(CSR-2015)
* Earth work in excavation of foundation in hard soil within initial lead of 50m and 1.5m initial lift including rough
dressing and leveling the bed.
*
R.R Masonary in CM(1:6) in foundation and plinth including cost,carriage and royality etc. Complete.
Stone 1.00 Cum @ Rs. 230.00 /Cum Rs. 230.00
Sand 0.34 Cum @ Rs. 59.00 /Cum Rs. 20.06
Cement
0.8151 Qtl @ Rs. 640.00 /Qtl Rs. 521.66
Masson 1st class 0.35 nos @ Rs. 273.50 /day Rs. 95.73
Masson 2nd class 1.41 nos @ Rs. 253.50 /day Rs. 357.44
Man Mulia 3.17 nos @ Rs. 213.50 /day Rs. 676.80
Add carriage and royality
Stone 1.00 Cum @ Rs. 294.90 /Cum Rs. 294.90
Sand 0.34 Cum @ Rs. 194.90 /Cum Rs. 66.27
Cement
0.8151 Qtl @ Rs. 16.90 /Qtl Rs. 13.78
Total Rs. 2276.62 /Cum
*
Cement concrete in (1:2:4) with 12mm size CBHG chips including cost,carriage and royality etc. Complete.
CHBG chips 0.90 Cum @ Rs. 1185.00 /Cum Rs. 1066.50
Sand 0.45 Cum @ Rs. 59.00 /Cum Rs. 26.55
Cement
3.23 Qtl @ Rs. 640.00 /Qtl Rs. 2067.20
Masson 2nd class 0.68 nos @ Rs. 253.50 /day Rs. 172.38
Man Mulia 4.60 nos @ Rs. 213.50 /day Rs. 982.10
Add carriage and royality
HBG Metal 0.90 Cum @ Rs. 294.90 /Cum Rs. 265.41
Sand 0.45 Cum @ Rs. 194.90 /Cum Rs. 87.71
Cement
3.23 Qtl @ Rs. 16.90 /Qtl Rs. 54.59
Total Rs. 4722.43 /Cum
Add extra for first floor 15% (Labour only) Rs. 162.48
Total Rs. 4884.91
* Cement concrete in (1:1.5:3) with 12mm size CBHG chips including cost,carriage and royality etc. Complete.
* RCC work of M20 grade with 20mm and down grade black hard granaite (Crusher Broken) stone chips including
hosting and laying and cost,carriage and royality etc. Complete.
* Reinforcement for RCC works including cutting,bending,tying and placing in position including cost of the materials
etc. Complete.
Blacksmith special 3 nos @ Rs. 273.50 /day Rs. 820.50
Mate 0.44 nos @ Rs. 233.50 /day Rs. 102.74
Man Mulia 8 nos @ Rs. 213.50 /day Rs. 1708.00
Binding wire 8 kg @ Rs. 78.00 /kg Rs. 624.00
Cost of Reinforcement 1 MT @ Rs. 45000.00 /MT Rs. 45000.00
Rs. 48255.24 /MT
Rs. 4825.52 /Qtl.
OR Say Rs. 48.26 /Kg.
OR Say Rs. 48.00 /Kg.
* Rigid and smooth centering and shuttering for RCC works and dismentaling them after casting including cost of all
materials etc. Complete.
a RCC floor / RCC slab / Chajja /Balcony upto 4.30m height.(Data for 9.00sqm)
Non sal wood scantling 0.112 Cum @ Rs. 19721.00 /Cum Rs. 2208.75
38mm dia. Plank 0.34 Cum @ Rs. 19721.00 /Cum Rs. 6705.14
120mm dia. Ballahs 56.00 Rmt @ Rs. 102.00 /Rmt. Rs. 5712.00
Carriage of wood 1.142 Cum @ Rs. 169.00 /1.25Cum Rs. 154.40
Rs. 14780.29 /10 times
OR Say Rs. 1478.029
Carpenter 2nd class 2.75 nos @ Rs. 253.50 /day Rs. 697.13
Semi-skilled mulia 2.75 nos @ Rs. 233.50 /day Rs. 642.13
Rs. 2817.279 /9 Sqm
OR Say Rs. 313.03 / Sqm
* 12mm tkick Cement plastering in C.M (1:6) including cost,carriage and royality etc. Complete.
Sand 0.015 Cum @ Rs. 59.00 /Cum Rs. 0.89
Cement
0.04 Qtl @ Rs. 640.00 /Qtl Rs. 22.91
Masson 2nd class 0.14 nos @ Rs. 253.50 /day Rs. 35.49
Man Mulia 0.12 nos @ Rs. 213.50 /day Rs. 25.62
Add carriage and royality
Sand 0.015 Cum @ Rs. 194.90 /Cum Rs. 2.92
Cement
0.04 Qtl @ Rs. 16.90 /Qtl Rs. 0.61
Total Rs. 88.44 /Sqm
Add extra for first floor 15% (Labour only) Rs. 8.64
Total Rs. 97.08
* 6mm thick cement plastering (1:4) to RCC surface finished smooth including closed deep chipping and slurry
including cost,carriage and royality etc. Complete.
