Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INFORME DE SUFICIENCIA
PROMOCION 2007-I
LIMA-PERU
2011
TABLA DE CONTENIDO
PRÓLOGO ............................................................................................................. 1
CAPITULO 1
INTRODUCCIÓN .................................................................................................. 4
1. 1 Antecedentes .............................................................................................. 4
CAPITULO 2
'ELECTROMECÁNICA......................................................................................... 8
CONSTRUCCIÓN ................................................................................... 8
'CAPITULO 3
ELECTROMECÁNICAS .................................................................................... 57
3.1.1 Generalidades.................................................................................... 57
111
CONTROL ............................................................................................. 62
PRODUCTIVIDAD ................................................................................ 80
CAPITULO 4
ELECTROMECÁNICAS .................................................................................... 83
CAPITULO 5
CAPITULO 6
CONCLUSIONES.................................................................................................. 117
RECOMENDACIONES........................................................................................ 121
PRÓLOGO
gestión existentes en la empresa con el fin de tener un mejor control, identificar las
áreas de mejora, así como tomar las medidas adecuadas a fin de garantizar el
cumplimiento de los plazos y costos mediante el uso eficiente de los recursos sin
estuvo a cargo del Consorcio Perú LNG, se desarrolló en Pampa Melchorita muy
cerca de las ciudades de Cañete y Chincha, a 169 kilómetros al sur de Lima y tuvo
como contratista principal a la empresa Chicago Bridge & Iron (CB&I), quienes
los sistemas de gestión en cualquier proyecto, así mismo se señala el objetivo del
construcción, así como los procesos que integran el eje básico entre los que tenemos:
proyecto fue crítico y que permitieron que el proyecto culmine con éxito, como son:
de los reporte de HH, la gestión contractual a través del taller de cliente socio y la
3
INTRODUCCIÓN
1. 1 Antecedentes
cumplimiento a las necesidades cada vez más exigentes de los clientes. De allí que la
realidad específica de cada proyecto, de manera que se logre mantener la eficacia del
Sistema. Es por esto que todo Sistema de Gestión debe ser mejorado continuamente
1.2 Objetivo
que permitió llevar un mejor control de avance, tener un panorama más claro del
1.3 Alcances
manera especial a la línea de mando y gerencia del proyecto, quienes tienen en sus
manos las riendas de la ejecución de los mismos y donde es clave tener una
perspectiva clara del proyecto a fin de tomar las decisiones más idóneas para el
6
construcción a nivel nacional, no solo del rubro electromecánico, sino que también
1.4 Limitaciones
Construcción usados con frecuencia para alcanzar los objetivos del proyecto de
manera eficiente y de los cuales nos centraremos en aquellos que por su naturaleza
mención son:
• Planeamiento
• Programación
• Gestión Contractual
• Control de Productividad
• Control de Avanee
1.5 Justificación
control de los avances en campo, así como el mal reporte de los mismos, es algo con
7
lo que se tiene que lidiar constantemente, lo que trae consigo que lo valorizado no
causada tanto a los clientes internos como externos; resulta de vital importancia el
Como se sabe cada proyecto en único y tiene múltiples factores que lo afectan, como
ejecución, entre otros, que hacen que cada proyecto sea diferente. Si bien es cierto,
buenas prácticas a nuestro proyecto en particular. Por lo que por medio del presente
informe se pretende demostrar que con un buen ajuste de nuestro Sistema de Gestión
construcción electromecánica.
CAPITULO2
ELECTROMECÁNICA
Sistema
un fin común.
Gestión
Proyecto
final definidos.
¡sistema de Gestión
más abajo.
Construcción para alcanzar los objetivos de manera eficiente. Los Procesos que
• Planeamiento
• Programación
• Gestión Contractual
• Control de Calidad
• Control de Costos
• Control de Productividad
• Logística
• Control Financiero
lugar en un orden planificado, para dar como resultado el producto final: el Proyecto.
Los Procesos son un conjunto de actividades ordenadas que transforman los insumos
los procesos.
11
para poder obtener el producto final. Pero para poder ejecutar estos procesos es
Las pérdidas en el Sistema de Producción se dan tanto por paras en el flujo, como por
técnicas y teorías formales que nos permitan lograr continuidad del flujo de
utilizados.
procesos.
la Variabilidad, y
de Proyectos.
ACTIVIDADES DE EJECUCION
Excavación, Instalación de tubería, Compactación de zanja
�VV'J
,A_ A._ /'\... � �PRODUCCION
ACTIVIDADES SOPORTE
Logística, Reclutamiento, QA/QC, PdR
Planeamiento, la Programación, Opt11n,zaci611 de Flujos y Procesos
APLICACIÓN DE PRINCIPIOS
DE FISICA DE PRODUCCION:
+
-Uso de Buffers MANEJO DE LA
-Reducción del Tamaño del Lote VARIABILIDAD
-Balanceo de Carga de trabajo
1 GESTION DE LA PRODUCCION
2.2 PLANEAMIENTO
Planeamiento
Análisis de lodos los
aspectos e/el Proyec10 ·
Información
Plan del
del Proyecto
Proyecto
(Transferencia)
Figura 2.2 - A través del Planeamiento se obtienen las estrategias de gestión y ejecución del Proyecto.
14
Planeamiento
Diséño dél Sistema de Aspectos Organizativos y
Producción Estratéaicos
Definición de: Definición de:
,/ Etapas y frentes del ./ Factores claves de éxito
Proyecto ./ Estructuras de control
./ Secuencia de ejecución ./ Organización y facilidades
Duración de las etapas ./ PdR/GA
Recursos necesarios ./ Gestión contractual
,/ Actividades críticas ./ QA/QC
Etc. ./ Recursos humanos
,/ Temas administrativos
,/ Temas financieros
./ Logística
./ Responsabilidad social
Etc.
Figura 2.3 - El Planeamiento debe cubrir todos los aspectos del Proyecto.
El análisis del Proyecto es un proceso iterativo y dinámico, que debe cubrir todo el
El alcance del Proyecto está definido por el Contrato y sus documentos relacionados,
y está conformado por todas las necesidades, requerimientos y obligaciones bajo las
cuales fue adjudicado. El equipo del Proyecto debe consolidar toda la información
aceptadas y/o asumidas, etc.), con la finalidad de definir con claridad el alcance real
a ser considerado.
El alcance debe incluir todos los trabajos requeridos y sólo los trabajos requeridos
en el Contrato respectivo.
exista en la documentación entregada por el Cliente. En tal caso, se deberá tomar las
identificado.
alcance definido, a fin de que pueda ser transmitido de manera eficaz a todo el
• La estrategia de ejecución.
debe identificar los aspectos principales del mismo, como por ejemplo la Ruta Crítica
variará dependiendo del tipo de recurso. Los responsables de realizar esta revisión
experiencia de los ingenieros que pertenecen al Proyecto. Para esta labor se debe
tener en cuenta todas las restricciones del Cliente y las restricciones externas que
puedan afectar el desaITollo del Proyecto, así como las que pudiesen retrasar el inicio
siguientes temas:
• Identificar los hitos (tanto por exigencia contractual como por decisión del
Proyecto).
17
siguientes temas:
• Gestión Contractual
• Logística
• Temas Administrativos
• Recursos Humanos
• Responsabilidad Social
• Ingeniería de Acompañamiento
18
• Puesta en marcha
• Servicios post-venta
• Etc.
Proyecto con el fin de facilitar su control y lectura. Pueden definirse según diversos
de control:
Estructura de
Utilizada en:
Control
Estructura de División Cronograma General
de Trabajo (EDT) Control de Plazo
Estructura de
Control de Costos
Control de Costos
Estructura de Control de Avances
Control de Avances
Partidas de Control Control de Productividad (IP)
Ítems de Pago Valorizaciones con el Cliente
Figura 2.4 - Estructuras de Control para los diferentes procesos de control del Proyecto.
Cada Proyecto podrá además definir otras estructuras de control, de acuerdo a los
los sistemas.
todo el personal del Proyecto. Los criterios generales para definir las estructuras de
confiable y oportuna.
• Los reportes de los sistemas deben mostrar información que agregue valor al
• Deben estar lo más vinculadas entre sí que sea posiblé;, de modo que se
Este último c1ite1io es muy importante. Vincular las estructuras significa lograr que
caso más favorable, las cinco estructuras de control serán idénticas, de modo que una
desfavorable, las cinco estructuras serán totalmente diferentes, de modo que haya que
tomar y procesar información de cinco maneras distintas para alimentar los mismos
procesos. Ambos casos son muy poco probables, siendo lo usual un punto
, ... -------------,
, Avances: Valorización:- - -- Cronograma:
· zai:iátas - ·_ - --..
: :. coñcréio ·¿é - Concreto dP. Z.a¡ir1tr1�
- Concreto de Losas de Piso : - Concreto de Losas de Piso
· :: ·co·ricrefo ae ·coliúñnas·. : .-_- cciñéreiéi-éie-éieiñiéñiéis
. : ;�.g·¿�b�IKHlI��ª�f"J--_��--�.[ ·; : :e¿tfL1E=EE!ti�2s=:::'.
\ :_- Concreto de Losas Elevada�� •• � olovadas por piso
1 - - - - - - - - - - - - - - - - - - • - - - - - - - - - - ,· ' --- - - - • - • -- -- • •- - - - - - • -,
:
, _____________ .. ------------,-----------------
a:
'---------'i Control de Plazo:
- Concreto de Zapatas
: Recursos: - Concreto de losas de Piso
-�_qfl�r9}_qy_�_'!_ances: :·.: cañ,:'riúc; iJe; éieríeritos·:
:·-- Concreto
·-· ·· ··· · .--�----- : _ ,��,1ff!)�,s, PP!,�l�9, ::,)
:�1
· .CC�nt.r�J. !;!�. P.r_oductividad: ,·- Concreto de Losas ;
.o::i
.
... ---- - ,---- -- ...
1
' Control de Costos:
:_: �:'��!�_l?_ - - - _; 1
:_. ':('::il?_�� P.C?� p_i�?.•• - - - .:
_ - Concreto
en dividir el Proyecto en las actividades que lo componen. Las actividades son las
tareas específicas que deben ser realizadas durante la ejecución de un Proyecto para
Proyecto y con el detalle necesario para poder plasmar las estrategias a utilizar a lo
conocida como WBS (Work Breakdown Structure) por sus siglas en inglés.
• Nivel 1: Proyecto.
� Descomponer cada nivel del EDT. Esta descomposición implica subdividir cada
nivel del EDT en sus respectivos componentes y elementos, tal como se muestra
en la figura 2.6:
22
{
INGENIERIA
NIVEL 2 120 PROCURA
130 CONSTRUCC/ON
----.
NIVEL 3 � 130.1 SECONDAR Y CRUSHER
NIVEL 4
NIVEL 5 ...... 130. 1. 1
130. 1.1. 1
Fresh Water Supp/y and Oistrib
Cimentaciones de bombas
{
1 30.1.1. 1.1 Excavación
130.1.1.1.2 Relleno
NIVEL 6
130.1.1.1.3 Encofrado
130. 1. 1. 1.4 Concreto
NIVEL 5
{ 130.1.2.1
130.1.2.2
Estructuras
Tuberías
NIVEL 6
{ 130.1.2.2.1
130.1.2.2.2
Fabricación
Montaje
NIVEL 1 1 PROYECTO 1
NIVEL4 1 SISTEMAS 1
NIVEL 5
IL-__. r
DISCIPLINA 1
1 ACTIVIDAD 1
NIVEL6
Control de Costos. Consiste en el ordenamiento del costo del Proyecto con el fin de
información de costos generada por el consumo de los recursos será cargada en los
control de modo que las sumatorias de los subtotales por rubro y fase/recurso
incluirán el costo directo y parte del costo indirecto del Proyecto. Por
• La cuenta de Costos Indirectos incluirá sólo la parte del costo indirecto del
Avance.
ESTRUCTURA i:>E
CONTROL DE AVANOE AVANCE
es expresado como un porcentaje del total del alcance del Proyecto. El proceso de
evaluación, y
calcular los porcentajes de avance de las mismas. Para que estos porcentajes
• Dado que cada actividad tiene unidades de medida diferentes (por ejemplo:
unidad común, generalmente usando como criterios las HH que las componen
cada actividad, de ese modo se tienen todas las actividades expresadas en una
% incidencia 1 % Avance 1
% incidencia 2 % Avance 2
o/o Avance
% lncidenda 3 % Avance 3 del
Proyecto
% incidencia N % Avance N
°
100 /4
Curva "S":
del Proyecto en función del tiempo, tanto para el avance previsto como para el
• El avance previsto está graficado para todo el Proyecto, con base en los
Si la curva del avance real se encuentra por encima de la curva del avance prevista,
avance real se encuentra por debajo de la curva de avance prevista, significa que el
Proyecto se encuentra retrasado con respecto a lo esperado. Para que esto se cumpla:
registro del seguimiento del avance real del Proyecto. Esta información pennite
27
preventivas.
' . ,
---- ---� --
18,000
-
17,000
éH�\J !\Jl
$" -
16,000 '-,sCf"U J5 l'.:U5,.55 ..
15,000
. . ·- 14, s�� ��·--
! 554
v..,
' 13,�05 .A"" u,138 1
'
,200
-
.
14,000
·1r /......1
.1�8 'tf
12,1 45 •
13,000 ..;04..
/ . ,56'3
,.,,
_/
12,000 1-h
V ,r
,·
1, ,177
.,,,
11,000
k11,3 8
q 1 •• /
10,000
V 1-
o 1�51 �VAN E, p;•OYE tw,
..
9,000
AV, lnCE. PI..Afl AOO
8,000 ../
' V 7·
/
7,000
o /V
J'• �
/' · ººª
,I
6,000
4,136 /
V k'Ít·¡;04
5,000
.
r/'
4,000
23
3,000 1/l·
Á,�16 i<VAN E""
�.
...
2,000
·=
,. ,030 / 4 52
1,000 C---1
1�
� 'º
o ,,
avance que fue ejecutado con dicho consumo. El consumo de recursos ordenado por
Partida de Control se obtiene de los sistemas (SISPO, SISME), por lo que está
eficiente de la información.
PARlllDAS DE
,CONTROL MO
Actividad 01 a HH
'
Actividad 02 HH
Actividad 03 HH
HH IPDE MANO
DE OBRA
AVANCE
ESTRUCTURA
DE C.ONllROL Avance Acr,01
DE AVANCE Avance AcT.02
Avance ACT.oJ
PARTIDAS DE ; EQUIPOS
I EQ02
CON:rROL ECll O� •EQ03
Actividad 01 1 11,.. HM
HM
HM
HM
Hfvl
HM
Actividad 02
Actividad 03 1 ,- HM HM
HM roo, HM
HM
IPOE
HM E001 E003
EQUIPOS
AVANCE
ESTRUCTURA
DE CONTROL Avance ACT.01
DE:AVANCE Avance Acr.02
Avance ACT.oJ
cronograma inicial y debe tener los cambios que el Proyecto considere necesarios,
etc. Para que cumpla sus objetivos como henamienta de gestión, el cronograma
Es usual que el Cronograma General sea parte del Contrato, de modo que quedan
establecidos de esa manera los compromisos de plazo, fechas (hitos) y recursos ante
cronograma que fue elaborado por Presupuestos y con el que se ganó la licitación,
El Cronograma Interno es aquel que se elabora para el control interno del Proyecto.
En principio deberían ser iguales, sin embargo podría resultar necesario elaborar dos
de forma interna.
30
2.3 PROGRAMACIÓN
las acciones necesarias para lograr la ejecución del plan de trabajo diseñado durante
PROTECCION
AL PLAN
PLANEAMIENTO
IM214i�M.U. EJECUCION
,-
:
-La- - Program.:icion
- - - --- - - - - --- ... - .. -----.
e::, lo
: protecclon del
: Planeamiento de modo
¡ que lo Ejecutado sea
: igual a lo Previsto.
·- ----------------------- J
RUTINA DE PROGRAMACIÓN:
Herramientas de Programación+ Reuniones
=::::;::;:.;,:__---r-r----
Programación Proyecto
(
E labor ación
de
Lookahead
�
Elaboración PRODUCCIÓN Análisis de
de PPC Restriccil)rle
�
Generación
do
Plan Somanal J
de gestión:
• Análisis de Restricciones
• Plan Semanal
32
• Plan Diario
• Análisis de Confiabilidad
más conveniente para el Proyecto, el cual suele ser de 3 a 6 semanas. Este horizonte
pueda afectar el Planeamiento del Proyecto, tal como cambios de ingenietia, plazos
Las actividades del Look Ahead deben desprenderse del Cronograma General de
ejecución del Proyecto actualizado y luego deben ser explotadas a un mayor nivel de
frente o área. Los Look Aheads deben ser entregados semanalmente al Oficina
•••<1
OUM(>Oo,
'.
03 ,,..
'
OS "' V ' O l II N J V 9
11 10 ,o � � 1: 13 � � � 21 n 2, �
O l M
u,,
, , , , ,
-�
u,, IZ0.00
20.00
__-�
_,.,...u,..,_,._..,.,._ .. .,.., • ..,
Und 40.00 -�...•.,a aa- .-- , ,
, , , , , ,
..
Und 120.00
Und 16.19 1 00
Und 20 00 1.00 ............ ............
""' , , , , , , ,
,..,, _
T••ro ""' 140,00
10.00
"'' __ ,..........
