Sei sulla pagina 1di 21

The Hydrocracker Explosion and

Fire: 22 March 1987

Photograph 3
Hydrocracker area looking
east

The hydrocracker unit temperatures of the reactor beds were


monitored and at 425O temperature cut
37 'Hydrocracking' describes an outs (TCOs) would operate to stop the
exothermic refinery process involving the input of wax feed and hydrogen.
break down of low grade waxy products Sequenced depressurisation of the
and thick viscous oils by subjecting them system would start through blow down
to hydrogen gas at high temperatures and valves into the flare system. Hydrogen
pressures in the presence of a catalyst to recycle would continue through the
form high grade light oils, petroleum reactors to assist cooling during
spirits and liquid petroleum gas (LPG). depressurisation. Hydrogen make up feed
Fig 7 shows a simplified representation of gas for the reactors came mainly from a
the hydrocracker process flow system. hydrogen production unit augmented by a
38 The hydrocracker unit at the refinery supply which was a by-product from the
consisted of a series of 4 fixed bed catalytic reformer. The gas composition
vertical reactors, operating in an was subject to minor variations according
atmosphere of hydrogen at 155 bar to its methane content.
(2250 psig) and 350°C. Waxy distillates
were continuously fed through the 39 From the reactors the hydrogenated
reactors from a feed surge drum at a liquidlgas mixture passed forward through
maximum rate of approximately 32 000 a series of heat exchangers and a fin fan
barrelslday (blday) (3500 litrelmin). The cooler into a vertical high pressure
Wax and heavy feed products
from vacuum unit, distillation units and tankage

surge

I Recycle
waxy
residue
1 Light products (LPG, spirit, kerosene, oils)

