Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
COMPILED BY:
EARTH GEO ENGINEERING NIG LTD
37, BISI ADELESI STREET, AGILITI,
MILE 12, KOSOFE L.G.A. LAGOS STATE.
TEL: +234803-421-4560 / +234808-771-7184
REF NO:earthgeo-03/20-0029
MARCH, 2020.
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
TABLE OF CONTENTS
SECTION PAGE
Table of Contents 1
Project Team 3
1.0. INTRODUCTION 4
1.1.0 General Information
1.1.1 Investigation Objectives
1.1.2 Scope of Work
1.1.3 Project Description
1.1.4 Site Accessibility
1.1.5 Regional Geology
1.1.6 Brief Site Geology
2.0 SYNOPSIS OF FIELD WORK 6
2.1.0 Dutch Cone Penetration Test (2.5 Tons Capacity)
2.1.1 Geotechnical Boring
2.1.2 Sampling in Non Cohesive Soil
2.1.3 Sampling in Cohesive Soil
3.0 SUBSOIL CONDITION 8
3.0 Subsoil Condition
3.1 Groundwater Condition
4.0 BEARING CAPACITY ANALYSIS 9
4.1.0 Bearing Capacity Analysis Based on CPT Data
5.0 RECOMMENDATION AND CONCLUSION 10
5.1 Recommendation
5.2 Conclusion
REFERENCE
NOTES
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 1
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
Reference: 03/20-0029
• The B.S. 8004: 1986 (Presently CP 2004: 1972) Code of practice for foundations
A Caple Percussion with shell and auger method was used to probe the site at one location
to a proposed depth of 30.0m, however, as at today, only 15m depth was achieved, to be
completed tomorrow. Recovered soil samples from the boring shall be taken to the
laboratory for test.
Also, eight number Cone Penetration Tests were performed until anchors were pulled at
designated building locations such as the administrative building, male hostel etc.
We hope that our findings and recommendations would be of assistance to the design
engineers.
We remain yours,
Engr.Shola Adegboye F.
FOR: Earth Geo Engineering Nig Ltd.
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 2
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
PROJECT TEAM
FIELD TEAM
Head Operator – Rig 1: Emma.
Head Operator – Rig 2: Isaac.
Assistant 1: Peter
Assistant 2: James
Labourers 3
Site Foreman Zagi Macus
CERTIFIED
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 3
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
1.0 INTRODUCTION
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 4
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 5
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 6
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 7
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
NOTE: The site was wet and it rained the previous night before the tests were conducted.
The boring performed on the site from the current ground level up to the depth of 13.5m confirmed
the occurrence of greyish silty sand from the top to lateritic clay material which was described on
the site as soft, and this layer overlies another yellowish brown clay which appear soft but denoted
as firm in the table below and shall be confirm from the laboratory afterwards. Below this layer of
clay is an occurrence of sandy clay material which overlies two main sand layers which are fine
layers and medium to coarse grained layer at 13.5m where the boring temporarily ended and to
be continued tomorrow the 27th March 2020.
The table below shows the presentation of soil stratification on the site as classified using the 1
number boring performed on the Administrative Building location.
TABLE 1: Summary of Subsoil Strata and Geotechnical Properties based on the Borehole.
3.1 GROUND WATER LEVEL: The field work activity was performed during the early rainfall
period of the year, it rained the previous night before the test were carried out, however, no
groundwater was encountered thus far.
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 8
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
TABLE 2: Allowable Bearing Pressure based on the data from the CPT Reading
CPT Data
Depth Mean QC Ultimate Bearing Allowable
(m) Value Capacity (kN/m²) Bearing Pressure
(Kg/m2) (kN/m²)
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 9
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
The recommendations made in this report are based on the results of the field analysis of the
acquired data, using the results of the allowable bearing pressure and our general assessment
of the assumed anticipated load as mentioned by the project engineer to be 2 storied building
i.e. a ground floor and 2 floor slabs for a school administrative building.
