Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PROJECT MANUAL
Jeffrey K. Griffin, AIA FOR THE
FOR THE
CONSTRUCTION
CONSTRUCTION OF
OF
Tenant:
Azura Vascular Care
52 East Swedesford Road
Suite 110
Malvern, PA 19355
ARCHITECT:
Jeffrey K. Griffin, AIA
931 Monroe Drive NE, Suite A102-181
Atlanta, GA 30308
404-310-8827
Project:
Azura Surgery Center Renalus Crestview
For Construction
June 27, 2019
Azura Surgery Center Renalus Crestview
SPECIFICATIONS-Tenant Improvements
TABLE OF CONTENTS
SPECIFICATIONS
DIVISION 2 - SITEWORK
No Sections
DIVISION 3 - CONCRETE
DIVISION 4 - MASONRY
No Sections
DIVISION 5 - METALS
DIVISION 8 - OPENINGS
DIVISION 9 - FINISHES
DIVISION 10 - SPECIALTIES
DIVISION 11 - EQUIPMENT
No Sections
DIVISION 12 - FURNISHINGS
No Sections
DIVISION 15 - MECHANICAL
DIVISION 16 - ELECTRICAL
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work Included: This Section applies to situations in which the Contractor or his
representatives including, but not necessarily limited to, suppliers, subcontractors, employees,
and field engineers, enter upon the Owner’s property.
B. Related Work:
1. Documents affecting work of this Section include, but are not necessarily limited to,
General Conditions, Supplementary Conditions, and Sections in Division 1 of these
Specifications.
END OF SECTION
PART 1 - GENERAL
1.01 INTERPRETATIONS
A. This Section is not intended to cover all definitions which may be required, nor all the
abbreviations which may be used in the Contract Documents.
1.02 DEFINITIONS
1.03 ABBREVIATIONS
A. The following list of abbreviations shall apply to the Drawings and Specifications. This list is
not all inclusive. Other abbreviations may exist on the drawings. If any questions arise
regarding abbreviations, contact the Architect for interpretation.
END OF SECTION
A. The conditions of the Contract and Division 1, General Requirements, apply to the work under
this Section.
A. Furnish all labor, materials and services necessary for the proper and complete execution of
accepted alternates. The amount of alternate prices to be added to or deducted from the base
bid shall be stated on the Bid Form and shall include the cost of any and all modifications made
necessary by the Owner’s acceptance of an alternate.
B. State the amount to be added to or deducted from the base bid for each of the following
alternates, if these alternates are added to the work of the Contract. The base bid shall not
include the following listed alternates or work required to be performed in connection thereto.
C. There should be no substitution and/or deviation from the specified products or design without
notable benefit to the owner by either enhanced quality, functionality or cost / scheduling
savings.
1.03 SUBSTITUTIONS
A. Substitution requests shall be made during the bidding process with sufficient time for the
Architect to respond.
B. No substitutions will be accepted after contract award.
C. Substitution requests shall include the following:
1. Effect substitution has on dimensions indicated on drawings.
2. Effect substitution has on Electrical, Mechanical, Plumbing, Life Safety, Structure,
Finishes, Architectural, etc.
3. Difference between proposed and specified item.
4. Manufacturer’s guarantee and if different from specified.
5. Include all product data.
6. Indicate savings or increase in contract sum if substitution is accepted by Owner.
D. GC agrees to pay all Architectural or Engineering costs, if required, to review, test or revise
drawings or specifications caused by the substitution.
END OF SECTION
PROJECT MEETINGS
PART 1 - GENERAL
END OF SECTION
PART 1 - GENERAL
B. In the event of conflict between requirements of the General Conditions and this Section covering
shop drawings, product data and samples, the requirements of Section 01340 shall govern.
Unaltered provisions remain in effect.
1.02 DESCRIPTION
A. Submit to the Architect shop drawings, product data and samples required by specification
sections.
B. Prepare and submit the Construction Schedule, a separate schedule listing dates for submission
and dates reviewed shop drawings, product data and samples will be needed for each product.
PART 2 PRODUCTS
A. Submit shop drawings electronically in PDF. Include fabrication, erection, layout and
setting drawings and other such drawings as required under various sections of the
specifications until final approval is obtained. Reproduction of Contract Drawings will not
be used for Shop Drawings.
1. Shop drawings and other data shall be combined (bound) in a single file.
B. Date and mark shop drawings to show name of the Project, the Architect, Contractor,
originating Subcontractor, Manufacturer or Supplier, and separate details as pertinent.
A. Submit manufacturer’s descriptive data including catalog sheets for materials, equipment
and fixtures, showing dimensions, performance characteristics and capacities, wiring
diagram and controls, schedule and other pertinent information as required.
B. Submit brochures and other submittal data. Mark product data to show the name of the
Project, Architect, Contractor, originating Subcontractor, Manufacturer or Supplier, and
separate details if pertinent.
2.03 SAMPLES
B. Date samples and mark to show the name of the project, Architect, Contractor, originating
Subcontractor, Manufacturer or Supplier and separate details if pertinent.
D. Provide wall and ceiling finish material samples from the manufacturer or supplier with
attached flame resistance testing classification information (Class A, B or C) for use in
Section 01700 Contract Closeout.
E. Provide floor finish material samples from the manufacturer or supplier with attached
critical radiant flux testing classification information (Class I or Class II) for use in Section
01700 Contract Closeout.
A. Review shop drawings, product data and samples prior to submission to the Architect.
C. Clearly identify where the submission deviates from the design intent or construction
drawings.
2.05 SUBSTITUTIONS
A. Approval required:
1. The Contract is based on the standards of quality established in the Contract
Documents.
B. “Or equal”:
1. Where the phrase “or equal” or “or equal as approved by the Architect” occurs in the
Contract Documents, do not assume that materials, equipment or methods will be
approved as equal unless the items have been specifically approved for this Work by
the Architect.
2. Substitutions shall be judged against the specified item for quality, durability,
operation, appearance, and other applicable qualities including fitness for use in this
situation. The decision of the Architect is final.
PART 3 - EXECUTION
A. Schedule submissions at least two weeks before date reviewed submittals will be needed.
B. Accompany submittals with transmittal letters containing the date, project title,
Contractor’s name and address, number of each shop drawing, product data and samples
submitted, and notification of deviation from Contract Documents.
MSDS copies should be included at the same submittal with shop drawings or
product submittal. The following products must include the MSDS copy with the
shop drawing or submittal:
a) Mechanical Insulation
b) Mastic or Adhesive
c) Ceiling Tiles or other Composite Materials
d) Sealants or Caulking
e) Materials containing or releasing volatile organic compounds (VOC’s)
f) Paints, Varnishes, Stains or other similar coatings
Flame Spread Certificate copies should be included at the same submittal with shop
drawings or product submittal. The following products must include the Flame
Spread Certificate copy with the shop drawing or submittal:
a) Carpet
b) Wallcovering
c) Fabrics
d) Cubicle curtains
A. Shop Drawings: Revise initial drawings as required and resubmit as specified for
initial submittals. Clearly identify on drawings any changes which have been made
other than those requested by the Architect.
B. Product Data and Samples: Submit new datum and samples as required for initial
submittal.
C. GC shall be responsible for costs associated with review of submissions beyond two
reviews. Such costs shall include but are not limited to the Architect’s and/or
Engineer’s time, cost of reproduction, scanning, and shipping charges.
A. Contractor is still responsible for obtaining and distributing prints of shop drawings as
necessary after as well as before final approval and for coordination of submittals
between his subcontractors and suppliers.
B. Make prints of approved shop drawings which carry the Architect's appropriate stamp.
END OF SECTION
TABLE OF CONTENTS
Sub-Section/Title
PART 1 GENERAL
A. These specifications for Testing and Inspection are applicable to the Project and the Contract
Documents therefore are hereby incorporated into these Specifications.
B. The Testing Agency shall conform to applicable requirements of ASTM E329, and any
additional requirements specified herein or in the Contract Documents.
1. Examine the Contract Documents and the Report on Subsurface Investigation and become
thoroughly acquainted with the detailed testing and inspection requirements, especially those
of the following Sections where incorporated into the work:
Division 2 - Site Work
Division 3 - Concrete
Division 4 - Masonry
Division 5 – Metal
Division 9 – Finishes
C. The Testing Agency shall make all necessary arrangements with the Contractor in ensuring the
presence of the required Inspectors at all Contract Operations specified to be included under the
Testing and Inspection Agreement.
D. The Contractor shall notify the Testing Agency a reasonable time in advance (not less than 24
hours) of the time when operations requiring inspection or testing are scheduled to start.
E. Provide necessary personnel, equipment and facilities for tests and inspection. Personnel shall be
experienced and competent in their particular specialties.
F. Nothing herein specified permits the Testing Agency to allow the Contractor to deviate from the
requirements of the Contract Documents.
H. The costs of the following tests and inspections shall be accounted for separately:
1. Tests and inspection of materials and workmanship not conforming to Specification
requirements.
2. Acceptance tests for materials because of changes in properties or changed sources.
3. Tests and services of inspectors required by a Public Authority.
A. The Testing Agency shall maintain and distribute a continuous record of the quality of materials
and workmanship under its control, and certify that such materials and workmanship meet the
Specification requirements.
B. The inspection and control shall be performed under the direction of the Architect.
A. To determine that materials to be used on the job meet Specification requirements, the following
tests shall be made prior to actual use of materials:
1. Composition, gradation and moisture-density relationships for compacted and ordinary fill
materials. One set of tests for each type of material from each source.
2. Review of Contractor's qualification test results for cements, and for fine and coarse
aggregates for:
A. The Testing Agency shall review and/or make acceptance tests as specified for concrete design
mixes provided by the Contractor:
1. A mix for each specified strength and type of concrete, and each admixture or combination of
admixtures specified.
2. All materials and design mixtures to be supplied by the Contractor at least five (5) weeks
prior to proposed use.
1.05 EARTHWORK
1.06 CONCRETE
A. Inspection and control shall, in general, conform to ACI Recommended Practice for Concrete
Inspection, ACI 311, and shall include:
1. Inspection of forms and form facing materials for line, grade, tightness, quality of surface,
and cleanliness.
2. Inspection of reinforcement for quantity, details, clearances and placement, including proper
use of accessories.
3. Inspection of concrete at the mixing plant, consisting of inspection of materials for
conformance to the approved materials, check of batch quantities for compliance with design
mixes and project requirements, recommendations for adjustment of batches for consistency.
4. Inspection of concrete at the job site, including transportation, mixing, placement, protection
and curing.
5. Sampling of concrete at site, fabrication of compression test specimens, transportation to
laboratory and performing standard compression tests. One set of three (3) specimens shall be
made for each 50 cubic yards of concrete placed, but not less than one (1) set for each day's
placement for each design mix used.
6. Periodic slump, air content and density tests at the site. These tests shall be made whenever
cylinders are taken or whenever field conditions indicate non-compliance with Specification
requirements.
1.07 MASONRY
A. Inspection shall be of a nature as to determine, in general, that the construction and workmanship
are in accordance with the Contract Documents, and shall include:
1. Inspection of materials in field for conformance to Specification requirements and adequacy
of Contractor's protection measures.
2. Full time inspection of installation of all reinforced masonry.
3. Inspection of reinforcement for quantity, details, clearances and placement.
4. Inspection of grouting to ensure that required spaces are properly filled.
5. Compression tests of field samples of mortar and grout at the rate of one set of 5 samples for
each 1,000 square feet of wall (but not less than one set for each day's production).
A. Inspection and Control shall be performed by an independent testing agency and include the
following:
1. Alkalinity and adhesion testing:
a) Perform all tests as recommended by manufacturer of flooring product(s) to be installed.
b) Proceed with flooring installation only after substrates pass testing.
2. Verify that substrates are dry and free from curing compounds, sealers and hardeners.
a) Perform anhydrous calcium chloride test per ASTM F 1869. Proceed with flooring
installation only after substrates have maximum moisture-vapor-emission rate within the
END OF SECTION
PART 1 - GENERAL
A. Section summarizes the responsibility of the Contractor and the Structural Testing/Inspection
Agency in the performance of the testing/inspection specified in the Contract Documents.
B. Neither the observation of the Design Professional in the administration of the contract, nor
tests/inspections by the Testing/Inspection Agency, nor approvals by persons other than the
Design Professional shall relieve the Contractor from his obligation to perform the work in
accordance with the Contract Documents.
1.02 REFERENCES
A. ASTM D3740 - Practice for Evaluation of Agencies Engaged in Testing and/or Inspection of
Soil and Rock as Used in Engineering Design and Construction.
B. ASTM E329 - Recommended Practice for Inspection and Testing Agencies for Concrete, Steel,
and Bituminous Materials as Used in Construction.
A. Owner will employ and pay for the structural testing/inspection services that are
required by the Contract Documents.
B. Contractor shall pay for any additional structural testing/inspection required for work or
materials not complying with Contract Documents due to negligence or nonconformance.
C. Contractor shall pay for any additional structural testing/inspection required for his
convenience.
D. Qualifications: Minimum Special Inspector qualifications shall be per Section 1704.2.1 of the
International Building Code, 2015 Edition.
PART 2 - MATERIALS
Not Used.
PART 3 - EXECUTION
A. A structural preconstruction meeting may be conducted at the construction site by the Design
Professional to discuss quality issues. The parties involved may be the Design Professional,
Contractor, Structural Testing/Inspection Agency, appropriate subcontractors, suppliers, and
detailers.
B. Upon arriving at the construction site, sign in and notify the Contractor of presence.
D. Perform tests/ inspections as outlined in Contract Documents, the applicable codes, and as
directed by the Design Professional.
E. Report work and materials not complying with Contract Documents immediately to the
Contractor and Design Professional.
F. Leave copies of field notes with the Contractor prior to leaving the construction site. Field
notes shall include the message given to the Contractor, date, time of message, name of
Contractor's representative informed, type and location of work or materials tested/inspected,
whether the work or materials complies with Contract Documents and name of the Structural
Testing/Inspection Agency's representative.
G. Report and distribute results of tests/inspections promptly in the form of written reports as
directed by the Design Professional.
G. Provide storage space for Structural Testing/Inspection Agency's exclusive use, such as for
storing and curing concrete testing samples.
END OF SECTION
2. Verification of proportions of
materials in premixed or
preblended mortar, prestressing
Field inspection N Continuous N/A
grout, and grout other than self-
consolidating grout, as delivered
to the project site
1705.11.3 Wind-resisting
Components
1. Roof cladding Shop (3) and field inspection Y Periodic TA
2. Wall cladding Shop (3) and field inspection Y Periodic TA
1705.12.1 Structural Steel
Special Inspections for Seismic
Resistance
SCHEDULE OF SPECIAL INSPECTION SERVICES
PROJECT AZURA SURGERY CENTER RENALUS CRESTVIEW
APPLICABLE TO THIS PROJECT
MATERIAL / ACTIVITY SERVICE Y/N EXTENT AGENT* DATE COMPLETED
Inspection of structural steel in
In accordance with
seismic force-resisting system in Shop (3) and field inspection N N/A
AISC 341
accordance with AISC 341
Inspection of structural steel elements
in seismic force-resisting system in
In accordance with
accordance with AISC 341 (including Shop (3) and field inspection N N/A
AISC 341
struts, collectors, chord and
foundation elements)
1705.12.2 Structural Wood
Special Inspections for Seismic
Resistance
1. Inspection of field gluing operations
of elements of the seismic-force Field inspection N Continuous N/A
resisting system
2. Inspection of nailing, bolting,
anchoring and other fastening of
Shop (3) and field inspection N Periodic N/A
components within the seismic-force-
resisting system
1705.12.5 Architectural
Components Special
Inspections for Seismic
Resistance
1. Inspection during the erection and
fastening of exterior cladding and Field inspection N Periodic N/A
interior and exterior veneer
2. Inspection during the erection and
fastening of interior and exterior Field inspection N Periodic N/A
nonbearing walls
3. Inspection during anchorage of
Field inspection N Periodic N/A
access floors
1705.12.6 Mechanical and
Electrical Components Special
Inspections for Seismic
Resistance
1. Inspection during the anchorage of
electrical equipment for emergency or Field inspection N Periodic N/A
standby power systems
SCHEDULE OF SPECIAL INSPECTION SERVICES
PROJECT AZURA SURGERY CENTER RENALUS CRESTVIEW
APPLICABLE TO THIS PROJECT
MATERIAL / ACTIVITY SERVICE Y/N EXTENT AGENT* DATE COMPLETED
2. Inspection during the anchorage of
Field inspection N Periodic N/A
other electrical equipment
Are Requirements for Seismic Resistance included in the Statement of Special Inspections ? No
Are Requirements for Wind Resistance included in the Statement of Special Inspections ? No
DATE:
SECTION 01420 SUBMITTAL TRANSMITTAL
Date: ___________________________________________________________
TO: FROM:
SUBMITTAL TYPE:
Re-Submittal Information (Waiver)
Comply with all submittal requirements in
Product Data Shop Drawings Quality Control/Assurance the Project Manual and the particular
Specification Section for which you are
Test Reports Certificate Contract Closeout
transmitting material.
Design Data Samples Other
Contractor’s Certification:
We have verified that all material or equipment contained in this submittal meets all the requirements specified or shown (no exceptions).
We acknowledge that in accordance with Article 4.7 of the General Conditions a re-evaluation fee can be assessed against our contract if this submittal
requires a re-submission and review, if the submittal requirements have not been met.
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work included: Provide temporary facilities and controls needed for the work including, but not
necessarily limited to:
1. Temporary utilities such as heat, water, electricity, and telephone;
2. Field office for the Contractor’s personnel;
3. Sanitary facilities;
4. Enclosures such as tarpaulins, barricades, and canopies;
5. Fire protective measures;
6. Staging and scaffolding.
B. Related work:
1. Documents affecting work of this Section include, but are not necessarily limited to, General
Conditions, Supplementary Conditions, and Sections in Division 1 of these Specifications.
2. Except that equipment furnished by subcontractors shall comply with requirements of
pertinent safety regulations, such equipment normally furnished by the individual trades in
execution of their own portions of the work are not part of this Section.
3. Permanent installation and hookup of the various utility lines are described in other Sections.
A. Maintain temporary facilities and controls in proper and safe condition throughout progress of the
work.
PART 2 - PRODUCTS
2.01 UTILITIES
B. Temporary Services:
1. Water:
a) Make all necessary arrangements, with the responsible local authorities, and with the
building Owner (if leased space), for all temporary water services for the construction
operations as required for his use and the use of all trades.
b) Obtain and pay for all permits or other sanctions required to furnish temporary water on
the job site. The cost of all water use on the job shall be borne by the Contractor.
c) Make all connections, furnish and install all pipes and fittings, including meter, and
remove all temporary materials when this service is no longer required.
d) Use due care to prevent waste of water, maintain in perfect condition at all times; pipes,
hoses, valves, and connections.
Azura Surgery Center Renalus Crestview 01500-1 07/17
e) Provide adequate drinking water satisfactorily cooled for all workmen on the job; water
units shall be strategically located throughout the job.
2. Temporary Electricity:
a) Make arrangements with local electric company for temporary electric service, pay
expenses in connection with installation, operation and removal thereof and pay cost of
energy consumed by all trades.
b) Provide power distribution as required throughout structure 120/208 - volt, 3-phase, 60
cycle, AC. Termination or power distribution shall be one location on each floor or each
major wing or section of building. Termination shall be provided complete with circuit
breakers, disconnect switches and other electrical devices as required to protect power
supply system.
c) Temporary lighting systems shall be furnished, installed and maintained by Contractor as
required to satisfy minimum requirements of safety and security. Temporary lighting to
illuminate staging, stockpiles, trenches, projections, etc., to the satisfaction of the
Architect and general illumination throughout, adequate for watchmen and emergency
personnel.
d) Temporary equipment and wiring for power and lighting shall be in accordance with
applicable provisions of governing codes. Temporary wiring shall be maintained in safe
manner and utilized so as not to constitute a hazard to persons or property.
e) When permanent electrical power and lighting systems are in operating condition, they
may be used for temporary power lighting for construction purposes, provided that
Contractor obtains written approval of Architect and Owner, assumed full responsibility
for entire power and lighting systems, and pays costs for operation and restoration of
systems.
f) At completion of construction work or at such time as Contractor makes use of
permanent electrical installation, temporary wiring, lighting and other temporary
electrical equipment and devices shall be properly removed by Contractor.
3. Temporary Heat:
a) Provide all heat as may be necessary for thawing out and heating the ground or materials,
and for the proper execution, protection and drying out of his and his Subcontractor’s
work before permanent apparatus is installed.
b) Temporary heaters shall be smokeless, portable unit heaters, (Underwriter’s
Laboratories, Factory Mutual, and Fire Marshall approved).
c) After the building or portion thereof has been enclosed, either temporarily or
permanently, provide temporary heat and maintain continuously at a temperature of not
less than 60 degrees nor more than 75 degrees until final acceptance of the work.
Comply with requirements under Division 15, Heating, Ventilating, and Air
Conditioning for use of permanent heating system for temporary heat.
d) Provide heat as required for temporary structures of a type approved by the Architect.
e) Include all costs of temporary heat in his proposal.
f) When permanent heating system, or suitable portion thereof, is in operating condition,
such system may be used for temporary heating, provided that Contractor obtains written
approval of Architect and Owner, assumes full responsibility for new heating system,
and pays costs for operation and maintenance, and restoration of system.
g) Furnish an acceptable operator for the new heating plant during the period when
temporary heat is required.
h) Upon conclusion of temporary heating period, remove temporary piping, temporary
radiators, other equipment and pay costs in connection with repairing damage caused by
A. Furnish, erect, and maintain all staging and scaffolding (exterior and interior) eight (8) feet or over
in height for all trades for such use. Furnish, erect and maintain all staging and scaffolding
(exterior and interior) for his own use during construction of the building. Staging and scaffolding
shall be of approved design, erected and removed by experienced stage builders, and shall have all
accident prevention devices required by Federal, State, and Local Laws.
B. Erect and maintain heavy duty air and dust barriers to completely isolate areas undergoing
demolition and construction from occupied areas. Barriers shall be erected so as to prevent the
passage of dust, air, debris, etc. into adjoining spaces. Maintain relative negative pressure within
areas of demo/construction activities.
C. Employ tacky floor coverings immediately outside of any entrances to the work area. Tacky
surfaces shall be renewed daily or as required to maintain effectiveness.
D. Erect such staging and scaffolding in sufficient time and in proper sequence so as not to delay
work. Subcontractors shall schedule and commence their work so that building progress is not
delayed or obstructed once staging and scaffolding become available.
E. Each Subcontractor entering upon the work shall furnish, erect, and maintain all staging and
scaffolding under 8 feet in height required for work under his subcontract, and where so indicated,
all other staging and scaffolding required for his work. On completion of his work, each
Subcontractor shall dismantle and remove such staging and scaffolding.
F. Erection of all staging, scaffolding, rigging, etc. shall be supervised and directed by a Licensed
Rigger and inspected by a Registered Engineer. A certified affidavit shall be submitted to the
Architect by this Engineer stating that all staging, scaffolding, rigging, etc. has been safely erected
and conforms in all respects to State and Local Codes. The General Contractor shall pay for all
services in connection with the erection and inspection of all staging, scaffolding, and rigging, etc.
G. Above facilities shall be constructed and maintained in accordance with applicable requirements
of “American Standard Safety Code of Building and Construction”, published by USASI, and be
removed after they have served their purpose or when directed by Architect.
H. Permanent stairs shall be erected as soon as possible and Contractor shall provide suitable
temporary treads, risers, etc. as required to protect permanent stair members, and provide
temporary railing as required for safety.
A. The General Contractor is to provide a complete contact list for all pertinent project personnel and
subcontractors.
B. An address where project-related mail can be received must also be made available for the
duration of the project.
A. The Contractor and Subcontractor shall construct and maintain, in locations approved by the
Architect, all temporary structures, sheds, and similar needs for the storing of their respective
materials for the duration of the Contract.
B. All temporary structures shall be of substantial construction and weather tight. Temporary
structures shall be removed from site when no longer needed by the Contractor or trade
responsible for their erection.
PART 3 - EXECUTION
A. The Contractor shall maintain a rubbish-free building and building site, and shall provide metal
barrels into which all luncheon refuse shall be deposited. All such barrels shall have tight-fitting
covers.
B. Store materials so they do not create natural pockets for papers or other combustible materials.
C. Construction debris shall not be thrown from the windows of the building but shall be removed
through tight strong chutes, and all debris shall be wet down if necessary, or as directed by
Architect.
D. When building materials with combustible contents are stored in the building during construction,
they shall be located within easy reach of fire protection equipment.
E. An approved number of fire extinguishers shall be placed throughout work areas, temporary paint
shop and within easy reach of mechanics who are operating plumber’s furnaces, burning or
welding apparatus. The number and location shall be approved from time to time by the local fire
department.
F. It shall be the duty and responsibility of the General Contractor or any subcontractor performing
any cutting or welding, to comply with the safety provisions of the national Fire Protection
Association’s “National Fire Codes” pertaining to such work and the respective contractor shall be
responsible for all damages resulting from a failure to do so comply.
A. Any police officer, fireman or inspector required by the local authorities having jurisdiction over
the work, shall be employed by the Contractor and paid the standard rate or wage for the
respective occupation of the work area. All personnel employed shall be covered by Workman’s
Compensation and Employer’s Liability Insurance by the Contractor.
A. Remove snow and ice which may impair progress of work, be detrimental to workmen, or impair
trucking, delivery or moving of materials at job site or prevent adequate drainage at site or
adjoining areas.
A. Maintain temporary facilities and controls as long as needed for safe and proper completion of the
work.
B. Remove such temporary facilities and controls as rapidly as progress of the Work will permit, or
as directed by the Architect.
END OF SECTION
PART 1 GENERAL
1.01 DESCRIPTION
A. Work included: Receive, unload, store and install Owner furnished equipment as shown on the
plans and called for in the Specifications.
B. Related Work:
1. Documents affecting work of this Section include, but are not necessarily limited to,
General Conditions, Supplementary Conditions, and Sections in Division 1 of the
Specifications.
2. Section 10440 Interior Signage
C. QUALITY ASSURANCE
D. Use adequate numbers of skilled workmen necessary to handle, receive and install Owner
Furnished Equipment.
A. The Owner shall pay the net cost of shipping owner furnished equipment F.O.B. job site.
PART 2 PRODUCTS
2.01 EQUIPMENT
A. Owner furnished Equipment includes certain plumbing and/or electrical items purchased by the
Owner and shipped to the job site.
B. See drawings and other sections of these specifications for items designated O.F.I.C. (Owner
Furnished Installed by Contractor) including but not limited to the following:
Owner Furnished
Procedure Rooms
OR Light Contractor Installed
and OR
-
2.02 NOT IN CONTRACT
A. "N.I.C." (Not in Contract) indicates equipment furnished by the Owner and installed under
another construction contract or by another Contractor, or operations at the site not included as
part of this Contract, unless the drawings or specifications require installation under this
Contract.
B. Any questions concerning the scope or intent of any N.I.C. items during the bidding period
shall be referred to the Architect.
C. The Owner reserves the right to let other contracts for work at the site.
PART 3 EXECUTION
2.03 RECEIVING/UNLOADING
A. The Contractor shall be responsible for noting any damage and/or short count on the Bill of
Lading for any Owner Furnished Equipment received by him; such listing of damages or short
count being required to establish the Owner's potential claim against the carrier. The
Contractor shall also notify the Architect and Owner directly on any such damage and/or short
count.
B. Unload Owner furnished equipment at the job site using necessary care and equipment as
required to handle the equipment in a safe manner.
C. Install Owner furnished equipment as called for on the drawings and in these specifications.
D. Contract shall provide blocking and electrical service for owner furnished equipment including
A/V equipment and millwork.
END OF SECTION
PRODUCT HANDLING
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work included: Products scheduled for use in the Work by means including, but not necessarily
limited to, those described in this Section.
B. Related Work:
1. Documents affecting work of this Section include, but are not necessarily limited to, General
Conditions, Supplementary Conditions, and Sections in Division 1 of these Specifications.
2. Additional procedures also may be prescribed in other Sections of these Specifications.
A. Include within the Contractor’s quality assurance program such procedures as are required to
assure full protection of work and materials.
A. Except as otherwise approved by the Architect and Owner, determine and comply with
manufacturers’ recommendations on product handling, storage and protection.
1.04 PACKAGING
A. Deliver products to the job site in their manufacturer’s original container, with labels intact and
legible.
1. Maintain packaged materials with seals unbroken and labels intact until time of use.
2. Promptly remove damaged material and unsuitable items from the job site, and promptly
replace with material meeting the specified requirements, at no additional cost to the Owner.
B. The Owner may reject as non-complying such material and products that do not bear identification
satisfactory to the Owner as to manufacturer, grade, quality and other pertinent information.
1.05 PROTECTION
A. Every precaution shall be taken to see that all building materials and equipment of all descriptions
and parts of the building under construction are properly braced and secured, protected from
injury by water, fire, accident, cold weather or other cause; both during work hours and non-
working hours.
B. Furnish, erect and maintain exterior barricades, fences and all other safety protection measures
required by traffic, municipal and state safety regulation. Remove all enclosures when no longer
needed.
D. Temporary wood doors with self-closing hardware and padlocks shall be provided for exterior
entrances and elsewhere as required.
E. Provide protection for all concrete and finished floors, treads, platforms and the like against
mechanical damage, oil, grease, paint and other material which will stain the floor finish. Install
and maintain adequate strips of Polyethylene laminated to sisal reinforced paper on finished floors
where further work will be done by trades or where subject to traffic.
F. After the installation of work by a given Subcontractor is properly completed, the Contractor shall
be responsible for protection and for repair, replacement or cleaning should the subject work be
damaged by other trades or by any other cause. All work shall be in perfect condition at the time
of final acceptance of the project.
G. Keep all access roads, walks and common corridors clear of construction equipment, materials,
debris and all other items. Repair all work disturbed by construction operation and leave in as
good or better condition after completion as found before new work started.
H. Protect everything on the premises from injury by water, frost, wind, fire, accident or other cause
and any interference.
I. Provide ways and means to control the flow of water from every source, which may cause
inconvenience or damage during the building operation.
J. All temporary protection and coverage shall be removed at the completion of the work.
A. In event of damage, promptly make replacements and repairs to the approval of the Architect and
at no additional cost to the Owner.
B. Additional time required to secure replacements and to make repairs will not be considered by the
Owner to justify an extension in the Contract Time of Completion.
A. The Contractor shall be responsible for all broken, scratched and cracked glass, regardless of
cause and no matter by who damaged, from the time construction has begun until the project is
accepted by the Owner. He shall replace all damaged glass and deliver the entire job with all
glazing intact and clean.
END OF SECTION
The Contractor shall deliver to the Owner the spare parts, extra stock and maintenance
materials listed below, and shall obtain a signed receipt for these materials. All materials
shall be neatly packaged and identified.
This completed checklist should be sent via fax or email to Owner’s Representative prior
to Final Payment.
_______________________________________
Project Name and Location
2. Resilient Flooring - 10% of each color VCT used throughout, 8 linear feet of
each color and type of base; 12 linear feet of each type of sheet vinyl
3. Painting - One full unopened gallon, each color and type of paint.
5. Wall Protection - One four foot long corner guard with two spare end caps.
6. Air Distribution - One full carton, each filter size and type.
7. NRP Wall Protection – Four (4) 48” x 96” high pieces of each type installed.
____________________________________________________________________
Signature of General Contractor Job Title
____________________________________________________________________
Name of Company Date
CONTRACT CLOSEOUT
PART 1 -GENERAL
1.01 DESCRIPTION
A. Work included: Provide an orderly and efficient transfer of the completed Work to the Owner.
B. Related work:
1. Documents affecting work of this Section include, but are not necessarily limited to, General
Conditions, Supplementary Conditions, and Sections in Division 1 of these Specifications.
2. Activities relative to Contract closeout are described in, but not necessarily limited to, the
General Conditions.
3. “Substantial Completion” is defined in the General Conditions.
A. Prior to requesting inspection by the Owner, use adequate means to assure that the Work is
completed in accordance with the specified requirements and is ready for the requested inspection.
1.03 PROCEDURES
A. Substantial Completion:
1. Prepare and submit the punch list required by the General Conditions. Punch list shall be
ordered by room number. Include photos of work to be completed or remedied.
2. Within a reasonable time after receipt of the list, the Owner and/or Architect will inspect to
determine status of completion and prepare Owner’s list of work to be completed or
remedied.
3. Should the Owner determine that the Work is not substantially complete:
a) The Owner promptly will so notify the Contractor, in writing, giving the reasons
therefore.
b) Contractor shall remedy the deficiencies promptly, and notify the Owner when ready for
re-inspection.
c) The Owner will re-inspect the Work.
4. When the Owner concurs that the Work is substantially complete:
a) The Architect will prepare a “Certificate of Substantial Completion” on AIA Form
G704, accompanied by the Contractor’s list of items to be completed or corrected, as
verified by the Owner.
b) The Architect will submit the Certificate to the Owner and to the Contractor for their
written acceptance of the responsibilities assigned to them in the Certificate.
B. Final Completion:
1. Prepare and submit the notice required by the General Conditions.
2. Verify that the Work is complete including, but not necessarily limited to, the items
mentioned in the General Conditions.
3. Certify that:
1. The Owner’s Representative must receive all closeout submittals and a final statement of
accounting from the Contractor within thirty (30) days of the Owner’s written acceptance of
the Certificate of Substantial Completion.
2. The Owner must receive all closeout submittals and a final statement of accounting from the
Contractor before final payment can be made.
A. Provide training and instruction for the Owner’s personnel in proper operation and maintenance of
all systems and equipment, after acceptance of Operation and Maintenance Manual. It is the
Contractor’s responsibility to schedule training with the Owner’s personnel.
B. Any appropriate personnel or subcontractors should be on site to train the staff on their particular
specialty.
C. It is intended for all facility systems to be reviewed with owner’s personnel on one complete day
at some point prior to the opening and operation of the facility.
D. Provide at the Final Completion walkthrough a schedule of such training, allowing the following
time periods:
END OF SECTION
Rm # Room Name Type of Size of Type of Damper Actuation Date Inspection Company Name of Person Initials
Duct Duct Inspected Name Inspecting
Azura Surgery Center Renalus Crestview 01700-0717 Damper Inspection Report - Appendix C
SECTION 01700 – APPENDIX B
SECTION 1 – CERTIFICATES
SECTION 2 - CORRESPONDENCE
SECTION 4 - SCHEDULES
* Sections 5A, 5B & 5C shall include physical samples and cut sheets from the manufacturer with technical
performance data and classifications. This information must state the smoke development and flame spread
rating of the material.
** See 01700 Appendix C – Damper Inspection Report for complete requirements
CLEANING
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work included: Throughout the construction period, maintain the building, work area and site in a
standard of cleanliness as described in this Section.
B. Related work:
1. Documents affecting work of this Section include, but are not necessarily limited to, General
Conditions, Supplementary Conditions, and Sections in Division 1 of these Specifications.
2. In addition to standards described in this Section, comply with requirements for cleaning as
described in pertinent other Sections of these Specifications.
A. Conduct daily inspection, and more often if necessary, to verify that requirements for cleanliness
are being met.
B. In addition to the standards described in this Section, comply with pertinent requirements of
governmental agencies having jurisdiction.
PART 2 - PRODUCTS
A. Provide required personnel, equipment, and materials needed to maintain the specified standard of
cleanliness.
2.02 COMPATIBILITY
A. Use only the cleaning materials and equipment which are compatible with the surface being
cleaned, as recommended by the manufacturer of the material.
PART 3 - EXECUTION
A. General:
1. Retain stored items in an orderly arrangement allowing maximum access, not impeding
traffic or drainage, and providing required protection of materials.
2. Do not allow accumulation of scrap, debris, waste material, and other items not required for
construction of this Work.
3. At least twice each month, and more often if necessary, completely remove all scrap, debris,
and waste material from the job site.
B. Site:
1. Daily, and more often if necessary, inspect the site and pick up all scrap, debris, and waste
material. Remove such items to the place designated for their storage.
2. Weekly, and more often if necessary, inspect all arrangements of materials stored on the site.
Restack, tidy, or otherwise service arrangements to meet the requirements of subparagraph
3.01-A-1 above.
3. Maintain the site in a neat and orderly condition at all times.
C. Structures:
1. Weekly, and more often if necessary, inspect the structures and pick up all scrap, debris, and
waste material. Remove such items to the place designated for their storage.
2. Weekly, and more often if necessary, sweep interior spaces clean.
a) "Clean," for the purpose of this subparagraph, shall be interpreted as meaning free from
dust and other material capable of being removed by use of reasonable effort and a hand-
held broom.
3. As required preparatory to installation of succeeding materials, clean the structures or
pertinent portions thereof to the degree of cleanliness recommended by the manufacturer of
the succeeding material, using equipment and materials required to achieve the necessary
cleanliness.
4. Following the installation of finish floor materials, clean the finish floor daily (and more
often if necessary) at all times while work is being performed in the space in which finish
materials are installed.
a) "Clean," for the purpose of this subparagraph, shall be interpreted as meaning free from
foreign material which, in the opinion of the Owner, may be injurious to the finish floor
material.
5. For work performed on continuously operated facilities, premises shall be cleaned on a daily
basis and more often as necessary in order to maintain premises free of dust in these instances
clean shall be interpreted as meaning free from dust and other material capable of being
removed by use of reasonable effort and a hand held wet mop.
A. "Clean," for the purpose of this Article, and except as may be specifically provided otherwise,
shall be interpreted as meaning the level of cleanliness generally provided by skilled cleaners
using commercial quality building maintenance equipment and materials. Facility shall be clean
and ready for occupancy by the tenant for the intended purposes.
B. Prior to completion of the Work, remove from the job site all tools, surplus materials, equipment,
scrap, debris, and waste. Conduct final progress cleaning as described in Article 3.1 above.
C. Site:
1. Unless otherwise specifically directed by the Architect, broom clean paved areas on the site
and public paved areas adjacent to the site. Blow and remove all accumulated dirt, dust, plant
material etc.
D. Structures:
1. Exterior:
a) Visually inspect exterior surfaces and remove all traces of soil, waste materials,
smudges, and other foreign matter.
b) Remove all traces of splashed materials from adjacent surfaces.
c) If necessary to achieve a uniform degree of cleanliness, hose down the exterior of the
structure.
d) In the event of stubborn stains not removable with water, the Owner may require light
sandblasting or other cleaning at no additional cost to the Owner.
e) Clean windows using commercial cleaning methods for streak free condition.
2. Interior:
a) Visually inspect interior surfaces and remove all traces of soil, waste materials, smudges,
and other foreign matter.
b) Remove all traces of splashed material from adjacent surfaces.
c) Remove paint droppings, spots, stains, and dirt from finished surfaces.
5. Glass and mirrors: Clean inside and outside surfaces with glass cleaner, streak free condition.
6. Millwork
a) Perform the following immediately following installation:
(1) Clean all surfaces with clean water and detergent to remove blemishes, marks and
soil.
(2) Clean interior of all cabinets, vacuum out dust and debris, clean surfaces with clean
water and detergent. Rinse with clean water.
b) Perform the following during final cleaning:
(1) Inspect each surface and clean to be dust and dirt free.
(2) Inspect each opening and drawer and clean to be dust and dirt free.
(3) Remove caulking from surfaces.
(4) Wipe all surfaces with 409 or other approved cleaner.
(5) Interior and exterior surfaces shall be completely clean and debris free.
7. Ceramic Tile:
a) Perform the following operation immediately 48 hours after completing ceramic tile
installation:
(1) Remove grout from face of tiles
(2) Remove adhesives and other blemishes from exposed surfaces.
(3) Clean surfaces thoroughly.
(4) Damp-mop floors with water and detergent to remove marks and soil.
10. Carpet:
a) Use manufacturer’s recommended cleaning products only.
b) Spot clean blemishes and stains.
c) Vacuum floor using commercial vacuum equipment to remove dust, dirt, debris.
d) Clean all exposed surfaces.
11. Polished Surfaces: Surfaces requiring routine application of buffed polish, apply the polish
recommended by the manufacturer of the material being polished.
1. Polished surfaces: To surfaces requiring routine application of buffed polish, apply the
polish recommended by the manufacturer of the material being polished.
B. Schedule final cleaning as approved by the Owner to Provide to the Owner a completely clean
project ready for occupancy and use as intended.
A. Should the Owner occupy the Work or any portion thereof prior to its completion by the
Contractor and acceptance by the Owner, responsibilities for interim and final cleaning shall be as
determined by the Owner in accordance with the General Conditions of the Contract.
END OF SECTION
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work included:
1. Throughout progress of the Work, maintain an accurate record of changes in the Contract
Documents, as described in Article 3.01 below.
2. Upon completion of the Work, transfer the recorded changes to a set of Record Documents,
as described in Article 3.02 below.
B. Related Work:
1. Documents affecting the work of this Section include, but are not necessarily limited to,
General Conditions, Supplementary Conditions, and Sections in Division 1 of these
Specifications.
2. Other requirements affecting Project Record Documents may appear in other pertinent
Sections of these Specifications.
A. Delegate the responsibility for maintenance of Record Documents to one person on the
Contractor's staff as approved by the Architect.
B. Accuracy of Records:
1. Thoroughly coordinate changes within the Record Documents, making adequate and proper
entries on each page of Specifications and each sheet of Drawings and other Documents
where such entry in required to show the change properly.
2. Accuracy of records shall be such that future searches for items shown in the Contract
Documents may reasonably rely on information obtained from the approved Project Record
Documents.
C. Make entries within 24 hours after receipt of information that the change has occurred.
1.03 SUBMITTALS
PART 2 - PRODUCTS
A. Job Set Documents: Promptly following the receipt of the Owner's Notice to Proceed, secure
from the Architect at no charge to the Contractor one complete set of all Documents comprising
B. Final Record Documents: At a time nearing the completion of the Work, the GC may print one
clean set of all Drawings in the Contract if job set becomes too difficult to read. Cost of printing
shall be borne by GC.
PART 3 - EXECUTION
A. Immediately upon receipt of the job set described in Paragraph 2.01A above, stamp or otherwise
identify each of the Documents with the title "RECORD DOCUMENTS - JOB SET".
B. Preservation:
1. Do not use the Job Set for any purpose except entry of new data and for review by the
Architect.
2. Maintain the Job Set at the site of work.
2. Show on the Job Set of Record Documents, by dimension, accurate within one inch, the
centerline of each run of items such as are described in subparagraph 3.01E.1 above.
a) Clearly identify the item by accurate note such as “cast iron drain”, “galv. water”, and the
like.
b) Show, by symbol or note, the vertical location of the item, such as “under slab”, “in
ceiling”, “exposed”, and the like.
c) Make all identification sufficiently descriptive that it may be related reliably to the
Specifications.
3. The Architect may waive the requirements for conversion of schematic layouts where, in the
Architect's judgment, conversion serves no useful purpose. However, do not rely upon
A. The purpose of the final Project Record Documents is to provide factual information regarding all
aspects of the Work, both concealed and visible, to enable future modification of the work to
proceed without lengthy and expensive site measurement, investigation, and examination.
B. Project Record Documents are also known as “As-Built” drawings because they represent what
was actually built on a given project. They are an important tool for the building owner when
making future repairs to the building.
A. The Contractor has no responsibility for recording changes in the Work subsequent to Final
Completion, except for changes resulting from work performed under Warranty.
END OF SECTION
E. ACI Publications: Comply with the following unless modified by requirements in the Contract
Documents:
1. ACI 301, “Specification for Structural Concrete.”
2. ACI 117, “Specifications for Tolerances for Concrete Construction and Materials.”
2. Review special inspection and testing, and inspecting agency procedures for field quality
control, concrete finishes and finishing, cold- and hot-weather concreting procedures,
curing procedures, construction contraction and isolation joints, and joint filler strips,
semi-rigid joint fillers, forms and form removal limitations, shoring and re-shoring
procedures, vapor-retarder installation, anchor rod and anchorage device installation
tolerances, steel reinforcement installation, floor and slab flatness and levelness
measurement, concrete repair procedures, and concrete protection.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and
damage. Avoid damaging coatings on steel reinforcement.
B. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other
contaminants.
PART 2 - PRODUCTS
2.1 CONCRETE MATERIALS
A. Cement: Shall be American-made Portland cement, free from water soluble salts or alkalis
which will cause efflorescence on exposed surfaces. Portland cement shall be Type II, ASTM
C150. Use only one brand of cement for each type of cement throughout project. Contractor
shall be responsible for whatever steps are necessary to ensure that no visual variations in color
will result in exposed concrete, and shall place on order and secure in advance a sufficient
quantity of this (these) cement(s) to complete concrete work specified herein.
1. Fly Ash: ASTM C 618.
2. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or 120.
B. Normalweight Fine Aggregate: Shall be washed, inert, natural sand conforming to ASTM C33
and following additional requirements:
Sieve Retained Percent
#4 0-5
#16 25 - 40
#50 70 - 87
#100 93 - 97
Azura Surgery Center Renalus Crestview 03300-5 07/17
Fineness Modulus 2.80 (Plus/Minus 0.20)
Organic Plate 2 maximum
Silt 2.0 percent maximum
Mortar Strength 100 percent minimum compression ratio sound 5 percent
maximum loss, magnesium sulfate, five cycles
C. Normalweight Coarse Aggregate: Shall be well graded crushed stone or washed gravel
conforming to ASTM C33 and the following additional requirements:
Designated Size
(Inches) 3 2 1-1/2 1 3/4 1/2 3/8
F.M. (+/-0.20) 7.95 7.45 7.20 6.95 6.70 6.10 4.50
Organic Plate 1 maximum
Silt 1.0 percent maximum
Soundness 5 percent maximum loss, magnesium sulfate five cycles
Maximum designated sizes for normalweight coarse aggregate to be used in concrete sections
shall be as noted below, except that sizes shall also be chosen in conjunction with required
clearances.
1. One and one-half inches for sections over ten inches in thickness.
2. One inch for sections more than eight and up to ten inches in thickness.
3. Three-quarter inch for sections more than three and up to eight inches in thickness.
D. ACI Publications: For slabs to receive moisture sensitive coatings or material, comply with the
following unless modified by requirements in the Contract Documents:
1. ACI 302.2R-06, "Guide for Concrete Slabs that Receive Moisture-Sensitive Flooring".
2. ACI 308-16 “Guide to External Curing of Concrete” Ref. Section 4.1.4 “Moisture
Sensitive Floors”
E. Concrete Fill for Steel Stair and Landing Pans: Shall be composed of 1:2:2 mix with three-
eighths inch maximum size normalweight aggregate and shall be placed with a 0 inches to 1
inch slump.
F. Water: Shall be from approved source, potable, clean and free from oils, acids, alkali, organic
matter, and other deleterious material.
G. Admixtures:
1. Water-reducing agent:
a. “WRDA” - W.R. Grace & Co.
b. “PDA25” - Protex Industries, Inc.
c. “Pozzolith 344H” - Master Builder’s Co.
d. Note: Water-reducing agent shall be by same manufacturer as air-entraining agent.
2. Air-entraining agent:
a. “DAREX AEA” - W.R. Grace & Co.
b. “PROTEX AEA” - Protex Industries
c. “MB-VR” or “MB-AE” - Master Builder's Co.
3. Porosity Inhibiting Admixture: ASTM C494 /C494M
a. Porosity Inhibiting Admixture “PIA” for interior slabs (on ground and elevated)
and structural roof deck construction shall be a non-toxic, liquid admixture that is
free of volatile organic compounds (VOC) and sodium silicates. This PIA shall
create a natural chemical reaction forming a permanent barrier (capillary break)
that is integral to the concrete, insoluble, and irremovable.
TABLE A
Minimum Max. Allowable Minimum Permissible
Allowable at Net Water Content Cement Factor
28 day (psi) Gallons/Sack* Sacks/Cubic Yard** Compressive
Strength
4000 5.75
6.00
3000 6.50
5.00
* Maximum; decrease if possible. This represents total water in mix at time of mixing,
including free water on aggregate.
** Minimum; increase as necessary to meet other requirements.
E. In all slabs and walls exposed to weather, all concrete shall contain the approved air-entraining
admixture as per manufacturer’s written instructions to provide entrained air, by volume, in the
cured concrete within 4.5 to 6.5 percent.