Fig 7 Hydrocracker process flow system


separator (V305) at a temperature of Events leading to the incident
about 50°C. In V305 the hydrogen and 42 On 13 March the hydrocracker unit
light gases were separated from the liquid was taken out of service to carry out
and passed to the inlet of centrifugal essential repairs. Late on Saturday 21
compressor C301 to be recycled to the March it was being recommissioned. At
reactors. This compressor vibrated at high
the start of the nightshift at 2200 hours,
differential pressures and although it gave
production was steady at 20 000 blday. At
reliable service, it was crucial to the
about 0130 hours on Sunday alarms
operation of the plant. Thus vibration was
sounded in the control room. The plant
closely monitored to prevent breakdown.
tripped and a number of pumps and
From V305 the liquor at 155 bar and 50°C compressors shut down automatically;
was then passed via control valves to a feed to the reactors was interrupted and
horizontal low pressure separator (V306)
the system started to depressurise. It was
where more hydrogen and light
noted that one of the TCOs on V303 had
hydrocarbon gases separated from the
caused the plant trip.
liquor as the pressure dropped to about
9 bar (135psig). 43 The hydrocracker appeared
40 The de-gassed liquor from V306 then satisfactory and the TCO was thought to
passed through heat exchangers into the be spurious. No over temperature
fractionation unit where products such as condition was found and the TCO trip
kerosene, gasoline, naphtha and was overridden enabling hydrogen
petroleum gases were separated from the circulation to be re-established. The
uncracked residue. The conversion instrument section verified the reactor
efficiency of the hydrocracking process temperature control circuits confirming
was typically 60%. Unconverted liquor that they were working. At about 0200
was recycled for further hydrocracking. At hours the night shift operators started to
bring the plant up to working pressure
32 000 blday throughput and 60%
conversion, the maximum flow of liquid and to stabilise reactor bed temperatures
from V305 to V306 was about 5900 preparatory to start up. From then until
litrelmin, consisting of 3500 litrelmin feed the time of the incident, the plant was
and 2400 litrelmin recycled residue. Gases being held on standby with no feed
from V306 passed to the amine treatment coming through. There was nothing of
plant to remove sulphur. special note in the operation except for a
slightly higher than usual vibration from
Table 1 Typical HP and LP separator operating parameters ~301.
44 In accordance with instructions
HP separator LP separator
Parameters
(V305) (V306) operators delayed introducing feedstock
until the arrival on site of the
Length 15.6 metres 9.1 metres hydrocracker supervisor. At 0600 hours
Diameter 3.05 metres 3.05 metres the shift changed. The day shift was told
Liquid Volume 33 000 litres 33 000 litres the plant had shut down because of an
Vapour Volume 79 000 litres 33 000 litres unexplained TCO, that there was excess
Temperature 4I0C 43OC
Pressure 155 bar 9 bar vibration on C301 compressor and that
Liquid specific gravity 0.85 0.85 the plant was to be kept on standby
Vapour molecular weight 5 15 pending the arrival of the supervisor.
Weight of liquid 27.7 te 28 te Between 0645 and 0655 the majority of
Weight of vapour 2.1 te 0.2 te
Weight of hydrogen 0.8te 0.04 te
operators returned to have breakfast in
the mess-room within the control room
building.
41 The process was operated locally The explosion and fire
from a plant control room, situated some
37 m from V306. A plot plan of the area 45 At 0700 hours there was a violent
is shown in Fig 8. explosion followed by an intense fire. The
Fig 8 Plan of hydrocracker complex
explosion was heard and felt 30 km away mutual aid arrangement from other
and it caused ccnsiderable local concern. localities throughout Scotland under the
A contractor who had just left the mess- refinery's emergency plans. HSE
room was killed. The explosion centred on inspectors were in early attendance.
V306 which was constructed from 18 mm
48 Difficulties in fighting the fire arose
steel plate and weighed 20 tonnes.
because waxy material from ruptured
Photograph 4 shows the hydrocracker
pipework blocked drains causing fire
area with two T-shaped plinths on which
water to accumulate. Leaking petroleum
V306 stood to the left of centre. The
spirit spread over a large area of the
vertical HP separator (V305) is on the far
resultant water surface and five hours
left. V306 had disintegrated and large
after the explosion it ignited. A number of
fragments were projected considerable
other process units in the hydrocracker
distances. A piece weighing nearly
complex were enveloped in flames.
3 tonnes was found on the foreshore
Fortunately, the fire brigade were able to
1 km away. Another was projected over a
regain control and that evening the fire
main road into a factory where it severed
was finally extinguished.
a steam line. A third went through the
roof of a workshop on an adjacent site. 49 The potential consequences of the
During the investigation almost all of incident could have been much greater. It
V306 was recovered and the positions occurred on a Sunday morning when few
where the main fragments landed are people were on site. V306 ruptured at
shown in Fig 9. support saddles underneath the vessel
46 At the time of the explosion there and the blast force was directed
were nine operators within the downwards with fragments being
hydrocracker complex. Two were in the projected upwards. Had it been otherwise,
control room; six were in the adjacent the control and mess room building could
mess room having breakfast; the ninth have been destroyed, increasing the
was out on the plant. Although the likelihood of death and injury. Fortunately
control room and mess room building of none of the fragments hit vulnerable plant
conventional brick construction suffered nor did they strike anyone. The risk did
considerable damage, it remained not warrant evacuating local residents but
standing. Those inside were uninjured and non essential personnel left the site. As a
escaped by the rear exit. The operator precaution traffic on the adjacent road
outside was far enough away and was diverted.
escaped the worst effects of the blast. Investigation by HSE
The only other person in the vicinity was
the contractor. 50 Initial fire and explosion evidence
suggested there had been an explosive
47 The Grangemouth Major Incident
pressure vessel failure involving V306
Plan was put into operation and its
followed by release of the gas and liquid
Control Committee comprising
contents as a cloud or mist. This
representatives of the Police, Fire produced not only a fireball but also blast
Brigade, District and Regional Councils,
effects due to the semi-confined nature of
and experts from the refinery and from
the plant. There were a number of
major chemical and petroleum companies
possibilities which could have lead to
in the Grangemouth area, co-ordinated the
such a failure including:
provision of emergency services and the
response to off-site events. The incident (a) an external event, such as sabotage
on-site was dealt with by the Police and or an incident on adjacent plant.
Fire Brigade, assisted by refinery staff.
(b) internal explosion.
Twelve units of the Central Scotland Fire
Brigade and the refinery fire brigade (c) mechanical failure under normal
fought the fire. Supplies of foam were operating conditions arising out of a
provided by BP and brought in under a critical defect within the vessel or
Photograph 4 LP separator support plinths

through other effects such as 52 With respect to (c) and (d), HSE were
vibration. alerted by the refinery management that
there had been alteration of some
(d) accidental overpressurisation.
instrument settings before security was
51 The investigation involved: fully established around the accident
location. The accounts given by some
(a) Recovery and metallurgical operators did not and still do not tally
examination of vessel fragments on with the physical evidence. It was not
which ballistic calculations were possible to establish unequivocally from
based. the operators' evidence the sequence of
(b) Recovery and examination of fire events which resulted in the explosion.
damaged components. The investigation therefore attempted to
reconstruct the physical conditions
(c) Examination of control room necessary to account for the incident.
instruments and records.
(d) Interviewing operating and 53 The normal operating pressure for
management staff. V306 was 9 bar (135 psig), its design
Fig 9 Refinery plan showing location of hydrocracker explosion and debris, and location of flare line incident
Photograph 5 Fragment
from LP separator; distance
340 metres

