Estimated bill cost of construction from start to dpc(1.5m)


Total number of wall = 257.360m

Total number of partition = total wall


3.6m
= 257.360 = 71.5partitions
3.6m

Cost of excavation = 3500x71.5 = 250,250+ 5%error = 5/10 x250, 250.00


=12,512.5 Total =N262,762.5 this is because of rocky topography

Cost of excavating column = 800x66= N52,,800

For Rod=Y16 or 16mm=72psc (2.1m)

Steel rope 8mm rod 1½ each = 1.5 x 66 lengths = 99 lengths

For basket = 12mm Rod = 13/4 x66 = 83lengths

Binding wire 2 bundles

Cost of labour iron work = 66 pillars = 66x700 N46,200

Basket= 600x66=N39,600

Cost of curing 3 trips = N68,000.00

Casting of base = total bags of cement at the ratio of 1:6:8 = 210bags =


190+20error

Cost = 700x210 = N147,000.00


Cost of block work to dpc

Total block = 40psc x 71.5 = 2,860blocks

Cost of block work = N40x2860 = N114,400

Carpintary work = cost of covering each column =600X66 = N39,600

Cost of casting pillars = 66bags = 700x66= N46,200

Fillings = negotiable = N80,000

Chaining beam = iron bender 71.5x600 = N42,900

Carprintery = 600x71.5 = N42,900

Casting of beams 63bags = 63x700 = N44,100

German floor
Germen floor = carpentry blasing = N30,000

Casting of germen floor Total area = 29,781x11, 322= 337.181m 2

Therefore 12.96=8bags

337.181 = x

208.1361 + 20error

228.1361bags

Labour

700x228 = N159,600

Cost servers for general work = N105,000

Total cost =

262,762.5+52,800+46,200+39,600+68,000+147,000+114,400+39,600
+46,200+80,000+42,900+42,900+44,100+30,000+159,600+105,000

Total = N1,280522.5
Error expectance/unforeseen event 10% = 10/100x1,107,100 = N110,710

Total labour cost to German floor 1,280522.5+ 110,710 = N 1,391,232.5

Handling Cost = N220,000.00 negotiable

Grand Total = 1,391,232.5+220,000 = N1,611232.5