Sei sulla pagina 1di 27

Project : 9 UNIT - RESIDENTIAL ROW HOUSE

Subject : BILL OF MATERIALS

ITEM OF WORK QUANTITY UNIT UNIT PRICE AMOUNT

A
I. Mobilization/Demobilization 1.00 lot 5,000.00 5,000.00
II. Temporary Facilities 1.00 lot 10,000.00 10,000.00
III. Electrical and Water Consupmtion Fees 1.00 lot 20,000.00 20,000.00
IV. Permits and insurances 1.00 lot 60,000.00 60,000.00
V. As-built Plans 1.00 lot 5,000.00 5,000.00
SUB TOTAL 100,000.00
B
I. CONCRETE AND MASONRY WORKS
Concreting Works
Portland Cement 265.00 bags 230.00 60,950.00
Aggregates:
B.1 White Sand 30.00 cu.m 750.00 22,500.00
B.2 Gravel 3/4" 32.00 cu.m 1,200.00 38,400.00
Steel Bars - Deformed
C.1 16mm dia. x 6.0mtr. 24.00 pcs 320.00 7,680.00
C.2 12mm dia. x 6.0mtr. 75.00 pcs 175.00 13,125.00
C.3 10mm dia. x 6.0mtr. 112.00 pcs 130.00 14,560.00
Tie Wire #18 20.00 kgs 70.00 1,400.00

Masonry Works
Portland Cement 75.00 bags 230.00 17,250.00
CHB 5" 750.00 pcs 14.00 10,500.00
White Sand 30.00 cu.m 700.00 21,000.00
10mm dia. x 6.0mtr. 35.00 pcs 130.00 4,550.00
Tie Wire #16 10.00 kgs 70.00 700.00

Formworks
E.1 Plywood 1/2" x 4 x 8' 5.00 shts 750.00 3,750.00
E.2 Coco lumber 2"x3"x10' . 50.00 pcs 80.00 4,000.00
E.3 Coco lumber 2"x2"x10' . 50.00 pcs 60.00 3,000.00
E.4 2"x3"x12' KD 50.00 pcs 120.00 6,000.00
E.5 CW Nail 3" 10.00 kgs 70.00 700.00
E.6 CW Nail 2" 10.00 kgs 70.00 700.00
E.7 Scaffolings 6.00 set 2,600.00 15,600.00
E.8 Phenolic Board 10.00 pcs 1,200.00 12,000.00
SUB TOTAL 258,365.00
II. ROOF/FLOOR FRAMING SYSTEM
A Long Span Roof, Rib Type 56.00 sq.m 1,200.00 67,200.00
B C-Purlins 2" X 4" X 6m 16.00 pcs 450.00 7,200.00
C Sag Rod 26.00 pcs 75.00 1,950.00
SUB TOTAL 76,350.00
III. Ceiling
A. Wall Angle 1" x 1" x 10' 5.00 pcs 35.00 175.00
B. Carrying Channel 12mm x 38mm x 5.0mtr 10.00 pcs 130.00 1,300.00
C. C- furrings 19mm x 50mm x 5.0mtr 20.00 pcs 112.00 2,240.00
D. Gypsum Board 4 x 8 x 10mm 18.00 pcs 360.00 6,480.00
E. Ficem Screw (1") 1.00 box 1,000.00 1,000.00
fF. Perforated Paper Tape 3.00 roll 150.00 450.00
G. Hardie Jointing Compound 1.00 gal 600.00 600.00
H. Concrete Nail # 1 1/2" 1.00 kgs 80.00 80.00
I. w clip 100.00 pcs 3.00 300.00
J. Blind rivets 1/8"x 1/2 1.00 box 1,200.00 1,200.00
k. Spandrell, stell 8.00 pcs 650.00 5,200.00
SUB TOTAL 19,025.00
IV. FENESTRATION
DOORS
Entrance Door 1.00 assy 8,000.00 8,000.00
Panel Door 1.00 assy 6,500.00 6,500.00
Flush Door 2.00 assy 3,500.00 7,000.00
PVC Door (0.6m x 2.10m) w/ Louver 1.00 set 1,450.00 1,450.00
WINDOWS
Aluminum Sliding and Fixed Window 1.00 lot 32,000.00 32,000.00
SUB TOTAL 54,950.00