Photograph 6 LP separator
end section projected
75 metres over control room
building
pressure 10.7 bar (160 psig) and its test had grown rapidly from the origin in two
pressure 21.6 bar (324 psig). It had a opposite directions, in a predominantly
single pressure relief valve with an orifice brittle manner, consistent with fracture
area of 18 cm2 and a relief capacity to under high strain rate conditions at a
flare of 12.25 tonnelhour, sufficient to temperature near the impact transition
cater for overpressure from fire temperature of the material in this
engulfment. There was no evidence to thickness. On a plant of this type it is
suggest that this relief valve was not foreseeable that fluid transfer could set
operating effectively at its set pressure of up vibration effects giving rise to high
10.7 bar (160 psig). transient strain rates. At operating
temperatures well below normal a vessel
54 The fragments of V306 were located, subjected to these vibration effects could
weighed and their positions logged. The have failed.
explosive forces were calculated using
ballistic techniques based on fragment 57 However the other evidence strongly
trajectories which confirmed that rupture suggested that there had been a
was caused by over-pressurisation. The breakthrough of high pressure gas from
results correlated well with the calculated V305 to V306 leading to
theoretical burst pressure of 50 bar overpressurisation of the vessel. The
(750 psig). Blast damage established that liquid in V305 had drained away through
the force of the explosion was equivalent an output flow control valve when the
to approximately 90 kg of TNT. hydrocracker was being held on standby
operation with no product passing,
55 The overwhelming weight of evidence thereby allowing high pressure gas to
from blast damage, ballistics and break through. Fig 10 shows a single
metallurgical examination pointed towards 300 mm diameter outlet pipe from the
internal overpressure of V306 applied in a bottom of V305 which split into two
single event. Nevertheless other parallel streams each with a separate
possibilities of vessel failure, as set out flow control valve. The valve nearest V305
in para 50, were also considered by was the right-angled, air-diaphragm-
detailed examination of the plant, plant operated valve LIC 3-22 which could be
records and eye witness accounts. There operated from the control room either in
was no indication of an external initiating automatic or manual mode. Some
event such as sabotage. An internal distance from V305 was the air-
explosion or ignition occurring within diaphragm-operated, straight-through flow
V306 was considered. This would have control valve HIC 3-22, which could only
required the presence in the vessel be operated via a manually applied
system of both oxygen and a source of control signal from the control room.
ignition, and the possibility was
eliminated not only by detailed 58 Fig 11 shows the LIC 3-22 and HIC
consideration of the process conditions 3-22 valve control system. A pneumatic
and controls, but also by evidence from diaphragm assembly opened each valve.
vessel fragments. On removal of air pressure the valve was
closed by a spring. Its position was
56 The possibility of mechanical failure selected by a control unit from which an
for reasons other than simple electrical signal passed to an IIP
overpressure was considered. The (electrical currentlair pressure) converter.
metallurgical evidence established that A pneumatic signal was then sent to a
the origin of the failure was in the heat positioner unit at the valve. By this means
affected zone of a saddle weld on the air pressure was applied to the
underside of the vessel at the east end diaphragm. Two hand-wheel-operated
near the support plinth. There was no valves (SP25) in series provided a manual
indication of pre-existing defects nor of a by-pass to the control valves. One was
progressive mode of failure on any part of found open but the other was shut and
the fracture surface examined. Cracks found to be gas tight. Gas breakthrough,
Recycle hydrogen
to C301 compressor
Gas

A -& Uc3-22
r------l
l
I
I
I
!l 1L I To Amtne plant
Bypass Pressure control l
Plc 3-73

Nucleon~c
SP25 SP25

!I rl Float
gauge
LP separator V306 -1
I
I
l

Ltqutd
II
1r 1r r---------- J
II la
4- FIC 3-21
h f,ct10nator

F--'
Sour water

Fig 10 HPlLP separator control system


Float gauge
Alr supply
on V305
Vent t o
atmosphere
1I
A
PI1 converter
l!
11

- d
'\

&
0 ,,c322
controller
lip
converter Pos~t~oner Dump
solenold
0
-

fi
d

Low alarm

for
W ~LIC
d~sconnected
r l n 3-22
g
t o s o valve
l e n o ~was
dd u m p

Audlble Vlsual

Relay unit

(Svstem simplified for clarity)

