VISUAL INSPECTION REPORT

Customer : PT Pupuk Indonesia Energi Report No. : 01/VIR/MP/IV/17


Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 2" - BFW - 4SSB - 002 - H45 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 Sheet 1 of 9
PLMB - 160346 - 43 - DWG - 40S
1 J-1 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 #6000
PLMB - 160346 - 43 - DWG - #6000
2 J-2 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S
PLMB - 160346 - 43 - DWG - 40S
3 J-3 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S
PLMB - 160346 - 43 - DWG - 40S
4 002 Sheet 1 of 9 J-4 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
40S
PLMB - 160346 - 43 - DWG - 40S
5 J-5 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 #1500
PLMB - 160346 - 43 - DWG - #1500
6 J-6 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S
PLMB - 160346 - 43 - DWG - 40S
7 J-7 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 #6000
PLMB - 160346 - 43 - DWG - #6000
8 J-8 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S
PLMB - 160346 - 43 - DWG - 40S
9 J-9 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 #6000
PLMB - 160346 - 43 - DWG - #6000
10 J-10 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S
PLMB - 160346 - 43 - DWG - 40S
11 J-11 1/MB/GTAW/X/06 GTAW W.07 23-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 #900
PLMB - 160346 - 43 - DWG - 40S
12 J-12 1/MB/GTAW/X/06 GTAW W.07 23-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 #900
PLMB - 160346 - 43 - DWG - #900
13 J-13 1/MB/GTAW/X/06 GTAW W.07 23-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S
PLMB - 160346 - 43 - DWG - #900
14 J-14 1/MB/GTAW/X/06 GTAW W.07 23-Feb-17 2 GTAW ACC
002 Sheet 1 of 9 40S

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 02/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 2" - BFW - 4SSB - 002 - H45 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 Sheet 2 of 9
PLMB - 160346 - 43 - DWG - 2"
1 J-1 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 2"
PLMB - 160346 - 43 - DWG - 2"
2 J-2 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 2" X 3/4"
PLMB - 160346 - 43 - DWG - 2" X 3/4"
3 J-3 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 3/4"
PLMB - 160346 - 43 - DWG - 3/4"
4 002 Sheet 2 of 9 J-4 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
3/4"
PLMB - 160346 - 43 - DWG - 2"
5 J-5 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 2" X 1"
PLMB - 160346 - 43 - DWG - 2" X 1"
6 J-6 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 1"
PLMB - 160346 - 43 - DWG - 2" X 1"
7 J-7 1/MB/GTAW/X/06 GTAW W.07 24-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 1"
PLMB - 160346 - 43 - DWG - 2" X 1"
8 J-8 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 2"
PLMB - 160346 - 43 - DWG - 2"
9 J-9 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 2" X 3/4"
PLMB - 160346 - 43 - DWG - 2" X 3/4"
10 J-10 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 3/4"
PLMB - 160346 - 43 - DWG - 3/4"
11 J-11 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 3/4"
PLMB - 160346 - 43 - DWG - 2"
12 J-12 1/MB/GTAW/X/06 GTAW W.07 25-Feb-17 2 GTAW ACC
002 Sheet 2 of 9 2"

