Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Answer Key
© Copyright 2019, Project Management Academy Inc, All rights reserved. Project Management Academy® and PMA® are registered trademarks of Educate 360, LLC. V6.1.3. Materials in this document are based on the A Guide to
the Project Management Body of Knowledge, (PMBOK® Guide - Sixth Edition, Project Management Institute Inc., 2017. PMBOK is a registered trademark of the Project Management Institute, Inc. Copyright and all rights reserved.
Contents
Section 1 - Matching Exercises
Matching Exercises
1. The type of organization where the project manager has Projectized Organization
full authority
2. The process where all project work is sub-divided and Create WBS
broken down to the work package level
10. Adjusting the level of resources when resources have Resource Smoothing
been over-allocated, without allowing the schedule to slip
11. Adjustments made to project expenditure to account for Funding Limit Reconciliation
funding limits
14. Tool used to ensure the team is following the quality Quality Audit
procedures as planned
17. A grid that shows relationships between work packages Responsibility Assignment Matrix (RAM)
(or activities) and team members
19. The point where seller has to absorb all cost overruns Point of Total Assumption (PTA)
4. The only knowledge area that has processes in all 5 process groups is Integration Management .
5. The two process groups with processes in all 10 knowledge areas are Planning and Monitoring & Controlling .
7. The EEF that determines that the correct work is done in the right sequence and by the right team is called a
Work Authorization System
9. Corrective actions are actions taken to realign the performance of the project
work with the project management plan.
15. A lead refers to starting a successor activity before completing the current activity, whereas
a lag is a delay in starting the successor activity.
16. 3 point estimate using a simple average is also known as a triangular distribution .
19. The 2 types of risk reserves are contingency reserves and management reserves.
20. On a control chart the limits set by the customer are known as specification limits whereas the
limits established by the process are control limits.
21. As a standard, the control limits are set to plus and minus three standard deviations from the mean
22. The tool used to test multiple factors at a time is Design of Experiments .
23. The quality pioneer that promoted the concept of zero defects was Philip Crosby .
24. The quality pioneer that promoted fitness for use was Joseph Juran .
25. The quality pioneer that said quality problems are a result of management 85% of the time was
W. Edwards Deming .
Crossword Puzzles
ACROSS DOWN
2. An example of this risk strategy is a teaming agreement 1. Occurs when measured value equals true value
4. The longest duration path through a network diagram 3. Expected costs to finish all the remaining project work
6. A schedule compression method which exchanges higher costs for 4. A technique that places the entire project team in one physical location
shortened durations 5. Uncontrolled changes result in ______
7. An example of a responsibility assignment matrix is a _______ diagram 9. An uncertain event or condition that may have a positive or negative
8. Customers, end users, operational managers, sponsor are all impact on the project
examples of _________ 10. Includes upper and lower control limits and upper and lower
10. Type of contract with the highest risk for the buyer and the least risk for specification limits
the seller 13. The least accurate method of estimating
11. An email or voicemail message is an example of this type of 15. Value of the work actually completed
communication method 18. The difference between what was budgeted and what is forecasted to
12. A risk strategy that involves a contract, such as an insurance policy have been spent at the end of the project
16. Costs that include training, testing, rework and warranty work 19. Knowledge gained during a project which shows how project events
17. These types of costs include training, equipment, time to do it right were addressed or should be addressed in the future with the purpose
20. A resource optimization technique which often can cause the original of improving future performance
critical path to change 21. A collection of related projects that are more beneficial to manage
21. A type of diagram that shows causes of defects by frequency collectively than individually
23. Should be signed off by project manager, project sponsor, project team 22. Responsible for providing funding for the project
and key stakeholders 25. A type of contract in which the seller is reimbursed all costs and the fee
24. Category assigned to products or services having the same functional does not change based on seller's costs
use but different technical characteristics 27. Industry standards and market conditions are examples
26. Using a previous project's activity list as a starting point for your project
is an example of this
28. Used to modify a non-conforming product, following a change request
ACROSS DOWN
2. A project generally produces a new product or ______________ 1. Allows acceleration of a schedule activity
5. A chart that show relationships between 2 variables to identify 2. The two methods are crashing and fast tracking
correlation and spot trends 3. _________ deliverables are correct per Control Quality
7. Is determined by late finish - early finish 4. Produce repetitive products, services or results
8. Costs that are related to producing specific goods or performing a 6. Includes prevention costs and appraisal costs
specific service 12. A speech is an example of this communication type
9. Type of contract with the highest risk for the seller and the least risk for 13. A risk strategy which reduces the probability of a risk occurring
the buyer 15. Stakeholder influence and risk ______ as time passes in the project
10. Third stage of team development in Tuckman's ladder life cycle
11. In this type of organization the project manager and functional 16. Early finish of predecessor activity + 1 = ___________
managers share the authority/power 17. Technique that determines the Estimate at Completion
18. A key stakeholder who will pay for the project’s product or service 19. A negative risk
20. The approved project charter formally ______ the project 23. Although lessons learned are documented throughout the project, in
21. Policies, procedures, corporate knowledge base are examples this process group they are formally gathered
22. Approved version of the schedule 24. Costs that include inspections
25. Keeping errors out of the process 26. Total planned value of all project work
27. A technique used to verify enough time and money is set aside for
contingencies
1. accepted
2. Lessons Learned Documents
3. Resource Management Plan
1. EV: CPI = EV
AC
Therefore: EV = CPI x AC
EV = 0.96 x $30,000
EV = $28,800
Because we know CPI and AC from the facts of the question, we use the CPI formula and simply solve for the
missing value (EV) by multiplying the CPI by AC. This should be your first step, because knowing EV will be
critical to answering the remaining questions.
