Sei sulla pagina 1di 12

21, rue d’Artois, F-75008 Paris Session 1998

http://www.cigre.org 12-308 © CIGRÉ

DESIGN AND APPLICATION OF VARIABLE MVAR OUTPUT


SHUNT REACTORS WITH ON LOAD TAP-CHANGER.
OPERATION EXPERIENCE IN AFRICA

by

G. BERTAGNOLLI A. BABARE F. ILICETO*) F.M. GATTA


ABB Trasformatori Consultant on Power University of Rome "La Sapienza"
Legnano (Milano) Transformers, Milano Roma
(Italy)

Summary1 The long transmission distance requires the choice of a HV,


say in the range of from 110 kV to 220 kV. Consequently, the
The technical requirements of charging power compensation LLLHV lines transfer initially only a fraction of surge
of long lightly loaded HV lines are at first discussed. impedance loading (SIL). The 3- phase short circuit power can
The concept and special design criteria of shunt reactors be of the same order of magnitude as the line charging power.
with variable Mvar output obtained by means of tapped This occurs at both the terminals if the LLLHV line originates
windings and on-load-tap-changer are presented. The feasible from a very small power plant. If the power source is strong, it
Mvar regulation range and size of steps, as a function of reactor occurs at the receiving end of very long lines. Consequently, line
rated voltage and power, are discussed. no-load energization and operation at low load, may require a
The analyses are reported of voltage regulation quality, compensation of the line charging power close to 100%,
voltage stability and overvoltages containment for a 161 kV long reasonably distributed along the line, to limit the injection of
radial system compensated with variable Mvar output shunt charging power into the feeding source and obtain an acceptable
reactors. voltage profile.
A comparison is made of the cost and losses of the novel Part of the necessary shunt reactors must be controllable,
shunt reactors, of conventional reactors and of thyristor continuously or in steps, as a function of line load variations and
controlled reactors. load power factor. Other requirements for shunt compensation
The 10-year operation experience of four 161 kV variable equipment to be installed in isolated regions of developing
Mvar output shunt reactors in Ghana is reported. At last, countries are low initial and operation costs, and simplicity of
recommendations are made for the specification and testing of operation and maintenance.
the novel type of shunt reactors. Use of shunt reactors with Mvar output controllable in steps
may also be of interest for the compensation of EHV lines, in
Keywords:shunt compensation, reactor design, regulation, on- order to make infrequent the need for switching on and off
load-tap-changers, voltage stability, overvoltages. reactors and to reduce the associated voltage jump.

1. Introduction 2. Applicable shunt compensation equipment of LLLHV


lines
Vast regions of many developing countries still lack electric
energy, or only the major towns are supplied by diesel driven A feature of LLLHV lines is that for many years of operation
generators, the operation of which is both expensive and there is no need of capacitive Mvar generation at the substations
unreliable. supplying the loads or in the distribution networks, because the
In several cases, low costs and reliable electric energy residential-agricultural-commercial loads generally have a
supplies are available in hydroelectric or thermal power plants, natural p.f. that is not low (frequently close to 0.9 at the HV
located some hundreds of kilometers from the loads to be busbars) and the required Mvar can be supplied by using the
served. The problem that has to be solved is the transmission of charging power of the long HV lines, loaded below SIL (say, at
small amounts of power over distances which are very large 0.25 - 0.75 SIL). Then in the initial operation, only shunt
compared with the power involved. The required long lightly reactors with suitable control capability of their Mvar output, in
loaded high voltage lines (LLLHV lines) may be up to 600-700 steps or continuous, are required.
km in length and the initial loading may be only 5 to 30 MW. In developing regions, load may undergo large daily
variations; the minimum load can be less than 50% of the peak
*) Department of Electrical Engineering- University of Rome load. Large induction motors are used in water pumping
stations, saw mills, and some times in rock crushing plants, or
"La Sapienza", via Eudossiana 18 - 00184 ROMA, Italy
2

crop and food processing plants. Individual motors have a rated power to be absorbed by each shunt compensator may range
power generally not exceeding 200 kW, are scattered in small from 50 to 200 Mvar at 50 Hz.
groups at different locations and are started by means of This paper deals mostly with the shunt compensation of
delta/star commutation or through an autotransformer, to allow LLLHV lines with use of tapped windings variable output shunt
start-up from local diesel generators. The prevailing loads are reactors (TWVO-SRs). As justified in the following paragraphs,
lighting and other domestic-commercial-rural appliances. this compensation scheme has the following features:
An important peculiarity of these loads is that they do not - with the usual number of taps of commercial OLTCs, it allows
cause sudden and repeated large variations of active and an almost continuous var-voltage control in normal operation
reactive power demand and therefore in normal operation they (see par. 7);
do not require a fast response of the Mvar compensators, as is - with appropriate var ratings, location, design and, where
needed by certain large industrial or electric traction loads. required, switching of TWVO-SRs, it allows trouble-free
Shunt reactors can be applied as follows: transient behaviour of LLLHV lines (see par. 8);
A. Conventional shunt reactors split in small units, most of - use of HV TWVO-SRs is the least costly among Solutions A,
which are individually switchable with a circuit breaker, to B and C, for the LLLHV lines with rated voltage in the range
allow Mvar control in large steps. The acceptable Mvar rating from 110 kV to 220 kV (see par.9).
of shunt reactors is limited by the voltage jump at switching The conceptual design and Mvar variation range of TWVO-
on and off, readily calculated with the known formula: SRs are examined also for the EHVs, up to 525 kV

