Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Intermediate heat exchanger. In the first Figure 1. Single-chiller plant (intermediate heat exchanger)
configuration (Figure 1), the water chiller
produces 40°F fluid (water or brine). Some
chiller plant
of this fluid is distributed to the
dehumidifying coils in the air-handling units; 56°F 40°F
40°F
If glycol is needed for freeze protection, it sensible coils in
terminal units dehumidifying
can be isolated to flow through the water coils in AHUs
chiller and dehumidifying coils only. Pure
water can be used on the indoor side of the 63°F 56°F
heat exchanger, so the glycol will not affect
the capacity of the terminal units. * included if variable-flow chiller pumps are used
** optional (or some systems use a separate air-to-water heat exchanger incorporated into the air-cooled chiller)
Blending valve. If glycol is not needed, or
if glycol will be circulated through the
terminal units also, a blending valve can be Figure 2. Single-chiller plant (blending valve)
chiller plant
exchanger (Figure 2). In this configuration,
the water chiller again produces 40°F water, 60°F 40°F
some of which is distributed directly to the
dehumidifying coils. The remaining cold
water is blended with warm water (63°F) chiller minimum flow
221 gpm bypass pipe and valve*
returning from the terminal units to produce
the required 57°F supply water for the
terminals.
blending
valve
This configuration provides a small efficiency
advantage, since the intermediate heat
exchanger used in the previous configuration
is not 100-percent effective. But the
432 gpm
hydronics are more challenging because the
blending valve must be carefully selected
and commissioned to provide accurate, dry cooler or fluid cooler for
stable control over the expected range of water economizing** 57°F
system operating pressures.
40°F
sensible coils in
terminal units dehumidifying
coils in AHUs
63°F 56°F
2 Trane Engineers Newsletter volume 44–3 providing insights for today’s HVAC system designer
ADM-APN055-EN_dual_tempFINAL.fm Page 3 Thursday, September 17, 2015 1:17 PM
chiller plant
more than one chiller to improve plant
60°F
efficiency and to provide redundancy if one 250 tons
of the chillers were to fail or require service. chiller 1
40°F
When the plant is designed with two
chillers, there are several configurations that 250 tons
might be used to provide the two different chiller 2
613 gpm
water temperatures. While either air- or
water-cooled chillers can be used in a two- chiller minimum flow blending
chiller plant, our example will assume water- bypass pipe and valve* valve
cooled chillers.
chiller plant
chiller cools the water from 60°F to 50°F,
while the downstream chiller cools it the 60°F 50°F 40°F
rest of the way to 40°F.
250 tons 250 tons
One benefit of configuring chiller chiller 1 chiller 2
(w/ free cooling)**
evaporators in series is lower overall plant 613 gpm
energy use. In this example system (see
Table 1), the upstream chiller operates much
chiller minimum flow blending
more efficiently (0.462 kW/ton) since it need bypass pipe and valve* valve
only cool the water to 50°F, resulting in less
total chiller power. Since the full water flow
rate (613 gpm) is pumped through both 300 gpm
chiller evaporators, the incremental pump 1200 gpm
power is higher (4.4 kW compared to 1.1 kW water
with chillers in parallel). But the total power economizer**
57°F
for both chillers plus incremental pumping
power is still 9 percent lower with the
chillers configured in series (261.2 kW sensible coils in 40°F
terminal units
versus 285.9 kW with chillers in parallel). dehumidifying
coils in AHUs
63°F 56°F
providing insights for today’s HVAC system designer Trane Engineers Newsletter volume 44–3 3
ADM-APN055-EN_dual_tempFINAL.fm Page 4 Thursday, September 17, 2015 1:17 PM
evaporator evaporator
chiller entering leaving evaporator incremental
evaporator water water chiller chiller chiller pressure pumping
flow rate, temperature, temperature, load, efficiency1, power, drop, power2,
gpm °F °F tons kW/ton kW ft. H2O kW
chillers in parallel
loads in parallel,
(upstream)
(Figure 4)
(upstream)
(Figure 5)
(upstream)
(split flow)
(Figure 7)
(Figure 8)
chillers
Another benefit of configuring the chiller so that one chiller operating alone can p.9), arranging the condensers in a series-
evaporators in series is that it simplifies provide a 60 or 70 percent of the design counterflow configuration can provide this
sequencing (turning chillers on and off) in capacity while the other chiller is serviced. redundancy without sacrificing
a variable-primary flow (VPF) system.3 performance. 4
To provide redundancy with chillers in
The drawback of configuring chillers in series, the upstream chiller may need to be In addition, a set of bypass pipes and
series is that it is more challenging to selected for "less-than-optimal" shutoff valves need to be added to the
provide redundancy if one chiller is not performance so that it is capable of plant to enable either of the chillers to
operational. With the chillers in parallel, producing 40°F water if the downstream operate while the other chiller is serviced
both chillers are likely to be identical, and chiller is not operational. Unless the (see Figure 4).