F. Water-Reducing Admixture - The approved water-reducing admixture shall be used in all
concrete, in accordance with manufacturer’s written instructions.
G. Concrete slabs, including slabs on grade, shall have a maximum water cement ratio of 0.45.
H. The approved superplasticizer shall be used in all concrete slabs, including slabs on grade.
I. Water content and cement content of concrete to be used in work shall be based on curve
showing relation between water content, cement content, and 7- and 28-day compressive
strengths of concrete made using proposed materials. Curves shall be determined by four or
more points, each representing an average of at least three test specimens at each age, and shall
have range of values sufficient to yield desired data, including all compressive strengths
required by Contract Documents, without extrapolation. Design mix of concrete to be used in
work, as determined from curve, shall correspond to following test strengths (TABLE B)
obtained in laboratory trial mixtures, but in no case shall resulting mix conflict with limiting
values as specified in TABLE A.
TABLE B
Minimum Strength of Lab Trial Mixes (psi)
Design Trial Mix Strength
Strength 7-days 14-days 28-days
4000 3800 5000
2700 3000 3750
J. Any deviation from approved mix design, which Contractor deems desirable under certain
project conditions, will not be allowed without written approval of Architect. Cost of any
additional testing by Testing Agency associated therewith shall be paid for by Contractor.
2.3 FORM MATERIALS
A. Construct formwork to shapes, lines, and dimensions required, plumb and straight, secured and
braced sufficiently rigid to prevent deformation under load, and sufficiently tight to prevent
leakage, all in conformance with ACI Standard 347, “Recommended Practice for Concrete
Formwork”.
Azura Surgery Center Renalus Crestview 03300-8 07/17
B. Formwork for exposed concrete shall be medium-density plastic overlaid plywood, 5/8"
minimum thickness; for concealed concrete shall be “Plyform” plywood, 5/8" minimum
thickness.
C. Chamfer Strips: Half-inch, 45 degree poplar wood strips, nailed six inches on center, and
installed in inside corners of all forms, unless otherwise directed by Architect.
D. Form Ties and Spreaders: Richmond Tyscrus by Richmond Screw Anchor Co.; Superior-ties
by Superior Concrete Accessories, Ind.; or Sure-Grip Ties by Dayton Sure-Grip and Shore Co.
Wire ties shall not be used. Ties for foundation walls shall be snap-ties or type specified above
with removal cones and shall incorporate water seal washer. Ties shall be arranged in a
symmetrical manner.
E. Form Release Agent: Non-staining and non-emulsifiable type, or equal approved by Architect.
Form release agent shall be biodegradable and shall not impart any stain to concrete nor
interfere with adherence of any material to be applied to concrete surfaces.
2.4 REINFORCEMENT AND ACCESSORIES
A. Reinforcing Steel Bars: Shall be newly rolled billet steel conforming to ASTM A615 Grade
60. Bars shall be bent cold.
B. Welded Wire Fabric: Shall conform to ASTM A185.
C. All structural steel reinforcement and embedded items shall be hot-dip galvanized after
fabrication in accordance with ASTM A123.
D. All hot-dip galvanized steel shall be inspected for compliance with ASTM A123 and shall be
marked with a stamp that indicates the number of ounces of zinc per square foot of steel. After
galvanizing, the bars shall be dipped in a 0.2 percent chromic acid solution. A notarized
Certificate of Compliance with all of the above shall be required from the galvanizer.
E. Reinforcement Accessories: Shall conform to Product Standard PS7-766, National Bureau of
Standards, Department of Commerce, Class C, as produced by Superior Concrete Accessories,
Inc.; Dayton Sure-Grip Co.; or R.K.L. Building Specialties Co., Inc. Reinforcement
accessories shall include spacers, chairs, ties, slab bolsters, clips, chair bars, and other devices
for properly assembling, placing, spacing, supporting, and fastening reinforcement. Tie wire
shall be galvanized or stainless wire of sufficient strength for intended purpose, but not less
than No. 18 gauge. Metal supports shall be of such type as not to penetrate surface of
formwork and show through surface of concrete. Accessories touching interior formed
surfaces exposed to view shall have not less than 1/8 inch of plastic between metal and concrete
surface. Plastic tips shall extend not less than 1/2 inch up on metal legs. Individual and
continuous slab bolsters and chairs shall be of type to suit various conditions encountered and
must be capable of supporting 300 pound load without damage or permanent distortion.
F. Generator pad reinforcement shall be two (2) layers of #5 rebar laid continuously at perimeter
of pad. Grid of #5 rebar to be laid at 12" o.c. at center of 8" slab.
2.5 MISCELLANEOUS MATERIALS
A. Grout: Shall be ready-to-use metallic aggregate product requiring only addition of water at job
site such as “Embeco Pre-mixed Grout” by Master Builder's; “Vibro-Foil Ready-Mixed” by
W.R. Grace & Co.; or “Ferrolith G” by Sonneborn Building Products, Inc. Grout shall be easily
workable and shall have no drying shrinkage at any age. Compressive strength of grout (2" x
2" cubes) shall not be less than 5000 psi at 7 days, and 7500 psi at 28 days.
B. Under Slab Vapor Barrier
1. Stego Wrap 15 mil Vapor Barrier
Azura Surgery Center Renalus Crestview 03300-9 07/17
2. Husky 15 mil Vapor Barrier
G. Provide ready-to-use mortar product for filling in trench openings in existing slab for the
installation and/or rerouting of utilities. Follow all installation requirements.
1. Approved products:
a. Mapei Topcem Premix, Ready To Use – Accelerated Cure Screed
PART 3 - EXECUTION
3.1 INSPECTION
A. Examine all work prepared by others to receive work of this Section and report any defects
affecting installation to the Contractor for correction. Commencement of work will be
construed as complete acceptance of preparatory work by others.
1. Inspection shall be performed by a structural engineer licensed by the local authorities
having jurisdiction. Certify compliance with shop drawings.
3.2 HANDLING, STORAGE, AND PROTECTION OF MATERIALS
A. Handle and store materials separately in such manner as to prevent intrusion of foreign matter,
segregation, or deterioration. Do not use foreign materials or those containing ice. Remove
improper and rejected materials immediately from point of use. Cover materials, including
steel reinforcement and accessories, during construction period. Stockpile concrete
constituents properly to assure uniformity throughout project.
3.3 ERECTION OF FORMWORK, SHORING AND RESHORING
A. Set and maintain formwork to ensure complete concrete work within tolerance limits listed in
ACI 347 latest edition, “Recommended Practice for Concrete Formwork”, and with following
additional requirements:
1. Maximum variations from plumb:
a. In surfaces of columns and walls:
In any 10 feet of length 1/4 inch
Maximum for entire length 1/2 inch
2. Maximum variations from established position in plan shown on the drawings:
Column 1/2 inch
Azura Surgery Center Renalus Crestview 03300-10 07/17
Walls 3/4 inch
3. Variations in cross-sectional dimensions of columns and beams and in thickness of slabs
and walls.
B. For a minimum of one hour prior to concrete placement, wet forms continuously with water to
swell forms in order to prevent leakage of concrete matrix and to minimize absorption of
concrete matrix water by form materials. This requirement may be waived for those specific
cases where Architect deems it unnecessary or impractical. Care must be exercised to prevent a
build-up of water at base of forms.
C. Before form materials can be re-used, surfaces that will be in contact with freshly cast concrete
shall be thoroughly cleaned, damaged areas repaired and projecting nails withdrawn. Re-use of
form material shall be subject to approval by Architect.
D. Re-tempering of concrete which has partially hardened, that is, mixing with or without
additional cement, aggregates, or water, will not be permitted.
4.5 PLACING CONCRETE
A. Intent of this Specification is that concrete shall not be pumped. Refer to “Submittals and
Concrete Constituents” in this Section for requirements should pumping be proposed.
B. Remove water and foreign matter from forms and excavations and, except in freezing weather
or as otherwise directed, thoroughly wet wood forms just prior to placing concrete. Place no
concrete on frozen soil and provide adequate protection against frost action during freezing
weather.
C. To secure full bond at construction joints, surfaces of concrete already placed, including
vertical and inclined surfaces, shall be thoroughly cleaned of foreign materials and laitance,
roughened with suitable tools such as chipping hammers or wire brushes, and re-cleaned by
Azura Surgery Center Renalus Crestview 03300-12 07/17
stream of water or compressed air. Well before new concrete is deposited, joints shall be
saturated with water. After free or glistening water disappears, joints shall be given thorough
coating of neat cement slurry mixed to consistency of very heavy paste. Surface shall receive
coating of approximately one-eighth inch thick; this shall be scrubbed in by means of stiff
bristle brushes. New concrete shall be deposited before neat cement dries or changes color.
D. Do not place concrete having slump outside of allowable slump range.
E. Transport concrete from mixer to place of final deposit as rapidly as practical by methods
which prevent separation of ingredients and displacement of reinforcement, and which avoid
rehandling. Deposit no partially hardened concrete. When concrete is conveyed by chutes,
equipment shall be of such size and U-shaped design as to ensure continuous flow in chute.
Flat (coal) chutes shall not be employed. Chutes shall be of metal or metal lines and different
portions shall have approximately same slope. Slope shall not be less than 25 degrees nor more
than 45 degrees from horizontal and shall be such as to prevent segregation of ingredients.
Discharge end of chute shall be provided with baffle plate or spout to prevent segregation. If
discharge end of chute is more than five feet above surface of concrete in forms, spout shall be
used and lower and maintained as near surface of deposit as practicable. When operation is
intermittent, chute shall discharge into hopper. Chute shall be thoroughly cleaned before and
after each run and debris and any water used shall be discharged outside forms. Concrete shall
not be allowed to flow horizontally over distances exceeding five feet.
F. Concrete shall be placed in such manner as to prevent segregation, and accumulations of
hardened concrete on forms or reinforcement above mass of concrete being placed. To achieve
this end, suitable hoppers, spouts with restricted outlets and tremies, shall be used as required.
G. During and immediately after depositing, concrete shall be thoroughly compacted by means of
internal type mechanical vibrators or other tools, or by spading to produce required quality of
finish. Vibration shall be done by experienced operators under close supervision and shall be
carried on only enough to produce homogeneity and optimum consolidation without permitting
segregation of constituents or “pumping” of air. Vibrators used for normalweight concrete
shall operate at speed at not less than 7,000 vpm and be of suitable capacity. Do not use
vibrators to move concrete. Vibration shall be supplemented by proper wooden spade puddling
to remove included bubbles and honeycomb adjacent to visible surfaces. At least one vibrator
shall be on hand for every 10 cubic yards of concrete placed per hour, plus one spare.
Vibrators shall be operable and on site prior to starting placement.
H. Vertical lifts shall not exceed 18 inches. Vibrate completely through successive lifts to avoid
pour lines. Vibrate first lift thoroughly until top of lift glistens to avoid stone pockets,
honeycomb, and segregation.
I. Concrete shall be deposited continuously, and in layers of such thickness that no concrete will
be deposited on concrete which has hardened sufficiently to cause formation of seams and
planes of weakness within section. If section cannot be placed continuously between planned
construction joints, as specified, field joint and additional reinforcement shall be introduced so
as to preserve structural continuity. Architect shall be notified in any such case.
J. Cold joints, particularly in exposed concrete, including “honeycomb”, are unacceptable. If they
occur in concrete surfaces exposed to view, Architect will require that entire section in which
blemish occurs be removed and replaced with new materials at Contractor’s expense.
K. When placing exposed concrete walls or columns, strike corners of forms rapidly and
repeatedly from outside along full height while depositing concrete and vibrating.
END OF SECTION
METAL FABRICATIONS
PART 1 - GENERAL
1.1 GENERAL PROVISIONS
A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections
within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made a part of this
Section of the Specifications.
1.2 DESCRIPTION OF WORK
A. Work Included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. All Work in this Section, including Schedule in Paragraph 2.1 of this Section.
B. Related Work: The following items are not included in this Section and will be performed
under the designated Sections:
1. Section 03300 - CAST-IN-PLACE CONCRETE for installing metal items into concrete.
2. Section 04200 - UNIT MASONRY for installing metal items into masonry walls.
3. Section 10605 - WIRE MESH PARTITIONS for interior wire mesh partitions.
1.3 PERFORMANCE REQUIREMENTS
A. Structural Performance of Ladders: Provide ladders capable of withstanding the effects of
loads and stresses within limits and under conditions specified in ANSI A14.3.
B. Thermal Movements: Provide exterior metal fabrications that allow for thermal movements
resulting from the following maximum change (range) in ambient and surface temperatures by
preventing buckling, opening of joints, overstressing of components, failure of connections,
and other detrimental effects. Base engineering calculation on surface temperatures of
materials due to both solar heat gain and nighttime-sky heat loss.
1. Temperature Change (Range): 120 deg F ambient; 180 deg F material surfaces.
1.4 SUBMITTALS
A. Product Data: For the following:
1. Paint products.
2. Grout.
B. Shop Drawings: Show fabrication and installation details for metal fabrications.
1. Include plans, elevations, sections, and details of metal fabrications and their
connections. Show anchorage and accessory items.
2. Provide templates for anchors and bolts specified for installation under other Sections.
3. For installed products indicated to comply with design loads, include structural analysis
data signed and sealed by the qualified professional engineer, licensed by the local
authorities having jurisdiction, responsible for their preparation.
4. Where fabrications are to receive sprayed-on fireproofing, include statement that primer
is compatible with fireproofing proposed for use.
C. Welding certificates.
D. Qualification Data: For professional engineer.
1.5 QUALITY ASSURANCE
A. Welding: Qualify procedures and personnel according to the following:
Azura Surgery Center Renalus Crestview 05500-1 07/17 Version
1. AWS D1.1, “Structural Welding Code--Steel.”
2. AWS D1.3, “Structural Welding Code--Sheet Steel.”
B. Metal Surfaces, General: Provide materials with smooth, flat surfaces, unless otherwise
indicated. For metal fabrications exposed to view in the completed Work, provide materials
without seam marks, roller marks, rolled trade names, or blemishes.
1.6 PROJECT CONDITIONS
A. Field Measurements: Verify actual locations of walls and other construction contiguous with
metal fabrications by field measurements before fabrication and indicate measurements on
Shop Drawings.
1. Established Dimensions: Where field measurements cannot be made without delaying
the Work, establish dimensions and proceed with fabricating metal fabrications without
field measurements. Coordinate wall and other contiguous construction to ensure that
actual dimensions correspond to established dimensions.
2. Provide allowance for trimming and fitting at site.
1.7 COORDINATION
A. Coordinate installation of anchorages for metal fabrications. Furnish setting drawings,
templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor
bolts, and items with integral anchors that are to be embedded in concrete or masonry. Deliver
such items to Project site in time for installation.
B. Coordinate installation of steel weld plates and angles for casting into concrete that are
specified in this Section but required for work of another Section. Deliver such items to Project
site in time for installation.
PART 2 - PRODUCTS
2.1 SCHEDULE
A. Miscellaneous items include the following. Requirements for materials, hot-dip galvanizing
and shop-applied primers are included with each item as applicable.
1. Steel framing and supports with shop-applied primer for sliding doors.
2. Steel framing and supports for countertops with shop-applied primer.
3. Galvanized steel framing and supports for mechanical and electrical equipment.
4. Steel framing and supports for applications where framing and supports are not specified
in other Sections; galvanized at exterior locations and in exterior walls.
5. Galvanized steel bollards with shop-applied primer.
2.2 FERROUS METALS
A. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.
B. Steel Tubing: ASTM A 500, cold-formed steel tubing.
C. Steel Pipe: ASTM A 53/A 53M, standard weight (Schedule 40), unless another weight is
indicated or required by structural loads.
D. Cast Iron: ASTM A 48/A 48M, Class 30, unless another class is indicated or required by
structural loads.
2.3 FASTENERS
A. General: Unless otherwise indicated, provide Type 316 stainless-steel fasteners for exterior use
and zinc-plated fasteners with coating complying with ASTM B 633, Class Fe/Zn 5, at exterior
walls. Provide stainless-steel fasteners for fastening aluminum. Select fasteners for type,
grade, and class required.
Azura Surgery Center Renalus Crestview 05500-2 07/17 Version
B. Anchor Bolts: ASTM F 1554, Grade 36. Provide hot-dip or mechanically deposited, zinc-
coated anchor bolts where item being fastened is indicated to be galvanized.
C. Cast-in-Place Anchors in Concrete: Anchors capable of sustaining, without failure, a load
equal to four times the load imposed, as determined by testing according to ASTM E 488,
conducted by a qualified independent testing agency.
1. Threaded or wedge type; galvanized ferrous castings, either ASTM A 47/A 47M
malleable iron or ASTM A 27/A 27M cast steel. Provide bolts, washers, and shims as
needed, hot-dip galvanized per ASTM A 153/A 153M.
D. Expansion Anchors: Anchor bolt and sleeve assembly with capability to sustain, without
failure, a load equal to six times the load imposed when installed in unit masonry and four
times the load imposed when installed in concrete, as determined by testing according to
ASTM E 488, conducted by a qualified independent testing agency.
1. Acceptable Manufacturers: Kwik-Bolt 3 by Hilti, Inc., TruBolt Wedge Anchor by ITW
Red Head or Power-Stud by Powers Fasteners.
2.4 MISCELLANEOUS MATERIALS
A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy
welded.
B. Universal Shop Primer: Fast-curing, lead- and chromate-free, universal modified-alkyd primer
complying with MPI#79. Use primer containing pigments that make it easily distinguishable
from zinc-rich primer.
C. Zinc-Rich Primer: Complying with SSPC-Paint 20 or SSPC-Paint 29 and compatible with
topcoat.
D. Galvanizing Repair Paint: High-zinc-dust-content paint for re-galvanizing welds in steel,
complying with SSPC-Paint 20.
E. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187.
F. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous
grout complying with ASTM C 1107. Provide grout specifically recommended by
manufacturer for interior and exterior applications.
2.5 FABRICATION, GENERAL
A. Shop Assembly: Preassemble items in the shop to greatest extent possible. Disassemble units
only as necessary for shipping and handling limitations. Use connections that maintain
structural value of joined pieces. Clearly mark units for reassembly and coordinated
installation.
B. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of
approximately 1/32 inch, unless otherwise indicated. Remove sharp or rough areas on exposed
surfaces.
C. Form bent-metal corners to smallest radius possible without causing grain separation or
otherwise impairing work.
D. Form exposed work true to line and level with accurate angles and surfaces and straight edges.
E. Weld corners and seams continuously to comply with the following:
1. Use materials and methods that minimize distortion and develop strength and corrosion
resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
Azura Surgery Center Renalus Crestview 05500-3 07/17 Version
4. At exposed connections, finish exposed welds and surfaces smooth and blended so no
roughness shows after finishing and contour of welded surface matches that of adjacent
surface.
F. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners
where possible. Where exposed fasteners are required, use Phillips flat-head (countersunk)
screws or bolts, unless otherwise indicated. Locate joints where least conspicuous.
G. Fabricate seams and other connections that will be exposed to weather in a manner to exclude
water. Provide weep holes where water may accumulate.
H. Cut, reinforce, drill, and tap metal fabrications as indicated to receive finish hardware, screws,
and similar items.
I. Provide for anchorage of type indicated; coordinate with supporting structure. Space anchoring
devices to secure metal fabrications rigidly in place and to support indicated loads.
2.6 MISCELLANEOUS FRAMING AND SUPPORTS
A. General: Provide steel framing and supports not specified in other Sections as needed to
complete the Work.
B. Fabricate units from steel shapes, plates, and bars of welded construction, unless otherwise
indicated. Fabricate to sizes, shapes, and profiles indicated and as necessary to receive adjacent
construction retained by framing and supports. Cut, drill, and tap units to receive hardware,
hangers, and similar items.
1. Furnish inserts if units are installed after concrete is placed.
2.7 METAL BOLLARDS
A. Fabricate metal bollards from Schedule 40 steel pipe.
2.8 FINISHES, GENERAL
A. Comply with NAAMM’s “Metal Finishes Manual for Architectural and Metal Products” for
recommendations for applying and designating finishes.
B. Finish metal fabrications after assembly.
2.9 STEEL PRIMERS AND FINISHES
A. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with
minimum requirements indicated below for SSPC surface preparation specifications and
environmental exposure conditions of installed metal fabrications:
1. Exteriors (SSPC Zone 1B) and Items Indicated to Receive Zinc-Rich Urethane Primer:
SSPC-SP 6/NACE No. 3, “Commercial Blast Cleaning.”
2. Interiors (SSPC Zone 1A): SSPC-SP 7, “Brush Off Blast Cleaning.”
3. Apply shop primer to uncoated surfaces of metal fabrications, except those with
galvanized finishes and those to be field welded, embedded in concrete or masonry,
unless otherwise indicated. Extend priming of partially embedded members to a depth of
2 inches.
4. Comply with SSPC-PA 1, “Paint Application Specification No. 1: Shop, Field, and
Maintenance Painting of Steel,” for shop painting.
5. Comply with SSPC-PA 2, “Measurement of Dry Coating Thickness with magnetic
Gages.”
B. Zinc-Rich Primer: Urethane zinc rich primer compatible with topcoat Specified in Section
09900 - PAINTING. Provide primer with a VOC content of 340 g/L (2.8 lb/gal.) or less per
OTC ozone standards when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
Azura Surgery Center Renalus Crestview 05500-4 07/17 Version
Provide Tnemec Series 394 Perimerprime or Ameron Series 68HS at 3.0 mils DFT or approved
equal by DuPont or Carboline.
C. Hot-Dip Galvanizing: For steel exposed to the elements, weather or corrosive environments
and other steel indicated to be galvanized, provide coating for iron and steel fabrications
applied by the hot-dip process. Comply with ASTM A 123 for fabricated products and ASTM
A 153 for hardware. Provide thickness of galvanizing specified in referenced standards. The
galvanizing bath shall contain high grade zinc and other earthly materials. Fill vent holes and
grind smooth after galvanizing.
D. Hot-Dip Galvanizing And Factory-Applied Primer for Steel: Provide hot-dip galvanizing and
factory-applied prime coat, certified OTC/VOC compliant less than 2.8 lbs/gal., and
conforming to EPA and local requirements. Apply primer within 12 hours after galvanizing at
the galvanizer’s plant in a controlled environment meeting applicable environmental
regulations and as recommended by the primer coating manufacturer. Blast cleaning of the
surface is unacceptable for surface preparation. Primer shall have a minimum two year re-coat
window for application of finish coat. Coatings must meet or exceed the following
performance criteria:
1. Abrasion: ASTM D 4060, CS17 Wheel, 1,000 gram load.
2. Adhesion: ASTM D 3359, Method B, 5 mm crosshatch.
3. Humidity Resistance: ASTM D 4585.
4. Salt Spray (Fog): ASTM B 117.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing
metal fabrications. Set metal fabrications accurately in location, alignment, and elevation with
edges and surfaces level, plumb, true, and free of rack; and measured from established lines and
levels.
B. Fit exposed connections accurately together to form hairline joints. Weld connections that are
not to be left as exposed joints but cannot be shop welded because of shipping size limitations.
Do not weld, cut, or abrade surfaces of exterior units that have been hot-dip galvanized after
fabrication and are for bolted or screwed field connections.
C. Field Welding: Comply with the following requirements:
1. Use materials and methods that minimize distortion and develop strength and corrosion
resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
4. At exposed connections, finish exposed welds and surfaces smooth and blended so no
roughness shows after finishing and contour of welded surface matches that of adjacent
surface.
D. Fastening to In-Place Construction: Provide anchorage devices and fasteners where metal
fabrications are required to be fastened to in-place construction. Provide threaded fasteners for
use with concrete and masonry inserts, toggle bolts, through bolts, lag bolts, wood screws, and
other connectors.
E. Provide temporary bracing or anchors in formwork for items that are to be built into concrete,
masonry, or similar construction.
F. Corrosion Protection: Coat concealed surfaces of aluminum that will come into contact with
grout, concrete, masonry, wood, or dissimilar metals with a heavy coat of bituminous paint.
END OF SECTION
ROUGH CARPENTRY
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK
A. Work Included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. Wood blocking, metal blocking, cants, and nailers.
2. Plywood backing panels.
3. Rooftop equipment bases and support curbs.
B. Related Work: The following items are not included in this Section and will be performed
under the designated Sections:
1. Section 06402 - INTERIOR ARCHITECTURAL WOODWORK for interior woodwork
not specified in this Section.
1.2 SUBMITTALS
A. Product Data: For each type of process and factory-fabricated product, indicate component
materials and dimensions, and include construction and application details.
1. Include data for wood-preservative treatment from chemical treatment manufacturer and
certification by treating plant that treated materials comply with requirements. Indicate
type of preservative used, net amount of preservative retained, and chemical treatment
manufacturer’s written instructions for handling, storing, installing, and finishing treated
material.
2. Include data for fire-retardant treatment from chemical treatment manufacturer and
certification by treating plant that treated materials comply with requirements. Include
physical properties of treated materials, both before and after exposure to elevated
temperatures when tested according to ASTM D 5516 and ASTM D 5664.
3. For products receiving a waterborne treatment, include statement that moisture content of
treated materials was reduced to levels specified before shipment to Project site.
4. Include copies of warranties from chemical treatment manufacturers for each type of
treatment.
5. Manufacturers’ product data for construction adhesive, including printed statement of
VOC content.
6. Composite wood manufacturer’s product data for each composite wood product used
indicating that bonding agent used contains no urea formaldehyde.
1.3 DELIVERY, STORAGE, AND HANDLING
A. Stack lumber, plywood, and other panels; place spacers between each bundle to provide air
circulation. Provide for air circulation around stacks and under coverings.
PART 2 - PRODUCTS
2.1 WOOD PRODUCTS, GENERAL
A. Lumber: DOC PS 20 and applicable rules of lumber grading agencies certified by the
American Lumber Standards Committee Board of Review.
1. Factory mark each piece of lumber with grade stamp of grading agency.
2. Where nominal sizes are indicated, provide actual sizes required by DOC PS 20 for
moisture content specified. Where actual sizes are indicated, they are minimum dressed
sizes for dry lumber.
Azura Surgery Center Renalus Crestview 06100-1 07/17 Version
3. Provide dressed lumber, S4S, unless otherwise indicated.
4. Provide dry lumber with 15 percent maximum moisture content at time of dressing for 2-
inch nominal thickness or less, unless otherwise indicated.
B. Plywood Panels:
1. Plywood: Either DOC PS 1 or DOC PS 2, unless otherwise indicated.
2. Thickness: As needed to comply with requirements specified but not less than thickness
indicated.
3. Factory mark panels according to indicated standard.
2.2 WOOD-PRESERVATIVE-TREATED MATERIALS
A. Preservative Treatment by Pressure Process: AWPA C2 (lumber) and AWPA C9 (plywood),
except that lumber that is not in contact with the ground and is continuously protected from
liquid water may be treated according to AWPA C31 with inorganic boron (SBX).
1. Preservative Chemicals: Acceptable to authorities having jurisdiction and not containing
arsenate.
B. Kiln-dry material after treatment to maximum moisture content of 19 percent for lumber and 15
percent for plywood. Do not use material that is warped or does not comply with requirements
for untreated material.
C. Mark each treated item with the treatment quality mark of an inspection agency approved by
the American Lumber Standards Committee Board of Review.
D. Application: Treat items indicated on Drawings, and the following:
1. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar
members in connection with roofing, flashing, vapor barriers, and waterproofing.
2. Wood sills, sleepers, blocking, furring, stripping, and similar concealed members in
contact with masonry or concrete in exterior walls.
2.3 MISCELLANEOUS LUMBER
A. General: Provide lumber for support or attachment of other construction, including the
following:
1. Rooftop equipment bases and support curbs.
2. Blocking.
3. Cants.
4. Nailers.
5. Furring.
6. Grounds.
B. For items of dimension lumber size, provide Construction, Stud, or No. 2 grade lumber with 15
percent moisture content.
2.4 PANEL PRODUCTS
A. Miscellaneous Concealed Plywood: Exposure 1 sheathing, span rating to suit framing in each
location, and thickness as indicated but not less than 5/8".
B. Telephone and Electrical Equipment Backing Panels, including those at Water Treatment:
DOC PS 1, Exposure 1, A-C Plugged, fire-retardant treated, in thickness indicated or, if not
indicated, not less than 5/8" thick.
2.5 FASTENERS
A. General: Provide fasteners of size and type indicated that comply with requirements specified
in this Article for material and manufacture.
Azura Surgery Center Renalus Crestview 06100-2 07/17 Version
1. Where carpentry is exposed to weather, in ground contact, or in area of high relative
humidity, provide fasteners with hot-dip zinc coating complying with
ASTM A 153/A 153M.
B. Nails, Wire, Brads, and Staples: FS FF-N-105.
C. Power-Driven Fasteners: CABO NER-272.
D. Wood Screws: ASME B18.6.1.
E. Screws for Fastening to Cold-Formed Metal Framing: ASTM C 954, except with wafer heads
and reamer wings, length as recommended by screw manufacturer for material being fastened.
F. Bolts: Steel bolts complying with ASTM A 307, Grade A with ASTM A 563 hex nuts and,
where indicated, flat washers.
G. Expansion Anchors: Anchor bolt and sleeve assembly of material indicated below with
capability to sustain, without failure, a load equal to 6 times the load imposed when installed in
unit masonry assemblies and equal to 4 times the load imposed when installed in concrete as
determined by testing per ASTM E 488 conducted by a qualified independent testing and
inspecting agency.
1. Material: Carbon-steel components, zinc plated to comply with ASTM B 633,
Class Fe/Zn 5.
2.6 MISCELLANEOUS MATERIALS
A. Adhesive, including Gluing Furring and Sleepers to Concrete or Masonry: Formulation
complying with ASTM D 3498 that is approved for use indicated by adhesive manufacturer.
1. Use adhesives that have a VOC content of 70 g/L or less when calculated according to
40 CFR 59, Subpart D (EPA Method 24).
B. Metal stud backing (alternate to replace wood blocking) as follows:
1. “Notch Tite” brand Flat-Reinforced Backing (1.25 x 6" x 16 GA; 9'-4" length).
2. “Metal-Lite” brand flush mount backing (1.25" x 6" x 14 GA).
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Discard units of material with defects that impair quality of carpentry and that are too small to
use with minimum number of joints or optimum joint arrangement.
B. Set carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit
carpentry to other construction; scribe and cope as needed for accurate fit. Locate furring,
nailers, blocking, grounds, and similar supports to comply with requirements for attaching
other construction.
C. Apply field treatment complying with AWPA M4 to cut surfaces of preservative-treated lumber
and plywood.
D. Securely attach carpentry work as indicated and according to applicable codes and recognized
standards.
E. Countersink fastener heads on exposed carpentry work and fill holes with wood filler.
F. Use fasteners of appropriate type and length. Predrill members when necessary to avoid
splitting wood.
G. Cutting and Repairing: Do such work as normally required and done for mechanical and other
trades.
J. Nailers and Wood Cants: Nailers, 2" stock unless otherwise noted, of the proper widths. Bevel
nailers for concrete ½" both sides and properly place in forms. Bolt nailers in place on steel or
masonry. Furnish ledgers bolted to wall in locations shown and as required.
K. Shoring: Furnish and place all necessary shoring and bracing of types and sizes best suited for
the conditions to be met. Shoring must comply with all governing requirements.
L. Provide wood curbs, required blocking and cants around all openings through the roof indicated
on all architectural, mechanical and electrical drawings. Check drawings for all trades and
furnish for all openings indicated.
M. Studs for interior walls shall be solid and continuous from floor to double place at trusses, and
shall not be cut for straightening; warped studs shall be replaced.
N. Studs shall be doubled at all corners, opening, and beam bearing points.
O. Headers over openings in walls shall be as follows, unless noted otherwise:
Opening Width Header Size
up to 6'- 0" 2-2x6
6’ to 8'-0" 2-2x8
8' to 10"-0" 2-2x10
P. Plywood Backer Boards:
1. Electrical, telephone, video and alarm equipment locations: Install 5/8" plywood over
gypsum board, fastening into studs @ 8" o.c. Seal all vertical joints top, bottom and ends
with Tremco sealant.
2. Water Treatment Equipment: Install 5/8" exterior grade plywood over gypsum board.
Finish with Class A FRP, panels to be butt jointed where they meet another panel. Apply
Type IA acrylic fire stop sealant along all top and side top edges.
3.2 WOOD BLOCKING, AND NAILER INSTALLATION
A. Install where indicated and where required for attaching other work. Form to shapes indicated
and cut as required for true line and level of attached work. Coordinate locations with other
work involved.
B. Attach items to substrates to support applied loading. Recess bolts and nuts flush with
surfaces, unless otherwise indicated.
END OF SECTION
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK
A. Work Included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. Interior standing and running trim.
2. Interior frames and jambs.
3. Wood cabinet.
4. Plastic-laminate cabinet.
5. Closet and utility shelving.
B. Related Work: The following items are not included in this Section and will be performed
under the designated Sections:
1. Section 06100 - ROUGH CARPENTRY for wood furring, blocking, shims, and hanging
strips required for installing woodwork and concealed within other construction before
woodwork installation.
2. Section 08211 - FLUSH WOOD DOORS.
3. Section 15200 - PLUMBING FIXTURES AND EQUIPMENT.
4. Section 09900 - PAINTING.
1.2 SUBMITTALS
A. Product Data: For each type of product specified, including cabinet hardware and accessories,
and finishing materials and processes.
1. Include data for fire-retardant treatment from chemical treatment manufacturer and
certification by treating plant that treated materials comply with requirements.
2. Manufacturers’ product data for installation adhesives, including printed statement of
VOC content.
3. Composite wood manufacturer’s product data for each composite wood product used
indicating that the bonding agent contains no urea formaldehyde. Adhesive
manufacturer’s product data for each adhesive used indicating that the adhesive contains
no urea formaldehyde.
B. Shop Drawings: Show location of each item, dimensioned plans and elevations, large-scale
details, attachment devices, and other components.
1. Show locations and sizes of furring, blocking, and hanging strips, including concealed
blocking and reinforcement specified in other Sections.
2. Construction details illustrating components and methods of construction.
C. Long Lead Items: Order long lead-time materials with sufficient time to comply with
manufacturers’ delivery schedule, without causing delay to the construction schedule.
1.5 PROJECT CONDITIONS
A. Environmental Limitations: Do not deliver or install woodwork until building is enclosed, wet
work is complete, and HVAC system is operating and maintaining temperature and relative
humidity at occupancy levels during the remainder of the construction period.
B. Field Measurements:
1. Millwork:
a. Where millwork is indicated to fit to other construction, verify dimensions of other
construction by field measurements and relay that information to the Millwork Vendor
before fabrication. Coordinate fabrication schedule with construction progress to avoid
delaying the Work.
b. Where woodwork is indicated to fit to other construction, verify dimensions of other
construction by field measurements before fabrication, and indicate measurements on Shop
Drawings. Coordinate fabrication schedule with construction progress to avoid delaying
the Work.
2. Locate concealed framing, blocking, reinforcements and floor drains that support
woodwork by field measurements before being enclosed, and indicate measurements on
Shop Drawings. Coordinate blocking locations with Millwork Vendor.
3. Established Dimensions: Where field measurements cannot be made without delaying
the Work, establish dimensions and proceed with fabricating woodwork without field
measurements. Provide allowance for trimming at site, and coordinate construction to
ensure that actual dimensions correspond to established dimensions.
1.6 COORDINATION
A. Coordinate sizes and locations of framing, blocking, furring, reinforcements, and other related
units of Work specified in other Sections to ensure that interior architectural woodwork can be
supported and installed as indicated.
B. Coordinate sizes of gypsum board soffits with approved Millwork Shop Drawings.
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Provide materials that comply with requirements of AWI’s quality standard for each
type of woodwork and quality grade specified, unless otherwise indicated.
B. Wood Species and Cut for Transparent Finish: Birch, plain sawn or sliced.
H. Glass Splash Guards and Hardware (at nurse station chases and prep station dividers):
1. Glass: Clear, Low Iron, Tempered Glass – 1/4" thickness.
2. Edge Trim at Vertical Chase: CR Laurence #FA10SC – Satin Chrome Finish.
3. 18" Vertical Posts: CR Laurence #D990A18E – Satin Chrome Finish.
2.2 CABINET HARDWARE AND ACCESSORIES
A. General: Provide cabinet hardware and accessory materials associated with architectural
cabinets, except for items specified in Section 08710 - DOOR HARDWARE.
B. All other cabinet doors: Frameless Concealed Hinges (European Type); BHMA A156.9,
B01602 100+ degrees of opening, self-closing.
C. Concealed panel clips (For all cabinet undersinks): Hafele 245.07.702.
D. Back-Mounted Pulls: BHMA A156.9, B02011.
1. Provide brushed chrome wire pulls for all operating drawers and panel fronts.
E. Double Roller Catches: Push-in magnetic catches, BHMA A156.9, B03131.
1. Provide Double Roller Catch – Hafele 244.01.125, black.
F. Adjustable Shelf Standards and Supports: KV85 Series Standards (KV85ANO); KV 185
Series Brackets (KV185ANO).
G. Drawer Slides: BHMA A156.9, B05091; side mounted and extending under bottom edge of
drawer; 3/4-extension type; epoxy-coated-steel with steel ball-bearings; of the following
grades:
Azura Surgery Center Renalus Crestview 06402-3 07/17
1. Box Drawer Slides: Grade 1.
2. File Drawer Slides: Grade 1HD-100.
H. Aluminum Slides for Sliding Glass Doors: BHMA A156.9, B07063.
I. Grommets for Cable Passage through Countertops: 3" Molded-plastic grommets and matching
plastic caps with slot for wire passage. Field locate and drill as directed by Owner.
J. Exposed Hardware Finishes: For exposed hardware, provide finish that complies with
BHMA A156.18 for BHMA finish number indicated, unless noted otherwise.
1. Satin Stainless Steel: BHMA 630.
2. Satin Chrome Finish: US26D (BHMA 626).
K. For concealed hardware, provide manufacturer’s standard finish that complies with product
class requirements in BHMA A156.9.
A. Quick Leveling Glide: Hafele 637.05.000.
2.3 MISCELLANEOUS MATERIALS
A. Furring, Blocking, Shims, and Hanging Strips: Softwood lumber, kiln dried to less than 15
percent moisture content.
B. Anchors: Select material, type, size, and finish required for each substrate for secure
anchorage. Provide nonferrous-metal or hot-dip galvanized anchors and inserts on inside face
of exterior walls and elsewhere as required for corrosion resistance. Provide toothed-steel or
lead expansion sleeves for drilled-in-place anchors.
C. Handrail Brackets: Cast from malleable iron with wall flange drilled for exposed anchor and
with support arm for screwing to underside of rail. Sized to provide 1-1/2 inch clearance
between handrail and wall.
D. Adhesives, General: Do not use adhesives that contain urea formaldehyde.
E. VOC Limits for Installation Adhesives and Glues: Use installation adhesives that comply with
the following limits for VOC content when calculated according to 40 CFR 59, Subpart D
(EPA Method 24):
1. Wood Glues: 30 g/L.
2. Contact Adhesive: 250 g/L.
2.4 FABRICATION, GENERAL
A. Wood Moisture Content: Comply with requirements of referenced quality standard for wood
moisture content in relation to ambient relative humidity during fabrication and in installation
areas.
B. Sand wood lightly to remove raised grain on exposed surfaces before fabrication.
C. Fabricate woodwork to dimensions, profiles, and details indicated. Ease edges.
D. Millwork Vendor shall complete fabrication, including assembly, finishing, and hardware
application, to maximum extent possible before shipment to Project site. Components will be
disassembled only as necessary for shipment and installation. Where necessary for fitting at
site product will provide allowance for scribing, trimming, and fitting.
E. Millwork Vendor will shop-cut openings to maximum extent possible to receive hardware,
appliances, plumbing fixtures, electrical work, and similar items. Locate openings accurately
and use templates or roughing-in diagrams to produce accurately sized and shaped openings.
1. Coordinate with Millwork Vendor for openings to be field cut.
Azura Surgery Center Renalus Crestview 06402-4 07/17
a. Seal edges of openings in countertops with a coat of varnish.
2.5 INTERIOR STANDING AND RUNNING TRIM FOR TRANSPARENT FINISH
A. Grade: Custom.
B. Wood Species and Cut: Match species and cut indicated for other types of transparent-finished
architectural woodwork located in same area of building, unless otherwise indicated.
1. Provide split species on trim that faces areas with different wood species, matching each
face of woodwork to species and cut of finish wood surfaces in areas finished.
C. For trim items wider than available lumber, use veneered construction. Do not glue for width.
D. For rails wider or thicker than available lumber, use veneered construction. Do not glue for
width or thickness.
E. Backout or groove backs of flat trim members and kerf backs of other wide, flat members,
except for members with ends exposed in finished work.
F. Assemble casings in plant except where limitations of access to place of installation require
field assembly.
2.6 PLASTIC-LAMINATE CABINETS
A. Grade: Custom.
2.7 SOLID-SURFACING-MATERIAL COUNTERTOPS
A. Grade: Custom.
B. Solid-Surfacing-Material Thickness: 1/2" SS material over 1" MDF.
2.8 SOLID SURFACE MATERIAL DIVIDERS, SIDESPLASHES & BACKSPLASHES
A. Grade: Custom.
B. Solid-Surfacing-Material Thickness: 1/2 inch.
2.9 CLOSET AND UTILITY SHELVING
A. Grade: Custom.
B. Shelf Material: 3/4-inch NAUF Particle Board with white melamine; .5mm edge band all
edges.
C. KV85ANO Standards, KV185ANO Standards.
PART 3 - EXECUTION
3.1 PREPARATION
A. Before installation, condition woodwork to average prevailing humidity conditions in
installation areas.
B. Before installing architectural woodwork, examine shop-fabricated work for completion and
complete work as required, including removal of packing and back priming.
3.2 INSTALLATION
A. Grade: Install woodwork to comply with requirements for the same grade specified in Part 2
for fabrication of type of woodwork involved.
B. Assemble woodwork and complete fabrication at Project site to comply with requirements for
fabrication in Part 2, to extent that it was not completed in the shop.
Azura Surgery Center Renalus Crestview 06402-5 07/17
C. Install woodwork level, plumb, true, and straight. Shim as required with concealed shims.
Install level and plumb (including tops) to a tolerance of 1/8 inch in 96 inches.
D. Scribe and cut woodwork to fit adjoining work, refinish cut surfaces, and repair damaged finish
at cuts.
E. Anchor woodwork to anchors or blocking built in or directly attached to substrates. Secure
with countersunk, concealed fasteners and blind nailing as required for complete installation.
Use fine stainless steel finishing nails or finishing screws for exposed fastening, countersunk
and filled flush with woodwork and matching final finish if transparent finish is indicated.
F. Standing and Running Trim: Install with minimum number of joints possible, using full-length
pieces (from maximum length of lumber available) to greatest extent possible. Do not use
pieces less than 60 inches long, except where shorter single-length pieces are necessary. Scarf
running joints and stagger in adjacent and related members.
1. Fill gaps, if any, between top of base and wall with plastic wood filler, sand smooth, and
finish same as wood base if finished.
2. Install wall railings on indicated metal brackets securely fastened to wall framing.
3. Install standing and running trim with no more variation from a straight line than 1/8 inch
in 96 inches.
G. Cabinets: Install without distortion so doors and drawers fit openings properly and are
accurately aligned. Adjust hardware to center doors and drawers in openings and to provide
unencumbered operation. Complete installation of hardware and accessory items as indicated.
1. Install cabinets with no more than 1/8 inch in 96-inch sag, bow, or other variation from a
straight line.
2. Secure wall-hung cabinetry into wall blocking and/or framing.
3. Coordinate installation with construction so that all drawers and doors are fully
operational.
4. Install door stops on walls where cabinets doors open and touch walls.
H. Countertops: Anchor securely by screwing through corner blocks of base cabinets or other
supports into underside of countertop.
1. Align adjacent solid-surfacing-material countertops and form seams to comply with
manufacturer’s written recommendations using adhesive in color to match countertop.
Carefully dress joints smooth, remove surface scratches, and clean entire surface.
2. Install countertops with no more than 1/8 inch in 96-inch sag, bow, or other variation
from a straight line.
3. Install removable access panels in the dialysis counter with a 1/16" gap at both ends so
that they are easily removable.
4. Secure side splashes to tops and to walls with adhesive.
5. Caulk space between backsplash and wall with sealant specified in Section 07920 -
JOINT SEALANTS.
3.3 ADJUSTING AND CLEANING
A. Repair damaged and defective woodwork, where possible, to eliminate functional and visual
defects; where not possible to repair, replace woodwork. Adjust joinery for uniform
appearance.
B. Clean, lubricate, and adjust hardware.
END OF SECTION
C. Set vapor-retarder-faced units with vapor retarder in location indicated of construction, unless
otherwise indicated.
1. Tape joints and ruptures in vapor retarder, and seal each continuous area of insulation to
surrounding construction to ensure airtight installation.
3.6 INSTALLATION OF VAPOR RETARDERS
A. General: Extend vapor retarder to extremities of areas to be protected from vapor transmission.
Secure in place with adhesives or other anchorage system as indicated. Extend vapor retarder
to cover miscellaneous voids in insulated substrates, including those filled with loose-fiber
insulation.
END OF SECTION
C. Do not cover up through-penetration firestop system installations that will become concealed
behind other construction until each installation has been examined by the building inspector, if
required by authorities having jurisdiction.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Available Products: Subject to compliance with requirements, through-penetration firestop
systems that may be incorporated into the Work include, but are not limited to, those systems
indicated in the Through-Penetration Firestop System Schedule at the end of Part 3.
1. Hilti, Inc.
2. BioFireshield; RectorSeal Corporation.
3. 3M; Fire Protection Products Division.
4. Or approved equal.
2.2 FIRESTOPPING MATERIALS
A. Compatibility: Provide through-penetration firestop systems that are compatible with one
another; with the substrates forming openings; and with the items, if any, penetrating through-
penetration firestop systems, under conditions of service and application, as demonstrated by
through-penetration firestop system manufacturer based on testing and field experience.
B. Materials: Provide through-penetration firestop systems containing primary materials and fill
materials which are part of the tested assemblies indicated in the Through-Penetration Firestop
System Schedule at the end of Part 3. Fill materials are those referred to in directories of
referenced testing and inspecting agencies as “fill,” “void,” or “cavity” materials.
C. Accessories: Provide components for each through-penetration firestop system that are needed
to install fill materials and to comply with Part 1 “Performance Requirements” Article. Use
only components specified by through-penetration firestop system manufacturer and approved
by qualified testing and inspecting agency for firestop systems indicated.
D. Approved Colors: Provide Firestopping materials (caulk, putty, sealants) that are red in color
whenever possible as they provide better visibility for inspection.
1. Fill voids and cavities formed by openings, forming materials, accessories, and
penetrating items as required to achieve fire-resistance ratings indicated.
2. Apply materials so they contact and adhere to substrates formed by openings and
penetrating items.
3. For fill materials that will remain exposed after completing Work, finish to produce
smooth, uniform surfaces that are flush with adjoining finishes.
Azura Surgery Center Renalus Crestview 07841-4 07/17
3.4 FIELD QUALITY CONTROL
A. Inspecting Agency: Engage a qualified, independent inspecting agency to inspect through-
penetration firestops. Independent inspecting agency shall comply with ASTM E 2174
requirements including those related to qualifications, conducting inspections, and preparing
test reports.
B. Where deficiencies are found, repair or replace through-penetration firestop systems so they
comply with requirements.
C. Proceed with enclosing through-penetration firestop systems with other construction only after
inspection reports are issued and firestop installations comply with requirements.
D. Provide one unopened tube of fire caulking for each type and color of fire caulking installed to
the Owner for storage and future reference.
3.5 CLEANING AND PROTECTING
A. Clean off excess fill materials adjacent to openings as Work progresses by methods and with
cleaning materials that are approved in writing by through-penetration firestop system
manufacturers and that do not damage materials in which openings occur.
B. Provide final protection and maintain conditions during and after installation that ensure that
through-penetration firestop systems are without damage or deterioration at time of Substantial
Completion. If, despite such protection, damage or deterioration occurs, cut out and remove
damaged or deteriorated through-penetration firestop systems immediately and install new
materials to produce systems complying with specified requirements.
