Sei sulla pagina 1di 7

Large-Scale Testing of a Replaceable “Fuse” Steel

Coupling Beam
Patrick J. Fortney1; Bahram M. Shahrooz2; and Gian A. Rassati3

Abstract: When coupled core wall 共CCW兲 systems are built in regions of high seismicity, the ductility demands on the coupling beams
can be of critical concern. Steel coupling beams, whether encased in concrete or not, offer a very high degree of ductility relative to
common concrete coupling beams. Hybrid core wall systems, that is CCW systems with steel or steel/concrete composite coupling beams,
Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

provide excellent lateral stiffness from the walls and coupling action, while providing excellent energy dissipation and ductility charac-
teristics of steel coupling beams. Previous research pertaining to steel coupling beams has made great strides in furthering the under-
standing of the behavior of steel coupling beams, and recommendations regarding design methodologies have been established. However,
as steel coupling beam ends are embedded in the wall piers, postdamage repair can be costly. This paper presents the results of large-scale
cyclic tests of a steel coupling beam designed and detailed based on the writers’ previous recommendations and an innovative “fuse” steel
coupling beam which provides an added feature to the steel coupling beam in that postdamage repair/replacement difficulties and expenses
are minimized.
DOI: 10.1061/共ASCE兲0733-9445共2007兲133:12共1801兲
CE Database subject headings: Coupling; Composite structures; Seismic design; Steel beams.

Introduction beams are alleviated with the use of steel coupling beams.
The design methodologies for steel coupling beams are well
Coupling beams have been shown to behave similarly to links in established, and are based on a wealth of information gathered
eccentrically braced frames 共Roeder and Popov 1978; Malley and from past research. To ensure ductility and chord rotation capac-
Popov 1983; Kasai and Popov 1986兲. When the strength of the ity, web stiffener plates are proportioned based on expected maxi-
coupling beams is distributed properly over the height of the mum rotations as prescribed by the American Institute of Steel
building, desirable hinge formation occurs in the beams prior to Construction 共AISC兲 design guidelines 共AISC 2005a,b兲. To maxi-
hinge formation at the base of the wall piers 共Aktan and Bertero mize energy dissipation, shear critical behavior is obtained by
1981, 1984; Aristizabal-Ochoa 1982; Fintel and Ghosh 1982; ensuring that the length of the beam is limited to some factor
Park and Paulay 1975兲. Therefore, formation of hinges in the greater than one times the ratio of the beam’s plastic moment
beams is critical. Steel beams have been shown to have outstand- capacity to the beam’s plastic shear capacity.
ing energy dissipation, provide tremendous lateral stiffness to the Critical to the behavior of the steel beam is performance of the
coupled core wall 共CCW兲 system, and exhibit stable hysteretic beam’s connection to the wall piers. The connection is achieved
response 共Fortney 2005; Gong and Shahrooz 2001a,b; Harries by embedding the beam into the wall pier. Past research has
2001; Harries et al. 2000兲. Further, certainty that plastic hinge developed recommendations for the embedment length and the
formation in the beams as the limit state governing behavior is detailing of the beam along its embedded region 共Gong and
significantly greater relative to the more common reinforced con- Shahrooz 2001a,b; Harries et al. 1993, 1995; Shahrooz et al.
crete coupling beams 共diagonally reinforced concrete beams兲. Ad- 1992, 1993兲. To improve distribution of stresses over the embed-
ditionally, the well-known construction difficulties associated ded portion of the beam, auxiliary transfer bars may be connected
with the placement of diagonal bar groups 共and the required trans- to flanges via half couplers welded to the top and bottom flanges
verse reinforcement兲 in diagonally reinforced concrete coupling of the beam. To improve ductility and minimize degradation of
the connection, face bearing plates 共web stiffeners兲 mobilizing
1 internal compression struts can be provided over the embedded
Assistant Professor, Dept. of Civil Engineering, Clemson Univ., 110
Lowry Hall, Clemson, SC 29634. region located within the wall pier’s boundary elements. Pooling
2
Professor, Dept. of Civil and Environmental Engineering, Univ. of the past research shows that steel coupling beams 共SCB兲 provide
Cincinnati, P.O. Box 210071, Cincinnati, OH 45221. outstanding strength, stiffness, and ductility, and simultaneously
3
Assistant Professor, Dept. of Civil and Environmental Engineering, demonstrating appreciable energy dissipation. However, although
Univ. of Cincinnati, P.O. Box 210071, Cincinnati, OH 45221. the performance of the SCB is outstanding for resisting seismic
Note. Associate Editor: James S. Davidson. Discussion open until loads, significant damage to the beam through inelastic deforma-
May 1, 2008. Separate discussions must be submitted for individual pa- tions can lead to very costly postevent repair.
pers. To extend the closing date by one month, a written request must be
The writers combined the recommendations of past studies
filed with the ASCE Managing Editor. The manuscript for this paper was
submitted for review and possible publication on June 14, 2006; approved and performed large-scale reverse cyclic testing of a wall pier–
on April 9, 2007. This paper is part of the Journal of Structural Engi- coupling beam subassembly fitted with a SCB designed based on
neering, Vol. 133, No. 12, December 1, 2007. ©ASCE, ISSN 0733-9445/ these guidelines. To further enhance the advantages of the steel
2007/12-1801–1807/$25.00. coupling beam, design methodologies have been developed for

JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007 / 1801

J. Struct. Eng. 2007.133:1801-1807.


beam; t f ⫽thickness of the flange; and tw⫽thickness of the web.
Substituting Eqs. 共2兲 and 共3兲 into Eq. 共1兲, a trial section can be
established using
关共h − 2t f 兲tw兴/Zx 艋 1.6/共0.6L兲 共4兲
Note that in Eq. 共4兲, the yield strengths of the flange and web
Fig. 1. Schematic drawing of fuse coupling beam
material are assumed to be the same. To prevent local flange and
web buckling, flange and web aspect ratios are limited, respec-
tively, by
the next generation of steel coupling beams that maintain their
outstanding performance while providing an additional feature b f /2t f 艋 0.31冑Es/Fyf 共5兲
consisting of a central “fuse” in which all inelastic deformations
and damage are concentrated. Subsequent to a seismic event, the h/tw 艋 3.05冑Es/Fyf 共6兲
damaged fuse is replaced avoiding the need for replacing or re-
Once the cross-sectional design is completed, all appropriate
Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

pairing the portions of the steel beam embedded in the wall piers.
strength checks have been made, and the size and quantity of
The embedded regions are intended to remain elastic, whereas the
intermediate web stiffeners have been determined, the length of
fuse reaches ultimate loads.
the embedment into the wall pier 共le兲 is determined using 共Gong
The fuse coupling beam 共FCB兲 design philosophy assumes
and Shahrooz 2001a,b兲
that all inelastic deformations will be concentrated in the middle
section 共fuse section兲 of the beam where a length of beam is Vu = f b␤1b f le关共0.58 − 0.22␤1兲兴/关0.88 + 共a/le兲兴 共7兲
connected to the outer sections 共main sections兲 of steel beams via
slip critical bolted connections. Fig. 1 shows a representative f b = 4.05冑 f ⬘c 共twall/b f 兲0.66 共8兲
sketch of a fuse steel coupling beam. The outer beam sections are
embedded in the wall piers using the same design methodologies In Eq. 共7兲, f b⫽stress over the embedded region of the beam
as those used for the typical SCB. However, the fuse section is 关see Eq. 共8兲兴, ␤1⫽factor relating depth of the equivalent rectan-
designed to have a shear capacity equal to the design shear, and gular stress block to neutral axis depth; b f ⫽width of the flange of
the outer sections are then sized such that their shear capacity is the beam; and a⫽one-half of the clear span of the beam. Vu
sufficiently greater than that of the fuse. This methodology will should be taken as 1.5 times the nominal shear capacity of the
ensure that the outer sections remain elastic through the inelastic beam to account for strain hardening and material overstrength. In
range of the fuse section, including development of its ultimate Eq. 共8兲, twall⫽thickness of the wall in which the steel beam is
capacity. In order to prevent damage to the interior ends of the embedded and f ⬘c ⫽specified compressive strength 共MPa兲 of the
outer sections, where the slip-critical connections are located, the concrete in the embedded region.
flange and web splice plates are sized such that the moment of A pair of stiffener plates 共on both sides of the web兲 placed
inertia of a cross section at the splice location is greater than or along the embedment length will mobilize compression struts in
equal to the moment of inertia of the outer section. A sufficient the connection region. These stiffener plates are commonly re-
size and quantity of bolts at the slip-critical connection are pro- ferred to as face-bearing plates. The first face-bearing plate should
vided such that the connection is robust enough to transfer the be directly outside of the confined core of wall boundary element
forces computed at the splice location. if present, or at the face of the wall. The distance between the
plates should be such that the angle of the compression struts is
approximately 45° 共hence, the distance between the plates should
Background be about equal to the clear distance between the flanges兲. To
ensure adequate contribution of face-bearing plates, the width of
Per the Seismic Provisions for Structural Steel Buildings 共AISC each face bearing plate should be equal to the flange width on
2005b, Sec. 15.3b兲, when the length of a steel link is less than or either side of the web. Thickness of the face bearing plates can be
equal to that given by the following equation, intermediate web established based on available guidelines for detailing of shear
stiffeners shall be provided at intervals not exceeding 30tw − d / 5 links in eccentrically braced frames 共AISC 2005a兲. “Auxiliary
共tw⫽thickness of the link’s web and d⫽height of the link’s web兲 transfer bars” should be used to facilitate transfer of bearing
when the link rotation angle 共LRA兲 is expected to be equal to or stresses from the flanges to the surrounding concrete, and to allow
greater than 0.08 rad, or 52tw − d / 5, when the LRA is expected to for a more symmetric distribution of strength and stiffness under
be 0.02 rad or less load reversal due to transfer of tension at the flange concrete
interface, thereby limiting separation of flange and concrete.
L 艋 共1.6M p兲/V p 共1兲 These bars may be connected to the flanges through mechanical
half-couplers that are welded to the top and bottom flanges. To
minimize the length of the auxiliary transfer bars while achieving
M p = F yZx 共2兲 sufficient development length, terminator blocks may be used at
the end of each transfer bar. Fig. 2 shows a representative detail.
V p = 0.6Fy共h − 2t f 兲tw 共3兲
Linear interpolation is permitted when the expected LRA is Research Objective
between 0.02 and 0.08 rad. In Eq. 共1兲, M p⫽calculated plastic mo-
ment capacity of the link and V p⫽calculated plastic shear capac- The objective of the research project presented in this paper was
ity of the link. In Eq. 共2兲, Fy⫽yield strength of the steel and to enhance features of steel coupling beams by providing post-
Zx⫽plastic section modulus. In Eq. 共3兲, h⫽total height of the damage replacement capabilities without costly repair of the wall

1802 / JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007

J. Struct. Eng. 2007.133:1801-1807.


Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 2. Example of use of face-bearing plates and auxiliary transfer


