NOC for Controlled Blasting for excavation

Name of
Approval/Noc/License NOC for controlled blasting for Excavation
/Registration
1. Competent Authority Revenue Department
2. Stage Pre-Commissioning Stage
3. SLA/ Number of Days 60 Days (As per Citizen Charter)
Resident Deputy Collector of every district office across Maharashtra State
4. Details of the HoD Refer Annexure-III for detailed list of district offices and their contact details

5. Department Refer Annexure-III for Telephone number for District Collector office of every district across
Tel. No. / Toll free No Maharashtra
6. Website & eMail Website – Refer Annexure-III for Web URL of District offices across Maharashtra
7. Approving Authority  Resident Deputy Collector (District Office)
Every application shall be accompanied by
 Area Map
 Latest copy of 7/12
 Lease or Rent Agreement from applicant if land ownership in not with him
8. Supporting Documents  NOC from Gram Panchayat/BDO
Required  Location Plan of the Area
 Work-order & Sub-contracting agreement ( If applicable)
 Short Firer License copy
 Explosive License copy
 Explosive Transport License copy

9. Fee & Mode of  Court Fee Stamp of Rs. 5/- needs to be affixed in the application.
Payment  No fees is required for controlled blasting NoC
 Refer to Annexure III – Region and District wise Offices details for form submission
10. Form Submission at
based upon the location of the applicant
 Duly filled form (Please check sample filled form attached in Annexure-II)
 List of supporting documents as per point no. 8 that needs to be submitted at the
11. Criteria for acceptance time of application submission.

12. Special Conditions/Remarks:

The NOC is issued subjected to the following conditions:

1. The blasting operations should be carried out only between sunrise & sunset
2. The explosives to be transported through explosive vans from magazine to the blasting site. After the blasting
operation is over, the balance explosives should be returned to the magazine before sunset.
3. The blasting operation should be carried out with the help of approved blaster holding valid Shot Firer Permit.
4. Before carrying out the blasting operation the nearest police station should be informed.
5. The applicant will be responsible for damage of public lives and property any wilful conduct or negligence
occurs.
6. This NOC is issued on a condition to obtain a necessary permission from Dy. Chief Controller of explosives &
Maharashtra Pollution Control Board if required.
13. Annexures:
 Annexure I- Application Form: Application form which needs to be submitted on plain paper with required
supporting documents at the local distinct office of the applicant
 Annexure II- Sample Filled application form: Filled form incorporating necessary details mentioned in the
application form
 Annexure III- Region and District Wise offices with details for form submission: Region and District wise Offices
details for form submission based upon the location of the applicant in Maharashtra
 Annexure IV- Frequently Asked question (FAQs) for NoC to be given under The Explosives Act 1884: Frequently