ANALISIS HIDRAULICO

TIPO DE CAMINO D
PERIODO DE RETORN 25 AÑOS
Coeficiente de Manni 0.015

CALCULO DE LA PENDIENTE GEOMETRICA MEDIA

PUNTO CADENAMIENTO LONGITUD ELEVACION


1 0.42 ------ 194.237
2 5.42 5 196.777
3 10.42 5 200.166
4 15.42 5 203.972
5 19.74 4.32 207.326
SUMAS
PENDIENTE MEDIA 0.6825

CALCULO DE LAS CARACTERISTICAS GEOMETRICAS DE UNA SECCION HIDR

SECCION HIDRAULICA N° 1

ELEVACION DEL
TRAMO CADENAMIENTO LONGITUD
TERRENO

0.42 ------ 194.237


5.42 5 196.777
1 10.42 5 200.166
15.42 5 203.972
19.74 4.32 207.326

CALCULO DE LA VELOCIDAD Y EL GASTO DEL FLUJO EN UNA SECCION HIDR

〖𝑅𝐴𝐷𝐼𝑂〗 ^
TRAMO AREA (M²) RADIO (M) (2/3)

1 31.58 1.35

GASTO MAXIMO OBSERVADO EN CAMPO QMOC


ANALISIS HIDROLOGICO

Calculo del gasto teorico de diseño QTDI=

CALCULO DE REGISTRO DE INTENSIDADES DE LLUVIA OBTENIDAS DE ISOYETAS P


DIFERENTES ISOYETAS PARA DIFERENTES DURACIONES DE TORMENTA Y PERIOD
RETORNO

PERIODO DE RETORNO Tr, (años)


DURACION t (min)
10 20
INTENSIDAD DE LLUVIA I, (mm/hr)
5 2.5 300
10 177 210
20 152 181
30 124 149
60 77 91
400
120 51 61
240 32 39
350

300
Intensidad de lluvia I, (mm/hr)

250

200

150

100

50

0
1 10 100

Duracion t, (min)

𝑳^(𝟎.𝟕𝟕)/𝑺^(𝟎.𝟑𝟖𝟓)

Calculo del Tiempo de Concentracion=


tc= 0.0662

tc= 0.0045 hr
tc= 0.272 min

AREA DE LA CUENCA = 0.37 Km² 0.04


PERIMETRO DE LA CUENCA = 0.078 Km
Elevacion Inicial = 207.326 m
Elevacion Final= 194.237 m
Longitud del Cauce Principal= 0.02 Km
Pendiente del Cauce=
(𝒌 〖𝑻𝒓〗 ^𝝁)/𝒕^ϒ 0.56

Calculo de la Intensidad de lluvia por el Método de Correlación Lineal


Multiple=

I=

Periodo de Retorno para 10 años


N° X Y Ln X
1 5 2.5 1.6094
2 10 177 2.3026
3 20 152 2.9957
4 30 124 3.4012
5 60 77 4.0943
6 120 51 4.7875
7 240 32 5.4806
SUMA 485.0000 615.5000 24.6714
Ln (d )= 3.045 d= 21.0001

27.6780 7 24.6714
100.4412 24.6714 98.1559
X= 3.045
Y= 0.258

Periodo de Retorno para 20 años


N° X Y Ln X
1 5 300 1.6094
2 10 210 2.3026
3 20 181 2.9957
4 30 149 3.4012
5 60 91 4.0943
6 120 61 4.7875
7 240 39 5.4806
SUMA 485.0000 1031.0000 24.6714
Ln (d )= 6.646 d= 769.3198

33.5386 7 24.6714
112.3132 24.6714 98.1559
X= 6.646
Y= -0.526

Periodo de Retorno para 25 años


N° X Y Ln X
1 5 316 1.6094
2 10 221 2.3026
3 20 191 2.9957
4 30 157 3.4012
5 60 96 4.0943
6 120 65 4.7875
7 240 41 5.4806
SUMA 485.0000 1087.0000 24.6714
Ln (d )= 6.696 d= 808.7888

33.9147 7 24.6714
113.6505 24.6714 98.1559
X= 6.696
Y= -0.525

Periodo de Retorno para 50 años


N° X Y Ln X
1 5 366 1.6094
2 10 2.53 2.3026
3 20 219 2.9957
4 30 180 3.4012
5 60 110 4.0943
6 120 75 4.7875
7 240 47 5.4806
SUMA 485.0000 999.5300 24.6714
Ln (d )= 4.409 d= 82.2003

30.2810 7 24.6714
106.4603 24.6714 98.1559
X= 4.409
Y= -0.024

RESUMEN
Término ctte. De Coeficiente de
Periodo de Retorno regresión (d) Regresión (n )
10 21.000 0.258
20 769.320 -0.526
25 808.789 -0.525
50 82.200 -0.024
Promedio 420.327 -0.204