Extra low
alarm

Audible Visual

Fig 11 LIC 3-22 & HIC 3-22 v a l v e control system


therefore, did not occur through the by- which stopped the audible alarm and
pass route. made the flashing light steady until the
alarm condition was cleared on plant. The
59 HSE tested the HIC 3-22 and LIC 3-22 low level alarm was in working order. By
valves. Apart from fire damage to the 0620 hours the liquid level had fallen
diaphragm assembly and positioner on below the 20% set value and the
LIC 3-22, they were found to be in consequent alarm was accepted by the
working order and sealing reasonably operator. The low level alarm did not have
effectively when in their closed positions. a trip function.
When valves were removed, waxy material
was found in all except LIC 3-22 evidence 63 The nucleonic level sensing gauge
that gas had passed through it purging it had a range of 900 mm, and provided a
of wax. means to verify the float gauge reading
over the middle of its range. It had no
60 The possibility that a valve positioner direct control, alarm or trip function. The
fault could have caused a valve to open float gauge and the nucleonic mid points
was considered. The positioner on coincided and there gave equal readings
HIC 3-22 was working but that on LIC 3-22 of 50%. A 100% reading (nucleonic) was
was destroyed. Fault conditions were equivalent to 63% on the float gauge;
simulated on an identical positioner while at 0% (nucleonic) the float gauge
which showed that in the event of a registered 38%.
component failure a valve would close
rather than open. Positioner failure 64 There was an 'extra-low' level
leading to LIC 3-22 opening was thus detection system on V305 comprising two
discounted. float switches which were attached to the
bridle assembly beneath the float gauge.
61 The liquid level in V305 was Each consisted of a chamber with a
measured by a 3.6 m long tubular float pivoted float, movement of which was
gauge, and a nucleonic level sensing actuated when the liquid level inside it
gauge both attached to a pipework bridle. fell. This then broke a magnetic circuit,
Levels were shown in the control room on operated an electrical switch, and
indicators and chart recorders. V305 initiated audible and visual alarms. This
contained 11 500 litres or less when the system was also intended to close both
float gauge registered 0%. A 1OO/ variation flow control valves from V305 to V306
in the float gauge reading was equivalent stopping the outflow of liquid and thus
to 266 litres, and at a 50% reading V305 preventing gas breakthrough. Operation of
thus contained 24 800 litres. Signals from this trip also prevented the valves from
the float gauge also provided input to the being opened until a safe liquid level was
LIC 3-22 controller (shown in photo 8) to established in V305.
provide level indication and to control the
opening of LIC 3-22 to a level set by the 65 The liquid pressure from V305 was
operator with the controller set to reduced solely by the throttle action of
automatic. The LIC 3-22 and HIC 3-22 the flow control valves. However, in the
controllers were tested and found to be in original installation some pressure drop
working order and correctly calibrated. was effected by a power recovery turbine
located in the line between V305 and
62 If the level in V305 fell to 20°/0 V306, which the extra-low level trip
(16 800 litres) on the float gauge, signals system was intended to protect against
triggered a 'low liquid level' audible alarm gas breakthrough. The turbine was never
and a warning light showed on the used and was removed in the mid 1970s.
control panel to alert the operator, so that A safety audit carried out in 1975
he could monitor it or take corrective nevertheless confirmed a need to retain
action. Operators could 'accept' the alarm the extra-low level trip, because it was
by pressing an 'acknowledge' button critical to prevent over-pressure in V306.
The audit also identified operational temporarily at the rear of the control
problems in controlling the level in V305 panel". There are three possible reasons
and recommended duplicate tappings on why the trip was disconnected.
it for level detection instruments. This
recommendation was not implemented. (a) It was considered part of the
The nucleonic gauge operating over a redundant turbine system and
restricted range was fitted instead. The thought unnecessary.
audit recognised that the pressure relief (b) Liquid in V305 vortexed and often
valve on V306 could not cope with gas caused the extra-low level trip to
breakthrough. operate spuriously. At high
throughput this caused production
66 In 1980 a study of the pressure difficulties.
reliefs to flare was carried out by a
specialist contractor. It assumed that the (c) Because it was cumbersome to use
extra low level trip system on V305 would the manual bypass valves (SP25) the
function correctly and concluded that operators wanted LIC 3-22 to open at
existing precautions precluded gas levels below the extra-low trip so
breakthrough. No recommendations were that, for example, V305 could be
made for further pressure relief. completely drained prior to shut
down.
67 As part of the extra-low level trip
system LIC 3-22 and HIC 3-22 valves each 70 Many operators knew this trip was
originally incorporated an electrically inoperative as they had taken the level of
operated 'dump' solenoid to interrupt and liquid in V305 below the notional trip
release the air pressure on the valve point and the valve remained open. No
diaphragm, thus causing the valve to assessment of the potential
close. The HIC 3-22 solenoid dumped consequences was carried out before the
when de-energised, but the LIC 3-22 trip was disconnected. Routine
solenoid dumped when energised. Thus if procedures for testing and defect
the electrical supply to the LIC3-22 reporting did not highlight its absence.
solenoid failed, the valve would not close This state of affairs was accepted by
and therefore in this respect it failed to those concerned with the hydrocracker, at
danger although the electrical supply was least up to the level of process
monitored by a 'trip-supply-fail alarm'. supervisor.
68 The electrical supply wiring to the 71 The trip solenoid on HIC 3-22 was
LIC 3-22 trip solenoid was found to have removed and bypassed in 1986 after being
been deliberately disconnected at the damaged in a fire. It too would not have
control room and on HIC 3-22 the trip closed on 'extra-low' liquid level and
solenoid had been removed and could be opened with a dangerously low
bypassed. In consequence neither of level. There was therefore the potential
these flow control valves could trip to for gas breakthrough as with LIC 3-22.
close on extra-low levels in V305. It was The investigation revealed that HIC 3-22
thus possible to open the valves with remained shut and played no part in the
little or no liquid in V305. Safety of this incident, but the absence of its solenoid
part of the plant had for many years thus is considered by HSE to have been of
depended solely on the vigilance of equally serious potential.
operators.
72 Operators stated that the extra-low
69 Disconnection of the LIC 3-22 trip level alarm visual indication had been in
solenoid was commented on in a 1985 continuous operation for many months
memo by the refinery senior instrument until the light bulbs failed some time
engineer. A manuscript amendment before the explosion. The alarm had been
probably made some years before on a regarded as spurious. The extra-low level
wiring plan showed it was "disconnected alarm circuit board was tested and found
to be in working order. The two float- boardman controlling the hydrogen,
switches were fire damaged but there vacuum and amine units. Operators were
was evidence to suggest that the first largely trained on-the-job by experienced
switch was incorrectly assembled, and colleagues.
that the small bore pipework to the
second switch was blocked. The Senior Technician
possibility thus existed that both extra-
low level switches were inoperative.
Control Room Plant
73 Trend chart recorders provided a
permanent record of aspects of the
hydrocracker operation. However they
were not synchronised and the
information they provided needed to be Grade A Operator Grade A Operator

