1. SCOPE
1.1. General This specification specifies the requirements and general technical
delivery conditions for aluminium constructions designed for static loaded
conditions.
1.2. Cross-references For cross-references:
• To tables or clauses in this specification no reference will be
given to the document number of this specification.
2. NORMATIVE REFERENCES
2.1. General These normative references are cited at the appropriate places in the text
and the publications are listed hereafter. For dated reference, subsequent
amendments to, or revisions of any for these publications apply to this
specification only when incorporated by amendment or revision.
3. DEFINITIONS
SWP The term “SWP” means Siemens Wind Power A/S.
IWE / EWE The term “IWE / EWE” means International Welding Engineer / European
Welding Engineer.
IWT / EWT The term “IWT / EWT” means International Welding Technologist /
European Welding Technologist.
Construction The term “construction” means all welded constructions for SWP, except
towers.
PO The term “PO” means Purchasing Order.
WPS The term “WPS” means Welding Procedure Specification.
WPQR The term “WPQR” means Welding Procedure Qualification Record.
NDT The term “NDT” means Non- destructive testing.
VT The term “VT” means Visual testing.
PT The term “PT” means Penetrant testing.
CI The term “CI” means Control Instruction.
ECN The term “ECN” means Engineering change note.
FCS The term “FCS” means Factory control system
The base material shall have the heat/charge number stamped with soft
nose, or painted onto each plate or profile, to ensure traceability.
5.2.2. Use of The use of alternative material must be in accordance with the Appendix
alternative grade 3
and quality
5.3. Manufacturing process
5.3.1. Cutting If plasma or water-jet cutting is used, the edges shall be ground clean to
remove any traces of impurities. The area shall be ground flush to match
the required geometry.
5.3.2. Grinding. All grinding discs shall be those designed specifically for aluminium and
o de-burr to radius 2 mm
o chamfer to 2x1,5x22,5°
5.6.1.1. Sequence for The sequence for performing NDT shall be:
performance of • Visual Testing (VT)
NDT. • Penetrate Testing (PT)
•
5.6.1.2. Requirement to EN 12062 must be used for determination of examination techniques and
examination their acceptance levels for VT and PT.
techniques
6. Modifications
6.1.1. PS 1005341- First issue.
30201
The WPQR can not be split up into the used processes, and then qualify a
WPS on each process.
1.1.1.9. Verification of The welding of the welding procedure test pieces must be verified by an
welding WPQR. external third party that will be responsible for ensuring that the correct
welding parameters used during the welding are transferred to the WPQR
– documentation. Furthermore, the third party must verify that all non-
destructive and destructive tests are performed in accordance with the
relevant standards, and conclude whether the test results are in
accordance with the requirements stated in this section.
5754 (H114) 5754 (H114) 3.3535.26 AlMg3 five bar Quintet 5/7 alu
(F24)
*1 on the drawings where material is written as EN 6060/63, bought base materials can be use.