVA x 2
-86.80 -165.84 93.35 -93.14 3 3 276.73 129.35
-44.47
Sohar
Khahorah.. 37.26 -80.40 124.93
0.95
80.51
3 3 3 3
174.56 93.55 Wadi Al Kabir
Wadi Al..
40.09 34.53 24.97 24.97 Rusail A132 66.45 31.80
13.69
Mobalah..
Filaj-Mula..
-157.00
SIP-A 3.. 10
-48.29 Rusail B132 6
MIS-Kha..
32.88
Interconnection SS 72.61
Barka ..
1.00 125.68 129.96
-0.00 -316.03 79.17 0.95 0.98
0.00
86.80 48.14 0.00
-158.17 78.42 Mobalah 72.49 173.63 13.15 115.19 7.00 23.84 14.19
Rusail 75MV..
3 56.82
Moballah..
134.09 134.01 -80.65
1.02 1.02 22.37 -48.27 3 7 6
0.00 MW 21.68 -0.00 236.86 16.68 32.26
0.00 Mvar -0.00 79.75 khabora.. 12.37 32.93
0.00 4 4 1.00
1.00 sip33A_load 47.45 -0.00 Ax Rusail -144.33
0.00 -0.00 125.70 -0.00
-0.00 -0.00 -19.91 -19.91
127.08 0.00 brk cap2(1) brk cap2 67.85
0.415 busbar.. 0.96
126.34
brk33_load -72.30 -114.80 0.00
14.48
SIS-Soha..
0.41 48.39 -37.04 -71.15
35.64 Mobalah.. 49.75
0.415 busbar..
wdk 0.2MVA
1.00 56.20
78.14 Rusail..
0.42 3 4 4
1.01
Filaj-MS..
khaborah1..
-110.88 32.90
32.88 1.00 wdk cap2(1) wdk33_load wdk cap2
Al Khabourah 8 0.00 72.30 1.00 -140.58 114.80 0.00 MW
Rusail-Boushe..
87.52 47.08
80.72
0.415 busbar.. 95.44 19.80
0.42
1.00
Muladha (Old)
Muladah..
-110.55 Muladah-..
32.70 4
0.00 0.00 178.00 0.00 0.99
-0.00 -19.63 100.88 -19.63 36.56
soh 0.315 MVA
0.00
sohar temp
-204.80
4 4 -54.21
27.00
13.83
-0.00
95.44 Mulada.. -82.33
0.00 -47.95
0.00 soh cap2(1) soh cap2 32.63 19.80
soh Temp 60MVA x1
Sohar-Wa..
soh33_load
11
0.99
Line(3) -143.19 Rustaq ..
-27.06
-16.67
-27.00
-13.83
27.06
16.67
12.31
12.31
27.06
16.67
53.49
53.49
0.415 busbar.. 0.00 0.00 204.80 0.00
-0.00 -19.55 93.31 -19.55 121.83
Rusail-Sumai..
0.41
3
alw220 (1) 4 4 7.70 49.80
-0.00
-0.00
0.00
0.00
0.00
0.00
-0.00 3.70 15.07
0.00 63.77 57.81
212.28
11.00
76.60
Rustaq ..
Sohar Temp..
1.00
0.00 mld cap1 mld33_load mld cap1(1)
69.61
0.96
0.41
0.99
9.99 -0.00 3
0.415 busbar..
0.00
gbr GT1-3 TX
gbr ST1-3 TX
0.415 busbar..
32.74
39.61
1.10
0.99
0.41
0.99
-113.19
-82.10
-37.41 Ghubra..
3 3
Ghubrah P/S
81.93
Line(4)
Ghubrah 4..
Al wasit-UAE 220 kV 16.30 25.80 21.80 49.20 37.41 0.00
18.06 ~ 20.86 ~ 5.75 ~ 43.32 ~ -141.72
0.00
79.18 66.52 92.52
76.63 G 95.44 G 64.86 G 90.79 G
gbr ST5-6 TX
5
3
-10.20 33.97
wdj GT6-7 TX
wdj GT5 TX
gbr GT10-11 TX
gbr GT12-13 TX
-16.15 29.07 16.76 16.83
1.10 105.35 9.04 9.03
Al Wasit 220kV 0.415 busbar.. 189.33 -165.58 166.39 185.39 7.00 28.00
Wadi Al.. 0.41 129.51 -119.31 121.22 162.03
3 3
3.59 14.34
wdj GT12-13 TX
1.00
Bousher
wdj GT8 TX
212.00 -111.72
wdj GT11 TX
0.96 131.50
Bousher ..
9.99 -0.00 1.00 209.86 7.00 9 9 0.00 MW
16.15 13.40 67.63 3.59 0.00 Mvar Ghubrah-Bous..
2.66 9 9 4
68.07 1.00
50.80 178.00
143.40 Ax Ghoubrah(2)
Dsl Ghoubrah(2)
Al Wasit ( Mhadah) 54.90
79.57 95.64
Al Wasit 315..
-188.60 G G
Wadi Al .. -96.62 ~ ~
15 32.90 97.16
gbr_GT10-11 gbr_GT12-13
1.00 Bousher.. 0.42
24.60 50.20 26.20 54.90 -144.27 0.415 busbar.. 1.00
Ax_wdj 22.50 G 46.50 G 1.75 G 3.56 G
alwasit-..
88.90 ~
wdj GT8
88.29
wdj GT9-10
~ 70.02 ~
wdj GT11
59.48
wdj GT12-13
~ OMCO 0.00 188.60 -0.00
-113.25
Ghubrah-..
-96.56 98.92 -13.17 -205.33
-41.02 43.39 2.66 -57.02
3
0.43 0.00
1.04 163.00 0.00
0.415 busbar..
