DAILY PROGRESS REPORT

Job Title : Replace corroded 3" & 2" FG line prep'd by : Agus Dwi Laksito
Job item : 11864/C Date : 9-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine

NO D E S C R I P T I O N. QTY. WF PROGRESS REMARKS

PREVIOUS TODAY CUMUL

1 Mob - demob & stringing material 5 ea 2 0.0 1.0 1.0

2 Install & remove scaffolding (5 place 6 ea 10 0.0 2.0 2.0

3 Double joint (5 scope) 10 ea 15 0.0 0.0 0.0

4 Install & remove spade (5 scope) 5 ea 10 0.0 0.0 0.0

5 Replace corroded spool (5 scope) 5 ea 50 0.0 0.0 0.0

6 NDT 5 ea 10 0.0 0.0 0.0

7 Site clean up 5 ea 3 0.0 0.0 0.0

OVERALL PROGRESS 100 0.00 3.00 3.00 In progress

MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10

REMARKS :

Today:
a Mobilization material at power p/f (scope 1)
b Stringing material at power p/f (scope 1)
c Install scaffolding at power p/f (scope 1)

Next :
a Double joint 3" & 2" fuel gas
b NDT

NOTE:

'file:///conversion/tmp/scratch/469415678.xls'#$09Jan2012
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by : Agus Dwi Laksito
Job item : 11864/C Date : 10-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine

NO D E S C R I P T I O N. QTY. WF PROGRESS REMARKS

PREVIOUS TODAY CUMUL

1 Mob - demob & stringing material 5 ea 2 1.0 0.0 1.0

2 Install & remove scaffolding (5 place 6 ea 10 2.0 0.0 2.0

3 Double joint (5 scope) 10 ea 15 0.0 1.0 1.0

4 Install & remove spade (5 scope) 5 ea 10 0.0 0.0 0.0

5 Replace corroded spool (5 scope) 5 ea 50 0.0 0.0 0.0

6 NDT (Radiography) 5 ea 10 0.0 0.0 0.0

7 Site clean up 5 ea 3 0.0 0.0 0.0

OVERALL PROGRESS 100 3.00 1.00 4.00 In progress

MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10

REMARKS :

Today:
a Double joint 3" at underdeck power p/f (scope 1)
b Radiography at underdeck power p/f (scope 1)
c Prepare for tie in 3" & 2" at underdeck power p/f (scope 1)

Next :
a Double joint 2" fuel gas at gangway (scope 3)
b Radiography at gangway area (scope 3)

NOTE:

'file:///conversion/tmp/scratch/469415678.xls'#$10Jan2012
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by : Agus Dwi Laksito
Job item : 11864/C Date : 11-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine

NO D E S C R I P T I O N. QTY. WF PROGRESS REMARKS

PREVIOUS TODAY CUMUL

1 Mob - demob & stringing material 5 ea 2 1.0 0.0 1.0

2 Install & remove scaffolding (5 place 5 lot 10 2.0 1.0 3.0

3 Double joint (5 scope) 10 lot 15 1.0 1.0 2.0

4 Install & remove spade (5 scope) 5 lot 10 0.0 0.0 0.0

5 Replace corroded spool (5 scope) 5 lot 40 0.0 0.0 0.0

6 NDT (Radiography) 5 lot 10 0.0 0.0 0.0

7 Leak test (5 scope) 5 lot 10 0.0 0.0 0.0

8 Site clean up 5 ea 3 0.0 0.0 0.0

OVERALL PROGRESS 100 4.00 2.00 6.00 In progress

MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10

REMARKS :

Today:
a Double joint 2" at gangway (scope 3)
b Scaffolding works at underdeck metering area (scope 3)

Next :
a Double joint 2" fuel gas at metering area (scope 3)
b Radiography at metering area (scope 3)

NOTE:

'file:///conversion/tmp/scratch/469415678.xls'#$11Jan2012
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by
Job item : 11864/C Date
Contractor : PT. MEINDO Start
Dwg. No. : Finish
W/permit : Weather

NO D E S C R I P T I O N. QTY. WF PROGRES
PREVIOUS

1 Mob - demob & stringing material 5 ea 2 1.0

2 Install & remove scaffolding (5 place 5 lot 10 3.0

3 Double joint (5 scope) 10 lot 15 2.0

4 Install & remove spade (5 scope) 5 lot 10 0.0

5 Replace corroded spool (5 scope) 5 lot 40 0.0

6 NDT (Radiography) 5 lot 10 0.0

7 Leak test (5 scope) 5 lot 10 0.0

8 Site clean up 5 ea 3 0.0

OVERALL PROGRESS 100 6.00

MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine
FOREMAN 1 - Grinding mach, cut s
FITTER 1 - Speed boat
WELDER 1 - LCT
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10

REMARKS :

Today:
a Repair welding at 3" FG line, under deck of power platform area, sheet 2 of 4
b Stringing material and double joint activity 2" FG line under deck of process pla
c NDT

Next :
a Continue double joints of 2" FG line, sheet 4 of 5, remaining 2 joints
b NDT

NOTE:

'file:///conversion/tmp/scratch/469415678.xls'#$12 jan 2012


REPORT
prep'd by : I Gede Andi D
Date : 12-Jan-12
Start : M =08.00 A =
Finish : M= A =17.00
Weather M =Fine A =Fine