V. PAINTING WORKS
A Flat Latex 10.00 tin 1,900.00 19,000.00
B Semi-gloss latex 15.00 tin 2,500.00 37,500.00
C QDE (white) 1.00 gals 485.00 485.00
D Acry Color ) 3.00 ltrs 200.00 600.00
F Flat Enamel 1.00 gals 125.00 125.00
G Neutralizer 2.00 gals 60.00 120.00
H Paint Thinner ( 3ltr. Per gall. ) 3.00 gals 185.00 555.00
I Patching Compound 10.00 kgs 35.00 350.00
J Paint brush 2" 5.00 pcs 25.00 125.00
K Roller brush 7" 5.00 pcs 35.00 175.00
L Sand paper # 100 20.00 ft 15.00 300.00
M. Water Proofing 1.00 lot 5,000.00 5,000.00
SUB TOTAL 64,335.00
VI. ELECTRICAL WORKS
A. Wiring
A.1 THHN Wire#8 50.00 m 90.00 4,500.00
A.2 THHN Wire#12 150.00 m 30.00 4,500.00
A.3 THHN Wire#14 150.00 m 25.00 3,750.00
B. Junction Box 4" x 4" 10.00 pc 25.00 250.00
C. Utility Box 2" x 4" 12.00 pcs 25.00 300.00
D. Panel Board w/ Breaker 6 Branches 1.00 pc 3,500.00 3,500.00
E. Switches:
E.1 One gang switch 1.00 pc 60.00 60.00
E.2 Two gang switch 2.00 pc 90.00 180.00
E.3 Three gang switch 1.00 pc 110.00 110.00
F. Two gang Convinience Outlet 5.00 pc 110.00 550.00
H. Electrical Tape big 2.00 roll 19.00 38.00
I. Flexible pipe 3 175.00 m 6.00 1,050.00
J. Downlight 2.00 set 750.00 1,500.00
K. Wall Lamp 2.00 set 1,500.00 3,000.00
L. Electrical Pipe 1/2" 15.00 pcs 60.00 900.00
M. PVC Pipes 120.00 lm 30.00 3,600.00
SUB TOTAL 27,788.00
VII. PLUMBING WORKS
A. Sewer Lines
A.1 PVC Pipes:
4" x 3mtr. 6 pcs 300.00 1,800.00
2" x 3mtr. 2 pcs 200.00 400.00
A.2 PVC Elbow:
4" x 90 degree 5 pcs 40.00 200.00
4" x 45 degree 5 pcs 40.00 200.00
A.3 PVC Wye:
4" x 4" 3 pcs 40.00 120.00
4" x 2" 2 pcs 30.00 60.00
A.4 PVC P-Trap 2" 2 pcs 70.00 140.00
A.5 PVC Clean Out 4" dia. 2 pc 30.00 60.00
A.7 PVC Tee 4" x 4" 1 pcs 40.00 40.00
PVC Tee 4" x 2" 1 pc 40.00 40.00

B. Water lines:
B.1 PVC Pipe 1/2" x 3.0mtr. 6 pcs 70.00 420.00
B.2 PVC Elbow:
1/2" Plain 6 pcs 8.00 48.00
1/2" Threaded 3 pcs 15.00 45.00
B.3 PVC Tee 1/2" Plain 3 pcs 10.00 30.00
B.4 PVC Female Adapter 1/2 2 pcs 10.00 20.00
C. E.B. Solvent 1 ltr 180.00 180.00
D. Teflon Tape big 2 roll 15.00 30.00
SUB TOTAL 3,833.00
VIII. MISCELLANEOUS
A. Hardwares
A.1 Door Knob 4 pc 600.00 2,400.00
A.2 Hinges 4" x 4" 15 pc 200.00 3,000.00

B. Fit-outs
B.1 Water Closet 1 set 8,500.00 8,500.00
B.2 Lavatory w/ accesories 1 pc 4,500.00 4,500.00
B.3 Floor Drain Stainless Steel 2 pc 110.00 220.00

