DAILY SITE PROGRESS REPORT

DF SILVERLINE CONSTRUCTIONS logo

PROJECT: Hennur site


CLIENT : DF Silverline
Weather Conditions: CLOUDY Date: 7-Sep-19
Temperature: Avg 24°C Day: SATURDAY
Humidity: 50% WIND WSN 25Kph
Site Team
Project Engineer 1 Stie Supervisor 0
Site Engineer 0 Store Keeper 0
Purchase Incharge 0 Time keeper 0 Total 1
Site Qs 0 Electrician 0
Safety Officer 0 Security 0
I Contractor - NMR Lbr
Block work @ store area, soil filling.
a) Planned:

Block work @ store area is in progress, Approx 100 blocks completed, All 4 sides upto roof lvl completed,
soil filling @ store area is in progress.
b) Achieved:

MAN
SuperPOWER
Visitor 1+1+1
1 Mason 0 lab ours 2
VII Water / Power Supply STATUS
a) EB power Running
b) Water
VIII ANY VISITOR Nil
IX ANY SITE INSTRUCTIONS Nil
X ANY BILLS RECEIVED AT SITE: Nil
XI Any Stoppage At Work With Reason. Nil

Page 1 of 2
PROGRESS PHOTOS

Image size 2.5" x 2.5" Image size 2.5" x 2.5"

Block work is in progress @ store area. Block work is in progress @ store area.

Image size 2.5" x 2.5" Image size 2.5" x 2.5"

Block work is in progress @ store area. Block work is in progress @ store area.

Soil filling @ store area is in progress. Soil filling @ store area is in progress.

Page 2 of 2