Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Thaiba, Lalipur
Bill Of Quantities
Item.
Description Rate
No
Main building
Providing and construction of temporarily necessary site office for the construction team and consultant
with facilities (telephone, email with a computer and laser printer, stationeries, toilets etc.) and similarly
1
temporarily sheds for store, labour quater etc. all necessary electricity, sanitary and water supply system ,
all complete as per requirement.
Earth Work in excavation in foundation, site leveling etc. in ordinary soil including clearance of
2 vegetation, shrubs, hedges, stacking of excavated materials beyond 3.00 mtr. clear from the edge of
excavation as per drawing, specifications and instructions.
Earth back filling work in trenches, foundation, inside building area with water sprinkle at every 150mm
3 layer with necessary compaction as per drawing, specification and instruction of the Consultant, all 20.00
complete.
Providing and laying, dry brick soling in foundation trench and floor with chimney made bricks complete
4 to level including sand filling on joints, as per drawing, specification and instruction of the engineer, all 99.00
complete.
Providing and laying 500 Micron Plastic Sheet as damp proofing member with required lap as per drawing
5 8.00
and instruction.
Providing and laying machine mixed plain cement concrete (P.C.C) in nominal mix in volumetric
6.1.1 proportion of 1:3:6 (1 Cement:3 Sand : 6 Course graded aggregate 20mm down) including the necessary 334.00
compaction, leveling, curing etc., all complete as per drawings, specifications and instructions.
Providing and laying machine mixed plain cement concrete (P.C.C) in nominal mix in volumetric
6.1.2 proportion of 1:2:4 (1 Cement:2 Sand : 4 Course graded aggregate 20mm down) including the necessary 387.00
compaction, leveling, curing etc., all complete as per drawings, specifications and instructions.
Providing and laying, plain cement concrete for R.C.C. columns, beams, slabs, isolated foundation, lintel
sills and all kinds of R.C.C. works with cement, sand and aggregate including mixing, laying, curing
6.2
finishing etc. excluding reinforcement, centering and shuttering as per drawings, specification and
instruction of the Engineer, all complete.
Providing, fabricating, erecting, centering and shuttering of plywood formwork in foundation, columns
7 slabs, lintel, sills etc. in line and level including bracing, propping, de-shuttering at all levels and heights 75.00
all complete as per drawings, specifications and instructions.
Providing and fixing TMT Fe500 Steel Reinforcement in R.C.C work including straightening, cutting,
bending, binding with 20gauge annealed wire for tying the reinforcement of all sizes of bars at each
junctions including all waste and cut pieces, provision for adequate numbers of spacers, chairs, providing
8 123.00
and placing cement mortar(1:1) cover blocks to keep the bars in intended position at all levels all complete
as per drawing, specifications and instructions. Lap length shall be measured separately for the bar length
exceeding 10m in length.
Providing and laying, Brickwork in foundation & superstructure with approved quality first class brick in
perfect line and level, finished including wetting the bricks, packing the joints and curing the work
9
complete in all types and thickness of walls, columns, etc. as per drawings, specification and instruction of
Engineer, all complete.
230mm tk. chimney made brickwork in 1:6 Cement Sand Mortar including joint racking with approved
9.1 432.00
tools, all complete in foundation
230mm tk. chimney made fair face brickwork in 1:5 Cement Sand Mortar including joint racking with
9.2 483.00
approved tools, all complete
110 mm tk. chimney made fair face brickwork in 1:4 Cement Sand Mortar including joint racking with
9.3 242.00
approved tools, all complete
9.4 4" thick local chimney made brick masonry work in 1:4 cement mortar. 191.00
230mm tk. chimney made brickwork in 1:5 Cement Sand Mortar including joint racking with approved
9.5 445.00
tools, all complete in superstructure
Providing and laying, cement sand plastering on walls, etc.of good finish, accurate line, level and plumb
10 including raking the joints, cleaning and wetting the surface and curing the works and necessary
scaffolding etc. all complete, as per drawing, specification and instruction of Engineer, all complete.
Providing and laying 50mm thick IPS (1:2:4) with cement, sand, stone chips including mixing, laying,
11 finishing to approved line, level and dimension, curing all complete as per drawing, specification and 98.00
instruction of the Engineer, all complete.
