Sei sulla pagina 1di 12

Recommendations by CII

for Cement Plants

Electrical Energy Consumption

Section / Equipment Electrical energy consumption


(in units / ton of cement)
Mines, crusher & stacking 1.5

Reclaimer,grinding & transport 18.0

Kiln feed, kiln & cooler 22.0

Coal mill 5.0

Cement grinding & transport 23.0

Packing 1.5

Lighting, pumps & services 4.0

Total 75.0

Electrical energy consumers

Mines & Crusher

The first step in the cement manufacturing process is the mining of limestone. Mining
has conventionally been with compressed air drilling and subsequently blasting with
explosives. The surface miner has been developed primarily for mining in locations,
which are located close to human inhabited areas. This equipment has proved to be
so useful that, they are fast replacing the conventional mining systems.

In one of the new plants, a surface miner was installed and the mining energy
consumption (compressors) was avoided. The size of the limestone mined is also
lower, resulting in reduction of crushing energy consumption to 0.5 units / ton of
cement, as against 1.5 - 2.0 units / ton in conventional plants. The surface miners
are presently available for medium limestone. Hence, wherever possible, the surface
miner can be installed for achieving energy saving. The operation of surface miner is
also environment friendly, with less dust & noise generation.

Hence, consider application of surface miner for soft and medium hard Limestone.

The next step in the cement manufacturing process is the crusher. The choice of
crusher type depends on the grindability and the type of down-the-line grinding
system.
Typically, for a VRM system/ball mill with roll press system, it is recommended to
have a single stage hammer crusher, with a high efficiency screen before the
crusher.

Install single stage hammer crusher with high efficiency screen.

The other points to be taken care during the design stage are the additional auxiliary
power consumption. The auxiliary capacity and controls should be designed, such
that, the idle power consumption is avoided during operation of the crusher.

  Per ton of Limestone Per ton of


Cement
Target power consumption for
the crusher 1.0 unit 1.5 unit
(for medium hard limestone)

Transportation of Limestone
The transportation of the mined limestone to the crusher is normally done through
dumpers or trucks. In case of mountainous terrain, the ropeways are installed. The
detailed life cycle cost analysis of transportation with dumpers & ropeway indicates
that, the ropeway is more beneficial in some cases, where the distances are more
than 5 kms. The ropeway calls for higher investment, but the operating costs are
much lower. In one of the operating cement plants, the ropeway was installed
replacing the dumpers for transportation of limestone from the mines to the crusher
in the plant, resulting in substantial benefits. The option of installing a rope-way can
also be considered at the design stage.

Hence, consider installation of rope way for limestone transportation, where the
distances are more than 5 kms.

Pre-blending system

The pre-blending system plays a vital role in providing a uniform feed to the raw
mill. The statistics of the performance of the pre-blending stockpiles in various
operating cement plants in the country indicate that, the longitudinal stockpile has a
better pre-blending efficiency.

Hence, it is recommended to install a longitudinal pre-blending system.

In locations where the


1. Rain-fall is more
2. Raw material is sticky in nature

it is recommended to install closed stockpiles. This will help in avoiding feed failure
to the raw mill during the monsoon / rainy seasons.

The target operating pre-blending efficiency should be 10.

Raw mill

The raw mill is a major energy consumer and should be designed based on the
grindability and moisture of the limestone available. The Vertical Roller Mill (VRM)
has at least 30% lesser power consumption, than the comparable ball mill system.
Hence, for upto medium hard limestone, the VRM should be the first choice.
Wherever the moisture percentage is also higher, say >15%, VRM should be the first
choice. Only in case of very abrasive raw materials or raw materials with higher free
silica content, the plant can consider installing a closed circuit ball mill, with a pre-
grinding system.

The VRM (wherever the design allows), should be installed with a reject handling /
mechanical re-circulation system, to ensure lower pressure drop across the mill.

The energy efficient alternative therefore is to install a VRM with mechanical re-
circulation system.