can be selected for a little extra capacity upstream chiller is a free-cooling chiller (see
4 Trane Engineers Newsletter volume 44–3 providing insights for today’s HVAC system designer
ADM-APN055-EN_dual_tempFINAL.fm Page 5 Thursday, September 17, 2015 1:17 PM
Blending valve with loads in series Figure 5. Two-chiller plant (loads in series, chillers in series)
(chillers in parallel or series). When
chiller plant
the temperature of the water returning
from the dehumidifying coils (56°F in 60°F 51.5°F 40°F
this example) is colder that the water 63°F
being supplied to the sensible-only 250 tons 250 tons
terminal units (57°F), some designers chiller 1 chiller 2
consider configuring these loads in (w/ free cooling)**
series (Figure 5). In this configuration, 522 gpm
40°F water from the chiller plant is first
distributed to the dehumidifying coils.
The 56°F water returning from these blending
valve
coils is then blended with warm water 678 gpm
(63°F) returning from the terminal units
(and maybe some additional 40°F 222 gpm
water from the chiller plant) to produce 1200 gpm
57°F water for the terminals. cold-water supply
water valve and chiller
economizer** minimum flow
Configuring the loads in series offers
bypass valve*
an efficiency benefit compared to the 57°F
loads in parallel (255.4 kW with chillers
in series, versus 261.2 kW with the sensible coils in 40°F 300 gpm
terminal units
loads in parallel and chillers in series),
since the chiller plant flow rate is lower
(522 gpm compared to 613 gpm with 63°F dehumidifying
56°F
loads in parallel) and the larger plant coils in AHUs
delta T allows the upstream chiller to
* used to ensure adequate supply of cold water for sensible coils when dehumidification AHU coil control valves are modulating or
be selected for a warmer leaving-water closed AND also used to ensure minimum evaporator flow if variable-flow chiller pumps are used
temperature. ** some systems configure one chiller as a “free-cooling” chiller, while others include a separate plate-and-frame heat exchanger for
water economizing
However, this configuration does
introduce some added control
complexity. The chiller minimum flow
bypass valve now has a second to deliver the required 57°F water to Figure 6. Cold-water bypass when loads in series
purpose. In addition to ensuring the terminals (Figure 6, bottom). This
minimum evaporator flow through any amount of bypass varies as the control blending
valve
operating chiller, it must also ensure an valves on the dehumidifying coils returning 63°F
from 900 gpm cold-water
adequate supply of cold water at the modulate or close, and may require the terminal bypass valve
units
blending valve. bypass pipe to be larger than if it were 61°F 0 gpm
1200 gpm from
only needed to ensure minimum chiller
At design load for this example, 300 evaporator flow. plant
supply to 56°F
gpm of 40°F water is supplied to the terminal units 300 gpm
dehumidifying coils, which returns at For this loads-in-series configuration, returning from
56°F. Blending only this 300 gpm of the chiller evaporators can be piped dehumidifying
coils
56°F water with 63°F water returning either in parallel or series. Similar to
from the terminal units results in a the previous example, configuring the
63°F
61°F supply temperature to the chiller evaporators in series results in 678 gpm
terminals (Figure 6, top). 11 percent less total power (255.4 kW 40°F
versus 285.9 kW with the chiller 222 gpm
So the bypass valve must open to mix 57°F
evaporators in parallel, see Table 1). 1200 gpm
222 gpm of 40°F water with the 300 56°F
But as mentioned, configuring the 300 gpm
gpm of 56°F water returning from the chillers in series makes it more
dehumidifying coils, to ensure that the challenging to provide redundancy in
blending valve has enough cold water case one chiller is not operational.