Proving and laying tile on floor, wall/skirting (1:4) and floor (1:6) of approved brand & color with perfect
12 line, level, plumb and finishing the joint of tile by chemical grout as per drawing, specification and
instruction of the Engineer, all complete.
Providing and laying Marble in 20mm thick Cement Sand mortar (1:6) in proper slope for draining wash
water, joint not exceeding 3 mm. and pointed with White Cement slurry, grinding, polishing to smooth
13
glazed surface and waxed finish in floor, of the approved color and quality, as per drawing, specification
and instruction of the engineer, all complete.
13.1 452.00
Marble flooring on floor/staircase landing with polishing
13.2 773.00
Marble flooring on tread with polishing
13.3 351.00
Marble flooring on Riser with polishing
13.4 214.00
Marble skirting with polishing
14.1 233.00
Mosaic tile flooring with polishing
14.2 179.00
Mosaic tile skirting with polishing
Providing and laying 12'' wide marble sill on window sill at 1:3 cement sand mortar including one line
15.1 490.00
grooving and polishing as per drawing, specification and instruction of the engineer all complete
Providing and laying 9'' wide marble coping at 1:3 cement sand mortar including polishing as per drawing,
15.2 460.00
specification and instruction of the engineer all complete
Supplying and laying 6'' x 4'' clay tile parapet over exterior concrete surface with 1:6 cement sand mortar
16 244.00
with approved brand and color clay tile
Supplying and fitting 1.2 mm th. approved coloured anodized Aluminium Door/windows including
17 frame with shutters, 5mm thick float glass, window locks and necessary accessories as per drawings,
specification and instruction of the engineer, all complete.
Supplying and fixing 12 mm th. Waterproof type gypsum false ceiling with necessary accessories as per
18 124.00
drawings, specification and instruction of the engineer, all complete.
Providing and applying approved brand water proofing on new concrete structures, Walls, Sunken Slabs,
19 Toilets applied by the process of crystallization as specified by the Site Engineer/Consultant or as 66.00
manufactures specification all complete
Providing and applying POP of approved brand over cement plaster surface or concrete surface in perfect
20 line and level in wall and ceiling as per drawings, specification and instruction of the Engineer, all
complete.
Supplying and fitting salwood door frame with shutters, locks and necessary accessories as per drawings,
21
specification and instruction of the engineer, all complete.
21.1 Sal Wood Door frame as per drawing all complete 9,589.00
21.2 Solid core door shutter (normal type) including locks, accessories all complete 642.00
22.2 Solid core door shutter (waterproof type) including locks, accessories all complete 798.00
22.3 Wooden panel door shutter for main gate including locks, accessories all complete 1,376.00
22.4 Wooden staircase handrail as per drawings and instruction of engineer all complete. 947.60
Providing and applying, inside and outside painting work on wall and ceiling of approved color including
24 necessary primer (as per product manual) to give uniform color after rendering surface clean and moist
(where necessary) as per specifications, drawings, and instruction of the engineer, all complete.
Supplying and fixing toughen glass decorative railing , handrail including steel post etc. as per drawing,
25 1,725.00
specification and instruction of the engineer, all complete.
26 Metal work
Supplying and fixing MS staircase railing including red-oxide paint etc. as per drawing, specification and
26.1 1,599.00
instruction of the engineer, all complete.
Supplying and fixing MS verandah parapet railing including red-oxide paint etc. as per drawing,
26.2 533.00
specification and instruction of the engineer, all complete.
Supplying and fixing MS straight type staircase with railing including red-oxide paint etc. as per drawing,
26.3 40,000.00
specification and instruction of the engineer, all complete.