The other aspects to be taken care are

Conveying system - only mechanical conveying systems such as, bucket


elevators/belt conveyor should be installed

Classifier - dynamic high efficiency classifier ( cage type classifier ) should be


installed

Mill inlet sealing - This is very essential, since majority of air infiltration in an
operating plant is through the inlet. The present day plants use either rotary / triple
gate seals for the mill inlet. These seals though effective in the initial days, start
developing leaks over a period, demanding regular maintenance.
In one of the new plants, a material seal at the VRM has been attempted with
satisfactory results. Hence, it is better to strongly consider installation of material
seal or reliable triple gate/rotary seals at the design stage itself
High efficiency mill internals (for ball mills)

In the case of ball mills, the present trend is to replace existing mill internals with
high efficiency internals (grinding media, liners and diaphragms). This has the
following advantages

Higher mill output

Less wear

Lower power consumption (up to 5% reduction is expected)

Lesser maintenance

Hence, all the new plants installing ball mills, should prefer high efficiency mill
internals.

Target power consumption of (VRM) 18 units/ton of cement


for medium hard limestone (or) 11-12 units/ton of limestone

Fans in raw mill

The fans are the major power consumers, next only to the main drive in the raw mill
section and hence need attention during the design stage. The major power
consuming fans are the raw mill fan and the vent ESP/BH fan (with kiln).
The fans should be high efficiency (> 80%) backward curved fans with variable
speed controls.

The typical variable speed mechanisms proposed are


Variable frequency drive (VFD) - up to 250 kW LT drives.
RRC, fluid coupling, SPRS (HT only) - in increasing order of energy efficiency.

The best variable speed systems are VFD for all LT fans and SPRS for all HT fans.
The other major decision, whether to adopt a 3-fan system or 2-fan system, should
be carefully weighed and taken at the design stage itself. The various conditions and
the corresponding decision making table is given below

Operational Three Fan System Two Fan Systems


Characteristics
Entire PH air passes through Not Will serve
the VRM and no flow of air Advantageous the purpose
through by-pass
Higher power
Part of PH air is passed Advantageous consumption
through by-pass always

P/H fan/ESP fan operates Advantageous Higher power


with damper throttling when and lower power consumption
R/M is stopped and expected
R/M stoppage say >25% of
time

The other major decision is to decide the excess margin for the fans. The closer the
operating point to the design point, the higher will be the efficiency of the fan.
However, a safety margin is required to meet the contingency requirements.

The fans are to be designed typically with 15 % margin over the operating condition.

Raw mill and kiln main dust collection system

The Electro Static Separator (ESP) has been conventionally used for collecting the
dust in the kiln and raw mill circuits. The operating efficiency of the ESPs are
normally around 99.5 %. The operation of the ESP also depends on the CO content
of the flue gas. Whenever the CO content goes beyond 0.6 %, the ESP trips. The
amount of time the tripping occurs is less; it nevertheless, leads to particulate
emissions. With the increased emphasis on the environmental regulations, it is
necessary to have a dust collection system, that is say 99.9 % efficient and operate
continuously.

The present trend has been to install bag houses for the kiln and raw mill exhaust.
The comparisons of the ESP and bag house are as below

1. The bag house has a pressure drop of about 150 mm Wg as against 20 - 40


mm Wg in the ESP. Hence, the power consumption of the exhaust fan is
higher.
2. The ESP trips, whenever the CO content goes beyond 0.6 %, while the
operation of the bag house is not dependant upon the CO value.
3. The collection efficiency of the bag house is much higher at 99.9%, while that
of the ESP is marginally lower. However, presently ESP's with efficiencies of
99.9% require higher investments.
4. The ESP requires conditioning with power consumption for the GCT pump and
screw conveyors.
5. The GCT in the ESP system needs water for conditioning, while the bag house
does not need water.

Hence, at the design stage itself, the decision to install the Bag house or ESP has to
be taken, after carefully weighing the above aspects.

Blending and homogenisation

This is a very important operation having a major bearing on the operation of the
kiln and the thermal energy consumption of the kiln. The comparisons of the
effectiveness & energy efficiency of various systems indicate that, the continuous
blending & storage system is more efficient.

Hence, it is recommended to install a continuous blending & storage system. The target
blending efficiency should be 10.

Kiln and pre-heater

Kiln feed conveying

Kiln feed conveying should be carried out by mechanical bucket elevator, as


pneumatic conveying is more energy consuming and also adds false air to the
system. The pneumatic conveying system consumes about 1 unit / ton of kiln feed,
as against 0.25 units / ton of kiln feed for a mechanical conveying system.

Hence, it is recommended to install a mechanical conveying system.

Pre-heater - stages & sizing

The more the number of stages in a preheater, the higher the thermal efficiency of
the system.