3.6 LABELING/STENCILING OF FIRE WALLS
A. All rated walls are required to be labeled with a spray-applied stencil above the finish ceiling, or in the
absence of a ceiling as high on the wall as practical. Color shall be red. The labels shall read:
1. Fire Rated Walls: “XX HOUR FIRE WALL – PROTECT ALL PENETRATIONS”.
2. Smoke Partition: “SMOKE PARTITION – SEAL ALL PENETRATIONS”
B. Letters shall be a minimum of 3" in height and should be legible from 20'-0" distance. A non-serif
typeface should be used for maximum legibility.
2 WL WL WL 2133
2078, 2088
WL ,
2075, WL
WL 2002
2128
2 FC FC FC
2025, 2024 2059
FC
2126
4 WL N/A
2184, *
WL
2245
2 WL WL WL
7040, 7008, 7037
WL WL
7042 7013,
WL
7016
4
MIXED 1 FC FC N/A MIXED 1 WL WL WL
PENETRANTS 8014, 8013 PENETRANTS 8004, 8010 8017
FC 8026 WL
8013
2 WL WL WL
8004, 8010, 8017
WL WL
8013 8002
2 N/A* N/A* N/A 4 WL N/A*
8014
4 WL
8014
* No UL-Classified system is available as of August 2003. Engineer
Judgement Drawing Required.
NOTES:
1. Jobsite conditions of each through-penetration firestop system must meet all details of the
UL-Classified System selected.
2. If jobsite conditions do not match any UL-classified systems in the schedules above, contact
firestop manufacturer for alternative systems or Engineer Judgement Drawings.
3. Coordinate work with other trades to assure that penetration-opening sizes are appropriate
for penetrant locations, and vice versa.
4. For 3-hour rated gypsum walls, contact the firestop manufacturer for a UL-classified sys-
tem or engineer judgement drawing.
5. The Contractor shall verify that the schedule is current at the time of construction, and that each
referenced system is suitable for the intended application.
END OF SECTION
A. Available Products: Subject to compliance with requirements, fire-resistive joint systems that
may be incorporated into the Work include, but are not limited to, those systems indicated in
the Fire-Resistive Joint System Schedule at the end of Part 3.
1. Hilti, Inc.
2. BioFireshield; RectorSeal Corporation.
3. 3M; Fire Protection Products Division.
4. Or approved equal.
2.2 FIRE-RESISTIVE JOINT SYSTEMS
A. Compatibility: Provide fire-resistive joint systems that are compatible with joint substrates,
under conditions of service and application, as demonstrated by fire-resistive joint system
manufacturer based on testing and field experience.
B. Accessories: Provide components of fire-resistive joint systems, including primers and forming
materials, that are needed to install fill materials and to comply with Part 1 "Performance
Requirements" Article. Use only components specified by fire-resistive joint system
manufacturer and approved by the qualified testing and inspecting agency for systems
indicated.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with requirements for
joint configurations, substrates, and other conditions affecting performance of work.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Surface Cleaning: Clean joints immediately before installing fire-resistive joint systems to
comply with fire-resistive joint system manufacturer's written instructions and the following
requirements:
1. Remove from surfaces of joint substrates foreign materials that could interfere with
adhesion of fill materials.
2. Clean joint substrates to produce clean, sound surfaces capable of developing optimum
bond with fill materials. Remove loose particles remaining from cleaning operation.
3. Remove laitance and form-release agents from concrete.
B. Priming: Prime substrates where recommended in writing by fire-resistive joint system
manufacturer using that manufacturer's recommended products and methods. Confine primers
to areas of bond; do not allow spillage and migration onto exposed surfaces.
C. Masking Tape: Use masking tape to prevent fill materials of fire-resistive joint system from
contacting adjoining surfaces that will remain exposed on completion of Work and that would
otherwise be permanently stained or damaged by such contact or by cleaning methods used to
remove smears from fire-resistive joint system materials. Remove tape as soon as possible
A. General: Install fire-resistive joint systems to comply with Part 1 "Performance Requirements"
Article and fire-resistive joint system manufacturer's written installation instructions for
products and applications indicated.
B. Install forming/packing/backing materials and other accessories of types required to support fill
materials during their application and in position needed to produce cross-sectional shapes and
depths required to achieve fire ratings indicated.
C. Install fill materials for fire-resistive joint systems by proven techniques to produce the
following results:
1. Fill voids and cavities formed by openings and forming/packing/backing materials as
required to achieve fire-resistance ratings indicated.
2. Apply fill materials so they contact and adhere to substrates formed by joints.
3. For fill materials that will remain exposed after completing Work, finish to produce
smooth, uniform surfaces that are flush with adjoining finishes.
3.4 FIELD QUALITY CONTROL
A. Inspecting Agency: Engage a qualified independent inspecting agency to inspect fire-resistive
joint systems and prepare inspection reports.
B. Testing Services: Inspecting of completed installations of fire-resistive joint systems shall take
place in successive stages as installation of fire-resistive joint systems proceeds. Do not
proceed with installation of joint systems for the next area until inspecting agency determines
completed work shows compliance with requirements.
1. Inspecting agency shall state in each report whether inspected fire-resistive joint systems
comply with or deviate from requirements.
C. Remove and replace fire-resistive joint systems where inspections indicate that they do not
comply with specified requirements.
D. Additional inspecting, at Contractor's expense, will be performed to determine compliance of
replaced or additional work with specified requirements.
E. Proceed with enclosing fire-resistive joint systems with other construction only after inspection
reports are issued and fire-resistive joint systems comply with requirements.
3.5 CLEANING AND PROTECTING
A. Clean off excess fill materials adjacent to joints as Work progresses by methods and with
cleaning materials that are approved in writing by fire-resistive joint system manufacturers and
that do not damage materials in which openings occur.
B. Provide final protection and maintain conditions during and after installation that ensure fire-
resistive joint systems are without damage or deterioration at time of Substantial Completion.
If damage or deterioration occurs despite such protection, cut out and remove damaged or
deteriorated fire-resistive joint systems immediately and install new materials to produce fire-
resistive joint systems complying with specified requirements.
UL-CLASSIFIED SYSTEM
NUMBER
JOINT WIDTH LESS THAN OR JOINT WIDTH LESS THAN
EQUAL TO 2" OR EQUAL TO 6"
JOINT TYPE F- HILTI 3M BIO- HILTI 3M BIO-
RATIN FIRESHI FIRESHI
G ELD ELD
CONCRETE 1 see note 2 FF-D-0002 N/A** FF-D- FF-D- N/A**
FLOOR-TO- 1026, FF- 1002, FF-
FLOOR D-1039 D-1003,
FF-D-
1004
2 see note 2 FF-D-0002 N/A** FF-D- FF-D- N/A**
1026, FF- 1002, FF-
D-1039 D-1003,
FF-D-
1004
3 see note 2 N/A** N/A** FF-D- N/A** N/A**
1026, FF-
D-1039
EDGE OF 1 see note 2 - N/A** FW-D- FW-D- FW-D-
CONCRETE 1011, FW- 1002, FW- 1023
FLOOR SLAB- D-1012, D-1003,
TO-WALL (also FW-D- FW-D-
see CURTAIN 1013, FW- 1009
WALLS & note D-1021
1))
2 see note 2 - N/A** FW-D- FW-D- FW-D-
1011, FW- 1002, FW- 1023
D-1012, D-1003,
FW-D- FW-D-
1013, FW- 1009
D-1021
3 see note 2 - N/A** FW-D- FW-D- N/A**
1011, FW- 1002, FW-
D-1021 D-1009
CONCRETE OR 1 HW-D- HW-D- HW-D- HW-D- HW-D- HW-D-
BLOCK WALL 0097 0023, HW- 0114 1008, HW- 1003 1023
TO FLAT D-0029 D-1009
CONCRETE
SLAB FLOOR
(TOP-OF-WALL)
2 HW-D- HW-D- HW-D- HW-D- HW-D- HW-D-
0097 0023, HW- 0114 1008, HW- 1003 1023
D-0029 D-1009
3 see note 2 - HW-D- HW-D- HW-D- N/A**
Azura Surgery Center Renalus Crestview 07844-5 07/17
0114 1008 1002,
HW-D-
1007
CONCRETE OR 1 HW-D- HW-D- HW-D- HW-D- 1037 HW-D N/A**
BLOCK WALL 0080, HW- 0022, HW- 0200 1041
TO CONCRETE D-0081, D-0030,
OVER FLUTED HW-D- HW-D-
METAL DECK 0098, HW- 0040HW-
(TOP-OF-WALL) D 0181 D-0013
2 HW-D- HW-D- HW-D- HW-D- 1037 HW-D N/A**
0080, HW- 0022, HW- 0200 1041
D-0081, D-0030,
HW-D- HW-D-
0098, HW- 0040HW-
D 0181 D-0013
3 N/A** N/A** N/A** N/A** N/A**
END OF SECTION
PART 2 - PRODUCTS
2.1 MATERIALS, GENERAL
A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible
with one another and with joint substrates under conditions of service and application, as
demonstrated by sealant manufacturer, based on testing and field experience.
B. VOC Content of Interior Sealants: Provide interior sealants and sealant primers that comply
with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D
(EPA Method 24):
1. Sealants: 250 g/L.
2. Sealant Primers for Nonporous Substrates: 250 g/L.
3. Sealant Primers for Porous Substrates: 775 g/L.
C. Colors of Exposed Joint Sealants: As indicated by manufacturer’s designations.
2.2 JOINT SEALANTS
A. Elastomeric Sealants: Comply with ASTM C 920 and other requirements indicated for each
liquid-applied chemically curing sealant specified, including those referencing ASTM C 920
classifications for type, grade, class, and uses related to exposure and joint substrates.
B. Stain-Test-Response Characteristics: Elastomeric sealants shall be nonstaining to porous
substrates. Provide products that have undergone testing according to ASTM C 1248 and have
not stained porous joint substrates indicated for Project.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with
requirements for joint configuration, installation tolerances, and other conditions affecting joint
sealant performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to
comply with joint sealant manufacturer’s written instructions and the following requirements:
1. Remove all foreign material from joint substrates that could interfere with adhesion of
joint sealant, including dust, paints (except for permanent, protective coatings tested and
approved for sealant adhesion and compatibility by sealant manufacturer), old joint
sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.
2. Clean porous joint substrate surfaces by brushing, grinding, blast cleaning, mechanical
abrading, or a combination of these methods to produce a clean, sound substrate capable
of developing optimum bond with joint sealants. Remove loose particles remaining after
cleaning operations above by vacuuming or blowing out joints with oil-free compressed
air. Porous joint substrates include concrete, masonry and unglazed surfaces of ceramic
tile.
3. Remove laitance and form-release agents from concrete.
4. Clean nonporous surfaces with chemical cleaners or other means that do not stain, harm
substrates, or leave residues capable of interfering with adhesion of joint sealants.
Nonporous joint substrates include the following metal, glass, porcelain enamel and
glazed surfaces of ceramic tile.
B. Joint Priming: Prime joint substrates, where recommended in writing by joint sealant
manufacturer, based on preconstruction joint-sealant-substrate tests or prior experience. Apply
primer to comply with joint sealant manufacturer’s written instructions. Confine primers to
areas of joint sealant bond; do not allow spillage or migration onto adjoining surfaces.
C. Masking Tape: Use masking tape where required to prevent contact of sealant with adjoining
surfaces that otherwise would be permanently stained or damaged by such contact or by
cleaning methods required to remove sealant smears. Remove tape immediately after tooling
without disturbing joint seal.
END OF SECTION
C. Fire-Rated Door, Sidelight and Transom Frame Assemblies: Assemblies complying with
NFPA 80 that are listed and labeled by a testing and inspecting agency acceptable to authorities
having jurisdiction, for fire-protection ratings indicated. Identify each fire door or frame with
UL labels, indicating the applicable fire rating of both door and frame.
1. Temperature-Rise Limit: At vertical exit enclosures and exit passageways, provide doors
that have a maximum transmitted temperature end point of not more than 450 deg F
above ambient after 30 minutes of standard fire-test exposure.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Deliver doors and frames palletized, wrapped, or crated to provide protection during transit and
Project-site storage. Do not use non-vented plastic.
B. Deliver welded frames with two removable spreader bars across bottom of frames, tack welded
to jambs and mullions.
C. General Contractor must inspect and inventory all deliveries within 24 hours of delivery. All
freight damage must be signed as damaged on the Bill of Lading document and reported to the
freight carrier. General Contractor must report to the supplier any missing, incorrect or
damaged goods immediately. Failure to report missing, damaged or incorrect material within
48 hours means the receiver has accepted the shipment as complete and correct.
D. Store hollow metal work under cover at Project site. Place in stacks of five units maximum in a
vertical position with heads up, spaced by blocking, on minimum 4-inch-high wood blocking.
Do not store in a manner that traps excess humidity.
1. Provide minimum 1/4 inch space between each stacked door to permit air circulation.
1.5 PROJECT CONDITIONS
A. Field Measurements: Verify actual dimensions of openings by field measurements before
fabrication.
1.6 COORDINATION
A. Coordinate installation of anchorages for hollow metal frames. Furnish setting drawings,
templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor
bolts, and items with integral anchors. Deliver such items to Project site in time for
installation.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include, but are not limited to, the following:
1. Steelcraft Hollow Metal Door and Frames
2. Curries Hollow Metal Doors and Frames
2.2 MATERIALS
A. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B; suitable
for exposed applications.
Azura Surgery Center Renalus Crestview 08111-2 07/17
B. Hot-Rolled Steel Sheet: ASTM A 1011/A 1011M, Commercial Steel (CS), Type B; free of
scale, pitting, or surface defects; pickled and oiled.
C. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, Commercial Steel (CS), Type B; with
minimum G60 metallic coating.
D. Frame Anchors: ASTM A 591/A 591M, Commercial Steel (CS), 40Z coating designation; mill
phosphatized.
1. For anchors built into exterior walls, steel sheet complying with ASTM A 1008/A 1008M
or ASTM A 1011/A 1011M, hot-dip galvanized according to ASTM A 153/A 153M,
Class B.
E. Inserts, Bolts, and Fasteners: Hot-dip galvanized according to ASTM A 153/A 153M.
F. Powder-Actuated Fasteners in Concrete: Fastener system of type suitable for application
indicated, fabricated from corrosion-resistant materials, with clips or other accessory devices
for attaching hollow metal frames of type indicated.
G. Grout: ASTM C 476, except with a maximum slump of 4 inches, as measured according to
ASTM C 143/C 143M.
H. Mineral-Fiber Insulation: ASTM C 665, Type I (blankets without membrane facing);
consisting of fibers manufactured from slag or rock wool with 6- to 12-lb/cu. ft. density; with
maximum flame-spread and smoke-development indexes of 25 and 50, respectively; passing
ASTM E 136 for combustion characteristics.
I. Glazing: Comply with requirements in Section 08800 – GLASS AND GLAZING.
J. Bituminous Coating: Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-mil dry
film thickness per coat. Provide inert-type noncorrosive compound free of asbestos fibers,
sulfur components, and other deleterious impurities. All bituminous coating to be supplied and
installed by the General Contractor.
2.3 STANDARD STEEL DOORS
A. General: Provide doors of design indicated, not less than thickness indicated; fabricated with
smooth surfaces, without visible joints or seams on exposed faces, unless otherwise indicated.
Comply with ANSI A250.8.
1. Design: Flush panel.
2. Core Construction: Manufacturer’s standard kraft-paper honeycomb, polystyrene,
polyurethane, mineral-board, or vertical steel-stiffener core that produces doors
complying with ANSI A250.8.
a. Fire Door Core: As required to provide fire-protection and temperature-rise ratings
indicated.
b. Thermal-Rated (Insulated) Exterior Doors: Where indicated, provide doors
fabricated with thermal-resistance value (R-value) of not less than 4.0 deg F x h x
sq. ft./Btu when tested according to ASTM C 1363.
3. Top and Bottom Edges: Closed with flush or inverted 0.042-inch-thick end closures or
channels of same material as face sheets.
4. Tolerances: Comply with SDI 117, “Manufacturing Tolerances for Standard Steel Doors
and Frames.”
B. Exterior Doors: Face sheets fabricated from metallic-coated steel sheet. Provide doors
complying with requirements indicated below by referencing ANSI A250.8 for level and model
and ANSI A250.4 for physical-endurance level:
Azura Surgery Center Renalus Crestview 08111-3 07/17
1. Level 3 and Physical Performance Level A (Extra Heavy Duty), Model 1, 1-3/4 inches
thick.
C. Interior Doors: Face sheets fabricated from cold-rolled steel sheet, unless otherwise indicated
to comply with exterior door requirements. Provide doors complying with requirements
indicated below by referencing ANSI A250.8 for level and model and ANSI A250.4 for
physical-endurance level:
1. Level 2 and Physical Performance Level B (Heavy Duty), Model 1, 1-3/4 inches thick.
D. Interior Frame for Hospital Privacy Set at Patient Toilets: Fabricated from cold-rolled steel sheet,
unless otherwise indicated to comply with exterior frame requirements.
1. Fabricate frames without integral stop and prep for jamb mount pivot hinge set per HW
Set 30.
E. Hardware Reinforcement: Fabricate according to ANSI/SDI A250.6 with reinforcement plates
from same material as frames.
F. Plaster Guards: Formed from same material as frames, not less than 0.016-inch thick.
2.5 FRAME ANCHORS
A. Jamb Anchors:
1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit frame size, not
less than 0.042 inch thick, with corrugated or perforated straps not less than 2 inches
wide by 10 inches long; or wire anchors not less than 0.177 inch thick.
2. Stud-Wall Type: Designed to engage stud, welded to back of frames not less than 0.042
inch thick.
3. Compression Type for Drywall Slip-on Frames: Adjustable compression anchors.
4. Post installed Expansion Type for In-Place Concrete or Masonry: Minimum 3/8 inch
diameter bolts with expansion shields or inserts. Provide pipe spacer from frame to wall,
with throat reinforcement plate, welded to frame at each anchor location.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of the
Work.
B. Examine roughing-in for embedded and built-in anchors to verify actual locations before frame
installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Remove welded-in shipping spreaders installed at factory. Restore exposed finish by grinding,
filling, and dressing, as required to make repaired area smooth, flush, and invisible on exposed
faces.
B. Prior to installation, adjust and securely brace welded hollow metal frames for squareness,
alignment, twist, and plumbness to the following tolerances:
1. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90 degrees from
jamb perpendicular to frame head.
END OF SECTION
C. Samples: Three (3) 6” square samples of proposed finish. Note provide photographic evidence that
proposed finish matches existing.
1.3 QUALITY ASSURANCE
A. Wood Doors covered in this section shall be provided and installed by the General Contractor
unless otherwise noted on the drawings.
B. Source Limitations: Obtain flush wood doors through one source from a single manufacturer.
C. Quality Standard: complying with WDMA I.S 1A-11 Industry Standard for Architectural
Wood Flush Doors, Windows and Door Manufacturers’ Association.
D. Fire-Rated Wood Doors: Doors complying with NFPA 80 that are listed and labeled by a
testing and inspecting agency acceptable to authorities having jurisdiction, for fire ratings
indicated, based on testing according to UL 10-C Positive Pressure fire test requirements.
Provide Category A intumescent concealed in door edge.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine doors and installed door frames before hanging doors.
1. Verify that frames comply with indicated requirements for type, size, location, and swing
characteristics, and have been installed with level heads and plumb jambs.
2. Reject doors with defects.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Hardware: Refer to 08710 - DOOR HARDWARE section for type and location. Receive and
retain custody of door hardware furnished for the work of this section under Section 08710 of
these specifications and, except as otherwise directed by the Architect, install all such hardware
in strict accordance with manufacturer’s installation instructions.
B. Manufacturer’s Written Instructions: Install doors to comply with manufacturer’s written
instructions, referenced quality standard, and as indicated.
1. Install fire-rated doors in corresponding fire-rated frames according to NFPA 80.
C. Factory-Fitted Doors: Align in frames for uniform clearance at each edge.
3.3 ADJUSTING
A. Operation: Rehang or replace doors that do not swing or operate freely. Once inserted do not
remove hinge screws from stiles of positive pressure fire doors.
1. Doors shall remain in position without stops.
B. Finished Doors: Replace doors that are damaged or do not comply with requirements. Doors
may be repaired or refinished if work complies with requirements and shows no evidence of
repair or refinishing.
3.4 COMPLIANCE
A. The Owner reserves the right to request and pay for an inspection by a representative of the
referenced organization to determine that the work of this Section has been performed in
accordance with the specified standards.
B. In the event such inspection determines that the work of this Section does not comply with the
specified requirements, immediately remove the non-complying items and replace them with
items complying with the specified requirements, all at no additional cost to the Owner, and
reimburse the Owner for the cost of the inspection.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Provide and install glass, aluminum frames and related hardware provided under Section 08710
as shown on architectural drawings.
1. Exterior Storefront, insulated, 2 inch by 4-1/2 inch profile:
a. Kawneer, VG451T.
Azura Surgery Center Renalus Crestview 08411-3 07/17 Version
b. Approved equal.
c. Finish – Match existing
2. Interior Storefront, 2 inch by 4-1/2 inch profile:
a. Kawneer, VG450-2.
b. Raco Interior OfficeFronts Classic.
c. Approved equal.
d. Finish – Fluropon, Medium Bronze.
3. Exterior Doors, Thermal, Medium Stile (Warm Climates):
a. Kawneer, Series 350.
b. Approved equal.
c. Finish – Match Existing
4. Interior Doors, Medium Stile:
a. Kawneer, 360.
b. Raco Interior OfficeFronts – Series 550.
c. Approved equal.
d. Finish – Match Existing
2.2 MATERIALS
A. Aluminum: Alloy and temper recommended by manufacturer for type of use and finish
indicated.
1. Sheet and Plate: ASTM B 209.
2. Extruded Bars, Rods, Profiles, and Tubes: ASTM B 221.
3. Extruded Structural Pipe and Tubes: ASTM B 429.
4. Structural Profiles: ASTM B 308/B 308M.
5. Welding Rods and Bare Electrodes: AWS A5.10/A5.10M.
B. Steel Reinforcement: With manufacturer’s standard corrosion-resistant primer complying with
SSPC-PS Guide No. 12.00 applied immediately after surface preparation and pretreatment.
Select surface preparation methods according to recommendations in SSPC-SP COM and
prepare surfaces according to applicable SSPC standard.
1. Structural Shapes, Plates, and Bars: ASTM A 36/A 36M.
2. Cold-Rolled Sheet and Strip: ASTM A 1008/A 1008M.
3. Hot-Rolled Sheet and Strip: ASTM A 1011/A 1011M.
2.3 FRAMING SYSTEMS
A. Framing Members: Manufacturer’s standard extruded-aluminum framing members of thickness
required and reinforced as required to support imposed loads.
1. Construction for Exterior Framing: Thermal-break.
B. Brackets and Reinforcements: Manufacturer’s standard high-strength aluminum with
nonstaining, nonferrous shims for aligning system components.
C. Fasteners and Accessories: Manufacturer’s standard corrosion-resistant, nonstaining,
nonbleeding fasteners and accessories compatible with adjacent materials.
1. Where fasteners are subject to loosening or turning out from thermal and structural
movements, wind loads, or vibration, use self-locking devices.
2. Reinforce members as required to receive fastener threads.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas, with Installer present, for compliance with requirements for installation
tolerances and other conditions affecting performance of work.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
1. Comply with manufacturer’s written instructions.
2. Do not install damaged components.
3. Fit joints to produce hairline joints free of burrs and distortion.
4. Rigidly secure non-movement joints.
5. Install anchors with separators and isolators to prevent metal corrosion and electrolytic
deterioration.
6. Seal joints watertight, unless otherwise indicated.
7. Comply with original design and approved shop drawings and governing codes and
regulations.
B. Metal Protection:
1. Where aluminum will contact dissimilar metals, protect against galvanic action by
painting contact surfaces with primer or by applying sealant or tape or installing
nonconductive spacers as recommended by manufacturer for this purpose.
END OF SECTION
B. Product:
1. Double hung, self closing, vertical sliding pass through window.
2. Model No PTW-2436 Pass Thru Window w/Wall Frame
3. Size: 24” W x 36” H (Nominal)
2.2 MATERIALS
A. Window and Frame: Type 304 Stainless Steel. Exposed surfaces polished to #4 finish
B. Glass: 1/4” thick, tempered, clear
C. Shelf: Type 304 Stainless Steel – Size as indicated on drawings.
D. Gaskets: Fully gasketed to prevent passage of air.
2.3 CONSTRUCTION
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas, with Installer present, for compliance with requirements for installation
tolerances and other conditions affecting performance of work.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
1. Comply with manufacturer’s written instructions.
2. Do not install damaged components.
3. Fit joints to produce hairline joints free of burrs and distortion.
4. Rigidly secure non-movement joints.
5. Install anchors with separators and isolators to prevent metal corrosion and electrolytic
deterioration.
6. Seal joints watertight, unless otherwise indicated.
B. Install components plumb and true in alignment with established lines and grades, without warp
or rack.
END OF SECTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Furnishing and installation of all mechanical and electrical finish hardware necessary for all
doors and hardware as specified herein; as enumerated in hardware sets; and as indicated
and required by actual conditions at the building. The hardware shall include the furnishing
of all necessary screws, bolts, expansion shields, drop plates, and all other devices
necessary for the proper application of the hardware. Installation shall include field
modification and preparation of existing doors and/or frames for new hardware being
installed. Provide necessary fillers, Dutchmen, reinforcements, and fasteners for mounting
new hardware and to cover existing door/frame preps.
B. Vendors:
1. All door hardware covered in this section shall be provided and installed by the General
Contractor.
2. Division 6 Section - FINISH CARPENTRY.
3. Division 8 Section - HOLLOW METAL DOORS AND FRAMES.
4. Division 8 Section - WOOD DOORS.
5. Division 8 Section - ALUMINUM FRAMED STOREFRONTS.
6. Section 08720 - AUTOMATIC DOOR OPERATORS for doors with low-energy operators.
7. Division 16 Section - ELECTRICAL for electrical connections including conduit and wiring
for electrified hardware.
C. Specific Omissions: Hardware for the following is specified or indicated elsewhere, unless
specifically listed in the hardware sets:
1. Windows.
2. Cabinets of all kinds, including open wall shelving and locks.
1.3 REFERENCES
A. Applicable state and local building codes and standards.
B. FIRE/LIFE SAFETY
1. NFPA - National Fire Protection Association
a. NFPA 70 – National Electric Code
b. NFPA 80 - Standard for Fire Doors and Fire Windows
c. NFPA 101 - Life Safety Code
d. NFPA 105 - Smoke and Draft Control Door Assemblies
C. UL - Underwriters Laboratories
1. UL 10C - Positive Pressure Test of Fire Door Assemblies
2. UL 1784 - Air Leakage Tests of Door Assemblies
3. UL 305 - Panic Hardware
D. Accessibility
1. ADA - Americans with Disabilities Act
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Approval of manufacturers other than those listed shall be in accordance with paragraph 1.5.A.
B. Note that even though an acceptable substitute manufacturer may be listed, the product must
provide all the functions and features of the specified product or it will not be approved.
C. Hand of Door: Drawings show direction of slide, swing, or hand of each door leaf. Furnish each
item of hardware for proper installation and operation of door movement as shown.
D. Where the hardware specified is not adaptable to the finished shape or size of the members
requiring hardware, furnish suitable types having the same operation and quality as the type
specified, subject to the Architect's approval.
2.2 MATERIALS
A. Fasteners
1. Provide hardware manufactured to conform to published templates, generally prepared for
machine screw installation.
2. Furnish screws for installation with each hardware item. Finish exposed (exposed under any
condition) screws to match hardware finish, or, if exposed in surfaces of other work, to
match finish of this other work as closely as possible including “prepared for paint”
surfaces to receive painted finish.
3. Provide concealed fasteners for hardware units that are exposed when door is closed except
to the extent that no standard units of type specified are available with concealed fasteners.
Do not use thru-bolts for installation where bolt head or nut on opposite face is exposed in
other work unless their use is the only means of reinforcing the work adequately to fasten
the hardware securely. Review door specification and advise Architect if thru-bolts are
required.
4. Hardware shall be installed with the fasteners provided by the hardware manufacturer.
B. Hinges
1. Provide five-knuckle, ball bearing hinges of type, material, and height as outlined in the
following guide for this specification:
a. 1-3/4 inch thick doors, up to and including 36 inches wide:
Azura Surgery Center Renalus Crestview 08710-5 07/17 Version
Exterior: standard weight, BB1191 stainless steel, 4-1/2 inches high
Interior: standard weight, BB1279 steel, 4-1/2 inches high
b. 1-3/4 inch thick doors over 36 inches wide:
Exterior: heavy weight, BB1199 stainless steel, 4-1/2 inches high
Interior: heavy weight, BB1168 steel, 4-1/2 inches high
2. Provide three hinges per door leaf for doors 90 inches or less in height, and one additional
hinge for each 30 inches of additional door height.
3. Provide continuous hinges on doors with lead lining and as scheduled.
a. Continuous Hinge: 790-905, stainless steel, machine screw with adjustment studs.
Hagar.
4. Hinge Pins: Except as otherwise indicated, provide hinge pins as follows:
a. Steel Hinges: Steel pins
b. Non-Ferrous Hinges: Stainless steel pins
c. Out-Swinging Exterior Doors: Non-removable pins
d. Out-Swinging Interior Lockable Doors: Non-removable pins
e. Interior Non-lockable Doors: Non-rising pins
5. Adjust hinge width as required for door, frame, and/or wall conditions to allow proper degree
of opening.
6. Provide hinges with electrified option where specified. Provide with sufficient number and
gage of concealed wires to accommodate electric function of specified hardware. Locate
electric hinge nearest to the electrified locking component.
7. Provide mortar guard for each electrified hinge specified, unless specified in hollow metal
frame specification.
C. Emergency Release Pivots
1. Provide emergency release pivot sets, where specified, offset-hung to allow door to swing
open in opposite direction unless detailed otherwise.
D. Double Lipped Strike
1. Provide double lip strike, where specified, offset-hung to allow door to swing open in
opposite direction unless detailed otherwise. Size for specific frame depth. Coordinate
special latchbolt-hole location and/or special template, as required, to operate with the
mortise lock being used as specified.
2. Provide a compatible emergency stop/release as recommended by the manufacturer of the
double lip strike or engineered to operate with the double lip strike.
E. Emergency Stop/Release
1. Provide emergency stop/release, where specified, for doors with double lip strikes offset-
hung to allow door to swing open in opposite direction unless detailed otherwise.
F. Flush Bolts
1. Provide automatic and manual flush bolts with stainless steel face plates, levers, and guides
and strikes. Provide 12 inch steel rods at doors up to 90 inches in height. Top rods at
manual flush bolts for doors over 90 inches in height shall be increased by 6 inches for each
additional 6 inches of door height. Provide dust-proof strikes at each bottom flush bolt.
G. Coordinators
1. Provide a bar-type coordinating device, surface applied to the underside of the stop at the
frame head where pairs of doors are equipped with automatic flush bolts, an astragal, or
other hardware that requires synchronized closing of the doors.
2. Provide a filler bar of the correct length for the unit to span the entire width of the opening,
and appropriate brackets for parallel arm door closers and surface vertical rod exit device
strikes. Factory-prep coordinators for vertical rod devices if required.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Prior to installation of any hardware, examine all doors, frames, walls and related items for
conditions that would prevent proper installation of finish hardware. Correct all defects prior to
proceeding with installation.
3.2 INSTALLATION
A. Coordination:
HW SET: 06 NON-SECURE ENTRANCE - ALUM STOREFRONT OR EXISTING- SGLE WITH PANIC DEVICE
– EMERGENCY EGRESS FROM PRE/POST OP
HW SET: 07 SECURE ENTRANCE - ALUM SGLE WITH ACCESS CONTROL PANIC DEVICE – STAFF
ENTRANCE
HW SET: 07A SECURE ENTRANCE - ALUM SGLE WITH ACCESS CONTROL– MECH ROOM
HW SET: 08 SECURE MAIN ENTRANCE - ALUM SGLE WITH PANIC DEVICE, ELEC STRIKE, AND AUTO
OPERATOR- PATIENT ENTRANCE
HW SET: 18EX SECURE SNGL EXTERIOR DOOR - HOLLOW METAL SGLE – SPRINKLER, VACUUM
3 EA HINGES B1191 4-1/2 X 4-1/2 NRP HAG
1 EA LOCKSET B581BD D X 626 FAL
1 EA PERMANENT CORE 80-036 B123 KEYWAY SCH
1 EA CONSTRUCTION CORE 80-035 SCH
1 EA SURFACE CLOSER SC71 SS FAL
1 SET SEALS 303AS PEM
1 EA DRIP CAP 346C PEM
1 EA THRESHOLD 2005AT PEM
HW SET: 19 EMERGENCY EXIT/EGRESS DOOR - HOLLOW METAL SGLE WITH RIM PANIC HARDWARE –
EMERGENCY EXIT OFF PRE-POST RECOVERY ROOM
HW SET: 20 SECURE ENTRANCE - HOLLOW METAL PR WITH PANIC DEVICE NIGHT LATCH FUNCTION X
FLUSH BOLT – DOUBLE DELIVERY DOORS
HW SET: 22 INTERIOR - NON-RATED SGLE WITH PASSAGE – STAFF LOUNGE, DOUBLE OCCUPANCY
TOILET, CORRIDORS, SOILED UTILITY, CLEAN UTILITY, STERILE SUPPLY, MED WASTE, RECEIVING
HW SET: 28 INTERIOR - RATED OR NON-RATED SGLE WITH PASSAGE X CLOSER – CORRIDORS, MED
GAS, JANITOR
HW SET: 29 INTERIOR - RATED OR NON-RATED SGLE WITH PRIVACY X CLOSER – STAFF TOILET
HW SET: 30 INTERIOR - RATED OR NON-RATED SGLE WITH HOSPITAL PRIVACY X CLOSER – IN/OUT
SWINGING PATIENT TOILET AND CHANGING ROOM
HW SET: 35 INTERIOR - RATED OR NON-RATED SGLE WITH POWERED OPENER– PRE-POST TO SEMI-
RESTRICTED COORIDOR
HW SET: 36 INTERIOR - RATED OR NON-RATED SGLE WITH ACCESS CONTROL LOCKSET X CLOSER –
WAITING ROOM TO ADMINISTRATIVE AREA
END OF SECTION
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, provide products by the following:
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine conditions, with Installer present, for compliance with requirements for installation
tolerances, door and frame supports, and other conditions affecting performance of automatic
door operators.
1. For the record, prepare written report, endorsed by Installer, listing conditions detrimental
to performance.
B. Examine roughing-in for electrical systems to verify actual locations of power connections
before automatic door operator installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General: Install complete automatic door operator system, including activation and safety
devices, control wiring, and remote power units.
B. Power Door Operator Installation Standard: Comply with BHMA A156.10 for installation.
C. Low-Energy Power Door Operator Installation Standard: Comply with BHMA A156.19 for
installation.
D. Automatic Door Operators: Install door operator system, including control wiring, as follows:
1. Refer to Division 16 - ELECTRICAL for connection to electrical power distribution
system.
E. Activation and Safety Devices: Install devices and wiring, including connections to automatic
door operators, according to BHMA A156.19 and as follows:
1. Wall Switches: Provide push plates on both sides of each opening indicated to receive
automatic door operators.
F. Connect wiring according to Division 16 - ELECTRICAL.
3.3 FIELD QUALITY CONTROL
A. Testing Agency: Contractor will engage a qualified independent testing and inspecting agency
to perform field tests and inspections and prepare test reports.
B. Testing and Inspecting: After installation has been completed, testing and inspecting of each
automatic door operator shall be performed to verify compliance with applicable BHMA
standards.
1. Inspection Report: Submit report in writing to Architect and Contractor within 24 hours
after inspection.
C. Remove and replace automatic door operators where test results indicate they do not comply
with specified requirements.
END OF SECTION
PART 2 - PRODUCTS
2.1 INSULATING-GLASS UNITS
A. Insulating-Glass Units for Vertical Glazing: 1 inch thick insulating glass consisting of two lites
of 1/4 inch glass, low-e coating on the No. 2 surface and argon gas filled. Provide one of the
following or equal, Match existing color and tint:
1. VE1-2M by Viracon.
a. Visible Light Transmittance: 70 percent.
b. Reflectance Visible Light: 11 percent.
c. U Value (Winter): 0.25.
d. Shading Coefficient: 0.43.
e. Solar Heat Gain Coefficient: 0.37.
2. Solarban 60 by PPG Industries.
a. Visible Light Transmittance: 70 percent.
Azura Surgery Center Renalus Crestview 08800-5 07/17 Version
b. Reflectance Visible Light: 11 percent.
c. U Value (Winter): 0.29.
d. Shading Coefficient: 0.44.
e. Solar Heat Gain Coefficient: 0.38.
3. SN-68 by Guardian Industries.
a. Visible Light Transmittance: 68 percent.
b. Reflectance Visible Light: 10 percent.
c. U Value (Winter): 0.29.
d. Shading Coefficient: 0.43.
e. Solar Heat Gain Coefficient: 0.37.
2.2 INTERIOR GLAZING
A. Tempered Float Glass: ASTM C 1048, Type I (transparent flat glass), Quality-Q3, Kind FT,
1/4 inch thick unless indicated otherwise.
B. Wired Glass: ASTM C 1036, Type II (patterned and wired flat glass), Class 1 (clear), Quality-
Q-6, form 1 and square mesh pattern.
C. Radiation Shielding Glazing: Meeting requirements as specified by Owner’s radiation shielding
report
1. Refer to 13090 – Radiation Shielding Protection.
D. Glazing Film: Frosted type, to be selected by Architect.
2.3 GLAZING SEALANTS
A. General: Provide products of type indicated, complying with the following requirements:
1. Compatibility: Verify glazing sealants that are compatible with one another and with
other materials they will contact, including glass products, seals of insulating-glass units,
and glazing channel substrates, under conditions of service and application, as
demonstrated by sealant manufacturer based on testing and field experience.
2. Suitability: Comply with sealant and glass manufacturer’s written instructions for
selecting glazing sealants suitable for applications indicated and for conditions existing at
time of installation.
3. Colors of Exposed Glazing Sealants: As selected by Architect from manufacturer’s full
range.
B. Elastomeric Glazing Sealants: Comply with ASTM C 920 and other requirements indicated for
each liquid-applied chemically curing sealant specified, including those referencing
ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint
substrates.
1. Single-Component Neutral- and Basic-Curing Silicone Glazing Sealants:
a. Dow Corning Corporation; 790.
b. GE Silicones; SilPruf LM SCS2700.
c. Tremco; Spectrem 1 (Basic).
2.4 GLAZING TAPES
A. Back-Bedding Mastic Glazing Tapes: Preformed, butyl-based elastomeric tape with a solids
content of 100 percent; nonstaining and nonmigrating in contact with nonporous surfaces; with
or without spacer rod as recommended in writing by tape and glass manufacturers for
application indicated; packaged on rolls with a release paper backing; and complying with
ASTM C 1281 and AAMA 800 for project conditions.
Azura Surgery Center Renalus Crestview 08800-6 07/17 Version
B. Expanded Cellular Glazing Tapes: Closed-cell, PVC foam tapes; factory coated with adhesive
on both surfaces; packaged on rolls with release liner protecting adhesive; and complying with
AAMA 800 for the following types:
1. Type 1, for glazing applications in which tape acts as the primary sealant.
2. Type 2, for glazing applications in which tape is used in combination with a full bead of
liquid sealant.
2.5 MISCELLANEOUS GLAZING MATERIALS
A. General: Provide products of material, size, and shape complying with referenced glazing
standard, requirements of manufacturers of glass and other glazing materials for application
indicated, and with a proven record of compatibility with surfaces contacted in installation.
B. Cleaners, Primers, and Sealers: Types recommended by sealant or gasket manufacturer.
C. Setting Blocks: Elastomeric material with a Shore, Type A durometer hardness of 85, plus or
minus 5.
D. Spacers: Elastomeric blocks or continuous extrusions with a Shore, Type A durometer
hardness required by glass manufacturer to maintain glass lites in place for installation
indicated.
E. Edge Blocks: Elastomeric material of hardness needed to limit glass lateral movement (side
walking).
2.6 FABRICATION OF GLAZING UNITS
A. Fabricate glazing units in sizes required to glaze openings indicated for Project, with edge and
face clearances, edge and surface conditions, and bite complying with written instructions of
product manufacturer and referenced glazing publications, to comply with system performance
requirements.
B. Clean-cut or flat-grind vertical edges of butt-glazed monolithic lites in a manner that produces
square edges with slight kerfs at junctions with outdoor and indoor faces.
C. Grind smooth and polish exposed glass edges and corners.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine framing glazing, with Installer present, for compliance with the following:
1. Manufacturing and installation tolerances, including those for size, squareness, and
offsets at corners.
2. Presence and functioning of weep system.
3. Minimum required face or edge clearances.
4. Effective sealing between joints of glass-framing members.
5. Do not remove labels from glass until so directed by the architect.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Clean glazing channels and other framing members receiving glass immediately before glazing.
Remove coatings not firmly bonded to substrates.
END OF SECTION
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and substrates, with Installer present, and including welded hollow metal frames
and framing, for compliance with requirements and other conditions affecting performance.
B. Examine panels before installation. Reject panels that are wet, moisture damaged, and mold
damaged.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Suspended Assemblies: Coordinate installation of suspension systems with installation of
overhead structure to ensure that inserts and other provisions for anchorages to building
structure have been installed to receive hangers at spacing required to support the Work and
that hangers will develop their full strength.
1. Furnish concrete inserts and other devices indicated to other trades for installation in
advance of time needed for coordination and construction.
B. Coordination with Sprayed Fire-Resistive Materials:
1. Before sprayed fire-resistive materials are applied, attach offset anchor plates or ceiling
runners (tracks) to surfaces indicated to receive sprayed fire-resistive materials. Where
offset anchor plates are required, provide continuous plates fastened to building structure
not more than 24 inches o.c.
2. After sprayed fire-resistive materials are applied, remove them only to extent necessary
for installation of non-load-bearing steel framing. Do not reduce thickness of fire-
resistive materials below that required for fire-resistance ratings indicated. Protect
adjacent fire-resistive materials from damage.
3.3 INSTALLATION, GENERAL
A. Installation Standard: ASTM C 754. Also comply with requirements in ASTM C 840 that
apply to framing installation.
B. Install supplementary framing, and blocking to support fixtures, equipment services, heavy
trim, grab bars, toilet accessories, furnishings, or similar construction.
C. Install bracing at terminations in assemblies.
D. Do not bridge building control and expansion joints with non-load-bearing steel framing
members. Frame both sides of joints independently.
B. Install with acrylic coated water barrier side facing away from framings, so that finishes shall be applied
to coated side.
END OF SECTION
PART 2 - PRODUCTS
2.1 TILE SCHEDULE
A. Floor Tile: Interior floor installation on concrete; thin-set mortar; TCA F113 and
ANSI A108.5.
1. Tile Type: See Finish Schedule
2. Thin-Set Mortar: Latex-Portland cement mortar
a. Custom Building Products ProLite Fortified Mortar
b. Laticrete 254 Platinu
3. Grout: Polymer-modified unsanded grout.
a. Custom Building Products Prism SureColor Grout (Prism can be applied from
1/16" to 1/2")
b. Laticrete PermaColor Grout
4. Joint Width: 3/16 inch
B. Colors: Provide colors of exposed sealants to match colors of grout in tile adjoining sealed
joints, unless otherwise indicated.
C. One-Part, Mildew-Resistant Silicone Sealant: ASTM C 920; Type S; Grade NS; Class 25;
Uses NT, G, A, and, as applicable to nonporous joint substrates indicated, O; formulated with
fungicide, intended for sealing interior ceramic tile joints and other nonporous substrates that
are subject to in-service exposures of high humidity and extreme temperatures.
1. Available Products:
a. Laticrete Latasil 100% silicone caulk
b. Custom Building Products 100% Silicone Commercial Sealant (27 Colors)
c. Dow Corning Corporation; Dow Corning 786
d. GE Silicones; Sanitary 1700
e. Pecora Corporation; Pecora 898 Sanitary Silicone Sealant
f. Tremco, Inc.; Tremsil 600 White
D. Multipart, Pourable Urethane Sealant for Use T: ASTM C 920; Type M; Grade P; Class 25;
Uses T, M, A, and, as applicable to joint substrates indicated, O.
1. Available Products:
a. Bostik; Chem-Calk 550
b. Mameco International, Inc.; Vulkem 245
Azura Surgery Center Renalus Crestview 09300-5 07/17
c. Pecora Corporation; NR-200 Urexpan
d. Tremco, Inc.; THC-900
2.7 MIXING MORTARS AND GROUT
A. Mix mortars and grouts to comply with referenced standards and mortar and grout
manufacturers’ written instructions.
B. Add materials, water, and additives in accurate proportions.
C. Obtain and use type of mixing equipment, mixer speeds, mixing containers, mixing time, and
other procedures to produce mortars and grouts of uniform quality with optimum performance
characteristics for installations indicated.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions where tile will be installed, with Installer present, for
compliance with requirements for installation tolerances and other conditions affecting
performance of installed tile.
1. Verify that substrates for setting tile are firm; dry; clean; free of oil, waxy films, and
curing compounds; and within flatness tolerances required by referenced ANSI A108
Series of tile installation standards for installations indicated.
2. Verify that installation of grounds, anchors, recessed frames, electrical and mechanical
units of work, and similar items located in or behind tile has been completed before
installing tile.
3. Verify that joints and cracks in tile substrates are coordinated with tile joint locations; if
not coordinated, adjust joint locations in consultation with Architect.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Remove coatings, including curing compounds and other substances that contain soap, wax, oil,
or silicone, that are incompatible with tile-setting materials.
B. Provide concrete substrates for tile floors that comply with flatness tolerances specified in
referenced ANSI A108 Series of tile installation standards.
1. Fill cracks, holes, and depressions with trowelable leveling and patching compound
according to tile-setting material manufacturer’s written instructions. Use product
specifically recommended by tile-setting material manufacturer.
2. Remove protrusions, bumps, and ridges by sanding or grinding.
C. Blending: For tile exhibiting color variations within ranges selected during Sample submittals,
verify that tile has been factory blended and packaged so tile units taken from one package
show same range of colors as those taken from other packages and match approved Samples. If
not factory blended, either return to manufacturer or blend tiles at Project site before installing.
3.3 INSTALLATION, GENERAL
A. ANSI Tile Installation Standards: Comply with parts of ANSI A108 Series “Specifications for
Installation of Ceramic Tile” that apply to types of setting and grouting materials and to
methods indicated in ceramic tile installation schedules.
B. TCA Installation Guidelines: TCA’s “Handbook for Ceramic Tile Installation.” Comply with
TCA installation methods indicated in ceramic tile installation schedules.
END OF SECTION
PART 2 - PRODUCTS
2.1 ACOUSTICAL PANELS, GENERAL
A. Products: Subject to compliance with specified requirements, provide one of the following
products for each type indicated.
B. ACT-1: General office use and as indicated.
1. Manufacturer and Model Number:
a. Armstrong Fine Fissured
Azura Surgery Center Renalus Crestview 09511-2 07/17
2. Panel Size: 24 inches by 24 inches by 3/4 inch.
3. Panel Mounting: Square edge.
4. Noise Reduction Coefficient (NRC): Not less than 0.50.
5. Ceiling Attenuation Class (CAC): Not less than 35.
6. Color: White.
7. Grid Material: Painted aluminum. ASTM C 635, standard profile
8. Grid Face Width: 15/16 inch.
C. ACT-2: Semi Restricted areas.
1. Manufacturer and Model Number:
a. Armstrong: Clean Room VL, 870- Class A
2. Panel Size: 24 inches by 48 inches.
3. Panel Mounting: Square edge.
4. Noise Reduction Coefficient (NRC): Not less than 0.50.
5. Ceiling Attenuation Class (CAC): Not less than 40.
6. Color: White.
7. Grid Material: Painted aluminum.
8. Grid Face Width: 15/16 inch.
2.2 METAL SUSPENSION SYSTEMS
A. Metal Suspension System Standard: Provide manufacturer’s standard direct-hung metal
suspension systems of types, structural classifications, and finishes indicated that comply with
applicable requirements in ASTM C 635.