∆Vi%=100 (∆Qi/Psc,i ), (2.1) 3. Conception and design of HV and MV TWVO-SRs with


OLTC
where ∆Qi is the reactor Mvar rating at operation voltage
and Psc,i is the short circuit power at node i. Psc,i can be 3.1 Basic concepts on conventional shunt reactors
calculated by assuming constant voltage at the nodes with fast
acting regulation equipment: power plant busbars, if their There are two basic designs of shunt reactors: namely
Mvar regulation capacity exceeds ∆Qi and their voltage coreless and gapped-core. For technical reasons, in most cases
correction time is neglected (usually, it is less than 1 s). preference is given to gapped-core reactors. At a quick glance,
The acceptable voltage jump, ∆Vi, depends on the frequency the core-and-coil structure of a gapped-core reactor looks quite
of its occurrence in operation and on the required quality of similar to that of a core type transformer, with the obvious
service to consumers. In highly electrified countries, a rule difference that in the reactor there is only one winding per
for good service is ∆Vi%≤3% for daily switching of shunt phase. The main peculiarity lies in the physical structure of the
reactors or capacitors. In developing countries, the ∆Vi limit core limbs bearing the coils, which hold built-in non-magnetic
can be raised, say up to 4-5% for daily switching and up to 7- gaps along their length (see Fig.1). The gaps are needed for
8% for very infrequent switching. increasing the reluctance of the magnetic circuit and decreasing
B. Use HV shunt reactors with variable Mvar output in steps, by the inductance of the winding proportionally.
means of tapped windings and on-load-tap-changer (OLTC), Each gapped limb consists of a number of cylindrical core
firstly proposed in [1] [2] . As justified in par. 4, the Mvar sections piled up one on top of the other, separated by spacers
regulation range can be from 40% to 100% for HV reactors made of a very stiff and inert material, like ceramic or slate,
(BIL of 650 to 950 kV) and from 30% to 100% for MV forming the gaps. The core sections are built in the form of
reactors. Then the need to switch these reactors on or off cylindrical blocks of radially laminated core steel sheets
(with OLTC set for minimum Mvar output prior to switching) arranged in a wedge shaped pattern. Each block is moulded in
becomes infrequent. Part of these reactors may be required to epoxy resin to a solid piece, which includes the spacers glued at
be always in service (at minimum Mvar output at peak load). the top surface of the block. The radial configuration of the
C. Use thyristor controlled reactors (TCRs), which provide laminations is such that a laminated surface is presented to all
continuous fast var control. The TCRs are usually connected of the fringing flux crossing the gaps. This is highly effective for
to the HV line terminals via an HV/MV step-down minimizing the losses caused by eddy currents at the end parts
transformer, and should be preset to absorb the line charging of the core sections, and enables the subdivision of the required
power, prior to energization as one block with the total gap length into a relatively small number of fairly wide
compensated line. This requires special circuits, because no gaps instead of many thin gaps.
synchronized driving voltage is available at the line receiving
end. Even if TCRs allow a very fast var control, the actual
control speed is to be limited to avoid voltage instability, Yoke
because the short circuit power may be very low in LLLHV
lines.

An objection to the application of TCRs in isolated regions Spacer


Outer leg
of developing countries is that they need specialists for
troubleshooting and repair. Drawbacks of TCRs are high cost
and high losses compared with conventional or tapped windings
shunt reactors (see par.9), and their generation of some Core section
harmonic currents.
By considering the application of a var shunt compensator
every 150 to 250 km of LLLHV line operated at 50 Hz, with
rated voltage in the range 110-220 kV, the 3-phase charging
power to be absorbed by each compensator may range from 7.5 Fig. 1- Magnetic circuit of a single-phase gapped-core shunt
to 35 Mvar. At rated voltages of 380-500 kV, with a var reactor
compensator every 200 to 300 km of line, the 3-phase charging
3

A peculiarity of a gapped-core reactor is that there are The time derivative of energy is the instantaneous power,
pulsating attraction forces at twice the power frequency acting p(t), exchanged with the source:
within the core structure because of the different permeabilities dE 1
p( t ) = = ω L I m sin( 2ω t ) [W]
2
of the materials of gapped limbs: core steel laminations and
spacers. In gapped-core reactors it is necessary to design the dt 2
core parts so that they are strong, stiff and sufficiently
The reactive power, or rated power, QN, of the reactor is the
prestressed to handle the force without excessive strain or
displacement of the parts. The mechanical arrangement shall peak value of p(t):
2
then be adequate to compress each core column with the due U
QN = ω L I = X I = = U I [VAr] , (3.2.2)
2 2
force, attaining some hundreds kN in large units. A well X
designed mechanical structure is essential for assuring small
vibration amplitudes in the various parts of the reactor and a where I=Im/√2 is the r.m.s. value of current [A], U is the r.m.s.
low acoustic emission. value of the AC supply voltage [V] and X =ωL is the reactance
Finally, the winding and the main insulation structures of of the reactor [Ω ].
reactors do not differ significantly from those of power Energy is stored mainly in the gaps (70%-90%, depending on
transformers, with one exception: as shunt reactors do not the reactor voltage) and the rest in the cylindrical duct and in
undergo any short-circuit events, the mechanical requirements the winding. The reactive power in the reactor is shared in the
for the windings are far less stringent in reactors compared with same proportion. If, for sake of simplicity, the gap volume only
transformers. is considered, the following considerations can be made:
• for a given flux density in the gap region, the gap volume is:
3.2 Reactor design fundamentals
2 µ0 Q N
Vg = [m3];
ω Bg
2
From the magnetic circuit theory and Hopkinson's law, the
following expression is applicable to reactor magnetic circuits: • by selecting the cross sectional area for the gaps, Ag [m2],
N i = Φ Rm [A], the total gap height can be calculated;
where: N i is the magnetomotive force (amperturns) [A]; Φ is • the number of turns of the winding is:
the magnetic flux [Vs]; Rm is the reluctance [H-1]. L gt
In the unsaturated state, the reactor is a linear circuit, the N = ;
inductance of which is: Ag µ0
L = N Φ / i [H], • the total height of the winding is calculated on the basis of a
where N is the number of the turns of the winding. reasonable value of the magnetic field intensity and of
The two above equations yield: dielectric requirements;
2
N • the mass and the volume of the winding are calculated upon
L= (3.2.1) setting the current density value;
Rm
• the total gap height is subdivided into a number of gaps of
The inductance is proportional to the square of the number equal height, not too large, to avoid problems due to the
of turns. The reluctance Rm depends only on the geometrical fringing of the flux in the gap region.
properties of the flux path within the winding space, as the
reluctance of the external ferromagnetic path can be 3.3 Gapped-core shunt reactors with variable Mvar output
disregarded. There are two paths in parallel in the winding
volume, one through the gaps and another through the If one disregards the possibility of exploiting the non-linear
cylindrical duct between the core limb and winding, and in the magnetic properties of the steel laminations - which would
winding itself. The flux densities are quite different in the two entail problems and negative effects - the equations of par. 3.2
spaces. According to the equation: give evidence that variable Mvar outputs can be achieved by
N i µ0 means of each one of the following measures:
B= [T],
h - variation of the gap volume
⋅10 − 6 [H m-1] is the permeability of air, both
- variation of the number of turns in the winding
where µ 0 = 1256
.
The change of the gap volume achieved by altering the gap
flux densities are proportional to the magnetomotive force N i length, is actually adopted in a few cases: for example in arc
produced by the winding. The induction in the gaps, Bg, is suppression coils (Petersen coils), where any tuning of the
inversely proportional to the total length, gt, of the gaps, and the inductance is achieved by means of a plunger or sliding core
induction in the duct, Bd, is inversely proportional to the axial moved by a motor drive. However, such arrangements are
length of the winding. restricted to the lower reactive power range (some thousands
The energy in the reactor, E, is: Kvar) and are impractical for larger continuous ratings, due to
E=
1
2
2
Li =
2 µo
1
(B 2
g Vg
2
+ B d Vd ) [J], the problems associated with the magnetic flux control in large
gaps and with the overall mechanical behaviour of the device.
where i is the value of the current [A], Vg=Ag gt is the total The other alternative relies on the variation of the number of
volume of the gaps [m3], and Vd is the total volume of the turns in the winding, and is accomplished in the same and very
cylindrical duct and of a part of the winding [m3]. reliable way which the manufacturers of power transformers
With a sinusoidal voltage excitation at frequency f [Hz], the have been adopting for decades, that is by switching in or out,
current is also sinusoidal: by means of an OLTC, the turns of a tapping winding supplied
purposely in addition to the main winding. The maximum Mvar
i =Im sin (ω t), where ω= 2 π f
output corresponds to the minimum number of turns inserted
and the energy E(t) stored in the circuit at time t is:
and vice versa. As shunt reactors for HV and EHV applications
1
E( t ) = L I m sin ( ω t )
2 2 are star connected and the neutral terminal has graded
[J]
2 insulation as allowed by the grounded neutral (solidly or
4

