Sei sulla pagina 1di 4

CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009

Paper 0393

THE TESTING OF VACUUM GENERATOR CIRCUIT BREAKERS

René SMEETS Jürgen JÄGER*


Henk TE PASKE Nils ANGER**
Sander KUIVENHOVEN Siemens – Germany
*
KEMA T&D Testing – Netherlands jay-jay43@web.de
**
rene.smeets@kema.com nils.anger@siemens.com

the TRV are its rate-of-rise (RRRV) and peak value. Test-
ABSTRACT circuits have to be designed to reproduce the specified
TRV. After decay of the transient (recovery) voltage, the
Testing of generator breakers is usually in accordance with normal power frequency voltage remains across the breaker.
the standard IEEE Std. C37.013, to be included in the IEC
framework soon. This contribution emphasizes the importance of not only
These tests are preferably carried out in direct test-circuits, reproducing (in testing) the transient recovery voltage, but
that supply current and voltage from one source. Above a also the power frequency recovery voltage (RV) that
certain voltage level, in KEMA's case 17.5 kV, the remains across the breaker after the TRV has disappeared.
requirement of very high rate-of-rise of recovery voltages Reproduction in testing of both TRV and RV is clearly
needs a synthetic test circuit, normally exclusively applied acknowledged in the (IEC) standard for general purpose
for high-voltage circuit breakers. circuit breakers [1], but it is absent and thus not required in
In such a circuit, a charged capacitor is used as the source the (IEEE) standard for generator circuit breakers [2].
that supplies the transient recovery voltage. The This is not in conformity with the service situation, where
disadvantage of this method is that due to the gradual the TRV is always followed by the RV.
discharge of the capacitors, after interruption the (power
frequency) voltage across the breaker cannot be kept
II GENERATOR CIRCUIT BREAKER FAULT
constant. Power frequency voltage of at least 300 ms dur-
ation after interruption is required in the general purpose
SITUATIONS
circuit breaker standard IEC 62271-100, in order to verify
absence of restrike(s) that may lead to failure to interrupt. The following faults are known to have a far more severe
A new type of hybrid test-circuit is described, combining impact on the breaker than faults in a standard distribution
the advantages of a direct circuit (adequate duration of network:
power frequency voltage) and a synthetic circuit (adequate 1. The system source (SS) fault (fault between generator
rate of rise of recovery voltage). breaker and generator) produces very steep transformer-
Testresults with a circuit for 24 kV 50 kA are summarized. dominated transient recovery voltages (TRV). The rate of
In this circuit, both transient recovery voltage and power rise of this TRV can reach extreme values due to the low
frequency recovery voltage are applied in full conformity capacitance of the transformer and the short connections.
with the service situation. 2. Generator source (GS) faults (faults between generator
breaker and transformer) can result in missing current
zeroes that prolong the arcing time. Missing current
I INTRODUCTION
zeroes arise because of the combination of various
Generator circuit breakers are normally located between reactances and time constants of the generator, causing a
generator and step-up transformer in power plants. This DC component that can be temporarily higher than the
location (the vicinity of transformer and generator) calls for AC component of the fault current.
a number a special requirements that generator breakers 3. In addition, also the out-of-phase (OoP) requirements are
have to fulfill differing greatly from "general purpose" much more severe than the out-of-phase requirements of
circuit breakers. Apart from the very high nominal current general purpose circuit breakers (higher current and
carrying capacity, the faults that have to be dealt with by steeper TRV).
generator breakers have a special nature. This is notably
clear in the voltage that appears across the breaker III STANDARDISATION STATUS
immediately after interruption of the fault current. This
voltage is generally known as Transient Recovery Voltage The IEC standard 62271-100 [1] on circuit breakers
(TRV). The capability of a breaker to withstand this TRV is explicitly excludes generator circuit breakers. Therefore, the
a prime requirement to pass a test. The key parameters of IEEE Std. C37-013 [2, 3] is generally accepted for this

CIRED2009 Session 1 Paper No 0393


CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009

Paper 0393

60 OOP fault
sense, direct testing (especially three-phase) is the best
SS fault envelope for general simulation of network reality. Distribution breakers are
50
purpose CB T100 normally tested by this method and in three-phase test
GS fault
40 circuits voltage stresses are like in fig. 2a.
TRV (kV)