PROGRESS REMARKS
TODAY CUMUL

0.0 1.0

0.0 3.0

3.0 5.0

0.0 0.0

0.0 0.0

0.0 0.0

0.0 0.0

0.0 0.0

3.00 9.00 In progress

Welding machine = 1ea


Grinding mach, cut set =
Speed boat = -
= LCT. Teluk Bontang
area, sheet 2 of 4
deck of process platform, 4 of 6 joints, sheet 4 of 5
DAILY PROGRESS REPORT
Job Title : Replace corroded 3" & 2" FG line prep'd by : I Gede Andi D
Job item : 11864/C Date : 13-Jan-12
Contractor : PT. MEINDO Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Fine A =Fine

NO D E S C R I P T I O N. QTY. WF PROGRESS REMARKS

PREVIOUS TODAY CUMUL

1 Mob - demob & stringing material 5 ea 2 1.0 0.0 1.0

2 Install & remove scaffolding (5 place 5 lot 10 3.0 0.0 3.0

3 Double joint (5 scope) 10 lot 15 5.0 1.0 6.0

4 Install & remove spade (5 scope) 5 lot 10 0.0 0.0 0.0

5 Replace corroded spool (5 scope) 5 lot 40 0.0 0.0 0.0

6 NDT (Radiography) 5 lot 10 0.0 2.0 2.0

7 Leak test (5 scope) 5 lot 10 0.0 0.0 0.0

8 Site clean up 5 ea 3 0.0 0.0 0.0

OVERALL PROGRESS 100 9.00 3.00 12.00 In progress

MANPOWER : EQUIPMENT :
SUPERVISOR - - Welding machine = 1ea
FOREMAN 1 - Grinding mach, cut set =
FITTER 1 - Speed boat = -
WELDER 1 - LCT = LCT. Teluk Bontang
HELPER 5
PAINTER 0
SCAFFOLDER 1
SAFETY MAN 1
10

REMARKS :

Today:
a Continue double joint 2" FG line under deck of process platform, 2 joint, sheet 4 of 5
b NDT

Next :
a Tie ins at scope 1, sheet 2 of 5
b NDT
c Leak test
NOTE:

'file:///conversion/tmp/scratch/469415678.xls'#$13 jan 2012


DAILY PROGRESS REPORT
Job Title : Assist INS for internal inspection at V-860 TPA prep'd by : I Gede Andi D
Job item : WO. 8478281 Date : 5-Mar-20
Contractor : PT. ARUNG Start : M =08.00 A =
Dwg. No. : Finish : M= A =17.00
W/permit : Weather M =Clear A =Rain

NO D E S C R I P T I O N. QTY. WF PROGRESS REMARKS

PREVIOUS TODAY CUMUL

1 MOB and de MOB LOT 10 3.0 0.0 3.0

2 Scaffolding job 3 set 20 10.0 0.0 10.0

3 Spading Activity and spool removal LOT 15 15.0 0.0 15.0

4 Open manhole and external cleaning LOT 15 10.0 2.0 12.0

5 Internal cleaning LOT 15 0.0 0.0 0.0

6 Remove/reinstall internal parts LOT 10 0.0 0.0 0.0

7 Despading, close manhole LOT 10 0.0 0.0 0.0

8 Housekeeping LOT 5 0.0 0.0 0.0

OVERALL PROGRESS 100 38.00 2.00 40.00 In progress

MANPOWER : EQUIPMENT :

SUPERVISOR - - Welding machine =


FOREMAN 1 - Grinding mach, cut set =
FITTER 1
WELDER 0
HELPER 5
PAINTER 0
SCAFFOLDER 2
SAFETY MAN 1
10

REMARKS :

Today:
a Continue external cleaning
b sand recovering, (3 drums)

Next :
a Continue external cleaning
b Start internal cleaning and sand recovering

NOTE: start activity at 15.00, due to rain (after BTX measurement by Medic)
'file:///conversion/tmp/scratch/469415678.xls'#$05 Maret 2020
DAILY PROGRESS REPORT
Job Title : Assist INS for internal inspection at V-860 TPA prep'd by
Job item : WO.8478281 Date
Contractor : PT. ARUNG Start
Dwg. No. : Finish
W/permit : Weather

NO D E S C R I P T I O N. QTY. WF PROGRESS
PREVIOUS TODAY

1 MOB and de MOB LOT 10 3.0

2 Scaffolding job 3 set 20 10.0

3 Spading Activity and spool removal LOT 15 15.0

4 Open manhole and external cleaning LOT 15 12.0

5 Internal cleaning LOT 15 0.0

6 Remove/reinstall internal parts LOT 10 0.0

7 Despading, close manhole LOT 10 0.0

8 Housekeeping LOT 5 0.0

OVERALL PROGRESS 100 40.00

MANPOWER : EQUIPMENT :

SUPERVISOR - - Welding machine


FOREMAN 1 - Grinding mach, cut se
FITTER 1
WELDER 0
HELPER 6
PAINTER 1
SCAFFOLDER 1
SAFETY MAN 1
11

REMARKS :

Today:
a Mobilization scaffolding material
b Revalidation scaffolding (3 set), done
c Continue external cleaning and sand recovering (4 drums)
Next :
a Start internal cleaning
b Sand Recovering

NOTE: Open permit at 10.00, due to rain


BTX measurement by Medic at 13.30
Stop activity at 15.00,due to lifting activity at V-860 (by small team/kota minyak

'file:///conversion/tmp/scratch/469415678.xls'#$06 maret 2020


REPORT
prep'd by : I Gede Andi D
Date : 6-Mar-20
Start : M =08.00 A =
Finish : M= A =17.00
Weather M =Rain A =Clear

PROGRESS REMARKS
TODAY CUMUL

0.0 3.0

0.0 10.0

0.0 15.0

1.0 13.0

0.0 0.0

0.0 0.0

0.0 0.0

0.0 0.0

1.00 41.00 In progress

lding machine =
nding mach, cut set =
team/kota minyak, PSV replacement)