AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Notes :
1. The amount of excavation is given as a provisional
quantity. The actual amount shall be measured by
Meridian Survey and paid by Contractor. The amount
measured shall be final
b) 300mm thick crusher run as road base material m2 3,185 24.60 78,351.00
Gravel Carpark
Supply, lay, spread 50mm thick sand blanket and
300mm thick compacted approved gravel for gravel
carpark. m2 3,485 12.50 43,562.50
External road
a) 75mm thick binder course and 50mm thick wearing 34.30 138,297.60
course including a layer of tack coat m2 4,032
b) 450mm thick crusher run as road base material m2 4,032 12.30 49,593.60
B - 1/28
OPTION 1
479,829.10
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Road Kerbs
2.2 Precast concrete kerb grade 20 c/w discharge opening
together with 230mm concrete pipe at every 5m
interval as per drawing. Prepare and apply one coat
alkali resisting and 2 coats of emulsion paint of black
and white colors alternately at 600mm length to sides m 300 19.10 5,730.00
and on top of kerb
B - 2/28
OPTION 1
75,080.40
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
B - 3/28
OPTION 1
2,615.00
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
B - 4/28
OPTION 1
56,998.00
TO COLLECTION RM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Rubbish Trap
5.15 To supply and install rubbish trap at the drainage brick no 20 120.20 2,404.00
sump outlet discharge, compised of 20mm dia. M.S.
bars welded
Precast BoxatCulvert
50mm c/c, 10mm thk x 50mm wide
m.S. plate at 450mm c/c max c/w 13mm dia. Holes,
5.16 Supply,
10mm thk layxand
t5mmfix wide
precast
M.S.reinforced
flat plateconcrete box
to be suit on
culverts
a) 600mm c/w dry
(b) x weather
600mm flow
(h)
site and as per specification. and
not lids.
exceedingRate to
3.5m include
deep m 13 634.20 8,244.60
excavation, get out, part return, fill in and ram, remove
surplus excavated materials from site, 150mm thk
concrete base with one layer of BRC A6 throughout,
200mm thk well compacted hardcore on 50mm thk
sand bedding, concrete copping, 10-20mm gap to be
jointed with cement mortar and etc. as per
specification
10,648.60
TO COLLECTION RM
B - 5/28
OPTION 1
376,811.10
TO COLLECTION RM
PAGE………………..B - 7/14 RM
PAGE………………..B - 8/14 RM
PAGE………………..B - 9/14 RM
PAGE………………..B - 10/14 RM
PAGE………………..B - 1114 RM
PAGE………………..B - 12/14 RM
PAGE………………..B - 13/14 RM
B - 6/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
PAGE………………..B - 1/14 RM
PAGE………………..B - 2/14 RM
PAGE………………..B - 3/14 RM
PAGE………………..B - 4/14 RM
PAGE………………..B - 5/14 RM
PAGE………………..B - 6/14 RM
PAGE………………..B - 7/14 RM
PAGE………………..B - 8/14 RM
PAGE………………..B - 9/14 RM
PAGE………………..B - 10/14 RM
PAGE………………..B - 1114 RM
PAGE………………..B - 12/14 RM
PAGE………………..B - 13/14 RM
B - 7/28
B - 8/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
TO COLLECTION RM
B - 9/28
TO COLLECTION RM
B - 10/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Road Kerbs
B Supply and fix complete precast concrete G20 road as M 5,000
per drawings and/or approved design by the local
authorities. Rate to include round opening at every
6m, concrete bedding, setting, jointing, painting, etc
and including discharge pipe to nearest drain/
TO COLLECTION RM
B - 11/28
TO COLLECTION RM
B - 12/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
TO COLLECTION RM
B - 13/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Pillar Hydrant
C Supply and install pillar hydrant including, flanged No 10
extension pipe, r.c. duct foot bend and all necessary
accessories, excavation and disposal
Pipe Crossing
D Supply and lay M.S Pipe sleeves for crossing the
track/metalled road .