interpreted with care and by reference to


(Senior Boardman) I
other evidence. Several of their pens were
not working. The float gauge chart did
register the falling liquid level in V305 in Junior Boardman
the 45 minutes prior to the explosion, as
shown in Fig 12(A), but does not show
the minutes before the incident when the Amine Hydrogen Vacuum Hydrocracker
liquid level fell, V305 emptied, and gas Unit Unit Unit Unit
breakthrough occurred. Four minutes Operator Operator Operator Operator
before the explosion the chart (Fig 12B2)
shows a rapid fall in V305 pressure. This Table 2 Shift operator
responsibilities
along with eye witness reports, which
suggested that the pressure relief valve Causes
on V306 was lifting immediately before
the explosion, confirmed that gas 76 Operators denied taking action or
breakthrough had occurred. The rate of making adjustments which could explain
pressure drop could not be explained by the incident. However all the evidence
other mechanisms such as emergency suggested that LIC 3-22 had been opened
depressurisation. and closed on manual control at least
three times after the shift changeover at
74 There was no chart indication to 0600 hours. Liquid level in V305 fell and
confirm the pressure conditions in V306. when LIC 3-22 was opened again just
The amine plant pressure registered no prior to the incident all remaining liquid
change which taken with other evidence drained away allowing high pressure gas
confirmed that the gas output valve from to break through. LIC 3-22 did not close
V306 was shut and consequently this automatically because its trip solenoid
outlet for gas escape was closed. There was disconnected.
was no alarm or trip on V306 for high
pressure or over-pressure conditions. 77 Despite the presence of steam trace
heating, wax inside the float gauge and
75 The hydrocracker operated the small bore pipework to the extra-low
continuously. Shift hours were from level switches had been known to solidify
0600-1400 hours (day), 1400-2200 hours when it was cold. The float gauge
(back) and 2200-0600 hours (night). Each sometimes gave false readings and a
shift of eight operators is shown in number of operators mistrusted it. They
Table 2. A ninth operator on shift that placed more trust in the nucleonic gauge
morning was a trainee. The senior readings because the bridle itself was
boardman had primary responsibility for less prone to blockage. On that cold
all control room operations, in particular March morning the boardman paid no
the hydrocracker, with the junior attention to the falling
40

HPSeparator (V3051liquid level

30

%
chart 20
indication

10

40

B,
30
V
LP Separator (V3061liquid level
%
Chart 20
indication

10
float gauge
1
f Zero offset

80

%
Chart O'
indication
HP Separator (V3051Pressure

60

-
,h I I I I
l a s breakthrough -O6OohrS -0500hrs -0400hrs -0300hrs
Explosion
t
Shift changeover
Time
Approx 1 hr

