Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Table of Content
1. Scope..............................................................................................................................2
2. References.....................................................................................................................2
3. Materials.........................................................................................................................2
4. Delivery, Storage and Handling....................................................................................2
5. Quality.............................................................................................................................2
6. Work Prerequisites........................................................................................................3
7. Equipment & Tools........................................................................................................3
8. Personal..........................................................................................................................3
9. Sequence of Work.........................................................................................................3
10. Tolerances......................................................................................................................4
11. Health and Safety Provisions.......................................................................................5
1
GENERAL AUTHORITY OF
CIVIL AVIATION BUILDING
PROJECT
Method Statement for: Excavation, Backfilling and Compaction for Utility Lines
Ref No.: Rev.: 0
Date: Monday, March 23, 2020 Page: Page 2 of 5
1. Scope
The purpose of this Method Statement is to describe the steps involved in Excavation,
Backfilling and Compaction for Utility Lines at car parking in accordance and compliance
with approved shop drawings and project’s Specifications.
2. References
2.1. Specifications
a) Ref # K1502-GACA-DCS-QC-17-0001-R-1
3. Materials
a) Satisfactory Excavated Materials. Shall be piled neatly along the side of the trench
by the mean of Backhoe and to be used later in backfilling after final testing of
pipeline by the mean of Skid-steer loader (Bobcat).
b) Bedding Materials. Shall be imported and delivered to the site by the mean of
tractor where the bedding material will be piled near the work area. Sand will be
placed by the mean of Bobcat/ Backhoe.
5. Quality
All works are carried out in accordance with the project quality plan (PQP) and the
approved ITP which will be issued after the Method Statement Approval.
a) One test for classification of soil according to ASTM D 2487 for every 1000 m2 for
every completed layer.
6. Work Prerequisites
Clearance by the Main Contractor of preceding piping works shall be provided for each zone.
Main contractor shall provide grids, centerline offset lines, level datum and benchmarks in
accordance with the approved shop drawing.
7.1. Equipment
Bobcat
7.2. Tools
Water hoses
8. Personal
Surveyors; Labors.
9. Sequence of Work
1) Setting out trench location in accordance with utility lines layout drawings with a
minimum of 20 cm clearance on both sides of pipes and conduits.
3) Clean bottom of trench from organic material, roots, trash, lumber, and debris.
3
GENERAL AUTHORITY OF
CIVIL AVIATION BUILDING
PROJECT
Method Statement for: Excavation, Backfilling and Compaction for Utility Lines
Ref No.: Rev.: 0
Date: Monday, March 23, 2020 Page: Page 4 of 5
5) Place and compact sand bedding material with thickness 20 cm by plate compactor to
a maximum density of 90%.
7) After pipes have been bedded, surveyed and tested. Backfilling with satisfactory
excavated material will be done by backhoe/Bobcat in one thick lift (Max 900 mm) to
protect the pipes from cracking/crunching under compaction loads up to an elevation
of mm above crown level of pipe and compacted to maximum density of 90%.
8) Backfill with satisfactory excavated material with 95% compaction density up to bottom
level of slab on grade in 300 mm compacted layers.
10. Tolerances
All the safe practices will be adopted during the Excavation, Backfilling and
Compaction for Utility Lines.
Safe working platforms and continuous edge barricades will be maintained on site.
Wherever the special work permit is required will be taken before commencing that
particular work.
Proper access for the labors and equipment’s will be provided as required.
Minimum PPE will be: hard hat; safety shoes; reflective vest and eye wear