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 03/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 2" - BFW - 4SSB - 002 - H45 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 3 OF 9
PLMB - 160346 - 43 - DWG - 2"
1 J-1 1/MB/GTAW/X/06 GTAW W.06 22-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"
PLMB - 160346 - 43 - DWG - 2"
2 J-2 1/MB/GTAW/X/06 GTAW W.06 18-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"
PLMB - 160346 - 43 - DWG - 2"
3 J-3 1/MB/GTAW/X/06 GTAW W.06 18-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"
PLMB - 160346 - 43 - DWG - 2"
4 002 SHEET 3 OF 9 J-4 1/MB/GTAW/X/06 GTAW W.06 18-Feb-17 2 GTAW ACC
2"
PLMB - 160346 - 43 - DWG - 2"
5 J-5 1/MB/GTAW/X/06 GTAW W.06 20-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"
PLMB - 160346 - 43 - DWG - 2"
6 J-6 1/MB/GTAW/X/06 GTAW W.06 20-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"
PLMB - 160346 - 43 - DWG - 2"
7 J-7 1/MB/GTAW/X/06 GTAW W.06 16-Mar-17 2 GTAW ACC
002 SHEET 3 OF 9 2" X 3/4"
PLMB - 160346 - 43 - DWG - 2" X 3/4"
8 J-8 1/MB/GTAW/X/06 GTAW W.06 16-Mar-17 2 GTAW ACC
002 SHEET 3 OF 9 3/4"
PLMB - 160346 - 43 - DWG - 3/4"
9 J-9 1/MB/GTAW/X/06 GTAW W.06 16-Mar-17 2 GTAW ACC
002 SHEET 3 OF 9 3/4"
PLMB - 160346 - 43 - DWG - 2"
10 J-10 1/MB/GTAW/X/06 GTAW W.06 20-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"
PLMB - 160346 - 43 - DWG - 2"
11 J-11 1/MB/GTAW/X/06 GTAW W.06 21-Feb-17 2 GTAW ACC
002 SHEET 3 OF 9 2"

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 04/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 14" - MPS - 3A - 003 - H - 135 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 4 OF 9
PLMB - 160346 - 43 - DWG - 19/MB/GTAW/IV/0 80
1 J-1 GTAW W.06 20-Feb-17 2 GTAW ACC
002 SHEET 4 OF 9 8 80S
PLMB - 160346 - 43 - DWG - 80S
2 J--2 1/MB/GTAW/X/06 GTAW W.06 20-Feb-17 2 GTAW ACC
002 SHEET 4 OF 9 80S
PLMB - 160346 - 43 - DWG - 80S
3 J-3 1/MB/GTAW/X/06 GTAW W.06 11-Apr-17 2 GTAW ACC
002 SHEET 4 OF 9 80S
PLMB - 160346 - 43 - DWG - 6 mm
4 002 SHEET 4 OF 9 J-3A 1/MB/GTAW/X/06 GTAW W.06 11-Apr-17 2 GTAW ACC
80S
PLMB - 160346 - 43 - DWG - 80S
5 J-4 1/MB/GTAW/X/06 GTAW W.06 8-Apr-17 2 GTAW ACC
002 SHEET 4 OF 9 #600

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 05/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 14" - MPS - 3A - 003 - H - 135 DRAWING NO : PLMB - 160346 GTAW
- 43 - DWG - 002 SHEET 5 OF 9
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 W.07 80
1 J-1 16-Feb-17 2 GMAW ACC
002 SHEET 5 OF 9 20/MB/GMAW/IV/08 GTAW GMAW W.30 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 W.07 80
2 J-2 17-Feb-17 2 GMAW ACC
002 SHEET 5 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
PLMB - 160346 - 43 - DWG - 80
3 J-3 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 GTAW #3000
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 W.07 80
4 J-4 17-Feb-17 2 GMAW ACC
002 SHEET 5 OF 9 20/MB/GMAW/IV/08 GTAW GMAW W.30 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 W.07 80
5 J-5 16-Feb-17 2 GTAW ACC
002 SHEET 5 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 80
6 002 SHEET 5 OF 9 J-6 W.30 16-Feb-17 2 GMAW ACC
20/MB/GMAW/IV/08 GMAW #600
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 #600
7 J-7 16-Feb-17 2 GMAW ACC
002 SHEET 5 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
PLMB - 160346 - 43 - DWG - 80
8 J-8 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
9 J-9 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 40
40
10 PLMB - 160346 - 43 - DWG - J-10 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 #1500
PLMB - 160346 - 43 - DWG - #1500
11 J-11 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 40
40
12 PLMB - 160346 - 43 - DWG - J-12 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
13 J-13 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 40
PLMB - 160346 - 43 - DWG - 40
14 J-14 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
15 J-15 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 40
40
16 PLMB - 160346 - 43 - DWG - J-12 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
17 002 SHEET 5 OF 9 J-13 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
40
PLMB - 160346 - 43 - DWG - 80
18 J-8 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 5 OF 9 #3000
Prepared By Reviewed / Witnessed by Reviewed / Witnessed by
VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 05/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 05/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 14" - MPS - 3A - 003 - H - 135 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 6 OF 9
40
16 PLMB - 160346 - 43 - DWG - J-16 15/MB/GT- GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 SM/VIII/07 #3000
PLMB - 160346 - 43 - DWG - 15/MB/GT- #3000
17 J-17 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 SM/VIII/07 40
PLMB - 160346 - 43 - DWG - 15/MB/GT- 40
18 J-18 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 SM/VIII/07 #3000