a) 200mm dia. MS Pipe M 50
b) 350mm dia. MS Pipe M 50
Water Meter
E Supply and install water meter including all necessary No 8
jointing and connection and paying all fees and
charges on connection as required by the local
Authorities for the installation
Pipe Marker
G Concrete pipe marker at every 50m interval complete No 35
including all excavation and backfilling as detail
shown in the drawing
TO COLLECTION RM
B - 14/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Manhole
B Supply and construct the following sewer manhole c/w
cover. Ratedepth
a) Manhole to include all necessary
not exceeding 2M depth excavation, No 7
backfilling, precast R.C. chamber,
b) Ditto, exceeding 2M but not exceeding concrete base,
3M depth No 3
heavy duty ductile iron frame and cover, stainless
c) Ditto,
steel stepsexceeding 3M but
and all details not drawing
as per exceeding 4Masdepth
and p No Rate Only
d) Ditto, exceeding 4M but not exceeding 5M depth No Rate Only
e) Ditto, exceeding 5M but not exceeding 6M depth No Rate Only
f) Ditto, exceeding 6M but not exceeding 7M depth No Rate Only
B - 15/28
TO COLLECTION RM
B - 16/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Brick sump
B Construct and complete varies type and size of No 70
bricksump c/w mild steel grating cover. Rate to
including excavation and backfilling, concrete base
with reinforcement and plastering to expose surfaces
as per detail drawing.
Rubbish Trap
C To supply and install rubbish trap at the drainage brick No 5
sump outlet discharge, compised of 20mm dia. M.S.
bars welded at 50mm c/c, 10mm thk x 50mm wide
m.S. plate at 450mm c/c max c/w 13mm dia. Holes,
10mm thk x t5mm wide M.S. flat plate to be suit on si
TO COLLECTION RM
B - 17/28
TO COLLECTION RM
B - 18/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Culvert
F Supply and lay r.c. culvert including concrete base and
surrounding, excavation and backfilling works
a) 900mm diameter M 20
b) 1200mm diameter M 20
B.6 TURFING
A Supply and lay turfing with approved turf of not less
than 200mm square and laid at 380mm centers both
ways from approved source. Rate to including all
necessary surface preparation, vegetable soil,
watering, tending, caring, protection and maintenance
a
B - 19/28
TO COLLECTION RM
B - 20/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
Brick Fence
B Construct one brick thick 2.10M height brick fence M 2,000
complete with plaster and paint on both sides
including all necessary r.c. footing, excavation and
backfilling all as per detail drawing.
Main Gate
D Supply and install G.I. main entrance gate overall size No 1
6000mm x 2100mm high with G.I. Post, r.c. footing,
barrel bolt and all necessary accessories including
painting works
B - 21/28
TO COLLECTION RM
B - 22/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
AMOUNT
BIL DESCRIPTION UNIT QTY RATE
(RM)
B.12 OTHERS
A Other item not mentioned above but necessary to
complete the works
a. ……………………………………
b. ……………………………………
c. ……………………………………
d. ……………………………………
e. ……………………………………
TO COLLECTION RM
B - 23/28
TO COLLECTION RM
B - 24/28
PEMBANGUNAN KOMPLEKS LATIHAN FELDA TANJUNG LEMAN
MUKIM TENGGAROH, MERSING, JOHOR DARUL TAKZIM
PAGE………………..B - 1/10 RM
PAGE………………..B - 2/10 RM
PAGE………………..B - 3/10 RM
PAGE………………..B - 4/10 RM
PAGE………………..B - 5/10 RM
PAGE………………..B - 6/10 RM
PAGE………………..B - 7/10 RM
PAGE………………..B - 8/10 RM
PAGE………………..B - 9/10 RM
B - 25/28
B - 26/28
Bill Unit Length Width Depth Qtty Note
B1 M2 270 300 81000
M3 270 300 0
M2 270 300 81000
R/O
B2 M2 120 12 1440 entrance
300 8 2400 main road
110 8 880 stp
160 8 1280 tnb
100 8 800 surau
140 50 7000 parking (blok utama)
90 25 2250
60 50 3000 parking (dewan makan)
40 40 1600
60 8 480
21130
M 200 200 entrance
170 170 round about
280 280 parking (blok utama)
80 80
730
M 48 48 entrance
480 480 parking (blok utama)
224 224
352 352
145 145
585 585 parking (dewan makan)
1834
B3 NO 9 9
B6 M2 300 100 30000
300 10 3000
40 40 1600
90 30 2700
90 30 2700
37300
M2 25 5 125
15 10 150
15 15 225
30 5 150
650
53 5 265
26 5 130
23 5 115
15 5 75