1. Manufacturer and Model Number:
a. Certainteed - 15/16" Classic Aluminum Capped Stab System.
b. USG – Donn DX/DXL Suspension System.
c. Armstrong – Prelude ML 15/16" Exposed Tee System.
2. Structural Classification: As recommended by manufacturer for the specified seismic
region.
3. Cross Tee End Condition:
a. Stainless Steel stab-in clip.
b. Hook-over end tab.
4. Face Design: Double web construction.
5. Cap Material:
a. Hot-dipped galvanized steel.
b. Aluminum capped components (for humid environments).
6. Color: White, prefinished.
7. Grid Face Width: 15/16".
B. Attachment Devices: Size for five times the design load indicated in ASTM C 635, Table 1,
“Direct Hung,” unless otherwise indicated.
1. Anchors in Concrete: Anchors with holes or loops for attaching hangers of type indicated
and with capability to sustain, without failure, a load equal to five times that imposed by
ceiling construction, as determined by testing per ASTM E 488 or ASTM E 1512 as
applicable, conducted by a qualified testing and inspecting agency; zinc-plated for Class
SC1 service.
2. Power-Actuated Fasteners in Concrete: Fastener system of type suitable for application
indicated, fabricated from corrosion-resistant materials, with clips or other accessory
devices for attaching hangers of type indicated, and with capability to sustain, without
failure, a load equal to 10 times that imposed by ceiling construction, as determined by
testing per ASTM E 1190, conducted by a qualified testing and inspecting agency.
Azura Surgery Center Renalus Crestview 09511-3 07/17
C. Wire Hangers, Braces, and Ties: Provide wires complying with the following requirements:
1. Zinc-Coated Carbon-Steel Wire: ASTM A 641/A 641M, Class 1 zinc coating, soft
temper.
2. Size: Select wire diameter so its stress at three times hanger design load (ASTM C 635,
Table 1, “Direct Hung”) will be less than yield stress of wire, but provide not less than
0.106 diameter wire.
D. Hold-Down Clips: At vestibules and areas subject to wind uplift, provide manufacturer’s
standard hold-down clips spaced 24 inches on all cross tees.
2.3 METAL EDGE MOLDINGS AND TRIM
A. Roll-Formed Sheet-Metal Edge Moldings and Trim: Type and profile indicated or, if not
indicated, manufacturer’s standard moldings for edges and penetrations that fit acoustical panel
edge details and suspension systems indicated; formed from sheet metal of same material,
finish, and color as that used for exposed flanges of suspension system runners.
1. For lay-in panels with reveal edge details, provide stepped edge molding that forms
reveal of same depth and width as that formed between edge of panel and flange at
exposed suspension member.
2. For circular penetrations of ceiling, provide edge moldings fabricated to diameter
required to fit penetration exactly.
3. For narrow-face suspension systems, provide suspension system and manufacturer’s
standard edge moldings that match width and configuration of exposed runners.
2.4 ACOUSTICAL SEALANT
A. Acoustical Sealant for Concealed Joints: Manufacturer’s standard nondrying, non-hardening,
non-skinning, nonstaining, gunnable, synthetic-rubber sealant, with a VOC content of 250 g/L
or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24), recommended
for sealing interior concealed joints to reduce airborne sound transmission.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, including structural framing to which acoustical
panel ceilings attach or abut, with Installer present, for compliance with requirements specified
in this and other Sections that affect ceiling installation and anchorage, and with requirements
for installation tolerances and other conditions affecting performance of acoustical panel
ceilings.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Measure each ceiling area and establish layout of acoustical panels to balance border widths at
opposite edges of each ceiling. Avoid using less-than-half-width panels at borders, and comply
with layout shown on reflected ceiling plans.
3.3 INSTALLATION
A. General: Install acoustical panel ceilings to comply with ASTM C 636 per manufacturer’s
written instructions and CISCA’s “Ceiling Systems Handbook.”
B. Suspend ceiling hangers from building’s structural members and as follows:
1. Install hangers plumb and free from contact with insulation or other objects within ceiling
plenum that are not part of supporting structure or of ceiling suspension system.
Azura Surgery Center Renalus Crestview 09511-4 07/17
2. Splay hangers only where required to miss obstructions; offset resulting horizontal forces
by bracing, countersplaying, or other equally effective means.
3. Where width of ducts and other construction within ceiling plenum produces hanger
spacings that interfere with location of hangers at spacings required to support standard
suspension system members, install supplemental suspension members and hangers in
form of trapezes or equivalent devices. Size supplemental suspension members and
hangers to support ceiling loads within performance limits established by referenced
standards and publications.
4. Secure wire hangers to ceiling suspension members and to supports above with a
minimum of three tight turns. Connect hangers directly either to structures or to inserts,
eye screws, or other devices that are secure and appropriate for substrate, and that will
not deteriorate or otherwise fail due to age, corrosion, or elevated temperatures.
5. Do not support ceilings directly from permanent metal forms or floor deck. Fasten
hangers to cast-in-place hanger inserts, post-installed mechanical or adhesive anchors, or
power-actuated fasteners that extend through forms into concrete.
6. Do not attach hangers to steel deck tabs.
7. Space hangers not more than 48 o.c. along each member supported directly from hangers,
unless otherwise indicated; provide hangers not more than 8 inches from ends of each
member.
C. Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and
where necessary to conceal edges of acoustical panels.
1. Apply acoustical sealant in a continuous ribbon concealed on back of vertical legs of wall
moldings before they are installed.
2. Screw attach moldings to substrate at intervals not more than 16 inches o.c. and not more
than 3 inches from ends, leveling with ceiling suspension system to a tolerance of 1/8
inch in 12 feet. Miter corners accurately and connect securely.
3. Do not use exposed fasteners, including pop rivets, on moldings and trim.
D. Install suspension system runners so they are square and securely interlocked with one another.
Remove and replace dented, bent, or kinked members.
E. Install acoustical panels with undamaged edges and fit accurately into suspension system
runners and edge moldings. Scribe and cut panels at borders and penetrations to provide a neat,
precise fit.
1. Paint cut edges of panel remaining exposed after installation; match color of exposed
panel surfaces using coating recommended in writing for this purpose by acoustical panel
manufacturer.
2. Install hold-down clips in areas indicated, in areas required by authorities having
jurisdiction, and for fire-resistance ratings; space as recommended by panel
manufacturer’s written instructions, unless otherwise indicated.
3.4 CLEANING
A. Clean exposed surfaces of acoustical panel ceilings, including trim, edge moldings, and
suspension system members. Comply with manufacturer’s written instructions for cleaning and
touchup of minor finish damage. Remove and replace ceiling components that cannot be
successfully cleaned and repaired to permanently eliminate evidence of damage.
END OF SECTION
PART 2 - PRODUCTS
2.1 DISTRIBUTERS:
A. Mannington Commercial.
2.2 HETEROGENEOUS SHEET FLOORING
A. Sheet Vinyl – Field Color (Woodgrain), Typical: ASTM F-1303, Type 1, Grade 1, Class B.
1. Product: Realities, by Mannington
2. Style and colors: Refer to Finish Schedule
3. Thickness: .080 inch
4. Size: 12'-0" wide x 37'-0" Long, Roll stock (standard)
B. Sheet Vinyl - Accent (Woodgrain), Typical: ASTM F-1913, Type 1, Grade 1, Class B.
1. Product: Realities, by Mannington
2. Style and colors: Refer to Finish Schedule
3. Thickness: .080 inch
4. Size: 12'-0" wide x 37'-0" Long, Roll stock (standard)
A. For a documented moisture vapor emission rate (MVER), no more than 8 lb/1000 sq. ft. as
determined by ASTM F-1869 test method, and no more than 90% RH, PH between 5 and 9, as
determined by ASTM F-2170, use the following products unless in accordance with Owner’s
Moisture Testing Agency recommendations:
1. IVC iGrip Permanent Adhesive for Sheet Vinyl. No Substitution permitted.
a. 180 sq. ft. per gallon applied with recommended notched trowel.
b. Apply in full compliance with manufacturer instructions.
i. Apply IVC iGrip Permanent Adhesive for Sheet Vinyl to the substrate using the
appropriate trowel. If a seam is required, leave and 18” dry zone at the edge of the
seam. Then follow the manufacturer’s Seaming Instructions in a Permanent Full
Spread Bond Installation (Commercial)
C. When the moisture vapor emission rate (MVER) is above 12 lb/1000 sq. ft. as determined by
ASTM F-1869 test method and not more than 90% RH as determined by ASTM F-2170:
D. For high concrete alkali conditions (above 10 pH), concrete slab must be washed with an auto-
scrubber and clean water to reduce pH to below 10 prior to flooring installation.
PART 3 - EXECUTION
3.01 PREPARATION
A. General: Prepare and clean substrates according to resilient flooring manufacturer’s written
instructions for substrate indicated.
B. Concrete Substrates: Provide sound concrete surfaces free of laitance, glaze, efflorescence,
curing compounds, form-release agents, dust, dirt, grease, oil, and other contaminants
incompatible with resinous flooring.
1. Prepare floor substrate in accordance with ASTM F710-11, ‘Standard Practice for
Preparing Concrete Floors to Receive Resilient Flooring.’
2. Repair damaged and deteriorated concrete according to resilient flooring manufacturer’s
written recommendations.
C. Slab Moisture and Alkali Testing:
1. Provide access for and cooperate with Owner’s Moisture Testing Agency.
2. Maintain ambient temperatures of not less than 65 F or more than 85 F in spaces to
receive testing for 48 hours prior to commencement of and during testing.
3. Maintain relative humidity between 40 and 60 percent in spaces to receive testing for 48
hours prior to commencement of and during testing.
4. Notify Owner’s Moisture Testing Agency no less than 30 calendar days prior to the
building being enclosed and temperature and relative humidity meeting the requirements
for testing.
5. Notify Owner’s Moisture Testing Agency no less than 10 working days prior to
commencement of testing.
6. Moisture Testing to commence no less than 12 working days prior to scheduled flooring
installation.
7. Owner’s Moisture Testing Agency will require no more than 7 working days for testing
on Site and issuing Moisture Testing Report.
8. Perform anhydrous calcium chloride test in accordance with ASTM F 1869-11, Standard
Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using
Anhydrous Calcium Chloride and manufacturer’s instruction.
a. The number of tests required is determined by the square footage of the project:
i. Three (3) tests are required for the first 1,000 square feet, and One (1) additional test
for each 1,000 square feet or fraction thereof.
9. Perform relative humidity test in accordance with ASTM 2170-11 Standard Test Method
for Determining Relative Humidity in Concrete Floor Slabs Using In Situ Probes.
a. The number of tests required is determined by the square-footage of the project:
3.09 WARRANTIES
A. Mannington Commercial Flooring provides a 10 year warranty to Fresenius Medical Care on all
flooring installations with Mannington products that are installed according to the
manufacturer's installation instructions. Proper slab testing must be in place prior to flooring
installation. All installations must be documented with flooring and adhesive material purchase
orders and slab moisture-testing reports in order to achieve the full flooring installation warranty
from Mannington.
END OF SECTION
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. The work shall consist of preparation of the substrate, the furnishing and application of a cementitious
urethane based self-leveling seamless flooring system with decorative chip broadcast and Epoxy
broadcast and topcoats.
B. The system shall have the color and texture as specified by the Owner with a nominal thickness of
3/16 inch. It shall be applied to the prepared area(s) as defined in the plans strictly in accordance with
the Manufacturer's recommendations.
C. Cove base (if required) to be applied where noted on plans and per manufacturers standard details un-
less otherwise noted
1.4 SUBMITTALS
A. Product Data: Latest edition of Manufacturer's literature including performance data and installation
procedures.
B. Manufacturer’s Material Safety Data Sheet (MSDS) for each product being used.
C. Samples: A 3 x 3 inch square sample of the proposed system. Color, texture, and thickness shall be
representative of overall appearance of finished system subject to normal tolerances.
A. The Manufacturer shall have a minimum of 10 years experience in the production, sales, and technical
support of epoxy and urethane industrial flooring and related materials.
B. The Applicator shall have experience in installation of the flooring system as confirmed by the manu-
facturer in all phases of surface preparation and application of the product specified.
C. No requests for substitutions shall be considered that would change the generic type of the specified
system.
D. System shall be in compliance with requirements of United States Department of Agriculture (USDA),
Food, Drug Administration (FDA), and local Health Department.
E. System shall be in compliance with the Indoor Air Quality requirements of California section
01350 as verified by a qualified independent testing laboratory.
1. The Applicator shall be provided with a dry storage area for all components. The area shall be
between 60 F and 85 F, dry, out of direct sunlight and in accordance with the Manufacturer's rec-
ommendations and relevant health and safety regulations.
2. Copies of Material Safety Data Sheets (MSDS) for all components shall be kept on site for review
by the Engineer or other personnel.
C. Waste Disposal
1. The Applicator shall be provided with adequate disposal facilities for non-hazardous waste gener-
ated during installation of the system.
A. Site Requirements
1. Application may proceed while air, material and substrate temperatures are between 60 F and 85
F providing the substrate temperature is above the dew point. Outside of this range, the Manu-
facturer shall be consulted.
2. The relative humidity in the specific location of the application shall be less than 85 % and the
surface temperature shall be at least 5 F above the dew point.
3. The Applicator shall ensure that adequate ventilation is available for the work area. This shall
include the use of manufacturer’s approved fans, smooth bore tubing and closure of the work ar-
ea.
4. The Applicator shall be supplied with adequate lighting equal to the final lighting level during
the preparation and installation of the system.
1. Concrete shall be moisture cured for a minimum of 3 days and have fully cured a minimum of 5
days in accordance with ACI-308 prior to the application of the coating system pending mois-
ture tests.
2. Concrete shall have a flat rubbed finish, float or light steel trowel finish (a hard steel trowel finish
is neither necessary nor desirable).
3. Sealers and curing agents should not to be used.
4. Concrete shall have minimum design strength of 3.500 psi. and a maximum water/cement ratio
of 0.45
5. Concrete surfaces on grade shall have been constructed with a vapor barrier to protect against the
effects of vapor transmission and possible delamination of the system.
.
C. Safety Requirements
1. All open flames and spark-producing equipment shall be removed from the work area prior to
commencement of application.
1.8 WARRANTY
A. Dur-A-Flex, Inc. warrants that material shipped to buyers at the time of shipment substantially free
from material defects and will perform substantially to Dur-A-Flex, Inc. published literature if used in
accordance with the latest prescribed procedures and prior to the expiration date.
B. Dur-A-Flex, Inc. liability with respect to this warranty is strictly limited to the value of the material
purchase.
PART 2 – PRODUCTS
2.1 FLOORING
A. Dur-A-Flex, Inc, Hybri-Flex EC (self leveling chip broadcast ), epoxy/aliphatic urethane topcoat
seamless flooring system.
1. System Materials:
a. Topping: Dur-A-Flex, Inc, Poly-Crete MD resin, hardener and SL aggregate.
b. The broadcast aggregate shall be Dur-A-Flex, Inc. Macro or Micro chip.
c. Broadcast: Dur-A-Flex, Inc. Dur-A-Glaze #4, epoxy based two-component resin.
d. Seal coats: Dur-A-Flex, Inc Dur-A-Glaze #4, epoxy-based, two-component resin.
e. Top coat: Dur-A-Flex, Inc. Armor Top aliphatic urethane 2 component resin with grit.
2. Patch Materials
a. Shallow Fill and Patching: Use Dur-A-Flex, Inc. Poly-Crete MD (up to ¼ inch).
b. Deep Fill and Sloping Material (over ¼ inch): Use Dur-A-Flex, Inc. Poly-Crete WR.
2.2 MANUFACTURER
A. Dur-A-Flex, Inc., 95 Goodwin Street, East Hartford, CT 06108, Phone: (860) 528-9838, Fax: (860)
528-2802
B. Manufacturer of Approved System shall be single source and made in the USA.
A. Topping: Poly-Crete SL
1. Percent Reactive: 100 %
2. VOC: 0 g/L
3. Bond Strength to Concrete ASTM D 4541: 400 psi, substrates fails
4. Compressive Strength, ASTM C 579: 9,000 psi
5. Tensile Strength, ASTM D 638: 2,175 psi
6. Flexural Strength, ASTM D 790 : 5,076 psi
7. Impact Resistance @ 125 mils, MIL D-3134: 160 inch lbs
No visible damage or deterioration
PART 3 – EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas and conditions, with Applicator present, for compliance with requirements
for maximum moisture content, installation tolerances and other conditions affecting flooring perfor-
mance.
1. Verify that substrates and conditions are satisfactory for flooring installation and comply with re-
quirements specified.
3.2 PREPARATION
A. General
1. New and existing concrete surfaces shall be free of oil, grease, curing compounds, loose particles,
moss, algae growth, laitance, friable matter, dirt, and bituminous products.
2. Moisture Testing: Perform tests recommended by manufacturer and as follows.
. a. Perform anhydrous calcium chloride test ASTM F 1869-98. Application will proceed only
when the vapor/moisture emission rates from the slab is less than and not higher than 20
lbs/1,000 sf/24 hrs.
b. Perform relative humidity test using is situ probes, ASTM F 2170. Proceed with installation
only after substrates have a maximum 99% relative humidity level measurement.
c. If the vapor drive exceeds 99% relative humidity or 20 lbs/1,000 sf/24 hrs then the Owner
and/or Engineer shall be notified and advised of additional cost for the possible installation of
a vapor mitigation system that has been approved by the manufacturer or other means to lower
the value to the acceptable limit.
3. Mechanical surface preparation
a. Shot blast all surfaces to receive flooring system with a mobile steel shot, dust recycling ma-
chine (Blastrac or equal). All surface and embedded accumulations of paint, toppings hard-
ened concrete layers, laitance, power trowel finishes and other similar surface characteristics
shall be completely removed leaving a bare concrete surface having a minimum profile of
CSP 4-5 as described by the International Concrete Repair Institute.
b. Floor areas inaccessible to the mobile blast machines shall be mechanically abraded to the
same degree of cleanliness, soundness and profile using diamond grinders, needle guns, bush
hammers, or other suitable equipment.
3.3 APPLICATION
A. General
B. Topping
1. The topping shall be applied as a self-leveling system as specified by the Architect. The topping
shall be applied in one lift with a nominal thickness of 1/8 inch.
2. The topping shall be comprised of three components, a resin, hardener and filler as supplied by
the Manufacturer.
3. The hardener shall be added to the resin and thoroughly dispersed by suitably approved mechani-
cal means. SL Aggregate shall then be added to the catalyzed mixture and mixed in a manner to
achieve a homogenous blend.
4. The topping shall be applied over horizontal surfaces using ½ inch “v” notched squeegee, trowels
or other systems approved by the Manufacturer.
5. Immediately upon placing, the topping shall be degassed with a loop roller.
6. Chip aggregate shall be broadcast to excess into the wet resin, Macro chip at the rate of 0.1 lbs/sf
and Micro chip at the rate of 0.15 lbs/sf.
7. Allow material to fully cure. Vacuum, sweep and/or blow to remove all loose chips.
C. Broadcast
1. The broadcast coat resin shall be applied at the rate of 100 sf/gal.
2. The broadcast coat shall be comprised of liquid components, combined at a ratio of 2 parts resin
to 1 part hardener by volume and shall be thoroughly blended by mechanical means such as a
high speed paddle mixer.
3. Chip aggregate shall be broadcast into the wet resin, Macro chips at the rate of 0.1 lbs/sf, Micro
chips at the rate of 0.15 lbs/sf.
4. Allow material to fully cure. Vacuum, sweep and/or blow to remove all loose chips.
D. Topcoat
A. Tests, Inspection
1. The following tests shall be conducted by the Applicator:
a. Temperature
1. Air, substrate temperatures and, if applicable, dew point.
b. Coverage Rates
1. Rates for all layers shall be monitored by checking quantity of material used against the
area covered.
A. Cure flooring material in compliance with manufacturer’s directions, taking care to prevent their con-
tamination during stages of application and prior to completion of the curing process.
B. Remove masking. Perform detail cleaning at floor termination, to leave cleanable surface for subse-
quent work of other sections.
END OF SECTION
PART 2 - PRODUCTS
2.1 CARPET TILE
A. Products:
1. CPT-1: For Offices and as scheduled24" x 24" carpet tile:
a. As scheduled
2. 24" x 24" Walk Off carpet for staff and patient entry areas
a. As schedule
B. VOC Limits: Provide carpet that complies with the following limits for VOC content when
tested according to ASTN D 5116:
1. Total VOCs: 0.5 mg/sq. m x h.
2. 4-PC (4-Phenylcyclohexene): 0.05 mg/sq. m x h.
3. Formaldehyde: 0.05 mg/sq. m x h.
4. Styrene: 0.4 mg/sq. m x h.
2.2 INSTALLATION ACCESSORIES
A. Trowelable Leveling and Patching Compounds: Latex-modified, hydraulic-cement-based
formulation provided by or recommended by the carpet manufacturer.
1. Ardex Feather Finish – Rapid Drying Smoothing and Patching Compound or approved
equal.
B. Adhesive:
1. For Shaw carpet tile use premium grade pressure sensitive anit-microbial adhesive:
a. Shaw 5036.
2. For excessive moisture locations, use:
a. Shaw 5800 (no greater than 10lb/95% RH/pH 7 to 10)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions for compliance with requirements for maximum
moisture content, alkalinity range, installation tolerances, and other conditions affecting carpet
performance. Verify that substrates and conditions are satisfactory for carpet installation and
comply with requirements specified.
B. Concrete Subfloors: Verify that concrete slabs comply with ASTM F 710 and the following:
1. Slab substrates are dry and free of curing compounds, sealers, hardeners, and other
materials that may interfere with adhesive bond. Determine adhesion and dryness
characteristics by performing bond and moisture tests recommended by the carpet
manufacturer.
2. Subfloors are free of cracks, ridges, depressions, scale, and foreign deposits.
END OF SECTION
PART 2 - PRODUCTS
2.1 WALL-COVERING PRODUCTS
A. General: Provide rolls of each type of wall covering from the same run number or dye lot.
B. Vinyl Wall Covering:
1. Products: As indicated on Finish Schedule
a. Class A
2. Vinyl Wall Covering Standards: Provide mildew-resistant products complying with the
following:
a. FS CCC-W-408 and CFFA-W-101 for Type II, Medium-Duty products.
3. Width: 54 inches.
4. Colors, Textures, and Patterns: Refer to Finish Schedule.
2.2 ACCESSORIES
A. Adhesive: Mildew-resistant, nonstaining, strippable adhesive, for use with specific wall
covering and substrate application, as recommended in writing by wall-covering manufacturer,
and with a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
B. Primer/Sealer: Mildew-resistant primer/sealer complying with requirements in Section 09900 -
PAINTING, and recommended in writing by wall-covering manufacturer for intended
substrate.
C. Seam Tape: As recommended in writing by wall-covering manufacturer.
D. Plastic Moldings and End Caps: As recommended in writing by wall-covering manufacturer.
Color to match wall-coverings.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with requirements for
levelness, wall plumbness, maximum moisture content, and other conditions affecting
performance of work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
E. Coating Maintenance Manual: Upon conclusion of the project, the Contractor or paint
manufacturer/supplier shall furnish a coating maintenance manual, such as Sherwin-Williams
“Custodian Project Color and Product Information” report or equal. Manual shall include an
Area Summary with finish schedule, Area Detail designating where each product/color/finish
was used, product data pages, Material Safety Data Sheets, care and cleaning instructions,
touch-up procedures, and color samples of each color and finish used.
1.4 QUALITY ASSURANCE
A. Applicator Qualifications: A firm or individual experienced in applying paints and coatings
similar in material, design, and extent to those indicated for this Project, whose work has
resulted in applications with a record of successful in-service performance.
B. Source Limitations: Obtain block fillers and primers for each coating system from the same
manufacturer as the finish coats.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials to Project site in manufacturer's original, unopened packages and containers
bearing manufacturer's name and label and the following information:
1. Product name or title of material.
2. Product description (generic classification or binder type).
3. Manufacturer's stock number and date of manufacture.
4. Contents by volume, for pigment and vehicle constituents.
5. Thinning instructions.
6. Application instructions.
7. Color name and number.
8. VOC content.
B. Store materials not in use in tightly covered containers in a well-ventilated area at a minimum
ambient temperature of 45 deg F. Maintain storage containers in a clean condition, free of
foreign materials and residue.
1. Protect from freezing. Keep storage area neat and orderly. Remove oily rags and waste
daily.
b. Two Coats
1) Moore Ultra Spec 500 Acrylic Zero VOC Eggshell Enamel (N538)
2) DE Everest Zero VOC Eggshell Enamel (EVER30)
3) SW Harmony Interior Latex Eg-Shel (B09-1000 Series)
2. Paint Type P-2: Reserved
3. Paint Type P-2A: Interior Gypsum Wallboard and Plaster for Eggshell Finish (Ceilings):
a. One Coat
1) Moore Ultra Spec 500 Acrylic Zero VOC Primer Sealer (N534)
2) DE Ultra-Grip Zero VOC Multi Surface Primer (UGPR00)
3) SW Harmony Zero VOC Interior Latex Primer (B11W001000)
b. Two Coats
1) Moore Ultra Spec 500 Acrylic Zero VOC Eggshell Enamel (N538)
2) DE Everest Zero VOC Eggshell Enamel (EVER30)
3) SW Harmony Interior Latex Eg-Shel (B09-1000 Series)
4. Paint Type P-3: Interior Galvanized Metals, for Latex Eggshell Finish:
a. One Coat
1) Moore Acrylic Metal Primer (P04)
2) DE Ultra-Grip Zero VOC Multi Surface Primer (UGPR00)
3) SW Multi-Purpose Latex Primer (B51W8020)
b. Two Coats
1) Moore Ultra Spec 500 Acrylic Zero VOC Eggshell Enamel (N538)
2) DE Everest Zero VOC Eggshell Enamel (EVER30)
3) SW Harmony Interior Latex Eg-Shel (B09-500 Series)
5. Paint Type P-4: Interior Unprimed Metals, for Latex Eggshell Finish:
a. One Coat
1) Moore Super Spec HP Acrylic Metal Primer (P04)
2) DE Ultrashield Zero VOC Gray Metal Metal Primer (ULDM00-GR-0)
3) SW Multi-Purpose Latex Primer (B51W8020)
b. Two Coats
1) Moore Ultra Spec 500 Acrylic Zero VOC Eggshell Enamel (N538)
2) DE Everest Zero VOC Eggshell Enamel (EVER30)
3) SW Harmony Interior Latex Eg-Shel (B09-500 Series)
6. Paint Type P-5: Interior Architectural Woodwork and Finish Carpentry for Opaque
Finish (chair rail, wood trim, exposed framing, adjustable shelving, and miscellaneous
backboards):
a. One Coat
1) Moore Fresh Start Interior 100% Acrylic Superior Primer (046)
2) DE Ultra-Grip Zero VOC Multi Surface Primer (UGPR00)
3) SW Harmony Zero VOC Interior Latex Primer (B11W001000)
Azura Surgery Center Renalus Crestview 09900-9
b. Two Coats
1) Moore Ultra Spec 500 Acrylic Zero VOC Eggshell Enamel (N538)
2) DE Everest Zero VOC Eggshell Enamel (EVER30)
3) SW Harmony Interior Latex Eg-Shel (B09-1000 Series)
7. Paint Type P-7: Interior Primed Metals (door frames, exposed grilles, louvers, panels,
un-insulated HVAC sheet metal):
a. Two Coats
1) Moore Advance Waterborne Acrylic Alkyd Semi-Gloss Enamel (793)
2) DE - Aristowall Alkyd Emulsion Semi-Gloss Enamel (AWLL50)
3) SW Promar 200 Waterbase Acrylic Alkyd Semi-Gloss (B-34 Series)
10. Paint Type P-10: Exposed Concrete Floor Sealer: Mechanical Rooms:
a. Primer/Etcher – One Coat
1) Moore – Super Spec HP 100% Solids Floor Epoxy (P41-
00, Clear)
2) SW – H & C Concrete Etcher
b. Finish – Two Coats
1) Moore – Super Spec HP 100% Solids Floor Epoxy (P40-
00, Clear)
2) SW - H & C High Performance Industrial Clear Sealer
3) H&C SharkGrip Slip Resistant Additive
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. Work included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. Cubicle curtains.
2. Cubicle curtain track and associated hardware.
B. Note – Cubicle Curtains are only required in certain states as required by individual state
regulations.
C. Related work: The following items are not included in this section and will be performed
under the designated Sections:
1. Section 09511 – ACOUSTICAL PANEL CEILINGS for grid-mounted curtain track.
1.02 SUBMITTALS
A. Comply with pertinent provisions of Section 01340; shop drawings, product data and samples.
1. Product Data: Within 20 calendar days after the Contractor has received Owner’s Notice
to Proceed, submit:
2. Materials list of items proposed to be provided under this Section.
3. Shop Drawings showing proposed method of installation, anchoring, and interface
between the work of this Section and the work of adjacent trades.
4. Manufacturer’s recommended installation procedures.
1.03 QUALITY ASSURANCE
A. Use adequate numbers of skilled personnel who are thoroughly trained and experienced in the
necessary crafts and who are completely familiar with the specified requirements and the
methods needed for proper performance of the work of this Section.
1.04 PRODUCT HANDLING
A. Deliver materials in unopened factory packaging to the jobsite.
B. Inspect materials at delivery to ensure that specified products have been received.
C. Store in original packaging in a climate controlled location away from direct sunlight.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Inpro Corporation, P.O. Box 406, Muskego, Wisconsin 53150
Phone: 1.800.222.5556, Fax: 888.715.8407
www.inprocorp.com
2.02 TRACK COMPONENTS
A. Cubicle Track: Provide extruded aluminum cubicle track with white baked acrylic enamel
finish. Section size is 3/4" high by 1-3/8" wide. Track to be prefabricated to shape in one
continuous piece whenever possible. Corner radius to be 12".
1. Acceptable Product: Clickeze “Optitrac” Cubicle Track.
PART 3 - EXECUTION
3.01 SURFACE CONDITIONS
A. Examine the areas and conditions under which work of this Section will be performed. Correct
conditions detrimental to timely and proper completion of the Work. Do not proceed until
unsatisfactory conditions are corrected.
3.02 INSTALLATION
A. Install the work of this Section in strict accordance with the manufacturer’s recommendations.
B. Install curtains after final cleaning has been completed.
C. Provide two (2) extra sets of curtains to the clinic.
END OF SECTION
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK
A. Work Included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. Corner guards.
2. Impact-resistant wall coverings.
3. Molded Chair Rail
B. Related Work: The following items are not included in this Section and will be performed
under the designated Sections:
1. Section 08710 - DOOR HARDWARE for metal armor, kick, mop and push plates.
1.2 SUBMITTALS
A. Product Data: Include construction details, material descriptions, impact strength, and fire-test-
response characteristics, dimensions of individual components and profiles, and finishes for
each impact-resistant wall-protection unit.
B. Shop Drawings: For each impact-resistant wall-protection unit showing locations and extent.
Include sections, details, and attachments to other work.
C. Samples for Verification: For each type of exposed finish required, prepared on Samples of
size indicated below.
1. Corner Guards: 12 inches long. Include examples of joinery, corners, end caps, top caps,
and field splices.
2. Impact-Resistant Wall Covering: 6 by 6 inches square.
D. Material Certificates: For each impact-resistant plastic material, signed by manufacturer.
E. Maintenance Data: For each impact-resistant wall-protection unit to include in maintenance
manuals.
1. Include recommended methods and frequency of maintenance for maintaining optimum
condition of plastic covers under anticipated traffic and use conditions. Include
precautions against using cleaning materials and methods that may be detrimental to
plastic finishes and performance.
F. Warranty: Special warranty specified in this Section.
1.3 QUALITY ASSURANCE
A. Installer Qualifications: An employer of workers trained and approved by manufacturer.
B. Source Limitations: Obtain impact-resistant wall-protection units through one source from a
single manufacturer.
C. Fire-Test-Response Characteristics: Provide impact-resistant, plastic wall-protection units with
surface-burning characteristics as determined by testing identical products per ASTM E 84,
NFPA 255, or UL 723 by UL or another testing and inspecting agency acceptable to authorities
having jurisdiction.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Extruded Rigid Plastic: ASTM D 1784, Class 1, textured, chemical- and stain-resistant, high-
impact-resistant PVC or acrylic-modified vinyl plastic with integral color throughout; thickness
as indicated.
1. Impact Resistance: Minimum 25.4 ft-lb-ft/in. of notch when tested according to
ASTM D 256, Test Method A.
2. Chemical and Stain Resistance: Tested according to ASTM D 543.
3. Self-extinguishing when tested according to ASTM D 635.
4. Flame-Spread Index: 25 or less.
Azura Surgery Center Renalus Crestview 10260-2 07/17
5. Smoke-Developed Index: 450 or less.
B. Aluminum Extrusions: Alloy and temper recommended by manufacturer for type of use and
finish indicated but with not less than strength and durability properties specified in
ASTM B 221 for Alloy 6063-T5.
C. Fasteners: Aluminum, nonmagnetic stainless steel, or other noncorrosive metal screws, bolts,
and other fasteners compatible with items being fastened. Use security-type fasteners where
exposed to view.
2.2 CORNER GUARDS
A. Surface-Mounted, Resilient, Plastic Corner Guards: Assembly consisting of snap-on plastic
cover installed over continuous retainer; including mounting hardware; fabricated with 90- or
135-degree turn to match wall condition.
1. Acceptable Products:
a. Model No. 150BN, 3” Wing, 90 Degree Surface Mount Corner Guard Profile.
b. Model No. 130BN, 135 Degree Surface Mount Corner Guard Profile.
c. Manufacturer - IPC Door and Wall Protection Systems; Division of InPro
Corporation, Muskego, WI 53150; www.inprocorp.com.
2. Cover: Extruded rigid plastic, minimum 0.08-inch wall thickness; as follows:
a. Profile: Nominal 2-inch-long leg and 1/4-inch corner radius.
b. Required Heights:
1) 48" – at typical corners.
2) 96" – at full height FRP and vinyl wall paneling.
c. Color and Texture: Refer to Finish Schedule.
3. Retainer: Minimum 0.070-inch-thick, 1-piece, extruded aluminum.
4. Top and Bottom Caps: Prefabricated, injection-molded plastic; color matching cover;
field adjustable for close alignment with snap-on cover.
5. Custom Angles – Provide vinyl covers and retainers with custom angles. Custom angles
shall be between 112.5° and 157.5°. Provide flexible top caps to bend to retainer angle.
6. Fire Rating: Same rating as wall in which corner guard is installed; UL listed and labeled
according to UL 2079.
2.3 IMPACT-RESISTANT WALL COVERINGS
A. Impact-Resistant Sheet Wall Covering: Fabricated from rigid plastic sheet material.
1. Designation on Drawings: RVP
2. Acceptable Product: IPC Rigid Vinyl Sheet by IPC Door and Wall Protection Systems;
Division of InPro Corporation, Muskego, WI 53150; www.inprocorp.com.
3. Size: 48 by 96 inches for sheet, minimum.
4. Sheet Thickness: 0.040 inches (standard); 0.080 (on wall behind scale).
5. Color and Texture: Refer to Finish Schedule.
6. Height: As indicated.
7. Trim and Joint Moldings: Extruded rigid plastic that matches sheet wall covering color.
8. Mounting: Use adhesive as recommended by manufacturer.
B. NON-Fiberglass Reinforced Plastic Panels (NRP-FR) with top coat; Class A (ASTM E-84):
1. Acceptable Product: Parkland Plastics NRP-FR panels; Part numbers: FRE3110C (4x8),
FRE3120C (4x10).
2. Size: 48 by 96 inches for sheet, minimum.
3. Sheet Thickness: 0.090 inches (standard).
4. Color and Texture: Refer to Finish Schedule.
Azura Surgery Center Renalus Crestview 10260-3 07/17
5. Height: As indicated.
6. Trim and Joint Moldings: Extruded rigid plastic that matches sheet wall covering color
Almond. 2-piece Divider moulding; 1-piece Inside Corner moulding; 1-piece Cap
moulding; 2-piece Outside Corner moulding.
7. Mounting: Refer to Manufacturers “Installation Guide”. Use adhesive only as
recommended by manufacturer.
2.4 FABRICATION
A. Fabricate impact-resistant wall-protection units to comply with requirements indicated for
design, dimensions, and member sizes, including thicknesses of components.
B. Assemble components in factory to greatest extent possible to minimize field assembly.
Disassemble only as necessary for shipping and handling.
C. Fabricate components with tight seams and joints with exposed edges rolled. Provide surfaces
free of wrinkles, chips, dents, uneven coloration, and other imperfections. Fabricate members
and fittings to produce flush, smooth, and rigid hairline joints.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and wall areas, with Installer present, for compliance with requirements for
installation tolerances, fire rating, and other conditions affecting performance of work.
1. Examine walls to which impact-resistant wall protection will be attached for blocking,
grounds, and other solid backing that have been installed in the locations required for
secure attachment of support fasteners.
2. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Complete finishing operations, including painting, before installing impact-resistant wall-
protection system components.
B. Before installation, clean substrate to remove dust, debris, and loose particles.
3.3 INSTALLATION
A. General: Install impact-resistant wall-protection units level, plumb, and true to line without
distortions. Do not use materials with chips, cracks, voids, stains, or other defects that might be
visible in the finished Work.
1. Install impact-resistant wall-protection units in locations and at mounting heights
indicated on Drawings.
2. Provide splices, mounting hardware, anchors, and other accessories required for a
complete installation.
a. Provide anchoring devices to withstand imposed loads.
b. Where splices occur in horizontal runs of more than 20 feet, splice aluminum
retainers and plastic covers at different locations along the run, but no closer than
12 inches.
c. Adjust caps as required to ensure tight seams.
B. Impact-Resistant Wall Covering: Install top and edge moldings, corners, and divider bars as
required for a complete installation. Install panels vertically, with butt joints between panels.
C. Installation of Mannington Effectual vinyl wall base and chair rail: Install per manufacturer’s
specifications. Vinyl trim sections (particularly chair rail) can be nailed to the drywall substrate
to assist the adhesive bond. Nail holes should be filled to match trim for complete installation.
END OF SECTION
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturer: Best Sign Systems, Inc., 1202 N. Park Avenue, Montrose, CO 81401, phone
970-249-2378
PART 3 - EXECUTION
3.1 PREPARATION
A. Verify mounting heights and locations comply with referenced standards.
B. Clean surfaces thoroughly prior to installation to remove dust, debris and loose particles.
C. Prepare surfaces using the methods recommended by the manufacturer for achieving the best
result for the substrate under the project conditions.
3.2 INSTALLATION
A. Locate the signage system as indicated on drawings for the appropriate substrate and in
accordance with manufacturer's installation instructions.
B. Install signage systems level and plumb at the height indicated on the drawings.
3.3 PROTECTING AND CLEANING
A. After installation, protect all signage from damage during construction.
B. If damage occurs despite such protection, remove and replace damaged components or entire
unit as required to provide units in their original, undamaged condition.
C. Touch-up, repair or replace damaged products before Substantial Completion.
END OF SECTION
PART 2 - PRODUCTS
2.1 APPROVED MANUFACTURERS
A. ASI Storage Solutions.
2.2 PHENOLIC LOCKERS
A. Phenolic Lockers: Provide phenolic lockers with louvered vents and ADA compliant handles.
B. Doors shall be constructed of ½” solid phenolic core decorative plastic laminate with multiple
resin-impregnated kraft and surface sheets fused at high temperature and pressure.
C. Side and Back Panels shall be constructed of 3/8” solid phenolic core with Folkstone Celesta
decorative plastic laminate with multiple resin-impregnated kraft and surface sheets fused at
high temperature and pressure.
D. Tops, Bottoms, End Cover Panels, and Shelves shall be constructed of ½” solid phenolic core
decorative plastic laminate with multiple resin-impregnated kraft and surface sheets fused at
high temperature and pressure.
2.3 CONSTRUCTION
A. Doors shall be fitted with recessed handle, number plate, padlock hasp, and optional locking device.
Perimeter ventilation. Doors shall be mounted to side panel using powder coated steel piano-type hinges
and machined fasteners. Door edges shall be smooth and chamfered with corners radiused.
B. Side Panels shall be attached to all Tops, Bottoms, and Shelves, using rust-resistant and steel fasteners.
Exposed edges shall be smooth and chamfered.
C. Tops, Bottoms, and Shelves shall be attached to all Side Panels, using rust-resistant and steel fasteners.
Exposed edges shall be smooth and chamfered.
D. The color and texture of the finish on Phenolic Lockers is determined by the selected decorative plastic
laminate pattern. Color selection is allowed for Doors and End Cover Panels only; all other components
are Folkstone Celesta.
Azura Surgery Center Renalus Crestview 10500-1 07/17 Version
2.4 HARDWARE
A. Doors
1. All Hinges shall be of powder coated steel, 120° Limited hinge
2. Door Latches shall be mounted at the mid-point of each door. Hasps shall be mounted below each
handle and will accept standard padlock styles.
B. Fasteners shall be of rust resistant door hinges and latches, and handles will be mounted with rivets
and/or machine screws. Hooks and number plates will be mounted with rivets.
C. End Cover Panels will be mounted with stainless steel barrel screws.
D. Locker Units can be banked together will stainless steel barrel screws.
2.5 Acceptable Products:
a. ASI Traditional Phenolic Lockers by ASI Storage Solutions
1) Two Person Z Style: 12” x 12” x 72”
2) Color: As selected from manufacturer’s standard color chart. Submit chart to
Architect for selection
2. Sizes and Configurations: As indicated on Drawings.
3. Lockers must be able to accept padlocks by others.
4. Accessories: Coat hooks, coat rods, operating hardware, filler panels, and continuous
sloped tops.
2.6 FABRICATION
A. Assemble lockers to be truly straight, plumb, level and square with flat planes free from warps,
kinks and dents. Fabricate work with uniform, light-tight joints. Assemble lockers using
manufacturer’s standard methods. Do not expose fasteners on locker faces.
B. Number Plates: Provide etched, embossed or stamped plates with 3/8 inch high numbers
centered on each door near eye level. Provide numbering sequence as indicated on approved
shop drawings.
C. Filler Panels: Provide factory-fabricated filler panels as necessary to form a continuous locker
face of dimension indicated and between lockers and adjacent construction. Finish filler panels
to exactly match lockers.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Strictly comply with manufacturer’s instructions and recommendations, except where more
restrictive requirements are specified in this section. Provide lockers at locations shown.
Install lockers plumb, level and in accurate alignment. Beginning work means Installer accepts
substrates and conditions.
B. Space fasteners at not more than 48" on center. Conceal fasteners as much as possible. Install
base, flat tops, and filler panels. Provide trim, fillers and other accessories as necessary to
provide a complete, uniform assembly.
END OF SECTION
PART 2 - PRODUCTS
2.1 PORTABLE FIRE EXTINGUISHERS
A. General: Provide fire extinguishers of type, size, and capacity for each fire-protection cabinet
and mounting bracket indicated.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine roughing-in for hose valves and cabinets to verify actual locations of piping
connections before cabinet installation.
B. Examine walls and partitions for suitable framing depth and blocking where recessed cabinets
will be installed.
C. Examine fire extinguishers for proper charging and tagging.
1. Remove and replace damaged, defective, or undercharged units.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Prepare recesses for recessed fire-protection cabinets as required by type and size of cabinet
and trim style.
3.3 INSTALLATION
A. General: Install fire-protection specialties in locations and at mounting heights indicated on the
Drawings and acceptable to authorities having jurisdiction.
B. Fire-Protection Cabinets: Fasten fire-protection cabinets to structure, square and plumb.
1. Unless otherwise indicated, provide recessed fire-protection cabinets. If wall thickness is
not adequate for recessed cabinets, provide semi-recessed fire-protection cabinets.
2. Provide inside latch and lock for break-glass panels.
3. Fasten mounting brackets to inside surface of fire-protection cabinets, square and plumb.
C. Mounting Brackets: Fasten mounting brackets to surfaces, square and plumb, at locations
indicated.
D. Identification: Apply vinyl lettering at locations indicated.
END OF SECTION
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include the following:
STAPLES/
AMERICAN
DESCRIPTION BOBRICK BRADLEY
KIMBERLY SPECIALTIES
CLARK
Toilet Tissue
Dispenser B-6637 - 7403 5105
(Recessed)
Toilet Tissue
Dispenser (Surface
Mounted) Use B-6857 - 0710 5084
where recessed not
practical
Clothing Hook -
B670 - 7340 9114
Large
2.3 FABRICATION
A. General: Fabricate units with tight seams and joints, and exposed edges rolled. Hang doors
and access panels with full-length, stainless steel continuous hinges. Equip units for concealed
anchorage and with corrosion-resistant backing plates.
B. Keys: Provide universal keys for internal access to accessories for servicing and resupplying.
Provide minimum of six keys to the Owner’s representative.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install accessories according to manufacturer’s written instructions, using fasteners appropriate
to substrate indicated and recommended by unit manufacturer. Install units level, plumb, and
firmly anchored in locations and at heights indicated.
B. Grab Bars: Install to withstand a downward load of at least 250 lbf, when tested according to
method in ASTM F 446.
3.2 ADJUSTING AND CLEANING
A. Adjust accessories for unencumbered, smooth operation. Replace damaged or defective items.
B. Remove temporary labels and protective coatings.
C. Clean and polish exposed surfaces according to manufacturer’s written recommendations.
END OF SECTION
PART 2 - PRODUCTS
2.1 MANUFACTURER
A. Available Manufacturer: Subject to compliance with requirements and basis of design,
manufacturer offering products that may be incorporated into the Work is limited to the
following:
1. Inpro Corporation – Solarity Solar Shades, Dawn Solar Screen Fabric
2. Hunter Douglas – M Screen 8505
3. MechoShade Systems – Urban Shade, Thermoveil Dense Basket Weave, 1300 Series.
4. Draper – Clutch FlexShade XD-Phifer 2920
2.2 MANUALLY OPERATED ROLLER SHADE TYPES
1. Mounting: Surface mounted with fascia.
2. Configuration: Single solar shadecloth.
3. Solar Shadecloths:
a. 5% Openness Factor
4. Shade Color: Match Inpro White/Bone with matching valance.
2.3 SHADE BAND
1. Shade Bands: Construction of shade band includes the fabric, the hem weight, hem-
pocket, shade roller tube, and the attachment of the shade band to the roller tube. Sewn
hems and open hem pockets are not acceptable.
END OF SECTION
RADIATION PROTECTION
PART 1 GENERAL
1.3 REFERENCES
C. Federal Specifications:
1. QQL-171 Grade C.
2. QQL-201 F Grade C.
E. National Council on Radiation Protection (NCRP): Reports No. 33, No. 35 and No.
49.
1.4 DEFINITIONS
A. Design Requirements:
1. Provide materials and workmanship, including joints and fasteners, that
maintain continuity of radiation protection at all points and all directions
equivalent to materials specified in thicknesses and locations indicated.
a. Refer to Owner’s Physicist Report provided by Onwer.
2. Lead-Lined Assemblies: Provide lead thickness in doors, door frames,
window frames, and other items located in lead-lined assemblies, not less
than that indicated for assemblies in which they are installed unless indicated
1.6 SUBMITTALS
C. Shop Drawings:
1. Indicate dimensions, description of materials and finishes and general
construction.
2. Indicate layout of radiation-protected areas.
3. Indicate lead thickness or lead equivalencies of components.
D. Selection Samples: For each finish product specified, two complete sets of color
chips representing manufacturer's full range of available colors and patterns.
E. Verification Samples: For each finish product specified, two samples, minimum size
6 inches (150 mm) square, representing actual product, color, and patterns.
1.10 WARRRANTY
PART 2 PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. Lead Sheets: 99.9 percent pure unpierced virgin lead, free from dross, oxide
inclusions, scale, laminations, blisters, and cracks.
1. Sheet Lead shall meet or exceed the Federal Specification QQL-201 F Grade
C and ÅSTM B 749 Standard Specification for Lead and Lead Alloy Strip,
Sheet, and Plate Products, see NCRP reports No. 33, No. 35 and No. 49.
2. Thickness: As determined by Radiation Protection Survey, or not less than
1/16 inch (1.5 mm) if not indicated.