Nizwa-Bah..
3 6 -114.27 33.13 87.98
123.91 1.00
-65.18 0.94 -143.25
-40.35 10.05 68.56 103.61
38.86 -22.95
31.12 MSQ 33k..
-96.40 -22.10 Bahla 1.. 66.63 21.69
-31.97 -11.93 Bahla -163.00
-87.98
Sumail 63M..
MSQ 125M..
124.76
0.95
65.18 5.86 5 3
33.14 40.35
1.00 32.94
1.00 32.43
-146.04 0.00 96.40 0.00 0.00 0.00 0.00 22.10
burimi 0.315 MVA
Bahla 125MVA x2
-20.17 72.30 -20.17 -0.00 -0.00 -0.00 11.93 37.50
alw0.16 MVA
MSQ 500MVA x 2
0.00 39.84 22.32
Bahla ..
Sumail-Iz..
0.42 0.41 3
1.00 1.00
-116.04 67.50 0.41 MSQ-Wadi ..
32.89 13
0.415 busbar.. 1.00
67.50 0.00 65.00 1.00 -0.00
0.00 35.08 -146.74 0.00
0.415 busbar..
0.00 suml33_load 363.62
99.89
3 39.84
0.415 busbar..
alwasit..
MSQ220..
0.41
-0.00 1.00 jah 0.315 MVA(2)
3
-0.00 -114.69
208.53
-0.00
-0.00
0.00
0.00
0.00
0.00
0.00
bhl33_load 0.95
-363.62 17.74
-99.89
0.415 busbar.. 26.10
-113.04
Nizwa-Ib..
0.41
0.99
0.43
1.04
-116.74 Nizwa-..
-94.32
-51.56
22.32
0.415 busbar..
jah 0.315 MVA
3
-0.00
-0.00
0.00
0.00
0.00
0.00
61.53 65.69 42.01 -41.66 -102.67 Jahloo..
Nizwa
8
40.54 39.78 76.83 -78.70 21.69
-94.20
-42.92
94.32
51.56
46.54
46.54
16.41 31.12 18.13 18.13 21.69
Nizwa 1.. Izki 13.. Jahloot
-113.04
jah33_load
Izki
0.41
0.99
124.37
94.20
42.92
127.48
0.97 0.94
Jahloot..
7.15 -38.39 98.57 -229.41 57.21 6.64 87.13
Jahloo..
-24.48 60.59 -193.25 34.73 22.28
57.77 47.91 59.58 88.90 18.72
-143.04
32.72
Izki 40M..
0.99
Nizwa 1..
Al Hail 8 5
Al Hayl..
121.95
10.76
0.92
-98.30 -57.00
-50.36 -29.20
115.93 47.91 88.90
Nizwa 3.. Izki 3..
Izki-Mudh..
-30.82 30.82 0.88
2.86
-14.34 14.34
43.41 48.38
Al Hayl 40M..
32.79 33.10
0.99 1.00
0.00 98.30 -146.76 0.00 57.00 -147.29
2
3 3
-30.70
-12.29
32.89
48.38
1.00 Al Hay.. -0.00 -0.00
30.31 0.00 0.00
0.00 0.00
nzw33_load izk33_load
Manah P/S
Manah-Ni..
0.415 busbar.. 0.415 busbar.. -86.40
0.00
-4.97
30.70
22.23
0.00
-4.97
0.00
-0.00
0.00
0.00
0.00
0.00
0.43
mnh GT1-3 mnh GT4-5
0.44
-25.12
18.72
Mhdhabi
40.00 1.04 1.05
24.79 -116.76 -117.29 Mudhaibi..
~ ~
alh 0.2 MVA(1)
57.77
alh 0.2 MVA
-30.20 -60.57 G G
1 1 3 3
3.70
19.25
-48.81
16.41
Ibri Nahda132k.. 136.63
1.04 121.70
9.72 62.84 0.92 23.57
dank-Al hayl 132kV Ibri 13.. 36.88 3.85 -11.76
alh33_load Nahada-Niz.. 80.79 178.00 62.72 5.48
alh cap(1) alh cap 40.00 .. 54.30 198.00
Mudhaibi 6..
120.04
0.91 24.79 .. 83.74 80.68
-0.00 -0.00 3.71 0.85
0.00 -0.00 90.76 4 Mudharib-M..
-137.11
-136.45
45.11
11.55
15.55
1.05
1.04
0.00 0.00 88.74
Ibri 63MVA x2
0.41 -62.70
1.00 0.41 3 -30.37
1.00
-81.21 31.48
0.31 0.415 busbar.. 0.31 0.415 busbar.. 62.72
-12.61 14.07 Mudhaib..
mnh GT4-5 TX
mnh GT1-3 TX
50.46 43.41
-90.50 -23.51
Dank132.. -36.39 32.81 5.02 122.04
88.74
Ibri .. PDO Network
3 12 0.00 62.70
0.99
-150.40
5.48
Mudhairb.. 0.92
3.04
Mudarb
mudb0.315 MVA
120.56 0.00 30.37
0.91 0.00
5.13 19.27 30.46
5.93 -7.40 32.96
73.59 19.25 1.00 3
Dank 0.00
0.00
-0.00
-4.99
90.50
46.36
-0.00
-4.99
29.43
PDO 231.77
206.09
59.58
91.32
57.75
-67.80
-62.77
Dank 15MV..
Mudhairib 1..
mudb33_load
1 1 132.57
7
-0.00 20.10
1.00
6.00
0.415 busbar..