10/2/2018
Unit Quantity Amount Remark
12.97 124,382.75
cft
82.49 52,958.84
sft
43.99 35,105.94
sft
28.59 39,341.49
sft
34.45 32,644.82
rft
1.00 7,274.00
no
sft 157.53 12,759.58
6,725,298.52
General Notes :
1 Tools & plants is (of Labor) 0.03 0.03
2 Over head and profit 0.15 0.15
1 Cement (Structure) -Shivam/Argakhachi or equivalent bag 703.54 bag 703.54 141.00 32.00
2 Cement ( Non Structure) -Briz Cement bag 615.04 bag 615.04 141.00 32.00
3 White cement bag 1,350.00 m 1,350.00 50.00 10.00
4 Sand - Washed, Belkhu cft 110.00 m3 3,885.20 423.77
5 Sand ( for Plaster Works) cft 118.80 m3 4,196.02 423.77
6 Filling sand cft 65.00 m3 2,295.80 423.77
7 Aggregate cft 100.00 m3 3,532.00 423.77
8 Chips cft 90.00 m3 3,178.80 423.77
9 Local Brick nos 16.00 nos 16.00
10 Rebar TMT - Jagadamba or equivalnet kg 85.65 MT 85,650.00 1,500.00 450.00
11 Binding Wire kg 100.00 kg 100.00
12 500 gauge Polythene sheet kg 210.00 kg 210.00
13 12mm marine Plywood sft 90.00 m2 968.40
14 Timba (Sallo) cft 960.00 m3 33,907.20
15 G.I Wire (14g) kg 110.00 kg 110.00
16 Nail kg 98.00 kg 98.00
17 Concrete nail kg 225.00 kg 225.00
18 Burnt Mobil ltr 70.00 ltr 70.00
19 Diesel ltr 95.00 ltr 95.00
20 Ceramic tile : Floor (Base rate =120/sft) sft 120.00 m2 1,291.20 21.52
21 Ceramic tile : Wall (Base rate = 125/sft) sft 125.00 m2 1,345.00 21.52
22 Mosaic tile (Bars rate = 58.06/sft) sft 58.06 m2 624.73 75.32
23 Clay Tile no 20.40 no 20.40
23 KatanyMarble Base rate = 200/sft) sft 200.00 m2 2,152.00
24 Metal pipe, angle kg 90.00 kg 90.00
25 Granite (Base rate = 350/sft) sft 350.00 m2 3,766.00 75.32
26 Sal Wood cft 6,000.00 m3 211,920.00 1,766.00
27 19 mm x 6 mm, 375 mm long flat iron hold fast kg 100.00 kg 100.00
28 Solid Core Door Shutter- Normal sft 200.00 m2 2,152.00
29 Solid Core Door Shutter- Waterproof sft 210.00 m3 2,259.60
30 Sallo wood cft 5,000.00 m3 176,600.00
31 4" Hinge (Brass) no 290.00 no 290.00
32 6" Hinge (Brass) no 310.00 no 310.00
33 7 Lever Lock no 860.01 no 860.01
34 Tower Bolt 8" (Brass) no 350.00 no 350.00
35 Tower Bolt 12" (Brass) no 670.00 no 670.00
36 Tower Bolt 10" (Brass) no 410.00 no 410.00
37 Door Stopper (Rubber) no 30.00 no 30.00
38 Door Closer no 1,500.00 no 1,500.00
38 6" Handle (Brass) no 340.00 no 340.00
39 MS Sq Rod kg 90.00 kg 90.00
2 Plaster Works
2.1 Internal Plaster 22.50 sft 242.10 m2
2.2 External Plaster 28.50 sft 306.66 m2
2.3 Rain drip 29.90 rft 98.10 rm
2.4 Band Plaster 29.90 rft 98.10 rm
4 Tile
4.1 Floor tile 42.00 sfr 451.92 m2
4.2 Wall tile 39.60 sfr 426.10 m2
4.2 Clay tile 30.00 sfr 322.80 m2
4.3 Skirting 39.60 rft 129.93 rm
4.4 Telia tile flooring 40.25 sft 433.09 m2
4.5 Telia tile skirting 32.20 rft 105.62 rm
5 Wall putty work
5.1 Concrete surface 20.70 sft 222.73 m2 With material
5.2 Plaster surface 18.40 sft 197.98 m2 With material
6 POP work
6.1 Concrete surface 16.80 sft 180.77 m2 With material
6.2 Plaster surface 14.40 sft 154.94 m2 With material
7 Aluminum window
