METALLURGY 4
CHEMISTRY 10
PETROLEUM CHEMISTRY 14

CONTENTS
MACHINE CONSTRUCTION 17
CONSTRUCTION MATERIAL PRODUCTION 19
AGROINDUSTRIAL COMPLEX 24
ENERGY INDUSTRY 29
TRANSPORT INFRASTRUCTURE 32
PHARMACEUTICALS SECTOR 35
LIGHT INDUSTRY 37
TOURISM 39
OTHER INDUSTRIAL SECTORS 41
SPECIAL ECONOMIC ZONES 44
INVESTORS SERVICE CENTERS 50
METALLURGY
METALLURGY
INDUSTRIAL INNOVATION PROJECTS

ORGANIZATION OF FOUNDRY FOR CASTING

Aim of the project: localization of production of Advantages: This project will enable the Company to
parts and components from different kinds of alloys for increase the local content in the final product due to
assembly of finished goods castings of finished parts that were previously imported
Applicant: “NC “Kazakhstan Engineering” JSC Sales market: domestic market - 60%, export - 40%
Implementation period: 2015 – 2025 Job creation: construction – 30, operation - 120
Place of implementation: SEZ Astana
Total project cost: 21,97 million US dollars
Required investments: 10,99 million US dollars CONTACT INFORMATION:
Current status: Submitted for consideration by JSC «NC «Kazakhstan Engineering “
the Investment and Innovation Committee of “NC Aidos Izmagambetov
“Kazakhstan Engineering” JSC + 7 (7172) 69 55 99, 1945
IRR -18,20%, NPV - 4,5 million US dollars
Payback period: 7 years
Capacity: Steel: molten metal - 1300 tons, finished
castings - 520 tons
Aluminum: molten metal - 450 tons, finished castings, * — if it is current project / calculated
- 180 tons ** — Feasibility studies, pre-project documentation

INDUSTRIAL INNOVATION PROJECTS

DEVELOPMENT OF THE VELIKHOVSKY IRON-ORE FIELD


WITH THE CONSTRUCTION OF CONCENTRATING FACTORY

Aim of the project: Construction of the mining and investigated the world market and gives the expected
processing works (MPW) in the Kargalinsky district price of the Titano-vanadium concentrate (TVC) till 2030.
Applicant : «Aktobe Temir-VS» DP» JSC Shareholders should determine the feasibility of building
Implementation period: 2018-2020 the (MPV) mining and processing works in response of
Place of implementation: Aktobe region Kargalinsky falling of the world prices for an iron ore concentrate (from
district 140 US dollars to 40 US dollars per ton.).
Total project cost: 133 million US dollars Infrastructure and Resources: The Velikhovskoye
Yuzhnoye field
Financing scheme: own funds - 20%, borrowed
funds - 80% Sales market: Domestic market, export (50%)
Required investments: equity, credit Job creation: 700
Expected outcome: the creation of 700 workplaces, tax Requirements for investor: The sum – 19 320 million
revenues to the budget. tenge, return term – 10 years, a grace period for return –
3 years, the planned remuneration rate – 8%
Current status: Development of pre-feasibility report.
According to the results of research works the report on
enrichment is received from “SGS Vostok Limited” LLP . CONTACT INFORMATION:
For these purposes the company signed the contract with The project manager – Mateshev T.S.
the Russian consulting company JSC «B2B Connect» which + 7 (7132) 51 43 55

5
METALLURGY
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF THE IRON-ORE PROCESSING


MINING AND METALLURGICAL PLANT
Aim of the project: The organization of an innovative, receiving a concentrate and co-investment of the project.
hi-tech and competitive, complex for processing of IRR-87,9%, NPV - 2 334,75 million US dollars
ferriferous ore and release of finished goods Payback period: 4,2 years.
Applicant: Aktobe steel production LLP Productivity: 8,0 million tons of a concentrate
Implementation period: 2015-2019 Availability of documentation: the feasibility report is
Place of implementation: Shalkar area Aktobe region developed
Total project cost: 162,2 million US dollars Advantages: New workplaces, increase in tax
Financing scheme: own means – 48,6 million US contributions to the budget, increase of export potential
dollars, borrowed funds – 113,6 million US dollars Infrastructure and Resources: The right of production
Required investments: credit/leasing, equity share in on the Kokbulakskoye field.
the capital Sales market: People’s Republic of China, Russian
Expected outcome: Processing of ferriferous ore and Federation, Europe
production of an iron ore concentrate, the agglomerate, Job creation: 939
pellets and cast iron used in production of steel. Requirements for investor: credit/leasing, individual
Current status: approval documents are signed, share in the capital
geological survey is carried out. Contracts intentions with
suppliers and consumers of production are signed. The CONTACT INFORMATION :
work is in progress with the Chinese company «Xin-Yen The project manager – Timofeev Y.I.
Scientific and Industrial Trading Company» (SUAR People’s +7 (7132) 778254
Republic of China) on the development of technology of

INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF PLANT ON PRODUCTION


OF STRAIGHT-LINE-SEAM PIPES

Aim of the project: Create modern and competitive Available documentation: Business plan of the project
products Advantages: 100% security of raw materials, there is a
Applicant: “SEC “Saryarka” National Company qualified personnel and developed markets for products
Implementation period: 2015—2018 Infrastructure and Resources: available
Place of implementation: Karaganda, Special economic Sales market: The Republic of Kazakhstan
zone “Saryarka” Job creation: 300
Total project cost: 26 million US dollars Requirements for investors: Availability of funds
Financing scheme: Investments in share capital required for the project
Required investments: 26 million US dollars
Expected outcome: Creation of modern, competitive CONTACT INFORMATION:
production “SEC “Saryarka” National Company
Current status: The design estimate documentation is +7 (7212) 40 09 71
under development, the equipment is being selected
IRR-18%, NPV - 3 millions US dollars
Payback period: 5 years

6
METALLURGY
INDUSTRIAL INNOVATION PROJECTS

PRODUCTION AND PROCESSING OF POLYMETALLIC


ORES AT ALAIGYR DEPOSIT
Aim of the project: Production and processing of Availability of documentation: There are feasibility
polymetallic ores study business plan, process regulation and design
Applicant: “Tau-Ken Samruk” JSC estimate documentation is partially
Implementation period: 2014 – 2017 Advantages: The project is located very close to one
Place of implementation: Karagandy region of the largest world zinc importers – China, allowing
effective transportation ways of zinc products to China
Total project cost: 102 million US dollars
Infrastructure and Resources: Railway line, power
Financing scheme: Own means – 51%, borrowed
lines, availability of water, substation, nearest village
funds – 49%
Sales market: Kazakhstan, China
Required investments : Investments needed for capital
expenditures Job creation: 345
Expected outcome: A loan borrowing
Current status: Feasibility study, technical regulation CONTACT INFORMATION: Rabiga Omarova – Head of
for beneficiation has been developed, land registration the Corporate Finance Department, Tau-Ken Samruk JSC,
for mining complex construction is in process, designs of tel: +7 (7172) 55 27 79, r.omarova@tks.kz;
mining under development Serik Ramazanov – Senior manager of Corporate Finance
Productivity: Lead in concentrate – 34 thousand tons, Department, Tau-Ken Samruk JSC, tel: +7 (7172) 55 93
silver in concentrate 15 thousand tons 51, s.ramazanov@tks.kz

INDUSTRIAL INNOVATION PROJECTS

MANUFACTURE OF AN ALUMINIUM PROFILE AND FOIL

The purpose and idea of the project: Manufacture of Availability of documentation: feasibility study
an aluminium profile and foil approval
The applicant: ALKOMET company Advantages: Absence manufacture of a foil in Kazakhstan
The period of realization: 2015-2019 Infrastructure and Resources: SEZ Pavlodar
Place of realization: Pavlodar oblast, Pavlodar Sales market: Kazakhstan, EAEU
Total cost of the project: 110 millions US dollars Creation of workplaces: 300
Financing scheme: 50 % own means The requirement to investors: 50 % financing
Required investments: 55 million US dollars
Expected result: Manufacture of aluminium production CONTACT INFORMATION:
The current condition: The feasibility study approval Alibek Shaidarov
is developed +7 (7172) 79 15 65, +7 777 999 88 00
Payback period: 8 years a.shaidarov@gmail.com

7
METALLURGY
INDUSTRIAL INNOVATION PROJECTS

PROCESSING OF ALUMOSILICATES RAW MATERIALS

The purpose and idea of the project: Processing of Fe, Al, Ca, Mg, impurity of rare metals in chloride
ash after coal combustion in order to receive high quality solution and reception seashtofe (insoluble in an acid)
industrial product in the quantity of 100 thousand ton Processing of seashtofe under alkaline circuit Na2SiO3
The applicant: Dmitriev L.N. and the subsequent allocation amorphous SiO2 a method
The period of realization: 2016-2017 carbonization, water - acid washing SiO2 from impurity
Place of realization: Pavlodar region, Pavlodar Al2O3, CaO, MgO with reception high-quality amorphous
Total cost of the project: 53 million US dollars SiO2 with the developed surface more than 650 m2/gr of
The circuit of financing: Creation of joint venture substance
Required investments: 50 million US dollars Infrastructure and resources: SEZ Pavlodar
Expected result: questions of improvement of ecology Commodity market: Export beyond Republic of
are solved due to reduction of volumes of warehousing Kazakhstan
of ashes. Creation of workplaces: 300 person
The current condition: it is developed by the feasibility The requirement to investors: 100 % financing
study approval
Time of recovery of outlay - 2 years THE CONTACT INFORMATION:
Presence of the documentation: the feasibility study Dmitriev L.N.
approval +7 705 707 9902, +7 701 544 5325,
Advantages: Ld1333@mail.ru
Sintering of ashes about sodium containing alloy, acid
processing with translation аcid-soluble connections

INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF THE ELECTRIC FURNACE


STEELMAKING PLANT

Aim of the project: The construction of electric furnace Payback period: indicators of efficiency will be determined
complex to provide the rail and structural steel plant with after development of the feasibility study
high quality raw materials of own production. Productivity: 533 thousand tons
Applicant: «Aktobe Generation“ LLP Availability of documentation: available business plan
Implementation period: 2016-2019 Advantages: Production of rail steel and continuous
Place of implementation: Aktobe casting billets for rail and section works. Export substitution
Total project cost: 275.7 million US dollars Infrastructure and Resources: There is no infrastructure.
Financing scheme: being defined After the selection of the supplier, development and the
Required investments: credit / leasing, equity approval of the feasibility study report the issues of signing
participation contracts on the delivery of raw materials for the long-term
Expected outcome: the creation of 450 workplaces, period will be considered.
tax revenues to the budget. Construction of the electric Sales market: LLP “Aktobe Rail and Section Works”
furnace steelmaking complex is necessary to provide the Job creation: 450
rail and structural plant with high quality raw materials of Requirements for investors: credit / leasing, equity
own production. participation
Current status: feasibility study on the development
stage IRR- indicators of efficiency will be determined CONTACT INFORMATION:
after development of the feasibility study NPV- indicators The project manager – Ibragimov Marat Yadykarovich
of efficiency will be determined after development of the +7 (7132) 74 11 96, 74 11 98, 74 11 99
feasibility study

8
METALLURGY
INDUSTRIAL INNOVATION PROJECTS

DROZHILOVSKY MINING AND PROCESSING


COMPLEX IN THE DENISOVSKY DISTRICT
Aim of the project: Development of a molybdenum- Payback period: 4,2 years
tungsten field with construction of a mining and processing Productivity: 14 074 tons of a molybdenum concentrate,
complex with an annual production rate of 5 million tons 3 397 tons of a tungsten concentrate.
on production and processing of ore. Availability of documentation: The feasibility report
Applicant: LLC Kazakhstan-Russian ore company is executed
Implementation period: 2015-2017 years Advantages: close arrangement rail ways and
Place of implementation: Kostanay region, Denisovsky power lines
district Infrastructure and Resources: Land plot of 452,9
Total project cost: 90,93 million US dollars hectares in size for conducting works on development of
Financing scheme: 30% means of LLC Kazakhstan- a field and construction and operation of concentrating
Russian ore company, 70% borrowed funds factory.
Required investments: 63,65 mln million US dollars Sales market : CIS
Expected outcome: creation of production of a full Job creation : 863
industrial cycle of molybdenic and tungsten concentrates
Current status: At a realization stage CONTACT INFORMATION:
IRR 67%,NPV 656,5 million US dollars +7 (7272) 32 35 00