,._ ..... , , , , , , , ,
""'
- .
100.00 1.00
20.00 1.00
..�......... ........ . , , , , , , ,
., .... ,......
.
Und 11).JO U0,00 l•M•O
Und J0.00 20.00
,.
,.
·-- ""'
u,,
""'
-i0,00
110 00 , '. " ,
""' 40.00
20.00
1.00
1.00 ,........... ,,,_,,..__ .i
"º' , ,
""'
...
··--�
L.00
110.00 100 l l l l
20.00 ,__
Und •S.
1\).:,0 1.00 �.......... •.....
, ,
r.,.... 1.00 ..... .
,...........
,.
,.
...
u,o.oo
...
u.oo
..
45.00
,.........._,,._, 1.•l ,
y proveer con adecuada anticipación de todo aquello que falta para poder ejecutar
REGISTRO
1
1
GESTION DE PROYECTOS P.t.\.'Cén:
�1:
LOOKAHE.AO
hgna:
-·
'-""lGOOlt MOfu.1u ,�-uvC<T ,-v.
,m ,.ooucaóH
'
n
o o 'so o
n , � ; � � � � ! ! �n� p� !� 1P � � ! 1 !
DCSCE.í•CI0/11 0[ ACTtYU).-.0 Fíi'.kJ.0( H
"º
� .
W.1. UflQO
OQ.rA/DJflODtALDI/N,<:• IJUJl'UD,I,
P: � � g � � � 8 �
....... ....
Q g o
1
�
'
V.__ Ct:i\,W::,!,;U. ,..,,
"-""
•:tW«.
m"'°'
R!l.J.!NO CCt4 �..t.JE� GS-AA
u. ,.uA.,•u¡_.r.l,lás..Il..!.UjLó( 1
GESTION DE PROYECTOS Re,.•&Ó-\:
rnrr.,,,...,.ceA.
1
Ulll!GO PROYECTO/ PROPUESTA
ANAUSIS DE RESTRICCIONES
AREA/DPTO NO. REGISTRO
....,,....,.:
li>agra:
lSJ� PRODUCCIÓN
NOMBRE PROYECTO / PROPUESTA illEKTE U8ICAGON
YAN.ACIIOtA OS MINERAYAHAWCHASRL YANACDCHA S
--
DESCIUPCION DE LA IICTMDAIJ FEOtAINIOO DESCJIIPCION DE LA FECR..\DE
RESP.
l'LANEAIM RESTRICCION I..E\1!L�'!AMil11''!'0
DELJ.51071� Al11'08""'
AREAl
'-... F.1b d? nu:etl en G:rlEtrJ, n?O!!Eiad :EFECc
.¡,- k:mOCAOCNUcl\. CF,,>00/Nl,
Ó:- i-c-emE-'ta 02 e,,-c.;,r..ó:r.iis m35,
03/08(/.cx:6
CJW1ElAS
siguientes:
Materiales.
cantidad suficiente.
descrito se irán generando actividades listas para ser programadas en las semanas
semana siguiente; no basta con duplicar la primera semana del Look Ahead. Esto es
ANÁLISIS DE
RESTRICCIONES
ACTIVIOAOfS
su,
RESTRICCIOUES
' ... ,.
OESCRIPCJOH OE LA ACTMOAO A:UPOHSABLE
, X
j!1i!i!¡a-P...11@MtJ-1.�-
•""l!.5...
.... 'ifa·fQ fr@IJirn•f:lifJ"'"� • ss;q:/·l·J.:-i'@�U(.._··-
IH 1 1..- _..,:::•::::•:•:�
Desa rrono en Desarrollo en Análisis de las Compromiso de Se evalUa la
detalle del de1al� de '°s Producción para ca,dad de la
actividades del
Cronograma materiales a lookahead para la semana.en Program.Klón y
Gener.al bajo un utilizar en las funck5n de las se toman
dar tratamiento a
hor-tzonte actividad•• actlvld.:,des libre s au:1oMs �hr� la�
las restrk.cione:S
determinado. programadas en de ProduccJón. de restrlcd6n. c.ausas de
el look ahead. lncumpllmlento.
El cálculo del PPC se hace en base al Plan Semanal o Programa Diario y se debe
Diario.
medición.
• Si durante la semana se tiene que descartar una tarea y hacer otra, esta nueva
CUMPLIMIENTO
HASTA T/!REAS PROGRN.IADAS TMEAS FEAUZJ\DAS PPC
MES SENNIA
ELDIA SEMANAL ACUMULADO SEMANAL ACUr.'l.l.AO<? �ll'ANAI. AQJMUlAIXJ
actividades del Plan Semanal que no se completen al final de la semana, así como
Los responsables de determinar las causas de incumplimiento son los jefes de cada
frente de producción. Dichas causas deben ser validadas por el Oficina Técnica, y/o
programación, etc.
en el Proyecto.
realizados.
incumplimiento que son particulares en cada Proyecto, por lo que se hace necesario
subcontratado.
personal.
constrncción. Una guía para la con-ecta clasificación de las causas según las
TOTAL TOTAL
CAUSAS DE INCUMPL"1ENTO SEM:S SEIV, 1 SEM7 ,SEMO :SEfl1 9 SEM ·10 SEM 1-1 SEN 12
•;.
PROG f' rogrMl8C Ión 7% ·e, e 0 o 1) o o o
LOG Log ctica 7,,4 '1 e 1) 5 o o o 1 o
ING ingeniería 11'½ ·e e ,) o o 2 o o
EXT E)hMO& O'½ 'S 1 o o o o o o
cu r..10111� 25'½ 37 3 2 () 3 o n 4
EQ t-rI1ro� :l•/c, 4 1 ,, n JI JI o 1 JI
En general, cada causa de incumplimiento debe generar una medida correctiva, las
Producción.
siguiente nos puede mostrar las causas de incumplimiento más recurrentes para
actuar sobre ellas. Debemos entender que las causas de incumplimiento fueron en su
ACTPRE 0%
arriba:
N•!-lltell:i'IIINJ-Sy
01.STRJBUCJÓN POlt.
RE:SPOHUBU
OTCONSOL.ID.6
RE'GT.RICCJOllES DE
MEAS·DE SOPORTE
PARA PRESENTARLO
cr•nCUNION
"'• 2:00 PIA
6:00 PM Nt-llNIUN
ENVfDDE -MNAnAI.\DE .a·o PM
t-NVÑtlH INFDIU'MClénOE PRODUOCIÓN
CXJNSOUOADOS PROGllAl'II\CIÓN R[lJNION
DESOí'ORTE (iadu,. kMtk.-.••ad 11P PdR 5l!O\ilROI)
SOII\Nlll DE
.1 PRODUCCION y dll nl.VM.tM) COfl DEPW\ �IIYt-CIII
UDfl\DELAS s1 OT Y llDERDE LA5 (.. mflU.11)
RliSTTUCCIONCS R�t.!OIONES
Se definen dos rutinas para llevar a cabo el proceso de programación. Ambas rutinas
Gestión al Proyecto por el Gerente de Proyecto. Es posible que las características del
Proyecto definan que ambas rutinas puedan ser utilizadas en determinadas etapas y/o
Rutina 1
partir del cual se elabora el Look Ahead, el análisis de restricciones y el plan semanal
Rutina 2
Es una rutina particular para Proyectos o sectores de las mismas características, cuya
!j
LOOKAIIEAD
D!talle c1e 1! I:
i·Hbii!l·t-:��:� =�·� I
detalle d@ los !!
ANÁLlS50E
RESTRICCIDNE
: : de resb·icc16n). :
l :t a d l'IC"cion,e<; t:obre r !
¡
i ___ elloQk .JhcJd. -- .• 1ncumpf1m1ento .____:
n
Áreas de Soporte y verificar el estado macro del Proyecto. La relación entre ambas se
Revisión de:
Herramientas de
Progr.amacl6n 1 d1cadorcr; de product v1dcd
Reunión -Anél11s1s de co11fiab1l1doa del µrcyec:o PPC y causa·,
Semanal de de 1ncumpl11111ento.
E!:todo de lcvnntornicnto de rc::;lrccic11r.s o cnrgo de
Hvram1e11t• d• Proclucción r i:11eas de suµur l�
C�llll"OI de -Pr0Qra11ación de las siouientes semanas. look aread.
Procluctlvldad análisis de restricciones y plan semanal
Resultados:
;::::::::::::::::::::::::::::::::::.::: t::===========:::
Restricciones de
¿_/"--..
IHereude
·] Reunión Soporte
Revisión de:
Semanal de
-RP.si'11·H=-nes olohAIP.c; clP.t prnyP.r.lo Obra
(indicodcres de productividuc y o vence 1
-Restncaones de las areas de sopone Temu rotativo•
--Olros temas principales de manera rotativa.
Objetivos:
producción.
Objetivos:
de Soporte.
• Dar tratamiento a los inconvenientes de las Áreas de Soporte para levantar las
restricciones de Producción.
Planeamiento Programación
IP
Figura 2.26 - El Control de Productividad como herramienta de Optimización de Procesos.
la ejecución del Plan a través del proceso de Programación. Los resultados del
Proyecto
cuales permiten identificar posibles áreas de oportunidad, que dan origen a una
alternativa de mejora.
dure el Proyecto.
enfoca en reducir los tiempos improductivos (esperas, v1aJes con las manos vacías,
47
tiempos ociosos, etc), las interferencias con otras actividades, el uso inadecuado de
equipos, etc.
productividad:
causas que producen tiempos muertos, y que han sido identificadas por
ellos mismos.
48
Tiempos o Estudio del Trabajo, que se explica más adelante. Con este análisis
Para realizar un estudio de tiempos se pueden usar vanas técnicas, entre ellas se
� Cartas de balance.
contenido de trabajo productivo dentro del total del trabajo realizado, tanto en
cantidad como en calidad. La división del trabajo en estas categotias puede resultar
hasta cierto punto arbitraria, por lo que será importante establecer una división clara
para las diferentes mediciones que se hagan durante el Proyecto. Las comparaciones
tiempo, y en la abscisa se indican los recursos (obreros, equipos, etc.) que pa11icipan
en la actividad que se estudia, asignándole una barra ve11ical a cada recurso. Cada
barra se subdivide para mostrar el tiempo dedicado a cada uno de los diferentes tipos
obrero trabaje más duro, smo en forma más inteligente. Las vías para mejorar la
eficiencia del grupo de trabajo son la reasignación de tareas entre sus miembros o la
modificación del tamaño del grupo que conforma la cuadrilla. Para hacer una caiia
e. Procesar los datos recogidos en una hoja de excel, graficando las barras de
puede distribuir porcentualmente el uso del tiempo para cada uno de los
integrantes de la cuadrilla.
instantánea.
51
treinta observaciones en total (30 minutos), o las que sean necesarias para
.,_ -
DESCRIPCIÓN: Vft,¡1dt:Jot.teL�Sat Ju1 "'I ,1
T1.tbakt No C6ffl.1l�uto,lo
N� ...,. P�...,.,,,..,
ru...._
15'1b
,., 1
b5'tb "S� t-
Al
Y:i�
....M__
]�'l.
AJ
2�'-, :;,,. ............
-29"4
,�
T,a••J• Conulín.no,1• is-.. 5'ló S% S'il> IU� ';,'l(, 5� 6o/.
VH,uu _ _o.Q'!_ O!i.,,., 23¾ -
llu.lea,. r .. ,.,••, -- - �
,�,- -- J(J,., -.iú<...
,.
20'>,-
,,,11, -:�;
1CM4
l,•mp-cin1 15� 2'>� :!f>'II 21¾
V�d._, 65� 10% 9"A.
frawch.. , l�� 2"l'o
dw·ante la semana, se hace uso del Informe Productividad (IP) como hen-amienta
52
El IP es un informe que mide la eficiencia con que se ejecutan las actividades que
Presupuesto Meta.
IP de Mano de Obra:
consumida se mide en horas hombre (HH), siendo ésta la unidad utilizada para medir
Estructura de Control:
definidas, de manera que se pueda evaluar la eficiencia de toda la mano de obra y/o
53
equipos del Proyecto. En caso existan partidas de menor cuantía que no ameriten una
global.
Avances reales:
partidas a analizarse en el Control de Productividad, así como sus alcances, deben ser
las mismas generadas por los reportes del Control de Avance, bajo la misma
periodicidad.
Metrados totales:
con el estado del avance de las mismas, es decir, atendiendo a los saldos de metrado
por ejecutar para así poder estimar una proyección de la Productividad de las
actividades al término del Proyecto. Las cantidades totales actualizadas del Proyecto
Consumo de HH:
CATEGORIA GyM N RO.OB HOR.N ORMAL HOR.EXT 60 % HOR.EXT.100% HOR.TAREA TOTAL COSTO
Ratios Meta:
los análisis de precios unitarios del Presupuesto Meta, en función de la cuadrilla y del
rendimiento previsto para ejecutar la actividad, tal como se muestra en la figura 2.30.
(EDC), por lo que los ratios meta serán obtenidos de manera análoga a como fue
elaborada la EDC.
55
I
Operador Pesado HH 3.:rn 0.026923 J.28 0.09
0.19
,
Equipos
Camión Cisterna 3000 gin 4x2 {Agua) 170 210 hp HM o.so O.OOJ04G 24.99 0.10
Rodillo Liso Vibratorio Autopropulsó3do 10-12 ton, 101-135 hp HM 2.00 0.015395 31.56 0.49
Tractor de Oruga� :260-360 hp Ht.l 1.00 0.007692 93.01 0.72
1
1.31
� 1 REND. META
REND. META MO= 0.07 hh/m3
EQ= 1.31 US$im3
1
Figura 2.30 - Obtención de los ratios meta de mano de obra y equipos.
Compara los ratios de HH reales y previstos para cada partida de control, obteniendo
perdidas del saldo. Con la suma de ambas se obtiene las HH ganadas o perdidas
indicadas.
• Los ratios reales son el resultado del cociente entre las HH utilizadas y el
avance ejecutado.
56
IP �O ALCANTARILLADO
0B11A: YANACOCHA 05 !% Avance: Por1idn Nº 1 18.8\{,
COtHROL DE AVANCE SISPO 1[CIIA: 16.Jul-07 º' 22.Jul-07
.... 1
¾ Ratio
Ac....,_ Acum. Acum. Ratio Ratio Real
ltem l'AIHIUAS lJt CUIIIHUL und lotal
Actual
Acum. l'l'I U
Previsto Real
und
Previsto
Heal
5emanal
ctuol Acum.
Colocac,ón y Compactación
m3 100,000 18,830 18.8% 7,000 1,3 '8 'l,?35 hh/ ,3 0.07 O 071 O.C68
de Matenal je 1-<Elleno
2 Adi,ic.Jad B 1112 100,000 18 880 18.9% 2,000 378 �45 1,1,/ 112 0.02 O OIE O.CH
Arlivicfaci C: m1 rnn.ooo 1A )",[) 1111°,;. J'i,ílOíl f;_,RR F F10 hh/m, 0.'.l'i n ::i._� n 1" 1
'
_ HH Acum. previsto = Avance Acum. * Ratio previsto
Ratio Real Acum. = HH Acum. / Avance Acum_
==============º=:t=r;a===="==========il
A la Fecha Fin de Obra
; i.''l t ,l 1 • HORASHOMEREGAltADAS
• • 1, 1 ' ,'
O PERDIDAS DEL SALDO
(Rdliu lllW - Rdliu AlJJIII) X Mt,\IdJu l\l.urn (Rdüu m�ld - Rdliu Pluy)x l'\;Ud�u Sdloo
IP MO
'" ,,,
notio
... •10111111
sem U:)
..,- " ·-··
�emu�
... ......
sem l 1
. . ,.,
Ratio Ratio Real Gan/ Per Gan/ Per Gan/ Per Gon/ Per Gan/Per 3onr Per
ltem PARTIDAS DE CONTR L und Real AlüFed1u Fill tJe 01.JIU Aht Fedn.1 fin u� OlJrn Alu Fecll� Fi11 ll� Ot..11
P,�vi�o S�lllillUII
Acum.
L:0IocacIor y com¡:act;c,on de 7 2 2 -1 -1
1 hhlm3 0.070 0070 0.069 7
M::itcri.JI de Rcl cno
2 Perfilajo de subrasante hhlm2 0.020 0018 0.017 33 114 12 99 6 100
3 Colocaciór de :ann de 1ubería hhlm3 o.:,so 0350 0.345 g 23 -23 -30 10
ELECTROMECÁNICAS
3. 1. 1 Generalidades
cúbicos por día), estuvo a cargo del Consorcio Perú LNG S.R.L. (liderado por la
Incluye:
• Planta de Procesos
m3
• Áreas Administrativas
58
• Comunidad permanente.