0.00 9.07
4.81 3.07 0.41
0.00
ibr33_load 4.41
-19.10
-4.32
73.59
Dank33.. 0.415 busbar..
ibr cap2(1) ibr cap2 0.99
-120.40
-91.20
Al Kamil P/S
-49.22
0.41 46.75
1.00 alk GT1-3
33.02 Ibri-Dank 132kV -0.57 Mudhairb..
1.00 Ax Manah ~
0.00 19.10 31.02 Manah-Ad.. G
-0.00 14.32 33.03
0.00
0.00
0.00
91.20
49.22
1.00
-150.55 261.60
218.25 OMIFCO
dank 0.2 MVA
alkamil GT1-3 TX
-0.00 0.00
0.00 0.00
Ax Alkamil
132.02
0.415 busbar.. 1.00
8.66 20.07
0.415 busbar.. 11
0.42 Alkamil-sur..
1.00 11.18 0.42
1.02
V o lt a g e L e v e ls 28.75 1.00
-120.55
68.40
-260.11
-163.60
6.00
3.07 92.42
Static Va..
SVS
Adam 60.46
19.17 alkamil 132..
99.75 48.05
21.75
Adam..
13
220. kV 93.29
126.21
0.96
4.61 -91.31
-49.62
0.00 MW
0.00 Mvar
Sur 132k..
Alkamil- JB..
52.01
-20.00
33. kV -10.25
28.75
Adam33 .. -92.41
-53.02
120.97
0.92
1.34 Sur 91.31
49.62
22.11
19. kV
45.36
32.85 JBB Ali 1..
1.00
0.00 20.00 -142.79
122.04
17. kV 0.00
0.00
10.25
0.92
adm 0.315 MVA
2.16 92.41
53.02
Sur 12..
46.09
1 5 .7 5 k V 3
BB Ali 7
15. kV
JBB Ali ..
-0.00 adm33_load
0.00 7
0.00
1 1 .5 k V 1.00
-112.79
-92.30
-44.70
46.09
JBB Ali ..
Sur 33..
32.91
11. kV 33.14
1.00
1.00
-152.29 91.20
41.55
0.00
-0.00
0.00
92.30 -151.46
Figure C.1 OETC Transmission System 2009 Max. Load Flow Condition.
Page | 135
Five-Year Annual Transmission Capability Statement (2009 - 2013)
DIgSILENT
seb33 Tem_load seb33_load
AES Barka P/S
brk GT1-3 Ph-2 brk ST1-2 Ph-2 brk GT1-2 brk ST1
~ ~ ~ ~
G G G G 40.00
20.49
32.70 65.10
33.35
0.99
Seeb Temp 33 kV -140.37 seb33
Sohar Aluminum
369.90 245.62 226.60 208.60 -149.16
202.35 152.43 139.82 124.34 128.01 -55.74
80.31 71.24 83.73 86.73 0.97 31.50
brk GT1-3 P2 TX
brk ST1-2 P2 TX
brk GT1-2 TX
brk ST1 TX
liwa-shns x 2 149.16
seb 125x2
-0.00 -0.00
brkps220 8 0.00 -0.00 wda cap1 wda cap1(1)
12 0.00 0.00
wda33_load
alf125
60.00 0.00 0.00 91.10
23.71 -20.01 -20.01 36.01 4 4 6
380.10 223.44
-37.12 37.16 160.98 208.60 1.02
490.20 490.20 6.00 6.00 25.00 31.20 maw Tem33 maw33
wda-alf2
10.95 -13.54 133.32 76.87 82.37 24.47 0.41 0.41
1.01 222.40 222.40 3.07 3.07 12.81 15.98
7.51 7.51 81.55 0.99 0.99
shns132 liwa 132 21.09
34.88 34.88 40.18 65.28 0.415 busbar.. -110.37 -110.37
-0.00 120.90 -0.00
25.82 38.57 32.98 33.01 -20.01 55.08 -20.01 33.01
77.13 30.82 1.00 1.00 1.00
0.415 busbar.. -144.15 -148.80
seb132 -142.28 -60.00 -141.27 -91.10 0.00 -36.11
filaj-brkps3-4
1.01 54.60 36.95 0.00
-108.83
alf33
Shinas Liwa
17.00
37.12 -132.36 75.20 20.00
1.00
20.73 129.89
-10.95 -40.99 44.84 9.69
sps GT1-3 TX
filaj-brkps 1-2
3 wda33A
sps ST1 TX
30.86 26.32 34.67 Ax Barka ph-2 Ax Barka phase1
Dsl Barka phaseDsl
1 Barka phase 2 0.98
12.27
Seeb Main -105.45 -120.90 0.00
shns 63 x 2
maw125x2
-0.00
liwa125x2
14 0.00 148.80
filaj-mis 0.00
-0.00 76.23
-145.89
12 9 12 0.00 3
maw-seb
178.86.. 0.42
0.85 1.00 3
-37.00 Garamco load (132 liwa) -0.00
wda125x2
sps220 -111.27
12.81 -0.00
4 4
30.86
-75.00
0.415 busbar.. 10 0.00
-0.00
-38.42 -0.00
34.67 232.29 0.00
shns33 1.06 -7.45 -489.37 -489.37 105.61 60.17 91.32
alf cap2(1) alf33_load alf cap2
33.23 liwa33 34.56 143.37 31.00 6.00 695.95 43.67 -216.28 -216.28 Filaj 64.32 30.62 3.45 0.42
55.15 15.88 3.07 275.79 4.43 34.88 34.88 24.09 54.60 36.95
1.01 1.00
48.99 37.00 0.00 0.00 0.00
10.34 47.22
filaj220 maw132 0.415 busbar.. -114.15 0.42
27.75 -20.28 -20.28 0.00 33.07 sis-sps x2 1.00
shns 0.2MVA
sps-sia x 2
wda132
4 4 3
23.50 423.29
148.73
44.65
562.91
240.16
40.15
12.63
AlMawalih -257.10
-98.39
55.57
-0.00
-0.00
shns cap1 shns cap2 0.00 128.29
shns33_load -0.00 Ax Sohar 0.97
-153.86
Wadi Adai 152.70 -269.31
rsl-maw
0.00 10.75
filaj 500 x 2
-71.13 64.23 -76.18
0.00
0.415 busbar.. liwa33_load Dsl Sohar
15
33.46 65.52 55.24
0.42
1.01 0.415 busbar..