bars
Fig. 3. South elevation of test setup with a specimen installed

pier/coupling beam connections. This objective was achieved by


designing the beam such that all of the inelastic damage would be protocol of FCB-2 was to load up to a point where the fuse
concentrated in the middle portion of the beam where a fuse yielded, whereas the outer sections remained elastic. At this point,
section would be located as previously described. Subsequent to a the loading was stopped, and the damaged fuse replaced with a
seismic event, the damaged fuse could be replaced. new fuse 共FCB-1兲 which had a shear capacity of 70% of the outer
beam sections. Upon replacing the fuse, testing recommenced and
continued until failure.
Experimental Setup and Specimen Design The target shear capacity for both specimens was taken as
534 kN, which is assumed to approximate the maximum design
shear demand for a practical CCW system 共i.e., beam span-to-
Test Setup and Loading
depth ratio between 2.5 and 3.5, and 50 and 65% degree of cou-
A specimen consisting of two wall pier segments connected with pling兲. As the shear capacities of the FCB-2 fuse and the FCB-1
a single coupling beam is used 共see Fig. 2兲. To simulate the fuse was taken as 50 and 70%, respectively, of the outer sections,
double curvature expected in a coupling beam, one of the subas- the target shear capacities of the FCB-2 and FCB-1 fuses were
sembly’s wall piers 共fixed wall兲 was connected to a reinforced 267 and 374 kN, respectively. It should be noted that the fuse
concrete pedestal 共posttensioned to the laboratory’s strong floor兲 capacities of 50 and 70% of the main sections were arbitrarily
by means of tensioned rods threaded into the pedestal. The other chosen based on engineering judgment as no previous data exists
wall pier 共load wall兲 and coupling beam were cantilevered from for this new beam concept.
the pedestal beneath the cross beam of a steel load frame. All beams had a clear span equal to 914 mm, a flange width of
Clamped atop the load wall pier was a very stiff I-shape beam 127 mm, and a depth of 356 mm. The reinforcement used in the
共load beam兲 used to transfer applied actuator load to the load wall piers was the same for both specimens. The specified mate-
wall. To prevent load wall rotation, the load beam extended be- rial strengths used for design of the specimens was also the same
neath the cross beam of a second load frame and connected to a for all specimens. Grade 60 steel 共Fy = 414 MPa兲 was used for all
secondary actuator used to stabilize the system and prevent in- reinforcing bars, the specified strength of the concrete was
plane rotation of the load wall. Fig. 3 shows a photograph of the 35 MPa, and the steel plate material used to fabricate the built-up
test apparatus with a test subassembly installed. I-shape coupling beams was A36 steel 共Fy = 248 MPa兲.
The test specimens were similarly loaded with sets of increas-
ing amplitudes of force or displacement in a reverse cyclic fash-
SCB Design
ion. Each set of cycles was followed by one cycle of decreased
amplitude to capture stiffness degradation. A representative plot The SCB specimen was designed and detailed following the de-
of the loading history incorporated during testing is shown in Fig. sign methodology discussed previously 关Eqs. 共1兲–共4兲兴. As rolled
3. To capture critical responses during loading, a sufficient num- I-shapes are less likely to have the required cross-sectional prop-
ber of strain gages, displacement transducers, and rotation meters erties needed in coupling beams, a built-up I-shape was designed
were installed. using A36 steel plate material 共Fy = 248 MPa兲 with the following
dimensions: t f = 25.4 mm, b f = 127 mm, and tw = 12 mm and an
overall height, d = 356 mm. The calculated shear capacity, V p, of
Experimental Specimens
the SCB, using measured material strengths 共see Tables 1 and 2兲,
A SCB was designed based on past recommendations. The test is 578 kN. Fig. 4共a兲 shows the cross-sectional geometry of the
results were then compared and contrasted to the results of a steel SCB specimen.
coupling beam fitted with a central fuse 共as described previously兲. The embedment length was determined using Eq. 共7兲 and tak-
To evaluate the feasibility of fuse replacement, two different fuses ing Vu to be equal to 1.25 times the calculated plastic shear
were tested. strength of 578 kN; as the plastic shear strength equal to 578 kN
The first fuse coupling beam 共FCB-2兲 utilized a fuse with a was computed using measured material strength, Vu for comput-
shear capacity of 50% of that of the outer beam sections. The test ing embedment length is multiplied only by 1.25 in lieu of 1.5 to

JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007 / 1803

J. Struct. Eng. 2007.133:1801-1807.


Table 1. Measured Steel Material Properties Table 2. Concrete Strength at the Time of Each Test
Fv Specimen Compressive strength
Component description 共MPa兲 name 共MPa兲
FCB-2—fuse web 243 SCB 35.4
FCB-2—fuse flange 305 FCB 36.5
FCB-1—fuse web 264
SPCB—web plate 294
SCB, FCB-1—main section web 245 ensure that the splice connection can transfer at least a shear force
SCB, FCB-1, FCB-2—main section flange 277 equal to the shear capacity of the main section 共V p = 578 kN兲, the
web splice plates 共one on each side of the web兲 were assumed to
have the same thickness as the main section web thickness, and
account for strain hardening. The required embedment length was the height of the web splice plates was sized to ensure clearance
determined to be 775 mm. As recommended by past research of the weld root. Clearances between the top and bottom edges of
共Gong and Shahrooz 2001a,b兲, face-bearing plates and auxiliary the web splice plate and the flanges of the beam were taken as
Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

transfer bars were incorporated along the embedded regions of 25 mm. Hence, twsp = 12 mm and hwsp = d-50 mm= 305-50
the beam. Details of the SCB specimen are shown in elevation in = 255 mm. A check was then performed to ensure that Isp
Fig. 5. 艌 Imain section. The splice connection is shown in Fig. 6共d兲. Refer-
ring to Fig. 6共d兲, the moment of inertia of the splice connection,
Isp = 269,176,863 mm4 ⬎ Imain section = 206,159,425 mm4. There-
FCB Design fore, the splice plate sizes are adequate.
The outer sections of the FCB and their embedment length into The design shear for the connection was 578 kN 共the shear
the wall piers were designed like that of the SCB. The main-fuse capacity of the outer section using measured yield strength兲 and
connection was designed as slip critical, and the web and flange each bolt will be in double shear. The design was based on
splice connections were designed to transfer the shear and mo- 25.4 mm diameter A490X bolts. In order to minimize the number
ment calculated at the location of the splice. of required bolts, a mean slip coefficient equal to 0.33 was as-
The design procedure for the fuse section is relatively straight- sumed. Per AISC, Section J6, the shear capacity of a single
forward. The top and bottom flanges were designed to be the 25.4 mm diameter bolt was calculated to be
same size as that of the main sections. Thus, the flanges of both
␾ f rst = 1.13␮TbNs = 共1.0兲共1.13兲共0.33兲共284 kN兲共2兲 = 212.3 kN
fuses had b f = 127 mm and t f = 25.4 mm. The overall height of the
beam was the same 共h = 356 mm兲. The only section dimension Therefore, the number of bolts required was 578 kN/
needed is the value of tw. As h = 356 mm and t f = 25.4 mm⫽same 共212.3 kN/ bolt兲 = 2.7 bolts. Three 25.4 mm 共1 in.兲 diameter bolts
for all the sections, the web thickness of the fuse, tw, is simply on each side of the web splice connection were provided. The
proportional to the percentage of the design shear strength of the design moment at the end of the beam is 244 kN m. The same
main section. Hence, tw = 共0.5兲共12 mm兲 = 6 mm for the 50% fuse size bolts used for the web splice plates were used to transfer the
and tw = 共0.7兲共12 mm兲 = 8.4 mm for the 70% fuse. The final step total flange force developed at the location of the flange splice
involves the design of the slip-critical main/fuse connections. plates. Assuming that two rows of bolts are required and that the
To simplify the design of the flange and web splice plates, the length of the fuse must be at least 356 mm long to allow room for
flange splice plates were assumed be the same size as the flanges the splice plates, the splice was located 191 mm from the point of
of the main section. Hence, tfsp = 25.4 mm and bfsp = 127 mm. To zero moment 共at midspan of the beam兲. Therefore, the moment to

Fig. 4. Beam cross sections 共a兲 SCB and main section of FCB; 共b兲 fuse section of FCB-1 and FCB-2