El contratista principal estuvo a cargo de la empresa Chicago Bridge & Iron (CB&I),
tanto de las obras civiles (COSAPI / GYM), así como las obras mecánicas, eléctticas,
/
, 1/
Almacenamiento de
Refrigerantes
Principales Metrados:
• Generadores
• Conmutador y MCC
• Transformadores
• Paneles
• Protección Catódica
• Estaciones de Control
• Tomacorrientes
• Conexión a Tierra
• Cables transportadores
• Cableado
• PCS
• ESD
• Instrumentación en el Campo
• Válvulas
• Cables transportadores
• Cable
• Tubería y Accesorios
• Teléfonos
• PA/GA
• Radios
• CCTV
Trabajo):
WBS-300-Fuera de Obra
WBS-400- Marítima
WBS-600-Instalaciones Permanentes
r
1 1 1 1 1
100 LNG PROCESS
TRAIN
200UTILITIES &
POWER GENERATOR
300 LNG STORAGE,
FLARES & l 400
JETTY
1 600 PERMANfllT
COMMl!JNJTY
W·AREHOUSING
'Tl
(JQe
¡;¡
--{ 110AGRUJHOT OIL 1 -i 210ENLET GAS U N.IT 1 H 410JETTY 1 610 PERMANENT
- 310 LNG STORAGE 1 COMMUN.ITY
l,J ,...._
-
1_
tT1
STORAGE
- 14-0 REFRIGERA - AII24-0R PLANT & INST
(./)
Q,
::i TION
COOLING
o.
o
...,
¡;¡O"
C0MPRESSOR
--{ 340 LNG LOAOING 1
�-
º
,......_
7 150PR COMPRESOR 1 250 NITROGEN 1
� 160 MR
COMPRESOR
(/J
'-'
7 170 LIQUEFACTION 1
- 180 LOCAL
CONTROL ROOM
Partidas Directas
XX M010 Trabajos Adicionales Glb
XX M020 Topografia Glb
XX MOJO Operadores de Equipo Pesado Glb
XX M040 Stand By por Paradas en Obra y Charlas por lnduccion Glb
XX M120 Conduits ML
XX M125 Tendido de Cables de Fuerza (Electrice e lnstrument acion) ML
XX M135 Tendido de Cables Enterrados ML
XX M137 Proteccion de cables ML
XX M140 Conexionados varios Und
XX M145 Bandejas ML
XX M147 Stub Ubs Und
XX M149 Banco de Duetos Und
XX M171 Montaje y pre Ensamble de SoJX)rtes FRAME e INSlRUMENTOS KG
Instalaciones Electricas
10 M150 Artefactos y Oisposfti\os Und
10 M155 Equipos Und
10 M160 lnstalacion de Proteccion Catodica Und
10 M170 Montaje y pre Ensamble de Soportes (bandejas ) KG
10 M175 Cable de Puesta alierra ML
10 M180 Postes de lluminacion Und
lnstrumentacion
20 M210 Paneles de instrumentacK>n Und
20 M220 lnstalacion de Instrumentos Und
20 M230 lnstalacion de Tubing Und
20 M240 Equipos de Telecomunicaciones Und
20 M250 Calibracion de Instrumentos UNO
Pintura
30 M730 Limpieza y Arenado m2
30 M740 Pintura m2
Obras Civiles
50 M110 Excavacion M3
50 M111 Excavacion Manual M3
50 M115 Relleno M3
50 M116 Relleno con arena seleccionada M3
50 M117 Colocacion de Concreto Rojo M2
50 M118 Colocacion de Concreto Pedestales y Fundaciones (!ne. Encofrado. Acero } M3
50 M119 Eliminación de material Excedente M3
Partidas I n d i rectas
DIRECC ION DE PROYECTO
90 M910 Mo...;lización y DesmO\,ilización Glb
90 M920 Prevencion de Riesgo Glb
90 M930 Control de Calidad Glb
90 M935 Oficina Tecnica Glb
ADMINISTRACION Y LOGI STICA
95 M950 Almacen. lmportaciones,Tareadores, controladores, Manteniamiento de Taller Glb
95 M960 Transporte Fletes de equipos y Mate,iales CilAles/ Electromecanicos Viaje
MANT ENIMIENTO EQUIPOS Y CAMPAMENTO
97 M980 Mantenimiento de Campamentos Glb
97 M981 Mantenimiento de Equipo Glb
97 M982 Construccion de campamento Glb
lnstrumentacion
20 MT20 Materiales de instrumentación-soportes de conduits, terminales, conectores, cajas, cables Glb
20 MT21 Soporte para instrumentación Glb
20 MT22 Materiales electrices-soportes de conduits. terminales, conectores, cajas, cables Glb
20 MT23 Pre nsacab\e para Cable Glb
AISLAMIENTO Y PINTURA
30 MT30 Pinturas Glb
30 MT31 Arena Glb
Obras Civiles
50 MT50 Materiales Ci\.11es Glb
Partida s lndire_f.!__a_s
D\RECC\ON DE PROYECTO
90 MT90 Movrnario y Articulas de Oficina Glb
90 MT91 Implementos de Seguridad y Medio ambiente (Materiales de Seg uridad) Glb
90 MT92 Mo\.11ización de Materiales Glb
ADMINISTRACION Y LOGISTICA
95 MT95 Mo\.11iario y Articulas de Oficina Glb
95 MT96 Material de Embalaje (Compra Local) Glb
MANTENIMIENTO EQUIPOS Y CAMPAMENTO
97 MT97 Mantenimiento. Utensilios de Campamento, Muebles y Enseres Glb
97 MT98 Materiales Cosntruccion Campamento Glb
Gastos Financieros
98 9500 Gastos Financieros Glb
98 9501 Capital de trabajo Glb
98 9502 Garantías y fianzas Glb
98 9503 Seguros Glb
98 9504 ITF Glb
98 9505 Sencico Glb
-
'
70 E700
�rtidas Indirectas
DIRECCION DE PROYECTO
90 E910 Camioneta 4x4 DIA
90 E950 Equipos de Laboratorio MES
90 E960 Torre de Iluminación MES
90 E965 Camioneta Rural Tipo VAN MES
ADMINI STRACION Y LOGISTICA
95 E951 Ambulancia DIA
95 E952 Camión de 03 Toneladas DIA
95 E953 Camioneta 4x4 DIA
95 E954 Mo'IAlizacion Equipos Glb
95 E955 DesmolJlizacion de Equipos Glb
95 E956 Custer MES
95 E957 Montacargas (Telehander ) MES
95 E958 Camión Grúa HIAB HM
95 E959 Bus de 25 y 35 Pasajeros HM
MANTENI MIENTO DE EQUIPOS Y CAMP AMENTO
97 E990 Cisterna de Combustible HM
97 E992 Gn,po Electrogeno MES
estaban perdiendo HH y por tanto poder tomar las medidas correctivas a tiempo.
67
El cronograma del Proyecto se realizó haciendo uso del Software Primavera P3. Para
1t
�,IT(T� �I
�j
!')91�:5.........�,., �l,'Jl•li)
CN:10\'lfCIQO ..-.«11nvu1 �.o, O,l-fRC,-11)
···---······-·---······---····-Í----· ····---······-------·-···-·---·······---·-···-·----·
�-000.Jllr.001 CR00�$11 ¡1-.ec,rru.,nlC.tdttlnlJ
UD'l,.DOQ..IWOC:Z CJ.100�-ACCC�SARLAS
DJ1.)QOJW'.llD �UILkGITOl'lACE&BOCCOIIP
tm:mf:llWnG »l!IUIKf.S&UHUOffl.!11..A
-1.Jn::,QCI_J'#..):sl �l(l.JRltiUlANTSIORACl:.
-,m�OM3ao �lNOLOADl1fO
programando las actividades haciendo uso del Lookahead, Plan semanal, Análisis de
•.. 1 "'""- ,.,.. 1• "' • 1111111 � ., 1,.1 � .,, .. l'-il" .. •· .. ·• ·• f( "' " " " ·�1•· • " •· " '"l'l"J·J'I' '' '•" ., "i"
�-... ,-... --
•...;-;r-r--------.,.._;r
�:::=
·--
-·-
,.,.,-
tfW'llO>CTAA .. O.•••• ......
....,IOter.u:lliQ.1........ .:v
--
- f-----..a.."w
úO
��
t<W0101<r .... ,u:.,....o .. ....,
,...,-
<ROMJHO�.... ,m ... ,_.,
��--
:: 1-----------f;:;c
.... f\,UIN),_
;��
:-.;:;;;
-··-· ·�
UKl�....... , .. 1<1A ... ,<1.W,
,,,_,._
,...,'-'!
1 ...,'V
-;:_.:;...·�·=::=-:-�--,--.-...........
_.,_
....�-·---- -�+--�1-7,"
00(>,.ote,""'""""'«l,.¡,.,�-
� f---¡,-
r· ·
,......
,_
-��--
..- -
-- ------- -
�
1
r-· 1 r·
· 1 1 -
·
REOl5TRO
GESTION DE PROYECT05 REVISION 1
PLAN SEMANAL
¡co0tGO OE PROYECTO DIVl510N
1 ....,.. PA� p 1c• ,__.,.,.,.,. EtECTRO-P.IECA..NCA
!NOMBRE DE PROYECTO CUENTE
º '""" "" º '"" º wº º
Metrado pa I•
c:'�-���·,.,, -=.-:.-:.�:::�r------------t
F-'�'�'��r'���'�"'�="�'"�'�·"��"��""='-------------+-------,--------,F'�'-,-------i-:,-:,-:_-:.:,.-:.-::•"'
"'
1-,c�.+,�..,i',-. +--,,.;,-+,!;�-r.:',-,r.o,',-l
ra
Ár•• Oe.c:rlpe:IOn d• la At;tlvldad OOSEAVACIOND
----t- -
-
ELECTRICAL ---
uo P�=��::a,;!��,ooo�"e.,.e_______,
130 SWG 04 BUS A,OA8 KV
130 BUS BAR80°1004A - --- 1--+-1�+-+-1-+--l
uo As!iembtv X X X X X X
uo SWITCHG EARSG-10(M 0..48 KV
130
130 eC�S:.��'=e�o-�,oosA�-
=
� -1�-�td X X X
===t::;:=�;:;�'.:;:¡��t���;��;:::
130 Sunnort X X X X X X
OINGRESISTORNR 01005B --
!��
130 1-
-
����
BU�BARBD•10058
--- -- 06� 1�9 -� X X X X
-,-d--
no ___ s_ue� ___ _ 22-mar-09 1- 2 1-abr-09 31 d __ X X X X X X
130 GROUNDINO RESISTORN�R-� 1�0�06�9�- - --- --I----
UD Sel Un 06-abr-09 6 d X X X X
uo �AR BD-10068
130
220 LlghUng
�� ___ 22-mar-09
23-mar-09 _1_>-a_b_,_-0_, _
31 d
2
X X X X X X
ELABOR.ADO POR:
NOMBRE ING EOSON ROt.ANOO ROSILLO CARRIi.LO
ARGO INGENIEROAREAELECmCIOAO
ECHA. 01-c)4..0Q
que dicha actividad no sea cumplida durante la semana y el PPC salga con un
REGISTRO
OESTION 0!. PROYECTOS
ANÁLISIS DE RESTRICCIONES
ONISION
ElECTRO·MECA.NCA
!NOMBRE DE PRO'l'ECTO
.....
ietECTR:ICAL Ar-o tNSTRUMENTATION WOAl(S
F•cll•R�11erlda
e110bB
. l'QWERiDISFRIBUil'l©N
SUMTATION 10008
Aun no se puede colocar los equipos en so ala FALTA OE AP ROBACON DE PROCEDMENTOS PARA MONTAGE DE EQUIPOS 01'1:>412000 CBI
Aun no so puede colocar los equipos en sala FAl TA PLANOS DE DETALLES PARA NS TALAR PA NELES DE PAREO OIA'.>4/2009 CBI
SE NECESITA CON T E NEDOR (OACINA) NO LLEGA CONTEr-EOOR QUE ESTACON REOUERIMENT0052-2009 01A>412000
NOSE INSTALALVMINACION FALTA PLANOS DE MONTAGE OE LUMINARIAS NTEROR YEXTEROR CBI
Glf9011olopez
JoMOiu.
CbnteRqat OAIQC 01:1
c-1-1...,...
S1eta,,Co,a1 P_,o,,d•lill•p se
......... cu1-z Jd3.luQ4,0l>,,.tC..in .J(¡
So,toPoo<:i¡ps � ...,o,oo-.,eiect""as
_,...,...,o,o-1n11"',._,'"°°"
.a.._..._,fl.t.00 POR:
,-.ot.l8RE ING EOSON ROl.-.NOO ROSIU.O �RRlllO
�00 INGENERO AREA ElECTR:ICIOAO C-'RGO GERENTE OE CONSTRUCCION
ECHA 01�..oo
etc)
respectivo.
• Colocar las restricciones por más menores que sean para que las áreas de
-
���-=·
--"'•�ero
r.::ir-.,. _,.,,.,..,.. ,,,,,.,...,.
PORCENTAJE DEL PLAN COMPLETAOO
1-
-·�>---
::�:�:
... 1 _,.01
n....,.o,
, ........
1�
�··
11�
.JI.·�·-:;=
_,... tto.11....
. .
8V9 8Aft 80•10048
..
,.
"
'n,.
-
J!.......L
.. .....
......
,.,, ....,
semana.
3 .4 REPORTE DE AVANCE
ltom /
Código DESCRIPTION
QTY UNIT
- .
r. r:7 1.
PAMPA MELCHORITA PERU
E ELECTRICAL
E1 TRENCH INSTALLATION
E1.1 Electrical Cab\o Trenches M3
E.2 CABLE RACKING ANO TRAY metre
E.3 CONDUIT ANO MISCELLANEOUS FITTINGS ANO SUPPORTS
EJ.1 Conduít metra
E3.2 Mlscello.neous Fittings and Supports metra
EB INSTALLATION OF EQUIPMENT
ES.1 lnstallatlon of Equipment at/ln IBuildings metra
E8.2 lnstallation of Equipmont In Fiold Area.s metre
E11 TESTING
E11.1 TESTING of Equipment lnstalled by Othors each
E11.2 TEST DOSSIER Glb
E12 AS BUILDING Glb
ltem /
-.
Código DESCRIPTION
í-
UNIT
1 INSTRUMENT ATION
0.1 CABLES
0.1.1 INSTRUMENT CABLE TRENCHES M3
0.1.2 CABLE TRAY/LADDER RACK Metre
0.1.3 CABLE LAYlNG In TRENCHES Metra
0.1.4 CABLE LAYlNG on LADDER RACK/TRAY Metra
0.1.5 CABLE TERMINATION Each End
0.4 TESTING
0.4.1 CABLE INSPECTION AND TESTING Eech
0.4.2 CALIBRATION of FIELO INSTRUMENTS lnstallod by Subcontrector Eech
0.4.3 CALIBRATION of FIELD INSTRUMENTS not lnstalled by Subcontrador Each
05 TEST DOSSIER
05.5 TEST DOSSIER LS
06 A,,.BUILTS
06.1 As-BUILTS LS
ltem /
Código DESCRIPTION
QTY UNIT
F r- 1• [•
PAMPA MELCHORITA PERU
T TELECOMMUNICATIONS
Para ilustrar como se venían haciendo los controles de avance de las diferentes
LUMINAIRES
To 25/05/09
By GyM 1620 Technlcal Offlce
Data íield
LOO
E.4,1.1 157883·00-El·l Y·1001 LOO
4.00
E.4.2.1 230 El-2550-02-01 EFLF02 212 157883-230-EL-LY-4432 LOO 1.00
E.4.2.1 200 230 EL-25S0-01·01 EFLF02 212 157883·230-El·lY-4432 LOO LOO
E.4.2.1 200 230 EL-2550-01·03 EFLF02 212 157883· 230-EL-l Y -4432 LOO LOO
E.4.2.1 200 230 El-2550-01-02 EFLF02 212 157883-230-El-LY-4432 LOO LOO
E.4.2.1 200 230 EL-2550-02-02 EFLF02 212 157883-230-EL-lY-4432 1.00 LOO
Total E.4.2.1 5.00 5.00
E.4.2.S 200 230 EL-255 0-03-01 EFWG02 207 157883-230-El-LY-4432 1.00 LOO
E.4.2.5 200 230 EL-2550-01-01 EFWG02 207 157883-230-El-LY-4432 LOO LOO
E.4.2.S 200 230 El-2520-01-02 EFWGOl 209 157883-230-El-lY-4433 LOO 1.00
E.4.2.5 200 230 EL-2520-02-02 EFWGOl 209 157883·23(}.EL-lY -4433 LOO LOO
E.4.2.S 200 230 El-2520-03-01 EFWGOl 209 157883-230-EL· LY-4433 LOO LOO
E.4.2.5 200 230 EL-2520-03-02 EFWGOl 209 157883--230-El-lY-4433 LOO LOO
E.4.2.S 200 230 El-2550-01-06 EFWG02 207 157883-230-El-LY-4433 LOO LOO
E.4.2.S 200 230 El-2550-02-06 EFWG02 207 157883-230-EL-LY-4433 LOO LOO
E.4.2.5 200 230 EL-2550-02-� EFWG02 207 1S7883· 230-El-LY-4433 LOO LOO
E.4.2.5 200 240 El• 2550-04-01 EFWG02 207 157883-240-EL-LY-4438 LOO LOO
E.4.2.5 200 240 El-2550-06-01 EFWG02 207 1S7883-240-El-lY -4 438 LOO 1.00
E.4.2.S 200 250 EL-2520-04·03 EFWGOl 209 157883· 250-El·lY-4440 LOO LOO
E.4.2.S 200 250 EL-2520-04·02 EFWGOl 209 157883·250-El· L Y -4440 LOO LOO
E.4.2.5 200 250 El-2550-14-02 EFWG02 209 157883-250-El-LY-4440 LOO LOO
Total E.4.2.5 14.00 14.00
O 50
4.16kV/0.48kV Transformar, Substation HXlOA 50% O 50
Total EB.1.1 1.50
ES.1.2 TR 130 TR-1004A 2000kVA 13.BkV/0.48kV Transformar, Substalion 10008 10008 Und 50% O 50
EB.1.2 TR 130 TR-10048 2000kVA 13.8kV/0.48kV Transformar, Subslation 10008 10008 Und 50% o.so
ES.1.2 TR 130 TR-1005A 2000kVA 13.8kV/0.48kV Transforme,, Substetlon 10008 10008 Und 50% O.SO
ES.1.2 TR 130 TR-10058 2000kVA 13.BkV /0.48kV Transformar, Subslation 10008 10008 Und 50% O 50
EB.1.2 TR 130 TR-1006A 2000kVA 13.8kV/0.48kV Transformar, Substation 10008 10008 Und 50% O 50
EB.1.2 TR 130 TR-10068 2000kVA 13.8kV/0.48kV Transformar, Subslation 10008 10008 Und 50% O 50
EB.1.2 TR 220 TR-4001A 2000kVA 13.8kV/.48kV Transformar, Substation 4000 4000 Und 50% O 50
EB.1.2 TR 220 TR-40018 2000kVA 13.8kV/.48kV Transforme,. Substation 4000 4000 Und 50% O 50
EB.1.2 TR 220 TR-1001A 2000kVA 13.8kV/0.48kV Transformar. Substation 1000A 1000A Und 50% O 50
ES.1.2 TR 220 TR-10018 2000kVA 13.8kV/0.48kV Transformar. Substalion 1000A 1000A Und 50% O 50
ES.1.2 TR 220 TR-1002A 2000kVA 13.8kVI0.48kV Transformar. Substation 1000A 1000A Und 50% O 50
EB.1.2 TR 220 TR-10028 2000kVA 13.8kV/0.48kV Transformar. Subslation 1000A 1000A Und 50% O 50
EB.1 2 TR 220 TR-1003A 2000kVA 13.8kV/0.48kV Transformar, Subsletion 1000A 1000A Und 50% 0 50
ES.1.2 TR 220 TR-1003B 2000kVA 13.8kV/0.48kV Transformar. Substation 1000A 1000A Und 50% O 50
ES.U TRE 220 TRE-4001A 2000kVA 4. 16kV/0.48kV Transformar, Substation 4000 4000 Und 50% O 50
ES.1. 2 TRE 220 TRE-40018 2000kVA 4. 16kV/0.48kV Transformar, Substation 4000 4000 Und 50% O 50
Total EB.1.2 8.00
ES.1.3 TR 130 TR-1444A 2500kVA 13.8kV/0.48kV Transformar. Oafrost Gas Haatar 10008 Und 50% O 50
EB.1.3 TR 130 TR-1444B 2500kVA 13.8kV/0.48kV Transformar, Oefrost Gas Heater 10008 Und 50 °/o O 50
Total EB.1.3 1.00
EB.1.4 TR 220 TR-4000A 7500 I 10500 kVA 13.BkV/4. 16kV Transformar, Substation 4000 4000 Und 50% O 50
EB.1.4 TR 220 TR-40008 7500 / 10500 kVA 13.8kV/4.16kV Transformar. Substation 4000 4000 Und 50% O 50
Total EB.1.4 1.00
ES.1.6 SG 220 SG-4100 3000A 13.SkV Switchboard. Substalion 4000 4000 Und 50% O 50
Total EB.1.6 o.so
ES.1.7 SG 220 SG-4000 2000A 4.16.kV Switchboard, Substalion 4000 4000 Und 50% O 50
Total EB.1.7 o.so
estas etapas un peso o porcentaje por cada etapa completada, obteniendo así
campo.