In the older plants, the conventional cyclones offer a pressure drop of 550 to 600
mm wg resulting in higher power consumption of the pre-heater fan. Presently low-
pressure drop cyclones, having a pressure drop of 380 - 420 mm wg are available.
With the installation of these low pressure drop cyclones, it is possible to achieve a
pre-heater fan power consumption of about 6 units / ton of clinker, as against the
present consumption of more than 8 units / ton of clinker. The target pre-heater fan
air flow capacity should be below 1.8 Nm3/kg of clinker.

The margins in all the sections of the plant, also influence the energy efficiency of
the plant. It is recommended that all the equipment in the pre-heater system, be
designed for a kiln loading of 5 ton/m3/day.

Coal conveying system


The coal after grinding in the mill, is conveyed pneumatically to the kiln & calciner for
firing. Generally, identical conveying equipments are used for both calciner and kiln.
The coal fired in the calciner is about 50 % more than that fired in the kiln.
Correspondingly, the capacity of the conveying system and the blower are lower for
the kiln firing. The installation of a lower capacity conveying system, reduces the
quantity of the ambient air entering the kiln. This increases the secondary air by an
equivalent quantity, resulting in increased thermal efficiency. Hence, by design
separate right capacity conveying systems should be installed for kiln & calciner.

Install separate right capacity coal conveying system for kiln & calciner .

Water sprays

Water spray systems can be installed, particularly in cooler vent, pre-heater outlet or
other areas, where further utilisation of heat is not required. The volume of the gas
can be reduced by spraying of water, which ultimately results in reduction of fan
power consumption. Presently, water spray systems, which can reduce temperature
by more than 100oC in a small area, are available. These systems can aid in
reducing the power consumption of the exhaust fans.

GCT water pumps

Water is sprayed in GCT (located before R/M or in the by-pass line) through high
pressure pumps. The capacity of pumps required depends on the operation of raw
mill and coal mill. The water requirement will be maximum, when none of the hot air
users are in operation. The water requirement will be least, when all hot air users are
in operation. Hence, it is better to install pumps of different capacities to suit both
the different requirements.

Install two GCT pumps of different capacities to meet the raw mill operation and
stoppage condition.

Coolers

The cooler is a critical equipment used for cooling and also to recuperate the heat
back into the kiln system. This has a major bearing on the thermal efficiency of the
system. This is being dealt with in Section-5.4. The cooler is also a major consumer
of electrical energy. The major energy consumers are the cooler fans.

It is recommended to install high efficiency backward curved fans for cooler, with
Variable Frequency Drives (VFD) for all the fans.

Target energy consumption - 5 units / ton of clinker

Coal section

The coal is generally procured from the coalfields through rail or road, crushed,
ground to fine powder and then used in the mill. The coal receipts vary in quality
continuously. Hence, it will be better to install a longitudinal pre-blending stockpile
for coal also. The installation of pre-blending stockpile for coal will ensure uniform
quality of coal feed to the kiln.

Install pre-blending stockpile for coal.


The coal mill is also a major energy consumer. Presently, majority of the coal mills
are air-swept ball mills. The VRM has been installed in some of the modern plants,
with at least 40% lower energy consumption, in comparison to the conventional air-
swept ball mills, used in older cement plants. Hence, it is recommended to install
vertical roller mills for coal grinding.

Install VRM for coal grinding.

Fine coal bins

The calciner can accept coarser coal, in comparison to the kiln. Hence, it is
recommended to have separate fine coal hoppers, for kiln coal and calciner coal. This
will enable differential grinding of coal for calciner & kiln.

Install separate bins for calciner and kiln.

Fans in kiln & coal mill

The fans are major power consumers in the kiln and pre-heater system. Hence, by
design the fans should be of higher efficiency (>80%) and equipped with a variable
speed mechanism for speed control. The typical variable speed arrangements for the
fans in the kiln and coal mill sections are as below

Fan Type of variable speed drive (VSD)

P H fan SRPS/GRR/LRS

RM fan/ESP fan SPRS/GRR/LRS

Cooler vent fan SPRS/DC/Fluid coupling/ GRR/LRS

Cooler fans VFD


Coal mill fans
VFD/GRR (or) fluid coupling for HT

The VSDs are given in the order of reducing efficiency.