SUB TOTAL 18,620.00


IX. TILEWORKS/ARCHITECTURAL FINISHES
A.1
a.1.1 Floor Tiles - 60cmX60cm 106.00 pc 180.00 19,080.00
A.2 T & B
a.2.1 Floor Tiles - 8" x 8" 63.00 pc 93.00 5,859.00
a.2.2 Wall Tiles - 8" x 8" 115.00 pc 93.00 10,695.00
B. Mics Materials
B.1 Tile Grout 5.00 kg 46.00 230.00
B.2 Tile Adhesive 8.00 bags 225.00 1,800.00
B.3 Portland Cement 15.00 bags 230.00 3,450.00

SUB TOTAL 41,114.00

SUMARY
MATERIAL COST = 664,380.00
LABOR COST = 265,752.00

TOTAL MATERIALS AND LABOR = 930,132.00

GRAND TOTAL = 930,132.00

Prepared by:

EngJOHN PAUL P. QUILON


REG. NO. 123150
PTR NO. 7507019
Date 1/18/2019
Place Quezon City
Project : PROPOSED THREE STOREY TOWNHOUSE
Subject : BILL OF MATERIALS

Total Floor Area: 437.2 m

ITEM OF WORK QUANTITY UNIT UNIT PRICE AMOUNT

A
I. Mobilization/Demobilization 1.00 lot 75,000.00 75,000.00
II. Temporary Facilities 1.00 lot 75,000.00 75,000.00
III. Electrical and Water Consupmtion Fees 1.00 lot 60,000.00 60,000.00
IV. Permits and insurances 1.00 lot 100,000.00 100,000.00
V. As-built Plans 1.00 lot 30,000.00 30,000.00
SUB TOTAL 340,000.00
B
I. CONCRETE AND MASONRY WORKS
Concreting Works
Portland Cement 1,200.00 bags 230.00 276,000.00
Aggregates:
B.1 White Sand 75.00 cu.m 750.00 56,250.00
B.2 Gravel 3/4" 120.00 cu.m 1,200.00 144,000.00
Steel Bars - Deformed
C.1 16mm dia. x 6.0mtr. 850.00 pcs 320.00 272,000.00
C.2 12mm dia. x 6.0mtr. 75.00 pcs 175.00 13,125.00
C.3 10mm dia. x 6.0mtr. 1,100.00 pcs 130.00 143,000.00
Tie Wire #18 40.00 kgs 70.00 2,800.00

Masonry Works
Portland Cement 250.00 bags 230.00 57,500.00
Starken AAC 600mm x 200mm 2,800.00 pcs 250.00 700,000.00
White Sand 38.00 cu.m 700.00 26,600.00

Formworks
E.1 Plywood 1/2" x 4 x 8' 156.00 shts 750.00 117,000.00
E.2 Coco lumber 2"x3"x10' . 90.00 pcs 80.00 7,200.00
E.3 Coco lumber 2"x2"x10' . 261.00 pcs 60.00 15,660.00
E.4 2"x3"x12' KD 120.00 pcs 120.00 14,400.00
E.5 CW Nail 3" 10.00 kgs 70.00 700.00
E.6 CW Nail 2" 5.00 kgs 70.00 350.00
E.7 Scaffolings 10.00 set 2,600.00 26,000.00
E.8 Phenolic Board 20.00 pcs 1,500.00 30,000.00
SUB TOTAL 1,846,585.00
II. ROOF/FLOOR FRAMING SYSTEM
A 2" x 2" x 3/16" angle bar, 6m 65.00 pcs 650.00 42,250.00
B 2" X 4" Tubular steel 16.00 pcs 850.00 13,600.00
C Dynabolt 200.00 pcs 75.00 15,000.00
D Long Span Roof, Rib Type 196.00 sq.m 1,200.00 235,200.00
E C-Purlins 2" X 4" X 6m 65.00 pcs 450.00 29,250.00
F Metal Deck 0.80 x 1.00 242.00 lm 380.00 91,960.00
SUB TOTAL 427,260.00
III. Ceiling
A. Wall Angle 1" x 1" x 10' 120.00 pcs 35.00 4,200.00
B. Carrying Channel 12mm x 38mm x 5.0mtr 30.00 pcs 130.00 3,900.00
C. C- furrings 19mm x 50mm x 5.0mtr 180.00 pcs 112.00 20,160.00
D. Gypsum Board 4 x 8 x 10mm 150.00 pcs 360.00 54,000.00
E. Ficem Screw (1") 3.00 box 1,000.00 3,000.00
fF. Perforated Paper Tape 30.00 roll 150.00 4,500.00
G. Hardie Jointing Compound 10.00 gal 600.00 6,000.00
H. Concrete Nail # 1 1/2" 3.00 kgs 80.00 240.00
I. w clip 150.00 pcs 3.00 450.00
J. Blind rivets 1/8"x 1/2 3.00 box 1,200.00 3,600.00
k. Spandrell, stell 300.00 pcs 650.00 195,000.00
SUB TOTAL 295,050.00
IV. FENESTRATION
DOORS
Entrance Door 3.00 assy 12,000.00 36,000.00
Panel Door 9.00 assy 9,500.00 85,500.00
Flush Door 6.00 assy 4,500.00 27,000.00
PVC Door (0.6m x 2.10m) w/ Louver 2.00 set 1,450.00 2,900.00
Aluminum Sliding Door 12.00 assy 27,000.00 324,000.00
WINDOWS
Aluminum Sliding and Fixed Window 1.00 lot 180,000.00 180,000.00
SUB TOTAL 655,400.00