sipA 500 x 2
mis-sis
128.84
sis-sps x2(1)
-292.10 7.50 0.98
15 440.61 18.06
-26.69 -66.70
rusail-Wadi Adai
66.49
19.35 4.43 87.61 -152.05
mis220 brk-filaj 126.94 -62.08
0.96 65.52
-93.01
-52.50
10.55
sip220_load
218.83
0.99 -438.30
Rusail P/S wdk132
9.87
mis 500 x 2
137.48 ~ ~ ~ ~ ~ ~ 62.08
1.04 G G G G G G 68.30
25.30 .. 88.31 30.00 15
33.47 15.68 .. 53.65 14.53
0.85 39.68
wdk125x2
Musanna
169.95
78.75
77.54
268.36
-26.27
53.51
153.00 79.50 76.50 159.00 90.90
33.93
90.00
39.26
8
Wadi Al Kabir
-690.00 294.56 -284.18 164.40 63.45 45.07 103.46
-248.79 17.52 -68.65 81.96 96.19 64.81 89.69 64.68 83.92
sip125x2 10
47.60
sis220
19.35
mis132A 30.16
Interconnection SS
brk125
-151.60 32.69
rsl GT1-2 TX
5 0.99
rsl GT8 TX
mob-brk -42.56
rsl GT3 TX
222.41 128.59 -146.24
rsl GT4-5 TX
68.30
sip132_load wdk33
rsl GT6 TX
rsl GT7 TX
1.01 0.97
29.55 395.44 -39.55 80.22 243.52
231.27 -46.20 19.94 48.15 66.70 3 3
-88.10 45.38 11.98 38.41 49.80 -266.92 188.64 -188.15 3 3 259.90 155.58
-45.13 33.77 -39.88 127.41 41.81 105.36 76.08
sis 500 x 2
39.68 53.51 38.32 0.97 38.32 3 55.57 33.46
14.13
-169.50 mob132 Rusail A 132 kV
mis125x2
sip33A 8 3 -0.00 151.60 -0.00 0.00
filaj-mld
-55.52
Sohar 10 77.54
brk33
-19.63 81.83 -19.63 0.00
mis-khb
0.00
wdk 0.2MVA
33.15 127.55
88.10
1.00
59.94 0.00 -394.83
-187.23
Interconnection SS khb-sah x2
Mobalah 78.28 195.98 142.20
0.97
13.16 7.00 74.79
133.17
1.01 3
rsl 75 x 4
3 38.41 wdk cap2(1) wdk33_load wdk cap2
mob125x2
-117.27
-0.00
138.67
1.05
-51.97
24.70
Al Khabourah 39.79 3 11
7 -0.00
0.00
191.74 25.23 203.09 40.49
0.00 78.10 109.13 khb132 11.98
0.00 32.94 4 4
sip33A_load Ax Rusail
Sohar Refinery
38.09 42.48 1.00 -0.00 -141.70
0.00 80.00
0.00 40.99 46.77 0.00 -87.82 0.41
sis-soh
1.00 31.45 20.57
89.94 0.99 32.54 arph220
-139.12 0.99
0.42
-0.00 1.01 -141.48
0.00 MW 141.70
-0.00 -110.19 0.00 Mvar 87.82
khb125x2
0.00
mis33_load 1.00
13 0.00 78.10 -0.00 -0.00 -560.13 479.50 80.63
arph 500 x 2
soh132 -201.30
-101.77
42.48
118.08
51.61
24.70
-77.30
1.00
76.77
-0.00
4 4 OCC OCC rsl33_load
14
135.65 sah132 -5.88 -0.00 arph-Filaj
1.03 31.45 0.00 Moballah cap 1 Moballah cap 2
mob33_load
123.52 23.07 19.76 47.11 khb33A
43.11 6.74 23.57 134.45 mld-mis
50.92 8.03 19.67 1.02 0.415 busbar.. -80.32
Sohar Grid (Old) 22.81 83.22
50.16
38.15
Saham 32.99
1.00 0.41
-17.02
8.57
130.05
0.99
-132.37 -0.00 77.30 -0.00 0.00 0.99 arph132 19.53
-109.12
soh 125x2
sah125x2
14 -61.73 -38.63
13 3 49.80 8.48
4 4
mld132 50.15
29.19
23.55
Air Port High 30.18
-12.16
6.90
-0.00
-0.00
arph125x2
khb cap1 khb cap1(1) 0.00 127.26
-123.20 -83.00 khb33_loadA 0.96
arph-azb
Oman - UAE
134.30 90.21 18.56 11
-29.91 -42.52
50.92 soh33 38.15
35.92 64.43
0.415 busbar..
rsl-bsr
57.70 22.43
sah33
Line(3)
mld125x2
-102.37 mld-rtq -25.62 -18.58
32.96 32.86 7 23.55 6.90
0.00 0.00 123.20 0.00 1.00 1.00 83.00 0.00 arph33 azb 132
32.81
48.83
0.99
3 3 32.96 129.86
-134.00 1.00 0.98
-21.63 0.00 50.00 -132.47 30.14 19.49
4 4 -0.00 25.62 18.58
azb50x3
0.00 0.00 -64.88
-136.74
3
0.415 busbar.. 0.415 busbar..
rsl-sumi x2
0.00 0.00 134.00 0.00 -30.00
0.00 -19.71 61.05 -19.71 125.07 -15.37
0.41 0.41 23.99
122.70.. 1.00 1.00 0.00 0.95 arph33_load azb11 gbr_ST3 gbr_GT1-3
76.04 ..