Sand 0.0075 Cum @ Rs. 59.00 /Cum Rs. 0.44
Cement
0.0372 Qtl @ Rs. 640.00 /Qtl Rs. 23.81
Masson 2nd class 0.14 nos @ Rs. 253.50 /day Rs. 35.49
Man Mulia 0.12 nos @ Rs. 213.50 /day Rs. 25.62
Add carriage and royality
Sand 0.0075 Cum @ Rs. 194.90 /Cum Rs. 1.46
Cement
0.0372 Qtl @ Rs. 16.90 /Qtl Rs. 0.63
Total Rs. 87.45 /Sqm
Add extra for first floor 15% (Labour only) Rs. 8.64
Total Rs. 96.09 /Sqm
* Finishing walls with water proofing cement paints of approved shade in new works two coats to give an shade
including cost of paints.
Cost of Paints 2.50 Kg @ Rs. 46.00 /Kg Rs. 115.00
Painter Special 0.22 nos @ Rs. 273.50 /day Rs. 60.17
Man Mulia 0.36 nos @ Rs. 213.50 /day Rs. 76.86
Total Rs. 252.03
Add 2% Sundries and T&P. Rs. 5.04
Total Rs. 257.07 /10Sqm
Rs. 25.71 /Sqm
Add extra for first floor 5% (Labour only) Rs. 6.46
Total Rs. Rs. 32.17 /Sqm
* 2.5 cm thick A.S Flooring with cement concrete (1:2:4) with 20mm size CBHG chips including cost , carriage and
royality etc. Complete.
CHBG chips 0.02 Cum @ Rs. 1185.00 /Cum Rs. 27.26
Sand 0.012 Cum @ Rs. 59.00 /Cum Rs. 0.71
Cement
0.0858 Qtl @ Rs. 640.00 /Qtl Rs. 54.91
Masson Special class 0.13 nos @ Rs. 273.50 /day Rs. 35.56
Man Mulia 0.36 nos @ Rs. 213.50 /day Rs. 76.86
Add carriage and royality
HBG Metal 0.02 Cum @ Rs. 294.90 /Cum Rs. 6.78
Sand 0.012 Cum @ Rs. 194.90 /Cum Rs. 2.34
Cement
0.0858 Qtl @ Rs. 16.90 /Qtl Rs. 1.45
Total Rs. 205.86 /Sqm
Add extra for first floor 5% (Labour only) 5.29
Total Rs. 211.15 /Sqm
* Fixing tiles in floors treads steps and landing on 25mm thick bed of cement morter(1:1) jointed with wax polishing
complete. (Data for 10 sqm)
Sand 0.130 Cum @ Rs. 59.00 /Cum Rs. 7.67
Cement
2.74 Qtl @ Rs. 640.00 /Qtl Rs. 1751.68
Masson Spl. 2.16 nos @ Rs. 273.50 /day Rs. 590.76
Semi-skilled mulia 5.50 nos @ Rs. 233.50 /day Rs. 1284.25
Man Mulia 2.16 nos @ Rs. 213.50 /day Rs. 461.16
Total Rs. 4095.52
Add 5% sundries including carbarandom stone T&P etc. 204.78
Add carriage and royality
Sand 0.130 Cum @ Rs. 194.90 /Cum Rs. 25.34
Cement
2.737 Qtl @ Rs. 16.90 /Qtl Rs. 46.26
Total Rs. 4371.89 /10Sqm
OR Say Rs. 423.12 /Sqm
Add wax polishing Rs. 8.50 /Sqm
Add cost of tiles Rs. 726.00 /Sqm
Total Rs. 1157.62 /Sqm
OR Say Rs. 1157.60 /Sqm
* Fixing tiles in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with wax polishing
complete (Data for 10sqm)
Sand 0.150 Cum @ Rs. 59.00 /Cum Rs. 8.85
Cement
1.375 Qtl @ Rs. 640.00 /Qtl Rs. 880.00
Masson Spl. 3.25 nos @ Rs. 273.50 /day Rs. 888.88
Semi-skilled mulia 7.60 nos @ Rs. 233.50 /day Rs. 1774.60
Man Mulia 3.25 nos @ Rs. 213.50 /day Rs. 693.88
Total Rs. 4246.20
Add 5% sundries including carbarandom stone T&P etc. 212.31
Add carriage and royality
Sand 0.150 Cum @ Rs. 194.90 /Cum Rs. 29.24
Cement
1.375 Qtl @ Rs. 16.90 /Qtl Rs. 23.24
Total Rs. 4510.98 /10Sqm
OR Say Rs. 430.94 /Sqm
Add wax polishing Rs. 8.50 /Sqm
Add cost of tiles Rs. 387.00 /Sqm
Total Rs. 826.44 /Sqm
OR Say Rs. 826.40 /Sqm
* Supplying and laying of GCI sheets in roof including cost of materials labour and T&P etc. Complete. (Data for 9.30
sqm)
Carpenter 1st. class 0.50 nos @ Rs. 273.50 /day Rs. 136.75
Fitter 1st. class 1.00 nos @ Rs. 273.50 /day Rs. 273.50
Man Mulia 2.00 nos @ Rs. 213.50 /day Rs. 427.00
Total Rs. 837.25
Add 2% sundries including carbarandom stone T&P etc. 16.75
Total Rs. 854.00 /9.3Sqm
OR Say Rs. 91.83 /Sqm
Add cost of GCI sheets 3MM thick. Rs. 286.00 /Sqm
Total Rs. 377.83 /Sqm
* Providing and fixing to wall or ceilling and floor PVC pipes class conforming to ASTM-D-1785/89 (Sch-80) and
pipe fittings of the following nominal bore with clamps including making good the wall,ceilling and floor all
complete as per specification complete.