INDUSTRIAL INNOVATION PROJECTS

CONTACT INFORMATION: Alekhin Sergey


Tel .: +7 (777) 240-91-62 E-mail: negs_alehin@mail.ru

EXPLORATION, EXTRACTION,
ENRICHMENT AND PROCESSING OF KAOLIN-QUARTZ-
FELDSPAR ORES AT BISEMBAYEVSKOYE DEPOSIT
Aim of the project: Thorough exploration and entering the revealed aluminum - 500 thousand tons of cement - 2600 thousand tons of
industrial reserves of the deposit complex ores to the State Balance of bricks - 50 million units and other products.
the Republic of Kazakhstan. Designing and construction of the open Availability of documentation: The work program and the financial
pits for development of the deposit, designing and construction of the and economic model in accordance with the contract for subsoil use,
processing facility for mined ore and production of feldspar, quartz, reports on geological exploration, reports on technology enrichment
kaolin and other commercial products. complex raw materials.
Applicant : «NEGS Geosphere» LLС Advantages: products annual value will exceed 1,150 mln. USD, unique
Implementation period: 2015 – 2045 reserves and a very simple structure of the deposit. This project will
Place of implementation: Denisovskiy district, Kostanay region, solve the problems of mineral resources development for construction
Total project cost: 918,5 million US dollars industry and create ceramic, glass and other product plants. The project
Financing scheme: private investments, including direct (portfolio) is focused on replacement of up to 85-90 % of import with the similar
foreign investment and loans products made in the Republic of Kazakhstan.
Required investments: - 915,8 million US dollars Infrastructure and Resources: The distance to the railway station is
Expected outcome: It is reasonable to build facing products (ceramic 25 km, asphalt roads are available, power lines 200 and 500 go through
tiles, ceramic granite), glass, facing brick, tiling, packing materials, the area, the gas pipeline «Bukhara-Ural» is 3 km away from the
mineral fertilizers production plants at the unique deposit. deposit, proximity to the settlements with well-developed infrastructure
Current status: Implementation Phase 1 - the completion of detailed for extraction and processing
exploration deposits and reserves statement, design work on the Sales market: The Republic of Kazakhstan is 65-80 %, export to the
completion of the detailed exploration of the deposit. CIS countries is 20-35 %.
Payback period: 2,5 – 8 years Job creation: up to 2,5 thousand new highly qualified jobs.
Productivity: Facing products - 26 million sq. M. m, the glass - Requirements for investor : domestic and/or foreign investors
20 million sq. m. m, cardboard and gypsum board 700 ths. tons of interested in the project.
9
CHEMISTRY
CHEMISTRY
INDUSTRIAL INNOVATION PROJECTS

PLANT FOR THE PRODUCTION


OF HYDROGEN PEROXIDE
Aim of the project: Production of highly chemical Advantages : Demand in RK is growing by 5.5%,
products, such as hydrogen peroxide by innovative however, own production of hydrogen peroxide in
scheme Kazakhstan is absent.
Applicant : “AziaTechnoService” LLP Infrastructure and Resources : large amount of raw
Implementation period : 2 years material availability.
Place of implementation : Atyrau region, Makat Sales market : The largest consumers of the Republic of
district, Dossorvillage, Embinskiy area Kazakhstan and the CIS.
Total project cost : 35 million US dollars Job creation : 120
Financing scheme : New construction Requirements for investor : willingness to give up a
Required investments : 35 million US dollars share of 70%.
Expected outcome: Production of 100% hydrogen
peroxide (technical). CONTACT INFORMATION :
Current status: Pre-invstment Uali Orynbasarov
Payback period : 3 years +7 (778) 67 81 316
Productivity : 15 000-30 000 tons/year +7 (777) 19 61 121
Availability of documentation: Business plan and E-mail: ualitex@mail.ru
agreements with foreign partners.

INDUSTRIAL INNOVATION PROJECTS

CONTACT INFORMATION:
Managing director – Nurzhan Sultanaliyev.,
+7 (701) 97 90 989, sultanaliyev@ucc.com.kz
Head of inorganic department – Sayagul Ibraimova.,
+7 (701) 42 37 656, ibraimova@ucc.com.kz

PRODUCTION OF METHANOL AND AMMONIA


AND PRODUCTS ON ITS BASIS
Aim of the project: Construction of the plant for the production of Availability of documentation: absent
methanol, ammonia, basic products of the chemical industry, with Advantages : «Production of methanol and ammonia and
the possibility to recycle in the country and to export with high products based on them» is one of the major long-term projects
value added. that affect the positive activity of the SEZ, and is the raw material
Applicant: United Chemical Company LLP for the production of the project a large range of chemical products
Implementation period: 2015 – 2022 (including in the framework of 11 projects). Currently there are no
Place of implementation: Zhambyl region, SEZ Chem-park Taraz factories for the production of methanol in Kazakhstan . Ammonia
Total project cost: 1 154 million US dollars production may have a positive impact on the development of
agriculture
Financing scheme: Own funds– 346 million US dollars (30%).
Infrastructure and Resources : Necessary transport
Debt funds – 808 million US dollars (70 %)
infrastructure will be provided by SEZ «Chempark Taraz» (access
Required investments: 808 million US dollars
road, rail way). Connection to the necessary communications will be
Expected outcome: Development of chemical industry in
provided by SEZ «Chempark Taraz» (drinking and industrial water,
Kazakhstan, creation of new workplaces electricity, gas, sewage, etc.)
Current status: Concept of the project is developed. Sales market : Will be determined by the results of preliminary
Work on pre-DFS and DFS development in process. Feasibility Study and Feasibility Study
IRR-7,6 %, NPV - 113,4 million US dollars Job creation : Will be determined by the results of preliminary
Payback period: 14,9 years Feasibility Study and Feasibility Study
Productivity : Methanol: 200 mln. m3/year of natural gas Requirements for investor : The experience in implementation
Ammonia: 500 mln. m3/year up to 800 mln. m3/year of of similar projects, providing debt financing, providing the project
natural gas by off-take contracts.
11
CHEMISTRY
INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF SODA ASH


Aim of the project: Construction of plant on production Infrastructure and Resources:
of the calcinated soda Sorkol field of rock salt (stocks of 1,93 billion tons, the
Applicant: Akimat of Zhambyl oblast maintenance of NaCl - 66%)
Implementation period: 2016-2018 limestone fields Aksay (stocks of 12,7 million tons), Aktau
Place of implementation : Zhambyl oblast, Sarysu and Aktau-1; existence near sources of gas, water and
region power supply
Total project cost : 274 million US dollars Sales market: Kazakhstan, CIS countries
Financing scheme: installation and construction works: Job creation: 500
129 million US dollars, equipment: 145 million US dollars
Required investments: 274 million US dollars CONTACT INFORMATION:
Expected outcome:creation of production of the +7 (72 62) 43 89 02, 43 89 03
calcinated soda power: brand B - 400 thousand tons/ tarazinvest@mail.ru
year, brand A - 200 thousand tons/year, sodium two-
carbonic - 10 thousand tons/year
products cost: 100 millions US dollars IRR - 11,78%,
NPV - 92,5 millions US dollars

INDUSTRIAL INNOVATION PROJECTS

INNOVATIVE PRODUCTION OF CARBIDE OF SILICON

Aim of the project: Technology of receipt of silicon expenses) + 5 million US dollars (for oper. charges)
carbide in a reactor with electrothermal boiling a layer Expected outcome: 20000 тon per year of carbide of
was developed by the partners of the Innovative park of silicon
L.N.Gumilov Eurasian National University - by scientists Current status:
from А.V. Luikov Heat and mass transfer institute Realization of a 1 stage,offer the Chinese investor, for
of the National academy of science of Belarus. The 2 and 3 to the stage: ТЭО is worked out
innovativeness and reliability of technology is confirmed
Payback period: 5 years
by diplomas and quality certificates.
Productivity :* 1 stage -project power 700 тon/year,
Declarant : Innovative park of L.N.Gumilov Eurasian
National University 2 stage -project power 20000 тon/year
Implementation period: Development, making, Availability of documentation :** Presentation
delivery and editing and start-adjusting of equipment Job creation: 100
after signing of contract and receipt of advance - 1.5 year.
Place of implementation: Kyzylorda region CONTACT INFORMATION:
Total project cost : 4,7 million US dollars +7 (7172) 47 27 11, 42 28 11
Required investments: І stage - 4, 7 million US dollars
(for all expenses) + 230 thousand US dollars (for oper.
charges),ІІ stage of - 130 million US dollars (for all

12
CHEMISTRY
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF FERROALLOY PLANT MANUFACTURING


OF LOW-ALUMINIUMFERROSILICIUM IN KYZYLORDA
Aim of the project: “NC» SEC «Baikonur “ JSC «Ningxia Baota Petrochemical Technology Industrial
Implementation period : 2014 – 2017 Development Co., Ltd» (Baota).
Place of implementation : Kyzylorda oblast Feasibility study of the project «Building of ferroalloy
Total project cost : 253,2 million US dollars plant on the production of the special and complex alloys
Financing scheme : in city Kyzylorda» is prepared.
- “NC» SEC «Baikonur“ JSC Infrastructure and Resources : Currently, the work
is underway to modernize existing power plants and by
- Partner and other investors
2016 it is planned a settlement of 200 MW of electricity to
Required investments : 67% the industrial zone for the ferroalloy plant
Expected outcome: Production capacity of ferroalloy Job creation : 600
plant is 160 thousand ton per year
Current status: Implementation of 1st stage is
CONTACT INFORMATION:
considered the technology proposed by Chinese investors
on 2nd and 3rd stages: Feasibility study developed NC» SEC «Baikonur JSC
Payback period : 6 years +7 (7242) 60-50-82, 60-51-63,
Productivity : 160 thousand ton per year office_spk@mail.ru
Availability of documentation : Memorandum
between Akimat of the Кyzylorda region and company

INDUSTRIAL INNOVATION PROJECTS

MANUFACTURE OF POLYALUMINIUM OF
CHLORIDE (PAC) PRODUCTION
Aim of the project: Production organization Advantages : There is no similar production in
Applicant : Himpromprodukt LLP Kazakhstan
Implementation period : 2016 – 2019 The product is superior that its analogues economically
Place of implementation : SEZ Pavlodar, Pavlodar and technologically. There are all the necessary raw
oblast materials of local production, it is easy to increase
Total project cost : 9,25 million US dollars production, the existence of the market in the Republic
of Kazakhstan, the market is not susceptible to the
Financing scheme : Loans
macroeconomic risks, partners with vast experience in the
Required investments : 9,25 million US dollars production of chemicals.
Expected outcome : Manufacture of Polyaluminium of Sales market : Utilities, power plants, chemical industry,
chloride oil and metals extraction in Kazakhstan.
Current status: The implementation of 1, 2 and 3 Job creation : 25
stages:feasibility study, development of the design -
budget documentation,
CONTACT INFORMATION :
construction.
Zeinullov Kabiden Kashkenovich
Payback period : 5 years (in view of time for start)
+7 701 22 31 094
Productivity : 10 0000 ton / year
zigkaz@gmail.com
Availability of documentation : Feasibility study in
development
13
PETROLEUM CHEMISTRY
PETROLEUM CHEMISTRY
INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF ETHYL TERT-BUTYL ETHER (ETBE)


Aim and idea of the project: production of motor Advantages: The main uses of ethyl tertiary butyl ether
gasoline as oxygenizing additive that increases octane - production of motor gasoline as oxygenizing additive
Applicant : “Batys power” LLP that increases octane. ETBE is significantly safer for the
Period: 2015—2020 environment and the engine compared to ethyl fluid
Location: West Kazakhstan, Uralsk (tetraethyl lead) and aromatic hydrocarbons, which are
also used to enhance the octane number of gasoline.
Total project cost: 350 million US Dollars
Sales market: Domestic and foreign markets
Required investments: 350 million US Dollars
The requirement to investors: individual share
Expected outcome: The project will involve innovative
technologies from European countries to increase exports
of gasoline in Europe, create new jobs and contribute to
the oil and gas sector. CONTACT INFORMATION :
Payback period: 5 year Jakupov Zhaslan,
+ 7 (7112) 986269,
jakupovzhaslan@gmail.com

