Sei sulla pagina 1di 8

Cheah Yi Ben, Benjamin

Outstanding works.
Agenda (7 April 2020) Day 1 of 28
4) Reminder : Details update of outstanding works/28-day Program
by Wed 11am
Code Project Task Receive Deadline Status
180070 RSKU PB transfer plate honeycomb issue - site rectification 20/3/2020
180070 RSKU PB podium slab exposed tendon head - site rectification 20/3/2020
180070 RSKU PB podium slab exposed tendon head - ptid review 17/3/2020
180070 RSKU Flat roof design temp work design coordination 20/3/2020
180070 RSKU Flat roof design temp work design to site and approval
180070 RSKU Bus stop submission 13/3/2020
180070 RSKU Syabas comment with amended drawing 20/3/2020
180070 RSKU Fencing details 13/3/2020
Working &
180070 RSKU Receive fencing from safwan 17/3/2020
Following Up
180070 RSKU GME to check the end cap 17/3/2020
180070 RSKU Ramp opening parapet wall column details 20/3/2020
180070 RSKU Roof level 2 design and drawing 20/3/2020
180070 RSKU New crack issue at level 2 6/4/2020
180053 KEPONG Summarize the scope of all EIA in table format 7/4/2020
180053 KEPONG Meeting with SW and architect 10/4/2020
80530 NOG Steel frame design for additional rock surface 24/3/2020
- SSR1 Sky Santuary Structural Plan study and model Continuous
- SSR1 Building design member element optimization 25/3/2020
- Curvo Curvo column load loadting from tower block Continuous
- Seremban slab with beam VE 25/3/2020
Ta Mun Whye, Edwin
Outstanding works.
Lee Chee Kien
Outstanding works.
Agenda (7 April 2020) Day 22 of 28
4) Reminder : Details update of outstanding works/28-day Program
by Wed 11am
Job ID Project Title Outstanding works Target Date Team members Remarks
ST, TRR, Design, Tender
180080 TRX Plot 1c 1. Minor comments 1. 10 Apr Benjamin Cheah Possibly last minor
2. R&D on pile raft behaviour 2. TBD Yi Ben comment.
SSR1 Sky Sanctuary 1 1. Additional SI Proposal 10 Apr
2. Foundation pile optimisation based
on column loads
180051 LRT3 (East Portal) 1. Pending structural output of break Ang MH, Tan KC,
out wall for GFRP. Aina
2. Other comments on East Portal
design.

PE Report PE Report 50%


Nge Jia Sheng
Outstanding works.
Details update of outstanding works of 08.04.2020
Job ID Project Title Outstanding works Target Team Remarks
ST, TRR, Design, Date members
Tender
180051 LRT3 Minor admentments - -
(from time to time)
SG - Linkway Study design criteria
(Mayflower)