0.85
78.00
soh Temp 60MVA
-100.50 17.54 89.80
64.88 Rustaq ~ ~
-0.00
alw220 (1) Line(4) -0.00
10.92
48.30
-27.46
-16.95
-27.40
-14.04
4 4 0.99
27.46
16.89
12.05
12.05
27.46
16.95
52.35
52.35
rtq 63x2
0.00 5.67
-14.03 gbr Tem33_load
4 0.00 30.00 54.03
228.93 0.00 15.37
11.00
76.65
1.00
0.415 busbar..
1.04 soh Temp 0.16 MVA mld cap1 mld33_load mld cap1(1) 0.00
3
23.21 122.70
76.04 0.41
gbr GT1-3 TX
gbr ST1-3 TX
-0.00
0.00
0.00
0.00
0.00
0.00
1.00 3
9.77 -0.00 -89.50 0.415 busbar.. -102.47
-0.00 -50.72
0.00 92.80
78.83
3
0.41
0.99
gbr33 3
ghb33 kV
0.41
gbr_GT4-9
~
0.99 32.73
0.99 89.50 0.00 G
-106.74 50.72 -0.00 0.41 32.68 32.77
-138.55 0.99 0.99 ~
wdj GT3 wdj GT4 wdj GT5 wdj GT6-7 0.00 0.415 busbar.. 0.99
G 58.70
gbr 42 x 2
3
16.60 26.40 22.30 50.40
12.11 -2.67 41.23 9
10.31
gbr GT4-9 TX
gbr ST5-6 TX
61.54 83.56 64.61 90.19 6
rtq33_load
wdj GT6-7 TX
0.00 11.49 15.68 Ghoubrah B 132 kV 39.88 90.07
wdj GT 3 TX
wdj GT 4 TX
wdj GT 5 TX
bsr132
-122.44 133.00 -19.74 -19.62 0.415 busbar..
-91.39 41.20 -8.33 -8.26 135.12 129.60
0.41
gbr GT13 TX
9.77 26.32 8.03 7.98 1.02 0.98
alw220 (Interconnected) 9 9 9 9 0.99 11.81
22.67 110.27 108.31 -144.56 108.60
-108.55 26.30 66.99 -105.60 39.80
47.24 53.07 35.73 12.64 3
wdj GT12-13 TX
225.83 wdj132
wdj GT9-10 TX
wdj GT 11 TX
1.03
wdj GT8 TX
bsr125B
bsr125A
91.39 43.81 3.59 8.92 Mvar Ghb-Bousher
23.63 57.85 0.85 9 9 9 10 8
9
-110.00 -108.00
wdj-alw 32.98 -16.39 -55.33 32.90
15 1.00 47.24 53.07 1.00
56.10 -142.82 bsr33B -142.62 gbr_ST4 G
25.20 51.30 26.80
-21.87 bsr33A ~
MSQ-Arph
46.50 -10.96
Ax_wdj
15.40
77.22 65.10 ~ gbr_GT13
78.75 89.34 G
alw-bur G G G G 37.20
~ ~ ~ ~ 0.00 0.00 110.00 0.00 108.00 0.00
gbr-msq
-55.33 59.11 -122.18 -37.58
79.98 79.98 -80.20 57.85 3 3
msq Tem33_load
bur132 alw132
23.63
4 4
gbr ST4 TX
OMCO -0.00 -0.00
0.43 0.43
alw 30 x 2
-142.72
0.415 busbarB 1.05 0.415 busbar.. 1.04 60.00
30.74
msq Tem 33
nzw-bhl2
5 8 -112.82 -112.62
124.28
gbr GT10-11 TX
-74.30 0.94
gbr GT 12
-46.55
36.30
Sumail 9.83 78.21
45.47
3
7.00
3.59
28.00
14.34
-110.80 -24.00 bhl132 76.26
-43.27
53.21
-12.95
47.42
Bahla -60.00
-30.74
57.97
3
bur33 alw33
msq Tem125
sum 63 x 2
122.34
0.93
74.30 5.84 5 6
32.93 46.55
1.00 32.96
0.00 1.00 37.83 Ax Ghoubrah Dsl Ghoubrah
-136.96 0.00 110.80 0.00 0.00 0.00 24.00 91.05
-19.92 83.10 -19.92 -0.00 0.00 -0.00 12.95 47.04 71.70
44.65
alw0.16 MVA
sumi-izk
0.00 0.00 -0.00
msq125x2
msq 500 x 2
0.00 0.00 0.00 3
8
32.50
mqb-wda
0.415 busbar 0.415 busbar.. 10
0.00 74.10 0.98 -0.00
0.41 -0.00 39.99 -147.19 -0.00
0.415 busbar..
116.90 0.00 34.81
nzw-ibr 63.10
0.43 3
1.03
-117.19 izk-nzw
-136.52
-30.38
4 4
27.90
-0.00 jah 0.315 MVA(2)
3
-0.00
-0.00
-0.00
0.00
0.00
0.00
0.00
MSQ CB2 MSQ CB1 msq33_load 0.00
-115.17
46.64 46.94 61.22 -62.13 -4.01
0.41
1.00
12.56 36.30 21.02 21.02 23.67
nzw132 izk132 Jahloot
0.415 busbar..