7.1 Aluminum window 600.00 sft 6,456.00 m2 With material
7.2 Aluminum doors 650.00 sft 6,994.00 m2 With material
8 Paint work
8.1 Inside emulsion paint 16.80 sft 180.77 m2 With material
8.2 Outside weather coat paint 21.60 sft 232.42 m2 With material
8.3 Enamel paint on wooden surface 18.00 sft 193.68 m2 With material
8.4 Chapra polishing work 60.00 sft 645.60 m2 With material
8.5 Enamel paint on metal surface work 18.00 sft 193.68 m2 With material
9 Marble work
9.1 Marble flooring work 48.00 sft 516.48 m2
9.2 Marble polishing work 23.00 sft 247.48 m2
9.3 Marble skirting 46.00 rft 150.93 rm
9.4 Marble flooring at tread 48.00 sft 516.48 m2
9.5 Marble flooring at riser 46.00 rft 150.93 rm
9.6 Half molding with polishing 48.00 rft 157.49 rm
9.7 Double molding with polishing 103.50 rft 339.58 rm
9.8 Marble on sill with polishing 74.75 rft 245.25 rm
9.9 Grooving 28.75 rft 94.33 rm
10 False ceiling work
9.1 12 mm th. Gypsum false ceiling (waterproofing) 97.75 sft 1,051.79 m2 With material
11 Waterproof work : MC Special DM Coating 57.50 sft 618.70 m2 With material
12 Wood work
12.1 Door / Window frame (fabrication & fitting only) 300.00 cft 10,596.00 m3
12.2 Door frame fitting 375.00 nos 375.00 nos
12.3 Labor charge for door shutter fitting 230.00 nos 230.00 nos
12.4 Lock fitting & other fitting( door stopper, hinge, tower bolt) 460.00 nos 460.00 nos
12.5 Labor & material Charge for extra 6 pc sallo wood 345.00 nos 345.00 nos
12.6 Shisum hand rail 800.00 rft 2,624.80 rm With material
12.7 Newel Post 6,325.00 nos. 6,325.00 nos With material
13 Steel railing work 306.69 sft 3,300.00 m2 With material
14 Metal work
15.1 Main staircase railing 57.50 kg 57.50 kg
15 Glass railing 1,500.00 sft 16,140.00 m2 With material
RATE ANALYSIS
EARTHWORK
1 Earth work in Excavation and disposal surplus earth within site premises
Analysis for 1m3
S.No. Description Quantity Unit Rate Amount
1 Labor Cost
Excavation and Disposal 1.00 m3 649.89 649.89
Dewatering/Trimming 1.00 m3 50.00 50.00
2 Labor
Labor charge 1.00 m2 61.87 61.87
2 Labor
Labor charge 1.00 m2 12.37 12.37
5 CONCRETE WORKS
5.1 PCC M10 (1:3:6)
Analysis For 1m3
S. No. Description Quantity Unit Rate Amount
1 Materials
Cement (PPC) 4.40 bags 788.04 3,467.39
Sand 0.47 m3 4,308.97 2,025.21
Aggregate 0.89 m3 3,955.77 3,520.63
2 Labor
Labor charge 1.00 m3 1,218.54 1,218.54
2 Labor
Labor charge 1.00 m3 1,218.54 1,218.54
7 Normal Formwork
Analysis for 1 m2
S.No. Description Quantity Unit Rate Amount
1 Material
12 mm marine plywood 0.167 m2 968.40 161.40
Timba 0.004 m3 33,907.20 135.63
Nails 0.250 kgs 98.00 24.50
Concrete nail 0.004 kgs 225.00 0.90
GI wire 0.070 kgs 110.00 7.70
Diesel 0.010 ltr 95.00 0.95
Burnt Mobil 0.030 ltr 70.00 2.10 571.07
Scaffolding Materials 1.000 m2 64.56 64.56
2 Labor
Labor charge 1.00 m2 296.98 296.98
8 Reinforcement ( TMT)
Analysis for 1MT
S.No. Description Quantity Unit Rate Amount
1 Materials
Rebar 1.06 MT 87,600.00 92,856.00
Binding wire 15.00 kg 100.00 1,500.00 65.24
2 Labor