3. Variation in sheet thickness: Not to exceed 3 percent.
B. Lead Plates: 99.9 percent pure virgin lead, free from dross, oxide inclusions, scale,
laminations, blisters, and cracks.
1. Lead plate shall meet or exceed the Federal Specification QQL-201 F Grade
C and ÅSTM B 749 Standard Specification for Lead and Lead Alloy Strip,
Sheet, and Plate Products, see NCRP reports No. 33, No. 35 and No. 49.
2. Thickness: As indicated on drawings.
C. Lead-Lined Hollow Metal Door Frames: 16 gage (1.5 mm) welded steel frames with
throat required for wall that frame is installed in, and 2 inches (51 mm) face. Provide
angle iron spot welded at 6 inches (152 mm) on center, and anchor bolts to secure
frame if lead thickness is 1/8 inch (3 mm) or greater. Design lead-lined door frames
to accommodate lead lining up to 1/2 inch (13 mm) thick.
1. Door Frame Supports: 2-1/4 inches (57 mm) steel angle iron.
2. Operation: Swinging.
a. Frame: Fabricate from 1/4 inch (6 mm) thick steel. Provide lead lining
and bottom lead lined sill, and welded wall and sill anchors. Provide
five gussets.
3. Operation: Sliding.
a. Structural Steel Supports: Engineer structural support system based
upon the length, width, thickness, and weight of the door.
b. Structural Steel Compliance:
1) Beams: ASTM A 36.
2) Rectangular Tubing: ÅSTM A 500.
4. Perimeter of Door:
a. Stiles and Rail Thickness: As indicated on Drawings.
b. Reinforcing Bar Thickness: 3/4 inch (19 mm), full length of door at
hinge face.
5. Face Plates: Door manufacturer's lead shielding and polyethylene at hinge
face plates of door. Provide 1/2 inch (13 mm) by 5 inches (127 mm) welded
diagonally to interior of face plate.
a. Back Face: 1/4 inch (6 mm) thick steel welded to frame at 6 inches
D.Radiation Shielding Leaded Glass: Clear leaded glass containing 48 percent lead oxide
(by weight) and 15 percent barium. Thickness as required to provide radiation
protection equivalent to that provided by sheet lead in partition in which lead glass is
installed.
E. Radiation Shielding X-Ray Safety Glass: Lead glass laminated to clear float glass to
comply with applicable building codes for safety glass.
1. Total Thickness: 17/32 inch (13.5 mm).
2. Outer Lite: 5/16 inch thick leaded X-Ray glass (2.1mm lead equivalency).
3. Interlayer: 1/16 inch (1.5 mm) thick PVB.
4. Inner Lite: 5/32 inch (4 mm) thick clear float glass.
5.
2.4 ACCESSORlES
B. Lead Strips: 2 inches (51 mm) wide, unless indicated otherwise, by same thickness
C. Lead Discs: 3/8 inch (9.5 mm) diameter lead discs for use with screw heads.
PART 3 EXECUTION
3.1 EXAMINATION
B. Verify that steel framing is not less than 20 gage (0.9 mm) with studs spaced not
more than 16 inches (406 mm) on center, unless noted otherwise.
C. Shim studs and other framing members as necessary to provide flat, flush finished
surfaces.
D. Adhere lead discs to fastener heads. In each case, use method that provides
continuous radiation shielding.
F. Where second layer of gypsum board occurs over lead-laminated gypsum board,
comply with Section 09260 for application of second layer.
A. Install lead-lined steel door frames per Section 08 11 13 - Hollow-Metal Doors and
Frames. Comply with NAAMM HMMA 840 unless otherwise indicated. Set frames
accurately in position, plumb, and braced securely until permanent anchors are set.
1. Secure door frames with steel stud anchors if lead lining is below 1/8 inch (3
mm) thick.
2. Door Frame Supports (utilize if lead thickness is 1/8 inch (3 mm) or greater):
a. Run steel angle supports full height on each door frame jamb to
structure above.
b. Bolt supports to wood joists.
3. Provide 3 anchors per jamb, located adjacent to hinge on hinge jamb, and at
corresponding heights on strike jamb.
4. In metal stud construction, use wall anchors attached to studs with screws.
5. Lap lead lining of frames over lining in walls at least 1 inch (25 mm).
6. Lead Lining of Frames: Line inside of frames with lead of thickness not less
than that required in doors and walls in which frames are used. Form lead to
match frame contour, continuous in each jamb and across head, lapping
stops. Form lead shields around areas prepared to receive hardware. Lap
lining over lining in walls at least 1 inch (25 mm).
B. Install lead-lined wood doors per Flush Wood Doors Section unless otherwise
indicated. Install doors in frames level and plumb, aligned with frames and with
uniform clearance at edges.
C. Line covers, escutcheons, and plates to provide effective shielding at cutouts and
penetrations of frames and doors. Refer to the Door Hardware Section for other
installations requirements.
B. Provide lead linings, sleeves, shields, and other protection in thickness not less than
that required in assembly being penetrated.
C. Cut wall penetration covers from lead sheet of equal or greater thickness than
backing on adjacent wall panels. Cut wall penetration covers to size required to
cover wall penetrations with laps 1 inch (25 mm) minimum wide as indicated on
penetration detail drawings.
E. Install outlet boxes and conduit between studs using steel telescoping mounting
brackets. Cover or line with lead sheet lapped over adjacent lead lining at least 1
B. Duct Penetrations with Greater than 8 psf Lead Sheet and Where Duct Shielding
Exceeds 24 Inches (610 mm) in Width:
1. Laminate wall penetration covers to plywood or other similar structural panels
conforming to shape of duct, lapping lead joints 1 inch (25 mm) minimum.
2. Secure lead laminated panels to ducts with mechanical fasteners located at
duct seams and corners.
3. Where necessary to prevent lead laminated panels from overloading duct
supports, independently suspend panels from hangers secured to overhead
building structure.
4. Cover fastener heads with lead sheet matching thickness of adjacent lead.
C. Piping: Unless indicated otherwise, wrap piping with lead sheet for 10 inches (250
mm) from point of penetration.
C. Install sheet lead lining within steel door frames to provide radiation protection to
levels indicated or levels required to match adjacent wall protection.
D. Wrap electrical outlet boxes, view window frames, and other penetrations through
lead barrier material with sheet lead to provide radiation protection to levels
indicated or levels required to match adjacent wall protection.
A. Field Inspection: Owner will engage qualified independent testing and inspecting
agency to perform field tests and inspections and prepare test reports.
B. Correct deficiencies in, or remove and replace, radiation protection that inspection
reports indicate does not comply with specified requirements.
C. Testing: After radiology equipment has been installed and placed in operating
condition, Owner will engage radiation health physicist to test radiation protection.
D. Correct deficiencies in, or remove and replace, radiation protection that testing
indicates does not comply with specified requirements, including finishes and other
Work covering defective Work.
3.8 ADJUSTING
A. Check and readjust operating hardware items, leaving doors and frames
undamaged and in proper operating condition.
A. Remove excess materials from site and leave Work areas broom clean.
3.10 PROTECTION
B. Tape temporary paper signs on radiation-resistant walls with the following text:
1. "Do not mount equipment on this wall without covering penetrating fasteners
with lead sheet of thickness required by contract documents".
END OF SECTION
15010
GENERAL MECHANICAL REQUIREMENTS
1.0 GENERAL
1.01 SUMMARY
C. No deviation from the Contract Documents shall be made without the written
consent of the Architect and Engineer.
E. The Drawings are schematic and are not intended to show the exact location
of duct, piping, equipment, etc.
A. All work shall comply with the most recently revised versions of all local, state
and federal codes, ordinances of the authority having jurisdiction, laws, rules
and regulations. Any modifications required by any of the above shall be
7. National Fire Protection Association (NFPA) 90A & 90B, 25 & 99.
15. SMACNA - Sheet Metal and Air Conditioning Contractors’ Nat’l Assoc.
D. All materials shall be new and shall bear the label of UL.
B. Where existing slabs are to be cut or core drilled, the contractor shall x-ray
the existing slabs to avoid cutting or disrupting existing conduits, cables,
plumbing or structural members.
C. HVAC systems, plumbing systems, and electrical service to the building shall
not be interrupted without written consent of the building owner.
E. At the completion of the project, all work under this Division shall be
completely integrated with the existing systems and left in perfect operating
condition.
F. Where work under this Division disrupts the continuity of any existing to
remain electrical circuit or feeder, the Contractor shall repair/replace as
necessary to return to a perfectly functional and safe operating condition.
G. Prior to any demolition or construction the Contractor shall have the existing
conditions inspected by an EPA, OSHA certified asbestos abatement agency
to identify the presence of asbestos. Should any asbestos be found, it shall
be brought to the immediate attention of the Architect and Owner and
specifically identified in writing.
1.04 DEFINITIONS
2.0 PRODUCTS
2.01 MANUFACTURERS
B. When specific names are not stated, only the best available quality of
material or equipment shall be submitted for review and used in the
installation.
A. The Contractor shall obtain complete shop drawings, product data and
samples from the manufacturers, suppliers, vendors, and all Division 15
Subcontractors, for all materials and equipment as specified herein in various
Sections of the Specifications, and shall submit data and details of such
materials and equipment for review by the Architect and Engineer. Prior to
submission of the shop drawings, product data and samples to the Architect
and Engineer, the Contractor shall thoroughly review the shop drawings,
product data and samples and certify they are in compliance with the
Contract Drawings. Further, the Contractor shall check all materials and
equipment upon their arrival on the Project site and verify their condition and
compliance with the Contract Documents. Any Work which proceeds prior to
receiving reviewed shop drawings shall be modified as required to comply
with the Contract Documents and the shop drawings. A minimum period of
ten (10) working days, exclusive of transmittal time, will be required in the
Engineer’s office each time a shop drawing, product data and/or sample is
submitted or resubmitted for review. This time period shall be considered by
the Contractor when scheduling his Work. The initial shop drawing review for
equipment and materials may be expedited through the mutual consent of the
Contractor, Architect, Engineer, and Owner providing the Contractor agrees
to submit complete, certified, documented, and coordinated shop drawings
for review in accordance with the requirements of the Contract Documents.
B. The review of shop drawings, product data, and samples by the Architect and
Engineer shall not relieve the Contractor of the responsibility for dimensions
or errors that may be contained therein, or for deviations from requirements in
the Contract Documents. Is shall be clearly understood that the noting of
some errors by the Engineer but overlooking others does not grant the
Contractor permission to proceed in error.
E. All shop drawings and submittals shall include a stamped indication signifying
that the submittal has been reviewed for compliance with the Contract
Documents by the Contractor. This stamped indication also represents the
fact that the Contractor has checked this submittal for its interaction with all
other Divisions and certifies by his signature or initials that all coordination
has taken place. The stamp shall include the date, name of the Contracting
Firm, the signature of the Contractor, certification of compliance and
approval. This stamp shall be on the submittal before the Engineer will
review it.
F. The Engineer will review an individual submittal not more than twice. If the
submittal is rejected again on the second review, the Contractor will bare all
responsibility for paying for the Engineer’s time for additional reviews. Such
payments to the Engineer shall be withheld from the next monthly pay
application.
G. Shop drawings and/or product data shall be submitted for the following for
review:
1. HVAC duct system layouts, including supply air, return air, exhaust air,
and outside air. HVAC piping system layouts. Plumbing piping system
layouts. These drawings must include associated equipment, drawn to
scale based on submittals for that equipment, must be dimensioned, and
must include duct, piping and equipment elevation tags (distance above
finished floor to bottom).
2. Equipment, including but not limited to: chillers, cooling towers, boilers,
pumps, heat exchangers, rooftop units, split systems, fans, heaters,
water-cooled self-contained units, water-source heat pumps, coils, air
distribution devices (diffusers, etc.), air terminal units (PIU’s, etc.),
ductwork accessories, louvers, hoods, water heaters, plumbing fixtures,
booster systems, lift stations, heat tracing, insulation, piping specialties,
etc.
A. The Contractor shall maintain on a daily basis at the Project site a complete
set of “Record Drawings”. The “Record Drawings” shall consist of a set of
black-line or blue-line prints or AutoCAD files of the Contractor Coordination
Drawings for this Division. The prints shall be marked or the AutoCAD file
electronically updated to show the precise location of all work and equipment,
and all changes and deviations in the work from that shown on the Contract
Documents. This requirement shall not be construed as authorization for the
Contractor to make changes in the layout or work without definite instructions
C. The Contractor and Subcontractor shall mark all “Record Drawings” on the
drawings with a rubber stamp impression or an AutoCAD image that states
such.
3.0 EXECUTION
3.01 INSTALLATION
A. Furnish and install the necessary sleeves, inserts, hangers, anchor bolts, and
related structural items. Install at the proper time.
1. Welding shall be done by the electric arc method with fully competent
welders. Supporting members shall be shop coated with a suitable
primer.
G. Flashing:
1. Wherever ductwork and/or piping pass through the roof or outer walls,
base flashing and counter-flashing shall be provided.
H. Anchor bolts and inserts shall be galvanized and of adequate size and
strength for installation of electrical work and shall be placed in forms before
concrete is poured.
WEATHERPROOF EQUIPMENT
B. Air distribution devices located in damp areas our outside shall be weather-
resistant (aluminum, etc.).
CLEANING
A. Brush and clean work prior to concealing, painting and acceptance. Perform
in stages if directed.
C. Remove dust and debris from inside and outside of material and equipment.
B. All motors shall be checked and adjusted for correct direction of rotation.
C. Any work found not to be in compliance with the Contract documents shall be
repaired or replaced without incurring additional cost to the Contract price.
WARRANTIES
A. The warranty period for all systems, equipment, components, work, etc. shall
be no less than one (1) year, unless specified otherwise hereinafter and shall
include at least one (1) full heating season and one (1) full cooling season.
The warranty shall include parts and labor.
B. The Contractor shall, without cost to the Owner, remedy any defects within a
reasonable time to be specified in notice from the Architect. In default
thereof, the Owner may have such work done and charge all costs to the
Contractor.
D. The Subcontractor shall confer with the General Contractor prior to the bid
date concerning the project schedule and determine if there is a need to
operate any items of equipment or systems for temporary heating and/or
cooling or other reasons prior to “Substantial Completion”. All required
extended warranty costs for equipment, materials, and systems shall be
included in the Subcontractor’s bid.
15140
HANGERS & SUPPORTS FOR PIPING & EQUIPMENT
1.0 GENERAL
PART 2 – PRODUCTS
D. Piping in Single Runs: Provide Fee and Mason Fig. 239 or Grinnell No.
260 clevis hanger.
F. Riser Clamps: Provide Fee and Mason Figure 241 riser clamps. Riser
clamps for copper tube shall be copper-plated.
PART 2 – EXECUTION
3.01 INSTALLATION:
H. Leveling: Adjust hangers and supports and place grout as required under
supports to bring piping to proper levels and elevations.
15190
EQUIPMENT AND PIPING IDENTIFICATION
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
identification of equipment and piping. Comply with other Division 15
sections and drawings as applicable. Refer to other divisions for coordination
of work.
1. In general, all equipment shall be labeled. This shall include all central
plant, air handling or air conditioning equipment, and other similar and
miscellaneous equipment.
3. Each valve shall be identified with a stamped tag. Valves and tagging
shall be scheduled typewritten on 8 ½” x 11” paper, tabulating valve
number, piping system, system abbreviation, location of valve (Room or
area), and service (e.g. – 2nd Floor North Domestic Hot Water). The
valve schedule shall be submitted to the Engineer for approval prior to
ordering or installing valve tags. See Section 15010, “General
Mechanical Requirements” for information and requirements regarding
Operation and Maintenance Manuals.
4. Labels, tags, and markers shall comply with ANSI A13.1 and other
applicable state and local standards for lettering size, colors, and length
of color field.
2.0 PRODUCTS
B. On piping and insulation 6” and greater diameter, full band as specified above
or strip-type markers fastened to the pipe or insulation with laminated or
bonded application or by color-coded plastic tape not less than 1 ½” wide, full
circle at both ends of the marker. Pipe markings can also be applied with the
stick type backing in lieu of he semi-rigid snap-on-type.
C. Arrows for direction of flow provided integral with the pipe marker or separate
at each marker.
A. Valve tags shall be polished brass or plastic laminate with solid brass S hook
and chain. Tags shall be stamped or engraved with the appropriate
abbreviation for the type of service (e.g. – CHW, HW), as well as the
designated valve number.
3.0 EXECUTION
3.01 GENERAL
E. Pipe and ductwork markers shall be placed on piping and ductwork on 25’
centers in mechanical rooms and concealed spaces. In locations where
piping and ductwork is exposed, place markers on 50’ centers. Flow
directional arrows should be marked on the piping at taps from the main and
riser.
F. Valve tags shall be placed on each valve except those intended for isolation
of individual heat pumps or terminal units (e.g. - VAV boxes, fan coil units,
unit heaters, etc.). Valve tag schedules shall be prepared as specified
hereinbefore. Copies of one schedule shall be laminated in clear plastic and
placed where directed by the Owner. Other sets shall be included in the
Operating and Maintenance Manuals.
15200
INSULATION – HVAC AND PLUMBING
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
insulation of HVAC and Plumbing piping, duct, and equipment. Comply with
other Division 15 sections and drawings as applicable. Refer to other
divisions for coordination of work.
C. Furnish and install all components of the insulation system specified herein,
as indicated on the drawings, and as required to provide complete and
operating systems.
B. All insulation, jacket and adhesive shall have a fire and smoke hazard ratings
as tested under ASTM E 84, NFPA 255, and UL 723 not exceeding:
Flame Spread: 25
Fuel Contributed: 50
Smoke Developed: 50
1.03 SUBMITTALS
B. Product Data
1. Type A Insulation
2. Type B Insulation
3. Type D Insulation
4. Type E Insulation
5. Type F Insulation
6. Vinyl Lacquer Paint for Type B Insulation
7. Metal Jacket
1.04 DEFINITIONS
A. The phrase "Storm Drainage Conductor" refers to that portion of the storm
drain interior to the building, between the roof drain body and where the pipe
goes below grade.
B. The word “plenum” shall mean a ceiling space or mechanical room used for
the transfer of conditioned return and/or outside air.
2.0 PRODUCTS
1. One Piece glass fiber, rigid molded sectional pipe covering with factory
applied aluminum foil and white craft paper flame retardant vapor barrier
jacket, conforming to ASTM C547, Class II, Mineral Fiber Preformed Pipe
Insulation.
3. Similar to Johns Manville Corp “Micro Lox 650 AP T”, or approved equal.
C. Type E
1. Duct insulation shall be 2" thick, minimum 3/4 lb. density fiberglass with
an FSKL aluminum foil jacket, reinforced with fiberglass scrim.
11. Wire Mesh: 1 inch by 20-gage stainless steel hexagonal wire netting.
3.0 EXECUTION
F. Refrigerant Suction Lines & Valves (in plenums and fire partitions/floors), and
hot gas bypass piping – Type A insulation required:
Notes:
b. Exposed supply and return ductwork will be double wall, internally lined.
c. The above thicknesses are the minimum required. All local codes and
local energy codes shall be complied with.
f. No type of duct liner shall be used for any unit associated with the ASC.
A. Preparation
2. All surfaces to be insulated shall be dry and free of loose scale, rust, dirt,
oil or water.
B. Application:
9. The adhesive used in connection with all covering work shall contain an
approved vermin and rodent proof ingredient.
C. Application at Fittings:
B. PVC fitting jackets shall be used when they are available for the particular
application. When molded or routed coverings are not available, the
coverings shall be fabricated in the field similar to equipment insulation.
Molded or routed fitting covers are highly recommended. Order PVC pre-
curled.
C. Cold Piping:
1. Cover valves, fittings and flanges with insulation having the same
thickness as adjacent pipe covering, securing in place reforming tape up
to 12” O.D. and ½” wide SST bands on larger O.D. Apply a PVC jacket
and seal joints with PVC cement (solvent welding).
D. Hot Piping:
1. Covers shall overlap the pipe insulation by the thickness of the insulation
or 2” min. Cover valves, fittings and flanges with insulation similar to the
adjacent pipe covering, securing in place with reforming tape up to 12”
O.D. and ½” wide SST bands on larger O.D. Apply a PVC jacket and
tape end joints to adjacent pipe insulation.
2. Do not use PVC fitting jackets where the surface of the insulation is
above 150 degrees F.
E. Exterior Piping:
A. Type B insulation shall be slipped on the pipe prior to connection, and the
butt joints shall be sealed. Where the slip on technique is not possible, the
insulation shall be carefully slit and applied to the pipe.
E. This Contractor shall paint Type B insulation exterior to the building with two
coats of a vinyl acrylic paint recommended by the insulation manufacturer for
protection against ultraviolet degradation and shall be flexible with no
cracking. It is recommended in high humid areas to coat the insulation with a
vapor barrier mastic to .037 min. DFT.
A. Exterior
2. Finish shall be factory applied All Service Jackets. All fittings shall be
finished with vapor seal mastic reinforced with white glass mesh.
Minimum 0.037 thick DFT of mastic.
3. Piping exposed in machine rooms shall be finished with vapor seal mastic
and open weave membrane 10 x 10.
4. Piping exposed to weather shall be finished with all service jacket and
additional finish of 0.16 thick aluminum jacket. Aluminum jacket shall be
secured with stainless bands located on maximum centers of 12 inches
and at the overlap. No screws or pop rivets shall be used.
5. Fittings and valves shall be finished with vapor seal mastic, reinforced
with minimum 0.037” DFT of mastic, glass mesh and aluminum
preformed fitting covers.
2. Secure insulation on the bottom of ducts and plenums and on the sides of
plenums and other places where the insulation will sag and max 3” from
any corner.
3. Impale insulation over pins or anchors located not more than 18 inches
apart and hold in place with washers and clips.
4. Cut off protruding pin after clips are secured and seal with 2-mil.
aluminum foil backed pressure sensitive tape.
6. Seal all ductwork joints, punctures and fittings with a mastic type sealant
containing a vapor barrier.
7. Cover all breaks, joints, punctures and voids with a vapor seal mastic and
cover with a vapor barrier material identical to vapor barrier on the
insulation, where gaps exceed 2”.
A. Cover all piping insulation exposed to the exterior with metal jacket as
specified herein.
3.09 HANGERS
B. Provide rigid insulation (on non-insulated piping) or sheet metal inserts (on
insulated piping) between the pipe and pipe hanger - shall be of a thickness
equal to the adjoining insulation and shall be provided with vapor barrier
where required. Insulation insert shall not be less than the following lengths:
C. Inserts for cold piping shall have a vapor barrier facing of the same material as
the adjacent pipe insulation. Seal inserts into insulation with vapor seal mastic.
A. Pipe insulation and vapor barrier shall be continuous through sleeves in walls
and floors.
B. Type B insulation shall not be used in sleeves through firewalls or fire rated
(2-hour) floor systems. Use Type A or Type C through the sleeve instead
and vapor seal the joint between the two insulations.
D. Where penetrating interior walls, extend the metal jacket 2 inches out either
side of the wall and secure each end with a metal band compressing the
insulation slightly.
E. Where penetrating floors, extend the metal jacket 2 inches below the floor
and 5 inches above the floor. Secure with metal bands.
15210
VIBRATION ISOLATION
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
vibration isolation systems. Comply with other Division 15 sections and
drawings as applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the vibration isolation systems specified
herein, as indicated on the drawings, and as required to provide complete
and operating systems.
2.0 PRODUCTS
2.01 MATERIALS
A. Chilled, Condenser and Heating Hot Water Pumps: Provide concrete inertia
bases with structural steel pouring forms sized and reinforced as required for
the intended service. Size bases to support the piping elbow supports and
furnish with Type RSW recessed spring isolators properly sized for one-inch
static deflection. Mount springs on concrete bases 3-1/2" high. Inertia base
is not required for pumps installed on slabs on grade.
B. Suspended Fans: Isolate with not less than four combination spring and
rubber-in-shear vibration isolators.
C. Suspended Heat Pump Units: Unit shall be isolated with hanger and
vibration isolation kit supplied by unit manufacturer or a vibration isolation
manufacturer.
D. Suspended Fan & Coil Unit: Isolate with not less than four combination
spring and rubber “in-shear” vibration isolators.
E. Flexible Pipe Connections at Cooling Tower: Isolate supply and return piping
to the cooling tower with flanged rubber, spherical double-arch expansion
joints.
H. Roof Mounted Air Handling Units: Provide housed spring type isolators with
vertical limit stops. Provide with 1” deflection (0 to 500 rpm) or .75” deflection
(501 and over rpm).
3.0 EXECUTION
15400
PLUMBING PIPING
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
plumbing piping systems. Comply with other Division 15 sections and
drawings as applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the plumbing piping systems specified
herein, as indicated on the drawings, and as required to provide complete
and operating systems.
B. Applications: Applications of piping systems include, but are not limited to,
the systems as listed below:
Working Operating
System Pressure Temperatures
Makeup Water
High 350 psig 55 to 80°F
Medium 300 psig 55 to 80°F
Low 150 psig 55 to 80°F
Sanitary Drainage -- --
Storm Drainage -- --
Natural Gas -- --
2.0 PRODUCTS
A. General: Provide pipe and tube of type, joint, grade, size, and weight (wall
thickness, schedule or class) indicated for each service. Comply with
applicable governing regulations and industry standards.
1. Steel Pipe: ASTM A53, ASTM A106, or ASTM A120, black or hot-dipped
galvanized as specified.
2. Copper Tube: ASTM B88, Types "K", Type "L", or Type "M" copper water
tube as defined by the Copper and Brass Research Association.
3. Ductile Iron Pipe: ANSI A21.51, Class 150 with bell and spigot ends for
push-on joints.
4. Cast Iron Soil Pipe: ASTM A74, standard weight, hub and spigot-type.
5. Hubless Cast Iron Pipe: CISPI 301-78, standard weight with spigot bead
ends for coupling assembly.
6. Polyvinyl Chloride (PVC) Pipe: Sewer main SDR 41, ASTM D3034 with
bell ends and pre-inserted gasket joints.
7. Pre-insulated Steel Pipe: ASTM A53, ASTM A106, ASTM A120, and
ANSI B31.1.
8. Polyvinyl Chloride (PVC) Water Pipe: Class 150, thickwall, Schedule 80,
AWWA C90 mechanical joint.
1. Cast Iron Flanged Fittings: ANSI B16.1, Class 125 or Class 250, black or
galvanized as specified, including bolting and gasketing.
2. Cast Iron Threaded Fittings: ANSI B16.4 or ASTM A126, Class 125 or
Class 250, black or galvanized as specified.
3. Malleable Iron Threaded Fittings: ANSI B16.3, Class 150 or Class 300,
black or galvanized as specified.
4. Malleable Iron Threaded Unions: ANSI B16.39, select for proper piping
fabrication and service requirements including style, end connections,
and metal-to-metal seats (iron, bronze, or brass), plain or galvanized as
specified.
8. Wrought Steel Butt-welding Fittings: ANSI B16.9, except ANSI B16.28 for
short radius elbows and returns; rated to match connected pipe.
10. Pipe Nipples: Fabricated from same pipe as used for connected pipe,
except do not use less than Schedule 80 pipe where length remaining
unthreaded is less than 1/2". Do not thread nipples full length (no all-
thread nipples).
12. Hub-less Cast Iron Pipe Fittings: CISPI 301-78 and comply with
governing regulations.
16. Grooved End Fittings: ASTM A47 or ASTM A536 joined with Victaulic
Style 77 couplings and Grade "E" gaskets.
17. Flanged Fittings: Comply with ANSI B16.15 for bolt-hole dimensioning,
materials, and flange-thickness.
18. Flange Bolts: Bolts shall be carbon steel ASTM A307 Grade A hexagon
head bolts and hexagonal nuts. Where one or both flanges are cast iron,
furnish Grade B bolts. Cap screws utilized with flanged butterfly valves
shall be ASTM A307 Grade B with hexagon heads.
3. Gaskets for Flanged Joints: 1/8" thick gaskets. Ring-type shall be used
between raised face flanges and full face-type between flat face flanges
with punched bolt holes and pipe opening. Gaskets shall be Garlock
Style 3400 compressed non-asbestos or equal.
5. Gaskets for Cast Iron Soil Pipe: ASTM C 564, neoprene, compression-
type.
7. Hub-less Cast Iron Joints: CISPI 310, stainless steel corrugated shield
and clamp assembly over one piece neoprene sealing sleeve.
3.0 EXECUTION
A. General:
C. Steel Pipe: Ream steel pipe after cutting and before threading. Thread with
clean-cut taper threads of length to engage all threads in fittings and leave no
full-cut threads exposed after make-up.
D. Copper Pipe: Cut copper pipe square and ream to remove burrs. Clean
fitting socket and pipe ends with sand cloth or wire brush.
E. PVC Pipe: Cut PVC pipe square and remove all burrs. Clean fitting and pipe
butt prior to installation. Install all PVC piping in accordance with the
manufacturer's recommendations. PVC piping shall not be installed in return
air plenums unless wrapped with 25/50 flame spread complaint plenum rated
wrap.
1. Layout: Pipes shall be laid and pipe joints made in presence of the
General Contractor and field measurements, layouts, batter board
alignment, grade establishments, and similar locations shall be performed
by a Professional Engineer in the employ of the Contractor. The
Contractor's engineer shall be on the job during all underground work. A
"Bench-Mark" reference shall be provided by the General Contractor.
2. Pipe Grading: Lay and maintain all pipes at required lines and grades
during the course of the Work.
3. Trench: Excavate the trench to the depth required. Properly brace and
de-water the trench and keep it free of water during installation, testing
pipe, and backfilling. No water shall be discharged onto the street or
freeway without approval by the Owner.
4. Excavation: The trench shall be at least 18" wider than the maximum
diameter of the pipe or largest bell and the pipe shall be laid in the center
of the trench. The trench shall be excavated to a depth sufficient to
provide for pipe cushions or supports as specified. Trench width may be
increased as required and piling left in place until sufficient compacted
backfill is in place. Properly sheet and brace all open trenches to render
them secure and remove all such sheeting and bracing before completing
the backfill. Comply with all applicable national, state, and local codes
and regulations. The quantity of excavation required to install sheeting
and the installation and removal of sheetings and bracings will not be
regarded as Extra Work. All costs incurred for this excavation and the
installation of sheeting shall be included in the Contract Price.
a. Domestic Water Pipes: Material for pipe cushion shall comply with
local codes and conform with the geo-technical report. In absence of
local code requirements and/or geo-technical report, the cushion shall
be bank sand or select backfill material approved by the General
Contractor. Any material used shall pass a one-inch screen.
b. Sanitary and Storm Sewers: Material for pipe cushion shall comply
with local codes and conform with the geo-technical report. In
absence of local code requirements and/or geo-technical report, the
cushion shall be bank sand or select backfill material approved by the
General Contractor. Any material used shall pass a one-inch screen.
6. Anchors: Cast iron pipes shall have concrete anchors at each change in
direction and/or as directed. Any change in direction exceeding 15
degrees shall be anchored. Concrete anchors shall rest against solid
(virgin) ground with the required area of bearing on pipe and ground to
provide suitable anchoring.
7. Backfill: Backfill trenches only after piping has been inspected, tested,
and approved by the General Contractor. Backfill shall be provided as
recommended in the geo-technical report included in these Contract
Documents, or in the absence of a geo-technical report, as required by
site conditions. Refer to Division 2 or elsewhere in the Contract
Documents for additional trenching and backfill requirements.
A. Scope:
1. This Contractor shall provide the building sanitary sewer to 5 feet outside
the building and shall extend the domestic water service from the main
shutoff valve stubbed above floor in the building.
1. Slope domestic hot and cold water piping to drain and provide with hose
valves (drain valves) at low points.
2. Install soil, waste, and vent piping with horizontal lines pitched in
accordance with local codes, but in no case less than 1/4" per foot for
pipe 2-1/2" and smaller, and 1/8" per foot for pipe 3" and larger. Install
soil, waste, and vent piping with hubs of each length of piping in the
upstream position.
3. Make-up lead and oakum joints with molten lead run into hubs in one
continuous pour, to a minimum depth of one inch.
D. The domestic water service shall be Class 150 AWWA cement lined C.I. with
Class 250 fittings, mechanical joints or push-on rubber ring gaskets, ASTM
A377-66 or PVC AWWA C900 with solvent welded fittings. Provide tie rods
and thrust blocks as required.
A. General: Provide a condensate drain pipe to connect each cooling unit drain
pan or funnel and to extend to and discharge into an open type drain in the
sanitary plumbing system. Funnel type floor drain requirements are to be
coordinated with the Plumbing Contractor. Provide union or solder joint at
connection to HVAC equipment.
B. Assembly: Use hard drawn Type “M” or DWV copper tubing with matching
fittings. Assemble fittings to form a trap with depth equal to or greater than
operating pressure of the unit served. Drains shall be of the size not less
than the full size of the drain pan connection. Air handling unit drains shall
have deep seal traps to permit unit pan drainage. The deep seal trap shall be
installed for each blow-through or draw-through air handling unit to maintain
the water seal.
C. Contractor Options:
3. Piping 3" and smaller, Type "L" copper tubing with wrought copper solder
end fittings. At the Contractor's option, this piping may be as specified for
piping 4" and larger.
4. Piping 4" and larger, Schedule 10, stainless steel pipe, ASTM A312 with
stainless steel fittings, or stainless steel flanged fittings.
6. Option: At the Contractor's option, for piping 3" or larger, Victaulic Style
77 couplings, Victaulic fittings and tees may be used instead of the
above, if Victaulic groove depth control tool is used for field grooving.
Victaulic flanges and reducing couplings shall not be installed.
A. Piping Two-and-a-half Inches and Smaller: Type "K", copper tubing with
wrought copper brazed end fittings.
B. Piping Three Inches and Larger: Ductile iron bell and spigot, push-on joint,
pressure water pipe. Joints shall be of the push-on-type employing a molded
rubber gasket retained in a ring recessed into the inside of the bell. Pipe and
joints shall be manufactured by Tyler Pipe and Foundry Company or equal.
Coat pipe and fittings inside and outside with the manufacturer's standard
coal tar enamel suitable for domestic water service. PVC AWWA C900
piping with solvent welded fittings can be used where acceptable by the local
authorities.
A. Soil, Waste, and Vent Piping Underground: Service weight cast iron soil pipe
and fittings with lead and oakum joints or neoprene gasket joints made up
with "Lubrifast" joining material or PVC piping with solvent welded joints.
Provide and install code-approved manholes as required.
B. Soil, Waste, and Vent Piping Above Ground: Service weight cast iron soil
pipe and fittings with neoprene gasket joints or hub-less cast iron pipe and
fittings with coupling assembly.
(UL 910 & 1887). Each pump discharge shall be carried separately to the
horizontal gravity main and shall discharge into the top of the horizontal
gravity main.
D. Cleanouts:
2. Finished Floor: Jay R. Smith No. 4434, cast iron adjustable assembly
with nickel bronze cover and tapered thread bronze plug. Provide
clamping collar when installed in floors having waterproof membrane.
4. Walls: Jay R. Smith No. 4434, cast iron with nickel bronze, square,
smooth, access cover, vandal-proof screws.
6. Locations:
B. Flushing: Flush piping systems with clean water prior to performing any
required tests.
C. Piping Tests:
1. General: Blank off equipment during tests. Perform tests before piping is
enclosed in walls, floors, partitions or in any other way concealed from
view. Tests may be performed in sections. Tests shall be witnessed by
the General Contractor and local inspectors and the test results
presented to the Engineer for acceptance and approval prior to
concealing piping from view. Provide all necessary equipment for testing,
including pumps and gauges. Note: All test results are to be submitted to
the Engineer as specified in Section 15995.
3. Soil, Waste, and Vent Piping System: Test soil, waste, and vent piping by
plugging all openings and filling system to height required by City
Plumbing Inspector, but not less than 10'. Inspect all joints for leaks,
repair all leaks found, and retest until piping is demonstrated to be free
from leaks. In addition to water test, apply peppermint or smoke tests, if
required by local code. All underground main piping shall be inspected
with a camera and the taped test results submitted to the Owner.
5. Natural Gas Piping System: Test natural gas piping with compressed air
or nitrogen at 5 times service pressure but not less than 100 psig for 24
hours and in accordance with the requirements of the local codes and the
serving utility company. Repair all leaks, replacing materials as
necessary, and repeat test until systems are proven tight.
E. Inspecting: Visually inspect each run of each system for completion of joints,
adequate hangers, supports, and inclusion of accessories.
15405
MEDICAL GAS SYSTEMS
1.0 GENERAL
A. This Section pertains to all other labor, equipment and services necessary for
and incidental to the piped medical gas and vacuum systems (PMGVS)
including oxygen, medical air, medical vacuum, waste anesthesia gas
disposal (WAGD), nitrogen, nitrous oxide and carbon dioxide systems as
shown on the drawings and/specified herein.
B. All materials used shall be new and of the best grade and quality obtainable,
and workmanship shall be first class in every respect. Contractor shall be
responsible for compliance with all Local, State or Federal codes.
C. Provide all elements and accessories required for complete systems per
NFPA 99 most recent edition.
G. Perform Installer pressure testing, cross connection testing and final testing
per NFPA 99 most recent edition in every material respect and ready to be
put into operation.
I. Retain a qualified third party verifier acceptable to the engineer and owner to
Perform and attest to final verification of the systems. Make corrections as
required, including additional testing if necessary to attain full and unqualified
certification.
1.02 COORDINATION
A. Medical Gas Contractor shall coordinate with other trades to ensure timely
installations and avoid conflicts and interference.
B. Work with metal stud partition installer and/or mason to ensure anchors,
sleeves and similar items are provided in sufficient time to avoid delays;
chases and openings are properly sized and prepared.
C. Medical Gas Contractor shall supply and install all medical gas alarm
systems, including the signal wiring and conduit. The electrical contractor
shall provide power wiring to each alarm panel. Termination shall be done by
or under supervision of manufacturer of alarm panels. Alarm panel wire shall
be of type specified by the alarm manufacturer. Wire limitations shall be as
specified by the alarm manufacturer. Install all alarm wiring in conduit.
D. Coordinate with owner to ensure medical gas outlets, whether owner supplied
or contractor supplied, in walls, ceiling and all equipment is provided by the
same MGEM as may be present in existing facility.
1.03 REFERENCES
1.04 SUBMITTALS
B. Pre-approval:
1. Written pre-approval is required for equipment not matching specifications
exactly. Submit the information required under Submittals above,
attaching a cover letter stating the exact areas of deviation.
2. A Request for pre-approval of equipment must be received by the
Engineer not less than ten working days prior to bid.
3. The contractor shall be responsible for providing evidence that substituted
equipment will fit into space provided for equipment as shown on the
medical gas plans.
A. Regulatory Requirements:
1. Electrical Control systems and Medical Gas Alarms are to be UL listed as
assemblies with label affixed.
2. Medical air, instrument air, medical vacuum and WAGD controls are to be
wired in accordance with NEC.
3. MGEM will include with submittals affidavit attesting to compliance with all
relevant paragraphs of NFPA 99 most recent edition including (d) below.
4. MGEM personnel assembling medical air, instrument air, vacuum and
WAGD plant shall meet NFPA 5.1.10.6.11 Qualification of Installers and
hold medical gas endorsements as under ASSE 6010.
5. The installer shall furnish documentation attesting that all installed piping
materials were purchased cleaned and complied with the requirements of
NFPA 99 5.1.10.1 and 5.1.10.2.
C. Warranty:
1. All Medical Air, Instrument Air, Medical Vacuum and WAGD source
equipment will be warranted by the MGEM of record:
a. For 24 months or longer from start-up.
b. Warranty will be expressly complete, include all components
of the system and be the responsibility of the MGEM of
record only. Warranties limiting the responsibility of the
MGEM for any system component or which pass through the
MGEM to another manufacturer are not acceptable.
c. Warranties shall include on site repairs including travel, labor
and parts. Warranties requiring return of equipment for
adjustment are not acceptable.
D. Maintenance:
1. MGEM shall demonstrate a national service capability able to perform
major overhauls.
E. Certification:
1. Medical Gas Contractor shall deliver to the owner a complete system
certification without qualifications.
2.0 PRODUCTS
2.02 MATERIALS
B. All vacuum and WAGD tubing 3 inch and smaller shall be:
1. Type ‘L’, ‘M’, or ASTM B-280 ACR copper.
2. Brazed with BCuP-5 Brazing alloy or equivalent alloy with at least 1000
degree F melting point.
B. Pipe hangers and accessories shall be Elcen, Fee & Mason, Grinnell, or
Carpenter and Paterson, Inc., and all hangers shall be the adjustable type.
F. Except where used for anchor purposes or supports for vertical pipes, and
pipe clamp type, hanger shall be free fit on the pipe and spacers shall be
used to prevent binding.
of reserve unit if required. A lag alarm on control cabinet and contacts for
the master alarm will be provided.
8. The complete control system and all electrical components shall be
NEMA 12 and UL labeled.
9. The control system shall provide:
a. Automatic lead/lag sequencing including self adjusting minimum
run timers which optimize the number of pump starts based on
demand.
b. Circuit breaker disconnects for each vacuum pump with external
operators. Units with fuses instead of circuit breakers in motor
circuit are not acceptable. The control system shall include an
automatic minimum run time adjustment to automatically adjust
run time based on demand.
c. Full voltage motor starters with overload protection.
d. Redundant 120 volt control circuit transformers.
e. Visual and audible reserve unit alarm with isolated contacts for
remote alarms and audio cancel.
f. Control cabinet shall have lighted HOA selector switches.
g. Panel mounted vacuum gauge.
h. Runtime hourmeter for each pump.
10. Provide oil lubricated rotary vane pumps, dynamically balanced multi
vane design with heavy duty aluminum alloy vanes for maximum heat
dissipation. Minimum vane life is 50,000 operation hours. Oil
recirculation is differential pressure with full recirculation and multistage
exhaust oil separation rated at not less than 99.998% efficiency. Each
pump is provided with an oil non-return valve, filter change indicator for
exhaust oil separation filters, and high discharge temperature switch.
Service to the oil lubrication system filters does not require disconnection
of the exhaust piping. The oil lubrication system shall all be enclosed in
one module to minimize oil leaks. Systems with external piping for oil
lubrication are not acceptable. Systems requiring separate additional
external electric motors for oil cooling are not acceptable. Rubber hose
flex connectors and hose clamps are not acceptable for assembling
package.
4. The latch mechanisms shall be designed for one handed, single thrust
mounting and one handed fingertip release of secondary equipment.
5. The complete outlet shall be made, cleaned and packaged to NFPA 99
Standards, UL Listed and CSA certified. Medical gas outlets shall be
cleaned for oxygen service in accordance with CGA Pamphlet G-4.1.
The assembly shall be capped and the finish assembly poly bagged for
shipment.
6. The rough in assembly shall be of modular design and include a gas
specific 16 gauge steel mounting plate designed to permit on-site ganging
of multiple outlets, on 5” centerline spacing. A machined brass outlet
block shall be permanently attached to the mounting bracket to permit the
½” OD, type-K copper inlet to swivel 360 degrees for attachment to the
piping system. The rough in assembly shall contain a double seal to
prevent gas leakage between the rough in and latch-valve assemblies
after the wall is finished. A single 0-ring seal shall not be acceptable.
7. The latch-valve assembly shall telescope up to ¾” to allow for variation in
finished wall thickness from ½” to 1-1/4”.
8. DISS Outlets shall be used for all ceiling mount applications.
9. Furnish hose assemblies for all ceiling outlets for the finished ceiling
height as indicated on drawings. Provide each hose with a heavy-duty
chain type dual retractor for pressure gases and triple for vacuum.
Retractors made of stainless cable are not acceptable. Allow an extra 18”
of hose length for retractors.
6. Each rough-in box shall contain a base and tube assembly consisting of a
Type K copper pigtail, flared to accept a ¼” ID, 3/8”OD supply line, brass
block and base housing a secondary check valve in accordance with
NFPA 56F (not required in vacuum), primary valve O-ring seal, check
valve deflator spring, (except vacuum), pressure testing cap plug, and
plaster shield. The copper inlet tube shall be capable of rotating 360º to
adjust for field piping conditions.
7. Medical gas outlets shall be cleaned for oxygen service in accordance
with CGA Pamphlet G-4.1. The assembly shall be capped and internal
parts poly-bagged for shipment. The outlet assembly shall bear the label
of listing under Re-examination Service of Underwriters Laboratory.
2. Ball valves shall be rated 600 WOG, actuate from full “ON” to full “OFF”
by 90 degree turn of vinyl gripped valve handle.
3. Furnish and install only valves with factory installed type K copper tubing
extentions.
4. Valves not in valve boxes shall be provided with locking handles, Beacon
Medical series 4255 (locks to be installed by owner).
5. All valves shall be cleaned for oxygen, capped and sealed in a
polyethylene bag for shipping and storage.
3.0 EXECUTION
3.01 INSTALLATION
C. Copper, tubing, valves and fittings shall be pre-cleaned and prepared for
oxygen service by the manufacturer and received sealed on the job.
Certificates of origin and of proper preparation shall be maintained on the job
site attesting the above.
D. The use of flux is prohibited when making of joints between copper to copper
pipes and fittings.
E. During any brazing operation, the interior of the pipe shall be purged
continuously with oil free, dry nitrogen following the procedure in NFPA 99
5.1.10.5.5. At the completion of any section, all open pipe ends shall be
capped using an EXTERNAL cap.
H. After installation of the piping, but before installation of the outlet valves, blow
lines clear using oil-free air or nitrogen.
J. Label piping with name of gas service, identification color and direction of
flow. Where nonstandard pressures are piped, label for pressure. Labels
shall be placed at least once every 20 feet of linear run or once in each story
(whichever is more frequent. A label shall additionally be place immediately
on each side of each wall or floor penetration. Pipe labels shall be self
adhesive vinyl or other water resistant material with permanent adhesive
colored in accordance with NFPA 99 Table 5.1.11 and shall be visible on all
sides of the pipe. Pipe labels shall be Beacon Medical Series 6-435.
K. Alarms and valves shall be labeled for gas service and areas monitored or
controlled. Coordinate with owner for final room or area designations. Label
valves with name and identification color of the gas and direction of flow.
A. Provide a concrete equipment pad for the Medical Air Compressor and the
Medical Vacuum pump.
B. Construct concrete bases of dimensions indicated, but not less than 4 inches
(100 mm) larger in both directions than supported unit and not less than 4
inches high.
A. Prior to declaring the lines ready for final verification, the installing contractor
shall follow strictly the procedures for verification as described in NFPA 99
5.1.12.2 and attest in writing over the notarized signature of an officer of their
company to the following:
1. That all brazing was conducted by brazers qualified to ASSE 6010 and
holding current medical gas endorsements.
2. That all brazing was conducted with nitrogen purging. (Procedure per
NFPA 99 5.1.10.5.5).
3. That the lines have been blown clear of any construction debris using oil
free dry nitrogen or air are clean and ready for use. (Procedure per NFPA
99 5.1.12.2.2).
4. That the assembled piping, prior to the installation of any devices,
maintained a test pressure 1 ½ times the standard pressures listed in
NFPA 99 Table 5.1.11 without leaks (Procedure per JFPA 99 5.1.12.2.3).
5. That after installation of all devices, the pipeline was proven leak free for
24 hours at a pressure 20% above the standard pressures listed in NFPA
99 Table 5.1.11. (Procedure per NFPA 99 5.1.12.2.2.6).
6. That the systems have been checked for cross connections and none
were found. (Procedure per NFPA 99 5.1.12.2.4).
B. Provide four originals of the affidavit, distributed: (1) to the engineer, (1) to the
owner’s representative, (1) to the general contractor and (1) to the verifier.
A. Prior to handing over the systems to the owner, contractor shall retain a
Verifier acceptable to the owner who shall follow strictly the procedures for
verification as described in NFPA 99 5.1.12.3 and provide a written report
and certificate bearing the notarized signature of an officer of the verification
company which contains the following:
1. A current ACORD insurance certificate indicating a policy valid at least
one year from the date of the affidavit.
2. A listing of all tests performed, and listing each source, outlet, valve and
alarm included in the testing.
3. An assertion that all tests were performed by a MGPHO Certified Medical
Gas Verifier (CMGV) or by individuals qualified to perform the work and
under the immediate supervision a CMGV Verifier. Include the names,
credential numbers an expiration dates for all individuals working on the
project.
