Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Paper 0131-
Mojtaba KHEDERZADEH
Shahid Beheshti University, A.C., - IRAN
m_khederzadeh@sbu.ac.ir
SAMPLE SYSTEM SET-UP It is assumed that a severe fault at the upstream grid occurs
and forces the test system to transfer to the autonomous
Figure 1 shows the IEEE 33-bus network single-line mode. A microgrid is formed with the supply resources at
diagram that is used as the test system for simulations. The Bus 9 and Bus 30. The formed microgrid with radial feeders
parameters of the test system such as loads and lines are is not desired from the resiliency point of view. If the formed
found in [7]. Figure 1 is considered as the base case. In autonomous microgrid has only radial feeders, it is likely
order to simulate the proposed method, Distributed that the outage of a unique line may lead to the loss of a
Generators (DGs) are considered and installed on buses 9 large portion of the loads energized by any of the DGs.
and 30. Bus 9 is equipped with fixed-generation supply and Hence, it is preferable to establish different loops in the
Bus 30 is equipped with intermittent generation such as formed microgrid by closing tie-switches in the test system
wind power [6]. Critical loads are assumed at Bus 7, Bus 9, so that the DGs could be interconnected with each other [6].
Bus 18 and Bus 33, so they should be kept in service with Figure 2 shows the possible interconnecting sectionalizing
high priority. Upstream utility-grid is connected at Bus 1. sections that could provide closed loops. They are marked
S by dashed lines in Figure 2; namely Buses 25-29, 18-33, 9-
15 and 12-22. Among different available choices to form a
1 loop, closing the tie-switch between Bus 18 and Bus 33;
1 also the tie-switch between Bus 25 and Bus 29 is selected,
2 as it provides the N-1 contingency criterion, i.e., losing one
2 line in this microgrid does not de-energize any connected
3
load.
3 22 1
4 1
2
18 4 23 2
5 23 18 3
5
24 3 22
19 6 4
24
19 6 25 25 4 23
5 23
20 7
5
24
20 7
19 6
24
21 8 26 19
6 25 25
8 20
26 7
21
22 9 27 20 7
21
27 8 26
9 8 33
21 34 26
10 28
22 9 27
Critical Load 28
10 27
9
11 29 DG 10 28
28
11 29 10
12 30 11 29
36 11
12 30 29
35 12 30
13 31 36
12 30
13 31 WT
13 31
14 32 13 31
14 14
32 32
15 14
32
33
15
15 33
16
15
16
17 16
17 16
18 17
17 37
18
Paper No 0131
Page 2 / 4
CIRED Workshop - Helsinki 14-15 June 2016
Paper 0131-
12
29
30
Distribution System by Microgrids Formation after
35
36 Natural Disasters,” IEEE Trans. Smart Grid, vol. 7, pp.
12
30
WT
958-966.
13 31
Paper No 0131
Page 4 / 4