V. PAINTING WORKS
A Flat Latex 45.00 tin 1,900.00 85,500.00
B Semi-gloss latex 56.00 tin 2,500.00 140,000.00
C QDE (white) 5.00 gals 485.00 2,425.00
D Acry Color ) 30.00 ltrs 200.00 6,000.00
F Flat Enamel 5.00 gals 125.00 625.00
G Neutralizer 2.00 gals 60.00 120.00
H Paint Thinner ( 3ltr. Per gall. ) 3.00 gals 185.00 555.00
I Patching Compound 40.00 kgs 35.00 1,400.00
J Paint brush 2" 5.00 pcs 25.00 125.00
K Roller brush 7" 5.00 pcs 35.00 175.00
L Sand paper # 100 20.00 ft 15.00 300.00
M. Water Proofing 1.00 lot 5,000.00 5,000.00
SUB TOTAL 242,225.00
VI. ELECTRICAL WORKS
A. Wiring
A.1 THHN Wire#8 300.00 m 90.00 27,000.00
A.2 THHN Wire#12 600.00 m 30.00 18,000.00
A.3 THHN Wire#14 600.00 m 25.00 15,000.00
B. Junction Box 4" x 4" 90.00 pc 25.00 2,250.00
C. Utility Box 2" x 4" 90.00 pcs 25.00 2,250.00
D. Panel Board w/ Breaker 12 Branches 2.00 pc 3,500.00 7,000.00
E. Switches:
E.1 One gang switch 15.00 pc 60.00 900.00
E.2 Two gang switch 30.00 pc 90.00 2,700.00
E.3 Three gang switch 6.00 pc 110.00 660.00
F. Two gang Convinience Outlet 45.00 pc 110.00 4,950.00
H. Electrical Tape big 4.00 roll 19.00 76.00
I. Flexible pipe 3 750.00 m 6.00 4,500.00
J. Downlight 30.00 set 750.00 22,500.00
K. Wall Lamp 6.00 set 1,500.00 9,000.00
L. Electrical Pipe 1/2" 60.00 pcs 60.00 3,600.00
M. Lighting Fixtures 3.00 lot 20,000.00 60,000.00
N. PVC Pipes 300.00 lm 30.00 9,000.00
SUB TOTAL 189,386.00
VII. PLUMBING WORKS
A. Sewer Lines
A.1 PVC Pipes:
4" x 3mtr. 45 pcs 300.00 13,500.00
2" x 3mtr. 30 pcs 200.00 6,000.00
A.2 PVC Elbow:
4" x 90 degree 120 pcs 40.00 4,800.00
4" x 45 degree 30 pcs 40.00 1,200.00
A.3 PVC Wye:
4" x 4" 30 pcs 40.00 1,200.00
4" x 2" 30 pcs 30.00 900.00
A.4 PVC P-Trap 2" 15 pcs 70.00 1,050.00
A.5 PVC Clean Out 4" dia. 12 pc 30.00 360.00
A.7 PVC Tee 4" x 4" 30 pcs 40.00 1,200.00
PVC Tee 4" x 2" 30 pc 40.00 1,200.00