125.55
0.95
Izki 122.77
0.93 jah 0.315 MVA
3
-47.52 112.42 -232.33 65.25 130.23
jah132
7.36 6.12
-28.75 70.28 -196.33 40.33 25.82
-0.00
-0.00
0.00
0.00
0.00
0.00
71.54 55.75 61.35 103.65 27.67 jah125x2
13
-101.20
101.31
nzw125x2
14.52
42.58
42.58
-6.32
izk40 x 2
Al Hail 6 5
-115.17
alh132
jah33_load
-163.40
0.41
1.00
126.92
0.96
8.99
ytt 33
-33.93
101.20
-143.18
46.11
98.52
32.76
0.99
-112.10 -65.00
wds132
115.20 -57.43 -33.30 Yitti
jah33
0.87 55.75 103.65
-32.23 32.23 nzw33 izk33
izk-mudb
125.39 8.81
0.95 -15.73 15.73
15.74 46.08 51.36
18.09 145.31
4
-145.17
125.87
32.90
jahloot CB 1
32.91
32.74
-19.89
0.95
8.34
1.00
10.19 23.74
alh 40 x 2
1.00
0.00
17.35 87.22 0.99
-147.05
ytt33_load
2 0.00 112.10 0.00 65.00 -148.30
35.00
17.93
0.00 0.00 yitt125x2
wds 63 x 2
10
Wadi Sa'a
-35.00
-17.93
35.12
20.39
17.06
17.06
-113.18
9 3 3
0.41
0.99
-32.10
ytt132
4
jahloot CB 2
-13.47 32.61
-19.89
0.99
0.00
51.36 yitt 0.315 MVA
36.11 -0.00 -0.00
3
alh33 0.00 -0.00
0.415 busbar..
-0.00
-0.00
-0.00
0.00
0.00
0.00
0.00 0.00
nzw33_load izk33_load
-18.00
Manah P/S
mnh-nzw
-9.22 jah-ytt x2
-35.12
-20.39
35.21
15.86
8.17
8.17
17.35
wds33 0.415 busbar.. 0.415 busbar..
wds-dnk x 2
-128.63
0.00 32.10 0.00 0.00 0.00
-22.66 Mhdhabi
alh 0.2 MVA(1)
mudb 63 x 2
30.99 .. 92.99 79.48
0.41 0.85
118.02 96.28 2
0.99 0.89 48.62
-0.00 wds33_load 6.11 0.415 busbar.. 0.41
0.99
0.415 busbar.. 7.17 95.75
-0.00 6.11
ibr 63 TX2
0.00
0.41 82.59 182.10 -71.50
2 -34.63
0.99 69.75 188.77 73.35
0.415 busbar.. 74.90 -140.84 32.97 76.29 83.92
mudb33
-15.21 15.71
mnh GT4-5 TX
mnh GT1-3 TX
87.22 46.08
-95.90 -56.64
dnk132 -39.16 32.81 15.78 120.22
95.75
ibr33 PDO Network
3 10 0.00 71.50
0.99
-153.21
12.83
mdrb132 0.91
-0.26
Mudarb
mudb0.315 MVA
120.22 -0.00 34.63
0.91 0.00
11.18 20.09 87.78
6.83 -7.33 32.95
77.66 54.23 1.00 3
mdrbx2
mudb33_load
6
1 1 130.80
-19.90 -0.00 22.91
0.99
6.00
0.415 busbar..
-5.05 -0.00 9.35
6.68 3.07 0.41
77.66 0.00
dnk33 ibr33_load 5.10
0.415 busbar..
ibr cap2(1) ibr cap2 0.99
-123.21
-104.00
-56.13
54.43 Al Kamil P/S
32.80 mdrb33
0.99 0.41
1.00 alk GT1-3
0.00 19.90 36.87
0.00 14.93
ibr-dnk x 2 2.89
~
dank 0.2 MVA
32.75
0.00 Ax Manah 0.99 G
0.00 104.00
alkamil GT1-3 TX
6.87
0.41
0.99 Ax Alkamil OMIFCO
-124.39
V o lt a g e L e v e ls adm132
-22.88
-12.81
5.10 11
alk-sur x2
Static Va..
-266.06 6.00
48.17 -161.57 3.07 105.26 SVS
130.13 81.11 101.64 14.56
0.99 20.13 21.71
125.46
132. kV
11 0.95
106.63 0.71 -104.12 0.00 MW
sur132A -16.03 0.00 Mvar
62.83 21.71 1.00
alk-bbali 1
-22.80 25.67
17. kV
0.00 11.68
0.00
adm 0.315 MVA
sur125x2
Annex: OETC BB Ali
53.53
10
15. kV -0.00
-0.00
adm33_load
bbali125
0.00
6
1 1 .5 k V 1.00
-112.74
-105.30
-104.00
-7.43
45.27
-51.00 sur33
11. kV 53.53
bbali33 32.98
1.00
Figure C.2 OETC Transmission System 2010 Max. Load Flow Condition.
