Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Photograph 3
Hydrocracker area looking
east
surge
I Recycle
waxy
residue
1 Light products (LPG, spirit, kerosene, oils)
through other effects such as 52 With respect to (c) and (d), HSE were
vibration. alerted by the refinery management that
there had been alteration of some
(d) accidental overpressurisation.
instrument settings before security was
51 The investigation involved: fully established around the accident
location. The accounts given by some
(a) Recovery and metallurgical operators did not and still do not tally
examination of vessel fragments on with the physical evidence. It was not
which ballistic calculations were possible to establish unequivocally from
based. the operators' evidence the sequence of
(b) Recovery and examination of fire events which resulted in the explosion.
damaged components. The investigation therefore attempted to
reconstruct the physical conditions
(c) Examination of control room necessary to account for the incident.
instruments and records.
(d) Interviewing operating and 53 The normal operating pressure for
management staff. V306 was 9 bar (135 psig), its design
Fig 9 Refinery plan showing location of hydrocracker explosion and debris, and location of flare line incident
Photograph 5 Fragment
from LP separator; distance
340 metres
Photograph 6 LP separator
end section projected
75 metres over control room
building
pressure 10.7 bar (160 psig) and its test had grown rapidly from the origin in two
pressure 21.6 bar (324 psig). It had a opposite directions, in a predominantly
single pressure relief valve with an orifice brittle manner, consistent with fracture
area of 18 cm2 and a relief capacity to under high strain rate conditions at a
flare of 12.25 tonnelhour, sufficient to temperature near the impact transition
cater for overpressure from fire temperature of the material in this
engulfment. There was no evidence to thickness. On a plant of this type it is
suggest that this relief valve was not foreseeable that fluid transfer could set
operating effectively at its set pressure of up vibration effects giving rise to high
10.7 bar (160 psig). transient strain rates. At operating
temperatures well below normal a vessel
54 The fragments of V306 were located, subjected to these vibration effects could
weighed and their positions logged. The have failed.
explosive forces were calculated using
ballistic techniques based on fragment 57 However the other evidence strongly
trajectories which confirmed that rupture suggested that there had been a
was caused by over-pressurisation. The breakthrough of high pressure gas from
results correlated well with the calculated V305 to V306 leading to
theoretical burst pressure of 50 bar overpressurisation of the vessel. The
(750 psig). Blast damage established that liquid in V305 had drained away through
the force of the explosion was equivalent an output flow control valve when the
to approximately 90 kg of TNT. hydrocracker was being held on standby
operation with no product passing,
55 The overwhelming weight of evidence thereby allowing high pressure gas to
from blast damage, ballistics and break through. Fig 10 shows a single
metallurgical examination pointed towards 300 mm diameter outlet pipe from the
internal overpressure of V306 applied in a bottom of V305 which split into two
single event. Nevertheless other parallel streams each with a separate
possibilities of vessel failure, as set out flow control valve. The valve nearest V305
in para 50, were also considered by was the right-angled, air-diaphragm-
detailed examination of the plant, plant operated valve LIC 3-22 which could be
records and eye witness accounts. There operated from the control room either in
was no indication of an external initiating automatic or manual mode. Some
event such as sabotage. An internal distance from V305 was the air-
explosion or ignition occurring within diaphragm-operated, straight-through flow
V306 was considered. This would have control valve HIC 3-22, which could only
required the presence in the vessel be operated via a manually applied
system of both oxygen and a source of control signal from the control room.
ignition, and the possibility was
eliminated not only by detailed 58 Fig 11 shows the LIC 3-22 and HIC
consideration of the process conditions 3-22 valve control system. A pneumatic
and controls, but also by evidence from diaphragm assembly opened each valve.
vessel fragments. On removal of air pressure the valve was
closed by a spring. Its position was
56 The possibility of mechanical failure selected by a control unit from which an
for reasons other than simple electrical signal passed to an IIP
overpressure was considered. The (electrical currentlair pressure) converter.
metallurgical evidence established that A pneumatic signal was then sent to a
the origin of the failure was in the heat positioner unit at the valve. By this means
affected zone of a saddle weld on the air pressure was applied to the
underside of the vessel at the east end diaphragm. Two hand-wheel-operated
near the support plinth. There was no valves (SP25) in series provided a manual
indication of pre-existing defects nor of a by-pass to the control valves. One was
progressive mode of failure on any part of found open but the other was shut and
the fracture surface examined. Cracks found to be gas tight. Gas breakthrough,
Recycle hydrogen
to C301 compressor
Gas
A -& Uc3-22
r------l
l
I
I
I
!l 1L I To Amtne plant
Bypass Pressure control l
Plc 3-73
Nucleon~c
SP25 SP25
!I rl Float
gauge
LP separator V306 -1
I
I
l
Ltqutd
II
1r 1r r---------- J
II la
4- FIC 3-21
h f,ct10nator
F--'
Sour water
- d
'\
&
0 ,,c322
controller
lip
converter Pos~t~oner Dump
solenold
0
-
fi
d
Low alarm
for
W ~LIC
d~sconnected
r l n 3-22
g
t o s o valve
l e n o ~was
dd u m p
Audlble Vlsual
Relay unit
Extra low
alarm
Audible Visual
30
%
chart 20
indication
10
40
B,
30
V
LP Separator (V3061liquid level
%
Chart 20
indication
10
float gauge
1
f Zero offset
80
%
Chart O'
indication
HP Separator (V3051Pressure
60
-
,h I I I I
l a s breakthrough -O6OohrS -0500hrs -0400hrs -0300hrs
Explosion
t
Shift changeover
Time
Approx 1 hr
m
0 'h l
Fig 12 Diagrammatic representation of charts (traces enhanced and time corrected for clarity)
float gauge trace, assuming instead that had no previous experience of it.