2. PV: SPI = EV
PV
Therefore: PV = EV
SPI
PV = $28,800
1.2
PV = $24,000
Now that we have the value for EV, we can plug in the other known values to the SPI formula to solve for PV.
Here, we are given the SPI in the question and we now know EV, so we simply plug those in and solve for the
missing PV value by dividing EV ($28,000) by our SPI (1.2).
3. BAC: BAC = PV x 4
BAC = $24,000 x 4
BAC = $96,000
Here we have to determine BAC, which is our original total budget. The first step is to know where we are in time,
and the facts tell us we are ¼ of the way done. It may be tempting to just take AC and multiply it by 4 to get the
total BAC, but don’t take the bait. Remember, AC is what we actually spent, not necessarily what we planned to
spend. We need to know what we planned to spend in total, so we look to the current PV because there are no
other clues given. Because we know the work is evenly spread across the 12 weeks, we know that our produc-
tion rate should be linear, and therefore the PV for the next 3 periods should each match that of the current
period. Thus, we multiply our PV at the ¼ mark by 4 and get our BAC of $96,000. This will tell us the total value
of work we planned to achieve, using the spend rate we built into our budget.
Things get a lot easier now, since we have the key values we need (EV, PV, BAC and AC) to perform any earned
value equation. Because spending is expected to continue at the current rate (meaning variances are typical),
we use the BAC/CPI formula to get our Estimate at Completion forecast (which is what we now believe we will
spend in total to complete the project).
ETC tells us what we will spend from this point forward, to complete the project. The ETC formula is always the
same (EAC-AC) regardless of the circumstances (we already accounted for those circumstances when we
calculated EAC). Thus, we subtract our Actual Costs of $30,000 from our Estimate at Completion of $100,000,
and we know we will need to spend another $70,000 to complete the project (assuming spending continues at
the current rate).
Another easy one. VAC (Variance at Completion) just tells us the difference between our EAC (updated total
budget forecast now that we are doing the work) and our BAC (original budget we established during planning).
This formula is always the same regardless of the circumstances (we already accounted for those circumstances
when we calculated EAC). The VAC of -$4,000 tells us we expect to spend $4,000 over our original budget to
complete the project.
TCPI, or “To Complete Performance Index,” tells us how efficient we must be with costs moving forward in
order to finish within our original budget (BAC). This tells us that we need to get $1.02 in value from every $1
spent for the remaining 9 weeks of the project to make up for our current shortfall in cost efficiency and deliver
the project on budget.
