A brief back ground for your information and valuable advice

1. System Details:

Equipment: Schneider Unitized Substation, PSS PSS13622000101


Rating : 2000kVA
Power Transformer: 11000/415 V, 2000kVA, Oil filled, 105 / 2783 Amps

2. Applied Relay Settings:

Relay Make/Model: Schneider / DPX-V5


CTR: 75 /1 A
Freq: 50Hz
PChr: DEFT
EChr: DEFT
I > : 1.0In
ti > : 0.2 s
t > : 0.1 s
I >> : Not used
Ie > : 0.2In
Tie > : 0.2 s
Te > : 0.05 s
Ie >> : Not used

3. First instance breaker trial charging trip details dt. 09.04.2020:

Tripped on: L1 Over Current

Trip Log recorded by relay:

FL1 : 127.0 A
FL2 : 123.7 A
FL3 : 100.5 A
FIe : 9.7 A
Trip Time : 0.1 s

4. Our further proposal before 2nd recharging trial tomorrow:

To set relay at:

CTR: 150 /1 A
Freq: 50Hz
PChr: DEFT
EChr: DEFT
I > : 0.7In (Considering 105A as full load primary current)
ti > : 0.2 s
t > : 0.1 s
I >> : Not used
Ie > : 0.15In [considering 20% of rated primary current of transformer (105 A) as the threshold for
earth fault]
Tie > : 0.2 s
Te > : 0.05 s
Ie >> : Not used