Cement mill

The cement mill is another major energy consumer in a cement plant. In the present
operating plants, majority of the cement mills are open circuit ball mills. In some of
the plants, closed circuiting has been done, to increase the capacity & reduce the
energy consumption. The installation of the pre-grinding system, has also been
taken up in some plants, with substantial benefits. Recently, the VRM has also been
installed for grinding of cement in three cement plants in India. The results reported
by one of the plants (23-24 units/ton of OPC-43 grade) is very encouraging.

Hence, every new plant should go for either a VRM or a ball mill with pre-grinding
system & high efficiency separator.

The VRM should have a high efficiency separator and mechanical re-circulation
system. The ball mill if installed should have high efficiency internals (grinding
media, liner plates, diaphragm). The conveying of cement to the silo should be
through a mechanical conveying system.

Utilise mechanical conveying for cement.

Target power consumption for OPC - 43 grade cement are as follows

VRM - 23 units / ton of cement


Ball mill with roll press - 27 units / ton of cement
Ball mill ( closed circuit ) - 29 units / ton of cement

Cement silo and packing plant

The cement silo should have a blower extraction system, to reduce the power
consumption. The packing should be through an electronic packer, for accurate
weight and reduced energy consumption.

Target power consumption - 1.5 units / ton of cement

Thermal Energy Consumption


The thermal energy contributes nearly half of the energy cost in a cement plant. The
major consumption is the fuel used in the kiln. The other thermal energy consumers
are
1. Coal furnace - Used for drying of coal in some plants
2. Raw mill furnace - Used for drying of raw meal during starting of the plant
3. Cement mill furnace - Used in some plants for drying of slag

The major aspects which affect the thermal energy consumption in a cement plant
are listed below.

Pre-heater - stages & sizing

The number of stages in the pre-heater system has a major bearing on the thermal
energy consumption of the kiln.

The more the number of stages in the preheater, the higher the thermal efficiency of
the system. Presently, it is recommended to install a 6-stage / 5-stage pre-heater
system. One additional stage, will on one hand reduce the thermal energy
consumption by 10 - 15 kcal / kg of clinker. On the other hand it increases the pre-
heater fan power consumption by 1 unit / ton of clinker. The net benefit is to be
quantified before taking the decision. It is also important to note that, the pre-heater
outlet temperature reduces by about 25oC, when an additional stage is added. This
reduces the heat available for drying the limestone and coal. This aspect also has to
be borne in mind, while deciding the number of stages in the pre-heater.

Target specific thermal energy consumption - 715 kCal / kg of clinker


Pre-heater - monitoring

The continuous monitoring of the pre-heater is very essential, to maintain the pre-
heater system leak proof. Hence, it is recommended to install oxygen and CO
analysers at the kiln inlet, pre-heater outlet to enable continuous monitoring of the
system.

Kiln - inlet & outlet seals

The inlet & outlet seals of the kiln are important, as it helps reduce the air infiltration
into the system. The inlet seal is more important, as the infiltration chances are
higher. Based on the experiences of the Indian cement plants, recommend installing

1. v Pneumatic seal for kiln inlet


2. Spring loaded mechanical seal for kiln outlet

The pre-heater flanges, poking holes & inspection holes are all potential sources of
leakage during operation of the plant. Hence the number of flanges should be
reduced to a bare minimum. The inspection & poking holes in the pre-heaters should
be provided with air tight covers, so that, the air infiltration into the system is
minimum.

Coolers

The cooler is a critical equipment used for cooling and also recuperate the heat back
into the kiln system. In majority of the existing plants, conventional grate coolers are
being used. These coolers have lower recuperation efficiency, occupy more space &
need more cooling air. The latest high efficiency coolers, have higher recuperation
efficiency, need lesser cooling air, are compact in size and has lower radiation loss.
The typical comparison of a conventional cooler and a high efficiency cooler are as
below.

Parameters Units Conventional High


cooler efficiency
cooler
Loading ton/m2/day 35 50
Nm3/kg of 2.2 1.8
Cooling air
Clinker
Cooler vent Nm3/kg of 1.0 0.6- 0.8
air Clinker
TA 800 - 900 950 - 1050
deg C
temperature
units / ton of 5 5
Power cons.
clinker

Typically, the high efficiency cooler can reduce the thermal energy consumption by
30 - 40 kCal/kg of clinker.

Hence, it is recommended to install a high efficiency grate cooler at the


initial stage itself.

Wherever possible, the cooler exhaust air should be used for raw material
drying/coal drying/slag drying.
The cooler should also have an ESP/bag house for collection of clinker dust.