TOTAL PAYMENT(USD$)
100%
1,043,700.54
�
614,276.51
41.14%
429,424.03
�
ElECTRICAL 403 947.60 254 220.67 149 726.93
E.2 Bande'as 146 418.20 61 303.00 85 115.20
e.s UG CABLE 87,622.17 64,052.97 23.S69.20
E.6 AG CABLE -6,549.60 6.549 60
E.8 MAJOR EQUIPMENT 149 692.19 119 695.29 29,996.90
E.9 ELECTRICAL BULKS 10 716.65 7 650.44 3,066.21
E.10 CATHOOIC PROTECTION 4,ll6.40 4 116.40
E.11 TESTING 8S6.03 837.04 18.99
E.12 AS BUILDING 4,525.97 3,115.14 1.410.63
�
INSTRUMENTATIO N 76,867.61 48,019.30 28 848.31
0.1.3 CABLE LAYING in TRENCHES 20 1S8.18 13 174.87 6,983 30
0.1.4 CABLE LAYING on LADDER RACK/TRAY 4,672.77 1,481.94 3,190.83
0.2.2 lnstallatlon of Junction Boxes and Sunnorts 48,972.50 32,380.30 16, 592.:!0
0.4.1 CABLE INSPECTION ANO TESTING 2 14S.70 645.20 1,500.SO
0.5 As-BUILTS 918.47 337.00 581.48
9.26 •
CJVIL 246 349.19 121 349.66 124 999.53
E.l ELECTRICAL TRENCH 181 370.77 80 539.70 100.831.07
0.1 INSTRUMENTTRENCH 64,978.41 40,809.96 :!4,168.-lS
1ir;�¡1�
l..........�.... ..·...... . ...!
..._____.
Generación de
tareos
Pago a personal
IPde MO
..
..._
Control de Costos......
,.
• Los Capataces encargados de llenar los tareos diarios, no tenían claro las
llenarán de manera correcta los partes diarios, asignando los códigos de las
Del informe de productividad de finales del mes de Febrero del 2009, que se muestra
.;.a..-----�
Proyecto: 1820- Pampa Melchorib E&I
a Influyentes1 Todas
!:::� : 1:;::!e
... .... . . . .
--
ACUMULADO TOTAL
. . -
e1o•,1:· , ,,. • • 1111 • ..
TOTAL TOTAL- RfAI. TOTA[
>-J CÓDIGO
ACUMUl!ADO \tACIMU..AOO ACUMI.UDO AC\.Nll.AOO ACLMll.AOO PRO'IB:TADOPARA B. ACUMI.UDO
� PARTll)\8 DE CQNTfl)l. lN) PREVISTO A PREVISTO A META Lt.TIMA P�ISTOA ÚlTIMA satANA
e- EJS:llT�
RfAI. REAL
COH!IUMIR
PREVISTO �L
,, RfAI. SAl.[)O REAL
ANOEOBRA
M110..1 Excawci6n con equipo m3 41,263.31 17.013.45 25.E52.n 10.329.60 13,124.64 0.607 0.771 0.965 0.586 .2.795 04 -2 271 66 -49069
� 41%
w M110-2 Excavación manual m3 4,584.81 2.752.11 60% 20,m:12 12,108:43 13,121.40 4400 4.788 7.649 4.400 ·1.012 97 ·1.012 97 -1.466 90
.....
.....
M115
M116
Relleno
Relleno /Cama de Arenal
m3
m3
30.823.66
16.063.07
8.670.00
7.068.47
28% -
44%
56,872.65
30,037.96
15,1.72.51
1s:21e;04
17,039.00
17.612.03
1.750
1.870
1.965
2.492
6.655
5.808 _
-
1.750
1..770
·1.866 49
-4.393 99
·1.f..66 J9
.3 493 63
-598 10
_, 353 97
M117 Concreto ro10 m3 1,788.70 395.69 22¾ 5,755:ee 1,286.19 "1,241.05 3.200 3.136 4.230 s:200 25.14 25.14 ·1072
Concreto y Pedestales y
M118 fundaciones �ne. encofrado y m3
acoro)
M119 Eliminación de material m3 45.648.12 24.219.69 93% 5; 5.93.47 2,954.60 6,9.TT.80 0.122 0.268 0.439 0.122 -4.023 00 -4.023 00 -755 J5
a. 10M125 •
M135 •
Tendido de Cables • Cables
mi 377.140.05 198.919.03 53% 101,760.92 53,8n.88 56,311.75 0.270 0.283 1.322 0.250 -2.636.89 893.92 -4.006.60
(1)
enterrados • Megado de Cables
M430
'"1
-
o 10M140 Conexionados wrios uad 10.329.00 23,657.17 12.00 2290 2290 -12 00 -12 00 -2 00
a. - -
i::
n 10M145 Bandejas mi 51.042.00 5,619.51 11%[ 206,720.10 22759.02 21,232.00 4.050 3.778 1.509 4.050 1.527.02 1.527.02 651.40
o. Artefactos y Dispositi\Os
< M150
(fvlienores)
uad 7,298.00 7.00 0% 23:072.30 22.13
-
190,00 3.161 27.143 2.857 3.181 -167 87 -167 87 2.13
a. M155 EQuipos (MaYores) uad 1,500.00 0.45 0% � 81'.232:20 18.37 442.222 ..ieo 63
� 499.00 40.821 1,108.889 40.82·1
-
48063 -18063
a. lnstalacion de Proteccion
M160
Catodica
Pre emsamblaje yMontaje
uad 544.00 0.50 0%
-- 3;837.10 3.34 n.oo 6.686 154.000 154.000 8.688 .73 66 -73 66 .73 66
10M170 k9 74,861.60 570.09 1'/o 17,218-17 1'31.12 3,543.50 0.230 8.216 5.292 0.230 -3.412.38 -3,412 38 -1,730.37
Soportes (bandejas Conduitsl
M175 Cable de Puesta anerra mi 57.800.00 15.816.95 9,536:64 -
� M180 Postes de ituminacion uad 627.00 4.00
27%
1%
34;650.54
5,"(30.78 36.56
1.0:323.0ll
- 649.00
0.603
Q, 140
0.653
162.250
0.795
51.000
0.600
9.1<10
-766 20
-612 44
-662 33
-<)12 44
-159 26
-113 72
N 20M120 Conduits mi 4,500.00 9,716.00 153.00 2159 2.159 -153 00 -15300
-..J
a. 20M125 •
Tendido de Cables • Cables
(1)
M,35+ mi 560.250.45 116.956.67 21% 151,188-25 31,557.58 33,79803 0.270 0.289 0.585 0.270 ·2.240.47 ·2.31910 -778.49
enterrados + M�gado de Cables
'T1 M430
(1)
proyecto.
• En las Obras Civiles, casi todas las partidas que presentaban HH.
• Por tal sentido se tenían que evaluar las causas de aquellas HH pérdidas para
poder tomar las acciones pertinentes a fin de tomar las medidas correctivas a
tiempo.
Para el proyecto se utilizó como línea base las HH totales del Presupuesto
incidencia del recurso humano está muy por encima de los equipos y materiales. A
continuación se muestra la curva "S" del proyecto en marzo del 2009 (mes 11 del
proyecto):
� �e: � �
00
9-;; 9-;;
o 00 00 00 00 00
A
V
"
A 1.200.00
1.000.00
A
e
J 8:,0.00
J
L
600 00
,
A
o
-Avance Planeado GW
<100.00
"
-Avance Ganado GW
200.00
.. -AvanceRealGW
• El índice de desempeño del Costo (CPI), que es la medida del valor del
nos muestra que si bien es cierto se inició con CPI> 1, es decir, que se tenía un
costo infe1ior con respecto al desempeño a la fecha, se notó que luego esto se
80
• Es decir, desde inicio del 2009, se observa que el proyecto mostraba un atraso
de lo debido, por lo que se tuvo que tomar acciones al respecto para poder
orden planificado, para dar como resultado el producto final: "El Proyecto".
Pero para poder ejecutar estos procesos es necesario realizar actividades de soporte
idóneo, etc. La producción por ende, está conformada por actividades tanto de
flujo.
dependencia que tiene un proceso en sus predecesores, y las condiciones difíciles que
muy complicados, o climas agresivos, aunque para el caso del proyecto en mención
el clima, y la ubicación fueron por el contrario factores que actuaron a favor del éxito
del proyecto.
Sin embargo para la ejecución del proyecto hubo otros factores, además de los
involucradas.
82
ahorro significativo.
cliente debido a cambios en el alcance del contrato que luego no querían ser
• Así mismo, a pesar que parezca algo trivial e irrelevante, fue que no se
durante la reunión.
CAPITULO4
ELECTROMECÁN1CAS
Para el caso de los reportes de avance, en reunión con los ingenieros de campo y en
avance para todas aquellas partidas que tenían varias etapas en su proceso de
cliente, lo que trajo consigo que al final de mes los porcentajes de avance estaban
A continuación se muestra los cuadros con los porcentajes de avances parciales para
INSTALLATION &
1()()',' 30% SUPPORT FA8RICATION 65%
FIXATION 1 5% IRELEASE BY QC 1 1 1 1 /AGREEO
...,
1
Unde,¡round cable 100',' 100% INSTALLATION & FIXATION AGREED
i:,,
O" E6 ABOVE GROUND CABLE
0..
(l)
IAbove Ground úble
"O
o C.ible Gl1n d .i nd Termi na1e 100% 100% INSTALLATION & FIXATION AGREEO
(l)
::,
E8 INSTALlATION OF EQUIPMENT
AVXILIARY
(l) lnsUll¡Uon of Equipme nt 1,t/in IB uild/n¡s 100% 50% INSTALLATION 40% 110% 1 TEST 1 1 1 1 1 AGREEO
EQUIPMENTS
o..
(l) E9 ELECTRICAL BULKS
i:,,
E9.19 ToE.9:23 SpHce :md S tress Rellevlrc o
f r Cable 100% "" PURCHASE ORDER &
T r.insoort
O',' SITE TRANSPORT 55%
INSTALLATION &
FIXATION
1 0',< RELEA.SE BY QC AGREEO
(l) E9.24ToE.9.27 Groundinll woni:.s (rod pit5, conaete, weldinll ) 100% 90% INSTALLATION & FIXATION 10',' RELEA.SE BV QC AGREED
V,
E.9.28 U1htnine Protec tion for Sut>-Stnions & LCR's 100'• 100'• INSTALLATION & FIXATION AGREED
tT1
o
(')
E9.29 ToE.9.3S Tracine worb 100'• 100'-' INSTALLATION & FIXATION AGREEO
5.
(')
E9.36 ToE.9.37 C�ble Cleaa 100',< 100',' INSTALLATION & FIXATION AGREED
o.. E9.38 ToE.9.40 Groundinll Bar1 100',' 100',' INSTALLATION & FIXATION AGREED
i:,,
o.. ElO CATHOOlC PROíECTKJN
E.10.1 ToE.10.4 Cathodic Protection 100% 90% FINISHEO 10'.4 RELEASE BV QC AGREEO
1 1
EU TESTING
INSJBWENTAJION
Cableler m lnalion 100% 1 190% 1:::: ��=t 1,,,.1 RE LEAS[ BYOC AGREED
T
OS As·BUILTS
ELECTRICAL LUMINAIRES
To 2S/'12/10
By GyM 1620 Tethnlcal Office
Oata field
9 414.00
1.00
1.00
,oo,. ,oo,.
l.00
,oo,. ,oo,.
El-4090-01-AB-16 EfRLOl 100% 1.00 1.00
El-4000-01-AB-19 EFRtOI
,oo,.
StreelS 100% 1.00 l.00
E.4.1.l
E.4.1.l
Streets
S11eets
Streets
H-4090-01 -BC-05
El-4090-01-BC-08
El-4090-01-BC-14
EFRLOl
EFRLOl
EFRLOl
157883-000-El-SK-9000- 61
157883-000-El-Sk-9000-61
IS7883-000-EL-SK-9000-61 '"""
100% '"""
100%
,oo,.
100%
100%
100%
1.00
l.00
1.00
1.00
1.00
1.00
TotalE.4.1.1
E.4.1.2 Streets
Streets
El-4090-01-AB-04 EFRLOl 157883-000-El-SIi:-9000-61 NA
NA
'"""
'""" 100%
113.00
1.00
113.00
1.00
,oo,.
E.4.1.1 [l-4090-01-AB-07 EfRlOl 15 7883-000-El-SK-9000-61 100% 1.00 1.00
NA
,oo,.
E.4.l.2 EL-4090-0l-A8-13 EfRLOl 1S788 J.OO().El•SK·9000·61 100% l.00 1.00
E.4.1.2 Streets EL-4090-01-A8-16 EFAlOt lS7883-00().[l. SK-9000-61 NA 100% 1.00 1.00
TotalE.4.Ll
E.4.2.S Ptoceu
P,oceu
El-1926-04-0J EFWGOl 1S7883- ll0-El-LY-4l 10
'"""
100% '""" ,oo,.
113.00
1.00
113.00
1.00
,oo,. ,oo,.
E.4.2.S El-1926-04-04 EFWGOl 157883-110-El-L Y- 4111 100% 100% 1.00 1.00
Proce-ss
,oo,.
E.4.2.S El-1926-04-05 EFWGOl 1S7883-llC>-El·lY·4110 100% 1.00 1.00
E.4.2.5 Proceu El-1926-04-06 EFWGOl lS7883- llO-El-LY- 4110 100% 100% J.00 1.00
P1oceu
,oo,.
E.4.2.S El-1926-04-07 EfWGOI lS7883- l 10-El·lY-4111 100" 100% 100% 1.00 1.00
f.4.2.S
E.4.2.S
TotalE.4.2.S
Process
Proceu
110 PlantAreaU htln
110 Pl,11ntAre.ill htin
E L -1926.04-08
El-1926-04-09
fFWGOl
EFWGOI
lS788.3• llO-El·lY·4lll
1S7883-ll0-Et-LY-4lll '""" ,oo,.