1804 / JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007

J. Struct. Eng. 2007.133:1801-1807.


Experimental Results

Steel Coupling Beam


The SCB sustained 11% chord rotation with no appreciable dam-
age. Cyclic loading was applied only up to 4% due to concerns
for load frame stability 共after this test, lateral braces were added
to the test apparatus兲. The test was finished with monotonic load-
ing up to 11% rotation 关Fig. 7共a兲兴. The shear forces plotted on the
vertical axis in Fig. 7 have been normalized by dividing the ap-
plied shear force by V P 共calculated shear capacity using measured
material properties兲. As can be inferred from the shear versus
chord rotation diagram in Fig. 7共a兲, the SCB demonstrates stable
Fig. 5. Elevation of SCB specimen 共mm兲
postelastic hysteretic response and excellent energy dissipation.
Using experimentally measured strains, Vyield was established as
Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

the shear force causing first shear yielding in the web. The ratio of
be resisted at the splice, M SP, is Vyield to V P was 0.98 indicating that the design methodology used
M SP = 关共191 mm兲共244 kN m兲兴 / 共914 mm/ 2兲 = 102 kN m and the for the SCB correlates very well with the experimentally mea-
total flange force that the bolts must transfer is sured shear capacity. Further, as can be seen in Figs. 8共a and b兲,

冋 冉 冊 册冒
Pfsp = M SP
h
2
bftf Imain section
the SCB exhibits very good stiffness and energy-dissipation
characteristics.

Fuse Coupling Beam


Pfsp = 关共102 kN m/共1 m/1,000 mm兲兲共共127 mm兲
The 50% fuse 共FCB-2兲 was tested up to 2% rotation at which
⫻共25.4 mm兲兲兴/206,159,425 mm4 = 284 kN
point the fuse had reached approximately two times its calculated
The flange splice bolts were in single shear and therefore have a shear capacity while the main sections 共outer sections兲 had
capacity equal to half of that calculated for the web splice plate reached approximately 96% of their calculated shear capacity
bolts 共the same size bolts are assumed兲. The capacity of one bolt 关Fig. 7共b兲兴. In Fig. 7共b兲, the normalized shear plotted on the ver-
in single shear is ␾rst = 共212.3 kN/ bolt/ 2 = 106.2 kN/ bolt兲. The tical axis is the applied shear force divided by the calculated shear
number of bolts needed to transfer the force in the flange was capacity 共using measured material properties兲. As discussed pre-
284 kN/ 共106.2 kN/ bolt兲 = 2.7 bolts. In the interest of having a viously, the FCB-2 test was stopped at 2% chord rotation, the
symmetric bolt pattern, four 25 mm diameter A490X bolts were loaded wall of the specimen was returned to zero force, and the
provided on each side of the flange splice plates. FCB-2 fuse was replaced with the FCB-1 fuse. Upon bringing the
The spacing of the bolts was determined based on minimum FCB-2 test specimen to zero force, there was approximately
distances required for entering and tightening. Bolt bearing and 3.6 mm of residual vertical displacement which presented no dif-
block shear were not considered. This decision is considered to be ficulty in the replacement of the fuse. The bolts in the splice
