CRONOGRAMA DE ADQUISICION DE INSUMOS O MATERIALES

: “RENOVACIÓN DE VIAS URBANAS EN EL(LA) AVENIDA 20 ENERO DESDE CALLE PRINCIPAL HASTA CALLE PRINCIPAL EN EL DISTRITO DE ANCO, PROVINCIA CHURCAMPA, DEPARTAMENTO HUANCAVELICA”.
PROYECTO:
LUGARES : Av. 20 de Enero-Jr. 8 octubre FECHA : JUNIO- 2018
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE ANCO DISTRITO : ANCO
MOD. EJECUCION : ADMINISTRACION INDIRECTA-CONTRATA A ZUMA ALZADA PROVINCIA : CHURCAMPA

DURACION : 3.00 MESES DE EJECUCIÓN DEPARTAMENTO : HUANCAVELICA

PRESUPUESTO MES 1 MES 2 MES 3


DESCRIPCION UND
CANT PRECIO PRESUP. (S/.) CANT COSTO CANT COSTO CANT COSTO

MANO DE OBRA
OFICIAL JORNAL 226.8600 134.40 30,489.98 21.60 2,903.04 55.94 7,518.34 149.32 20,068.61
OPERARIO JORNAL 180.0600 167.36 30,134.84 13.17 2,204.13 92.72 15,517.62 74.17 12,413.09
PEON JORNAL 779.2500 120.32 93,759.36 217.09 26,120.27 236.50 28,455.68 325.66 39,183.41
TOPOGRAFO JORNAL 12.4000 217.60 2,698.24 12.40 2,698.24 0.00 0.00 0.00 0.00
MATERIALES 0.0000 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 352.8000 3.22 1,136.02 0.00 0.00 352.80 1,136.02 0.00 0.00
AGUA m3 239.6300 2.97 711.70 0.00 0.00 203.58 604.63 36.05 107.07
ALAMBRE NEGRO RECOCIDO # 16 kg 145.2200 4.07 591.05 0.00 0.00 108.81 442.86 36.41 148.19
ALAMBRE NEGRO RECOCIDO # 8 kg 268.2800 4.07 1,091.90 0.00 0.00 178.32 725.76 89.96 366.14
ALQUILER DE LOCAL mes 3.0000 180.00 540.00 3.00 540.00 0.00 0.00 0.00 0.00
ARENA FINA m3 0.7000 84.75 59.33 0.00 0.00 0.00 0.00 0.70 59.33
ARENA GRUESA m3 78.2800 76.27 5,970.42 0.00 0.00 24.51 1,869.38 53.77 4,101.04
ASFALTO RC-250 gal 57.1200 10.59 604.90 0.00 0.00 0.00 0.00 57.12 604.90
BOTAS DE JEBE PAR 20.0000 28.50 570.00 20.00 570.00 0.00 0.00 0.00 0.00
BOTIQUIN CON MEDICAMENTOS und 1.0000 460.00 460.00 1.00 460.00 0.00 0.00 0.00 0.00
CAMILLA und 2.0000 380.00 760.00 2.00 760.00 0.00 0.00 0.00 0.00
CARTEL DE OBRA INC/ INSTALACION u 1.0000 850.00 850.00 1.00 850.00 0.00 0.00 0.00 0.00
CASCO DE PROTECCIÓN und 20.0000 15.20 304.00 20.00 304.00 0.00 0.00 0.00 0.00
CEMENTO PORTLAND TIPO I (42.5KG). BOL 2,937.8300 21.19 62,252.62 0.00 0.00 1,155.46 24,484.20 1,782.37 37,768.42
CHALECO REFLECTIVOS und 20.0000 22.40 448.00 20.00 448.00 0.00 0.00 0.00 0.00
CHARLAS DE CAPACITACIÓN EN SEGURIDAD AL PERSONAL glb 1.0000 5,000.00 5,000.00 1.00 5,000.00 0.00 0.00 0.00 0.00
CILINDRO VACIO ABIERTO u 2.0000 32.50 65.00 2.00 65.00 0.00 0.00 0.00 0.00
CINTA DE SEÑALIZACIÓN m 500.0000 0.15 75.00 500.00 75.00 0.00 0.00 0.00 0.00
CLAVOS PARA MADERA CON CABEZA DE 2 1/2" kg 61.4500 4.07 250.10 0.00 0.00 54.25 220.80 7.20 29.30