B. Water lines:
B.1 PVC Pipe 1/2" x 3.0mtr. 120 pcs 70.00 8,400.00
B.2 PVC Elbow:
1/2" Plain 45 pcs 8.00 360.00
1/2" Threaded 15 pcs 15.00 225.00
B.3 PVC Tee 1/2" Plain 30 pcs 10.00 300.00
B.4 PVC Female Adapter 1/2 15 pcs 10.00 150.00
C. E.B. Solvent 6 ltr 180.00 1,080.00
D. Teflon Tape big 30 roll 15.00 450.00
SUB TOTAL 42,375.00
VIII. MISCELLANEOUS
A. Hardwares
A.1 Door Knob 24 pc 600.00 14,400.00
A.2 Hinges 4" x 4" 72 pc 200.00 14,400.00

B. Fit-outs
B.1 Water Closet 9 set 15,000.00 135,000.00
B.2 Lavatory w/ accesories 9 pc 15,000.00 135,000.00
B.3 Floor Drain Stainless Steel 12 pc 110.00 1,320.00

SUB TOTAL 300,120.00


IX. TILEWORKS/ARCHITECTURAL FINISHES
A.1
a.1.1 Floor Tiles - 60cmX60cm 1,200.00 pc 315.00 378,000.00
A.2 T & B
a.2.1 Floor Tiles - 8" x 8" 864.00 pc 93.00 80,352.00
a.2.2 Wall Tiles - 8" x 8" 486.00 pc 93.00 45,198.00
B. Mics Materials
B.1 Tile Grout 30.00 kg 46.00 1,380.00
B.2 Tile Adhesive 360.00 bags 225.00 81,000.00
B.3 Portland Cement 150.00 bags 230.00 34,500.00

SUB TOTAL 620,430.00

SUMARY
MATERIAL COST = 4,958,831.00
LABOR COST = 1,983,533.00

TOTAL MATERIALS AND LABOR = 6,942,364.00


12% VAT = 833,083.68
MARK-UP (10%) = 694,236.40
CONTINGENCY (5%) = 347,118.20

GRAND TOTAL = 8,816,802.28

Prepared by:

Engr. JOHN PAUL P. QUILON


SIMPLIFIED CONSTRUCTION ESTIMATE

PROJECT:
SUBJECT:
LOCATION:

DATE:

CONCRETE SLAB

Designation Thickness (m) Width (m) Length (m) Volume (m3)

CF CF1 0.35 1.2 1.5 0.63


COLUMN C1 0.4 0.25 10.2 1.02
BEAM B1 0.4 0.2 123.9 9.912
B2 0
FTB FTB 0.3 0.125 72.4 2.715
FTB 0.125 18 0
SLAB on Grade 0.075 20 14 21
Suspended 1 0.15 14 12.1 25.41
Suspended 2 0.15 14 12.1 25.41
TOTAL

CEMENT
SAND
GRAVEL

MASONRY WORKS (4" THICK)

Designation Height (m) Length (m) AREA (m2) LESS No. Of CHB

6.35 6 38.1 9.87 466.38


0 0
T
ON

0 0
FR

0 0
6.35 6 38.1 5.6 406.25
A R

0 0
RE

6.35 9.8 62.23 11.34 636.125


0 0
T

0 0
F
LE

0 0
0 0

9 12 108 1350
18.1
T
GH

0 0
RI
0 0
T&B 4.29 0 0
SEPTIC TANK 120

TOTAL 246.43 26.81 2996.855


3080.375
TOTAL CHB 2996.855
PLUS 5% 149.84275
TOTAL CHB 3146.69775
SAY 3147

MORTAR CEMENT
(By the Hundred Block Method)

No. of CHB 3147


CEMENT 131.41872 say 132 bags
SAND 10.95156 say 11 cu.m

(By the Area Method)