reasonable considering that for bolt bearing or block shear to connections were easily removed using a standard commercial
occur, the connection must slip. If slipping occurs, the intended electric torque wrench. The replacement fuse 共FCB-1兲 and shim
behavior of the beam will not be achieved. plates were installed, and the bolts were tensioned to the desired
Additionally, allowances were made for shim plates at the web level. Two of the writers replaced the fuse in approximately 3 h.
splices between the web of the fuse and the web splice plate to With the 70% fuse in place, test FCB-1 was started and con-
make up for the difference in the web thicknesses of the main and tinued up to 11% rotation 关see Fig. 9共a兲兴 at which point the beam
fuse sections. The same connections were used for both of the was considered to have failed completely and the testing was
fuse beam tests. However, due to the difference in the web thick- stopped. This specimen reached a maximum peak shear of
nesses between the 50 and 70% fuses, the thickness of the shim 816 kN. The beam behaved as intended up to 4% rotation at
plates are different. Fig. 6 illustrates details of the final beam which point, slippage of the web splice connections was observed
designs. 关see Fig. 9共b兲兴. As loading continued, weld cracks formed at the
flange–web interface in the main sections 关see Fig. 9共c兲兴 and con-
tinually increased in severity for the remainder of the test. At the
Subassembly Design
end of the test, weld failures, block shear failure, and bolt bearing
The wall piers for the test specimens were designed to resist the failure were observed 关Fig. 9共d兲兴. It should be noted that block
axial loads that were imparted to the walls by the clamping forces shear and bolt bearing failure were not observed until well into
needed to attach the fixed wall to the pedestal and to transfer the the 8% rotation cycles. A detailed damage record is available in
forces in the load beam to the load wall 共see Fig. 3兲. The required Fortney 共2005兲.
clamping forces applied to the walls were determined based on The early plastic energy dissipation of the FCB 关shown in Fig.
the expected capacities of the coupling beams. The clamping 8共b兲兴, relative to the SCB can be attributed to the lower plastic
loads on the fixed and load wall piers resulted in axial forces of shear capacity of the fuse relative to the SCB 关Fig. 8共a兲兴. The
0.25f ⬘c Ag and 0.34f ⬘c Ag, respectively. The wall pier reinforcement effects of lower shear capacity and hence earlier yielding in the
consisted of two curtains of #4 共db = 12.7 mm兲 bars at 203 mm FCB are also evident in lower stiffness of the FCB in comparison
intervals. See Fortney 共2005兲 for detailed discussion on the design to the SCB, as shown in Fig. 8共a兲. At 4% chord rotation, the
of the wall piers. Figs. 5 and 6 show the elevations of the final plastic energy dissipation characteristics of the two specimens are
SCB and FCB subassemblies, respectively. the same 关Fig. 8共b兲兴.

JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007 / 1805

J. Struct. Eng. 2007.133:1801-1807.


Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 6. 共a兲 Elevation, enlarged; 共b兲 top view; 共c兲 elevation; and 共d兲 cross sections of FCB specimen

Conclusions in coupled core wall systems, particularly those at floors where


coupling beam demands are the highest. Nevertheless, very little
The SCB performed very well demonstrating that the design rec- damage was observed at the coupling beam–wall pier interfaces,
ommendations formulated from previous research can lead into suggesting that the auxiliary transfer bars, face-bearing plates,
steel coupling beams with adequate performance. The necessary and computed embedment length would result in sufficiently duc-
wall clamping forces were somewhat larger than those expected tile coupling beam–wall pier connections.
The design of the FCB specimen involved using main section
properties identical to those of the SCB, and using smaller web

Fig. 7. Normalized shear force versus shear angle 共applied shear


force normalized to calculated plastic shear capacity兲 Fig. 8. Stiffness and energy dissipation

1806 / JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007

J. Struct. Eng. 2007.133:1801-1807.


and hybrid structures. Any opinions, findings, and conclusions or
recommendations expressed in this paper are of those of the writ-
ers and do not necessarily reflect the views of the sponsors.

References

Aktan, A. E., and Bertero, V. V. 共1981兲. “The Seismic resistant design of


R/C coupled shear walls.” Rep. No. UCB/EERC-81/07, Earthquake
Engineering Research Center, Univ. of California, Berkeley, Calif.
Aktan, A. E., and Bertero, V. V. 共1984兲. “Seismic response of R/C frame-
wall structures.” J. Struct. Eng., 110共ST8兲, 1803–1821.
American Institute of Steel Construction AISC. 共2005a兲. Manual of steel
construction, 13th Ed., Chicago.
American Institute of Steel Construction AISC. 共2005b兲. Seismic provi-
Downloaded from ascelibrary.org by Vit University on 06/02/15. Copyright ASCE. For personal use only; all rights reserved.