through a neutral grounding reactor), the most suitable electrical 4.1 Number of OLTC tap positions
location of the tapping winding is at the neutral side. This
arrangement allows the use of three-pole star point OLTCs in The minimum number of taps should be chosen, if
three-phase reactors. compatible with other constraints, like the capabilities of
The reactor's inductance is substantially proportional to the standard type OLTCs and the allowable busbar voltage change
square of the number of turns (see par. 3.2, equation (3.2.1)). at the installation site consequent to a tap changing operation. If
The minimum number of turns giving the maximum Mvar one excludes any special OLTCs, the products commonly
output is assumed to be the unit reference value for the turns. available on the market are built with a number of steps ranging
Let us define the required ratio of the TWVO-SRs: from 9 to ±17, resulting in 10 to 35 tap positions. Especially
Minimum Mvar output when a high number of taps is required, the use of a change-
K= ; over selector implying a coarse-fine tapping winding
Maximum Mvar output
arrangement or a polarity reversal applied to a fine tapping
then the winding turns, ∆T, to be added in order to attain the winding allows the number of contacts needed on the OLTC tap
minimum Mvar output, expressed in p.u. of the above reference selector to be halved (see Fig.3). The chosen number of tap
value, are (see diagram in Fig.2): positions shall fall within the limits set above.
1
∆T = − 1
K 4.2 OLTC maximum rated step voltage
It is easy to recognize that, starting from K=0.6 downwards,
the p.u. turns, ∆T, to be added increasingly exceed the usual This is one of the most important factors to be considered when
tapping ranges adopted in power transformers. This has an setting the feasible regulation range of a TWVO-SR. All
impact on the following quantities: calculations shall be based on the specified maximum
- number of tap positions needed for the OLTC continuous operating voltage of the reactor which usually
- OLTC step voltage exceeds the rated voltage of the network by 5 or 10% .
- physical size of the tapping winding
- differential voltage across the whole winding (fixed part +
tapping winding) and across the tapping part when lightning
and switching overvoltages are applied to the TWVO-SRs
1 2 1 3 2 1 2
with different tap positions of OLTC
- voltage to ground caused on the tapping winding by the above
overvoltages
- differential voltages originated by lightning and switching
surges across the various parts of the OLTC affecting its
internal insulation requirements a) b) c)
- difference of the Kvar steps within the range of variable Fig. 3- Basic tapping connections: a) without change-over
outputs selector; b) with coarse tap selector; c) with reversing
∆T 1/K -1 [p.u.] switch - 1) main winding; 2) fine tap winding; 3)
0.8 coarse tap winding
0.6
The performance limits of the OLTC diverter switch are set
0.4 for three quantities, namely:
Q min - maximum rated step voltage [V]
0.2 K [p.u.]
Q - maximum rated through current [A]
N
- rated switching capacity [KVA]
0 0.3 0.4 0.5 0.6 0.7 0.8 These three quantities are interdependent. In a typical
Fig. 2- Turns to be added, ∆T [p.u.], to the minimum winding voltage vs. current graph (see Fig.4), we can identify three
turns versus ratio of min. to max. Mvar output regions. A low current region (a) in which the limit is set by the
maximum rated step voltage. A region (b) with higher but less
One final factor to be considered is the physical layout of the than rated current in which the limit is set by the switching
tapped part of the winding and its geometrical position with capacity of the diverter switch. Finally, the last part (c) of the
respect to the fixed part. In this respect, the rated voltage of the graph where the limit is the maximum rated through current,
reactor plays an important role. Reactors for MV applications which defines the thermal limit also for the selector switch
allow more flexibility in selecting the location of the tapping contacts.
Ui
winding and its subdivision in taps. On the contrary, HV and U
im a
EHV applications set more stringent conditions on this and also b
on some other aspects.

4. Feasible Mvar regulation range and step size of TWVO- c


SRs as a function of rated voltage
I um I
For the assessment of the feasible regulation ranges of Fig. 4- Correlation of step-voltage, Ui and through current, I;
TWVO-SRs the quantities listed in par.3.3 should be considered Uim= max. rated step voltage; Ium= max. rated
individually. When setting values for feasibility, one has to bear through current
in mind that the service reliability of the TWVO-SRs shall not
be affected at all with respect to conventional fixed-output shunt When dealing with MV applications, the maximum rated
reactors. step voltage is never a limiting factor. On the contrary, for HV
and EHV applications, the step voltage is almost always the
5

controlling parameter of the minimum number of steps needed windings, with the various rated withstand voltages of the
in order to cover the required range of variable Mvar output. In OLTC.
fact, the rated through-current values of standard OLTCs in It is known that the interwound spiral regulation winding is
general significantly exceed the rated current of the equipment inherently exposed to high oscillatory overvoltages originated by
under consideration. the lightning and switching surges, because it is not sufficiently
Two reputable manufacturers of OLTCs list on their antiresonant as is an interleaved main winding. The application
catalogues the following maximum rated step voltage limits, of MOVs connected across the taps increases the series
Uim: capacitances, owing to the high dielectric constant of the
material, and therefore improves the distribution of transient
Production Range Uim overvoltages, even in the region of low conductivity of MOVs
Manufac. A Manufac. B (normal operation with low leakage current).
Lower range 3500 V 3300 V Another important aspect is the physical location of the
(300 A - 600 A) tapping windings with respect to the main winding, which also
Upper range 5000 V 4000 V to influences the transient voltage behaviour. The problem is
(1000A-2000A and above) 5000 V negligible for MV applications. On the other hand, for EHV
The minimum number of taps consistent with the above applications (400 kV and 500 kV), the feasibility of placing the
limits is to be selected, with due regard also to the cost of the tapping windings in the duct between the gapped limb and the
OLTC. In this context, it is advisable not to use for example an main winding should at least be checked carefully, as this layout
OLTC of the upper range simply to reduce the number of taps, if is well consistent with the splitting of the main winding in two
the current requirement is fully compatible with the lower range parallel parts axially superimposed, with the EHV line terminal
equipment. at the centre. Inner side tapping windings lead to an increase of
As a first estimate, the minimum number of taps, Nmin, to the size of the duct between core limb and main winding, as
be foreseen in the fine tapping winding can be calculated by well as of the mass. However, the enlargement of the duct also
means of the following expression: provides a benefit in terms of increase of inductance.
n max − n min In the HV TWVO-SRs, when the main winding is not split
N min = U m , into two parallel parts and the HV terminal is close to the upper
2 n min U im yoke, the regulation winding should be placed externally. This
where: Um is the maximum continuous phase-to-ground solution simplifies the insulation, makes the tap connections
operation voltage [V]; nmax and nmin are the maximum and very easy, and could be realized with a progressively increasing
minimum number of turns; Uim is the OLTC maximum rated number of the turns per step so that the Kvar steps are equal or
step voltage [V]; the factor 2 in the above equation accounts for almost equal (see par.4.5). An outer regulation winding is still
the use of a coarse-fine or a polarity reversal tapping feasible if the main winding has the HV terminal at the center;
arrangement. however in this case it must be realized in two parallel parts as
the main winding, and insulation is more complex.
4.3 Physical size of the tapping winding In conclusion, the electrical design of the tapping winding
and connection leads is a key aspect as regards TWVO-SRs.
The physical size of the tapping winding is directly
dependent on the extension of the tapping range with respect to 4.5 Difference of amplitude of the Kvar steps within the variable
the fixed part of the winding. This factor is more important in output range
HV and EHV applications because the dielectric requirements
for the tapping windings are more severe and result in more Winding tapping arrangements based on equal or fairly
stringent conditions when selecting the winding configurations. equal numbers of turns per step, as is customary in power
One should avoid tapping windings consisting of more than two transformers, produce in TWVO-SRs uneven reactive power
or three physical parts (shells). steps at subsequent tap changings. The Kvar output change for
the various taps differs according to the position of OLTC, it
4.4 Differential transient voltages within single windings, being the largest when the minimum number of turns is inserted
between windings and OLTC parts, and to ground. (position of max. Mvar output).
Graph a of Fig.5 shows the ratio max. to min. Kvar step as a
This is a rather complex matter, affecting the physical layout function of the design ratio K of TWVO-SR when the tapping
of the tapping windings and their location with respect to the range consists of 16 steps with a constant number of turns per
fixed part of the winding. The amplitude of the tapping winding each step. It is evident that the Kvar difference becomes large, if
or windings in terms of turns and their performance in terms of K is lower than 0.5.
lightning impulse voltage distribution, are both important
factors in HV and especially in EHV applications. The tapping ∆ Q max
windings shall be designed for high internal capacitance so as to ∆ Q min