m
0 'h l
Fig 12 Diagrammatic representation of charts (traces enhanced and time corrected for clarity)
float gauge trace, assuming instead that had no previous experience of it.
the nucleonic chart reading which
appeared steady at 1O0/0 reflected the 80 The following factors may account
actual level in V305 Unknown to him the for LIC 3-22 being opened, and liquid level
pen had been offset so that a zero in V305 falling during standby operation:
reading was shown on the chart as 10%.
(a) In cold weather and on standby with
He was thus unaware of the actual level no flow, wax could solidify in the
in V305 and of the imminent danger. unlagged and unheated HIC 3-22 and
78 Liquid level in V306 was similarly LIC 3-22 lines. To prevent blockages
measured by float and nucleonic gauges. the valves were opened on manual to
The charts indicated that liquid flowed pass warm liquid through. Flow was
from V306 to the fractionator some hours verified by noting changes in V305
prior to the incident and the gauges went and V306 levels and in V306 pressure
off-scale. The evidence indicated that which rises as gas escapes from the
V306 then emptied requiring 17 000 litres liquid. Alternatively V305 was drained
to bring its float gauge on-scale. Fig 12B1 of liquid allowing gas to
shows liquid surges in V306 breakthrough and blow the lines
corresponding to falls in the level of V305. clear of wax. Gas entering V306 was
The level also appears to rise in the again verified by a pressure increase.
minutes before the explosion. HSE With the reactors under standby
calculated from this that V306 contained conditions liquid transferred from
about 20 000 litres confirmed by V305 was not replaced. The duty
calculating the amount of liquid boardman had not practised the
transferred from V305 following closure of above techniques nor had they been
the outlet valve from V306 to the explained to him. However, he had
fractionator (para 80(b) refers). been in the control room the previous
day when a senior technician had
79 That morning the hydrocracker was blown gas through the lines in
on standby following the TCO trip with preparation for start-up. Another
feedstock from V308 (Fig 7) stopped. operator remembered that 2 years
However, residual liquid from the reactors earlier there was an occasion when
(V301 - V304) continued to pass into V305 gas was heard surging into V306 and
by the action of the recycling gas, its pressure relief valve operated.
although diminishing over a period of Almost certainly this was gas
hours. V305 level was controlled during breakthrough. However an incident
routine steady operation by having a fixed was avoided by the boardman
flow through HIC 3-22 on manual and closing the flow control valve. This
with flow variations controlled by LIC 3-22 near miss was not reported to either
on automatic. On standby, however, flow supervisors or management and there
was erratic and LIC 3-22 on automatic was no investigation.
would be too slow to cope with sudden
increases. Because it responded more (b) The fractionator feed valve (FIC 3-21)
quickly on manual, this was the preferred passed liquid significantly when
method of operation, but in this mode the closed using its control room
maintenance of safe levels required strict controller, and V306 emptied.
operator control. After about 0600 hours However before start up V306
liquid flow had almost ceased and the required sufficient liquid in it to
boardman said he had HIC 3-22 and ensure that gas breakthrough to the
LIC 3-22 shut on manual. He was mainly fractionator would not occur. To
concerned with the unexplained TCO, the ensure sufficient liquid it was
vibration on C301 and conditions on the therefore necessary for FIC 3-21 to
amine and downstream plants rather than be tightened (hand jacked shut)
the level in V305. However because manually on plant and this was done.
prolonged standby operation was rare he To get sufficient liquid level into
V306 for its float gauge to register, 82 Tests were carried out by HSE to
LIC 3-22 would then be opened on establish the gas and liquid flow
manual control. characteristics of the flow control valves.
Water flow rates at comparatively low
(c) Although unlikely, the array of similar pressure were used to calculate the flow
controllers could have resulted in an of hydrocarbon liquid which would have
operator turning the LIC 3-22 thumb been expected in service at the 155 bar
wheel in error. He may then not have pressure drop between V305 and V306.
noticed the level drop in V305. The results for LIC 3-22, the valve which
(d) The operator believed the V305 was opened are shown in Table 3. The
nucleonic gauge chart recorder variation between the HSE figures and
reading with its zero offset. In the manufacturer's data at mid-range is
addition he was not aware of the attributable to the effects of in-service
extent to which the liquid level in conditions and valve seat wear. Despite
V306 was below that which would there being no means on plant for
show a reading on its float gauge. measuring flow between V305 and V306,
Thus if LIC 3-22 was opened in an operators estimated flow rates against
attempt to establish a level of liquid percentage valve openings. Their
in V306 and no instrument changes estimates correlated closely with the
resulted, it could be concluded that calculated figures.
LIC 3-22 had not opened. The valve