1. EV: CPI = EV
AC
Therefore: EV = CPI x AC
EV = 0.96 x $125,000
EV = $120,000 (i.e. this is the amount of work you have completed)
2. PV: SPI = EV
PV
Therefore: PV = EV
SPI
PV = $120,000
0.89
PV = $134,831.46 (i.e. this is the amount of work you SHOULD have completed up until now)
3. BAC: We are 1/3 of the way through the project. Our PV is $134,831.46, so our Budget at completion is:
BAC = PV x 3
BAC = $134,831.46 x 3
BAC = $404,494.38 (i.e. the original baseline budget)
4. EAC: Since the question states budgeted rate is going to be used we need to use the following formula:
EAC = AC + (BAC - EV)
EAC = $125,000 + ($404,494.38 - $120,000)
EAC = $409,494.38 (i.e. the new estimated budget)
7. TCPI: Since the original budget may still be achievable we will use the following formula:
TCPI = (BAC - EV)
(BAC - AC)
TCPI = ($404,494.38 - $120,000)
($404,494.38 - $125,000)
TCPI = $284,494.38
$279,494.38
TCPI = 1.01 (or 101%) (i.e. ‘if we work at 101% efficiency rate between now and the end of the
project we will meet our original budget’)
3. AC = $60,000
Provided in the facts of the question
4. BAC = $100,000
Provided in the facts of the question
5. CV: CV = EV - AC
CV = 40,000 - 60,000
CV = -$20,000
This tells us that we are currently $20,000 over budget, since we have spent $60,000 but only obtained $40,000
of work value.
6. SV: SV = EV - PV
SV = 40,000 - 50,000
SV = -$10,000
This is how far behind schedule we are right now, i.e. we should have completed $10,000 worth of work at this
point. It may seem odd that we gauge our schedule performance in dollars, but keep in mind we had to assign
a dollar value for all of this work during planning (which was based on what we planned to spend to get the work
done).
7. CPI: CPI = EV
AC
CPI = 40,000
60,000
CPI = 0.667
For every dollar we are spending we are only getting 66.7 cents worth of work done (relative to the budgeted
spend rate).
8. SPI: SPI = EV
PV
SPI = 40,000
50,000
SPI = 0.8
We have only completed 80% of the work that we should have completed at this point in time.
The Problem: You don’t have all the values you need to perform your calculations
The Solution: You must solve for the missing values using the information you are given.
Steps to follow:
1) Determine what information you need to provide. In this case, they are looking for AC.
2) Determine what values are given in the facts. Here, we are given CPI and SPI directly, and are given PV
indirectly (we should have completed $1 million worth of work at this point). So we know CPI, SPI and PV, and
can work backwards from there.
CPI = 0.8
SPI = 1.2
PV = 1,000,000
3) Next we take the values we have and look to our formula sheet to see which of them utilizes the figure that
we need to solve for (AC). We find that CPI utilizes AC, since that formula is:
CPI = EV
AC.
4) The next step is to determine EV so we can solve for the AC component of the CPI formula. Since we are
given PV ($1 million) and SPI (1.2) we can solve for EV. We know that SPI = EV/PV. Hence, we use the
formula:
SPI = EV
PV
EV = SPI x PV
EV = 1.2 x 1,000,000
EV = 1,200,000
5) Now that we have CPI and EV, we can back into the AC value we are looking for.
CPI = EV
AC
AC = EV
CPI
AC = 1,200,000
0.8
AC = 1,500,000
You are managing a project to install flooring for a 10-room building. Each room will take 1 week to complete and
will cost $1,000. You are 4 weeks into the project and have completed 4.5 rooms to date at a cost of $4,200.
Assume spending will continue at current rate.
EV 4.5 rooms X $1,000 $4,500 How much work has actually been
completed so far
EAC BAC / CPI $9,337.06 At this rate we should finish our project at
= 10000 / 1.07 a cost of $9,337.06, instead of $10,000
Answer: $1,200
We get the planned value by determining where we are in time, and calculating what amount of the work should
have been done by this point, according to our plan. In this case, we know that each activity was scheduled to
take one week, with equal amounts of work being performed each day. Since we know our BAC for Activity D is
$6,000, we simply divide that by 5 to get $1,200. After one day we should have completed $1,200 worth of work,
and $1,200 worth of additional work the next day (for a total PV of $2,400 at that point), and so forth.
Answer: $3,000
In this case we need to calculate the value of what we have created at this point. Note that the value is based
on what we planned to spend to perform the work. In other words, think of EV as what a piece of work is worth
to us based on how much we planned to spend to accomplish it (as opposed to what we could sell it for). We
therefore have a piece of work valued at $6,000 total to us (BAC), and we are 50% done with that work. We
therefore multiply $6,000 by .5 and get $3,000.