Labor charge 1.00 MT 12,650.00 12,650.00
2 Labor -
Labor charge 1.00 m2 309.35 309.35
24 Marble Skirting
Analysis For 1 m
S. No. Description Quantity Unit Rate Amount
1 Materials
Marble 0.11 m2 2,152.00 236.72
Cement (PPC) 0.02 bags 788.04 17.97
Sand 0.002 m3 4,619.78 10.16
Miscellaneous 0.15 m2 193.68 29.05
-
2 Labor -
Labor charge for skirting 1.00 rm 150.93 150.93
Molding and local polishing with necessary materials 1.00 rm 157.49 157.49
30 Aluminum Windows
Analysis for 1 m2
S.No. Description Quantity Unit Rate Amount
1 Material
Subcontractor 1.00 m2 6,456.00 6,456.00
31 Aluminum Door
Analysis for 1 m2
S.No. Description Quantity Unit Rate Amount
1 Material
Subcontractor 1.00 m2 6,994.00 6,994.00
a Total of Material/Labor /Tools & Plant 6,994.00
b Over head & Profit @ 15% of (a) 1,049.10
c Total (a+b) 8,043.10
Item Rate per 1m2 8,043.00
Item Rate per 1sft 747.00
33 Waterproofing work
Analysis for 1 m2
S.No. Description Quantity Unit Rate Amount
1 Material
Subcontractor : MC Special DM Coating 1.00 m2 618.70 618.70
Tools
3 & Plant @ 3% of Labor 27.14
Tools
3 & Plant @ 3% of Labor 31.05
38 Solid core door Shutter (Toilets, pooja and store) for 2'6''x7'0''
Analysis for 1.371 m2
S.N Description Unit Quantity Rate Amount
1 Material
Solid core door shutter m2 1.371 2,259.60 3,097.91
Sal wood m3 0.005 213,686.00 1,086.73 560.52
Tower Bolt 8" no 1.000 350.00 350.00 408.84
Mortice Lock set 1.000 2,000.00 2,000.00
4" Hinges (Brass) no 3.000 290.00 870.00
Magnetic door Stopper no 1.000 90.00 90.00
Door closer no 1.000 1,500.00 1,500.00
Fevicol 300gm kg 0.300 250.00 75.00
Head Lace, Nails etc. L.S 1.000 100.00 100.00
-
2 Labor
Labor charge for fitting door no 1.00 230.00 230.00
Lock fitting & other fitting( door stopper, hinge, tower bolt) no 1.00 460.00 460.00
Labor & material Charge for extra 6 pc sallo wood no 1.00 345.00 345.00
Tools
3 & Plant @ 3% of Labor 31.05
39 Wooden Panel Door Analysis For 1 No (2.246 Sqm) (Frame Size: 4'-0" X 7'-0", Shutter Size 3'-7"X6'-9")
Analysis for 2.246 sqm
S.N Description Unit Quantity Rate Amount
1 Material
Sal Wood cum 0.104 213,686.00 22,184.14 1,583.24
6" Hinge (Brass) nos 6.000 310.00 1,860.00 704.91
7 Lever Lock nos 1.000 860.01 860.01
Tower Bolt 12" (Brass) nos 2.000 670.00 1,340.00
Tower Bolt 10" (Brass) nos 2.000 410.00 820.00
Door Stopper (Rubber) nos 2.000 30.00 60.00
6" Handle (Brass) nos 2.000 340.00 680.00
Miscellaneous (Mobical, Nail etc.) LS 1.000 100.00 100.00
2 Labor
Labor Charge For Fabrication sqm 2.250 230.00 517.50
Labor Charge For Fitting nos 1.000 460.00 460.00
Tools
3 & Plant @ 3% of Labor 29.33
Tools
2 & Plant @ 3% of Labor 78.74
41 Newel post
Analysis for 1no
S.N Description Unit Quantity Rate Amount
1 Labour
Sub-Contractor Rate rm 1.00 6,325.00 6,325.00
42 Surkhi Pointing
Analysis For 1 Sft
S. No. Description Quantity Unit Rate Amount
1 Materials + Labour
Sub contractor Rate 1.00 Sft 70.00 70.00
Surface
preparation
180.77
Thaiba Heights (Type B)