30 50
transient recovery voltage
20 40
envelope for general temporary pow freq voltage for first-pole-to-clear
10 purpose CB OOP 30
permanent power frequency recovery voltage
0 20
0 20 40 60 80 100 120
time (us) 10

0
Fig. 1: Standardized values of TRV of generator (for 200-
400 MVA transformers, red ) - and general purpose circuit -10
breaker (blue). Rated voltage is 24 kV. -20
reality & direct three-phase testing

purpose, and will be included in the IEC framework in 2009 0 50 100 150 200 250 300
by a joint IEEE / IEC working group. 50

40 transient recovery voltage


III 1 Transient recovery voltage 30 DC revovery voltage
In fig. 1, (IEEE) standardized values of TRV's of 24 kV
generator breakers for step-up transformer rated 200-400 20

MVA are compared with (IEC [1]) standardized 24 kV 10


breakers for distribution systems. In the generator breaker
0
case, IEEE prescribes the (sinusoidal) TRV waveshapes
directly: in fig. 1 the TRVs associated with system source -10

(SS), generator source (GS) and out-of-phase (OOP) fault. synthetic testing with unipolar recovery
-20
In the general purpose breaker case, IEC prescribes only the 0 50 100 150 200 250 300
required TRV envelopes: in fig. 1 the terminal fault (100% 50
rated short-circuit breaking current) and out-of-phase faults transient recovery voltage
40
(25% rated short-circuit breaking current).
From the figure it is immediately clear that the rate-of-rise 30

depends greatly on the application: either generator- or oscillatory recovery voltage


20
distribution application.
10

III 2 Power frequency recovery voltage 0


The pole of the breaker most severely stressed is the first- -10
pole-to-clear. The power frequency recovery voltage across
-20 synthetic testing with oscillatory recovery
this pole has temporarily a value of 1.5 times the phase-to-
ground voltage (in medium voltage networks). The elevated 0 50 100 150 200 250 300
voltage lasts until all phases have interrupted (after a quarter Fig. 2: Recovery voltage across breaker:
cycle) the current. After this temporarily elevated power a: upper: in network and in three-phase direct testing
frequency voltage, the rated power frequency voltage (at b: middle: in synthetic testing with unipolar recovery voltage
phase-to-ground value) sets in and remains. c: lower: in synthetic testing with damped oscillatory recovery
In fig. 2a, all components of voltage across a breaker (in
this case a 24 kV generator breaker) are outlined.
III 2.2 Synthetic tests
III 2.1 Direct tests In synthetic test circuits, normally applied for high-voltage
For general purpose circuit breakers, IEC 62271-100 clause circuit breaker testing, current is normally supplied by a
6.104.7 [1] requires the presence of at least 95% of the generator (or power grid, or capacitor bank) and recovery
(phase-to-ground) power frequency voltage until 300 ms voltage is supplied by a pre-charged capacitor bank.
after interruption. This is to verify the dielectrical withstand Whereas such a capacitor bank is very well suited to supply
of the breaker also beyond the TRV region, where the the adequate TRV, it cannot maintain an adequate recovery
switchgear has not yet reached a mechanically (and possible voltage for a sufficiently long time.
dielectrically) stable situation. Basically, there are two possibilities:
In direct test circuits, where current and voltage are supplied 1) Maintain the remaining capacitor bank voltage as a
from the same source, this is a natural situation. In this unipolar (DC) voltage across the breaker. This is
unrealistic, and stresses the test-object in a way very

CIRED2009 Session X Paper No 0393 Page 2 / 4


CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009

Paper 0393

different from reality. This situation is shown in fig. 2b.


2) Realization of a damped oscillatory voltage by applying
current: 50 kA/div
a large inductor across the capacitor bank. Strong
1 0 0

cs
voltage: 10 kV/div
damping can not be avoided in the circuit, even when 5 0
time: 20 ms/div

inductors with a high quality factor are applied.


