IPDS (Integrated power development scheme) Project of JBVNL

STATUS REPORT OF ROW issues

Sl.
District Town Name Activity Submission by Ashoka Buildcon Limited Compliance from JBVNL
No
Submission made by ESE, Daltonagnj vide letter dated 24.02.2020 is enlisted as follows:
Total Length of 33KV New Line - 24.3 Km, work Firstly, the ROW issue was started on 29.07.2019 after some unknown persons uprooted 5nos. of poles erected by
completed for 22.5Km, agency. Due to which agency stopped the work. However, the matter was not informed to Police by agency officials. It
while balance for 1.8Km due to ROW Issues. was tried out to identify the miscreants. Further incident accured on 04.09.2019 & accordingly Police Station Sadar
ROW in erection and stringing of 1.8 CKm line. ROW Problems are persisitent for the past 14 Months. Thana was informed about the incident for taking necessary action after investigation.
New 33 KV O/H Location: Dubhiyakhad (Jhorkut) - 1.2Km, Heritage School - Contact Details : -
2
Line 0.3Km , Grid SS - 0.3Km for Sudna Feeder from Existing EEE Project, Daltonganj - Mr. Basant Kumar Again, it was tried to be start the work in the month of Nov, 19, but some villagers gathered & stopped the work. After
Sudna GSS to New 33/11kV Pokhra PSS (7979062753) the matter could not be resolved by local police station, district administration was being requested for deputation of
CO, Daltonganj - 7992386105 Magistrate for execution of work vide letter ref no. 20 dated 04.01.2020. Accordingly, Sub-divisional Magistrate Sadar,
Ashoka Buildcon Engineer : - Mr. Ravi Kumar Medininagar vide letter ref no. 99 dated 04.02.2020 passed an order for the deputation of Magistrate. Accordingly, work
(7992302335) was started by agency in ROW area in co-ordination with Deputed Magistrate by District Administration and Police
force at Jhorkut site on 12.02.2020.
Daltonganj
Since, a local annual fair/Dubhiyakhad Adivasi Mela was ongoing in the same area, the hindrance put forth by local
people was too high and uncontrollable. Taking into consideration the prevailing scenario, the work was put on hold till
Total Length of 11KV New Line - 13.6 Km, work further instruction. As of now, the matter has been escalated to Civil SDO & a meeting is being scheduled to take place
completed for 12.4Km, on 25.02.2020 for further necessary action.
while balance for 1.2Km due to ROW Issues.
ROW Problems are persisitent for the past 14 Months. ROW issue evolved at Heritage School will be taken up after resolving the Jhorkut issue because the work site is
ROW in erection and stringing of 1.2 CKm line.
New 11 KV O/H Contact Details : - advance to the Jhorkut. In context to Sudna PSS, it is completely typical construction issue, hence agency may be
3 Location: Dubhiyakhad (Jhorkut) for 11kV outgoing feeder
Line EEE Project, Daltonganj - Mr. Basant Kumar directed to start the work at the earliest in co-ordination with local field officals of JBVNL & PMA.
from New 33/11kV Pokhra PSS to Ranchi Road
(7979062753)
CO, daltonganj - 7992386105
Ashoka Buildcon Engineer : - Mr. Ravi Kumar
(7992302335)

Total Length of 33KV Line Reconductoring- 6.2 Km, work


completed
Shutdown issue and ROW for 1.2 CKm line due to for 5Km, while balance for 1.2Km due to ROW Issues.
Palamu 33 KV
4 agriculture land. Location: Deori PSS to Ahara locality (33 Contact Details : -
Reconductoring
KV Deori Feeder) JEE, Hussainabad - Mr. Pradip Kumar (9431707420)
Ashoka Buildcon Engineer : - Mr. Kundan Kumar
(7008528127)
Submission made by ESE, Daltonagnj vide letter dated 24.02.2020 is enlisted as follows:

As of now wheat crop is being planted in the area and work can only be completed after a month / after the crop
cultivation gets over since the feasibilty of carrying the work in the present condition is not possible.
Total Length of 11KV New Line - 6.445 Km, work
completed for
ROW in erection & stringing of 0.6 Km line (11 KV Town
5.845Km, while balance for 0.6Km due to ROW Issues.
Feeder)
New 11 KV O/H ROW Problems are persisitent for the past 6 Months.
5 Location: Japla Choubey Railway Line – 0.250 CKm &
Line Contact Details : -
Purandhar Bigha – 0.350 CKm. Charging of 2 Nos. DTR also
Hussainabad JEE, Hussainabad - Mr. Pradip Kumar (9431707420)
heldup due to this ROW issue.
Ashoka Buildcon Engineer : - Mr. Kundan Kumar
(7008528127)

Submission made by ESE, Daltonagnj vide letter dated 24.02.2020 is enlisted as follows:
Total Length of 11KV Line Reconductoring- 16.939 Km,
work
The 11kV line is concerned with charging of 2nos. DTR which was erected around 6months ago without stringing the
ROW for 1.539 CKm due to agriculture land. completed for 15.4Km, while balance for 1.539Km due to
concerned 11kV Line. More than three (3) attempts has been made to complete the stringing of 11kV line with the help
11 KV Location: Gamaria to Mohamdabad – 0.8 CKm, ROW Issues.
6 of police force at Japla Choubey Nagar, but the matter could not be resolved.
Reconductoring Mohamdabad to Datanagar – 0.5 CKm, & Near Mehedinagar Contact Details : -
– 0.239 CKm. JEE, Hussainabad - Mr. Pradip Kumar (9431707420)
At Purandar Bigha the 11kV Line passes through Railway Lane. M/s ABL did not took proper care and proposed the
Ashoka Buildcon Engineer : - Mr. Kundan Kumar
line where railway permission will be required. Railway has been requested but they have denied to give permission &
(7008528127)
hence the quantity will be descoped.
ROW for 3.6Km
River crossing tower.
Total Length of 33KV New Line - 13.3 Km, work
1. ROW issue due to Public hindrance. Tower Foundation
completed for 9.7Km,
Works stopped by Locals.
while balance for 3.6Km due to ROW Issues.
Tower for Koel River crossing - 0.57Km. (Garhwa New Submission made by ESE, Garhwa vide letter ref no. 175 dated 24.02.2020 is enlisted as follows:
ROW Problems are persisitent for the past 7 Months.
feeder -
Contact Details : -
New 33 KV O/H From existing Rehla GSS to New Garhwa PSS 1. The tower erection work & other related works where ROW issues has been raised by agency during erection work is
7 ESE, Garhwa Supply Circle, JBVNL - Mr. Dhananjay
Line 2. Garhwa New feeder (ROW for 3 CKm stringing due to due to public hindrance created by huge nos. of villagers. In this regard, a meeting has been arranged with DC, Garhwa
Kumar
agricultural land.) however, it was directed to start the work after completion of assembly election.
(9431707402)
Location – Near Railway Track Garhwa Road Station (Near
CO, Garhwa - Mr. J. K. Mishra (7352050666)
existing 33kV Garhwa feeder). 2. After govt. formation, EEE & AEE again had a meeting with DC, Garhwa & accordingly agency was directed to start
Ashoka Buildcon Engineer : - Mr. Kanhaiya Kumar
3. ROW issue for erection of 2 No Mid Span pole at Darhu the work. DC, Garhwa also suggested to have a meeting with C.O. Garhwa should any problem / objection may arise in
(8789471223)
River future.
Garhwa Garhwa Bank Near Garhwa New PSS.
3. During the erection work at site, due to huge public protest work was stopped. Accordingly, AEE & Agency officers
tried to consult with C.O., Garhwa, however the meeting failed.