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 05/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 06/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 14" - MPS - 3A - 003 - H - 135 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 6 OF 9
15/MB/GT-SM/VIII/07 GTAW 14"
1 PLMB - 160346 - 43 - DWG - J-1 W.07 13-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 GMAW W.30 14"
PLMB - 160346 - 43 - DWG - 14"
2 J-2 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 14" x 1"
PLMB - 160346 - 43 - DWG - 14"
3 002 SHEET 6 OF 9 J-3 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
14"x1"
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 14"
4 J-4 13-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 14"x10"
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 14"x10"
5 J-5 13-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 14"
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 10"
6 J-6 14-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 10"
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 10"
7 J-7 14-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 10"
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 14"x10"
8 J-8 13-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 14"
GMAW
15/MB/GT-SM/VIII/07 GTAW 14"
9 PLMB - 160346 - 43 - DWG - J-9 W.07 9-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 14"
GMAW
15/MB/GT-SM/VIII/07 GTAW 14"
10 PLMB - 160346 - 43 - DWG - J-10 W.07 9-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.72 14"x10"
GMAW
PLMB - 160346 - 43 - DWG - 14"x10"
11 J-11 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 14"x3/4"
PLMB - 160346 - 43 - DWG - 14"x3/4"
12 J-12 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 3/4"
PLMB - 160346 - 43 - DWG - 3/4"
13 J-13 15/MB/GT-SM/VIII/07 GTAW W.06 4-Mar-17 2 GTAW ACC
002 SHEET 6 OF 9 3/4"
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 14"x10"
14 J-14 9-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 GMAW W.72 10"
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 10"
15 002 SHEET 6 OF 9 J-15 W.30 10-Feb-17 2 GMAW ACC
20/MB/GMAW/IV/08 GMAW 14"x10"
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 14"x10"
16 J-16 10-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 14
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.07 14
17 J-17 10-Feb-17 2 GMAW ACC
002 SHEET 6 OF 9 20/MB/GMAW/IV/08 W.30 14"
GMAW

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 06/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 07/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 14" - MPS - 3A - 003 - H - 135 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 7 OF 9
15/MB/GT-SM/VIII/07 GTAW #600
1 PLMB - 160346 - 43 - DWG - J-1 W.06 13-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
PLMB - 160346 - 43 - DWG - 80
2 J-2 15/MB/GT-SM/VIII/07 GTAW W.06 17-Feb-17 2 GTAW ACC
002 SHEET 7 OF 9 #3000
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
3 002 SHEET 7 OF 9 J-3 W.30 17-Feb-17 2 GMAW ACC
20/MB/GMAW/IV/08 GMAW 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
4 J-4 16-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 #600
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
5 J-5 20-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
6 J-6 13-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
7 J-7 13-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
8 J-8 14-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
15/MB/GT-SM/VIII/07 GTAW 80
9 PLMB - 160346 - 43 - DWG - J-9 W.06 14-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
15/MB/GT-SM/VIII/07 GTAW 80
10 PLMB - 160346 - 43 - DWG - J-10 W.06 14-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
15/MB/GT-SM/VIII/07 GTAW 80
11 PLMB - 160346 - 43 - DWG - J-11 W.06 13-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 GMAW W.72 80
15/MB/GT-SM/VIII/07 GTAW 80
12 PLMB - 160346 - 43 - DWG - J-12 W.06 13-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
PLMB - 160346 - 43 - DWG - 80
13 J-13 15/MB/GT-SM/VIII/07 GTAW W.06 15-Feb-17 2 GTAW ACC
002 SHEET 7 OF 9 #3000
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
14 J-14 9-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
15 002 SHEET 7 OF 9 J-15 W.30 9-Feb-17 2 GMAW ACC
20/MB/GMAW/IV/08 GMAW 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
16 J-16 9-Feb-17 2 GMAW ACC
002 SHEET 7 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 07/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 08/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 14" - MPS - 3A - 003 - H - 135 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 8 OF 9
15/MB/GT-SM/VIII/07 GTAW 80
1 PLMB - 160346 - 43 - DWG - J-1 W.06 9-Feb-17 2 GMAW ACC
002 SHEET 8 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
15/MB/GT-SM/VIII/07 GTAW 80
2 PLMB - 160346 - 43 - DWG - J-2 W.06 9-Feb-17 2 GMAW ACC
002 SHEET 8 OF 9 20/MB/GMAW/IV/08 GMAW W.30 80
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 80
3 002 SHEET 8 OF 9 J-3 W.30 9-Feb-17 2 GMAW ACC
20/MB/GMAW/IV/08 GMAW #600
PLMB - 160346 - 43 - DWG - 15/MB/GT-SM/VIII/07 GTAW W.06 #600
4 J-4 9-Feb-17 2 GMAW ACC
002 SHEET 8 OF 9 20/MB/GMAW/IV/08 W.30 80
GMAW
PLMB - 160346 - 43 - DWG - W.06 80
5 J-5 15/MB/GT-SM/VIII/07 GTAW 9-Feb-17 2 GTAW ACC
002 SHEET 8 OF 9 W.30 #600