In both cases, for general purpose circuit breakers, IEC 0

62271-101 [4] clause 4.1.3 allows recovery voltage to drop


not lower than 50% of the rated phase-to-ground voltage
- 5 0

after 100 ms. Although this is also not realistic, it is a - 1 0 0

generally accepted compromise. TRV


- 1 5 0

IV GENERATOR BREAKER TESTING


- 2 0 0

IV 1 Direct testing current

Since the transient recovery voltage for generator breakers - 8 0 - 6 0 - 4 0 - 2 0 0 2 0 4 0 6 0 8 0

is much steeper than for general purpose breakers, testing of Fig.3: Interruption of 80.1 kARMS current with 53% asymmetry
these breakers is not straightforward. Conventional direct by a vacuum generator circuit breaker. cs: contact separation.
test-circuits are normally designed for distribution breakers The figure shows one phase of a three-phase current.
and may have problems with these steep TRVs. This is
circuit is necessary to produce a realistic arc duration in
mainly due to the relatively large capacitance of the supply
synthetic tests.
transformers, that limits the upper frequency of transient
Basically, three-phase- or single phase currents are applied:
recovery voltages. For KEMA, generator breaker TRVs can
1) Three-phase current tests correctly represent the dynamic
be produced in direct three-phase test circuits roughly up to
interaction between the phases as well as between
17.5 kV rated voltage. This was demonstrated with a
extinction chambers and mechanism. Experience at
vacuum generator breaker rated 17.5 kV successfully tested
KEMA with this circuit is up to 120 kA at 25.3 kV [6].
up to 80 kA [5]. In fig. 3, the result (of one pole of such a
2) Single phase current tests. In case the circuit breaker
breaker) is demonstrated. In this case, test current with an
poles share a single common drive, verification of the
RMS value of 80.1 kA with an asymmetry of 53% reached a
influence of the three-phase current and arc on the contact
peak value of 230 kA.
motion is necessary. This is done by comparison of the
mechanical contact travel characteristics recorded during
IV 2 Synthetic three-phase testing
In this case KEMA’s synthetic installation is added to the direct three-phase make and break tests at full current
high-current circuit. Hereby, the appropriate values of TRV with these characteristics during the single phase test.
can be produced using the current injection method. This philosophy is taken from IEC 62271-100 and is not
KEMA’s synthetic installation is a double LC circuit described in ANSI/ IEEE. Experience at KEMA with this
(energy 2*1.7 MJ), that enables three-phase synthetic circuit is up to 210 kA at 25.3 kV [7].
testing. One LC circuit applies the adequate TRV on the
first pole-to-clear- and the other circuit applies TRV across IV 4 Hybrid direct - synthetic testing
In order to fulfil Siemens' requirements of producing both
the last clearing poles.
generator breaker TRV as well as a constant power
frequency recovery voltage, a new type of (single phase)
IV 3 Single-phase synthetic testing
This method is used for testing the larger SF6 and airblast circuit is developed and tested that combines the advantages
units typically 25 kV with 100 – 120 kA (for generators in of direct and synthetic circuits. It has the capabilities to:
the order of 1000 MVA). The main problem is in the - produce the required fault current;
magnitude of current involved (up to 600 kApk). This - produce TRV's of steepness adequate for generator
requires very tight control of the extreme forces on the breakers as in IEEE C37.013;
conductors supplying the main current. Specially designed - produce realistic, constant power frequency recovery
heavy buswork is in use, yet allowing a certain degree of voltages (not specified in IEEE, but specified in IEC);
flexibility. This is connected to the main 400 kA busbar - independent control of current, TRV and RV voltages in
system of the laboratory which is directly connected to the development tests;
current source (four generators in parallel). - realistic simulation of events occuring at restrike. Upon
In these tests one synthetic unit supplies TRV to the first restrike, upto the full fault current is provided by the
clearing pole, the other unit is used for arc prolongation. A current circuit.
method for arc prolongation is developed that can produce At the same time, a number of challenges had to be met, the
far higher current than the arc prolongation circuits most severe one dealing with arc prolongation. Arc pro-
normally used in high-voltage synthetic testing. Such a longation is necessary in synthetic testing, because, unlike in
direct test circuits, the adequate TRV can only be applied at