reduce the amplitude of the voltage transients during lightning 4


and switching surges. Any presence of large voltage swings
3
would require heavy and complicated insulation structures for
their containment. The calculation of the impulse voltage a
2
b
distribution must be carried out for different tap positions and
the worst condition should be considered for design purposes. 1 c Q min
K
At least in the EHV TWVO-SRs, the use of metal oxide Q
N
varistors [MOVs] connected across taps, as applied on power 0
transformers, is worth considering for a better control of the 0.4 0.5 0.6 0.7
overvoltages. It is essential also to check the compatibility of the Fig. 5- Ratio of max. to min. Kvar step across the tapping
absolute and differential voltage values calculated for the range, versus ratio K; OLTC with 17 positions; a): with
6

equal number of turns per step; b): by connecting any In laying down the graph, the authors have tried to take into
second spiral end to selector for part of winding; c): account different aspects in a general view and to make a
with steps of progressively increasing number of turns judgement, bearing in mind that what can be considered still
technically affordable is not always economically convenient
Based on service requirements, arrangements resulting in too.
even or fairly even steps Kvar are far more preferable (∆Qmax/ For MV applications, K ratios down to 0.30 can be
/∆Qmin≅1; graph c in Fig.5) . The solution is to consider tapping considered still achievable.
windings with steps of progressively increasing number of turns TWVO-SRs with output variable from 7.2 to 18 Mvar at 161
per step. Such a layout can be accomplished fairly easily in MV kV (K=0.4) in 20 steps, are planned for application in a new
applications, where the dielectric constraints are less stringent. LLLHV line in West Africa.
Layer type windings with taps brought out radially at increasing
intervals is a simple solution. 4.7 Remarks concerning the OLTCs
In the HV range each case shall be considered separately.
For example, when interwound spiral taps (loop layer winding) The switching conditions of OLTCs equipping TWVO-SRs
are adopted, as the turns per spiral cannot differ mutually by differ from the those occurring on power transformers, the
more than one turn, a solution is to still connect all spirals in reason being that in shunt reactors the load current has a 90° lag
series, bringing any second spiral end to the OLTC selector referred to the voltage. This does not affect the behaviour of the
contacts for a part of the winding. With this arrangement some OLTCs, as ten years of positive operation experience has
steps will have double the number of turns compared with the demonstrated (see par.10). Being the total current during a
remaining ones. However, in this case the voltage across two switching operation the sum of the load current and of the
spirals in series shall be checked so they are still compatible temporary current flowing through the transition resistors, and
with the OLTC max. rated step voltage. Graph b in Fig.5 shows owing to the phase shift of these two components, a lower total
how this arrangement can reduce the ratio of max. to min. Kvar current value is attained and the switching operation is
steps across the tapping range. somewhat relieved.
Another means for reducing the Kvar steps unevenness The conclusion is that the conventional and thoroughly
consists of equipping the OLTC motor drive unit of the TWVO- tested OLTCs are ideally well suitable for application on
SR for the automatic jump over of positions across the end part TWVO-SRs. In this context, it appears premature to consider
of the tapping range. other types of OLTCs, like for example static electronic tap
In EHV applications there are more restrictions for adopting changers, which would have the advantage of an extremely fast
steps consisting of a high difference in the number of turns. On response time. Such devices are suitable in terms of current
the other hand, EHV applications are also those for which low performance, but are still deficient in terms of step voltage and
values of the K ratio cannot be attained (see sub-par.4.6) and insulation performance, at least in comparison with the standard
therefore unevenness of Kvar steps is reduced (Fig.5). types.

4.6 Feasible Mvar regulation ranges of TWVO-SRs as a 5. Planning of shunt compensation schemes of LLLHV
function of voltage and rated power lines by means of TWVO-SRs

An attempt has been made to condense the various technical The LLLHV lines may require a shunt compensation close
issues connected with the design of TWVO-SRs into a graph to 100%, to limit the injection of charging power into the
(see Fig.6), showing the feasible regulation range of such feeding source at no-load and low load, and to allow the
devices as a function of their rated or maximum continuous emergency line no-load energization and operation even with
operating voltage. Any reference to the maximum rated power one shunt reactor out of service for repair or maintenance.
has been omitted intentionally, as power in itself does not set When the length of a radial HV line exceeds 300-400 km,
any limits, at least in the range of usual applications. part of the shunt compensation should be connected to the
The graph is a guide and is not intended to be exhaustive. In receiving end, and part to one or more intermediate stations, in
the area above the dashed part, feasibility is basically taken for order to allow for:
granted. It the area below the dashed part, more or less severe - an easy line no-load energization, by switching on the line
restrictions are to be expected. The dashed zone covers sections one by one in succession, with a preconnected shunt
applications where more detailed investigations are required in reactor, possibly located at the receiving end of each long
each individual case. section;
Q min - a good (flat) voltage profile along the line in any operation
K condition;
Q
0.6 N - an acceptable transient performance of the transmission
system, in particular: limitation within acceptable values of the
0.5 temporary overvoltages caused by line energization, load
rejection, unsymmetrical faults to ground, etc.;
0.4
- good steady state and dynamic voltage stability;
0.3
- feasibility of line single-pole high-speed reclosure.
In most LLLHV lines, intermediate substations for the
110 525
supply of important loads along the line route are necessary.
However, these stations are generally not evenly distributed
0 100 200 300 400 500 U m [kV] along the line. For example, the initial LLLHV line of Northern
Fig. 6- Feasible regulation ratio, K, of TWVO-SRs versus the Ghana [2] (see Fig.8) was 526 km long (750 km from power
highest operation voltage source to remote end) with one lateral line and two intermediate
transformer stations subdividing the line in three sections of 119
km, 248 km and 159 km, respectively.
7

