GNPOWER DINGININ LTD. CO.

OPERATION AND MAINTENANCE MANAGEMENT

Electrical Progress Report

Unit: 1
Date: July 29, 2019
(Strikethrough if not
applicable)
System Walk Down Inspection System WTP Inspection
AREA
Item
System /EQUIPME Description
No. NT

- ongoing construction and fan motor assembly


- power, instrument and control cable laying unavailable
1 PA/FD - motor terminal box unverified
FAN - temporary power supply for space heater
MOTOR - motor installation unavailability at air damper
- grounding system not connected to the equipment

for PROGRESS REPORT ONLY Page 1 of 4


GNPOWER DINGININ LTD. CO.
OPERATION AND MAINTENANCE MANAGEMENT

Electrical Progress Report

- some motors are installed


2 MILLS - motor’s space heater de-energized for preservation
- ongoing construction and assembly

- ongoing instrument and control cable pulling


3 MVSG - power cable pulling unavailable @ 13.2kV Medium Voltage Switchgear
- verified PA, FD and MILL MOTORS KKS code at the Medium Voltage Switchgear

for PROGRESS REPORT ONLY Page 2 of 4


GNPOWER DINGININ LTD. CO.
OPERATION AND MAINTENANCE MANAGEMENT

Electrical Progress Report

4 Control - installation of control panel ongoing at Boiler Area 41.6M (inspection cancelled due to SEPC
Panel docs unavailability), no schematic diagram

Turbine Extraction Steam System


Seal Oil System
- 7 Motors are installed (Vacuum Seal Oil Pump, Seal Oil Pump 1 & 2,
Emergency Seal Oil pump, H² Seal Oil Pump DE & NDE, Exhaust Filter Behind
Vacuum Pump)
5
- Seal Oil System motor’s space heater not yet installed.
Main Steam & HP Bypass Steam System – no update
Condenser Polisher Cartridge Filter System – no update
BFP Lube Oil System – no update
Seal Cooling Water System – no update