INDUSTRIAL INNOVATION PROJECTS

MODERNIZATION OF GAS PROCESSING PLANT

Aim of the project: Upgrading the existing gas Advantages: Existence of the mastered gas field and the
processing plant with new equipment and technology to operating production
meet product standards of EURO 4 Infrastructure and Resources: Existence of the
Applicant: “Amangeldy GPZ” LLP operating production base, infrastructure and the
Implementation period: 2016 - 2017 region personnel
Total project cost: 54 million US dollars Sales market: Kazakhstan
Required investments: 54 million US dollars Job creation: 150
Expected outcome: increase of profitability of the
enterprise and increase in capacity to 180 thousand tons/ CONTACT INFORMATION:
year, including: Address: Republic of Kazakhstan,
- light distillate: 27 thousand tons/year (15%) Zhambyl oblast, Zhambyl area, Abay St. 129
- fraction of kerosene: 36 thousand tons/year (20%) Republic of Kazakhstan, Almaty, Abylay khan Ave. 3
- diesel fuel: 45 thousand tons/year (25%) + 7 (7272) 66 92 62, + 7 (7272) 66 92 63
fuel oil: 72 thousand tons/year (40%) info@agpz.kz, agpz_oralbay@mail.ru
Current status: The enterprise operating the project at
a stage of design development

15
PETROLEUM CHEMISTRY

DEVELOPMENT OF GAS FIELDS

Aim of the project: Production and processing of inert Current status: The enterprise operating the project at
gases (nitrogen and helium) and production of mineral a stage of design development
fertilizers Advantages: The operating production, existence of
Applicant: «Amangeldy GAZ» LLP new gas fields with considerable reserves of gas
Implementation period: 2016 - 2018 Infrastructure and Resources:
Place of implementation: Zhambyl oblast Talas region - fields Ucharal, Kempirtobe, Western Ucharal and
Total project cost: 360 million US dollars Northern Ucharal (content of gases: nitrogen of 96%,
Financing scheme: helium of 2%) existence of the operating production
base, infrastructure and the personnel
- building of cryogenic installation: 60 million US dollars
Sales market: Kazakhstan
construction of chemical fertilizers plant: 300 million US
dollars
Required investments: 360 million US dollars CONTACT INFORMATION:
Expected outcome: development of gas fields and +7 (7262) 57 45 38
release of the following production: info@amangeldygas.kz
- nitrogen: 176 million Nm3/god
- helium: 1 222 thousand Nm3/god
- carbamide: 5 500 thousand tons/year

16
MACHINE CONSTRUCTION
MACHINE CONSTRUCTION
INDUSTRIAL INNOVATION PROJECTS

THE BUILDING OF ULTRA-


MODERN FACTORY PRODUCING
INNOVATIVE ENERGY EFFICIENT AND ECOLOGICALLY CLEAR CABLE PRODUCTION
WITH ISOLATION FROM CROSS-LINKED POLYETHYLENE ON UP TO 330 KV
VOLTAGE IN NATIVE CREATION

Aim of the project: The production and realization Current status: the project is on realization stage
ultra-modern cable and wire production in markets, IRR - 55%, NPV – 11,04 million US dollars
namely: the Republic of Kazakhstan, Russian Federation, Payback period: 1 year
the Republic of Belarus, and countries of Persian Gulf Availability of documentation: the resolution of
(UAE, Qatar, Iran, Saudi Arabia, etc.) Almaty city administration; the contract of land zone rent;
Applicant: “KMK construction – Investment” LLP. The the governmental act on ground.
building of ultra-modern factory producing innovative Infrastructure and Resources: machine manufacturing
energy efficient and ecological clear cable production with
Sales market: home market – realization of products
isolation from cross-linked polyethylene on up to 330 KV
on the whole territory of Kazakhstan – 40%, on export
voltage in native creation.
– 60%, Kazakh goods, services and works content in
Implementation period: 2015-2020 project – 80-85%
Place of implementation: The Republic of Kazakhstan, Job creation: in the period of building 400 people, in the
Almaty city, Alatau district. period of exploitation – 539 people
Total project cost: 24,36 million US dollars
Financing scheme: personal funds 5,1 million US dollars CONTACT INFORMATION:
Loan funds 19,26 million US dollars + 7 (7273) 34 03 30
Expected outcome: the producing and realization of
ultra-modern cable and wire production

INDUSTRIAL INNOVATION PROJECTS

MANUFACTURE OF 220-500 KV POWER


TRANSFORMERS
Aim of the project: manufacture of 220-500 kV power Payback period: 7-8 years.
transformers. Availability of documentation: A business plan is
Applicant: Asia Trafo LLP. being developed.
Implementation period: 2015 – 2017. Advantages: Electrotechnical products clustering (with
Place of implementation: Industrial zone, Shymkent JSC «Kentau Transformer Plant»).
city, South-Kazakhstan region, Kazakhstan Infrastructure and recourses: under construction.
Total project cost: 50 million USD. Sales market: CIS – 50%, Kazakhstan – 50%.
Financing scheme: Equity capital – 20%, Job creation: 400
bank loan – 80%.
Required investments: 40 million USD. CONTACT INFORMATION:
Expected outcome: 160 units per year. Alageum Electric Holding company
Current status: A plot of land is allocated for the Zhaina Kuntuarova
construction in the industrial zone of Shymkent. +7 701 554 8656
Developing design estimates, fund raising. zh.kuntuarova@alageum.com

18
CONSTRUCTION MATERIAL
PRODUCTION
CONSTRUCTION MATERIAL PRODUCTION
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF PENOPLEX PRODUCTION PLANT


Aim of the project: The opening of production of Capacity: 400 cubic meters of Penoplex per day,
modern heat-insulating building materials, provision of 52.0 thousand cubic year
foreign and Kazakhstan market of construction materials. Availability of documentation : In development
Applicant : «Turan Industry» LTD Advantages : the proximity to Astana
Implementation period : 2016 – 2018 Infrastructure and Resources : 5,7 Ha land plot,
Place of implementation : Tonkeris station, Akmola railway line
region Sales market : Kazakhstan, export
Total project cost : 2,0 million US dollars Job creation : 20
Financing scheme : Own / borrowed
Required investments : 2,0 million US dollars CONTACT INFORMATION :
Expected outcome : The plant for the production of Executive director Murdinov Murat
penoplex +7 701 75 81 738
Current status: Acquisition of land in private ownership Deputy director Arman Sultanov
of an area of 5.7 hectares on Tonkeris station with further +7 702 21 08 673
leased-purchase about 2 hectares.
Payback period : 2 years

INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF CONTAINER GLASS


Aim of the project: Construction a factory of glassware Availability of documentation: available business plan
with a productivity of 300 tons of glass per day, creation Advantages : The main producers of vodka located
of the new enterprise. in Aktobe and Akmola regions. These are plants LLP
Applicant : Aynek LLP «Geom», LLP «AkrossPischeprom» and LLP «Maximus»
Implementation period : 2 years in Aktobe.
Place of implementation : Aktobe region The proximity of consumers, transport logistics for the
Total project cost : 100 million US dollars main raw materials and auxiliary materials. The presence
Financing scheme : The investor - 15%, JSC «Samruk- of quartz sand.
Kazyna» - 15%, JSC «DBK» -70% Infrastructure and Resources : Mugalzhar deposits of
Required investments : credit / leasing, equity capital, quartz sand, more than 600 million tons.
off-take contract Sales market : Kazakhstan
Expected outcome : the creation of 186 workplaces, Job creation : 186
tax revenues to the budget. Requirements for investor : credit / leasing, equity
Current status: Searching of the investor participation
IRR-6%, NPV-1,2 millions US dollars
Payback period: 6,1 years CONTACT INFORMATION :
Productivity: 91.8 thousand tons The project manager – Dzhidzhiyeshvili V. H.
+7 701 5032545
20
CONSTRUCTION MATERIAL PRODUCTION
INDUSTRIAL INNOVATION PROJECTS

PLANT FOR THE PRODUCTION OF EXPANDED


CLAY AND COMPOSITE PRODUCTS
Aim of the project: The development of expanded clay Availability of documentation : Business Plan and
field with a further construction of a plant to produce information on the field.
expanded clay blocks Advantages : The largest field of expanded clay in the
Applicant : “ZhayikBetonInvest” LLP western part of the country.
Implementation period : 2 years Infrastructure and Resources : Pre proven reserves
Place of implementation : Atyrau region, Makat district of clay at the Makat field estimated at amounts more
Total project cost : 6 million US dollars than 15-20 million m3.
Financing scheme : New construction Sales market : Regions of RoK and RF.
Required investments : 4 million US dollars Job creation : 70
Expected outcome : Expanded clay pellets, expanded Requirements for investor : Financing
clay blocks, gravels tiles, expanded clay curb.
Current status: Pre-investment stage CONTACT INFORMATION :
IRR -39,04%, NPV – 1,85 million US dollars Atashev E.N.
Payback period : 22 months +7 701 55 99 958
Productivity : 50 thousand m3 too.jbs@mail.ru

INDUSTRIAL INNOVATION PROJECTS

EXTRACTION AND PROCESSING OF MARBLE

Aim of the project: The organization of production of Current status: The enterprise operating is available
marble on the Tesiktas field and release of products from a field for marble production IRR - 108,65%; NPV - 5,5
marble million US dollars
Applicant: “Karatau Mramor” LLP Documents: the business plan of the project is developed
Implementation period: 2016 Infrastructure and Resources:
Place of implementation : Zhambyl oblast, Talas area there is a field for marble production
Total project cost : 19,6 million US dollars Sales market: Kazakhstan, CIS countries and foreign
Required investments: 9,3 million US dollars countries
Expected outcome: Job creation: 50
Expansion of power of production:
- marble blocks: 20 400 CBM/year CONTACT INFORMATION:
- marble tiles: 120 000 CBM/year +7 (7262) 45 28 61
other products: 2 400 CBM/year +7 701 79 97 754

21
CONSTRUCTION
CONSTRUCTIONMATERIAL
MATERIALPRODUCTION
PRODUCTION
INDUSTRIAL INNOVATION PROJECTS

MINING AND PROCESSING OF LIMESTONE


Aim of the project: Profit at the expense of the needs Availability of documentation : Pre-project
of metallurgical, construction and other enterprises of the documentation
Northern regions of Kazakhstan calcareous products of Advantages : A high level of competitiveness in the
varying degrees of redistribution (lime lump, hydrated, context of the programm of the Government of the
etc.)Applicant : LLP «KEREMET ASIA” Republic of Kazakhstan for import substitution
Implementation period : 2016—2023 Infrastructure and Resources : there is in the region
Place of implementation : Pavlodar region, the field of the field
Carabidae. Sales market : Implementation within the country
Total project cost : 3,5 million US dollars (Northern and other regions of Kazakhstan)
Financing scheme : The establishment of a joint Job creation : 45
venture. Requirements for investor : solvency, absence of
Required investments : 1,75 million US dollars debts to third parties outstanding for more than three
Expected outcome: maximum profitability, market months, the availability of own funds to participate in the
coverage of Kazakhstan and the CIS. project.
Current status: developed feasibility study IRR
10,3%,NPV 8,58 million US dollars CONTACT INFORMATION : «KEREMET ASIA“ LLP
Payback period : 7 years +7 (7187) 33 98 48
Productivity : 441 000 tons per year Arbutin Gennady Nikolaevich

INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF UREA FORMALDEHYDE


RESIN AND CHIPBOARD
Aim of the project: The production of urea formaldehyde Advantages : the availability of logistics, process
resin, production of wood boards equipment
Applicant : «Pavlodar woodworking plant» LLP Infrastructure and Resources : there are
Implementation period : 2014 – 2015 Sales market : Kazakhstan, Russia
Place of implementation : Pavlodar Job creation : 65
Total project cost : 5,83 million US dollars
Financing scheme : 49%-51% CONTACT INFORMATION :
Required investments : 5,83 million US dollars Director of project management Center
Current status: commissioning work of JSC «NATD» - Sayabek Kanakhin
IRR - 23%, NPV - 1,1 million dollars. USA +7 (7172) 571 014 (222)
Payback period : 3 years + 7 701 713 71 61
Productivity : 40 000 cubic meters
Availability of documentation : Feasibility studies,
Pre-project documentation