However, from the allowable pressure stated in table 2 and the observed underlying subsoil
strata in table 1, shallow foundation and deep foundation may be considered:
SHALLOW FOUNDATION RECOMMENDATION
Though, the actual total load of the proposed building was not stated or mentioned but
for the purpose of this report, we have assumed an average floor loading of 15kN/m2 for
a floor. Hence, an overall ground – bearing pressure for a maximum loaded 3 – floors
would be 45kN/m2 i.e. the ground floor and two floor slabs.
From the CPT data stated in table 1 having 40.5 kN/m2 Bearing Capacity at 2.0m
depth, it is suggested that a well Reinforced Shallow Foundation in the form of
RAFT could be adopted to a minimum depth of 1.5m.
With this observation, we cautiously advised that the Engineer ensure that the
top soil on the building area is removed to accommodate an approved and
suitable import filling material.
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 10
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
Some form of deep foundations such as deep reinforced concrete columns of medium to big size
cross-sectional area can be used to transmit the column loads from the building base to terminate
within the medium dense sand indicated to occur below 6.00m depths and as such, the piles can
be terminated at 6.50m depth, see the table 1 for reference. Such foundations should be
capable of mobilizing moderate safe working loads sufficient for the proposed building.
Bored cast-in-place piles should be used to avoid the risk of damage to adjacent structures
resulting from the other types of pile and their vibrations.
The following piles working loads are quoted as a guide based on data obtained from the SPT
results for bored cast-in-place piles:
As per our analysis, a toe bearing capacity of 2560 kN/m² is calculated;
Factors considered for the Tip/Base and Frictional Resistance are stated herein:
PILE TERMINATION DEPTH ≥ 7.0m
Qb – Adopted Factor of Safety is 2.5
Qs – Adopted Factor of Safety is 2.0
Df – Disturbance Factor for bored piles adopted in both analysis is 0.6.
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 11
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
5.1 CONCLUSION
Despite an objective soil investigation and reporting, a poorly designed and/or constructed
foundation may lead to structural failure if all other environmental conditions remain constant.
EARTH GEO ENGINEERING NIGERIA LIMITED advised that the design and construction of all
foundation and earthwork be carried out by a competent company in accordance with good and
strict engineering practice expected of a professional. The construction contractor shall be guided
by reference Code of Practices such as; British Institution CP 2004, 1973: Code of Practice for
Foundation and BS 6031: Code of Practice for Earth Works and our relevant National Standards;
General Specification for Road and Bridges (F.M.H. Abuja) on Material and Geotech latest edition.
Kind regards,
27/03/2020.
Abayomi Akinwalere
Engineering Geologist (B.Sc, M.Sc, MNMGS, COMEG).
ISO/IEC 17025 Certified.
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 12
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
REFERENCES
• British Standards Institution, ‘BS EN 1997-2-2007, Geotechnics Designs (Ground Investigation and Testing, section
5. British Standards Institution, ‘British Standards Methods of Test for Soil for Civil Engineering Purposes’, BS1377.
London, 1990.
• S. K. Garg ‘Soil Mechanics and Foundation Engineering’ 2nd Edition, Seventh Revised Edition, Khanna Publishers,
2009.
• Research Journal of Environmental and Earth Sciences 3(5): 571 – 577, 2011, Maxwell Scientific Organization, 2011.
• S. N. Smith and Ian G. N Smith ‘Elements of Soil Mechanics’, 7th Edition. Blackwell Science, USA. 1998.
• International Standards Organisation, ‘Geotechnical Investigation and Testing – Identification and Classification of
Soil – Rent 1: Identification and Description’, ISO14688-1. 2002.
• Federal Ministry of Works and Housing, ‘General Specification for Roads and Bridges’. 1997
Revised Edition.
• Department of Transport “Specification for Roads and Bridge Works.
• Skempton, A. W., ‘The Colloidal Activity of Clays,’ proceedings, 3rd International Conference on Soil Mechanics and
Foundation Engineering, London, Vol. 1, pp 57-61, 1953
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 13
PRE – RECOMMENDATION GEOTECHNICAL INVESTIGATION REPORT
COMPILED BY: EARTH GEO ENGINEERING NIG LTD – TEL: +234803-421-4560 Page 14