Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
If circumstances arise for which the Civil Engineer is not responsible and which make it i
mpractical or impossible for the Civil Engineer to perform in whole or in part the Services in acc
ordance with their Agreement then the Civil Engineer shall promptly notify the Client of the sam
e.
If by reason a certain services had beed suspended , the time for their completion shall be
extended by the extent of the delay plus a reasonable period for their resumption, or if the speed
of performinf certain Services has to be reduced, the time for their completion shall be extended
Regardless of your role in construction, you’ll have noticed that almost all the construction proj
ects don’t finish in their contractual finish date. In fact, a delayed project has become a very nor
mal thing to witness and at a certain point, it almost feels like it’s an unavoidable outcome. How
ever, delays in most construction projects delay could actually be avoided if a proper project stud
y was conducted.
● Inefficient Management
The construction knowledge we have today enables us to conduct proper manage
ment for construction projects to ensure the delivery of the desired quality within the requ
ired time. Without this management, the above-mentioned requirements cannot be achiev
ed. On the contrary, a more severe outcome might wait just around the corner if your con
Executing a construction project requires the full knowledge of the method statem
ents made for each construction item/element; that’s why it’s essential for any contractor
to submit these method statements before the start of the project to ensure they are approv
ed and that they will enable the engineers to execute the construction works properly to m
Thus, one of the common causes of construction project delays is the contractor’s
failure to execute certain items properly which results in re-doing the whole process agai
n after discovering what went wrong in the execution. Each item must be studied accurate
Each construction project that lasts more than a year will definitely be exposed to
some unavoidable environmental events due to the change of seasons throughout the year.
For example, in the winter there are some heavy rainy days that make it absolutely impos
sible for workers to execute any construction activity (especially concrete).When such cir
cumstances take place, all the safety measures can do is protect the workers’ lives. Nevert
heless, safety cannot enable them to overpass these conditions and continue the execution
phase.
However, environmental catastrophes can be a lot of things other than rain. Here are a fe
● storms
● hurricanes
● earthquakes
● Design Issues
Each construction project can be summed up in 3 phases that represent all the acti
vities required to finish the project from day one until the very last day of the project. In s
Here we will talk mainly about the very first stage (Design). This stage can be a re
al threat to the timeline of the project as its problems mostly get discovered in the executi
on phase. No matter how well the design is revised or reviewed, the execution phase sho
ws you exactly what’s wrong with the design. It might actually be discovered in a very ha
rsh way where you, for example, construct a concrete element and then see it collapse or
The design issues are various and their number is so big that it can delay a project
for months once it’s discovered. Now we can understand the importance of the engineerin
g work (Shop-drawing) required before and within the execution phase. It does not only h
elp the execution team to implement the project properly, but it also helps to find the prob
lems in the design in the early stages of the project, giving us time to solve the problem b
● Scope Increase
● The contractor
However, the owners usually start the projects without knowing the full details of
what or how they want it to be in the future. For instance, the owner decides that the proje
ct is going to consist of 4 buildings, 3 of them are designed but the 4th one is yet to be det
ermined/designed. So they start the project until they decide what to do with the rest of th
e project that the contractor is not aware of, in this case, the owner tells the contractor tha
t there is going to be an increase in their scope, which by default means an increase in the
project duration.
● Economical Changes
We all know that construction is after all an industry that gets affected by the econ
omic conditions of the country just like any other industry. Thus, if any country was subj
ected to an economic collapse or its currency value has changed, all the construction proj
ects will be affected in so many ways, one of them is “delay”. Due to the surprising chan
ge in the price of everything, the project cash flow becomes dull and no longer represents
the true valued/budgeted cost per time. This immediately drops a massive effect on the pr
oject’s timeline making it double or triple the original duration (maybe put the project on
hold or even exterminate it) unless both the contractor and the owner can find/afford a fin
portance of a time schedule for the project. A proper time schedule enables the project to
The Client may suspend all or part of the Services or terminate the Agreement by written
notice of not less than 30 days to the Civil Engineer who shall immediately make arrangements t
o stop the Services and minimize further expenditure.
The Civil Engineer by written notice of no less than 30 days may terminate the Agreemen
t or at his and or her discretion without prejudice to the right to terminate, suspend the performan
● When 30 days after the due date or payment of any account the Civil Engineer has not rec
eived payment of that part of which has not by that time been contested in writing, or
● When Services have been suspended for a period exceeding 6 calendars months, or if it is
clear to the Civil Engineer that it will be impossible or impractical to resume the suspend
t for the Services carried out including consequential costs, expenses and disruption fees incurred
or termination of the Agreement shall not prejudice or affect accrued rights or claimes and liabili
If a dispute arises on either party, then that party shall by notice in writing served on the o
ther party of the details of the dispute and request that the dispute be resolved by conciliation. If t
he matter in dispute is not resolved in consiliation between the parties within the prescribed time
ervice owned by the Professional Engineer and shall be used only for the specific project covered