Regresion Potencial
N° X Y Ln X
1 10 21.000 2.3026
2 20 769.320 2.9957
3 25 808.789 3.2189
4 50 82.200 3.9120
SUMA 105.0000 1681.3090 12.4292
Ln (d )= 2.601 d= 13.4714

20.7947 4 12.4292
(𝟑𝟗𝟎.𝟖𝟓𝟕𝟕 〖𝑻𝒓〗 ^(𝟎.𝟐𝟐𝟒))/𝒕^(𝟎.𝟓𝟐𝟕)
65.7193 12.4292 39.9414
X= 2.601
Y= 0.836

I=

Tabla de Intensidades - Tiempo de duración ( mm/hr)


Duracion en Minutos
Frecuencia en años 0.27 5 10
2 910.166 3585.362 4874.223
5 1117.530 3754.050 4924.680
10 1305.239 3886.910 4963.195
15 6000.000 1429.336 3966.798 4985.865
20 1524.476 4024.473 5002.013
25 5000.000 1602.613 4069.786 5014.573
30 1669.418 4107.188 5024.860
50 1871.799 4213.821 5053.792
INTENSIDAD ( mm/hr)

4000.000

3000.000

2000.000

1000.000

0.000
0 2 4 6 8 10 12 14
TIEMPO DE DURACION ( Minutos)

〖𝑲𝒎𝒎𝒎/𝒉𝒓
〗 ^𝟐
𝒎^𝟑/𝒔𝒆𝒈
QTDI= 0.278 Ce I A

Ce= 0.3 𝒎^𝟑/𝒔𝒆𝒈

A= 0.37
I= 1602.613

QTDI= 49.45

AÑOS AÑO GASTO


1 1989 252
2 1990 240
3 1991 73
4 1992 100
5 1993 183
6 1994 80
7 1995 90
8 1996 131
9 1997 92
10 1998 171
11 1999 43
12 2000 47
13 2001 68
14 2002 78
15 2003 69
16 2004 67
17 2005 135
18 2006 248
19 2007 45
20 2008 40

METODO GUMBEL

Media= 112.6
Desviacion Estandar= 70.0
Coeficiente de Variación= 0.62

Tr (Años) Parametro (Y) Gastos ( m³/ seg)


Probabilidades ( % )
0.01 10000 9.21 584
0.1 1000 6.91 458
0.5 200 5.30 370
1 100 4.60 332
3 33.33 3.49 272
4 25 3.20 256
10 10 2.25 204
20 5 1.50 163
25 4 1.25 149
30 3.33 1.03 137
40 2.5 0.67 118
50 2 0.37 101
60 1.67 0.09 86
70 1.43 -0.19 71
75 1.33 -0.33 63
80 1.25 -0.48 55
90 1.11 -0.83 36
95 1.05 -1.10 21
97 1.03 -1.25 13
99 1.01 -1.53 -2
99.9 1.00 -1.93 -24
DESNIVEL DISTANCIA PENDIENTE DISTANCIA.PENDIENTE
------ ------ ------ ------
2.54 5.61 0.5080 2.85
3.389 6.04 0.6778 4.09
3.806 6.28 0.7612 4.78
3.354 5.47 0.7764 4.25
23.40 15.97

EOMETRICAS DE UNA SECCION HIDRAULICA

AULICA N° 1 NIVEL DEL AGUA (NA) = 207.326 m

AREA AREA PERIMETRO PERIMETRO RADIO


DESNIVEL TIRANTE HIDRAULICA DEL MOJADO HIDRAULICO
HIDRAULICA MOJADO
TRAMO DEL TRAMO DEL TRAMO
------ 13.089 ------ ------
2.54 10.549 6.35 5.61
3.389 7.16 8.47 6.04
3.806 3.354 9.52 6.28
3.354 0 7.24 31.58 5.47 23.40 1.350

TO DEL FLUJO EN UNA SECCION HIDRAULICA

〖𝑅𝐴𝐷𝐼𝑂〗 ^
(2/3) n VELOCIDAD( GASTO ( M³/S)
M/S)
0.015 1.22 67.33 2126.42
SUMA 2126.42
BSERVADO EN CAMPO QMOC= 2126.42 m³/s
QTDI= 0.278 Ce I A

E LLUVIA OBTENIDAS DE ISOYETAS PARA


RACIONES DE TORMENTA Y PERIODOS DE

25 50
AD DE LLUVIA I, (mm/hr)
316 366
221 2.53
191 219
157 180
96 110
65 75
41 47

Tr=10 años
Tr= 20 años
Tr= 25 años
Tr= 50 años

100 1000

acion=
Hac.

