AL DABB'IYA SURFACE FACILITIES PROJECT

Scope of Work Split - Piping and Pipe Support Pre-fabrication (including NDE Works) and Pipe Spool Painting

Contractor : RP Group; Sub Contractor: OGASCO


Note: All the jobs shall be executed at OGASCO shop in Mussafah Date: 03/05/2017
RESPONSIBILITY REMARKS
NO. DESCRIPTION
OGASCO RP GROUP
1.0 PROJECT MANAGEMENT
1.01 Provision of overall Project Management Team. ü Interface with Company, PMC is by Contractor
Provision of independent, self sufficient prefabrication team including dedicated All HSE and QA/QC personnel shall meet Company
1.02 ü
HSE supervisor and Quality team for all works under this Subcontract. qualification criteria
1.03 Project Control - Overall ü
1.04 Project Control - Piping, NDE & painting ü
Adherence to Schedule sequence (priorities) provided by Contractor for Contractor to communicate the fabrication priorities
1.05 ü
Fabrication Work from time to time
1.06 Provision of Daily, Weekly & Monthly Progress reports ü
Implementation of computerised record / data capture and updation of all
1.07 fabrication related QA/QC records as per project requirement / instruction of ü Digitalization of RT films not included.
Contractor's representative.

Provide all Quality related documents in native forms (viz. Line wise weld history,
1.08 ü
etc.) and hard copy to contractor

If training is required, Contractor shall train


Implementation of Project Material Management software during Fabrication
1.09 ü Subcontractors personnel on the Material Management
works
Software used for the Project

Kickoff, progress review and any other meetings


1.10 Attend meetings at Contractor/ Company offices, if required. ü ü
as may be required inside UAE
All scrap material & unused material shall be
1.11 Month wise Material reconciliation report along with Invoice ü
returned to Contractor

Page 1 of 5
AL DABB'IYA SURFACE FACILITIES PROJECT
Scope of Work Split - Piping and Pipe Support Pre-fabrication (including NDE Works) and Pipe Spool Painting

Contractor : RP Group; Sub Contractor: OGASCO


Note: All the jobs shall be executed at OGASCO shop in Mussafah Date: 03/05/2017
RESPONSIBILITY REMARKS
NO. DESCRIPTION
OGASCO RP GROUP
Insurance (For Subcontractor Works only)
- Workmen Compensation (Including Employer's Liability)
- Motor Vehicle Third Party and Passenger Liability
1.12 ü
- Construction Plant and Equipment
- General Third Party Risks Insurance (Public, Pollution, and products /Completed
Operations Liability)
Shall be mutually discussed and agreed in line
1.13 Commercial Conditions ü
with Main contract

Page 2 of 5
AL DABB'IYA SURFACE FACILITIES PROJECT
Scope of Work Split - Piping and Pipe Support Pre-fabrication (including NDE Works) and Pipe Spool Painting

Contractor : RP Group; Sub Contractor: OGASCO


Note: All the jobs shall be executed at OGASCO shop in Mussafah Date: 03/05/2017
RESPONSIBILITY REMARKS
NO. DESCRIPTION
OGASCO RP GROUP
2 ENGINEERING
2.1 All relevant Specifications for Piping fabrication & Pipe Support fabrication ü

2.2 Issue of Piping Isometrics ü

2.3 All Method statements as required by Project Specifications ü

2.4 Preparation of Weld map (Marking of Field joints) ü

2.5 Preparation of Spool Fabrication Drawings ü


Red markup drawings (hand made sketches on isometrics provided by client to
2.6 ü
show as-built)
3 MATERIAL SUPPLY
3.1 Pipes, Flanges & Fittings ü

3.2 Supply of all Temporary Material ü

3.3 Complete Painting material as per Specification & ITT requirement ü

3.4 Complete Equipments required for blasting & Painting Works ü


4 LOGISTICS & TRANSPORTATION & MATERIAL MANAGEMENT
Transportation & delivery of Free issue Materials (Piping material) upto
4.1 ü
Subcontractor's Fabrication facility (in trailers)
4.2 Unfastening & Unloading of Material at Fabrication shop ü