Answer: .9375
TCPI shows us the efficiency rate at which we must work going forward to finish on budget. The formula is (BAC
– EV) / (BAC-AC). We know the BAC for this activity is $6,000. And since it is 50% complete at the time
referenced in the question, we know our EV is $3,000 (50% of $6,000). Finally, we know we have spent $2,800
to get where we are, so we have our AC. Plugging in the numbers, we get (6,000 – 3,000) / (6,000 – 2,800), or
3,000/3,200. When we do the math, we get .9375.
Answer: ($500)
Cost Variance tells us the difference between the budgeted value of the work we completed (EV) and the
amounts we had to spend to get that work done (AC). The formula is EV-AC. In this case, the EV is $8,000 since
that is the amount we budgeted for that work to be completed. However, we actually spent $8,500 to get the work
done (AC). Thus, $8,000 - $8,500 results in a Cost Variance of ($500). Note that negative values will usually be
shown in parentheses. Negative costs variances tell us we are over budget. Positive Cost Variances tell us we
are under budget. A Cost Variance of 0 means we spent exactly what we planned to spend for that activity.
Note that we would calculate Cost Performance Index using the same values, but we would divide instead of
subtracting. Hence, $8,000 / $8,500 = CPI of .941. This tells us that, for every dollar we are spending on this
activity, we are only getting 94 cents of value. CPI is generally considered the most important Earned
Value metric.
Answer: ($1,000)
Schedule Variance tells us the difference between what we have completed at a particular point in time and what
we should have completed at that point. The formula is EV – PV. Here, we only completed 80% of the work for
Activity A after one full week, and we know Activity A was planned to be complete after one full week. Thus, our
earned value is 80% of the original budget for the activity (.8 x $5,000 = EV of $4,000). But we were supposed
to have completed all the work at this point, which was budgeted for $5,000. Thus, we subtract $5,000 from
$4,000 to get a Schedule Variance of ($1,000).
Note that Schedule Performance Index uses the same values, but you simply divide instead of subtracting.
Thus, our SPI at this point in time would be .8 ($4,000 / $5,000). We should have completed 20% more work at
this point in time than we actually did.
Answer: B.
This activity is behind schedule and under budget. We are looking at the status at the end of week 4. At that
time, the activity should have been completed, but was only 50% done, so we are behind schedule. But we have
managed to stay slightly under budget, however, since we have completed half the work (which was originally
budgeted at $6,000) while only spending $2,800. Our Cost Variance therefore is $200 (EV of $3,000 – AC of
$2,800) and our CPI is 1.07 (EV of $3,000 / AC of $2,800).
7. Assuming variances encountered to date will not continue, what is the EAC of the entire project (all 4 activities
combined) at the end of week 4?
Answer: $31,300
Because variances are atypical, we use the following formula: AC + (BAC - EV). Because we are looking at the
entire project, we need to aggregate the figures from each activity, which yields the following totals: AC -
$28,300; EV - $26,000; BAC - $29,000. We therefore calculate 28,300 + (29,000 – 26,000) to get $31,300. Our
Variance at Completion (VAC), would therefore be ($2,300), since VAC = BAC – EAC.
1. Draw a network diagram based on the data listed in the table below.
5. The early start, early finish, late start, late finish and float for each activity based on the network diagram:
Float = 2 Float = 6
14 19 20 25
ES B EF ES C EF
Float = 0 Float = 0
1 13
LS 6 LF LS 6 LF
32 40
16 21 26 31
ES A EF ES F EF
LS 13 LF
14 21 22 31
LS 9 LF
1 13 32 40
ES D EF ES E EF
LS 8 LF LS 10 LF
14 21 22 31
Float = 0 Float = 0
6. The path with the least schedule risk based on the network diagram:
ABCF, with a duration of 34 weeks (13+6+6+9)
7. If the duration for activity B changes to 9 weeks, the impact to the project is that there is a new critical path:
ABCF=37 (13+9+6+9)
ABEF=41 (13+9+10+9) – New Critical Path
ADEF=40 (13+8+10+9)
8. All options to reduce the schedule must be analyzed with respect to overall project impacts, and those
options include:
• “Crashing,” which involves adding resources to a project activity to make it finish sooner. Here, either
internal or external resources can be added to Activity E on the critical path. Crashing almost always
increases costs, however. The activity on the critical path with the lowest crashing cost should be
considered first.
• Utilizing the same resource on a critical path activity but having that person work overtime.
This could be considered a form of crashing because you are using more resource hours and costs
will rise.
8. Cont.
• Adding a more skilled resource (if possible) on a critical path activity to reduce time. This is also
a form of crashing in that you are adding greater resources in an effort to finish sooner.