Thaiba, Lalipur
Cost Summary
S.No. Description of work Unit Quantity Rate Amount
Main building
II Concrete Works
V Masonry works
1 9" thick Local Brickwork in (1:6 ) c/m at foundation Cft 476.36 432.00 205,788.51
2 9'' th. Fairface brickwork (1:5) c/m Cft 27.93 483.00 13,490.19
3 4.5'' th. Fairface brickwork (1:4) c/m Sft 120.29 242.00 29,109.12
4 4.5" thick Local Brickwork in (1:4) c/m Sft 1,030.88 191.00 196,898.65
5 9" thick Local Brickwork in (1:5) c/m at superstructure Cft 1,127.50 445.00 501,739.42
VI Plaster works
2 12.5 mm th. Internal concete surface plaster (1:4) Sft 59.04 46.00 2,715.75
4 Jamb & Sill Plaster (9" Avg. width) Rft 375.65 52.00 19,533.80
IX Marble Works
XII Clay (Prajapat) tile works as per drawing, site instruction all complete;
1 Sal Door frame as per drawing all complete Cft 12.97 9,589.00 124,382.75
3 Solid core door shutter water proof ply Sft 43.99 798.00 35,105.94
D Total 7,935,852.25
Add vat 13% extra
E 1,031,660.79
Grand Total
F 8,967,513.04
0.00
221,518.03
1,379,659.15
442,488.21
1,086,236.73
947,025.90
400,642.33
Remarks
80,262.00
290,675.25
276,981.71
195,187.25
107,375.00
54,709.68
322,061.33
13,640.00
88,852.50
Remarks
107,772.64
291,707.84
12,759.58
230,106.22
75,667.13
99,970.05
6,725,298.52
Thaiba Heights (Type B)
Thaiba, Lalipur
i Footing: 3,827.74
Isolated footings
Strap footing: -
At X direction : -
At Y direction :
a Footing: 2,679.41
At X direction : -
At Y direction :
b Floors: 579.02
a Footing: 522.92
Isolated footings
Strap footing: -
At X direction : -
At Y direction :
c Floors : 579.02
2 15.58 Slope
2 15.58 Flat
2 16.33 Slope
2 16.33 Flat
2 16.33 Slope
2 16.33 Flat
5.14
4.32
2.89
10.78
4.53
12.50
17.35
8.17
9.47
a Footing: 130.73
Isolated footings
Strap footing:
At X direction : -
At Y direction :
Floors: 144.76
6 RCC work
a Foundation
At X direction : -
At Y direction :
At X direction :
At Y direction :
At X direction :
At Y direction :
(deduction) : Column
At 9'' th.
At X direction
At Y direction :
4.5'' th.
At X direction
At Y direction
At X direction :
At Y direction :
(deduction) : Column
9'' th.
At X direction
At Y direction :
4.5'' th.
At X direction :
At Y direction
At X direction :
At Y direction :
(deduction) : Column
iii
RCC band : 2 layer 50.06
9'' th.
At X direction :
At Y direction :
4.5'' th.
At X direction :
At Y direction
i Column
i Column
i Column
For PCC(1:3:6)
a Footing: 61.25
Isolated footings
Strap footing:
At X direction : -
At Y direction :
a Foundation
At X direction : -
At Y direction :
At X direction :
At Y direction :
At X direction :
At Y direction :
(deduction) : Column
At 9'' th.
At X direction
At Y direction :
4.5'' th.
At X direction
At Y direction
At X direction :
At Y direction :
(deduction) : Column
9'' th.
At X direction
At Y direction :
4.5'' th.
At X direction :
At Y direction
At X direction :
At Y direction :
(deduction) : Column
iii
RCC band : 2 layer 205.48
9'' th.
At X direction :
At Y direction :
4.5'' th.