23.44 m

elación Lineal

10 años
Ln Y Ln X . Ln Y ( Ln X )²
0.9163 1.4747 2.5903
5.1761 11.9185 5.3019
5.0239 15.0502 8.9744
4.8203 16.3947 11.5681
4.3438 17.7850 16.7637
3.9318 18.8236 22.9201
3.4657 18.9944 30.0374
27.6780 100.4412 98.1559
n= 0.258

1.25179961 -0.31463916
-0.31463916 0.08927226

20 años
Ln Y Ln X . Ln Y ( Ln X )²
5.7038 9.1799 2.5903
5.3471 12.3122 5.3019
5.1985 15.5733 8.9744
5.0039 17.0194 11.5681
4.5109 18.4690 16.7637
4.1109 19.6808 22.9201
3.6636 20.0787 30.0374
33.5386 112.3132 98.1559
n= -0.526

1.25179961 -0.31463916
-0.31463916 0.08927226
25 años
Ln Y Ln X . Ln Y ( Ln X )²
5.7557 9.2635 2.5903
5.3982 12.4297 5.3019
5.2523 15.7344 8.9744
5.0562 17.1973 11.5681
4.5643 18.6880 16.7637
4.1744 19.9848 22.9201
3.7136 20.3527 30.0374
33.9147 113.6505 98.1559
n= -0.525

1.25179961 -0.31463916
-0.31463916 0.08927226

50 años
Ln Y Ln X . Ln Y ( Ln X )²
5.9026 9.4999 2.5903
0.9282 2.1373 5.3019
5.3891 16.1442 8.9744
5.1930 17.6623 11.5681
4.7005 19.2454 16.7637
4.3175 20.6699 22.9201
3.8501 21.1013 30.0374
30.2810 106.4603 98.1559
n= -0.024

1.25179961 -0.31463916
-0.31463916 0.08927226

l
Ln Y Ln X . Ln Y ( Ln X )²
3.0445 7.0103 5.3019
6.6455 19.9082 8.9744
6.6955 21.5521 10.3612
4.4092 17.2487 15.3039
20.7947 65.7193 39.9414
n= 0.836

7.56441917 -2.35394382
-2.35394382 0.75755181

m/hr)
s
15
5221.326
5233.384
5242.525
5247.879
5251.682
5254.633
5257.045
5263.811

Curva IDF PARA Tr = 25 años

10 12 14 16
N ( Minutos)
Probabilida
d Empirica%
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
METODO GUMBEL
MAYOR A Probabilidad
AÑOS AÑO PRECIPITACION MEN0R Empirica %
1 1989 84 250 4.76
2 1990 85 183 9.52
3 1991 73 171 14.29
4 1992 100 135 19.05
5 1993 183 131 23.81
6 1994 80 126 28.57
7 1995 90 120 33.33
8 1996 131 100 38.10
9 1997 92 92 42.86
10 1998 171 90 47.62
11 1999 250 85 52.38
12 2000 126 84 57.14
13 2001 68 83 61.90
14 2002 78 80 66.67
15 2003 69 78 71.43
16 2004 67 73 76.19
17 2005 135 69 80.95
18 2006 62 68 85.71
19 2007 83 67 90.48
20 2008 120 62 95.24

Media = 107.35
Desviacion Estandar= 47.95
Coeficiente de Variación= 0.45

Probabilidades Tr (Años) Parametro Precipitacion


(%) (Y)
0.01 10000.0 9.21 430
0.1 1000.0 6.91 344
0.5 200.0 5.30 284
1 100.0 4.60 258
3 33.3 3.49 216
5 20.0 2.97 197
10 10.0 2.25 170
20 5.0 1.50 142
25 4.0 1.25 132
30 3.3 1.03 124
40 2.5 0.67 111
50 2.0 0.37 99
60 1.7 0.09 89
70 1.4 -0.19 79
75 1.3 -0.33 74
80 1.3 -0.48 68
90 1.1 -0.83 55
95 1.05 -1.10 45
97 1.03 -1.25 39
99 1.01 -1.53 29
99.9 1.00 -1.93 13

METODO LOG PEARSON TIPO III


AÑOS AÑO PRECIPITACION Orden Precipitacion
Jerarquico Años Ordenados Mayor a Menor
1 1989 84 12 1999 250
2 1990 85 11 1993 183
3 1991 73 16 1998 171
4 1992 100 8 2005 135
5 1993 183 2 1996 131
6 1994 80 14 2000 126
7 1995 90 10 2008 120
8 1996 131 5 1992 100
9 1997 92 9 1997 92
10 1998 171 3 1995 90
11 1999 250 1 1990 85
12 2000 126 6 1989 84
13 2001 68 18 2007 83
14 2002 78 15 1994 80
15 2003 69 17 2002 78
16 2004 67 19 1991 73
17 2005 135 4 2003 69
18 2006 62 20 2001 68
19 2007 83 13 2004 67
20 2008 120 7 2006 62