22
CONSTRUCTION MATERIAL PRODUCTION
INDUSTRIAL INNOVATION PROJECTS

PRODUCING OF COMPLETE STEEL CONSTRUCTIONS


FOR PRE-ENGINEERED BUILDINGS
INDUSTRIAL INNOVATION PROJECTS

Aim of the project: 1. Foundation of modern competitive The presence of documentation: Marketing
plant on producing of complete steel constructions with researches and business plan available
high grade of manufacture Advantages: trade market available
2. Forming of national producer with high potential on Infrastructure and resources: Existing plant,
import substitution and export access Raw materials of Kazakhstan, Russian and European
Initiator: «Alma Grad Real Estate» LLP manufacturers
Period of implementation: 2012– 2020 Trade market: Kazakhstan, Russia (from Ural to Far
Project location: Zagorodniy village, Ust-Kamenogorsk East)
city, East-Kazakhstan region Creation of new jobs: 290
Project Cost: 21.8 million US dollars Requirements for investors: financial opportunities
Financial structure : investments and experience in this field
Investments required: 21.8 million US dollars
Expected result: export access CONTACT DETAILS:
Current status of the project: The project is being Director General Terehov I.S.
implemented +7 (7232) 25 45 59
IRR: 29,80 %, NPV: 6.9 million US dollars
Payback period: 5 years
Production: 65 thousand ton of metal constructions per
year

23
AGROINDUSTRIAL COMPLEX
AGROINDUSTRIAL COMPLEX
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION AND OPERATION OF THE


GREENHOUSE COMPLEX FOR GROWING TOMATOES
Aim of the project: Getting high-quality, export- Availability of documentation :** attached
oriented, competitive products for realization on Advantages : Uninterrupted distribution of the provision
domestic and foreign markets of basic agricultural products to the population of the
Applicant : Limited Liability Partnership “Greencor” northern region of Kazakhstan
Implementation period : 2014 – 2016 Infrastructure and Resources : Land of 18 ha has
Place of implementation : North Kazakhstan region, taken to the long-term rent in the city of Petropavlovsk
Petropavlovsk city Sales market : Domestic market of Kazakhstan, Export
Total project cost : 32,5 million US dollars to Russia
Financing scheme : Own funds 17% Job creation : 150
Borrowing funds/Investments 83% Requirements for investor : willingness to pay a share
of 80%
Required investments : 24.6 million US dollars
Expected outcome : 1.5 million US dollars
CONTACT INFORMATION:
Current status: The implementation of design and
Director Mr.Kustubayev Arman Saparbekovich
estimate documentation
+ 7 701 731 8100
IRR- 22 %,NPV-10.076 million dollars. USA
Payback period : 60 month
* — if it is current project / calculated
Productivity :* 7000 tons ** — Feasibility studies, pre-project documentation

INDUSTRIAL INNOVATION PROJECTS

GREENHOUSE COMPLEX CONSTRUCTION WITH A CAPACITY


OF 300 TONS OF VEGETABLES PER YEAR IN LISAKOVSK CITY

Aim of the project: Growing high-quality, export- Current status: Feasibility study is developed,
oriented, non-GMO vegetables (tomato’s and cucumbers) Examination of design estimates and construction permit
Applicant : «Green Island Kazakhstan» LLC was received. In 2014 2.5 ha earthworks was made,
Implementation period : 2013 – 2016 foundation work: Housing and administrative complex
Place of implementation : Kostanay region, Lisakovsk city and warehouses, produced 70% of the foundation for
Total project cost : 4.5 million US dollars the greenhouse. Built frame building ABK. Infrastructure:
heating, gas, electricity, water and the road to the
Financing scheme : own funds, development institution
complex in the amount of 51 million tenge.
funds, FDI
Payback period : 3,9
Required investments : 4.1 million US dollars
Productivity : 300 tons/year
Expected outcome : The design capacity in kind - 500
Availability of documentation : business plan,
tons / year, stated 300 tons / year. the creation of 40
jobs during construction and 20 jobs during operation. feasibility study
- Production is focused on the domestic market and Infrastructure and Resources : 2.5 Ha, gas, electricity,
export (70/30)% - Estimated effect - providing the water and the road.
population of the city and nearby communities of finished Sales market : Kostanay region, near by region
products, participation in social projects, conducting fairs, Job creation : 20
increase trade in the region, the creation of a healthy
competitive environment among wholesale and retail CONTACT INFORMATION :
trade organizations. Abilgazy Kadirsizov+7 777 271 40 22
ae_kadirsizov@mail.ru
25
AGROINDUSTRIAL COMPLEX
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF THE PLANT FOR THE PRODUCTION OF


HERBAL PULP WITH THE CAPACITY OF 14,400 TONS PER YEAR

Aim and idea of the project : The project involves the of pulp from annual plants. In the pilot plant produced
production of herbal cellulose (sorbent dorotsel) from experimental batches of samples of herbal cellulose.
cane, sunflower stalks and other crop A pilot batch of paper for sanitary purposes (type of
Applicant : “Uralenergostroy” LLP tissue). At OAO «Tasma-Holding» released batch of linen
Period: 2013—2016 y.y. cellulose weighing 5 tons for road tests.
Location: Darinsk v., Zelenovskiy district, WKR IRR - 15,7%, NPV - 19 million US Dollars
Total project cost: 21 million US Dollars Payback period: 3,7 years
Required investments: 21 million US Dollars Availability of documentation: Business plan available
Expected Result: The creation of additional jobs, Market: Domestic market
increase tax revenues. Job Creation: 70
Current Status: The technology of cellulose Requirements to investors: individual share
(hemicellulose) abbreviated production cycle (unbleached)
and on a full cycle (bleached), and the technology for CONTACT INFORMATION:
producing a stabilizing additive for road construction on Sarmin Petr Yurevich
the basis of herbal cellulose. Developed initial version of +7 702 91 18 062
the business plan, technical project to place production
sarmin58@inbox.ru

INDUSTRIAL INNOVATION PROJECTS

THE ESTABLISHMENT OF
PRODUCTION OF DEEP PROCESSING
OF GRAIN IN KARAGANDY ON THE BASIS OF THE MILLING
INDUSTRY COMPANY “NOMAD” LLP

Aim of the project: The establishment in Karaganda city IRR 26%,NPV 36,8 million US Dollars
on the basis of the milling industry Company LLP «NOMAD» Payback period: 5 years
products of deep processing of grain Productivity : 47,2 thousand tons per year
Applicant : «NOMAD» LLC Availability of documentation : Business plan, financial
Implementation period : 2012 – 2018 model, design and estimate documentation
Place of implementation: Karagandy city, Republic of Advantages : Availability of infrastructure, location,
Kazakhstan experience, availability of markets, production subsidies
Total project cost : 36,4 million US Dollars Infrastructure and Resources : The current flour enterprise
Financing scheme : Replenishment of authorized capital, with appropriate infrastructure that has experience in this
financial assistance field, the availability of qualified personnel
Required investments: 35,4 million US Dollars Sales market : The food, agriculture, pharmaceuticals
Expected outcome: production of dry wheat gluten, starch industries of the Kazakhstan, Russia, China and the European
syrup (caramel, maltose), dry feed ingredients for $ 3.7 million Union
US Dollars per year in the amount of 1.1 million US Dollars per Job creation : 95
year, the processing of livestock health. Requirements for investor : expression of interest, and
Current status: The implementation of 1st stage, on wait for the result
stages 2 and 3: a drafting team (technologists, engineers,
management); the project is included in the Industrialization CONTACT INFORMATION :
Map of the oblast; the contract and the terms of reference for Nurgazy Adekenov
the design and adaptation of engineering documentation is +7 777 071 78 72
developed

26
AGROINDUSTRIAL COMPLEX
INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF STARCH, GLUTEN AND CONDENSED


CONCENTRATED FEED WHEAT, CAPACITY OF 5 TONS/HOUR

Aim of the project: Production of starch, gluten and Productivity : Gluten humidity 8% - 4,500 tons / year,
condensed concentrated feed wheat starch humidity 10% - 23600 tons / year,
Applicant : «Al-BM» LLC dry pelleted feed 12% - 23,000 tons / year
Implementation period : 2011– 2016 Sales market: Kazakhstan Netherland, and Iran
Place of implementation : Kostanay region Job creation: 305 permanent jobs and 20 jobs during
Total project cost : 45,4 million US Dollars the construction period
Required investments : 45,4 million US Dollars Requirements for investors: domestic and/or foreign
Current status: There is a presentation and business investors interested in the project.
plan of the project in English and Russian languages.
Availability of land with infrastructure. CONTACT INFORMATION :
IRR- 25% Khaliolla Murzaguzhinov
NPV - 38 million US Dollars +7 701 70 55 597
Payback period : 5-7 years

INDUSTRIAL INNOVATION PROJECTS

VIKTORIYA AGRICULTURAL COMPLEX

Aim of the project: Сultivation and processing of crops, Productivity : 1 000 heads of cattle , milk and milk
animal breeding and processing of livestock and poultry. products - 22 000 tons, meat and meat products - 730
Processing of meat. Dairy production. Cattle fodder tons, cattle hides 500 pcs, Chicken eggs - 75 million
production. pieces , chicken meat - 900 tons, sheep - 8000 heads,
Applicant : Almaty Engineering LLP meat and meat products Lamb - 500 tons, wool - 37 tons,
Implementation period : 2016 - 2017 sheep skins - 3,000 pcs, beef - 500 tons , 83 000 tons of
Place of implementation : Almaty Region fodder crops.
Total project cost : 95,5 million US Dollars Availability of documentation: Business plan,
Required investments : 95,5 million US Dollars financial model, design specification and estimates
Expected outcome: Creation of a modern farm: 3,600 Advantages : Full cycle of production, economies of
heads of cattle, 20,000 sheep, 2000 pigs, 1000 horses, scale
500 000 laying hens, 100,000 broiler chickens. Growing Infrastructure and Resources : water, electricity,
of cereals (wheat, corn, oats, barley, and others.). highway.
Greenhouse farming for cultivation of vegetables and Sales market : Kazakhstan, CIS countries.
fruits. Cultivation of oilseeds. Cultivation of genetically Job creation : 850
modified varieties of soybeans. Growing silage, haylage Requirements for investor: Strategic investor
crop.
Current status: Pre investment phase CONTACT INFORMATION:
IRR - 25%, NPV – 92,5 million US Dollars Cheremnih Sergey Nikolaevich,
Payback period: 5 years +7 777 27 22 288, sergey-61h@mail.ru
27
AGROINDUSTRIAL COMPLEX
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF THE INDUSTRIAL COMPLEX


INDUSTRIAL INNOVATION PROJECTS

Aim of the project: Ecological improvement of a district Availability of documentation : Business plan and
(business project includes the section of ecology), the agreements with partner
creation of about 100 work places, the launch of this Advantages : Minimal vulnerability planned release of
project contributes to the economic growth of the area. different types of products in demand in the market,
Applicant : “Bakhyt” farm increasing profitability and lasting lesson segments.
Implementation period : 1.5 years Infrastructure and Resources : Area growing cane
Place of implementation : Atyrau region, Kurmangazy and cocklebur whitish tens of thousands of hectares, and
district, Ganyushkino village is increasing annually
Total project cost : 6 million US Dollars Sales market : Regions of RK.
Financing scheme : Construction of Universal production Job creation : 82
plant for the production of GVTM, pellets and WPC. Requirements for investor : Financing
Required investments : 4 million US Dollars
Expected outcome : CONTACT INFORMATION :
Granulated grass meal and meadow grasses. Kabdeshev Rashid Gallamovich
Fuel Pellets, based on the dry reeds. +7 (71233) 2 52 43
Wood-plastic composite (fuel wood), based on the dry kx-bakyt@mail.ru
reeds.
Current status: The implementation of Phase 1, 2 and
3 stage:feasibility study
Payback period : 24 months
Productivity :
Granular grass meal (pellets) - 16 560 tonnes / year;
Pellets - 5520 tons / year;
Wood - polymer composite (fuel wood) – 828 tons /
year.