may then have been opened further Table 3 Liquid flow characteristics of LIC 3-22 valve
or for a longer period to get the
levels to respond, whilst in reality LIC 3-22
levels were falling rapidly.
81 Opening LIC 3-22 on manual control Manufacturers
HSE values
% Open data
to pass warm liquid or gas through the
lines was permitted by supervisors. This
litreslmin litreslmin
necessitated bypassing the safety trips.
Because the danger was recognised this
was only supposed to be done under
carefully controlled conditions and with
extreme care. Operators were required to
pay close attention to instruments! The
shift instructions log book entry on 17
October 1986 stated:
"once all wax appears to have been
removed, block in and leave for 2 hours, 83 Gas flow characteristics of LIC 3-22
then check by opening LIC 3-22 carefully were obtained from the manufacturer and
to avoid over-pressurising the confirmed by calculation based upon the
LP separator. Repeat every 2 hours" liquid flow test results (Table 3). A
computer programme was then used to
and again on 13 March, 1987 stated: predict the expected pressures in V306,
"with caution and care, sweep hydrogen assuming hydrogen passing into it at
from the HP through the LP and the 155 bar, as a function of percentage open
multilocks to the fractionator to try to of LIC 3-22. Flow through its pressure
remove as much wax from the lines as relief valve (PRV) and its estimated liquid
possible". content (para 78) were taken into account.
The results are shown in Table 4
This was clearly a dangerous practice the (columns 1 and 2). The time taken for
potential consequences of which were not V306 to reach its calculated burst
fully understood. pressure of 50 bar is shown in Table 4
(columns 1 and 3). The times shown time of 108 seconds to reach its burst
commence once V305 is drained of liquid. pressure (Table 4) this would give a total
It can be seen that if LIC 3-22 was time to the explosion of about 6 minutes.
opened less than 40% the maximum The precise timing of the opening of LIC
pressure in V306 would be less than 3-22 beyond the 40% position may never
50 bar and it would therefore not rupture be known but the calculations
but would vent via its PRV. With LIC 3-22 demonstrate clearly the potential to over-
open more than 40% the PRV was not of pressurise V306.
sufficient capacity to prevent rupture.
These calculations therefore established 85 An indication of events in the
that for V306 to explode LIC 3-22 must minutes before the explosion is provided
have been opened beyond 40%. by the chart (Fig 12B2) showing V305
pressure. It shows a drop in pressure of
Table 4 Relationship between position of LIC 3-22 18 bar (270 psig) over 4 minutes and then
and pressure rise in V306 and time taken to reach a rapid drop as V306 ruptured. Although
burst pressure of 50 bar the complexity of the high pressure
system precluded using pressure drop
information to determine LIC 3-22
'10 Opening of Pressure Time to 50 bar (based position, close examination of the chart
LIC 3-22 bar (psig) on the models used) shows the rate of pressure drop increased
within that 4 minute period confirming
14 (200) Will not reach 50 bar that LIC 3-22 opened further. The volume
21 (300) Will not reach 50 bar of gas represented by the pressure drop
28 (400) Will not reach 50 bar was calculated as being sufficient for
35 (500) Will not reach 50 bar V306 to reach its burst pressure.
41 (600) Will not reach 50 bar
48 (700) Will not reach 50 bar 86 When the control room was entered
53 (800) 108 seconds after the explosion, a supervisor reported
35 seconds that the LIC 3-22 controller was on
25 seconds manual and 100% open. Later, when seen
22 seconds by HSE Inspectors it was found fully shut
and other controls were also in different
positions from those first reported. The
84 The chart recording of V305 level supervisor's report was correct, two
(Fig 12A) ceased some time before the operators who altered the controls
incident (para 73). The time taken after confirmed it several months later.
this for the incident to occur is the sum However no explanation for LIC 3-22
of the time to empty V305 of liquid and being fully open has been given. The
the time to raise V306 to its rupture reasons described in para 80 could
pressure. The LIC 3-22 liquid flow account for it being opened on manual
characteristics (Table 3) were used to during standby. The hydrocracker controls
estimate its percentage open when levels were typical of the late 1960s and the
in V305 were dropping prior to the following features could have led to
explosion and to calculate the time for it operator error:
to empty. The downward steps in the
float gauge trace (Fig 12A) show that (a) Errors could be made when
LIC 3-22 was open less than 5%. The final assessing the volume or depth of
downward trend no more than 20 minutes liquid in V305 and V306 as their
before the explosion starts at 6% on the measuring devices related to different
float gauge trace when 13 200 litres of indicated lengths, not to each other
liquid remained in V305 and in order to nor to the content of the vessels.
empty this amount in that time LIC 3-22 (b) False assumptions could be made
must have been opened much more. If it about the time to discharge the
was for example 40% open V305 would liquid in V305 since there was no
empty in 4 mins and when added to the means of measuring flow other than
Photograph 7 LIC 3-22 and
HIC 3-22 controllers