Precipitacion
Años Ordenados K
AÑO ORDEN Precipitacion Posicion Mayor a Menor
1989 1 84 12 250 1999 2.329
1990 2 85 11 183 1993 1.705
1991 3 73 16 171 1998 1.593
1992 4 100 8 135 2005 1.258
1993 5 183 2 131 1996 1.220
1994 6 80 14 126 2000 1.174
1995 7 90 10 120 2008 1.118
1996 8 131 5 100 1992 0.932
1997 9 92 9 92 1997 0.857
1998 10 171 3 90 1995 0.838
1999 11 250 1 85 1990 0.792
2000 12 126 6 84 1989 0.782
2001 13 68 18 83 2007 0.773
2002 14 78 15 80 1994 0.745
2003 15 69 17 78 2002 0.727
2004 16 67 19 73 1991 0.680
2005 17 135 4 69 2003 0.643
2006 18 62 20 68 2001 0.633
2007 19 83 13 67 2004 0.624
2008 20 120 7 62 2006 0.578
107.35 SUMA

Coeficiente de Variación= 0.45


Coeficiente de Asimetria = 0.01
n= 20

Pendiente 2.222 0.707 0.900 1.414


INTERPOLACION Ordenada 3.718 3.089 2.569 2.329
Cs 0.01 0.1 0.5 1
Lim. Sup. 0.001 3.720 3.090 2.570 2.330
Lim. Inf. 0.1 3.940 3.230 2.680 2.400
Valor 0.01 3.745 3.098 2.580 2.346
Probabilidad (%) Tr (años) Coef. De Precipitacion
Asimetria
(Cs)
0.01 10000.0 3.745 287
0.1 1000.0 3.098 256
0.5 200.0 2.580 231
1 100.0 2.346 220
3 33.3 1.908 199
5 20.0 1.677 188
10 10.0 1.391 174
20 5.0 1.952 201
25 4.0 0.559 134
30 3.3 0.409 127
40 2.5 0.139 114
50 2.0 -0.056 105
60 1.7 -0.306 93
70 1.4 -0.631 77
75 1.3 -0.781 70
80 1.3 -0.951 62
90 1.1 -1.169 51
95 1.1 -1.603 30
97 1.0 -1.852 19
99 1.0 -2.316 -4
99.9 1.0 -3.082 -40

500

400

300
recipitacion mm

200
300

Precipitacion mm
200

100

0
0.01 0.10 1.00 10.00

-100

Probabilidad %
Probabilidad
K-1 (k-1)² (k-1)³
Empirica%
1.329 1.766 2.346 4.76
0.705 0.497 0.350 9.52
0.593 0.352 0.208 14.29
0.258 0.066 0.017 19.05
0.220 0.049 0.011 23.81
0.174 0.030 0.005 28.57
0.118 0.014 0.002 33.33
-0.068 0.005 0.000 38.10
-0.143 0.020 -0.003 42.86
-0.162 0.026 -0.004 47.62
-0.208 0.043 -0.009 52.38
-0.218 0.047 -0.010 57.14
-0.227 0.051 -0.012 61.90
-0.255 0.065 -0.017 66.67
-0.273 0.075 -0.020 71.43
-0.320 0.102 -0.033 76.19
-0.357 0.128 -0.046 80.95
-0.367 0.134 -0.049 85.71
-0.376 0.141 -0.053 90.48
-0.422 0.178 -0.075 95.24
2.608

2.475 3.300 9.900 99.000 -9.900 -9.900 -9.900 -4.950


1.878 1.637 1.270 0.741 0.680 0.530 0.260 0.005
3 5 10 20 25 30 40 50
1.880 1.640 1.280 0.840 0.670 0.520 0.250 0.000
1.920 1.670 1.290 0.841 0.660 0.510 0.240 -0.020
1.908 1.677 1.391 1.952 0.559 0.409 0.139 -0.056
Probabilidad empirica
Gambel
PERSON III
Probabilidad empirica
Gambel
PERSON III

10.00 100.00
-4.950 -9.900 -9.900 -9.900 9.900 3.300 2.475 1.238
-0.245 -0.510 -0.660 -0.830 -1.290 -1.643 -1.882 -2.331
60 70 75 80 90 95 97 99
-0.250 -0.520 -0.670 -0.840 -1.280 -1.640 -1.880 -2.330
-0.270 -0.530 -0.680 -0.850 -1.270 -1.610 -1.840 -2.250
-0.306 -0.631 -0.781 -0.951 -1.169 -1.603 -1.852 -2.316
0.707
-3.091
99.9
-3.090
-2.950
-3.082