providing insights for today’s HVAC system designer Trane Engineers Newsletter volume 44–3 5
ADM-APN055-EN_dual_tempFINAL.fm Page 6 Thursday, September 17, 2015 1:17 PM
Chillers in series with split flow. Figure 7. Two-chiller plant (chillers in series with split flow)
With the chiller evaporators configured in
series, some designers consider splitting
1500 gpm 300 gpm
the flow between the two chillers (Figure
chiller plant
7). In this example, the upstream chiller 57°F 40°F
62°F 288 tons 212 tons
cools all the water to 57°F. Some of this
water is then distributed directly to the chiller 1 chiller 2
terminal units for space sensible cooling, (w/ free cooling)**
while the rest passes through the
downstream chiller and is cooled to 40°F
for the dehumidifying coils. supply temperature
control valve 300 gpm
Since the upstream chiller operates at an
even warmer leaving-water temperature
1200 gpm
(57°F), it is more efficient (0.399 kW/ton). chiller minimum flow chiller minimum flow
bypass pipe and valve* bypass pipe and valve*
However, because there is no blending, 57°F
the full flow rate required by the terminal
units (1200 gpm) plus the flow rate
required by the dehumidifying coils water
(300 gpm) passes through the upstream economizer**
chiller, resulting in a higher evaporator
pressure drop and pump energy penalty. 57°F 40°F
sensible coils in
terminal units
This configuration is an attempt to
dehumidifying
maximize the efficiency of the upstream coils in AHUs
chiller, since it does not cool the water 63°F 56°F
intended for the terminal units any more
than needed. However, if the water * included if variable-flow chiller pumps are used
returning from the dehumidifying coils (at ** some systems configure one chiller as a “free-cooling” chiller, while others include a separate plate-and-frame heat exchanger for
water economizing
56°F in this example) is cooler than the
water leaving the upstream chiller (57°F),
there is energy wasted. The 56°F return
water is mixed with 63°F water returning additional temperature control valve for
For this example, the total power for both
from the terminal units and passes the 57°F water loop. Since most
chillers plus incremental pumping power
through the upstream chiller. Rather, it sensible-only terminal units cannot allow
is 6 percent lower than the loads-in-
would be more efficient to simply direct condensation, the water supplied to
parallel/chillers-in-series configuration,
that 56°F return water right into the them must always remain at a
and 4 percent lower than the loads-in-
downstream chiller. temperature above the space dew point
series/chillers-in-series configuration
(Table 1). Splitting the flows does avoid temperature. Depending on how
So splitting the flows provides an
the complication of controlling the chiller accurate and stably the upstream chiller
efficiency benefit for the upstream chiller,
minimum flow bypass valve to also is able to control its leaving-water
but directing all of the flow through the
bypass cold water if needed, but the temperature, the designer may want to
upstream chiller is inefficient unless the
interaction of the two pumping systems include this additional valve to ensure
water returning from the dehumidifying
may be difficult to balance and control. that too cold of water is never
coils is significantly warmer than the
Plus, it provides very little redundancy distributed to the terminal units. Under
water leaving the upstream
since the chiller flow rates and water low load conditions, if the chiller has
chiller…which is unlikely.
temperatures are drastically different. reached its minimum stage of capacity
and begins to produce water that is
This configuration requires two separate colder than the desired 57°F setpoint,
chiller bypass pipes with minimum flow this valve will blend in a small amount of
control valves. Figure 7 also shows an warm return water.
6 Trane Engineers Newsletter volume 44–3 providing insights for today’s HVAC system designer
ADM-APN055-EN_dual_tempFINAL.fm Page 7 Thursday, September 17, 2015 1:17 PM
Dedicated chillers. In this final Figure 8. Two-chiller plant (dedicated chillers with hydraulic connections)
configuration, one chiller supplies 57°F
water directly to the terminal units,
while a separate chiller supplies 40°F cold cold supply
chiller plant
return 40°F stub
water directly to the dehumidifying V-2
stub
coils (Figure 8).
200 tons
chiller 2 warm
The benefit of this configuration is that supply
V-4 57°F stub
it maximizes the efficiency of the V-1 V-3
"warm-water" chiller. Only the flow rate
300 tons
required by the terminal units passes
warm chiller 1
through it and this water is only cooled return (w/ free cooling)**
to the required 57°F setpoint (not over- stub
supply temperature 1200 gpm 300 gpm
cooled). The "cold-water" chiller control valve
handles only the flow required by the
dehumidifying coils. chiller minimum flow chiller minimum flow
bypass pipe and valve* bypass pipe and valve*
57°F
The total power for both chillers plus
incremental pumping power is the
lowest of all the configurations water
analyzed—242.8 kW (Table 1). economizer**
providing insights for today’s HVAC system designer Trane Engineers Newsletter volume 44–3 7
ADM-APN055-EN_dual_tempFINAL.fm Page 8 Thursday, September 17, 2015 1:17 PM
Plant with Three or More Figure 9. Dual-temperature plant with third chiller for redundancy
Chillers
40°F V-2
chiller plant
When the plant is designed to include
chiller 2
three or more chillers, the most V-6 V-5
efficient configuration is likely to use
the dedicated-chillers approach with
chiller 3
interconnecting pipes and shutoff V-4 V-3
57°F V-1
valves to provide redundancy.