the nucleonic chart reading which
appeared steady at 1O0/0 reflected the 80 The following factors may account
actual level in V305 Unknown to him the for LIC 3-22 being opened, and liquid level
pen had been offset so that a zero in V305 falling during standby operation:
reading was shown on the chart as 10%.
(a) In cold weather and on standby with
He was thus unaware of the actual level no flow, wax could solidify in the
in V305 and of the imminent danger. unlagged and unheated HIC 3-22 and
78 Liquid level in V306 was similarly LIC 3-22 lines. To prevent blockages
measured by float and nucleonic gauges. the valves were opened on manual to
The charts indicated that liquid flowed pass warm liquid through. Flow was
from V306 to the fractionator some hours verified by noting changes in V305
prior to the incident and the gauges went and V306 levels and in V306 pressure
off-scale. The evidence indicated that which rises as gas escapes from the
V306 then emptied requiring 17 000 litres liquid. Alternatively V305 was drained
to bring its float gauge on-scale. Fig 12B1 of liquid allowing gas to
shows liquid surges in V306 breakthrough and blow the lines
corresponding to falls in the level of V305. clear of wax. Gas entering V306 was
The level also appears to rise in the again verified by a pressure increase.
minutes before the explosion. HSE With the reactors under standby
calculated from this that V306 contained conditions liquid transferred from
about 20 000 litres confirmed by V305 was not replaced. The duty
calculating the amount of liquid boardman had not practised the
transferred from V305 following closure of above techniques nor had they been
the outlet valve from V306 to the explained to him. However, he had
fractionator (para 80(b) refers). been in the control room the previous
day when a senior technician had
79 That morning the hydrocracker was blown gas through the lines in
on standby following the TCO trip with preparation for start-up. Another
feedstock from V308 (Fig 7) stopped. operator remembered that 2 years
However, residual liquid from the reactors earlier there was an occasion when
(V301 - V304) continued to pass into V305 gas was heard surging into V306 and
by the action of the recycling gas, its pressure relief valve operated.
although diminishing over a period of Almost certainly this was gas
hours. V305 level was controlled during breakthrough. However an incident
routine steady operation by having a fixed was avoided by the boardman
flow through HIC 3-22 on manual and closing the flow control valve. This
with flow variations controlled by LIC 3-22 near miss was not reported to either
on automatic. On standby, however, flow supervisors or management and there
was erratic and LIC 3-22 on automatic was no investigation.
would be too slow to cope with sudden
increases. Because it responded more (b) The fractionator feed valve (FIC 3-21)
quickly on manual, this was the preferred passed liquid significantly when
method of operation, but in this mode the closed using its control room
maintenance of safe levels required strict controller, and V306 emptied.
operator control. After about 0600 hours However before start up V306
liquid flow had almost ceased and the required sufficient liquid in it to
boardman said he had HIC 3-22 and ensure that gas breakthrough to the
LIC 3-22 shut on manual. He was mainly fractionator would not occur. To
concerned with the unexplained TCO, the ensure sufficient liquid it was
vibration on C301 and conditions on the therefore necessary for FIC 3-21 to
amine and downstream plants rather than be tightened (hand jacked shut)
the level in V305. However because manually on plant and this was done.
prolonged standby operation was rare he To get sufficient liquid level into
V306 for its float gauge to register, 82 Tests were carried out by HSE to
LIC 3-22 would then be opened on establish the gas and liquid flow
manual control. characteristics of the flow control valves.
Water flow rates at comparatively low
(c) Although unlikely, the array of similar pressure were used to calculate the flow
controllers could have resulted in an of hydrocarbon liquid which would have
operator turning the LIC 3-22 thumb been expected in service at the 155 bar
wheel in error. He may then not have pressure drop between V305 and V306.
noticed the level drop in V305. The results for LIC 3-22, the valve which
(d) The operator believed the V305 was opened are shown in Table 3. The
nucleonic gauge chart recorder variation between the HSE figures and
reading with its zero offset. In the manufacturer's data at mid-range is
addition he was not aware of the attributable to the effects of in-service
extent to which the liquid level in conditions and valve seat wear. Despite
V306 was below that which would there being no means on plant for
show a reading on its float gauge. measuring flow between V305 and V306,
Thus if LIC 3-22 was opened in an operators estimated flow rates against
attempt to establish a level of liquid percentage valve openings. Their
in V306 and no instrument changes estimates correlated closely with the
resulted, it could be concluded that calculated figures.