100% 100%
100%
1.00
l.00
1376.00 29.00
1.00
1.00
<105.00
INSTALLATION Of EQUIPMENT
Tol.S/02 /10
U>
u.u s..bu•tlon7601 UD
u.u SubiUtlon7601 UD
--
Sub•UtlonllCOO 4.161<V 0,3,SkVlondom,er Sub,titlonBOCI)
SubU•II SCDO 4 61,.V O.l8kVt,.nt/om,_, Sub•t•llon SOCI)
-
4.lt\liV O.l8kV lr•n•lom,e,. Subu•tlon 7001
......... .......
"""
lS7883-l].0Q•lY-0006 USlcV0.481iVTn,n1lor,...., Sut,u1tlonlOCD8 , ,
LOO
--
ts788J-UO.U•lY-0006 U.AV0.48kVTran1f01..-.., Sub�tu!on 10CD8
ts7!1U•ll00.•lY<0008 1l.lkV .48kVTran1l01,....,s..b,11tionl6CO LOO
ts711S)•l&O-n•lY«JO.!I 11.31<\1 .48kVTn,ndor,..,.,,S..0111tlonl6CO LOO LOO
.... ...
lS71l8)-22').Q-tY� u.av .48lVTn,n,fo,,,.., Sub1tnlon 1000-' LOO LOO
lS788)•220-El.-tH)00S Tll-10018 13.StV0.4.SkV ,,.,,..,10,nw, 5..t>netlon1000-' LOO
El.1.2
ts7SIU·226Q-lY-<1005
ts1&u-no-n-t•-<100s
ts78!U-2:ZOQ-lY-<1005
SubU&llonlom,.
Sub1t1tlon1om,.
111·1002" l3SllV0.48kVTn,r»fo,,...., Sut11tetlonlOOOA
1J.llV0.481<VTn,n,fo,,....,Sub111\/on IOCDA
U.8lV0.4811V Tts,ufo,,...., Subu.,tlon IOCDA
"'"'
'"" """'
,
LOO
LOO
LOO
{3.1.2
UO 8ulldln ts78&J-llOR-lY-0006
........
- ....º·"'
8ulldln 78!3- ]0-Q-lY-0006
SS-9000
o1all&...l.J ,oo
'°"
El.1.4
u.u �leld ts7118l•lll6El.•lY470S
U.L4 8ulldf lS71Dl•lll6n-tY-0008 LOO
Para el caso de los reportes de HH, se trabajó de manera intensiva con los capataces
los capataces son los encargados de llenar los partes diarios, por tal motivo ellos
87
gastadas en cada una de las actividades ejecutadas por su cuadrilla a cargo, de igual
del frente y la partida de la actividad en la que trabajaron los obreros, antes de ser
Técnica.
1 1
Q(MS.A. � -o
z
o !i'
-; FECHA
"' 3
05/10/2009
8� �j
Melchorita IE&I
Project 1620
.¡
PARTE DIARIO DE TRABAJO
:!:
¡¡ 1 r
:§ -�
.d 1 w[)(j Mil,ul VI ¡..jool
TIME SHEET � 8 o
� �
::¡: ::¡: !A
OlSCJPUti4.: EU:CTRICIDA D
�
s s � �
ÁREA: w
�·�$
t!t8o
�t
'tJ
e:
"'
:,
'tJ
:,
N
1
--;;-;--
NO CATRiORiA MANO DE OBRA • APELUOOS V NOl'tiRES 11011.AS OBSERVACIOJ\ES
.
' Awdante Hilario Mamani Quisoe >+< 10 10
7 AVl dante Minuel Ramos Conde >+< 10 10
>+<
, >+<
'º >+<
TOTAl.fS >+< 35 35
HM
HM
2
OBSERVAC!Or,.ES:
Area 190 - 5° Nivel, según planos: 157883-190-EL-LY-2120 Rev. O y 157883-190-EL-LY-2124 Rev. O Respectivamente
FASES ACTIVIOAOES
UNO ALCANCE
COOIGO OESCRIPCION CODGO OESCRIPCION
M010 Trabajos Adicionales Glb Incluye todos los trabajos no contempados en el presupueslo
M020 Topografía Glb Incluye los trabajos de trazo y replanteo para todos los frentes.
M030 Operadores de Equipo Pesado Glb Incluye las HH de los operadores de equipos pesados.
Suministro e instalación de conduits de 314� a 6. e/ accesorios
M120 C.Onduits ML
y soportes de aluminio y acero inoxidable
M125 Tendido de Cables de Fuerza ML Tendido de los cables de fuerza, cables de control y cables de
XX M135 Tendido de Cables Enterrados ML Tendido de los cables enlerrados. Electrico e lnstrumentacion
M175 Cable de Puesta aTierra ML Incluye Tendido de Cable soldadura cadwel y accesorio
M180 Postes de lluminacion Und Montaje de Poste de 10.5 ML de Concreto y acero galvanizado
Montaje de Soporte Frame e lnstn imenlos (Transporte Pre
M171 Montaje de Soportes FRAME E INTRUMENTOS Und
ensamblaje)
M210 Paneles de instrumentación und Instalación de los paneles, JB y Accesorio
M910 Mo\11izaci6n y Desmo\l'Ílización Glb Incluye las HH de transporte y mo\11ización del personal
M935 Oficina Tecnica Glb Incluye las HH de los Trabajos en Oficina Tecnica
Recolección
de
Información
obra, basada en la información proveniente de los reportes de avance, los cuales unas
vez definidos y aprobados los porcentajes de avances parciales por pa11e del cliente y
�\'orc:t:Nn.: _ _ ________ _
ADVA1'CEl'AYMe-t (1)1�.
L'"\"OICED,\Jt::: ---��==�----
l'�OIJTO: - --------- -
R'-'\.,eE
rom,1N1 tU \,V\1,\111.E
-'J'l'I.IC'\IIOS tl"-11 11..\11!)
cD•I!) 101),\TI,
..
ID•EI
,
:.o
,t/Jl'Ai\"l'T.,,Al"ME.NTOJ lf º,
A/Jl'AV<'EP,O:H.ESJ (:J.'"'
i,u.>1;.tVCEPABtDTfJ;.' J"
I.J/1• ."/J.OI
J"1,JH.1J
J11.J1!1J
J
S
S
'Ἴ..
.. ,, ••
J
J
J.JJA!JJ.lf
J:1,J1J7J
r�JJJ .,
.......,,.,,....
,
,
),476.}6,I 0 7 J J,P.:f:.�/1,H 4_.1()6_l.,1l(,) SI.OO!l.110 �= S•Y,Hb.61
4,l�Jj!6.0! J 1::,.:r.t.10 IJ,6\,0\7"7 S!.361_1�:, S\\,1.?0�1
El""'n."1\\,•U !.}i),I !:0 �0 J :.�J.:,J//0 S :"6,14ll<JO 1.!70.000,00 1'1,.12:l<i 10w. s=•.61� �"
IAMNll'led F...,Q..,.!Jdt•.»tT>ltU !.717,7�}7 J ,'lt07.MJJ7 S ��-176,71 1.�.8�61 Sl.<,117.�i<::ibi 10.0U', ,::.!1161
(91.111)
TOTAl SI$ 102 1!-0A0 $9'191.,1.11 61.711"'•
SI ln:nclit111
¡ra,rn.,I Ba."1n.alo......_-,. u:,J::SIJ 4�,JQ, ll SOLJ)li.:•
Trmch.,.1Mlnlrna,talo0fl011'G:to 11r.,u:,J·J :•.J6,J4 YK,.>s10,
lra,ffl...,1...i.....
.,. 1•1t,::r..1J S 17,<i;J?: 196.U!." IOO<r,
t..,:,1 o0!,'1779 S 90.7�4 ..\6 !>}),S!!.16
º"'"'
º"'"' e.,,1.;o.
a-.uo,.....
º"" f\a,bl11dro."10
-· . ,.
Periodo : To 3 lf'I Oclober 2000
TIHALnll>Dn'�UHD
,_
,_ �.. . ' r.
-.
----
....e AO...Ou.otr
�,,.,,.,....
-..o,tDJLl'.. O,f
-,....... mi..,._...._,_
a•
Como se menciono en el capitulo anterior, uno ele los problemas más comunes que se
presentó en el proyecto fue el cobro ele aquellos trabajos adicionales que no fueron
autorizados formalmente sino ele manera verbal por el cliente, en tal sentido se
implemento un formato para registrar aquellos trabajos o solicitudes ele cambio, tal
variaciones en el plazo.
ejecución.
alcance.
92
Ravision: A
Propo,ed Solution:
Estlmeted M111erlalo:
E,tlmated Con•umables:
Cliantsi Directiva:
\YORK CUMPIF.l'ED
(MANIIOIJR)
rr 1 oe;cru PTION OF WORK MEASUR.EMENT
:
MODE WITIIOlff RJ·MARK.S
SIGNJn
: JOTAL
SIGN
(MIi) tl,.·111)
·'":" tl',.1M) ,-
¡. ,-;-
1.1 4!2!.TI.Q!i.�LffiST IN I.EnERCOl-(iY>.-t-LOl67
u Cl-lANGEORDER HANDER IN
C'OR-009 A TEMl'ORARY l'OWl:H MISCl:U.ANEOUS WORKS TIMESIII:l�T 20.00 4,609.60 4,62'-J.(-.(l In l'ri.Jl!íCSS
C'OR-OIO MODIFICATIONS IN ·rRJ".NCII SI TIMESI-IEEf D.:ktcd
COR-O 13 REMOVING NIPl'U:S A ND RJ-J'LACE T!-101.t W!Tll STUB UPS FOR DP TlMESHEEl 494.SO -19 4.50 Fmishcd
COR-014 A OU(T BANKJNSTAUED(WITH Ln..USHD tJNITPRlCE
COR-0148 DUCT 81\NKTNSTAl.lLl){WITI-I ln.. USTl:D UNIT l'Rl('E Fuiishcd
COR-015A STUB UPS - UNIT PRJCE P0-JDING UNIT PRJCE
COR-016 CONCRETE FOUNDATION · UNJT PRJCE PDIDING UNIT PRICE
COR-020 EXCAYATION AND I EVEUNG OONEHAND flMESIIEEf 9,202.00 2,(,..12 .50 11.834.SO Wih Ouan1i1l-:. 10 !l.iard1 20U')
COR-021A rNSTAU.ATION OF C'ONDUíf 9.1131:DDEDAND REDAR FOR POWER IJGHTlNGCAHIE UNIT PRICE With Qu.antiil-S 10 Fchniary 200')
COR-022 NEOPRfNE INSTAU . ATION, DEFINITION WAS TllENCABI.E TRA YMOUNTING. l'lMESIIEl:.T 241400
COR-024 C/\IUETl:ST ADDITIONAL(INFIBJ)) TIME SIIEET IRX.00 188.00 Fa1ishcd
J ' _"'E RE ,NT_ERF_EREN·_ _,_<_TI_-:_w_,_n__
COR-026
�;�:!:��-�A�;,_, �-"-º_
T N_'º
"_N_T _ª_ir_A_'_,s_F_r_" _ A_ __ _ _, f-_
.. _•M_E_Sl-!E
_ _'E_sr_f-_,_.,_.oo-+--""-·OO+---''l()-·(l(l, _ '"-'-""-"-'"_''-'--------l
_
COR-027
:.�.¡�
GROUNOINGRODS WJTJIGl?ll,-1 COMPOIJND 1 {MESHEET -+-
l\:udiJ.1, l'ji..'C"t1lio11
COR-028 · � � ENCII � PRI ?, N A �,� � \ ON 180, Rll)Ull- : RBACKfU.l.AND RID.'.CAVATION Til\iESl-10:J' 4l,.OO ln Pnign:s,;;
COR-029 TRANSPOR T FOR E:1.Jt::TRICAL MAJOR IDUIPMENT(HWM WARE IIOUSE TO SS) UNIT PRlCE
COR-OJO FOUNDATIONS/\ RE RJDUlRJD FOR Vl�TICALCABLE TRA't'S IN SURST ATIONS TIME SHEET l'cndin• l'ii..--c11111111
COR-031 NAJLREl\-tOVAL Tll\.1ESIIIXT
COR-032 FORMS FOR RED CONCREfE POURID BYOTHERS TIMESJIEEJ'
COR-033 fRl:i-iCIIES MODll-lCATIONS FOR DWGSUl'ERS031Ell TIMESHEEf l\:ndiul! i:il,-..·utiarn
COR-034 C,l{QtJNDINGHARS SUl'l'LY IN¼)ICE l\:nJiu• cii.-c-11111111
T
COR-OH RBJ\X"TORS AND NIPPIJ.� SUl'l'LYFOR OOX UGII TNG IN'AllCE l\:ndin • �··"C\1tiam
T
COR-036 EDUJJ> MENTS RIDUJ:STED HYCB&:.I (M/\ N Uf ) TIMESllEEf l'cndiu, c�-c-utia,n
SUB TOTAL
la aceleración de los trabajos a pedido del cliente a mediados del 2009, y la negativa
orientada a buscar una relación productiva, eficiente y duradera con los clientes a
mutuos.
Proyecto y sus similares por parte del contratista, se consideraron las siguientes
Etapas:
95
ETAPA ACTIVIDADES
•
..
Explicación al Cliente de Objefr,os y Tecnología .
1 Pre - Taller
• Presentación de las organizaciones .
Planeamiento de la Reunión .
..
Presentación de los Equipos de cada organ1zac1ó
Desarrollo de Metas y Objetivos comunes .
2 Taller Inicial
Identificación de problemas actuales o futuros .
Seguimiento y
... Plan de acción y Compromiso de los Socios .
Seguimiento de lo5 Compromisos .
Evaluación del trabajo en Equipo .
.
3 Cierre
Reunión de Cierre .
del Taller
Feed Back del Cliente .
proye cto, donde en parte los acuerdos fueron los mostrados a continuación:
Monto del
Fecha Hito
HITO ACTNIDAD % Incentivo
fijada
US$
A Firma del Pcuerdo N/A N/A
B Finalización de la Construcción & Entrega de las "K sheets. 13/12/2009 8.33% $250.000
Finalización de la construcción&. Entrega de las "A" sheets.
c Culminación de los Loop Folders y eliminación de los ítems 20/12/2009 8.33% $250.000
restantes del punch list Apara el hito B.
Finalización de la construcción&. Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los ítems del
D 27/12/2009 8.33% $250,000
punch lis! Apara el hito C. Eliminación de los ítems restantes del
punch list AyB para el RFC de los subsistemas del hito B.
Finalización de la construcción&. Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los ítems del
E 03/01/2010 8.33% $250,000
punch lis! Apara el hito D. Eliminación de los ítems restantes de la
punch listpara el RFC de los subsistemas del hito C.
Finalización de la construcción&. Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los ítems del
F 10/01/2010 8.33 $250,000
punch list Apara el hito E. Eliminación de los ítems restantes del
punch list Apara el RFC de los subsistemas del hito D.
Finalización de la construcción& Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los ítems del
G 17/01/2010 8.33% $250,000
punch líst Apara el hito F. Eliminación de los ítems restantes del
punch list Apara el RFC de los subsistemas del hito E.
Finalización de la construcción& Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los items del
H 24/01/2010 8.33% $250,000
punch líst Apara el hito G. Eliminación de los ítems restantes del
punch listApara el RFC de los subsistemas del hito F.
Finalización de la construcción&. Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los ítems del
1 31/01/201 O 8.33% $250,000
punch lis! Apara el hito H. Eliminación de de los ítems restantes del
punch listApara el RFC de los subsistemas del hito G.
Finalización de la construcción& Entrega de las "A" sheets.
Culminación de los Loop Folders y eliminación de los ítems del
J 07/02/201 O 8.33% $250,000
punch list Apara el hito l. Eliminación de los ítems restantes del
punch listApara el RFC de los subsistemas del hito H.
Finalización de los Loop Folder y aclaración de de los ítems del Punch
K listApara el hito J. Eliminación de los items restantes para el RFC de 14/02/2010 8.33% $250,000
los subsistemas del hito l.
Finalización de los loop Folders& Eliminación de los items de la
L punch lis!Apara el hito K. Eliminación de los ítems restantes de la 21/02/201 O 8.33% $250,000
punch listpara RFC de los subsistemas del hito J.
Eliminación de los items pendientes de la punch listpara RFC de los
M 28/02/2010 8.33% $250,000
subsistemas del hito K& Logro de la finalización total.
Monto del Incentivo TOTAL por rendimiento S3'000,000
permite identificar las áreas que requieran mayor atención. Es en este sentido que el
todo el proyecto.
y actividades que requerían mayor atención y de donde las más resaltantes y las
esta manera poder cumplir con los plazos de tiempos es través de la correcta
programación de las actividades, es por este sentido que se dio un énfasis especial a
decir, de la primera semana del Look Ahead, estas no deben presentar ningún
Herramientas en mención:
., d '"" p ,_ .,
- CKA :01-04-09
� LOOKAHEAD
Pagiro: 1
. . .. .