Burners

The burner system also plays a vital role, in determining the thermal efficiency of the
system. The present operating burners operate with, a primary air ranging from 12%
- 18%. The latest trend is to install multi-channel low primary air burners. These
burners have the following advantages

Lower primary air requirement (7 - 8%)


Sharper and shorter flame
Better flame control

In an operating plant, the replacement of a conventional burner with a new burner (7


% primary air, including conveying air) resulted in reduction of thermal energy
consumption by nearly 15 kCal / kg of clinker.

Hence, it is recommended to install a high efficiency low primary air burner.

Refractory lining - kiln, pre-heaters & coolers

The refractory lining in the kiln, pre-heaters & coolers are very vital for conserving
thermal energy within the system and protect the outside supporting metallic part.
The older systems used to utilise all along only high alumina bricks. The present
trend is to install basic bricks in the kiln, which have comparatively higher life
(more than twice) and lower consumption. Since this reduces the stoppages of the
plant, the run factor of the plant improves, resulting in lower thermal and electrical
energy consumption. In all other areas of the pre-heaters and the cooler, it is
recommended to install alumina bricks (30 - 40%), preceded by insulation
bricks.

Other energy efficiency aspects

The other miscellaneous energy efficiency aspects, which need to be taken care in
the design stage, are listed below

1. The bag filters & de-dusting fans distributed over the entire plant consume
about 2 -3 % of the over-all energy consumption. These fans should be
designed, based on the individual user requirement and not from the point of
standardisation. The typical de-dusting air requirements for different
applications are given below
Equipment De-dusting air quantity
Hammer crusher 100m3/hour/ton
Bucket elevators 1800m3/hour/m2 of BE cross section
Pneumatic conveyor Conveying air + 50 %
Air slides Air supplied + 20 %
Cement packers 2000 m3/hour/spout
Bins section 4000 m3/hour/m2 of bin cross

2. It is always better to have individual dedicated package compressor, for the


individual bag-filters. This will help avoid long compressed air lines &
minimise leakages. The small compressors are 'ON/OFF' types, while the
bigger compressors are controlled by loading/unloading machanism. Hence,
the installation of smaller dedicated compressors for individual bag filters, will
ensure energy efficiency. We recommend installing separate small package
compressors for individual bag filters.
3. The rating of motors should be done, such that, the motor operates at higher
loading factor, say more than 80 % during the normal operation. The safety
margins of the motors, should be discussed with supplier in detail, to avoid
under loading of the motor during operation. Wherever the starting load
decides the motor capacity, it is recommended to install soft starters, to take
care of the starting torque.
4. The transmission of power from the prime mover to the driven equipment
should be 'Direct' as far as possible. Wherever a belt drive is required, it is
recommended to install a flat belt drive.
5. Installation of LED's for indication lamps. Presently filament lamps are being
used for the indication purposes. The LED lamps can be installed in place of
filament lamps, with reduced energy consumption & longer life.

Electrical systems

Lighting system

In a cement plant, lighting consumes between 1 - 1.5 units / ton of cement,


depending on the extent of lighting. There is a good potential to save energy in
lighting system by optimising the system voltage. This can be achieved by having a
separate line and transformer, so that the lighting voltage can be regulated and
maintained at about 210 V. At the design stage itself, a cement plant should install
only energy efficient lighting as below
1. HPSV lights for plant and outdoor lighting
2. Fluorescent tube lights with electronic chokes and compact fluorescent lamps
( CFL ) for inside lighting

Electrical distribution

The electrical distribution should have an auto PF control system and an 'on-load' tap
changing facility for the main transformer. The auto PF control system will aid in
maintaining high PF on a consistent basis. This will enable consistent PF and better
demand management of the plant.

The 'on-load' tap changing facility of the main transformer, enables maintenance of
the optimum voltage as required by the system. The optimum voltage helps in
operating the motors at higher efficiency.

Generators

The oil fired generators are also being installed to supply power to the plant during
power failures.

The generators should have the facility of operating in parallel with the grid. The
facility should be such that, the kiln continues to operate, even when the grid power
fails.
These generators should have the following facilities
1. Operation with multiple fuels
2. Waste heat recovery systems, which can be used for generator oil heating.
The waste heat can also be used for meeting the plant A/C load by installing a
vapor absorption refrigeration system.

Potrebbero piacerti anche