If the load is concentrated at the line receiving end, total If the line is loaded below SIL, some TWVO-SRs will need
load rejection is a credible event. If the load is distributed along to be always in service, also at peak load demand, with the
the line, the load rejection at the same instant in all the OLTC set for low or minimum Mvar output. In this case, a
substations is very unlikely and the partial load rejection TWVO-SR can be solidly connected to the line end, without a
overvoltages are much reduced. CB, simply by means of a disconnecting switch. Of course, with
For an assigned total Mvar capacity of shunt compensation, this arrangement the protection of TWVO-SRs requires a
the choice of the rating of each TWVO-SR should be based on reliable telecommunication channel, for the fast transfer tripping
the following requirements: of the line at the sending end in the case of fault in the reactor.
(i) The minimum Mvar output (see Fig.6) shall not exceed the As justified in par. 8, power transformers located at the end
value, ∆Qi, calculated by formula (2.1), by entering for or in intermediate substations of a LLLHV line where the short
∆Vi% the voltage jump permitted for very infrequent circuit power is low, should never be energized in a block with
switching, say 6% to 8%; the supply line, to avoid the risk of ferroresonance overvoltages.
(ii)The permitted size of the Kvar steps of the OLTC should be Time delay undervoltage relays should be installed in each
calculated again using formula (2.1), by entering for ∆Vi% a substation, to trip out all the power transformers and all the
value of 1-1.5%, as normally accepted for the steps of associated MV feeders in case of outage of the supply line. Each
OLTCs of power transformers. In fact, it is expected that the transformer will be re-energized at no-load, following busbar
OLTC of TWVO-SRs may run through the full regulation voltage restoration, and MV feeders will be picked up one by
range twice in a day (1 up + 1 down) to compensate for the one thereafter.
day-to-night load demand variations, with one or two Energization or de-energization of a TWVO-SR is required
possible additional partial runs during the daylight hours. only in infrequent cases. This is to be made by adjusting the
The 1-1.5% voltage change limit normally does not impose OLTC for minimum Mvar output prior to switching, such as:
an increase of the number of taps available on commercial - voltage jump is minimized;
OLTCs, which is more strictly controlled by the need of - inrush current is negligible, since with all the turns in the
limiting the step voltage on regulation windings and OLTC circuit the flux density in the core is very low and TWVO-SR
(par.4). behaves like a linear reactor;
(iii) If possible, the TWVO-SRs to be installed along a LLLHV - the electrodynamic stresses in the windings are negligible;
line, should be identical for the sake of standardization. - saturation of core and any harmonic distortion thereof is
If the number of TWVO-SRs arrived at with criteria (i), (ii) avoided, also in substations where short circuit power is very
and (iii) is lower than the number of sections in which the line low.
is divided by the transformer stations, some reactors may be Operation of OLTCs of the various TWVO-SRs of a LLLHV
located so as to compensate adjacent short lines. If the required line is to be carried out in a consistent manner, in order to keep
TWVO-SRs exceed the number of line sections, two reactors a flat voltage profile along the line in spite of load variations, as
should be installed in substations where long lines terminate. shown in par.7.
It is necessary to avoid a possible interference and hunting
6. Switching procedures of TWVO-SRs and LLLHV lines of the OLTCs of reactors located in different substations, among
them and with the OLTCs of power transformers, liable to cause
HV TWVO-SRs can be connected to the line terminals or to unnecessary wear of OLTCs. This can be achieved by manual
the substation busbars. Connection to the line terminal, control of reactor OLTCs, by local operators if substations are
preferably at receiving end, allows the energization of the line manned, or by manual remote control from the Network Control
and associated reactor as one block. By adjusting the OLTC, Center if substations are unmanned. Alternatively, if the
prior to energization, for a Mvar output about equal to line LLLHV line is supervised by a SCADA system, a computer
charging power, the energization is achieved without any program can be implemented for the on-line coordinated
voltage jump at the energizing busbar. This is useful when the automatic control of the OLTCs of the various reactors; the
network has a low short circuit power at the node of supply, and busbar voltages, the busbar loads where appropriate, and the
in particular when the last section of a long radial line is actual positions of OLTCs of reactors in service should be
energized. Energization of TWVO-SR terminated lines also telemeasured from the various substations to the Control Center
reduces the switching overvoltages (see par. 8). and input to the programme.
It should be noted that, in a radial transmission system with In any case, the OLTCs of transformers can be operated
power supply from one terminal only, the connection of a reactor automatically by the AVR in each substation, as usual.
to the substation busbar (Fig.7a) instead of to the line end In case of load rejection at the remote end of a LLLHV line,
(Fig.7b), makes no difference as far as line no-load energization or simultaneously in more than one substation, two simple
is concerned, because the substation is de-energized when the automatic protection schemes can be applied, as follows:
line is out of service on the power source side. Therefore the (i) Switch-on the TWVO-SRs that are out of service, by means
reactor can be preconnected to the line end prior to energization of overvoltage relays with a time delay of 1-1.5 s. This
by closing both the line and reactor circuit breakers (CB1 and requires operation of the reactor CB under potential on line
CB2 in Fig. 7a). side in open position, an operation mode well acceptable for
CB1 modern SF6 CBs. The OLTC of stand-by reactors can be
preset for max. Mvar output, if appropriate.
Optional CB (ii)If provision (i) is deemed to be not fast enough, trip-out
instantaneously, at sending end by transfer tripping, the long
CB2 line sections that happen to be operated open ended.
Transfer tripping, on available telecommunication links, is
to be initiated at the line section receiving end,
a) b) instantaneously by the load rejection (line open-ended).
Fig.7- Connection to the network of TWVO-SRs: a) to
substation busbar; b) to line end
8

7. Analysis of normal operation of a long radial 161 kV line V [kV] V [kV]


compensated with TWVO-SRs. Steady-state and 160
160
dynamic voltage stability
Kumasi
The results of the analyses are reported for the 161 kV Bol 17 10.6 8.5 0 0 140
LLLHV line of Northern Ghana, represented in Fig.8. The Tam 17 All SRs
15.9 13.8 15.9 8.5 outaged
circuits represented with solid lines have been in operation at Tec 11.1 15.9 8.5 8.5 9.6 Sawla
161 kV for about 10 years. The circuits represented with dotted Saw 11.3 9 9 9 0 Sunyani 120
lines, at present in operation at 34.5 kV, will be up-rated to 161
Tamale
kV in 1998-2000. a
100 Bolgatanga 100
Tumu Bolgatanga ~ ~
0 10 20 30 40 50 60 70 80 Ptot [MW]
40 VCPI Mvar
Mvar
b
Q [Mvar]
Tamale Kum
Sawla 20
Yendi VCPI
0