4. A statement form the intended third party verifier stating that the verifier
undertakes to verify this project and thus agrees to disqualify themselves
from supplying any equipment which will be included in the scope of there
verification. No verifier who supplies equipment shall be permitted to
verify that equipment or any component of the system connected to that
equipment.
5. A statement that equipment used was calibrated at least within the last six
months by a method traceable to a National Bureau of Standard
Reference and enclosing certificates or other evidenced of such
calibrations(s). where outside laboratories are used in lieu of on site
equipment, those laboratories shall be named and their original reports
enclosed.
6. A statement that where and when needed, equipment was recalibrated
during the verification process and describing the method(s) used.
7. A statement that the systems were tested and found to be free of debris
to a procedure per NFPA 99 5.1.12.3.7.
8. The flow from each outlet when tested to a procedure per NFPA 99
5.1.12.3.10.
9. A statement that the systems were tested and found to have no cross-
connections to a procedure per NFPA 99 5.1.12.3.3.
10. A statement that the systems were tested and found to be free of
contaminants to a procedure per NFPA 99 5.1.12.3.8.
11. A statement that all local signals function as required under NFPA 99
5.1.3.4.7 and as per the relevant NFPA 99 sections relating to the
sources.
12. A listing of local alarms, their function and activation per NFPA 99
5.1.12.3.14.
13. A listing of local alarms, their function and activation, including pressures
for high and low alarms per NFPA 99 5.1.12.3.5.2.
14. A listing of area alarms, their function and activation pressures per NFPA
99 5.1.12.3.5.3.
15. A statement that the sources include all alarms required by NFPA 99
Table 5.1.9.4.
16. The concentration of each component of NFPA 99 Table 5.1.12.3.12 in
he medical air after 24 hours of operation of the medical air source.
17. The concentration of each gas at each outlet as specified in NFPA 99
5.1.12.3.11.
18. A statement that all valves and alarms are accurately labeled as to zone
of control.
B. Provide four originals of this affidavit, distributed: (1) to the engineer, (1) to
the owner’s representative, (1) to the general contractor and (1) to the
installing contractor.
15410
PLUMBING FIXTURES
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
plumbing fixtures. Comply with other Division 15 sections and drawings as
applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the plumbing fixtures specified herein,
as indicated on the drawings, and as required to provide complete and
operating systems.
1. Fixtures
a. American Standard
b. Kohler Company
c. Crane Company
d. Toto
e. Zurn
2. Faucets
b. Speakman Company
d. Delta
f.
g. American Standard
h. Moen
3. Flush Valves
4. Seats
b. Olsonite Corporation
c. Beneke Corporation
d. Bemis
5. Carriers
6. Drinking Fountains
c. Ebco/Oasis
2.0 PRODUCTS
2. All handwashing sinks must be no less than 144 square inches with a
minimum dimension in either direction of 9”. Discharge point of the faucet
to the sink basin must be no less than 10”. Wrist blades must be at least
4” long. Substitution of the Basis of Design fixtures must comply with
these dimensional requirements and verification of compliance is the
burden of the contractor.
3.0 EXECUTION
3.01 INSTALLATION
B. Caulking: This Contractor shall caulk the joint between the finished wall
surface and all plumbing fixtures. Verify colors with the Architect. Caulking
material shall comply with the appropriate section of these Specifications.
D. Each fixture shall be provided with a shut-off valve for each supply line. All
exposed lines shall be chromium-plated.
15500
FIRE PROTECTION SYSTEMS
PART 1 - GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the fire
protection system. Comply with other Division 15 sections and drawings as
applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the fire protection system specified
herein, as indicated on the drawings, and as required to provide complete
and operating systems.
C. Applications: Application of the fire protection system shall include, but are
not limited to, the systems as listed below:
1. Hydraulically designed sprinkler system.
D. Quality Assurance:
1. Materials shall be installed in accordance with NFPA 13. Valves, fittings,
sprinkler heads, and equipment shall be UL listed and FM approved.
2. Hose threads shall conform to local fire department requirements.
3. Coordination Drawings: The following supplements, and does not replace,
the provisions for submittals called for in Section 23 01 00, "Basic
Mechanical Requirements", of this Specification.
a. Before starting fabrication or installation of equipment, the Contractor
shall submit to Architect, for his consideration, three sets of Shop
Drawings noted as reviewed by the ISO for insurance rate making
purposes only.
b. After Contract award and prior to releasing any equipment orders for
fabrication, six sets of Shop Drawings showing dimensions, weights,
performance data, structural details, and physical appearance of
valves, and controls shall be submitted to the Architect for review and
approval.
E. Pipe Hangers and Supports: Support fire protection pipe with UL-listed and
FM approved hangers and support devices. Provide any special hangers or
supports that may be required. The design, selection, spacing, and
application of horizontal pipe hangers, supports, restraints, anchors, and
guides shall be in accordance with the NFPA 13 and NFPA 14. Support
vertical pipes at least every other floor with approved riser clamps.
F. Sprinkler System:
1. System piping shall be hydraulically designed throughout areas in
accordance with the rules and regulations of NFPA 13, using design
densities of:
a. Light hazard areas: 0.10 gpm per 1,500 square feet with maximum
Sprinkler head spacing of 225 square feet per sprinkler head.
b. All ordinary hazard areas: 0.20 gpm per 1,500 square feet with
maximum sprinkler head spacing of 130 square feet.
2. Cross main pipe sizes shall be a minimum of 2" diameter for loop systems
and 2 1/2" for single main (non-loop) systems. Generally, provide
coverage at the rate required by NFPA and applicable state and local
codes.
3. System shall include required drain lines, drum drip (for maintenance),
test connections, spare heads, tools, fire department inlet connections,
water motor alarms, circuit closers, monitor switches, alarm valves,
isolation valves and similar items.
4. Sprinkler heads, valves, alarms, and similar items shall be as
manufactured by Viking, Grinnell, or other approved manufacturer.
Sprinkler heads shall be plain brass, up-right type in unfinished areas and
concealed pendent sprinklers in areas with ceilings. Material and
equipment used in the installation of the sprinkler systems and standpipes
shall be listed and approved by the Underwriters' Laboratories, Inc., and
shall be the latest design of the manufacturer.
bonnet, and bronze seats. 300 and 400 psig valves shall have bronze
wedge disc, union bonnet, and bronze body seat rings.
3. Gate valves over 2" shall be iron body, OS&Y, bolted bonnet, bronze
seats, ANSI 16.1, flanged ends. 150 psig valves shall have double or
single disc, and bronze trim. 300 and 400 psig valves shall have wedge
disc and brass stem.
4. Butterfly valves 2" and larger shall be grooved type. Furnish with built-in
supervisory switches.
5. Supervised valves shall include valve tamper switches. Valve tamper
switches shall be double-pole single-throw type with cast aluminum
housing and tamperproof cover. Switch rating shall be at least 7 amperes
at 125/250 volts.
PART 2 - PRODUCTS
2.01 PIPING
B. Fittings: Fittings shall be cast iron threaded sprinkler fittings ANSI B16.4 or
grooved ends fittings joined by grooved couplings Victaulic Firelock or equal
or welded fittings, ANSI B16.9. Flanges shall be screwed or welded neck
type ANSI B16.5.
2.02 EQUIPMENT
PART 3 - EXECUTION
2. Grade piping to eliminate traps and pockets. Where air pockets or water
traps cannot be avoided, provide hose bibs for drainage.
3. The Sprinkler Contractor shall arrange with the General Contractor to
notch or pre-drill the occasional beam in order to maintain the sprinkler
mains as high as possible.
4. All required sprinkler heads shall be individually dropped from the main to
the ceiling. Provide each drop with a horizontal swing arm type branch
run to allow future movement of the head.
5. All sprinkler heads in areas to be finished shall be installed at finished
ceiling height only where the ceiling is to be installed at this time such as
elevator lobbies and restrooms. In future tenant spaces, install upright
heads at a maximum of 100 square feet per sprinkler head, pending
development of the areas. Also, in future tenant spaces, a 1” outlet shall
be provided with a temporary 1” nipple and 1” x ½” reducer and a
temporary sprinkler head. Coordinate locations to ensure sprinkler heads
are centered in ceiling tiles.
6. Sprinkler piping shall be installed and coordinated with the duct and other
mechanical and electrical services in the ceiling cavities by this
Contractor, to provide the clearances for lighting fixtures as required.
7. Sprinkler piping shall be installed so as not to impede access to
mechanical, electrical, or plumbing equipment.
8. Refer to Section 15190, “Equipment and Piping Identification” for painting,
nameplates, and labeling requirements. Painting is not part of this
contract scope unless otherwise specified within the contract documents.
9. Sprinkler piping shall be flushed to remove excess oils and contaminants
that support the growth of microorganisms.
B. No other trade shall come in contact with fire protection piping. All piping
shall be suspended in the ceiling cavity as to not come in contact with
ductwork, domestic water piping, conduit, etc.
15530
REFRIGERANT PIPING
1. GENERAL
2. PRODUCTS
2.01 MATERIAL:
A. PIPE:
B. FITTINGS:
3. EXECUTION
3.01 EXAMINATION:
B. Install refrigerant piping with 1/8" per foot (1%) downward slope in direction of
oil return to compressor.
C. Provide oil traps and double risers where required to provide oil return.
E. Remove excess oil by swabbing with cloth soaked in high flash point
petroleum solvent, squeezed dry.
B. During evacuation, apply heat to pockets, elbows, and low spots in piping.
E. Complete charging system using new filter dryer core in charging line.
Section 15535
REFRIGERANT SPECIALTIES
1. GENERAL
2. PRODUCTS
2.01 MANUFACTURERS:
2.02 EQUIPMENT:
B. Refrigerant Valves:
1. Globe Shutoff Valves:
a. Cast iron, packed, back seating type with winged seal cap.
b. 300F temperature rating, 300 psi working pressure.
2. Check Valves:
a. Cast iron, accessible internal parts.
b. 300F temperature rating, 300 psi working pressure.
I. Receiver:
1. Copper shell with brazed points and fusible relief plug
3. EXECUTION
3.01 EXAMINATION:
A. Examine areas and conditions under which refrigerant piping materials and
products are to be installed.
B. Do not proceed with work until satisfactory conditions are present.
15720
PACKAGED DX CONSTANT VOLUME ROOFTOP UNITS
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
packaged direct expansion constant volume rooftop units. Comply with other
Division 15 sections and drawings as applicable. Refer to other divisions for
coordination of work.
A. Work Included: Provide roof top constant air volume air-conditioning system,
complete with controls and accessories as specified. Roof curbs are
furnished under this section. Coordinate installation of curbs with Roofing
Contractor.
1.04 SUBMITTALS
A. Shop drawings submittals shall include, but are not limited to, the following:
5. Warranty information.
2.0 PRODUCTS
2.01 MANUFACTURERS
1. York
2. Carrier
3. Trane
A. General
B. Unit Cabinet
2. Cabinet panels shall be hinged or removable for easy servicing and shall
provide a water tight seal. All panels and covers shall be insulated with ½
inch, one pound density matt faced, fire resistant, permanent, odorless,
fiber glass insulation.
C. Fans
1. Evaporator Fan
2. Condenser Fan
a. Outdoor fans shall be of the direct driven propeller type statically and
dynamically balanced in the factory and be protected by a wire guard.
b. Outdoor fans shall discharge air vertically upward and shall have
permanently lubricated bearings and thermal overload protection.
D. Compressors
E. Coils
G. Refrigerant Components
1. Refrigerant circuit components shall include: Filter dryers, liquid line sight
glasses, compressor discharge valves, liquid line service valves and
thermal expansion valves.
H. Filter Section
1. Standard filter section shall consist of low velocity, disposable two inch
thick glass fiber filters in commercially available sizes. Filters shall be not
less than 30% efficient when tested in accordance with ASHRAE
Standards. Temporary filer media shall be provide throughout the course
of construction and shall be changed as required to maintain proper unit
operation and filtration. Provide new set of filters when building is turned
over to the Owner.
c. Crankcase heaters.
J. Operating Characteristics:
4. Unit shall be factory equipped with shutoff valve and tubing to maintain
capacity control at minimal cooling loads.
K. Electrical Requirements: All unit power wiring shall enter cabinet at single
location.
L. Motors
M. Accessories to include:
1. Integrated Economizer: For units 7.5 tons and greater, enthalpy controlled
integrated type consisting of dampers, motors and linkages, and
potentiometer in conjunction with control system to provide primary
cooling using outdoor air, enthalpy permitting, supplemented with
mechanical cooling when necessary.
b. Linkages shall have spring return feature which shuts dampers upon
power interruption or unit shutdown.
3. Curb:
A. Each unit shall be provided with a full perimeter, curb and allow for MERV 14
filter installation where indicated on the schedule. The roof curb shall be of
the same manufacturer as the unit, shall support the unit and provide a
3.0 EXECUTION
3.01 START-UP
3.02 INSTALLATION
2. The rigging and setting of the units shall be in accordance with the unit
manufacturer’s recommendations.
15770
DUCTLESS SPLIT SYSTEM UNITS
PART 1 GENERAL
1.1 SUMMARY
B. This section describes the basic materials and installation methods for the ductless,
variable capacity, heat pump heat recovery air conditioning system. Comply with other
Division 15 sections and drawings as applicable. Refer to other divisions for
coordination of work.
C. Furnish and install all components of the variable capacity, heat pump heat recovery air
conditioning system specified herein, as indicated on the drawings, and as required to
provide complete and operating systems.
A. Work Included: Provide a UL listed split system air conditioning unit work including, but
not limited to, the furnishing and installation of an indoor evaporator unit, an air-cooled
condensing unit, filters, refrigerant piping thermostat, accessories and other controls as
required by local, state, and other applicable codes.
1. Daikin
C. The units shall be listed by Electrical Laboratories (ETL) and bear the ETL label.
D. All wiring shall be in accordance with the National Electrical Code (N.E.C.).
E. The units shall be manufactured in a facility registered to ISO 9001 and ISO14001 which
is a set of standards applying to environmental protection set by the International
Standard Organization (ISO).
F. A full charge of R-410A for the condensing unit only shall be provided in the condensing
unit.
1.4 SUBMITTALS
A. Shop drawings submittals shall include, but are not limited to, the following:
A. Deliver split system air conditioning units and accessories in factory-fabricated water-
resistant wrapping.
C. Store units and accessories in a clean, dry space and protect from the weather.
1.6 WARRANTY
A. The units shall be covered by an extended manufacturer’s limited warranty for a period
of five (5) years from date of installation.
B. In addition the compressor shall have a manufacturer’s limited warranty for a period of
six (6) years from date of installation.
C. If, during this period, any part should fail to function properly due to defects in
workmanship or material, it shall be replaced or repaired at the discretion of the
manufacturer. This warranty shall not include labor.
D. System shall be installed by an authorized dealer with factory installation and service
training.
PART 2 PRODUCTS
A. General:
The R2-Series PURY outdoor unit shall be used specifically with CITY MULTI VRFZ
components. The R2-Series shall consist of the PURY outdoor unit, Branch Circuit (BC)
Controller, indoor units (-E models), and M-NET DDC (Direct Digital Controls). The
PURY outdoor units shall be equipped with multiple circuit boards that interface to the M-
NET controls system and shall perform all functions necessary for operation. The
outdoor unit shall have a powder coated finish. The outdoor unit shall be completely
factory assembled, piped and wired. Each unit shall be run tested at the factory.
1. The sum of connected capacity of all indoor air handlers shall range from 50% to
150% of outdoor rated capacity.
B. Unit Cabinet:
C. Fan:
1. The PURY-P72 / P96 / P108 / P126 / P144TGMU outdoor unit shall be furnished
with one direct drive, variable speed propeller type fan.
2. The PURY-P168 / P192 / P204 / P216 / P234TGMU outdoor unit shall be
furnished with two direct drive, variable speed propeller type fans.
3. All fan motors shall have inherent protection, have permanently lubricated
bearings, and be completely variable speed.
4. All fan motors shall be mounted for quiet operation.
5. All fans shall be provided with a raised guard to prevent contact with moving
parts.
6. The outdoor unit shall have vertical discharge airflow.
D. Refrigerant
E. Coil:
4. Refrigerant flow from the outdoor unit shall be controlled by means of an inverter
driven compressor.
5. The outdoor coil shall include 4 circuits with two position valves for each circuit,
except for the last stage.
F. Compressor:
G. Electrical:
1. The outdoor unit electrical power shall be 208/230 volts, 3-phase, 60 hertz.
2. The outdoor unit shall be capable of satisfactory operation within voltage limits of
187-228 volts (208V/60Hz) or 207-253V (230V/60Hz).
3. The outdoor unit shall be controlled by integral microprocessors.
4. The control circuit between the indoor units, BC Controller and the outdoor unit
shall be 24VDC completed using a 2-conductor, twisted pair shielded cable to
provide total integration of the system.
A. General:
The BC (Branch Circuit) Controllers shall be specifically used with R410A R2-Series
systems. These units shall be equipped with a circuit board that interfaces to the M-NET
controls system and shall perform all functions necessary for operation. The unit shall
have a galvanized steel finish. The BC Controller shall be completely factory
assembled, piped and wired. Each unit shall be run tested at the factory. This unit shall
be mounted indoors. The sum of connected capacity of all indoor air handlers shall
range from 50% to 150% of rated capacity.
B. BC Unit Cabinet:
C. Refrigerant
D. Refrigerant valves:
1. The unit shall be furnished with multiple branch circuits which can individually
accommodate up to 54,000 BTUH and/or three indoor units. Branches may be
twinned to allow more than 54,000 BTUH.
2. Each branch shall have multiple two-position valves to control refrigerant flow.
3. Service shut-off valves shall be field-provided/installed for each branch to allow
service to any indoor unit without field interruption to overall system operation.
4. Linear electronic expansion valves shall be used to control the variable
refrigerant flow.
F. Electrical:
A. General:
The PKFY shall be wall-mounted indoor unit section with a slim silhouette and shall have
a modulating linear expansion device. The PKFY shall be used with the R2-Series
outdoor unit and BC Controller, Y-Series outdoor unit, or S-Series outdoor unit. The
PKFY shall support individual control using M-NET DDC controllers.
B. Indoor Unit
The indoor unit shall be factory assembled, wired and run tested. Contained within the
unit shall be all factory wiring, piping, electronic modulating linear expansion device,
control circuit board and fan motor. The unit shall have a self-diagnostic function, 3-
minute time delay mechanism, an auto restart function, and a test run switch. Indoor
unit and refrigerant pipes shall be charged with dehydrated air before shipment from the
factory.
C. Unit Cabinet:
D. Fan:
1. The indoor fan shall be an assembly with one or two line-flow fan(s) direct driven
by a single motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. A manual adjustable guide vane shall be provided with the ability to change the
airflow from side to side (left to right).
4. A motorized air sweep louver shall provide an automatic change in airflow by
directing the air up and down to provide uniform air distribution.
E. Filter:
F. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. Both refrigerant lines to the PKFY indoor units shall be insulated.
G. Electrical:
H. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options.
A. General:
1. The PLFY shall be a four-way cassette style indoor unit that recesses into the
ceiling with a ceiling grille. The indoor unit shall be factory assembled, wired and
run tested. Contained within the unit shall be all factory wiring, piping, electronic
modulating linear expansion device, control circuit board and fan motor. The unit
shall have a self-diagnostic function, 3-minute time delay mechanism, an auto
restart function, an emergency operation function and a test run switch. Indoor
unit and refrigerant pipes shall be charged with dehydrated air before shipment
from the factory.
B. Unit Cabinet:
C. Fan:
1. The indoor fan shall be an assembly with a turbo fan direct driven by a single
motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor fan shall consist of five (5) speed settings, Low, Mid1, Mid2, High and
Auto.
4. The fan shall have a selectable Auto fan setting that will adjust the fan speed
based on the difference between controller set-point and space temperature.
5. The indoor unit shall have an adjustable air outlet system offering 4-way airflow,
3-way airflow, or 2-way airflow.
6. The indoor unit shall have switches that can be set to provide optimum airflow
based on ceiling height and number of outlets used.
7. The indoor unit vanes shall have 5 fixed positions and a swing feature that shall
be capable of automatically swinging the vanes up and down for uniform air
distribution.
8. The vanes shall have an Auto-Wave selectable option in the heating mode that
shall randomly cycle the vanes up and down to evenly heat the space.
9. If specified, the grille shall have an optional i-see sensor that will measure room
temperature variations and adjust the airflow accordingly to evenly condition the
space.
D. Filter:
E. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. The unit shall include a condensate lift mechanism that will be able to raise drain
water 33 inches above the condensate pan.
7. Both refrigerant lines to the PLFY indoor units shall be insulated.
F. Electrical:
G. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system.
A. General:
1. The PLFY shall be a four-way cassette style indoor unit that recesses into the
ceiling with a ceiling grille. The indoor unit shall be factory assembled, wired and
run tested. Contained within the unit shall be all factory wiring, piping, electronic
modulating linear expansion device, control circuit board and fan motor. The unit
shall have a self-diagnostic function, 3-minute time delay mechanism, an auto
restart function, an emergency operation function and a test run switch. Indoor
unit and refrigerant pipes shall be charged with dehydrated air before shipment
from the factory.
B. Unit Cabinet:
1. The cabinet shall be a compact 22-7/16” wide x 22-7/16” deep so it will fit within a
standard 24” square suspended ceiling grid.
2. The cabinet panel shall have provisions for a field installed filtered outside air
intake.
3. Four-way grille shall be fixed to bottom of cabinet allowing two, three or four-way
blow.
C. Fan:
1. The indoor fan shall be an assembly with a turbo fan direct driven by a single
motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor fan shall consist of three (3) speeds, Low, Mid, and High.
4. The indoor unit shall have an adjustable air outlet system offering 4-way airflow,
3-way airflow, or 2-way airflow.
5. The auto air swing vanes shall be capable of automatically swinging up and
down for uniform air distribution.
D. Filter:
E. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. The unit shall include a condensate lift mechanism that will be able to raise drain
water 19-3/4” inches above the condensate pan.
7. Both refrigerant lines to the PLFY indoor units shall be insulated.
F. Electrical:
G. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system.
A. General:
1. The PMFY shall be a one-way cassette indoor unit that recesses into the ceiling
with a ceiling grille and shall have a modulating linear expansion device. The
PMFY shall be used with the R2-Series outdoor unit and BC Controller, Y-Series
outdoor unit, or S-Series outdoor unit. The PMFY shall support individual control
using M-NET DDC controllers.
B. Indoor Unit.
1. The indoor unit shall be factory assembled, wired and run tested. Contained
within the unit shall be all factory wiring, piping, electronic modulating linear
expansion device, control circuit board and fan motor. The unit shall have a self-
diagnostic function, 3-minute time delay mechanism, an auto restart function, an
emergency operation function and a test run switch. Indoor unit and refrigerant
pipes shall be charged with dehydrated air before shipment from the factory.
C. Unit Cabinet:
D. Fan:
1. The indoor fan shall be an assembly with one line-flow fan direct driven by a
single motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor fan shall consist of four (4) speeds, Low, Mid1, Mid2, and High.
E. Filter:
F. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. The condensate lift mechanism shall be able to raise drain water 23 inches
above the condensate pan.
7. Both refrigerant lines to the PMFY indoor units shall be insulated.
G. Electrical:
H. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options.
A. General:
The PDFY shall be a ceiling-concealed ducted indoor fan coil design that mounts above
the ceiling with a 2-position, field adjustable return and a fixed horizontal discharge
supply and shall have a modulating linear expansion device. The PDFY shall be used
with the R2-Series outdoor unit and BC Controller, Y-Series outdoor unit, or S-Series
outdoor unit. The PDFY shall support individual control using M-NET DDC controllers
B. Indoor Unit.
The indoor unit shall be factory assembled, wired and run tested. Contained within the
unit shall be all factory wiring, piping, electronic modulating linear expansion device,
control circuit board and fan motor. The unit shall have a self-diagnostic function, 3-
minute time delay mechanism, and an auto restart function. Indoor unit and refrigerant
pipes shall be charged with dehydrated air before shipment from the factory.
C. Unit Cabinet:
D. Fan:
1. The indoor unit fan shall be an assembly with one or two Sirocco fan(s) direct
driven by a single motor.
2. The indoor fan shall be statically and dynamically balanced and run on a motor
with permanently lubricated bearings.
3. The indoor unit shall have a ducted air outlet system and ducted return air
system.
E. Filter:
1. Return air shall be filtered by means of a standard factory installed return air
filter.
2. Optional return filter box (rear or bottom placement) with high-efficiency filter
shall be available for all PDFY indoor units.
F. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. The condensate shall be gravity drained from the fan coil.
7. Both refrigerant lines to the PDFY indoor units shall be insulated.
G. Electrical:
H. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options.
A. General:
B. Indoor Unit.
1. The indoor unit shall be factory assembled, wired and run tested. Contained
within the unit shall be all factory wiring, piping, electronic modulating linear
expansion device, control circuit board and fan motor. The unit shall have a self-
diagnostic function, 3-minute time delay mechanism, and an auto restart function.
Indoor unit and refrigerant pipes shall be charged with dehydrated air before
shipment from the factory.
C. Unit Cabinet:
D. Fan:
1. The indoor unit fan shall be an assembly with one Sirocco fan direct driven by a
single motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor fan shall consist of three (3) speeds, High, Mid, and Low.
4. The indoor unit shall have a ducted air outlet system and ducted return air
system.
E. Filter:
1. Return air shall be filtered by means of a standard factory installed return air
filter.
F. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. The condensate shall be gravity drained from the fan coil.
7. Both refrigerant lines to the PEFY indoor units shall be insulated.
G. Electrical:
H. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options.
A. General:
B. Indoor Unit.
1. The indoor unit shall be factory assembled, wired and run tested. Contained
within the unit shall be all factory wiring, piping, electronic modulating linear
expansion device, control circuit board and fan motor. The unit shall have a self-
diagnostic function, 3-minute time delay mechanism, and an auto restart function.
Indoor unit and refrigerant pipes shall be charged with dehydrated air before
shipment from the factory.
C. Unit Cabinet:
2. The cabinet panel shall have provisions for a field installed filtered outside air
intake.
D. Fan:
1. The indoor unit fan shall be an assembly with one or two Sirocco fan(s) direct
driven by a single motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor unit shall have a ducted air outlet system and ducted return air
system.
E. Filter:
F. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. The condensate shall be gravity drained from the fan coil.
7. Both refrigerant lines to the PEFY indoor units shall be insulated.
G. Electrical:
1. The unit electrical power shall be 208/230 volts, 1-phase, 60 hertz, except for the
PEFY-P72NMHU-E and PEFY-P86NMHU-E. The PEFY-P72NMHU-E and
PEFY-P96NMHU=E shall be 208/230 volts, 3-phase, 60 hertz.
2. The system shall be capable of satisfactory operation within voltage limits of 187-
228 volts (208V/60Hz) or 207-253 volts (230V/60Hz).
H. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options.
A. General:
1. The PFFY shall consist of a floor-standing indoor section with and shall have a
modulating linear expansion device. The PFFY shall be used with the R2-Series
outdoor unit and BC Controller, Y-Series outdoor unit, or S-Series outdoor unit.
The PFFY shall support individual control using M-NET DDC controllers.
B. Indoor Unit
1. The indoor unit shall be factory assembled, wired and run tested. Contained
within the unit shall be all factory wiring, piping, electronic modulating linear
expansion device, control circuit board and fan motor. The unit shall have a self-
diagnostic function, 3-minute time delay mechanism, an auto restart function, and
a test run switch. Indoor unit and refrigerant pipes shall be charged with
dehydrated air before shipment from the factory.
E. Fan:
1. The indoor unit fan shall be an assembly with one or two Sirocco fan(s) direct
driven by a single motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor fan shall consist of two (2) speeds, High and Low.
F. Filter:
G. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
5. A condensate pan and drain shall be provided under the coil.
6. Both refrigerant lines to the PFFY indoor units shall be insulated.
H. Electrical:
I. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options.
A. General:
B. Indoor Unit
1. The indoor unit shall be factory assembled, wired and run tested. Contained
within the unit shall be all factory wiring, piping, electronic modulating linear
expansion device, control circuit board and fan motor. The unit shall have a self-
diagnostic function, 3-minute time delay mechanism, an auto restart function, and
a test run switch. Indoor unit and refrigerant pipes shall be charged with
dehydrated air before shipment from the factory.
C. Unit Cabinet:
D. Fan:
1. The indoor unit fan shall be an assembly with two, three, or four Sirocco fan(s)
direct driven by a single motor.
2. The indoor fan shall be statically and dynamically balanced to run on a motor
with permanently lubricated bearings.
3. The indoor fan shall consist of four (4) speeds, Low, Mid1, Mid2, and High.
E. Filter:
F. Coil:
1. The indoor coil shall be of nonferrous construction with smooth plate fins on
copper tubing.
2. The tubing shall have inner grooves for high efficiency heat exchange.
3. All tube joints shall be brazed with phos-copper or silver alloy.
4. The coils shall be pressure tested at the factory.
G. Electrical:
H. Controls:
1. This unit shall use controls provided by Mitsubishi Electric to perform functions
necessary to operate the system. Please refer to Part 5 of this guide
specification for details on controllers and other control options
The Deluxe MA Remote Controller shall only be used in the same group with other
Deluxe MA Remote Controllers (PAR-21MAA), Wireless MA (PAR-FL32MA / PAR-
FA32MA), or Simple MA Remote Controllers (PAC-YT51CRB), with up to two remote
controllers per group.
The Deluxe MA Remote Controller shall require no addressing. The Deluxe MA Remote
Controller shall connect using two-wire, stranded, non-polar control wire to TB15
connection terminal on the indoor unit. The PAR-21MAA shall require cross-over wiring
for grouping across indoor units.
PART 3 - EXECUTION
3.1 INSTALLTION
B. Mounting: Provide foundation, platforms, and hangers required for proper installation of
equipment.
C. Fans: Install fans to operate without noticeable vibration or noise after installation.
D. Guards: Arrange belt guards to permit accessible tachometer readings, oiling, and
testing with guards in position.
E. Refrigerant Piping: Install, test, evacuate and charge refrigerant piping per the
manufacturer's recommendations and as specified in Section 15530, “Refrigerant
Piping”. Technician performing this work shall be certified and shall utilize proper
refrigerant reclaim procedures.
15800
DUCTWORK
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
duct systems. Comply with other Division 15 sections and drawings as
applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the duct systems specified herein, as
indicated on the drawings, and as required to provide complete and operating
systems.
A. Work Included:
B. Types: The types of ductwork specified in this Section include, but are not
necessarily limited to the following:
1. Air conditioning cooling and/or heating supply and return air systems
D. VAV Supply Air Ductwork Upstream of Terminal Units (round or flat oval):
Ductwork shall be sheet metal designed for velocities up to 2,800 fpm. The
ductwork shall meet the latest SMACNA Standards for construction and
stiffening based on the maximum pressure in the ductwork. Ductwork shall
be 3” W.C. pressure class.
6. NFPA 90-B, Standard for the Installation of Warm Air Heating and Air
Conditioning Systems, 2009 edition.
B. Fire and Smoke Rating Test Standards: ASTM E84, NFPA 255 and UL 723.
1.04 SUBMITTALS
2.0 PRODUCTS
3.0 EXECUTION
B. All ductwork required for the heating, ventilating and air conditioning systems
shall be constructed and erected in a first class workmanlike manner. This
work shall be guaranteed for a period of one year from and after the date of
acceptance of the job against noise, chatter, whistling, vibration, and free
from pulsation under all conditions of operation.
C. The interior surface of all ductwork shall be smooth with no parts projecting
into the air stream unless specified to do so. All seams and joints shall be
external. The inside of all ductwork shall be thoroughly cleaned and all fans
operated to remove any debris prior to connection of air devices.
D. All holes in ducts for damper rods and other necessary devices shall be either
drilled or machine punched (not pin punched), and shall not be any larger
than necessary. All duct openings shall be provided with sheet metal caps if
the openings are to be left unconnected for any length of time.
G. Ductwork which is exposed to weather shall have soldered joints and seams
and shall be painted with a suitable epoxy coating. In lieu of solder joints, the
use of duct-mate or TDC manufactured flanges are acceptable.
3.02 COORDINATION
2. Round Ductwork: Minimum metal gauges for longitudinal and spiral seam
round ductwork shall be in accordance with SDCS Table 3-2. Minimum
aluminum gauges for longitudinal and spiral seam round ductwork shall
be in accordance with SDCS Table 3-3. Longitudinal seam ductwork
larger than 12" diameter shall not be permitted unless welded seams are
used.
4. Minimum Gauges: The metal gauges listed in the SDCS for round and
rectangular ductwork are the minimum recommended. It shall be the
Contractor's responsibility to select a metal gauge heavy enough to
withstand the physical abuse of installation.
1. General: Make all joints airtight. The distance between transverse joints
on any size duct shall not exceed 5'.
3. Spin-in Fittings: Spin-in fittings may be used for duct taps to air supply
and exhaust devices and shall include quadrant dampers even though a
volume damper may be specified for the air device. Spin-in fittings shall
be sealed at the duct tap with a gasket and compression fit or sealed with
duct sealant. The location of spin-in fittings in the ducts shall be
determined after terminal units are hung and the location of the light
fixtures is known so as to minimize flexible duct lengths and sharp bends.
Spin-ins shall be installed with their damper axis parallel to airflow. A
minimum of 18” must be provided between fittings.
F. Air Device Connections: Make connections to air devices and fabricate air
device plenums as detailed on the Drawings and in accordance with SDCS
Fig. 2-16 through 2-18.
4. Horizontal Ducts: Ducts larger than 50" in their greatest dimension shall
be supported by means of hanger rods bolted to angle iron or half round
trapeze hangers. Duct shall have at least one pair of supports 8'-0" on
centers according to the following:
Angle
Length Angle Rod Diameter
5. Vertical Ducts: Ducts shall be supported where they pass through the
floor lines with 1-1/2" x 1-1/2" x 1/4" angles for ducts up to 60". Above
60", the angles must be increased in strength and sized on an individual
basis considering space requirements.
G. Flexible Ductwork:
3. Terminal Unit Flexible Duct Connections: The terminal ends of the duct
core shall be secured by stainless steel worm gear type clamps. The
fittings on terminal units and on sheet metal duct shall be coated with
sealant, then the flexible duct core slipped over duct and the clamp
tightened, and the connections shall sealed with duct sealant. Insulation
of flexible duct shall be slipped over connection to point where insulation
abuts terminal unit or insulation on duct and attached with self-locking
nylon straps. The insulation connections shall then be sealed using foil
duct tape to provide vapor barrier. Refer to SDCS Page 3-13 and 3-15
for additional requirements.
4. Air Device Flexible Duct Connections: All joints and connections shall be
made by turning back the insulation and securing the inner liner with self-
locking nylon straps and sealing with two wraps of duct tape. The
insulation shall then be placed over the joint, attached with a self-locking
nylon strap and sealed on the exterior with an approved foil duct tape.
Refer to SDCS Page 3-13 and 3-15 for additional requirements.
1. Install duct mounted sensors and control devices furnished under Section
“Building Controls". Provide access doors at each duct mounted control
device. Coordinate location of devices and installation requirements with
the Controls Contractor.
2. Install duct type smoke detectors furnished under Division 16. Provide
access doors at each sampling tube assembly. Coordinate location of
detectors and installation requirements with Division 16.
3. Provide duct test ports in ductwork as required to properly balance all air
systems. Test ports shall be located per ANSI/ASHRAE Standard III to
allow accurate pitot-tube traverse measurements in ductwork.
B. Repairs: Strip protective paper from stainless ductwork surfaces and repair
finish or replace ductwork portion wherever it has been damaged.
15810
FANS AND HOODS
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the fan
and hood systems. Comply with other Division 15 sections and drawings as
applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the fan and hood systems specified
herein, as indicated on the drawings, and as required to provide complete
and operating systems.
A. Work Included: Provide U.L. listed fans and ventilators as required by code
and as specified.
2.0 PRODUCTS
A. Ratings: Fans shall be licensed to bear the AMCA certified ratings seal.
Ratings of fans shall be based on 70°F and 29.92" of Hg atmospheric
pressure. Air handling equipment shall be sized in conformance with
applicable codes and good engineering practice. Roof-mounted units shall
be located in coordination with the Architect to ensure proper sight lines.
selected for the rated fan rpm and shall be adjustable to as close as 10%
above and below the rated fan speed.
F. Belts: Provide standard "V-groove" belts suitable for the service intended
with the required capacities. The belts shall be closely matched and tagged
prior to delivery to the job site. If the belts do not appear to be properly
matched during operation, they shall be rechecked and, if necessary,
replaced. Belts shall be as manufactured by Gates, Durkee-Atwood,
Goodyear, Browning, or Uniroyal.
B. Motors: Provide standard drip-proof motors. Provide cast iron housings for
motors larger than 10 hp, riveted or spot-weld wheels with steel rims and hub
plates.
C. Fan: Blades shall be die cut, die-formed, and hubs shall be machined close-
grained cast iron. Steel housings shall have lock-seam construction with
discharge reinforcement and shall be adjustable with continuous inlet collars.
Provide weatherproof enclosure for motors and drive, if units are exposed to
weather.
A. General: Provide direct driven ceiling exhaust fans as required. Fan shall be
acoustically insulated and have a maximum sound level rating as scheduled.
C. Accessories:
3. Provide terminal box on the housing with cord, plug, and receptacle inside
the housing.
3.0 EXECUTION
A. General: Ventilating and exhaust fans not having integral vibration isolation
shall be mounted on or suspended by vibration isolators as specified under
Section 15210. Where ductwork is connected to fans, Contractor shall
provide UL labeled flexible duct connections.
3.02 SYSTEMS
B. Placement of fans and noise levels generated by the fans shall be taken into
consideration. Refer to specification 15010 for additional information.
15820
REGISTERS, GRILLES, AND DIFFUSERS
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
registers, grilles, and diffusers. Comply with other Division 15 sections and
drawings as applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the registers, grilles, and diffusers
specified herein, as indicated on the drawings, and as required to provide
complete and operating systems.
A. Work Included: Provide air outlets and inlets as required for the finished or
non-tenant areas of the project including the following:
2.0 PRODUCTS
A. General: Provide air outlets and inlets of the size, shape, and type,
constructed of materials and components, and with finishes as required.
Apply corrosion resistant treatment to surfaces prior to applying prime coat.
2. Supply Air Register: Provide supply air registers of the double deflection
type.
4. Return Air Grilles and Return Air Registers: Provide grilles and registers
as required.
1. Provide supply linear diffuser with length and width as required. The
supply diffuser shall be installed above the ceiling and located as
indicated on the Architectural and Mechanical Drawings.
3. The plenum shall be painted flat black on interior surfaces and the
exposed surfaces as viewed from below the ceiling system shall be
painted flat black.
3.0 EXECUTION
3.01 INSTALLATION
2. In all cases duct connection/elbow shall be made with a bend that has not
less than one duct diameter centerline radial.
15830
DUCTWORK ACCESSORIES
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
ductwork accessories. Comply with other Division 15 sections and drawings
as applicable. Refer to other divisions for coordination of work.
C. Furnish and install all components of the duct systems specified herein, as
indicated on the drawings, and as required to provide complete and operating
systems.
1. Turning vanes,
2. Access doors,
3. Fire dampers.
1.04 SUBMITTALS
A. Shop Drawings: Show modifications of indicated requirements, if applicable,
made to conform to local shop practice and show how these modifications
ensure that the materials and weights are not reduced and that the fabricated
units are equivalent to the specified requirements in every significant way.
2.0 PRODUCTS
A. General: Provide ductwork accessories that comply with the Section 15800,
"Ductwork", and other applicable product requirements of ductwork materials
noted in this Section.
A. General: Provide all direction and volume control and fire dampers shown or
noted on Drawings. All damper control devices shall be installed so as to be
fully concealed in finished rooms and spaces.
B. Control Dampers:
2. Extractors: Provide extractors of the size and type required, with hex-key
operated adjustable blades, and with gang operated galvanized steel
blades on one-inch centers.
4. Round Taps: Where taps to main ducts or their branches are made,
provide 45 degree angle taps or 90 degree spin-in taps with manual
volume dampers and nylon bushings on both sides of damper blade rod.
A. General: Provide hinged duct access doors, gasketed and with insulation
where ductwork is indicated to be insulated. Provide construction per
SMACNA Standards. Access doors shall be at least 15" x 15".
3.0 EXECUTION
3.01 INSTALLATION
A. Access Doors: Install access doors so that the doors open against the
system air pressure wherever feasible and that their latches are operable
from either side, except where the duct is too small to be entered. Provide
access to each fire damper link to permit resetting. Comply with the
applicable building codes or authority having jurisdiction and NFPA 96.
B. Inspection Plates: Install plates at each primary zone damper and where
otherwise required for inspection of operable mechanisms within the duct
systems.
E. Turning Vanes:
1. Install turning vanes for all rectangular mitered elbows. Install turning
vanes in accordance with SMACNA Standards.
2. Turning vanes for Ducts with air velocity less than 2500 FPM: Use single
wall type vanes for ducts having width equal to or less than 12 inches.
3. Use double wall type vanes for (2” radius, 2–1/8” spacing) for ducts
having widths greater than 12 inches.
4. If duct sizes change in a mitered elbow, use single wall type vanes with a
trailing edge extension.
3.02 TESTING
15980
TESTING, ADJUSTING, AND BALANCING
1.0 GENERAL
1.01 SUMMARY
B. This section describes the basic materials and installation methods for the
testing, adjusting, and balancing of HVAC systems. Comply with other
Division 15 sections and drawings as applicable. Refer to other divisions for
coordination of work.
A. Work Included:
1. All air and water systems shall be tested, adjusted, and balanced to
optimize operating and comfort conditions. Record test data as outlined
hereinafter and submit for review and approval. Systems shall be fully
tested and balanced prior to Building commissioning and acceptance.
4. All tenant finish air balancing will be by the tenant finish contractor. All air
and water moving equipment installed under the shell building contracts
will be balanced by the shell contractor.
A. Personnel: Submit evidence to show that the personnel who will actually
balance the systems are qualified. Evidence showing that the personnel
have passed the tests required by the Associated Air Balance Council
(AABC) or the National Environmental Balancing Bureau (NEBB) will be
sufficient.
2.0 PRODUCTS
Not applicable.
3.0 EXECUTION
A. General: Record test data after balancing has been completed and deliver
recorded data to the Engineer for review and evaluation. Should deficiencies
or discrepancies be found, repeat balancing procedures to achieve correct
test data results. Certify the test and balancing data as being true and
correct over the Contractor's signature. Execute the Certification by an
authorized officer if the contracting firm is a corporation, by a partner if the
firm is a partnership, by the firm's owner if the firm is a sole proprietorship, or
by the authorized representative if the firm is a joint venture. Include a copy
of the approved test and balancing data in the Owner's Manual.
B. Test Forms: Record and submit test and balancing data on forms similar to
those of the AABC or NEBB.
A. Submit evidence to show that the balancing devices are properly calibrated
before proceeding with system balancing.
A. General: When equipment start-up and pipe cleaning and testing procedures
have been completed, and systems are complete and ready for operation,
perform the following steps of water balancing and record the results.
1. Compression Tanks and Air Vents: Verify that compression tanks have
water-showing gauge glasses, but that tanks are not water logged.
Check air vents at system high points and at water coils to ensure all air
has been removed from the circulating systems.
2. Open System Tests: Open stops, balancing, and control valves. Read
and record pressure rise across pumps.
3. Adjusted System Tests: Adjust balancing valves at each coil for design
flow. Adjust balancing valves at pumps to obtain design water flow.
Record pressure rise across pumps and gpm flow from pump curve.
Permanently mark the balanced position for each valve.
4. Ampere Readings: Read and record full load amperes for each pump
motor.
A. General: When tests have been completed and systems are complete and
ready for operation, perform the following steps of final air balance and record
the results.
C. Filters: Check air filters or filter media. Balance system only with clean filters
or filter media.
D. Airflow at Each Unit: Read and record return and/or outside air, supply air
cfm, and temperature at each fan and blower.
E. Water flow at Each Unit: Set thermostat for full cooling and for full heating
loads. Measure and record supply and return water flow at each
cooling/heating coil.
F. Coil Temperatures: Set thermostat for full cooling and for full heating loads.
Read and record entering and leaving dry bulb and wet bulb temperatures at
each cooling and heating coil.
G. Outlet Airflow: Adjust each air exhaust inlet and supply diffuser, register, and
grille to within 10% of design air cfm. Dampers in diffusers (if specified) may
be used for only 10% adjustment from full open airflow. Include terminal
points of air supply and points of exhaust.
16010
GENERAL ELECTRICAL REQUIREMENTS
1.0 GENERAL
1.01 SUMMARY
C. No deviation from the Contract Documents shall be made without the written
consent of the Architect and Engineer.
E. The Drawings are schematic and are not intended to show the exact location
of outlets, devices, etc. or the routing of conduit.
G. The right is reserved to relocate any device (receptacle, switch, fire alarm,
audio/visual, junction box, outlet, etc.) a maximum of 10’-0” before it is
permanently installed without incurring additional cost to the Contract.
A. All work shall comply with the most recently revised versions of all local, state
and federal codes, ordinances of the authority having jurisdiction, laws, rules
and regulations. Any modifications required by any of the above shall be
made without any additional cost to the owner. Where requirements between
D. All materials shall be new and shall bear the label of U.L.
B. Where existing slabs are to be cut or core drilled, the contractor shall x-ray
the existing slabs to avoid cutting or disrupting existing conduits, cables,
plumbing or structural members.
C. The electrical service to the building shall not be interrupted without written
consent of the building owner.
E. At the completion of the project, all work under this Division shall be
completely integrated with the existing systems and left in perfect operating
condition.
F. Where work under this Division disrupts the continuity of any existing to
remain circuit or feeder, the Contractor shall repair/replace as necessary to
return to a perfectly functional and safe operating condition.
G. Prior to any demolition or construction the Contractor shall have the existing
conditions inspected by an EPA, OSHA certified asbestos abatement agency
1.04 DEFINITIONS
C. Install: to join, unite, fasten, link, attach, set-up or connect together, complete,
tested, and ready for normal satisfactory operation.
H. Conduit: rigid steel; intermediate metal conduit (IMC), plastic conduit (PVC),
electrical metallic tubing (EMT), or flexible steel conduit.
2.0 PRODUCTS
2.01 MANUFACTURERS
B. When specific names are not stated, only the best available quality of
material or equipment shall be submitted for review and used in the
installation.
A. The Contractor shall obtain complete shop drawings, product data and
samples from the manufacturers, suppliers, vendors, and all Division 16
Subcontractors, for all materials and equipment as specified herein in various
Sections of the Specifications, and shall submit data and details of such
materials and equipment for review by the Architect and Engineer. Prior to
submission of the shop drawings, product data and samples to the Architect
and Engineer, the Contractor shall thoroughly review the shop drawings,
product data and samples and certify they are in compliance with the
Contract Drawings. Further, the Contractor shall check all materials and
equipment upon their arrival on the Project site and verify their condition and
compliance with the Contract Documents. Any Work which proceeds prior to
receiving reviewed shop drawings shall be modified as required to comply
with the Contract Documents and the shop drawings. A minimum period of
ten (10) working days, exclusive of transmittal time, will be required in the
Engineer’s office each time a shop drawing, product data and/or sample is
submitted or resubmitted for review. This time period shall be considered by
the Contractor when scheduling his Work. The initial shop drawing review for
equipment and materials may be expedited through the mutual consent of the
Contractor, Architect, Engineer, and Owner providing the Contractor agrees
to submit complete, certified, documented, and coordinated shop drawings
for review in accordance with the requirements of the Contract Documents.
B. The review of shop drawings, product data, and samples by the Architect and
Engineer shall not relieve the Contractor of the responsibility for dimensions
or errors that may be contained therein, or for deviations from requirements in
the Contract Documents. Is shall be clearly understood that the noting of
some errors by the Engineer but overlooking others does not grant the
Contractor permission to proceed in error.