4.3 Transit Insurance for Piping Materal and Fabricated Spools ü


Materials Management (computerized as per Contractor requirement) after receipt
AMOG software shall be handled/operated by
4.4 at Fabrication facility (i.e. storage, inventory, handling with in the fabrication ü ü
Contractor
facility)
4.5 Monthly Material reconciliation, stock / Material availablity report to Contractor ü

Packing (if required), Loading & fastening of fabricated Spools on to Contractor's


4.6 ü
trailer for Tranport to Site

Page 3 of 5
AL DABB'IYA SURFACE FACILITIES PROJECT
Scope of Work Split - Piping and Pipe Support Pre-fabrication (including NDE Works) and Pipe Spool Painting

Contractor : RP Group; Sub Contractor: OGASCO


Note: All the jobs shall be executed at OGASCO shop in Mussafah Date: 03/05/2017
RESPONSIBILITY REMARKS
NO. DESCRIPTION
OGASCO RP GROUP
4.7 Transportation of Fabricated Pipe spools to Site ü
Proper Storage / Preservation of all Project Material in accordance with Storage of material for a period of more than 1 month
4.8 ü
Specifications to avoid any material contamination / damage shall be charged back to Contractor
4.9 Loading & fastening of all Scrap & unused raw material ü

4.10 Tranportation of Scrap & unused raw material ü


Transportation and disposal of all general waste material from Fabrication yard to
4.11 ü
the designated area as per applicable Local regulation.
5 GENERRAL REQUIREMENTS (Construction, HSE, QC etc.)
5.1 All utilites (Power, water, air etc.) required for Subcontractor Works ü
Provision of all Plant & Machinary required for material handling & fabrication
5.2 ü
works
5.3 All necessary Tools (incl. any special tools) and Consumables ü

5.4 Safety Equipments / aperatus / PPE / Facilities ü

5.5 Training for HSE, QA/QC etc ü

5.6 Welding Procedure Specification (WPS) f or piping pre-fabrication works ü Exisitng WPS shall be used
Welding by Sub-contractor
5.7 PQR piping pre-fabrication and Pipe support fabrication ü
Others necessary action by Contractor
5.8 Painting Procedure Specification (WPS) ü
to be witnessed & approved by Company
5.9 Procedure Qualification Record ü
approved TPI
to be witnessed & approved by Contractor /
5.10 Welder Qualification Test / Record ü
Company, if required.
All activities of Piping Pre-fabrication works at SubCon shop / yard as per
5.11 ü
approved method statement and project specifications

Page 4 of 5
AL DABB'IYA SURFACE FACILITIES PROJECT
Scope of Work Split - Piping and Pipe Support Pre-fabrication (including NDE Works) and Pipe Spool Painting

Contractor : RP Group; Sub Contractor: OGASCO


Note: All the jobs shall be executed at OGASCO shop in Mussafah Date: 03/05/2017
RESPONSIBILITY REMARKS
NO. DESCRIPTION
OGASCO RP GROUP
Following Quality procedures and maintaining Quality records for Piping
5.12 Fabrication as per approved QA/QC plan / procedure and Contractor's ü
requirement.

Following HSE procedures and maintaining HSE records for Piping Fabrication as
5.13 ü
per approved HSE plan / procedure and Contractor's requirement.
5.14 Preservation of flange faces from damage ü

5.15 NDT Activities such as DPT/MPI/RT/PMI/Hardness Test/Ferrite Test/PWHT ü

5.16 Pipe Spools handling for Painting works ü

5.17 Spool Cleaning and stacking ü

5.18 Spool and Joint No. Tagging ü

5.19 Cleaning and general house-keeping ü


Storage of material for a period of more than 1 month
5.20 Stacking & Preservation of Fabricated Spools as per Specifications ü
shall be charged back to Contractor.

Page 5 of 5