Total Area 258.7515


CEMENT 135.068283
SAND 11.25569025

METAL REINFORCEMENT
HOW TO DETERMINE SPLICING LENGTH OF STEEL BAR

TYPES OF REINFORCEMENT
1. Tension Bars
2. Compression Bars

REINFORCEMENT OF CONCRETE HOLLOW BLOCKS


(By the Area Method) 10MM

AREA 247
VERTICAL BARS 395.2
HORIZONTAL BARS 531.05
TOTAL 154.375 say 155 pcs

(By the Unit Block Method)

COLUMN FOOTING 16 MM
N L W NET LENGTH LONGITUDINAL TRANSVERSA
CF 1 16 1.5 1.2 0.7 5
WALL FOOTING 10MM
N L W LONGITUDINAL N
FTB 1 72.4 0.125 72.4 3
FTB 1 2 0.125 2 3

Guard House (10


No.of intersec

POST & COLUMN REINFORCEMENT (MAIN BARS) 16 MM BARS

N L W total length of reinf. No. of Bars


C1 16 10.2 0.25 10.65 6

12MM DIA. BAR


10MM DIA. BAR

LATERAL TIES (10MM BARS)

N L W total length of reinf. Spacing


C1 16 10.2 0.25 10.65 0.25
#REF! 0 0 0 0 0.25
#REF! 0 0 0 0 0.25
#REF! 0 0 0 0 0.15
#REF! 0 0 0 0 0.15

No. of intersection
Tie Wire
BEAM REINFORCEMENTS - MAIN BARS (16MM BARS)

N L W T total length of reinf.


B1 1 123.9 0.2 0.4 124.3
B2 1 0 0 0 0.4
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!

16MM DIA. BAR


SAY
STIRRUPS (10MM DIAM.)

N L W T Spacing
B1 1 123.9 0.2 0.4 0.2
B2 1 0 0 0 0.2
#REF! #REF! #REF! #REF! #REF! 0.2
#REF! #REF! #REF! #REF! #REF! 0.2
#REF! #REF! #REF! #REF! #REF! 0.2
#REF! #REF! #REF! #REF! #REF! 0.15
#REF! #REF! #REF! #REF! #REF! 0.15
#REF! #REF! #REF! #REF! #REF! 0.15
#REF! #REF! #REF! #REF! #REF! 0.15
#REF! #REF! #REF! #REF! #REF! 0.15

No. of intersection
Tie Wire
PEDESTRIAN
SLAB (10MM DIAM BAR)

N L W Spacing Longitudinal Transversal


T&B ROOF SLAB #REF! #REF! #REF! 0.3 #REF! #REF!

SLAB REINFORCEMENT (12MM DIAM BAR)

L W Spacing longitudinal Transversal


Slab 14 20 0.3 47 67
#REF! #REF! 0.5 #REF! #REF!
#REF! #REF! 0.2 #REF!
#REF! #REF! 0.2 #REF!

10MM DIA BAR


Tie Wire
SEPTIC COVER (10mm Dia. Bar)

1.20M 9 2
2.00M 6 2
1.00M 2 0.5
.40M 4 0.5

FORMWORKS
N H W L AREA
16 10.2 0.25 0.4 212.16
0 0 0 #REF! #REF!
COLUMN
COLUMN 0 0 0 #REF! #REF!
0 0 0 #REF! #REF!
0 0 0 #REF! #REF!

1 123.9 0.2 0.4 99.12


1 0 0 0 0
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
BEAM
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!

Plywood 1/2" x 4 x8' 311.28 156

COCO LUMBER
2"X2"X10' 261 pcs
2"X2"X8' #REF! ppcs

ROOF FRAMING
L N
Rafter 50mmx150mmx6m C-Purlins, T=1.2mm 12 13 156 26
0

27 PCS

Rafter 50mmx100mmx6m C-Purlins, T=1.2mm

2.8 4 11.2 4
5.4 6 32.4 6
2.4 6 14.4 1

11 PCS

50mmx75mmx6m C-Purlins, T=1.0mm 5.4 4 21.6 4


4.4 2 8.8 2
3.52 2 7.04 2
3 6 18 3
3.95 2 7.9 3
3 2 6 1

15 pcs

Fascia 50mmx200mmx6m C-Purlins, T=1.2mm 5.4 2 10.8


5.4 2 10.8

4 pcs

CEILING (including eaves)