Item of work
Transporting charge by Truck
Quarry site
Distance in
Royality
Carriage
Sl.No
Km.
5KM 50KM 50KM Total Materials Total Cost Royality Unit
H.G Metal of 4cm Local near
1 5 156.4 0 0 156.4 645.00 138.50 939.90 255.40 Cum
size by Area
2 R.R Stone boulder Local near 5 156.4 0 0 156.4 230.00 138.50 524.90 255.40 Cum
other than granite by Area
Local near
3 12mm size HB chips 5 156.4 0 0 156.4 1185.00 138.50 1479.90 255.40 Cum
by Area
4 20mm size HB chips Local near 5 156.4 0 0 156.4 1147.00 138.50 1441.90 255.40 Cum
by Area
Local near
5 10mm size HB chips 5 156.4 0 0 156.4 1254.00 138.50 1548.90 255.40 Cum
by Area
Local near
6 6mm size HB chips 5 156.4 0 0 156.4 814.00 138.50 1108.90 255.40 Cum
by Area
Local near
7 Sand for mortar 5 156.4 0 0 156.4 59.00 38.50 253.90 183.90 Cum
by Area
Local near
8 Sand for filling 5 156.4 0 0 156.4 56.00 38.50 250.90 183.90 Cum
by Area
Local near
9 Cement 5 16.9 0 0 16.9 640.00 0.00 656.90 28.94 Qtl
by Area
10 Morrum Local near 5 156.4 0 0 156.4 50.00 38.50 244.90 183.90 Cum
by Area
Local near
11 CB Brick khoa 5 156.4 0 0 156.4 148.00 0.00 304.40 156.40 Cum
by Area
12 Fly ash Brick size Local near 25 505.4 414 0 1333.4 4598.00 110.00 6041.40 1333.40 1000 Nos
(23cmx11cmx8cm) by Area
LABOUR RATE
Labour catagory Rate in Rs.
High skilled 273.50
Skilled 253.50
Semi-Skilled 233.50
Unskilled 213.50
Certified that the lead royality stated above are correct to the best of my knowledge the cost of MS Rod and cement are
provisional which will be paid as per actual during execution of work. Lead statement and cost of materials have been followed
as per current S.R. 2014 vide G.O No. 12845 , dated 10.11.2014 of works Deppt. enhanced labour rate dated 20.07.2015 with
basing on latest letter.
Raft
12mm dia bar@150mm
c/c both way 20 nos x 1.10 m x .888kg/m x 19.536
column
16mm diaMain bar 16 nos x 1.65 m x 1.58kg/m x 41.686
8mm dia 40 nos x 0.90 m x .395kg/m x 14.220
stirups@150mmc/c
plinth beam
12mm diaMain bar 24 nos x 2.20 m x .888kg/m x 46.886
8mm dia 48 nos x 0.95 m x .395kg/m x 18.012
stirups@150mmc/c
16mm dia foundation 16 nos x 0.70 m x 1.58kg/m x 17.685
Bolt
Total = 158.025 kg
@ Rs 48.26 / Cum Rs 7626.29
6
Rigid and smooth centering and shuttering for RCC work in foundation,plinth
bend,footing bases of column,mass concrete etc and dismentalling them after
casting including cost of all materials.
Technically sanctioned Rs.25900.00 /- ( Rupees Twenty five thousand nine hundred ) Only.