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 08/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 09/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 1" - MPS - 3A - 004 - H - 80 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 9 OF 9
PLMB - 160346 - 43 - DWG - 40S
1 J-1 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
2 J-2 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
3 002 SHEET 9 OF 9 J-3 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
#3000
PLMB - 160346 - 43 - DWG - #3000
4 J-4 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
5 J-5 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 #1500
PLMB - 160346 - 43 - DWG - #1500
6 J-6 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
7 J-7 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
8 J-8 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
9 J-9 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
10 J-10 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
11 J-11 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 #1500
PLMB - 160346 - 43 - DWG - #1500
12 J-12 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
13 J-13 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 #1500
PLMB - 160346 - 43 - DWG - #1500
14 J-14 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
15 002 SHEET 9 OF 9 J-15 15/MB/GT-SM/VIII/07 GTAW W.07 W.07 2 GTAW ACC
#3000
Prepared By Reviewed / Witnessed by Reviewed / Witnessed by

Date : Date : Date :


VISUAL INSPECTION REPORT
Customer : PT Pupuk Indonesia Energi Report No. : 09/VIR/LO/IV/17
Project : GRESIK GAS COGENERATION PLANT PROJECT SPPr No. : 160346
Item Name : MP STEAM DESUPERHEATER Refernsi Standard : ASME B 31.3

Welding Welder Welding Check of Completed Weld


NO Drawing No Joint No WPS No. Sch Result Remark
Process Stamp Date Reinforcement Weld Surface
LINE 1" - MPS - 3A - 004 - H - 80 DRAWING NO : PLMB - 160346 - 43 - DWG - 002 SHEET 9 OF 9
#3000
16 PLMB - 160346 - 43 - DWG - J-16 15/MB/GT-SM/VIII/07 GTAW W.07 21-Feb-17 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
17 J-17 15/MB/GT-SM/VIII/07 GTAW W.07 21-Feb-17 2 GTAW ACC
002 SHEET 9 OF 9 #3000
PLMB - 160346 - 43 - DWG - #3000
18 002 SHEET 9 OF 9 J-18 15/MB/GT-SM/VIII/07 GTAW W.07 21-Feb-17 2 GTAW ACC
40S
PLMB - 160346 - 43 - DWG - #3000
19 J-19 15/MB/GT-SM/VIII/07 GTAW W.07 21-Feb-17 2 GTAW ACC
002 SHEET 9 OF 9 40S
PLMB - 160346 - 43 - DWG - 40S
20 J-20 15/MB/GT-SM/VIII/07 GTAW W.07 21-Feb-17 2 GTAW ACC
002 SHEET 9 OF 9 #3000

Prepared By Reviewed / Witnessed by Reviewed / Witnessed by

Date : Date : Date :