CLAVOS PARA MADERA CON CABEZA DE 3" kg 187.1800 4.07 761.82 0.00 0.00 145.49 592.14 41.69 169.68
CONO DE SEGURIDAD u 20.0000 23.50 470.00 20.00 470.00 0.00 0.00 0.00 0.00
ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE SEGURIDAD
glb 1.0000
Y SALUD 6,000.00
EN EL TRABAJO 6,000.00 1.00 6,000.00 0.00 0.00 0.00 0.00
EQUIPOS DE PROTECCIÓN COLECTIVA und 1.0000 3,500.00 3,500.00 1.00 3,500.00 0.00 0.00 0.00 0.00
ESTACA DE MADERA TORNILLO TRATADA p2 123.9700 2.37 293.81 123.97 293.81 0.00 0.00 0.00 0.00
EXTINTOR DE POLVO SECO und 2.0000 700.00 1,400.00 2.00 1,400.00 0.00 0.00 0.00 0.00
FLETE TERRESTRE glb 1.0000 27,771.29 27,771.29 0.85 23,605.60 0.15 4,165.69 0.00 0.00
GRAVA GRUESA PARA DRENAJE m3 5.8000 63.56 368.65 0.00 0.00 0.00 0.00 5.80 368.65
GUANTES DE CUERO PAR 20.0000 14.63 292.60 20.00 292.60 0.00 0.00 0.00 0.00
HORMIGON DE RIO m3 77.8500 67.80 5,278.23 0.00 0.00 34.99 2,372.32 42.86 2,905.91
LENTES DE PROTECCIÓN und 20.0000 8.44 168.80 20.00 168.80 0.00 0.00 0.00 0.00
MADERA NACIONAL P/ENCOFRADO-CARP p2 4,391.2400 3.39 14,886.30 0.00 0.00 3,287.45 11,144.46 1,103.79 3,741.85
MARCO Y TAPA DE FF° BUZON 0.60 m X 125 KG u 12.0000 322.03 3,864.36 0.00 0.00 12.00 3,864.36 0.00 0.00
MATERIAL GRANULAR PARA AFIRMADO m3 1,206.3400 33.90 40,894.93 0.00 0.00 1,206.34 40,894.93 0.00 0.00
MITIGACION DE IMPACTO AMBIENTAL glb 1.0000 2,680.00 2,680.00 0.00 0.00 1.00 2,680.00 0.00 0.00
PEGAMENTO PARA PVC gal 0.7100 93.22 66.19 0.71 66.19 0.00 0.00 0.00 0.00
PIEDRA CHANCADA DE 1/2" m3 104.5800 63.56 6,647.10 0.00 0.00 33.06 2,101.29 71.52 4,545.81
PIEDRA CHANCADA DE 3/4" m3 1.6800 63.56 106.78 0.00 0.00 1.68 106.78 0.00 0.00
PIEDRA GRANDE m3 129.7500 50.85 6,597.79 0.00 0.00 58.32 2,965.57 71.43 3,632.22
PINTURA ESMALTE gln 6.2000 32.20 199.64 6.20 199.64 0.00 0.00 0.00 0.00
POSTE DE SEGURIDAD u 30.0000 50.00 1,500.00 30.00 1,500.00 0.00 0.00 0.00 0.00
REJILLA DE ACERO CORRUGADO m 60.3300 65.00 3,921.45 0.00 0.00 0.00 0.00 60.33 3,921.45
RESPIRADOR CONTRA POLVO und 20.0000 6.04 120.80 20.00 120.80 0.00 0.00 0.00 0.00
ROLLO DE MALLA DE SEGURIDAD rll 20.0000 35.00 700.00 20.00 700.00 0.00 0.00 0.00 0.00
SEÑAL VERTICAL PREVENTINA u 30.0000 25.00 750.00 30.00 750.00 0.00 0.00 0.00 0.00
TAPONES AUDITIVOS PAR 20.0000 18.69 373.80 20.00 373.80 0.00 0.00 0.00 0.00
TECKNOPORT E= 1" m2 25.3700 4.24 107.57 0.00 0.00 0.00 0.00 25.37 107.57
TRANSPORTE DE EQUIPO Y MAQUINARIA glb 1.0000 23,788.32 23,788.32 0.78 18,554.89 0.22 5,233.43 0.00 0.00
CRONOGRAMA DE ADQUISICION DE INSUMOS O MATERIALES