At X direction :
At Y direction
i Column
i Column
b Column : 2126.20
e Slab 2148.71
f Staircase 378.61
Ground floor 69.81
Volumn=
kg
1.50%
3%
2%
1.30%
1.30%
2221.75
1.00%
1%
Thaiba Heights (Type A)
Thaiba, Lalipur
9 Brickwork:
At X direction :
At Y direction :
AT X direction :
At Y direction :
ii
First floor 13.97
At Y direction :
i
Second floor 120.29
At Y direction :
At X direction :
At Y direction
At X direction
At Y direction
ii
First floor 351.52
At X direction :
At Y direction
At X direction :
At Y direction
i
Groiund floor 416.98
At X direction
At Y direction :
(deduction) : D1
ii
First floor 475.07
At X direction
At Y direction :
(deduction) : D1
iii
Second floor 235.45
At X direction :
At Y direction :
476.36 cft
27.93 cft
120.29 sft
1,030.88 sft
1,127.50 cft
10 Plaster Work
W2 -
(deduction) : DW1
Staircase area
1 44.08 8.91 392.75
10.2 12.5 mm th. Internal concete surface plaster (1:4) 59.04 sft
a
Ground floor 1,159.53
12 Tile Work
Ceramic Tiles
12.3 87.75
Tile skirting - rft
a
Ground floor - 60.25
b
First floor 27.50
W2 1 6.00 7.00
W4 1 4.00 5.00
W7 2 2.00 4.00
W2 1 6.00 7.00
W1 1 7.00 8.00
W6 1 2.00 3.00
ii
First floor - 33.00
W2 1 6.00 7.00
W4 1 4.00 5.00
W3 1 5.00 6.00
W6 2 2.00 4.00
W1 1 7.00 8.00
iii
Second floor - 14.00
16
9'' wide Marble coping work with grooving
a
First floor 15.50
a
Second floor 125.25
87.00 rft
140.75
rft
Thaiba Heights (Type A)
Thaiba, Lalipur
Lower terrace :
Upper terrace :
sft
83.19467554
48080
249.5840266
150250
Thaiba Heights (Type A)
Thaiba, Lalipur
18 Aluminium works
ii
First floor 146.00
iii
Second floor 42.69
Sub-
S. Total
Description Nos Length Breadth Height Quantity Total
No. Quantity
Quantity
c Second Floor
S.No Description of works Nos L (mtr.) B (mtr.) Quantity Unit unit wt. Total Wt. (kg)
3 Metal railing works at terrace areas 89.87
Lower terrace:
Horizontal pipe (1.5''dia) 1 3.35 3.35 rm 3.61 12.10
Horizontal pipe (1/2''dia) 1 3.35 3.35 rm 1.22 4.09
Vertical pipe (1.5''dia) 4 0.34 1.37 rm 3.61 4.95
Big balcony
Horizontal pipe (1.5''dia) 1 3.99 3.99 rm 3.61 14.39
Horizontal pipe (1/2''dia) 3 3.99 11.96 rm 1.22 14.59
Vertical pipe (1.5''dia) 7 0.34 2.40 rm 3.61 8.66
Small balcony: 1.25''dia.
Horizontal pipe: (1.25'' dia.) 1 2.31 2.31 rm 3.15 7.28
Horizontal pipe: (9'' dia.) 1 2.31 2.31 rm 1.58 3.65
vertical pipe (9''dia) 5 0.38 1.90 rm 1.58 3.01
Upper terrace:
Horizontal pipe (1.5''dia) 1 1.88 1.88 rm 3.61 6.78
Horizontal pipe (1/2''dia) 2 1.88 3.75 rm 1.22 4.58
Vertical pipe (1.5''dia) 3 0.53 1.60 rm 3.61 5.78
Unit Remark
sft
Remarks #REF!
Kg
131.81 rft
Kg
188.15 rft
36.44 sft
kg/m2
Kg
135.19 rft
13.3
50000
30000
21200 16000
24000
10000
20000
6300 18900 5000
3100
583.333333 96000
2777.77778
3361.11111
2173.33333
1833.33333
Thaiba Heights (Type A)
Thaiba, Lalipur
21 POP Work
22 Wood Work
c Second floor
cft
sft
sft
sft
rft
no
ii
First floor 18.62
iii
Second floor 120.29
-
8/3/2018
Remark
Thaiba Heights (Type A)
Thaiba, Lalipur
24.1
Emulsion Paint work 5780.93 sft
i
Wall puty surface area (Concrete surface) 2227.01
ii
Wall putty on plaster surface 3443.92
Sub-
S. Total
Description Nos Length Breadth Height Quantity Total
No. Quantity
Quantity
Upper terrace:
Horizontal pipe (1.5''dia) 1 1.88 1.88 rm 3.61 6.78
Horizontal pipe (1/2''dia) 2 1.88 3.75 rm 1.22 4.58
Vertical pipe (1.5''dia) 3 0.53 1.60 rm 3.61 5.78
Unit Remark
sft
Remarks #REF!
Kg
131.81 rft
Kg
188.15 rft
36.44 sft
kg/m2
Kg
135.19 rft
13.3
50000
30000
21200 16000
24000
10000
20000
6300 18900 5000
3100
583.333333 96000
2777.77778
3361.11111
2173.33333
1833.33333
Thaiba Heights (Type A)
Thaiba, Lalipur
Sub-
S. Total
Description Nos Length Breadth Height Quantity Total Unit
No. Quantity
Quantity
26 Metal work
1 13.48 13.48
1 17.64 17.64
a Second floor