Wall Angle 1" x 1" x 10' 4.88 pcs


11.28667 pcs
1.366667 pcs
1.966667
total 19.5 pcs

Carrying Channel 12mm x 38mm x 5.0mtr 5 pcs

C- furrings 19mm x 50mm x 5.0mtr 8 pcs


2
1
total 11 pcs

Ficem Board 4 x 8 x 3.5mm 11 pcs

Ficem Screw (1") 392 pcs


50 pcs
92 pcs
70 pcs
total 604 pcs

Concrete Nail # 1 1/2" 150 pcs

Blind rivets 1/8"x 1/2 80 pcs


32 pcs
15 pcs
15 pcs
total 142 pcs

PAINTING WORKS
AREA
MASONRY AND DRY WALL
MASONRY 483.3116 SQ.M
structural #REF!
0pcs DRYWALL 0pcs SQM.
C joist
11 ceiling 32.7448
TOTAL #REF!

0.1518 Flush/Panel Door doors 0.1435


0.287 PVC Door total 0.1435
Flat Latex #REF!
Neutralizer ltr
Paint Thinner ( 3ltr. Per 0.007175
elasto Semi-gloss latex #REF!
Assorted Acri colors
QDE (white) 0.0095666667

Elastomeric paint
Flat Wall enamel 0.0047833333
Glazing Putty (white)
Patching Compound

FLOOR TILES

FloorTiles 50 pcs AREA 3.75


T&B 30 pcs 2.25
Wall Tiles 100 pcs 8.1
14.1 SQ.M

CONCRETE TRELLIS
Trellis 0.05m x 0.150 x .50m 8 PCS
Trellis 0.10m x 0.150 x 2.50m 20 PCS

RAILINGS

TUBULAR Pipe
ramp 1

2 X 2 dia. 2.95M 2 4 8 2
2.5M 2 4 8 2
1M 6 4 24 4
8
TOTAL
1 X 1 dia. 0.75M 34 4 136 17

17

pcs

11/2 dia. 6 3 3 3
6 3 3 3
6 3 3 3
6 3 3 3
6 3 3 3
15 pcs
QDE area 4.7124

VII. ELECTRICAL WORKS


A. Wiring A.1 TW Wire#8 23.00 m

A.2 TW Wire#12 8.20 m


A.3 TW Wire#14 229.00 m
pc
B. Junction Box 4" x 4" 10.00 pcs
C. Utility Box 2" x 4" 10.00 pc
D. Panel Board w/ Royu Breaker 4 Branches 1.00
E. Switches: E.1 One gang switch - original 1.00 pc
E.2 Two gang switch - original 1.00 pc
E.3 Three gang switch - original 1.00 pc
pc
F. Two gang Convinience Outlet 1.00 pcs
G. Porcelain receptacle 4" x 4" 9.00 roll
J. Electrical Tape big 4.00 m
K. Flexible pipe 3 130.10 set
L. Compact Flourescent Lamp 9.00
L.wall Lamp 6
VIII. PLUMBING WORKSSewer Lines
A. A.1 PVC Pipes: Black
4" x 3mtr. 3.633333333333
3" x 3mtr.
2" x 3mtr. 1.39
PVC Pipes: Orange
3" x 3 Meters
2" x 3 Meters
A.2 PVC Elbow: Black
3" x 90 degree
4" x 90 degree 2
4" x 45 degree
2" x 90 degree
PVC Elbow: Orange
4" x 90 degree
3" x 90 degree
3" x 45 degree
2" x 90 degree
A.3 PVC Wye: Black
4" x 4"
4" x 2" 1
PVC Wye:Orange
4" x 2"
3" x 2"
3" x 3"
A.4 PVC P-Trap 2" black 1
PVC P-Trap 3" black
PVC P-Trap 2" orange
A.5 PVC Clean Out 4" dia. black 1
PVC Clean Out 3" dia. orange
A.6 PVC Tee 3" x 2" orange
A.7 PVC Tee 4" x 4" orange
PVC Tee 4" x 4" black 3
PVC Tee 4" x 2" black 1