Q Kum
-20

-40
0 10 20 30 40 50 60 70 80 P [MW]
tot
Techiman
30
θ [o] c
Sunyani 20 P [MW]
Kumasi θ
10
P

0
Fig. 8- Single-line diagram of the 161 kV LLLHV radial system 0 10 20 30 40 50 60 70 80 Ptot [MW]
of Northern Ghana supplied from the node of Kumasi
Results of analyses are here summarized for operation of all Fig. 9- Analysis of voltage regulation and voltage steady-state
the lines at 161 kV in radial configuration, shunt compensated stability of the 161 kV radial system of Fig.8,
by 5 TWVO-SRs, each rated 8.5 to 17 MVAR, with 16 steps, compensated with TWVO-SRs, with lines Techiman-
located as shown in Fig.8. One of the TWVO-SR is redundant Sawla and Tamale-Yendi operated at 161 kV
(installed spare). Ptot = total power distributed at 0.9 p.f. by the various
It should be noted that, to face the increasing loads, a new stations, as follows: 18% at Bolgatanga; 20% at
line is planned between Kumasi and Sunyani. Then the here Tamale; 7% at Yendi; 20% at Techiman; 25% at
reported analyses will apply for the contingency case operation, Sunyani; 10% at Sawla
with this new line outaged. a) Voltage at supply busbar of Kumasi and at some
It is assumed that, as time goes by, the loads increase with receiving busbars, versus Ptot . The Mvar outputs of
the same growth factor in all the substations, and with TWVO-SRs in service are reported for six values of
unchanged power factor of 0.9 at the 161 kV busbars. Ptot , including no-load operation
The results of the steady-state voltage stability analyses are b) Voltage Collapse Proximity Indicator, VCPI, and
shown by the curve charts of Fig.9. Load flows have been run by Mvar flow at supply station, QKum, versus Ptot
uniformly increasing in small steps all the loads and by reducing c) Total transmission losses, ∆P, and electrical phase
in each stage the Mvar output of the TWVO-SRs by means of shift, ∆θ, between Kumasi and Bolgatanga busbars,
OLTCs, until the minimum Mvar output has been reached and versus Ptot
reactor is switched-off in the subsequent load step. In Fig.9a the voltages at significant 161kV busbars are
plotted versus the total load distributed by the system. The
analysis has been performed by simulating the complete
network of Ghana, with voltage held constant in the power
plants that are not less than 220 km distant from Kumasi, the
supply station of the radial line. With the assumed loads' p.f. of
0.9, the voltage can be sustained to not less than 150 kV in all
the nodes, if total load does not exceed 73 MW. This condition
is close to voltage collapse however, and therefore the
practically transmissible power is somewhat lower.
The graphs of Fig.9a show that a good voltage regulation is
ensured, from no-load up to the maximum practically
transmissible power, with use of the OLTCs of the reactors and
on the assumption that load variation is rather slow, which is
realistic for developing countries. With a voltage variation at the
supply node of Kumasi from 153 kV to 157 kV, the variation is
kept from 156 kV to 159 kV at Bolgatanga (remote end), and
9

from 157 kV to 159 kV at Sawla, i.e. line voltage profiles are Analyser (TNA). Operation experience has confirmed the
about flat. viability of the measures adopted at the planning-engineering
In Fig.9b two significant parameters of voltage stability are stages.
plotted versus total distributed power. The Voltage Collapse As reported in par. 7, the power frequency overvoltages at
Proximity Indicator (VCPI) is defined as the ratio of a reactive no-load energization are eliminated with the appropriate use of
power demand increase at the remote end (Bolgatanga in Fig.8) TWVO-SRs. In systems with low short circuit power, the
and the corresponding increase of reactive power absorbed at TWVO-SRs, if designed for Xo=X1, are sufficient for drastically
the supply node of the LLLHV line (Kumasi in Fig.8). The other reducing the power frequency overvoltages caused by the
plotted parameter is the total reactive power flow at the sending unsymmetrical faults to ground, and for effectively grounding
end of the radial line (QKum). The diagrams show that when the system neutral.
the total distributed power exceeds 70 MW the VCPI and Mvar The line no-load energization and load rejection overvoltages
demand at the supply point increase rapidly. A reasonable rule have been analysed with the EMPT for the 161kV radial system
is that the VCPI should not exceed 3 and 5 Mvar/Mvar in of Fig. 8, including the dotted lateral lines Techiman-Sawla and
normal and emergency operation, respectively. Tamale-Yendi operated at 161 kV. Only a few results are
In Fig. 9c, the total transmission losses, ∆P, and the summarized here for the sake of brevity.
electrical angle between the remote receiving end and the The no-load energization of the longest line, Techiman-
supply node, ∆θ, are plotted versus total distributed power. Tamale, with a TWVO-SRs linear up to 1.3x161 kV, connected
An additional analysis, not reported here for the sake of at the line end prior to energization with the OLTC present for
brevity, has shown that the voltage change at any load busbar the max. output of 17 MVAR, causes the following highest
does not exceed 3% for a sudden simultaneous load change of switching overvoltages at the Tamale end:
10% in all the nodes, if the total distributed power does not - with a purely inductive source at Kumasi: Vmax= 2.4 p.u.;
exceed 67 MW. Vmean = 1.98 p.u.; σ = 0.145 p.u.;
To appraise the dynamic performance of the long radial
system of Fig.8, a 3-phase short circuit has been simulated at - with the real network fully simulated: Vmax = 1.7 p.u.;
the sending end of the Tamale-Yendi 161 kV line. The analysis Vmean= 1.37 p.u.; σ= 0.11 p.u..
has been performed with a transient stability program, by
simulating the loads at the various substations as follows: The analysis has also been made of the extreme case of no-
- 33% motor load, by equivalent motors with constant loading load energization of all the radial network originating at Kumasi
torque versus speed, H = 0.2s, Zsc = 0.07 + j 0.13 p.u.; (Fig.8) - which is of course not allowed in operation - with the
- 67% static load, by constant impedances. following two assumptions:

ω [p.u.] V [p.u.] I [p.u.]


A) All the TWVO-SRs are connected prior to energization, with
the Mvar output of each reactor preset for an optimal no-
load system voltage profile and an almost nil reactive power
exchange at the energizing busbar. Switching overvoltages
are as follows:
V Vmax = 2.55 p.u.; Vmean= 2.25 p.u.; σ= 0.16 p.u.

ω I The power frequency overvoltages are negligible.