Junior Engineer
Panpatria GP
7
GOVERNMENT OF ODISHA
A Raft:-
i 10mm dia bar @200mm
c/c both ways. 36 nos x 1.05 m x 0.617 kg/m 23.323
B Column:-
i 12mm dia. Main bar 16 nos x 4.7 mx 0.888 kg/m 66.778
ii Lapping 16 nos x 0.6 mx 0.888 kg/m 8.525
iii
8mm dia. Stirups
@200mm c/c 92 nos x 0.75 m x 0.395 kg/m 27.255
C Plingth Beam :-
i 12mm dia. Main bar 4 nos x 2.2 mx 0.888 kg/m 7.814
4 nos x 1.9 mx 0.888 kg/m 6.749
ii
8mm dia. Stirups
@200mm c/c 30 nos x 0.85 m x 0.395 kg/m 10.073
D Slab Beam :-
i 12mm dia. Main bar 8 nos x 3.1 mx 0.888 kg/m 22.022
8 nos x 1.7 mx 0.888 kg/m 12.077
ii
8mm dia. Stirups
@200mm c/c 50 nos x 0.85 m x 0.395 kg/m 16.788
E Roof slab
i 8mm dia bar @175mm
c/c both ways.
8mm dia bar @175mm
c/c both ways. 12 nos x 3.6 mx 0.395 kg/m 17.064
22 nos x 1.7 mx 0.395 kg/m 14.773
ii Binder 10 nos x 3.6 mx 0.395 kg/m 14.220
6 nos x 1.7 mx 0.395 kg/m 4.029
F Basin slab
i
8mm dia bar @175mm
c/c both ways. 12 nos x 1.0 mx 0.395 kg/m 4.740
8 nos x 2.5 mx 0.395 kg/m 7.900
Total = 264.128 Kg.
@ Rs 48.00 / Kg Rs 12678.16
7 CB Bricks(23x11x8cm) masonry in C.M (1:6) in foundation and supper structure
including cost,carriage and royality etc. Complete.
A Long walls :-
i Outside 2 nos x 2.0 m x 3.45 m = 13.80
ii Inside 2 nos x 1.4 m x 2.75 m = 7.70
B Short wall:-
i Outside 2 nos x 1.6 m x 3.45 m = 11.04
ii Inside 2 nos x 1.2 m x 2.75 m = 6.60
C Sintex protection wall 1 nos x 6.2 m x 0.9 m = 5.58
Inside 1 nos x 5.2 m x 0.9 m = 4.68
D Front varandha 1 nos x 3.0 m x 0.45 m = 1.35
Total = 50.75 sqm
E Deduction:-
i Grill Window 0.5 nos x 0.55 mx 0.75 m= (-) 0.21
ii Door 1 nos x 1.5 mx 2.75 m= (-) 4.13
Total = 46.42 Sqm
@ Rs 93.40 / Sqm Rs 4335.51
9 Finishing walls with water proofing cement paints of approved shade in new works
two coats to give an shade including cost of paints.
A Long walls :-
i Outside 2 nos x 2.0 m x 3.45 m = 13.80
ii Inside 2 nos x 1.4 m x 2.75 m = 7.70
B Short wall:-
i Outside 2 nos x 1.6 m x 3.45 m = 11.04
ii Inside 2 nos x 1.2 m x 2.75 m = 6.60
C Side wall 2 nos x 1.5 m x 1.5 m = 4.50
D Slab 1 nos x 1.5 m x 1.1 m = 1.65
F Sintex protection wall 1 nos x 6.2 m x 0.9 m = 5.58
Inside 1 nos x 5.2 m x 0.9 m = 4.68
Total = 55.55
G Deduction:-
i Grill Window 0.5 nos x 0.6 mx 0.75 m= (-) 0.21
ii Door 1 nos x 1.5 mx 2.75 m= (-) 4.13
Total = 51.22 Sqm
@ Rs 24.90 / Sqm Rs 1275.35
10 Supplying and Fixing tiles in floors treads steps and landing on 25mm thick bed of
cement morter(1:1) jointed with wax polishing complete.
i 1 nos x 1.00
Total = 1.00 nos
@ Rs 30000.00 / nos Rs 30000.00
20 Supplying and installation and fixing of water purifier,Ag pure chill 120 PSS
with in built purifier (UV based) Eureka Forbes Ltd. Make And 1.5 KW voltage
stabilizer including labour and T&P etc. Complete.
i 1 nos x 1.00
Total = 1.00 nos
@ Rs 116200.00 / nos Rs 116200.00
Add photograph and sign board Rs 1500.00
Total = Rs. 320009.79
OR say Rs. 320010.00
Limited to Rs. 320000.00
( Rupees Three Lakh Twenty thousand ) Only
Junior Engineer - II
RWS&S,Boudh,Block.
Technically sanctioned amount Rs.3,20,000.00/- ( Rupees Three Lakh Twenty thousand )Only.
GOVERNMENT OF ODISHA