4. On 23rd Feb, 2020, EEE/S/Garhwa I & AEE/S/Garhwa I again visited office of C.O. Garhwa & it was directed to
agency to start the work at the earliest. As stated by C.O. Garhwa, land is of Road department & in case of any
Total Length of 11KV New Line - 5.645 Km, work objection, the matter should be immediately highlighted for resolving the issue.
completed for 4.2Km,
while balance for 1.445Km due to ROW Issues. 5. ESE, Garhwa directed agency officials to start the work from 25.02.2020. M/s ABL confirmed the same.
ROW Problems are persisitent for the past 7 Months.
11kV O/G feeder from New PSS
Contact Details : -
New 11 KV O/H ROW issue in 1.445 CKm due to Public hindrance regarding
8 ESE, Garhwa Supply Circle, JBVNL - Mr. Dhananjay
Line Pole Pitching.
Kumar
Location: near new PSS- Bank of Daru River.
(9431707402)
CO, Garhwa - Mr. J. K. Mishra (7352050666)
Ashoka Buildcon Engineer : - Mr. Kanhaiya Kumar
(8789471223)
IPDS (Integrated power development scheme) Project of JBVNL
STATUS REPORT OF ROW issues

Sl.
District Town Name Activity Submission by Ashoka Buildcon Limited Compliance from JBVNL
No
Submission made by ESE, Ranchi vide letter dated 24.02.2020 is enlisted as follows:

1. There are more than 10 Nos. of ROW Issues in 33kV Hatia Bero feeder.
2. Out of these, 7 Nos. of ROW issues has been resolved from Nagri Bazar to Raj International
School.
3. From near Pakur Masjid to Nearest DP:- In this feeder near Pakur Masjid, there exists a DP
Structure adjoining Masjid. Although 4-5 attempts were made for carrying out the
reconductoring work, but due to strong protest from Local people work could not be completed
till now.
4. From Nagri Bajar to Raj International School:- In this section dense population exists below
ROW at Bero feeder (2.15 CKm) due to public 33KV Bero feeder Several attempts were made for carrying out reconductoring work.
hindrance & Shutdown.
Total Length of Tatisilwai Feeder - 17Km, in Strengthening of this line was being done by agency once, but there after local people
Bero Feeder: forcefully stopped the work.
which work completed
1. From Near Pakur Masjid to Nearest DP –
for 11.1Km, and Balance for 5.9Km due to 5. Raj International School to Sahar Basti:- In this section several attempts were made but local
0.15 CKm. people forcefully stopped the work. Also dense populations area exists under this feeder.
ROW issue.
2. From Nagri bazar to Raj International School
Total Length of Bero Feeder - 15 Km, in However restrengtheing work i.e. replacement of V-cross arm pin insulator has been
– 1.0 CKm completed, but reconductoring could not be completed till now.
which work completed for
3. Raj International School to Sahar Basti – 0.6
33 KV 12.85Km, and Balance for 2.15Km due to 6. Action Plan:- Team shall visit in all three siteson 25.02.2020 and all efforts will be under
CKm taken to complete the work within 15 days.
1 Ranchi Ranchi Reconductor ROW issue.
4. From Tasar Power House – 0.4 CKm
ing ROW Problems are persisitent for the past 12 7.Sadabhar PSS to Namkum Thana (Total length of line is 0.9 Km):- Agency attempted several
ROW at Tatisilwai feeder (5.9 CKm) due to times to carryout re-conducting work but due to ROW issue from newly constructed house
Months.
public hindrance & agricultural land. owners near Sadabhar PSS the work was stopped. AEE/Tatisilwai asked agency to take
Contact Details : -
1. From Sadabahar PSS to Namkum Thana- 0.9
ESE, Ranchi Supply Circle, JBVNL - Mr. another attempt in co-ordination with local Thana. However, due to marshy land near Namkum
CKm Thana agency informed that work shall be taken after the land becomes ready to work.
P.K. Shrivastava (9431135662)
2. From Baram Village to Railway Crossing –
Ashoka Buildcon Engineer : - Mr. Vinod 8. Baram village to Railway Crossing work:- Work in this section was going on but due to
3.5 CKm construction of Ring Road around 12 Nos. Poles cant be erected till demarcation of Ring Road,
Kumar (7360018224)
3. From Railway Crossing to Tatisilwai PSS – NH is completed.
1.5 CKm 9. Work near Sarla Birla School stopped by School authoirty near Sarla Birla PSS.
10. Railway crossing of Tatisilwai PSS work not started by agency due to marshy land.
11. All efforts will be under taken to complete all balance works within 15 days.