28
ENERGY INDUSTRY
ENERGY INDUSTRY
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF A FACTORY ON MANUFACTURE


OF FUEL PELLETS FROM BIOMASS
Aim of the project: Creation of production of fuel pellets documentation, business plan
from biomass (cane) and implementation of the project Advantages : at present the company already has land
on the European market and a patent
Applicant : «Ak Kamys» LLP Infrastructure and Resources : - Land plot, area of
Implementation period : 2015 – 2022 10 hectares;
Place of implementation : Kurmangazy district, Atyrau - Rent the land for the mowing of the reed, 25 thousand
region hectares.
Total project cost : 11.4 million US Dollars - Innovative patents.
Financing scheme : 49%-51% Sales market : European union
Required investments : 8.4 million US Dollars Job creation : 74
Expected outcome : Net profit of 2.5 million Euro/ year
Current status: The implementation of Phase 1, 2 and CONTACT INFORMATION :
3 stage:feasibility study Amirali Ayan – Director of AK «Kamys» LLP
IRR-42%, NPV- 6,9 million US Dollars +7 701 111 37 48
Payback period : 3.5 years ayan@temirali.kz
Availability of documentation : pre-project www.akkamys.kz

INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF A WIND FARM IN ARKALYK CITY


Aim of the project: Construction of a wind farm in Productivity : 48 MVt
Arkalyk city Availability of documentation : The scheme of
Applicant : «Synergy Astana» LLC power supply has been developed by «Energy System
Implementation period : 2011 – 2017 Researches» LLP, international company «8.2 Consulting
Place of implementation : Kostanay region Arkalyk city AG» (Germany) was attracted as a consultant.
Total project cost : 54.4 million US dollars. Advantages : high wind potential, proximity to the
Financing scheme : own funds - 8.16 million US dollars; substation of JSC «KEGOC».
Borrowed funds - 46,2 million US dollars. Infrastructure and Resources : The selected area has
Expected outcome : Implementation of the project a high wind potential which has been confirmed by annual
will solve the problem of power shortages and reliability wind measurements at a height of 50 m.
of regional power supply, create new jobs, increase Sales market : United Power System of Kazakhstan,
export potential of the region, which will have a positive Kostanay region.
multiplier effect on the economy of the region, improve Job creation : 10-50
regional environment, increase taxes to the budget.
Current status: feasibility study has been developed CONTACT INFORMATION :
according to the use of maximum tariff of 19 KAZ/kWh Daniyal Duysengaliev
(0.095 eurocents/kWh) +7 701 788 12 90
IRR – 27,6%, ROE-19,48% dd@synergy.kz
Payback period : 7-9 years
30
ENERGY INDUSTRY
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION AND OPERATION OF TWO 25 MW WIND


FARMS TO EL. SUPPLY OF ASTANA AND AKMOLA REGION

Aim of the project: Decrease Power shortage, Power Availability of documentation :** Feasibility studies,
cost, -Power Losses-, pollution , increase reliability of pre-project documentation
power supply Use of a more potential of wind energy of Advantages : ------------------------------
Ereimentau region. Infrastructure and Resources : two existing 110 kV
Applicant : EcoWatt LLP (Almaty) power lines for providing consumers with electric power.
Implementation period : 2016 – 2018 roads, railway land, powerful wind energy Yereimentau,
Place of implementation : Ereimentau district of water reservoir.
Akmola region ( 150 km from Astana) Sales market : -Astana City -Akmola region
Total project cost : 70mln USD Job creation : --60 during erection, 12 during
Financing scheme : JV exploitation
Required investments : 35 mln USD
Expected outcome : two Wind power plant on 25 MWt CONTACT INFORMATION :
175 mln kwt-h power a year + 7 777 27 15 615
Current status: The implementation of Phase 1, pre mared.k@mail.ru
-feasibility study
IRR-23,7-%,NPV-213 million dollars. USA
Payback period : 7 years * — if it is current project / calculated
** — Feasibility studies, pre-project documentation
Productivity :*

INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF THE FIRST BIOPOWERSTATION

Project’s purpose and idea: Producing electricity Advantages: Additional features: creation of
under clean non-waste technology with the usage of additional production sawmilling and wood up to 1 million
high-technology equipment m3, with the manufacture of prefabricated panel houses
Initiator: «BIO-TES» LLP for Afghanistan by special request of the U.S. $ 300
Period of implementation: 2014 – 2015 years million to the Republic of Kazakhstan
Project location: East-Kazakhstan region, Infrastructure and resources: There are material
Shemonaikhinskiy district, Shemonaikha village and technical resources, production area (2700 m2) with
Project Cost: 100 million US dollars. storage, railway siding; infrastructure available. The area
of the land plot is 2 ha
Financial structure : investments
Trade market: East-Kazakhstan region
Investments required: 100 million US dollars.
Creation of new jobs: 150
Expected result: foundation of a competitive enterprise,
providing people with electric power Requirements for investors: financial opportunities
and experience at this field
Current status of the project : Project is available for
implementation after feasibility study development
Payback period: 60 months CONTACT DETAILS:
The presence of documentation: under development Starostin Viktor Aleksandrovich
+7 777 13 07 246,
staroston_62@mail.ru
31
TRANSPORT
INFRASTRUCTURE
TRANSPORT INFRASTRUCTURE
INDUSTRIAL INNOVATION PROJECTS

LRT CONSTRUCTION
Aim of the project: LRT construction Advantages : Decrease in emissions, increase in city
Applicant : Almaty Akimat transport system efficiency.
Implementation period : 2018 – 2020 Infrastructure and Resources : Existing infrastructure
Place of implementation : Almaty city along the old tramway line
Total project cost : 346,55 million US dollars Sales market : Almaty inhabitants and guests
Financing scheme : DBFOT concession Job creation : 476
Required investments : 346,55 million US dollars Requirements for investor : Will be defined by
Expected outcome : New LRT line consultants in tender documentation
Current status: Tender among possible consultants
for tender documents preparation CONTACT INFORMATION:
IRR Economic 9%,NPV 102,9 million US dollars «Almaty Develoment Center»
Payback period :11 years +7 (727) 334 1378 (79,80)
Productivity : 62 thsd. passengers/day Aidarkhan Kussainov
Availability of documentation : Feasibility study Head of concession projects management group.

INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF LOGISTIC CENTER IN ATYRAU CITY

Aim of the project: Construction of major transport- Payback period: 6 years


logistics center Productivity : 276 thousand US dollars
Applicant : Atomex group (Czech company) Availability of documentation : Business plan
Implementation period : 2 years Advantages: the absence of a similar center
Place of implementation : Atyrau city, Republic of Infrastructure and Resources: Absent
Kazakhstan Sales market: Potential clients are the MC retail chains,
Total project cost : 8 million US dollars markets and small commercial enterprises, which would
Financing scheme : New construction be convenient to use the services of the MC in the
Required investments : 100 % of the cost implementation of its economic activity.
Expected outcome: Job creation: 32
Renta cold storage; Requirements for investor: Financing
Rent a dry storage;
Rent of open warehouse platforms; CONTACT INFORMATION:
Rent of office space; Turlan Yermukhanov
Current status: Pre-investment stage +7 701 799 14 95
IRR – 20.19 %, NPV - 13 million US dollars turlan@mail.ru

33
TRANSPORT INFRASTRUCTURE
INDUSTRIAL INNOVATION PROJECTS

TRANSPORT AND LOGISTICS CENTER BASED ON THE


INTERNATIONAL AIRPORT «AULIE-ATA»
Aim of the project: Creation of the transport and logistic - expansion of internal and international passenger flights
center on the basis of the international airport «Auliye- expansion of cargo flights (Tajikistan/India – Russia;
Ata» Taraz (reconstruction of the passenger terminal, Southeast Asia – Europe; The Middle East- Siberia)
creation of a cargo of the terminal of a class A, the logistic Current status: The feasibility report of the project on
and cargo companies, expansion of geography of flights, development stages, in 2013 constructed a new runway,
purchase of special equipment) reconstruction of the passenger terminal, of 6 200 sq.m,
Applicant: JSC International Airport Auliye-Ata capacity - 200 pass / is conducted hour
Implementation period: 2013 - 2017 IRR - 59 %, NPV - $ 21,8 mln.
Place of implementation : Zhambyl oblast, Taraz Expected outcome - 2,5 year
Total project cost : 11,3 million US dollars Infrastructure and Resources:
Financing scheme: Existence of a field and the land plots under construction
cargo terminal (class A): the equipment - 2,7 million US of a complex
dollars, installation and construction works - 5,3 million Sales market: Kazakhstan, CIS countries and foreign
US dollars, air terminal complex: the equipment - 2,3 countries
million US dollars, installation and construction works - 1
million US dollars CONTACT INFORMATION:
Required investments: 9,7 million US dollars +7 (7252) 99 88 80
Expected outcome: increase of passenger traffic till + 7 701 712 46 49
200-250 persons/hour and freight transportation of 10
thousand tons freights/year

INDUSTRIAL INNOVATION PROJECTS

CREATION OF TRANSPORT AND LOGISTICS


HUB IN AYAGOZ DISTRICT
Project’s purpose and idea: Creation and development 140 000 tn of cargo (7 000 cars)
of transport corridor West-East from Europe, trough the The presence of documentation: Under development
Caucasus and the Caspian sea to the Central Asia and Advantages: advantageous geographical location for
China transport and logistics hub creation
Initiator: Government of Ayagoz district (Akimat) Infrastructure and resources: Land plot (area 18 ha)
Period of implementation: 2012– 2017 years chosen for the project is situated at the city outskirts
Project location: Ayagoz city, East-Kazakhstan region along railway siding
Project Cost: 12.5 (approximate) million U.S. dollars Trade market: Republic of Kazakhstan, Russian
Financial structure : investments Federation, People’s Republic of China, Europe
Investments required: 12.5 million U.S. dollars Creation of new jobs: during construction – 150,
Expected result: increasing the turnover during operation - 70
Current status of the project: Searching for investors Requirements for investors: financial opportunities
IRR: 21 % and experience at this field
Payback period: 8 years
Production: Customs checkpoints East Kazakhstan CONTACT DETAILS:
region - People’s Republic of China, 9 months of 2013: Enterprise department of Ayagozskiy district,.
«Maykapchagay» customs checkpoint – approx. 270 000 +7 (7232) 25 45 59
tn (13 500 cars), «Bahty» customs checkpoint – approx

34
PHARMACEUTICALS
SECTOR
PHARMACEUTICALS SECTOR

CONSTRUCTION OF THE PHARMACEUTICAL PLANT FOR


THE DRUG PRODUCTION TAGANSORBENT AND DIETARY
SUPPLEMENTS OF NATURAL MINERAL MONTMORILLONITE
JOINT INDUSTRIAL INNOVATION EXHIBITION
The purpose and idea of the project: Production of Payback deadline - 3,5 years
drugs and dietary supplements Productivity: 2000 thousand packages per year
Applicant: “Altai Geology and Ecology Institute” LLC, Documentation availability: the project with state
STC “Parasat” JSC, expertise conducted, feasibility study and business plan
Implementation period: 2016—2017 are availible
Implementation location: EKR, Ust Kamenogorsk Advantage: The project is completely innovative.
Total project coast: 4,91 million US dollars The drug Tagansorbent and dietary supplements are
Funding scheme: Private investments, borrowings, and the first in Kazakhstan enterosorbents of the mineral
grants montmorillonite. It has no analogues in the CIS countries
Investment required: 4,91 million US dollars Infrastructure and resources: The research infrastructure
Expected results: Capacity of designed plant - – 1 is available. It is currently under exploration basing on
000 000 packages of Tagansorbent and 1 000 000 the subsoil use contract of pharmaceutical raw materials
packages of dietary supplements in a year, in total 2 000 deposits Tagan-2, with the approval of reserves for 30
000 packs. years.
Current status: Construction plan of pharmaceutical Markets for products: Potential consumers of these
plant is developed, the state is conducted. Feasibility products are pharmaceutical companies in Kazakhstan
study and business plan is developed. and the Eurasian Union.
The land area of 0.4 hectares for the construction of the Job Creation: 85
building was acquired. Technology line for production Requirement for Investors: phased funding of the
of the drug Tagansorbent and nutritional supplements project during construction
to food was purchased. Pilot industrial production was
established with the implementation of commercial CONTACT DETAILS:
products in the amount of 290-360 thousand US dollars. +7 (7172) 21 07 18,
IRR-25% info@parasat.com.kz, aziz@parasat.com.kz
NPV- 5,0 million US dollars

36
LIGHT INDUSTRY
LIGHT INDUSTRY
INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF FABRIC

Aim of the project: Expansion of production on Advantages: the enterprise adjusted release of
production of woolen fabric intermediate raw materials for production of woolen
Applicant: Posh Taraz LLP fabric - recycles wool and lets out TOPS (power of 873,6
Implementation period: 2016 - 2017 tons TOPS/year and a worsted yarn (power of 500 tons
Place of implementation: Zhambyl oblast, Taraz yarn/year)
Total project cost : 13 million US dollars Infrastructure and Resources:
Required investments: 13 million US dollars existence of the operating production base, infrastructure,
the personnel
Expected outcome:
Sales market: Kazakhstan, CIS countries and foreign
- realization of the 3rd stage of modernization of the
countries
enterprise (the 1st stage - production TOPS, the 2nd
stage – production of worsted yarn) Job creation: 200
- modernization and expansion of production of fabric,
shoulder strap with power up to 2,5 - 3 million. meters/ CONTACT INFORMATION:
year +7 (7262) 43 28 05
IRR - 50,5 %, NPV - $ 32,8 million US dollars posh_taraz@mail.ru
Expected outcome - 7 year
Current status: the enterprise is operating, the project
at a development stage