LIC 3-22 had not opened. The valve
may then have been opened further Table 3 Liquid flow characteristics of LIC 3-22 valve
or for a longer period to get the
levels to respond, whilst in reality LIC 3-22
levels were falling rapidly.
81 Opening LIC 3-22 on manual control Manufacturers
HSE values
% Open data
to pass warm liquid or gas through the
lines was permitted by supervisors. This
litreslmin litreslmin
necessitated bypassing the safety trips.
Because the danger was recognised this
was only supposed to be done under
carefully controlled conditions and with
extreme care. Operators were required to
pay close attention to instruments! The
shift instructions log book entry on 17
October 1986 stated:
"once all wax appears to have been
removed, block in and leave for 2 hours, 83 Gas flow characteristics of LIC 3-22
then check by opening LIC 3-22 carefully were obtained from the manufacturer and
to avoid over-pressurising the confirmed by calculation based upon the
LP separator. Repeat every 2 hours" liquid flow test results (Table 3). A
computer programme was then used to
and again on 13 March, 1987 stated: predict the expected pressures in V306,
"with caution and care, sweep hydrogen assuming hydrogen passing into it at
from the HP through the LP and the 155 bar, as a function of percentage open
multilocks to the fractionator to try to of LIC 3-22. Flow through its pressure
remove as much wax from the lines as relief valve (PRV) and its estimated liquid
possible". content (para 78) were taken into account.
The results are shown in Table 4
This was clearly a dangerous practice the (columns 1 and 2). The time taken for
potential consequences of which were not V306 to reach its calculated burst
fully understood. pressure of 50 bar is shown in Table 4
(columns 1 and 3). The times shown time of 108 seconds to reach its burst
commence once V305 is drained of liquid. pressure (Table 4) this would give a total
It can be seen that if LIC 3-22 was time to the explosion of about 6 minutes.
opened less than 40% the maximum The precise timing of the opening of LIC
pressure in V306 would be less than 3-22 beyond the 40% position may never
50 bar and it would therefore not rupture be known but the calculations
but would vent via its PRV. With LIC 3-22 demonstrate clearly the potential to over-
open more than 40% the PRV was not of pressurise V306.
sufficient capacity to prevent rupture.
These calculations therefore established 85 An indication of events in the
that for V306 to explode LIC 3-22 must minutes before the explosion is provided
have been opened beyond 40%. by the chart (Fig 12B2) showing V305
pressure. It shows a drop in pressure of
Table 4 Relationship between position of LIC 3-22 18 bar (270 psig) over 4 minutes and then
and pressure rise in V306 and time taken to reach a rapid drop as V306 ruptured. Although
burst pressure of 50 bar the complexity of the high pressure
system precluded using pressure drop
information to determine LIC 3-22
'10 Opening of Pressure Time to 50 bar (based position, close examination of the chart
LIC 3-22 bar (psig) on the models used) shows the rate of pressure drop increased
within that 4 minute period confirming
14 (200) Will not reach 50 bar that LIC 3-22 opened further. The volume
21 (300) Will not reach 50 bar of gas represented by the pressure drop
28 (400) Will not reach 50 bar was calculated as being sufficient for
35 (500) Will not reach 50 bar V306 to reach its burst pressure.
41 (600) Will not reach 50 bar
48 (700) Will not reach 50 bar 86 When the control room was entered
53 (800) 108 seconds after the explosion, a supervisor reported
35 seconds that the LIC 3-22 controller was on
25 seconds manual and 100% open. Later, when seen
22 seconds by HSE Inspectors it was found fully shut
and other controls were also in different
positions from those first reported. The
84 The chart recording of V305 level supervisor's report was correct, two
(Fig 12A) ceased some time before the operators who altered the controls
incident (para 73). The time taken after confirmed it several months later.
this for the incident to occur is the sum However no explanation for LIC 3-22
of the time to empty V305 of liquid and being fully open has been given. The
the time to raise V306 to its rupture reasons described in para 80 could
pressure. The LIC 3-22 liquid flow account for it being opened on manual
characteristics (Table 3) were used to during standby. The hydrocracker controls
estimate its percentage open when levels were typical of the late 1960s and the
in V305 were dropping prior to the following features could have led to
explosion and to calculate the time for it operator error:
to empty. The downward steps in the
float gauge trace (Fig 12A) show that (a) Errors could be made when
LIC 3-22 was open less than 5%. The final assessing the volume or depth of
downward trend no more than 20 minutes liquid in V305 and V306 as their
before the explosion starts at 6% on the measuring devices related to different
float gauge trace when 13 200 litres of indicated lengths, not to each other
liquid remained in V305 and in order to nor to the content of the vessels.
empty this amount in that time LIC 3-22 (b) False assumptions could be made
must have been opened much more. If it about the time to discharge the
was for example 40% open V305 would liquid in V305 since there was no
empty in 4 mins and when added to the means of measuring flow other than
Photograph 7 LIC 3-22 and
HIC 3-22 controllers