B) All the TWVO-SRs are disconnected from the system; one
power transformer protected by 144 kV MOV surge
arresters is preconnected without load at the line remote end
(Bolgatanga, Fig.8).
Switching overvoltages are of same order as found in case
A). A large sustained overvoltage occurs (1.49 p.u.) with
t [s]
harmonic distorsion, liable to damage the surge arresters
and the transformer.
Fig.10- Transient following a 3-phase short circuit at Tamale in
the Tamale-Yendi line, cleared in 0.2 s: V is the voltage The load rejection events have been analysed for a credible
at Tamale 161 kV busbars; ω and I are the speed and case, i.e. rejection of the total load at anyone substation, and
current of the equivalent induction motor connected to also for an extremely unlikely case, i.e. the simultaneous
the LV busbars at Tamale rejection of the loads of all the six substations. In both cases it is
The network is assumed to be in service at the maximum assumed that the total system load prior to load rejection is 73
load prior to short circuit (see Fig.9; Ptot= 71 MW). The MW (close to the voltage collapse limit; see Fig. 9a), with all
analysis has shown a satisfactory voltage recovery in all the the TWVO-SRs disconnected. The partition of the loads among
network busbars and speed recovery of all the equivalent the various substations is shown in the caption of Fig.9.
motors, with a short circuit clearing time of up to 0.2s. Some To limit the duration of the temporary overvoltages, it is
results are plotted in Fig.10 for the Tamale substation. assumed that in the substation(s) where load has been rejected,
TWVO-SR(s) preset for 17 Mvar output are automatically
8. Overvoltages in LLLHV lines compensated by switched on 1s after load rejection. Results of EMTP analyses
TWVO-SRs can be summarized as follows:
- Load rejection at Tamale or Bolgatanga MV busbars: the
By their conception, LLLHV lines seem to be more exposed temporary overvoltage is 1.1 p.u. or 1.08 p.u.; voltage is
to internal overvoltages than conventional transmission lines of restored at 1 p.u. shortly after insertion of one reactor.
the same voltage level. In the early applications, extensive - Load rejection at the MV busbars of all the substations, with
studies were therefore performed [1] [2], with the Electromag- all the power transformers remaining energized at no-load: the
netic Transients Program (EMTP) and Transient Network
10

temporary overvoltage at Bolgatanga is 1.39 p.u., with C. TCRs


considerable harmonic distortion; voltage is restored to about The compensation scheme can consist of 3 TCRs with an output
1 p.u. in all the nodes a few seconds after insertion of four of from 0 to 18 Mvar, to be installed in the same substations
reactors preset for full Mvar output. foreseen for the TWVO-SRs of Alt.B. Each TCR is connected to
As a summarizing comment, it can be said that the the 161kV network via a 161kV/MV transformer and is pro-
appropriate application of TWVO-SRs, specified to be linear up vided with harmonic filters.
to at least 130% of rated voltage and to have Xo=X1 (no
magnetic coupling between phases), allows a safe limitation of The total installed cost and power losses of the three shunt
the temporary and switching overvoltages in LLLHV lines. The compensation schemes are summarized in the following Table.
possibility of 1-pole high speed reclosure has been explored in Costs include 161 kV CBs for 4 of the conventional reactors, for
ref. [2] and [3] . 2 of the TWVO-SRs and for each TCR. The losses are estimated
for 44 Mvar absorption, i.e. the total charging power of the line
(no-load operation) and for half of this Mvar value (light load) .
9. Economic comparison of alternative static shunt
compensation equipment for LLLHV lines Total cost Total losses with output
Compensation (1998 prices) of 44 Mvar of 22 Mvar
The cost increase of a TWVO-SR in comparison with the scheme in million
cost a conventional reactor depends on rated voltage, UN, on U.S.$ [kW] | [kW]
ratio K and on rated power, QN. For UN=161 kV, K=0.5 and 8 conventional
QN=20 Mvar, the cost increase is about 30%. However, the SRs rated 4.6 250 125
percent increase in total installed cost is much smaller, because 5.5Mvar
items such as HV switchgears, protections, civil engineering 3 TWVO-SRs 2.4 160 60
works, transport, etc. are about the same for the two rated 7.2-18Mvar
alternatives. 3 TCRs 5.50 1020 290
A comparison has been made for a radial 161 kV line rated 0-18 Mvar
equipped with single ACSR conductors of 350 sqmm in
triangular configuration, with a total length of 600 km, supplied The TWVO-SRs are the least cost and least power loss
from a node of a network distant from the major power plants, alternative. Also, maintenance costs are the lowest, because the
with a short circuit power of 500 MVA. It has been assumed maintenance of OLTCs is much less than the maintenance of the
that the line is divided in at least 3 sections and it supplies an larger amount of equipment required by Alt. A and of power
initial load of 16 MW (0.25 SIL). electronic equipment required by Alt. C.
The charging power of the line, when energized at no-load
with a flat voltage profile of 161 kV, is about 44 Mvar. 10. 10-year operation experience of 161 kV TWVO-SRs in a
The following three shunt compensation schemes have been LLLHV line
compared:
Four TWVO-SRs with an output at 161 kV ranging from 8.5
A. Conventional shunt reactors Mvar to 17 Mvar, in 16 steps, have been in successful operation
An acceptable voltage jump ∆Vi ≤ 8% has been assumed for in Ghana during about 10 years, for the shunt compensation of
infrequent reactor switching at the line remote end, and ∆Vi ≤ the Kumasi-Techiman-Tamale-Bolgatanga 161 kV radial line
5% for frequent switching of reactors located up to 450 km from (Fig.8) [2]. The TWVO-SRs have been operated as described in
the line supply node. With these conditions, formula (1) yields a par. 6.
maximum acceptable rating of reactors of 5.5 Mvar. During normal operation, the daily voltage regulation at the
To standardize construction and spares, 8 equal 3-phase reactors various substations is mostly performed by manoeuvering only
rated 5.5 Mvar can be installed along the line. Initially, half of the OLTCs of the TWVO-SRs. Switching on and off of TWVO-
the reactors need to be switchable. As the load increases, all the SRs with the 161kV CB has been relatively infrequent.
reactors will have to be equipped with a CB. The operation time of OLTC, of about 5 s per step, proved
Use of MV small reactors for part of the shunt compensation has to be fully satisfactory in relation with the network demand of
not been considered, because these reactors would have higher voltage regulation speed.
losses and would cause additional voltage drops and losses in In the early period of operation, with a total load of 10-15
the HV/MV transformers. MW, 3 or 4 TWVO-SRs had to be permanently in service. At
the time of writing, the total power distributed by the line has
B. TWVO-SRs exceeded 45 MW and 3 reactors are out of service at peak load,
The specified ∆Vi ≤ 8% for infrequent switching at the remote ready to be switched on by the overvoltage relays if a sustained
end (Psc=90 MVA) requires a minimum output of the TWVO- temporary overvoltage occurs. Most of the reactors will be
SRs of 7.2 Mvar. By specifying a regulation range of 40% to required again in continuous service at partial output, when the
100%, TWVO-SRs rated 7.2 to 18 Mvar can be applied, with a lateral 161 kV lines Techiman-Sawla, Tamale-Yendi and
21 position OLTC. Bolgatanga-Tumu will be energized at 161 kV (at the time of
The compensation scheme may consist of 3 TWVO-SRs, writing these lines are operated at 34.5 kV).
connected at the receiving end of long line sections, possibly at The average number of operations of each OLTC has been
about 1/3, 2/3 and 3/3 of the line length. Total shunt 8000 per year, i.e. about 80000 in 10-year operation for each
compensation is 54 Mvar, i.e. redundant with the three reactors TWVO-SR. The recent inspection of one diverter switch has
in operation, and still acceptable in an emergency with one shown no appreciable wear.
reactor not available for operation. Initially, two TWVO-SRs The TWVO-SRs have been in service for most of the time
need to be switchable with a CB, to be provided also for the 3rd with less than maximum Mvar output: correspondingly, the
reactor when line load increases. average mechanical vibrations, sound level, power losses and
oil/windings overtemperatures have been lower than at
11