Page | 136
Five-Year Annual Transmission Capability Statement (2009 - 2013)
DIgSILENT
New Barka GT 1-2
seb33_load
AES Barka P/S ~
G
blue33_load brk GT1-3 Ph-2 brk ST1-2 Ph-2 brk GT1-2 brk ST1 358.30
162.15
~ ~ ~ ~ 83.90
G G G G 32.66 108.30
55.48
0.99
-144.43
Sohar IWPP Sohar Aluminum 20.00 372.00 163.97 228.40 210.20 -103.52
10.25 173.79 125.01 119.60 106.54 seb33 129.03 -23.15
78.21 50.82 81.08 84.16 0.98 20.82
blue33 358.30 9.04
brk ST1-2 P2 TX
Sohar Al
AlFalaj
brk GT1-3 P2 TX
33.22 0.00 -108.30 0.00
brk ST1 TX
0.00 -20.00 54.16 16 Mawallah cap1 Mawallah cap2 103.52
seb 125x2
~ ~ -0.00 -10.25 3 3 23.15
G G 0.00 7.17
-357.38 4 4
43.42
358.30 -110.70 11
78.86 3 17 83.68
16 17 16 -0.00 -0.00
78.27 wda cap1 wda cap1(1)
brkps220 0.00
0.00
0.00
0.00
alf125x2
-0.00 108.61 77.10 0.00 0.00 80.00 wda33_load
-0.00 67.70 30.47 -19.94 -19.94 31.62 4 4 8
383.10 0.00 228.08 51.73
maw33 B
blue 160x2
171.48 210.20 1.04
134.74 628.98 628.98 6.00 6.00 25.00 31.20 4.00 seb132
wda-alf2
78.16 87.52 26.35 0.41 0.41
1.02 16 240.45 240.45 3.07 3.07 12.81 15.98 2.05
liwa 132 23.77 82.80 0.415 busbar.. 42.71 42.71 0.415 busbar.. 0.99
-114.43
0.415 busbar.. 0.99
-114.43
-0.00 94.40 -0.00
358.30 filaj-Blue 32.95 -19.76 43.01 -19.76 32.80
78.86 0.42 130.62 maw33 A 32.77
Ax New Barka
Dsl Barka phase1
1.01 0.99 1.00 0.99 0.99
filaj-Blue(1)
78.06 -108.61 -77.10 -143.07 0.00 -80.00 0.00 -144.71 -103.30
9.89 -143.10
Ax Barka ph-2
-13.31
2-Winding..
filaj-brkps3-4
24.81 31.12 0.00 35.77 0.00
-107.43
alf33
Liwa Seeb Main
17.00
42.17 -157.50 85.33 30.00
1.00
-9.05 -57.03 51.55 14.53
sps GT1-3 TX
filaj-brkps 1-2
3 3 wda33A
sps ST1 TX
8.11 31.48 39.06
15
Blue -94.40 0.00
maw125 A
-0.00
maw125 B
-0.00
liwa125x2
0.00 103.30
maw-seb
12.20 -66.76 0.00 0.00 -145.56
nhl33A
-0.00 52.92
liwa-shns
13 7.17 5.23 13 0.00 11 0.00 3
-131.99
33.12
78.06 0.85 3
1.00
Garamco (132liwa) -0.00
sps220
wda125
225.60 0.41 0.41 -0.00
12 0.00 4 4
1.03 Nkh 125x2 1.00 0.99
0.415 busbar.. 0.415 busbar..
nhl33_load
-85.10 24.86 26.92 -0.00
-113.07 -113.10
0.415 busbar..
-43.60 0.00
mis-blue
-41.00
-21.00
231.65 54.56
41.00
21.00
19.27
41.13
23.77
19.27
39.06 7.26 0.00 alf cap2(1) alf cap2
-42.13 1.05 47.07 -627.74 -627.74 108.78 77.29 80.21 alf33_load
6.45 liwa33 35.89 240.78 31.00 70.34 4.00 6.00 816.64
Filaj-Nakhal x2 -1.57 -229.35 -229.35 Filaj 67.69 -3.64 38.53 0.41
-41.13
-23.77
105.26 15.88 11.32 2.05 3.07 216.19
9.24
8.11 3.09 42.71 42.71 24.81 31.12 35.77 0.99
shns132
8
17.19 5.06 53.13
filaj220 maw132 0.415 busbar.. -114.71 0.41
32.90 1.00
1.00 94.62 103.57 0.415 busbar.. -115.56
Nhl132
85.10 0.00
sis-sps x2
-129.61 11.24 23.03
sps-sia x 2
sps-sib x 2
23.39 42.13
-6.45 Shinas 419.37
175.83
25.15 789.04
284.45
10.27
AlMawalih -266.27
-102.58
-0.00
-0.00
-0.00
0.00
0.00
0.00
3
-101.99
33.99 44.36 53.81 28.64
0.42
1.00
shns 63 x 2
130.18
Wadi Adai 129.17
19.60
15 -70.16 105.13
0.99
-0.00
filaj 500 x 2
0.98 -48.24 26.02
0.00 9.20 -233.16
liwa33_load Dsl Sohar 16.69 42.54 -12.06
15
45.77
0.415 busbar..
mis-blue(1)
-42.00 -240.75 -70.34
8.56 0.41 -134.38 -40.64
33.99 1.00 17.19 5.06 rsl-maw
msf-wda x2
-104.86
-99.61 -25.62
42.54
shns33 sipA220 sipB220 18.40 41.18 -418.77
33.03
1.00
231.55
1.05
35.85
231.63
1.05
35.88
56.93
12.65
21.42
9.24
-127.63
44.36
wdk132 Wadi Al Kabir
51.40 42.00 0.00 0.00 0.00 120.75 120.00 70.34 filaj132
31.50 -20.03 -20.03 0.00 76.26 58.12 40.64 128.50
shns 0.2MVA
sis-sps x2(1)
sipA 500 x 2
sipB 500 x 2
8.59
mis-sis
130.80 25.62
3 0.99 70.49 44.34
18 -262.74 -26.74 359.20 45.51
15 -12.22 -125.30 19.96
4 4 49.29 16.69
wdk125x2
17.13 8.35 70.22
-0.00
0.00 mis220 brk-filaj Misfah132 10
shns cap1 shns cap2 0.00
shns33_load
0.415 busbar..
