Sei sulla pagina 1di 4

JOB TITLE / AIM: JSA for the blowing of air in underground piping

JSA DATE:24-08-06 JSA NO./ REVISION:


SUPERVISOR/ JSA LEADER:Qamar Zaman SCRIBE: Abdullah
PARTICIPANTS: Abdullah Khan, Masood Memon, Muhammad Afzal, Asad Nadeem
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps:
1.Mobilization of Equipment.
-----Compressor
-----Hose Pipe
-----Tractor for mobilization

2.Mobilization of compressor with tractor to different locations

3.Blowing of air in the underground pipes

4.Demobilization.

Alternatives Considered: N/A

Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the Hse personnel is the first response in case of
emergency

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 Mobilization of equipment and Unauthorised equipment/tools brought out to Before mobilizing any equipment/tools make sure
workers site that the E &P Personnel got inspected the
equipment. Checklist are in equipment
Unskilled and uninducted personnel starting Ensure that all personnel prior to start the have
the job been inducted and oriented about the hazard in the
job site

Workers starting the job unfit to work All personnel not fit to work shall not be allowed
to work at the project site.
Workers starting the job without JSA JSA must be in place prior to work. Ensure all the
persons take part in the tool box meeting
discussion. Persons signed at the back of JSA

0 Back Injury Ensure workers/operators properly inducted about


the proper positioning
Ensure workers are complying with the min. PPE
req..Safety shoes, helmet, safety glass, dust mask.
Heat Exhaustion Ensure potable water/sufficient shelter is available
each area where workers are doing the job. First
aid kit available at site.

2 Mobilization of compressor with Proper access Ensure that proper access is there for the
tractor to different locations mobilization of tractor
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
Heat Exhaustion Ensure potable water/sufficient shelter is available
each area where workers are doing the job. First
aid kit available at site.

Fire Ensure that DCP fire extinguisher is in place

Tripping hazards Ensure that workers accessing the right


walkway and watch your steps.
Area with excavation/holes to be barricaded
Excavated holes/opening
Other workers/contractors working on the area
SIMOPS will be inform and advised to stop if necessary
Oil spillage Ensure that the absorbing pads are
available at the time of spillage
Pinch point hazard Ensure that no loose dress will be used by operator
during refilling.
Ensure that compressor belt were properly
safeguard prior to operation
3- Blowing of air in underground pipes Eye injury/Hand injury Ensure that proper PPE (safety
googles,safety gloves are worn)
Back Injury Ensure proper hauling of materials/get help if
required/Wear leather gloves.
Heat Exhaustion Ensure potable water/sufficient shelter is available
each area where workers are doing the job. First
aid kit available at site.
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)

4 Demobilization Elevated area left unsecured and untidy Ensure that area left safe and sound eliminating
materials that are not required at elevated area
after finishing the shift.
After performed such activity keep good house
keeping.