the terminal units. ** some systems configure one chiller as a “free-cooling” chiller, while others include a separate plate-and-frame heat
exchanger for water economizing
• If the "cold-water" chiller (chiller 2)
fails, valve V-2 is closed, valves V-5
and V-6 are opened, and chiller 3 is Incorporating a Water Water economizing with water-
operated to supply 40°F water to cooled chillers. If water-cooled
Economizer chillers are used, a water economizer is
the dehumidifying coils.
typically provided using either
Even if the chiller plant was originally Most buildings that include sensible- 1) a separate plate-and-frame heat
conceived to include only two chillers, only terminal units use a dedicated exchanger, or 2) by configuring one of
it may be desirable to design it for outdoor air (OA) system for ventilation, the water chillers as a "free-cooling"
three chillers instead, so that the plant so conventional air economizing is centrifugal chiller (i.e., a thermosiphon).
provides added redundancy in the usually not possible. Therefore, a water
event of a chiller failure. This would
economizer may be used to provide When a plate-and-frame heat
allow the "warm-water" chiller to be
"free" cooling during mild weather.5 exchanger is used, cold water from
optimized to supply 57°F water,
without sacrificing efficiency by having This can be particularly valuable for the cooling tower passes through one
to select it to be capable of making systems that use chilled-water terminal side of the heat exchanger, which cools
40°F in an emergency (as would be units for space cooling, since interior the chilled water flowing through the
required in a plant with only two zones may require a supply of water for other side. In most applications,
chillers). cooling, even when it’s cold outside. In locating this heat exchanger to pre-cool
this case, water economizers can allow the warm water returning from the
the chillers to be turned off during the terminal units provides the greatest
colder months of the year. benefit (see Figures 3-9). This location
is where the chilled-water loop is
Water economizers are most prevalent warmest, so the water economizer is
in systems that use water-cooled able to reduce the chiller load any time
chillers, but they can also be used in the cooling tower is able to produce
systems with air-cooled chillers. water that is colder than about 61°F for
this example (63°F return water minus
a 2°F heat exchanger approach).
8 Trane Engineers Newsletter volume 44–3 providing insights for today’s HVAC system designer
ADM-APN055-EN_dual_tempFINAL.fm Page 9 Thursday, September 17, 2015 1:17 PM
Some engineers express concern that, Figure 10. Water economizing likely not useful for dehumidifying coils
in this location, the water economizer
can only reduce the cooling load from
the terminal units, but not from the outdoor conditions when the
cooling tower is able to 80
dehumidifying coils. In this example,
provide cool enough water to
for the water economizer to reduce the reduce the load from
75
load from the dehumidifying coils, the dehumidifying coils, but
cooling tower must be able to produce these coils are now off
because the outdoor air is 70
water that is colder than 54°F (56°F outdoor conditions when
below 47°F DPT
dehumidifying coils in air-handling 65
return water minus a 2°F approach). units must operate to dehumidify air
This would likely require the outdoor 60
to the required 47°F DPT
wet-bulb temperature to be below 55
providing insights for today’s HVAC system designer Trane Engineers Newsletter volume 44–3 9
ADM-APN055-EN_dual_tempFINAL.fm Page 10 Thursday, September 17, 2015 1:17 PM
10 Trane Engineers Newsletter volume 44–3 providing insights for today’s HVAC system designer
ADM-APN055-EN_dual_tempFINAL.fm Page 11 Thursday, September 17, 2015 1:17 PM
www.Trane.com/bookstore
Learn HVAC design strategies and earn credit
providing insights for today’s HVAC system designer Trane Engineers Newsletter volume 44–3 11
ADM-APN055-EN_dual_tempFINAL.fm Page 12 Thursday, September 17, 2015 1:17 PM
Trane, Trane believes the facts and suggestions presented here to be accurate. However, final design and
A business of Ingersoll Rand application decisions are your responsibility. Trane disclaims any responsibility for actions taken on
the material presented.
For more information, contact your local Trane
office or e-mail us at comfort@trane.com