Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Job Title : Replace corroded 3" & 2" FG line prep'd by : Agus Dwi Laksito
Job item : 11864/C Date : 9-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine
MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10
REMARKS :
Today:
a Mobilization material at power p/f (scope 1)
b Stringing material at power p/f (scope 1)
c Install scaffolding at power p/f (scope 1)
Next :
a Double joint 3" & 2" fuel gas
b NDT
NOTE:
'file:///conversion/tmp/scratch/469415678.xls'#$09Jan2012
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by : Agus Dwi Laksito
Job item : 11864/C Date : 10-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine
MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10
REMARKS :
Today:
a Double joint 3" at underdeck power p/f (scope 1)
b Radiography at underdeck power p/f (scope 1)
c Prepare for tie in 3" & 2" at underdeck power p/f (scope 1)
Next :
a Double joint 2" fuel gas at gangway (scope 3)
b Radiography at gangway area (scope 3)
NOTE:
'file:///conversion/tmp/scratch/469415678.xls'#$10Jan2012
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by : Agus Dwi Laksito
Job item : 11864/C Date : 11-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine
MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10
REMARKS :
Today:
a Double joint 2" at gangway (scope 3)
b Scaffolding works at underdeck metering area (scope 3)
Next :
a Double joint 2" fuel gas at metering area (scope 3)
b Radiography at metering area (scope 3)
NOTE:
'file:///conversion/tmp/scratch/469415678.xls'#$11Jan2012
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by
Job item : 11864/C Date
Contractor : PT. MEINDO Start
Dwg. No. : Finish
W/permit : Weather
NO D E S C R I P T I O N. QTY. WF PROGRES
PREVIOUS
MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine
FOREMAN 1 - Grinding mach, cut s
FITTER 1 - Speed boat
WELDER 1 - LCT
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10
REMARKS :
Today:
a Repair welding at 3" FG line, under deck of power platform area, sheet 2 of 4
b Stringing material and double joint activity 2" FG line under deck of process pla
c NDT
Next :
a Continue double joints of 2" FG line, sheet 4 of 5, remaining 2 joints
b NDT
NOTE:
PROGRESS REMARKS
TODAY CUMUL
0.0 1.0
0.0 3.0
3.0 5.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10
REMARKS :
Today:
a Continue double joint 2" FG line under deck of process platform, 2 joint, sheet 4 of 5
b NDT
Next :
a Tie ins at scope 1, sheet 2 of 5
b NDT
c Leak test
NOTE:
MANPOWER : EQUIPMENT :
REMARKS :
Today:
a Continue external cleaning
b sand recovering, (3 drums)
Next :
a Continue external cleaning
b Start internal cleaning and sand recovering
NOTE: start activity at 15.00, due to rain (after BTX measurement by Medic)
'file:///conversion/tmp/scratch/469415678.xls'#$05 Maret 2020
DAILY PROGRESS REPORT
Job Title : Assist INS for internal inspection at V-860 TPA prep'd by
Job item : WO.8478281 Date
Contractor : PT. ARUNG Start
Dwg. No. : Finish
W/permit : Weather
NO D E S C R I P T I O N. QTY. WF PROGRESS
PREVIOUS TODAY
MANPOWER : EQUIPMENT :
REMARKS :
Today:
a Mobilization scaffolding material
b Revalidation scaffolding (3 set), done
c Continue external cleaning and sand recovering (4 drums)
Next :
a Start internal cleaning
b Sand Recovering
PROGRESS REMARKS
TODAY CUMUL
0.0 3.0
0.0 10.0
0.0 15.0
1.0 13.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
lding machine =
nding mach, cut set =
team/kota minyak, PSV replacement)