INDUSTRIAL INNOVATION PROJECTS

PRODUCTION OF NONWOVEN
MATERIALS AND PRODUCTS
Aim of the project: Production of nonwoven materials Payback period: 4,4 years
and products Productivity : 35 mln m2 (or 1120 tons)
Applicant : Dolce LLP Availability of documentation : business plan
Implementation period : 2016 – 2018 Advantages : The company has 18 years of experience
Place of implementation : South Kazakhstan Region, in the field of pharmaceuticals, has signed a contract with
Shymkent, Ontustik SEZ Samruk Kazyna Pharmatsia
Total project cost : 14,92 million US dollars Infrastructure and Resources : yes
Financing scheme : investors Sales market : Kazakhstan and Eurasian Economic
Required investments : 11,92 million US dollars Union (EEU)
Expected outcome : Production of import-substituting Jobs to be created : 150
raw materials for the textile industry of the region. Requirements for investor : financial assets
Production of own products: disposable medical
clothing and linen , personal protection against seasonal CONTACT INFORMATION :
and blood-borne infections, hygienic products Kanapyanova Ainur Tileuzhanova
Current status: the business plan is prepared, the +7 701 55 51 245, +7 702 77 79 199
equipment supplier is determined
IRR- 24,73%, NPV 21,82 million US dollars

38
TOURISM
INDUSTRIAL INNOVATION PROJECTS

INDUSTRIAL INNOVATION PROJECTS


TOURISM
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF THE 5-STAR


HOTEL COMPLEX «SAMAL»

Aim of the project: improving the business image of Availability of documentation: The following
the region, tourism development documents for the project.
Applicant : Bolashak-T LLP * Business plan
Implementation period : 2015 – 2016 * Perform preliminary design
Place of implementation : Republic of Kazakhstan, * Design documentation
Uralsk, “Samal” area, Esenzhanova st., 45 Advantages : creation of a modern hotel complex
Total project cost : 8.2 million USD and comfort, 5 star in WKO. Similar complexes in West
Financing scheme : the joint venture and the Kazakhstan are not available. The closest competitors
capitalization of investments have a level of comfort of 4 stars.
Current status: created a joint venture LLP «Bolashak-T» Infrastructure and Resources : the necessary
with a share of 51%, and JSC «NC» SEC «Oral» with a infrastructure there, as on the land previously existed
share of 49%. As a contribution to the JSC «NC» SEC Hotel «Samal». In 2011, as a result of the flood in Uralsk
«Oral» provided 2 plots of land with a total area of 3.5 hotel was damaged and decommissioned
hectares. Design documentation. Sales market : West Kazakhstan
IRR – 10.3%, NPV – 0.8 million USD Job creation : 50
Payback period: 6 years Requirements for investor : joint venture and
Productivity : 50 hotel rooms, designed to receive financing 7.2 million. dollars. USD.
foreign visitors, VIP guests, as well as international
governmental delegations: CONTACT INFORMATION :
- 1 Presidential Suite (Penthouse); +7 775 73 59 901,
- 8 Deluxe; +7 701 53 35 748 (“Bolashak-T” LLP)
- 20 Luxe; +7 (7112) 50 59 47,
- 21 Economy +7 705 33 15 311 (“Oral” SEC” NC” JSC)

40
OTHER INDUSTRIAL SECTORS
INDUSTRIAL INNOVATION PROJECTS

INDUSTRIAL INNOVATION PROJECTS


OTHER INDUSTRIAL SECTORS
INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION WASTE RECYCLING PLANT AND


LANDFILL FOR WASTE DISPOSAL FOR ALMATY CITY
Aim of the project: Construction of the biogas and Advantages : preserving the environment and secondary
electricity production plant products
Applicant : Almaty Municipality Infrastructure and Resources : 245 hectares of land
Implementation period : 2016 – 2019 Sales market :
Place of implementation : Almaty Job creation : 200
Total project cost : 149,4 billion US dollars Requirements for investor : 100% financial investment
Financing scheme : EBRD loan and the Clean and loan
Technology Fund, Government and local budgets
Required investments : 149,4 billion US dollars CONTACT INFORMATION :
Expected outcome : Waste Management system +7 (7273) 34 13 79 ,78,
upgrade + 7 (7273) 34 13 81
Current status: the completion of the feasibility study cda@cda.kz
IRR----%,NPV---- www.investinalmaty.com
Payback period :
Productivity :* 300 thousand tons per year
Availability of documentation :** project Feasibility

INDUSTRIAL INNOVATION PROJECTS

CONSTRUCTION OF A WASTE-PROCESSING
COMPLEX IN URALSK CITY
Aim of the project: The project is considered as Productivity : 100 thousand tons per year
ecological and social as activity of plant will allow not only Availability of documentation: There are all necessary
to reduce the volume of rubbishy masses by 3–4 times, documents for implementation of the project
but also to return valuable components to economic * The working draft is executed
circulation: ferrous and non-ferrous metals, cardboard * Feasibility report, Predproyektnaya documentation
and paper, plasticity, rags and also to receive initial raw Advantages : solution of ecological and social tasks
materials for receiving: consumer goods, electric power, Infrastructure and Resources : gas pipeline, road
heat power, construction materials. Sales market : 360 enterprises for Kazakhstan,
Applicant : Arktur LLP are available the signed agreements on perspective
Implementation period : 2014 – 2015 cooperation
Place of implementation : Republic of Kazakhstan, Job creation : 105
Uralsk Requirements for investor : grace period of 12
Total project cost : 6,36 million US dollars months.
Financing scheme : in coordination
Current status: The implementation of Phase 1, 2 and CONTACT INFORMATION :
3 stages: feasibility study developed +7 (7112) 52 21 36
IRR - 7,4%,NPV – 103,2 thousand US dollars arktyr@list.ru
Payback period: 6 years

42
OTHER INDUSTRIAL SECTORS
INDUSTRIAL INNOVATION PROJECTS

INTERACTIVE MODEL OF SPECIAL ECONOMIC


ZONES, INDUSTRIAL FIRMS AND
INFRASTRUCTURE OF ASTANA CITY
Aim and idea: Given model allows to choose in interactive Given work serves as an effective instrument for presenting
mode any special economic zone, find date and place of to potential investors. The virtual model is irreplaceable
its creation, area, goals, and prioritized activities. While on exhibitions, conferences, and investment forums.
choosing any SEZ region, it is possible to see given region’s Applicant: ТОО TKR GROUP
residents, information about implementation stages, and Implementation: period: 2015—2016
detailed infrastructure. The important advantage is not Place of implementation: Astana
only great amount of information from one resource but
Total cost: 1 500 000 US dollars
also the possibility to send an application on a portal
online. Required investment: $ 750 000
The virtual environment reflects in 3D any industrial firm’s Current status: realization of stage 1, stages 2 and 3:
model, which contains information about a firm’s history, development of feasibility study
description of activities, plans, publications in media, etc. IRR-41,96%, NPV- 5.1 million US dollars
Also, the virtual model contains description of a firm’s Payback period: 6 months
equipment, its picture and schemes. It visually reflects Availability of documentation: feasibility study
a firm and its equipment’s modernization. Additionally, it * --- in case if project is existing/counted
is possible to see productive cycle of technology used by ** -- feasibility study, pre-project documentation
a firm. The speaker tells about stages of technological
Advantages: short terms of the project’s realization and
cycle; according to each stage, activated equipment is
payback, final product’s high technology and ability to
illuminated.
update constantly
Also, given interactive model presents roads and transport
Infrastructure and resources: office and storage
infrastructure in Astana, which involves initial condition of
spaces are available
highways, streets, interchanges, and sidings connected to
Market outlets: Countries of Near and Far abroad
EXPO area, their upcoming building and reconstructing.
The reconstruction of city’s highways, entering to the Workplaces creation: 15 and more
capital, streets’ building and reconstructing are reflected.
It is possible to observe building and reconstructing roads CONTACT INFORMATION:
and engineering networks in Astana’s housing estates. +7 701 32 99 400, +7 707 77 88 950

43
SPECIAL ECONOMIC ZONES

SEZ «Burabay
«Burabay»
Burabay
Tourism (2008)
SEZ «Pavlodar»
Petrochemistry (2011)

SEZ «Astana – new city»


Mixed (2001)
SEZ «
«NIPT»
NIPT»
Petrochemistry (2007)
SEZ «Saryarka»
Metallurgy (2011)

SEZ «Khorgos – Eastern gates»


Logistics (2011)
SEZ «Chemical Park Taraz»
SEZ «Seaport Aktau
Aktau» Chemistry (2012)
Oil and gas mechanical engineering (2002)

SEZ «Park of Innovative Technologies»


SEZ «Ontustik» IT-innovations (2003)
Textile (2005)

1
SEZ
INDUSTRIAL INNOVATION PROJECTS
Industrial park №2
area: 433.1 ha
Industrial park №1,
area: 598, 1 ha.

Administrative and business center


area: 6604 ha

SPECIAL ECONOMIC ZONE “ASTANA – NEW CITY”

Location: Astana city optical devices, photovoltaic modules, passenger cars,


Founder: Akimat of Astana helicopters, construction materials, glass products, LED
Management company: Administrative department of products, furniture, etc.
the special economic zone “Astana – new city” Total of attracted investments: 2,2 trillion tenge
Total area: 7634,71 hectares Quantity of implemented projects: 266
Priority activities: other non-metals mineral products; administrative and residential complexes, social, cultural
machinery and equipment; household electric appliances; and infrastructure and 24 industrial facilities.
rubber and plastic products; electric equipment, including Quantity of realizable projects: 37 industrial projects,
electric lighting equipment; glass components for lighting 73 administrative and residential complexes, welfare and
equipment; food; wood mass and cellulose, paper and infrastructure.
carton; furniture; vehicles, trailers and semitrailers; Quantity of jobs created: 2707
railroad locomotives and rolling stock; avian- and Major investors: Company «Sovico Holdings», «GE
spacecraft; basic pharmaceutical products and equipment; Transportation», «ALSTOM», «Talgo Kazajstan SL»,
electronic parts; chemicals; metals; construction and «Aselsan Elektronik Sanayi ve Ticaret AS», «Airbus
commissioning of the infrastructure, administrative and Helicopters», «Patentes Talgo SA»
residential complexes and commissioning of hospitals, Infrastructure - willingness to 80%
schools, kindergartens, museums, theaters, universities
and secondary schools, libraries, palaces, schoolchildren, CONTACT INFORMATION:
sports complexes. + 7 (7172) 703303,
Manufactured goods: locomotives, electric, electro- sezastana@mail.ru

INDUSTRIAL INNOVATION PROJECTS

SPECIAL ECONOMIC ZONE


«SEAPORT AKTAU»

Location: Маngystau region, Aktau city. Major investors: ARCELOR MITTAL,


Founder: 100% administration of Маngystau region UNITED CHEMICALS MANAGMENT, AZERSUN HOLDING,
Management company: SEZ «Seaport Aktau» JSC KEPPEL OFFSHORE & MARINE, TENARIS.
Total area: 2000 hectares Major projects: «Arcellor Mittal Tubular
Priority activities: Manufacture of chemical and Products Aktau» JS, «Caspian Offshore & Marine
petrochemical products, leather products, fabricated Construction» LLP, «Аktau North Sea Terminal»,LLP
metal products, non metallic mineral products, machinery «Kazakhstan Pipe Traders» LLP.
and equipment, metallurgical and electrical products, Infrastructure:
pharmaceutical products, warehousing. subzones № 1, 3 -100 %;
Total volume of production: 225 bln. tenge subzones № 2,4 - construction 2016-2018;
Total volume of attracted investments : 40 bln. subzones № 5,6 - construction 2019-2021
tenge
Quantity of implemented projects : 9 CONTACT INFORMATION :
Quantity of realizable projects : 20 +7 (7292) 30 27 72, 30 27 77
Quantity of jobs created : 1000 info@sez.kz
WWW.SEZ.KZ