E. All shop drawings and submittals shall include a stamped indication signifying
that the submittal has been reviewed for compliance with the Contract
Documents by the Contractor. This stamped indication also represents the
fact that the Contractor has checked this submittal for its interaction with all
other Divisions and certifies by his signature or initials that all coordination
has taken place. The stamp shall include the date, name of the Contracting
Firm, the signature of the Contractor, certification of compliance and
approval. This stamp shall be on the submittal before the Engineer will
review it.
F. The engineer will review an individual submittal not more than twice. If the
submittal is rejected again on the second review, the contractor will bare all
responsibility for paying for the Engineer’s time for additional reviews. Such
payments to the engineer shall be withheld from the next monthly pay
application.
G. Shop drawings and/or product data shall be submitted for the following for
review:
1. Switchboards, panelboards, transformers, busway, motor control centers,
ground fault system and other equipment associated with the main
distribution.
2. Disconnect switches, fuses, motor starters.
3. Life Safety System.
4. Lighting fixtures, lighting control system, dimming system, emergency
batteries and other equipment associated with lighting.
5. Transient voltage surge protection.
6. Generator, UPS, transfer switches, batteries, static switches, transition
switches, switchgear and other equipment associated with emergency
and/or standby back-up power systems.
7. Devices, receptacles, switches, coverplates, motion sensors. The
product data shall include the manufacturers name, model number, size
and color.
8. Conduit, wire, boxes, fittings.
A. The Contractor shall maintain on a daily basis at the Project site a complete
set of “Record Drawings”. The “Record Drawings” shall consist of a set of
blueline prints or AutoCAD files of the Contractor Coordination Drawings for
this Division. The prints shall be marked or the AutoCAD file electronically
updated to show the precise location of all buried or concealed work and
equipment, including embedded conduit and junction boxes, and all changes
and deviations in the Electrical work from that shown on the Contract
Documents. This requirement shall not be construed as authorization for the
Contractor to make changes in the layout or work without definite instructions
C. The Contractor and Subcontractor shall mark all “Record Drawings” on the
drawings with a rubber stamp impression or an AutoCAD image that states
such.
3.0 EXECUTION
3.01 INSTALLATION
A. Furnish and install the necessary sleeves, inserts, hangers, anchor bolts, and
related structural items. Install at the proper time.
G. Flashing:
1. Wherever conduits pass through the roof or outer walls, base flashing and
counterflashing shall be provided.
H. Anchor bolts and inserts shall be galvanized and of adequate size and
strength for installation of electrical work and shall be placed in forms before
concrete is poured.
1. Placement of bolts in bases shall be done under other Division. Furnish
detail drawings, templates, and anchor bolts for bases to the General
Contractor in time to avoid delaying work schedules.
2. Expansion shields shall only be used with specific approval of the
Architect. Wooden or soft metal plugs shall not be used.
B. Surface mounted outlet boxes shall be cast metal with threaded bolts. Pull or
junction boxes shall be cast metal with bolted and gasketed covers.
D. Lighting fixtures shall be installed with suitable gasket, and UL labeled for
location.
3.04 CLEANING
A. Brush and clean work prior to concealing, painting and acceptance. Perform
in stages if directed.
C. Remove dust and debris from inside and outside of material and equipment.
B. Junction and Pull boxes shall have covers stenciled with box number when
shown on the drawings, or circuit numbers according to panel schedules.
Data shall be lettered in a conspicuous manner with a color contrasting to
finish.
B. All motors shall be checked and adjusted for correct direction of rotation.
D. Any work found not to be in compliance with the Contract documents shall be
repaired or replaced without incurring additional cost to the Contract price.
3.07 WARRANTIES
A. The warranty period for all systems, equipment, components, work, etc. shall
be no less than one (1) year, unless specified otherwise hereinafter and shall
include at least one (1) full heating season and one (1) full cooling season.
B. The Contractor shall, without cost to the Owner, remedy any defects within a
reasonable time to be specified in notice from the Architect. In default
thereof, the Owner may have such work done and charge all costs to the
Contractor.
D. The Subcontractor shall confer with the General Contractor prior to the bid
date concerning the project schedule and determine if there is a need to
operate any items of equipment or systems for temporary heating an/or
cooling or other reasons prior to “Substantial Completion”. All required
extended warranty costs for equipment, materials, and systems shall be
included in the Subcontractor’s bid.
END OF SECTION
16110
RACEWAYS AND WIRING – 600 VOLT
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the basic materials and installation methods for
raceways and wiring of which are acceptable. Comply with other Division 16
Sections and Drawings as applicable. Refer to other Divisions for
coordination of Work.
C. Furnish and install all raceways and wiring specified herein and as required to
provide a complete system throughout the project as indicated on the
Drawings.
2.0 PRODUCTS
2.01 CONDUIT
D. Rigid Plastic Conduit (PVC): PVC conduit shall be polyvinyl chloride rigid
scheduled to heavy wall type. PVC conduit shall be joined with PVC
couplings of the solvent cement type to provide complete watertight joints.
Conduit systems shall be UL listed for direct burial and exposed use.
E. Flexible Metal Conduit: Shall be flexible steel conduit tubing spirally wound
having a hot-dip galvanized coating and meeting requirements of UL for
flexible metal conduit.
G. PVC coated galvanized rigid conduit: Shall be UL listed. The PVC coating
must have been approved by UL as providing the primary corrosion
protection for the rigid conduit. The PVC coated conduit must be ETL Verified
to the Intertek ETL SEMKO High Temperature H2O PVC Coating Adhesion
Test Procedure for 200 hours. The PVC coated conduit must bare the ETL
Verified PVC-001 label to signify compliance to the adhesion performance
standard. Ferrous fittings for general service locations must be UL Listed with
PVC as the primary corrosion protection. Hazardous location fittings, prior to
the plastic coating must be UL Listed. All conduit and fittings must be new,
and unused material. Applicable UL standards may include: UL6 Standard for
Safety. Rigid Metal Conduit, UL514B Standard for Safety, Fittings for Conduit
and Outlet Boxes. Conduit and Fittings shall be evaluated for reliability and
performance. Certified test results and the respective test data that have
been witnessed and certified to be accurate by an independent, recognized
third party.
A. GRC and IMC: shall be factory-made taper threaded and of the same
material as the conduit. Provide with molded nylon insulating bushing or
throat at all boxes and cabinets with locknuts inside and outside. Provide
watertight hubs in wet locations for terminations into enclosures. Provide
insulated grounding bushing where required.
B. EMT: shall be of the same material as the conduit and shall be hexnut
compression or steel setscrew. Provide with molded nylon insulating bushing
or throat at all boxes and cabinets. Provided insulated grounding bushing
where required.
F. PVC Coated Galvanized rigid conduit: Acceptable conduit and fitting PVC
bonds shall be confirmed with a minimum average of 30 days in a heat and
humidity test (ASTM D1151 and D2247) with the temperature at 150 degrees
F AND 95% relative humidity. Acceptable seal performance shall be
confirmed at 15 psig (positive) and 25 in. of mercury (vacuum) for 72 hours.
G. Wire Support Bushings: Provide for vertical runs as required by the NEC.
A. Pre-wired manufactured cable may be used for branch circuit wiring for
receptacle and lighting circuits where acceptable by the AHJ.
H. Cable termination fittings shall be T&B # 3131-TB, Steel City Series XC-730,
Bridgeport AMC-50 or approved equal clamp-type, malleable iron fittings.
Die-cast fittings are not acceptable.
A. Junction boxes and Pull boxes shall be galvanized steel with mode size and
gauge as required by the NEC in accordance with voltage parameters.
Covers shall be of the same gauge as the box as shall be screw fastened.
Boxes shall be sized as required but no smaller than 4 inches square and 1-
1/2 inches deep.
C. Provide galvanized cast iron or aluminum with threaded hubs and gaskets for
outdoor and damp locations.
A. Outlet boxes shall be UL listed, and of sizes and types required for the
application.
C. Boxes Used Outdoors or in Damp/Wet Locations: Cast metal boxes (iron and
alloy) with gasketed covers and threaded hubs.
A. Surface metal raceway shall be UL listed and labeled; shall be used together
with couplings, clips, bushings, straps, connectors, connection covers,
elbows, extension boxes, fixture boxes, extension adapters, blank covers and
all other required fittings; shall be of the proper size to accommodate the
conductors to be installed therein in each case.
C. All conductor sizes shown on the Drawings are copper unless specifically
noted otherwise. All ground conductors shall be copper.
2.09 MANUFACTURERS
3.0 EXECUTION
3.01 CONDUIT
B. GRC or Intermediate Metal Conduit (IMC) shall be used where exposed and
subject to physical damage, or installed in damp or wet locations.
E. Electrical Metalic Tubing (EMT) shall be used for branch circuits concealed in
walls and ceilings. EMT may be used for feeders where not exposed to
damage and/or not installed in wet or damp locations.
J. Conduits shall be secure to all boxes, cabinets, panels and equipment with
locknuts and bushings and shall be securely fastened in place on intervals
required by the Code and local codes; hangers, supports or fastenings shall
be provided at each elbow and at the end of each straight run within 3’ of a
termination to a box or cabinet. All supports shall be independent and shall
not use ceiling supporting system wires.
K. Use threaded rods and hangers for supporting single conduit. Multiple
conduits shall be supported using a trapeze of Unistrut (or Kindorf) channels
and threaded rods with double nut/washer.
M. The minimum size conduit shall be ½” diameter. Homeruns shall extend from
the first outlet or device to the panel designated and shall be a minimum ¾”
diameter.
N. Provide non-hardening elastic type duct seal compound for each conduit
entering the building from the outside and from one space to another having
a normal operating temperature differential greater or less than 10 degrees F.
O. Provide seals around all conduit and sleeves penetrating through walls,
partition or ceilings. Provide UL approved fire resistant seal around all
penetrations through fire rated barriers to maintain the barrier rating.
A. Install underground conduit with a top cover at least 30“ below finished grade
and no more than 48”.
B. Mark all duct bank runs with a detectible warning tape specifically formulated
for prolonged use underground, resistant to alkalis and acids found in soil,
installed no less than 8 inches and no more than 12 inches above the top of
the duct bank concrete. Place warning tape along the approximate center line
of the duct bank run. Warning tape shall be permanent, red in color,
continuous printed, aluminum backed tape, compounded for direct burial not
less than 3 inches wide and 4 mils thick. Printed legend shall be indicative of
general type of underground line below.
C. Mark all underground conduit runs with a detectible warning tape specifically
formulated for prolonged use underground, resistant to alkalis and acids
found in soil, installed no less than 6 inches and no more than 10 inches
above the top of the conduit. Place warning tape along the approximate
center line of the conduit run. Warning tape shall be permanent, red in color,
continuous printed, aluminum backed tape, compounded for direct burial not
less than 3 inches wide and 4 mils thick. Printed legend shall be indicative of
general type of underground line below.
A. No conductor shall be smaller than No. 12 except for signal or control circuits.
E. For homeruns of 120 Volt, 20 amp circuits, where the length of run from the
panelboard to the center of the load exceeds 100’-0” the conductors shall be
No. 10 minimum. If that length exceeds 200’-0” the conductors shall be No. 8
minimum.
F. For homeruns of 277 Volt, 20 amp circuits where the length of run from the
panelboard to the center of the load exceeds 200’-0” the conductors shall be
No. 10 minimum.
I. Conductors shall have color coded jackets the entire length for sizes No. 6
and smaller. The conductors No. 4 and larger shall have color coded
conductor jackets the entire length. Colors shall be as follows:
J. Where phase marking tape is used it shall be wrapped 2” wide and located at
two (2) locations 6” and 18” from the termination. Phase marking tape for the
neutral and grounding conductors shall be provided where visible at any point
where the conductor is accessible.
K. Before pulling any wire into conduit, thoroughly swab the conduit and clean
the boxes of debris.
M. Run conductors for emergency power in conduits separate from all other
wiring.
A. All junction boxes and pullboxes shall be size in accordance with the Code.
C. Outlet boxes shall be flush with the finished wall or ceiling, or not more than
¼” back, unless specifically shown as surface mounted or its purpose is to be
above the ceiling.
D. Provide galvanized steel or cast type outlet boxes. Where exposed GRC or
IMC terminates in a box, provide cast box with threaded hubs.
G. Where outlets are shown at the same location but at different heights, they
shall be mounted one above the other along the same centerline.
H. The exact mounting height of an outlet may be adjusted slightly to align with
masonry joint where approved by the Architect.
I. Verify outlet locations in finished spaces with Drawings of interior details and
finishes.
J. Outlets shall NOT be located back to back. Where outlets are shown on
opposite sides of a wall, they shall be located in separate stud spaces.
K. Protect floor boxes from entering debris during construction using temporary
covers approved by the floor box manufacturer.
L. Provide barriers in outlet boxes for switches separating different phases for
voltages exceeding 150 volts to ground.
END OF SECTION
16140
DEVICES
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the basic materials and installation methods for
devices of which are acceptable. Comply with other Division 16 Sections and
Drawings as applicable. Refer to other Divisions for coordination of Work.
C. Furnish and install all devices specified herein, as indicated on the Drawings
and as required to provide complete and operating systems.
E. All devices (Outlets, Switches, Cover Plates, etc) shall be provided by the
same manufacturer to ensure all devices match in appearance and color.
2.0 PRODUCTS
2.01 GENERAL
A. The color of all devices, wall plates and coverplates shall be as selected by
the Architect.
2.02 SWITCHES
D. Motor rated switches and switches indicated as pilot switches, unless noted
otherwise, shall be flush mounted industrial grade, red pilot light “on” with
overload protection as follows (note: wire per manufacturers
recommendation):
1. 120V, 20 amp Circuits – Hubbell HBL1221PL
2. 277V, 20 amp Circuits – Hubbell HBL1221PL7
3. 120V, 30 amp Circuits – Hubbell HBL3031PL
G. Timer switches, unless noted otherwise, shall be digital time switch 24VAC or
120/277VAC as required. ,Timeout adjustments from 5 minutes to 12 hours.
Set timer in the field to 4 hours for equipment rooms and 30 minutes for all
other areas. For timer setting greater than 2 hours select the visual flash
option and audible sound option. Color shall match that selected for the
switches unless noted otherwise.
2.03 RECEPTACLES
C. Ground Fault Interrupter Receptacles (GFCI) shall be plastic, 2P, 3W, 125
volt, 20 amp, self protecting type Leviton 8898 series or equal by Hubbell,
P&S or Cooper. Hospital GFCI receptacles shall be Leviton 8898-HG or
equal by Hubbell, P&S or Cooper.
E. Arc Fault Interrupter Receptacles (AFCI) shall be plastic, 2P, 3W, 125 volt, 20
amp, self protecting type Leviton AFTR2 or equal by Hubbell, P&S or Cooper.
2.04 COVERPLATES
A. Coverplates shall be satin finish 302 stainless steel standard size (provide
jumbo size for concrete and masonry walls) by Leviton or equal by Hubbell,
P&S or Cooper.
B. Provide multigang plates for devices shown at the same location. Coordinate
gang configuration with the Architect where more than 3 devices are shown
at one location.
3.0 EXECUTION
3.01 INSTALLATION
B. Provide plaster ring reducer for boxes larger than the device plate.
H. Mount receptacles and special systems outlets vertical and 18” above the
finished floor to the device centerline, unless noted or required otherwise.
I. Mount switches vertical and 48” above the finished floor to the device
centerline and 6” from a door strike, unless noted or required otherwise.
L. Install a green insulated bonding jumper for all grounded devices and bond to
the outlet box.
M. Each outlet used as a junction box, or for future device or fixture, shall be
fitted with a blank coverplate to match other device coverplates.
N. Floor outlets shall be of the necessary type suitable for the application and
installed per the manufacturers recommendation. Fire ratings shall be
maintained. Where the installation of a specified or required floor box effects
the elevated slab/floor fire rating, the necessary fire assembly (approved by
the Architect) shall be constructed below the slab.
O. Do not locate junction boxes or voice/data conduit stub downs for poke-thru
devices above a non-accessible ceiling. In these cases extend the poke-thru
conduit to an accessible ceiling.
END OF SECTION
16175
ELECTRICAL IDENTIFICATION
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the materials and methods required for identification
of electrical equipment and related accessories.
C. Furnish and install all equipment, materials, tools and labor to properly
identify electrical equipment and related accessories as specified in this
Section, other relation Division 16 Sections and the Drawings.
2.0 PRODUCTS
2.01 IDENTIFICATION
A. Nameplates
1. Nameplates shall have the surface color and core color for engraved
letters as follows:
a. Normal distribution
1) 120/208V. equipment – black surface with white core
b. Emergency distribution
1) 120/208V. equipment – red surface with white core
2. Provide a nameplate for each switchgear, switchboard, panelboard,
distribution panel, motor starter, disconnect switches, motor control center
and similar distribution equipment clearly identifying the equipments’
name to match that indicated in the Drawings.
3. Provide a nameplate for each feeder protective device in each
switchgear, switchboard, distribution panel, motor control center and any
other similar equipment. Identify the specific load it serves.
4. Nameplates shall be bakelite, 1/16” thick minimum with 3/8” high letters.
G. Wire markers
1. Wire markers for identification of wiring shall be self-adhesive type having
letters and numerals indicating feeder or branch circuit number. Locate
markings on wiring where visible near the terminations and taps in all
junction boxes, outlet boxes, panelboards, distribution panel boards,
switchboards and motor control centers.
H. Electrical services
1. Where multiple electrical services are provided to a building, provide
nameplates as described above identifying the appropriate service
number. Letters shall be 1” high.
2. Where the multiple electrical services are in different locations, provide a
nameplate at each service noting the locations of the other service(s) as
required by the NEC and the AHJ.
END OF SECTION
16200
SERVICE AND DISTRIBUTION – 600 VOLT
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the basic materials and methods for service and
distribution equipment rated 600 volts or less of which are acceptable.
Comply with other Division 16 Sections and Drawings as applicable. Refer to
other Divisions for coordination of Work.
E. Provide nameplates for all distribution equipment as specified herein and per
Section 16175.
1.02 SUBMITTALS
A. Furnish and install the building electrical service from the Power Company
transformer(s) to the main service distribution equipment as shown on the
Drawings. Any charges required by the Power Company for permanent
power shall be included in this Contract.
B. Coordinate all installation requirements with the Power Company prior to bid
and include all trenching, conduits, vaults, equipment pads, current
transformers, potential transformers, potential taps as required. Coordinate
all Work with the Power Company.
D. The secondary service to the building shall be 120/208 volts, 3 phase, 4 wire,
60 Hertz AC
2.0 PRODUCTS
2.02 PANELBOARDS
A. System Description
1. Short circuit rating of panelboards shall be the interrupting rating of lowest
rated device in the panel or application UL series for proper main and
branch device combinations.
2. Panelboards shall have a maximum of 42 protective devices per panel,
including sub-feeders and excluding main overcurrent protective devices.
For more than 42 devices, 2 or more panelboards are required.
3. With 2 or more panelboards, sub-feed lug or thru-feed lugs shall be used
in all by 1 section of each panelboard. Lugs shall have same capacity as
incoming mains.
4. Protective devices shall be molded case circuit breakers.
B. Enclosure
1. Boxes shall be a nominal 20 inches wide and 6 inches deep with wire
bending space per the National Electric Code.
2. Fronts shall be door-in-door construction with reinforced steel with
concealed hinges and concealed trim adjusting screws. Trim clamps are
unacceptable.
3. All door locks shall be corrosion proof Valox (or equal) with retractable
latches. All door locks shall be keyed for a single key.
4. Clean Lexan (or equal) directory card holders shall be permanently
mounted on front door.
5. All panelboard series ratings shall be prominently displayed on dead front
shield.
6. Interiors shall permit top or bottom incoming cables.
C. Bus bars
1. Bus bars shall be copper, phase sequenced, fully insulated and
supported by high impact Noryl (or equal) interior base assemblies.
2. Bus bars shall be mechanically supported by zinc finished galvanneal
steel frames to prevent vibration and damage from short circuits.
3. Terminations shall be UL tested and listed and suitable for UL copper.
4. Provide 1 continuous bus bar per phase. Each bus bar shall have
sequentially phased branch circuit connectors for bolt-on branch circuit
breakers. Bus bars shall be rated as indicated in Drawings.
D. Circuit Breakers
1. Molded case circuit breakers shall be bolt-in devices for 120/208V panels
and 277/480V panels.
2. All circuit breakers shall have thermal and magnetic trip elements in each
pole.
3. Multiple pole breakers shall have internal common trip crossbars for
simultaneous tripping of each pole.
4. Circuit breakers rated below the panel ratings shall not be restricted to
any mounting location within a panel due to physical size.
5. All branch breakers 15 to 100 amperes shall be able to be mounted in
any panel position for twin or double mounting without space penalty.
Sum of ratings for 2 such twin mounted devices shall not exceed 180
amperes.
6. Main and sub-feed circuit breakers may be vertically or horizontally
mounted.
7. Branch breaker panelboard connections shall be copper to copper.
8. All panelboard terminations shall be rated as indicated in Drawings.
9. All breakers shall have an over center mechanism and be quick make
and quick break.
10. All breakers shall have handle trip indication and a trip indicator in window
of circuit breaker housing.
11. Breaker handle and faceplate shall indicate rated ampacity.
12. Circuit breaker escutcheon shall have standard ON/OFF markings.
13. Main breakers shall be UL listed for use with: Shunt, Under Voltage, and
Ground Fault Shunt Trips; Auxiliary and Alarm Switches; and Mechanical
Lug Kits.
14. Branch breakers shall be UL listed for use with: Shunt Trips, Auxiliary and
Alarm Switches.
E. Finish
1. Boxes shall be corrosion resistant, zinc finish galvanneal.
2. Fronts shall be powder finish painted ANSI 61 gray.
3. Panels shall be manufactured by General Electric, Square D, Cutler-
Hammer or Siemens.
B. Enclosures
1. Panel box shall be galvanized code gauge sheet steel with removable
end walls.
2. Enclosures shall be surface mounted.
C. Fronts
1. Provide a four-piece front to cover wiring gutter and wiring access areas.
Provide a lockable hinged door with semi-concealed hinges to cover
access to circuit breakers.
2. Hinged door fronts, when specified, shall be provided with a lockable
inner door with leaf hinges. An inner door shall cover the circuit
protective devices and shall be able to be locked.
3. Door hinges shall be continuous piano hinges, welded to door(s) and
bolted on front.
4. Door locks shall be Yale #511.
D. Interiors
1. Panelboard interior shall by symmetrically designed and assembled such
that circuit protective modules are connected onto bus bar with positive
gripping jaw assemblies and locked pressure connections.
2. Circuit-protective modules shall be designed for removal or replacement
without disturbing adjacent protective devices and without removing main
bus and branch circuit connections.
3. Interiors shall allow installation of molded-case circuit breakers in same
panelboard.
4. Lugs shall be UL listed to accept solid or stranded copper cables. Lugs
shall be bolted in place.
5. Panelboards shall be rated as indicated in Drawings. Main devices shall
have maximum rating of 1200 amperes.
6. Panelboards shall have flat, stacked, vertically aligned bus bars.
7. Bus bars shall be copper. The bus bars shall have sufficient cross
sectional area to meet UL 67 temperature rise requirements through
actual tests. The bus bars shall be standard density rated for 1000
amperes per square inch.
8. Bus bars shall be phase-sequenced and rigidly supported by high impact
resistant, insulated bus supporting assemblies to prevent vibration or
short circuit mechanical damage.
9. Neutral bus shall be fully rated and able to be located in either corner of
enclosure at line end to facilitate conductor termination. Furnish 200%
rated neutral bus, if required by plans or another specification section.
10. All solderless terminations shall be suitable for copper UL listed wire or
cable and shall be tested and listed in conjunction with appropriate UL
F. Series Ratings
1. Panelboard series-connected ratings shall be attached to the panelboard
enclosure.
2.04 TRANSFORMERS
A. System Description
1. Power transformers shall be 2 winding dry type for general power and
lighting applications. Transformers rated 1000 KVA or below shall be UL
listed, DOE 2016 efficiency standard, and bear required UL Listing Mark.
H. Transformer Construction
1. Transformer cores shall be constructed of high grade, non-aging silicon
steel with high magnetic permeability and low hysteresis and eddy current
losses. Magnetic flux densities shall be kept well below core saturation
point. Core laminations above 112.5 KVA shall be miter cut at core
corners to reduce hot spots, core loss, current and sound level. Core
laminations shall be clamped together with steel angles. Cores for
transformers above 300 KVA shall be clamped using insulated bolts
through core laminations to provide proper pressure throughout core
length. Completed core and coil shall be bolted to enclosure base and
isolated from base by rubber vibration-absorbing mounts. There shall be
no metal-to-metal contact between core and coil and enclosure. Sound
isolation systems requiring complete removal of all fastening devices is
not acceptable.
2. Transformer core shall be visibly grounded to enclosure by flexible
grounding conductor meeting UL and NEC size requirements.
3. Enclosure shall be constructed of heavy gauge steel.
4. Coils shall be copper.
I. Load Taps
1. Transformers shall have following high voltage load tap arrangements
unless noted otherwise in plans:
a. Through 2 KVA – no taps;
b. Through 23 KVA – no taps;
c. 3 though 23 KVA 2 above, 2 below nominal 4, 2-1/2 percent taps
voltage;
J. Finish
1. Finish shall consist of degreasing, phosphate cleaning, and
electrodeposits ANSI gray enamel paint.
2.05 BUSWAY
A. System Description
1. Busway shall be a totally enclosed, indoor low-impedance system.
2. Material and installation shall comply with all applicable codes,
recommended practices, and standards of ANSI, IEEE, NEMA, UL, CSA,
and ASTA. All busway components shall be UL listed. Arrangements,
details, and location shall be as indicated in Drawings. Busway shall be
tested and conform to Seismic Zone 4 requirements.
3. Short circuit rating of fittings with protective devices shall be equal to the
lower short circuit rating of the protective device or the busway. Short
circuit rating of busway plugs equals the rating of the fuses of circuit
breaker used in the plug.
C. All bus insulation material shall be epoxy NEMA Class B (130 degree C).
Insulation shall be UL rated as self-extinguishing and shall be impervious to
acids, alkalis, acetones, machine oils and lubricants commonly found in
industrial environments. Manufacturer shall provide test data documenting
insulation’s impact resistance, chemical resistance, and expected life (50
years).
E. Bus bars shall be 98% conductivity copper or aluminum. The aluminum bus
bars shall be silver or tin plated. Temperature rise at any point in busway
shall not exceed 55 degrees C above ambient when operating at rated load
current.
G. Hanger System
1. Horizontal busway runs shall be UL listed to hang on 10 foot centers in
any position. Vertical busway riser runs shall be supported with spring
hangers.
I. Joints shall have plus or minus 5/8 inch adjustability and be the one-bolt
removable type. Joints shall be able to be made from one side when busway
is installed against a wall or ceiling. Plug-in and feeder shall use identical
parts. All multi-stack shall be phase collected.
M. Accessories
1. Thermal expansion fittings for:
a. Runs longer than 150 feet when busway is not free to move at ends of
run;
b. When busway run crosses building expansion joint.
2. Reducer cubicles and special adapter cubicles, as required in Drawings.
3. Furnish Joint-Guard Protective System that uses a “torque sensing bolt”.
The system shall measure the “elongation of the busway joint bolt”.
When the bolt looses proper torque, a “red indication shall appear in the
bolt head”. After re-torquing the bolt, the red indication shall recede and
N. Finish
1. ANSI-61 gray enamel.
O. Installation
1. Provide floor or wall flanges at all fire separations s as required.
Coordinate installation of floor flanges and firestop systems with
waterproof curbs.
2. All busway joints shall be torqued as recommended by the manufacturer.
A recheck of torque setting shall be made by the Electrical Subcontractor
after the busway has been in service and subjected to varying load
conditions. The Electrical Subcontractor shall submit a report of this
recheck to the Owner upon completion.
3. All connections to bus switches shall be made with flexible meal conduit.
No “hard-pipe” connections to bus switches are allowed. All bus switch
connections shall be in place prior to final adjustment and isolation of all
vertical bus risers.
equal.
E. Provide NEMA type enclosure suitable for the application (indoor, outdoor,
wet or damp, corrosive, etc.). Type 3R enclosure shall contain no knockouts
(supply watertight hubs).
H. Fused disconnect switches shall have rejection type fuse clips with dual
element current limiting fuses of rating shown or required by the
Manufacturer’s nameplate of the equipment being supplied. The UL short
circuit rating shall be 200,000 amps RMS SYM when used with Class R or J
fuses.
2.07 FUSES
B. Fuses for circuits 1 to 600 amperes shall be dual element, current limiting
time delay (500% of rated current for minimum of 10 seconds) with separate
overload and short circuit clearing chamber. Bussman “Low Peak” or equal
by Littlefuse or Ferraz Shawmut. UL Class J.
C. Fuses for circuits above 600 amperes shall be current limiting, time delay
(500% of rated current for minimum of 4 seconds, clear 20 times rated
current in 0/1 seconds or less). Bussman, “Hi-Cap” or equal by Littlefuse or
Ferraz Shawmut. UL Class L.
D. Provide one (1) set of spare fuses for each set of three (3). A maximum of
three (3) sets of fuses is required to be provided for the same type and rating.
3.0 EXECUTION
2.01 GENERAL
A. Infra-red Testing
1. After the electrical distribution system has been checked, adjusted,
calibrated and under load just prior to substantial complete, it shall be
subjected to an infra-red thermograph test by a NETA certified technician.
The test shall be performed with a minimum load of 20% of the rating of
the equipment/connection being tested. Load banks shall be supplied if
necessary to provide this load factor.
2. Two (2) copies of the test report shall be furnished to the Engineer upon
completion of the test. Connections indicated having higher temperatures
than acceptable shall be tightened or corrected as required. After
corrections have been made, the connections shall be subjected to an
addition thermograph test and rechecked to confirm the problem has
been corrected.
3. The following components and connections shall be included in the
thermograph testing:
a. Service entrance
b. Switchboards
c. Switchboard main and feeder devices
d. Feeder taps
e. Busway cable terminations
f. Busway joints
g. Bustaps and busplug connections
h. Emergency distribution system
i. UPS system
j. Motor control centers
k. Distribution panels
l. Panelboards
m. Mechanical equipment connections (over 100 amps)
n. Transformers
END OF SECTION
16430
MOTOR CONTROLS AND WIRING
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the materials and methods required for the operation of
motors and motorized equipment.
C. Furnish and install all equipment, materials, tools and labor to provide a
complete system for motor operation. Refer to other related Sections of
Division 15 and 16 and the Mechanical, Electrical and Plumbing Drawings.
D. A Motor starter shall be proved by Division 16 for each motor except for those
specified in Division 15 to be furnished by that Division. All motor starters not
integral to the equipment served shall be installed and connected by Division
16.
F. Provide 120 volt line voltage for controls as required. Provide 120 volt to all
line voltage motor operated dampers. Provide fire alarm connections to all fire
and smoke dampers. Coordinate with Division 15.
2.0 PRODUCTS
B. The motor starters shall be front wired with all terminals accessible for wiring
directly from the front. All contacts shall be solid silver cadmium oxide alloy.
Bare copper or silver-flashed type shall not be permitted. Operating coils shall
be pressure molded and so designed that if accidentally connected to
excessive voltage they will not expand, bubble, or melt. When a coil fails under
over-voltage conditions, the motor controller shall definitely drop out and not
freeze the contacts in the “ON” position.
C. All three-phase full voltage magnetic motor starters shall have overload
protection in all three phases. All single phase full voltage magnetic motor
controllers shall have overload protection in ungrounded phases. All two-
E. Provide necessary terminal strips and relays as required for interface with the
motor operation, the Building Automation System, Fire Alarm System, and
Fireman’s Override Panel (if applicable). Coordinate with Division 15.
G. Generally, holding coils in full voltage magnetic motor starters shall be suitable
for use on 120 volt, AC control voltage. Each controller shall have a control
power transformer with primary and secondary fuses. Control power
transformer shall have at least 50 VA capacity over and above the standard
capacity required for holding coil and LED pilot light duty. Sizing of control
transformers shall be coordinated with Division 15.
H. Two-speed motor starters for two-speed motors shall have “decelerating relay”
between high and low speed.
A. A combination starter shall be provided in the motor control center for each
motor and shall be plug-in circuit breaker with voidable cover interlock. Provide
provision for padlocking the cover and operating handle. Provide interrupting
capacity as required, minimum 65KA RMS SYM.
E. Provide a control terminal strip in the Motor Control Center. The control wiring
from these terminal strips, external to the Motor Control Center, to the
respective control device, shall be included in Division 15.
3.0 EXECUTION
3.01 INSTALLATION
B. Provide all power wiring to motors unless prewired as part of a packaged unit.
C. Provide line voltage power wiring through a control device (i.e. fire stats,
thermostat, aqua stat) where required. Coordinate with Division 15.
END OF SECTION
16450
GROUNDING SYSTEM
1.0 GENERAL
1.01 SUMMARY
C. Furnish and install all equipment, materials, tools, and labor to provide a
complete grounding system.
D. Ground all metallic parts of the electrical system which are not intended to
carry current such as conduit, busduct, switchgear, panelboards, cabinets and
enclosures, motor frames, device boxes, etc., in accordance with the NEC and
applicable codes.
2.0 PRODUCTS
2.01 GENERAL
A. All equipment and materials provided under this Section of the Specifications
shall be new, UL listed, and bear the UL label.
C. All conduit, cable tray, manufactured wiring systems, raceways, junction boxes,
pull boxes, etc. shall be made electrically continuous by means of grounding
conductors, bonding jumpers, grounding bushings, etc. as required by the NEC
and the authorities having jurisdiction.
A. All ground rods shall be a minimum of ¾” x 10’-0” copper clad steel unless
otherwise indicated on the Drawings.
3.0 EXECUTION
3.01 INSTALLATION
C. Bonding and grounding conductors shall be sized, shall be run in conduit, and
shall be connected to various services in accordance with the requirements of
the authorities having jurisdiction and the NEC.
3.02 TESTS
C. Perform tests in dry weather and not less than 48 hours after rainfall.
D. Test instruments: Null balance type, Biddle Meggar Earth Tester or approved
equal.
END OF SECTION
16500
LIGHTING
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the materials and methods required for lighting fixtures.
Comply with other Division 16 Sections and Drawings as applicable. Refer to
other Divisions for coordination of Work.
C. Furnish and install lighting fixtures complete with all lamps as specified on the
Electrical, Architectural, Interior and Lighting Designer Drawings. Furnish and
install all supports, brackets, connectors, materials, tools, wiring, controls and
labor to provide a complete and operating lighting system.
F. All lamps shall be operating at project completion and for a period of six (6)
months after the final acceptance by the Owner.
H. All recessed lighting fixtures shall match the ceiling type and be tested and
certified by the fixture manufacturer for the type of mounting.
A. Handle lighting fixtures carefully to prevent breakage, denting and scoring the
fixture finish. Do not install damaged lighting fixtures; replace and return
damaged units to equipment Manufacturer.
B. Store lighting fixtures in clean, dry space. Store in original cartons and protect
from dirt, physical damage, weather and construction traffic.
1.03 SUBMITTALS
2.0 PRODUCTS
C. Each lighting fixture shall comply with local codes and the authority having
jurisdiction.
F. Where fixtures are specified with acrylic lenses, provide virgin acrylic with
0.125 inch thickness.
G. Exit lighting fixtures shall meet the requirements of all federal, state and local
codes.
2.02 LAMPS
2.03 BALLASTS
A. General
1. All ballasts shall be UL listed and CBM certified. Ballasts shall be CSA
certified where applicable.
2. Ballast shall be approved for operating with specified lamp. Ballast shall
provide normal rated lamp life as stated by acceptable lamp
manufacturer.
B. The test button and indicator light shall be integral in the fixture reflector and
shall be positioned within or on the surface of the fixture so as to be accessible
and identifiable.
C. Under normal mode the battery ballast shall keep the batteries at full charge.
Upon loss of normal power the battery ballast shall operate the fluorescent
lamp or lamps for 90 minutes.
D. Battery recharge time shall not exceed 16 hours to fully recharge and shall not
exceed 225 milliamperes charging current.
E. The lumen output of the lamp or lamps powered by battery unit shall be not
less than 1100 lumens initially for a four foot fluorescent lamp.
F. The battery ballast shall meet or exceed all the requirements set forth in UL924
“Emergency Lighting and Power Equipment” and shall be UL listed for
installation on top of or remote from the fixture. Emergency illumination shall
meet or exceed the requirements set forth in the National Electric Code, Life
Safety Code and UL 90-Minute Requirements.
D. Thermal Management
1. The thermal management (of the heat generated by the LEDs) shall be of
sufficient capacity to assure proper operation of the luminaire over the
expected useful life.
2. The LED manufacturer’s maximum thermal pad temperature for the
expected life shall not be exceeded.
3. Thermal management shall be passive by design. The use of fans or
other mechanical devices shall not be allowed.
4. The luminaire shall have a minimum heat sink surface such that LED
manufacturer’s maximum junction temperature is not exceeded at
maximum rated ambient temperature.
3.0 EXECUTION
3.01 GENERAL
C. Fixtures of the same type and in the same ceiling shall have lamps, socket
assembling and door hinges oriented in the same direction.
D. Reflector cones, baffles, aperture plates, light controlling element for air
handling fixtures and decorative elements shall be installed after completion of
ceiling tiles, painting and general cleanup.
E. Target and focus adjustable lighting fixtures after regular working hours and
before building acceptance. Permanently indicate targeting on fixture and
provide positive locking devices to preclude mis-focus relamping. Target and
focus in the presence of the Architect and Lighting Designer.
G. Clean all fixture reflectors, lenses, louver, decorative accessories and lamps
immediately prior to Owner’s acceptance of building. Destaticize plastic lenses
and diffusers after cleaning.
A. Support directly from building structure, any lighting fixture which weighs in
excess of the capacity of the suspended ceiling on which it is installed.
Support each such fixture with the quantity of threaded rods or fixture support
wires required to prevent fixture warping; however provide no less than two
rods or wire per fixture.
B. Outlets, which are recessed in a suspended ceiling and support the weight of
surface-mounted or suspended fixtures, shall be supported from a channel
spanning and secured to the ceiling support system. Support each end of the
channel with a fixture support wire attached to structure.
END OF SECTION
16610
EMERGENCY STANDBY GENERATOR
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the basic materials and installation methods for
Emergency Stand-by Systems of which are acceptable. Comply with other
Division 16 Sections and Drawings as applicable. Refer to other Divisions for
coordination of Work.
C. Provide all labor and material necessary to install a standby diesel engine
generator set in accordance with the contract documents and manufacturer’s
drawings and installation instructions in a complete and operating condition.
D. The engine – generator set shall be suitable for outdoor use and complete
with weather-protective enclosure and components as identified in this
specification.
1.02 SUBMITTALS
d. Number of leads
e. Weight, total
f. Weight, rotor
g. Air flow
4. Technical Data at rated voltage:
a. Efficiency at 0.8 power factor for: 50%, 75%, 100% load
b. Time constants, short circuit transient (T'D)
c. Time constants, armature short circuit (TA)
d. Reactance, subtransient - direct axis (X"D),
e. Reactance, transient - saturated (X'D)
f. Reactance, synchronous - direct axis (XD)
g. Reactance, negative sequence (X2)
h. Reactance, zero sequence (X0)
i. Fault current, 3 phase symmetrical
j. Decrement curve
5. Radiator:
a. Model
b. Type
c. Fan drive ratio
d. Coolant capacity, radiator
e. Coolant capacity, radiator and engine
f. Weight: dry & wet
6. System: Dimensions: length, width, height
Weight: dry & wet
7. Performance - Based on SAE J1349 standard conditions of 100kPa
(29.61 in hg) and 25C (77F); also at conditions of ISO 3046/1, DIN 6271
and BS 5514. Fuel rates are based on ISO 3046 and on fuel oil of 35
degrees API (16C or 60F) gravity having a LHV of 42780 kJ/kg (18,390
Btu/lb) when used at 29C (85F) and weighing 838.9 g/l (7.001 lbs/U.S.
gal). Performance of the genset shall also meet the design site
conditions.
8. Auxiliary Equipment – Specification and data sheets, including
switchgear, transfer switch, vibration isolators, enclosure, muffler, battery
charger, batteries, cooling system and fuel tank.
9. Drawings - General dimensions drawings showing overall generator set
measurements, mounting location, and interconnect points for load leads,
fuel, exhaust, cooling and drain lines.
10. Wiring - Wiring diagrams, schematics and control panel outline drawings
published by the manufacturer in Joint Industrial Council (JIC) format for
controls and switchgear showing interconnected points and logic
diagrams for use by contractor and owner.
11. Warranty Statements - Warranty verification published by the
manufacturer.
A. The electric power generating system shall have a site capability of that
shown on the drawings. This power shall be applied for Standby operation.
B. The system shall consist of generator set(s) which include all controls,
protection, wiring, and accessories for automatic start-stop operation. After
starting, the unit(s) will attain rated speed and voltage, and accept rated load.
Generator set speed shall be controlled by the engine governor, while
generator output voltage regulation shall be a function of the generator
automatic voltage regulator. Manual adjustment of generator speed and
voltage shall be provided.
C. The set shall immediately shut down in the event of overspeed, low oil
pressure, high water temperature and overcrank. Cause of shutdown shall
be indicated by a light annunciator. System logic shall prevent restart until
fault is cleared. There shall also be a provision for manual shutdown.
C. Diesel engines shall be able to deliver rated power at design ambient when
operating on No. 2 diesel fuel having 35 degree API (16C, 60F) specific
gravity. Fuel rates shall be based on a low heating value of 42,780 kJ/kg
(18,390 Btu/lb) when used at 29C (85F) and weighing 838.9 g/l (7.001
lbs/U.S. gal).
D. Generators shall start, achieve rated voltage and frequency, and be capable
of accepting load within 10 seconds when properly equipped and maintained.
E. The generator set shall be capable of accepting a 100% block load as applied
in a single step and shall be able to recover to a steady state condition within
the timeframe identified in the following paragraph. Generator transient
response performance shall conform to ISO 8528. No other definition of
transient response shall be accepted.
F. The maximum voltage dip shall be no greater than that identified in the
following paragraph. The voltage dip shall be identified as that recorded by a
light beam oscilloscope and strip chart recorder. No other definition of voltage
dip shall be accepted.
G. The power generating system shall satisfy the following performance criteria
at site conditions:
2.0 MATERIALS
2.01 MANUFACTURER
B. All components shall have been designed to achieve optimum physical and
performance compatibility and prototype tested to prove integrated design
capability. The complete system shall have been factory fabricated,
assembled and production tested by the manufacturer.
D. Prototype and production testing must be performed for the specific rating
and consist being offered and certified test reports shall be provided.
2.02 ENGINE
B. The engine block shall be of one piece design and cast of high tensile
strength iron in the system manufacturer's own foundry. The crankshaft shall
be a one piece forging with regrind able wear surfaces hardened through
heat treat methods. The cylinder wear surfaces shall be induction hardened
over their entire length. Main and rod bearings shall consist of aluminum
bonded by copper to a steel backing.
A. The lubrication oil pump shall be a positive displacement type that is integral
with the engine and gear driven from the engine gear train. The system shall
incorporate full flow filtration with bypass valve to continue lubrication in the
event of filter clogging. The bypass valve must be integral with the engine
filter base or receptacle. The oil filter shall incorporate a self-lubricating, free
rotating seal and have a nonmetallic core sufficiently rigid to minimize
movement or shifting of the filtration media.
A. The engine fuel system shall consist of a fuel filter, engine mounted fuel
transfer pump, injection pumps, lines, and nozzles. The fuel transfer pump,
injection pumps, rack and pinion assembly, and timing mechanism shall be
maintenance and adjustment free for the life of the equipment. The fuel filter
shall not require changing more frequently than once per year or every 250
hours, whichever comes first.
B. The engine transfer pump shall deliver fuel under low pressure to individual
injection pumps - one for each cylinder. External, high pressure (greater than
5,000 psi) fuel systems will not be accepted.
C. Racor brand fuel/water separator shall protect the fuel system from water
damage. A manual fuel priming pump shall facilitate priming and bleeding air
from the system. Flexible fuel lines between engine and fuel supply shall be
installed to isolate vibration.
D. A primary fuel filter shall also be provided to protect the fuel transfer pump
from impurities and debris in the fuel system.
A. Sub-base Fuel Tank - UL142 listed, double wall, sub-base fuel tank shall be
provided with the generator set. The tank shall have a low level alarm, critical
low shutoff, high level alarm, leak detection and shall have flexible supply and
return line connections. The sub-base fuel tank shall be furnished with a
stub up area for mechanical and electrical connections. Steel cross members
shall support genset and add rigidity to the base with vibration isolators install
between the generator set and supports. Fuel tank shall be sized for 24 hours
of run time.
2.06 GOVERNOR
A. The engine governor shall control engine speed and transient load response
within commercial and ISO 8528 tolerances. It will be selected, installed, and
tested by the generator set manufacturer.
A. A radiator with blower fan shall be provided to maintain safe operation at the
specified ambient temperature. Air flow restriction through the radiator shall
not exceed 0.5” H2O. Provide ductwork with flexible connection between
radiator and discharge louver frame.
B. A radiator with blower fan shall be provided to maintain safe operation at the
specified ambient temperature. Air flow restriction through the radiator shall
not exceed 0.5” H2O. Provide ductwork with flexible connection between
C. The radiator shall be sized to cool the engine continuously while operating at
full rated load and at site conditions based on a site air flow restriction of 0.5”
and a minimum ambient temperature of 110-degrees F. Any required
additional de-rations of the radiator resulting from placing the genset inside a
standard enclosure, sound attenuated enclosure or inside a building, shall be
taken into consideration by the system supplier.
A. The engine air cleaner shall be engine mounted with dry element requiring
replacement no more frequently than 250 operating hours or once each year.
If external ducting is required, maximum restriction to the combustion air inlet
shall be 27 in H2O with air flow of 932 cfm. Design inlet air restriction shall
be based on 0.75” H2O for use with an enclosure or 0.50” for use inside a
building.
A. The engine starting system shall include 24 volt DC starting motor(s), starter
relay, and automatic reset circuit breaker to protect against butt engagement.
C. Batteries shall be maintenance free, lead acid type mounted near the starting
motor and supplied with a corrosion resistant battery rack. Required cables
will be furnished and sized to satisfy circuit requirements. The system shall
be capable of starting a properly equipped engine within 10 seconds at
ambient temperatures greater than –10 Degrees F. For gensets above
1000kW, the batteries shall have a 2600 CCA, 380 AH rating and shall be
rated for operation in ambient temperatures of –10-degrees F.
D. For generators rated 800kW and below, 10 ampere, dual rate, constant
voltage charger shall be provided. For generators over 800kW, a 20 ampere
dual rate, constant voltage, battery charger shall be provided. The charger
shall accept 120 - 208 - 240 volt AC single phase input to provide 24 volt DC
output. It shall be fused on the AC input and DC output, and incorporate
current limiting circuitry to avoid the need for a crank disconnect relay. An
AC voltage power switch shall be mounted on the face of the charger and
shielded from accidental switching. The charger shall include an AC
ammeter and voltmeter, a failure malfunction alarm switch, and be housed in
a NEMA 1 enclosure suitable for wall mounting.
2.12 GENERATOR
A. The generator shall be close coupled, drip proof and guarded, constructed to
NEMA 1 and IP 22 standards, single bearing, salient pole, revolving field,
synchronous type with amortisseur windings in the pole faces of the rotating
field.
D. The generator terminal box shall provide generous space for entrance and
installation of power cables.
B. The regulator shall be a solid state design which includes electronic voltage
buildup and overcurrent protection. The voltage regulator shall be equivalent
to either a Caterpillar VR3 or DVR. It shall incorporate 1:1 volts per Hertz
characteristics with the regulated voltage a linear function proportional to
frequency over a 30 to 70 Hz range.
C. The regulator shall be suitable for mounting within or external to the alternator
assembly, and have provision for remote voltage level control, using 16 ga
shielded wire.
D. As installed, the voltage regulator shall meet the applicable sections of the
Canadian Standards Association (CSA),International Electrotechnical
Commission (IEC), Institute of Electrical and Electronic Engineers (IEEE),
National Electrical Manufacturers Association (NEMA)
2.14 MOUNTING
B. The generator set shall be mounted to the sub-base fuel tank with spring type
vibration isolators between the generator rails and sub-base fuel tank.