00000�"'""º �'�'" NRO. REGISTRO
610 ..........., UCI cunRITA �IC"rfflf'l.·�'"'h""._
• : • t ••• • CUENTE UBICACION:
. '. CBI PMPA M:LCHORíl"A/CHNCHA- CAt":ETE
FECHA DE FECHA DE DlRACIÓN
>•-•A15 s 16 17 ANA18
RATIO RATIO
ARE.A OESCRIPCION D E LA ACTIVIDAD UNO
META PROPUESTO
NETRAOO INICIO TERMINO
(dlasj
V SIDIL M M J vis D L M MI J V s D L M MI J V I S I D I L M M J
PLNEAOA PLANEADA 03 04 1 05 1 06 07 08 1 00 10 I 11 12 13 14 15 l 15 17 18 19 20 21 22 1 23 24125126127 28 20 30
r
.._
HtwNO Hli'UNO
�,
ELECTRJCAL
- f _·
'7-
PONERDISTRIBUTION -,
220 SUBSTATI O N SS-4000 ";, - i
-;
MAINSWITCHGEAR
=�
220 TRANSFORMERTR-«IOOA, 10.5 WVA. 13.8-4.115 KV
-
e-
2lll SetUp Und 32.37 40.00 1.00 07·04·09 08-04-09 2 d 2 2
2lll A=iembly 113.30 120.00 2 2 2 2 2 2
--
Und 1.00 09-04-09 15-04-09 • d
�
<•
--
16-04-09 16-04-09
220 Testing Und 20.00 20.00 1.00 2
220 GROUNDING RESISTOR NR�0A
17-04-09 17-04-09 1 d
�
-
;;;i
--
2lll 2 2 2 2 2 2 2
O" 220
SetUp
Testirg
Und
Und
161.86
20.00
140.00
20.00
1.00
1.00
15-04-09 22-04-09 7 d
- '"' 2
¡;; 220 BUS BAR BD-'O00A
23·04-09 23-04-09 l d
-- - !
� 220 S1.pport Und 72,8'1 80.00 1.00 11-04-09 15-04-09 4 d 2 2 2 2 � J
\O 220 A�embly Und 89.02 100.00 1.00 16-04-09 21-04-09 5 d ,. 2 2 2 2 2 -
1 220 Testing Und 20.00 20.00 1.00 22-04-09 22-04-09 l d ...;, 2
t'"" 220 SWIT CHGEARSG-4000, ,, 10 KV ' l --
o
o 220 SetUp Und 48.56 60.00 1.00 03-04-09 06-04-09 3 d 2 2 - 2
-- �
;:,;--
.
220 A�embty Und 113.30 120.00 1.00 07-04-09 13-04-09 6 d 2 2 2 2 2 2 1
220 Testirg Und 20.00 20.00 1.00 14-04-09 14-04-09 l d 2
·-
::r
(1)
220
220
BUS A. 0A8 KV
-- -
220 1 ,.
60.00
Und 48.56 1.00 3 d 2
� 2 2
St.ppon 18-04-09 21-04-09
tl)
::i 220 Assembty Und 113.30 120.00 1.00 22-04-09 28-04-09 • d 2 2 2 2 2 2
tl)
(/) 220 Testirg Und 20.00 20.00 1.00 29-04-09 29-04-09 3 d ' ' 7'-"l 2
2lll SWITCHGEAR SG-4001, 0.4 KV
• :•
..1
t
:::,
•••
•
1620 PAMPA MELCHORITA
•
1 • •
OESCR1PClON DE LA ACTIVIDAD
••
CUENTE
UNO
I
':� �
RATIO
PROPUEST ME"TRAOO
FECHA DE
REG1smo
GESTION DE PROYECTOS
PROGRAMA SEMANAL
ELEClRO-MECANICA
FECHA DE
TERMINO
CBI
OUAACIÓN
V I S
SEMANA 15
O I L • • J
NO. REGISTRO
UBICACION
ANALISIS DE CUMPLIMIENTO
REVISION: 1
FECHA :01-04-09
Paglro:2
220
MAIN SWITCHGEAA
SWITCHGEAR S0-4100, 13.1 KV MAIN
-
220 Set Up Und 48.56 60.00 1.00 03-04-09 06-04-09 3 d 2 2 2
220 Assembty Und 113.30 120.00 o.so 07-04-09 09-04-09 3 d 2 2 2
220 BUS.A., 4,16 KV
-
O" 220 Assembty Und 113.30 119.76 0.17 2
09·04-09 10-04-09 1 d
¡I) 220 SWITCHGEAR SG-4000, 4,16 KV
.¡:. 220 Set Up Und 48.56 60.00 1.00 03-04-09 06-04-09 3 d 2 2 2
Assembly Und o.so 2 2 2
o 220
Eloolrical O lltrlbution Cable
11l.J0 120.00 07-04-09 09-04-09 3 d
'°'°
REGISTRO
1
GESTION DE PROYECTOS REVISION: 1
FECHA: 01-04-09
PORCENTACE DE PLAN CUMPLIDO {PPC)
Pagina: 2
NO. REGISTRO
1620 • P.AMPA MaCHORITA ElECTRO-MECANCA
• :• 1 • •• • CLIENTE UBICACION
--·-�" �-··r::,":;�
• 1 • ;: ' ,. ca, PAMPA MELCHORITA / CHNCHA • CAÑETE
..,n
o 220
220
lo&ting
GAOUNOING RESIST OR NR-1001.A.
Und 20.00 30.00 1.00 03-04-09 06-04--09 1 d
�
3 X
X
220 Und 3 3 - . 3
- 3 3
(1) SolUp 161.86 150.00 1.00 03-04-09 06·04-09 5 d
::i Toebng
220 Und 20.00 20.00 1.00 03·04-09 06-04-09 1 d 2 X
'"""''
220 BUS BAR 80-1001.A.
(1)
3 3 X
Und
-
220 72.84 60.00 1.00 03-04-09 06·04--09 2 d
a. AHembly Und 89.02 60.00 1.00 03·04-09 06-04--09 3 d 2 2 2 X
(1)
220 T011ing Und 20.00 30.00 1.00 03-04-09 06-04--09 1 d 3 X
'"e
220 SWITCHGEAR SG-1001, 0.43 KV
tll AH001bly
220 Und 113.30 116.67 0.60 03-04-09 06·04-09 3 d 2 2 3 X
n
::i
Tottino
220 Und 20.00 20.00 1.00 03-04-09 06-04-09 1 d ' 2 X EO Equipo de Prvobaa con lala Se 1epmg1Wnri acb"lldad a1 1oluc10na1 blla té<:n1ca
e
CANTIDAD DE OBREROS 10 10 10 10 10 10
1D 1
AHALISIS DE LA CONFIABILIDAD (EN¼)
01% 9%
o
PROG EflOf en la prognrnación, cambi01 en p,o¡r,rnaciál o mala ubbaoón de lat herramientas de
LOG Falta de rea.rr101 en obra (&QJipos mayoroe y menores. h&1Tarni&nta1. 1ubcoroatos y matDri�os
n
'"e ING Entmga inoporture de información (contrato. propueeloe. planos) ylo cambios en la iOJMi&ria 11.uante
EXT Retraso po, clima o por e\UIIOI extraodlflal\C9 (matcha. hoolgas) y po, bllade entrega de J*ffilt08 o
EO Awriat o lala• en �1po&
ADM No ingreeo de p&faonal &1pecializado
Cll.PER No ingreso de l)!lfSonal pa lalla de cupo en ..uelo aéreo
CLI.MAT No 1UT1initbtl de materialee por p]rte dol denle
Cll.PRI cambio rnpenlillo del clie-ll& ya 100 en ingMi«ta o rocbtñbuaón de loa rocun;os
CU.lNG Entraga noportur0 de 11/omación de lfl{18rueria
ACT PRE Reir.no en acthldadol pr&.iaa
o
o
-1 REGISTRO 1
Íill!lllllla:AREA
,__ 1
GESTION DE PROYECTOS 1 REVISION: 1
FECHA : 0Hl4-0Q
ANALISIS DE RESTRICCIONES
� Pagina: 4
. . ...
COOIGO PROYECTO I OPTO NO. REGISTRO
1620 · PAMPA ELECTRO-MECANK:A
:· CUENTE UBICACION
- . . ) CBI PAMPA MELCHORITA I CHINCHA· CAÑETE
FECHA REQUERIDA DE RESPONSABLE
FECHA INICIO OESCRIPC1ON DE LA RESTRJCCION LEVANTAMIENTO DE
AREA OESCRIPCION DE LA ACTIVIDAD
PERSONAL
PLANEADA AREA
RESTRICCIÓN
-
ti)
� 220 TRANSFORMER TR-4001A, 2 MVA, 13.8-0.43 KV
Falta accesorios (Someras. pernos. Lainas de Ni.elación. etc). Según listado
220 Assembly 14-abr 10-abr Logística -CBI DBR
N enviado xmail(01-04-09l
1 220 Oil Chart1i11<1 and Filteri11<1 21-abr Falta aceite entreaado porVendor 17-abr Looistica MR
� 'Elecll:lcal.D.lstdllu.tion.C.lible
:l. 220 200 Rina Groundina Svstem
(")
(") 220 Area 220 Rina
o 220
220
Groundi11<1 Line220 - GL- 04
Groundi11<1 Line220 - GL- 05
14-abr
18-abr
Falta liberación de zania oor oarte de calidad CBI
Falta liberación de zania oor Darte de calidad CBI
12-abr
16-abr
Control de Calidad -CBI
Control de Calidad -CBI
PS
PS
::i
(1)
<Jl
LEYENDA DE RESPONSABLES
Jose ZoDa lZ Gerente de Construcción
José Zavaleta lZA Oiclna Técnica
Martin Rodriauez MR logistica
Daniel Berrocal DB Control de Calidad
Jimmy Maguiña JM Equipos
Marco Ca macho MC Administración I Persooal
Renil Rojas RJ lngenierla · CBI
Oann\l Bra\lO DBR logistica • CBl
Pablo Castillo PC Equipos· CBI
Petar Smith PS Control de Calidad - CBI
o
102
todo el tiempo que duro el proyecto. En tal sentido se enfocó en reducir los tiempos
improductivos (esperas, viajes con las manos vacías, tiempos ociosos, etc.), las
Es por eso que durante las reuniones Semanales de Producción donde se analiza el
informe de Productividad (IP), se encontró a mediados del mes de febrero del 2009,
Para lo cual se hizo el análisis de una cuadrilla de la especialidad eléctrica, las cuales
• Número de Personas: 32
• Turno: Día
...,
MEDICIONES DE CUADRILLA PARA CARTA BALANCE Claslflcaclón del Racurso:
.,.
Origw ..._1<1oddo doCo p0Nt8dodo únado c>.do de C dooo Co pmnam peinad>do de údo09 Ooo do (madod)lfladodo peinad:) peNódode C.dodo O.dode Cdo de Cdo do CdodaCadodaCdodo Ckk> de CJ'do de(n:jo doOidodeOidodo Oidodo Oidodecabl&
.,,
-. -.
e Op1 (1,2 OpJ Op4 Ol1 º"
OIJ 0!41 0!5 016 ! 017 018 Ay1 Ay2 Ay'J Ay5 Ay6 Ay7 Ay8 Ay10 I Ay11 1 Ay\2 Ayl3 Ay14 Ay15 Ay16 Ayl7 Ay18 Ay19 08SERVAOO>ES Acti\4dad
¡:,:,
A A A H uA A A A ! H I H u u A A A A A A A A A I A I A A A A A A A A
,· -,.-
O" 1 C
A A H A A A A H ¡ H A D D A A A A A A A ' A- A A A A A A A A e Dirigir
¡:,:, ,,-e o·
2 c D
A A
D
D A A A A A ! A u u A A A A
A
A A -¡:-
-A
A A A A A A A Op1 Oesbobinado de cable
� 4 c D A A A D A A A A A i A A D D A A A A A A A A A A c c e e c c e Op2 Jalado da Cable
...... 5 �
i5·· 8 -ci
o 8 G A D e e A " 1 A Ae u _u " A C C C C C C C C C C C C C C C Op3 Acomodo o peinado da cable
l,.) B G A D c e A G A ! A e D D A G e e e c e e e e e e e e e e c Op4 Meaado de Cable
1e D B G A D e e e e A I A F D o e e e e e e e e e e F F F F F F F 011 Oesbobinado decable
1
e e e e e e '
n
¡:,:,
8
·g-c-
10 e
-· D
o
o
B
B
B
G
G
G
A
A
A
D
o
o
e
e
e
e
e
e
e
e e
C i A !
A ! A
A I A
A
F
F
Fe
o
D
D
D
D
o
c. e
e e
e
e
c
e
e
c
e
e
e
e
e
e
e
e
e
e
e
.
e
e
e
e
e
F
F
F B
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
012
OPJ
014
Jalado de Cable
Jalado de Cable
Acomodo o peinado da cable
;:¡_ e D B G e o E E e e e I e F o o e e E E E E E E E E A F F F F F F 016 Acomodo o peinado da cable
-o
11
¡:,:,
12--A B G e D E E G G e e F D D G G E E E E E E E E F F F F F F F 018 Mogado de Cable
o; 13 e
14 e
D
D
E
E
G
G
e
e
o
D
E
E
E
E
G
G
G
G
e I e
e I c F
o
D
o
D
G
G
G
G
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
F
F
F
F
F
F
F
F
F
F
F
F
F
F
017
018
Megado de Cable
Tendido de Cable
¡:,:,
¡:,:,
15 e e E G e e E E G G e I e F e e G G E E E E E E E E F B F F F F F Ay1 Oesbobinado de cable
16 e o E G e o E E G G e I e F D D G G E E E E E E E E F F F F F F F Ay2 Dei.bobinado decable
::i
17 e D E G A o E E G G ! A l A F o D G G E E E E E E E E F F F F F F F Ay'J k::omodo o peinado decable
-.-
(")
(1) 18 B D E G A D E E G G A A F D o G G E E E E E E E E A F F F F F F Ay4 Acomodo o peinado da cable
¡:,:, ,·o� o" E G A D E E G G A e-¡; D D G G E E E E E E E E F F F F A F F Ay5 Jalado da Cable
o..
¡:,:,
23 e
" e
o
o
T"
E
E
G
G H
H o
D
E
E E
E
E
G
G
G
G
G I H
H H
H
F
F
D
D
D
o
D
G
G
G
G
G
G
E
E
E
E
E
E
E
E
E E
E
E
E
E
E
E
E
E
�E
E , E
E I E
F
F
F --
F
F
A
F
F
F
F
F
B
F
F
F
F
A
B
F
F
F
.,.
Ay8
Ay10
Jalado de Cable
Jalado de Cable
Jalado de Cable
-¡r e-
::i .
T5-¿- '""o°"'
'-g- "i; H D E- 'E-
.G G I H H F o o .E E E E E E ! E F F F F F F F Ay11 Jalado de Cable
.
7;-
·H+
¡:,:, 26 c D E G H D E E G G I H H F D o G G E E E E E E E I E F F F F F F F Ay12 Jalado de Cable
o.. 27 B
·i'e ·-e ,C A E G H A E- E G
E- 1-É- 7;¡-G
-
H .-- ""T
H F A A G G E E E E E E E I E F F F F F F F Ay13 Tendido de Cable
(1)
29 e
30 e
A
A
E
E
E
G
G
G
H
H
H
A
A
A
t
A A
e
c I e
l; . t1 • t1
H
'
H
H
F
1-¡¡- -A
A
A
A
A
G
C
e
G
C
e
E
t
A
E
t
A
E
t
A
E
t
A
E
t
A
E
t
A
E I E
t ' t
A I A
' F
F
"
F
F
' ' ' ' '
F
F
F
F
F
F
F
F
F
F
Ay10
Ay\1
Jalado de Cable
Jalado de Cable
(1)
Ay12 Jalado de Cable
31 1 1 Ay13 Tendido de Cable
o..
::i
o..
o A 1
3
5 4
8
4 ,. 4 5 5 6 4
1!.
"1
'.
" 4 4 4 6 4
1
5 5 5 5 51 51 51
'.
5 5 4 3 3
1
4 4 3
TOTAL
168
Oaslflcaclón del Trabajo:
1 - 1 • 3 1 16
o..
B
e 26 2 6 2 6 6 7 7. 6I 6 2 2 2 7 7 6 6 6 6 61 6' 6 6 3 3 3 3 3 3 3 183 §A T<a..,,Ok>coo,i,ulo<o
(1) D • 1 • 24 ' - 1 •
n
¿J . 24 24 95 8 /lb0$1apreaente
E 18 19 19 . ! . 19 19 19 19 19 i 19 ! 19 19 208 C Trat>a,ocontrbulorio
¡:,:, F . ! - 24 • 1 • 1 • 22 20 24 23 23 22 24 182
O" G 26 17 181 1. 17 18 00 TrabaJo Producuw
(1) 10 10' 10 • 1 • 1 • JO
TT JO JO 30 30 30 JO JO JO JO 301 30. 30 JO JO JO 30 30 30 JO JO 30 30 I 30 30 30 30 30 JO 30 30 'º JO 00:,
�-�--�-
E JabdodeClblo
F T ena1do de cablo
G Acorrodoopoinadodecable
H Migadode C3blo
1
J
o
w
104
25%
Gráfico de Distribución del Tiempo
21%
3%
2%
Trah,1j,, tJn No t"�T a Traba.o í)p�bnhinarln 1,1l;1<1n rlP TPnr.lrln ;lp .\rnmorln n MPgM1n rl,
contr bu torio presente contributorio de cal:le Cable Cabe oeinado de Cable
cable
tiempo fue:
frentes.