maximum output. The mechanical vibration level did not •The inductance in the saturated part of the L-I characteristic
increase after 10-year operation. depends on the tap position and is basically proportional to the
When reactors are energized at minimum Mvar output, the square of the number of turns connected in the circuit.
inrush current is negligible (about 2 p.u., referred to peak rated •A standard value of max. peak-to-peak vibration amplitude is
current) as in a reactor without magnetic core or shield. When a 100 µm with an average value not exceeding 30 µm.
reactor terminated line is energized, temporary overvoltages are •The IEC standard value of the asymmetry of the reactance of
negligible and switching overvoltages generally do not exceed 2 one phase with respect to the average of the three phases is
p.u.. 2%; however values down to 1% or better can be easily
The gas chromatographic analysis of oil has been performed achieved .
as usual for large power transformers, with satisfactory results. •A reasonable number of OLTC switching operations without
No major or minor failures have affected the four TWVO- maintenance may be specified as 100,000, or 10-year
SRs so far. Maintenance expenses have been negligible and are operation.
expected to be small in future.
11.2 Testing requirements
11. Specification and testing requirements of TWVO-SRs
The testing procedures of TWVO-SRs do not differ
11.1 Specification significantly for those applied to normal shunt reactors. The
same precautions shall be taken as regards for example the
The specification requirements of TWVO-SRs are basically determination of reactance and the measurement of loss. What
identical to those of conventional shunt reactors, with the makes the real difference is the presence of taps, which suggests
addition of some specific requirements, associated with the adopting the following specific procedures:
variable Mvar output and special application in LLLHV lines; in •the determination of reactance and the measurement of loss
particular: shall be carried out at least at the two extreme taps, that is at
max. and min. reactive power;
- Min. and max. Mvar output at max. continuous operation •for the dielectric tests the procedure specified for power
voltage transformers having the same value of highest voltage should
- Number of OLTC positions; max. Kvar size of the steps be adopted. This means that lightning impulse tests should be
- Type of magnetic core performed at different tap positions on the three phases,
- Range of linearity (in p.u. of max operation voltage) including the two extreme taps. The tap with minimum
- Zero-sequence reactance number of turns is normally the one giving the highest
- Inductance in the saturated part of the magnetic characteristic dielectric stress in the windings;
- Max. mechanical vibration amplitude on external parts •the temperature rise test shall be performed at max. reactive
- Max. asymmetry between phases power. However, this procedure might exclude the tapping
- minimum number of OLTC switching operations without need winding(s) from the circuit, as the test is carried out at the
for maintenance. minimum number of turns, unless a tapping arrangement
based on polarity reversal of a fine tapping winding is
The following comments can be made on the items above: adopted. This aspect should be considered when the procedure
for the temperature rise test is specified;
•The ratio Qmin/QN should be consistent with the indications •the measurement of the sound power or sound pressure level
given in par.4. and of vibration should be carried out with three-phase
•Only the max. size of the Kvar steps should be specified and excitation at rated voltage or maximum operating voltage - as
the min. number of steps of the OLTC; the manufacturer shall agreed if the two values are different - on the tap
be allowed to increase the number of steps, if necessary. corresponding to the maximum reactive power. In any case,
•In HV star connected shunt reactors with neutral grounded, for sake of comparison, it is interesting to repeat the
the zero-sequence reactance, Xo, depends on the core arrange- measurements also on the tap corresponding to the minimum
ment. In a three-phase unit Xo is low if the zero-sequence flux reactive power. Lower values of vibration and sound emission
has to find its way for reclosing through the air, as occurs in a are obviously to be expected at minimum reactive power.
3-legged core. If use is made of a core consisting of five limbs,
the zero-sequence flux finds a low reluctance reclosure path Values of reactance, loss, sound pressure level and vibration
through the external unwound limbs, which results in Xo=X1 amplitude measured on the two extreme taps on the TWVO-SRs
and decoupling of the phase limbs from each other, for the rated 17-8.5 Mvar - 161 kV in operation in Ghana are given
values of zero-sequence voltage which can build up in below for reference (measurements performed at 161 kV).
operation. If the line single-pole reclosure is foreseen and
reactor is connected to the line terminal (Fig. 7b), a 5-legged Tap 17 - Tap 1 -
core (or 3 single-phase cores) must be specified. The 5-legged 17 Mvar 8.5 Mvar
core is in any case recommended for grounded neutral star 1562.5 3119.4
Reactance (Ω /phase)
connected reactors exposed to single-phase disconnection.
Loss [kW] 75.5 23.9
•The range of linearity on the tap at max. Mvar rating has an
Sound pressure level [dB-A] 74.4 69.7
impact on the cost of the equipment. The minimum
recommended value for TWVO-SRs to be used in LLLHV Max. peak-to-peak vibration (µm) 96 34
lines is 1.3 p.u. An increase from 1.3 p.u. to 1.5 p.u. increases Average peak-to-peak vibration (µm) 25 11
the reactor cost by a few percent. The linearity range is
automatically extended on the taps at reduced power in an
inverse proportion to the number of turns connected in the
circuit.
12

12. Conclusions

The tapped windings variable Mvar output shunt reactors


have proved to be the least cost and least loss technically
appropriate shunt compensation equipment of the long lightly
loaded HV lines in developing countries. The reliability and
functional responsiveness are confirmed by the very good 10-
year operation experience of these novel reactors in Ghana.
Other reactors of the same type are being commissioned and
planned for installation in 220 kV-161 kV long transmission
lines in Africa.
The applicability of the novel shunt reactors in the EHV
networks, up to 525 kV, is also explored in the paper.

13. References

[1] Iliceto F.-"Lightly Loaded Long HV Transmission Lines.


Guidelines prepared at the request of the World Bank",
Washington D.C., 1982-83
[2] Iliceto F., Cinieri E., Casely-Hayford L.-"Long lightly loaded
HV transmission lines to expand electrification of
developing countries. Applications in Ghana", CIGRE paper
37- 11 of 1984 Session.
[3] Cinieri E., Iliceto F., Di Vita A.-"Overvoltages due to open-
phase occurrence in reactor compensated EHV Lines", IEEE
Transactions on Power Apparatus and Systems, Vol. PAS -
105, N°3, March 1984, pp.474-482.

14. Acknowledgement

The authors wish to thank the Volta River Authority for the
permission to publish the operation results of the TWVO-SRs in
Ghana. The authors also acknowledge the contribution of Mr. A.
Gallucci to the analysis of LLLHV lines, as part of his master
thesis work.

Potrebbero piacerti anche