Measurement Sheet for 10.

0 mtr
note: this qty work out for 10.0 mtr but we want 20 mtr so I m doing a multiplication by two with 10.0 mtr qty.
ESTIMATE FOR THE SLAB CULVERT OF M/S.Indsur global ltd.

Sr.No. DESCRIPTION NO L B D QTY. UNIT


(1) Excavation for found.
Upto 1.50mt.depth
(a) up to 1.50 m. 1 12.00 2.98 1.15 41.12 Cu mt.
2 2.50 2.98 0.30 4.47 Cu mt.
91.19 Cu mt.
say 91.19 Cu mt.

(b) Dismentling the 1 7.00 2.98 0.30 12.52 Cu mt.


existing road say 12.52 Cu mt.

(2) P.C.C. (1:4:8) 1 10.00 2.98 0.15 8.94 Cu mt.


say 8.94 Cu mt.

(3) Bk. Masonry (1:6) 2 10.00 0.57 0.35 3.99 Cu mt.


" 2 10.00 0.45 0.25 2.25 Cu mt.
2 10.00 0.35 0.30 2.10 Cu mt.
Parapet 2 2.24 0.23 0.45 0.46 Cu mt.
17.61 Cu mt.
say 17.61 Cu mt.

(4) Form Work


(a) Coping 2X2 10.35 0.15 - 6.21 sq. mt.
(b) Slab bottom 1 10.00 1.54 - 15.40 sq. mt.
Slab sides 2 10.00 0.25 - 5.00 sq. mt.
2 2.24 0.25 - 1.12 sq. mt.
55.46 sq. mt.
say 55.46 sq. mt.

(5) R.C.C. (1:1.5:3)


Slab 1 10.00 2.24 0.25 5.60 Cu mt.
Coping 2 10.00 0.35 0.15 1.05 Cu mt.
13.30 Cu mt.
13.30 Cu mt.

(6) Plaster (1:4)(I/S 15 mm) 2 10.00 1.05 - 21.00 Sq mt.


U/S & D/S walls 4 0.35 0.45 - 0.63 Sq mt.
4 0.45 0.30 - 0.54 Sq mt.
4 0.57 0.30 - 0.68 Sq mt.
Slab side 2 0.25 2.24 - 1.12 Sq mt.
Parapet wall
Long side 2x2 2.24 0.45 - 4.03 Sq mt.
Short side 2x2 0.35 0.45 - 0.63 Sq mt.
Top 2 0.35 2.24 - 1.57 Sq mt.
60.41 Sq mt.
Say 60.41 Sq mt.
(7) Bottom IPS 1 10.00 1.50 - 30.00 Sq mt.
Say 30.00 Sq mt.

(8) Vata 2 10.00 - - 20.00 Rmt.


2X2 0.45 - - 1.80 Rmt.
43.60 Rmt.
Say 43.60 Rmt.

(9) Reinforcement
16 mm dia. 81 2.70 (= 218.70 x 1.6 Kg) 349.92 Kg.
8 mm dia. 16 10.00 (= 160.00 x 0.40 kg) 64.00 Kg.
8 mm dia. 8 8.00 (= 64.00 x 0.40 kg) 25.60 Kg.
10 mm dia. 8 10.00 (= 80.00 x 0.62 kg) 49.60 Kg.
8 mm dia. 136 0.90 (= 122.40 x 0.40 kg) 48.96 Kg.
1076.16 Kg.
Say 1076.16 Kg.

(10) Earthfilling
Excavated qty.
46.00+6.30=52.30 46.00 + 6.30 = 52.30 mt3. 52.30 cu mt.
Deduction :
P.C.C (-) - - - -4.50 cu mt.
Masonary (-) - - - -8.34 cu mt.
Slab (-) - - - -6.65 cu mt.
Below Slab Space -1 10.00 1.50 1.05 -15.00 cu mt.
(-) -34.49 cu mt.
17.26 cu mt.
Say 17.30 cu mt.

(11) Rubble Solling 2 5.00 0.40 0.30 2.00 cu mt.


Say 2.00 cu mt.
n by two with 10.0 mtr qty.
SLAB CULVERT.

BILL OF QUANTITIES FOR SLAB CULVERT FOR PROPOSED


FACTORY PROJECT FOR J B SPICES AT KURALI.
SR. ITEMS QTY. RATE UNIT AMOUNT
NO. Rs. Ps.
1 Excavation for foundation upto 1.5 M.
depth including sorting out and stack-
ing of useful materials and disposingof
the excavated studd up to 50 M.lead.
(a) Loose or soft soil 91.19 180.00 Cu mt. 16413.84

2 Providing and laying cement concrete 8.94 4200.00 Cu mt. 37548.00


1:4:8 (1 cement : 4 coarse sand :8hand
broken stone aggregates 40 mm
nominal size) and curing complete
excluding cost of form work in :(a)
Foundation and plinth

3 Brick work using common brunt clay 17.61 4200.00 Cu mt. 73950.91
building bricks having crushing strength
not less than 35 Kg./Sq..Cm.in
foundation and plinth in cement mortar
1:6 (1 cement : 6 fine sand)(b)
Conventional

4 Providing and laying cement concrete 13.30 8500.00 Cu mt. 113050.00


work 1:1.5:3and curing complete
excluding cost of form work and
reinforcement for reinforcement
concrete work in; (C) Slabs, Landing
shelves,Balconies, Lintels, Beams,
Girder and Cantilever upto floor two
level. Uptofloor two level.scaffolding
curing and finishing complete.

5 Providing 20 mm. thick cementplaster 60.41 420.00 Sq. mt. 25371.36


in single coat on rough sideof single or
half Brick wall for interior plastering
upto floor two level finishedeven and
smooth in :Cement mortar 1:4(1
cement : 4 sand)

PAGE NO:4
SLAB CULVERT.

6 Providing and laying cement concrete 30.00 520.00 Sq. mt. 15600.00
flooring 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregates20
mm. nominal size) laid in one layer
finished with a floating coat ofneat
cement(A) 40 mm. thick

7 Providing cement vata (10 cm x 10cm 43.60 110.00 Rmt. 4796.00


size) quarter round in cement mortar
1:1 including neat cement finishing
watering etc. complete.

8 Providing and Placing in position 1076.16 55.00 Kg. 59188.80


H.Y.S.D. bar reinfor cement including
cutting bending hooking and tying
complete as per detailed drawing for
(A) Solid slab.

9 Filling available excavated earth 17.30 100.00 Cu mt. 1730.00


(excluding rock) in trenches, plinth,
sides of foundations etc. in layernot
exceeding 20 cm. in depth
consolidating each deposited layerby
ramming and watering.

TOTAL AMLOUNT Total 347648.91