CIRED2009 Session X Paper No 0393 Page 3 / 4


CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009

Paper 0393

80
voltage [20 kV/div] current [20 kA/div]

V SUMMARY AND CONCLUSIONS


60 transient recovery voltage

40 power frequency recovery voltage


At higher rated voltages (> 15 - 17 kV), in order to obtain
the required very steep transient recovery voltage generator
20
breakers can only be tested in synthetic circuits. Standard
0 synthetic circuits do not have the opportunity to supply
-20 power frequency recovery voltage as in reality. To
-40 recovery voltage overcome this deficiency, a hybrid test circuit has been
current
developed, able to provide both transient - as well as power
-60
frequency recovery voltage.
-80
250 300 350 400 450 500 550 600 650 700 Now it is possible to test with voltages in conformity both
time [50 ms/div] with the generator breaker standard regarding transient
50 recovery voltage as well as with the general purpose breaker
transient recovery voltage standard regarding power frequency recovery voltage.
40 This guarantees full equivalence with reality.
TRV [10 kV/div]

30
REFERENCES
20
[1] IEC 62271-100, High-voltage switchgear and controlgear –
10
Part 100: Alternating-current circuit-breakers, 2008
0
[2] IEEE Std. C37.013-1997: "Standard for AC-High Voltage
Generator Circuit Breakers Rated on a Symmetrical Current
-10 Basis", IEEE New York
341.9 341.92 341.94 341.96 341.98 342
[3] IEEE PC37.013a/D6, Nov. 2006, "Standard for AC High
time [20 us/div]
Voltage Generator Circuit Breakers Rated on a Symmetrical
Fig.4: Result of test with vacuum generator circuit breaker (24 kV Current Basis - Draft Amendment 1: Supplement for use with
50 kA) in accordance with IEEE C37.13 and continuous power Generators Rated 10 - 100 MVA", IEEE New York
frequency recovery voltage. Upper: Full interruption, incl. current [4] IEC 62271-101 High-voltage switchgear and controlgear –
and 60 Hz recovery voltage lower: transient recovery voltage Part 101: Synthetic testing, 2006
[5] R. Smeets, J. Hooijmans, J. Jäger, N. Anger, Test experiences
with a new generator circuit breaker based on vacuum
a single current zero. This implies that a suitable method technology, CIRED Conference 2007, paper 0383.
must be applied to test with the same arc duration as [6] R.P.P. Smeets, W.A. van der Linden, 1998, "The Testing of
expected in reality. Normally a so-called Re-Ignition Circuit SF6 Generator Circuit-Breakers", IEEE Trans. Pow. Del.,
(RIC) is applied, forcing a reignition in the breaker on a vol.13, no.4, pp. 1188 - 1193
microsecond scale. Traditional RIC’s that are commonly [7] R.P.P. Smeets, H.D. Barts, L. Zehnder, 2006, "Extreme
used at high-voltage SF6 circuit breaker testing rely on a Stresses of Generator Circuit Breakers", CIGRE Conference,
paper A3-306
charged capacitor that releases its energy by means of a
steep current pulse just before the moment the breaker
would interrupt the test current. The zero crossing of the
current is now forced by this current, that is much steeper
(several hundred A/µs) compared to the decline of the
power frequency short-circuit current (few tens A/µs).
Vacuum circuit breakers, however, have such an excellent
interrupting capability that they can interrupt even the steep
current pulse of the RIC. An adjustable and modified RIC
has been used to gain experience in this field. In com-
bination with a high-frequency and high-resolution
measurement the critical parameters that result in a reliable
reignition could be identified.

A result of such a test is shown in fig. 4. The test-object is


shown in fig. 5. An interesting feature for development
testing is the possibility to control current, TRV and RV
completely independent from each other. In one of such
single phase tests, power frequency recovery voltage up to
26.1 kV did not result in a restrike after interruption of 51.5
kA.
Fig. 5: Siemens vacuum generator breaker 3AH3727-8 at KEMA

CIRED2009 Session X Paper No 0393 Page 4 / 4

Potrebbero piacerti anche