Por lo que se tomó la decisión de crear una cuadrilla exclusiva para megado
destinado para esa función, por lo que llevando una coordinación adecuada de
• De tal forma la cuadrilla de tendido de cables se acordó que debería ser entre
al tema de la rutina y reuniones de programación, ya que este tema también era vital
entre las diferentes disciplina. Entre las principales medidas adoptadas fueron:
• En primer lugar fue la habilitación de una sala más amplia que pudiera
---·
RUTINA DE REUNIONES - MELCHORITA E&I
- -··
HORA LJfiES .JUe\/ES 'J'ERHES SAB/00 OOf,UIGO
T:00-8:00
!nvioJe las
lleffllmknta1do 1!'"'10 del •et• ff .. l!n'ilo a prodllCldMI dd
...111... ,..
t---------< ��at,�Jj:'IL � ... ,.u,
Plane.an'-1to
IJl!S1'1 ffRI.Hl'l!I DE "'"''
•••� ru..1.N a.ate kebf"J ')lu,Ar, CAS,.L-U•
VUA
-
PIODUC.ClÓN
·�-·
SISPOa OJ.
Rf:SPl:JOSf ,,......_.elmetertel
.....
10:00-11:00
l.AVALl!l,lt,/SllPO ir:,aralllla-,nl6.
&.manal ch Obra�
11:00· 12:CO ...u.a.. .._,_...._,..,_ ..._ lavfor ... an90Nacb AC:H'r JUAN ..cARlOI
MOOUCOONB.AIICftA FROOUCCIOH aD.BOf;A
>-----< HEIVWIIBITAS llf -·- 1--------t---------1 HEARAHlfH'Tt.S DE
?ffllQIAM>aOIIANll/8. lítts�1•11t 11r�o� P.'IO�A,..\'=l.
IU.... lUA'iCAUOt
12:00-1:ot DE SURRVIIOR Y pac,,oucaóJrt.
VnA DE SUPEfMSOR Y
llFERDITB«>fNT: SU'ERINiENDENTE
PAOOUCCION ELA80RA
1ERRAIIIENTAS DE
2.-00-3:00 Rl!.\JNIÓN Sl!MAN.A.L Dl Al.UNIÓN Sl!MA...J\l oe PROGftAIIACONA.NIVB.
lNTl!GllACIÓN DI!
PROGRAMACIÓN --------l ..... ut: :SLWt:tG'laUlt T
IUPEUITTNllEJITE
((ONffRUtCIÓN) ,(A<ó)
3:00-4..-00
Fla
l11ldo
RESULTADOS
5. 1. 1 Reporte de avance
Debido a las medidas correctivas tomadas en este caso se obtuvo como resultado:
94.14%
SUB TOTAL DIRECT COST 801,426.23 754,500.17 35,826.79
PARTIDA GYM CB&I DIFFERENCES
E.2 CABLETRAYS
ELECTRICAL 449 447.90
145,506.08
422 -�
145,380.16
19,888.58
125.92
E.3 CONOUIT ANO MISCELLANEOUS FITTINGS ANO SUPPORT5 S S52.69 5 552.69
E.4 ELECTRICAL LUMJNAIRES 10 509.52 10 323.02 186 50
E.S UGCABLE 50,018.20 47,804.46 ::?. 213.75
E.6 AG CABLE 128 013.59 115 505.00 12 508. 59
E.7 CABLEGLANOANO TERMINATE 34 096.13 32 928.89 1 167 24
E.8 MAJOR EQUIPMENT 46,000.74 44,385.26 1,615.48
E.9 ELECTRICAL BULKS 20 919.44 18 996.65 1,922.78
E.10 CATHOOIC PROTECTION 836.77
E.11 TESTING 2,140.95 1,992.63 148.32
Ell.2 TEST DOSSIER
E.U AS BUILDING 5,853.79
../ Como se aprecia en el gráfico siguiente se logró ir acortando las brechas entre
ambas partes.
que se generaron.
../ Así mismo debido a llevo se pudo incrementar el monto del presupuesto con
contrato inicial.
32,000
Curva "S" de Valorización
30,000 : ! 1 ,. 2a,J�
t l a 29, oJ �.;75Q
756
¡!8,09l ,..-2
28,000 - 'I! !; ' ZJ QOJ �¡__.--� ,8f!2 AV...,, ·E mt\'/SIO
¡
:zs, 1129 V1
• ·[
1
26,000 �---+--f---+--+'--+--+.'-;-- -'i---+----+-+--+-l -+ r9 --
-+--, -+---+-
l +--í - , 1 --+--+.r------P,.,t-·'ª'w.
.
, -�. t-
· + _
24,000 - -. f _J_ I
I
�- [ 24:T/
,.\ .!!·f1
..---
22,000 1 �,BJ6
1,
z _...,
e i -- -
f i V --
-1- 1J!,�7 !_/
--V· 1J1
20,000
e
18,000
- -- 1
1
t
1
16,783 1 A
1
/
! 14,t09 1/ ! [/111:m
16,000
- --4·
--·- 1 1 - 12,��J¿_ --- --�
- +-
z 14,000
10,000 1 L I AVJNCERe,\L
1 /
8,000
6,000
4 000
2,000
Se alcanzó:
..
PPC
1\.6 SEMI\NA SEMI\.NAL ACUM..v.00 SEMI\NAL ACLM.LAOO PPCSemanal PPCMota
Acum.Aado
Sem35 29 20 14 14 48% 48% 80%
l
Se1Tl36 21 50 11 25 52% 50¾ 80%
..
Sem37 45 05 28 53 62% 56% 80%
Sem38 51 146 24 77 47% 53% 80%
Sem3Q 62 206 38 115 61% ss•1. 80%
Sem40 86 204 34 140 40% 51-Jo 80¾
Sem41 362 30 170 44% 4Q% eo•1.
Sem42 77 430 40 210 52% 50•1. 80%
Sem43 91 530 43 262 47% 49% 80%
Sem44 53 563 31 203 58% so•1. 80%
Sem45 72 655 47 340 65 º/, 52°/, 80%
g Sem46
Sem47
85
81
740
821
51
38
301
420
60°/o
47%
53o/,
52¾
80%
80%
Sem48 82 003 60 480 73¾ 54% 80¾
� Sem4Q
Sem50
123
98
1026
1124
70
64
550
623
57%
65%
54°/o
551/o
80%
80%
,1! Sem51 74 1198 52 675 10•1. 56% 80%
Sem52 63 1261 44 710 70% 57% 60%
Sem1 37 1208 25 744 68% 57 º/, 80%
g
t
Sem2 65 1363 32 776 49% 57º1. 80%
Sem3 65 1428 30 806 46% 56°/, 80%
Sem4 64 1402 43 640 67º/, 57 °/, 80%
Sem5 74 1588 46 607 65% 57% 80%
g Sem6 49 1615 32 020 65% 58% 80%
Sem7 82 1607 53 082 65% 58'/, 80%
Sem6 71 1 768 56 1038 79'1, SOo/, 80¾
SemO 43 1811 32 1070 74% 50°/, 801/o
9 Sem10 157 1988 95 1165 81% 50°/o 80%
� Sem11
Sem12
139
179
2107
2266 116
99 1264
1380
71%
65%
60%
60%
80%
80%
Sem13 172 2458 120 1500 10•1. 61% 80%
�
Sem15 195 2987 118 1775 61% 611/, 80%
Sem16 192 3070 143 1918 74% 621/o 80%
Sem17 236 3315 165 2083 70% 63'1. 80%
1e
Sem18 109 3424 77 2160 71% 63% 80%
Sem19 262 3666 175 2335 67% 63 °/o 80%
Sem20 277 3063 186 2521 67% 64% 80%
Sem21 292 4255 166 :687 57% 63% 80%
Sem22 63 4318 37 2724 W¾ 63% 80%
g Sem23 82 4400 49 2773 60º/, 63°/, 80¾
·"' Sem24
Sem25
103
308
4503
4611 193
63 2836
3020
61º/,
63%
631/,
63%
80%
80%
Sem26 148 4959 101 3130 68% 63% 80%
g Sem27 3 .. 5327 211 3341 57% 63% 80%
1 Sem28 645
2 ..
5072
6240
350
197
3601
3888
54¾
74%
62%
82'/o
80%
80%
Sem29
Sem30 301 6541 207 4095 00¾ 53% 80%
�
Sem32 187 8082 121 4370 65% 63% 80%
Sem33 173 7155 116 4486 67% 63% 80%
Sem34 163 7318 121 4607 74% 63% 80¾
Sem35 161 7479 112 4710 70% 63°/, 80%
Sem36 185 7664 139 4858 75% 63º/, 80¾
� Sem37
Sem38
136
239
7800
6030
101
199
4050
5158
74%
83%
64%
64 º/,
80¾
80%
Sem30 192 8231 159 5317 83% 65'/o 80%
Sem40 243 8474 193 5510 79¾ 651/, 80%
Sem41 189 8663 146 5656 77¾ 65% 80%
Sem42 211 6874 169 5825 80'/o 86'/o 80%
Sem43 202 0076 1 .. 5903 83% 66% 80%
6174 66'1, 80%
�
Sem44 221 0207 181 82%
Sem45 251 0546 220 6304 88% 67% 80%
g Sem46 256 0804 227 6621 89% 68% 80'/o
Sem47 245 10049 204 6825 83% e8•;, 80%
Sem48 266 10315 231 7056 87% 68% 80%
••
Sem52 205 11226 177 7858 86% 70% 80%
Sem1 177 11403 157 8015 80¾ 70% 80%
o 71 º/, 80%
Sem2 197 11600 179 8104 91%
Sem3 231 11831 194 8388 84% 71% 80%
Sem4 234 12065 182 8570 78% 11•1, 80%
Sem5 188 12253 185 8755 98% 71 º/4 80%
o
i
Sem6 221 12474 191 8046 86'/, 72'/4 80%
Sem7 204 12678 189 9135 93% 72% 80%
Sem8 216 12894 163 9298 75% 72% 80%
Todas 1
IN)
TOTA&:.Pfl!'IISTO-A
ACUMII.ADOBL
..., ..,.
·1.ACLllll.l.00 TOTAi.PtEVISl'OA A<LIIUWIO
ACUllu..ADOfBI.
.
PRMCTADO
REALSIMAJraL
..,.
<óaoo PAR110UDECON111ll
iillCUTAR C<NIJ!!II PMVIÍTO MM ILU.LDO
>-l 10M120 Ccnduil1 4,Hi6,00 4,071.00 8,971.11 8.789.74 3,81 4.50 0.94 0.56 185.78
¡i) mi 216
10M125 • Tond,do deCablot • Cable, ont«rado, • M&gado
..
O"
M135 • M-iX> doCablOII
mi 611,768.40 678,827.03 206,162.58: 195.064.71 219.565.39 0.34 0.38 º·"' 0,45 -165!<!
Pi" º·"'
10M137 P,otocciondoC.:iblol
"""
mi 3oo.m.09 XKJ,m.oo
"""
100% 60,617,131 60,817.13
,.,... 60.817 13 60.817 13'
-..,.
V,
w
10Ml40 Cowxiorodo1 -.orioa
10Ml45 8:r.dejas
ZUH12.0C
31,458.20
20,019.IXI
30,522.14 "" 54.9 2 7.5 1
137.956.1 6
45.850.80
133,861.18
70.806 40
108,018.37 '·"'
229 7.46
6.42
·24,05760
25,832 82
.25nn20
26,009.95
-2.c:9510
�8.18
"'"' '·"'
mi
Artobc!Oi, d11positl\01 rooooro,. Luminaria,.
MISO 11,784.00 9,969.00 85% 48,176.28 40.758,50 32,12 2.10 3.22; 1268 8.636,41 11.155. -438.00
MISS
l..lmparas
Enunns Mavoros """ 357.00 34261 57,783.95 55.455 43 42,223.18 181.66 123.24 U2 1l232 25 14.122 17 1,701.81
�
MISO
lnttal..c
- ion dO prolocom cntodica (lnelalac10n de
Shilomas,cabloe y Torminal01)
""" 1200 11.82 3,11743 3,071 13 3,085.52 269.79 261,00 -14)'1 -1.i.r,¡
3
10Ml70 122,51tl.10 122,616.10 100% 46,938.03 46,938.03 10 4,811.34 0.36 0.86 284 -67,87331 -67873 31 -2,662.93
IOM171
Ccndullsl
�!.ilación do Frame, Transfl (RoKl&c) """ 22:1.00 214.00 ,.,.
..,. 4,21781 4,058 96 3,003.50 18.QI 14.42 17.80 96546 973 151 3.87
o..
M175
MlllO
Csblo do PU(IISla aflorra
Poatoado �umi'laclon
20M120 Ccilduit1
"""
mi 84,393.80
2Zl.00
1,787.00
63,862.Xl
224.00
1,174.18
100%
38,826 28
2.038.22
3.858.33
36,505.81
2.047.38
2,535 14
73,527 29
6,312.99
1.87900
0.00
Q.14
218
1.16
28.18
1.00
1.37
16.00
.J'i()7140
-4.265 03
656 14
- J\23}52
4.26277
1,00007
-647 46
-2:344
(1) mi 68"
'"O
20M125 • Tonclldo doCablea • Cablo1 enturados • Megado
M135+ M4JO doCablEII
mi 524,278.83 488,576.77 .,,. 119,081.93 111.354.10 127.J00.61 Q23 Q,O 0.33 -15,fl.HJ62 -26.100 ri11 -1,416.04
o 20 M137
20M145
Pro locciondoCabl91
20M140 Co11ox10rodo1101101
BMdojae
"""
mi
mi
343,28'1.93
9,979.00
22,485.30
343,269.93
8,174.00
21,110.21
""
100%
""
48.�.33
16.66742
60,959.61
46.959. 33
13,862 62
57,231 81
37,25650
68,07882
Q1'
1.67
2 1
4.56
3.22
4.64
3.30
46.�. 33
-23.002/�
-10!::,17 CJI
46.959
-l2.120"JJ
-1:_ia,"44'.il
31.73
-1,03J.21
..rn,.ai:,
....
() 20M170
Pro 0011.rnblajeyMmt3jo Sopotles (bardajas
kg 84,180.88 84,180.86 100% 32.251.14 32.251.14 70,922.90 0.36 0.84 -3ecl717tJ -38 U71 7 6 -2.081.63
Ccrlduit1)
"""
1.351
:::o... 20M171
M210
lnltalocion do Frnmo1 , y Soporto nJtrvmont01
PM&la. do lr&lrumentaclon """
1,600.0C
1,096.0C
1,632.00
996.00
85%
""
28,8 00.00
41,738.92
24,521 60
37,930 62
40,656 00
16.008.51
18.00
,._..,
26.63
16,57
35.5'
14.31
-16,13 440
21,422 12
.\().JJJ2'0
Zl_S3041
1
- 1 .153.60
360.33
¡i)
o.. M220 • M230
'""""
ln1talac10ndo 1Mtnmenl06 • ln1talacion de
""" 3,351.00 2,448.00 13% 62 ,032.45 4�. 279.43 53.814,05 18.51 2'00 78.04 .J3:,5J,I t32 ,8 071 001 -2.003.69
,.-._ M250 Callbraciondoln1lrumon!os """ 5.091.00 6.001.()0 100% 24.945.90 24,945.90 1 9,172.33 4.10 3.77 5.773.57 5,773.57
M110 ExcalOCión con eq1,.11po 34,900.89 34,998.89 100% 21.248.11 21,248.11 28,245.94 0,61 0.81 -000/83 -o,007 83
�
..._, M\11 Exca10CIOn manual
m3
m3 20,2n.11 202n.11 100% 89,213.10 89.213.10 82.018.21 4.40 4.04 7_ 194 89 7.194 89
M1Hi Rd!ono 13.no.93 13,770.93 100% 24,0 99.13 24.099.13 28,350.23 1.75 -4 7'it 00 -4 l51 00
,...
m3
�
2"'
M116 Rollooo Cam.1 do A,1)'13) m3 14,313,06 14,313.00 100% 26,765 43 26,765.43 45.904 81 1.87 3.21 .10 13" J6 -19 139 J8
M117 Coic1o10,oio m3 566.07 �97 100% 1,814.32 1.814.32 2.745.71 3.20 .l\"J1t-l -�l"Y!
\Q Conc1olo y Pod0&lalo1 y fundacione& (inc
..,.
.¡::. M\18 m3
oncolrodoy acoro)
o
M119
M147
M149
El•nlnaciondomalenal
SlubUps
83'1Codo0uct01
"""
m3
"""
70,444.76
1,06200
70,444.76
1,040.00
100% 8,594.26
54,455.45
8.594 .26
53.327,37
26,49710
52 .763.50
Ql2
51.28
Q36
50.13 41.33
-17 'll?P,,l
563 87
-17"02PAl
563. 871
75.00 75.00 100% 16,948.50 16.948.50 16 .948.50 .225.96 225.98
M240
M440
ElfJipos de Tolocomincac10001
A1i11ooaa a P1 ocornml11iooi11g
UrnJ
1emana1 1
1,561.00,
30.47
156.00
30.47
'º"
100%
8,62121
34,24615
aon3
39,37662
1.175 00
38.217 00
5.56 7.53 70,13 ...,!JJ/27 -.:JJf2I -2f•tf2t>
¡i) 1,2"2.31 1,264.25 1,756.36 1,159 62 1.159 6 21
1 �
¾ Av.anee Acumulado Sem Anterior
S.m Actual
93.3
94.�/.I 0,&9¾
Ele�cldad
lnttrumentaci6n .,,,
95% 95%
.,,, .J2.17179
-33,073.76
-34.34191
-60,39476 �
!Total 1 94.26% 1� -111, 71134 -136,200 � -13 358.51)
1
91.1
-
1 12
obreros.
las mismas.