by noting changes in liquid level. If experience could move a thumbwheel


that level was below the range of the and not monitor the consequence of
level measuring devices the operator his action.
was working 'blind' further increasing Errors could arise if a valve controller
the probability for error. (e)
was adjusted directly from automatic
(c) Errors could occur as controls of a to manual mode without going
similar appearance carried out through a balancing procedure and
different functions. If one controller without checking the manual
was adjusted when the intention was thumbwheel setting (Photo 7). The
to adjust another, a valve could move balancing procedure should ensure
to a ~ o s i t i o nnot anticipated. that the valve position on manual
corresponds to the position on
In situations of high stress an error automatic before the change to
could be made if the manual manual mode is made. Failure to
thumbwheel controller (photo 7) were follow this procedure could lead to
moved in the wrong direction. The the valve moving to a position not
valve could then be opened instead anticipated. The LIC 3-22 controller
of closed. The LIC 3-22 thumbwheel
operated in this manner.
action was to close the valve when
moved from right to left but this was Conclusions
not clearly indicated. On some other
controllers where the valve action 87 The investigation established the
was different, thumbwheels operated following:
in the opposite manner. It is possible (a) V306 was subjected to an internal
that an operator relying upon long pressure of about 50 bar, significantly
in excess of its normal working (n) The pressure relief valve on V306 was
pressure and sufficient to cause it to not of sufficient capacity to relieve
explode. the maximum potential flow of high
pressure gas to prevent overpressure.
V306 overpressurised when hydrogen
at 155 bar entered it from V305. (0) Too much reliance was placed on
operators for the safe control of flow
The high pressure gas was able to from high pressure plant into a low
pass from V305 because liquid in it pressure system.
had drained through an open valve.
(p) The refinery was aware of the
The open LIC 3-22 valve formed the potential for gas breakthrough
route for liquid and then gas to pass following audits in 1975 and 1980.
into V306. HIC 3-22 and one of the
by-pass valves were closed. 88 It was very dangerous not to have
accurate knowledge of liquid levels at all
LIC 3-22 was not on automatic times given that the safety trip
control. Hence the possibility that the mechanisms on the two control valves
incident was caused by failure of the were inoperative. Excessive reliance was
V305 float gauge, which provided being placed on operators with
level signals for automatic control, insufficient appreciation of the risks
and its associated control circuitry, associated with gas breakthrough.
can be discounted. Without 'extra-low level' protection in
LIC 3-22, its level indicator controller V305, V306 was at risk of being over-
and its pneumatic positioner did not pressurised at any time when the
fail and the valve did not open of its maintenance of a liquid level in V305
own accord. could not be assured andlor was not
under precise control. This was most
LIC 3-22 was selected on manual likely when LIC 3-22 was on manual
control, was more than 40% open control, during start up, interruption to
and was very probably 100% open. normal operation and standby.
Safety shut off in the event of extra- 89 The refinery had procedures for
low levels in V305 relied solely on the routine monitoring of interlocks, alarms,
process flow control valves LIC 3-22 and trips, but on the checklist for toe
and HIC 3-22. There was no hydrocracker some were omitted. The
independent shut-off valve in the line detection, trip and alarm systems for
from V305 to V306. extra-low liquid level in V305, had been
The LIC 3-22 dump solenoid wiring inoperative for a long time and
was disconnected about 5 years maintenance staff and operators
earlier and as a result it did not presumed that these were no longer
close on extra low level liquid level in required. Training of new operators,
V305. carried out by experienced operators
helped to perpetuate this misconception.
The HIC 3-22 trip solenoid was Although the refinery chief instrument
bypassed in 1986. engineer noted in 1985 that the LIC 3-22
The alarms on the extra-low level trip solenoid had been disconnected, this
detection system had failed and was not followed up.
operators were not alerted as a Preventive measures to avoid the incident
dangerous situation developed.
90 The following preventive measures if
Because the hydrocracker was on taken, could have avoided the incident.
standby the normal process routes
from V306 were valved off so that (a) V306 should have had a high integrity
gas entering could leave only via its automatic safety system to protect
pressure relief valve. against gas breakthrough and also
pressure relief provision to cater for
maximum anticipated gas flow rates.
The safety shut off system shculd
have included a secondary shut off
valve in the line from V305, in
addition to the control valves. Dual
extra-low level detection should also
have been fitted on V305 to provide
independent shut off trips.
(b) The trip systems and alarms as
installed should nevertheless have
been connected and in full
operational order. They should have
been included in comprehensive
testing schedules. Defects should
have been reported, recorded and
actioned.
(c) Changes to plant should only have
been made after full consideration of
the possible safety consequences.
(d) Control room practices should have
been monitored to detect possibilities
for malpractice or error. Ergonomic
factors in the design and layout of
controls should have been
periodically reassessed.
(e) The problem of wax blockages in the
level detection system on V305 and
the associated small bore pipework
should have been fully analysed.
Steps should have been taken to
reduce the likelihood of blockage by
for example the use of larger bore
pipework and monitored trace
heating. The identification of
blockages could have been assisted
by dual level detectors and more
sophisticated level instrumentation.
(f) Wax blockages in the HIC and LIC
3-22 lines could have been prevented
by the provision of lagging and trace
heating.
(g) Finally, a full analysis of the dangers
and potential consequences inherent
in the operation of the hydrocracker
should have been carried out, and
documented. Adequate safeguards
should have been provided and all
concerned should have been made
aware of the potential dangers and
necessary precautions.

Potrebbero piacerti anche