sions for structural steel buildings, supplement to AISC Manual of


Steel Construction, 13th Ed., Chicago.
Aristizabal-Ochoa, J. D. 共1982兲. “Dynamic response of coupled wall sys-
tem.” J. Struct. Div., 108共ST8兲, 1846–1857.
Fintel, M., and Ghosh, S. 共1982兲. “Case study of a seismic design of a
Fig. 9. FCB-1 specimen 16-story coupled wall using inelastic dynamic analysis.” ACI Struct.
J., 79共3兲, 171–179.
Fortney, P. J. 共2005兲. “The next generation of coupling beams.” Disser-
thickness for the fuse to develop smaller shear capacities 共due to
tation, Univ. of Cincinnati, Cincinnati.
limitations of the test setup, fuse shear capacity could not be
Gong, B., and Shahrooz, B. M. 共2001a兲. “Concrete-steel composite cou-
increased relative to the main beams兲. This approach led to early pling beams. I: Component testing.” J. Struct. Eng., 127共6兲, 625–631.
energy dissipation and lower stiffness relative to the SCB. In Gong, B., and Shahrooz, B. M. 共2001b兲. “Concrete-steel composite cou-
actual practice, the writers recommend that the fuse be designed pling beams. II: Subassembly testing and design verification.” J.
for ultimate loads and then the main section properties be in- Struct. Eng., 127共6兲, 632–638.
creased relative to the fuse. This should ensure that the system has Harries, K. A. 共2001兲. “Ductility and deformability of coupling beams in
ultimate shear capacities at least equal to or greater than the an- reinforced concrete coupled walls.” Earthquake Spectra, 17共3兲, 457–
ticipated shear demands without compromising the overall phi- 478.
losophy of the design. Harries, K. A., Cook, W. D., Mitchell, D., and Redwood, R. G. 共1995兲.
Additionally, the fillet welds used in the built-up I-sections had “The use of steel beams to couple concrete walls.” Proc., 7th Cana-
been terminated at the ends of the beam sections. It is the opinion dian Conf. on Earthquake Engineering, Montreal, 509–516.
of the writers that this led to the onset of the fillet weld failures. It Harries, K. A., Gong, B., and Shahrooz, B. M. 共2000兲. “Behavior and
design of reinforced concrete, steel, and steel-concrete coupling
should be noted that weld fractures were observed after success-
beams.” Earthquake Spectra, 16共4兲, 775–799.
fully reaching 5% chord rotation. Providing end returns at the Harries, K. A., Mitchell, D., Cook, W. D., and Redwood, R. G. 共1993兲.
ends of the beam, thereby creating continuous welds, might have “Seismic response of steel beams coupling concrete walls.” J. Struct.
delayed the formation and propagation of the weld fractures at Eng., 119共12兲, 3611–3629.
very large chord rotations, and eliminated potential end effects Kasai, K., and Popov, E. P. 共1986兲. “A study of seismically resistant
associated with terminated fillet welds. Moreover, providing par- eccentrically braced frames.” Rep. No. UCB/EERC-86/01, Earthquake
tial or full penetration groove welds in lieu of fillet welds may Engineering Research Center, Univ. of California, Berkeley, Calif.
minimize the potential for weld fracture and further enhance the Malley, J. O., and Popov, E. P. 共1986兲. “Design of links and beam to
overall ductility of coupling beams with a central fuse. Additional column connections for eccentrically braced frames.” Rep. No. UCB/
research is recommended to evaluate potential improvements in EERC-83/03, Earthquake Engineering Research Center, Univ. of Cali-
fornia, Berkeley, Calif.
ductility and overall performance offered by more robust welded
Park, R., and Paulay, T. 共1975兲. Reinforced concrete structures, Wiley,
flange-to-web connection details.
New York.
Roeder, C. W., and Popov, E. P. 共1978兲. “Eccentrically braced steel
frames for earthquakes.” J. Struct. Div., 104共3兲, 391–412.
Acknowledgments Shahrooz, B. M., Remmetter, M. E., and Qin, F. 共1992兲. “Seismic re-
sponse of composite coupled structural walls.” Proc., Int. Conf. on
The reported research is sponsored by the National Science Foun- Concrete, 465–481.
dation under Grant No. BCS-CMS-9714860, with Dr. Shih Chi Shahrooz, B. M., Remmetter, M. E., and Qin, F. 共1993兲. “Seismic design
Liu as the program director. These projects were part of the fifth and performance of composite coupled walls.” J. Struct. Eng.,
phase of U.S.–Japan cooperative research program on composite 119共11兲, 2858–2896.

JOURNAL OF STRUCTURAL ENGINEERING © ASCE / DECEMBER 2007 / 1807

J. Struct. Eng. 2007.133:1801-1807.

Potrebbero piacerti anche