COSTOS
control de modo que las sumatorias de los subtotales por rubro y fase/recurso
incluyen el costo directo y parte del costo indirecto del Proyecto. Por
(tareadores), etc.
• La cuenta de Costos Indirectos incluye sólo la parte del costo indirecto del
30 97
INSTRUMENTACION AOMINISTRACION Y LOGISTICA
99
AISLAMIENTO Y PINTURA MANTENIMIENTO EQUIPOS Y CAMPAMENTO
40 PRUEBAS Y ASISTENCIA A PRECOMMISSIONG GASTOS GENERALES
so
80
OBRAS CIVILES
88
PARTIDAS INTERMEDIAS
CONTINGENCIAS
1
LB Deaerlpclón 1 ObMrv�don 1 Und 1 Oea,crlpclón 1 Obeorvaclon
L001 TrabaJo• Adk:lonal• M001 Ma1ort.olos Cons1n•blo,
MT
Stand By por Paracsae on Obm y Charlali por loducclon M004 Ropua.loe, Mantenimionlo do oqupos
hh
L008 Roleoo (Cama do A,orn) M008 Malo,ialos oloctricoe. cojas. cablo., m::Uc.'ldoroe.
hh
l009 Coloc:acion de Conc,oto ROjo M009 Sis torro de n11ninaclón Lineal con Lurnl.-nria
hh
L013 Tendido do Cabloa M013 Malorialos do il'l9trumon1ac·ión.. oport98 do confoila. l&rmlo.ales, conecto1oe, ca Glb
hh
l014 Tendido do Cables Enlonadoa M014 Matonalo1 ohxtricoa,..opor188 do condulls. torminaloa. COl'l8Clo10., cajas,. cablt GI>
hh
L019 n&talacion de Protooclon Calodica M019 Mal Voriol ceo (Contal do EqUpos) Glb
hh
l02' Cablo do P�la aliena M021 Alm3Cen. lmportaciooea,Tamadoros. conl1oladoto1. Manlonlamlonlo do Ta•a• Glb
L022 Poe 109 do lh.nllnacion M022 Tru,...porto Floloe do oqu!pos yMalorialoe Ci'-'loa/ Eloctromocanlco11 Viajo
hh
L029 PtVObaa do lazoe y contJnuidad M020 Malorlal do Embalajo (Comi,m Local) Glb
hh
LOOO Mogado do Cabloa M030 Man1onlmionto Ut-11108 do Campan1onto. Muoblos y Eo101os Glb
hh
l002 Embwque y Doeomb arquo M032 Mal Varios ceo (Contal de EqUpos) GI>
hh
l003 Pon1onal CEO (Contal do EqUpoe) M033 SunUrisho Moteriatoe Maln 0'41 <:C 1!>82 Glb
hh
L004 Suministro Personal Main CiVI <x:: 1582 M034 Suminstro Materialos Undorg,ou-ld -CC 1!»68 GI,
hh
LOOS SumlnlstJo Personal Undergrolm -ce 1568 M035 Suministro Matorialos SEMS <:C 1607 GI>
hh
l006 Sumlnlatro Personal SEMS -CC 1607 M036 Sumiristro Matoriat06 BUtding .CC 1618 Glb
hh
l007 Sumiríatro Personal 8Uld1ng -CC 1618 M037 Sum1nlaho Malaria!OI Sor.ilclos Compar1Klos -CC 1624 GI,
hh
l008 Suministro Personal E&l -0:: 1620 M038 Combusliblo,. aceites lubricantes Glb
hh
L040 Caibraclon do lnatrumonlos M040 SofVcio Cornpartido (C ombuilible, Busoe. • Cislonl3) GI,
M�
L053 BORRAOOR
hh
1
se 1 Ooscrlpclón Subcontratiste 1 Und
S001 Sistema de Proteccion Catodica Glb
5002 Desarrollo de lngenieria Glb
S003 Pintura Glb
5004 Pruebas lectricas y pre cominionamiento Glb
saos Asbulding Glb
S006 Test Dossier Glb
S007 Conexion ado de F ibra Optica de 48 hilos Glb
S008 Derecho de cantera
5009 S istemas de Telecomunicaci ones Glb
m3
1 Tipo
ea 1 Descrlpc16n Propietario 1 Und SP 1 Descr1pcl6n 1 Cargo
1
Planilla
eoo, Camion Grue Hiab 12 tn (01) WGB-008 Gruas y Equipc,s hm POOi Juan Carlos Pume.riea lng da Campo E
E002 Comion Plataforma 30 Tn hm P002 Gutienaz Mendoza Jaime lng Rospon!Mlble F1re P,oofing E
E003 Gamlon Cama Baja hm P003 Arca Jimanez Glirio Lebofatorlsta
E004 GRUA 30 TON hm P004 Hc,encla Acuna Hidalgo Gabriel Supeniisor da Eleclrico 08 E
E005 Grupo Electrogono de 85 Kw hm P005 Pec:lfagas Al..araz Sbtlo Supel'intandanta Elactnco E
E006 Grupo Electrógeno 75 kw hm P006 Roslllo Carrillo Edson Rolando Aslslente Electrico E
E007 Grupo Electrogeno da 40 Kw hm P007 Uacza lozano Wllly SupeNsor Electrico 01 E
eooa Grupo Electrógeno 30 kw hm P008 Seg,0"111 Lomza Juan Super\lisor Electrico 02 (LIOUOADO)
eoog Compresora 250 PSI hm P009 Vargas Hueya,. Nel!.On Supe,,..,so, Electrico 03
eo10 Maquinas de Solda, electrice de 400A hm P010 Hu.aman Palomino lrinco Oro Supeniisor Electrieo 04
E011 Motosoldadora dia P01t Isidro Cordova, Monuel Superintendente Electrice
E012 Torre de Dumlnaclón d,a P012 Mañn Pineda, Joequin Guillermo Asl:.tente lnstrumentt1c1on
E013 Menteo1miento de Equipos d,a P013 Jeancaflo Portugal l.Jllbofalofio lnstrumenlac E
E014 Cuerpo de Andamio Glb P014 Morales Campos F1del Super,faor lnstrumentac,o 01 E
E015 Equipo da Topograria GEO Set,..¡ca Tent SAC Mo, P015 Uagas M1lian V!clor Antonio SuperAsor lnstrumenlaclo 02 E
E018 Equ�os menores Glb P018 Modos to Ouispe Supet,..¡SOf de Electrice 09 E
E017 He namientas Glb P017 Cashl1o Pardo Vic;tor Super,._sor de Electrico 10
EOt8 Monlift hm P018 Ricardo Rodriguez Lazo Gerenle de P1oyecto
E019 Trab&Jo Adicionales hm P019 Zolla Dlaz Jose Anton10 Gerente de Coristrvccl6n
E020 Retroexcawdora 01 CAT 416E (3516019) UN11v1AO hm P020 De la Ouz Hueynntes, Edwin Gonzalo Jefe de Oficina Tkmca (l.lOUOADO)
E021 Retroexca-.odo,a 02 CAT 416E GYM Mo, P021 2.a-.oteta Lu¡an Jose Asistente de Oficana Tknlca 1
E022 Retroexca\Odora 03 CAT 4200 (3520022) UNIMAO hm P022 otlvefa Angulo Isaac Proyectista Electncidad
E023 Volqueles (15m3) hm P023 0.iedros Paz Cerios Proyectista lnstrumentacion E
E024 Equipo de Pruebas Electrices Varios Glb P024 Dale Bellido Hairo Jocalin Traductor (LIQUIDADO) E
E025 High..Pot hm P025 Medina Escala Carl� Controlador da documentos E
E026 Camión Baranda 129 hp hm P026 Oespo Mertinez Richard Control da Avance E
E027 Marcador de cable Glb P027 Mardla Tello. Jos.e Audaz A:.lstonte de Oficina Técnica 2
E028 Laboratorio lnstrumentacion Glb P028 Pcrer. Rodnguez. Marco Antonio Asistente de Oficina Tkmca 3
E020 Equipo de Pintura Mu P029 Raul 0.Jsíhuallpa MolSnedo Co=¡t Conlrol Engmea,
E030 EO Suministrados a CEO Glb P030 Ramiraz Na-.erro Osear Asistente Control da Costos
E031 Equipo menor C\11 Glb P031 CUlldros Cornejo Alvaro Mehin Planning Enginee1 E
E032 Cam� Ostoma hm P032 OlaVde Proar'IO Roft1ci ..lose Control v Prog,amaclon E
E033 Mini CatgadOf 01 CAT 246B GYM Mu P033 Coral Jaimes Stefan Jefe de Praw,nción da Riesgos E
E03'1 Mini Calgador 02 CON ACCESORIO UNIMAO hm P034 Veta Palomino Juan Carios Ronatd Asisleo!e Planeamiento E
E035 Camion Volquete 01 MERCEDES BENZ WD-8739 Transporte ci Trebo/ hm P035 Requena Arias. Jorgo Luis lng Pro-.enclonista R
E036 Camion Volquete 02 LK 2638140 WD� Trensporte el Trebol hm P036 Rojas Malias. Dante Oemetfio Jefe do OA-OC • Ro¡as Mallas E
E037 Zarande de loibratoria hm P037 Tones Terrones Ja...ie, OC Conlrol de Calidad E
E036 Camión Gf\la de 8 lon hm P036 Femandez Cetvantes En\ef OC Electrice
E039 Camioneta 4x4 (O,i Llda Rhera Buleje P039 Pacho Apaza Da.,.¡d Mllrtln OC Control de Calidad 01
E040 Camioneta 4x4 (02) Lida Rhera Buleje P040 Mendoza AIV81ez Alex Angel OC Control de Calldad 02 (LIOUlDAOO)
E041 Sef'\oicios Atqulle, Camioneta 4x4 Lima • Obre • Lima Glb P041 Garcle Zapata Josa Albet10 OC Control de Calidad 03
E042 Equ'1os de Laboratorio P042 Camocho Zegarm Maico Antonio Jefe Administrador de Obra�
E043 Torre de auminacl6n Transporte Tachin Die P043 Fuj,no Jara Tornas Mauricio Control de Tareo!l 1 (PASO A 1607) R
EO« Ambulancia o,. P044 Segura Loyola Osee, Felix Control de Tareos 2 (LIOUOADO) R
E045 Camión de 03 Toneladas Dia P045 Diaz Ríos Jos6 Jefa de Almacén
E046 MoWir.aclon Eq1.1ípos Glb P046 Sulco Mart1naz Ale,andro Asistente Almacén 01
""'
E047 Desmo.,.¡1izacion de Equipos Glb P047 c:canocunto Vilce Fellx Despachadores 01 R
E048 Custer P048 l.Jcas Guerra. Julio Cesar Despachadores 02 R
E049 Montacargas (Tclehander ) Mu P049 Tasayco Hemandez. Josa Martln Despachadores 03 R
E050 Camión Gf\la HIAB 12 Tn (02) )P-6727 Jo..ise Transportes hm POSO Ydme Cruz, RonaJd Despachadores 04 {LIQUOAOO) R
E051 Camión Gf\la HIAB (03) hm P051 Guardián 01 • Por Detmr Guarduín 01 e
E052 Clst01oa de Combusllb1o Mu P052 Sara>Ja lrma Limpieza 01 e
E053 Grupo Electrogeno Mo, P053 Capcha Yupanqu1, Zenon Alex Olofer 01 R
EOS< Camioneta Rural Tipo VAN (01) Tre:. Cumbres Minera Y P054 Oler\& Marco, Fermin O\ofer 02 R
E055 Cam10nota Rural lipo VAN (02) Tres Cumbrec Minera Y POSS Andrade Barrientos Da,..d O,ofer 03 R
E056 BUS DE PERSONAL SPRINTER (RHB-627) Musuq Sef'\oiclo:. Genera P056 Correa Bonitas Edgar O\ofer 04 R
E057 Bus de 25 Pasajeros T,ansN1I P057 Diosas Espinoza. Merco Antonio O\ofer 05 R
..
27,292,23&.81 1,Ml,99'.11 823.1$1.00 29750,0lt.N 1e,1nso�«1 22.au.121.n
:
"º MANO DE OBRA 811,9811 75 5 ll0 12573 11111llll00 94 335 0111311 119113774 10 43485605 10 13738879 5 25102325 1132Q7752I
, MATERIALES 130Jle;ll03 $<147<1111 4UMS:H46 64.311720 2945740 4258 39206 422834605 2,318 02111 4 0IIOOII.J30
'º EOUPOS 1�25687 1'.!11134117 33838653<1 82241132 3 411G 1131111 3 438 05044 2!>1127505-1 3 24751031
se SUBCONTRATO 14 550N 2011'2114 58<1&850$ 34 73048 010415� 5781107$0 502204-12 �050113
SUPERV\SION 51 031123 70 037 118 1 170$33 3<1 45891133 125117344 1 1741100 74 81•11531n
� Recordemos que para que el Sistema de Gestión siga vigente, útil, eficaz y
herramienta para saber que tan eficaz y eficiente es el proyecto, y por lo tanto
saber en qué se está fallando, que está bien y en que se puede mejorar .
Indicadores de Gestión .
como el caso de megado de cables, que fue una cuadrilla que no tenía
un frente fijo, sino que iba recorriendo los diferentes frentes, pero
./ Como sabemos todo proyecto es único y tiene infinidad de factores que hacen
que la variabilidad sea muy alta, por eso al aseguramos de tener una correcta
que lo ejecutado sea igual a lo previsto, por lo cual cuanto mejor se realice la
integrantes. Para ello debe estar basado en un adecuado análisis del Proyecto4,
medido.
avance y productividad.
>" Se recomienda que la EDT del cronograma contractual sea acordada con el
Autor: C. F. Riveros
Edición: Primera
APENDICE
l. REGISTRO FOTOGRAFICO
Las Causas de Incumplimiento son el output directo del analisis de cumplimiento del Plan Semanal . Este Plan Semanal debe constar de todas la
actividades libres de restricciones y revisado por las jefaturas correspQndientes, a fin de detectar actividades que tiene baja probabilidad d
realizarse.
11 Todas las causas que implican errores en la programación, cambios en programación, o mala
utilización de las herramientas de programación (lookahead, análisis de restricciones y Plan
PROGRAMACIÓN PROG
Semanal). En este rubro también se consideran las programaciones de las áreas de
administración, ingeniería, equipos y las áreas de soporte que considere el Proyecto.
LOGISTICA DE Todo lo que comprende a la falta de materiales en el Proyecto, ya que dichas actividades fueron
LOG MAT
MATERULES considerados dentro del plan semanal sin estar totalmente libre de res tricciones.
INCUMPLIMIENTO DE Esta causa indica el no cumplimiento de las actividades por retrasos en actividades previas. las
IOF
OTRO FRENTE cuales incumplen la fecha por motivos como programación, loglstica. etc.
Estas causas implican todo lo relacionado a compromisos del cliente que no fueron realizados)
CLIENTE-SUPERVISIÓN CLI que afectaron al cumplimiento de las actividades del plan semanal, así como cambios o
modificaciones que surgen a raíz de necesidades del cliente.
Todas las causas que originan retrasos por razones climáticas extraordinarias o por eventos
EXTERNO EXT
extraordinarios como marchas sindicales sin previo aviso, huelgas, accidentes, etc.
Son las causas que corresponden a cambios en la ingeniería durante el desarrollo del Piar
INGENIERÍA ING Semanal. Incongruencias de los planos con la realidad del campo.
MAN'l'ENIMIENTO DE Todas las causas que implican averías o fallas en los equipos que no permitieron el cumplimientc
EQ
EQUIPOS de las actividades del Plan Semanal.
En este punto se consideran todas las causas de mcumpllm,ento relacionadas a la falla en le
SUBCONTRATAS se entrega de algún recurso subcontratado o al atraso debido al no cumplimiento de alguna labo1
ene.aroada a una subcontrata.
En este punto se consideran las causas de incumplimiento que corresponden a la fa Ita de
LOGÍSTICA DE PERSONAL LOGEQ
equipos en el Proyecto debido a fallas en la logística.
Todas las causas que competen a1 area oe topografía del proyecto y sus act1v1dad es ne
TOPOGRAFÍA TOP pertenecen al área de producción; por e j emplo. cuando hay atrasos por falta de replantee
tooooráfico etc.
LOGÍSTICA DE PERSONAL LOG PER Todas las causas que competen al área encargada de reclutar el personal del Proyecto.
En este punto se consideran todas las causas que implican el incumplimiento de los organismo5
PERMISOS PERM
responsables de otorgar las licencias o permisos solicitados de antemano por el Proyecto.
Se consideran las causas que corresponden a atrasos debido a retrabaJos en el proceso
ERRORES DE EJECUCIÓN EJEC constructivo, es decir, que por errores de ejecución no se pudieron cumplir otras actividade5
lorooramadas.
En este punto se consideran las causas de incumplimiento que corresponden a fallas o atraso5
CONTROL DE CALIDAD QA/QC del área de control de calidad del Proyecto y que perjudicaron a las actividades programadas.