Date 01/12/2019.

Field Name: ABIGBORODO


PETINENT DATA: JACKET: 01 BARGE: SIRPI FJORD./CO/NAME : BENEK
TEL(FAX) CAPT/CO-MAN: FOLARIN

SINGLE DUAL
WELL NAME INITIAL FINAL FINAL INITIAL
PRESS

TREE SIZE 3-1/8 mod B


FTHP/FLP

TREE TYPE Vetco Gray


SITHP

BASE MANAGER Clifford Odia CHP:A


BENEK TEAM DIGA PHILIP/
ONWUFUJU C LMV

WV
FLOWLINE PLUG VALVE UMV
CONTROL PILOT SETTING SV

POB 2 SCSSV
TEST
SDV

START FINISH DESCRIPTION : Zonal Isolation


0600hrs 0630hrs Attended Safety meeting with focus on OE Tenent 2 , Topic - Teamwork.
1140hrs 1245hrs Stand By to resolve community issues
1700hrs 1800hrs Wellhead inspection and Preparation for night work.( Note: Short String (AG-01D) bull plug 3" E
1800hrs 1900hrs Stand by for Scaffolders to complete erection of scaffold before commencing Tree valve test
BENEK

Remarks
FINAL

(AG-01D) bull plug 3" E


ncing Tree valve test