Explain also about cementing company, bit company, wellhead & XMT company, casing and
tubing company,.…
Example:
Source: www.apexindo.com/offshore_rigs
Component Function/Definition Standard Operating mechanism
Drill Bit Make a hole by crush API 7-1 The tool used to crush or cut rock by
and cut the rocks. applying drag and or torque force.
(Schlumberger Oilfield Glossary).
A recommended bit program is being prepared for a new well using bit performance records
from nearby wells. Drilling performance records for three bits are shown for a thick limestone
formation at 9000 ft. Determine which bit gives the lowest drilling cost if the operating cost
of the rig is $400/hr, the trip time is 7 hours, and connection time is 1 minute per connection.
Assume that each of the bits was operated at near the minimum cost per foot attainable for
that bit.
Depth below
drill floor Pressure
(ft) (psi)
0 0
1000 465
5000 2325
8000 3720
8500 6800
9000 6850
9500 6900
b. Calculate the pore pressure gradients in the formations from surface; to 8000ft; to 8500ft;
and to 9500ft. Plot the overburden gradient (1 psi/ft) on the above plot. Determine the
mud weight required to drill the hole section: down to 8000ft; down to 8500ft; and down
to 9500ft.
a. Whilst drilling the 12 1/4" hole section of a well the mud loggers were recording the data
as shown in the table below. Plot the d and dc exponent and determine whether there are
any indications of an overpressured zone.
b. If an overpressured zone exists, what is the depth of the top of the transition zone.
c. Use the Eaton equation to estimate the formation pressure at 8600 ft.
12. Explain the definition of swelling, types of clays and how to prevent and solve the swelling
problem!
14. A well is drilling ahead at 10,000 ft MD (9,000 ft TVD) with a bottomhole assembly
comprised of 400 ft of 8-in x 3-in drill collars (147 lb/ft) and 4 ½-in, 16.60 lb/ft drill pipe
(18.40 lb/ft adjusted weight). A bit trip is required. Assume there is no mud lost to the
formation and the drillstring is pulled dry (e.g., there is no loss of mud at the surface).
Calculate the total volume (barrels) of drilling mud required to keep the hole full while
tripping completely out of the hole.
17. A rig is equipped with 10,000 ft of 5-in., 19.5-lbm/ft, Class E, XH drill pipe (adjusted weight
of 20.6 lbm/ft). A well is being drilled with 13 lbm/gal and the entire drillstring is to be
utilized in the well. Calculate the buoyed weight (lbf) of the entire drillstring.
19. A circulating system of 1000 bbl has a density of 12.0 lb/gal. There are 300 bbl of 10.0 lb/gal
mud in storage on the rig site. How many barrels of 10.0 lb/gal mud are needed to reduce the
fluid density to 11.6 lb/gal?
20. Explain about the specification and standardization of drill pipe, drill collar, HWDP, casing,
and tubing!
Notes:
a. Do This Exam Individually
b. This exam must be done in hand writting
c. Format: A4 paper, margin 1x1cm. Language Indonesia or English
d. Submission: December 5th, 2019, 12.30 PM (Jadwal UAS dari ITB).
e. 70%
SECTION B (GROUP)
1. Work in group consists of three
2. Choose a topic based on the materials that has been given in this semester.
3. Make a poster:
a. Paper size A0
b. Form: SPE
c. English is preferred
4. Submission: TU-TM ITB. Deadline December 20th, 2019, 12.00 PM.
5. 30%