Flexible fuel lines shall be connected from the sub-base fuel tank to the
generator fuel supply and return connections.
C. Enclosure shall have oil drain, coolant drain and crankcase breather lines
extended to exterior of enclosure.
A. The amperage rating of the automatic load transfer switch shall be as shown.
Each transfer switch shall be 4-pole or 3-pole with cross-over neutral.
Manufacturer shall be ASCO, Russell or Zenith.
C. The automatic load transfer control shall be open transition and rated for
continuous duty when enclosed in a non-ventilated NEMA 1 enclosure. It
shall be rated for all classes of load, including inductive and non-inductive, at
600 volts and tungsten lamp load at 250 volts. The transfer switch portion of
the control shall be designed, built and tested to close on an inrush current up
to and including twenty (20) times the continuous rating of the switch without
welding or excessive burning of the contacts. The transfer switch shall be
capable of enduring six thousand (6000) cycles of operation, at rated current,
at a rate of six (6) cycles per minute, without failure. One cycle shall consist
of one complete opening and closure of both sets of contacts on an inrush
current of ten (10) times the continuous rating of the switch.
D. The transfer switch shall be as listed under U.L. 1008. Switch utilizing
reversing contactor mechanisms as a means to transfer load are disallowed
and will not be considered.
E. The automatic load transfer switch shall include the following accessories:
1. Engine starting contacts to provide for generator starting.
2. Full phase protection. Three-phase relays shall be field adjustable, close
differential type with 92-95% pickup and 82-85% drop out. Relays are to
be connected across live lines.
3. Test switch, to simulate a power outage.
4. Adjustable time delay on engine starting to override momentary outages
and nuisance voltage dips.
5. Adjustable time delay on transfer of load to emergency source.
Adjustable time delay to open transfer switch contact to allow motor loads
to decay.
6. Adjustable time delay on retransfer of load to normal with 5 minute cool-
down timer wherein the generator set runs unloaded after transfer to line.
7. Plant exerciser to start and run the generator set with or without load
each 168 hours for a 30 minute interval. Selector switch will be provided
for with-load or without-load testing.
8. Two auxiliary contacts closed on emergency and two auxiliary contact
open on emergency.
9. Pilot lights to indicate the normal and emergency position of the transfer
switch.
10. Isolated (un-grounded) neutral bar.
11. Disconnect plug.
A. The controls, protection, and monitoring systems of the generator set and its
operation shall be the responsibility of the generator set manufacturer. All
B. The control panel shall be shock mounted on the generator and have the
capability to face either side or the rear of the generator and shall control,
protect, meter and annunciate all functions necessary to confirm the
operational status of the generator set.
C. The control panel shall be sealed in a dust tight and watertight module with
sealed wire entries into the enclosure so as to protect the circuitry and
internal components from oil, soot, fumes, diesel fuel, dirt, moisture and
debris. The panel module shall comply with NEMA 4 for environmental
protection, while the total panel shall qualify for IEC 144 and NEMA 12.
D. The 24 volt DC system shall incorporate energize to run logic and include:
Control:
The engine start-stop switch shall be door mounted and include positions for
off/reset, run, start and automatic mode. Start-stop logic shall have provisions
for cycle cranking programmable from 5-60 second cycles, for total crank
time of 5-120 seconds. Cooldown operation shall be programmable from 0-30
minutes with a signal to allow removal of the load from the generator set
during cooldown.
Shutdowns/Annunciation:
The generator set shall shut down and red flashing LEDs shall signal
operational faults of overcrank, overspeed, high water temperature, and low
oil pressure. High water temperature, low coolant level, and low oil pressure
shall be programmable for shutdown or alarm. A minimum of three (3) spare
fault inputs shall be available which can be programmed for alarm or
shutdown, with 0-250 second time delay. There shall be a lamp test
switchpad accessible from the front of the panel.
Monitor:
Safety Devices:
ISO red emergency stop pushbutton shall be provided, and all controls,
annunciation, and monitors labeled with ISO symbols.
Protection:
A lockable door shall be included which is bottom hinged to allow full panel
exposure when open.
E. A cycle crank timer shall provide five 10 second cranking periods separated
by 10 second rest periods. A cool down timer shall provide an adjustable 0-30
minute engine running period before shutdown after removal of load.
B. The circuit breaker shall be sized such that the generator will be capable of
producing the 100% rated kW of the genset at a 0.8 power factor for a
minimum of 4 hours. If a molded case breaker is provided, the breaker shall
be have a breaker frame size with a minimum of 120% of the full load
amperage of the generator. If an insulated case breaker is provided, the
breaker can be sized for 100% of the full load amperage of the generator.
3.0 EXECUTION
3.01 GENERAL
B. The genset shall be subjected to a full load, resistive load test prior to
shipment to the jobsite. The tests shall demonstrate at a minimum the full
rated load capability of the genset, voltage, amperage, fuel consumption shall
be recorded.
3.03 INSTALLATION
PRESTART CHECKS:
oil level
water level
day tank fuel level
battery connection and charge condition
air start supply pressure (if so equipped)
engine to control interconnects
engine generator intake/exhaust obstructions
engine room ventilation obstructions
removal of all packing materials
OPERATION:
Load - 1-hours operation at 50% of full load rating. 1 hours at 75% full load
rating. 1- hours operation at 100% of full load rating. 0 to 100% step load, 0
to 50% step load, 0 to 75% step load and 15 minute intervals. The following
shall be recorded at fifteen minute intervals:
Upon successful completion of the above test, the generator set shall be
subjected to a 100% block load test and the recovery timeframe to steady
state recorded. This test shall be repeated a total of 4 times.
A. The manufacturer's warranty shall in no event be for a period of less than five
(5) years from date of initial start-up of the system or 1500 operating hours,
whichever comes first.
B. The warranty shall include repair parts, labor, reasonable travel expense
necessary for repairs at the jobsite, and expendables (lubricating oil, filters,
antifreeze, and other service items made unusable by the defect) used during
the course of repair. Applicable deductible costs shall be specified in the
manufacturer's warranty.
C. The system supplier shall provide factory trained servicemen and shall have
sufficient parts inventory to maintain over the counter availability of at least
90% of any required parts and shall guarantee 100% parts availability within
48 hours from the time an order is entered with the dealer. Manufacturers
who do not meet this qualification will be rejected in their entirety.
3.06 ORIENTATION
A. The system supplier shall provide a complete orientation for the owner's
engineering and maintenance personnel. Orientation shall include both
classroom and hands-on instruction. Topics covered shall include control
operation, schematics, wiring diagrams, meters, indicators, warning lights,
shutdown system and routine maintenance.
A. The system manufacturer's authorized local dealer shall furnish one copy
each of the manuals and books listed below for each unit under this contract:
1. OPERATING INSTRUCTIONS - with description and illustration of all
switchgear controls and indicators and engine and generator controls.
2. PARTS BOOKS - that illustrate and list all assemblies, subassemblies
and components, except standard fastening hardware (nuts, bolts,
washers, etc.).
3. PREVENTATIVE MAINTENANCE INSTRUCTIONS - on the complete
system that cover daily, weekly, monthly, biannual , and annual
maintenance requirements and include a complete lubrication chart.
4. ROUTINE TEST PROCEDURES - for all electronic and electrical circuits
and for the main AC generator.
5. TROUBLESHOOTING CHART - covering the complete generator set
showing description of trouble, probable cause, and suggested remedy.
END OF SECTION
16650
SURGE PROTECTIVE DEVICE
1.0 GENERAL
1.01 DESCRIPTION
A. The Surge Protection Device (SPD) covered under this section includes all service
entrance type surge protection devices suitable for use as Type 1 or Type 2 devices
per UL1449 3rd Edition, applied to the line or load side of the utility feed inside the
facility.
B. A SPD is located at Service Entrance (see plans for additional SPD devices).
C. Contractor shall provide all labor, materials, equipment and incidentals as shown,
specified and required to finish and install surge protection devices.
A. Reference Standard: Comply with the latest edition of the applicable provisions and
recommendations of the following, except as otherwise stated in this document:
1. UL 1449 3rd Edition 2009 Revision (effective 9/29/2007).
2. UL 1283.
3. ANSI/IEEE C62.41, Recommended Practice for Surge Voltages in Low-
Voltage AC Power Circuits.
4. ANSI/IEEE C62.45, Guide for Surge Testing for equipment connected to
Low-Voltage AC Power Circuits.
5. UL96A
6. IEEE 1100 Emerald Book.
7. National Fire Protection Association (NFPA 70: National Electrical Code).
A. Package must include show drawings complete with all technical information, unit
dimensions, detailed installation instructions, maintenance manual, recommended
replacement parts list and wiring configuration.
D. Copies of actual let through voltage data in the form of oscillograph results for both
ANSI/IEEE C62.41 Category C3 (combination wave) and B3 (Ring wave) tested in
accordance with ANSI/IEEE C6245.
G. Copy of warranty statement clearly establishing the terms and conditions to the
building/facility owner/operator.
2.0 PRODUCTS
A. Current Technology – Transguard3 or TG3 Series 200kA per mode surge rating or
approved equal by Liebert, General Electric.
A. Refer to drawing for operating voltage, configuration and surge current capacity per
mode for each location, or you may list locations and information here.
B. Declared Maximum Continuous Operating Voltage (MCOV) shall be greater than 115
percent of the nominal system operating voltage and in compliance with test and
evaluation procedures outlined in the nominal discharge surge current test of
UL1449 3rd Edition, section 37.7.3. MCOV values claimed based on the
component’s value or on the 30-minute 115% operational voltage test, section 38 in
UL1449 will not be accepted.
C. Unit shall have no more than 10% deterioration or degradation of the UL1449 3rd
Edition Voltage Protection Rating (VPR) when exposed to a minimum of 5,000
repeated category C3 (20kV/10kA) surges. The SPD manufacturer must provide a
test report validating the repetitive surge test was performed.
D. Protection Modes UL1449 3rd Edition VPR(6kV, 3kA) for grounded WYE/delta and
High Leg Delta circuits with voltages per the contract documents shall be as follows
and comply with test procedures outlined in UL1449 3rd Edition section 37.6:
B3 C3 Comb. UL 1449
System Ringwave Wave 20kV, Third Edition
Voltage Mode MCOV 6kV, 500A 10kA VPR Rating
120/240, L-N 150 490 980 700
120/208 L-G 150 570 980 700
N-G 150 640 1170 700
L-L 300 500 1600 1200
277/480 L-N 320 450 1420 1200
L-G 320 540 1540 1200
N-G
Azura 320Center Renalus
Surgery 570 1600
Crestview 1000
L-L 552 530 2600 2000
16650
SURGE PROTECTIVE DEVICE 16450-3
6/27/19
E. Electrical Noise Filter - each unit shall include a high performance EMI/RFI noise
rejection filter with a maximum attenuation of 54dB per MIL-STD-220B.
1. SPD shall include a EMI/RFI noise rejection filter for all L-N modes as
well as a removable filter in the N-G mode.
G. The UL1449 Voltage Protective Rating (VPR) shall be permanently affixed to the
SPD unit.
I. The SCCR rating of the SPD shall be 200kAIC without the need for upstream over
current protection.
J. The SPD shall be listed as Type 1 SPD, suitable for use in Type 1 or Type 2
applications.
3.0 EXECUTION/INSTALLATION
3.01 The SPD manufacturer’s technician shall perform a system checkout and start-up in the
field to assure proper installation, operation and to initiate the warranty of the system.
The technician will be required to do the following:
A. Verify voltage clamping levels utilizing a diagnostic test kit, comparing factory
readings to installed readings.
3.02 Unit may be installed on either the line or load side of the main service disconnect. If
installed on the line side unit shall be installed with an integral disconnect. If installed on
the load side the unit shall be installed on the largest breaker size available. If installed
lead length exceeds 5’ installer shall use a low impedance (HPI) cable to reduce the lead
lengths effect on the installed performance of the SPD.
SECTION 16702
PART 1 - GENERAL
1.01 WORK INCLUDED
A. Furnish and install a complete nurse call system between the Nurse’s Station and the
Separation, Pre and Post OP, Operating Rooms and Patient Toilet Rooms.
B. This work includes a master station, remote stations, dome lights, transformer, conduit and
wiring as illustrated on the accompanying drawings and hereinafter specified.
C. All nurse call equipment/systems shall be UL 1069 listed.
1.02 REFERENCE DOCUMENTS
A. The Special Provisions for electrical work are hereby made a part of this Section of the
Work. Refer to Section 16010.
1.03 SUBMITTALS
A. Submit complete manufacturer’s specification data on the complete system and each type of
material to be used.
PART 2 - PRODUCTS
2.01 MASTER NURSE CALL UNIT
A. Furnish and install Cornell Series 4000 Annunciator, Model #A-4006. Provide Model #A-
4010 if more than 6 nurse calls, #A-4020 if more than 10, #A-4030 if more than 20, etc.
Station complete with flush box, cover, visual LED’s, buzzer and silence switch for
operation at 24V A.C. at Nurse Station and Reception ASC where applicable, as shown on
drawings.
B. Furnish and install Cornell Series 4000 Power Supply, Model #P-512243A, 120/24V, 30 VA
capacity.
2.02 REMOTE STATIONS
A. Patient toilet stations shall be Cornell Series 4000, Model #E-114-3 single switch, with flush
cover plate and Germ Free & Glow in the Dark Nylon pull cord mounted adjacent to water
closet as noted on plans. All pull strings shall be fire retardant and devices shall be rated for
Oxygen Rich Environments.
B. Separation Room and Exam Rooms – in states where required. Call stations (one required)
shall be Cornell Series 4000, Model #E-114-3 single switch, flush wall plate, with call-
placed indicator light mounted on single gang flush cover.
1. Install DS-110 Duty Station (audio annunciator) as indicated on plans.
C. Dome lights shall be Cornell Series 4000, Model #L-101, with white lamp mounted above
door trim, outside room and model #L-102 with Blue Lamp/Cover on top and White
Lamp/cover on the bottom.
D. Changing Rooms shall be Cornell Series 4000, Model #E-114-3, pull station with single
switch, flush wall plate, and call placed indicator light mounted on single gang flush cover.
E. Lounge Duty Station shall be Cornell Series 4000, Model #DS-110, annunciator with LED
indication and manual high or low volume tone.
2.03 SYSTEM WIRING
A. Wire transformer (2) 12# THHN, (1) 12# Cu Gnd. - 1/2" C; from transformer secondary
extend (2) 14# THHN, (1) 14# Cu Gnd. fused at transformer, to master nurse call
annunciator.
B. From annunciator extend (4) 16# AWG to each call station with (2) 16# to each call station
dome light.
PART 3 - EXECUTION
3.01 STATIONS
A. Mount master station flush at 50" above finished floor, or at Nurse’s Station where specified
on the drawings.
B. Mount signal devices flush as shown on the plans.
C. All Low-Voltage interconnecting wiring shall be 16#AWG or larger.
END OF SECTION
16721
LIFE SAFETY SYSTEM – LO RISE
1.0 GENERAL
1.01 SUMMARY
A. The Fire Alarm System survivability requirements for the system shall be a
Level 0. All wiring and devices shall be provided in accordance with 2013
NFPA 72 sections 12.4 and 24.3.6.
B. This Section describes the basic materials and installation methods for the
Life Safety System. Comply with other Division 16 Sections and Drawings as
applicable. Refer to other Divisions for coordination of Work.
C. Drawings are diagrammatic. The devices shown on the plans are for general
architectural and owner coordination and shall be considered a minimum;
additional devices shall be provided as required as part of this contract. The
contractor shall provide all components, devices, and connections necessary
to provide a complete and operating system as required by NFPA and the
authority having jurisdiction. The contractor shall coordinate with all trades
and provide the necessary devices, connections and zone required (included,
but not exclusive, duct mounted smoke detectors, sprinkler system flow and
tamper switches, HVAC controls, elevator controls, etc.) Provide quantity of
audio/visual devices and power supplies as required by NFPA and the
authority having jurisdiction.
1.02 MANUFACTURER
E. All control panel assemblies and connected field appliances shall be both
designed and manufactured by the same company, and shall be tested and
cross-listed as to ensure that a fully functioning is designed and installed.
The system supplied under this specification shall be a microprocessor-
based, system. The system shall utilize independently addressed,
microprocessor-based smoke detectors, heat detectors, and modules as
described in this specification.
1.03 ALTERNATES
B. All equipment and components shall be the manufacturer's current model and
all equipment shall be by the same manufacture. The materials, appliances,
equipment and devices shall be tested and listed by a nationally recognized
approvals agency for use as part of a protected premises protective signaling
system, access control, and smoke control. The authorized representative of
the manufacturer of the major equipment, such as control panels, shall be
responsible for the satisfactory installation of the complete system.
1.04 REFERENCES
A. General (references)
1. All work and materials shall conform to all applicable Federal, State and
local codes and regulations governing the installation. If there is a conflict
between the referenced standards, federal, state or local codes, and this
specification, it is the bidder's responsibility to immediately bring the
conflict to the attention of the Engineer for resolution. National standards
shall prevail unless local codes are more stringent. The bidder shall not
attempt to resolve conflicts directly with the local authorities unless
specifically authorized by the Engineer.
2. System components proposed in this specification shall be UL listed to
operate together as a system. The supplier shall provide evidence, with
his submittal, of listings of all proposed equipment and combinations of
B. Codes
1. Fire - The equipment and installation shall comply with the current
provisions of the following codes and standards:
a. NFPA 70 - 2017 National Electric Code®
b. NFPA 72 - 2013 National Fire Alarm Code®
c. NFPA 90A - 2015 Air Conditioning Systems
d. NFPA 101- 2013 Life Safety Code®
e. UL 864 - Control Units for Fire Protective Signaling Systems.
f. UL 268 - Smoke Detectors for Fire Protective Signaling Systems.
g. UL 268A - Smoke Detectors for Duct Applications.
h. UL 521 - Heat Detectors for Fire Protective Signaling Systems.
i. UL 228 - Door Closers-Holders, With or Without Integral Smoke
Detectors.
j. UL 464 - Audible Signaling Appliances.
k. UL 38 - Manually Actuated Signaling Boxes for Use with Fire-
Protective Signaling Systems
l. UL 346 - Waterflow Indicators for Fire Protective Signaling Systems.
m. UL 1971 - Signaling Devices for the Hearing-Impaired.
n. UL 1481 - Power Supplies for Fire Protective Signaling Systems.
o. Factory Mutual (FM) approval
p. AHJ
q. Federal Codes and Regulations
r. Americans with Disabilities Act (ADA)
A. General
The Contractor shall furnish all labor, services and materials necessary to
furnish and install a complete, functional fire alarm system (System). The
System shall comply in respects with all pertinent codes, rules, regulations
and laws of the Authority, and local jurisdiction. The System shall comply in
all respects with the requirements of the specifications, manufacturer's
recommendations and Underwriters Laboratories Inc. (ULI) listings.
B. System Features
1. Provide and install a new fire detection and alarm system that shall
consist of:
a. Fire Alarm Control Panel.
b. LCD remote annunciator(s).
c. Printer.
d. Manual pull stations, smoke detectors, heat detectors, beam detectors
C. Sequent of Operations
1. The alarm activation of any area smoke detector, heat detector, manual
pull station, sprinkler waterflow, the following functions shall automatically
occur:
a. The internal audible device shall sound at the control panel and
remote annunciator.
b. The LCD display shall indicate all applicable information associated
with the alarm condition including; device type, device location and
time/date.
c. All system activity/events shall be documented in system history and
on the system printer.
d. Any remote or local annunciator LCD/LED's associated with the alarm
shall be illuminated.
e. Activate notification audible appliances throughout the building or as
required by code.
f. Activate visual strobes notification appliances throughout the building
or as required by code. The visual strobe shall continue to flash until
the system has been reset. The visual strobe shall not stop operating
when the "Alarm Silence" is pressed.
g. Transmit an alarm signal to the central station.
h. All automatic events programmed to the alarm point shall be executed
and the associated outputs activated.
i. All stairwell/exit doors shall unlock throughout the building.
j. All self-closing fire/smoke doors held open shall be released.
2. The Alarm activation of any duct smoke detector, the following functions
shall automatically occur:
a. The internal audible device shall sound at the control panel and
remote annunciator.
b. The LCD display shall indicate all applicable information associated
with the alarm condition including; device type, device location and
time/date.
c. All system activity/events shall be recorded on the system printer and
system history file.
d. Any remote or local annunciator LED's associated with the alarm shall
be illuminated.
e. Transmit signals to remote annunciators located as shown on the
contract drawings.
f. Transmit an alarm signal to the central station.
g. Shutdown the local air handling unit.
h. All automatic events programmed to the alarm point shall be executed
and the associated outputs activated.
D. System Configuration
1. General
a. All Life Safety System equipment shall be arranged and programmed
to provide a system for the early detection of fire, the notification of
building occupants, the automatic summoning of the local fire
department, the override of the HVAC system operation, and the
activation of other auxiliary systems to inhibit the spread of smoke and
fire, and to facilitate the safe evacuation of building occupants.
b. The System shall utilize independently addressed, smoke detectors,
heat detectors and input/output modules as described elsewhere in
this specification.
2. Power Supply
a. The power supply shall be a high efficiency switch mode type with line
monitoring to automatically switch to batteries for power failure or
brown out conditions. The automatic battery charger shall have low
battery discharge protection. The power supply shall provide internal
power and 24 Vdc at 6.0A continuous for notification appliance
circuits. All outputs shall be power limited. The battery shall be sized
series modules.
6. Audio Notification Appliance Circuits
a. One-way audio notification appliance circuits (NAC) shall Class B. All
notification appliance circuits shall have a minimum circuit output
rating of 35W @70Vrms. The notification circuits shall be power
limited. Non-power limited circuits are not acceptable.
b. The one-way audio notification appliance circuits shall be EST
Signature series modules.
7. Signaling Line Circuits
a. The signaling line circuit shall communicate from a panel/node to
analog/addressable detectors, input modules, output modules,
isolation modules and notification appliance circuits.
b. Each signaling circuit connected to addressable/analog devices shall
provide a minimum of 20 spare addresses.
c. When a signaling line circuit covers more than one fire/smoke
compartments, a wire-to-wire short shall not effect the operation of the
circuit from the other fire/smoke compartments.
d. The signaling line circuit (SLC) connecting panels and annunciators
shall be Class B.
e. The signaling line circuit connecting to addressable/analog devices
including, detectors, monitor modules, control modules, isolation
modules, and notification circuit modules shall be Class B.
8. DACT
a. The panel shall have a dialer (alarm communicator transmitter
(DACT)) module to transmit alarm, supervisory and trouble signals to
a Central Monitoring Station (CMS). The DACT shall support two
separate technologies for communication with telephones lines, 20
PPS 4/2 communications, and configured for dual tone multi-
frequency (DTMF) or pulse modes, cellular or radio system. It shall be
possible to delay AC power failure reports, auto test call, and site
program using a touch tone phone and password.
b. The dialer shall be an EST model DL2.
c. The dialer shall utilize two separate technologies for notification in
accordance with 2013 NFPA 72 26.6.3.2.1.
E. Submittals
1. Project Submittal
a. The contractor shall purchase no equipment for the system specified
herein until the owner has approved the project submittals in their
entirety and has returned them to the contractor. It is the responsibility
of the contractor to meet the entire intent and functional performance
detailed in these specifications. Approved submittals shall only allow
the contractor to proceed with the installation and shall not be
construed to mean that the contractor has satisfied the requirements
of these specifications. The contractor shall submit ten (10) complete
sets of documentation including point to point CAD drawings and
submittals within 30 calendar days after award of purchase order.
b. Each submittal shall include a cover letter providing a list of each
variation that the submittal may have from the requirements of the
d. Product Data - Data sheets with the printed logo or trademark of the
manufacturer for all equipment. Indicated in the documentation will be
the type, size, rating, style, and catalog number for all items proposed
to meet the system performance detailed in this specification. The
proposed equipment shall be subject to the approval of the
Architect/Engineer.
e. Shop Drawings - A complete set of shop drawings shall be supplied.
The shop drawings shall be reproduced electronically in digital format.
This package shall include but not be limited to:
i. Control panel wiring and interconnection schematics.
ii. Complete point to point wiring diagrams. A vertical riser is not
acceptable. All drawings must be in CAD.
iii. Detailed system operational description and operational
matrix.
iv. Complete system bill of material.
f. All drawings shall be reviewed and signed off by an individual having
a minimum of a NICET III certification in fire protection engineering
technology, subfield of fire alarm systems.
2. Qualifications of Contractor
a. The contractor shall have successfully installed similar system fire
detection, signaling control components on a previous project of
comparable size and complexity. The owner reserves the right to
reject any control components for which evidence of a successful prior
installation performed by the contractor cannot be provided.
b. The contractor shall have in-house engineering and project
management capability consistent with the requirements of this
project. Qualified and approved representatives of the system
manufacturer shall perform the detailed engineering design of central
and remote control equipment. Qualified and approved
representatives of the system manufacturer shall produce all panel
and equipment drawings and submittals, operating manuals. The
contractor is responsible for retaining qualified and approved
representative(s) of those system manufacturers specified for detailed
system design and documentation, coordination of system installation
requirements, and final system testing and commissioning in
accordance with these specifications.
c. Quality Assurance/Control Installer's Certification
i. The engineered systems distributor must be licensed in the
state of project location and have been incorporated in the
business in that state for a minimum of 5 years.
ii. Provide in the submittal a copy of the contractors training
certification issued by the manufacturer of the Life Safety
System.
d. Provide a copy of the installing technician's NICET certification level
III or IV.
e. System Calculations - complete calculations shall be provided which
show the electrical load on the following system components:
i. Each system power supply, including stand alone booster
supplies.
ii. Each standby power supply (batteries).
iii. Each notification appliance circuit.
iv. Each auxiliary control circuit that draws power from any
system power supply.
3. Closeout Submittal
a. Four (4) copies of the following documents shall be delivered to the
building owner's representative at the time of system acceptance.
The close out submittals shall include:
i. Project specific operating manuals covering the installed Life
Safety System. A generic or typical owner's instruction and
operation manual shall not be acceptable to fulfill this
requirement.
ii. As-Built drawings consisting of: a scaled plan of each building
showing the placement of each individual item of the Life
Safety System equipment as well as raceway size and routing,
junction boxes, and conductor size, quantity, and color in each
raceway. All drawings must reflect point to point wiring, device
address and programmed characteristics as verified in the
presence of the engineer and/or the end user unless device
addressing is electronically generated, and automatically
graphically documented by the system.
iii. Provide all drawings shall be provided in standard .DXF
format.
iv. Provide the name, address and telephone of the authorized
factory representative.
v. A filled out Record of Completion similar to NFPA 72, 1999
edition figure 1-6.2.1.
ii. Manual fire alarm stations - Two (2) percent of the installed
quantity of each type.
iii. Glass rods or panels for break glass manual fire alarm stations
(if used) - <Ten> percent of the installed quantity, but no less
than two devices.
iv. Audible and visible devices - One (1) percent of the installed
quantity of each type, but no less than two (2) devices.
v. Keys - A minimum of three (3) sets of keys shall be provided
and appropriately identified.
G. Training
1. The System Supplier shall schedule and present a minimum of 4 hours of
documented formalized instruction for the building owner, detailing the
proper operation of the installed System.
2. The instruction shall be presented in an organized and professional
manner by a person factory trained in the operation and maintenance of
the equipment and who is also thoroughly familiar with the installation.
3. The instruction shall cover the schedule of maintenance required by
NFPA 72 and any additional maintenance recommended by the system
manufacturer.
4. Instruction shall be made available to the Local Municipal Fire
Department if requested by the Local Authority Having Jurisdiction.
2.0 PRODUCTS
2.01 MANUFACTURER
A. General
1. The control panel shall be a multi-processor-based system designed
specifically for fire and releasing system applications. The control panel
shall be listed and approved for the application standard(s) as listed
under the General section.
2. The control panel shall include all required hardware, software and
system programming to provide a complete and operational system. The
control panel shall assure that life safety takes precedence among all
panel activities.
3. The control panel shall include the following capacities:
a. Support up to 380 analog/addressable points per panel (1,900 total
with 5 networked panels)
b. Support up to 5 fully supervised network remote annunciators.
c. Support a DACT (dialer) for off premise notification.
d. Support up to 576 chronological events in history.
B. Annunciation
1. The system shall be designed and equipped to receive, monitor, and
annunciate signals from devices and circuits installed throughout the
building. Manufacturer's standard control switches shall be acceptable if
they provide the required operation, including performance, supervision
and position indication. If the manufacturers' standard switches do not
comply with these requirements, fabrication of custom manual controls
acceptable to the owner is required.
2. Receipt of alarm, trouble, and supervisory signals shall activate integral
audible devices at the control panel(s) and at each remote annunciation
device.
3. The annunciator shall contain the following system status indicators:
a. 80 character Backlit Liquid Crystal Display
b. System Power Indicator – green LED
c. System Common Alarm – red LED
d. System Common Trouble – yellow LED
e. System Common Supervisory – yellow LED
f. System Common Monitor – yellow LED
g. System Ground Fault – yellow LED
h. System CPU Fault – yellow LED
i. System Disables – yellow LED
j. System Test Point(s) – yellow LED
k. System Reset Switch with Integral yellow LED
l. System Alarm Silence Switch with Integral yellow LED
m. System Local Silence Switch with Integral yellow LED
n. System Drill Switch with Integral yellow LED
o. System Message Queue Scroll Switches
C. Power Supply
1. Each system power supply shall be a minimum of 6 amps @ 24 vdc.
2. Upon failure of normal (AC) power, the affected portion(s) of the system
shall automatically switch over to secondary power without losing any
alarm, trouble or operator acknowledgment signals.
3. Each system power supply shall be individually annunciated and shall
identify the inoperable power supply in the event of a trouble condition.
4. All standby batteries shall be continuously monitored by the system. Low
battery and disconnection of battery power supply conditions shall
immediately annunciate as a trouble signal, identifying the deficient
batteries.
5. All system power supplies shall be capable of recharging their associated
batteries, from a fully discharged condition to a capacity sufficient to allow
the system to perform consistent with the requirements of this section, in
48 hours maximum.
6. All AC power connections shall be to the building's designated emergency
electrical power circuit and shall meet the requirements of Section 1-5.2
of NFPA 72 - 1999. The AC power circuit shall be installed in conduit
raceway. The power circuit disconnect means shall be clearly labeled
FIRE ALARM CIRCUIT CONTROL and shall have a red marking. The
location of the circuit disconnect shall be labeled permanently inside the
each control panel.
7. The power supply shall be an EST model 2-PPS/6A.
D. Display
1. The system shall allow message routing to be configured to any or all
annunciators.
2. All system printer port shall be configurable to output any combination of
alarm, supervisory, trouble, or monitor, event messages.
3. Each LCD display on each annunciator shall be configurable to display
the status of any combination of alarm, supervisory, trouble, or monitor,
event messages.
4. Clear distinction shall be provided between alarm, supervisory, trouble,
and monitor status messages.
5. The system shall provide the ability to retrieve data from the
analog/addressable detectors to a PC while the system is on-line and
operational in the protected premises. The uploaded data may then be
analyzed in a diagnostic program supplied by the system manufacturer.
6. A standby power supply shall automatically supply electrical energy to the
system upon primary power supply failure.
E. Dialer – DACT
1. The system shall provide an off premise Digital Alarm Communications
Transmitter (DACT) capable of transmitting system alarm, trouble and
supervisory events to a central monitoring station (CMS). The DACT shall
support dual telephone lines, 20 PPS 4/2 communications, and
F. Reports
1. The system shall provide the operator with system reports that give
detailed chronological description of the last 576 system events. The
system shall provide a report that gives a listing of the sensitivity and
environmental compensation usage of all of the detectors on the system,
or specified analog/addressable circuit.
2. The system report shall also include facility name, compiled date,
compiler revision, project revision and report date. The system shall
output these reports via the main LCD, and reports shall be capable of
being printed on the system printer.
A. Initiating Devices
1. Smoke Detectors & Accessories
a. Analog Addressable Smoke General
i. Each analog addressable smoke detector's sensitivity shall be
capable of being programmed individually as: most sensitive,
more sensitive, normal, less sensitive or least sensitive.
ii. The system shall allow for changing of detector types for
service replacement purposes without the need to reprogram
the system. The replacement detector type shall automatically
continue to operate with the same programmed sensitivity
levels and functions as the detector it replaced. System shall
display an off-normal condition until the proper detector type
has been installed or change in the application program profile
has been made.
b. Smoke Detector Photoelectric or Photo/Heat
i. Provide analog/addressable photoelectric smoke detectors as
required. The system shall have the ability to set the
sensitivity and alarm verification of each of the individual
detectors on the circuit. It shall be possible to automatically
change the sensitivity of individual analog/addressable
detectors for the day and night periods. Each smoke detector
shall be capable of transmitting alarm signals as well as
normal, trouble and need cleaning information. It shall be
possible to program control panel activity to each level. Each
smoke detector may be individually programmed to operate at
any one of five (5) sensitivity settings. Each detector
microprocessor shall contain an environmental compensation
algorithm that identifies and sets ambient environmental
thresholds approximately six times an hour. The
microprocessor shall monitor the environmental compensation
value and alert the system operator when the detector
approaches 80% and 100% of the allowable environmental
compensation value.
ii. The analog/addressable photoelectric smoke detector shall be
an EST model SIGA-PS.
iii. Where required by designed drawings provide a combination
photo/heat detector in one device. The unit shall be EST
model SIGA-PHS.
c. Duct Detector Housing
i. Provide smoke detector duct housing assemblies to mount an
analog/addressable detector along with a standard, relay or
isolator detector mounting base. The housing shall also protect
the measuring chamber from damage and insects. The
housing shall utilize an air exhaust tube and an air sampling
inlet tube that extends into the duct air stream up to ten feet.
Drilling templates and gaskets to facilitate locating and
mounting the housing shall also be provided. The housing
shall be finished in baked red enamel. Remote alarm LED
indicators and remote test stations shall be provided.
ii. The smoke detector duct housing shall be an EST model
SIGA-DH.
d. Relay Module
i. Provide addressable control relay circuit modules as required.
The module shall provide one (1) form C dry relay contacts
rated at 24Vdc @ 2 amps (pilot duty) to control external
appliances or equipment. The position of the relay contact
shall be confirmed by the system firmware.
ii. The addressable control relay circuit module shall be an EST
model SIGA-CR.
2. Fixed Temperature – ROR Heat Detector
a. Provide analog/addressable combination fixed temperature / rate-of-
rise detectors at the locations shown on the drawings. The heat
detector shall have a nominal fixed temperature alarm point rating of
135°F (57°C) and a rate of rise alarm point of 15°F (9°C) per minute.
The heat detector shall be rated for ceiling installation at a minimum of
70 ft (21.3m) centers and be suitable for wall mount applications.
b. The analog/addressable combination fixed temperature / rate-of-rise
detector shall be EST model SIGA-HRS.
3. Detector Bases – Standard
a. Provide standard detector mounting bases suitable for mounting on
either North American 1-gang, 3½ or 4 inch octagon box and 4 inch
square box, or European BESA or 1-gang box. The base shall,
contain no electronics and support all series detector types.
b. The standard detector base shall be an EST model SIGA-SB4.
4. Manual Station - Double Action Single Stage
a. Provide analog/addressable double action, single stage fire alarm
stations at the locations shown on the drawings. The fire alarm
station shall be of polycarbonate construction and incorporate an
internal toggle switch. A locked test feature shall be provided. The
station shall be finished in red with silver "PULL IN CASE OF FIRE"
lettering. The manual station shall be suitable for mounting on North
B. Control Modules
1. Control Relay Module - SIGA-CR
a. Provide intelligent control relay modules as required. The Control
Relay Module shall provide one form "C" dry relay contact rated at 2
amps @ 24 VDC to control external appliances or equipment
shutdown. The control relay shall be rated for pilot duty and releasing
systems. The position of the relay contact shall be confirmed by the
system firmware. The control relay module shall be suitable for
mounting on North American 2 ½" (64mm) deep 1-gang boxes and 1
½" (38mm) deep 4" square boxes with 1-gang covers.
C. Notification Appliances
1. General (signals)
a. All appliances, which are supplied, for the requirements of this
specification shall be UL Listed for Fire Protective Service, and shall
be capable of providing the "equivalent facilitation" which is allowed
under the Americans with Disabilities Act Accessibilities Guidelines
(ADA(AG)), and shall be UL 1971 Listed.
b. All appliances shall be of the same manufacturer as the fire alarm
control panel specified to insure absolute compatibility between the
appliances and the control panels, and to insure that the application of
the appliances are done in accordance with the single manufacturer's
instructions.
c. Any appliances that do not meet the above requirements, and are
submitted for use must show written proof of their compatibility for the
purpose intended. Such proof shall be in the form of documentation
from all manufacturers that clearly states that their equipment (as
submitted) is 100% compatible with each other for the purpose
intended. All strobes shall be provided with lens markings oriented for
wall mounting.
d. All notification appliances shall be white unless noted otherwise on
the drawings.
2. Low Profile Horns
a. Provide low profile wall mount horns as required. The horn shall
provide an 84-dBA sound output at 10 ft. when measured in
reverberation room per UL-464. The horn shall have a selectable
steady or synchronized temporal output. In and out screw terminals
shall be provided for wiring. The horn shall mount in a North
American 1-gang box.
b. The low profile wall mount horns shall be EST Genesis series.
3. Low Profile Horn-Strobes
a. Provide low profile wall mount horn/strobes as required. The
b. The low profile wall mount horn/strobes shall be EST Genesis series.
4. Low Profile Strobes
a. Provide low profile wall mounted strobes as requried. In and out
screw terminals shall be provided for wiring. Strobes shall provide
synchronized flash outputs. Strobe output shall be determined as
required by its specific location and application from a family of 15cd,
30cd, 60cd, 75cd, or 110cd devices. Low profile strobes shall mount
in a North American 1-gang box.
b. The low profile wall mounted strobes shall be EST Genesis series.
3.0 EXECUTION
3.01 INSTALLATION
A. General
B. Installation Sequence
1. Installation of the systems shall be conducted in stages and phased such
that circuits and equipment are installed in the following order:
a. Riser conduits, AC power conduits and control cabinets.
C. Conductors–Open Cable-Raceway
1. The requirement of this section apply to all system conductors, including
all signaling line, initiating device, notification appliance, auxiliary function,
remote signaling, AC and DC power and grounding/shield drain circuits,
and any other wiring installed by the Contractor pursuant to the
requirements of these Specifications.
2. All circuits shall be rated power limited in accordance with NEC Article
760.
3. All circuits shall be installed in raceway or plenum rated cable at the
discretion of the Engineer.
4. All new system conductors shall be of the type(s) specified herein.
5. All initiating circuit, signaling line circuit, AC power conductors, shield
drain conductors and grounding conductors, shall be solid copper,
stranded or bunch tinned (bonded) stranded copper.
6. All signaling line circuits, including all addressable initiating device circuits
shall be 18 AWG minimum multi-conductor jacketed twisted cable or
twisted shielded or as per manufacturer's requirements.
7. All non-addressable initiating device circuits, 24 VDC auxiliary function
circuits shall be 18 AWG minimum or per manufacturer's requirements.
8. All notification appliance circuit conductors shall be solid copper or bunch
tinned (bonded) stranded copper. Where stranded conductors are
utilized, a maximum of 7 strands shall be permitted for No. 16 and No. 18
conductors, and a maximum of 19 strands shall be permitted for No. 14
and larger conductors.
9. All audible notification appliance circuits shall be 14 AWG minimum
twisted pairs or twisted pairs shielded or per manufacturer's requirements.
10. All visual notification appliance circuits shall be 14 AWG minimum THHN
or twisted pairs or twisted shielded pairs or per manufacturer's
requirements.
11. Conductors and Raceway
a. The contractor shall neatly tie-wrap all field-wiring conductors in the
gutter spaces of the control panels and secure the wiring away from
all circuit boards and control equipment components. All field-wiring
circuits shall be neatly and legibly labeled in the control panel. No
wiring except home runs from life safety system circuits and system
power supply circuits shall be permitted in the control panel
enclosures. No wiring splices shall be permitted in a control panel
enclosure.
b. All penetration of floor slabs and firewalls shall be fire stopped in
accordance with all local fire codes.
12. Open Cable
a. Power-limited cable in accordance with NEC 70, where used, not
installed in UL listed metal conduit or raceway shall be mechanically
protected by building construction features.
b. Installation shall be in areas not subjected to mechanical injury.
c. All circuits shall be supported by the building structure. Cable shall be
attached by straps to the building structure at intervals not greater
than 10 feet. Wiring installed above drop ceilings, cable shall not be
laid on ceiling tiles. Cable shall not be fastened in a manner that puts
tension on the cable.
d. Cable type shall be FPLP, FPLR or FPL, or permitted substitutions,
selected for the installation application as required by NEC 70,
Section 760-61.
e. All cable that is not enclosed by conduit shall be supported and
anchored with nylon straps or clamps. The use of staples is
prohibited.
13. Conduit Raceway
a. All systems and system components listed to UL864 Control Units for
Fire Protective Signaling Systems maybe installed within a common
conduit raceway system, in accordance with the manufacture's
recommendations. System(s) or system components not listed to the
UL864 standard shall utilize a separate conduit raceway system for
each of the sub-systems.
b. The requirements of this section apply to all system conduits,
raceways, electrical enclosures, junction boxes, pull boxes and device
back boxes.
c. All system conduits shall be of the sizes and types specified.
d. All system conduits shall be EMT, 3/4 -inch minimum, except for
flexible metallic conduit used for whips to devices only, maximum
length 6 feet, 3/4-inch diameter, minimum.
e. All system conduits, which are installed in areas, which may be
subject to physical damage or weather, shall be IMC or rigid steel, 3/4
-inch minimum.
f. Conduits shall be sized according to the conductors contained therein.
Cross sectional area percentage fill for system conduits shall not
exceed 40%.
g. Provide all new conduit raceway and conduit riser.
h. All fire alarm conduit systems shall be routed and installed to minimize
the potential for physical, mechanical or by fire damage, and so as not
to interfere with existing building systems, facilities or equipment, and
to facilitate service and minimize maintenance.
i. All conduits, except flexible conduit whips to devices, shall be solidly
attached to building structural members, ceiling slabs or permanent
walls. Conduits shall not be attached to existing conduit, duct work,
SECTION 16730
PART 1 - GENERAL
1.01 WORK INCLUDED
A. Furnish and install Category 6 and coaxial wire for the phone, data, patient care
entertainment and Clinical Network System.
B. This work includes conduit, wiring and terminations as illustrated on the accompanying
drawings and hereinafter specified.
1.02 REFERENCE DOCUMENTS
A. The Special Provisions for electrical work are hereby made a part of this Section of the
Work. Refer to Section 16010.
1.03 SUBMITTALS
A. Submit complete manufacturer’s specification data on the type of CAT 6 wire and RG6
coax cable material to be used.
B. Submit a certified copy of the following for approval.
1.Voice and data, CAT6 test reports required and described by this specification and in
accordance with ANSI/TIA 568-C.1 and ANSI/TIA 568-C.2 field testing procedures.
1.04 REFERENCES
A. ANSI/NFPA 70 – National Electrical Code.
B. Local and State Code.
C. Electronic Industry Association (EIA).
D. Telecommunication Industry Association (TIA).
PART 2 - PRODUCTS
2.01 CATEGORY 6 CABLE
A. Cable Construction
1. Cable Conductors shall be 23 AWG solid bare annealed copper with Polyolefin for
non-plenum and (3) pairs FEP plus (1) pair Polyolefin for plenum insulation.
2. Cable Conductors shall be color coded as follows:
Pair 1: Blue – White/Blue
Pair 2: Orange – White/Orange
Pair 3: Green – White/Green
Pair 4: Brown – White/Brown, non-plenum Brown – White, plenum.
3. Rip cord is applied longitudinally under cable jacket.
4. Cable jacket shall be :
a. Non-plenum, flame retardant PVC
b. Plenum, low-smoke, flex guard flame-retardant PVC
B. Cable Physical Data
1. Nominal cable diameter, 0.022 inches
PART 3 - EXECUTION
3.01 CATEGORY 6 INSTALLATION
A. Provide recessed mount 4-square box with single gang mud ring with 1" conduit sleeve to
6" A.F.C. for all locations and at heights as shown on contract drawings.
B. Run cables continuously without splice from wiring closet rack punch down to wall box jack
with corresponding identification numbers on each end of each wire.
C. Terminate wire in accordance with 568B standard wiring code at all telephone, data,
patient entertainment, and Clinical Network System terminal locations as designated on
the contract drawing.
3.02 COAX TV CABLE INSTALLATION
A. Run coax cable continuously without splice from wiring closet patch panel to each patient
entertainment location as shown on the contract drawing with corresponding identification
numbers on each end of every cable. Provide 5'-0" whip at each end for television vendor
to terminate.
3.03 AUDIO CABLE INSTALLATION
A. Run coax cable continuously without splice from electrical panel @ dialysis chase to each
patient entertainment location as shown on the contract drawing with corresponding
identification numbers on each end of every cable. Provide 5'-0" whip at each end for
television vendor to terminate.
3.04 CABLE SUPPORT
A. Where wires and cables are permitted to be run without conduit. They shall be
independently supported from the building structure at intervals not exceeding four (4) feet
on center, utilizing cable supports (J-Hooks, Arlington Loops) specifically approved for the
purpose.
B. Wires and cables shall not rest on or depend on support from suspended ceiling media
(tiles, spines, runners, bars, or support wires in the plane of the ceiling), nor shall they be
supported from pipes, ducts or conduits.
C. Where cables are bundled together, separate bundles shall be provided separately for
each type of cabling and separately for each independent system. Bundling and/or
supporting ties shall be of a type suitable for use in a ceiling air handling plenum
regardless of whether or not installed in a plenum.
1. Cables shall be tagged or labeled at each termination point and in each intermediate-
junction box, pull box or cabinet through which they pass.
D. Comply with applicable requirements for locating and routing circuitry, for installing
circuitry, and for-fire-stopping as described in other sub-section of Section 16010 and
Section 07841.
3.04 FIELD TESTING AND CERTIFICATION
A. The installing Contractor shall submit test plans, test design specifications and procedures
for all field tests to the Architect. The test plans shall be sufficiently documented by the
Contractor to ensure that each test is comprehensive and representative of the functions
noted in item “D” below.
B. 100 OHM transmission performance testing for Category 6 cables shall meet or exceed
the applicable requirements in AHSI/TIA 568-C.1 and C.2 including their addenda.
C. Link test configuration shall be tested as a channel from each outlet connector through the
patch panel device.
D. The wire map test for all pairs shall be performed and recorded for all segments. Wire
map test electrical performance at 100MHz frequency shall meet or exceed the values
expressed below in db per 328ft (100m) length.
1. PSACR 10.32
2. ACR 13.3
3. Attenuation 22.0
4. PSNEXT 32.3
5. NEXT 35.3
6. PSELFEXT 20.8
7. ELFEXT 23.8
8. Return Loss 20.1
Any pair that fails to meet the above performance values will require cable replacement
and retesting.
E. Field test measurements data documentation for each pair shall be printed in a summary
report and made available to Fresenius Medical Care, Project Manager within 5 days
following the test.
END OF SECTION
16780
LIGHTNING PROTECTION
1.0 GENERAL
1.01 SUMMARY
B. This Section describes the material and methods required for all UL Master
label lightning protection system for the Generator.
A. The shop drawings shall be complete including all system components, wiring
diagrams, devices, parts, installation details, etc.
B. Provide 1/8”=1’-0” scaled plans (minimum 24”x36” sheet) indicating all air
terminal locations, downleads, horizontal conductors, grounding locations, bi-
metal taps, and the like and all associated details and specifications.
2.0 PRODUCTS
2.01 CONDUCTORS
C. The angle of any turn shall not exceed 90 degrees nor have a radius smaller
than 24”.
A. Air terminals shall be copper or aluminum and extend a minimum 10” above
the object it protects.
B. Air terminals shall have a proper base support for the surface on which they
are used and shall be securely anchored to the surface.
3.0 EXECUTION
3.01 INSTALLATION
B. Provide a counterpoise loop for buildings more than 100 feet above finished
grade.
END OF SECTION