B.1 E.B. Pipe 1/2" x 3.0mtr. 3.466666667


B.2 E.B. Elbow:
1/2" Plain 3
1/2" Threaded 3
B.3 E.B. Tee 1/2" Plain 2
B.4 E.B. Female Adapter 1/2 2
E.B. Solvent
Teflon Tape big
TOTAL
No.
Volume (m3)

16 10.08
16 16.32
1 9.912 0
1 0
1 2.715
1 0
1 21
1 25.41
1 25.41
110.847

831.3525 832 bags


72.05055 72.1 cu.m
110.847 110.9 cu.m

by counting
26.81
0
Wall footing for stairs 68.75
132.5
PCS 202 pcs
16.16

G LENGTH OF STEEL BARS

MIN. SPLICE LENGTH


25 x Bar size + 150
20 x Bar size + 160

TIE WIRE FOR CHB REINFORCEM

0 AREA
0 G.I WIRE
0
0 say 0 pcs

Tie Wire 1.11849057 kg

TRANSVERSAL TOTAL TIE WIRE FOR FOOTING


5 18.6666667 No. of intersections
Total ties
G.I WIRE

18.6666667
GATE & GUARD HOUSE 19 PCS
Tie Wire 1.69811321 kg

TRANSVERSAL N TOTAL TIE WIRE FOR FOOTING


0.37 242.333333 51.1438888889 No. of intersections
0.37 7.66666667 1.47277777778 Total ties
G.I WIRE

Guard House (10MM) 53 pcs


No.of intersection 750
Tie Wire 4.24528302 kg

USE 6M-12MM diam. Bar Excess


96 -4.65 m FOOTING

2MM DIA. BAR 96 pcs 64


0MM DIA. BAR 0 pcs
12.8

No. of Lateral Ties Net Length of Ties No. of Bars


48 0.95 128
6 0.95 0
6 0.25 0
4 0.95 0
4 0.95 0

o. of intersection 272 12 10MM DIA. BAR 128 pcs


1.53962264 kg

No. of Bars USE 6-16MM dia. Bar


6 124.3
4 0.26666667
4 #REF!
4 #REF!
4 #REF!
4 #REF!
4 #REF!
4 #REF!
4 #REF!
4 #REF!

6MM DIA. BAR 125.00 pcs


No. of Stirrups Net Length No. of Bars
627 1 105
7 1 2
#REF! 1 #REF!
#REF! 1 #REF!
#REF! 1 #REF!
#REF! 1 #REF!
#REF! 1 #REF!
#REF! 1 #REF!
#REF! 1 #REF!
#REF! 1 #REF!

o. of intersection 2536 71.00 10 MM DIA BAR #REF! pcs


14.354717 kg
#REF! kg

Net Length No. of Bars


2 #REF!
0
#REF!
12MM DIA BAR #REF! pcs
#REF!
Tie Wire #REF! kg

335.357143
#REF!

55.8928571
0MM DIA BAR 56 pcs
18 kg

5 pcs
PCS

excess 3.7 8pcs


excess 2.8 4pcs

excess 2.8 4pcs


excess 0.6 6pcs
DECOSTONE AREA
PEDESTRIAN COLUMN #REF! sq.m
FRONT OF GH 7 sq.m

CONCRETE MOULDINGS

Window mouldings 5 L.M Decorative mouldings

20mm thk Groove


Pedestrian 50 L.M
Signage Mouldings 10 L.M

GROOVE AREA 1.662


PEDESTRIAN #REF!
GAL
#REF! 13 3.25 TIN
1 gal
1
#REF! 18 4.5 TIN
6 ltrs
0.1 1 gal

0.5 1 GAL
0.25
15

TILE GROUT 7.05 10 KG


TILE ADHESIVE 1.551 3 BAGS
PORTLAND CEMENT 1.2126 3 BAGS
4 pcs

2 pcs
4 pcs

3
3
2
2
TIE WIRE FOR CHB REINFORCEMENT

247
1.118491 say 1.2 kg

TIE WIRE FOR FOOTING


No. of intersections 216
216
1.222642 1.3 kg
TIE WIRE FOR FOOTING
No. of intersections 312
312
1.766038 1.8 kg

192
128
25.6