: “RENOVACIÓN DE VIAS URBANAS EN EL(LA) AVENIDA 20 ENERO DESDE CALLE PRINCIPAL HASTA CALLE PRINCIPAL EN EL DISTRITO DE ANCO, PROVINCIA CHURCAMPA, DEPARTAMENTO HUANCAVELICA”.
PROYECTO:
LUGARES : Av. 20 de Enero-Jr. 8 octubre FECHA : JUNIO- 2018
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE ANCO DISTRITO : ANCO
MOD. EJECUCION : ADMINISTRACION INDIRECTA-CONTRATA A ZUMA ALZADA PROVINCIA : CHURCAMPA

DURACION : 3.00 MESES DE EJECUCIÓN DEPARTAMENTO : HUANCAVELICA

PRESUPUESTO MES 1 MES 2 MES 3


DESCRIPCION UND
CANT PRECIO PRESUP. (S/.) CANT COSTO CANT COSTO CANT COSTO

TUBERIA PVC SAL 4" m 53.5500 8.47 453.57 53.55 453.57 0.00 0.00 0.00 0.00
TUBERIA PVC SAP PRESION C-10 C/R. 1/2" X 5m m 53.5500 2.12 113.53 53.55 113.53 0.00 0.00 0.00 0.00
TUBO PVC 3" m 43.4700 6.78 294.73 0.00 0.00 0.00 0.00 43.47 294.73
YESO EN BOLSAS DE 28 KG. BOL 61.9800 9.32 577.65 61.98 577.65 0.00 0.00 0.00 0.00
EQUIPOS E HERRAMIENTAS 0.00 0.00 0.00 0.00 0.00 0.00
CAMION CISTERNA 4 X 2 (AGUA) 122 HP 2,000 gl DIA 8.0700 813.52 6,565.11 0.00 0.00 8.07 6,565.11 0.00 0.00
CAMION VOLQUETE 15 m3 DIA 49.9400 1,016.96 50,786.98 23.94 24,346.02 23.76 24,162.97 2.24 2,277.99
CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3 DIA 13.2000 1,220.32 16,108.22 5.99 7,309.72 6.76 8,249.36 0.45 549.14
COMPACTADOR VIBRATORIO TIPO PLANCHA 7HP DIA 4.1600 115.28 479.56 0.83 95.68 3.33 383.88 0.00 0.00
ENCOFRADO METALICO STANDARD DIA 2.4000 78.00 187.20 0.00 0.00 2.40 187.20 0.00 0.00
ESTACION TOTAL DIA 12.4000 101.68 1,260.83 12.40 1,260.83 0.00 0.00 0.00 0.00
HERRAMIENTAS MANUALES S/. 6,436.8646 1.00 6,436.86 1,169.07 1,169.07 2,229.55 2,229.55 3,038.25 3,038.25
MEZCLADORA DE CONCRETO DE 9 -11p3 DIA 25.7400 101.68 2,617.24 0.00 0.00 10.81 1,099.16 14.93 1,518.08
MOTONIVELADORA DE 125 HP DIA 8.0700 1,220.32 9,847.98 0.00 0.00 8.07 9,847.98 0.00 0.00
RODILLO LISO VIBRATORIO AUTOPROPULSADO 70-100 HP 7-9 ton DIA 8.0700 881.36 7,112.58 0.00 0.00 8.07 7,112.58 0.00 0.00
TRACTOR DE ORUGAS DE 190-240 HP DIA 10.2200 1,694.88 17,321.67 8.02 13,592.94 2.20 3,728.74 0.00 0.00
VIBRADOR DE CONCRETO 4 HP 2.40" DIA 25.7400 67.76 1,744.14 0.00 0.00 10.81 732.49 14.93 1,011.66
ZARANDA MECANICA DIA 3.4700 61.04 211.81 0.00 0.00 3.47 211.81 0.00 0.00

TOTALES S/.514,452.35 S/.149,912.81 S/.221,607.07 S/.142,932.47

AVANCE MENSUAL 100.00% 0.00% 29.14% 43.08% 27.78%

AVANCE MENSUAL ACUMULADO 100.00% 0.00% 29.14% 72.22% 100.00%