45
SEZ
INDUSTRIAL INNOVATION PROJECTS

SEZ «INNOVATIVE TECHNOLOGIES PARK»

Location : Almaty city Total volume of attracted investments: 92 mln.$


Founder : Non-government organization Quantity of implemented projects: 70
Management company: Autonomous Cluster Fund Quantity of realizable projects: 50
«Innovative Technologies Park» Quantity of jobs created: + 2000
Total area: 163.02 ha Major investors: Elbit Systems (Israel), LS Group
Priority activities: (South Korea), DS Multimedia Со (South Korea), Yamaha
- Information Technologies; (Japan), HP (USA).
- Technologies in Telecommunication and Communication; Major projects: LLC «Delta IT», LLC «Eltex Alatau», LLC
- Electronics and Instrumentation; «KT Cloud Lab», LLC «Kazakhstan Computer Graphics»,
- Renewable sources of energy, resource saving and LLC «DS Multimedia CA» , ТОО «KazTechInnovations».
effective use of natural resources; Infrastructure: readiness 50%
- Technologies in creation and application of materials for
different purposes; CONTACT INFORMATION:
- Technologies in the field of production, transportation Almaty city, Medeu district
and processing of oil and gas. Alatau microdistrict, 9, Ibragimov street
Manufactured goods: software, telecommunication +7 727 320-18-56
equipment info@sezpit.kz

INDUSTRIAL INNOVATION PROJECTS

SEZ ONTUSTIK

Location : SKO, Shymkent city. Carpet production


Founder : Business Management, Industrial-Innovative Spinning
Development and Tourism clothing industry
Government: National company of the “Social Entrepreneurial Pulp production
Corporation wool processing
“Shymkent” Joint Stock Company corrugated cardboard
Management company: Management company of the “Special Writing paper (A4)
Economic Zone “Ontustik” Joint Stock Company Total volume of attracted investments: 122,6 billions tenge
Total area: 200 ha Quantity of implemented projects: 8
Priority activities: Quantity of realizable projects: 15
production of finished textile products, except clothing; Quantity of jobs created: 1445 workers
Manufacture of other knitted and crocheted; Major investors: «Bal Textile» LTD and «Hlopkoprom Cellulose»
manufacture of wearing apparel, except fur apparel and leather; LTD
spinning, weaving and finishing of textiles; Major projects: 100%
production of non-woven products, except for clothes; Infrastructure: 100%
manufacture of carpets and rugs; CONTACT INFORMATION: Address: Republic of Kazakhstan,
production of pulp; Shymkent, Enbekshi region, “Zhuldyz” residential area,
paper and cardboard; 095 Block, 1158 Building.
manufacture of leather products, except for the Tel.: +7 (7252) 92-11-02, +7 (7252) 92-11-04
tanning and dressing of leather; dressing and dyeing of fur; +7 701 707-30-02, +7 702 741-47-79, +7 775 565-73-39.
10) Manufacture of paper stationery. E-mail: ao_sez@mail.ru
Manufactured goods: Web-site: sez-ontustyk.kz
46
SEZ
INDUSTRIAL INNOVATION PROJECTS

SEZ «PAVLODAR»

Location : Pavlodar, North industrial zone Quantity of created jobs : 885


Founder : Akimat of Pavlodar region Major investors: JSC « CAPEC « JSC « Kazatomprom «,
Management company: Joint-stock company LLP « Pavlodar Oil Refinery “
“Managing Major projects: JSC « Caustic «, LLP « UPNK -PV «
company of SEZ “Pavlodar” LLP « AgroHimProgress “
Total area: 1200 hectares Infrastructure: There is working infrastructure
Priority activities: production of chemical , of JSC «Caustic», new engineering networks
petrochemicalproducts, and products of related industries and communications are under construction
and technology
Manufactured goods: liquid chlorine , caustic soda, CONTACT INFORMATION :
sodium hypochlorite, inhibited hydrochloric acid , JSC « Management Company SEZ « Pavlodar «
household chemical goods, disinfectants Pavlodar , North industrial zone
Total volume of attracted investments: 39,3 billion +7 (7182) 66 06 26
tenge
+7 (7182) 20 85 30
Quantity of implemented projects: 3
aouksezpavlodar@mail.ru
Quantity of projects put in operation 2015 : 2

INDUSTRIAL INNOVATION PROJECTS

SEZ «BURABAY»

Location : Akmola region Quantity of realizable projects: 2


Management company: republican public institution Quantity of jobs created: 216 person currently
“Territorial department of committee of the investments Major investors: BI Group- the biggest building
of Ministry on investments and development of Republic company and confessed leader at the property of
of Kazakhstan, administration of the special economic Kazakhstan market
zone ‘’Burabay” Major projects: Tourist hotel complex “Burabay Lakes
Total area: 370 hectare Resort Hotels”, which is under the management of
Priority activities: providing of tourist services; building worldwide known operator in the field of hotel business
and putting into the operation of places for tourists, “Rixos”
sanatory and health objects at the observance of next Infrastructure: readiness – 100%
terms: building and putting into operation of the objects
are not connected with gambling business; building and CONTACT INFORMATION :
putting into operation of the objects comes according
Schuchinsk town, Auezov Str, 80
with project estimate documentation.
+7 (716 36) 4 21 45
Total volume of attracted investments: 14,290 bln
tenge sez_burabay@mail.ru
Quantity of implemented projects: 1

47
SEZ
INDUSTRIAL INNOVATION PROJECTS

SEZ “NATIONAL INDUSTRIAL PETROCHEMICAL PARK”

Location : Atyrau region. Major projects:


Management company: National Industrial Polypropylene production – 500 th. ton;
Petrochemical Technopark SEZ Management Company Polyethylene production – 800 th. ton;
JSC Polymer products – 19 th. ton;
Total area: 3 475,9 ha Butadiene production – 250 th. ton.
Priority activities: Production of chemicals,
petrochemical and related products and technologies Infrastructure:
Total investments amount: 1,65 trln. Kazakhstan Gas-turbine power plant;
tenge
Compressed air and nitrogen production
Amount of investment made: 140,3 billion Kazakhstan
Water treatment;
tenge
Plant wide infrastructure.
Quantity of jobs created: 613
Major investors: “UCC”LLP, LG Chem Ltd.
CONTACT INFORMATION :
Atyrau, 38 Abylkhair av.
+ 7 (7122) 209315;
atyrau_sez@mail.ru

INDUSTRIAL INNOVATION PROJECTS

SEZ “SARYARKA”

Location : Karaganda region Major investors: german companies - Bohmer Armatura,


Founder : Akimat of Karaganda region Isoplus, Austrian company - Seven Refractories,
Management company: “Karaganda Invest” JSC korean company – Hyunwoo, russian company -
Total area: 595,01 hectare TechnoNIKOL
Priority activities: metallurgy, construction, Major projects: “Bouhmer Armatura” LLP,
chemical industry, engineering “Isoplus Central Asia” LLP
Manufactured goods: ball cocks, isolation valves, Infrastructure: readiness – 90%
thermally insulated pipes
Total volume of attracted investments: CONTACT INFORMATION :
121,7 bln tenge Karaganda city, 4 Stroiteley ave., office 308
Quantity of implemented projects: 2 +7 (7212) 40 09 83
Quantity of realizable projects: 6 aokaragandainvest@gmail.com
Quantity of jobs created: 140 person currently

48
SEZ
INDUSTRIAL INNOVATION PROJECTS

SEZ «KHORGOS – EAST GATE»

Location: Almaty region Volume of attracted investments: for construction of SEZ


Founder: «KTZ Express» JSC infrastructure - 37 bln.tenge (RB), for construction of
Management company: Dry port – 40,4 bln.tenge («NC «KTZ» JSC), volume of
JSC Managing company of special economic zone attracted private investments - 150 bln. tenge.
«Khorgos – East gate» Quantity of implemented projects : 1
Total area: 4591,5 hectares Quantity of created jobs: 300 person currently
Priority activities: Storage facility and related Major investors: holding negotiations with such
additional transport activities; Construction of buildings companies, like Toyota, Hewlett-Packard.
for exhibitions, museums, storage and administrative Infrastructure: readiness – 82%
buildings; food production; manufacture of textile
products; manufacture of leather and relevant products; CONTACT INFORMATION:
manufacture of chemical industry products; manufacture Khorgos village, 14 Stroiteley str.
of other non-metal mineral products; manufacture of +7 (7172) 55 00 30
finished metal products, except machines and equipment;
sez_almaly@mail.ru
manufacture of machines and equipment omitted from
other categories.

INDUSTRIAL INNOVATION PROJECTS

SPECIAL ECONOMIC ZONE «CHEMICAL PARK TARAZ»

Location: Zhambyl region, Shu district 400 during operation


Founder: «United chemical company» LLP Major investors: 1) «CHEMplus» LLP; 2) «QADAM
Governing body: - Industries»
Management company: «Management company of LLP; 3) «Kyzylorda Munay Gas» LLP.
the special Major projects: 1) Production of caustic soda and chlorine,
economic zone «Chemical park Taraz» JSC glyphosate and trichloride phosphorous; 2) Production of
Total area: 505 hectares pesticides;
Priority activities: 1) Production of the chemical 3) Production of methanol.
industry products; Infrastructure: 1) External objects of infrastructure:
2) Production of the rubber and plastic materials; 3) access highway, access railroad with station, objects of
Production of other non-metal mineral products; 4) gas supply, water supply and power supply; 2) Internal
Production of the machines and equipment for the objects of infrastructure: administrative- household
chemical productions; 5) Construction and commissioning building, fire station, check-point, water-gas-power supply
of the industrial facilities state inspection. circuits, and sewage treatment facilities.
Manufactured goods: -
Total volume of investments: 34 186,7 million tenge CONTACT INFORMATION:
Quantity of implemented projects: - Republic of Kazakhstan, 081127, Shu town, 24
Quantity of realizable projects: 5 Shakirov St.; +7(72643) 6 21 31;
Quantity of jobs created: 4 000 during construction; 2 www.seztaraz.kz invest.sez.cpt@gmail.com

49
INVESTORS SERVICE CENTERS

INVESTORS
SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

INDUSTRIAL INNOVATION PROJECTS

50
INVESTORS SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTRE OF ALMATY CITY

Aim of ISC: consulting services, organization of events Major investors:


related to Almaty investment opportunities - Alstom (France)
Location: 85, Dostyk ave., Almaty - CLAAS (Germany)
Founder: Almaty Municipality - John Deere (USA)
Government: Almaty Municipality - Samsung (South Korea)
Total volume of attracted investments: (january-august CISCO (USA)
2015) : 313 billion tenge LG (South Korea)
Provided services: МАЗ (Belarus)
- attracting investments into Almaty economy; Major projects:
- advisory support of investmentprojects according to the -Construction and operation of the light-rail transit
principle of a “one stop” system; -Industrial zone in Alatau District
assistance in implementation of government support -Project management of solid household waste
instruments
Quantity of implemented projects: 1 Contact information:
Quantity of realizable projects: 4 projects Address: 4 floor, 85, Dostyk ave., Almaty, 050010
Quantity of jobs created: Projects created with the +7 (7273) 334 13 79,78, +7 (7273) 34 13 81
participation of IAC Almaty, more than 20 jobs. cda@cda.kz
www.investinalmaty.com

INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF AKTOBE REGION

Location : Aktobe, Aktobe region CONTACT INFORMATION :


Management company: “Aktobe” SEC” NC” JSC Aktobe city, Sankibay Batyr st., 22k,
Priority activities: all activities business center «Kazyna»,
Total volume of attracted investments: in 2015 - +7 (7132) 74 20 40 , + 7 701 03 64 040
more than 40 billion KZT iscAktobe@gmail.com
Quantity of implemented projects: 3 www.spk-aktobe.kz
Quantity of realizable projects: 10
Major investors: Netherlands investment companies
(RenTeh BV, DBTechnologies), Canada (Anaergia),
Singapore (Azura International), China and Germany
Major projects: «Batis Potassium» LLP, «Kimpersay
Energy» LLP, “Metaplast-A» LLP (RenTeh BV),
“TERMOKOKS» LLP