• “Fast tracking,” which involves changing the sequence of activities so that some activities run in
parallel, instead of sequentially. Fast tracking assumes that the dependencies between the activities
are discretionary. Fast tracking almost always increases the risk of rework.
A project has six activities: A, B, C, D, E and F. Activity A can start anytime and takes 13 weeks to finish. Activity
A must be completed before Activities B and D can start. Activity B requires 6 weeks to complete and Activity D
requires 8 weeks to complete. Activity B must be completed before Activity C can start. Activity C requires 12
weeks to complete. Activities B and D must be completed before Activity E can start and Activity E requires 10
weeks. Activity F takes 9 weeks and can start as soon as Activities C and E are completed.
A F
13 9
D E
8 10
2. The paths based on the network diagram:
ABCF, ABEF, ADEF
4. There are two critical paths based on the network diagram. Having multiple critical paths increases the
project risks:
ABCF = 40 weeks (13+6+12+9)
ADEF = 40 weeks (13+8+10+9)
5. The early start, early finish, late start, late finish and float for each activity based on the network diagram:
Float = 0 Float = 0
14 19 20 31
ES B EF ES C EF
Float = 0 Float = 0
1 13
LS 6 LF LS 12 LF
32 40
14 19 20 31
ES A EF ES F EF
LS 13 LF
14 21 22 31
LS 9 LF
1 13 32 40
ES D EF ES E EF
LS 8 LF LS 10 LF
14 21 22 31
Float = 0 Float = 0
6. If the relationship for activity C changed to Start-to-Start (S-S) with activity B, path ABCF is no longer a critical
path. Path ACF will complete in 34 weeks. Because activities B and C start at the same time, only the one
with the longer duration (C) needs to be included in the critical path analysis. The critical path is ADEF, with
a duration of 40 weeks: Float = 6
14 25
ES C EF
LS 12 LF
20 31
14 19
ES B EF Float = 2
Float = 0 Float = 0
1 13 LS 6 LF 32 40
ES EF 16 21 ES EF
A F
14 21 22 31
LS 13 LF LS 9 LF
ES D EF ES E EF
1 13 32 40
LS 8 LF LS 10 LF
14 21 22 31
Float = 0 Float = 0
3. The critical path based on the network diagram is path BEHI, with a total duration of 28
34 (12+8+8+6)
4. The path with the least schedule risk based on the network diagram is ADGI = 24 (10+4+4+6).
5. The early start, early finish, late start, late finish and float for each activity based on the network diagram:
11 18 19 24
ES C EF Float = 4 ES F EF Float = 4
Float = 4
1 10 LS 8 LF LS 6 LF
ES A EF 15 22 23 28
LS 10 LF 13 16 17 20 29 34
5 14 ES EF Float = 8 ES EF Float = 8 ES EF
D G I
LS 4 LF LS 4 LF LS 6 LF
1 12
21 24 25 28 29 34
ES B EF 13 20 21 28
Float = 0
LS 12 LF ES E EF ES H EF
1 12 LS 8 LF LS 8 LF
Float = 0
13 20 21 28
Float = 0 Float = 0
6. If the duration for activity H changes to 6 and the relationship for activity H changes to Finish-to-Finish (F-F)
with activity E, the start dates for Activity H are calculated based on activity H and E finishing at the same time.
In other words, you start by taking the EF and LF of Activity E and plugging them in for the EF and LF of Activity
H as well (since it is a F-F relationship). You then subtract the duration of 6 and add one back in to get the ES
and LS for Activity H. The path BEI has a duration of 24 26 weeks. Activity H does not have to be added to the
calculation, since it is ongoing at the same time as Activity E, and takes less time in duration. The new critical
path is ACFI, with a duration of 30 weeks and has the least amount of float.
11 18 19 24
ES C EF Float = 0 ES F EF Float = 0
Float = 0
1 10 LS 8 LF LS 6 LF
ES A EF 11 18 19 24
LS 10 LF 13 16 17 20 25 30
1 10 ES EF Float = 4 ES EF Float = 4 ES EF
D G I
LS 4 LF LS 4 LF LS 6 LF
1 12
17 20 21 24 25 30
ES B EF 13 20
Float = 0
LS 12 LF ES E EF Float = 4
5 16 LS 8 LF
Float = 4
17 24
15 20
ES H EF
LS 6 LF
Float = 4
19 24