-120.41
-66.93
13.77
sip220_load -70.00
-33.90
7.73
221.58
1.01 -357.72
Rusail P/S Al-Misfah 131.42
1.00
-104.60
0.42
1.00
sipA132 Sohar Ind Port-A sipB132 Sohar Ind Port-B 289.48
137.52
31.86
24.71 129.83
0.98
18.45
Barka Main -40.74
70.22 rsl_GT1-2 rsl_GT6 rsl_GT3 rsl_GT4-5 rsl_GT7 rsl_GT8
-150.68
-93.67
34.19
80.19
48.16
37.58
10.29
-16.29
44.34
81.40 brk132 rsl-mob wdk33
Misfah125x2
mis 500 x 2
137.66
132.11
1.04 ~ ~ ~ ~ ~ ~
1.00 19.20 .. 89.61 50.00 35.07 70.00 15 G G G G G G 8
34.36 11.90 .. 54.61 24.22 33.90 33.07
0.85 41.94 1.00
135.62 222.10 0.00 -0.00 104.60 -0.00 -145.63
Musanna 51.33 -10.58 154.20 80.20 77.10 160.40 91.60 90.70 0.00 -20.08 56.46 -20.08
wdk 0.2MVA
249.21 -809.13 264.68 -289.04 58.99 43.37 149.04 63.45 49.16 112.92 37.67 42.75 -80.00 0.00
130.00 -170.02 -4.11 -110.42 78.27 96.70 66.75 92.75 66.03 85.70 -40.99
sip125x2 8
18.91 53.38
sis220
17.13
mis132A 31.86
Interconnection SS 37.58
msf33
3
4 4
brk125x2
sip-B
rsl-msf x2
-0.00
7 mob-brk 32.90 0.00
223.55 129.00 1.00
rsl GT4-5 TX
0.00 wdk cap2(1) wdk33_load wdk cap2
rsl GT1-2TX
rsl GT8 TX
sip132_load
rsl GT6 TX
rsl GT3 TX
rsl GT7 TX
1.02 0.98 -142.91
sis 500 x 2
41.94 43.37 26.83 0.98 26.83 28.64 34.19
16.84 0.415 busbar.. 1.00
-135.30 mob132 3 -0.00
mis125x2
sip33A 15 64.37
filaj-mld
-36.41 0.00
Sohar 10 58.99
brk33 0.00
mis-khb
32.92 129.55 132.67 Rusail A 132
muttr132 Muttrah
SRC
89.40
1.00
60.73 0.00 -294.81
-20.03
Interconnection SS khb-sah x2
Mobalah 86.40 250.72 Rusail B 132 0.98
16.17 110.58 7.00
1.01
10.92
msf33_load
qrm-muttr..
-89.60
sis132 -45.90
0.00
-0.00
0.00
-20.13
135.30
76.68
0.00
-20.13
-136.74 -112.91 8.87 -100.21
-20.21
100.21
20.21
rsl 75 x 4
3 43.03
mob125x2
-105.88
Muttrah 125x2
-0.00
132.89
1.01
-6.88
20.86
Al Khabourah 20.58 3 12
9
sis-soh
1.00 35.68 32.60 21.17
90.73 0.99 arph220 muttr33 -145.13
0.42 -137.47
-0.00 1.00 0.00 MW 110.20
-0.00 -106.74 0.00 Mvar 68.30
0.00
khb125
mis33_load 1.00
11 0.00 86.20 -0.00 -0.00 -784.04 605.47 178.57 0.00 0.00 100.00 0.00
qrm-muttr x2
-91.83 0.00 53.81 41.82 18.59 0.00
48.59
20.00 0.41 3 3
soh132 -200.92 106.46 1.00
OCC
arph 500 x 2
-63.20 5.38 77.45 4 4 4 4
41.11 20.86
-85.10 -0.00 OCC rsl33_load -0.00
133.93 sah132 -10.67 0.00
15
0.00
1.01 35.68 0.00 Moballh cap1 Moballh cap2 Muttrah cap2 Muttrah cap1 0.00
mob33_load muttr33_load
134.67 25.04 -35.29 -7.55 khb33A
51.28 -58.52 -41.36 129.75 mld-mis arph-Filaj
56.81 25.84 15.90 0.98 0.415 busbar.. 0.415 busbar..
Sohar Grid (Old) 23.61 94.46
57.82
45.06
Saham 32.93
1.00 0.41 0.41
-131.91 -0.00 85.10 -0.00 0.00 1.00 100.49 0.99
-106.72 10.25 -115.13
soh 125x2
sah125x2
12 -48.76 -61.26 -36.41
10 3 44.41 12.65 18.59
arph132
4 4
mld132 Air Port High 128.83
0.98
-0.00 9.38
-0.00 60.15 -160.64
khb cap1 khb cap1(1) 0.00 127.90 130.08 35.20 -45.45
-134.30 -94.20 khb33_loadA 0.97 0.99 28.57 32.81
qrm125x2
Oman - UAE
141.03 96.11 19.76 55.46 18.88 69.38 20.00 33.40
sis-alw x2
-35.80 -48.26
56.81 soh33 45.06
40.09 69.94 32.42 4.26 9.69 -9.96 7
0.415 busbar.. 60.55 23.91 26.07 14.10 7.66
sah33
arph125x2
220kV Interconnection
Line
0.41
1.00 -60.00
Muladha (Old)
mld125x2
arph-azb
mld-rtq 11 -30.74
-101.91 33.11
33.13 32.65 7 1.00 28.57
0.00
-0.00
0.00
-20.16
134.30
76.11
0.00
-20.16
1.00
49.60
0.99
-130.18
94.20
48.26
0.00 -142.93 qrm33
-28.33 -20.79
3 26.07 7.66
-140.70
3 -24.47 arph33 azb 132 60.00 0.00