51
INVESTORS SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

“REGIONAL CENTRE FOR DEVELOPMENT


OF ALMATY REGION” LLP

Aim of ISC: Assistance in the development of the Global Farm” LLP, DP World, “CocaCola Almaty Bottlers”,
competitiveness of the Almaty region and the creation “Hyundai Auto Kazakhstan“LLP
of favorable conditions for attracting investment and Major projects:
industrial development of the region. - Construction of the plant for the production of container
Location : Ablay hana 113, Taldykorgan, Almaty region glass (JSC “GALANZ bottlers”)
Founder : Akimat of Almaty region Construction of dairy - farm for 2,000 heads (LLP
Government: Department of entrepreneurship and «LOYALMATY GROUP»)
industrial-innovation development Constrution of wind electric plant with capacity 60 Mwt
Total volume of attracted investments: 16 bln tenge (JSC “Samruk Energo”
Provided services : Support for effective innovation Construction of hydropower plants on r.Charyn 4 (JSC
implementation and development of high-tech industries. «Aktogay HPP»)
Assistance to investors in the diversification of the Construction of solar power capacity of 25 MW (JV
economy , industrialization of the industrial sector , the “Promondis Kazakhstan”)
development of small and medium-sized businesses in Construction of industrial complex of deep processing of
the region wheat (JSC “Verniy Capital»)
Quantity of implemented projects: 6
Quantity of realizable projects: 36 CONTACT INFORMATION :
Quantity of jobs created: 923 Director Azhmat Alimov Kamzaevich
Major investors: “Danone Berkut” LLP, “FoodMaster +7 (7282) 32 97 33
trade” LLP, “Phillip Morris Kazakhstan” LLP, “Abdi Ibrahim info@rcd.kz

INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF ATYRAU REGION

Purpose: Searching for investors, service and escort - «AtyrauNefteMash» (Kazakhstan)


investors in the Atyrau region Major projects:
Location: Atyrau region, Atyrau city, Southern Industrial Reconstruction and modernization of the Atyrau refinery -
Zone, 1 JSC NC
Founder: Department of business and industrial-innovative «KazMunayGas»
development of Atyrau Region Construction of an integrated gas-chemical complex -
Governing: «Atyrau Innovations» LLP «Kazakhstan Petrochemical Industries Inc.» JSC
Total investments: 8 011,7 million US dollars Construction of the plant for the production of plastic pipes -
Services: Corporation «Chevron Munaygas Inc.»
- search of investments for financing of projects; Construction of the plant for the production of chemicals for
- implementation of functions of «the first window» for the oil industry - «Rauan Nalco LLP»
investors; Production of goat’s milk and cattle - «Rozmetov» LLP farm.
- information and analytical providing investors. Modernization of production (service, repair and
Realized projects : 35 projects maintenance of directional drilling using telemetry systems)
Realizing projects : 7 projects - «ZhigerMunayServis» LLP
Workplaces : about 5 455 person
Major investors: CONTACT INFORMATION:
- «Novus Sealing Limited» (Great Britain) Adress: 060000, RК, Atyrau region, Atyrau city, Southern
- «Chevron Corporation» (USA) Industrial Zone, 1
- «Nalco Champion» (USA) + 7 (71 22) 58 63 35
- «Pera plastic» (Azerbaijan) atyrauinvest@mail.ru
- «Brando» (Kazakhstan) www.atyrauinnov.kz, www.atyrauinvest.kz
52
INVESTORS SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF WEST KAZAKHSTAN REGION

Aim of ISC: creating a favorable economic environment for Kazakhstan)


investments and innovations in the West Kazakhstan region Major projects: «The organization and the construction of
Location : West Kazakhstan region, The Republic of the Kazakh-Turkish industrial zone in the West Kazakhstan
Kazakhstan region» worth 10,0 billion tenge, «Extensive repairs and
Founder : Akimat of the West Kazakhstan region of the reconstruction of the administrative building in the business
Republic of Kazakhstan center of «А» class» worth 1,0 billion tenge, «Construction
Government: JSC «NC «SEC «Oral» of five-star hotel in the «Samal»area of the Uralsk» worth 2,5
Total volume of attracted investments: 21,0 bl. tenge billion tenge, «Exploration and production of potassium salts
Provided services : organizing and conducting meetings, on the «Shugul» dome in Akzhaik District of WKR» worth
negotiations and «round tables» with domestic and foreign 7,4 billion tenge, «Exploration and production of potassium
investors, searching for foreign and domestic investors for salts at the Grigoryevskaya salt structure in Burlin district of
the region, potential partners for joint ventures between the WKR» worth 3,5 billion tenge, Upgrading of the coastal zone
Kazakh and foreign parties and others of Shalkar Lake
Quantity of implemented projects: 2
Quantity of realizable projects: 8 CONTACT INFORMATION :
Quantity of jobs created: 35 Dostyk-Druzhba avenue, 206/1, Uralsk,
Major investors: «Chagala Group» (Netherlands, Great +7(7112) 50 59 47
Britain, Kazakhstan) «Bolashak-T» LLP (Kazakhstan), + 7 (7112) 50 66 28
«Akgun Group» (Turkey) and «Batys Mineral» LLP (Cuba, info@spk-oral.kz

INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF ZHAMBYL REGION

Purpose: Search of investors, service and escort of investors - «Energy Emissions BV» (Netherlands)
in Zhambyl oblast - «Fonroche Renewable Energies» (France)
Place: Zhambyl oblast, Taraz, Tole be st. 35 - «Agrostanferms» (Malaysia)
Founder: «Nacional company «Sociality-enterprise - «Relight» holding (Turkey/Italy)
corporation «Taraz» JSC Projects:
Governing: Entrepreneurship and industrial - innovative - Special economic zone «Chemical park «Taraz»
development department of Zhambyl region - Plant on production of mineral fertilizers of «EuroChem» LLP
Total investments: 483,6 million US dollars - Cement works «Mynaral Tas Company» LLP
Services - Solar power station of «Burnoe Solar»
- search of investments for financing of projects - Сomplex on processing of meat of «Ontustik Halal
- implementation of functions of «the first window» for Tagamdary» LLP
investors - Plant on processing of municipal solid waste of «Recowaste»
- information and analytical providing investors LLP
Realized projects: 6 projects - Plant on production of construction materials from plaster
Realizing projects: 13 projects and dry construction mixes of «Zhambyl gips» JSC
Workplaces : near 2 000 person
Investors: CONTACT INFORMATION:
- «EuroChem» (Russian Federation) Adress: 080000, RK, Zhambyl oblast, Taraz, Tole bi st.35
- «VICAT Group Company» (France) +7 (7262) 43 89 02, +7 (7262) 43 89 03
- «United Green» (Great Britain) tarazinvest@mail.ru
- «ADEAS Development» (UAE) www.dppzhambyl.gov.kz
53
INVESTORS SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF KARAGANDA REGION

Location : Karaganda region CONTACT INFORMATION :


Management company: “Saryarka” SEC” NC” JSC Karaganda city, 4 Stroiteley ave., office 308
Priority activities: all activities +7 (7212) 40 09 83
Total volume of attracted investments: in 2015 - info@spk-saryarka.kz
33,5 billion tenge
Quantity of implemented projects: 2
Quantity of realizable projects: 6
Major investors: german companies - Bohmer Armatura,
Isoplus, Austrian company - Seven Refractories,
korean company – Hyunwoo, russian company -
TechnoNIKOL
Major projects: “Bouhmer Armatura” LLP,
“Isoplus Central Asia” LLP

INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF KOSTANAY REGION

Aim of ISC: Providing proper information, analytical and «Peugeot»;


service support based of principle of “single window“ for «ENRC»;
domestic and foreign investors. «IVECO»;
Location : Kostanay region, Kostanay city «Hyundai»;
Founder : Akimat of Kostanay region «ArcelorMittal»;
Government: JSC «Social – entrepreneurial corporation «Ssang Yuong».
«Tobol» Major projects:
Provided services : - Car manufacturing - CKD assembly of Toyota Fortuner
operational and organizational services to potential model including body welding and painting;
foreign and domestic investors; Construction of small-section rolling mill plant with
PR of investment potential of Kostanay region; capacity of 450 thousand tones of rebar per annum.
promotion and monitoring of investment projects.
Quantity of implemented projects: 10 CONTACT INFORMATION :
Quantity of realizable projects: 4 65 Al-Farabi St, office 1001, Business Center «City
Quantity of jobs created: 1 561 Kostanay» 110000, Kostanay, Republic of Kazakhstan
Major investors: +7 (7142) 392500/390020
«Metallurgical Corporation of China Limited»; www.investinkostanay.kz,
«EVRAZ»; info@investinkostanay.kz
«Toyota»;
54
INVESTORS SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTER OF MANGYSTAU REGION

Purpose: Search of investors, service and escort of «CITIC Group» (China)


investors in Mangystau oblast «HeidelbergCement» (Germany)
Place: Mangystau oblast, Aktau, micro district 35, building «Markmore Group» (Malaysia)
of National Chamber of entrepreneurs «Halliburton» (USA)
Founder: «Special economic zone «Aktau Seaport» JSC «Schlumberger» (France/Netherlands)
Governing: industrial - innovative development Projects:
department of Mangystau region - Plant on production of cables and transformers
Total investments: 625 million US dollars «AktauEnergoMash»
Services - Plant on production of methanol «Kazmeth» LLP
- implementation of functions of «the first window» for - Plant on production of cement «Caspi Cement» LLP
investors - Center of Production and Logistics Azersun
- participation in solving problems of investors at the - Plant on production of bitumen «Caspi Bitum» LLP
regional level, protection of the investors interests Plant on release of the oil equipment «AktauOilMash» LLP
- information and analytical providing investors Plant on release of pipes with a gas-tight threaded
Realized projects: 9 projects connection of a premium class «Kazakhstan Pipe Traders»
Realizing projects: 10 projects LLP
Workplaces : near 4 000 person CONTACT INFORMATION:
Investors: Adress: 130000, RK, Mangystau oblast, Aktau, micro district
- «Azersun Holding» ( Azerbaijan) 35, building of National Chamber of entrepreneurs
- «ENI SPA» (Italy) Tel. 8 (72 92) 334540, fax: 8 (72 92) 302777
- «IDE Technologies» (Israel) E-mail: info.coi@mail.ru Web-site: www.sez.kz

INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTRE OF


NORTH KAZAKHSTAN REGION

Location: Major investors:


North Kazakhstan region Russian Company LLP Aulie Gold Maining,
Founder: Finnish Company Sampo Rosenlew Ltd
Social-entrepreneurial Сorporation «Soltustik“ Major projects:
Regulatory body: SE Сorporation «Soltustik“ LLP Aulie Gold Maining
Total volume of external investments: LLP «KAZTEHMASH»
50,4 million US Dollars
Number of realized projects: 2 CONTACTS:
Number of realizable projects: 14 Kazakhstan, Petropavlovsk
Produced goods: Mira st, 69-14
gold mining, combine assembly +7 702 233 30 94
jas-sko@mail.ru

55
INVESTORS SERVICE CENTERS
INDUSTRIAL INNOVATION PROJECTS

INVESTOR SERVICE CENTRE OF «ERTIS»SEC»NC»JSC

INDUSTRIAL INNOVATION PROJECTS


Aim of ISC: Searching for the investors, service Major projects:
support,consulting and support investors in the East -Construction of a meat processing plant «AGRO PORTAL»
Kazakhstan region. LLP
Location : East Kazakhstan region, Ust-Kamenogorsk, 61 -The construction of greenhouse complex «AlZhan Agro
Kirov street. Trade» LLP
Founder : Akimat of East-Kazakhstan region -Plant for production of basalt insulation
Government: Business and Industry Administration «Techstroynovaciya»LLP
Total volume of attracted investments: 313,7 billion tenge -Plant for the production of paper products «Ust-
Provided services : Kamenogorsk paper mill»LLP
-Search for investment to finance projects.
-Information and analytical support of investors CONTACT INFORMATION:
Quantity of implemented projects: 4 Address: 070019 , East Kazakhstan region,
Quantity of realizable projects: 6 Ust-Kamenogorsk, 61 Kirov street.
Quantity of jobs created: 940 +7 (7232) 26-89-67, +7 (7232) 26-89-50
Major investors: info@spkertis.kz
-«FRÝDLANTSKÉ STROJÍRNY - RASL A SYN A.S»(Czech www.spkertis.kz
Republic)
- «Rifa»(China)
- «Posco e&c»(Korea)
- «Powerchina»(China)

56
Transport Tower building,
32/1 Kabanbai batyr avenue, Astana
010000, Republic of Kazakhstan
Administrative office telephone:
tel.: +7 (7172) 75 44 11
fax: +7 (7172) 75 40 80, 75 40 00
e-mail: mid@mid.gov.kz

Potrebbero piacerti anche